SUMMARY

FOR PROPOSED NEW PROJECT

OF

SHREE SHYAM INORGANICS PVT. LTD.

At

J.L.No. 7, Dag No. 15, Bhagabatipur, P.S. Sankrail, Kandua Gram Panchayet, District. – 711302,

PREPARED BY:

PACIFIC SCIENTIFIC CONSULTANCY PVT. LTD., KOLKATA

1

Executive Summary Shree Shyam Inorganics Pvt. Ltd.

SUMMARY

FOR PROPOSED NEW PROJECT

Setting up manufacturing unit of Acid Slurry (LABSA)

At Bhagabatipur, P.S. Sankrail, Kandua Gram Panchayet, District: Howrah, West Bengal - 711302

1. COMPANY

M/s. Shree Shyam Inorganics Pvt. Ltd. has proposed for setting up manufacturing unit of Acid Slurry (LABSA) at J.L.No. 7, Dag No. 15, Bhagabatipur, P.S. Sankrail, Kandua Gram Panchayet, District. Howrah – 711302, West Bengal. The Khatian number is 2590. The Company’s registered office is situated at 27/1, Armenian Street, Kolkata – 700001, West Bengal. Four reaction vessels will be introduced to produce Acid Slurry (1400 MT/month) and Spent Sulphuric acid (1180 MT/month) considering 25 working days/month.

Sl. Equipment Qty. Type Size/ No. Capacity 1. Reaction Vessels Sets 4 Agitator 7 MT 2. Separator 1 Colonical 30Tonne 3. Storage Tank 5 Horizontal 125 KL 4. Measurement Tank 2 Rectangle 5.7 KL 5. Pumps 6 V2BB 3”/2 ½” 6. Cooling Tower 1 3842 ID 5 TR 7. Diesel Generator 1 Engine Alternator With Silencer 62KVA

2. PROJECT SITE

The factory located at J.L.No. 7, Dag No. 15, Bhagabatipur, P.S. Sankrail, Kandua Gram Panchayet, District. Howrah – 711302, West Bengal is well connected through NH-6. Sankrail Railway Station is about 4 km from the location. Original land surface is little undulating and irregular in shape which has been already developed.

2

Executive Summary Shree Shyam Inorganics Pvt. Ltd.

The company has acquired 0.33 acre (1335.463 sqm) of land. The Khatian number is 2590. The land is already converted into Factory Land and muted in company’s name. The factory will be constructed on the said land. The site is falling under Kandua Gram Panchayet. The latitude and longitude of the project site is 22°33'42.84"N, 88°10'30.52"E respectively. The place is connected to railway station and towns by bus, jeeps, taxi and rickshaw. All the civic amenities like market, bus stand, hospital, school, college, hotel, restaurant etc. all are available in the town which is about 5-7 km from the site.

3. PROJECT DETAILS

The proposed project has been planned based on the following condition:

Capacity, TPM : Acid Slurry (LABSA) 1400

Spent Acid 1180

Batch Size, MT : 28 MT

No. of Batches/Day : 2

Working Days : 25

Total Project Cost: The Project cost of the proposed project has been estimated at Rs. 16,772,676. Raw materials: Required Raw Materials for Acid Slurry (LABSA) and Spent Acid are given below. Sl. Raw Material Kg/Batch MT/Batch TPD TPM Remarks No. INPUT 1. Linear Alkyl Benzene 19178 19.178 38.356 958.9 Raw 2. Sulphuric Acid 27808 27.808 55.616 1390.4 Materials 3. Water 4614 4.614 9.228 230.7 TOTAL 51600 51.6 103.2 2580 OUTPUT Acid Slurry (LABSA) Finished 1. 28000 28.00 56.00 1400 Product By 2. Spent Acid 23600 23.60 47.20 1180 Product Total 51600 51.60 103.2 2580 3

Executive Summary Shree Shyam Inorganics Pvt. Ltd.

4. OTHER REQUIREMENT

Water: The company will meet its water requirement from deep water tube well. The water will also be available from Rain Water Harvesting (RWH) system. The estimated demand for water is 9.77 KLD for meeting the entire requirements for domestic consumption, gardening and Industrial uses.

Sl. No. Particulars Water Requirement (KLD) 1. Domestic 0.15 2. Gardening 0.05 3. Industrial Process 9.3 Cooling (Make up) 0.27 Washing - Total 9.77

Manpower: The total requirement of manpower for the proposed project is estimated at 17 numbers. The required manpower is available locally. The implementation of industrial laws and regulations and locational factors of labour employment will also have to be considered. Power: The contracted power will be 93KVA. The power will be obtained from West Bengal State Electricity Board (WBSEB). Apart from this, there will be one D.G. set with capacity of 62 KVA as backup unit.

5. MANUFACTURING PROCESS Manufacturing process is briefly described in this section along with brief process description and chemical reaction. Detailed manufacturing process: In Batch process measured LAB (Linear Alkyl Benzene) is taken in a reaction vessel and then measured Sulphuric Acid is fed in the reaction vessel through measuring tank with controlled temperature then whole mass is left for some time

4

Executive Summary Shree Shyam Inorganics Pvt. Ltd. for complete reaction and digestion. After proper testing when it is found the sulphonation is completed, measured water is added for diluting the mass and is transferred to settling tank for setting or separation of acid for 12 to 14 hours. After proper separation of the total mass the lower layer which is the Spent Sulphuric Acid is transferred to Spent Sulphuric Acid tank and the Upper layer which is Acid slurry is transferred to Acid Slurry Storage tank. It requires very sound knowledge of all steps and this process has some definite advantages as stated below:  Uniform and consistent quality  Better yield/higher productivity

 Saving in use of H2SO4  Simple Process  Instant start and stopping arrangement  Very easy to operate  No Noise, Air, Water Pollution  Low cost of Labour & Electricity  Improved Odour  Improved Colour  Shorter Acid holding time Process Parameters to be maintained during Sulphonation: Time to time cooling is required because of exothermic reaction which leads to generation of heat.  Temperature during Sulphonation: 450C – 600C  Temperature during Digestion: 500C – 550C  Temperature during Dilution: 500C – 600C Max.

Time taken for Sulphonating agent: 1/2  Addition of H2SO4: 2 hrs to 3 hrs  Duration of Digestion: 2 hrs  Adding of Water Dilution: 2 hrs to 3 hrs  Settling Time: 12 hrs to 14 hrs

5

Executive Summary Shree Shyam Inorganics Pvt. Ltd.

LAB- Linear Alkyl Benzene

H2SO4- Sulphuric Acid

6

Executive Summary Shree Shyam Inorganics Pvt. Ltd.

6. ENVIRONMENTAL CONSIDERATIONS

The factory is planned as far as practicable as an inherently non polluting unit.  In this unit, the production type is totally closed system. So, no possibility of generation of any type of emission from the production process.  There will be combustion of Diesel in Generators (62 KVA). The emission will be discharged through a chimney having a proper height as per the norms of WBPCB.  There will be no generation of effluent water from process and the domestic sewerage about 0.1 KLD will be discharged in the local Govt. Body’s Sewerage system after treated as per PHE rules.  During operational stage 125 Kg/month solid waste (approx) will be

generated. From process 1180 MT/ month H2SO4 (75-85 %) will be generated which will be collected, stored, transported and sold to Authorized Actual Users. 20 Kg/month (approx) sewage sludge will be given to Govt. approved incinerators. However, necessary precaution for storage and handling of other chemicals will be taken as per requirement.  No Noise will be generated from operation. There will be one Acoustic DG sets. Therefore no significant noise will be generated.  An extensive plantation programme will be taken for inside the boundary premises and both side of internal road. The total area covered for plantation programme is 440.703 m2. i.e., 33% of total area.

Air pollutants

The sources of air pollution from the plant activities are as follows:  In the process there will be no chance of generation of air pollution as all the reaction vessels will be kept closed during the reaction process.  In the D.G. Set; the chimney of proper height is provided as per the regulation of W.B.P.C.B. So emission of flue gas will disperse efficiently.  Air quality will be regularly monitored.

7

Executive Summary Shree Shyam Inorganics Pvt. Ltd.

Source Fuel APC System Concentration of dust Inlet Outlet D.G. Set Diesel Proper stack with exhaust - <75 (62KVA) mg/Nm3

Solid Waste Management The solid waste generation and management are proposed as follows:

Type of Solid Waste Estimated Generation Process of Disposal (Kg/Month) Discarded Containers/ 125 Decontamination and reuse or sell to scrap vendors Barrels Sewage Sludge 20 To be given to Govt. approved incinerators

Liquid Effluent Generation and Control There will be no generation of effluent water from process. There will be liquid effluent (approx 0.1KLD) from domestic section. Part of this effluent will be taken into septic tank and to soak pit; other part will be discharged to Panchayet drain. The Domestic waste water will be treated as per PHE norms. So there will be no such risk of contamination of ground or surface water. Noise Pollution Control Proper acoustic enclosure for rotating equipment and providing silencers for DG set (62KVA) will help in keeping noise level within CPCB norms. Greenbelt An extensive plantation within the boundary limits of the plant is considered during project work by planting about 2300 saplings making a two row deep green belt along the periphery (spacing 2.0 m x 2.0 m) and all along internal roads and dumps leaving only adequate truck access. The total land area covered for greenbelt will be 33% of the total area i.e., 440.703 sqm.

8

Executive Summary Shree Shyam Inorganics Pvt. Ltd.

Lit of big trees for proposed plantation is given below.

No. Common name Scientific name Family 01. Radhachura Delonix regia Caesalpinaceae 02. Arjun, Arjuna Terminalia arjuna Combretaceae 03. Nim Azadirachta indica Meliaceae 04. Ghoranim Melia azedarch Meliaceae 05. Tantul, Tentuli Tamarindus indica Caesal pinaceae 06. Chatim Alstonia scholaris Apocynaceae 07. Akashmoni Acacia moniliformis Mimosaceae 08. Aam Mangifera indica Anacardiaceae 09. Sisso Dalbergia sissoo Papilionaceae 10. Pakur Ficus infectoria Moraceae 11. Sirish Albizia Lebbeck Mimosaceae 12. Jarul Lagerstroemia speciosa Lythraceae 13. Debdaru Polyalthia longifolia Anonaceae 14. Bot Ficus benghalensis Moraceae 15. Ashwatha Ficus religiosa Moraceae 16. Karanj Derris indica Fabaceae 17. Jhaun Casuarina equisetifolia Casuarinaceae 18. Krishnachura Caesalpinia pulcherrima Caesalpinaceae

7. ENVIRONMENTAL MANAGEMENT COST

An initial budget of Rs. 6.0 lacs to be made on the following heads as included in the project cost in the proposed project. The recurring cost is estimated to be around Rs. 1.0 lacs. Capital cost Recurring (lac) cost (lac) Air Pollution Control Equipment 1.0 0.25 Water harvesting system 2.0 0.25 Water sanitation and septic tank 2.0 0.25 Plantation 1.0 0.25 9

Executive Summary Shree Shyam Inorganics Pvt. Ltd.

This budget provision may be reviewed at the time of commissioning of the unit.

8. ENVIRONMENTAL SETTING OF THE PROJECT SITE

Land- is at J.L.No. 7, Dag No. 15, Bhagabatipur, P.S. Sankrail, Kandua Gram Panchayet, District. Howrah – 711302, West Bengal. The selected and purchased site has already been converted to industrial land after proper recording of mutation in BL & LRO. Air Quality - Industrial and Residential Air Quality is important for the area. Water Quality - Zero discharge will be attempted to minimize water pollution so that there is no impact on local water resources. Ecology - Not significant, no reserve forest area or sensitive place is around. Social - Significant for job and development.

10