Connect Plus and M25 Widening and operating ’s orbital motorway Connect Plus and the M25 | Widening and operating London’s orbital motorway Overview

Connect Plus is a Skanska-led availability London and to two of the world’s busiest payment-based design, build, finance and airports (Heathrow and Gatwick), plus the operate (DBFO) Public Private Partnership road’s 1,800 structures, including 750 bridges (PPP) designed to add capacity to the M25, and 150 gantries, five tunnels and one long span London’s orbital motorway, which carries bridge. The 30-year concession with the UK's 15% of the UK’s motorway traffic, or 200,000 (formerly the Highways vehicles a day. The construction project Agency) is one of the UK’s largest ever PPPs. included four components: Construction was completed in two phases: • Widening 38 miles of highway to four lanes, the first in 2012 in time for the London in four sections Olympics, and the second in 2014. Operation • Refurbishing a three-quarter-mile, two- and maintenance are ongoing, and the bore tunnel concession runs from May 2009 to September • Widening and converting a further 28 miles 2039, with services having started in September into the UK’s first 2009 on financial close. The entire contract • Removal of the toll plazas and cash was worth US$9.78bn* at Financial Close. collection at the Crossing Construction accounts for $2.17bn of this and lifecycle/operations and maintenance (O&M) The partnership also includes operation the remainder. and maintenance of the whole 117 miles of the M25’s existing and new road, as well as * Exchange rate based on prevailing rates, from British Pound to a further 117 miles of ‘stubs and tails’ into US Dollar, at Financial Close.

Skanska ID M25 case study 2 Connect Plus and the M25 | Widening and operating London’s orbital motorway

Skanska has 40% ownership in Connect The $2.01bn project funding was made up of Plus (an investment of $124m), alongside $1.43bn of floating rate senior debt provided Balfour Beatty (40%), Egis (10%) and Atkins by 16 commercial banks, a separate $285m (10%). Construction was delivered by a 50/50 facility from the European Investment Bank construction joint venture between Skanska and $309m provided by the shareholders of UK and Balfour Beatty, where Skanska’s share Connect Plus. A complex series of interest rate of the contract was $1.08bn. Connect Plus has swaps saved $465m on the cost of borrowing. responsibility for lifecycle management, with operations and maintenance (O&M) being The construction project was delivered early delivered by Connect Plus Services, a joint and to budget, despite additional availability venture between Balfour Beatty (52.5%), pressure created by the 2012 Olympics, which Atkins (32.5%) and Egis (15%). used the M25 as the key route from Heathrow to the Olympic Park. The lifecycle/O&M Financing this immense project was associated with such a vast, complex and aging challenging, as negotiations took place in asset have been more challenging. But a unitary the teeth of the global financial crisis and charge linked to inflation has allowed Connect immediately after the collapse of Lehman Plus to invest beyond its contract in renewal, Brothers. With the cost of debt soaring and safety and capacity, and to maintain its key the appetite for risk low, Skanska took the target of 50mph across the whole motorway. lead in negotiations, bringing together a wide group of lenders and developing a risk profile that satisfied the Highways England client.

Skanska ID M25 case study 3 M10 A1(M)

21 22 20 M25 Connect Plus and the M25 | Widening and operating London’s orbital27 motorway 24 25 26 1 19 18 17

M11 28

M40 29

16 1a M25

30 M4 15 M4 4b London 31 14 Heathrow 1a Airport 1b 13 2

M3 12 2 3 11 4 M20 M3 10 9 M26 M25 5

7 8 8 6

Gatwick Airport

Transportation Sector M25 Junction 18 to 21 (12 km) widening Highway and interchanges Section 1z M25 Junction 21 to 23 (13 km) widening Project Details Section 4 Complex Design-Build contract M25 Junction 27 to 30 (25 km) widening DBFO PPP in the UK Section 6 Large financing size Hatfield Tunnel refurbishment Large participation by developer/contractor All completed September 2012

Reference Design, construction and finance Highways England (formerly the Highways of Phase two - the Later Upgraded Agency) Sections (LUS), including: The project in figures Section 2 Concession: 2009-2039 M25 Junction 5 to 7 (17 km) widening Construction: 2009-2014 Section 5 Construction: Skanska 50% M25 Junction 23 to 27 (27 km) widening Construction value to Skanska: $1.08bn All completed December 2014 Skanska investment: $124m Payment Mechanism: Availability Shareholding: Connect Plus Consortium – Date of Financial Close: May 20, 2009 Skanska (40%), Balfour Beatty (40%), Atkins Construction Start Date: Early works started (10%), Egis (10%) before FC (Jan 2009 Early works agreement) Skanska Balfour Beatty construction JV – Concession Period Length: 30 years Skanska (50%), Balfour Beatty (50%) Concession Period Year End: 2039 Project Value at time of Financial Close Design, construction and finance $9.78bn of Phase one - the Initial Upgraded Equity Investment/Financing Size at time of FC: $309m/$1.71bn senior debt Sections (IUS), including: ID’s Equity Investment at time of FC (and Section 1x percentage): $124m (40%) M25 Junction 16 to 18 (12 km) widening O&M Value at time of FC: $7.6bn Section 1y Debt/Gearing 85:15

Skanska ID M25 case study 4 Connect Plus and the M25 | Widening and operating London’s orbital motorway

The challenge

London’s 117-mile M25 is one of the world’s • The contract also includes the operation largest orbital motorways. Originally intended and maintenance of the new and existing as an orbital bypass of the city for long distance sections of the M25 and a further 117 miles traffic, the road’s design included numerous of associated stretches of motorway and junctions that have attracted local and trunk roads and the commuter traffic. for 30 years

Since its completion in 1986, the M25 has The widening work was completed on behalf become increasingly congested, carrying of Connect Plus by the Skanska Balfour 200,000 vehicles a day, of which 50% use the Beatty Joint Venture (SBBJV) in two phases, M25 to travel to and from work. For many supported by designer Atkins, alongside the years, the M25 was often called ‘the world’s Hyder Halcrow Joint Venture acting as the biggest parking lot’. client’s representative.

In May 2009, the Highways England awarded The benefits of the scheme include: the Skanska-led consortium Connect Plus a • Improved and more reliable journey times 30-year DBFO contract to add capacity to the • Reduced congestion M25 and manage it and key arterial link roads. • Enhanced motorway safety • Better driver information • An initial project to widen two sections of • Faster-flowing traffic at the Dartford Crossing the road to four lanes by adding 38 miles of new road, plus refurbishing the Hatfield At the peak of construction, the team Tunnel on the A1(M), was completed in delivered a mile of road a month at a cost 2012 in time for the London Olympics of $1.55m per day, employing between • A second phase of widening was 3,500 and 4,000 people. completed in 2014, adding 28 more miles of road to two sections, which have also During the life of the concession, we been converted to smart highway, and are spending around $3m per week converting the tolled Dartford Crossing to on lifecycle and maintenance, with a freeflow system 700 permanent jobs.

Skanska ID M25 case study 5 Connect Plus and the M25 | Widening and operating London’s orbital motorway

A major construction programme Phase one • 38 miles of road widened • 39 emergency telephones • 35 months • 167 overhead signals • 125 gantries, including 44 super-span • 91 verge mounted signs gantries • 95 CCTV cameras • 2,168,092m3 of material excavated and recycled Phase two was completed as part of the • 58 miles of sheet piling to retain the Connect Plus Smart Motorway All Lanes embankment Running (SM-ALR) initiative, the UK’s first • 350 miles of cable highway of this type, which also developed • 124 miles of drainage and deployed cutting edge technology. Under • 360,000m3 of concrete SM-ALR, the hard shoulder is permanently • 500,000 tonnes of recycled road planings converted into a traffic lane on these sections • 11,872,000 man-hours worked of the motorway and replaced by regularly • Two three-quarter mile bores at Hatfield spaced emergency refuge areas, each one with Tunnel refurbished to EU standards an emergency telephone. CCTV cameras help • 170 miles of cabling and 56 jet fans installed the operations room to spot incidents and deal in the tunnel with them as fast as possible. Other innovative technologies used include LED signs, radar Phase two vehicle detection and remote diagnostics. • Two new sections converted to ‘all-lane running’ For vehicles which can’t make it to an • 28 miles of new road emergency refuge, smart motorway technology • Delivered 22 weeks early, saving 25% of allows the closure of any lane by the display program duration of a red “X” on the gantries, moving traffic • $37m cost saving shared with client away from the incident and keeping it clear for • 9 gantries that span both carriageways emergency vehicles. • 23 refuge areas

Skanska ID M25 case study 6 Connect Plus and the M25 | Widening and operating London’s orbital motorway

All-lane running increases the capacity of the • Consultation with regulatory and advisory motorway to reduce congestion and makes bodies journeys more reliable at a considerably lower • Moving species and habitats that might be cost and with less disruption than a traditional affected road widening scheme. • Assessment of ecological information to inform the detailed design of the work Collaborative planning with our supply chain and Highways England client allowed us to The following measures helped to minimize reschedule the program for concurrent working disruption caused by construction work: on two phases, which helped us deliver the • Use of the quietest possible plant and project 22 weeks early at a saving of $37m, construction methods which we shared 50/50 with the client. • Controlling dust by covering vehicles carrying dry, dusty materials and mechanically sweeping hard surfaces and Sustainability and exits onto public roads environmental • Use of low noise surfacing materials • Noise and visual protection management A bespoke materials and waste strategy was The M25 DBFO partners were committed designed to maximize the use of recycled, to working in the most environmentally secondary and manufactured aggregates responsible manner. Before starting work, the in preference to primary aggregates. This project team carried out a full environmental approach diverted significant quantities of impact assessment including ecological and material from landfill, reducing traffic impact archaeological surveys. The comprehensive on the local network as well as enhancing the environmental management plan they overall sustainability of the project. produced took into account: • Ecological works to protect plants and Phase one used a total of 2,300,000 tonnes, wildlife including 1,200,000 tonnes of material

Skanska ID M25 case study 7 Connect Plus and the M25 | Widening and operating London’s orbital motorway

processed on site from inert construction and of embodied carbon – saved by value demolition waste, imported from other projects engineering during pavement design in the south . This represents • 125,670 trees, 28,000 shrubs planted 92% recycled content for bulk materials • major grassland planting and a saving of 35,000 tonnes of embodied • 400 bird boxes carbon. Where use of primary aggregate was • 2,800+ animals moved unavoidable, responsible procurement was undertaken in line with BES 6001. Phase two of the project continued this environmental performance, reducing our A supplementary earthworks strategy carbon footprint by 80% against traditional retained 100% of inert material on site. road widening programs and savings Over 1,800,000 tonnes of surplus inert soil approaching $17m per mile completed. was diverted from landfill and reused to create eight environmental bund structures at appropriate locations. Saving the client money through value These environmental bunds provide visual and noise screening to nearby residential areas with engineering and up to 5dB reduction in traffic noise. The bunds were designed to enable the slope facing away alternative technical from the motorway to be returned to agriculture. solutions

Key statistics Throughout construction, our team was alerted • 2,200,000 tonnes of high-quality aggregates to the potential to save our client money produced on site – 98% recycled materials through a variety of technical and value • 250,000 tonnes of glass sand used for engineering measures. Some of the most drainage and backfill, saving virgin effective of these were: aggregates • King Sheet Piling – our innovative, • 320,000 tonnes of asphalt – 15,000 tonnes patent pending King Sheet Pile (KSP)

Skanska ID M25 case study 8 Connect Plus and the M25 | Widening and operating London’s orbital motorway

system reduces the quantity of steel by retaining wall was adopted as a preferred 33% and eliminates 45,000 tonnes of widening solution in the verges, with embodied carbon, as well as allowing communications installed behind the wall. faster construction. The system replaces Walls up to 2.3m were constructed by this alternative pairs of the traditional, heavy process, which is believed to be the highest piles used in the construction of hard slipformed wall in Europe. The slipforming retaining walls with lighter, thinner process was faster than other widening and shorter piling sections spanning options and the resulting narrower verge horizontally between the remaining full- reduced excavation volumes and overall length sheet piles. The 15 miles of wall CO₂ emissions. This technique has also installed on the M25 has saved up to been used for slot drains, surface water 33% of steel and delivered a four-fold channels and pavement widening. increase in productivity in the chalky earth between junctions 16 to 23 of the road, as • Smart motorway – Phase two of the well as doubling overall installation speed. road widening program converted the The sheet piles were sourced from 100% sections of highway concerned to a ‘smart scrap steel using a highly efficient electric motorway’, which uses the hard shoulder arc furnace, reducing the embodied carbon as a permanent lane, and replaces it with by 75%. regularly spaced refuges. This saves a substantial proportion of cost as seen by the • Slipforming – Innovative slipform concrete comparison between phases one and two: processes incorporated ducting into the o Phase one – road widened and 38 miles central safety barrier during installation. added – $1.55bn This carries the miles of cable required to o Phase two – converted to all-lane connect the motorway’s lighting columns. running and 28 miles added – $621m A much higher slipformed concrete

Skanska ID M25 case study 9 Connect Plus and the M25 | Widening and operating London’s orbital motorway

Our approach to collaborative planning The same laser scanning data were used to also saved a further $37m on the bid price identify a temporary works clash with the by delivering the highway 22 weeks early, existing structure. A constructed model which reduced the program duration by of the existing structure was compared 25% and saved $37m. to the second drawings, which allowed early identification of discrepancies and • Building Information Modeling (BIM) allowed the design to be adapted before and Laser scanning – we have used laser construction, avoiding delay, duplication of scanning techniques to improve worker work and reordering materials. safety and deliver cost, program and CO₂ emissions savings. Survey data from laser scans were used to redesign Keeping traffic running the carriageway over Ockendon Railway on this hugely busy Bridge, located between junctions 29 and 30, which kept trains running while the highway work was carried out. The engineering team initially produced laser scan data to While some disruption during construction investigate the design and sequencing of was unavoidable, our team minimized the widening works across the bridge, which impact of our work on local communities, saved repeat journeys to the site. As the keeping delays to a minimum and protecting scan was completed from a place of safety the environment while prioritizing the safety of away from the live carriageway and railway our workforce and the public. boundary, the program gained 18 weeks by eliminating the need for a three-night The fast paced program required both day and railway possession. night working; at peak the team was working

Skanska ID M25 case study 10 Connect Plus and the M25 | Widening and operating London’s orbital motorway

24 hours a day/7 days a week. Advance notice the hard shoulder. These risks were carefully was routinely given for all lane and slip road managed through risk assessments and closures, in agreement with local motorway effective controls, combined with an ethos that police. Several principles were strictly followed: united the project delivery partners behind • The need to maintain three lanes in the aspiration of achieving a completely contraflow injury-free environment and a shared vision • Overnight and slip road closures as of what constitutes good safety practice. These necessary principles supported the Highways England’s • Temporary 50mph running with average ‘Aiming for Zero’ health and safety strategy. speed enforcement • Regular liaison with local police and The 24-month refurbishment of the highways maintenance stakeholders Hatfield Tunnel was completed with • 24/7 free recovery available from the no accidents, lost time injuries or dangerous carriageway occurrences reported under the UK regulatory • Customer care unit where motorists framework RIDDOR, totaling almost 1 million could wait in safety for their own recovery incident-free man-hours. The project team’s service. The unit included a kitchen area, vigilance and devotion to safe working was vending machines, playhouse and toys for commended with a Gold RoSPA* Award in children, payphone, TV and toilets with 2011 and shortlisting in the NCE International baby changing facilities Tunneling Award for industry leading achievements in safety. Phase two of the The widening works required a stringent program completed 1.2 million man-hours safety strategy due to the close proximity of without a reportable incident. road workers, plant and site vehicles to the live network and within the limited space of *The Royal Society for the Prevention of Accidents

Skanska ID M25 case study 11 Connect Plus and the M25 | Widening and operating London’s orbital motorway

However, although our safety record was network of 234 miles, including five tunnels exceptional, the inherent danger of the project and the Queen Elizabeth II (QE2) Bridge. Our was demonstrated by a fatality in 2010, which contract specifies that at the end of our 30 led to prosecutions of a subcontractor and an year concession we must hand back the whole individual last year, and another incident that network in a condition no worse than when we resulted in a double amputation. To reinforce took it over. the role of safety at the heart of the project, the construction joint venture (CJV) partners Around-the-clock monitoring captures all share information about safety alerts from their aspects of the network’s performance, and whole organizations, not just the M25. a Travel Time Monitoring System helps us deploy our resources to tackle congestion, ease traffic flow and identify potential improvement Operation and initiatives. We use GPS technology to track the Maintenance – position of our 16 incident support vehicles (ISUs) and winter maintenance fleet, which a journey of discovery enables a more dynamic approach to incident and winter service management. In addition to undertaking major improvement and lifecycle works, Connect Plus is With our target of traffic flow at 50mph, responsible for the operation and routine and substantial financial penalties for not maintenance of the M25 and key spur roads. maintaining this or closing lanes, we have From two control centers and a network clear priorities and over 8,000 contractual of seven depots, 700 employees interface obligations. However, the road is immense, closely with Highways England, managing a with tens of thousands of different components,

Skanska ID M25 case study 12 Connect Plus and the M25 | Widening and operating London’s orbital motorway

from 6,000 signs and 18,000 lamp standards primary transport corridor for 2012 London (complete with light bulbs) to the Dartford Olympics, but only 12 weeks before the games Crossing, made up of two, two-lane tunnels and were due to start, we discovered cracks on the four-lane, 812m cable-stayed QE2 Bridge. a major steel ramp and were forced to close the road in the face of considerable opposition Such a vast and complex network, much from senior members of the government. By of it dating back to 1986, had many secrets bringing together an emergency team and that were not uncovered until Connect Plus using advanced laser scanning techniques that began work in earnest on the O&M contract. had never been tried in construction before, The ongoing ‘journey of discovery’ by the we were able to map the existing structure, lifecycle and maintenance teams has unearthed with all its complex load-bearing distortions, major challenges ranging from a lack of and mill steel plates that would reinforce standardization that means maintenance it. Under intense political pressure, which crews can’t carry enough equipment to have demanded photographs of daily progress for the right tools for every job, to construction the Prime Minister, we resolved the situation through chalky terrain and major structural and opened the road the day before the first faults that threaten lives. A brief selection of visitors arrived. We invested the cost of the the challenges we have faced and the way we repairs ($10m+) as part of our commitment have responded with investment from our own to safety. finances and an attitude that seeks innovation in adversity include: • QE2 Bridge joints replacement – every bridge has joints that enable it to ‘breathe’, expanding • Potential ramp collapse in the run up to the or contracting in response to temperature 2012 London Olympics – the M25 was the changes. When the O&M team started work

Skanska ID M25 case study 13 Connect Plus and the M25 | Widening and operating London’s orbital motorway

on the M25 they discovered that the joints them, it’s still not clear approaching six years on QE2 were old and fatigued and needed after financial close, exactly what makes up replacing. There were two issues: the network. To address this, Connect Plus o The cost fo replacing these 19m x 1m is investing $4m in an asset management grids was not included in the original system, which will be used to store details contract, but they could be crucial to the about all the individual elements on the safe operation of the bridge – Connect M25, support maintenance and manage Plus would have to invest risk. Connect Plus is working with the US o The potential disruption to traffic caused supplier of the system, AMSIT, to create by closing lanes to replace the joints one of the world’s most advanced highways threatened to expose us to massive management systems, with two financial penalties main capabilities: o Routine management data based on the Our solution was to research the market condition scoring required by our client, carefully and select high quality joints that Highways England were expensive at more than $10m but that o Decision support – where we input would only need to be replaced this one time scenarios and the system identifies in the 30-year concession. Beyond that, we various ways of optimizing them developed a way of working on the bridge at night and under it during the day, we Again, the cost of this system was not replaced the grids over the course of two included in our contract, but we believe it summers without slowing down the traffic. will deliver major across a program that is currently costing $3.1m per week. • Asset management system – with over 60,000 separate components and a contract to hand them back in as good a condition as we found

Skanska ID M25 case study 14 Connect Plus and the M25 | Widening and operating London’s orbital motorway

Awards

• Institute of Civil Engineers Health & Safety Project of the Year 2014 • Construction News Sustainable Project of the Year award 2014 • RoSPA Gold Award for Occupational Health & Safety 2011 • Institute of Civil Engineers Merit Award 2010 • Brownfield Briefing • Construction News Environmental Project of the Year (shortlisted) • National Recycling Award • International Green Apple: Environmental Best Practice and Bronze award 2011 • Considerate Constructors Scheme: 5 Silver and 1 Bronze awards to date; ‘Performance Beyond Compliance’ • Recycling Stars Gold award • CEEQUAL, 87% Excellent

Skanska ID M25 case study 15 Skanska Infrastructure Development www.skanska.com/ppp United States 99 Canal Center Plaza Alexandria, VA, 22314 United States +1 703 340 1200 One London Wall London EC2Y 5HB United Kingdom +44 207 429 4200 Sweden Warfvinges väg 25 112 74 Stockholm Sweden +46 10 448 00 00