Form-1

Expansion Project of Miter & Miter Engineers Pvt. Ltd. (Introduction of PU Foam Components)

at Plot No.: 04, Sector- 11,TML Vendor Park Sidcul, Rudrapur, District U.S. Nagar ()

Prepared By:

ABC Techno Labs Pvt. Ltd. (Accreditation No. NABET/EIA/70 001) B.O.-: CP 101, Nehru Colony, Dehradun-248001 (Uttarakhand) Ph.No-91+135-26522979, 09412058326

Form-I

APPENDIX I (See paragraph-6) FORM 1 (1) Basic Information

S.No Item Details 1. Name of the Project/s PU Foam Components icluding PU Steering Wheels by Miter & Miter Engineers Pvt. Ltd. 2. S. No. in the schedule Category B of activity 5 (f) 3. Proposed Capacity/area/ length/tonnage The plant is set up in land area of to be handled/ command area/lease area/ 8160m2, located at Plot No 04, number of wells to be drilled Sector- 11, SIDCUL, TML Vendor Park, Rudrapur, U. S. Nagar, Uttarakhand.

Presently unit is manufacturing Injection moulding, Plastic auto component, Rubber components 375 Lakh per annum, now the unit is planning to introduce PU foam components including PU steering wheels- 50,000 Nos per Month. 4. New/ Expansion/Modernization Expansion (Manufacturing of PU Foam Components) 5. Existing Capacity/ Area etc/ Capacity of Injection moulding, plastic auto component, rubber components will remain same and PU foam components manufacturing facility will be introduced which is presently purchased from open market. 6. Category of Project i.e. A or B Category B of Project Activity 5 (f) 7. Does it attract the general condition? if No yes, please specify. 8. Does it attract the specific condition? If No yes, please specify 9. Location Plot No 04, Sector- 11, IIE SIDCUL, TML Vendor Park, , U.S. Nagar, Uttarakhand. Plot/Survey/Khasra No. Plot No. 04 Village Pantnagar Tehsil Rudrapur District U.S. Nagar State Uttarakhand 10. Nearest railway station/airport along with Railway Station Rudrapur (10km) distance in kms. (12 km) 11. Nearest Town, City, District Headquarters Rudrapur along with distance in kms. 12. Village Panchayats, ZillaParishad, Rudrapur municipal Corporation, Local body (

M/s Miter & Miter Engineers Pvt. Ltd. (2.) Form-I

complete postal Addresses with telephone nos. to be given) 13. Name of the applicant Mr. Nishchay Miterr 14. Registered Address 9, Cantonment, The Mall, Amritsar 15. Address for correspondence: As above Name Mr. Nishchay Miterr Designation (Owner/Partner/CEO) Mg. Director Address As above Pin Code 143001 E- mail [email protected] Telephone No. 0183-2562403 Fax No. 0183-2223522 16. Details of Alternative Site examined, if any No location of these sites should be shown on a toposheet 17. Interlinked Projects No 18. Whether separate application of NA interlinked project has been submitted 19. If yes, date of submission NA 20. If no, reason NA 12. Whether the proposal involves No approval/clearance under: if yes, details of the same and their status to be given. (a) The Forest (Conservation Act, 1980 (b) The Wildlife (Protection Act, 1972 (c) The C.R.Z notification, 1991 22. Whether there is any Government Order/ NA Policy relevant/relating to the site 23. Forest land involved (hectares) No 24. Whether there is any litigation pending No against the project and /or land in which the project is proposes to be set up (a) Name of the Court (b) Case No. (c) Orders/direction of the Court, if any and its relevance with the proposed project.

Screening Category: 5 (f) • Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease area and production capacity for mineral production, area for mineral exploration, length for linear transport infrastructure, generation capacity for power generation etc.)

M/s Miter & Miter Engineers Pvt. Ltd. (3.) Form-I

(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.

S.No. Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible)with source of information data 1.1 Permanent or temporary change in No No additional land/construction is land use, land cover or topography required for the commencement of PU including increase in intensity of land Foam Components manufacturing use (with respect to local land use facility. plan) The proposed activity will not result in any permanent or temporary change in land use, land cover or topography. 1.2 Clearance of existing land, vegetation No No clearance of existing land, and buildings? vegetation or building is required, as the proposed activity will be undertaken within existing plant premises. 1.3 Creation of new land uses? No As the proposed activity will be undertaken within existing plant premises, creation of new land use is not envisaged. 1.4 Pre-construction investigations e.g. Yes N.A bore houses, soil testing? 1.5 Construction works? No No additional construction works will be required in the project site for proposed project activity. 1.6 Demolition works? No No demolition works will be done in the project site for proposed enhancement. 1.7 Temporary sites used for No N.A. construction works or housing of construction workers? 1.8 Above ground buildings, structures or No N.A. land fill or excavations 1.9 Underground works including mining No N.A. or tunneling? 1.10 Reclamation works? No N.A. 1.11 Dredging? No N.A. 1.12 Offshore structures? No N.A. 1.13 Production and manufacturing Attached as Annexure-1 processes? 1.14 Facilities for storage of goods or Yes Separate store yard for storage of raw materials? materials (Polyol and Isocyanate), which shall be brought from supplier in sealed drums, stored in separate storage area near the manufacturing facility of PU Foam. Pre conditioning will be done for storage of drums in between 150C to 250Cand the area will

M/s Miter & Miter Engineers Pvt. Ltd. (4.) Form-I

be dedicated with sand bed to absorb any kind of spillage. 1.15 Facilities for treatment or disposal of No Waste generated from PU Foam will solid waste or liquid effluents be given to TSDF. 1.16 Facilities for long term housing of No The operational workers come from operational workers? nearby area. Hence no facilities are required for long term housing of operational workers. 1.17 New road, rail or sea traffic during No No, as the proposed activity will be construction or operation? undertaken within existing plant premises. 1.18 New road, rail, air waterborne or No No, as the proposed activity will be other transport infrastructure undertaken within existing plant including new or altered routes and premises. stations, ports, airports etc? 1.19 Closure or diversion of existing No No, as the proposed activity will be transport routes or infrastructure undertaken within existing plant leading to changes in traffic premises. movements? 1.20 New or diverted transmission lines or No No, as the proposed activity will be pipelines? undertaken within existing plant premises. 1.21 Impoundment, damming, culver ting, No No, as the proposed activity will be realignment or other changes to the undertaken within existing plant hydrology of watercourses or premises. aquifers? 1.22 Stream crossings? No N.A. 1.23 Abstraction or transfers of water form Yes Total water requirement shall be 12 ground or surface waters? KLD for industrial / domestic consumption only. No additional requirement of water in proposed process. This water requirement shall be met from existing tube well. 1.24 Changes in water bodies or the land No No effluent is being discharged to surface affecting drainage or run-off? water body as no additional requirement of water in proposed process. 1.25 Transport of personnel or materials No The workers and staff come to work for construction, operation or by their own means. decommissioning? 1.26 Long-term dismantling or No No long term dismantling or decommissioning or restoration decommissioning or restoration works? works will be done. 1.27 Ongoing activity during No N.A. decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in either No Influx of people in an area is temporarily or permanently? temporary as workers work during day hours only. 1.29 Introduction of alien species? No N.A. 1.30 Loss of native species or genetic No N.A. diversity? 1.31 Any other actions? No N.A

M/s Miter & Miter Engineers Pvt. Ltd. (5.) Form-I

2. Use of natural resources for construction or operation of the project (such as land, water, materials or energy, especially any resources which are non – renewable or in short supply): S.No. Information/checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information date 2.1 Land especially undeveloped or No The proposed activity will be agricultural land (ha) undertaken in the existing plant premises hence no extra land will be acquired. 2.2 Water (expected source &competing No Ground Water will be extracted from users) unit: KLD tube well. About 05 KLD fresh water is required (for Domestic/ industrial purpose). 2.3 Minerals(MT) No No minerals are being used as the proposed activity will be undertaken within existing plant premises. 2.4 Construction material – stone, N.A. No, as the proposed activity will be aggregates, and /soil (expected undertaken within existing plant source-MT) premises. 2.5 Forests and timber (source –MT) No No, as the proposed activity will be undertaken within existing plant premises. 2.6 Energy including electricity and fuels Yes Power supply from Uttarakhand Power (source, competing users) unit: fuel Corporation Ltd. connected load 300KW (MT), energy (MW) And at the time of power failure DG set of 500 KVA existing & 380 KVA DG set proposed for the proposed expansion. 2.7 Any other natural resources (use No N.A. appropriate standard units) 3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

S.No. Information/checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information date 3.1 Use of substances or materials, Yes Isocyanate is only hazardous chemical, which are hazardous (as per MSIHC which shall be used approximately-375 rules) to human health or the Kg./day (Polyol – 550 kg/day is Non environment (flora, fauna, and water Hazardous ). supplies) 3.2 Changes in occurrence of disease or No Proper precautionary measures will be affect disease vectors (e.g. insect or provided to workers to avoid any water borne diseases) hazard. 3.3 Affect the welfare of people e.g. by No Social development of the area will changing living conditions? increase and of the people involved. 3.4 Vulnerable groups of people who No Vulnerable groups of people are strictly could be affected by the project e.g. prohibited in nearby and inside factory hospital patients, children, the elderly area where the process is being done. etc. 3.5 Any other causes - -

M/s Miter & Miter Engineers Pvt. Ltd. (6.) Form-I

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

S.No. Information/checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information date 4.1 Spoil, overburden or mine wastes No N.A. 4.2 Municipal waste (domestic and or No Septic/Soakage pit for domestic waste. commercial wastes) 4.3 Hazardous wastes (as per Yes Hazardous waste as per schedule 1 Hazardous waste Management rules) (See rules 3 (1) category 33.3 discarded containers/barrels /liners contaminated with hazardous wastes/ chemicals will be sealed with proper sealant and then sent to TSDF for safe disposal. The area around the storage and chemical filling will be dedicated with sand bed. 4.4 Other industrial process wastes No Chemical containers 200 No/ annum (category 33.3 of schedule 1) shall be disposed through TSDF. 4.5 Surplus product No - 4.6 Sewage sludge or other sludge from Yes Septic/Soakage pit for domestic waste. effluent treatment 4.7 Construction or demolition wastes No Nil 4.8 Redundant machinery or equipment No Nil 4.9 Contaminated soils or other materials Yes Contaminated sand will be disposed to TSDF in sealed drums. 4.10 Agricultural wastes No Nil 4.11 Other solid wastes No Nil

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) Information/checklist confirmation Yes/No Details thereof (with approximate S.No quantities /rates, wherever possible) . with source of information date 5.1 Emission from combustion of fossil Yes Source of emission is one DG set (500 fuels from stationary or mobile KVA is existing & 380 KVA DG set is sources Proposed) as standby measure used only at time of power cut and is equipped with proper sound proofing and stack of 4.5 m & 4.0 m height above roof. 5.2 Emissions from production processes Yes The entire operations will be done in proper ventilated surroundings. 5.3 Emission from materials handling No The proposed chemicals will be kept in including storage or transport safe storage, properly handled and transported carefully. 5.4 Emission from construction activities No No additional construction work is including plant and equipment required. 5.5 Dust or odors from handling of Yes Odor from manufacturing process will materials including construction take place. material, sewage and waste Workers will be provided with mask and proper clothing to mitigate adverse effects. Following safety tools/equipment will

M/s Miter & Miter Engineers Pvt. Ltd. (7.) Form-I

be provided to workers:-

i) RESPIRATORY: Facemask with absorbent filter will be provided.

ii) VENTILATION: Proper ventilation with exhaust fans shall be provided.

iii) PROTECTIVE GLOVES: Chemical & heat resistant gloves will be provided.

iv) PROTECTIVE SHOES: Chemical & heat resistant shoes will be provided.

v) EYE PROTECTION: Goggles or safety glasses will be provided.

vi) OTHER PROTECTION: Chemical & heat resistant suit will be provided to avoid any hazard. 5.6 Emissions from incineration of waste No No incineration process is involved.

5.7 Emissions from burning of waste in No N.A. open air (e.g. slash materials, construction debris) 5.8 Emission from any other sources No N.A.

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S.No. Information/checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information date 6.1 From operation of equipment e.g. Yes It is expected that there will be no engines, ventilation plant, crushers increase in the noise level with the establishment of “PU foam manufacturing facility” in-house.

Noise level outside the plant is ranging between 40-50 dB (A) and in plant noise level ranges between 40-65 dB(A).The machinery involved in the proposed process will not produce much noise pollution. Besides, the process is done in properly designed shed. The workers in noisy zone will be equipped with ear muffs. 6.2 From industrial or similar processes Yes The noise levels within the existing facility for manufacturing unit will vary from 45 to 65 dB (A). The workers in noisy zone will be equipped with ear muffs. 6.3 From construction or demolition No Nil 6.4 From blasting or piling No Nil 6.5 From construction or operational Yes Proper maintenance of machinery

M/s Miter & Miter Engineers Pvt. Ltd. (8.) Form-I

traffic including transport vehicles is/ will be ensured and only vehicles with valid PUC certificate are/ will be allowed during operation. 6.6 From lighting or cooling systems No N.A. 6.7 From any other sources Yes One DG set (500 KVA) already exists & 380 KVA DG set is proposed as standby measure with proper acoustic enclosure.

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers surface waters, groundwater, coastal waters or the sea: S.No. Information/checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information date 7.1 From handling storage, use or Yes Proper sand bed and handling facility spillage of hazardous materials will be followed while chemical filling and storage. 7.2 From discharge of sewage or other No N.A. effluents to water or the land (expected mode and place of discharge) 7.3 By deposition of pollutants emitted to Yes The flue gases from DG sets (500 KVA & air into the land or into water 380 KVA) lay to atmosphere by suitable height of chimney. 7.4 From any other sources No N.A. 7.5 Is there a risk of long term build up of No N.A. pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the project, which could affect human health or the environment S.No Information/checklist confirmation Yes/N Details thereof (with approximate . o quantities /rates, wherever possible) with source of information date 8.1 From explosions, spillages, fires etc Yes • Calibration of safety valves and from storage, handling, use or gauges to be calibrated as per production of hazardous substances supplier’s manual to ensure any chemical leakage from the system. • A Fire Hydrant system of one lakh liter capacity is established with sprinkle facility. • Eye wash and shower will be provided near PU foam manufacturing area which is to be used by the operators in case of irritation.

8.2 From any other causes No N.A. 8.3 Could the project be affected by Yes The area under study falls in Zone –IV natural disasters causing according to the Indian Standards environmental damage (e.g. floods, Seismic Zoning Map. Design of the

M/s Miter & Miter Engineers Pvt. Ltd. (9.) Form-I

earthquakes, landslides, cloudburst structure of building/shed is as per etc)? latest I.S. Codes which are safe & stable under the gravity loads & designed for earthquake resistance.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality S.No. Information/checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information date 9.1 Lead to development of supporting. No N.A. as unit is operational utilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: • Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.) • housing development • extractive industries • supply industries • other 9.2 Lead to after-use of the site, which No N.A. could have an impact on the environment 9.3 Set a precedent for later No N.A. developments 9.4 Have cumulative effects due to No N.A. proximity to other existing or planned projects with similar effects

(III) Environmental sensitivity

S.No. Areas Name/ Aerial distance (within 15 km.) identity Proposed project location boundary 1 Areas protected under international N.A. National Corbett Park conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or N.A. Ind. Corbett Park sensitive for ecological reasons – 48 Km. from Ramnagar wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests 3 Areas used by protected, important N.A. Tanda forest Area or sensitive species of flora or fauna Ind. Area Rudrapur for breeding nesting, foraging, By Uttarakhand Gov. resting, over wintering, migration etc. 4 Inland, coastal, marine or N.A. N.A.

M/s Miter & Miter Engineers Pvt. Ltd. (10.) Form-I

underground waters 5 State, National boundaries N.A. 14.2 Km – UP/Uttarakhand/ Bilaspur/Dist. Rampur 21.8 Km Bahedi /Dist. 36 Km. Tanda / Bareilly 6 Routes or facilities used by the public N.A. NH 87 Dist. 14.5 Km. for access to recreation or other tourist, pilgrim areas 7 Defense installations N.A. N.A. 8 Densely populated or built –up area N.A. Town of Rudrapur, ,,Kalyanpur. 9 Areas occupied by sensitive man- N.A. City Hospital (05 Kms) made land uses (hospitals, schools, Police Lines (5.5 Kms) places of worship, community facilities) 10 Areas containing important, high N.A. • Agriculture Research Area (08 quality or scarce resources Kms) (ground water resources, surface • Bagha Eco Tourism Surai Forest resources, forestry, agriculture, Area(62 Kms) fisheries, tourism, minerals) • Ginger Hotel (2.2Kms) 11 Areas already subjected to pollution N.A. No such areas are present nearby or environmental damage. (those which is already subjected to where existing legal environmental environmental damage. standards are exceeded) 12 Areas susceptible to natural hazard N.A. No such areas are present. which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

M/s Miter & Miter Engineers Pvt. Ltd. (11.) Form-I

(IV). Proposed Terms of Reference for EIA studies

Ans. As per EIA Notification, 2006 Synthetic organic chemicals industry located in a notified industrial area/estate are categorized as B category industry of project or activity covered in 5 (f) and hence does not require EIA Studies.

“I hereby given an undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost”

Date: 04.02.2016 Place: Pantnagar Nishchay Miterr (Managing Director)

M/s Miter & Miter Engineers Pvt. Ltd. (12.)