A comparative Wind Energy Analysis using the RETScreen Energy Model and the Virtual Farm Model for Switzerland

Grigorios Satanakis

SID: 3302160008

SCHOOL OF SCIENCE & TECHNOLOGY A thesis submitted for the degree of Master of Science (MSc) in Energy Systems

NOVEMBER 2018 THESSALONIKI – GREECE

-i-

A comparative Wind Energy Analysis using the RETScreen Energy Model and the Virtual Farm Model for Switzerland

Grigorios Satanakis

SID: 3302160008

Supervisor: Prof. Dimitrios Kanellopoulos Supervising Committee Mem- Assoc. Prof. Georgios Martinopoulos bers: Assist. Prof. Eleni Heracleous

SCHOOL OF SCIENCE & TECHNOLOGY A thesis submitted for the degree of Master of Science (MSc) in Energy Systems

NOVEMBER 2018 THESSALONIKI – GREECE

-ii- Abstract

This dissertation was written as a part of the MSc in Energy Systems at the International Hellenic University. Its purpose is to highlight the use of two freely available soft- ware/models for energy production estimation from renewable sources and specifically from wind. RETScreen and Virtual (available through www.renewa- bles.ninja) are the software in discussion and their use will be demonstrated by imple- menting them on six locations in Switzerland. Annual energy production and capacity factors were calculated (in each location) utilizing an E-101/3050 and an Ener- con E-82/2000 at three different hub heights each. Le Moléson and Renan and Schützenhof and Ovronnaz are the best and worst sites for RETScreen and VFM respec- tively. In addition, the results show that the Virtual Farm Model underestimates all the variables under study. I would like to acknowledge and thank the academic staff of the university for their sup- port and advice on the proceedings of the dissertation. However, above all I should acknowledge the contribution of my supervisor, who through prompt and useful advice and interventions aided discreetly in the successful completion of this dissertation.

Grigorios Satanakis Date 30/11/2018

-iii-

Contents

ABSTRACT...... III

CONTENTS...... V

1 INTRODUCTION ...... 1

1.1 THESIS STRUCTURE ...... 1

1.2 WIND ENERGY IN SWITZERLAND...... 2

2 LITERATURE REVIEW ...... 5

3 PROJECT METHODOLOGY ...... 11

3.1 PROPOSED METHODOLOGY...... 11

3.2 MODEL DESCRIPTION ...... 11 3.2.1 The RETScreen model ...... 11 3.2.2 The Virtual Farm Model...... 17 3.2.3 The “Swiss Data” website ...... 21

4 SITE AND SELECTION ...... 27

4.1 SITE SELECTION AND CHARACTERISTICS ...... 27

4.2 WIND TURBINE SELECTION AND CHARACTERISTICS ...... 32

5 RESULTS ...... 35

5.1 MODEL VALIDATION ...... 35

5.2 BASIC ASSUMPTIONS...... 38 5.2.1 RETScreen ...... 39 5.2.2 Virtual Farm Model ...... 39 5.3 RETSCREEN ...... 39 5.3.1 Data from RETScreen database ...... 40 5.3.2 Data from the “Swiss Wind Power Data” website ...... 43

5.4 VIRTUAL FARM MODEL...... 51 5.5 COMPARATIVE RESULTS ...... 54

6 CONCLUSIONS & OUTLOOK ...... 69

-v- BIBLIOGRAPHY ...... 73

APPENDIX ...... 79

LIST OF TABLES ...... 79

LIST OF FIGURES ...... 79 NOMENCLATURE ...... 82

-vi- 1 Introduction

1.1 Thesis structure This thesis deals with the estimation of energy production and of a 2 MW and 3 MW wind turbines tested in six distinct locations across Switzerland. In Chapter 1 an overview of the wind energy status in Switzerland is given along with the study’s structure. Chapter 2 contains the literature review of the field. Papers and publications related to wind energy potential, wind power production, wind power density, capacity factors and estimation methods are presented. Chapter 3 includes the project methodology. Emphasis is given on the two models used: RETScreen and Virtual Farm Model. The structure of each software is described in detail and screenshots explain their operation. In addition, the “Swiss Wind Power Data” web- site is presented. In Chapter 4 the site and turbine selection criteria are discussed. The sites are selected considering wind speed and meteorological data of each potential site, while the wind turbines are chosen according to their nominal power and appropriateness for the specific climatic conditions of the country. In addition, for both selections (sites and turbines) already operating projects in Switzerland are considered. Chapter 5 comprises of the results, which are commended and compared to existing data from operating wind turbines, which gives an opportunity to test the validity of the mod- els. Finally, in Chapter 6 the main conclusions of the study are highlighted and recommenda- tions for future research are given.

-1- 1.2 Wind energy in Switzerland Wind energy is one of the most rapidly growing industry sectors in the world since $107.2 billion have been invested in it in2017 [1] and 341,320 wind turbines were in operation as of 2016 [1]. In European Union the total installed wind power capacity was 15.6 GW (12.5 GW onshore and 3.1 GW offshore) as of 2017 [2] the total wind energy production was 336 TWh covering 11.6% of the total electricity consumption [3]. Today in Switzerland there are 65 operating wind turbines with total installed capacity of 75.46 MW and total annual energy output for 2017 of 128.26 GWh [4]. 37 of them are above 100 kW and they are listed in Table 1. Although between 2002 and 2017 there was an increasing trend in wind power investment (see Figure 1) [5] this amount corresponds only to 0.15% [6] of the electricity needs of the country.

Table 1: Operating wind turbines in Switzerland. Source: https://wind-data.ch/wka/list.php

Installed capacity Energy output 2017 Site Number of turbines (MW) (GWh)

Mt. Crosin 37.2 16 74.041

Gries 9.36 4 7.792

Peuchapatte 6.9 3 13.186

St. Brais 4 2 7.002

Gütsch 3.3 4 5.046

Charrat VS, Adonis 3 1 7.052

Haldenstein 3 1 4.137

Lutersarni 2.3 1 3.190

Collonges 2 1 4.395

Martigny 2 1 5.1951

Feldmoos/Rengg 1.85 2 1.240

Oberer Grenchenberg 0.15 1 0.117

TOTAL 75.46 37 128.26

-2-

Figure 1: Trend of installed wind capacity corresponding and electricity production. Source: http://www.suisse-eole.ch/de/service/folien/

However, the federal planning for energy states that wind power should become one of the main renewable electricity sources, covering 7% of Switzerland’s electricity needs by 2050 [7].

-3-

2 Literature Review

Wind energy is one of the most common renewable sources and the relevant literature available is quite extensive. There are several papers globally, dealing with the wind en- ergy potential assessment namely, the magnitude and/or direction of winds blowing in an area. The most utilized estimation method is the Weibull distribution and its parameters k and c. Weisser [8], stresses the importance of diurnal wind speed data for an accurate prediction of wind regimes when using the Weibull distribution. Hoogwijk et al. [9] use the same methodology to estimate the global technical potential for onshore wind energy (at 96 PWh annually). A study from Greece by Vogiatzis et al [10] found the appropriate size for a hybrid wind-solar desalination plant by estimating the Weibull distributions for 2000 and 2001. Eskin et al. [11] applied the same distribution and found the wind regime in Gökçeada island in Turkey. A recent study in Mauritius by Dhunny et al. [12] was also performed with the Weibull function and showed that the island has exploitable wind potential. Chang proposed in 2011 [13] two variations of the classical Weibull distribu- tion, the Gamma-Weibull and the truncated normal function, which were found to per- form well in predicting wind power densities compared to other mixture functions such as bimodal-Weibull. Another common probability density function is the Rayleigh distribution, which is a Weibull distribution with k=2 [14]. Celik [15] used both Weibull and Rayleigh distribu- tions to calculate the wind power density (30.2 W/m2) in Iskenderun of southern Turkey, concluding that the Weibull provided better results. Sliz-Szkliniarz and Vogt [16] com- bined measured wind speeds and the Rayleigh distribution to predict the technical poten- tial of a region in Poland and Siyal et al. [17] suggest that Sweden has enough wind po- tential, using an approach based on GIS methods and Rayleigh distribution. Bechrakis et al. [18] utilized artificial neural networks (ANN) to extrapolate yearly wind speeds measured in on site, to a another one. The simulated wind speeds were used to cal- culate the Weibull distribution. The suggested method works well and provides similar results with the renowned WAsP software.

-5- Mass-consistent models are also used in some studies. Kanellopoulos [19] used the NO- ABL model to validate the resources of Greece and found it to perform well but stressed the importance of good (temporal and spatial) measurements. A paper from Barnard [20] states that NOABL model and MS3DJH/3R and BZ models perform in similar manner when used for prediction of winds above complex terrains. As before, the models gave better results when the available data came from more than one meteor- ological station. Finally, Finardi et al [21] showed that the mass-consistent model MI- NERVE gave similar results to a non-hydrostatic model (RAMS). In both cases the loca- tion of meteorological stations was of paramount importance for the accuracy of the pre- dicted wind regime. A similar kind of studies deals additionally with the prediction of wind power density and the potential of a country or a region, again using mostly the Weibull distribution. Katsoulis in 1992 [22] identified regions of Greece with wind potential. Eastern coasts of the country and the Aegean Sea had a wind power density of 600 W/m2 while western coasts and Ionian islands had a much lower value of about 200 W/m2. However, in other regions of the country (mainly onshore) the wind potential failed to be revealed because of unavailability of data. Bagiorgas et al [23] studied Western Greece and found that for this area smaller hub heights are more favorable even though wind power density in- creases with increasing hub height and wind speed. This was attributed to the fact that the cost of bigger turbines exceeds the avail from larger capacity factors and wind power densities. Another study in Southern Greece from Xydis et al [24] examined the expected annual energy production (hereinafter referred as AEP) in ten different locations. Find- ings suggested speeds between 5.74 and 7.52 m/s and net AEP in the range of 13 to 18 GWh. Kavak Akpinar and Akpinar in 2004 [25] studied the Maden-Elazig region of Turkey and found mean speeds of 5 m/s to 6 m/s at 10m above ground level (hereinafter AGL) and average annual wind power density of 244.65 W/m2. This value means that the specific location belongs to wind power class 4 [26] and is suitable for off-grid applications like generators and water pumps. Gökçek et al. [27] showed that in Kirklareli mean speed at 10 m is 4.7 m/s and wind power density is 142.75 W/m2, meaning the exploitation is marginal. Mirhosseini et al. [28] assessed the wind energy potential in the Semnan region of Iran. Moalleaman was the best site with wind power density between 172 and 177 W/m2 at 10 m AGL, AEP of 2000 MWh/y and characterized as class 3 site. A study in

-6- Algeria from Himri et al. [29] in 2009 suggest that the potential of the provinces of inter- est is appreciable and suitable for small applications rather than grid-connected ones. Sites at Tindouf and Dely Brahim were the most promising with wind speeds of 5.8 m/s (138-238 W/m2 at 17m AGL) and 5.7 (259 W/m2 at 17m AGL) m/s respectively. Ouammi et al. [30] found that in Liguria, Italy only one site can be exploited due to vari- ous restrictions. In Capo Vado measured wind speed at 40 m AGL is 8.56 m/s with cor- responding wind power density of 487.7 W/m2 and annual energy output of 4271.7 MWh. In the wider region of South-eastern Europe (including Serbia, Croatia, Bosnia, Greece, Albania and other countries) an investigation from Ban et al [31] revealed that there is promising potential in several mountainous sites located approximately 2500 m above the sea. Data from 1980 to 2010 processed with NCEP/DOE reanalysis model gave a wind power density more than 250 W/m2. Islam et al. [32] in a paper from 2011, researched locations in Malaysia. It was found that sites at Kudat and Labuan were ill suited for large-scale applications since they demon- strated average yearly speeds of 3.37 m/s and 3.5 m/s respectively. However, small-scale endeavors (hub height of 100m maximum) are favored, because wind power densities are 67.4 W/m2 and 50.84 W/m2. Moreover, a study from Tamil, India by Mabel and Fernan- dez [33] was performed with artificial neural networks (ANN). The results showed that capacity factors ranged from 24% (at 7.65 m/s) to 4.4% (at 2.88 m/s), disclosing the in- termittent nature of wind power, which renders accurate prediction methods necessary. Li and Li [34] used the maximum entropy principal (MEP) to identify the diurnal, monthly and seasonal wind speed distributions and the corresponding wind power density in Waterloo, Canada. An average value of 105 W/m2 was extracted. Four sites in Arizona, USA (Acker et al.) [35] demonstrated different average capacity factors ranging from 26% to 37% (at 70 m AGL without losses) and the sites were ranked from wind power class 3 to 6. A third type of studies includes not only wind speeds and wind power densities but esti- mated wind power production from various wind turbine models. Köse [36] in 2004 investigated the possibility of wind energy production from a 600 kW Enercon wind turbine at 60 m inside the campus of Dumlupinar. The results showed that this site was inappropriate for economical electricity production, since the measured ca- pacity factor was 15.6% and the produced energy after 20 months 1372.2 MWh. Celik [37] performed a techno-economic analysis in Iskenderun aside from the wind regime

-7- estimation (see [15]). It was deduced that larger turbines (500 kW) are more economically efficient than smaller ones (0.6 kW). However, this site is class 1 (30.2 W/m2) and there- fore suitable only for applications like battery charging or water pumping. A series of publications from Ucar and Balo concerning the 6 regions across Turkey [38], Uludağ- Bursa [39] and Ankara [40] gave the following results. In the first paper 6 locations and 4 wind turbines were studied. The highest potential was found at Erzerum, where a DeWind D8 2 MW wind turbine was able to produce 7.46 GWh annually at 8.7 m/s mean wind speed. The capacity factor was 43% and the mean specific power density 65 W/m2 (at 70 m). In Uludağ-Bursa mean speeds of 8.3 m/s during summer and 5.6 m/s during winter where found. The associated annual wind energy was 300 MWh (DeWind D48, 600 kW) and 780 MWh (DeWind D6, 1250 kW) depending on the turbine size. At Ankara and Polatli the highest average monthly wind speeds recorded (data from 2000 to 2006) were 6.4 m/s and 5.84 m/s. Four different turbines were used. The maximum energy out- put was achieved by a 3 MW V-90 with almost 82 MWh/year and 43 MWh/year in Ankara and Polatli respectively. On the other hand, the highest capacity factors for the two locations were attained by a smaller machine a 1.65 MW Vestas V-82 with 45% and 37% respectively. Five sites were inspected in Saudi Arabia in study by Al-Abbadi [41]. Two of them had the highest potential with wind blowing at 5.7 m/s and 5.4 m/s in Dhulum and Aram respectively. There a N43 produced 1080 MWh and 990 MWh, rendering these underpopulated areas ideal for remote wind applications. In two coastal sites, namely Yanbu and Dharan wind speed peaks at 8 m/s and 7m/s and grid connected applications for load peak sharing are an option. Two studies from Egypt showed the promising po- tential of the country. Shata and Hanitsch [42] researched six sites. Three of them (Sidi Barrani, Mersa Martuh and El Dabaa) had wind power densities from 180-320 W/m2 to 260-330 W/m2 at 30-50 m AGL. A 1 MW wind turbine in El Dabaa produced 2718 MWh annually. Shata [43] studied a site in Ras Benas, where (northly) winds had speeds of 8.9- 9.8 m/s at 70-100 m AGL. At the same heights wind power densities in the range of 1063- 1200 kW/m2 were observed mainly during spring and summer. A wind park, consisting of 20 Nordex S77 turbines, installed at El Dabaa is expected to produce 130 GWh per annum, according to calculations made with WAsP software. Jowder [44] in 2009 ana- lysed 3-year wind speed data (at 60 m) to identify the potential in Bahrain. A Gamesa G58 with nominal power of 850 kW was found to be the most suitable turbine at 60 m giving a capacity factor of 40%. Adaramola et al. [45]underscore that in Lagos, Nigeria

-8- a DeWind D7-1.5 MW with 70 m hub height can produce 3767.7 MWh/year at 4.93 m/s with a capacity factor of 28.7%. Fyrippis et al. [46] investigated the potential of a location in Naxos island, Greece. The findings were exceptional. The mean yearly power density was 480 W/m2, which means that the site at Koronos belongs to wind power class 7 [26]. Installing wind turbines there is more than desirable since a 1 MW machine can produce 4 GWh of electricity per year while a 2.5 MW turbine doubles the amount reaching 8 GWh annually. In another study from Greece Bakos [47] examined the performance of two different turbines in a site aground. The study concluded that 4 Vestas V-82 1.65 MW each are less profitable than 4 Vestas V-100 1.8 MW each, because the larger machines performed better in this site and thus the larger initial cost was overcome. Other studies from Europe include one from Krewitt et al. [48] and one from Migoya et al. [49].The first showed that moving from a 1.5 MW to 3 MW wind turbine affects the produced energy in a positive way in both locations in question. Specifically, in Lower Saxony the AEP increased from 28.6 TWh to 33.2 TWh, while in Baden-Württemberg from 1.7 TWh to 2 TWh. To achieve this numbers 7060 and 500 turbines are needed respectively. The second suggests that in the region of Madrid-which is characterized as moderate regarding the wind potential-it is viable to install 200 MW of wind power outside protected areas. Raichle and Carson [50] analyzed data from the southern ridges of Appalachia in USA and found yearly mean speeds between 5.5 m/s and 7.4 m/s leading to wind power density of 400 W/m2 atop of these ridges, stretching 1600 m along the Appalachian Mountains. A hypothesized wind farm of 15 1.5 MW turbines in 9 locations gave promising results with AEP and capacity factors ranging from 39.5 GWh to 78.7 GWh and from 18% to 36%. Ali et al. [51] examined the possibility of installing five different wind turbine mod- els at three distinct sites in South Korea. The wind speeds were extracted with the Weibull distribution and graphical method of Gumble distribution led to the required classes of each turbine. In the two sites the most feasible turbine was found to be a WinDS134/3000 (3 MW), which could potentially produce 6.37 GWh per year with a capacity factor of 24.3% in the first site and almost 10 GWh of electricity with capacity factor of 40% in the second. In the third site a HJWT 87/2000 (2 MW) machine performs best, with a hypothesized annual energy output of approximately 7 GWh with capacity factor of 40%.

-9- In Switzerland most of the studies concentrate on research topics which are related to subjects relevant to the climatic conditions and the topography of the country, viz. icing and complex terrain. Barber and Abhari [52] analyzed measurements from Gütsch, where 4 Enercon wind turbines with total capacity of 3.3 MW are installed. Since Gütsch is at 2287 m elevation icing is an issue. The findings showed that icing lead to 1.6% reduction of AEP. In addi- tion, the AEP was 23% lower than the value extracted from the power curve provided by Enercon and it was caused by the local topography creating gusts and turbulence. Dierer et al [53] determined the relationship between meteorological and instrumental icing in the site of St. Brais. They found 11.5 days/y and 44.5 days/y respectively with a ratio of approximately 1/4. As a countermeasure blade heating was tested. With blade heating total losses were 3.5% (3% downtime due to ice and 0.5% heating) compared to 10% without heating of the yearly power production. Chokani and Abhari [54] performed measurements in the wind turbine test facility of ETH-Zürich and the Mont Crosin farm and in addition CFD simulations of the test site in Gütsch. The impact of flow inclination and elevated freestream turbulence on the output of wind turbines was examined. The results revealed that the output of a turbine decreases 7% when the incoming air flow is inclined at 15o compared to an inclination of 0o. On the contrary, for the same inclination the wake of the turbine is deflected at 6o and this favors a more compact placement of turbines in complex terrains. Finally, an elevated freestream turbulence of 8% increased the output of the turbine by 15% relative to a flow with low turbulence of 2.5%. The above findings illustrate the contradicting nature of the described effects in complex terrain and the necessity for investigation of each site’s conditions. Two studies from Subramanian et al. and Porte-Agel and Lungo dealt with wake meas- urement. In the first [55] LIDARs were used to measure the wake of a wind turbine and its thermal stability in Collonges. The results unveiled that during daytime, when convec- tive effects exist, wakes recovered faster due to more effective mixing of low speed flow (of the wake) and surrounding air with greater speed. On the contrary in the night the atmosphere is more stable and the turbulence at lower levels and thus the flow speeds remain low in the wake. In the second [56] it is also deduced that the near-wake of a wind turbine located on complex terrain is 35% shorter compared to flat terrain installations and reaches as far as two rotor diameters.

-10- 3 Project Methodology

3.1 Proposed methodology The methodology proposed is quite simple and was built on two models, RETScreen (see 3.2.1) and Virtual Farm Model (hereinafter VFM) (see 3.2.2). A first estimation was based solely on the database of RETScreen, while in the second step data taken from the “Swiss Wind Power Data” website [57] (see 3.2.3) were inserted into RETScreen to pro- duce better results. A first comparison showed the differences between the two databases. In the final step, the energy outputs and capacity factors from RETScreen (with swiss data) were compared with the estimations given by the VFM model. This process was repeated for each one of the six selected sites, utilizing the same 2 MW and 3 MW wind turbines, for three different hub heights. The results were compared to the performance of an operational wind turbine (see 5.1) located on another site. In addition, it was tested whether the smaller (2 MW) or larger (3 MW) wind turbine was more suitable for each site considering the selected hub heights.

3.2 Model description

3.2.1 The RETScreen model RETScreen is an energy management software focused on sources, but also dealing with industrial, commercial, residential and agricultural installations. RETScreen Expert is the professional version of the software that offers energy efficiency optimization, project feasibility study, energy analyses for already operating plants and financial analyses for all the above options [58]. In this way people entitled to decision making have at their disposal a powerful tool that enables them to swiftly assess and control performance and quickly identify optimization, enhancement and savings oppor- tunities [58]. The wide range of applications that RETScreen utilises, renders it as a quite popular software in the energy management market. Its acceptance is also amplified by its relatively low purchase cost and the fact that is freely available in viewer mode, which means that any kind of study can be performed but cannot be saved.

-11- In this thesis the feasibility option of the software was implemented on six locations across Switzerland. The main inputs to perform a feasibility study include Location, Fa- cility type, Energy model, Cost analysis, Emission analysis, Financial analysis and Risk analysis. However, this study was concentrated on energy estimation thus only Location, Facility type and Energy model were utilized. Below a detailed description of the process- based on the manual of the software is presented. Location selection (see Figure 2) includes all the relevant data such as coordinates, cli- mate zone and meteorological indicators taken from NASA [59] and ground stations. Firstly, the desired location is selected. By clicking the blue box (highlighted in red), a search bar appears, and the location name is entered. Then coordinates, climate type, el- evation and temperature are retrieved from the software’s database.

Figure 2: Facility location and climate data location selection. Source: RETScreen Expert

Next, all relevant climate data such as air temperature, relative humidity, precipitation, atmospheric pressure, wind speed etc. are provided either by the user or by the internal database. Measurement height is also required (see Figure 3) At the end of this tab is given a table of climate data for the entire year. The user can select any of the above data, to be plotted as bar graph or line. Each graph can represent the same or two different variables (see Figure 4).

-12-

Figure 3: Input of climate data such as air temperature, relative humidity, precipitation, atmos- pheric pressure, wind speed etc. Source: RETScreen Expert

Figure 4: An example of climate data graph. Monthly average values of wind speed are plotted either as bar graph or a line. Source: RETScreen Expert

In the facility tab the facility type is selected. Power plant, industrial, commercial, resi- dential or agricultural applications are among the options. For each category there are numerous subcategories such as different types of plants, buildings, RES facilities etc. The name, address, city, province and country of the facility can also be given (see Figure 5).

-13-

Figure 5: Facility type selection. Source: RETScreen Expert

In the energy model tab there are three subcategories: Fuels & Schedules, Technology and Summary (see Figure 6). The first is irrelevant in this case since a wind turbine does not use any fuel.

Figure 6: Energy model and subcategories. Source: RETScreen Expert

In Technology, the power production method is chosen, which is a wind turbine in this study. There are three levels of detail available. In Level 1 user inputs power capacity, number of turbines and capacity factor. Power capacity can be added manually or by the software’s database. The model returns the

-14- annual electricity exported to the grid. If a financial analysis is required, initial costs, operation and maintenance costs and electricity export rate are also inserted. Level 2 is divided in six subsections: Resource Assessment, Wind turbine, Power and energy curves, Losses, Summary and Other information. Resource assessment contains all the variables related to wind potential (see Figure 7). Wind speed or wind power density is selected as resource method and then measurement height is defined. Next, wind shear exponent is defined, to calculate the wind speed at hub height by using the power law (as described in [60]). Finally, annual values of air temperature and pressure can be added by user or from RETScreen database. Wind turbine (see Figure 7) includes all the associated parameters such as power capacity, per turbine, manufacturer, model, number of turbines, total power capacity, hub height, rotor diameter, swept area, energy curve data and shape factor. Although, all the above can be set manually, the best option is to search the extensive database of the software, which contains the most popular models available in the market. Energy curve data de- termines how the energy curve is calculated. There are two options Standard and Custom. In the first calculations are based on the Rayleigh distribution, which is a subcase (shape parameter k=2) of the Weibull distribution. The latter is used for the calculations under the Custom option.

Figure 7: Resource assessment and Wind turbine subsections and their parameters. Source: RETScreen Expert

In any case, the selected distribution ascribes a frequency percentage of operation time for each wind speed interval of 1 m/s, which is combined with the corresponding power curve value. This calculation is repeated for all wind speed values and the results are depicted in the energy curves section (see Figure 8). In addition, the power curve is

-15- automatically obtained when a turbine is selected from the software’s database. Otherwise a power value must be inserted for each speed increment.

Figure 8: Power and energy curves section. Source: RETScreen Expert

Losses section (see Figure 9) contains three types: Array losses, Airfoil losses, Miscella- neous losses and Availability. Array losses are caused by wake effects. Wake effects hap- pen between successive wind turbines because the air flow is partially blocked from the front turbine and reaches the next turbine with lower speed. Airfoil losses are caused from soiling and/or icing. Bugs and/or ice can build-up on the surface of the blades and induce aerodynamic losses. Miscellaneous losses represent losses due to start-stop of yaw mo- tors, cut outs from wind gusts and transmission losses from the site to the grid connection point. Availability includes downtime losses due to maintenance, failures and outage. In the Summary section (see Figure 9) user provides initial and O&M costs and electricity export rate and the model returns the capacity factor and the electricity exported to the grid which are the two variables that define the technical and financial viability of the project. Other information (see Figure 9) contains the unadjusted energy production, Pressure co- efficient, Temperature coefficient, Gross energy production, Losses coefficient and Spe- cific yield. Unadjusted energy production is the raw energy produced from the wind

-16- turbine at standard pressure and temperature conditions. It is obtained from the energy curve and corresponds to the wind speed at hub height. In Figure 8 at 5 m/s, the turbine’s nominal power is 258 kW and the corresponding energy output for this example is 4440 MWh. Pressure coefficient is proportional to the mean atmospheric pressure of the site and Temperature coefficient is inversely proportional to the mean temperature of the site. They are used to determine Gross energy production from the Unadjusted energy produc- tion. Finally, Losses coefficient is given by the formula:

퐿표푠푠푒푠 = 퐴푣푎푖푙푎푏푖푙푖푡푦 ∙ (1 − 퐴푟푟푎푦)(1 − 퐴푖푟푓표푖푙)(1 − 푀푖푠푐푒푙푙푎푛푒표푢푠)

It is used to calculate the Electricity exported to the grid by the Gross energy production.

Figure 9: Losses, Summary and Other information sections. Source: RETScreen Expert

3.2.2 The Virtual Farm Model Virtual Farm Model is a free online software that enables interested parties to perform simulations of the hourly power output of wind and solar installations in any place around the globe. It uses climate and weather data from NASA’s MEERA (and MEERA-2) reanalysis model [59] and CM-SAF’s SARAH dataset [61], [62]. Reanalysis is a model that blends an integration procedure of historic weather data with an atmospheric model to deduce the status of the global weather system. Historic data are obtained from satellites, ground stations etcetera and are reproduced. These data are

-17- difficult to elaborate, but via reanalysis they are restructured into datasets with uniform temporal and spatial coverage [63]. These datasets are the input of the Virtual Wind Farm model which was developed by Iain Staffell (lecturer at Imperial College London) and Stefan Pfenninger (postdoc at ETH Zürich). The model obtains wind speeds at 2, 10 and 50 m AGL for each grid point of MEERA (see Figure 10a) and interpolates them for the selected location using LOESS (Local Pol- ynomial Regression) (see Figure 10b). Next, the implementation of the logarithmic wind profile law produces wind speeds at hub height of each turbine (see Figure 10c), which are finally converted to power output via the power curve of the wind turbine provided by the manufacturer (see Figure 10d) [63]. The power curves are smoothed to include the hourly variations of wind speeds. Smooth- ing is achieved by a Gaussian filter given by the formula:

휎 = 0.6 + 0.2푤 where w is the wind speed. The parameters are found empirically and represent historic data for wind speeds in the most effective manner [63].

Figure 10: Virtual Wind Farm model methodology steps. Source: Staffell, I., & Pfenninger, S. (2016). Using bias-corrected reanalysis to simulate current and future wind power output. Energy, 114, 1224-1239.

However, MEERA (and MEERA-2) contains a systematic bias in wind speeds [63]. A first reason is the errors in the subjacent weather model. Another cause is that the model is spatially rugged, namely each point of the dataset is considered a flat surface and thus

-18- the topography of each site is failed to be accounted for. Finally, each cell is 50 km x 50 km, so each site’s unique microclimatic interactions and processes cannot be captured, which leads errors in wind speeds [63]. From the above it is understood that correction of this bias is imperative, to avoid mises- timations in capacity factors. A linear equation is utilized by Staffell and Pfenninger [63] as correction. Its only input is the ratio of historic to simulated capacity factors and it has proven extremely effective improving the calculated capacity factors. Virtual wind farm model is freely available online in a user-friendly interface [64]. The use of the model is relatively simple for a user with basic wind turbine background. First the exact location of the wind turbine is selected either directly on the map or by providing latitude and longitude (see Figure 11). Next, the dataset and data year are selected along with the capacity (in kW) and the hub height (in m) of the wind turbine. Finally, the wind turbine itself is selected from a quite extensive list (see Figure 12). The results provided are the daily mean power production (see Figure 13) as well as the monthly capacity factors and their total mean (see Figure 14), in graphical form. However, the complete data (with raw weather data included if the option is made) can be downloaded in csv form to be analyzed individually.

Figure 11: Location selection for the VFM model. Source: https://www.renewables.ninja

-19-

Figure 12: Required parameters for the VFM model. Source: https://www.renewables.ninja

Figure 13: Daily mean power output graph given by the VFM model. Source: https://www.renewa- bles.ninja

Figure 14: Monthly capacity factor and total mean capacity factor given by the VFM model. Source: https://www.renewables.ninja

-20- 3.2.3 The “Swiss Wind Power Data” website The “Swiss Wind Power Data” website provides data, planning information and tools related to wind power in Switzerland [4]. More specifically, a detailed wind atlas of the country is available along with an icing map [65]. In addition, a map with measurement stations across the country is available [57]. Moreover, useful calculation tools for wind profile, Weibull distribution, air density and power production can be found [66]. All the operating wind turbines (single projects or farms) are listed in a separate webpage with links to information about them [67]. Finally, there is a firm directory where all the Swiss firms related to wind power are listed [68]. The site is mandated by the Swiss Office of Energy [69] and produced by Meteotest [70]. In this study the sections of the website that are used are the wind atlas, the measurement data and the wind turbines.

Wind atlas The wind atlas of Switzerland provides yearly mean wind speeds at 50 m, 75 m, 100 m, 125 m and 150 m AGL (see Figure 15) and various additional information such as forests, water sources, animal habitats and other. By clicking on the map, the user has access to the average wind speed, the wind rose and the Weibull distribution for the selected site and height above the ground.

Figure 15: Wind atlas of Switzerland depicting annual average wind speeds at 125 m AGL. Source: https://wind-data.ch/windkarte/

The data rely on a modeling system that describes the whole country. Each cell of the mesh is 100 m wide and the yearly mean wind speed is shown in each grid point. The categorization of wind speeds is performed with an estimation based on the Weibull

-21- parameters i.e. the scale parameter A and the shape parameter k. As it stated in the site “It is not possible to directly derive the average wind speed from the Weibull parameters because the result is only an approximation to wind distribution and this cannot be ade- quately reflected for each location” [65]. However, the above sentence is ambiguous since it is known that the Weibull distribution is related to the average wind speed [66]. It prob- ably means that the average speed computed from the distribution is only the estimation and not the actual value that corresponds to measurements. Long-term data have been included in the model and the calculation of wind speeds is based on them. However, the density of measurement stations is not uniform across Swit- zerland and thus the results suffer from uncertainties, especially over complex terrain. These uncertainties vary from ± 0.5 m/s in the Jura region and ±0.8 m/s in the central plain to ± 1 m/s in the Alps [65]. From the above it is understood that these data should be utilized with caution and the assessment of wind regimes in each region should be based on accurate on-site measurements [65]. The wind map has two variations. The first depicts areas of Switzerland with wind poten- tial (see Figure 16) and the second illustrates the federal government’s other areas of interest (see Figure 17) or in other words areas where installation of wind turbines is restricted.

Figure 16: Areas with wind potential (in blue) in Switzerland. Source: https://wind-data.ch/wind- karte/

-22-

Figure 17: Areas where installation of wind turbines is prohibited. Source: https://wind- data.ch/windkarte/.

The restricted areas incorporate protected areas without a balancing of interests (in dark red), areas excluded in principle (in orange), areas subject to inter-authority coordination (in yellow), building areas with noise abatement (in grey) and areas on which other re- strictions apply (in white) [65]. However, the latter map is not legally binding and it should be used together with “Wind energy concept”, which is the basis of federal inter- ests [71].An assessment of the three maps along with the data from the measurement stations are the first step of siting potential locations for installation of wind turbines. Apart from the above, a map that depicts meteorological icing frequency at 100 m from August 2007 to July 2009 has been developed [72] (see Figure 18). Data from COSMO- 2 (a meteorological forecasting model developed by Meteotest) are used as input to an icing model which predicts the formation of ice on a rotating cylindrical object. Icing is a phenomenon that can be described in four stages, according to a report per- formed from Meteostet for the Swiss Office for Energy [73]. Meteorological icing refers to the period when the formation of ice is favored. Instrumental icing is the time period in which the smooth operation of wind turbines or measurement instruments is disturbed due to ice accretion on them. Incubation time is the period from the start of metrological icing to the start of instrumental icing, while recovery time is the delay between the end of meteorological icing and the end of instrumental icing.

-23-

Figure 18: Map of icing frequency, in days per year, across Switzerland. Source: https://wind- data.ch/windkarte/vereisung.php.

In areas in brown, icing appears for less than 5 days per year, while in areas in orange between 5 and 10 days. The phenomenon intensifies as the proximity to the Alps increases and a range from 10-20 days (in yellow) and 20-30 days (in green) of icing is character- istic for these areas. In greater heights atop of the mountains icing can last from 30 to 60 days (in blue) or longer (in dark blue). The map should be used in a qualitative manner and is just an indication of the icing frequency in each region. In addition, local topography of each area affects the ice for- mation and thus the values of the map may be over or underestimated. Finally, since the map shows the frequency of meteorological icing, it is expected that instrumental icing will last longer [73]. Icing is parameter that should be considered in turbine selection and counteractions will be discussed further in paragraph 4.2.

Measurement stations There are 132 meteorological stations across Switzerland (see Figure 19). Each one of them provides meteorological data but in the “Swiss Wind Power Data” website are avail- able data regarding wind. The user can select monthly or current data. Monthly data con- tain coordinates of the station, altitude, measurement height and wind speeds from 1987 to 2018 in tables and graphs. This data was used as input to the RETScreen model to estimate the capacity factor and energy output in the selected sites. Current data include wind speed and direction for the last week.

-24-

Figure 19: Meteorological stations that provide wind data across Switzerland. Source: https://wind-data.ch/messdaten/index.php?lng=en

Wind turbines In this section are listed all the operating turbines in the country [67] (see Figure 20). Currently there are 38 sites with installed wind turbines, either single machines or wind parks. For each listed site the following information are provided: Turbine model, rotor diameter, hub height, installed capacity, construction year and operational status. In ad- dition, yearly energy production is given for all the operational years to date.

Figure 20:Operating wind turbines and wind farms in Switzerland. Source: https://wind- data.ch/wka/index.php

-25-

4 Site and wind turbine selection

4.1 Site selection and characteristics Site selection was based on the list of the meteorological sites operating across Switzer- land [57]. The first criterion was the measured wind speed. At first, speeds above 5 m/s at 50 AGL were considered. The next step included inspection of the surroundings of each station using Google Maps, Google Earth and the wind atlas [65]. Emphasis was given on specific topographical formations such as ridges or valleys that favour the tun- nelling effect. Finally, the simultaneous observation of the maps led to the identification of the six sites (Table 2)

Table 2: Selected sites and their characteristics.

Average wind Annual Annual Annual Altitude Coordinates Wind Shear Site speed (m/s at tempera- pressure icing (m ASL) (lat, long) Exponent 100 m AGL) ture (oC) (kPa) (days)

1. Schützenhof, 47.40190 719 5.7 7.9 92.8 0.20-0.21 5-10 Russikon 8.79261 2. Käsern, 47.26207 1050 6.5 7.9 89.1 0.22-0.24 <5 Ebnat-Kappel 9.15914 3. Bad Ragaz, 46.99813 975 6.6 11 89.9 0.26-0.27 5-10 St. Galen 9.48670 4. Ovronnaz, 46.21044 1610 6.6 6.3 83.2 0.28-0.30 5-10 Valais 7.17172 5. Le Moléson, 46.54975 1829 7.5 7.9 81.0 0.28-0.30 5-10 Gruyères 7.01755 47.10778 6. Renan, Bern 1267 6.6 7.5 86.8 0.21-0.23 5-10 6.92742

-27-

Figure 21: The turbines’ locations across Switzerland. Source: https://www.google.com/maps

The first site is in Schützenhof, Russikon in the canton of Zürich. The altitude above sea level (hereinafter ASL) is 719 m and the average wind speed at 100 m AGL is 5.7 m/s. From Figure 22 it is evident that prevailing winds blow at SSW and SW directions. The surroundings are mainly fields and wooded hills and thus wind shear exponent between 0.20 and 0.21 is preferred [74]. Annual temperature is 7.9o C and annual pressure is 92.8 kPa. Icing is present from 5 to 10 days annually [72].

Figure 22: Windrose at 100 m AGL at the site of Schützenhof, Russikon. Source: https://wind-data.ch/windkarte/

-28- The second site is located east of the town of Ebnat-Kappel in St. Gallen canton. The altitude is 1050 m ASL and the mean wind speed at 100 m AGL is 6.5 m/s. At this altitude there isn’t a wind direction that prevails. However, directions ranging from SSW to WSW seem to be more frequent (Figure 23). The landscape consists of wooded or grassy hills and power law exponent values between 0.22 and 0.24 are suggested [74]. Annual tem- perature is 7.9 oC and annual pressure is 89.1 kPa. Formation of ice is an issue for less than 5 days per year [72].

Figure 23: Windrose at 100 m AGL at the site of Käsern, Ebnat-Kappel. Source: https://wind-data.ch/windkarte/

The location of the third site is near the town of Bad Ragaz in the canton of St. Gallen. The altitude is 975 m ASL. The average wind speed at 100 m AGL is 6.6 m/s. In this site there are four opposite prevailing wind directions (Figure 24) N, S and NNE, SSW, but in the latter wind of greater magnitude blow. The topography of the site (atop a plateau in front of mountains) dictates values of wind shear exponent of 0.26-0.27 [74]. Annual temperature is 11 oC and annual pressure is 89.9 kPa. Icing causes problems for approxi- mately 5 to 10 days per annum [72].

Figure 24: Windrose at 100 m AGL at the site of Bad Ragaz, St. Gallen. Source: https://wind-data.ch/windkarte/

-29- On a smooth slope between Ovronnaz and Mayens-de-Chamoson in the Valais canton, the fourth site is located at 1610 m ASL. Mean wind speed at 100m AGL is 6.6 m/s. The winds come mainly from the SSW and SW directions (Figure 25). The recommended power law exponent values lie in the range of 0.28-0.30 [74]. Annual temperature is 6.3 oC and annual pressure is 83.2 kPa. Icing frequency is 5-10 days annually [72].

Figure 25: Windrose at 100 m AGL at the site of Ovronnaz, Valais. Source: https://wind-data.ch/windkarte/

The scenery changes in the fifth site, which is atop the Le Moléson ridge at 1829 m ASL in the Gruyères region in the canton of Fribourg. There, the winds blow at an average speed of 7.5 m/s 100m AGL. Then main wind directions are W and WSW (Figure 26) Due to the landscape of the surrounding area favored values of the wind shear exponent are 0.28-0.30 [74]. Annual temperature is 7.9 oC and annual pressure is 81.0 kPa. The effect of icing is significant from 5 to 10 days per year [72].

Figure 26: Windrose at 100 m AGL at the site of Le Moléson, Gruyères. Source: https://wind-data.ch/windkarte/

-30- The sixth site is found southeast of the village of Renan in the canton of Bern. The altitude of the site is 1267 m ASL and the wind regime includes mean wind speed of 6.6 m/s at 100 m AGL. The winds come most frequently from SW and SSW directions. The power law exponent ranges from 0.21 to 0.23 since the topography consists of elevated croplands and some small forests and random buildings [74]. Annual temperature is 7.5 oC and annual pressure is 86.8 kPa. Due to the relatively high altitude, icing is present from 5 to 10 days yearly [72].

Figure 27: Windrose at 100 m AGL at the site of Renan, Bern. Source: https://wind-data.ch/windkarte/

Annual temperature is calculated from data taken from Meteoblue [75] for each location. It is the average value of the mean monthly maximum and mean monthly minimum tem- peratures. Annual pressure is calculated from the atmospheric pressure gradient, which is given from the following equation

푧 (− ) 푃푧 = 푃표 ∙ 푒 8200 where Pz is the pressure at altitude z ASL and Po=101.3 kPa is pressure at sea level.

-31- 4.2 Wind turbine selection and characteristics From the 65 installed wind turbines only 2 have an installed capacity of 3 MW and operate singly. In addition, there are several 2 MW wind energy converters installed as parts of wind parks. For the purpose of this study two wind turbines were chosen (see Table 3).

Table 3:Basic technical specifications of the selected turbines.

Model name Enercon E-101/3050 Enercon E-82/2000

Rated power (kW) 3050 2000

Cut-in speed (m/s) 2 2

Rated speed (m/s) 13 12.5

Cut-off speed (m/s) 28-34 34

Rotor diameter (m) 101 82

Hub heights (m) 99, 124, 135, 149 78, 84, 85, 98, 108, 138

Wind class IEC IIA IEC IIA

The larger one is an Enercon-101 with installed capacity of 3050 kW, hub heights of 99 m, 124 m, 135 m or 149 m, rotor diameter of 101 m and suitable for wind class IEC IIA [76]. The rotor has three blades and total swept area of 8012 m2. It is also equipped with active pitch control system. Its rotational speed varies from 4 to 14.5 rpm. Cut-in and cut- out speeds are 2 m/s and 28-34 m/s, respectively, while rated speed is 13 m/s. The power curve is shown in Figure 28 [76].

3,200

2,800

2,400

) 2,000

t

u

W

d

n

i

o

k

e

-

-

t

(

t

t

a

r u

1,600 u

R

e

C

C w

o 1,200 P

800

400

Enercon-101/3050 0 5 10 15 20 25 30

Wind speed (m/s)

Figure 28: Power curve of Enercon E-101/3050. Cut-in, rated and cut-off speeds are shown. Source (of data): https://www.enercon.de/fileadmin/Redakteur/Medien-Portal/broschueren/pdf/en/ENER- CON_Produkt_en_06_2015.pdf .

-32- The smaller (in terms of power capacity) alternative examined, is an Enercon E-82, with power capacity of 2000 kW, hub heights of 74 m, 84 m, 85 m, 98 m, 108 m or 138 m, 82 m rotor diameter and suitable for wind class IEC IIA [76].The rotor has three blades and total swept area of 5281 m2. It is also equipped with active pitch control system. Its rota- tional speed varies from 6 to 18 rpm. Cut-in speed is 2 m/s and cut-out speed ranges from 28 to 34 m/s, while rated speed is 12.5 m/s. The power curve is shown in Figure 29 [76].

2,400

2,000

1,600

)

t

W

u

d

n

i

k

e

o

-

t

-

(

t

t

a u

r 1,200

u

R

e

C

C

w o

P 800

400

Enercon E-82/2000 0 5 10 15 20 25 30

Wind speed (m/s)

Figure 29: Power curve of Enercon E-82/2000. Cut-in, rated and cut-off speeds are shown. Source (of data): https://www.enercon.de/fileadmin/Redakteur/Medien-Portal/broschueren/pdf/en/ENER- CON_Produkt_en_06_2015.pdf.

Enercon is a leading company in wind energy industry. Its converters were chosen for this study not only because they are used in other sites across Switzerland but also due to the fact that they offer technologies which deal with the effect of icing. Every wind energy converter (WEC) is equipped with an ice-detection system. It measures current operational data for the power curve and blade angle and compares them to an archive of past mean data. Any deviation is attributed to the formation of ice on the blades of the turbine [77]. To counteract the formation of ice on the blades’ surface, Enercon introduced the Rotor Blade Heating System (RBHS), which is an optional feature. It consists of a heater, a diffusor and a fan. It is located on the base of the blade (near the point where it attaches to the rotor) and propagates the hot air (with temperatures up to 72oC [78]) along the blade to the tip (see Figure 30) [77]. In this way, thawing times are reduced. RBHS usually operates with the turbine at standstill, which is restarted automatically or manually after inspection of the blades. However, in sites where icing is not extreme (and

-33- ice is formed in thin layers on the blades) the heating system can operate while the WEC is in operation [77]. The de-icing system is used primarily on sites where aerodynamics’ role is significant as it lessens the reduction of AEP caused by icing. The nominal power of RBHS ranges from 46 kW to 225 kW. For the Enercon E-82 and the Enercon E-101 it is 85 kW and 225 kW respectively. If the RBHS operates during standstill, the Enercon Power Consumption Management subtracts the costs of power supply from the grid [78].

Figure 30: Main parts and principle of operation of the Rotor Blade Heating System (RBHS). Source: http://response.enercon.de/files/20161117_K%20Roloff_Cold%20Climate%20Solution.pdf

-34- 5 Results

5.1 Model validation The models’ accuracy was validated by comparing their predictions with the annual en- ergy production of an operating wind turbine. For the validation were used data from the “Swiss Wind Power Data” website for RETScreen and the model’s database for VFM. The selected turbine is a Vestas V112-3000 installed in Haldenstein (latitude 46.8944, longitude 9.5383, elevation 546 m ASL). The wind turbine has hub height of 119 m, rotor diameter of 112 m and 3 MW capacity [79]. The AEP was 4.372 GWh and the capacity factor 16.63% (calculated from the AEP) for 2016 [80]. RETScreen uses data from the nearest meteorological ground station at Chur, viz wind speed of 2.8 m/s at 10 m AGL, annual air temperature of 9.6o C and atmospheric pressure of 88.5 kPa. However, these values were replaced with data from the wind atlas of Swit- zerland [65] and Meteoblue [75], for better accuracy. Thus, wind speed is 4.9 m/s at 100 AGL, annual temperature is 10.4o C and annual atmospheric pressure is 94.77 kPa (both calculated with the same method as in the end of chapter 4.1). Furthermore, we assume two wind shear exponent values (as described in [74]), the reference one which is 0.11 and the site dependent which is 0.28. Finally, miscellaneous and airfoil losses coefficients were set equal to 4% and 1.75%, respectively and availability to 97% (see chapter 5.2.1 for justification). The results are summarized in Table 4. The estimations of RETScreen of the electricity exported to the grid are 2.96 GWh and 3.24 GWh and the capacity factors are 11.27 % and 12.32 %, for a=0.11 and a=0.28 re- spectively (Figure 31). The deviation from the actual values are -32.30 % and -25.89 % for the AEP and -32.23 % and -25.92 % for the capacity factor, for a=0.11 and a=0.28 respectively. These values are high, but it should be noted that the wind speeds used were only average values and prevailing wind direction was not considered.

-35- Table 4: Model validation results.

Site AEP (GWh) Cf (%)

Actual VFM RETScreen Actual VFM RETScreen

a=0.11 a=0.28 a=0.11 a=0.28

Haldenstein 4.372 1.97 2.96 3.24 16.63 7.49 11.27 12.32

Deviation (%) 0 -54.94 -32.30 -25.89 0 -54.97 -32.23 -25.92

Annual energy production (GWh) Capacity factor (%) Haldenstein 5

16 4

12 3

8 2

1 4

0 0 Vestas V-112/3000 Vestas V-112/3000

Actual Actual VFM VFM RETScreen, a=0.11 RETSCreen, a=0.11 RETScreen, a=0.28 RETScreen, a=0.28

Figure 31: Annual energy production of electricity in Haldenstein. Actual production is com- pared with estimations from VFM and RETScreen.

VFM utilizes data from the MEERA-2 database (see 3.2.2). The estimated average annual wind speed is 3.89 m/s and its hourly variation for 2016 is shown in Figure 32. The esti- mated AEP is 1.97 GWh and the capacity factor is 7.49% (see Figure 33). These values differ from the official data by 54.9%, which is more than significant. In general, greater attention should be given to the deviations of the AEP, because they are calculated from actual data. On the contrary the capacity factor value for Haldenstein is simply estimated from the energy output.

-36- 14 v_ave=3.89 m/s Haldenstein, 2016

) 12

s

/

m

(

v

10

d

e

e

p s

8

d

n

i

w

y l

r 6

u

o

h

d

e 4

t

a

m

i t

s 2 E

0 1000 2000 3000 4000 5000 6000 7000 8000

Time (hours)

Figure 32: Hourly wind speed for 2016 and annual mean wind speed at Haldenstein. Source: https://www.renewables.ninja/

3,000

Haldenstein, 2016 AEP=1.97 GWh

) CF=7.49%

2,500

W

k

(

t

u p

t 2,000

u

o

r

e w

o 1,500

p

y

l

r

u

o h

1,000

d

e

t

a

m i

t 500

s E

0 1000 2000 3000 4000 5000 6000 7000 8000

Time (hours)

Figure 33: Estimated hourly power output for 2016 of 3 MW wind turbine at Haldenstein. Source: https://www.renewables.ninja/

Deviations in estimation of Deviations in estimation of annual energy production (%) capacity factor (%) Haldenstein 0 0

-20 -20

-40 -40

-60 -60

-80 -80

-100 -100 Vestas V-112/3000 Vestas V-112/3000

VFM VFM RETScreen, a=0.11 RETScreen, a=0.11 RETScreen, a=0.28 RETScreen, a=0.28

Figure 34: Deviations in estimations of annual energy production and capacity factors in Hal- denstein.

-37- However, to determine if the above deviation was caused by the specific site or it is an inherent model bias, three additional indicative tests were performed with wind farms located in other European countries. In Edinbane (Scotland) in 2014 the actual AEP was 128 GWh [81] and the estimated AEP 143 GWh, while in I (Denmark) the energy productions in 2010 were 600 GWh [82] and 725 GWh respectively. Finally, in the Baltic 2 wind farm (Germany) 1200 GWh [83] were recorded for 2016 and 1321 GWh were estimated by the model. In the first and third cases the model overestimates the annual energy production by 14.06% and 10.1% respectively, while in the second case it underestimates it by 4.17%. These errors are still large but significantly smaller than the test case in Haldestein. The results are summarized in Table 5.

Table 5: Additional validation of VFM in 3 European sites.

Site Actual AEP (GWh) Estimated AEP (GWh) Deviation (%)

Edinbane (2014) 128 146 14.06

Horns Rev I (2010) 600 575 -4.17

Baltic 2 (2016) 1200 1321 10.1

As it is described in 3.2.2, the systematic bias of MEERA model is caused by the treat- ment of each grid point as a flat surface. This is not the case in Haldenstein (and in most of the sites in Switzerland) unlike in Horns Rev, Baltic 2 and Edinbane wind farms, which are located offshore and in an almost flat site respectively. Thus, the larger errors are justified.

5.2 Basic assumptions For each site twelve simulations are performed with RETScreen, since three different hub heights (99 m, 124 m and 135 m for Enercon E-101 and 98 m, 108 m and 138 m for Enercon E-82) are selected for each turbine and two wind shear exponent values for each site. Moreover, three simulations with data from RETScreen database for each turbine. In addition, three more simulations are performed with VFM for each turbine in each site (one for each hub height), since this model does not provide the choice of power law exponent. Thus, twenty-four simulations for each site and one hundred and forty-four in total.

-38- 5.2.1 RETScreen In paragraph 3.2.1 the basic parameters of the RETScreen model were described. For this study the following assumptions were made. The annual wind speed value is the average wind speed at 100 m AGL, found in the wind atlas of Switzerland [65]. Wind shear exponent obtains two values for each site, 0.11 which is the reference value and another one which is site dependent (see Table 2). An- nual temperatures and pressures are taken from Table 2 (see paragraph 4.1). The shape factor is 2, meaning that the Rayleigh distribution is used by the software. Array losses are 0% since only one turbine is used and no wake from neighboring turbines exist, Airfoil losses include losses from icing. Enercon has validated icing losses in several sites in- cluding the wind turbines in St. Brais in Switzerland. The proposed losses range from 0.5% to 3% of the AEP, including the consumption of RBHS. Thus, airfoil losses are set equal to an average value of 1.75%. Typical values of miscellaneous losses are between 2% and 6% according to the user’s manual of the software, hence an average value of 4% is assumed. Finally, availability of the wind turbine is set to 97% which is the industry standard according to Harman et al [84]. The AEP that is studied is the electricity exported to the grid, which is derived from the unadjusted energy production by accounting for the losses and pressure and temperature corrections.

5.2.2 Virtual Farm Model In this model fewer parameters are selectable. The database used is MEERA-2 and data for year 2016 are selected. Site coordinates, turbine model and hub height are set in ac- cordance with paragraphs 4.1, 4.2 and 5.2 respectively. The assumptions regarding AEP are the same as for the RETScreen model. Although, VFM does not calculate losses or corrections, these (same as in RETScreen) were applied by hand to its results to ensure a fairer comparison of the models.

5.3 RETScreen RETScreen gave estimations for wind speed at hub height, electricity exported to the grid (referred as AEP) and capacity factor. At first data from RETScreen’s database were used, while in the next step accuracy was improved by using data from the “Swiss Wind Power Data” Website.

-39- 5.3.1 Data from RETScreen database In this first estimation, we assume that no external data regarding wind speed and topog- raphy are available for the sites. Thus, the data of RETScreen’s database are used. The reference values of wind speed, annual air pressure and annual mean temperature are taken from the nearest meteorological station. This is not the ideal case because the station may be several kilometers away. Subsequently the wind regime and the topography in the station’s location may vary significantly. The wind speed at hub height is estimated from the power law with wind shear exponent equal to 0.11, which is the reference value. The values of wind speeds are shown in Table 6 and Figure 35. The values of AEP and capacity factors are shown in Table 7 and Figure 36 and Figure 37. For reasons explained shortly above, these results are not analyzed now, but in paragraph 5.5 where they are compared with the results of RETScreen with data from the “Swiss Wind Power Data” website.

Table 6: RETScreen estimations of wind speed at hub height of the two wind turbines in the se- lected sites, with data taken from RETScreen’s database.

Wind speed at hub height (m/s)

Site

Schützenhof Käsern Bad Ragaz Ovronnaz Le Moléson Renan

Turbine Hub height Wind shear exponent a=0.11 model (m)

99 5.02 7.07 3.60 2.96 2.57 3.22

Enercon 124 5.14 7.26 3.69 3.03 2.64 3.30 E-101/3050

135 5.19 7.32 3.73 3.06 2.66 3.33

98 5.01 7.07 3.60 2.96 2.57 3.21

Enercon 108 5.07 7.15 3.64 2.99 2.60 3.25 E-82/2000

138 5.21 7.34 3.74 3.07 2.67 3.34

-40- Estimated wind speed at hub height (m/s)

8

7

6

5

4

3

2 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

Figure 35: RETScreen estimations of wind speed at hub height for different values of wind shear exponent, compared between locations, with data taken from RETScreen’s database.

Table 7: RETScreen estimations of annual energy productions and capacity factors in selected sites, with data taken from RETScreen’s database.

Turbine model Enercon E-101/3050 Enercon E-82/2000

Hub height (m) 99 124 135 98 108 138

AEP Cf AEP Cf AEP Cf AEP Cf AEP Cf AEP Cf

(GWh) (%) (GWh) (%) (GWh) (%) (GWh) (%) (GWh) (%) (GWh) (%)

Schützenhof a=0.11 3.82 14.55 4.09 15.57 4.20 15.97 2.57 14.64 2.64 15.08 2.84 16.20

Käsern a=0.11 8.33 31.71 8.69 33.06 8.83 33.58 5.56 31.73 5.66 32.31 5.92 33.79

Bad Ragaz a=0.11 1.42 5.42 1.53 5.81 1.57 5.97 0.96 5.48 0.99 5.66 1.07 6.10

Ovronnaz a=0.11 0 0 0.77 2.92 0.80 3.05 0 0 0 0 0.55 3.14

Le Moléson a=0.11 0 0 0 0 0 0 0 0 0 0 0 0

Renan a=0.11 1.06 4.03 1.16 4.42 1.20 4.57 0.72 4.09 0.75 4.26 0.82 4.68

-41- Estimated annual energy production (GWh)

9

8

7

6

5

4

3

2

1

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan Figure 36: RETScreen estimations of annual energy production for different values of wind shear exponent, compared between locations, with data taken from RETScreen’s database.

Estimated capacity factor (%)

35

30

25

20

15

10

5

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

Figure 37: RETScreen estimations of capacity factors for different values of wind shear expo- nent, compared between locations, with data taken from RETScreen’s database.

-42- 5.3.2 Data from the “Swiss Wind Power Data” website In the selected sites, in general, wind speeds range from 5.68 m/s to 8.23 m/s. The wind- iest location is Le Moleson with speeds from 7.5 m/s to 8.2 m/s depending on the wind shear exponent. On the contrary, Schützenhof’s wind regime is the less prominent with speeds from 5.68 m/s to 6.09 (see Table 8 and Figure 38).

Table 8: RETScreen estimations of wind speed at hub height of the two wind turbines in the se- lected sites, with data taken from the “Swiss Wind Power Data” website.

Wind speed at hub height (m/s)

Site

Schützenhof Käsern Bad Ragaz Ovronnaz Le Moléson Renan

Wind shear exponent

Turbine Hub height 0.11 0.205 0.11 0.23 0.11 0.265 0.11 0.29 0.11 0.29 0.11 0.22 model (m)

99 5.69 5.69 6.49 6.49 6.59 6.58 6.59 6.58 7.49 7.48 6.59 6.59

Enercon 124 5.84 5.96 6.66 6.83 6.76 6.99 6.76 7.02 7.68 7.98 6.76 6.92 E-101/3050

135 5.89 6.06 6.72 6.96 6.82 7.15 6.82 7.20 7.75 8.18 6.82 7.05

98 5.69 5.68 6.49 6.47 6.59 6.56 6.59 6.56 7.48 7.46 6.56 6.57

Enercon 108 5.75 5.79 6.56 6.62 6.66 6.74 6.66 6.75 7.56 7.67 6.66 6.71 E-82/2000

138 5.91 6.09 6.73 7.00 6.84 7.19 6.84 7.25 7.77 8.23 6.84 7.08

As it seen from the table above and Figure 39 below, the effect of the topography on the wind profiles becomes significant above 100 m AGL and intensifies with increasing alti- tude. Although the differences are small, they are magnified by the fact that wind power extracted, is proportional to the cube of wind speed.

-43- Estimated wind speed at hub height (m/s)

10 a=0.11

8

6

4

2

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

10

8

6

4

2

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof, a=0.205 Kaesern, a=0.23 Bad Ragaz, a=0.265 Ovronnaz, a=0.29 Le Moleson, a=0.29 Renan, a=0.22

Figure 38: RETScreen estimations of wind speed at hub height for different values of wind shear exponent, compared between locations, with data taken from the “Swiss Wind Power Data” website

-44- Estimated wind speed at hub height (m/s)

10 10 Schuetzenhof Kaesern

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

a=0.11 a=0.22 a=0.11 a=0.23

10 10 Bad Ragaz Ovronnaz

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

a=0.11 a=0.265 a=0.11 a=0.29

10 10 Le Moleson Renan

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

a=0.11 a=0.29 a=0.11 a=0.205

Figure 39: RETScreen estimations of wind speed at hub height for different values of wind shear exponent, at each location, with data taken from the “Swiss Wind Power Data” website.

The annual energy productions and capacity factors were estimated in all six sites for two different wind converters at three different hub heights for each one and for two values of wind shear exponent. The results are shown in Table 9. Two expected facts were confirmed, regarding the AEP. Firstly, the higher the wind speed the higher the energy production and secondly Enercon E-101 produced higher amounts of electricity compared to Enercon E-82, due to its larger swept area (see Figure 40).

-45- It is, also observed that at low altitudes, namely at 99 m for Enercon E-101 and at 98 m for Enercon E-82, the AEP is larger for the smaller value of the power law exponent (see also Figure 40). In the rest hub heights, the opposite is true.

Table 9: RETScreen estimations of annual energy productions and capacity factors in selected sites, with data taken from the “Swiss Wind Power Data” website.

Turbine model Enercon E-101/3050 Enercon E-82/2000

Hub height (m) 99 124 135 98 108 138

AEP Cf AEP Cf AEP Cf AEP Cf AEP Cf AEP Cf

(GWh) (%) (GWh) (%) (GWh) (%) (GWh) (%) (GWh) (%) (GWh) (%)

Schützenhof a=0.11 5.31 20.21 5.62 21.38 5.74 21.83 3.55 20.28 3.64 20.78 3.87 22.07 a=0.205 5.30 20.17 5.88 22.37 6.11 23.24 3.54 20.19 3.70 21.13 4.13 23.57

Käsern a=0.11 6.76 25.74 7.10 27.03 7.23 27.52 4.51 25.77 4.61 26.32 4.86 27.73 a=0.23 6.75 25.67 7.47 28.41 7.75 29.48 4.49 25.65 4.70 26.80 5.23 29.83

Bad Ragaz a=0.11 6.96 26.48 7.30 27.79 7.44 28.29 4.64 26.51 4.74 4.74 4.99 28.50 a=0.265 6.94 26.4 7.78 29.60 8.09 30.77 4.62 26.35 4.85 27.70 5.46 31.14

Ovronnaz a=0.11 6.55 24.92 6.87 26.15 6.70 26.62 4.37 24.95 4.46 25.47 4.70 26.82 a=0.29 6.53 24.83 7.39 28.12 7.71 29.32 4.34 24.77 4.58 26.16 5.20 29.70

Le Moléson a=0.11 7.97 30.32 8.29 31.56 8.42 32.04 5.31 30.32 5.40 30.85 5.64 32.21 a=0.29 7.94 30.23 8.82 33.57 9.13 34.73 5.28 30.14 5.53 31.55 6.15 35.08

Renan a=0.11 6.80 25.87 7.14 27.15 7.26 27.64 4.54 25.90 4.63 26.45 4.88 27.85 a=0.22 6.78 25.81 7.46 28.40 7.72 29.38 4.52 25.80 4.71 26.88 5.20 29.69

The most productive site is Le Moléson. At 99 m AGL 7.97 GWh and 7.94 GWh of electricity are produced annually by an Enercon E-101 for a=0.11 and a=0.28 respec- tively, while this amount rises accordingly to 8.42 GWh and 9.13 GWh at 135 AGL. For an Enercon E-82 the corresponding values are 5.31 GWh and 5.28 GWh at 98 m AGL and 5.64 GWh and 6.15 GWh at 138 m AGL.

-46- Estimated annual energy production (GWh)

10 10 Schuetzenhof Kaesern

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

a=0.11 a=0.205 a=0.11 a=0.23

10 10 Bad Ragaz Ovronnaz

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

a=0.11 a=0.265 a=0.11 a=0.29

10 10 Le Moleson Renan

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 a=0.11 a=0.29 a=0.11 a=0.22

Figure 40: RETScreen estimations of annual energy production, for different values of wind shear exponent, at each location, with data taken from the “Swiss Wind Power Data” website.

In Schützenhof the lowest production is observed. Electricity exported to the grid ranges from approximately 5.30 GWh to 6.11 GWh for Enercon E-101 and from 3.54 GWh to 4.13 GWh for Enercon E-82. In the rest sites the production is around 7 GWh and 4.5 GWh for the larger and smaller wind turbines respectively (see Figure 41).

-47- Estimated annual energy production (GWh)

10 a=0.11

8

6

4

2

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

10

8

6

4

2

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof, a=0.205 Kaesern, a=0.23 Bad Ragaz, a=0.265 Ovronnaz, a=0.29 Le Moleson, a=0.29 Renan, a=0.22

Figure 41: RETScreen estimations of annual energy production for different values of wind shear exponent, compared between locations, with data taken from the “Swiss Wind Power Data” website.

-48- Estimated capacity factor (%)

40 a=0.11 35

30

25

20

15

10

5

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

40

35

30

25

20

15

10

5

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Russikon, a=0.205 Kaesern, a=0.23 Bad Ragaz, a=0.265 Ovronnaz, a=0.29 Le Moleson, a=0.29 Renan, a=0.22

Figure 42: RETScreen estimations of capacity factors for different values of wind shear expo- nent, compared between locations, with data taken from the “Swiss Wind Power Data” website.

-49- The estimated capacity factors naturally, follow the trend observed in wind speeds and AEP as far as the different sites are concerned (see Figure 42). However, as it shown in Figure 43, the capacity factors in a specific site are comparable. The most interesting observation is that at comparable hub heights, namely 98 m and 138 m for E-82 and 99 m and 135 m for E-101, the smaller wind turbine has equal or higher capacity factors.

Estimated capacity factor (%)

40 40 Schuetzenhof Kaesern 35 35

30 30

25 25

20 20

15 15

10 10

5 5

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

a=0.11 a=0.205 a=0.11 a=0.23

40 40 Bad Ragaz Ovronnaz 35 35

30 30

25 25

20 20

15 15

10 10

5 5

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

a=0.11 a=0.265 a=0.11 a=0.29

40 40 Le Moleson Renan 35 35

30 30

25 25

20 20

15 15

10 10

5 5

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 a=0.11 a=0.29 a=0.11 a=0.22

Figure 43: RETScreen estimations of capacity factors for different values of wind shear expo- nent, compared between locations, with data taken from the “Swiss Wind Power Data” website.

-50- 5.4 Virtual Farm Model The estimations of wind speed at hub height of the Virtual Wind farm model are quite different (seeTable 10). The estimated values range from 3.76 m/s to 5.59 m/s and fur- thermore the classification of the sites is changed.

Table 10: VFM estimations of wind speed at hub height of the two wind turbines in the selected sites.

Wind speed at hub height (m/s)

Site

Turbine Hub height Schützenhof Käsern Bad Ragaz Ovronnaz Le Moléson Renan model (m)

99 4.69 4.26 3.77 3.76 4.40 5.37

Enercon 124 4.81 4.39 3.94 3.85 4.54 5.52 E-101/3050

135 4.86 4.44 4.00 3.89 4.59 5.58

98 4.68 4.25 3.76 3.75 4.40 5.37

Enercon 108 4.72 4.309 3.83 3.80 4.45 5.43 E-82/2000

138 4.85 4.45 4.02 3.90 4.60 5.59

Renan ranks first with speeds from 5.37 m/s to 5.59 m/s, while Ovronnaz (which was ranked second in the RETScreen estimations) exhibits the poorest wind speeds, ranging between 3.75 m/s and 3.90 m/s (Figure 44). The reasons for this erroneous change will be discussed in chapter 5.5. Table 11 depicts the VFM estimations of AEP and capacity factors. Regarding the esti- mated AEP, it is again obvious from Figure 45, that the more powerful converter can produce higher amounts of electricity than the smaller alternative. The energy produced is again analogous to the wind speeds and the deviations in them are transferred to the AEP and the capacity factors as well.

-51- Estimated wind speed at hub height (m/s)

7

6

5

4

3

2

1

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Turbine model

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

Figure 44: VFM estimations of wind speed at hub height, compared between locations.

The capacity factors computed by the VFM model are overall much smaller than the ones of RETScreen, however the relationship between them remains the same. The E-82 wind turbine has capacity factors of the same level or even larger from the ones of the E-101 (see Figure 46).

Table 11: VFM estimations of annual energy productions and capacity factors in the selected sites.

Enercon E-101/3050 Enercon E-82/2000

Hub height 99 124 135 98 108 138 (m)

AEP AEP AEP AEP AEP Cf AEP Cf Cf (%) Cf (%) Cf (%) Cf (%) (GWh) (GWh) (GWh) (GWh) (GWh) (%) (GWh) (%)

Schützenhof 3.09 12.63 3.33 13.63 3.43 14.02 2.03 12.68 2.04 12.87 2.24 13.97

Käsern 2.17 8.88 2.39 9.78 2.48 10.13 1.43 8.91 1.49 9.30 1.65 10.3

Bad Ragaz 1.55 6.33 1.81 7.39 1.91 7.81 1.02 6.35 1.09 6.80 1.28 7.99

Ovronnaz 1.41 5.76 1.54 6.28 1.59 6.49 0.93 5.83 0.97 6.02 1.06 6.60

Le Moléson 2.44 9.98 2.68 10.96 2.77 11.34 1.61 10.02 1.67 10.44 1.84 11.53

Renan 4.42 18.09 4.74 19.40 4.86 19.90 2.91 18.15 3.00 18.71 3.23 20.15

-52- Estimated annual energy production (GWh)

7

6

5

4

3

2

1

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Turbine model

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

Figure 45: VFM estimations of annual energy production, compared between locations.

Estimated capacity factor (%)

25

20

15

10

5

0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Turbine model

Schuetzenhof Bad Ragaz Kaesern Ovronnaz Le Moleson Renan

Figure 46: VFM estimations of capacity factors, compared between locations.

-53- 5.5 Comparative results The results presented in the last two chapters gave an insight of the capabilities of the models. In this chapter a comparison of the results is presented, to reveal the advantages and weaknesses of each model. As it was stated in paragraph 3.1, the first comparison concerns only the RETScreen model More specifically it is tested how RETScreen performs with data from its own database against data from the “Swiss Wind Power Data” website. In the following tables (Table 12 and Table 13) and figures (Figure 47, Figure 48, Figure 49, Figure 50, Figure 51 and Figure 52 ) it is clearly shown the large diversity and the deviations of the results. It is obvious that when RETScreen uses its own database the results are far from accurate. The proximity of the closest meteorological station (to each site) is very significant for the quality of the estimations. An example is the site of Käsern. There the turbine’s and the station’s locations are not only close but there are no significant landscape changes. Thus, the deviations are rela- tively small and RETScreen overestimates wind speed at hub height by 8% and annual energy production by 22%. On the contrary in the site of Le Moléson the model underrates the results 100%. This finding suggests that there are substantial differences in the wind regimes of the site and of the meteorological station. However, this should not be interpreted as a weakness of the model. The RETScreen model is capable of producing fairly accurate results given that the inserted data are val- idated.

-54- Estimated wind speed at hub height (m/s)

10 10 Schuetzenhof Kaesern

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen Database RETScreen Database Swiss Wind Power Data Swiss Wind Power Data

10 10

Bad Ragaz Ovronnaz

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen Database RETScreen Database Swiss Wind Power Data Swiss Wind Power Data

10 10

Le Moleson Renan

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen Database RETScreen Database Swiss Wind Power Data Swiss Wind Power Data

Figure 47: Comparison of wind speed at hub height estimations of the two RETScreen cases at each location

-55- Table 12: Deviations in estimations of wind speed at hub height of the two RETScreen cases in

selected sites.

60.96 60.96 60.96 60.96 60.96 60.96

Renan ------

Moleson

65.65 65.65 65.65 65.65 65.65 65.65

Le Le ------

55.11 55.11 55.11 55.11 55.11 55.11

Ovronnaz ------

45.35 45.35 45.35 45.35 45.35 45.35

Bad Ragaz Bad ------

Käsern 8.88 9.10 8.90 9.00 9.00 9.00

86

11. 11.856 11.86 11.86 11.86 11.86

Site Schützenhof a=0.11 exponent Wind shear ------

(m) Hub height 99 124 135 98 108 138

101/3050 82/2000

- -

Deviations in wind speed estimation speed in wind Deviations model Turbine Enercon E Enercon E

-56- Deviations in estimation of wind speed at hub height (%)

100

75

50

25

0

-25

-50

-75

-100 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

Figure 48: Deviations in estimations of wind speed at hub height, of the two RETScreen cases compared between sites.

Estimated annual energy production (GWh)

10 9 Schuetzenhof Kaesern

8 8

6 7

4 6

2 5

0 4 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen Database RETScreen Database Swiss Wind Power Data Swiss Wind Power Data

8 8 Bad Ragaz Ovronnaz 7 7

6 6

5 5

4 4

3 3

2 2

1 1

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen Database RETScreen Database Swiss Wind Power Data Swiss Wind Power Data

9 8 Le Moleson Renan 8 7

7 6 6 5 5 4 4 3 3 2 2

1 1

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen Database RETScreen Database Swiss Wind Power Data Swiss Wind Powe Data

Figure 49: Comparison of annual energy production estimations of the two RETScreen cases at each location.

-57- Table 13: Deviations in estimations of annual energy productions and capacity factors of the two RETScreen cases in selected sites.

Enercon E-101/3050 Enercon E-82/2000

Hub height 99 124 135 98 108 138 (m)

AEP AEP AEP AEP AEP AEP Cf (%) Cf (%) Cf (%) Cf (%) Cf (%) Cf (%) (GWh) (GWh) (GWh) (GWh) (GWh) (GWh)

Schützenhof a=0.11 -28.03 -28.02 -27.17 -27.17 -26.88 -26.87 -27.81 -27.82 -27.48 -27.45 -26.59 -26.58

Käsern a=0.11 23.22 23.21 22.33 22.32 22.02 22.00 23.13 23.13 22.74 22.74 21.83

Bad Ragaz a=0.11 -79.55 -79.55 -79.08 -79.31 -78.91 -78.91 -79.31 -79.31 -79.10 -79.10 -78.59 -78.60

Ovronnaz a=0.11 -100 -100 -88.83 -88.83 -88.56 -88.55 -100 -100 -100 -100 -88.30 -88.29

Le Moléson a=0.11 -100 -100 -100 -100 -100 -100 -100 -100 -100 -100 -100 -100

Renan a=0.11 -84.41 -84.41 -83.73 -83.73 -83.48 -83.48 -84.22 -84.21 -83.90 -83.91 -83.17 -83.18

Deviations in estimations of annual energy production (%)

100

75

50

25

0

-25

-50

-75

-100 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

Figure 50: Deviations in estimations of annual energy production, of the two RETScreen cases compared between sites.

-58- Estimated capacity factor (%)

40 40 Kaesern 35 Scuetzenhof 35

30 30

25 25

20 20

15 15

10 10

5 5

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen Database RETScreen Database Swiss Wind Power Data Swiss Wind Power Data

40 40

Bad Ragaz Ovronnaz 35 35

30 30

25 25

20 20

15 15

10 10

5 5

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen Database RETScreen Database Swiss Wind Power Data Swiss Wind Power Data

40 40

Le Moleson Renan 35 35

30 30

25 25

20 20

15 15

10 10

5 5

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen Database RETScreen Database Swiss Wind Power Data Swiss Wind Power Data

Figure 51: Comparison of capacity factor estimations of the two RETScreen cases at each loca- tion.

Deviations in estimation of capacity factor (%)

100

75

50

25

0

-25

-50

-75

-100 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

Figure 52: Deviations in estimations of capacity factors, of the two RETScreen cases compared between sites.

-59- The second comparison concerns the estimations of RETScreen (with data from the “Swiss Wind Power Data” website) and VFM. In Figure 53 it is highlighted that the estimations of the models differ in general. In Table 14 are presented the deviations between the results of the two models. More specifically it is tested how the VFM performs in comparison to RETScreen. It is deduced that VFM underestimates the wind speed at hub height in all the locations. The smallest deviations are found in Schützenhof and Renan and are roughly -18%, while the largest misestimations are observed in Bad Ragaz, Ovronnaz and Le Moléson with values of approximately -42% and -40% respectively (see Figure 54)

Estimated wind speed at hub height (m/s)

10 10 Schuetzenhof Kaesern

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen a=0.11 RETScreen a=0.11 RETScreen a=0.205 RETScreen a=0.23 VFM VFM

10 10 Bad Ragaz Ovronnaz

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Turbine model

RETScreen a=0.11 RETScreen a=0.11 RETScreen a=0.265 RETScreen a=0.29 VFM VFM

10 10 Le Moleson Renan

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen a=0.11 RETScreen a=0.11 RETScreen a=0.29 RETScreen a=0.22 VFM VFM

Figure 53: Comparison of wind speed at hub height estimations of RETScreen and VFM at each location.

-60- It also understimates the annual energy output, but the deviations are even larger (see Table 15 and Figure 55 and Figure 56). In Schützenhof,the deviations are approximately -42%, while in Käsern rise to -68%. In Bad Ragaz and Ovronnaz they are roughly -76%. In Le Moléson, they are slightly less and almost -70%. Finally, in Renan they obtain their smallest values of around -35%. These findings suggest that the deviations in wind speeds are magnified during the trans- formation of the wind speeds to power output. One reason is that wind power is propor- tional to the cube of the wind speed. Subsequently, deviations of the same magnitude occur for the capacity factors (see Figure 57 and Figure 58) The most effective way to minimize deviations would be the existence of accurate wind speeds. However, the basis of the VFM model is reanalysis, which has some inherent systematic errors or biases. It was mentioned before (see 3.2.2) that these are caused by imperfections of the weather forecasting model that is used to predict wind speeds. In addition, the model treats every location as a flat surface, thus failing to account for local topography. Moreover, local microclimatic conditions which affect wind speeds are also not considered since each cell has very large dimensions. In the publication of the creators of the VFM model [63] it is explained how the system- atic errors in the capacity factors of each country are calculated and corrected. In brief, a coefficient is calculated and is multiplied with the simulated capacity factors to correct them. However, this bias correction factor was not calculated for Switzerland and this severely affects the results of the model in this country.

-61- Table 14: Deviations of VFM estimations compared to RETScreen estimations of wind speed at

hub height in selected sites.

18.39 20.22 20.91 18.31 19.09 21.09

0.22 ------

18.48 18.31 18.26 18.49 18.80 18.25

Renan 0.11 ------

41.14 43.16 43.92 41.05 41.92 44.12

0.29 ------

1

41.24 40.92 40.81 41.26 41.1 40.78

Le Le Moleson 0.11 ------

42.89 45.12 45.95 42.79 43.76 46.17

0.29 ------

42.99 42.96 42.96 42.99 42.97 42.96

Ovronnaz 0.11 ------

42.75 43.60 43.94 42.71 43.06 44.04

0.265 ------

42.84 41.68 41.27 42.89 42.38 41.17

Bad Ragaz Bad 0.11 ------

5

34.3 37.71 36.24 34.29 37.84 36.73

0.23 ------

33.86

.11

34.43 34.03 33.90 34.45 34.27

Käsern 0 ------

17.56 19.17 19.79 17.55 18.56 20.31

0.205 ------

17.64 17.50 17.47 17.71 17.96 17.83

Site Schützenhof exponent Wind shear 0.11 ------

(m) Hub height 99 124 135 98 108 138

ind speed estimation speed ind

in w

bine model bine

101/3050 82/2000

- -

Deviations Tur Enercon E Enercon E

-62- Deviations in estimation of wind speed at hub height

0

-20

-40

-60

-80

a=0.11 -100 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

0

-20

-40

-60

-80

a: site dependent -100 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

Figure 54: Deviations of VFM estimations compared with RETScreen estimations for wind speed at hub height, compared between sites.

-63- Table 15: Deviations of VFM estimations compared to RETScreen estimations of annual energy productions and capacity factors in selected sites.

Enercon E-101/3050 Enercon E-82/2000

Hub height 99 124 135 98 108 138 (m)

AEP AEP AEP AEP AEP AEP Cf (%) Cf (%) Cf (%) Cf (%) Cf (%) Cf (%) (GWh) (GWh) (GWh) (GWh) (GWh) (GWh)

Schützenhof a=0.11 -41.86 -37.49 -40.70 -36.25 -40.28 -35.80 -42.78 -37.46 -44.07 -38.07 -42.10 -36.71 a=0.205 -41.73 -37.35 -43.32 -39.07 -43.88 -39.67 -42.53 -37.18 -44.99 -39.08 -45.79 -40.75

Käsern a=0.11 -67.92 -65.51 -66.35 -63.83 -65.78 -63.21 -68.36 -65.42 -67.69 -64.68 -66.03 -62.87 a=0.23 -67.84 -65.42 -67.99 -65.59 -68.05 -65.65 -68.21 -65.25 -68.27 -65.31 -68.42 -65.48

Bad Ragaz a=0.11 -77.75 -76.10 -75.26 -73.40 -74.32 -72.39 -78.08 -76.04 -77.02 -74.90 -74.34 -71.95 a=0.265 -77.68 -76.00 -76.78 -75.03 -76.39 -74.61 -77.94 -75.89 -77.54 -75.46 -76.51 -74.33

Ovronnaz a=0.11 -78.49 -76.88 -77.66 -75.98 -77.34 -75.64 -78.72 -76.62 -78.37 -78.35 -77.47 -75.38 a=0.29 -78.41 -76.79 -79.22 -77.66 -79.43 -77.88 -78.57 -76.46 -78.94 -79.98 -79.66 -77.76

Le Moléson a=0.11 -69.37 -67.07 -67.69 -65.27 -67.04 -64.60 -69.76 -66.95 -69.04 -66.16 -67.40 -64.21 a=0.29 -69.28 -66.97 -69.62 -67.34 -69.60 -67.34 -69.58 -66.75 -69.72 -66.91 -70.10 -67.14

Renan a=0.11 -34.96 -30.07 -33.55 -28.57 -33.05 -28.03 -35.88 -29.91 -35.26 -29.23 -33.79 -27.63 a=0.22 -34.82 -29.92 -36.48 -31.71 -37.01 -32.29 -35.60 -29.61 -36.31 -30.38 -37.90 -32.13

-64- Estimated annual energy production (GWh)

10 10 Schuetzenhof Kaesern

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen a=0.11 RETScreen a=0.11 RETScreen a=0.205 RETScreen a=0.23 VFM VFM

10 10 Bad Ragaz Ovronnaz

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen a=0.11 RETScreen a=0.11 RETScreen a=0.265 RETScreen a=0.29 VFM VFM

10 10 Le Moleson Renan

8 8

6 6

4 4

2 2

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen a=0.11 RETScreen a=0.11 RETScreen a=0.29 RETScreen a=0.22 VFM VFM

Figure 55: Comparison of annual energy production estimations of RETScreen and VFM at each location.

-65- Deviations in estimation of annual energy production

0

-20

-40

-60

-80

a=0.11 -100 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Scuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

0

-20

-40

-60

-80

a: site dependent -100 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kasern Bad Ragaz Ovronnaz Le Moleson Renan

Figure 56: Deviations of VFM estimations compared with RETScreen estimations for annual energy production, compared between sites.

-66- Estimated capacity factor (%)

40 40 Schuetzenhof Kaesern 35 35

30 30

25 25

20 20

15 15

10 10

5 5

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen a=0.11 RETSCreen a=0.11 RETScreen a=0.205 RETScreen a=0.23 VFM VFM

40 40 Bad Ragaz Ovronnaz 35 35

30 30

25 25

20 20

15 15

10 10

5 5

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen a=0.11 RETScreen a=0.11 RETScreen a=0.265 RETScreen a=0.29 VFM VFM

40 40 Le Moleson Renan 35 35

30 30

25 25

20 20

15 15

10 10

5 5

0 0 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

RETScreen a=0.11 RETScreen a=0.11 RETScreen a=0.29 RETScreen a=0.22 VFM VFM

Figure 57: Comparison of capacity factor estimations of RETScreen and VFM at each location.

-67- Deviations in estimation of capacity factor (%)

0

-20

-40

-60

-80

a=0.11 -100 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

0

-20

-40

-60

-80

a: site dependent -100 E-101/99 E-101/124 E-101/135 E-82/98 E-82/108 E-82/138

Schuetzenhof Kaesern Bad Ragaz Ovronnaz Le Moleson Renan

Figure 58: Deviations of VFM estimations compared with RETScreen estimations for capacity factors, compared between sites.

-68- 6 Conclusions & Outlook

Conclusions In this study the annual energy productions and capacity factors of two wind turbines in six locations in Switzerland were estimated and compared using two freely available models VFM and RETScreen. The main conclusions are as follows. (1) The most productive site, based on RETscreen estimations for a=0.11, is Le Moléson. An Enercon E-101 produces 7.97 GWh (at 99 m), 8.29 GWh (at 124 m) and 8.42 GWh (at 135 m), while an E-82 produces 5.31 GWh (at 98 m), 5.40 GWh (at 108 m) and 5.64 GWh (at 138 m). The least productive site is Schützenhof. An Enercon E-101 produces 5.31 GWh (at 99 m), 5.62 GWh (at 124 m) and 5.74 GWh (at 135 m), while an E-82 produces 3.55 GWh (at 98 m), 3.64 GWh (at 108 m) and 3.87 GWh (at 138 m). (2) The AEP at 98m (of an E-82) and at 99 m (of an E-101) is lower (or equal at best) for the site dependent value of the wind shear exponent, which is larger than the reference value of 0.11. This finding suggests that a wind profile diversifies sig- nificantly above 100 m AGL. (3) The most productive site, based on VFM estimations, is Renan. An Enercon E- 101 produces 4.42 GWh (at 99 m), 4.74 GWh (at 124 m) and 4.86 GWh (at 135 m), while an E-82 produces 2.91 GWh (at 98 m), 3.00 GWh (at 108 m) and 3.23 GWh (at 138 m). The least productive site is Ovronnaz. An Enercon E-101 pro- duces 1.41 GWh (at 99 m), 1.54 GWh (at 124 m) and 1.59 GWh (at 135 m), while an E-82 produces 0.93 GWh (at 98 m), 0.97 GWh (at 108 m) and 1.06 GWh (at 138 m). (4) In total, E-82 produces less energy than E-101 at the same height, since it has smaller rotor diameter and smaller power output. However, the corresponding ca- pacity factors are greater. Thus, the interested parties can choose efficiency or quantity of produced electricity depending on their needs (5) The results of the RETScreen model with two different types of data suggest that the RETScreen database should be used with caution, since the proximity of the

-69- nearest meteorological station to the site and the climatic conditions and/or topog- raphy in the intermediate distance can favor or severely impact the quality of the estimations. (6) The comparative results clearly show that VFM underestimates all the measures under study, compared to RETScreen, in all sites. Wind speed at hub heights de- viations range from 20% to 40%, while AEP and capacity factors present mises- timations of 40% to 80%. (7) The previous result is backed from the model validation. RETScreen achieves more accurate results than VFM in the “test” sites of Haldenstein. The deviations from actual AEP is 26% with a=0.28 (and 32% with a=0.11) and 55% respec- tively. (8) The VFM model suffers from inaccuracies related to the site topography. It treats every location as a flat surface and thus fails to predict the changes of wind pro- files above complex terrain. Subsequently, the flatter the site the better the results. This is depicted in conclusion 3, since Renan is a fairly flat site while Ovronnaz lies on a slope in front a mountain complex. It is additionally illustrated in model validation. In wind farms of Edinbane (onshore flat site), Horns Rev I (offshore) and Baltic 2 (offshore) the model produces results with significantly smaller de- viations which are 14%, -4% (underestimation) and 10% respectively. (9) There is no bias correction factor for Switzerland to lessen the topography related deviations. (10) In general, the VFM estimations are subject to the site’s topography and geo- graphic location and therefore it should be used with caution and only for rough estimations of the actual wind regime. The same, bar the topography, applies for the RETScreen model but only when using its own database. The model itself can produce satisfying results when properly loaded with accurate data. Outlook The future of wind power in Switzerland is promising since the reduction of fossil fuel emissions and the development of renewable energy sources are part of the na- tional “Energy strategy 2050” [85]. Hence, the availability of accurate measurements and data is of high importance. Future improvements of this study include inter alia: (1) the study of other sites in Switzerland and the evaluation of their wind poten- tial.

-70- (2) the estimation of AEP with RETScreen in the selected (or new) sites by using the prevailing wind direction and its magnitude and in addition the Weibull distribution based on the values of its parameters for each site. (3) the use of more accurate techniques for the estimation of AEP in the selected (or new) sites, such as CFD software.

-71-

Bibliography

[1] Global Wind Energy Council. 2017. Wind in numbers. [ONLINE] Available at: http://gwec.net/global-figures/wind-in-numbers/ . [Accessed 13 August 2018]. [2] Wind Europe (2018). Wind in power 2017. Annual combined onshore and offshore wind energy statistics. Wind Europe, p.17. [3] Wind Europe (2018). Wind in power 2017. Annual combined onshore and offshore wind energy statistics. Wind Europe, p.21. [4] The Swiss Wind Power Data Website. (2018). Home. [ONLINE] Available at: https://wind- data.ch/index.php . [Accessed 30 September 2018]. [5] Suisse Eole. 2018. Statistics. [ONLINE] Available at: http://www.suisse-eole.ch/de/windener- gie/statistik/. [Accessed 14 August 2018]. [6] Wind Europe (2018). Wind in power 2017. Annual combined onshore and offshore wind energy statistics. Wind Europe, p.22. [7] Suisse Éole. 2018. Good reasons for wind energy. [ONLINE] Available at: http://www.suisse- eole.ch/de/windenergie/gute-grunde/ . [Accessed 14 August 2018]. [8] Weisser, D., 2003. A wind energy analysis of Grenada: an estimation using the ‘Weibull’density function. Renewable energy, 28(11), pp.1803-1812. [9] Hoogwijk, M., de Vries, B. and Turkenburg, W., 2004. Assessment of the global and regional geographical, technical and economic potential of onshore wind energy. Energy Econom- ics, 26(5), pp.889-919. [10] Vogiatzis, N., Kotti, K., Spanomitsios, S. and Stoukides, M., 2004. Analysis of wind potential and characteristics in North Aegean, Greece. Renewable energy, 29(7), pp.1193-1208. [11] Eskin, N., Artar, H. and Tolun, S., 2008. Wind energy potential of Gökçeada Island in Turkey. Re- newable and Sustainable Energy Reviews, 12(3), pp.839-851. [12] Dhunny, A.Z., Lollchund, M.R. and Rughooputh, S.D.D.V., 2016. Evaluation of a wind farm pro- ject for a smart city in the South-East Coastal Zone of Mauritius. Journal of Energy in Southern Africa, 27(1), pp.39-50. [13] Chang, T.P., 2011. Estimation of wind energy potential using different probability density func- tions. Applied Energy, 88(5), pp.1848-1856. [14] MathWorks. 2018. Rayleigh Distribution. [ONLINE] Available at: http://uk.math- works.com/help/stats/rayleigh-distribution.html . [Accessed 30 July 2018]. [15] Celik, A.N., 2004. A statistical analysis of wind power density based on the Weibull and Rayleigh models at the southern region of Turkey. Renewable energy, 29(4), pp.593-604. [16] Sliz-Szkliniarz, B. and Vogt, J., 2011. GIS-based approach for the evaluation of wind energy po- tential: A case study for the Kujawsko–Pomorskie Voivodeship. Renewable and Sustainable En- ergy Reviews, 15(3), pp.1696-1707.

-73- [17] Siyal, S.H., Mörtberg, U., Mentis, D., Welsch, M., Babelon, I. and Howells, M., 2015. Wind en- ergy assessment considering geographic and environmental restrictions in Sweden: A GIS-based approach. Energy, 83, pp.447-461. [18] Bechrakis, D.A., Deane, J.P. and McKeogh, E.J., 2004. of an area using short term-data correlated to a long-term data set. Solar Energy, 76(6), pp.725-732. [19] Kanellpoulos, D., 1992. National wind resources validation in Greece. Journal of Wind Engineer- ing and Industrial Aerodynamics, 39(1-3), pp.367-372. [20] Barnard, J.C., 1990. An evaluation of three models designed for siting wind turbines in areas of complex terrain (No. PNL-7357). Pacific Northwest Lab., Richland, WA (USA). [21] Finardi, S., Tinarelli, G., Faggian, P. and Brusasca, G., 1998. Evaluation of different wind field modeling techniques for wind energy applications over complex topography. Journal of Wind En- gineering and Industrial Aerodynamics, 74, pp.283-294. [22] Katsoulis, B.D., 1993. A survey on the assessment of wind energy potential in Greece. Theoretical and applied climatology, 47(1), pp.51-63. [23] Bagiorgas, H.S., Assimakopoulos, M.N., Theoharopoulos, D., Matthopoulos, D. and Mihala- kakou, G.K., 2007. Electricity generation using wind energy conversion systems in the area of Western Greece. Energy Conversion and Management, 48(5), pp.1640-1655. [24] Xydis, G., Koroneos, C. and Loizidou, M., 2009. Exergy analysis in a wind speed prognostic model as a wind farm sitting selection tool: a case study in Southern Greece. Applied En- ergy, 86(11), pp.2411-2420. [25] Akpinar, E.K. and Akpinar, S., 2004. Determination of the wind energy potential for Maden- Elazig, Turkey. Energy Conversion and Management, 45(18-19), pp.2901-2914. [26] Renewable Resource Data Center. 2018. Classes of wind power density at 10 m and 50 m. [ONLINE] Available at: https://rredc.nrel.gov/wind/pubs/atlas/tables/1-1T.html . [Accessed 31 July 2018]. [27] Gökçek, M., Bayülken, A. and Bekdemir, Ş., 2007. Investigation of wind characteristics and wind energy potential in Kirklareli, Turkey. Renewable Energy, 32(10), pp.1739-1752. [28] Mirhosseini, M., Sharifi, F. and Sedaghat, A., 2011. Assessing the wind energy potential locations in province of Semnan in Iran. Renewable and Sustainable Energy Reviews, 15(1), pp.449-459. [29] Himri, Y., Himri, S. and Stambouli, A.B., 2009. Assessing the wind energy potential projects in Algeria. Renewable and Sustainable Energy Reviews, 13(8), pp.2187-2191. [30] Ouammi, A., Sacile, R. and Mimet, A., 2010. Wind energy potential in Liguria region. Renewable and Sustainable Energy Reviews, 14(1), pp.289-300. [31] Ban, M., Perković, L., Duić, N. and Penedo, R., 2013. Estimating the spatial distribution of high- altitude wind energy potential in Southeast Europe. Energy, 57, pp.24-29. [32] Islam, M.R., Saidur, R. and Rahim, N.A., 2011. Assessment of wind energy potentiality at Kudat and Labuan, Malaysia using Weibull distribution function. Energy, 36(2), pp.985-992. [33] Mabel, M.C. and Fernandez, E., 2008. Analysis of wind power generation and prediction using ANN: A case study. Renewable energy, 33(5), pp.986-992.

-74- [34] Li, M. and Li, X., 2005. Investigation of wind characteristics and assessment of wind energy po- tential for Waterloo region, Canada. Energy Conversion and Management, 46(18-19), pp.3014- 3033. [35] Acker, T.L., Williams, S.K., Duque, E.P., Brummels, G. and Buechler, J., 2007. Wind resource assessment in the state of Arizona: Inventory, capacity factor, and cost. Renewable Energy, 32(9), pp.1453-1466. [36] Köse, R., 2004. An evaluation of wind energy potential as a power generation source in Kütahya, Turkey. Energy conversion and management, 45(11-12), pp.1631-1641. [37] Celik, A.N., 2007. A techno-economic analysis of wind energy in southern Turkey. International Journal of Green Energy, 4(3), pp.233-247. [38] Ucar, A. and Balo, F., 2009. Evaluation of wind energy potential and electricity generation at six locations in Turkey. Applied Energy, 86(10), pp.1864-1872. [39] Ucar, A. and Balo, F., 2009. Investigation of wind characteristics and assessment of wind-gener- ation potentiality in Uludağ-Bursa, Turkey. Applied energy, 86(3), pp.333-339. [40] Ucar, A. and Balo, F., 2011. An investigation of wind turbine characteristics and the wind potential assessment of Ankara, Turkey. Energy Sources, Part A: Recovery, Utilization, and Environmental Effects, 33(13), pp.1291-1303. [41] Al-Abbadi, N.M., 2005. Wind energy resource assessment for five locations in Saudi Arabia. Re- newable Energy, 30(10), pp.1489-1499. [42] Shata, A.A. and Hanitsch, R., 2006. Evaluation of wind energy potential and electricity generation on the coast of Mediterranean Sea in Egypt. Renewable Energy, 31(8), pp.1183-1202. [43] Ahmed, A.S., 2010. Wind energy as a potential generation source at Ras Benas, Egypt. Renewable and Sustainable Energy Reviews, 14(8), pp.2167-2173. [44] Jowder, F.A., 2009. Wind power analysis and site matching of wind turbine generators in King- dom of Bahrain. Applied Energy, 86(4), pp.538-545. [45] Adaramola, M.S., Oyewola, O.M., Ohunakin, O.S. and Dinrifo, R.R., 2012. Techno-economic evaluation of wind energy in southwest Nigeria. Frontiers in Energy, 6(4), pp.366-378.McKenna, R., [46] Fyrippis, I., Axaopoulos, P.J. and Panayiotou, G., 2008. Analysis of wind potential and energy production in naxos island, Greece. WSEAS Transactions on Power Systems, 3(8), pp.567-576. [47] Bakos, G.C., 2011, November. Feasibility study of 6.6 MW wind farm in Greek mainland. In World Renewable Energy Congress-Sweden; 8-13 May; 2011; Linköping; Sweden (No. 57, pp. 4128-4135). Linköping University Electronic Press. [48] Krewitt, W. and Nitsch, J., 2003. The potential for electricity generation from on-shore wind en- ergy under the constraints of nature conservation: a case study for two regions in Germany. Re- newable energy, 28(10), pp.1645-1655. [49] Migoya, E., Crespo, A., Jiménez, Á., García, J. and Manuel, F., 2007. Wind energy resource as- sessment in Madrid region. Renewable Energy, 32(9), pp.1467-1483.

-75- [50] Raichle, B.W. and Carson, W.R., 2009. Wind resource assessment of the southern appalachian ridges in the southeastern united states. Renewable and Sustainable Energy Reviews, 13(5), pp.1104-1110. [51] Ali, S., Lee, S.M. and Jang, C.M., 2017. Techno-economic assessment of wind energy potential at three locations in South Korea using long-term measured wind data. Energies, 10(9), p.1442. [52] Barber, S. and Abhari, R. (2009). Development of wind turbines for safe operation in alpine envi- ronments. Bern: Swiss Office for Energy. [53] Dierer, S., Oechslin, R. and Cattin, R., 2011. Wind turbines in icing conditions: performance and prediction. Advances in Science and Research, 6(1), pp.245-250. [54] Chokani, N., Abhari, R. (2014). Siting of Wind Turbines in Complex Terrain. Effects of Inclined Freestream Flow and Elevated Freestream Turbulence. [ONLINE] Bern: Swiss Office For Energy, Available at: http://www.bfe.admin.ch/dokumentation/energieforschung/in- dex.html?lang=en#suchergebnisse .[Accessed 9 August 2018]. [55] Subramanian, B., Chokani, N. and Abhari, R.S., 2016. Aerodynamics of wind turbine wakes in flat and complex terrains. Renewable Energy, 85, pp.454-463. [56] Porte-Agel, F., Lungo, V. (2015). Field measurements of wind turbine wake flows. [ONLINE] Bern: Swiss Office for Energy, Available at: http://www.bfe.admin.ch/dokumentation/ener- gieforschung/index.html?lang=en#suchergebnisse .[Accessed 9 August 2018]. [57] The Swiss Wind Power Data Website. (2018). Measurement Data. [ONLINE] Available at: https://wind-data.ch/messdaten/index.php . [Accessed 30 September 2018]. [58] Natural Resources Canada. 2018. RETScreen. [ONLINE] Available at: http://www.nrcan.gc.ca/energy/software-tools/7465 . [Accessed 2 August 2018]. [59] Rienecker, M. M., Suarez, M. J., Gelaro, R., Todling, R., Bacmeister, J., Liu, E., ... & Bloom, S. (2011). MERRA: NASA’s modern-era retrospective analysis for research and applications. Jour- nal of climate, 24(14), 3624-3648. [60] Touma, J.S., 1977, Dependence of the wind profile power law on stability for various locations, J. Air Pollution Control Association, Vol. 27, pp. 863-866 [61] Müller, R., Pfeifroth, U., Träger-Chatterjee, C., Trentmann, J., & Cremer, R. (2015). Digging the Meteosat treasure-3 decades of solar surface radiation, Remote Sens., 7, 8067–8101. [62] Müller, R., Pfeifroth, U., Träger-Chatterjee, C., Cremer, R., Trentmann, J., & Hollmann, R. (2015). Surface Solar Radiation Data Set-Heliosat (SARAH)-Edition 1. Satellite Application Fa- cility on Climate Monitoring. [63] Staffell, I., Pfenninger, S. (2016). Using bias-corrected reanalysis to simulate current and future wind power output. Energy, 114, 1224-1239. [64] Staffell, I., Pfenninger S. (2018). Renewables.ninja. [ONLINE] Available at: https://www.renew- ables.ninja/ . [Accessed 25 October 2018]. [65] The Swiss Wind Power Data Website. (2018). Wind Map. [ONLINE] Available at: https://wind- data.ch/windkarte . [Accessed 30 September 2018]. [66] The Swiss Wind Power Data Website. (2018). Tools. [ONLINE] Available at: https://wind- data.ch/tools/ . [Accessed 30 September 2018].

-76- [67] The Swiss Wind Power Data Website. (2018). Wind Turbines. [ONLINE] Available at: https://wind-data.ch/wka/ . [Accessed 30 September 2018]. [68] The Swiss Wind Power Data Website. (2018). Firm Directory. [ONLINE] Available at: https://wind-data.ch/branche/ . [Accessed 30 September 2018]. [69] Swiss Federal Office of Energy. (2018). SFOE. [ONLINE] Available at: http://www.bfe.ad- min.ch/index.html?lang=en. [Accessed 8 August 2018]. [70] Meteotest. (2018). Home. [ONLINE] Available at: https://meteotest.ch/en/ . [Accessed 8 August 2018]. [71] SFOE, F., ARE (2004): “Konzept Windenergie Schweiz. Basis to take account of federal interests in the design of wind turbines,” Bern. [72] The Swiss Wind Power Data Website. (2018). Icing Map. [ONLINE] Available at: https://wind- data.ch/windkarte/vereisung.php?lng=en . [Accessed 30 September 2018]. [73] Cattin, R., Koller, S., Heikkilä, U. (2016). Icing at St. Brais and Mont Crosin. Consequences of icing for the operation and power production of wind turbines in the Jura Mountains. [ONLINE] Bern: Swiss Office For Energy, Available at: http://www.bfe.admin.ch/dokumentation/ener- gieforschung/index.html?lang=en&publication=11339 .[Accessed 9 August 2018]. [74] Bechrakis, D.A. and Sparis, P.D., 2000. Simulation of the wind speed at different heights using artificial neural networks. Wind Engineering, 24(2), pp.127-136. [75] Meteoblue. 2018. Climate. [ONLINE] Available at: https://www.meteoblue.com. [Accessed 3 Oc- tober 2018]. [76] Enercon, 2015. ENERCON Product Overview. Available at: https://www.enercon.de/filead- min/Redakteur/Medien-Portal/broschueren/pdf/en/ENERCON_Produkt_en_06_2015.pdf .[Ac- cessed August 2, 2018]. [77] Enercon-WEC Features. 2018. De-Icing. [ONLINE] Available at: https://www.ener- con.de/en/technology/wec-features/ . [Accessed 1 October 2018]. [78] Enercon, 2016. ENERCON’s Technologies to tackle Icing Conditions. [ONLINE] Available at: http://response.enercon.de/files/20161117_K%20Roloff_Cold%20Climate%20Solution.pdf .[Accessed September 29, 2018]. [79] The Windpower-Wind Energy Market Intelligence. 2018. Vestas V112-3000. [ONLINE] Availa- ble at: https://www.thewindpower.net/turbine_en_413_vestas_v112-3000.php. [Accessed 21 Au- gust 2018]. [80] Swiss Federal Office of Energy. 2018. Wind turbines-Haldenstein. [ONLINE] Available at: https://api3.geo.admin.ch/rest/services/ech/MapServer/ch.bfe.windenergieanlagen/facil- ity_HAL/extendedHtmlPopup?lang=de. [Accessed 21 August 2018]. [81] Vattenfall. 2014. Operational wind farms-Edinbane. [ONLINE] Available at: https://corpo- rate.vattenfall.co.uk/projects/operational-wind-farms/edinbane-isle-of-skye/. [Accessed 23 Au- gust 2018]. [82] Vattenfall. 2010. Power Plants-Horns Rev. [ONLINE] Available at: https://web.ar- chive.org/web/20110113032120/http://powerplants.vattenfall.com/powerplant/horns-rev. [Ac- cessed 23 August 2018].

-77- [83] EnBW. 2016. Wind farm in the Baltic Sea: EnBW Baltic 2. [ONLINE] Available at: https://www.enbw.com/renewable-energy/wind-energy/our-offshore-wind-farms/baltic-2/. [Ac- cessed 23 August 2018]. [84] Harman K, Walker R and Wilkinson M., 2008. Availability trends observed at operational wind farms. Proc. European Wind Energy Conference, Brussels Expo Belgium. [85] Swiss Federal Office of Energy, SFOE. 2018. Energy Strategy 2050. [ONLINE] Available at: http://www.bfe.admin.ch/energiestrategie2050/index.html?lang=en. [Accessed 20 November

2018].

-78- Appendix

List of Tables

Table 1: Operating wind turbines in Switzerland. Source: https://wind-data.ch/wka/list.php ______2 Table 2: Selected sites and their characteristics.______27 Table 3:Basic technical specifications of the selected turbines. ______32 Table 4: Model validation results. ______36 Table 5: Additional validation of VFM in 3 European sites. ______38 Table 6: RETScreen estimations of wind speed at hub height of the two wind turbines in the selected sites, with data taken from RETScreen’s database. ______40 Table 7: RETScreen estimations of annual energy productions and capacity factors in selected sites, with data taken from RETScreen’s database. ______41 Table 8: RETScreen estimations of wind speed at hub height of the two wind turbines in the selected sites, with data taken from the Swiss Wind Power Data website. ______43 Table 9: RETScreen estimations of annual energy productions and capacity factors in selected sites, with data taken from the Swiss Wind Power Data website. ______46 Table 10: VFM estimations of wind speed at hub height of the two wind turbines in the selected sites. _ 51 Table 11: VFM estimations of annual energy productions and capacity factors in the selected sites. __ 52 Table 12: Deviations in estimations of wind speed at hub height of the two RETScreen cases in selected sites. ______56 Table 13: Deviations in estimations of annual energy productions and capacity factors of the two RETScreen cases in selected sites. ______58 Table 14: Deviations of VFM estimations compared to RETScreen estimations of wind speed at hub height in selected sites. ______62 Table 15: Deviations of VFM estimations compared to RETScreen estimations of annual energy productions and capacity factors in selected sites. ______64

List of figures

Figure 1: Trend of installed wind capacity corresponding and electricity production. ______3 Figure 2: Facility location and climate data location selection. ______12 Figure 3: Input of climate data such as air temperature, relative humidity, precipitation, atmospheric pressure, wind speed etc. ______13 Figure 4: An example of climate data graph. Monthly average values of wind speed are plotted either as bar graph or a line. ______13

-79- Figure 5: Facility type selection. ______14 Figure 6: Energy model and subcategories. ______14 Figure 7: Resource assessment and Wind turbine subsections and their parameters ______15 Figure 8: Power and energy curves section. ______16 Figure 9: Losses, Summary and Other information sections. ______17 Figure 10: Virtual Wind Farm model methodology steps. ______18 Figure 11: Location selection for the VFM model. ______19 Figure 12: Required parameters for the VFM model. ______20 Figure 13: Daily mean power output graph given by the VFM model.______20 Figure 14: Monthly capacity factor and total mean capacity factor given by the VFM model. ______20 Figure 15: Wind atlas of Switzerland depicting annual average wind speeds at 125 m AGL. ______21 Figure 16: Areas with wind potential (in blue) in Switzerland. ______22 Figure 17: Areas where installation of wind turbines is prohibited. ______23 Figure 18: Map of icing frequency, in days per year, across Switzerland. ______24 Figure 19: Meteorological stations that provide wind data across Switzerland. ______25 Figure 20:Operating wind turbines and wind farms in Switzerland. ______25 Figure 21: The turbines’ locations across Switzerland. ______28 Figure 22: Windrose at 100 m AGL at the site of Schützenhof, Russikon. ______28 Figure 23: Windrose at 100 m AGL at the site of Käsern, Ebnat-Kappel. ______29 Figure 24: Windrose at 100 m AGL at the site of Bad Ragaz, St. Gallen. ______29 Figure 25: Windrose at 100 m AGL at the site of Ovronnaz, Valais. ______30 Figure 26: Windrose at 100 m AGL at the site of Le Moléson, Gruyères. ______30 Figure 27: Windrose at 100 m AGL at the site of Renan, Bern. ______31 Figure 28: Power curve of Enercon E-101/3050. Cut-in, rated and cut-off speeds are shown. ______32 Figure 29: Power curve of Enercon E-82/2000. Cut-in, rated and cut-off speeds are shown. ______33 Figure 30: Main parts and principle of operation of the Rotor Blade Heating System (RBHS). ______34 Figure 31: Annual energy production of electricity in Haldenstein. Actual production is compared with estimations from renewables.ninja and RETScreen. ______36 Figure 32: Hourly wind speed for 2016 and annual mean wind speed at Haldenstein. ______37 Figure 33: Estimated hourly power output for 2016 of 3 MW wind turbine at Haldenstein. ______37 Figure 34: Deviations in estimations of annual energy production and capacity factors in Haldenstein. 37 Figure 35: RETScreen estimations of wind speed at hub height for different values of wind shear exponent, compared between locations, with data taken from RETScreen’s database. ______41 Figure 36: RETScreen estimations of annual energy production for different values of wind shear exponent, compared between locations, with data taken from RETScreen’s database. ______42 Figure 37: RETScreen estimations of capacity factors for different values of wind shear exponent, compared between locations, with data taken from RETScreen’s database. ______42 Figure 38: RETScreen estimations of wind speed at hub height for different values of wind shear exponent, compared between locations, with data taken from the Swiss Wind Power Data website ____ 44

-80- Figure 39: RETScreen estimations of wind speed at hub height for different values of wind shear exponent, at each location, with data taken from the Swiss Wind Power Data website. ______45 Figure 40: RETScreen estimations of annual energy production, for different values of wind shear exponent, at each location, with data taken from the Swiss Wind Power Data website. ______47 Figure 41: RETScreen estimations of annual energy production for different values of wind shear exponent, compared between locations, with data taken from the Swiss Wind Power Data website. ___ 48 Figure 42: RETScreen estimations of capacity factors for different values of wind shear exponent, compared between locations, with data taken from the Swiss Wind Power Data website. ______49 Figure 43: RETScreen estimations of capacity factors for different values of wind shear exponent, compared between locations, with data taken from the Swiss Wind Power Data website. ______50 Figure 44: VFM estimations of wind speed at hub height, compared between locations. ______52 Figure 45: VFM estimations of annual energy production, compared between locations. ______53 Figure 46: VFM estimations of capacity factors, compared between locations. ______53 Figure 47: Comparison of wind speed at hub height estimations of the two RETScreen cases at each location ______55 Figure 48: Deviations in estimations of wind speed at hub height, of the two RETScreen cases compared between sites. ______57 Figure 49: Comparison of annual energy production estimations of the two RETScreen cases at each location. ______57 Figure 50: Deviations in estimations of annual energy production, of the two RETScreen cases compared between sites. ______58 Figure 51: Comparison of capacity factor estimations of the two RETScreen cases at each location. __ 59 Figure 52: Deviations in estimations of capacity factors, of the two RETScreen cases compared between sites. ______59 Figure 53: Comparison of wind speed at hub height estimations of the two models at each location. __ 60 Figure 54: Deviations of VFM estimations compared with RETScreen estimations for wind speed at hub height, compared between sites. ______63 Figure 55: Comparison of annual energy production estimations of the two models at each location. _ 65 Figure 56: Deviations of VFM estimations compared with RETScreen estimations for annual energy production, compared between sites. ______66 Figure 57: Comparison of capacity factor estimations of the two models at each location. ______67 Figure 58: Deviations of VFM estimations compared with RETScreen estimations for capacity factors, compared between sites. ______68

-81- Nomenclature VFM Virtual Farm Model

AEP Annual Energy Production CF Capacity factor

ASL Above Sea Level

AGL Above Ground Level WEC Wind Energy Converter

RBHS Rotor Blade Heating System

-82-