1.1.1

Gwent Farmers’ Community Solar Scheme September 2017

Environmental Statement

Gwent Farmers’ Community Solar Scheme

Land on the Caldicot Levels, South of Steel Works, Nr Newport,

www.savills.co.uk

Project: Gwent Levels Farmer’s Community Solar Scheme

Client: Gwent Farmers’ Community Solar Scheme Ltd

Job Number: 1045592

File Origin: Taunton

Document Checking:

Prepared by: Nick Beddoe Signed:

Checked by: Peter Grubb Signed:

Verified by: Peter Grubb Signed:

a

Contents

1.0 Introduction ...... 1

1.1 The Project ...... 1

1.2 Background to screening and scoping for EIA ...... 1

1.3 The Environmental Statement ...... 2

1.4 Professional expertise...... 3

2.0 The Site and Designations ...... 5

2.1 The Site ...... 5

2.2 Ecological Designations ...... 6

2.3 Gwent Levels Historic Landscape ...... 8

2.4 Severn Estuary Designations ...... 9

2.5 Public Rights of Way ...... 12

2.6 Heritage and Archaeological Designations ...... 13

2.7 Flood Risk ...... 13

3.0 The Proposed Development ...... 15

3.1 The Development ...... 15

4.0 Planning Policy Framework ...... 19

4.1 Introduction ...... 19

4.2 National Policy ...... 19

4.3 Energy Wales: A Low Carbon Transition ...... 21

4.4 Planning Policy Wales (Edition 9, 2016) ...... 21

4.5 Technical Advice Notes ...... 25

4.6 Practice Guidance: Planning for Renewable and Low Carbon Energy - A Toolkit for Planners ... 26

4.7 Newport Local Development Plan 2011 – 2026 ...... 27

4.8 Newport Local Development Plan – Proposals and Constraints Maps ...... 32

4.9 Renewable and Low Carbon Energy Assessment: Torfaen County Borough Council and Newport

City Council ...... 34

4.10 Capacity ...... 35

b

4.11 Targets ...... 35

4.12 Identified Opportunities ...... 36

5.0 Consultation ...... 38

5.1 Statutory Stakeholders...... 38

5.2 Public Consultation ...... 38

6.0 Site Selection and Alternatives ...... 39

6.1 Site Selection ...... 39

6.2 Site Credentials ...... 39

6.3 Deliverability of the Scheme ...... 41

6.4 Comparative Land Take Assessment ...... 42

6.5 Summary ...... 44

7.0 EIA Approach ...... 45

7.1 Background ...... 45

7.2 Screening ...... 45

7.3 Scoping ...... 46

7.4 Methodology ...... 48

8.0 Traffic and Transport ...... 51

8.1 Introduction ...... 51

8.2 Vehicular Access Arrangement ...... 51

8.3 Construction Traffic Management Measures ...... 55

9.0 Cultural Heritage ...... 59

9.1 Introduction ...... 59

9.2 Assessment Criteria and Methodology ...... 60

9.3 Scoping Opinion ...... 62

9.4 Legislative Context ...... 62

9.5 Planning Policy and Guidance ...... 63

9.6 Baseline Data Collection ...... 71

9.7 Assessment Methodology ...... 72

9.8 Technical Scope ...... 78

9.9 Temporal Scope ...... 80

9.10 Assumptions & Limitations ...... 80

c

9.11 Consultation ...... 80

9.12 Baseline Environment ...... 80

9.13 Statutory and local heritage designations ...... 82

9.14 Archaeological and Historical Context ...... 86

9.15 Inherent Design Mitigation ...... 90

9.16 Potential Environmental Impacts and Effects ...... 92

9.17 Additional Mitigation, Compensation and Enhancement Measures ...... 99

9.18 Residual Environmental Impacts and Effects ...... 100

9.19 Cumulative Effects ...... 101

9.20 Assessment Summary ...... 104

10.0 Landscape and Visual Effects ...... 107

10.1 Introduction ...... 107

10.2 Assessment Criteria and Methodology ...... 107

10.3 Planning Policy and Guidance ...... 108

10.4 Local Planning Policy ...... 112

10.5 Guidance/ Best Practice ...... 115

10.6 Baseline Data Collection ...... 117

10.7 Consultation ...... 129

10.8 Baseline Environment ...... 130

10.9 Inherent Design Mitigation ...... 142

10.10 Potential Environmental Impacts and Effects ...... 142

10.11 Effects on Visual Amenity ...... 154

10.12 Additional Mitigation, Compensation and Enhancement Measures ...... 174

10.13 Cumulative Effects ...... 176

10.14 Assessment Summary ...... 178

11.0 Ecology and Nature Conservation ...... 182

11.1 Introduction ...... 182

11.2 Legislative Context ...... 185

11.3 Planning Policy and Guidance ...... 188

11.4 Assessment Criteria and Methodology ...... 197

11.5 Assessment Methodology ...... 203

d

11.6 Consultation ...... 207

11.7 Baseline Environment ...... 207

11.8 Inherent Design Mitigation ...... 224

11.9 Key Ecological Features ...... 225

11.10 Potential Environmental Impacts and Effects ...... 226

11.11 Additional Mitigation, Compensation and Enhancement Measures ...... 238

11.12 Residual Environmental Impacts and Effects ...... 246

11.13 Cumulative Effects ...... 246

11.14 Monitoring ...... 247

11.15 Assessment Summary ...... 248

12.0 Ornithology...... 251

12.1 Introduction ...... 251

12.2 Scoping ...... 252

12.3 Legislative Context ...... 252

12.4 Assessment Criteria and Methodology ...... 255

12.5 Consultation ...... 262

12.6 Ornithological Baseline ...... 263

12.7 Valuation of the Baseline ...... 279

12.8 Inherent Design Mitigation ...... 281

12.9 Ornithological Impact Assessment ...... 282

12.10 Additional Mitigation, Compensation & Enhancement Measures ...... 294

12.11 Residual Environmental Impacts & Effects ...... 297

12.12 Cumulative Effects ...... 297

12.13 Monitoring ...... 298

12.14 Assessment Summary ...... 298

13.0 Flood Risk and Water Resources ...... 300

13.1 Introduction ...... 300

13.2 Flood Risk and Hydrology ...... 300

13.3 Surface Water Drainage ...... 305

13.4 Construction ...... 306

13.5 Safe Access ...... 307

e

13.6 Management and Maintenance ...... 308

13.7 Conclusions and Recommendations ...... 309

14.0 Additional Assessments ...... 311

14.1 Noise ...... 311

14.2 Agricultural Land Quality ...... 313

14.3 Tree Survey ...... 314

15.0 Summary of Mitigation Measures ...... 317

15.1 Introduction ...... 317

15.2 Operational ...... 318

15.3 Construction ...... 323

15.4 Decommissioning ...... 326

16.0 Population and Human Health ...... 328

16.1 Introduction ...... 328

16.2 Identifying Potential Impacts ...... 328

16.3 Assessment of impacts ...... 328

f

Figures

Figure 1 Photograph of site looking northwards

Figure 2 View of site showing electrical pylons

Figure 3 Map showing boundary of Nash and Goldcliff SSSI

Figure 4 Map showing boundary of SSSI

Figure 5 Gwent Levels Historic Landscape Area

Figure 6 Map showing location of Severn Estuary Special Protection Area

Figure 7 Severn Estuary Special Area of Conservation (SAC)

Figure 8 Public Rights of Way through the site

Figure 9 Natural Resources Wales flood map

Figure 10 Site location

Figure 11 Area covered by former site

Figure 12 Stock proof fencing

Figure 13 Caldicot Levels Special Landscape Area with site location shown as inset

Figure 14 NCC Proposals Map showing site area

Figure 15 NCC Local Plan Constraints Map

Figure 16 Ground-mounted solar PV constraints and technical potential - Verco Renewable and Low Carbon Energy Assessment

Figure 17 View of site and cables to which the scheme would connect

Figure 18 Met Office Average Annual Sunshine Hours 1971 – 2001

Figure 19 Solar comparative land take (DECC)

Figure 20 Vehicular Access Arrangements

Figure 21 Site location, Application Area, extent of study area and wider heritage data

Figure 22 Scheme land parcels and relationship to the Gwent Levels HLCAs

Figure 23 Designated and undesignated heritage assets within the revised study area for the Scheme

Figure 24 Extract from TAN15 DAM showing the area at risk of tidal flooding protected by the NRW managed defences, with the solar farm in red

Figure 25 Plan showing registered defences and formal condition. The defences are robust and man-made

Figure 26 Typical character of defences at Goldcliff which is continuous along the coast

g

Figure 27 Cable trenches underneath the reens

Figure 28 Transformer and inverter generator noise levels

Figure 29 Construction Operations

Figure 30 Operational Noise levels

Volume II – Appendices

1.1 – 2014 Screening Request

1.2 – 2015 Scoping response from NCC

2.1 – EIA Screening and scoping opinions – Based upon EIA (England and Wales) Regulations 1999

2.2 – EIA Screening and scoping opinions – Based upon EIA (Wales) Regulations 2017

6.1 – Site Selection Sequential Test

8.1 – Construction Traffic Management Plan

9.1 – Archaeology Desk-based Assessment

9.2 – Historic Landscape Assessment GGAT

9.3 – Geophysical Survey

9.4 – Gazetteer of Designated and Non-designated Heritage Assets

9.5 – ASIDOHL2 Report

10.1 – Landscape figures including viewpoints

11.1 – Phase One Target Notes

11.2 – Hedgerow Descriptions

11.4 – GCN Survey Ponds and Ditches HSI

11.5 – Bat Activity Transect Survey Details

11.6 – Bat Static Monitoring Survey Details

11.7 – Invertebrate Survey

11.8 – 2017 Water Vole and Otter Survey

11.9 – Consultation Responses

11.10 – Designated Sites

11.11 – Water Course Aquatic Survey Results

h

11.12 – Bat Tree Survey Results

11.13 – Supporting Ecology Figures

12.1 – Habitats Regulations Assessment

12.2 – RPS Data

12.3 – Winter Bird Reports

12.4 – Breeding Bird Reports

12.5 – BoCC 4 and BoCC 3

13.1 – Flood Consequences Assessment

14.1 – Agricultural Appraisal

14.2 – Arboricultural Impact Assessment

i

Environmental Statement

Gwent Farmers’ Community Solar Scheme

1.0 Introduction

1.1 The Project

1.1.1 This Environmental Statement (ES) has been prepared by Savills UK Ltd on behalf of the Gwent

Farmers’ Community Solar Scheme Ltd. It was been prepared in support of a planning application,

for the construction of a 49.9MW net installed generating capacity solar farm, on the Gwent Levels,

Nr Newport. The proposal is classed as a Development of National Significance (DNS) and will be

submitted to the Planning Inspectorate for determination.

1.1.2 The temporary development (30 years) requires a site of approximately 345 acres. A detailed

description of the development is provided in chapter 3.

1.1.3 The ES addresses the following principal considerations:

. Planning Policy Context;

. Traffic and Transport;

. Cultural Heritage;

. Landscape and Visual Effects;

. Ecology and Nature Conservation;

. Ornithology; and

. Flood Risk and Water Resources.

1.1.4 The cumulative assessment of the impact of the proposals with other existing and/or approved

projects in the vicinity of the site is considered in each relevant chapter.

1.2 Background to screening and scoping for EIA

1.2.1 A formal request for a screening opinion was first submitted to (NCC) on 10th

April 2014. A response from NCC was provided on 17th June 2014, which confirmed that the

proposed development would require Environmental Impact Assessment. The initial screening

request and the response from NCC is provided in Appendix 1.1.

1.2.2 Following this decision, a subsequent request for a scoping opinion was then submitted to NCC on

19th March 2015. At this point, 13 individual screening requests were submitted as the original intent

Gwent Farmers’ Community Solar Scheme September 2017 1

Environmental Statement

Gwent Farmers’ Community Solar Scheme

was to submit 13 separate planning applications covering the different land parcels which make up

the 345 acres. This was made under Regulations 5(1) and 10(1) of the Town and Country Planning

(Environmental Impact Assessment) (England and Wales) Regulations 1999. The Council

subsequently provided the requested scoping opinion on 26th April 2015 and this is provided in

Appendix 1.2.

1.2.3 Although this scoping opinion was appropriate to the full extent of the scheme (and has dictated the

principles for consideration listed in the section above), its title referred only to “Site 3” of the 13 sites,

which now constitute the single overall site being proposed. Furthermore, since the initial screening

and scoping opinions were issued by NCC, there have been substantial legislative changes and the

Environmental Impact Assessment process in Wales is now governed by the Town and Country

Planning (Environmental Impact Assessment) (Wales) Regulations 2017, which came into effect on

16th May 2017 (hereafter referred to as ‘the EIA Regulations’).

1.2.4 As a result, it was considered necessary to formally clarify the relationship between the Council’s

scoping opinion and the work completed as part of this EIA. Therefore, a further request for a

screening and scoping opinion was submitted to NCC on 6th June 2017. The LPA again confirmed

that the proposals constitute EIA development and provided a scoping opinion on 12th July 2017. The

screening/scoping request and NCC’s responses have been provided in Appendix 2.1

1.2.5 Due to the change in consenting procedure to the Developments of National Significance process,

the responsibility for EIA screening and scoping now lies with the Welsh Ministers and not NCC.

Therefore a request for a screening and scoping direction from the Planning Inspectorate on behalf of

the Welsh Ministers was submitted on 25th August 2017. The Planning Inspectorate confirmed on

31st August 2017 that the proposals constitute EIA development. A formal scoping direction was

received in September 2017. The screening/scoping request and the Planning Inspectorate's

responses have been provided in Appendix 2.1.

1.2.6 Therefore, to summarise, the work contained within this EIA accords with the EIA Regulations the

scoping opinions provided by NCC and the scoping direction provided by the Planning Inspectorate.

1.3 The Environmental Statement

1.3.1 The ES is presented in three separate volumes, which are:

Gwent Farmers’ Community Solar Scheme September 2017 2

Environmental Statement

Gwent Farmers’ Community Solar Scheme

. Vol 1: ES Main Report (including Parameter Plans and Chapter Figures)

. Vol 2: Technical Appendices

. Vol 3: Non-Technical Summary

1.3.2 The ES Main Report comprises of the following chapters:

Introductory Chapters

. Chapter 1: Introduction

. Chapter 2: The Site and Designations

. Chapter 3: The Proposed Development

. Chapter 4: Planning Policy Framework

. Chapter 5: Consultation

. Chapter 6: Site Selection and Alternatives

. Chapter 7: EIA Approach

Technical Chapters

. Chapter 8: Traffic and Transport

. Chapter 9: Cultural Heritage

. Chapter 10: Landscape and Visual Effects

. Chapter 11: Ecology and Nature Conservation

. Chapter 12: Ornithology

. Chapter 13: Flood Risk and Water Resources

. Chapter 14: Additional Assessments

(Agricultural Land Classification and Tree Survey)

. Chapter 15: Summary of Mitigation Measures

. Chapter 16: Population and Human Health

1.3.3 Cumulative impact is considered in each of the relevant technical chapters listed above.

1.4 Professional expertise

1.4.1 In accordance with the requirements of Article 17(4)(b) of the EIA (Wales) Regulations 2017, this

chapter of the Environmental Statement addresses sets out the relevant expertise of the person(s)

who have undertaken the Environmental Impact Assessment. In this respect the key professional

Gwent Farmers’ Community Solar Scheme September 2017 3

Environmental Statement

Gwent Farmers’ Community Solar Scheme

input has been provided by the following team of consultants:

Report / Plans Company Professional Qualifications Co-ordination of EIA and the following chapters Savills - Planning MRTPI of the ES: 1-7 and 14-16. Ecology Chapter Green Ecology MCIEEM Ornithology Chapter Green Ecology MCIEEM Landscape and Visual Impact Assessment White Young Green CMLI Transport Statement and Access Designs WSP TMICE Flood Consequences Assessment Clive Onions Ltd CEng, FICE, FCIWEM Desk Based Heritage Assessment Savills - Heritage MCIFA Arboricultural Impact Assessment Savills M Arbor. A

1.4.2 In addition to their professional qualifications, each consultant has accrued previous experience

working within the renewables sector and understand the key technical matters which must be

addressed.

1.4.3 Therefore, it demonstrated that all person(s) responsible for the production of this Environmental

Statement have sufficient expertise to ensure the completeness and quality of the statement.

Gwent Farmers’ Community Solar Scheme September 2017 4

Environmental Statement

Gwent Farmers’ Community Solar Scheme

2.0 The Site and Designations

2.1 The Site

2.1.1 The site is located on agricultural land on the Gwent levels in south Wales and lies within the local

plan area for Newport City Council. At a local level, the site lies within the Llanwern ward and the

Goldcliff Community Council Boundary.

2.1.2 The site occupies a distinctively flat area of land to the south of the former Llanwern steelworks site

and is shown below in Figure 1. It is split into six distinct parcels of land, lying either side of the

settlement of Whitson and there are no buildings within the site boundary.

2.1.3 There are a number of large pylons on the land that carry cables across the site towards the Magor

sub-station. These would facilitate a connection to the electricity grid and are shown below in Figure

2.

Figure 1 Photograph of site looking northwards

Gwent Farmers’ Community Solar Scheme September 2017 5

Environmental Statement

Gwent Farmers’ Community Solar Scheme

Figure 2 View of site showing electrical pylons

2.2 Ecological Designations

2.2.1 The site is subject to two Sites of Special Scientific Interest (SSSI) designations. The western area of

the site lies within the Nash and Goldcliff SSSI whilst the eastern area is located within the Whitson

SSSI. The boundaries for each of these areas are shown below in Figure 3 and Figure 4.

Gwent Farmers’ Community Solar Scheme September 2017 6

Environmental Statement

Gwent Farmers’ Community Solar Scheme

Figure 3 Map showing boundary of Nash and Goldcliff SSSI

Figure 4 Map showing boundary of Whitson SSSI

Gwent Farmers’ Community Solar Scheme September 2017 7

Environmental Statement

Gwent Farmers’ Community Solar Scheme