SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN

PROJECT MANAGEMENT (MGT60704)

DEFINING AND DOCUMENTING A PROJECT TABLE OF CONTENTS

1.0 INTRODUCTION 03 1.1 Project Information 04 1.2 Site Location 06

2.0 PROJECT TEAM 07 2.1 Project Manager 10 2.2 Architect 10 2.3 Civil & Structural Consultant 11 2.4 Mechanical & Electrical Consultant 13 2.5 Quantity Surveyor Consultant 14 2.6 Landscape Architect 16 2.7 Main Contractor 17

3.0 ORGANIZATION STRUCTURE 18

4.0 STAKEHOLDERS 20

5.0 PROJECT INFORMATION 22 5.1 Project Objectives & Goals 23 5.2 Implementation Phase 24 5.2.1 Schematic Design 5.2.2 Design Development 5.2.3 Contract Documentation 5.2.4 Contract Implementation 5.2.5 Final Completion 5.3 Implementation Tools 37 5.4 Monitoring Tools & Strategies 38 5.5 Risks & Mitigation 40 5.6 Procurement 42 5.7 Success Criteria 43

6.0 CONCLUSION 44

7.0 REFERENCES 46

8.0 APPENDIX 48

2 1.01.0

⬥ ⬦ ⬥ ⬦ ⬥ ⬦ INTRODUCTION

3 1.1 Project Information

Project : O’Hako Residence @ Jaya

Project Site : Jalan Pipit 1, Bukit Tandang, Pekan Puchong Jaya, Daerah Petaling, Darul Ehsan

Architect : Verge Architects

Client : Marimo Land SDN. BHD.

Final Completion Date : September 2019

Client

Marimo Land Sdn. Bhd. is the Malaysian subsidiary for Marimo Co., Ltd. from Hiroshima of Southern Japan. Marimo Co., Ltd. began as an architectural firm with expertise in providing affordable condominium designs to suit the burgeoning demand set by Japan’s rapid urbanisation. Building on the experience and techniques in residential planning and design, they transitioned into condominium development and set a goal to become leaders in the local market. Marimo Land Sdn. Bhd. made its debut in with the O’Hako Residence.

Project Scope

Renderings of O’Hako Residence

O’Hako Residences in Puchong Jaya the first service apartment project done by a Japanese company in suburb of Puchong. The project is situated near the River and surrounded near the existing residential area at site. Their concept, ‘O’Hako (十八番)’, which means a box is their drive in designing this prestigious apartment. The project has been designed to provide the most luxurious and attractive common areas in Puchong.

4 Specifications of the project includes:-

Total Land Area of O’Hako: 4.375 acres Total Land Area of Facilities: 1.5acres

2 blocks with 358 units each

Tower A - Residential units - 2 FLOORS of facilities provided - Kindergarten - Multipurpose Hall - Gymnasium - Swimming Pool - 4 units of retail outlets - Surau (LVL 1) - Management Offices - Basement Car Park - Guard House

Tower B - Housing Units - Basement Car Park

5 1.2 Site Location

The O’Hako Residence is located in Puchong Jaya, just at the side of the Klang River. The site is surrounded by existing residences which makes it a strategic location for people to dwell in. The site is located near places of leisure, malls, religious institutions and healthcare services.

O’Hako is built on 4.4 acres of commercial land, out of which approximately 1.5 acres or 99m X 66m or 63,000sq ft, is dedicated to the landscaped facilities podium in between the residential towers, a podium that showcases 53 exclusive facilities designed for the enjoyment of all ages within the family. This facilities zone is, by far and so far, the biggest among condominiums of its class in Malaysia.

6 2.02.0

⬥ ⬦ ⬥ ⬦ ⬥ ⬦ PROJECT TEAM

7 2.0 Project Team

PARTY PERSON IN CHARGE POINT OF CONTACT

Client Mr. John Taro (Japanese) Mr. Daniel Lim Marimo Land Sdn. Bhd. Mr. Frank Hiew (Malaysian representative of Mr. Masri Marimo Co., Ltd.) Marimo Land Sdn. Bhd.

C-G- 49 & 50, IOI Boulevard, Jalan Kenari 5, Bandar Puchong Jaya, 47100, Puchong, Selangor

Project Manager Mr.Teruo Funamoto Mr. Javier Llaneras

Puls PM Consultant S.B.

16-16, Level 16, Wisma UOA Ⅱ, Jalan Pinang, 50450 Kuala Lumpur

Project Architect Ar. CH Soo Ar. Jethro Koi Ar. KL Ewe

Verge Architects

11-1A, Jalan USJ 10/1C, 47630 UEP , Selangor Darul Ehsan

M & E Consultant Ir. Mervin Ung Ir. Lew LL

YG Ung Consultant

No.98B, Jalan SS 15/4, SS15, 47500 Subang Jaya, Selangor

C & S Consultant Mr. Cheah Kwee Sin

D&O Konsultant S.B

37b, Jalan Bukit Desa 5, Taman Bukit Desa, 58100 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur

8 PARTY PERSON IN CHARGE POINT OF CONTACT

C & S Consultant Mr. Samson Lee (Initial stage only - Terminated)

Perunding Reka Cekap S.B 9, Jalan Kenari 2, andar Puchong Jaya, 7100 Puchong, Selangor Darul Ehsan

Quantity Surveyor Consultant Sr. C.S. Chlu Ms. C.K Chla

DK-QS Sdn.Bhd 38-2, Jalan Sierra 10/2, Bandar 16 Sierra, 47110 Puchong, Selangor

Quantity Surveyor Consultant Mr. Mohd Razif (Initial stage only - Terminated) Ms. CL Wong

Perunding PQS 10-3, Jalan 13/48a, Sentul Raya Boulevard, 51000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur

Landscape Architect Mr. Khoo Eng Kee Ms. Helen Hui

Engky Design S.B No. 249, Jln BK 2/7, Bandar Kinrara,47180, Puchong, Selangor

Main Contractor Mr. Michael Ong Mr. Jason Pang Mr. Dennis Tan

PEMBINAAN INFRA E&J S.B No. 15, 1, Jalan Damai Raya 1, Alam Damai, 56000 Kuala Lumpur, Wilayah Persekutuan

9 CONSULTANT SCOPE OF WORK

This chapter covers the roles and responsibilities of the consultants involved in the project. The respective roles constantly work together in the project, which can be observed through an example of the project's site meeting minutes(in Appendix C) and client-consultant meeting minutes attached (in Appendix D).

2.1 PROJECT MANAGER

2.1.1 RESPONSIBILITIES

A professional in the field of project management. He/She is responsible to plan, procurement and execute a project, undertaking that has a defined scope, defied start and defined finish. Project manager is the first point person when there are discrepancies or issues. This individual aims to maintain the progress, mutual interaction and tasks in order to reduces the risk of overall failure, maximize benefits and minimise costs.

2.1.2 COMPANY BACKGROUND: Plus PM Consultant S.B.

Plus PM Consultant S.B. is a leading project and construction management company established by Japanese company to support investors that expand their business in ASEAN. "Our role is to bring the construction project built in line with your business strategy. Significantly different from Japan, overseas construction projects often encounter risks such as over construction budget, delay completion etc. Our mission is to ensure project completion on schedule, assurance of required quality and construction investment within budget in an environment away from Japan".

2.2 ARCHITECT

2.2.1 RESPONSIBILITIES

As lead consultant of the project, the architect carries one of the heaviest role in the team. The architect gets involved in every phase from the start of the project till the end. coordinating with other consultants and contractor along the way while constantly providing updates and progress to the project manager and client.

2.2.2 COMPANY BACKGROUND: Verge Architects

Verge Architects was established in Malaysia in 2009. In the ensuing 10 years, the firm has grown to serve an increasingly diverse and extensive clientele in both private and public sectors. "We believe that Architecture is one of the compelling forces that shape the lifestyles of society, behaviourial trends and the intrinsic emotions of each individuals in perpectual relation to the genus loci". (refer to Appendix H for letter of release by old architect)

10 2.2.3 TASK AT DIFFERENT STAGES

Before Construction

Architect and project manager are responsible to design the buildings according to the requirements of authority. Drawings submission to the authority and amend changes commented by authority. There are mainly three stages to coordinate all the drawings and documents; Schematic Design Phase, Design Development Phase and Contract Documentation Phase.

During Construction

Once the construction starts, they need to ensure efficient quality control on all projects. They need to ensure the resources availability and allocation. Having site inspection and site meetings to keep tracking the progress of the construction and having quick response to resolve any problem during construction.

After Construction

They will conduct a final site inspection. Ensure close-out documentation and project archives are completed.

2.3 CIVIL AND STRUCTURAL CONSULTANT

2.3.1 RESPONSIBILITIES

A Civil & Structural Consultant is a construction industry professional with expert knowledge on create, improve and protect the environment in which we live. They plan and design the construction and maintenance of building structures and infrastructure. They also design and build tall buildings and large structures that can withstand all weather conditions.

Civil engineers are divided into two types, which are consulting engineers and contracting engineers. Consultants are responsible for the design work of projects and work predominantly in an office. Contractors then take the designs and implement them during construction. Contractors work on site, managing the construction of the structure.

11 2.3.2 COMPANY BACKGROUND:

YG Ung Consultant

YG Ung Consultant majors in knowledge of construction methods and construction sequences in civil structural construction above or below the ground. Mr.James Ung has been praised by his high career growth thought a continuous process of a successful professional and leading to best opportunity.

Perunding Reka Cekap S.B ( Initial stage only - Terminated )

Perunding Reka Cekap S.B was incorporated in 1994 by Dato’ Ir. Tee Chai Seng to provide professional civil and structural engineering consultancy services in Malaysia and abroad. They are an established multi-disciplined engineering consulting firm with expertise in the design and supervision of mixed developments, corporate buildings, commercial complexes, infrastructural projects such as jetties, bridges and highways.

2.3.3 TASK AT DIFFERENT STAGES

Before Construction

Civil and Structural Engineer help with feasibility studies for a project. They are involved in the investigation and survey of build sites to determine the suitability of the earth for the requirements of the upcoming project.

They also need to assist the design team to design a safety building and according to the spaces that clients needs. They needed to consider about the strength of various of construction materials too.

During Construction

Once the construction starts, they need to ensure efficient quality control on all projects and provide support to engineering team at all times to maintain work schedule. Having inspection to keep tracking the quality of the construction.

After Construction

The Civil and Structural Consultant will conduct series of test to examine the structures quality and ensure it is structurally sound.

12 2.4 MECHANICAL AND ELECTRICAL CONSULTANT

2.4.1 RESPONSIBILITIES

Mechanical and Electrical Consultants are responsible for the mechanical or electrical components of different services in the building such as elevators, air-conditioning, gas and water supply. From installation to testing, operation, maintenance and repair, they help to ensure that buildings are equipped with the relevant services and are able to operate safely.

2.4.2 COMPANY BACKGROUND: D&O Konsultant S.B

D&O Konsultant was established in 1984, with more than 30 years of experience , they are leading the way in value driven, sustainable, energy efficient design solution. D&O Konsultant is positioned to efficiently respond to the rapid growth within the region and deliver solutions that meet the needs of their clients.

2.4.3 TASK AT DIFFERENT STAGES

Before Construction

Mechanical & Electrical Engineer discuss concept, requirements and thoughts with the other consultants regarding construction and implement the systems. Once mutual agreement have been achieve, M&E start to produce tender drawings and submit it to fire department to get the approval.

During Construction

After getting the green light from local authority, M&E will conduct site inspection to make sure the contractors do according to plan. During a period of time, meeting will held frequently to check the progress and coordinate with other building teams such as C&S engineer.

After Construction

Once the construction was completed, M&E will test the system and the installation every 2-3 days to ensure works are built according to requirements. Lift and other mechanisms usually will takes about one month due to its complexity.

13 2.5 QUANTITY SURVEYOR CONSULTANT

2.5.1 RESPONSIBILITIES

A Quantity Surveyor(QS) is a construction industry professional with expert knowledge on construction costs and contracts. They are responsible for managing all aspects of the contractual and financial side of construction projects. Quantity surveying about managing costs, ensuring that high-quality structures are built as economically as possible. A quantity surveyor could be involved in every stage of the project, depending on whether they work for a consultant or for a contractor.

A Quantity Surveyor manages all costs relating to building and civil engineering projects, from the initial calculations to the financial figures. They seek to minimise the costs of a project and enhance value for money, while still achieving the required standards and quality. This includes ensuring statutory building regulations are met. Quantity surveyor work for either the client or the contractor, in an office or on site. They will be involved in a project from the start, preparing estimates and cost of the work. When the project is in progress, they will keep track of any variations to the contract that may affect costs and create reports to show profitability. Their alternative job titles include construction cost consultant and commercial manager.

2.5.2 COMPANY BACKGROUND:

DK-QS Sdn.Bhd

DK-QS is a firm of Quantity Surveyors and Construction Economists with it's headquarters office at Puchong Jaya. They have established, implemented and maintained a documented Quality Management System(QMS), which meets the requirements of the Standard ISO9001 :2008 Quality Management System. "We act as cost advisor, technical accountant and specialist on contractual matters, providing the link between the designer and the producer, and is concerned with building projects from its inception to its ultimate financial completion".

Perunding PQS (Initial stage only - Terminated)

PERUNDING PQS was formed in 1989 as a wholly owned Malaysian firm registered with the Registar of Companies, Malaysia and the partners of the firm are: Lu Ping Liang and Low Kok Keong. both being profesional Chartered Surveyors and registered with the Lembaga Juruukur Bahan Malaysia (Board of Quantity Surveyors Malaysia) and The Royal Institution of Chartered Surveyors (RICS). (refer to Appendix E for old list of consultants)

14 2.5.3 TASK AT DIFFERENT STAGES

Before Construction

Quantity Surveyors help with feasibility studies for a project. They studies the architects' and engineers' plans, identifies the costs involved, and then sets an overall estimated budget for the project. The QS can then plan costs to help the design team stay within the project budget using practical solutions. This is called value engineering.

The final detailed estimate is prepared by the QS, together with a project architect. This is the basis for evaluating tenders.

During Construction

Once the construction starts, the QS keeps costs on track. They provide cash flow data so the client can arrange the finances needed for cash stage of the project. The QS also assess cost effects when changes to the project occur, such as delays, and agree on 'variation' with contractors.

They provide a bank with a project report and help a client by preparing to draw down certificates for money to be loaned by the bank. Resolving disputes between clients, designers and building contractors is another role in some projects.

After Construction

The QS can prepare a statement of final account, which records the actual costs for all sections of the job. The client shall pay the QS for the provision of the services required.

15 2.6 LANDSCAPE ARCHITECT

2.6.1 RESPONSIBILITIES

Landscape Architect is incharge in creating aesthetic layout of outdoor spaces that provide environmental benefits, focusing on master planning, site planning, landscape design to project management and implementation. The projects range that a landscape architect involve are vary, it can be minor projects like residential environment, parks, sport courses to regional recreation. In additional case, Landscape Architects will also be working with ecologist and geologist to investigate and reserve the environment follow by the requirement of clients and UBBL.

2.6.2 COMPANY BACKGROUND: Engky Design S.B

Engky Design is a professional landscape consulting firm who believes in balance of forms, function, architecture and the environment. It is the aspiration of two landscape designers with more than 10 years of design experience in the market. They express their work through art and blend their art with the environment. "We aims to create meaningful and unique landscape design to each site according to the essence of their context and brief history".

2.6.3 TASK AT DIFFERENT STAGES

Before Construction

Before construction, landscape architects will provide preliminary services which are inception and feasibility. During this period, the landscape architects with start analysing site and prepare site plans, specifications, materials, vegetations and cost estimates. They will propose the land features and structure and as well coordinate the arrangement of existing structure and vegetations. There will be meetings with consultants until everyone agreed with the final design and call tender.

During Construction

Once the construction starts, the landscape architect will attend site meeting along with engineers, architects and other consultants. During the period, the landscape architects will also monitor and understand the outdoor spaces and help to give advice on solving on site issues.

After Construction

After the project is completed, the landscape architects will pay a visit to the site and inspect the quality of work with the team, then prepare the schedule of defects and cerity completion.

16 2.7 MAIN CONTRACTOR

2.7.1 RESPONSIBILITIES

A main contractor is responsible for providing all of the material, labor, equipment (such as engineering vehicles and tools) and services necessary for the construction of the project. A general contractor often hires specialized subcontractors to perform all or portions of the construction work. When using subcontractors, the general contractor is responsible for the quality of all work performed by any and all of the hires. The contractor's number one priority is safety on the job site. A main contractor's responsibilities may include applying for building permits, advising the person they are hired by, securing the property, providing temporary utilities on site, managing personnel on site, providing site surveying and engineering, disposing or recycling of construction waste, monitoring schedules and cash flows, and maintaining accurate records.

2.7.2 COMPANY BACKGROUND: PEMBINAAN INFRA E&J SDN BHD

E&J established in year 1998, where the E&J group is an established company with a main focus in building and infrastructure. It has come a long way from a humble sewerage treatment plant sub contractor to being a sizeable contractor and developer companies. The group has grown from strength-to-strength, expanding its scope and expertise that today cuts across the whole spectrum of the construction industry. It moved away from doing just sewerage treatment plant to infrastructure and building construction, and in year 2010, property development.

Currently, E&J group has a total contract value of RM150 million on both building, sewerage and infrastructure projects. In its pipeline development, the group will be launching its warehouse and residential work in the in year 2012.

17 3.03.0

⬥ ⬦ ⬥ ⬦ ⬥ ⬦ ORGANIZATION STRUCTURE

18 3.1 ORGANIZATION CHART

Project Delivery : Since the client is a Japanese developer, they hired a "client side" project management consultant which is established in Japan. The consultant keeps in check the architect and other consultants then represents to the client. The second project manager,Verge Architect, is a local architectural firm. Basically all the on-site process were managed by the architect. They leads other local consultants then arrange several meetings with other stakeholders. This linear process is well understood and is suitable for international projects. Moreover, the project delivery method could provide the client with an unbiased third party ensuring successful completion of the project.

CLIENT

Marimo Land S.B

PROJECT MANAGER PROJECT MANAGER / ARCHITECT

Plus PM Consultant Verge Architect

CONSULTANTS

MECHANICAL & LANDSCAPE CIVIL & STRUCTURAL ELECTRICAL QUANTITY SURVEYOR ARCHITECT YG Ung Consultant D&O Konsultant DK-QS Engky Design

Figure 3.1 Organization Structure

19 4.04.0

⬥ ⬦ ⬥ ⬦ ⬥ ⬦ STAKEHOLDERS

20 4.0 Stakeholders

STAKEHOLDERS

PROJECT TEAM REGULATORY BODIES END USER

Unit owners Concept Architect MPSJ Verge Architect Jabatan Kejuruteraan Jabatan Bangunan Jabatan Kesihatan Jabatan Perancangan Shop owners OSC Contractor Pembinaan Infra E & J Sdn. Bhd. POS Malaysia

Quantity Surveyor DK-QS Sdn. Bhd. Jabatan Kerja Raya

Indah Water Konsortium M&E Engineer D&O Konsultant Syarikat Bekalan Air Selangor

C&S Engineer Tenaga Nasional Berhad YG Ung Consultant

Telekom Malaysia Landscape Architect Engky Design Lembaga Arkitek Malaysia

Project Manager Plus PM Consultant BOMBA

External Shareholders

Internal Shareholders

21 5.05.0

⬥ ⬦ ⬥ ⬦ ⬥ ⬦ PROJECT INFORMATION

22 5.1 Project Objectives & Goals

5.1.1 Project Objectives

● Create a special residency with a unique concept and identity known as O’Hako (十八番), to provide the luxurious and attractive place for the users ● Improve the quality of life for the residences in the area ● To be the leading market in providing affordable and quality residential developments ● Create a good asset that will be attractive to current and potential residents.

5.1.2 Project Goals

● Mark the first successful condominium development for the parent company in Malaysia ● Set a path for more future condominium or residential developments ● Create its own identity with unique concept to build an image in the public ● Find a proper land that has great value for the development ● Budget and completion time is met, and all other requirements to be approved on time

23 5.2 Implementation Phase

The 5 phases of a project cycle starts with schematic design, then followed by design development, contract documentation, contract implementation & management and completion phase.

5.2.1 Schematic Design

In this process, analysing the project brief, design concept, cost indication and submissions for Planning Approval are the main components. The client appoints all responsibility of a main consultant to the architect, in which the architect is then in charge of gathering all information of the site for the initial design stage. In determining a project brief, Client Consultant Meetings (CCM) are conducted.

Analysis of Project Brief

The client, Marimo Land S. B., approaches the architect regarding their proposal to build a service apartment in the suburban area of Puchong. However, there was no set of requirements given by the client except for the concept which was O’Hako. The architect, working together with the client, will come up with a proper brief with programmes. Once an agreement is achieved, the planner will brief on the site requirements and the authority guidelines. Site requirements include, density that can be built on site. During this process, the client was in the midst of procuring the land for the project from an agent. The agent will provide the land grant and the land surveyor would record the land size and bearings, as well as the soil condition.

Preparation of Preliminary Conceptual Sketches Proposal

The concept introduced by client is the O’Hako, box of surprises. The team started to design by using boxes as their main point of attraction. The architect aimed to create a special and well-designed residential building with

Development of Sketch Designs

The boxes were design from every single direction, including the guard house and tower itself. The concept of Ohako continued to be developed into complete sketch designs to be made for development order approval.

24 Figure of Appendix A: Development Order Approval

Figure of Appendix B: Sketch design showing the site plan of Ohako Residence.

25 Figure of Appendix C: Working drawings showing the site plan of Ohako Residence.

26 5.2.2 Design Development

Once approval of project development of the project is given by the authorities, the schematic design is then further developed alongside other relevant consultants. This consists of Preliminary Cost Estimation, and Submissions for Building Approval. The project is then divided with other consultants to begin with detailed drawings such as the architect, C & S Engineer and M & E Engineer. (refer to Appendix G for BOMBA APPROVAL)

Detailed Design Work

The design is to be developed and completed upon client’s agreement on the proposal.

The architect decided to provide efficient facilities for the residence in second floor such as swimming pool, hall and gym. The facilities included the five-level basement which is concealed from front entrance. Some facilities also changed from shop lots to kindergarten as the residents are intended to run the educational facilities and caters for Ohako residence. The residence is made for family concept, so the architect incorporated as much open space as possible for the children’s playing area. He also included disabled facilities such as wheelchair-friendly staircases and shower rooms for disabled.

The amount of bedrooms were designed according to market trend. The client has his marketing team to conduct the market survey. The architect proposed the standard residence with two bedrooms and two bathrooms. However, the client decided two types of accommodation: two bedrooms and three bedrooms. Three bedrooms is considered as average amount for architect’s design.

After that, the client started to engage with the architect for civil and structural proposal to decide for the structural design of the residence.

Relevant consultants will come in by this phase to produce technical drawings to ensure the project is feasible.

Preparation and Submission of Working Drawings

The architect was preparing for submission to obtain building approval. So, the civil and structural engineer, as well as quantity surveyor were involved. Civil and structural engineers played the major role in this phase. The drawings are developed along with the client’s approval before being sent to the authorities.

The drawings must abide by local authorities regulations and requirements in order to be approved. In our case study, the authorities involved were MBSJ and Bomba.

27 5.2.3 Contract Documentation

Building Permit Application

Preparation of documents for build permit application for the owner’s signature as applicant and assist with the submission of the application.

1. Zoning Land Use Amendment 2. Variance from UBBL 3. Site Plan Approval

Submission of Construction Documents

The construction documents are submitted to the clients and approval preparation of the bidding information, bidding forms and condition of the construction contract.

Contract Documentation

The architect, Ar.Soo provides accurate and detailed tender documentation for the clients, which provides a reliable baseline on which to tender for proposed construction works. Clients were also advised on the preparation of bidding information, bidding forms, drawings, specifications, timeline, costs and the conditions of the construction contract and the form of construction between the client and contractor.

Selective Tendering

Consists of a short-list of contractors that are known to have the appropriate qualifications to carry out the work satisfactorily. For this project, the client recommended 4 contractors while the architects, 3.

Tender Documentation

The Quantity Surveyor is first in charge of the compilation of documents which are then sent to the tenderers. From here, there are open quotations and comparisons are made by the Quantity Surveyor between the accepted tenders and the final cost plan.

Evaluation Criteria

Several evaluation criterias were set such as the overall costs and total costs, background and financialities. To further shortlist the selection, the would remove the contractor with the highest and lowest proposal and select the few in the middle range.

28 Evaluation Result

Once all the criteria has been met, the contract will be made. The architect would then prepare and collate the necessary contract documentations and incorporate any agreed alterations that may have been made post-tender.

Award of Contract

Standard or bespoke Forms of Contract would be completed and would be arranged for the contract to be signed by the client and the successful contractor.

The contractor was chosen among a group of many and all were categorised in terms of cost, a lower range, a mid range and a higher range. The contractor that was chosen was in the mid range category. In the end, the contractor recommended by the client was chosen.

Resource Planning and Timeline

A duration and resource types schedule which are detailed for the information and the types of resources in each task. Duration refers to the timeframe or timeline in which the tasks will be performed. Resource type is the skill set required to accomplish the task and identify the level of effort (LOE), both prepared by the contractor.

Budget and Cost Control

The quantity surveyor controls the estimation of costs, the setting of an agreed budget, and management of actual and forecast costs against the budget.

Project Baseline

Once a detailed budget is developed and approved with the clients, the architect publishes a baseline and seit it as a point of comparison or reference for actual performance and progress.

Project Planning and Schedule Implementation

Project plans and schedules are prepared as a summary to support the project. A schedule listing of project milestones, activities and deliverables, usually with intended start and finish dates are made. This is usually prepared by the contractors themselves and serve as a reference point of their progress at site.

29 5.2.4 Contract Implementation

The performance of all functions and duties of architectural consultancy practice under the building contract. In addition, providing advice to the client and site staff that are required for the project. Information and activities of the construction are provided by the architects to the contractor under the building contract to allow the contractor to proceed on the construction works. The contractor will then carry on with the construction works as instructed by the architect.

Progress of construction works are monitored and inspected regularly, with contractor meetings every fortnight, so that each construction works are executed according to the building contract. Also, quality of the construction works will be inspected and liaise with the contractor to rectify any errors.

Construction General Review

The examination, evaluation and report upon representative samples of work to keep the client informed of the progress and quality of work. Any defects or deficiencies in the work observed during site visitations will be reported.

Site Meetings

Site meetings are held with the contractor, major subcontractor, consultants and client to review progress of the work and to discuss critical site issues on the project details.

Architect’s Instructions

A set of instructions given by the architects, fortified by a contract for the contractors to comply. If they do not comply, there are severe consequences. (refer to Appendix I for AI)

Bonds and Insurance Policies

Arranged to receive from contractor as required under the building contract and deliver to client for client’s bond and insurance advisors to review.

Construction Schedule

Architect and project manager receive construction schedule from contractor which is then reviewed and forwarded to the client. Examination of the working programme submitted by the contractor and to be satisfied on the works can be completed within the contract period. In addition, inspection of the work schedule to ensure the work is being executed in accordance with the building contract.

Construction schedule is prepared and submitted by the contractor in conformity with the contract time. The construction schedule indicates timing of major construction works including details of critical events. Construction schedule is updated on a monthly basis based on progress of work. Contractor will advise 30 client on any revisions to the schedule as a result from request for any extensions.

Construction Contract Documentation Interpretation

Request on contractor, consistent with the intent and inferable from the documents, showing partially to the contractor on claims, disputes and other matters in question relating to the performance of work.

Schedule Value

Project manager received the schedule from the contractor to indicate and adjust. The client is advised and obtains the agreement from the contractor. Architect, contractor and client then work together to determine the cost value of each construction works that will be spent on construction of the project.

Payment Certification

Architect and project manager are involved to assess contractor’s application for payment. In addition, project manager determines the amounts owed to the contractor under construction contract based on the architect’s observations and evaluation of the contractor application of payment having factored in completeness against the schedule of value and issue certificate of payment to the client. (refer to Appendix J for Interim Certificate)

Drawings and Submittals

The architect will review the drawings, product data and samples for conformance with the general design concept of the work as provided in the documents.

Inspections

Architect and contractor provides assistance in having inspection and testing companies perform services as required by building contract. Project manager then receives and reviews the testing report to the client. The testing and inspection are required to fulfill the authority approval such as :

- TNB - JKR - SYABAS - BOMBA - TM (Internet) - VCAL (Aviation Department) - TAR (Traffic)

31 5.2.5 Final Completion

Certificate of Practical Completion (CPC)

Contractor is required to give a written notice that the works are practically completed. Within 14 days of this notice, Certificate of Practical Completion (CPC) will be issued by Verge Architects to the main contractor when the architect is satisfied with all the physical works being completed. All subcontractors will also be notified by the architect.

Figure 5.1 Copy of Certificate of Practical Completion (CPC)

32 Certificate of Completion and Compliance (CCC)

The Certificate of Completion and Compliance (CCC) will be issued by a principal submitting person (PSP). The PSP, namely an architect, engineer and registered draftsman carry responsibilities including submitting building plans for approval by the MBSJ, supervising erection and completion of the building in conformity with the approved plans and requirements of the provisions of Acts or By-Laws, Upon satisfactory completion of works and clearances from the six essential service departments obtained, CCC can be issued to the owner.

The six essential services :

1. Confirmation of electrical supply (TNB) 2. Confirmation of water supply (SYABAS) 3. Confirmation of connection to sewage treatment plants (JPP) 4. Clearance from lifts and machinery department (JKKP) 5. Clearance for active fire fighting systems (BOMBA) 6. Roads and Drainage

MBSJ may inspect the building at any time on its own initiative or due to any complaints. In the event of failure to comply with the approved plans, in the erection and construction of the building, MBSJ may issue a written notice requiring compliance within a period which fits the non-compliance to be rectified. Issuance of the CCC will also be withheld until such non-compliances are rectified.

33 Figure 5.2 Copy of Certificate of Completion and Compliance (CCC)

34 Client Handling Over

The handover of the building takes place once the contract administrator has confirmed that the works defined in the contracts are complete. However, it has been planned well in advance, and any special requirements included in appointment documents and contracts.

During the handover process, there are three parts :

1. The Schedule : Outlines the typical time frame of a project from design phase to the one-year warranty review stage. This graphic highlights the key stages in the project, along with recommended starting points for specific tasks. 2. The Checklists : Assists the consultants with planning, coordinating and monitoring the tasks to ensure a successful transfer. The checklists have columns for responsible parties, due dates and comments 3. The Companion Document : Provides background information for the checklists and identifies which consultant is typically responsible for a specific task relating to the building handover.

During the handover, the client should be issued with :

● Keys, fobs and transmitter controls for the development ● The health and safety file ● The draft building owner’s manual ● The building log book ● A building user’s guide ● Up to date testing and commissioning data ● All certificates and warranties in respect of the works ● As-built drawings from consultants and specialist suppliers and contractors (or as manufactured and installed). Or an as-constructed building information model. ● Copies of statutory approvals, waivers, consents and conditions ● Equipment test certificates for lifts, escalators, lifting equipment, cradle systems, boilers and pressure vessels ● Licences such as licences to store chemicals and gases to extract groundwater from an artesian wall

35 Defects Liability Period (DLP) & CMGD

Once practical completion has been certified, the defects liability period (DLP) which last six to twelve months begins. DLP commences based on the date stated on CPC. If no defects are found during the inspection of contractor and client, Certificate of Making Good Defects (CMGD) will be issued. During this DLP, any defects reported by the client will be decided by contract administrator whether they are in fact defects or are merely maintenance issues. If contract administrator considers they are defects, then they may issue instructions to the contractor to make good with the defects within reasonable time. When the contract administrator considers that all items on the defect schedule have been made good, CMGD will be issued.

Final Account Certificate

The final account certificate is made at the end of the defects liability period provided that all patent defects have been rectified. Preparing the final account is the process of calculating and agreeing any adjustments to the contract sum (amount originally set out in the contract to be paid to the contractor for completion of the works) so that the amount of the final payment can be determined. The amount of the final payment is then set out in the final certificate.

The financial statements prepared by the quantity surveyor will generally serve as the starting point for final account discussions, In addition, quantity surveyor will also ensure that all the contracts instructions have been accounted for any potential cost-related items. A draft copy of the final account is signed off by the contractor as a full and final settlement prior to the issue.

Strata Management Act

The client sets up the MGB and transfer MC. In the period of the first year after completion, the management cooperation of the building is taken care by the client. However, from there onwards a shift occurs where the occupants of the building are in-charge

36 5.3 Implementation Tools

5.3.1 Planning and Scheduling

Microsoft Excel

The software aids in creating Gantt Charts which helps in the planning and scheduling phase of the project. Creating a spreadsheet of all related items and allocating sufficient time periods to create a project timeline.

5.3.2 Drafting and Design

Autodesk AutoCAD

AutoCAD is a 2D aided drafting software used in architecture to assist in preparing drawings. This software is used as a standardised practice in Verge Architects throughout the whole firm. They use Drawing Management System (DMS) to track and manage the files digitally in the project.

Sketchup

Sketchup enables the 2D drawings become 3D designs. Via this application, it allows Verge Architects to convey their ideas to their clients with a better visual and understanding of the potential building. The 3D model are shown during meetings to the clients for approval.

Method of Collaboration

Various methods of collaboration was used. This allows prevention of misinformation and miscommunication among the consultants and other parties involved. For a big scale project like, O’Hako, misunderstandings in the process of construction have serious implications. Platforms used but not limited to are:

- Email - Documents from authorities - Formal letters - Phone communication (Call or Text)

37 5.4 Monitoring Tools & Strategies

Monitoring tools are used to oversee the progress on the tasks at hand throughout the project. This is necessary to ensure that the project is completed within the timeframe, scope and budget so that it may proceed with minimal risks. Throughout the project, the process will involve comparing actual performance with planned performance and taking actions on different outcomes.

Technical Meeting

Technical meetings only include members of the technical team which excludes the clients. The meetings are short and concise as it is aimed to resolve as many issues as possible within that span of time.

Site Meeting

SIte meetings include the consultants and contractors, and sometimes clients themselves to check on the current works on site. The meetings usually involves touring the site and check for any mistakes done on the site works. Site meetings are to make sure that all works on site are appropriate and any confusions are discussed

Meeting Minutes

Meeting minutes are used to record the important matters discussed on the meetings. The meetings minutes are also referred when there are confusions or any disagreement on contracts and site works / discussions.

38 Figure of Appendix D: Minutes of Meeting. Quality Assessment Committee Meeting

This meeting is to make sure that all quality of work is assessed and all defects are dealt with.

Gantt Chart

Gantt Chart are used to monitor scheduled works and its progress. The gantt chart will be to include works from different parties to make sure that all works are on sync and each party knows their timeline and works that needs to be done.

Figure of Appendix E: Gantt Chart of work progress and schedule

39 5.5 Risks & Mitigation

Risk management is a systematic process that is done throughout a project to identify, analyze and respond to certain risks that may present themselves. This allows the probability and consequences of an event beneficial to the project’s objectives to be maximised.

Risk management includes preparing a list of risk and mitigation plan so that allowances can be made for uncertain events in the project schedule and budget. These uncertain events include unexpected good events (beneficial/good risks), as well as unwanted events (negative risks) which can negatively impact project success. A risk plan can be used to track the status of risks during a project, check for risk events in a daily or weekly manner ad bring it under control.

RISKS IMPACT ON PROJECT SOLUTION/MITIGATIONS

Main contractor did not fulfill 1. Delay in construction 1. Architect issue warning contract duties on time process letter to relevant party 2. Extension of project 2. As no suitable actions deadline were taken,the party was terminated from further duties to lighten their workload 3. New party is hired to take over 4. non -conformance report is issued for unacceptable delays

Structural elements constructed 1. Additional time and costs 1. Architect’s instruction (all) not up to standard is needed to rectify the is issued to ensure that the mistake mistake is fixed within 7 2. Delay in construction days, process 2. When the consequential delay is significant, catch up program is created with the contractor

Insufficient manpower under 1. Delay in construction 1. Request work schedule of contractors process the contractor to make sure manpower is sufficiently delegated to relevant work 2. Monitor process to ensure balance f work

40 Client expressed dissatisfaction 1. Delay construction 1. Architect present logical with design proposed process to come up with reasonings behind decision proposed design, such as for bomba compliances 2. Discourage changes to match with plans proposed to purchasers

Delay of tenderer’s documents 1. Delay planning of works 1. To remind client and to hire relevant specialist to be in charge

Insufficient manpower under 1. Delay in construction 1. To inform tenderers and contractors process client of deadline

Failure of adhering to standards of 1. Construction process 1. Propose visitation to Construction Quality Assessment delayed existing construction sites System 2. Client’s wish was not that adhere to the realised system’s standard in Selangor

Table 5.5.1: Table shows the risks and solutions taken for the project studied

It is important to record down any risks that has happened in a project where risk forecasting is based on experience. Experience gained in the past is used to analyze and forecast what may happen in the future project.

41 5.6 Procurement

The project procurement method of Ohako Residence is the traditional procurement method. Procurement is a term which describes the activities of the client or employer who brought about the construction or renovation of buildings. In this traditional approach, the client will engage consultants such as Architect, Engineers and Quantity Surveyor to design the project. These consultants design will need to meet the client’s budget and satisfaction. This provides a high substantial control to the client as the client will be dealing with the consultants and contractors himself.

42 5.7 Success Criteria

In order to ensure the success of a project, three constraints will be implemented in Quality project management; Time, Cost and Quality, collectively known as the Triple Constraints. The three constraints combined would determine the scope of work delivered. Any delay of project will affect these constraints. Cost Time In this project, the success criteria is mainly to produce a design which fulfills client's expectations and satisfaction, constructed within 52 months and within the budget not exceeding the preliminary cost as agreed with the client.

Quality

Since this project is to create a special, well-designed residence, a lot of emphasis must be made ensuring that the quality of the materials used as well as the workmanship at the highest level possible. With that, the architect is tasked with ensuring that all works partaking the building is conducted as per the requirements. The client himself also involved a lot on every single detail so the client joined on-site meeting many times. During the meeting, every consultants and constructors were required to report their status directly to the client. They could bring out and discuss issues with the client if they need.

This ideal relationship between the client and the team members minimized construction defects and is one of the reason of success of this project.

Time

The overall timeline of construction took 8 years because of shifting of design and sourcing a suitable land. During the designing phase, there were several orders to change of design and component form the client so that the architect needed to resubmit some documents to the building authority again and again.

However, in terms of construction phase, this project is considered successful. They completed the project earlier than the tentative schedule. The tentative dead lines were October 2019 for Tower 1 and March 2020 for Tower 2, but both was done in August 2019.

Cost

The cost of this project was kept in accordance to the budget. They did not use many IBS method on this project, but standard form work and efficient use of materials saved time or speed up the process.

43 6.06.0

⬥ ⬦ ⬥ ⬦ ⬥ ⬦ CONCLUSION

44 In conclusion, conducting the case study on O’Hako Residences enabled us to gain a better understanding on the different stages of project management and how important it is to have an organised process of execution from start to finish of a project. The defining of roles is crucial to allow the frame of work to be established for each party. This allows accountability in work done in case of mishaps or unfortunate events.

From the project, we can understand in depth the different stages and phases involved, which includes implementation phases, prior to completion phase. These processes heavily involve back and forth communication between different parties. Thus, cooperation is necessary to ensure a successful project completion. Furthermore, it is important the project’s goals and achievements are determined so that there is a solid direction for the project. Project management allows mediation between different members of the project to allow a smooth documentation.

Additionally, success criteria of the project is studied to evaluate the quality based on the triple constraints. There is a consideration that the project may fail but harsh lessons are learned in order to improve on the next project and raise awareness in practice.

45 7.07.0

⬥ ⬦ ⬥ ⬦ ⬥ ⬦ REFERENCE

46 -Sdn.Bhd., P. P. M. consultant. (0AD). Overseas construction consulting service to investors in ASEAN Plus PM Consultant Sdn.Bhd. Retrieved from https://www.plus-pm.com/en/

-VergeArchitects. (0AD). Retrieved from https://www.facebook.com/VergeArchitects/

-QS Sdn. Bhd. (0AD). Retrieved from http://dkqs.com.my/Online.aspx

-EngkyDesign. (2017, May 4). Retrieved from http://engkydesign.com.my/v2/

-E & J Construction. (0AD). General Construction Contractor, Remodeling, and Handyman Services. Retrieved from https://ejconstructionrgv.com/

-PERUNDING PQS SDN. BHD. - Get More Info at RAMCI. (n.d.). Retrieved from https://buy.ramcreditinfo.com.my/index.php/search/Malaysia-Company/232045/PERUNDING-PQS-SDN.-BH D..html.

-ABOUT US. (n.d.). Retrieved from https://www.primareka.com/about-us/.

47 8.08.0

⬥ ⬦ ⬥ ⬦ ⬥ ⬦ APPENDIX

48 Content

Appendix A: Development Order Approval

Appendix B: Sketch Designs

Appendix C: Working Drawings

Appendix D: Minute of Site meeting

Appendix E: Consultants Lists at Initial Stage

Appendix G: BOMBA Approval

Appendix H: Letter of Release

Appendix I: Architect’s Instructions

Appendix J: Interim Certificate

49 Appendix A: Development Order Approval

50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 Appendix B: Sketch Designs

73 74 Appendix C: Working Drawings

75 76 77 78 79 80 81 82 Appendix D : Minutes of Meeting

83 84 85 Appendix E : Consultants Lists at Initial Stage

86 Appendix F : Gantt Chart

87 88 89 90 91 92 Appendix G: BOMBA Approval

93 94 Appendix H: Letter of Release

95 96 97 98 Appendix I: Architect’s Instructions

99 10 0 Appendix J: Interim Certificate

10 1