North-South Corridor Northern Connector Project Community Update – May 2018 The Northern Connector’s On-site Batch Plant The Northern Connector Project continues to deliver for local businesses and workers with the arrival of the project’s concrete batch plant, set to produce the concrete for the Northern Connector, ’s first major concrete road. Transported over a period of four days last year the plant was relocated from a previous project in NSW and is now at the rear of NorthHub site office at Waterloo Corner. The batch plant will produce approximately 175,000 cubic metres of concrete for the construction of the concrete pavement required for 13km of the 15.5km Northern Connector alignment. The four interchanges will be paved in asphalt. The construction of the concrete pavement will support more than 40 extra jobs and contribute another $11 million to the local economy. South Australian business Brighton Limited will supply the plant with cement and quarry materials, with Boral awarded the contract Batching plant – November 2017 to supply asphalt and additional quarry products. Both companies will source products and materials from South Australian quarries. The batch plant’s first pavement is Have you registered for traffic updates? expected to be poured in mid-2018, If you would like to receive regular traffic updates with the Northern Connector Project for the Northern Connector Project, please on schedule for completion at the register your details with the Project Team end of 2019. on 1300 916 221 or via email Employment opportunities are still [email protected] available through NorthHub as the project continues.

North-South Corridor – Northern Connector Project Community Update May 2018

diversion Use Path Use

Upcoming works>> Shared

LEGEND LEGEND N

N TEMPORARY NORTHERN BOLIVAR INTERCHANGE ON-RAMP (UNDER CONSTRUCTION) EXPRESSWAY ON RAMP WORKZONE MEDIAN WORKS >>Bolivar Interchange SHARED USE PATH N ONGOING EARTHWORKS Speed O Works are progressing well within SHARED USE PATH CLOSED R T HODGSON RD and lane Caravan H E CALVENGROVE RD the area of the Bolivar Interchange. R restrictions & Tourist N Shared E in place Park >>Northern Interchange X Service relocation works commenced P (northbound) Use R Median E S in mid-March 2018 on Hodgson Road Path Works are increasing on the S works W Northern Interchange, for the AY and preparation for the STANLEY RD intersection upgrade at new connections between the NORMA RD OTR Port Wakefield Whitehorse OTR Northern Connector, Port Wakefield Port Wakefield Road and Inn Bolivar HUXTABLE RD Road and Road and . Hodgson Road are underway Krispy BOLIVAR ROAD Kreme Local traffic management including some for the installation of PORT WAKEFIELD ROAD lane and speed restrictions will be required, traffic signals. however traffic will remain open in both Other works in the area include CHERRY LN directions during these works. Advanced earthworks and service locating BROWN RD Shared notice signage will be in place to notify adjacent the Bolivar and Kings Road roundabout. Ongoing Site Use Path users of the works. earthworks compound SYMES RD closed Northern Speed and lane restrictions will apply to ensure safe traffic movement. Interchange CURNOW RD Please note, access to all businesses and residents will be maintained at all times. ramp under ROAD KINGS construction .

BIRCHWOOD AVE

LEGEND Southern Interchange – Connection to the South Road Superway – March 2018 N NORTHERN CONNECTOR (UNDER CONSTRUCTION) >>Waterloo Corner SERVICE RELOCATION WATERLOO CORNER RD AND DRAINAGE WORKS Interchange HEASLLIP RD EARTHWORKS

Works are continuing for the construction of the Waterloo Interchange, including placement Interchange asphalt Ongoing of fill, concrete and asphalt works. works earthworks Works on Robinson Road will commence shortly to construct new drainage crossings. SUMMER RD Local traffic management and detours will be required with access through the work zone UNDO RD restricted to local residents only while works are undertaken. Advanced notice PORT WAKEFIELD ROAD signage will be in place,

ST KILDA RD and local residents will

be notified of access ANJANTO RD changes prior to works commencing. Bridge Construction Work Concrete batch Main site plant Upcoming compound service >>Southern Interchange and protection and NorthHub ROBINSON RD relocation Day and night works are continuing for the construction of the Southern Interchange. Works on and around works the Expressway include median repaving, service protection activities and bridge structural works.

Visit www.addinsight.com.au/app or Visit the traffic SA website >> If you would like to sign up for Northern Connector traffic updates, www.traffic.sa.gov.au FOR REALTIME ROADWORK please register your details with the Project Team on 1300 916 221 or Download the App (available in Apple and Android) INFORMATION via email [email protected] 2 3 North-South Corridor – Northern Connector Project

LEGEND

N BOLIVAR ROAD NORTHERN CONNECTOR HEASLIP RD PARAFIELD MAIN NORTH RD UNDER CONSTRUCTION KINGS RD GARDENS NORTHERN INTERCHANGE BURTON PORT WAKEFIELD ROAD WATERLOO INTERCHANGE NORTHERN EXPRESSWAY WATERLOO CORNER ROAD BOLIVAR INTERCHANGE SOUTHERN INTERCHANGE CAVAN RD MAIN ROADS WATERLOO CORNER PORT WAKEFIELD ROAD LOCAL ROADS GLOBE DERBY DR GLOBE DERBY PARK NO RTH >>Northern SA WATER ERN CO N N Connector WATER TREATMENT E C T SUMMER RD PLANT O R Project ST KILDA RD ANJANTO RD ROBINSON RD planned BOLIVAR works SYMES RD BROWN RD

OLD PORT WAKEFIELD ROAD Main site Concrete compound & batch plant

PORT RIVER EXPRESSWAY

KEY ACTIVITIES KEY ACTIVITIES KEY ACTIVITIES KEY ACTIVITIES >> Ongoing earthworks to build the new ramps as part of the interchange >> Earthworks for the interchange construction >> Earthworks for the interchange construction >> Works for the new pavement >> Demolition of concrete barriers to allow for widening of the roadway >> Bridge construction >> Service protection and relocation works on Hodgson Road >> Bridge construction >> Changed traffic conditions, including lane and speed changes >> Asphalt works >> Port Wakefield and Hodgson Road intersection upgrade, including >> Regular truck deliveries of fill material >> Speed restrictions on Port Wakefield Road and Northern Expressway works in the centre median on-ramp (northbound) >> Kings and Bolivar Road roundabout

ST.KILDA

>>Project milestones – to September 2018 <<2018>> >>May >>June >>July >>August >>September

4 5 North-South Corridor – Northern Connector Project Community Update May 2018

Interchange maps>> The Northern Connector will have four interchanges that will connect to the Northern Expressway, If you would like more information about the functionality of these interchanges, Port Wakefield Road, Salisbury Highway, the Port River Expressway and the South Road Superway, contact the Project Team on 1300 916 221 or email [email protected] see below to learn how these interchanges will connect in with Port Wakefield Road and the local area.

NORTHERN CONNECTOR NORTHERN CONNECTOR CALVENGROVE ROAD ROAD >>BOLIVAR INTERCHANGE IELD >>NORTHERN INTERCHANGE AKEF RT W BOLIVAR PO HODGSON

ROAD ROAD NORTHERN EXPRESSWAY ADELAIDE ADELAIDE PORT WAKEFIELD ROAD

GAWLER Highway 1 Caravan and Tourist Park

ERN CONNECTOR NORTH

PORT WAKEFIELD NORTHERN CONNECTOR NORTHERN CONNECTOR PORT WAKEFIELD

BROWN

ROAD

WATERLOO

CORNER NORTHERN CONNECTOR SALISBURY HIGHWAY NORTHERN CONNECTOR

SALISBURY ROAD >>WATERLOO CORNER SALISBURY >>SOUTHERN INTERCHANGE INTERCHANGE

PORT WAKEFIELD ROAD Salt Pans

ADELAIDE PORT WAKEFIELD ROAD Wingfield

PORT WAKEFIELD UNDO ROAD

NORTHERN CONNECTOR

SOUTH ROAD SUPERWAY NORTHERN CONNECTOR

PORT RIVER EXPRESSWAY

PORT WAKEFIELD

Barker Inlet Wingfield

ST KILDA ROAD

ROBINSON ROAD

6 7 North-South Corridor – Northern Connector Project

Artist's impression of the Northern Connector at the Southern Interchange

NorthHub news Contact us Piling contractor Wagstaff is now operating a site office and precast yard at the rear of the Waterloo Corner site Project Information office, and commenced piling works as part of bridge 1300 916 221 construction for the Northern Connector. dpti.sa.gov.au/northernconnector Wagstaff will install over 900 precast pileson the project [email protected] which will be cast from South Australian concrete, with materials from Boral sourced from the state’s quarries and reinforcements NorthHub made from billet supplied by Liberty OneSteel in Whyalla. 1277-1291 Port Wakefield Road Wagstaff are committed to hiring and upskilling a local Waterloo Corner workforce and meeting the project’s 20 per cent workforce Open Monday to Friday participation target. At the peak of construction Wagstaff has 10.00am – 4.00pm employed nine Aboriginal trainees on site, comprising almost 1300 731 071 50 per cent of their workforce. NorthHub.sa.gov.au The NorthHub Team will be working with the construction team [email protected] over the coming months to identify opportunities to transition these trainees to other concrete works within the project area once the Local Industry pre-cast piling works are complete. lendleasenorthernconnector.icn.org.au Overall, the Northern Connector Project continues to exceed [email protected] its targets to ensure at least 20 per cent of on-site hours are completed by people from target groups, with 32 per cent of hours currently being completed by local people with barriers to employment, Aboriginal people and apprentices and trainees and cadets, as of the end of April 2018.

Are you registered with NorthHub? NorthHub is the employment and training centre established by Lendlease to connect jobseekers with employment opportunties on the Northern Connector Project.

To apply for available jobs or register your interest for future employment visit www.NorthHub.sa.gov.au or visit the NorthHub team on-site.