Resettlement Planning Document

Resettlement Plan Document Stage: Revised Project Number: L2207 November 2007

PRC: Qingfeng Water Supply Sub-project under Wastewater Management and Water Supply Sector Project

Prepared by People’s Government

The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

1

REVISED RESETTLEMENT PLAN

Qingfeng Water Supply Sub-project

Under

Henan Wastewater Management and Water Supply Sector Project

IN THE

PEOPLE’S REPUBLIC OF

Qingfeng County Water Supply Company November 2007

2 Endorsement Letter of the Resettlement Plan

Qingfeng Water Supply Company has prepared the resettlement plan for Asian Development Bank (ADB) financed water supply project in our county. This resettlement plan fully complies with requirements of the relevant laws, regulations and policies of People’s Republic of China and Henan Province as well as ADB’s policy on involuntary resettlement.

According to the latest detailed survey and analysis of technical and economic comparison, the water source and the plant site are to be transferred within the county. This resettlement plan has been updated on basis of the preliminary design and measurement survey. Qingfeng County People’s Government hereby confirms the content of this resettlement plan and will guarantee the land acquisition, compensation and relocation budget being provided according to the provisions of this resettlement plan.

Signature of Head of the County: Jiang Jiding

Qingfeng County People’s Government

October 20th, 2007

3 ABBREVIATIONS

ADB Asian Development Bank APs Affected Persons LAR Land Acquisition and Resettlement DI Design Institute DMS Detailed Measurement Survey EA Executing Agency HWMWSP Henan Wastewater Management and Water Supply Project IA Implementing Agency LARO Land Acquisition and Resettlement Office LG Leading Group MEA Monitoring and Evaluation Agency NGO Nongovernment Organization PRC People’s Republic of China PMO Project Management Office VCRLT Village Committee Resettlement Leading Team RIB Resettlement Information Brochures RP Resettlement Plan TA Technical Assistance TOR Terms of reference

4 Table of Contents

Executive Summary...... 8 1. Introduction and Project Description ...... 11 1.1. Introduction...... 11 1.2. Project Background...... 11 1.3. Project Description...... 12 1.3.1. Project Location ...... 12 1.3.2. Main Construction ...... 12 1.3.3. Investment Estimation and Implementation Schedule...... 12 1.3.4. Socioeconomic Benefits of the Project ...... 12 2. Socioeconomic Background of the Affected Areas...... 13 2.1. The geography general situation of the affected areas...... 13 2.2. Socioeconomic Situation of the County...... 13 2.3. Socioeconomic Situation of the Towns and Villages ...... 13 2.4 The Socio-economic Situation of the Affected Villages ...... 13 2.5 The Socio-economic Situation of the Affected People ...... 14 2.4.1. Statistic Characteristics of APs ...... 14 2.4.2. Size of the Families Interviewed...... 14 2.4.3. Time of Living in the Village...... 14 2.4.4 Employment and Income of the APs...... 14 2.4.5. Minority Families and Vulnerable Groups...... 14 2.4.6. Willingness to obtain training ...... 14 2.4.7. Understanding and attitudes...... 15 3. Project Impacts ...... 15 3.1. Types of loss Caused by Land Acquisition...... 15 3.2. Measures to Minimize Land Acquisition...... 15 3.2.1. Measures to reduce land acquisition during project design Phase ...... 15 3.2.2. Measures to Minimize Land Acquisition and Resettlement in Construction Stage ...... 16 3.3. Project Impacts...... 16 3.3.1. Survey Methods ...... 16 3.3.2. Summary of Project Impacts...... 17 3.3.3. Cultural Relics and Vulnerable Groups...... 19 3.4. Project Impact Analysis ...... 19 4. Legal and Policy Framework...... 20 4.1. Legal framework - State/ Local Law and Regulations...... 20 4.1.1. Legal framework...... 20 4.1.2. Relevant Legal Extracts ...... 21 4.2. ADB Policy on Involuntary Resettlement...... 27 4.2.1. Overall Objective of ADB Involuntary Resettlement Policy ...... 27 4.2.2. Resettlement Plan Preparation ...... 28 4.3. Resettlement Objectives and Planning Principles...... 28 4.3.1. Resettlement Target...... 28 4.3.2. Resettlement planning principles ...... 29 4.4. Compensation Rate ...... 29 4.4.1. Compensation Principles...... 29 4.4.2. Compensation Rates for Land Acquisition and Resettlement...... 30 4.4.3. Cut-off Date ...... 31 4.4.4. Disbursement of Compensation Fund...... 31 4.4.5. Procedures for Compensation Payment ...... 31 4.4.6 Eligibility and Entitlement for Compensation ...... 32 5. Compensation and Rehabilitation Measures...... 35

5 5.1. Resettlement Strategy ...... 35 5.1.1. Resettlement Objective ...... 35 5.1.2. Principle of RP...... 35 5.2. Rehabilitation Plan for Permanent Land Acquisition ...... 35 5.2.1. Disbursement and Distribution of Compensation Fund...... 35 5.2.2. The task of Rehabilitation...... 36 5.2.3. Standards for rehabilitation...... 36 5.2.4. Agricultural rehabilitation plan...... 36 5.2.5. Non-agricultural rehabilitation plan...... 36 5.2.6. Measures for the income rehabilitation...... 37 5.3.6. The employment during construction period ...... 38 5.4. Women and Vulnerable Groups Rights Protection...... 38 6. Institutional and Organizational Structure ...... 38 6.1. Institutional Framework...... 38 6.2. Institutional Framework and Responsibilities...... 39 6.3 Staffing...... 40 6.3.1. Staffing for the Resettlement Institutions...... 40 6.3.2. Staff training of resettlement agency ...... 41 6.2. Measures to Strengthen Institutional Capacity Building...... 41 7. Public Participation and Consultation...... 42 7.1. Public Participation...... 42 7.1.1. Resettlement Information Brochure (RIB)...... 42 7.1.2. RP Distribution ...... 42 7.1.3. Public Consultation in Project Preparation Phase...... 42 7.1.4. Public Participation and Consultation during Project Implementation ...... 43 7.2. Grievance Redress Procedures...... 43 7.2.1. Targets for Grievance Redress Procedure ...... 43 7.2.2. Grievance Redress Approaches...... 43 7.2.3. Grievance Redress Scope...... 44 8. Monitoring and Evaluation ...... 45 8. Monitoring and Evaluation ...... 45 8.1. Internal M&E...... 45 8.1.1. Main Monitoring Contents...... 45 8.1.2. Internal Monitoring Objectives...... 45 8.2. External M&E...... 45 8.2.1. External Monitoring Objectives...... 45 8.2.2. Means and Methods ...... 45 8.2.3. Reporting Requisition ...... 46 8.2.4. Resettlement M&E Outline...... 46 9. Resettlement Budget ...... 48 9.1. Contents of Resettlement Costs ...... 48 9.1.1. Land Acquisition and Resettlement ...... 48 9.1.2. Compensation Cost for Infrastructure and Ground Attachments ...... 48 9.1.3. Other Costs...... 48 9.1.4. Contingencies...... 48 9.2. Budget Table on Resettlement Costs...... 49 9.3. Resettlement Investment Plan...... 50 10. Implementation Arrangements and Schedule...... 50 10.1. Principles on Confirming Resettlement Schedule...... 50 10.2. Overall Schedule of Land Acquisition and Resettlement Activities ...... 50 Appendix 1 Map of Qingfeng Water Supply Plant and the Water Source...... 52 Appendix 2 Social-economic Status of the Affected Villages in 2006 ...... 53 Appendix 3 Social-economic Survey of the Affected Households...... 54

6 Appendix 4 The Staff of Resettlement Leading Group...... 55

Tables

TABLE 2.1: EDUCATIONAL BACKGROUND OF THE APS IN SURVEY ...... 14 TABLE 2.2: THE APS’ ATTITUDE AND OPINION TOWARDS THE PROJECT...... 15 TABLE 3.1: TEMPORARY AND PERMANENT LAND ACQUISITION OF WATER SUPPLY PLANT AND PUMPING STATIONS ...... 17 TABLE 3.2: ANALYSIS ON IMPACT OF PERMANENT LAND ACQUISITION ...... 18 TABLE 3.3: TYPES AND QUANTITIES OF INFRASTRUCTURE AND GROUND ATTACHMENTS...... 19 TABLE 4.1: STANDARD OF THE COMPENSATION FOR THE GRAIN...... 26 TABLE 4.2: RESETTLEMENT PRINCIPLES ...... 29 TABLE 4.3: CALCULATION OF STANDARD OF COMPENSATION FOR PERMANENT LAND ACQUISITION...... 30 TABLE 4.5: COMPENSATION RATE FOR TEMPORARY LAND USE...... 31 TABLE 4.6 COMPENSATION RATE FOR FACILITIES ...... 31 FIGURE 4.1: COMPENSATION PAYMENT PROCEDURES FOR PERMANENT LAND ACQUISITION...... 32 TABLE 4.7: ENTITLEMENT MATRIX ...... 33 TABLE 5.1: LABOR SKILLS TRAINING MEASURES ...... 38 TABLE 6.1 STAFFING OF RESETTLEMENT ORGANIZATION...... 41 TABLE 8.1: RESETTLEMENT M&E OUTLINE...... 47 TABLE 9.1: RESETTLEMENT BUDGET...... 49 TABLE 9.2: RESETTLEMENT INVESTMENT PLAN ...... 50 TABLE 10.1: SCHEDULE OF LAND ACQUISITION AND RESETTLEMENT ACTIVITIES...... 51

7 Executive Summary

A. Background and Impacts Assessment

1. The Project includes construction of 24 deep wells, 24 water pump rooms and 1 second class pump room, 2 tank reservoirs of 2,700 m3, a water quality examining and measuring center, an office building and staff dormitory, 59.06 km of water-distributing pipeline network, and 13.06 km of connecting and water-carrying pipeline network.

2. Qingfeng Water Supply Project permanent land acquisition is 48 mu, including 30 mu (within Wuyanjing Village of Liuge Town) for the plant and 18 mu for wells and roads. Temporary land use is 812 mu, of which 688 mu irrigated land is for works associated with water source, 15 mu irrigated land for construction of the plant and 28 mu irrigated land and 81 mu (54,000m2) urban roads for construction of water-distribution pipeline network. Villages including Wuyanjing, Luojia, Bianjia and Xizhaodian within Liuge Town and villages including Meizhuang, Haozhuang, Zhifang, Zhangerzhuang and Niezhuang within Zhifang Town will be partially affected. There are 16,514 persons from 3,949 households in the project area, who will benefit from the project. The land acquisition for the Project permanently affected 39 households with 171 persons. Due to the decision taken to readjust the farmland within the village group, the Project also indirectly affected another 31 households with 92 persons of Wuyanjng Village.

B. Reasons for change of Plant site

3. The water source for the Plant was originally surveyed during preliminary design. According to the detailed survey, the water source should be shifted 3.5 km south-eastern of Qingfeng County and the numbers of wells is still 24. Through analysis of technical and economic comparison, the Plant site should be transferred from the Qingfeng County Station to the eastern part of Renmin Road. The new plant site is close to the water source, which results in less electricity consumption for water acquisition and less investment in water-distributing works due to less duplication of the works. The new scheme will also enlarge the service area and enhance the safety and reliability of water supply. Furthermore, the new site has easy access to roads and telecommunications which facilitates the implementation of construction. All the 30 mu land acquired for the new site is irrigation land without house demolition or resettlement.

C. Policy Framework and Entitlements

4. The resettlement principles of the Project are based on the land acquisition law and regulations of PRC and ADB’s Involuntary Resettlement Policy. And that for compensation, resettlement and income rehabilitation permits differences between villages and communities of cities, which exists in kind and cash compensation and selection of income rehabilitation between community-based and private organizations. The key point is to ensure that all the APs get sufficient compensation and assistance of income rehabilitation after demolition. The main purpose of RP is to rehabilitate APs’ income and living standard minimizing the damage on their own economic and social environment. Special attention has been given to meet the need of the affected underprivileged and vulnerable groups. Due to the principle and qualification of compensation entitlement, an entitlement matrix has been formulated to instruct payment of compensation and implementation of RP, and the matrix covers all varieties of loss including loss and rehabilitation cost of land, temporary/permanent income sources.

D. Rehabilitation and Income Restoration

8 5 All affected persons will be compensated as set out in the project entitlement matrix in this RP. During Project implementation, efforts will be made to further minimize the land acquisition and resettlement impacts.

6. The income restoration and rehabilitation measures has been drafted in this RP according to the local economic situation and the purpose of them is to guarantee the living standards and livelihood of the affected persons equal or better than the ones before the project. These income restoration and rehabilitation measures have been developed in consultation with all affected persons and they have reflected the most practical ways for the easy implementation during the project.

E. Institutional Arrangements

7. Qingfeng WSP Resettlement Leading Group is comprised of Qingfeng County Government, finance bureau; government office, planning office, Construction Commitment, Environment Bureau and Water Affair Group, and etc. There is sub-office set in finance bureau belong to leader team; this office is responsible for enhancing leadership of the project, formulating resettlement policy and coordinating the organizations. It is the responsibility of government to manage the project, make decision on important matters, and coordinate the organizations to direct the project; make project progress favoring. The office is responsible for making contact with project offices of province and city as well as ADB, and arranging project works, and compiling the schedule of project.

F. Public Consultation and Disclosure

8. Public participation is a key point in the Project. Within the project area there have been numerous consultation meetings. The officials from the county government, township government, village committees (including officials from land and resources administration bureau, civil administrative bureau, and women’s federation), the affected persons and consultants attended the meetings. These meetings and survey outcomes have had remarkable influences upon policies and compensation entitlement in the resettlement plan, particularly in formation of compensation rate, cash compensation and formation of income rehabilitation based on livelihood/training program. Although several public consultations have been made, the Project executors still bear in their mind the need of extra consultation meetings during the land acquisition and construction. Main activities include: (i) distribution of the Resettlement Information Brochure in Chinese version, including description of policy, compensation entitlements, compensation rate and amount, appeal procedure and resettlement/land acquisition plan; (ii) holding formal villager meetings to decide the allocation of compensation; and (iii) carefully making an on-the-spot measurement, and reaching consensus with the affected families/enterprises in land, property and other final necessities for acquisition and resettlement.

G. Complaints and Grievances

9 Appeal procedure was set up to solve the disputes in compensation and the resettlement interest on the purpose of responding to the affected persons’ grievances timely and transparently. The affected persons are entitled to file the grievances against any dissatisfaction in land acquisition and rehabilitation, including the amount of compensation paid to them. In the Resettlement Information Brochure, detailed procedures for acceptance and processing of grievance will be issued, and these procedures will also be interpreted to the affected persons at the public meeting held by the IA or the district land acquisition and resettlement offices prior to the land acquisition and resettlement.

9

H. Monitoring and Reporting

10. Implementation of the resettlement plan will be monitored internally and externally. The implementation agency has assumed responsibilities for the internal monitoring. County land acquisition and resettlement offices will be staffed with the independent supervisors. Qingfeng Water Supply Company will compile the quarterly report to submit to ADB, with contents cover the implementing progress of resettlement plan, emphasizing whether it conforms to the principle set forth in the Resettlement Plan and requirements in the compensation entitlements matrix. The EA has engaged an independent monitoring organization to make external monitoring together with the ADB, prepare evaluation report on the resettlement progress after commencement of construction, specifying the distribution of the compensation, and other measures to maintain or improve the affected persons’ social and economic living conditions against the “non-project” conditions.

I. Cost Estimate of Resettlement

11. According to the project feasibility study report and resettlement survey, the resettlement costs are estimated to be CNY4.84 million, including 15% contingency cost. The budget can be adjusted based on the actual measurement of physical losses during the project implementation. The EA has ensured adequate funding for resettlement implementation and will provide budgets as necessary to meet eventual shortfall that emerges in achieving the resettlement objectives.

10 1. Introduction and Project Description

1.1. Introduction

1. In accordance with ADB policies on involuntary resettlement and other principle regarding social securities along with related social aspects, this resettlement plan is developed in reference to PRC’s laws/regulations and local governments’ policies on land acquisition and resettlement. This plan describes a policy framework to mitigate the adverse impacts caused by the proposed Qingfeng Water Supply Project through series of remediation measures. Also the resettlement plan for the affected people and rehabilitation plan for the seriously affected villages are also involved in the framework including how and when to take these measures.

2. As Chinese governments and ADB are concerned, the primary purpose of resettlement plan is to ensure the people who unavoidably lose lands or properties in the development program have the same or better livelihood and living standards compared with that under “non-projects situations. All the policies, suggestions and compensation measures in this resettlement plan are oriented to this purpose. The implementation agency has organized the Qingfeng Water Supply Company to construct and manage this Project. The Company will directly assume the responsibility for the preparation, implementation, internal monitoring and financing of the resettlement plan.

3. This resettlement plan is formulated on the following basis: (i) “City Planning Act of PRC” (ii) “Land Administrative Law of PRC” (iii) “Interim ordinance of PRC on Farmland Occupation” (iv) “Decision of the State Council on the Strengthening of Land Management through Deepening the Reform”, October 21st, 2004” (v) ADB’s “Policy on Involuntary Resettlement” (vi) “Implementation Rules for Land Administration Laws of Henan Province” (vii) “ Municipal Government’s Announcement of the Compensation Standard for the Ground Attachment in the Land Expropriated for National Construction” (viii) Relevant project reports.

4. This resettlement plan covers all aspects of resettlement and income rehabilitation caused by the construction of the proposed water supply plant, water source and water carrying and distribution system.

5. On the basis of the feasibility study report and the preliminary designing report, this plan is made after survey on land acquisition and demolition impact and socioeconomic survey. The plan has been approved by Qingfeng People’s Government. This revised RP is now based on preliminary design.

1.2. Project Background

6. Qingfeng County is located in the northeast of Henan province, at the boundary of the , and Henan provinces. The north latitude is 32.22 degrees and the east longitude is 115.30 degrees, and the site is on the west edge of of Henan province, with its edge is connected with the Puyang city, and its north edge is connected with the , and the west is connected with the Xinxian County in Shandong province. The county covers a total area of 872 km2, and its total population is 670, 000, including 3 towns, 15 villages and 524 administrative villages. Qingfeng County seat lies in the central location, now it

11 population amounts to 92,000 in the urban area with its total acreage of 16 km2, the height above sea level is 46 to 50 m, and the whole county belongs to the Huanghe River rinse plain, Haihe water system.

7. There are two water supply companies in the urban area, the average water supply ability is 17,000 m3/d, and that for the self-provision source is 16000 m3/d (a total of 32 pumped wells provide for itself). The capacity of the water supply for industry and people’s daily life of the zhongzhou famous town—Mazhuangqiao town, which is located in the upstream of the urban area, and 4.5 kilometers away from the south of the urban area, is 10000 m3/d.

1.3. Project Description

1.3.1. Project Location

8. The Qingfeng Water Supply Plant is located in the southeast suburb planning area on the eastern part of Renmin Road; it occupies 30 mu irrigation land, with 160 meters from east to west and 125 meters from north to south.

9. The water source is in the southeast of Qingfeng County and within 10km north of Liuge Town. The pumped wells and roads are planned to occupy 18mu irrigated land southeast of the plant site. (See Appendix 1, Map of Qingfeng Water Supply Plant and the Water Source).

1.3.2. Main Construction

10. The Project includes construction of 24 deep wells, 24 water pump rooms and 1 second class pump room, 2 tank reservoirs of 2,700 m3, a water quality examining and measuring center, an office building and staff dormitory, a pipeline network of 59.06 km, and a 13.06 km connecting and water-carrying pipes.

1.3.3. Investment Estimation and Implementation Schedule

11. Investment in this project is estimated to be CNY65.32 million, of which about CNY 4,836,900 shall be paid as compensation for land to be acquired for the project.

12. The schedule of the Project is briefed as follows: (i) finished the Feasibility Study Report (FSR) in April 2005, (ii) to start scheduling and establishment of the resettlement institutions in July 2007, (iii) to workout the detailed design by May 2008, (iv) to start to allocate compensation for the land acquisition in June 2008 , and end by August 2010 (v) to complete the project from April 2008 to June 2010.

1.3.4. Socioeconomic Benefits of the Project

(A) Social benefit

13. This project brings about the good social effects after its construction: a) it improves the infrastructure; b) it improves the investment environment, which does benefit for the inflow of capital; c) it enhances the service function of the county and advances the taste of the county; d) it improves the quality of drinking water, which does benefit for the health of the local people; and e) it does benefit for protection of the underground water for the development of the district economy.

12 (B) Economic benefit

14. After the implementation of the project, it will increase the water supply capacity to 30,000 m3 per day, and if calculated 1.4 Yuan for each ton of water it will bring the economic benefits CNY14.40 million, in which the pure profit is CNY4.4 million, it will also increase by CNY0.4 billion the industrial production value. By solving the lack of water, it eliminates a constraint on the economic development and it is predicted that it will help generate 3,400 jobs each year.

2. Socioeconomic Background of the Affected Areas

2.1. The geography general situation of the affected areas

15. Qingfeng county is located in the central area of the north China plain, since belonging to temperate zone continental monsoon climate, the four seasons are clearly demarcated, with ample sunshine, the average temperature is 13.4°C, the most highly temperature is 42.2°C, the most lowly temperature is -20.7°C, the annual average rainfall is 585.5mm, the average relative humidity is 69.8%, and the rainfall in summer is 70% of the whole year.

2.2. Socioeconomic Situation of the County

16. With total area of 872km2 and population of 680,000 people, Qingfeng County has 3 towns, 15 townships and 524 villages. The GDP in 2006 was CNY3.66 billion, in which the first, second and third industry accounted for 37%, 39% and 24% respectively. The financial income of 2006 was CNY102 million, 24.15% more than 2005. On the 859,000 mu arable land, there grows main crops including wheat, corn, peanut, cotton and etc.

2.3. Socioeconomic Situation of the Towns and Villages

17. Liuge Town locates between county and municipal area. Influenced by the economic development of the municipality, the county and Mazhuangqiao, Liuge Town has become a new type of town with rapid growth of building construction and carpentry industry. There are 6,986 persons in 1999 households, 8052 mu arable land in the project affected area of Liuge Town, and the per capita net income is CNY2,965.

18. Zhifang Town lies in the east of the County. The commercial, handicraft industry and other third industries are developed in the affected area within the village. There are 9528 persons within 1950 households, 10,104 mu arable land in the affected area of Zhifang Town, and the per capita net income is CNY3,595. The status of the affected villages and groups is shown in Appendix 2 Table of Social-economic Survey of the Affected Villages.

2.4 The Socio-economic Situation of the Affected Villages

19. The permanent land acquisition of the Project impacted 9 villages in Liuge and Zhifang Towns, with 171 persons from 39 households affected. Socio-economic surveys were conducted respectively in August 2007 for the affected villages by the Plant and in September 2007 for the affected villages by the construction of water source. The surveys covered all the 39 households (respondents) with 171 persons that were affected by the permanent land acquisition. The integrated analyses are shown as follows.

13 2.5 The Socio-economic Situation of the Affected People 2.4.1. Statistic Characteristics of APs

20. All the 39 households with 171 family members, who lose their land permanently, were surveyed. Of the total respondents, 91 are male and 79 are female, with an average age of 49. As for their marital status, 123 (72%) of them have been married and 47 are single (28%). The detailed educational background of the APs in the survey is presented in Table 2.1.

Table 2.1: Educational Background of the APs in Survey Educational background No. of cases (person) Percentage (%) No schooling 17 10 Primary school 36 21 Junior school 60 35 Senior school 42 24 Post secondary school 9 5.5 College and above 7 4.5 Total 171 100

2.4.2. Size of the Families Interviewed

21. Among the 39 families interviewed, each family has 2 to 6 members with the average number of 4.4.

2.4.3. Time of Living in the Village

23. The survey indicates that all the people have been living in the village long for several generations.

2.4.4 Employment and Income of the APs

24. The APs gain income from both farming and non-farming business. The average farmland of the 171 APs is 1.2 mu per capita. Most of the affected labourers are engaged in sideline works during non-farming seasons. Of the affected persons, there are about 120 persons engaged in non-farming business, including building, decoration, transportation, and other small business. The annual gross income per household was CNY15,305, with the lowest of CNY6,600 and the highest of CNY27,720 per household. The average annual gross income per capita was CNY3,511. (See Appendix 3 Social-economic Survey of the Affected Households).

2.4.5. Minority Families and Vulnerable Groups

25. According to the survey, all the 171 APs are of Han nationality without minor nationality families.

26. Among the 39 families, neither female-household family nor widow/orphan family was found.

2.4.6. Willingness to obtain training

27. All the affected laborers wish they would accept retraining If possible for better reemployment.

14

2.4.7. Understanding and attitudes

28. The APs remain positive that they would get fair compensation corresponding to their losses, and actually, 98% of the 171 respondents believed in reasonable compensation; and 2% doubted. When questioned about whether their families would benefit from this project, 98% respondents said ”yes”, and 2% indicated uncertainty.

29 As also shown in the survey result, the respondents hold support to the project overwhelmingly, as 99% agree and 1% not sure. The survey result is shown in Table 2.2.

Table 2.2: The APs’ Attitude and Opinion Towards the Project

Questions Reply (%)

yes no not sure Would your family benefit from this project? 98 0 2

yes no not sure Would your losses be fairly compensated? 97 0 3

In addition to reasonable compensation, will the yes no not sure relevant departments in charge help you? 94 0 6

yes no Not care not sure Do you agree and support this project? 99 0 0 1

3. Project Impacts

3.1. Types of loss Caused by Land Acquisition

30. According to the FSR and field survey for the project, the types of losses caused by land acquisition and resettlement are shown as follows:

• Permanent arable land acquisition; • Temporary land use; • Infrastructure demolition; • Ground attachments (tombs); • Loss of other productive assets (standing crops).

3.2. Measures to Minimize Land Acquisition

3.2.1. Measures to reduce land acquisition during project design Phase

31. In the beginning, there was the comparison of the scheme on choosing the location of the Plant.

32. Scheme 1: The plant is located at the eastern part of Renmin Road at the southeast of

15 the County; the plant occupies 30 mu, with 15 mu temporarily occupied land, all of which are irrigated land within Liuge Village. There shall be no house demolition.

33. Scheme 2: The plant is situated at the southeast suburb of the county seat and at the crossing of Wenhua Road and Fengming Road; the permanent land acquisition of the plant is 30mu and temporary land is 10 mu, which belongs to the Government.

34. After comparing, we find the second scheme involves no demolition but is far from the water source which shall result in more investment in water-carrying pipeline works. So Scheme 1 is selected.

35. The water source of Qingfeng Water Supply Project is about 10 km2 area among Loujia Village, Bianjia Village, Xizhaodian Village and Zhifang Village within Liuge town. The above mentioned villages shall be affected to different extent. The wells are of east-west linear layout, with 500 to 600 meter distance between. There shall be altogether 24 wells, the wells and access paths permanently occupy 18 mu land and the construction of the wells and water conveyance pipeline requires 688 mu land temporarily. The existing paths in the farmland shall be used where possible for water-carrying, water-distributing pipes and power supply. The dimensions and lengths of the pipes shall be calculated scientifically to minimize the land acquired. The water-taking layer shall be reasonably decided to mitigate the influence to agricultural water consumption.

36. The trunk water-distributing pipelines are laid along No. 106 National Highway and Renmin Road. The design complies with the county planning. The pipes are laid along streets and pedestrian sidewalks without demolition of houses or shops.

3.2.2. Measures to Minimize Land Acquisition and Resettlement in Construction Stage

37. During the construction period, the water source well and the construction of pipelines will have more impact. Because the wells are broadly located, it cannot repeatedly utilize the land occupied, so the temporary occupied land is relatively more. During construction the scheme and the sequence of construction shall be confirmed according to terrain of water source and road distributing situation, combined with the practical demand of the project itself. The scheme of material transportation and laying and scrap disposing shall be carefully decided to improve the utilization of the existing road and the temporarily occupied land. This will help to control the area of temporary occupied lands as small as possible and try to keep away from the ground facilities in the farmland.

38. Before the construction of pipeline network, communications shall be carried out with the city planning bureau, natural gas company, water supply bureau and telecom communication company concerning detailed information about the direction, depth, location, the scheme of protection and emergency measures, and mitigation measures to minimize the project impacts. It was expected that the construction of the pipeline network will cause minor and very short-term disruption in the affected areas.

3.3. Project Impacts

3.3.1. Survey Methods

39 According to ADB’s Policy on Involuntary Resettlement and combined with the relevant

16 domestic laws and regulations, a baseline survey is to be conducted for inventory indicator survey about the influence of the land acquisition and relocation. The surveys included three kinds: land acquisition survey, census and socioeconomic survey. During land acquisition survey, with the help of the Qingfeng County Land and Resources Bureau, the degree of land loss and the affected graves, wells and compensation standard are determined. At the same time, we do survey about the underground facilities in the urban area with the construction bureau, power supply bureau, Telecom Communication Company to confirm the sections and length of streets which are affected by the pipeline construction. When doing the census, with the help of Zhifang Township Government, Liuge Township Government and Qingfeng County Government, we confirm the number of the affected households and the vulnerable groups, and while doing the socioeconomic survey, the income of affected persons is evaluated by sampling, and study out the rehabilitation and compensation plans.

3.3.2. Summary of Project Impacts

40. In the project affected area, there are 18,072 mu arable land in the 9 villages. Qingfeng water supply project acquires 48 mu permanently and 812 mu temporarily, the details are shown in Table 3.1 below.

Table 3.1: Temporary and Permanent Land Acquisition of Water Supply Plant and Pumping Stations

Permanent land Temporary land use (irrigated The name of Name of Area acquisition land) sub-projects (irrigated land) town village mu mu Water supply Wuyanjing Liuge Town 30 15 plant Village 40 (including access path - will 4 villages Water source Liuge Town 9 utilize the farming path where (14 wells) (including wells possible) and pumping 48 (including access path - will Zhifang 5 villages station) 9 utilize the farming path where Town (10 wells) possible) Liuge Town 4 villages 2. 300 Pipeline for Zhifang water-carrying 5 villages 3. 300 Town Chengguan Pipeline for 4 villages 4. 28 Town water-distribution Urban road 81 (54000m2) total 48 812

(i) Permanent land acquisition

41. Qingfeng water supply project needs 48 mu land permanently, in which (a) the plant occupies 30 mu collective owned arable land, with 83 persons in 18 households affected; and (b) the road access to the plant and the wells occupy 18 mu collective owned arable land, mainly for the pumps and access paths for maintenance and operation, with 87 persons in 21 households affected. The access paths occupy more land but are more flexible by utilizing the existing path in the farmland. The wells are scattered in the 9 villages. The total permanent land acquisition accounts for only 0.27% of the total arable land, with little influence to Liuge and Zhifang Towns. The specifics can be seen in Table 3.2.

17

Table 3.2: Analysis on Impact of Permanent Land Acquisition Arable land before Arable land after acquisition acquisition land House- Perso Househo Per acquir per Village Household land holds ns Total ld capita ed capita Average loss Average Average average (mu) (mu) (mu) (mu) (mu) (mu) (%) total 323 1116 1132 3.50 1.01 30 3.41 0.99 2.65 Wuyanj in ing which, 18 83 91.3 5.07 1.10 30 3.41 0.74 32.86 the APs total 751 2630 3145 4.19 1.20 5.2 4.18 1.19 0.17 Luojia in which, 5 22 26.4 5.28 1.20 5.2 4.24 0.96 19.70 Liuge the APs Town total 489 1713 1791 3.66 1.05 1.6 3.66 1.04 0.09 Xizhao in dian which, 2 10 16 8.00 1.60 1.6 7.20 1.44 10.00 the APs total 436 1527 1900 4.36 1.24 1.6 4.35 1.24 0.08 Bianjia in which, 2 7 11.3 5.65 1.61 1.6 4.85 1.39 14.16 the APs total 127 638 836 6.58 1.31 1.6 6.57 1.31 0.19 Meizhu in ang which, 2 8 10.4 5.20 1.30 1.6 4.40 1.10 15.38 the APs total 150 678 1081 7.21 1.59 1.6 7.20 1.59 0.15 Haozhu in ang which, 2 8 12.8 5.20 1.30 1.6 4.40 1.10 15.38 the APs total 561 2552 1993 3.55 0.78 3.2 3.55 0.78 0.16 Zhifan g Zhifang in Town which, 4 19 22.8 5.70 1.20 3.2 4.90 1.03 14.04 the APs total 382 2035 2353 6.16 1.16 1.4 6.16 1.16 0.06 Zhange in rzhuang which, 2 6 7.8 3.90 1.30 1.6 3.10 1.03 20.51 the APs total 730 3625 3841 5.26 1.06 1.6 5.26 1.06 0.04 Niezhu in ang which, 2 8 8.8 4.40 1.10 1.6 3.60 0.90 18.18 the APs

ii) Temporary land use

42. Qingfeng water supply project occupies 812 mu land temporarily, including 731 mu irrigated land. The water source occupies 688 mu, the construction of water supply plant occupies 15 mu, the construction of pipeline network occupies 28 mu and 81 mu (54,000m2) urban road. Apart from the 9 villages in Liuge and Zhifang Towns, another 4 villages in Chengguan Town shall be affected by the temporary land occupation. It is estimated that about

18 400 persons shall be temporarily affected. After construction of this project, the temporary land will be recovered by the affected farmers, the cost of is included in the compensation (see Table 4-5).

43. The temporary acquired land for water source is scattered broadly which results in less repeatedly utilization of the land acquired. Materials transportation and wells construction need more occupation of temporary land. Measures shall be taken to increase the repeated use of the land acquired and minimize the area of land acquisition. The temporary used land accounts for about 4.5% of the total arable land of the affected villages.

44. The land temporarily used for the construction of water plant is 15 mu irrigated land. iii) House Demolition

45. All the land expropriated in this project is farmland, without any house or facility demolition. iv) Infrastructure/Ground attachments

47. On the land permanently expropriated by the Project, the facilities shown in Table 3.3 have been identified. Table 3.3: Types and Quantities of Infrastructure and Ground Attachments

Items wells (ea.) tombs (ea.) Nos. 4 10

3.3.3. Cultural Relics and Vulnerable Groups

48. The project has no impact on cultural relics; and no vulnerable groups are affected.

3.4. Project Impact Analysis

1) The Scope of the Water Source Impact

49. The water source is located in the farmland within 10 km2 in the southeast of county seat, and wells and bypath will permanently occupy 18 mu land. Because of the scattered distribution of wells, the loss to the affected people is small, and land acquisition will not bring too much impact on their living. There will be no impact on infrastructure or ground attachment. The land temporarily used is 88mu, which affects Wuyanjing, Luojia, Bianjia, Xizhaodian, Meizhuang, Haozhuang, Zhifang, Zhangerzhuang and Niezhuang villages. But these are occupied for not too long, and after completion of the project it will be reused by reclamation. For both permanent land acquisition and temporary land use, the affected persons will be compensated, which they can use for the development of individual economy, so that they can live a better life. At the same time, they can take part in the livelihood training program, from which they can get the skills they want, and some can gain employment in the project construction.

2) The Scope of Water Supply Plant Impact

50. The plant needs to expropriate 30 mu irrigated land permanently and 15mu irrigated land temporarily without any house or other facility demolition. Land shall be readjusted after land acquisition to compensate land for the affected people. The analysis of specific impacts is shown

19 the above table 3.2.

3) Impacts of the water source and pipeline networks

51. The construction of wells and pumping stations will occupy 88 mu irrigated land within the 9 villages in Liuge and Zhifang Towns. The 13.06 km connecting and water-carrying pipeline network shall occupy 600 mu irrigated land temporarily within the 9 villages in Liuge and Zhifang Towns. The project will build 59.06 km water distribution pipeline, involving a total of 109 mu temporary land use including 28 mu irrigated land and 81 (54,000m2) urban road. All the distribution pipelines shall be laid along the roads and streets in the urban area, without any house demolition. (see Table 3-1)

4. Legal and Policy Framework

52. Legal and policy framework for this project has two sets of sources: PRC’s laws and regulations and policy requirements of ADB. This chapter is aimed to describe demolition and resettlement policies and strategy concerning land acquisition and compensation.

4.1. Legal framework - State/ Local Law and Regulations

4.1.1. Legal framework

53. Compensation to the affected people and land and resettlement adheres to the Land Administrative Law initiated in 1999, involving land access and ownership, land use and protection and compensation, resettlement subsidy and proper resettlement measures to the affected people. According to the Land Administrative Law (Article 8), rural land belongs to the state land, rural and suburb land is owned collectively by village (residential land, arable land and mountain regions). Such collective and its members (majority of two thirds) have the right to determine whether reallocate or rearrange the arable land (Article 31). Furthermore (Article 47) it elaborates when land acquisition is necessary, compensation shall be made as per the original land purpose containing land compensation, resettlement subsidy, compensation for land attachment and standing crops.

54. Arable land compensation shall be multiple of average annual output of 3 years preceding such acquisition (based on local standard as prescribed by law). Alike, the resettlement subsidy for each agricultural population to be settled shall be calculated based on multiple of the average annual output of 3 years preceding the land acquisition. Compensation for standing crops shall be calculated as per one season output. Compensation method and standard for the attachments will be carried out pursuant to prescription of Provincial People’s Government. Augmenting attachments will not be compensated at the date of announcement release for land acquisition. Article 48 and 49 demand consultation to the compensation standard and the compensation is appropriated to collective owned. All the compensations will be paid to the land owners including agency or collective organization.

55. Arable land occupancy tax will be calculated according to actual land area tax payers occupied which will be collected at once based on the specified amounts.

56. With regards to the specific implementation principle, compensation eligibility, deadline, procedures of information publicity, resettlement plans and monitoring have been specified. During urban building demolition, specialized state policy and local regulations will be in charge of the management, demolition, compensation and resettlement. The laws and regulations used

20 for the project are shown as follows:

z Land Administrative Law of PRC z State Council Notice of the Decision to Deepen the Reform for Restrict Land Administration. z Land Acquisition Announcement of State Land Resources Ministry z Urban House Demolition Management Regulations, China z Land Administrative Regulation of PRC z Provisional regulations for Arable Land Occupancy of PRC z Basic Farmland Protection regulations, Henan Province z Land Administrative Regulation of Henan Province z Puyang Municipal Government’s Announcement of the Compensation Standard for Ground Attachment in the Land Expropriated for National Construction (2003) z Announcement of Puyang People’s Government on Adjusting compensation standard of underground For National Construction (2003)

4.1.2. Relevant Legal Extracts

(i) Relevant regulations of Land Administrative Law of PRC:

57. Article 10. Land collectively owned by peasants will be organized legally by the collective economic committee; peasant collective-owned land respectively owned by more than two villages will be managed by the rural collective institutes of village or farmer teams; collective land subordinated to village (town) farmers will be managed and administrated by village (town) collective economic forms.

58. Article 14. Land owned by farmer collectives shall be operated under a contract by members of the economic organizations of the farmer collectives for crop cultivation, forestry, animal husbandry or fishery.

59. Article 24. National protective arable land is forbidden to be changed into non-arable land. Land occupancy compensation policy is implemented by nation. In case land is approved for non-agricultural construction, the principle of “ cultivating according to occupation” must be observed; non-observance cultivation or cultivated land not conforming to the requirements, land cultivation fees shall be paid as per the regulations as specified by province, autonomous or municipal level.

60. Article 31. Land damage caused by digging, sinking and occupying shall be restored in charged by relevant regulations of the nation; non-restoration or non-observance shall be subjected to land recovery expenses.

61. Article 42. Land acquired shall be compensated for on the basis of its original purpose of use.

62. Compensation for acquired cultivated land shall include compensation for land, resettlement subsidies and attachments and standing crop crops on the acquired land. Compensation for acquisition of cultivated land shall be six to ten times the AAOV of the acquired land for three years preceding such acquisition. Resettlement subsidies for acquisition of cultivated land shall be calculated according to the agricultural population to be resettled. The agricultural population to be resettled shall be calculated by dividing the amount of acquired

21 cultivated land by the average amount of the original cultivated land per person of the unit the land of which is acquired. The standard resettlement subsidies to be divided among members of the agricultural population needing resettlement shall be four to six times the AAOV of the acquired cultivated land for three years preceding such acquisition. However, the highest resettlement subsidies for each hectare of the acquired cultivated land shall not exceed fifteen times its AAOV for the three years preceding such acquisition.

63. Standards of land compensation and resettlement subsidies for acquisition of other types of land shall be prescribed by provinces, autonomous regions and municipalities directly under the Central Government with reference to the standards of compensation and resettlement subsidies for acquisition of cultivated land.

64. Standards for compensation for attachments and standing crop crops on the acquired land shall be prescribed by provinces, autonomous regions and municipalities directly under the Central Government.

65. For acquisition of vegetable plots in city suburbs, the land users shall pay towards a development and construction fund for new vegetable plots in accordance with the relevant regulations of the State.

66. If land compensation and resettlement subsidies paid in accordance with the provisions of the second paragraph of this Article are still insufficient to help the farmers needing resettlement to maintain their original living standards, the resettlement subsidies may be increased upon approval by people's governments of provinces, autonomous regions and municipalities directly under the Central Government. However, the total land compensation and resettlement subsidies shall not exceed 30 times the AAOV of the acquired land for the three years preceding such acquisition.

67. Article 47. After deciding on the policy of land acquisition compensation, announcement shall be issued by relevant local government and opinions of the collective farmers and local organizations shall be listened.

68. Article 48. The rural collective economic organization, the land of which is acquired, shall accept supervision by making known to its members the income and expenses of the compensation received for land acquisition.

69. The compensation and other charges paid to the unit for its land acquired is forbidden to be embezzled or misappropriated.

70. Article 49 Local people's governments at all levels shall support the rural collective economic organizations, the land of which is acquired, and the farmers in their efforts to engage in development or business operation or to start enterprises.

71. Article 50. Nation-owned land used by the construction unit shall be obtained by such compensable attitude as selling; however, the following types of construction land as approved by the people’s government above county level can be obtained by appropriation”: (i) National governmental organization land use (ii) Urban infrastructure land and public welfare land (iii) Infrastructure construction land primarily supported by the nation related to energy, transportation and water conservancy works (iv) Land of other purposes as specified by law or administrative regulations

22

72. Article 54. Where land owned by the State or by farmer collectives needs to be used temporarily for construction of projects or for geologic prospecting, the matter should be subject to approval by the land administration departments of people's governments at or above the county level. However, if the land to be temporarily used is located in the area covered by urban planning, the matter shall be subject to agreement by the urban planning administration department concerned before it is submitted for approval. The land user shall, depending on who owns the land and who has the land-use right, enter into a contract for the temporary use of the land with the land administration department concerned, or the rural collective economic organization, or the villagers committee and pay compensation for it in accordance with the provisions of the contract.

73. Article 57. In case that the following conditions are met, and subject to approval of the people’s government or government with approval right, national land use right may be retrieved: (I) land use for public interest; (II)when land needs to be regulated arising from old city reconstruction for implementation of urban planning.

74. Article 58. Rural peasants can only own one residence for each household, with the area not exceeding the standard for province, autonomous region and municipalities. Rural residences shall meet the overall planning of town land utilization and maintain the original residing base and village spare area. Rural residing land shall be inspected by town people’s government and approved by country-level government; in which, where farmer-used land is occupied; procedures shall be addressed according to Article XXXXIV of this law.

(ii) Relevant Stipulations of Provisional Regulations of Farmland Land Occupancy Tax in PRC, 1987

75. Article 2. The farmland referred in the regulations means the land for planting. And that for planting 3 years preceding the acquisition is regarded as the farmland as well.

76. Article 3. Both unit and individual who need to occupy farmland for building construction or other nonagricultural construction should be responsible to pay farmland occupancy tax (thereafter called taxpayer). They should pay farmland occupancy tax in accordance with the regulation.

77. Article 4. Farmland occupancy tax should be calculated based on the actual area of farmland occupation. The amount of tax should be collected payment once.

78. Article 5. The tax amount of farmland occupancy should be stipulated as follows: (1) Take a county as a unit (same thereafter), for the area that the average farmland area is less than one mu per capita(included), the tax should be CNY2 to CNY10 per square meter; (2) For the area that the average farmland ranges from one (1included) to two (2 included) mu per capita, the tax should be CNY1.6 to CNY8 per square meter; (3) For the area that the average farmland ranges from 2 to 3 mu per capita, the tax should be CNY1.3 to CNY6.5 per square meter; and (4) For the area that the average farmland is more than 3 mu per capita, the tax should be CNY1 to CNY5 per square meter.

79. Article 9. The farmland occupancy tax should be collected by finance department. The land administrative bureau should inform all finance departments timely after approval of land

23 occupation for unit and individual. The unit and individual should declare and pay tax to finance department with the document approved by land administration bureau above county level. The land administrative bureau will transfer the land to unit and individual based on the receipt of tax payment or approval document for land acquisition.

(iii) Relevant Regulations on the State Council Decision to Deepen Reform and Restrict Land Administration

80. Implications of new regulations for land use and land compensation “Document (28) 2004”—a State Council Circular on the “Decision to Deepen Reform and Strictly Enforce Land Administration” was issued on 21st October 2004 and contains several very important provisions in respect of LAR activity. The document points out that “the relationship between ensuring socio-economic development and protecting land resources must be correctly addressed” with the stated objectives “to bring the growth of land for construction use under strict control, take efforts to activate land reserves, strengthen (the awareness of) land saving, deepen reform, improve the legal system, take overall arrangements into consideration and further improve the strictest land system that is in tally with the national conditions of the country”.

81. The document urges local governments to take action to, inter alia: ▪ Strengthen land use planning and utilize approved land use plans as the basis for approving proposed construction projects. ▪ Involve local land use departments in the approval process for construction projects ▪ Publicize minimum values for sale and transfer land to avoid land acquisition taking place at below market rates ▪ Strengthen the application of “no detriment” for affected persons ▪ Ensure compensation payments are targeted to those most affected by LAR activity ▪ Strengthen audit and monitoring arrangements

82. The issue of document 28 was followed up by: (i) The issue (on 1st November 2004) of Decree 27 by the Ministry of Land Resources. Decree 27 contains administrative procedures for use by local Land Use departments in reviewing proposed construction projects. These procedures attempt to strengthen land use planning and control. (ii) Ministry of Land and Resources “Guidelines on Improving the System of Land Acquisition Compensation and Resettlement” which was issued on 3rd November 2004, makes specific reference to Document 28 and gives specific guidance on its implementation.

(iv) Guidelines for the Implementation of the Land Administrative Law of PRC in Henan Province

83. Article 25. Where non-agricultural construction project is approved for land occupancy, cultivation plans shall be made by land users, forwarding to land administrative department for approval responsible for cultivation the land quantity and quality as appropriate. Where there’s not proper condition for land cultivation, corresponding cultivation fees shall be paid and the cultivation fees collection, utilization and management method shall be otherwise specified by provincial people’s government. Where land is supplied in unified manner within urban construction land occupancy under overall land planning, arable cultivation shall be shouldered by land use unit; where arable land is occupied by village and towns, land cultivation shall be

24 taken charge by rural collective organizations or village committee.

84. Article 24. For acquiring farmer’s collective land, compensation should be made as follows: (1) Land compensation: compensation for acquired cultivated land in the outskirt of primary city shall be eight (8) to ten (10) times the AAOV of the acquired land for three years preceding such acquisition; in the outskirt of secondary city and mining area seven (7) to nine (9) times the AAOV; in other areas six (6) to eight (8) times the AAOV. Of the farmland acquisition, various sideline products (excluding vegetable) shall be counted as 15% to 20% of the annual production based on major products.(AAOV: arable land averaged output value) (2) Resettlement subsidies: for acquisition of cultivated land, compensation shall be paid based on each 667 m2: For the average farmland per capita is over 667 m2, compensation shall be four (4) to five (5) times the AAOV of the acquired cultivated land for three years preceding such acquisition; for the average farmland per capita is over 334 m2 and under 667 m2, compensation shall be six (6) to nine (9) times the AAOV of last three years; for the average farmland per capita is less than 334 m2, compensation shall be ten (10) to twelve (12) times the AAOV of last three years. Under special circumstance, compensation shall not be over 15 times the AAOV of the acquired cultivated land for last three years preceding such acquisition of 667 m2. (3) Standing crops: one times the AAOV. (4) Compensation standards for attachments shall be executed according to the regulation of Provincial People’s Government. No compensation shall be paid to the newly added attachments from the date of public notification.

85. Article 35. in case the land occupied belong to rural collective owners or village committee, land compensation shall be paid to rural collective owners or village committee; where it belongs to villagers team; compensation shall be paid to the team and where it belongs to town collective organizers, it shall be paid to the organizers. Compensation for land attachment and green crops subsidy shall be performed as per Article 26 of Promulgation Rules for Land Administrative Law.

86. Article 38. The annual production value for land compensation and resettlement subsidies shall be based on the average annual production and current average nation-regulated product price of last three years. If no nation-regulated price, the local market price shall be used.

87. Article 39. Within the area of land acquisition, if there is water source, culvert, culvert gate, pipeline, road, electric cable and production and living related facilities, the local People’s Government shall organize relevant departments as well as the land use unit and construction unit to resettle properly, without obstruction and damage on purpose; if obstruction and damage can not be avoided, the items shall be rehabilitated or constructed relevant facilities according to regulations.

88. Article 40. Temporary land use shall be implemented according to Article 57 of Land Administrative Law. Expiration of temporary land shall subject it to original status and land returned.

(v) Several regulations of compensation standards for land acquisition for national construction in Puyang City

25 89. Compensation rate for power supply, communication wires (electric pole) is 168-210 yuan/pc, for pumped well (50–80 m)is 7,000–10,000 yuan/pc, trees (big tree) are 21–56 yuan/pc, and small trees are 1–8.4 yuan/pc. Compensation standard for greenhouse is 10–20 yuan/m2; canals are 15 yuan/m; mechanical farming roads are 10 yuan/m2; and houses are 110–370 yuan/m2.

(vi) Announcement of Henan Province on adjusting compensation standard of over ground attachments for National Construction

90. The compensation standard for substance: facility rooms (asbestos title and oil felt roof), 40 to 60 Yuan per m2, (the muddy wall or the grass roof can follow the standards); tombs: 100yuan for a coffin and a grave, increase 50yuan for each increased coffin, power supply circuitry, cement pole with altitude from 8 to 10 is compensated 100 to 120yuan, with altitude from 11 to 15 is compensated 120 to 150yuan. (Including demolish of circuits);

(vii) Puyang Municipal Government’s Announcement of the Compensation Standard for Ground Attachment in the Land Expropriated for National Construction(2003)

91. The compensation standard of grain land.

Table 4.1: Standard of the Compensation for the Grain Unit: CNY/mu grade The standard for classification AAOV

Excellent quality, very good irrigation、very flat plot、very First grade 1300 fertile

Second grade good quality,、good irrigation、flat plot、fertile land 1105

generic quality, have the irrigation 、flat plot, generic fertile Third grade 940 land

In bad quality, with no irrigation facilities, with undulate plot, Fourth grade 800 with low fertilizer

92. The compensation for the acquisition land is accounted according to the value of the green seeding in one season, the time is from the beginning of the land acquisition. In the summer the compensation is account as 60% of the annual value. In autumn, it is account as 40% of the annual value. It is regulated that from June 10th to September 30th is autumn, and October 1st to the next year’s June 10th is summer.

93. The green seeding compensation standard for economic crops refers to the green seeding compensation standard for the temporary acquisition land.

94. From the beginning of land acquisition to the land acquisition document make known to lower levels or over the season from the beginning of transfer, if there is no start of work to occupy land, but only check the amount of the attachment over ground, acquisition land by negotiation, the compensation is not carried out as the transfer season, but during the implementation of acquisition, the demolish on green seeding because of measure,

26 reconnaissance should be compensated according to the fact. When implementing land acquisition, the land management department should consider the period of construction, if it needs long period and over season, the farmer should be notified in time, to avoid the unnecessary loss cause by miss cultivate.

(viii) Announcement of Puyang People’s Government on adjusting compensation standard of ground attachments for National Construction

95. The compensation standard of wells (build by concert): the wells with depth of 40 m, should be compensated with CNY5,000, based on the depth of 40 m, the compensation increases 150 for every increased 1 m. The compensation decreases CNY100 for every decreased 1 m. The deposed or withered wells are compensated at 50%.

96. The number of trees planted on the land should be limited according to be practical and realistic principle. And in the principle of scientific plantation, intercrop with Tungs the number should be below 5 for each mu; Intercrop with the jujube, the number should be less than 22 for each mu; intercrop with the mixed trees, the number should be 25 below. If the number of trees exceeds the limited number and, if the number is one time or lower, the compensation should be calculated as the lower land grade, if the number exceeds more than one time, the compensation should be calculated as the lower two grade.

97. The land management in the urban area should be strengthened. No matter what units and individuals who need to dig wells, build house, plant trees, transplant crops into flowers, vegetables and Chinese medical materials, they should come to the planning department to transact the procedure of approval, or they will not be compensated for such cases.

98. This regulation lists the other ground attachment specifically; they should be compensated according to the corresponding regulations.

4.2. ADB Policy on Involuntary Resettlement

4.2.1. Overall Objective of ADB Involuntary Resettlement Policy

(i) Involuntary resettlement should be avoided where feasible. (ii) When population displacement is unavoidable, it should be minimized by exploring all viable project options. (iii) If individuals or a community must lose their land, means of livelihood, social support systems, or way of life in order that a project might proceed, they should be compensated and assisted so that their economic and social future will generally be at least as favorable with the project as without it. Appropriate land, housing, infrastructure, and other compensation, comparable to the without project situation, should be provided to the adversely affected population, including indigenous groups, ethnic minorities, and pastoralists who may have usufruct or customary rights to the land or other resources taken for the project. (iv) Any involuntary resettlement should, as far as possible, be conceived and executed as a part of a development project or program and resettlement plans should be prepared with appropriate time bound actions and budgets. Resettlers should be provided sufficient resources and opportunities to re-establish their homes and livelihoods as soon as possible. (v) The affected people should be fully informed and closely consulted on resettlement and compensation options. Where adversely affected people are particularly vulnerable,

27 resettlement and compensation decisions should be preceded by a social preparation phase to build up the capacity of the vulnerable people to deal with the issues. (vi) Appropriate patterns of social organization should be promoted, and existing social and cultural institutions of resettlers and their hosts should be supported and used to the greatest extent possible. Resettlers should be integrated economically and socially into host communities so that adverse impacts on host communities are minimized. One of the effective ways of achieving this integration may be by extending development benefits to host communities. (vii) The absence of formal legal title to land by some affected groups should not be a bar to compensation. Affected persons entitled to compensation and rehabilitation should be identified and recorded as early as possible, preferably at the project identification stage, in order to prevent an influx of illegal encroachers, squatters, and other non-residents who wish to take advantage of such benefits. Particular attention should be paid to the needs of the poorest households and other vulnerable groups, such as indigenous peoples, and appropriate assistance provided to help them improve their status. (viii) The full costs of resettlement and compensation, including the costs of social preparation and livelihood program as well as the incremental benefits over the “without project” situation, should be included in the presentation of project costs and benefits.

4.2.2. Resettlement Plan Preparation

99. According to the Bank policy, the contents and level of detail of a resettlement plan, which may vary with circumstances, especially the magnitude of resettlement, should normally include a statement of objectives, policies and strategy, and should cover the following essential elements: (i) Corresponding measures shall be taken for resettlement within the policy frame making sure that the affected people have their optional right and other rights concerning the resettlement; familiar with the feasible schemes technologically and economically, participating in negotiation and enjoying opportunity of selection; obtaining compensation rapidly and duly based on the resettlement costs to counteracting the direct financial loss caused by project. (ii) In case resettlement is involved, corresponding measures shall be taken in line with resettlement planning or resettlement schedule, guaranteeing the affected people could get subsidy (such as resettlement subsidy); obtaining house or housing base, or farming site according to their requests. The production potential, positioning advantages and other comprehensive factors shall at least correspond with the advantageous conditions of the original site. And (iii) To achieve the objectives of this policy, necessary measures shall be taken regarding the policy frame for resettlement plans resettlement to ensure during the transitional period as expected reasonably the affected people could get proper assistance and subsidy in accordance with the livelihood and living standard restoration.

4.3. Resettlement Objectives and Planning Principles

4.3.1. Resettlement Target 100. Compensation and resettlement policy to the affected people are formed based on China State laws and regulations as well as requirements from ADB. The purpose of the resettlement and rehabilitation plan is to ensure that the affected people will regain or surpass their living standards after the resettlement. Priority shall be given to poverty-stricken people and vulnerable groups.

28

4.3.2. Resettlement planning principles

101. Requirements both from China State laws and Asian Development Bank are reflected in the Resettlement principles provided in Table 4.2 are principles involving compensation, dismantling and income rehabilitation; which are adequately flexible: allowing differences between villages, and urban communities; the differences are embodied on the one hand between land redistribution and cash payment; and on the other hand, the income rehabilitation of individual income based on community. The key lies in guaranteeing all affected people could get assistance and compensation for income rehabilitation after resettlement.

Table 4.2: Resettlement Principles Principles Compensation and entitlement provided to the affected people should maintain their living 1 standard at least no worse than ever “without project”, or better. All the affected people, legally entitled or non-entitled, should be compensated and assisted 2 for resettlement. Compensation by cash should ensure the standard of living of the affected people can be 3 maintained at least no worse than ever after resettlement. In case livelihood fails to be maintained after land acquisition, cash compensation or kind 4 compensation for land loss should be made thereto. Other income generation activities should all be carried out. The affected people should have full understanding of such items as eligibility, compensation 5 modes and rate, livelihood and income rehabilitation as well as the project implementation schedule, and participate in the implementation of the resettlement plan. Land acquisition should not be carried out until the affected people are satisfied with 6 compensation and resettlement and their schemes. Compensation and resettlement would be monitored by the executive agency or the third 7 party. Special assistance or treatment should be given to the vulnerable groups to ensure they have 8 a better life.

9 The affected people should have opportunities to get profits from the project.

10 Demolition and resettlement plans should be identical with the overall plan for Puyang.

4.4. Compensation Rate

4.4.1. Compensation Principles z Compensation rate should be determined according to replacement cost principle. z Compensations shall be paid before acquisition of land and property. z Construction management shall be consolidated to shorten the down time for enterprises and shops affected. z Land compensation rate and resettlement subsidy for land acquisition shall be executed in compliance with Henan Land Administrative Regulations and Administrative Method for Land Examination and Approval and Houses Demolition Compensation for Public Welfare Construction of Puyang.

29 z The attachments involving standing crops and trees shall be compensated to the land users or proprietors in line with the policy regulations.

4.4.2. Compensation Rates for Land Acquisition and Resettlement

(i) Compensation Rate for Permanent Land Acquisition 102. The Plant shall occupy 30 mu irrigated land and the water source shall occupy 18 mu irrigated land. The AAOV for the last 3 years is determined to be CNY1,300/mu. According to the latest regulations of Ministry of Land and Resources promulgated at the beginning of 2007, the local compensation standard has been improved by increasing the land compensation multiplier from 8 to 9 times of AAOV of the last 3 years. See Tables 4.3 and 4.4.

Table 4.3: Calculation of Standard of Compensation for Permanent Land Acquisition

Compensation Multiplier (time) Standard of compensation (yuan/mu) AAOV in last 3 Item years Land Land Resettlement Standing Resettlement Standing (CNY/mu/year) Compensat Compen Total Subsidy crops Subsidy crops ion sation

Farmland 1,300 9 15 1 11700 19,500 1,300 32,500

Table 4.4: Compensation Rates for Permanent Land Acquisition Unit: Yuan/mu user fee for Standard of compensation (yuan/mu) Type of Land land Tax on Land Land Cultivation occupation Farmland Management Total land Resettlement Standing Acquired Fee for new Acquisition Fee Compensation Subsidy Crops construction

farmland 11,700 19,500 1300 5850 10672 3335 975 53332

Village Village Land Finance Receiver Contractor Land bureau Land bureau committee committee bureau bureau

(ii) Compensation Rate for Temporary Land Use

103. The project involves temporary use of 731 mu irrigated land in the construction of the Plant, the water source and the pipeline network. The compensation rate for standing crops and land recovery is CNY715/mu for each season that will be affected. Normally there are two cropping seasons in one year.

30 Table 4.5: Compensation Rate for Temporary Land Use

Compensation Multiplier Compensation Rate AAOV (time) (Yuan/mu) Total Item (Yuan/ (Yuan) mu) Standing Land Recovery Standing Land Recovery Crops Cost Crops Cost Farmland 1,300 1 0.1 1,300 130 1,430

(iii) Compensation Rates for Ground Attachment and Facilities (See Table 4.6).

Table 4.6 Compensation Rate for facilities Unit: Yuan/m

item wells tombs

unit CNY/ea CNY/ea

Compensation standard 6500 200

4.4.3. Cut-off Date

104. The qualifying deadline for compensation for the ground attachment in Qingfeng water supply project was decided on 1 February 2008. Only pre-existing ground attachments and facilities can be compensated. Any newly built structures or trees planted after this date will not be compensated.

4.4.4. Disbursement of Compensation Fund

105. In principle, the compensation for the land acquisition and other attachment should be directly paid to the legal owners of the property.

106. Compensation for land acquisition and resettlement paid by the IAs should be distributed to the owner or user of the land directly before land acquisition. According to the Land Administrative Law of People’s Republic of China, the compensation for land loss should be handed to the former owners and users of the land before the land acquisition, while the resettlement subsidies must be put in the aim for relocating the farmers. Therefore, the collective land compensations will be handed to the collective economic entity who owns the lands; the resettlement subsidies will be handed to village committee for the resettlement of farmers.

4.4.5. Procedures for Compensation Payment

107. Figure 4.1 below shows the process and supervision of the compensation fund payment. The Compensation for land acquisition, demolition and resettlement should be paid to IA and township LAO. Then the township government will distribute the compensation fund to the village committee for management and supervision. The township government will monitor and audit the use of the fund, assess and evaluate the effect of the fund use and give necessary instruction to inspect for fraud.

31

Figure 4.1: Compensation Payment Procedures for Permanent Land Acquisition

Qingfeng Water Supply Company

Township Land Acquisition and Resettlement Office

Others Affected Village Affected Owners of (compensation for Committee (land other property (private infrastructure) compensation) owner)

4.4.6 Eligibility and Entitlement for Compensation

108. All the APs should get compensation for loss of their property based on replacement cost.

109. According to the compensation rules, entitlement and eligibility, a resettlement entitlement matrix (Table 4.7) is formulated to guide resettlement implementation, which includes loss of various types (such as loss of houses, land, shops/enterprises, temporary/fixed income resources), covering measures, regulations and standard as provided in this chapter and other chapters. See specifics in Table 4.7.

32 Table 4.7: Entitlement Matrix

Types of Causes for Eligible Quantity of Unit or Compensation Policy Compensation Detail Implementation Losses Occupation Unit or Individual who has Procedure or loss Individual Entitlement • Villager Adequate representative compensation to meetings determine Provide CNY32500/mu as collective economic the relevant issues compensation for land loss and Current organizations and on fund allocation resettlement subsidy. arable land farmers and the and allocating

is Village 9 villages with direct common parts are methods of It was decided to readjust the farmland expropriated committee, loss for 39 households determined by villager compensation fund, within the village. because of land users (171 persons) representative meeting timely and adequate

the Plant compensation Provide CNY1,300/mu as construction Land users get allocation to the compensation fund for standing crops compensation due to farmers who have

Permanent the compensation policy lost production. land • Apply the grievance acquisition and feedback basis. 30 mu • County government, Readjust farmland to minimize loss to collective district government, the 39 households land village committee

organize skills Utilize land compensation and training to strengthen Loss of Direct loss for 39 resettlement subsidy to restore all APs’ laborers’ knowledge production households (171 income Compensate the labor and skills and income Land persons) but losses will force for loss of land After village because of users be shared by entire Provide training and employment • acquisition committee placards land villages (16,514 opportunities and take measures to compensation rate acquisition persons) maintain their business income policy, the

compensation fund Formulate favorable measures for directly shall be laborers’ own business engagement allocated to all land

users.

33 Types of Causes for Eligible Quantity of Unit or Compensation Policy Compensation Detail Implementation Losses Occupation Unit or Individual who has Procedure or loss Individual Entitlement

Current arable land Provide CNY32500/mu as cash Permanent is compensation for land loss and land Inform in advance and expropriated About 90 households resettlement subsidy. Land users get cash acquisition Land pay to the village because of (360 persons) with compensation due to 18 mu users committee and land the water minor losses Provide CNY1,300/mu as the compensation policy collective users conveyance compensation fund for standing crops land pipeline construction

Temporary Temporary Land Hand out compensation fund annually farmland use land used by users About 98 households due to the AAOV of the last 3 years Due to the of 812 mu the Project with minor temporary and after its completion, the land Inform in advance and compensation rate the losses should be returned to the land user pay to the village owners of the crops after the land is recovered to be committee and land should get adequate original. The total of compensation for users compensation standing crops and land recovery cost amounts to CNY1,430/mu. Infrastructure Loss of Property Adequate RO pays compensation infrastructure owners Property owners CNY6500/each well compensation to the fund to property owners because of owners according to the of public facilities due to land regulations compensation rate and acquisition procedure. The allocation of compensation is decided by village committee. Ground Need to be Property Adequately compensate RO pays the attachment removed owners Property owners CNY200/each tomb the owners according to compensation fund to because of the regulations the property owners of land According to the options ground attachment due acquisition of the affected to compensation rate households, special and procedure, assistance shall be together with relevant conducted to help assistance and relocate the tombs. arrangements for the . relocation of the tombs.

34 5. Compensation and Rehabilitation Measures

5.1. Resettlement Strategy

5.1.1. Resettlement Objective

110. The general objective of this RP is to ensure that: the affected person (AP) will be compensated for their land loss and will improve their living standards or at least not be worse than the current level. Based on the features of economic development and employment of the affected village, with integrated analysis, the resettlement objectives are determined as follows: (i) develop the Second and Tertiary Industry and increase APs’ income and (ii) actively take economic rehabilitation measures to ensure AP regain or surpass their living standards after the resettlement.

5.1.2. Principle of RP

111. Based on the relevant state regulations and rules and the ADB involuntary resettlement policies, this RP should observe the following basic principles: z Implement resettlement soundly and put relevant compensation into action, so as to boost or at least restore the effected residents’ living standards. z The resettlement should consider the relations of nation, community and individual. z RP should be compiled in accordance with physical index and compensation rates for land acquisition and demolition. Resettlement projects scale and standards shall be subject to the principle of original scale and standards restoring. Meanwhile, the investment gap should not be left on the basis of planned amount limitation. z RP should involve comprehensive negotiation with APs. z The resettlement should take local city’s plan, resource plan, economic development and environment into consideration. We should take effective measures based on real and local conditions, so as to create the opportunity for APs’ own development.

5.2. Rehabilitation Plan for Permanent Land Acquisition

5.2.1. Disbursement and Distribution of Compensation Fund

(i) Disbursement of the Compensation Fund

112. The compensation fund will be disbursed by the Water Supply Company directly to the accounts of every township LARO and the latter will set up special accounts for APs and directly allocate the compensation fund to APs’ account in accordance with the allocation program.

(ii) Allocation of the Compensation Fund

113. The Water Supply Company, via township LAROs, held meetings with affected villages, village committees and villager representatives concerning distribution of the compensation funds. Regarding the 30 mu permanent acquired land within Wuyanjing Village for the plant construction, with agreement of more than 2/3 villagers, it was decided to readjust the remaining 258 mu farmland within the village group equally and pay the land compensation and resettlement subsidy to every household within the group. While for the

35 rest 18 mu permanent land in the 9 villages of Liuge and Zhifang Towns acquired for construction of wells and pumping stations, the APs did not agree to readjust land but would like to obtain the compensation for profit-getting self investment. The compensation funds will be fully distributed to the affected farmers as well as the indirectly affected people after land readjustment through the village committees. Each transaction will be registered.

5.2.2. The task of Rehabilitation

114. The task of the rehabilitation is to ensure that the income of all the APs is restored to at least the present level. Training programs will also aim to further boost incomes on a sustainable basis and to assist the poor in moving out of poverty (see also paras 117 and 118).

5.2.3. Standards for rehabilitation

115. According to the ADB resettlement policies and the requirement of State laws, the APs should be safeguarded to get benefit from the project without their living halted. Living standard and condition will exceed the level before the project to achieve the goal of rehabilitation.

5.2.4. Agricultural rehabilitation plan

116. Despite the land acquisition will not have much impact on the affected villages, the directly affected land contractors shall be influenced relatively more. Accordingly, the LARO discussed with the relevant village committees and consulted fully with the directly and indirectly affected land users on the utilization of the compensation fund and the rehabilitation of agricultural production. Following consensus were reached on rehabilitation measures.

i) Readjust land. As a result permanent land acquisition, the 83 APs from 18 households in Wuyanjing Village affected by the 30 mu land acquired for the plant site lost 33% of their irrigated land (see Table 3-2). The village committee will organize to readjust the land within the whole village group before construction to ensure the relatively balanced possession of arable land. Thus the other 179 persons from 52 households of the village group were also affected. Consequently, all 262 persons from 70 households of the village group will receive a relative portion of the total compensation fund. With a total of 258 mu land readjusted for the 70 households, each household will lose about 10.4% of their land. ii) Cash compensation. Villagers meeting has been held by the village committee on the allocation of the fee to make up the loss after land readjustment. Further meetings and discussions are needed to reach final agreement. iii) Adjust the agricultural structure. After the land is reduced, the affected persons shall be helped to increase the average yield by adjusting the agricultural structure. Such activities will also increase income per unit area of land and thereby offset the result of permanent land loss.

5.2.5. Non-agricultural rehabilitation plan

117. Develop the third industry. According to the advantages of each affected village, the affected persons shall be encouraged to engage in transportation, breed aquatics, processing industry and other business services to increase income.

36

118. For the affected people, appropriate training will be provided on breeding, edible mushroom plantation and machinery operation. This will broaden their employment opportunities, and enhance their abilities to gradually engage in non-agricultural work for which greater opportunities exist. About more than 100 employment opportunities shall be provided to both directly and indirectly affected persons (APs), with priority given to the directly affected persons, in the construction of the project.

5.2.6. Measures for the income rehabilitation

(i) Measures for the income rehabilitation

119. After permanent land acquisition, the land left shall be readjusted within villages or groups, compensation fund shall be allocated to affected people for income rehabilitation.

120. Following measures shall be carried out to recover the income loss: i) enhance technical training; ii) adjust sector structure and encourage scientific farming; iii) develop breeding and aquatics; iv) encourage to participate in processing industry; v) help to seek working opportunities.

(ii) Training Measures

121. The affected persons will get compensation after part of their land is lost or damaged, but if they want to exceed their present income before the project, they must develop new skills and create new economic opportunities. To provide training for the APs is the best way for them to maintain and develop their livelihoods. Both directly and indirectly affected persons can take part in the training at no cost to themselves and the training fee will be met by the Water Supply Company. According to the former Resettlement Plan, several training programs have already been conducted on livestock breeding, planting, growing mushrooms, and skills development in plumbing, electric welding, and business management for the APs originally planned for the construction Scheme 2. Some of the APs from Liuge Town have participated in the trainings. For the new APs, as well as including APs from Liuge Town, further training programs are planned as below.

37 Table 5.1: Labor Skills Training Measures

Cost Number Training Training Training (ten Training Place Trainer Trainees of Date Method Scope thousan Trainees d Yuan) The skills 1st –15th breeding Centralized Affected December Jingmao hotel Li Bo 180 pigs, 1.3 study persons 2007 chickens, ducks 4th-11th Planting skills Centralized Shao Affected Jingmao hotel 60 on garden 1 Feburary study Wuxian persons 2008 plants 7thMarch- Centralized Shen Affected Plant 1st April Jingmao hotel 190 1.5 study xianyou persons mushroom 2008 th th plumber’s 14 -20 Centralized Wang Affected Jingmao hotel 60 mate, electric 2 April 2008 study Zhangwen persons welding Meeting room 1st to 7th of Qingfeng Centralized Zheng Affected Business 320 6 May 2008 County Power study Yueqiang persons management Supply Bureau Total 810 11.8

5.3.6. The employment during construction period

122. The people who have the ability to work or the skills or who are competent for the suitable work after training will get priority to work for the water supply project during construction period.

5.4. Women and Vulnerable Groups Rights Protection

123. In the scope of land acquisition, we have not discovered the single woman-headed households caused by divorce, losing spouse and being abandoned or elders. In the affected area, the female has the same right as that of male. It includes cultivating, education, family planning, and village election, and etc. Most woman labor interviewed thought they had the same production and business right as that of men, such as doing the part-time job or doing tiny business or doing the farm work. Of course, there is a different division between male and female in the housework and production. The women will tend to choose the housework, farm work, handwork and native and specialty business, while more young people choose to make a living at coastal areas.

124. The construction and land acquisition of the Project will not have obvious or extra influence on the women whose land is expropriated.

6. Institutional and Organizational Structure

6.1. Institutional Framework

125. In order to ensure the successful operation of the resettlement, the organizations

38 responsible for planning, controlling, execution and supervision of the RP are listed as follows: (i) Qingfeng water supply project resettlement Leading Group and Office (ii) Qingfeng water supply plant (iii) Zhifang Town and Liuge Town resettlement Office (iv) Village Committee Resettlement Leading Team (VCRLT) (v) Relevant Government Functions (vi) Project Design Institute (DI) (vii) External Independent M&E Agency (MEA)

6.2. Institutional Framework and Responsibilities

(i) Qingfeng WSP Resettlement Leading Group and Office

126. It is comprised of Qingfeng County Government, finance bureau; government office, planning office, Construction Commitment, Environment Bureau and Water Affair Group, and etc. There is sub-office set in finance bureau belonging to leader team; this office is responsible for enhancing leadership of the project, formulating resettlement policy and coordinating the organizations. It is the responsibility of government to manage the project, make decision on important matters, coordinate the organizations direct the project; make project progress favoring. The office is responsible for making contact with project offices of province and city as well as ADB, and arranging project works specify, and compiling the schedule of project.

(ii) Qingfeng water supply plant

127. Qingfeng water supply plant Leading Group and Office are responsible for demolition, compensation, and carrying out resettlement work, maintenance of the affected person’s right, prompting their livelihood restoration and development. Its main responsibility covers: z constituting resettlement policies of land acquisition and demolition z entrusting DI to define the scope of affected area and to investigate the date of demolition and at the same time reserving dates. z application for land using & land construction licenses z training for the main resettlement cadres of the resettlement office. z formation and execution of resettlement plan z responsible for implementation and schedule z taking charge of and checking the internal supervise activities, and compiling the resettlement report z dealing with the disputation and problems occurred during the execution.

(iii) Liuge Town and Zhifang Town Resettlement Office

128. To set up resettlement office in Liuge Town and Zhifang Town with main functions to fulfill the compensation and resettlement policies and promote the work of land acquisition and resettlement.

129. Its duties mainly cover: z participating in the socioeconomic investigation of project and project impact survey z propagating the resettlement plan among the public z distributing land and organizing resettlement of production and exploitation z disbursement and management of land compensation fund z express the suggestions to the higher level departments for the APs

39 z to report resettlement implementation schedule z offer assistance to the underprivileged families.

(iv) VRLG

130. VRLG is made up of village committee, villager team made of APs, affected families and villager representatives. Its duties mainly cover: z participating in the socioeconomic reject influence investigation z organizing negotiation of public, propagating land acquisition policy among the public z distribution of land acquisition compensation fund and organizing rehabilitation activities z expressing the suggestions to higher level departments for the villagers z reporting on resettlement progress z offer assistance to the underprivileged families.

(v) Relevant Government Agencies

131. The Government Functions mainly cover commerce and business association, audit bureau, supervise bureau, and state land resource bureau. Such government departments shall offer assistance to the resettlement. Its duties mainly cover: z participating in preparation and review of resettlement plan z supervising and urging compensation fee can be give in time z implement training schedule z coordinating the affected facilities during the construction.

(vi) Project Design Institute

z reducing the projection influence via optimizing design z determining the scope of land acquisition impact z assisting to compile RP z offering TA to municipal project office while the data investigation and process concerned

(vii) External Independent MEA

z offering the advice for land acquisition and resettlement z monitors RP and its implementation and submits report to the Municipal Project Office and ADB as the independent supervision institute

6.3 Staffing

6.3.1. Staffing for the Resettlement Institutions

132. In order that the resettlement will operate successfully, the preparation office with each IA and relevant organizations involved in the resettlement implementation at various levels was assigned competent and devoted staff to form a channel for the free flow of information from bottom-up. The staff of resettlement organization will be made up of professional technicians and managements who possess the special managements and resettlement & relocation experiences. A special resettlement organization with professional technicians provided has been set up in 2007.

40

Table 6.1 Staffing of Resettlement Organization

Total No. of Resettlement No. of Full-Time Resettlement Staff Personnel Working Schedule organization Resettlement Staff During Peak Resettlement leader 7 15 Relative government leaders Start from July 2004 team Water Supply 6 12 Engineers and assistant engineers Start from July 2004 Company Acquisition and resettlement office 3 5 Director, operation cadre men Start from June 2007 in each town Planning department of 3 5 A department director and two staff Start from June 2007 construction commitment

Village committee director, Village committee 5 10 Start from June 2007 accountant, and team leader

External monitoring Professor, engineer, doctor and and evaluation 3 6 Start from May 2008 master agency

Total 29 57

6.3.2. Staff training of resettlement agency

133. Qingfeng Water Supply Company organized the relevant resettlement staff to have training on resettlement policy from August to September 2004. Further training was provided from July to September 2007 regarding new regulations and implementation procedures.

6.2. Measures to Strengthen Institutional Capacity Building

(1) Staffing Enhancement. All organizations are made up of professional technicians and administration personnel who possess the professional knowledge and management quality. (2) Training Enhancement z Major staff training and understanding of China state resettlement policies and the requirements of ADB. z To organize resettlement staff training so as to improve the operation quality and policy handling ability. (3) Ensuring sufficient capital and equipments so as to develop the working efficiency. (4) Establishment of perfect bonus-penalty measures concerning the demolition and resettlement so as to boost the performance of the staff. (5) Data base establishment and information feedback enhancement so as to guarantee the successful delivery of information. Meanwhile, the major issues shall be handled by resettlement leading group. (6) Enhancement of report system and internal supervision so that the problems can be settled soon. (7) Establishment of external independent M&E institute as well as the pre-warning system.

41

7. Public Participation and Consultation

7.1. Public Participation

7.1.1. Resettlement Information Brochure (RIB)

134. QFWSC has compiled and issued a brochure (Chinese) to APs according to the resettlement policy and entitlement model to inform them that: (1) applied policies and regulations, (2) entitlement, and (3) the plan to restore income and living standard after land acquisition and the brochure is to strengthen transparency. The brochure includes: I1) the necessity and feasibility of QFWSP, (2) the construction content and scale, (3) the affected scope and the check methods of ground attachment and deadline, (4) the compensation standard of ground attachment and the process and ways of drawing the compensation fees, (5) ADB’s resettlement policies and related laws and regulations of PRC, (6) the calendar of project resettlement, (7) the necessity of public participation, (8) grievance redress procedures, and (9) the roles and responsibilities of resettlement agencies.

135. The brochures have been handed to all the APs in September 2007, meanwhile, the copies were sent to the local government and village committees located in the affected areas.

7.1.2. RP Distribution

136. This updated RP was handed to all the affected villages in November 2007. Any affected person who wants to know the plan can get the access to the information in the villages. If there is any revision of the RP concerning the APs, relevant contents of revision shall be forwarded to the affected villages. The IA office will keep copies of the Chinese-version RP.

7.1.3. Public Consultation in Project Preparation Phase

(i) The approach of public participation and negotiation • Propagandize participation through village committee • Hand out the survey sheets of compensation for land acquisition • Hold the meeting of public representatives • Public can take their initiative to consult with the resettlement organization

(ii) The method of public participation

1) The resettlement office in each village held conference according to the actual progress of the land acquisition, such as information disclosure meeting, policies promulgating meeting, socioeconomic survey, compensation and resettlement and so on, to make public know the ongoing situation, and to propose requests and suggestions. The resettlement office reflected the public’s opinions faithfully. 2) The resettlement office of Water Supply Company held consultation meetings for affected persons, hearing the opinions of the public face to face, and feed back the situation of information releasing. 3) The project office of Water Supply Company conducted socioeconomic survey and family baseline survey and to register the loss of APs and understand their conditions and impacts. 4) Handing out the questionnaires, and let public provide responses.

42 5) Publicizing the compensation policies, standards of land acquisition and the approach of drawing compensation fee. 6) Publicizing Grievance Redress telephone number, agency and principal.

137 The above consultation activities were completed by October 2007.

7.1.4. Public Participation and Consultation during Project Implementation 138. During the implementation of RP and after the compensation payments are made, services will be continued, to keep abreast of the adaptation of APs, to ensure the APs are compensated adequately, and to ensure APs do not lose their rights and interests, and that their livelihoods can be maintained. General public awareness was/shall be addressed including:

(i) in June 2007, publicized the calendar of schedule of implementation. (ii) in March 2008, publicize the place, time and procedure for drawing the compensation fee for land acquisition and relocation. (iii) in May 2008, publicize the final affected scope, the names of affected persons and property lost, compensation standard and fund, and accept the supervision of the public. (iv) in June 2008, follow-up the allocation of compensation fee within the village (v) in June 2008, let the supervision agency investigate and review the livelihood of resident after the project land acquisition. (vi) in August 2008,have an informal discussion with the public to hear the opinions and suggestions of the public and to correct any deficiencies in work. (vii) in October 2008, visit the public to find the remaining problems to be solved.

7.2. Grievance Redress Procedures

7.2.1. Targets for Grievance Redress Procedure

139. In order to safeguard the relevant personnel and have proper resolutions to the issues on land acquisition and resettlement, the detailed grievance redress procedures have been established to guarantee the relevant persons’ opinions about the project can be solved fairly, properly and rapidly. The procedure is simple, feasible, open, and fair. In the long view, it aims to prevent APs from forcedly resorting to complicated formal channel to express grievance and opinions. The aim is to redress relevant persons’ grievance or opinions within the project management organizations, which minimizes impact on project progress and makes the redress process more efficient as well.

7.2.2. Grievance Redress Approaches

140. In order to safeguard benefit and property of relevant enterprises and individuals from damaging, their opinions and grievance redress should observe the following approaches: z Step 1. Any individual or enterprise who is dissatisfied with the resettlement plan or implementation should propose the verbal or written suggestions to the related resettlement office of village or town, it should be solved within 2 weeks. z Step 2. Any individual or enterprise who is dissatisfied with the reply of the step 1, they can it hand to the land acquisition offices water supply plant after receiving the reply, the office will give the reply within 2 weeks. z Step 3. Any individual or enterprise who is dissatisfied with the reply of the step 2, after received the reply of land acquisition office, they can propose to the resettlement leader team or state land resource bureau, to ask for administration

43 arbitration agency, the administration arbitration should arbitrate within 10 days, z Step 4. If any individual or enterprise who is dissatisfied with the administration arbitration of the administration arbitration agency, he can go to the Civil Affairs Count according to the code of civil law.

7.2.3. Grievance Redress Scope

141. The APs can dispute all aspects of resettlement and payment of compensation including the compensation amount. They are informed of the procedure through the resettlement information brochure. Also this information can be delivered to the APs via public meetings preceding land acquisition.

142. During the whole course of project construction, the grievance redress procedures are still available for safeguarding the villagers utilizing these to handle the issues regarding the infrastructure rehabilitation, such as irrigation, the entrance of usual roads, temporary utilization of land and the like. Thus, villages can propose the problems to the management agencies in an effective way for timely solution.

Figure 7: Grievance Redress Procedure

Municipal, County People’s Henan Provincial PMO Court

Monitoring and Municipal, district City project office Evaluation Institute discipline inspection

Municipal, district Project leader team Grievance Redress

Village committee

Households who are resettled and compensated

44 8. Monitoring and Evaluation

143. In order to implement land acquisition and RP strictly due to demands, regular M&E should be carried out in the implementation stage. The M&E on RP can be divided into two parts: internal and external M&E.

8.1. Internal M&E

144. The Leading Group, relevant functions and project preparation sector are responsible for the internal M&E with internal monitoring office of 3 persons in the preparation sect to carry out internal M&E safeguard timely resettlement due to project plan and to protect APs’ benefits.

8.1.1. Main Monitoring Contents z Compensation Payment. z Grievance acceptance. z Income restoration/ training plan. z Assistance to vulnerable groups.

8.1.2. Internal Monitoring Objectives z Inspecting the completing progress of land acquisition and demolition. z Safeguarding the establishment and being straightway communication and coordination channels between the project management personnel and the APs. z Safeguarding compensation payment for the APs full and punctual. z Ensuring the APs’ grievance being handled in the given time. z Strictly ensuring compensation payment for land loss to the APs and provision of resettlement subsidy due to rules and regulations.

8.2. External M&E

145. The external M&E on RP should be carried out by an organization or institution which is extremely independent of project executing agencies and local government. The project EA has engaged an independent institution to take charge of external M&E by means of bidding invitation.

8.2.1. External Monitoring Objectives z Confirming whether APs’ welfare is restored or maintained after completion of land acquisition and demolition. z Identifying the restraints in policy and implementation if no restoration or maintenance. z Evaluating the general efficiency, result, impact (APs’ behavior reaction included) and the sustainability of land acquisition and demolition policy and practice.

8.2.2. Means and Methods

146. The general method is monitoring the activities, evaluating project impact and safeguarding public participation of all the APs, especially of women and vulnerable groups. The monitoring tools include both qualitative and quantitative ones: z The baseline survey on the affected households is a representative sampling survey, which categorize due to gender and vulnerable groups to get relevant information of

45 main indicators such as compensation distribution, efficiency, validity, impact, sustainability and etc. 20% of the APs were taken as random samples. z Group discussion allows consultation from every related party of M&E stakeholders (local government, host site personnel, NGO, community leaders and affected groups). z The talks with key persons, visiting the significant persons with relevant experience in land acquisition, resettlement and implementation such as local leaders, village leaders. z Community public meetings: Holding the public meetings in the resettlement site, and explicating the information on the demolition resettlement. z Direct Structural/objective observation: Carrying out field study on the implementation of demolition and resettlement and cross-visiting the individuals and groups for the messages. z Informal survey or dialogues: Adopting non-sampling way to carry out informal survey on APs, main villages, workers, resettlement staff and those of executing agencies.

8.2.3. Reporting Requisition

147. The result of the internal M&E should be reported to the IA quarterly.

139. The internal M&E reports on project half-completion and total-completion should comprise evaluation reports on project key points, detailed interpretation of compensation payment and other measures to maintain or increase a little APs’ socioeconomic situations in “no project” state. And moreover, the experience and lessons from the land acquisition and resettlement should be included in the report for policy and method formulation in the future.

148. During the process of RP implementation, the external M&E institution should compile and submit M&E reports to ADB once half a year and then it should compile socioeconomic survey and evaluation reports every year until the APs’ livelihood was fully restored.

8.2.4. Resettlement M&E Outline

149. See Table 8.1 for resettlement M&E outline.

46

Table 8.1: Resettlement M&E Outline

M&E Types of M&E Indicators Institution M&E ·Has the capacity building and training activities been carried out as planned? Budget and ·Has resettlement implementation being completed due to the negotiated time frame implementation schedule? ·Has the compensation fund be paid to the resettlement office on time? ·Has all the land for project construction been acquired or occupied?

Delivery of ·Have all the APs got their entitlements as stipulated in Entitlement Matrix? AP ·Have the APs received compensation fee on time? Entitlements ·Has the income and livelihood rehabilitation been carried out as planned? Internal M&E ·Has the consultation been carried out as planned? Is the RIB ready to be Consultation, distributed to APs? Grievance ·How many APs know about their rights? How many APs know whether and special they are entitled to the rights? Issues ·Has any AP used grievance redress procedure? What is the result? ·Has the problem been solved? ·Has the APs’ income and expenditure pattern changed compared to that before the subproject was carried out? Effect M&E ·Has the living expense of the APs changed? Does their income match to the changes? Basic ·location, householder, nationality, housing types Information ·family member, structure, ages, education background and technical skills on Affected ·land and other resources owned and the usage pattern of those resources Households ·income source and level, occupation and employment type Restoration of living ·Whether do the APs obtain main substitutes in culture and society? standard ·Has the compensation fee been discounted due to depreciation and discounts? ·Is the compensation fee enough for the APs to recover their lost assets? ·Have the affected enterprises received enough compensation to Restoration reconstruct the enterprise? External of livelihoods ·Have the farmers been provided with opportunity to profit getting? Are the M&E measures effective and sustainable? ·Have the APs regain their living standards after the resettlement by using the proposed rehabilitation measures? ·How much do APs know about the resettlement process and their entitlements? Levels of AP ·How do APs assess their living standards and livelihood after the Satisfaction rehabilitation? ·Do the APs know about the grievance redress procedure and conflict solving approaches? ·Have the APs and their possessions been correctly recorded? Effectiveness ·Have the time frame and budget been carried out sufficiently? of the RP ·How does the IA deal with contingencies?

47 9. Resettlement Budget

150. The costs incurred by land acquisition and resettlement are included in the overall budget of the project. The total cost of land acquisition and resettlement for Qingfeng Water Supply Treatment Project is estimated to be CNY 4.65 million.

9.1. Contents of Resettlement Costs

9.1.1. Land Acquisition and Resettlement

(i) Compensation for Ground Attachment

151. According to the project plan and the contract signed between Water Supply Company and County Land Administrative Bureau as well as the agreement signed with village committees, the permanent land acquisition of this project is 48 mu, along with the compensation for this consists of land compensation, resettlement subsidy, compensation for standing crops, arable land reclamation, land use cost for augmenting construction land and management cost which amounts to CNY2.46 million.

(ii) Compensation for temporary land use

152. The construction of pipeline network for water supply will use 731 mu farmland and the compensation for standing crops plus land recovery cost amounts to CNY1,430/mu. Totally it amounts to CNY1.05 million. For construction of pipeline networks, another 81 mu (54000 square meter) urban road shall be temporarily occupied, the recovery of which shall be the responsibility of the contractor. The cost for the urban road occupation including recovery fee shall be included in the construction fee paid to the contractor.

(iii) Farmland Occupancy Tax

153. The farmland occupancy tax for permanent land acquisition amounts to CNY160,100.

9.1.2. Compensation Cost for Infrastructure and Ground Attachments

154. Affected ground attachment is of 2 kinds with 2 items. For wells, there are 4 wells with CNY6,500 each; for the 10 tombs, it is 200 yuan/grave. The total compensation is CNY28,000.

9.1.3. Other Costs

155. The designing and reconnaissance costs are 2% of the land acquisition and resettlement.

156. The M&E costs are 2% of the land acquisition and resettlement.

157. The management costs are 3% of the land acquisition and resettlement.

158. The training cost is CNY334,000, in which CNY190,000 have been paid for the previous trainings held according to the former RP. Another CNY144,000 is planned for 5 times of further training classes for APs and 6 times training on resettlement for relevant staff.

9.1.4. Contingencies

48 159. Contingencies budgeted are 15% of the total cost of land acquisition and rehabilitation, of which 10% is physical contingency for the purpose of various costs owing to the changes of qualities in the course of resettlement; 5% is price contingencies for currency inflation and any prices changes during the resettlement.

9.2. Budget Table on Resettlement Costs

160. The land acquisition and resettlement cost budget of Qingfeng Water Supply Project is shown in Table 9.1. Table 9.1: Resettlement Budget

Type Unit Quantity Compensation Budget Rate (Yuan/unit) (CNY10,000) A. Land Acquisition and 366.77 Resettlement i) Permanent land 246.23 acquisition compensation and mu 48 32,500 156.0 resettlement subsidy compensation for standing mu 48 1,300 6.24 crops farmland reclamation fee mu 48 5,850 28.08 land use fee for augment mu 48 10,672 51.23 construction management fee for land mu 48 975 4.68 acquisition ii) Farmland occupancy tax mu 48 3,335 16.01 iii) Temporary farmland use1 mu 731 1,430 104.53 B. Facilities and Ground 2.80 Attachments (2 kinds with 2 items) i) Facilities (1 kind with 1 item) wells ea. 4 6,500 2.60 ii) Ground Attachments ea. 10 200 0.20 Subtotal of A and B 369.57 C. Other cost 59.09 Reconnaissance and 2% 7.34 design M&E 2% 7.34 Administrative fee 3% 11.01 Training cost 33.4 D. Contingency 55.08 Physical contingency 10% 36.72 Price contingency 5% 18.36 E. Total 483.74

1 The cost for the 81 mu (54,000 square meters) temporary use of urban road shall be included in the construction fee paid to the contractor. See Para 152.

49

9.3. Resettlement Investment Plan

161. Details can be seen in Table 9.2.

Table 9.2: Resettlement Investment Plan

Investment by fiscal year (CNY10,000) Item Investment 2007 2008 2009 2010 A. Compensation for land acquisition 246.23 246.23 B. Compensation for infrastructure 104.53 8.00 89.53 7.00 C. Facilities 2.80 2.80 D. Other cost 40.09 3.90 15.68 5.32 15.19 E. Contingencies 55.08 2.00 25.00 28.08 F. Relevant tax 16.01 16.01 Gross investment 483.74 3.90 290.72 119.95 50.27 - Proportion 100.00% 0.84% 62.55% 25.81% 10.82%

10. Implementation Arrangements and Schedule

162. As the schedule of the water supply project will commence in April 2008, the progress of resettlement implementation shall be confirmed to be in conjunction with the project construction schedule.

10.1. Principles on Confirming Resettlement Schedule

z The scope of land acquisition and demolition should be eventually determined prior to the measurements and calculation in land acquisition and demolition and according to final engineering plan. z The land acquisition should be prior to the constructions of each area. z The labor settlement should be finished prior to the land acquisition. z The calculation and allocation of the compensation should be done before land acquisition or demolition and after agreement signed.

10.2. Overall Schedule of Land Acquisition and Resettlement Activities

163. The overall schedule of land acquisition and resettlement activities is prepared according to the schedule of land acquisition and resettlement preparation and implementation. See Table 10.1 for the overall schedule.

50 Table 10.1: Schedule of Land Acquisition and Resettlement Activities

标识号 Land Acquisition and Resettlement Activities 2008 2009 2010 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 1 A. land acquisition and compensation plan 2 DMS on the affected area 3 Application for approval of land acquisition licence 4 Identification and confirmation 5 of the poor and vulnerable groups in the Aps 6 Confirmation of compensation and resettlement plan 7 Signature of compensation contract 8 B. land acquisition and resettlement 9 Provision of compensation fund 10 Readjsut land 11 C. Income Restoration 12 Employment the Aps into the Project 13 Training for Reemployment 14 Other income restoration plan 15 D. M&E 16 Establishement of internal M&E mechanism and procedure 17 Recruitment of external MEA 18 ADB抯 approval TOR 19 Training of Resettlement Staff 20 M&E on resettlement activities 21 M&E on income restoration plan 22 External M&E conduction

51

Appendix 1 Map of Qingfeng Water Supply Plant and the Water Source

Note: The 24 wells are marked as from No. 1 to No. 24. The water conveyance pipelines shall be constructed along the road and connecting the wells. 52

Appendix 2 Social-economic Status of the Affected Villages in 2006

Total Liuge Town Zhifang Town

Wuyan Xizhao Mei Hao Zhange- Nie Luojia Bianjia Zhifang -jing -dian -zhuang -zhuang zhuang -zhuang A. Total population (persons) 1132 2630 1527 1713 638 678 2552 2035 3625 16530 B. Total household (households) 323 751 436 489 127 150 561 382 730 3949 C. Laborers (Number 709 1648 956 1074 404 431 1685 1363 2423 10693 1) farmers (person) 418 971 564 633 215 253 564 723 896 5237 2) construction labor(person) 121 281 163 183 33 55 144 155 270 1405 3) transportation (person) 6 14 8 9 28 34 146 74 251 570 4) industry 14 31 18 21 16 10 378 126 591 1205 5) commerce 79 185 107 120 34 42 268 159 181 1175 6) other industry 71 166 96 108 78 37 185 126 234 1101 D. Farmland area 1132 3145 1900 1791 836 1081 1993 2353 3841 18072 E. Gross income per capita (yuan) 3033 3124 2815 2887 2307 1971 4464 3325 3958 3400 1) agricultural (yuan) 517 591 615 517 569 640 510 547 580 561 2) construction (Yuan) 570 540 560 525 0 0 563 528 689 534 3) transportation (Yuan) 80 103 55 67 0 0 850 371 637 350 4) industry (yuan) 162 214 160 153 260 274 941 672 848 511 5) commerce (yuan) 1010 1107 910 934 620 655 1025 677 641 859 6) other industry (yuan) 694 569 515 691 858 402 575 530 563 584

53 Appendix 3 Social-economic Survey of the Affected Households No. Nos of Annual income In which, Area of land family (CNY/person) Town Village Householder labours Other employment acquired members Agricultural Other (persons) (mu) (persons) income income Liu Dianqing 4 2 Building construction 520 2575 1.4 1 Han Chaoliang 6 4 Building construction 520 2580 2.1 2 Zhang Shegang 5 3 Decoration 520 2630 1.75 3 Zhang Zigang 5 3 Transportation 520 2800 1.75 4 Zhang Xiangang 5 2 Transportation 520 2700 1.75 5 Zhang Jinzhong 4 2 Odd jobs 510 2700 1.4 6 Zhang JIngang 4 2 Food selling 525 2750 1.4 7 Zhang Heshan 6 4 Odd jobs 530 2700 2.1 8 Liu Junfang 5 3 Odd jobs 540 2700 1.75 9 Han Yufeng 4 2 Building construction 525 2650 1.4 Wuyanjing 10 Han Ruiqin 6 4 Building construction 510 2650 2.1 11 Han Ruiqing 5 3 Building construction 520 2650 1.75 12

Liu Zhaofeng 6 4 Building construction 535 2700 2.4 13 Liu Chunling 5 3 Odd jobs 540 2650 2.0 14 Liu Baoan 3 2 Building construction 520 2600 1.2 15 Liu Lanting 2 2 -- 530 2800 0.8 16 Liuge Liu Zhongfeng 3 2 Decoration 525 2700 1.2 17 Liu Yunfu 5 3 Transportation 530 2700 1.75 18 Subtotal of permanent land acquired 30 Chen Hebin 5 3 Building construction 530 2512 1.0 Xizhaodian 19 Liu Bao’an 5 3 Chicken breeding 507 2558 0.8 20 Luo Chaobang 5 3 Odd jobs outside Town 600 2545 1.0 21 Chen Shoubin 4 3 Odd jobs outside Town 584 2780 0.8 22 Luojia Luo Shegang 4 2 Highway construction 555 2800 1.0 23 Luo Chao’en 4 2 Electrician 598 2750 0.8 24 Liu Xianfu 5 3 Odd jobs outside Town 300 3100 1.0 25 Wang Engong 4 2 Swine breeding 600 2630 1.0 Bianjia 26 Deng Shewei 3 2 Hardware selling 603 2850 0.8 27 Zhou Wenyou 5 3 Printing service 500 4400 0.8 Zhifang 28 Li Zhiqiang 6 4 Fishery 520 4100 0.8 29 Lu HOngyu 4 2 -- 490 4000 0.8 30 Lu Hongfu 4 3 Transportation 510 3980 0.8 31 Zhanger- Ge Shikun 2 2 Food processing 505 4100 1.0 32 huang Wang Gangxian 4 2 Building construction 530 3950 0.8 Zhifang 33 Lu HOngguo 5 3 Brick plant 570 4200 0.8 Niezhuang 34 Lu Hongjun 3 2 Brick plant 570 4200 0.8 35 Deng Chuan 4 4 Odd jobs outside Town 570 2750 0.8 Meizhuang 36 Mei Jianwei 4 2 Small business 568 2890 0.8 37 Gao qingbo 2 2 Transportation 650 3000 0.8 Haozhuang 38 Hao Youming 6 3 Building construction 660 2900 0.8 39 Subtotal of temporary land acquired 18

54 Appendix 4 The Staff of Resettlement Leading Group

Education Personnel Sex Current position Duty in this Project Background

Lei Jipu male manager team leader junior college

Gao Xufeng vice manager vice team leader junior college

vice team leader; Zhang Junfeng male vice manager director of junior college resettlement office

Wang Yuefa male accountant staff accountant

vice chief of Zhang Fangbing male comprehensive affairs staff junior college office vice chief of Liu Mingqiang male comprehensive affairs staff senior high school office

55