SUBMISSION OF FORM – I & IA TOWARDS ENVIRONMENTAL CLEARANCE (EC)

For

M/s. K. R CONSTRUCTIONS (Construction of Residential High rise building) SY.NO. 125/P, Zone –II, East Point Colony, Near VUDA Park, G.V.M.C Limits ,

Prepared& Submitted by

Enviro House, Block –B, B-1, IDA, Auto Nagar, Visakhapatnam – 530 012 Ph: 0891-2755528, Telex: 0891-2755529, E-mail: [email protected] Cell: 9440338628 QCI No – 141 & Recognized by MOEF&CC, New Delhi, Accredited by NABL

FORM -1

(I) Basic Information Sl. No. Item Details 1. Name of the project(s) M/s. K. R. Constructions 2. S. No. in the schedule 8 (a) 3. Proposed capacity/area/length/tonnage to Construction of Residential high rise building be handled/command area/lease in an area of 4453.81 Sq.mts and total built-up area/number of wells to be drilled. area is 29785.44 sq.mts. 4. New/Expansion/Modernization New Construction of Residential high rise building with Stilt -1 + Stilt 2 + First basement + Second basement + third basement + G + 16upper floors. 5. Existing Capacity/Area etc. NIL 6. Category of Project i.e. ‘A’ or ‘B’ Category – B 7. Does it attract the general condition? If No yes, please specify. 8. Does it attract the specific condition? If No yes, please specify. 9. Location Plot/Survey/Khasra No. Sy.No:125/P Village Zone-II, Tehsil East Point Colony, Near VUDA Park, G.V.M.C. Limits District State Andhra Pradesh 10. Nearest Railway Station/Airport along Visakhapatnam Railway station at 5.40 kms with distance in kms. from the project site. is at a distance of 12.30 kms from the project site. 11. Nearest Town, City, District Headquarters Visakhapatnam Town at 6.50 kms, along with distance in kms. 12. Village Panchayats, Zilla Parishad, GVMC Municipal Corporation, Local body (complete postal addresses with telephone nos. to be given) 13. Name of the applicant M/s. K. R. Constructions 14. Registered Address M/s. K. R. Constructions Sy.No:125/P Zone-II, East Point Colony, Near VUDA Park, G.V.M.C. Limits VISAKHAPATNAM DISTRICT ANDHRA PRADESH 15. Address for correspondence: D.No: 10-50-5/23, G-5, Sunny side homes, , Visakhapatnam Name V. Koteswara Rao Designation (Owner/Partner /CEO) Managing Partner Pin code 530002 E-mail [email protected] Telephone No. 9848193123, 0891-2568350 Fax No. -- 16. Details of Alternative Sites examined, if NA any. Location of these sites should be shown on a Toposheet. 17. Interlinked Projects Nil 18. Whether separate application of NA interlinked project has been submitted? 19. If yes, date of submission NA 20. If no, reason NA 21. Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given.

i. The Forest (Conservation) Act, NA 1980?

ii. The Wildlife (Protection) Act, NA 1972? Yes iii. The C.R.Z. Notification, 1991? APCZMA Lr. No: 70/APCZMA/CRZ/Bldgs/2017 658 Dt: 06.03.2018 22. Whether there is any Government No Order/Policy relevant /relating to the site? 23. Forest land involved (hectares) Nil 24. Whether there is any litigation pending against the project and/or land in which Nil the project is propose to be set up? a) Name of the Court b) Case No. c) Orders/directions of the Court, if any and its relevance with the proposed project.

(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) S.No. Information/Checklist confirmation Details thereof (with approximate quantities /rates, wherever Yes/No possible) with source of information data 1.1 Permanent or temporary change in Yes The land earmarked for construction land use, land cover or topography of residential high rise building including increase in intensity of land project with an site area of about use (with respect to local land use 4453.81 Sq.mts and the total built up plan) area is 29785.44 Sq.mts. This land is sufficient for construction of residential high rise building for 72 nos of flats. A total of 4453.81 Sq.mts of land is available and is sufficient for the construction activity. Total Built up area = 29785.44 sq.mts Further the above land is barren land. Therefore no change in land use / land cover / topography. 1.2 Clearance of existing land, vegetation No The land is barren and developed and buildings? land. No vegetation or building existing in this land for clearance. 1.3 Creation of new land uses? No No extra land will be used. The project is having 4453.81 sq.mts of land and the total built up area is 29785.44 sq.mts. In this land only the proposed project will be constructed. 1.4 Pre-Construction investigations e.g. Yes For the total area already ground bore houses, soil testing? water and soil testing carried. 1.5 Construction works? Yes To construct apartment block with 72 units (Stilt -1 + Stilt 2 + First basement + Second basement + third basement + G + 16upper floors). It is proposed stilt floor & basement for parking. 1.6 Demolition works? No The site is leveled one and not contains any temporary / permanent structures. Therefore no demolition works in the proposed area. 1.7 Temporary sites used for construction No Local manpower will be utilized for works Or housing of construction the construction work. Therefore no workers? temporary site used for construction works. 1.8 Above ground buildings, structures or Yes BUILDINGS

earthworks including linear  Building structures, cut and fill or excavations  Sewage Treatment Plant  Water park  DG Set Room 1.9 Underground works including mining No No mining or tunneling activity. or tunneling? 1.10 Reclamation works? No No reclamation work

1.11 Dredging? No Not applicable

1.12 Offshore structures? No Not applicable 1.13 Production and manufacturing No -- processes? 1.14 Facilities for storage of goods or Yes Cement storage materials? Building materials storage 1.15 Facilities for treatment or disposal of Yes Liquid effluents The waste water generated from the solid waste or liquid effluents? proposed project will be in the form of sanitary waste water only and which will be routed to sewage treatment plant and thereby reuse and for firefighting if surplus to local municipal sewerage network. Waste Generation – 54.45 or say 54.50 KLD Solid Waste: Municipal waste – 224 Kg/day DISPOSAL: Convert to manure and reuse as manure for green belt development. 1.16 Facilities for long term housing of No Majority of manpower will be Operational workers? recruited from local people only. Therefore no housing scheme proposed. 1.17 New road, rail or sea traffic during No The site is well connected to Construction or operation? roadway. No new road or rail road development required. 1.18 New road, rail, air waterborne or N.A -- other transport infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing N.A -- transport routes or infrastructure leading to changes in traffic movements? 1.20 New or diverted transmission lines or No -- pipelines? 1.21 Impoundment, damming, culverting, No -- realignment or other changes to the hydrology of watercourses or aquifers? 1.22 Stream crossings? No -- 1.23 Abstraction or transfers of water form Yes Meet the water requirements from ground or surface waters? GVMC of 60.50KLD for drinking & domestic purpose. 1.24 Changes in water bodies or the land No -- surface affecting drainage or run-off? 1.25 Transport of personnel or materials Yes During construction activity, private for construction, operation or tippers will be used for supply of decommissioning? metal, sand, cement and iron & other building material. 1.26 Long-term dismantling or No -- decommissioning or restoration works? 1.27 Ongoing activity during No -- decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in either Yes There would be a marginal influx of Temporarily or permanently? people since the construction consists of residential building. 1.29 Introduction of alien species? No -- 1.30 Loss of native species or genetic No -- diversity? 1.31 Any other actions? Yes The proposed project will develop green belt all along the all sides of boundary wall.

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non- renewable or in short supply): Details thereof (with approximate S.No. Information/Checklist confirmation Yes/No quantities / rates, wherever possible) with source of information data 2.1 Land especially undeveloped or No The present status of land is barren agricultural land (ha) and non-agricultural. 2.2 Water (expected source & competing Yes During construction users) unit: KLD Construction for domestic –30.0 m3/day During Operation Domestic – 60.50 KLD 2.3 Minerals (MT) No Not applicable 2.4 Construction material – stone, Yes Stone aggregates – 7000 m3 aggregates, sand / soil (expected (foundation work) source – MT) Soil - no soil will be lifted or excavated. Sand - 13500 m3 2.5 Forests and timber (source – MT) Yes The timber that is required is procured from the approved local contractors. 2.6 Energy including electricity and fuels Yes Electricity will be supplied by (source, competing users) Unit: fuel APEPDCL. (MT), energy (MW) Diesel for DG Sets – 50 Litres/Day 2.7 Any other natural resources (use No -- appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. Details thereof (with approximate S. No. Information/Checklist confirmation Yes/No quantities /rates, wherever possible) with source of information data 3.1 Use of substances or materials, which No There are no materials that are being are hazardous (as per MSIHC rules) to utilized in the construction human health or the environment programme which endanger human (flora, fauna, and water supplies) health or water supply. 3.2 Changes in occurrence of disease or No -- affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. by changing living conditions? 3.3 Affect the welfare of people e.g., by Yes Living conditions will escalate changing living conditions? therefore welfare of the people will be on positive side. 3.4 Vulnerable groups of people who No -- could be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes? No --

4. Production of solid wastes during construction or operation or commissioning (MT/month)

S.No. Information/Checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine wastes No -- 4.2 Municipal waste (domestic and or Yes Municipal solid waste – 224 commercial wastes) kgs/day STP Sludge – 5 Kgs/day Waste Oil – 50 LPA Disposal: Convert to manure and use of for greenbelt development. 4.3 Hazardous wastes (as per Hazardous No There will not be any hazardous Waste Management Rules) waste generation. 4.4 Other industrial process wastes No Since it is construction project, no process/industrial activity involved. 4.5 Surplus product No -- 4.6 Sewage sludge or other sludge from Yes Sludge (5.0kgs/day) generated from effluent treatment sewage treatment plant will be disposed locally as manure. 4.7 Construction or demolition wastes No There is no demolition and as such the construction debris does not arise. 4.8 Redundant machinery or equipment No No redundant machinery would be available for disposal. 4.9 Contaminated soils or other materials No -- 4.10 Agricultural wastes No -- 4.11 Other solid wastes No --

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S.No. Details thereof (with approximate quantities /rates, wherever Information/Checklist confirmation Yes/No possible) with source of information data 5.1 Emissions from combustion of fossil No It is proposed to construct fuels from stationary or mobile residential building and does not sources involve any manufacturing process. 5.2 Emissions from production processes No This not a manufacturing facility. Hence no emissions from production process. 5.3 Emissions from materials handling Yes The transportation of construction including storage or transport materials will be taken with due care to safeguard against dust emissions by coverage as well as by sprinkling water during construction phase. 5.4 Emissions from construction activities Yes The only emission from including plant and equipment construction activities is of concrete miller. It will run on HSD. Remaining all the equipment like vibrator, etc, will operates on power. 5.5 Dust or odours from handling of Yes Dust will arise from construction materials including construction materials. Proper care will be taken materials, sewage and waste during handling of material. During unloading of metal, water will be sprayed. Hence, no fugitive emissions will be released. 5.6 Emissions from incineration of waste No No incineration proposed. 5.7 Emissions from burning of waste in No No open air burning. open air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources No Nil

6. Generation of Noise and Vibration, and Emissions of Light and Heat: Details thereof (with approximate S.No. Information/Checklist confirmation Yes/No quantities /rates, wherever possible) with source of information data 6.1 From operation of equipment e.g. Yes The DG sets will be established engines, ventilation plant, crushers with silencers and the buildings are also being constructed with noise absorbing materials. DG set will be operated only during power interruption and as a stand by unit in emergency. 6.2 From industrial or similar processes No It is proposed to construct residential high rise building and does not involve any manufacturing process. 6.3 From construction or demolition No There is no demolition proposed in the complex and no possibility of noise development 6.4 From blasting or piling No No blasting or piling operation required. 6.5 From construction or operational No There is a negligible noise from the traffic machines and vehicles during construction phase. 6.6 From lighting or cooling systems Yes The lighting and cooling systems are designed as per the notification of the National Building code. 6.7 From any other sources No Not applicable.

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Details thereof (with approximate S.No. Information/Checklist confirmation Yes/No quantities /rates, wherever possible) with source of information data 7.1 From handling, storage, use or No No hazardous materials will be spillage of hazardous materials stored. 7.2 From discharge of sewage or other Yes The domestic wastewater will be effluents to water or the land routed to sewage treatment plant (expected mode and place of and will be reused. discharge) 7.3 By deposition of pollutants emitted to No No deposition of pollutant emitted air into the land or into water to air into the land or into water is envisaged. 7.4 From any other sources? No Nil 7.5 Is there a risk of long term build up of No No pollutant will be built up in the pollutants in the environment from environment. Therefore no risk these sources? from any source.

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment Details thereof (with approximate S. No. Information/Checklist confirmation Yes/No quantities /rates, wherever possible) with source of information data 8.1 From explosions, spillages, fires etc No No hazardous substance will be from storage, handling, use or stored. Small quantity of HSD will production of hazardous substances be stored in the site for running the DG/concrete mixer during construction. The HSD will be stored in a secured place. 8.2 From any other causes No -- 8.3 Could the project be affected by natural Yes The project designed under disasters causing environmental damage earthquake resistance and other (e.g. floods, earthquakes, landslides, NBC design practices followed for cloudburst etc) construction activity.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality Details thereof (with approximate S.No. Information/Checklist confirmation Yes/No quantities /rates, wherever possible) with source of information data 9.1 Lead to development of supporting No No supply or ancillary units utilities, ancillary development or required for this project. The development stimulated by the project required material will be purchased which could have impact on the directly from vendors. environment e.g.: • Supporting infrastructure (roads, power supply, Waste or waste water treatment, etc.) • Housing development • Extractive industries • Supply industries • Other 9.2 Lead to after-use of the site, which No No impact will occur. could have an impact on the (Based on literature / standby of environment existing plants) 9.3 Set a precedent for later developments No No such cases. 9.4 Have cumulative effects due to No No cumulative effects will occur. proximity to other existing or planned projects with similar effects

(III) Environmental Sensitivity Aerial distance (within 15 km.) S. No. Area Name/ Proposed project location Identity boundary 1 Areas protected under international No -- conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or sensitive Yes Water Bodies for ecological reasons - Wetlands, – 0.39 Km watercourses or other water bodies, – 5.79 Kms coastal zone, biospheres, mountains, Reserve Forests forests Kambalakonda RF – 6.61 Kms Kailasakonda Forest – 5.38 Kms 3 Areas used by protected, important or No None within 15 km Aerial distance sensitive species of flora or fauna for from proposed construction site. breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or underground Yes Bay of Bengal at a distance of 0.39 waters m. 5 State, National boundaries No None within 10kms radius NH -5 at 2.21 Kms 6 Routes or facilities used by the public Yes hills at a distance of for access to recreation or other 5.38 kms tourist, pilgrim areas 7 Defense installations No None within 15 km Aerial distance from proposed construction site. 8 Densely populated or built-up area Yes Lawson’s bay colony at a distance of 0.45 kms 9 Areas occupied by sensitive man- Yes Hospitals, Schools and community made land uses facilities like telegraph office, (Hospitals, schools, places of worship, police station and public health community facilities) center are available at a distance of 2.0 kms from proposed site area. 10 Areas containing important, high No -- quality or scarce resources (Ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution or No -- environmental damage. (Those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard No -- which could cause the project to present environmental problems (Earthquakes, subsidence, landslides, erosion, flooding for extreme or adverse climatic conditions)

STANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS/ ACTIVITIES:-

S. No Information required Information to be furnished by the proponents 1 Name of the project or activity M/s. K. R. Constructions 2 Name of the organization/owner. M/s. K. R. Constructions. V. Koteswara Rao, Managing Partner 3 Address for communication D. No: 10-50-5/23, G-5, Sunny side homes, Waltair main road, Visakhapatnam. 4 Telephone numbers 9848193123 5 Email ID of the organization or contact person [email protected] 6 Location of the Proposed project or activity M/s. K.R CONSTRCTIONS Sy. no: 125/P, Zone –II, East Point Colony, Near VUDA park, G.V.M.C Limits, Visakhapatnam, Andhra Pradesh

7 Appraisal Category (B2 or B1) B2 8 Nearest habitation and distance from the project or Lawson’s Bay Colony at 0.45 kms activity 9 Installed capacity / Production Capacities Construction of Residential Building in an area of 4453.81 Built up area – 29785.44 Sq.mts Stilt floor (I + II) = 2542.06 Sq. m Basement (1+2+3) – 6721.32 Sq.mts Building – (G + 1 - 16) = 20522.06 Sq.mts 10 Specify the Fuel (Coal / CNG / biomass/Others) and Diesel for Generators of capacity 60 quantity required KVA 11 Details of Land use/Land Cover The project involves construction of residential high rise building. Brief details enclosed in conceptual plan. 12 Occupancy, ownership of the land in which the Own land activity is proposed: (Government land / Private land / Forest land /Revenue land /Temple land /leased land/ land belongs to other Department) 13 If it is a Forest land, the following details shall be No forest area covers under the furnished: proposed site area. (Whether it is a Reserved forest / Protected forest/Demarcated forest/ National Parks/Sanctuaries/any land in possession of Forest Department.) (The village map with Sy. No. indicating nearest forest boundary line from the site shall be enclosed) 14 Total investment of the project/activity. Rs. 72.0Crores a. Funds allocated for EMP (capital cost and Rs. 144.1Lakhs recurring cost per annum) 15 Brief description of the project with special Enclosed reference to specific pollution and its control measures. 16 Compliance report on the following : i. Status of compliance of the conditions and Not applicable environmental safeguards stipulated in the earlier clearance letters.

ii. Details of the court cases, if any, pending in NIL any Court of Law against the project as well as any directions passed by the Court relating to the project directly or indirectly. iii. Details of the notices, if any, given to the NIL project under Section 5 of the Environmental (Protection) Act, 1986 and Section 18 of the Air (Prevention & Control of Pollution) Act, 1981. 17 Whether the project attracts the provisions laid No under the OM dt. 16.11.2012 issued by the MoE&F, GOI, w.r.t. violation of EIA Notification, 2006 and its amendments thereof? (Yes/No) Present stage and status of the project: Construction not yet started 18 Name of the Consultant: SV Enviro Labs & Consultants, Visakhapatnam

FORM- 1A

1. LAND ENVIRONMENT S. No. ITEM COMPLIANCE 1.1 Will the existing land use get significantly The earmarked for Construction of altered from the project that is not residential high rise building in an area of consistent with the surroundings? 4453.81Sq.m (Proposed land use must conform to the Built up area – 29785.44.0Sq.mts approved Master Plan / Development Plan Further the above land is barren land. of the area. Change of land use if any and Therefore no change in land use / land the statutory approval from the competent cover / topography. authority be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii)the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. 1.2 List out all the major project requirements Area statement in terms of the land area, built up area, Built up area – 29785.44 Sq.mts water consumption, power requirement, Stilt I (GL) = 1271.03 Sq.m connectivity, community facilities, parking Stilt II (GL) = 1271.03 Sq.m needs etc. First Basement (BGL) – 2240.44 Sq.mts Second basement (BGL) = 2240.44 Sq.mts Third Basement (BGL) = 2240.44 Sq.mts Ground +16 upper Floor = 20522.06Sq.m Utilities 1. Water supply: Required fresh water of about 60.50 KLD during operation time will be met from the GVMC. 2. The required power will be met from APEPDCL. The connectivity is from nearby transformer. 3. Adequate site has been provided Sewage treatment plant, road network and DG room. 4. Light motor vehicles / car parking will be provided. 1.3 What are the likely impacts of the proposed There is no impact on the various facilities activity on the existing facilities adjacent to adjacent to the project site. the proposed site? (Such as open spaces, community facilities, details of the existing land use, disturbance to the local ecology). 1.4 Will there be any significant land The land is essentially a leveled ground, disturbance resulting in erosion, subsidence free from erosion or subsidence. & instability? (Details of soil type, slope The terrain is highly stable and does not analysis, vulnerability to subsidence, have possibility of erosion, subsidence or seismicity etc may be given). instability including vulnerability to city. 1.5 Will the proposal involve alteration of There is no alteration of natural drainage. natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site) 1.6 What are the quantities of earthwork Earth work – 150 m3 involved in the construction activity- No fill material from out side cutting, filling, reclamation etc. (Give The excavated earth will be used for filling details of the quantities of earthwork the basement. involved, transport of fill materials from outside the site etc.) 1.7 Give details regarding water supply, waste The water for construction is being handling etc during the construction period. received from existing water sources like bore wells and the waste water 1.8 Will the low lying areas & wetlands get The low lying and wetland do not exist. altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity) 1.9 Whether construction debris & waste The site is a vacant land and contains no during construction cause health hazard? construction waste. (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal)

2. WATER ENVIRONMENT S.No. ITEM COMPLIANCE 2.1 Give the total quantity of water requirement During operation for the proposed project with the breakup of Domestic requirements for various uses. How will the Fresh water– 60.50 KLD water requirement met? State the sources & Waste water generation: 54.50KLD quantities and furnish a water balance statement. 2.2 What is the capacity (dependable flow or The source is municipal water and consists yield) of the proposed source of water? of adequate ground water reserves. 2.3 What is the quality of water required, in The quality of the ground water is good case, the supply is not from a municipal and potable. The physiochemical analysis source? (Provide physical, chemical, of the ground water reveals all the biological characteristics with class of water parameters are well within the permissible quality) limits. 2.4 How much of the water requirement can be 100% of the waste water will be treated at met from the recycling of treated the Sewage treatment plant and 40% will be wastewater? (Give the details of quantities, used for green belt development and sources and usage) recirculation. Water source: Municipality 2.5 Will there be diversion of water from other There is no diversion of water from other users? (Please assess the impacts of the users. project on other existing uses and quantities of consumption) 2.6 What is the incremental pollution load from The characteristics of the treated sewage wastewater generated from the proposed will meet the on land for plantation limits as below: activity? (Give details of the quantities and Parameter Raw Treated composition of wastewater generated from pH 6.8-7.2 7.5-7.8 BOD 300-350 < 30 the proposed activity) COD 400-500 < 50 TSS 200-600 <0.5 TDS 1400-1700 < 1200 All values expressed in mg/l except pH. 2.7 Give details of the water requirements met Rain water harvesting will be implemented from water harvesting? Furnish details of from rooftops, channeled to the harvesting the facilities created. pits through appropriate piping systems. The storm water drains also would have recharging pits along the length of the drains for recharging the ground water. 2.8 What would be the impact of the land use There is no impact of the land use change changes occurring due to the proposed on the runoff characteristics. Care has been project on the runoff characteristics taken to ensure that the built up area is as (quantitative as well as qualitative) of the per the specifications of the municipal area in the post construction phase on a long regulatory authorities and no way has it term basis? Would it aggravate the problems affected the surface runoff characteristics. of flooding or water logging in any way? 2.9 What are the impacts of the proposal on the There will not be any impact on ground ground water? (Will there be tapping of water. ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any) 2.10 What precautions/measures are taken to The runoff from the construction activities prevent the run-off from construction are routed through water drainage network. activities polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts) 2.11 How is the storm water from within the site The runoff from the construction activities managed?(State the provisions made to are routed through water drainage network avoid flooding of the area, details of the and disposed through water disposal drainage facilities provided along with a site system. layout indication contour levels) 2.12 Will the deployment of construction Local manpower will be utilized for the labourers particularly in the peak period lead construction work. Therefore no temporary to unsanitary conditions around the project site used for construction works. site (Justify with proper explanation) 2.13 What on-site facilities are provided for the The sewage that collected from the flats collection, treatment & safe disposal of will be routed to sewage treatment plant sewage? (Give details of the quantities of and further to municipal sewerage wastewater generation, treatment capacities network. with technology & facilities for recycling and disposal) 2.14 Give details of dual plumbing system if A separate line will be installed in the treated waste used is used for flushing of water closet for operating with treated toilets or any other use. sewage.

3. VEGETATION S.No. ITEM COMPLIANCE 3.1 Is there any threat of the project to the There is no threat to the bio-diversity due biodiversity? (Give a description of the to the project as the site is devoid of local ecosystem with it’s unique features, vegetation. The land is a degraded and if any) unutilized land which does not consists of any specific/unique features of the eco- system. 3.2 Will the construction involve extensive The proposed site is devoid of vegetation clearing or modification of vegetation? and is a barren land. Hence, there are no (Provide a detailed account of the trees & such impacts on native species and on vegetation affected by the project) genetic diversity. 3.3 What are the measures proposed to be It is proposed to develop plantation along taken to minimize the likely impacts on the boundary walls. important site features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale)

4. FAUNA S.No. ITEM COMPLIANCE 4.1 Is there likely to be any displacement of The project area does not have any fauna fauna- both terrestrial and aquatic or both terrestrial and aquatic. There is no creation of barriers for their movement? reporting of wild life. As such there is no Provide the details. impact on terrestrial & aquatic fauna. There are no water bodies in the site. 4.2 Any direct or indirect impacts on the There is no impact on the avifauna. avifauna of the area? Provide details. 4.3 Prescribe measures such as corridors, fish There is no such activity and as such these ladders etc to mitigate adverse impacts on are not provided. fauna

5. AIR ENVIRONMENT S. No. ITEM COMPLIANCE 5.1 Will the project increase atmospheric There is no source for emissions as this is concentration of gases & result in heat not a processing industry. islands? (Give details of background air The emissions expected are from quality levels with predicted values based generators only. The generator will be on dispersion models taking into account operated whenever power fails and will be the increased traffic generation as a result run on HSD. of the proposed constructions) 5.2 What are the impacts on generation of There will not be any generation of dust, smoke, odorous fumes or other hazardous gases. hazardous gases? Give details in relation to all the meteorological parameters. 5.3 Will the proposal create shortage of There is no shortage of parking place. parking space for vehicles? Furnish details Adequate space has been provided for of the present level of transport parking lot exclusively for the usage of infrastructure and measures proposed for the proposed tourism project site during improvement including the traffic construction as well as in operation phase. management at the entry & exit to the project site. 5.4 Provide details of the movement patterns The internal roads would have pedestrian with internal roads, bicycle tracks, pathways and footpaths with adequacy to pedestrian pathways, footpaths etc., with meet the requirement of the tourists. areas under each category. 5.5 Will there be significant increase in traffic There will be a marginal increase of noise & vibrations? Give details of the traffic noise, but measures have been sources and the measures proposed for proposed for mitigation of this noise mitigation of the above. through an extensive plantation along the boundary wall. 5.6 What will be the impact of DG sets & The DG set will be housed in an acoustic other equipment on noise levels & enclosed room to reduce the noise levels vibration in & ambient air quality around and it will be mounted on anti-vibration the project site? Provide details. mounting pads to reduce vibration levels.

6. AESTHETICS S.No. ITEM COMPLIANCE 6.1 Will the proposed constructions in any Care has been taken to improve the way result in the obstruction of a view, Aesthetics, particularly in respect of scenic amenity or landscapes? Are these landscape and there is no obstructions are considerations taken into account by the created. proponents? 6.2 Will there be any adverse impacts from The impact of the proposed construction new constructions on the existing activity on the surroundings will be structures? What are the considerations minimum as it is away from the existing taken into account? structures. 6.3 Whether there are any local considerations Not applicable of urban form & urban design influencing the design criteria? They may be explicitly spelt out. 6.4 Are there any anthropological or There are no sites of anthropological or archaeological sites or artifacts nearby? archeological importance within and State if any other significant features in the around the site. vicinity of the proposed site have been considered.

7. SOCIO-ECONOMIC ASPECTS S.No. ITEM COMPLIANCE 7.1 Will the proposal result in any changes to There will not be any changes to the the demographic structure of local demographic structure of local population? Provide the details. populations, as it is a tourism project and the socio economic power of the surroundings will increase. 7.2 Give details of the existing social Majority of the people are agricultural infrastructure around the proposed project. labor and marginal workers. 7.3 Will the project cause adverse effects on There are no sacred sites or of cultural local communities, disturbance to sacred value sites within 10 km radius of the sites or other cultural values? What are the proposed tourism project. safeguards proposed?

8. BUILDING MATERIALS S.No. ITEM COMPLIANCE 8.1 May involve the use of building materials The construction materials like cement, with high-embodied energy. Are the bricks, concrete and sand will be procured construction materials produced with from local authorized vendors. energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency) 8.2 Transport and handling of materials during The material will be transported through construction may result in pollution, noise covered trucks and water sprinkling will & public nuisance. What measures are be taken to suppress the dust arise from taken to minimize the impacts? construction materials. 8.3 Are recycled materials used in roads and Usage of fly ash for road development structures? State the extent of savings from the local power plants is being achieved? envisaged. 8.4 Give details of the methods of collection, The municipal solid waste from the segregation & disposal of the garbage proposed project will be converting to generated during the operation phases of manure and reuse for gardening. the project.

9. ENERGY CONSERVATION S.No. ITEM COMPLIANCE 9.1 Give details of the power requirements, The proposed project will utilizes about source of supply, backup source etc. What 45 KVA power for its utilities from is the energy consumption assumed per square foot of built-up area? How have APEPDCL. you tried to minimize energy consumption? 9.2 What type of, and capacity of, power back- DG sets will be kept as standby to overcome the power failure if any. up to you plan to provide? 9.3 What are the characteristics of the glass Type of glass: High Efficiency Low e- you plan to use? Provide specifications of Glass(Solar screen 2000 VEI-2TM) with its characteristics related to both short specifications: wave and long wave radiation? Glass Thickness-0.25 Inches Visible Transmittance(%Daylight)-70 U-factor(Winter)-0.29 Solar Heat Gain Coefficient(SHGC)- 0.37 9.4 What passive solar architectural features Passive features include special glass are being used in the building? Illustrate panels for absorption of solar radiation. the applications made in the proposed project. 9.5 Does the layout of streets & buildings Yes, the layout of streets & buildings maximize the potential for solar energy maximize the potential for solar energy devices? Have you considered the use of devices. And the power utilized for the street lighting, emergency lighting and street lights and hot water systems. solar hot water systems for use in the building complex? Substantiate with details. 9.6 Is shading effectively used to reduce External shading is being provided in the cooling/heating loads? What principles design. have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected? 9.7 Do the structures use energy-efficient ENERGY CONSERVATION space conditioning, lighting and Double Glazing mechanical systems? Provide technical It is decided to use double glazing to details. Provide details of the transformers reduce the heat transmission through the and motor efficiencies, lighting intensity glass. and air-conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications. 9.8 What are the likely effects of the building Microclimate betterment would be activity in altering the micro-climates? achieved through proper emission Provide a self assessment on the likely control as well as environmental impacts of the proposed construction on greening programme. creation of heat island & inversion effects? 9.9 What are the thermal characteristics of the The exposed roots will be insulated with building envelope? (a) roof; (b) external under deck insulation. Cellar areas in the walls; and (c) fenestration? Give details of basement and staircase are mechanically the material used and the U-values or the R ventilated and with fire escape systems. values of the individual components. 9.10 What precautions & safety measures are Firefighting equipment proposed against fire hazards? Furnish  Sand buckets details of emergency plans.  Fire alarm  Fire escape (Stair case)  Smoke detectors  Automatic water sprinklers 9.11 If you are using glass as wall material No provides details and specifications including emissivity and thermal characteristics. 9.12 What is the rate of air infiltration into the No air filtration into the building. building? Provide details of how you are mitigating the effects of infiltration. 9.13 To what extent the non-conventional Solar energy will be used for street energy technologies are utilized in the lightings & for hot water. overall energy consumption? Provide details of the renewable energy technologies used.

(III) ENVIRONMENTAL MANAGEMENT PLAN

S.No. ITEM COMPLIANCE 1 The Environment Management Plan would Environmental Management Plan will consist of all mitigation measures for each be implemented during the construction item wise activity to be undertaken during phase as well as during operational the construction, operation and the entire phase. life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.