KEGOC

KEGOC JSC

General • System Operator of Unified Power System (UPS)

• Natural Monopolist

• Assets 35-1150 kV OHTLs – 24,380 km 74 substations – 34,493 MVA

• Manpower 4,600 employees

• Sole Shareholder NWF Samruk-Kazyna JSC

• Assets USD 1,295.2 million* • Equity USD 783.7 million

* as at 1 July 2011

Ñâåðíóòü âñå îêíà.scf Asset Profile

Equity share Core business

Maintenance of KEGOC’s information and telecommunication complex, Energoinform JSC 100% enhancement of telecommunication assets efficiency

Electricity transmission across Northern Batys Transit JSC 20% Kazakhstan – interconnector

Strategy

• KEGOC’s Long-Term Development Strategy extended to 2025

• Comprehensive Action Plan on implementation of KEGOC’s Long-term Development Strategy extended to 2025

• KEGOC’s Development Plan for 2011 - 2015 Strategy 2025

Mission: secure reliable operation and effective development of Unified Power System of Kazakhstan in accordance with up-to-date technical, economic, environmental requirements, and occupational health and safety standards

By 2025, KEGOC will become a world-class company and Vision: the regional centre of power industry expertise

Strategic goal: create a competitive company in the global economy

Strategic Goals

• Fulfill the Government requirements for reliability and quality of Kazakhstan UPS operation

• Achieve a level of System Operator functions to rival that of the best companies in the sector

• Ensure stable growth of the Company shareholder value through development of the core business, enhancement of the effective usage of National Power Grid transit potential, and realization of the export potential of Kazakhstan UPS

• Become a leader in corporate development in the sector, Kazakhstan and CIS Rendered Services

• Electricity transmission across Kazakhstan National Power Grid (NPG)

• Technical dispatching of supply and consumption in the network

• Balancing of electricity production and consumption Financial Indicators Million USD

2008 2009 2010 2011

actual actual actual estimated

Income 222.2 248.2 334.5 391.2

Expenses 183.6 277.0 273.1 350.6

Net income 49.7 -29.7 38.7 31.3

Dividends 5.0 5.8 4.7 Financial Stability Indicators

2008 2009 2010 2011

actual actual actual estimated

Current ratio 2.08 2.67 2.55 2.15

Debt/equity capital 0.48 0.53 0.47 0.66

Debt/ EBITDA 3.4 4.7 2.9 4.8

Interest coverage 4.1 3.9 8.5 6.4 Credit Ratings

S&P ВВ+/stable

Fitch Ratings BBB-/positive

Moody's Investors Service Ваа3/negative

Investment Projects of the Company

Investments Implementation USD million period

Alma Electricity Transmission Project 200.0 2009-2014

Kazakhstan Electricity Transmission Rehabilitation 346.7 2010-2016 Project, Phase II Moinak Electricity Transmission Project 68.7 2010-2012

Ossakarovka Transmission Rehabilitation Project 28.4 2010-2014

Strengthening of Interconnection between 26.7 2010-2017 Power Centre and Kazakhstan UPS

Balkhash Electricity Transmission Project 208.8 2010-2020

Construction of Interstate 500 kV Kemin – 150.0 2013-2018 Transmission Line Construction of 500 kV – ShGES – Ust- 283.0 2011-2017 Kamenogorsk OHTL Investment Projects of the Company

Investments Implementation USD million period

Construction of 500 kV ShGES – Aktogai – 400.0 2012-2018 Taldykorgan – Alma OHTL NPP Electricity Transmission Project / Construction of 500 kV Aktau – Beineu – – 474.9 2016-2020 Atyrau OHTL Construction of 220 kV Uralsk - Atyrau, Kulsary – 142.0 2016-2020 Tengiz OHTL Construction of 500 kV Astana SS including 500 kV 157.7 2016-2020 Nura - Astana OHTL Construction of 500 kV Nura – Zhezkazgan OHTL 179.7 2016-2020 Construction of 500 kV Atyrau – Ulke OHTL 196.3 2021-2025

Torgai TPP Electricity Transmission Project 85.3 2021-2025

National Power Grid Rehabilitation 565.2 2013-2020

Total 16 projects 3 513.4 2009-2025 Kazakhstan Electricity Transmission Rehabilitation Project. Phase II

Project Objective Improve the technical level, energy efficiency, reliability and stability of Kazakhstan UPS operation

Location Kazakhstan National Power Grid

Project provides for Stage I - Upgrading and replacement of high voltage equipment at 55 substations of Kazakhstan National Power Grid which have not been included in the scope of Phase I of the Project. Stage II - Construction of 220 kV Shu – Zapadnaya OHTL, 256.6 km, and Burnoye – Tulkubas OHTL, 60 km.

Project value: $ 346.7 million (EBRD - € 255 million plus company's funds) Implementation period: 2010-2016 Alma Electricity Transmission Project

Objective •Improve reliability of power supply and cover of power demand of Almaty city and Almaty region consumers; •Power delivery from TPP (1320 MW)

Location Almaty province

Project provides for: • Construction of 500/220/110 kV Alma SS including 2 AT, 500 MVA each • Rehabilitation and extension of 500 kV Almaty SS and 500 kV YuKGRES SS • Construction of 500 kV YuKGRES-Alma OHTL 320.65 km • Construction of 500 kV Almaty-Alma OHTL 62.71 km • Construction of 220 kV Alma-Kensai OHTL 54.3 km •Construction of 220 kV OHTL cross connection lines at Alma SS, including: •220 kV ACHPP-3 – Shelek OHTL 2х12.9 km •220 kV ACHPP-3 – Robot OHTL 2х2.8 km

Project value: $ 200.0 million (IBRD - $ 78 million plus company's funds) Implementation period: 2009-2014 Moinak Electricity Transmission Project

Objective Power delivery from Moinak HPP

Location Almaty province

Project provides for

•Construction of 220 kV OHTL Moinak HPP-Shelek SS, 97.73 km •Construction of 220 kV OHTL Moinak HPP-Robot SS, 227.457 km •Construction of 220 kV Moinak HPP Outdoor Switchyard •Extension of 220 kV Robot SS •Extension of 220 kV Shelek SS

Project value: $ 68.7 million (IBRD - $ 48 million plus company's funds) Implementation period: 2010-2012 Ossakarovka Transmission Rehabilitation Project

Objective Improve reliability of power supply and cover power demand of industry and domestic consumers of Astana power centre and Astana industrial area.

Location Akmola province

The Project provides for: - Replacement of two transformers of 125 MVA with the same of 250 MVA at 220/110 kV TsGPP SS - Rehabilitation of 220 kV TsGPP – Ossakarovka OHTL (118.7 km)

Project value: $ 28.4 million (EBRD – $ 14.2 million plus company's funds) Implementation period: 2010-2014 For detailed information visit our web-site www.KEGOC.KZ

Thank you for attention