Verrazano Narrows Storm Surge Barrier
ASCE Met Section Infrastructure Group Seminar 2009 Conference “Against the Deluge: Storm Surge Barriers to Protect New York City, March 31st 2009
Peter Jansen, Principal Engineer Hydraulic Structures, ARCADIS Piet Dircke, Program Director Water, ARCADIS Contents
• Introduction • Location• inhoudsopgave Verrazano Narrows • Passage of ships • Tide reduction and wet cross section • Conceptual design • Height and overtopping • Details • Reliability • Estimate of Costs • Concluding remarks
• Questions and discussion The Netherlands
1
2
3
5
4 Comparison of New York / New Jersey and the Netherlands
• Complex sea, tidal and river water systems • Urban area with high property values & densities • Large urban areas below or just above sea level vulnerable to floods • Environmental impact as a major issue • Large ports with intense shipping
New York Rotterdam Location Verrazano Narrows
New York Harbor Bay
North of Bridge Not too far Depth The Narrows
Alignment half a mile north of Verrazano Bridge Staten Island Long Island
Verrazano bridge Present Cross section Verrazano Narrows
Cross section
60 Cross section Cross section 40
20 Width: 6000 feet Width: 6000 feet Depth: 60 feet (max) 0 Depth: 60 feet (max) -20 Wet cross section: Wet surface: -40 310.000 ft2 310.000 ft2 -60
-80 Embankement above
0 Embankement above -330 330
660 50 feet within 990
1300 50 feet within 1650 1980 2310 2640
2970 300-600 feet 3300 R1 3630 3960 4290
4620 300-600 feet 4950 depth (ft) 5280 5610 5940
width (ft) 6270 6600 Impeding water only
tion ic op ealist No r Passing ships Tidal flow Passage of ships
Biggest ship afloat must be able to pass
Emma Maesk
Length: 1300 feet Beam: 185 feet Draft: 53 feet Heigth: 251 feet Cross section for biggest ships
Requirements for Requirements for passage of ships passage of ships Width: 860 feet Width: 860 feet Sill: - 66 feet Sill: - 66 feet Clearance: unlimited Clearance: unlimited = blue area Wet surface: Wet cross section: 57.000 ft2 19 % Additional cross section for smaller ships Additional cross section for smaller ships
2 gates 2 gates Width: 165 feet Width: 165 feet Sill: - 40 feet Sill: - 40 feet Clearance: 80 feet Clearance: 80 feet Total wet cross Total wet surface: Section 70.000 ft2 23 % Reduction tide in New York Harbor Bay (1)
Tides Limited wet cross section = limited tide Present tide NYHB
4,0
3,0
2,0
1,0
0,0 Waterlevel (ft) Waterlevel
20,0 30,0 40,0 50,0 60,0 70,0 80,0 90,0 -1,0
-2,0 Tide NYHB, limited cross section -3,0
-4,0 Reduction tide in New York Harbor Bay (2)
Limited wet cross section Tide in relation to wet cross section = limited tide
Reduction to 23% 100 = tide reduction to 85-90 % 90 Tide; basis model 80 ) with safety margin % ( 70 .. 60 Tide Tide 50
40
30
20
10
0
002 1030405060
Cross section (%) Reduction tide in New York Harbor Bay (3)
Limited wet cross section
8 = limited tide Maximum velocity 7 during mean tide Reduction to 70.000 sq ft2 6 = tide reduction to 85-90 % 5
4 .. and higher peak velocities Velocity (knots) 3 up to 6-8 knots 2
1 Additional wet cross 0 section for 0 102030405060• higher tidal range Cross section (%) • lower velocities Additional cross section tidal flow
16 gates
Width: 130 feet Sill: - 40 feet Clearance: 5 feet
Total wet cross section 155.000 ft2
= 50 % of present wet cross section Combination of three existing Dutch barriers …(1)
Maeslant storm surge barrier 1997 Combination of three existing Dutch barriers …(2)
Hartel Canal storm surge barrier 1997 Combination of three existing Dutch barriers …(1)
Easter Scheldt storm surge barrier 1986 … used in the right places (1)
Sector gate for large opening: Maeslant … used in the right places (2)
Sector gate for large opening: Maeslant Lifting gates, high clearance for smaller openings: Hartelkering … used in the right places (3)
Sector gate for large opening: Maeslant Lifting gates, high clearance for smaller openings: Hartelkering Lifting gates, fixed beam for extra wet cross section: Easter Scheldt Technical overview
Closed
Open Artist impression Requirements impeding water
- Structural reliability - Reliability closure - Limit overtopping and leakage Desig n sto Cate rm Water level outside gory Sur 3 hu 30,0 ge rri of 22 cane feet 25,0 Water level
20,0 Storm surge 15,0 Normal tide 10,0 Sea level rise
water level (ft) water 5,0
0,0 1 7 13 19 25 31 37 43 49 -5,0 time (hr) Height: allowing overtopping and some leakage
• Allowing overtopping is reducing height and reducing costs
30,0
25,0
20,0 Outside 15,0
10,0 water level (ft) level water 5,0 Inside
0,0 1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 -5,0 Opentime (hr) Closed Open Allowing overtopping and some leakage
• Allowing overtopping is reducing height and reducing costs • Inside water level will rise - allowable below safe water level
8,0
7,0 Safe level
6,0 With overtopping 5,0
4,0 With river discharge 3,0
water levelwater (ft) 2,0
1,0 No river, no overtopping 0,020,0 25,0 30,0 35,0 40,0 45,0 50,0
-1,0 time (hr) Open Closed Open Details sector gate
Enormous gates 640 feet long Sliding over sill Height -66 to + 30 feet Detail sector gate
Large Foundation Locomobiel Details 130-feet lifting gate
Fixed beam between + 5 and + 36 feet Sill at -40 feet Gate between -40 and + 5 feet Gate hanging on cylinders Maintenance road Details 130-feet lifting gate
Some leakage between gate and fixed beam Operating mechanism 130-feet lifting gates
Cylinders able to lift heavy gates Fail-safe solution: If operating system fails automatic closure of gates by local system, battery controlled, using gravity Applicable up to lifts of 80 feet Reliable if used / tested monthly Details 165-feet lifting gate
No fixed beam Sill at -40 feet Clearance of 80 feet No cylinders but winches in towers Height up to + 28 feet
Large lifting gate 1,000 kips (= 1 meps?) Reliability
Reliability is a key issue; meassures taken include
• Use proven concepts • Operating mechanism above water • Fail save design • Simple movement (horizontal or vertical only) • Easy accessible for maintenance
Operations is vital
• Early warning system • Dicision making (who en when) • Stopping of ships Maintaining reliability is essential
How to keep a structure reliable when you use it only one every 10 years
• Maintenance driven design • Thoughtful construction • Risk based management • Learning and cooperating with other storm surge barrier managers • Strong organization with sufficient budget Costs
Rough estimate Sector gate US$ 2.5 bln 16 + 2 lifting gates US$ 3.5 bln Tie-in structures US$ 0.5 bln Total US$ 6.5 bln
O&M Budget estimated US$ 75mln annually
Much lower costs with less lifting gates
Many additional studies required Concluding remarks
Storm surge barrier possible
Reliability is key issue
Barrier includes all state of the art knowledge of barrier design and operation
Requirements and dimensions will determine costs => additional studies
An extra landmark for New York … Conclusion
bringing safety when required Questions Questions