Finch West LRT Project Construction Liaison Committee Meeting - East Tuesday, July 2, 2019 Agenda
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 2 AGENDA
• Safety Moment
• Introductions and Review of Terms of Reference/Code of Conduct
• Review of Minutes
• Status of Action Items
• Project Overview
• Work Update
• Public Engagement Update
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 3 Project Overview
Paulette den Elzen, Communication and Public Engagement Lead
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 4 MOSAIC TRANSIT GROUP
Selected by Metrolinx and Infrastructure Ontario to design, build finance during construction and maintain the Finch West Light Rail Transit (LRT) project.
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 5 FINCH WEST LRT PROJECT OVERVIEW
. 11 km of fast, reliable transit from Keele Street to Humber College . 18 stops - 16 surface, 1 underground and 1 below grade . Renewal of Highway 400 at Finch Avenue West . Connections to TTC, GO Transit, MiWay, Viva and Züm . Transit to 46,000 passengers per weekday . $1.2 billion commitment from the Province of Ontario including $333 million from the Government of Canada . Design, Build, Finance and Maintain (DBFM) model . Contracting Authority - Infrastructure Ontario and Metrolinx . Owner - Metrolinx . Operator - TTC . Vehicle provider - Alstom
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 6 FINCH WEST LRT PROJECT
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 7 FINCH WEST LRT PROJECT
Finch West LRT
Electrical & Roadway Maintenance & Additional Stops Station Mechanical & Guideway Storage Facility Structures Systems
Light Rail Operation One Interchange 11 km LRT Track Buildings Portals 16 At-Grade Stops Terminus Station and Guideway Systems
Communications One Intermodal Cut and cover Roadway Widening Parking Lot, Yard, Grade Separation Terminus Stop tunnel (0.3 km) Landscaping and Public Interface
Rehabilitation of Utility Relocation MSF Existing Structures
Landscape/ Streetscape
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 8 16 AT GRADE STOPS
Key Components: Number of configurations: • Branded Crosswalk • 10 far-side configurations • Protective Bull-nose • 2 parallel configurations • Waiting Zone and Ramp • 4 island configurations • Two Shelters • Concrete platforms, 48m (length of a LRT Vehicle)
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 9 Construction Schedule
George Kelly, Construction Manager
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 10 CONSTRUCTION SCHEDULE
Commitment to Communicate Construction Timeline
(Typical Schedule of Works)
Activities 2018 2019 2020 2021 2022 2023
Design Preparatory Works Utilities and Civil Works Maintenance & Storage Facility Finch West Station (Keele) Humber College Stop (Hwy 27) Highway 400 Rehabilitation Testing and Commissioning (MTO) Systems Installation Testing and Commissioning (MX) Burn In Testing
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 11 Finch West Station Update
Josh Boroni, Project Coordinator, Civil Works Hayat Muhammad, Traffic and Transit Manager
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 12 FINCH WEST STATION – INTERCHANGE TERMINAL
• An underground station located at Keele Street and Finch Avenue intersection
• Connects to Finch West TTC station via pedestrian tunnel through concourse
• Will include an underground Station Box and island platforms.
• Platform lengths – a minimum of 98 m to accommodate the operation of trains
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 13 FINCH WEST STATION – PREPARATORY WORK
Activity Location Start and Impact Duration
Boreholes for geotechnical inspection Complete
Site setup, including Finch Avenue West at Keele Street August 2019 installation of site trailers Minimal (northeast and southeast lot)
Lights relocated and replaced Lane restrictions; Street light and signal light Summer 2019 relocation with temporary lights on north side, TTC stop on NE corner may then on south side be affected.
Dry and wet utilities Finch Avenue West at Keele Street Fall 2019 Traffic disruption relocation as well as road (northeast and northwest sides first, then widening the southeast and southwest sides)
Start of Support of September 2019 Noise due to pile driving Excavation (SOE) and secant Finch Avenue West and Keele Street and potential traffic wall for the station box (southeast corner) disruption
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 14 FINCH WEST STATION – PHOTOS OF PREPARATORY WORK
Bore hole drilling activity
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 15 KEELE AND FINCH AREA UPCOMING WORKS July 2019
• Noise and vibration measurements (near Romfield Ln and Driftwood Ave.)
What to expect
• Vibration caused by dropping a 50 kg weight multiple times on a portable impact testing rig
• Temporary and rotating road closures for approx. 2 hours at each location
Test dates (weather permitting):
• Overnight on dates between July 3 to 7 (9 pm to 7 am; weather permitting)
• In case of inclement weather, work will occur on dates between July 8 to 12 (9 pm to 7 am)
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 16 Maintenance and Storage Facility
George Kelly, Construction Manager
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 17 MAINTENANCE AND STORAGE FACILITY (MSF)
• An 8,993 m2 two-storey facility
• Bounded by Norfinch Drive to the west, York Gate Boulevard to the east, Finch Road to the south and the Hydro corridor to the north
• Will house trains, repair and washing facilities, offices and a parking lot
• A 32m set back from Finch Avenue will be used for future City urban development after project construction is complete
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 18 TRAFFIC ACCESS CHANGES TO ELANA DRIVE
What: In May 2019, Toronto City Council approved a temporary traffic by-law amendment to Elana Drive, which:
• Restricts westbound traffic from turning left on Elana Drive • Permits southbound traffic on York Gate Boulevard to continue through on to Elana Drive.
Duration: From June 10 to October 31, 2019
Why: • Mosaic recommends a permanent amendment of traffic access to Elana Drive to allow for safe LRT operations. • The City of Toronto’s Transportation Services division and Metrolinx require Mosaic to first conduct a traffic study, simulating traffic conditions from such a change. • Mosaic is conducting the study and will monitor, track and report its findings to the city and Metrolinx. • After, the city will review the report and decide on changes to the by- law. 19 MSF – COMPLETED WORK
Spring
• Installation of fencing around perimeter - Complete
• Installation of a stormwater containment pond that will collect runoff, thereby preventing flooding and minimizing erosion on the site – Complete
• Installation of noise and vibration monitors -- Complete
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 20 MSF – WORK IN PROGRESS Spring - Summer
• Ongoing clearing and grubbing of land
• Installation of tree protection
• Noise and vibration measurements (adjacent to 74 Elana Drive)
What to expect
• Vibration caused by dropping a 50 kg weight multiple times on a portable impact testing rig
Possible test dates:
• Overnight on dates between July 3 to 7 (9 pm to 7 am; weather permitting)
• In case of inclement weather, work will occur on dates between July 8 to 12 (9 pm to 7 am)
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 21 TRACK NOISE AND VIBRATION
July 2019
• Noise and vibration measurements (near Elana Drive.)
What to expect
• Vibration caused by dropping a 50 kg weight multiple times on a portable impact testing rig
• Temporary and rotating road closures for approx. 2 hours at each location
Test dates (weather permitting):
• Overnight on any of these date: July 3 to 7 (9 pm to 7 am; weather permitting)
• In case of inclement weather, work will occur on dates between July 8 to 12 (9 pm to 7 am)
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 22 MSF – UPCOMING WORK
July to November 2019
• Ongoing clearing and grubbing of land
• Installation of trailers and parking area – July 2019
• Construction of access road -- July 2019
• Excavation and foundation work -- August 2021
• Main building work – to start November 2019
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 23 Highway 400 Bridge Rehabilitation Update
Kevin Green, Superintendent, Hwy 400 Bridge Rehabilitation
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 24 HWY 400 BRIDGE REHABILITATION – COMPLETED WORK
Spring
• Geotechnical Testing - Complete
• Borehole Drilling – Complete
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 25 HWY 400 BRIDGE – UPCOMING WORK
July 2019
• Installation of concrete barriers along on- ramps; some on-ramp closures overnight
• Set-up of staging areas within all on-ramps; partial on-ramp lane reductions
• Start of refacing of abutment walls; expect partial on-ramp lane reductions and occasional day-time lane reductions for crew to access site.
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 26 TIME-LAPSE OF RAPID BRIDGE REPLACEMENT
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 27 Utility Relocation Keele Street to Islington Avenue
Adam Przewieda, Utility Project Coordinator
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 28 FROM KEELE STREET TO ISLINGTON AVENUE – UPCOMING UTILITIES WORK
Activity Location Start and Impact Duration
Finch Ave West from Signet Dr to Install underground hydro duct Fall 2019 Jane Street Short-term lane structures Around 6 months occupancy
Along Finch Ave West from East of Short-term lane Stormwater sewer relocation Tobermory Drive to Keele Street Fall 2019 6 weeks occupancy
Fall 2019 Relocate hydro poles Along Finch Ave West from Signet Short-term lane Road to Jane Street 4 months occupancy
Removal of existing street light and Finch Ave West and Keele Street Late-2019 traffic lights followed by installation Short-term lane intersection of temporary street lights and signals 6 weeks occupancy
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 29 UTITLITY RELOCATION ACROSS THE CORRIDOR
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 30 FINCH WEST STATION – TRAFFIC LIGHT RELOCATION
Fall 2019 Installation of temporary lighting and traffic signals
• Temporary poles will be in place throughout road widening work (about two years).
• Vacuum and bucket trucks will be used to perform this work
• Minimal noise
• Lane restrictions expected
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 31 Communication and Community Engagement
Paulette den Elzen, Communications and Public Engagement Lead
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 32 COMMUNICATIONS AND COMMUNITY ENGAGEMENT ACTIVITIES
May • Humber Summit Resident Assoc. AGM • May Open Houses:
• May 24, at York Gate Mall
• May 28, at St. Wilfrid Catholic School
• May 30, at Northwood C.C. June • 31 Division Open House BBQ & Bursary Awards – June 1 • Walk with Excellence – June 11 • Canada Pop Up – June 28 • Duke Eats – June 29
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 33 UPCOMING COMMUNICATION AND COMMUNITY ENGAGEMENT
July and August 2019
• Foodie Festival (Rexdale Community) Date TBD
• Fusion of Taste
• Black Creek Community Farm Duke Eats 2019 Duke Eats 2019 • Taste of Jane and Finch Canada Day Pop up Canada Day Pop up • Summer Camps
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 34 STAY IN TOUCH
Please sign-up to receive regular updates of construction activities and progress at: www.metrolinx.com/finchwestlrt Phone: 416-202-6500 Visit: www.metrolinx.com/finchwestlrt Email: [email protected] Follow: @finchwestlrt Drop-in: Finch West Community Office, 2540 Finch Avenue West
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 35 Appendix
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 36 FINCH WEST STATION – DESIGN CONCEPT
• Composed of a pavilion type two-storey main entrance building on the South-East corner of the intersection
• Main entrance will be easily recognized by its size, location and iconic presence at the Finch Avenue and Keele Street intersection
• Two skylights (in the median) will bring light to the underground spaces of the station
• Transparent with clear visibility towards the public areas and street
• Landscape treatment will encourage passengers to circulate and approach building.
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 37 FINCH WEST STATION – DESIGN CONCEPT
• Bright materials and skylight will improve internal circulation and improve passenger experience
• Stairs, escalators and an elevator direct people from the street to the concourse level where fare gates are located and connects to the TTC system
• From that level, another set of vertical circulation elements connect to the public platform where the LRT vehicles stop.
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 38 ROAD AND GUIDEWAY
LRT Track and Guideway includes: • 9.6 km at grade • 340m in cut-and-cover tunnel • 980m in open cut exclusive guideway • Centre running track with pole supported catenary system
Roadway Widening • To accommodate surface LRT
Landscape/Streetscape • Boulevard will consist of pavers, sidewalk, grass buffer strip, and planters • Median will also have planters, branded surface between stops and stop platforms • Branded crosswalks • Integrated public art
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 39 HUMBER COLLEGE – INTERMODAL TERMINUS STOP
• A below-grade stop to be integrated with Humber College facilities, infrastructure and multi-modal circulation
• Located on the west side of Highway 27, south of the Highway 27/Humber College Boulevard intersection
• Portal access to surface-level LRT
• Configuration: island platform
• Entrance(s): at stop and connected to the plaza areas for public access
• Building height: minimum 7.5 meters
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 40 Questions?
FINCH WEST LRT PROJECT COMMUNITY LIAISON COMMITTEE MEETING - EAST 41