Connecting Europe Facility Atlantic Corridor: Bergara-San Sebastian- TRANSPORT Bayonne section. Studies and works and
services for follow-up works. Phase 1 Member States involved:
Spain, France 2014-EU-TM-0600-M
Implementation schedule Atlantic Corridor
Start date: January 2014 End date: December 2019
Budget: Estimated total cost of the action: €1,147,441,753
Maximum EU contribution: €459,296,701.20
Percentage of EU support: Studies: 50% Works: 40%
Beneficiaries: Ministerio de Fomento www.fomento.gob.es Ministère de l’écologie, du développement durable et de l’énergie www.developpement-durable.gouv.fr Gobierno Vasco www.euskadi.eus Administrador De Infraestructuras Ferroviarias (ADIF) www.adif.es ADIF Alta Velocidad The Action is located on a pre-identified cross-border section of the Atlantic www.adifaltavelocidad.es Corridor. It aims to enhance the connection between the Iberian Peninsula and the rest of Europe through the connection Bergara-San Sebastian- Implementing bodies: Bayonne. The Action involves parts of three railway lines: the existing cross- Groupement Européen d'Intérêt border line and part of two new lines, the High Speed Line (HSL) San Économique Sud l'Europe Atlantique Sebastian-Bilbao/Victoria (namely “Y Vasca”) in Spain and the HSL Grand Vitoria-Dax (GEIE SEA Vitoria-Dax) Project of South West (GPSO) in France. The “Y Vasca” will be completed www.geie-seavitoriadax.com during the course of this Action, while the GPSO in France will be developed in the long run. SNCF Réseau www.sncf-reseau.fr The Action consists of work and studies. It includes works on the Mondragon-Astigarraga section of the HSL “Y Vasca”, and the upgrade of Additional information: the Astigarraga-Irun section on the existing line. Studies concern the upgrade the existing Dax - Victoria line and update of preliminary studies of Coordinator’s Report on the new international link. Works on the international cross-border stations the Corridor Hendaye-Irun and upgrading works of Atotxa-San Sebastian Station are also http://ec.europa.eu/transport/themes/i part of the Action. nfrastructure/ten-t-guidelines/corridors
European Commission http://ec.europa.eu/transport
Innovation and Networks Executive Agency (INEA) http://ec.europa.eu/inea
Please note that the present document is for information purposes only. The content and conditions of the grant agreement always prevail on any different information which may be included in this document or elsewhere.
Update: October 2015