DDHC Paper No. 15/2016 (for discussion on 25.7.2016) District Development and Housing Committee, Southern District Council Progress Report on Planning Works in Southern District

Annex 1 Matters discussed at previous meetings that required follow-up actions (Progress as at 11.7.2016)

Annex 2 Planning Department-Progress Report on Planning Works in Southern District (Progress as at 30.6.2016)

Annex 3 Highways Department-Progress Report on Road Works in Southern District (Progress as at 30.6.2016)

Annex 4 Civil Engineering and Development Department-Progress Report on Other Works in Southern District (Progress as at 30.6.2016)

Annex 5 Housing Department-Progress Report on Public Housing Works in Southern District (Progress as at 30.6.2016)

Annex 6 Food and Environmental Hygiene Department-Progress Report on FEHD District Minor Works in Southern District (Progress as at 30.6.2016)

Annex 7 Lands Department-Progress Report on Lands Department Temporary Government Lands Allocation in Southern District (Progress as at 30.6.2016)

Annex 8 Follow-up on the Land Use upon MTRC Handing Back the Lands Currently Used as Work Sites (Progress as at 30.6.2016)

Abbreviations for government departments in this report: (in alphabetical order) ArchSD Architectural Services Department CEDD Civil Engineering and Development Department DSD Drainage Services Department EPD Environmental Protection Department FEHD Food and Environmental Hygiene Department HD Housing Department HyD Highways Department LandsD Lands Department LCSD Leisure and Cultural Services Department MTR Corporation Mass Transit Railway Corporation Limited PlanD Planning Department WSD Water Supplies Department

1

Annex 1

Matters discussed at previous meetings that required follow-up actions (Progress as at 11.7.2016)

Latest Progress on Matters Date of First Discussion (Date of updates) 1. Ex- Quarry 30.11.2009 PlanD/HyD/MTR Corporation The ex-Shek O Quarry site falls within an area zoned “Undetermined” on the and Shek O Outline Zoning Plan. (19.5.2016) The then Civil Engineering Department in 1994 undertook rehabilitation works with the concept of developing the rehabilitated quarry site for recreation-related uses, such as water sports centre. The site is temporarily used as a casting basin for Shatin to Central Link by MTR Corporation and will be handed-over to LandsD in 2019. PlanD will review the zoning of the subject site and consult the District Council when appropriate or before 2019.

2

2. Request to Improve the Drainage System of the Villages in Southern District 16.5.2011

(I) On Pokfulam Village

DSD arranged a joint site visit with District Lands Office, West and South in May 2016 to ascertain the (14.7.2016) works boundaries within Pokfulam Village. DSD is now refining the project design.

(II) On Shek O Village, San Wai Village, Kau Wai Village and Tai Hau Wan Village

FEHD advised that Railway Development Section of LandsD had requested MTRCL to replant trees at the proposed (11.7.2016) location of Wong Chuk Hang San Wai Village Public Toilet according to the approved Tree Removal Application in 2011. FEHD has accordingly requested LandsD to waive to replant trees at the subject location so as to prevent affecting the construction works of the public toilet. Railway Development Section of LandsD is handling the application of waiver of trees compensation at the location and the tree expert of LandsD is now studying the proposal. FEHD is still pending the reply from LandsD regarding application of land allocation.

Also, FEHD is still pending Minor Building Works Committee of ArchSD to approve the funding application for construction of the Wong Chuk Hang San Wai Village Public Toilet.

3

3. Short-term and Long-term Uses of the Site of Former Aberdeen Fire Station (AFS) 26.3.2012

PlanD advised that the site is zoned “Other Specified Uses” annotated “Business(2)” (“OU(B)2”) on the Aberdeen & Ap (12.7.2016) Lei Chau Outline Zoning Plan No. S/H15/30. According to the Notes of the “OU(B)2” zone, ‘Office’ and ‘Place of Recreation, Sports or Culture’ use, including arts centre, arts gallery, artist studio and rehearsal room for arts performances, are always permitted within the site.

On 13 November 2015, the Legislative Council Panel on Home Affairs supported the proposed project to provide arts space and arts facilities for use by local artists and art groups, as well as a permanent office for the Hong Kong Arts Development Council in the future development at the subject site. The proposed project was endorsed by the Public Works Subcommittee of Finance Committee and the Finance Committee on 24 February and 22 April 2016 respectively.

LandsD advised that the site has been included in the 2016-17 land sale programme (i.e. Aberdeen Inland Lot No. 462). The Government announced on 29 June 2016 about the details of the land sale programme for the second quarter of 2016-17 (i.e. July to September 2016), including that the site will be sold by tender in the second quarter. LandsD will issue a press release later before putting up the site for tender, to announce the Tender Invitation Date, Tender Closing Date, and the major information of the site, including its size, user, minimum and maximum gross floor area etc.

4. Planning Application for the “Comprehensive Development Area” Site in Wong Chuk Hang 26.11.2012

Updates on the item will be reported when there is further progress.

5. Provision of Facilities in the Convenience of Residents at the Government Land Adjacent to Jumbo Pier 4.2.2013

Proposal 2: Construction of public lavatory

FEHD advised that there is no updating for the suggested construction of a public toilet near Jumbo Pier. (11.7.2016)

4

Annex 2

District Development and Housing Committee, Southern District Council Progress Report on Planning Works in Southern District (As at 30.6.2016) I. Outline Zoning Plan

District Plan No. Project Description Remarks

Aberdeen & S/H15/30 The Town Planning Board (TPB) on 24.12.2015 gazetted the draft Aberdeen & Ap Details of the amendments Lei Chau Outline Zoning Plan (OZP) No. S/H15/30 under section 5 of the Town please refer to DDEC Paper Planning Ordinance for public inspection for two months. The OZP amendments No. 2/2016. mainly involve the rezoning of a site at Lee Nam Road, Ap Lei Chau, from “Other Specified Uses” annotated “Cargo Handling Area” (“OU(Cargo Handling Area)”), “Government, Institution or Community” and “Industrial” (“I”) to “Residential (Group A)4” for residential development; rezoning of a strip of land fronting Ap Lei Chau West Industrial Area from “OU(Cargo Handling Area)” to “Open Space”; and rezoning the Ap Lei Chau West Industrial Area from “I” to “OU” annotated “Business(3)” and “Business(4)” to enhance the transformation of the area to business uses.

During the two-month exhibition period which ended on 24.2.2016, a total of 607 representations were received. On 15 April, the TPB published the representations for public comments. During the publication period which ended on 6 May, 16 comments related to the representations were received. The TPB will then hold a “hearing meeting” to hear and consider the representations and comments received. The representers and commenters, including their authorized representatives, will be invited to attend the hearing meeting. The date of hearing meeting and the related agenda are to be arranged by the TPB Secretariat.

5

II. Planning Application Application submitted for Town Planning Board’s Consideration (1.5.2016 to 30.6.2016)

District Application No. Applied Use Location Consideration / Result Remarks

Aberdeen Y/H15/11 To rezone the Junction of Shek On 24.6.2016, the Metro Planning Committee of the (Note : The proposed application site Pai Wan Road and Town Planning Board agreed to defer a decision on the development at Shek from Tin Wan Hill application as requested by the applicant. Pai Wan Road submitted “Government, Road, Tin Wan, by Hong Kong Housing Institution or Aberdeen Society to facilitate Community” redeveloping of Yue and an area Kwong Chuen) shown as ‘Road’ to “Residential (Group A)”

6

III. Hotel Developments in Wong Chuk Hang Business Area Approved by Town Planning Board with Planning Permission Still Valid

Location Remarks

Planning permission valid until Sep 2017. [The previous lease modification application for non-industrial use (including hotel) was 1. 39 Wong Chuk Hang Road withdrawn by the applicant in 11/2012. The existing lease is for industrial use and hotel is not permitted.] The lot owner is currently applying lease modification for proposed covered footbridge link.

Planning permission valid until Nov 2019. [The previous lease modification application for non-industrial use (including hotel) was 2. 41-43 Wong Chuk Hang Road withdrawn by the applicant in 11/2012. The existing lease is for industrial use and hotel is not permitted.]

7

Annex 3

District Development and Housing Committee, Southern District Council Progress Report on Road Works in Southern District (As at 30.6.2016)

I. Preliminary Project Plan of Construction Works

Project Est. (Actual) Start Est. (Actual) PWP No. / Cat. Type Agency Progress / Remarks Description Date Completion Date

N.A. – Junction Transport Chung Hom Kok Road and Stanley Gap – – Improvement at Department Road junction is confined by the adjacent Chung Hom Kok slopes, with limited road space. Junction Road / Stanley improvement works will require substantial Gap Road slope works, transplanting a large number of trees, and temporary closure of traffic lanes. Transport Department advised that they have recently carried out traffic survey in the area and the traffic condition is considered acceptable. If other works are to be carried out at the above area in future, such as slope upgrading works, or new private development, Transport Department will request the project proponent to carry out the junction improvement works.

8

Annex 4

District Development and Housing Committee, Southern District Council Progress Report on Other Works in Southern District (As at 30.6.2016)

I. Works Commenced

Est. (Actual) Est. (Actual) PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)] Start Date Completion Date 186WC/A Replacement and WSD Water mains replacement and rehabilitation works in (3.2009) 8.2016 Rehabilitation of Water Southern District under Contract No. 18/WSD/08 Mains Stage 3 commenced on 18 March 2009. Works currently being carried out in Southern District include:

(a) Road Footpath and Carriageway [96%]; (8.2010) 8.2016 (b) Road Footpath and Carriageway (Water (7.2011) 10.2016 mains replacement works completed, remaining abandonment of the existing covers of valve chambers to be completed after swimming season (Jul to Sep)) [99%]; (c) Red Hill Service Reservoir [100%]; (10.2010) (3.2016) (d) Stanley Gap Road Carriageway [100%]; ( 3 .2010) (4.2016) (e) Stanley Village Road Footpath and Carriageway (9.2010) 10.2016 (Water mains replacement works completed, remaining abandonment of the existing covers of valve chambers to be completed after swimming season (Jul to Sep)) [99%]; (f) Area in the vicinity of Pok Fu Lam Service (11.2011) (4.2016) Reservoir [100%]; and (g) Pok Fu Lam Village [100%]. (11.2011) (3.2016)

9

Est. (Actual) Est. (Actual) PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Start Date Completion Date 191WC/A Replacement and WSD Contract No.12/WSD/10, which consists of construction (7.2011) 7.2017 Rehabilitation of Water works in Southern District, commenced on 18 July 2011. Mains Stage 4 Phase 1 Works are being carried out. Works in Southern District are as below:

(a) Consort Rise Footpath and Carriageway (in progress) (1.2012) 12.2016 [96%][Reason: Additional mainlaying works are required to facilitate the site condition.]; (b) Bisney Road Footpath and Carriageway (in progress) (1.2012) 12.2016 [94%][Reason: Additional mainlaying works are required to facilitate the site condition. ]; (c) Area in the vicinity of Aberdeen Water Treatment (4.2012) 11.2016 Works (in progress) [99%] [Reason: Water suspension required for water connection works involved a large affected area which included sensitive consumers (i.e. Hospitals). Therefore, extra coordination work is required with the affected premises. The pressure logging for connection had been completed. Additional time is required for discussion on the arrangement of water suspension with WSD/HK&I.]; (d) Deep Water Bay Road Footpath and Carriageway (in (11.2012) 11.2016 progress) [99%] [Reason: Water suspension required for water connection works involved a large affected area which included Fresh Water Service Reservoir. Therefore, extra coordination work is required with the affected premises. The excavation permit has been expired and the new excavation permit is targeted to be granted in August 2016]; (e) Wah King Street Footpath and Carriageway (in (1.2014) 9.2016 progress) [88%] (f) Victoria Road Footpath and Carriageway (in progress) (1.2014) 3.2017 [92%];

10

Est. (Actual) Est. (Actual) PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Start Date Completion Date (g) Repulse Bay Road Carriageway near Belleview Drive (1.2016) 12.2016 (in progress) [20%]; (h) Aberdeen Praya Road Carriageway (in progress) (10.2015) 3.2017 [46%]; (i) Wong Chuk Hang Road footpath (in progress) [96%]; (10.2015) 8.2016 and (j) Kai Lung Wan Fresh Water Service Reservoir [23%] (1.2014) 7.2017 (in progress)

11

Contract No.3/WSD/12, which consists of construction (3.2013) 4.2017 works in Southern District, commenced on 15 March 2013. Works are being carried out. Works in Southern District are as below:

(a) Pok Fu Lam Road near Pok Fu Lam Garden Footpath (8.2013) 10.2016 and Carriageway (in progress) [91%] [Reason: The mainlaying works are almost completed and the pressure testing for connection works is in progress.]; and (b) Aberdeen Praya Road near Fish Marketing (11.2015) 12.2016 Organization at Footpath and Carriageway (in progress) [92%] [Reason: Water suspension required for wter connection works involved a large affected area which included Aberdeen Fish Market. Therefore, extra coordination work is required with the affected premises. The pressure testing for connection works is in progress.]. (c) Tin Wan Street Footpath and Carriageway (in progress) (1.2016) 12.2016 [45%]; (d) Tin Wan Praya Road Footpath and Carriageway (in (1.2016) 8.2016 progress) [80%]; (e) Victoria Road/Sha Wan Drive Footpath and (5.2016) 12.2016 Carriageway (in progress) [35%]; and (f) Wong Chuk Hang Road Footpath and Carriageway (in (7.2016) 4.2017 progress) [10%].

12

341DS/A Harbour Area Drainage The item comprises upgrading of the Stonecutters Island (8.2011) 12.2016 Treatment Scheme, Services Sewage Treatment Works and eight numbers of stage 2A - Department preliminary treatment works at Hong Kong Island. The Upgrading of project has been fully commissioned in December 2015. Stonecutters Island sewage treatment Contract DC/2009/24 (Harbour Area Treatment Scheme works and Stage 2A Upgrading of Preliminary Treatment Works preliminary (PTWs) at Sandy Bay, , Wah Fu, Aberdeen and treatment works Ap Lei Chau), being part of the works of the above item, has commenced on 31/8/2011. Since the full commission of the project in December 2015, the treated effluent from Sandy Bay, Cyberport, Wah Fu, Aberdeen and Ap Lei Chau sewage treatment works has been intercepted and conveyed to the newly expanded Stonecutters Island Sewage Treatment Works for further treatment. The water quality of the nearby waters is improved, as there is no more direct discharge of treated effluent into the areas. The works of DC/2009/24 mainly include the upgrading of the sewage treatment and de-odourisation facilities in these PTWs. About 85% of works under the contract has been completed.

13

Progress Report on Landslip Prevention and Mitigation Works

PWP No. Project Description Agency Progress / Remarks [Completion rate (%)] Est. (Actual) Est. (Actual) / Cat. Start Date Completion Date Head 705 Landslip Prevention CEDD Landslip prevention and mitigation works for 111 man-made slopes and 5 Subhead and Mitigation natural hillside study areas in the Southern District are completed. The 5001BX/D Programme (LPMitP) natural hillside study areas are 11SW-C/SA3, 15NW-B/SA1, 11SW-C/SA4, 11SW-D/SA12 and 15NW-B/SA5. Landslip prevention and mitigation works for 6 man-made slopes and 7 natural hillside study areas are currently in progress.

1. Slope No. 15NE-A/C96 at South Bay Road [90%] (3.2014) 7.2016* 2. Slope No. 15NE-A/C115 at Repulse Bay Road (3.2014) (5.2016) [100%] (Works Completed) 3. Slope No. 15NE-A/F68 at Repulse Bay Road [70%] (3.2014) 7.2016 4. Slope No. 15NE-B/C145 at Big Wave Bay Picnic Area (10.2015) (5.2016) [100%] (Works Completed) 5. Slope No. 15NW-B/C136 at Main Street, Ap Lei Chau [70%] (11.2015) 7.2016 6. Slope No. 11SW-D/C2259 at Deep Water Bay Drive [20%] (4.2016) 12.2016 7. Slope No. 15NE-C/FR154 at Behind Correctional Services Department (4.2016) 4.2017 Staff Quarters (Front Block), Stanley [15%] 8. Slope No. 11SW-D/C1440 at Yue Kwong Road [5%] (6.2016) 12.2016

14

PWP No. Project Description Agency Progress / Remarks [Completion rate (%)] Est. (Actual) Est. (Actual) / Cat. Start Date Completion Date 9. 2 Natural hillside study areas behind Queen Mary Hospital (1.2012) 9.2016* (Study Area Numbers 11SW-C/SA1 and 11SW-C/SA2) [96%] 10. 1 Natural hillside study area above Ruby Court at South Bay Road (3.2014) 9.2016 (Study Area Number 15NE-A/SA3) [60%] 11. 1 Natural hillside study area at Shouson Hill (4.2014) (5.2016) (Study Area Number 11SW-D/SA12) [100%] (Works Completed) 12. 1 Natural hillside study area above Pok Fu Lam Road (11.2014) 3.2017 (Study Area Number 11SW-C/SA5) [35%] 13. 1 Natural hillside study area at Shek Pai Wan Road, Aberdeen (9.2015) 3.2017 (Study Area Number 11SW-C/SA5) [20%] 14. 1 Natural hillside study area above Ap Lei Chau fronting the Aberdeen (12.2015) 2.2017 Channel (Study Area Number 15NW-B/SA2) [20%] 15. 1 Natural hillside study area at Ap Lei Chau (4.2016) 10.2017* (Study Area Number 15NW-B/SA6) [10%]

* Anticipated completion date is revised as the works have been affected by inclement weather

15

PWP No. Project Description Agency Progress / Remarks [Completion rate (%)] Est. (Actual) Est. (Actual) / Cat. Start Date Completion Date Head 705 Landslip Prevention CEDD In the coming year, CEDD is planning to progressively commence the landslip Subhead and Mitigation prevention and mitigation works for other 9 man-made slopes and 1 natural 5001BX/D Programme (LPMitP) hillside study area. 1. Slope No. 11SW-D/C1058 at Hong Kong Police College Lower Range, @ @ Police School Road, Aberdeen 2. Slope No. 11SW-C/CR874 at Victoria Road 8.2016 10.2016 3. Slope No. 11SW-C/R407 at Aberdeen Praya Road 8.2016 12.2016 4. Slope No. 11SW-D/R1222 at Near Lamppost No. 35053, Aberdeen 8.2016 1.2017 Reservoir Road 5. Slope No. 11SW-D/R1223 at Near Lamppost No. 35053, Aberdeen 8.2016 1.2017 Reservoir Road 6. Slope No. 15NE-A/R244 at Repulse Bay Main Sewage Pumping Station 8.2016# 1.2017# 7. Slope No. 15NW-B/C385 at Island Road 10.2016 7.2017 8. Slope No. 15NE-C/C320 at Canteen Outside The Prison Compound, 3.2017 10.2017 9. Slope No. 15NE-A/C193 at Tai Tam Road 5.2017 4.2019 10. 1 Natural hillside study area Behind Police College at Wong Chuk Hang 10.2016 3.2018 (Study Area Number 15NW-B/SA3)

# # # Anticipated start date and completion date are revised due to reschedule of works programme @ @ Anticipated start date and completion date will be re-scheduled due to re-programming of works

16

PWP No. Project Description Agency Progress / Remarks / Cat. Head 705 Landslip Prevention CEDD CEDD is carrying out stability investigation for other 19 man-made slopes in the Southern District, Subhead and Mitigation which are in the early stage of the LPMit Programme. The stability investigations of these slopes are 5001BX/D Programme (LPMitP) not yet completed. Therefore, upgrading works to these slopes may not be required if it is later confirmed that the slopes meet the required safety standards.

1. Slope No. 15NE-A/C176 at Tai Tam Road 2. Slope No. 15NE-A/C608 at Tai Tam Road 3. Slope No. 11SE-C/C237 at Repulse Bay Road 4. Slope No. 15NE-A/C90 at South Bay Road 5. Slope No. 15NE-A/C195 at Tai Tam Road 6. Slope No. 15NE-A/C197 at Tai Tam Road 7. Slope No. 11SW-C/R342 at Pok Fu Lam Village 8. Slope No. 11SW-D/FR651 at Wong Chuk Hang San Wai 9. Slope No. 15NE-A/CR454 at Tai Tam Road Catchwater 10. Slope No. 15NE-A/F45 at Tai Tam Road 11. Slope No. 11SE-D/C406 near the junction between Shek O Road & Cape Collinson Road 12. Slope No. 15NE-A/C192 at Tai Tam Road 13. Slope No. 15NE-A/C70 at Repulse Bay Road 14. Slope No. 15NE-A/FR34 at Repulse Bay Road 15. Slope No. 15NE-A/C241 at West of Eden View, Stanley Gap Road 16. Slope No. 15NE-A/C118 at Northeast of the junction of Repulse Bay Road and Headland Road 17. Slope No. 15NE-A/C240 near the junction of Stanley Gap Road and Headland Road 18. Slope No. 15NE-D/R8 at Ngai Choi Hang Village, Cape D’aguilar Road 19. Slope No. 15NW-B/C97 at Island Road

17

Annex 5

District Development and Housing Committee, Southern District Council Progress Report on Public Housing Works in Southern District (As at 30.6.2016)

I. Works Commenced (up to the end of two financial years later)

Project Description Est. (Actual) PWP / Estate Responsible Team Est. (Actual) Start Date Remarks Completion Date Lift Modernisation BSE/ECM2 May 2014 (May 2014) November 2017 The lift modernisation project for Ap Lei for Ap Lei Chau Chau Estate involves four sections of works. Estate The works for the fifteen lifts in Section I and Section II were completed. The works for the ten lifts in Section III (Lei Yee House L1; Lei Ning House L6; Lei Chak House L9, L12 and L13; Lei Tim House L18; Lei Fook House L19 and L23; and Lei Moon House L25 and L29), commencing in late February 2016 in phases, will be completed in the first quarter of 2017. The works for the last section, following the completion of Section III, will commence in the same of quarter of the year. The whole project is scheduled for completion in the fourth quarter of 2017.

18

Annex 6

District Development and Housing Committee, Southern District Council Progress Report on FEHD District Minor Works in Southern District (As at 30.6.2016)

Estimated Estimated Completion Item Proposed Start Date Date FEHD Contact ASD Contact Location Remarks No. Minor Works [Actual [Actual Person Person Start Date] Completion Date]

------

19

Annex 7

District Development and Housing Committee, Southern District Council Progress Report on Lands Department Temporary Government Lands Allocation in Southern District (As at 30.6.2016) Type of TGLA Item TGLA No./ (New/ Proposed Proposed Proposed User Dept. Date of Date of Remarks No. File Ref. Renewal) Location Area (m2) User Term (Allocatee) Allocation Withdrawn (Current Situation)

1. GLA-THK 1753 Renewal Government land 126 Car Extend up to C of P Regarding the objection 504/SHGS/82 between No.24 parking 11.2.2020 from DDHC, C of P and 25 Shum Wan spaces responded that the Road, Wong proposed parking was Chuk Hang for its operational needs.TD had no comment and Security Bureau had given approval to the proposed extension. Case in progress.

20

2. GLA-THK1853 Renewal Northern Coastline 1,550 Works Area Extend up to DSD - - DSD submitted this 546/SHGS/82 of Ap Lei Chau 16.5.2016 proposal for DDEC’s (i.e. next to Ap Lei the present DDHC) Chau Park consideration during meeting on 20.7.2015 who supported the proposal. The allocation has been expired and LandsD is in the course of arranging site handover from DSD.

3. GLA-THK1892 Renewal Tin Wan Praya 820 Works Area Extend up to DSD - - Departmental circulation L/M Road, Aberdeen 31.12.2017 completed. Pending 988/SHMS/82 A Approval. DSD had been requested to provide supplementary information before processing the application for renewal.

4. GLA-THK1550 Renewal Hok Tsui Village 667 Sitting out area Extend up to HAD, - - Departmental circulation 413/SHGS/82 and meeting 30.6.2017 DO(S) completed. Pending venue approval.

21

5. GLA-THK950 Renewal At Stanley Gap 127 Manoeuvring Extend up to WSD - - Departmental circulation 177/HGS/82 Road and/or Parking of 31.5.2020 completed. Pending Waterworks approval. Vehicles to/from Stanley Mound Fresh Water Pumping Station & Extension

6. GLA-THK 2003 New Sandy Bay, 3,590 Works Area From the date CEDD - - Approved for 2 years. 3/SHGS/2015 Pok Fu Lam of possession for 4 years

7. GLA-THK 1875 Renewal Sandy Bay, 1,480 Works Area Extended up DSD - - Under departmental 988/SHMS/82B Pok Fu Lam to 31.12.2017 circulation. DSD applied for further extension upto 31.12.2017. .

8. GLA-THK 1538 Renewal Pak Sha Wan, Ap 799 Works Area for Extended up LCSD - - Under departmental L/M 7/SHGS/82 Lei Chau installation and to 30.6.2018 circulation. (68) maintenance of Shark Prevention Nets

22

9. GLA-THK 1922 Renewal Ap Lei Chau Praya 666 Works Area for Extended up HyD - - Under departmental 574/SHGS/82 Road, Ap Lei Chau management and to 30.6.2021 circulation. maintenance of Roads

23

Annex 8 District Development and Housing Committee, Southern District Council Follow-up on the Land Use upon MTRC Handing Back the Lands Currently Used as Work Sites (As at 30.6.2016)

Location Anticipated Approximate Managing Planned Use/Follow-up Actions Date of First Discussion Handover Area Size Agent (Provided by Managing Department/Agent) Date (m2) (Date of updates) Site next to Handed over 6,230 LandsD Long-term planned use of the land is to be advised by 26.1.2015 Ocean Park in the end of PlanD. LandsD would facilitate any application for June 2016 use of the land in accordance with applicable (15.7.2016) procedures.

(PlanD’s comments: The subject site falls within an area zoned “Government, Institution or Community” (“G/IC”) on the approved Aberdeen & Ap Lei Chau Outline Zoning Plan No. S/H15/29 and is reserved for provision of GIC facilities.)

24

Location Anticipated Approxim Managing Planned Use/Follow-up Actions Date of First Discussion Handover ate Area Agent (Provided by Managing Department/Agent) Date Size (Date of updates) (m2) Chung Hom Handed over 2,500 LandsD Long-term planned use of the land is to be advised by 26.1.2015 Shan Magazine PlanD. LandsD would facilitate any application for Site use of the land in accordance with applicable (26.1.2015) procedures.

(PlanD’s comments: The subject site falls within an area zoned “Other Specified Uses” annotated “Composite Signals Organization Station Complex” on the approved Stanley Outline Zoning Plan No. S/H19/10 intended primarily to provide land for composite signals organization station complex and its ancillary facilities.)

25

Chung Hom 2nd Half 2017 6,400 LandsD Long-term planned use of the land is to be advised by 26.1.2015 Shan Nursery (To tie in with the PlanD. LandsD would facilitate any application for Site next to latest progress of use of the land in accordance with applicable (10.9.2015) Magazine Site the reprovisioning procedures. works at Harcourt Garden, some of (PlanD’s comments: The subject site falls within an the trees area zoned “Other Specified Uses” annotated temporarily “Composite Signals Organization Station Complex” transplanted from on the approved Stanley Outline Zoning Plan No. Harcourt Garden S/H19/10 intended primarily to provide land for at the Chung Hom composite signals organization station complex and Shan Nursery Site its ancillary facilities.) need to be maintained for a longer period. The reprovisioning is expected to be substantially completed by the end of 2017.)

26