Form - 1 Appendix- I (See Paragraph-6)

(I) Basic Information S.No Item Details 1 Name of the Project/s. Amendment of M/s Divi’s Laboratories Limited (Unit-2) – Bulk Drug Unit at Chippada and Annavaram Villages, , District, . 2 S.No. in the Schedule Project falls under 5 (f) Synthetic Organic Chemicals Industry 3 Proposed capacity / area / length / Total Land Area of the Project is 458.26 Acres tonnage to be handled /command area a) As per previous EC dated 10.10.2007. The land / lease area / number of wells to be Area is 314 Acres drilled. b) As per CFE issued by APPCB vide its Order No. APPCB/VSP/VSP/196/CFE/HO/2015 dated 14.09.2015. The land area of the project is 387 Acres (314 + 73 Acres) c) As per amended CFE issued by APPCB vide its Order No. APPCB/VSP/VSP/196/CFE/HO/2012 dated 07.01.2016 for including land area of 71.26 acres (387+71.26 = 458.26 Acres) 4 New / Expansion / Modernization Amendment 5 Existing Capacity / Area etc. Existing Area as per Previous EC dated 10.10.2007 is 314 Acres Existing Area as per CFE dated 14.09.2015. The land area of the project is 387 Acres (314 + 73 Acres) Total Area as per CFE Amendment dated 07.01.2016 for including of land area is 71.26 (387+71.26 Acres = 458.26 Acres) 6 Category of Project i.e. ‘A’ or ‘B’ A 7 Does it attract the general conditions? -NA- If yes, please specify 8 Does it attract the specific conditions? -NA- If yes, please specify 9 Location Chippada and Annavaram Villages Plot / Survey / Khasra No Sy No. 52, 134, 138, 139, 140, 159, 161 to 168, 183 and 184 of Chippada Village and Sy No. 2, 3, 4, 6, 45, and 46 of Annavaram Village Additional Sy.Nos. 168/1, 169, 170, 171 & 172. S.No Item Details Village Chippada & Annavaram Mandal Bheemunipatnam District Visakhapatnam State Andhra Pradesh 10 Nearest railway station / airport along Railway Station :- 27.4 km, North West with distance in kms Airport: Visakhapatnam 46.2 km South West. 11 Nearest town, city, district Vizianagaram– 27.4 km, NW headquarters along with distance in Visakhapatnam - 46.2 km, SW kms 12 Village Panchayats, Zilla Parishad, Chippada & Annavaram Panchayat, Bheemunipatnam Municipal Corporation, Local body Mandal, . (complete postal addresses with Pincode – 531162 telephone no.s, to be given) Tel no- 08922-248946. 8978799449 13 Name of the applicant Madhu Sudhana Rao Divi 14 Registered Address Divi’s Laboratories Limited 15 Address for Correspondence Name Madhu Sudhana Rao Divi Designation (Owner/Partner/CEO) Director (Projects) Address Divi’s Laboratories Limited, 7-1-77/E/1/303, Divis Towers, Dharam karan road, Ameerpet, Hyderabad Pin code 500016 E-mail [email protected] Telephone no. 8978971231 Fax no. 08922-248922 16 Details of Alternate Sites examined, if No Alternative sites are examined as this is an any. Location of these sites should be amendment of EC. shown on a top sheet 17 Interlinked Projects -NA- 18 Whether separate application of -NA- interlinked project has been submitted 19 If yes, date of submission -NA- 20 If no, reason -NA- 21 Whether the proposal involves Yes. The project proposal needs CRZ clearance. approval / clearance under: if yes, Environmental Clearance under CRZ Notification details of the same and their status to obtained for the existing plant. be given: (a) The Forest (Conservation Act, 1980?

2

S.No Item Details (b) The Wild life (Protection) Act, 1972 (c) The C.R.Z. Notification, 1991? 22 Whether there is any Government Yes. G.O. MS. No. 109, Panchayat Raj and Rural Order / Policy relevant / relating to the Development (Panchayats-IV) Department, dated site 09.03.1998.

23 Forest Land involved (hectares) No 24 Whether there is any litigation No pending against the project and / or land in which the project is proposed to set up? (a) Name of the Court

(b) Case No.

(c) Orders / directions of the court, if any and its relevance with the proposed project.

(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) S.No. Information / Checklist confirmation Yes Details thereof (with approximate quantities /No /rates, wherever possible) with sources of information data 1.1 Permanent or temporary change in land Yes Existing Open/Barren land. use, land cover or topography including increase in intensity of land use (with respect to local land use plan). 1.2 Clearance of existing land, vegetation Yes Existing vegetation will have to be cleared as and buildings? per the requirement specified in layout; However, compensation for trees removed will be covered by developing green belt. 1.3 Creation of new land uses? No Amendment of EC (Addition of Land) for relocation of Production blocks A,B,D,E,F,M & N. 1.4 Pre-construction investigations e.g. Yes Necessary soil investigations will be carried bore holes, soil testing? out before construction.

3

S.No. Information / Checklist confirmation Yes Details thereof (with approximate quantities /No /rates, wherever possible) with sources of information data 1.5 Construction works? Yes Production blocks will be constructed as specified in the layout. 1.6 Demolition works? No No demolition works envisaged. 1.7 Temporary sites used for construction Yes Amendment of EC (Addition of Land) for works or housing of construction relocation of Production blocks A,B,D,E,F,M works? & N. 1.8 Above ground buildings, structures or Yes Above ground buildings (production blocks) earthworks including linear structures, will be constructed as specified in the layout. cut and fill or excavations. 1.9 Underground works including mining No No mining or tunneling works required. or tunneling? 1.10 Reclamation Works? No Not Applicable 1.11 Dredging? No Not Applicable 1.12 Offshore structures? Yes Amendment of EC (Addition of Land) for relocation of Production blocks A,B,D,E,F,M & N. 1.13 Production and manufacturing Yes The production and manufacturing process of processes? APIs & intermediates involves various raw materials, where chemical reactions will take place involving various stages like precipitation, substitution, addition, centrifugation, purifications, solvent recovery, etc. 1.14 Facilities for storage of goods or Yes Storage facilities will be created for storing materials? various raw materials, finished products, fuels, etc. 1.15 Facilities for treatment or disposal of Yes Facilities will be installed with additional solid waste or liquid effluents? capacities for appropriate handling of liquid, Solid and Gaseous wastes. 1.16 Facilities for long term housing of Yes Housing facilities envisaged. operational workers? 1.17 New road, rail or sea traffic during No Only existing roads / improvements of internal construction or operation? roads envisaged 1.18 New road, rail, air waterborne or other No Only existing roads / improvements of internal transport infrastructure including new roads envisaged or altered routes and stations, p10000orts, airports etc? 1.19 Closure or diversion of existing No No closure or diversion of existing transport transport routes or infrastructure routes or infrastructure is foreseen. leading to changes in traffic

4

S.No. Information / Checklist confirmation Yes Details thereof (with approximate quantities /No /rates, wherever possible) with sources of information data movements? 1.20 New or diverted transmission lines or No Amendment of EC (Addition of Land) for pipelines? relocation of Production blocks A,B,D,E,F,M & N. 1.21 Impoundment, damming, culverting, No Not applicable as the site does not have any realignment or other changes to the water body, this requirement does not arise. hydrology of watercourses or aquifers? 1.22 Stream crossings? No There are no streams in the existing plant site. 1.23 Abstraction or transfers of water from Yes Water will be taken from (i.e., ground or surface waters? extraction of ground water from the alluvium of Gosthani River near Bridge, through the existing tube wells.

1.24 Changes in water bodies or the land No No change in water bodies or the land surface surface affecting drainage or run-off? affecting drainage or run-off.

1.25 Transport of personnel or materials for Yes Construction materials will be transported via construction, operation or the existing infrastructure decommissioning? 1.26 Long-term dismantling or No --NA-- decommissioning which could have an impact on the environment? 1.27 Ongoing activity during No --- decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in either No Only during construction, temporary temporarily or permanently? manpower influx is expected. 1.29 Introduction of alien species? No No introduction of alien species. 1.30 Loss of native species or genetic Yes Existing vegetation will have to be cleared as diversity? per the requirement specified in layout; However, compensation for trees removed will be covered by developing green belt. 1.31 Any other actions? No Not Applicable

5

2. Use of Natural resources for construction or operation of the Project (Such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

S.No Information /Checklist confirmation Yes Details thereof (with approximate quantities /No /rates, wherever possible ) with sources of information data 2.1 Land especially undeveloped or Yes Undeveloped Barren land agricultural land (ha) 2.2 Water (expected source & competing Yes Water requirement during operation = 2751.5 users) Unit : KLD KLD. Source of this water is Gosthani River. 2.3 Minerals (MT) No Not Applicable 2.4 Construction material – stone, Yes Requirement will be fulfilled from the nearby aggregates, and / soil (expected source- sources on the basis of the design condition of MT) the plant. 2.5 Forests and timber (source-MT) No. Not Applicable

2.6 Energy including electricity and fuels Yes The total power requirement for the entire plant (source, competing users) Unit : fuel 30.4 MW (38 MVA) will be acquired from (MT), energy (MW) APTRANSCO. In case of power failure the backup power supply is through DG sets. 2.7 Any other natural resources (use Yes Coal for Coal fired boiler appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. S.No Information /Checklist confirmation Yes Details thereof (with approximate quantities /No /rates, wherever possible ) with sources of information data 3.1 Use of substance or materials, which Yes Chemicals like solvents, acids, alkalies, etc. will are hazardous (as per MSIHC rules) to be used for manufacturing of products in human health or the environment (flora, controlled conditions. fauna and water supplies ) 3.2 Changes in occurrence of disease or No No occurrences of disease or effect disease affect disease vectors (e.g. insect or vectors are foreseen. water borne diseases) 3.3 Affect the welfare or people e.g. by Yes Improved living conditions expected by changing living conditions? contributing to economical growth. 3.4 Vulnerable groups of people who could No There is no effect envisaged for the vulnerable be affected by the project e.g. hospital groups of people who could be affected by the patient’s, children, the elderly etc., project. All the pollution control norms will be strictly followed. 3.5 Any other causes No. None

6

4. Production of solid wastes during construction or operation or decommissioning (MT/ month) S. No Information / Checklist Yes Details thereof (with approximate quantities Confirmation /No /rates, wherever possible ) with sources of information data 4.1 Soil, overburden or mine wastes No Minor quantity of excavated soil and that will be used for leveling the surface. 4.2 Municipal waste (domestic and or Yes Solid waste generated will be disposed of commercial wastes) complying with all applicable rules/guidelines. 4.3 Hazardous wastes (as per Hazardous Yes The hazardous waste generated from the Waste Management Rules ) production will be process residues, MEE salts, ETP sludge, used catalysts, used oil etc.; All the hazardous waste generated will be disposed of complying with all applicable rules/guidelines from CPCB. It is proposed to utilize services from nearby TSDF. Some streams of hazardous waste may be sent to cement industries for coprocessing etc. 4.4 Other industrial process wastes No Not Applicable. 4.5 Surplus product No Production will be done as per the demand in the market; hence no surplus product is envisaged. 4.6 Sewage sludge or other sludge from Yes Effluent treatment plant sludge will be sent to effluent treatment. TSDF.

4.7 Construction or demolition wastes. No Minor will be utilized within the site 4.8 Redundant machinery or equipment No Not Applicable. 4.9 Contaminated soils or other materials No --

4.10 Agricultural wastes No. Not Applicable. 4.11 Other solid wastes Yes Fly ash from boilers shall be send to brick manufactures.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S.No. Information /Checklist Yes/ No Details thereof (with approximate quantities confirmation /rates, wherever possible ) with sources of information data 5.1 Emissions from combustion of Yes Coal as fuel will be used for Boiler and Diesel for fossil fuels from stationary or DG set. mobile sources 5.2 Emissions from production Yes The major process emissions are VOCs, carbon di- processes oxide, ammonia and acids. The details of emission control utilizing pollution control devices will be provided in the EIA report.

5.3 Emissions from handling Yes Very Minimal emissions expected during storage including storage and transport and transport. All necessary precautions will be taken as per industry guidelines to minimize

7

S.No. Information /Checklist Yes/ No Details thereof (with approximate quantities confirmation /rates, wherever possible ) with sources of information data emissions. 5.4 Emissions from construction Yes Very minimal emissions expected during activities including plant and construction activities. All necessary precautions equipment including dust suppression measures etc. will be taken to avoid/minimize emissions. 5.5 Dust or odors from handling of Yes Necessary controls will be adopted to protect materials including construction ambient air from dust and odors. materials, sewage and waste. 5.6 Emissions from incineration of Yes Very minimal emission expected. Stack meeting waste MoEF guidelines is provided along with all necessary pollution control devices. 5.7 Emissions from burning of No. No material will be openly burnt in air. waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other No Emissions from other sources are not envisaged sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat: S.No. Information /Checklist Yes/ Details thereof (with approximate quantities confirmation No /rates, wherever possible ) with sources of information data 6.1 From operation of equipment Yes Noise will be generated during operation of boiler & e.g. engines, ventilation plant, DG sets. Necessary acoustic enclosures will be crushers provided in blower and compressor house to suppress the noise levels within the norms. Necessary PPEs (ear muffs) will be provided for the personnel working in the area. Vibration is not a significant factor since the most of the equipments & structures are static. The vibration effect of these will be only local and the design of supports and foundation will nullify the intensity of vibration. 6.2 From industrials or similar Yes Noise and Vibration will be very minimal and will be processes. within the industry/production block premises only. All the workers will be provided with necessary PPE wherever necessary. 6.3 From construction or demolition Yes Necessary controls will be adopted. 6.4 From blasting or piling No Not applicable. 6.5 From construction or operational Yes Noise from vehicles/equipment during construction traffic is expected but it will be very minimal. All necessary precautions will be taken to minimize noise. Minimal noise is expected from production blocks. Greenbelt

8

S.No. Information /Checklist Yes/ Details thereof (with approximate quantities confirmation No /rates, wherever possible ) with sources of information data will also reduce the transmission of noise outside industry premises. Impact of noise and vibration will be very minimal outside industry premises.

6.6 From lighting or cooling No Noise, vibration, heat and intensity of light will be systems negligible from the lighting and cooling systems. 6.7 From any other sources No Not Applicable.

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: S.No. Information /Checklist Yes Details thereof (with approximate quantities confirmation /No /rates, wherever possible ) with sources of information data 7.1 From handling, storage, use or Yes Minimum risk. All necessary precautions will be spillage of hazardous materials. taken to avoid the risk. The liquid raw materials will be stored in storage tanks in specific storage areas with dykes. Lime will be stored in lime shed with concrete flooring. All other hazardous materials will be temporarily stored in drums/tanks/barrels, and later shifted to incineration or secured landfill for disposal. Hence, there is no chance of contamination of water streams and land. 7.2 From discharge of sewage or Yes Minimum risk. Industrial wastewater and domestic other effluents to water or the wastewater will be conveyed to the ETP through land (expected mode and place pipes with proper containment and no leakage is expected anywhere in the system. of discharge ) 7.3 By deposition of pollutants Yes Minimum emissions expected. Pollution Control emitted to air, into the land or Devices will be installed to minimize the emissions. into water. VOCs are expected to be released from process vents of the production blocks, fugitive emissions etc. Particulate matter will be released from boiler and DG sets. Adequate control systems like cyclones, dust collectors, bag filter are provided to control the particulate matter emissions. The emissions will be monitored periodically to maintain within the stipulated standards. 7.4 From any other sources No Not Applicable 7.5 Is there a risk of long term build No. No long term build-up of pollutants expected. All up of pollutants in the pollution control measures will be adopted. An environment from these sources? approved Environmental Management Plan (EMP) will be followed to ensure zero or minimal pollution in the environment.

9

8. Risk of accidents during construction or operation of the Project, which could affect human or the environment. S.No Information /Checklist Yes/ Details thereof (with approximate quantities confirmation No /rates, wherever possible ) with sources of information data 8.1 From explosions, spillages, fires Yes Minimum risk. Spillages and fires will be handled by etc from storage, handling, use or trained emergency handling teams for minimum production of hazardous damage. substances 8.2 From any other causes No. Not Applicable 8.3 Could the project be affected by Yes The project location is in cyclone prone area; natural disasters causing however all necessary control measures including environmental damage (e.g. cyclone resistant structures, proper compound walls, selection of right green belt etc. will be taken to floods, earthquakes, landslides, minimize the damage. cloudburst etc)?

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activates in the locality.

S. No. Information /Checklist Yes Details thereof (with approximate quantities /rates, confirmation /No wherever possible ) with sources of information data 9.1 Lead to development of Yes Due to the project, local ancillary units will be supporting. facilities, ancillary developed. Local infrastructure as well as low scale development or development commercial facilities will be developed. stimulated by the project which could have impact on the environment e.g.:  Supporting infrastructure (roads, power supply, waste or waste-water treatment etc.)

 Housing development

 Extractive industries

10

S. No. Information /Checklist Yes Details thereof (with approximate quantities /rates, confirmation /No wherever possible ) with sources of information data  Supply industries

 Other

9.2 Lead to after use of the site, No. Not Applicable. The industry is planned for long term. which could have an impact on the environment 9.3 Set a precedent for later Yes Due to the project, local ancillary units will be developments developed. Local infrastructure as well as low scale commercial facilities will be developed. 9.4 Have cumulative effects due to No Not envisaged. proximity to other existing or planned projects with similar effects)

III) Environment Sensitivity S.No. Areas Yes Aerial distances (within 15 km.) Proposed project /No location boundary. 1. Areas protected under Yes Amanam Reserve forest in North and Gillman Field international conventions, Reserve Forest in South. national or local legislation for their ecological, landscape, cultural or other related values. 2. Areas which are important or Yes . 1.5 km, East sensitive for ecological reasons- Wetlands, water courses or other water bodies, coastal zone, biospheres. Mountains, forests 3. Areas used by protected, No. Not applicable important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration. 4. Inland, coastal, marine or Yes Marine water body (Bay of Bengal) 1.5 km East and underground waters Gosthani River 2 km West 5. State, National boundaries No. Not applicable

11

S.No. Areas Yes Aerial distances (within 15 km.) Proposed project /No location boundary. 6. Routes or facilities used by Yes NH - 16 (approximately 9 km away in North) the public for access to NH - 16 (approximately 8 km in Northwest) recreation or other tourist, pilgrim areas 7. Defense installations No. None in the study area within 15 km radius 8. Densely populated or built-up Yes Thagarapuvalasa Village located 9 km West area 9. Areas occupied by sensitive Yes Primary Schools, Worship places, hospitals etc. are man-made land uses existing in the nearby villages. (hospitals, schools, places of worship, community facilities) 10. Areas containing important, Yes Agriculture lands; coconut gardens; cashew high quality or scarce plantation; fisheries etc. resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)

11. Areas susceptible to natural Yes The project location is in cyclone prone area; however hazard which could cause the all necessary control measures including cyclone resistant structures, proper compound walls, selection project to present of right green belt etc. will be taken to minimize the environmental problems damage. (Earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic condi tions)

IV). Proposed Terms of Reference for EIA studies: I hereby undertaking that the data and information given in the application and enclosures are to the best of my knowledge & belief & I am aware that if any part of the data and information submitted is found to be false or mi eading at any stage, the project will be rejected and clearance given, if any to the project will revoked at ur risk & cost. -