6/15/2021 Ōmokoroa Peninsula Projects – April update

View this email in your browser

April 2021

Kia ora,

It's great to see work on the various Ōmokoroa Peninsula Projects continuing to progress well.

Here are the latest updates.

https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 1/12 6/15/2021 Ōmokoroa Peninsula Projects – April update

Upcoming events

Information sessions 2021

We look forward to seeing you at our upcoming information sessions for 2021:

Thursday 29 July 2021, 4.30pm to 6.30pm - Ōmokoroa Settlers Hall, 334 Ōmokoroa Road Thursday 18 November 2021, 4.30pm to 6.30pm - Ōmokoroa Settlers Hall, 334 Ōmokoroa Road

These drop-in information sessions are a great opportunity to meet with Council to find out more about the projects and ask any questions about specific projects. Note, there will be no formal presentation at these gatherings as they are an opportunity for residents to have an informal chat with Council staff. Feel free to turn up at any time.

https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 2/12 6/15/2021 Ōmokoroa Peninsula Projects – April update

Roading projects update

Ōmokoroa Road Urbanisation Stage 1 (Western Ave to Tralee St)

Since our March update, work continues along the berm on the eastern and western sides, in preparation for roadway and pavement construction to start this September.

We were also pleased to announce earlier this month that we are extending the undergrounding of power on Ōmokoroa Road. This work will be undertaken by Northpower Limited and J Swap and will involve the full undergrounding of power lines from the Western Ave Reserve through to the Country Estate https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 3/12 6/15/2021 Ōmokoroa Peninsula Projects – April update Boundary, as part of Stage 1 of the Ōmokoroa Road urbanisation project.

The undergrounding of the power lines is expected to occur in the next few months, as part of the enabling works involving stormwater connections, footpath and cycleway, kerbing and channelling on Ōmokoroa Road. You can read more about this here.

What to expect next:

Continued undergrounding of services in May 2021, including power. Further construction on stormwater connections, footpath and cycleway, kerbing and channelling. Construction of the roadway and pavement from the Western Avenue end of the roadway to Tralee Street from September 2021 to June 2022.

Click here to read more

Ōmokoroa railway pedestrian and cycleway bridges

Physical work by contractor HEB Construction continues on the two standalone pedestrian and cycleway bridges adjacent to the existing Ōmokoroa Road bridge over the railway line. The first pile has been installed on the south eastern end, and HEB is now working on the western side. https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 4/12 6/15/2021 Ōmokoroa Peninsula Projects – April update

Council is reviewing the pedestrian cycle design from the Kaimai Views roundabout to Tralee Street, with the objective of providing better walking and cycling facilities on the western side to complement the eastern side of the road.

What to expect next:

Once the piles have been installed, work will begin on the super structure (beams and deck) for the two bridges. The works are expected to be completed by June 2021. Traffic management remains in place for the duration of the project and HEB is in contact with neighbouring properties in the event there are any expected disruptions to traffic flow or access over the duration of the project.

https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 5/12 6/15/2021 Ōmokoroa Peninsula Projects – April update Keep up with the progress here

Prole Road Urbanisation (Ōmokoroa Road to Waipapa River)

Council is continuing discussions with landowners and progressing the design phase.

What to expect next:

Council expects to advertise for a contractor for physical works in mid- June, with the tender evaluation process to take place by August 2021, and construction starting in September. This project is taking a bit longer than what was anticipated, however Council is expecting it to be completed in 2022.

Western Ave Urbanisation (Ōmokoroa Road to north of Gane Place)

Thank you to those Western Ave residents who came along to our roadside meeting in April. It was great to receive your feedback on the preliminary design options.

What to expect next:

Council is now reviewing the design, taking into consideration the feedback received.

Ōmokoroa Southern Industrial Road and https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 6/12 6/15/2021 Ōmokoroa Peninsula Projects – April update stormwater pond

The design for the industrial road is now complete and Council is finalising the contract documentation to go out to market for tenders.

What to expect next:

Tender process to take place. Construction for the industrial road is expected to start towards the end of this year, and by completed in 2022. Council is in ongoing discussions with Waka Kotahi NZ Transport Agency to finalise the location of the pond. This will be a joint construction project with Waka Kotahi.

Community projects update Old Library Building and Old Sports Pavilion Building

Submissions have been evaluated and interviews have taken place. A final decision by Council is expected shortly.

https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 7/12 6/15/2021 Ōmokoroa Peninsula Projects – April update Recreation projects update Ōmokoroa Domain upgrade and new playground

As noted in the March edition, we continue to await delivery of some playground equipment items which have been imported from overseas. Supply chain issues on overseas materials means the project remains rescheduled to start in July/August 2021.

What to expect next:

The tender for construction will close soon, and we will announce a contractor for the works, following a period of negotiations. At this stage, the project is excepted to be completed in time for summer.

Find out more here

Western Avenue shared path

The new pathway connecting Ōmokoroa Road through the reserve to the new Sports Pavilion is now complete. Contractors are complementing the new path with a small area for seating between the playground and the ablutions facility.

A big thank you to the community for staying clear of the site while it was under construction.

Stormwater bund and cycleway

Stage 1 construction of the stormwater bund at the eastern end of the gold course has been completed.

https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 8/12 6/15/2021 Ōmokoroa Peninsula Projects – April update Continued construction of the stormwater bund is nearing completion, as part of stage 2 works.

What to expect next:

Subject to consents being obtained, Stage 3 works, which involves the construction of a small boardwalk linking the bund, the walkway and Kaylene Place, is expected to start in May/June.

Keep updated

Check out how the developments are tracking on our website and interactive story map.

The storymap is a useful interactive tool which displays a satellite image view of the areas being developed. Click on the various sections to read about what’s happening with each project.

https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 9/12 6/15/2021 Ōmokoroa Peninsula Projects – April update View map here

About the Ōmokoroa Peninsula Projects

By 2060, the Ōmokoroa peninsula will be fully developed and home to an estimated 12,000 residents. To cater for this significant growth and the need for continuing improvements to the peninsula’s infrastructure, we’re undertaking a series of projects – roading, reserves, cycleways, stormwater, building and planning – between now and 2022.

The roll-out of the projects across Ōmokoroa follow sound planning work and reflect the spatial planning needed to support all land use development in Ōmokoroa in the years to come.

Read more about our Ōmokoroa Peninsula Projects here

https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 10/12 6/15/2021 Ōmokoroa Peninsula Projects – April update Like us on Facebook Visit our Website

Stay up to date: Visit our projects page and interactive story map

Email: [email protected] Phone: 07 571 8008

https://mailchi.mp/westernbay/omokoroa-peninsula-projects-latest-updates-april2021?e=[UNIQID] 11/12 6/15/2021 Ōmokoroa Peninsula Projects – April update

This email was sent to <> why did I get this? unsubscribe from this list update subscription preferences Western District Council · 1484 Cameron Road · Greerton · , Bay Of Plenty 3112 ·