Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Dehat, Road, Near Form I Project Address Sirondhan More, District , A

APPENDIX II FORM-1 A (Only for construction projects listed under item 8 of the Schedule)

CHECK LIST OF ENVIRONMENTAL IMPACTS (Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed Environmental Management Plan & Monitoring Programme).

1. LAND ENVIRONMENT Attach panoramic view of the project site and the vicinity 1.1. Will the existing land use get significantly altered from the project that is not consistent with the surroundings? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority are submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans.

The project is a logistic park located at village- Sikandrabad Dehat, Tehsil- Sikandrabad, District-

Bulansher, Uttar Pradesh. VRY2 Logistic Park LLP has proposed to develop the logistic park on a land measuring 79,476.63m for the storage of other than agro product. The project provides the warehousing facilities/logistics services to other parties. 79,476.63 sq.m.(19.63 acres) It is a logistic park and the revenue documents are attached as Annexure-II. sq.m. 11,921.49 sq.m. The project covers the plot area of with built-up area of 38961.16 Development of green area takes place over an area of Annexure III Annexure IV. The site layout plan is attached in and section elevation plan is attached as Annexure I. Surrounding features within 500 meters of the project site is attached as Site Location:

The site is located at Village Sikandrabad Dehat, Tehsil Sikndrabad, District Table 1. Bulanshahr, Haryana. NH-91Tableis adjacent1: Latitude to andproject Longitude site inof theSW Project. The coordinates Site for location of the projectS. No. are shown Descriptionin of Point Latitude Longitude

1. Corner 1 28.459763°N 77.716278°E

2. Corner 2 28.460715°N 77.720719°E

3. Corner 3 28.462710° N 77.718370°E

4. Corner 4 28.460979° N 77.715929°E source:5. Site visit by Team.Centre coordinate 28.461229°N 77.717863°E

Environment Aplinka Solutions & Technologies Pvt. Ltd, Uttar Pradesh 15 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Surrounding Features:

The surroundingTable 2: Surrounding features of Features the projec of thet site Project are presented Site in Table 2. S. Description Surrounding Features Aerial Distance & Direction No. from the Project Site

1 Nearby Village Sikandrabad Rural 0.41 Km in South East

2 Nearest Highway/ State NH-91 Adjacent to project site in SW highway

3 Nearest Railway Station Baral Railway Station Approx. 10 Km in NE

4 Nearest Airport IGI Airport Approx. 59 Km in W

5 Nearby Place of worship  Bhajan Lal Mandir  Approx 1.5 km in SW  Markaz Wali Masjid  Approx. 2 km in SW  Devi Mandir  Approx. 2 Km in E

6 Nearby Hospital  Rana Hospital  Approx 2 km in SE  Ivory Hospital  Approx 17 Km in West

7 Nearby School/ college Prem Inter College Approx 8 km in East  Baral 

I. P. College Approx 8 km in SE 1.2. List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc.

Area Requirements: 79,476.63 sq.m.(19.63 acres) sq.m. The project covers the plot area of with 11,921.49 sq.m. Table 3. built-up area of 38961.16 Development of green area takes place over an area of The brief area statementTable is –show3: Area in Statement Percentage of plot S.N. Particulars Are in sqm area

1 Total Plot Area 79476.63 Permissible Ground Coverage @ 55 of 2 Plot area 43712.15 3 Proposed Ground Coverage 35543.16 44.72 3(a) Ground Coverage of Ware House 1 1977.90 3(b) Ground Coverage of Ware House 2 23650.44 3(c) Ground Coverage of Ware House 3 9914.82 4 Proposed FAR @0.47 of plot area 37961.16 Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 16 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

4(a) Proposed Area on Ground 35543.16 4(b) Proposed area of Mezanine Floor 2418.00 5 Amenities Area 1000.00 6 Parking Area 7000.00 8.81 7 Proposed open Area 43933.47 8 Proposed Green Area 11921.49 15.00 9 Road/Paved area 25011.98 31.47 10 Builtup area 38961.16 11 Maximum Height Upto 15 meter from floor finished level Water Requirement: Operation Phase:

During the non rainy season; it is estimated that the total water demand during the operation phase will be approx. 45 KLD. The fresh water requirement for the logistic park is estimated to be approx. 45 KLD including horticulture, flushing and domestic. The fresh water will be taken from Private water tanker Table 4: The fresh water requirement, treated water requirement and total water requirement are shown in Table 4: Water Calculation for Non Rainy Season

Fresh water Fresh Total Waste Rate of for domestic Water water water water and for dema Gener Arae in demand horticulture flushing nd ation SN Description Sqm Occupancy (liter) (KLD) (KLD) (KLD) (KLD)

….. Staff …. 1 Population 300 30 2.20 6.80 9.00 8.56 …. ….. 2 Visitors 20 15 0.07 0.23 0.3 0.29 Total 38.04 7.03 45.06 8.85 3 Horticulture 11921.49 3 liter/Sqm 35.76 35.76 Approx. Total Value ~38 ~7 ~45 ~9

Source:(i) Manual on norms and standards for environment clearance of large construction projects, Ministry of Environment and Forests, Government of

Power Requirements:

The estimated load for the project will be approx. 1000 KVA which will be supplied by Paschimanchal Vidyut Vitran Nigam Limited. Details of D.G Set

There is provision of 4 DG sets of total capacity 980 kVA (1X 80+3X 300 kVA). The DG sets has been equipped each with acoustic enclosure to minimize noise generation and adequate stack Parking Requirements: height to minimize the emission. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 17 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Table 5 : Adequate provision has been madeTable for-5 vehicle: Parking parking Area Statement at the project site so as to allow smooth movement at the site. . The provision of parking at the site is shown in the

Total surface Parking Area 7,000 Sqm Number of 2 wheelers 606 Number of Cars 16 Number of trucks 20 Connectivity and Community Facility Requirement:

Community facilities like hospitals, school, place of worship, etc. are available in near vicinity of the project site. 1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site? (Such as open spaces, community facilities details of the existing land-use, disturbance to the local ecology).

No negative impact is anticipated of the activity on the existing facilities adjacent to the site. The project site is surrounded by barren land. Hence, no significant impact on land use is expected due to construction of logistic park. The area is free from any eco-sensitive zone. The project enhances the ecological condition of the adjoining areas due to development of extensive green belt within its premises. 1.4 Will there be any significant land disturbance resulting in erosion, subsidence & instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given).

The project will not involves significant change in land profile and disturbance in natural setting of the area. The project will not be disturbed the natural vegetation and have also facilitate in Soildeveloping type green area in the project site. The details of soil type etc are given below:-

: The soil is dominantly sandy loam with medium water holding capacity and slightly Seismicityalkaline. It is alluvial in nature and fertile.

: The area falls under seismic zone IV and susceptible to earthquake. All civil structures are seismically resistant and designed as per IS codes.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 18 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Project Site

Source:-Uttar Pradesh State Disaster Management Plan for Earthquakes

Figure 1: Seismic Zone Classification

Flood Plain: Slope Analysis: No incidence of flooding / water logging is envisaged by the project. The project has flat topography. 1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site)

The area can be categorized as a plain land as it is having relative relief of less than 5 meter. The project is not likely to alter or obstruct any natural drainage courses. There is no natural watercourse passing through the project site. Hence, the project does not involve alteration of natural drainage systems. As a result of excavation of topsoil during construction phase, the impact on drainage pattern, and run off characteristics will be restricted to the project area. Proper rain water drainage facility will be provided and the run-off generated will be storing in underground water tank & reusing. 1.6. What are the quantities of earthwork involved in the construction activity-cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site etc?)

During construction phase excavation will be done for foundation in the project. This excavated soil will be properly stacked within the site under tarpaulin cover which will reuse for Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 19 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

landscaping and backfilling. Hence no immediate adverse impacts on the land environment will 1.7. Give details regarding water supply, waste handling etc during the construction be envisaged. period.

20 KLD The water requirement during the construction phase comprises mainly of two parts i.e. fresh water for labourers and treated water for building constructions. It is estimated approx. of fresh water will be required for drinking purpose which will be imported in form of bottled 50 KLD cans from the local fresh water supplier during the days of construction. About of water will be required for construction purpose. The treated water requirement will be met by the treated water from the nearby CSTP, which will be brought by the private water tank. . The solid waste will be generated during the construction phase mainly comprise concrete washout cement residue, litters, packaging waste, masonry blocks, scraps etc The generated waste water recycled and re-used to raise the level of the site. Conclusively, as per the mitigation plan maximum re-use of construction waste will be done on site, non-reusable waste will remove from the site and its proper disposal will be done to reduce the impact significantly. 1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity).

The site is not the part of any low lying area or wetland. 1.9 Whether construction debris & waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal).

The Construction debris & waste during construction will not cause any health hazard. Construction debris will segregate and store in storage bins provided at the site for waste like steel scrap, shuttering wood, gypsum & sand and paint cans etc. The waste generated from the brick masonary, concrete etc. will be used for plinth filling and for sub base of roads. The toilets with septic tanks will be provided for the labours and site staff thereby avoiding any health hazard. 2. WATER ENVIRONMENT 2.1 Give the total quantity of water requirement for the proposed project with the breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement. Water Management:

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 20 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Operation Phase:

During the non rainy season; it is estimated that the total water demand during the operation phase will be approx. 45 KLD. The fresh water requirement for the logistic park is estimated to be approx. 45 KLD including horticulture, flushing and domestic. The Table 6 source of fresh water in operation phase will be private water tanker. Detailed Water RequirementTable for6: WaterNon rainy Calculationand Rainy for SeasonNon Rainy is givenSeason in . Fresh water Fresh Total Waste Rate of for domestic Water water water water and for dema Gener Arae in demand horticulture flushing nd ation SN Description Sqm Occupancy (liter) (KLD) (KLD) (KLD) (KLD)

….. Staff …. 1 Population 300 30 2.20 6.80 9.00 8.56 …. ….. 2 Visitors 20 15 0.07 0.23 0.3 0.29 Total 38.04 7.03 45.06 8.85 3 Horticulture 11921.49 3 liter/Sqm 35.76 35.76 Approx. Total Value ~38 ~7 ~45 ~9

Source:(i) Manual on norms and standards for environment clearance of large construction projects, Ministry of Environment and Forests, Government of India

The water balance diagram during the Non Rainy Season is shown below in Figure 2:

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 21 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Total Water Requirement (45 KLD)

ment (50 KLD) Fresh Water (38+7=45KLD)

Domestic Water=2 Flushing Horticulture KLD (7 KLD) (36 KLD)

Waste water from Wastewater domestic=1.8 KLD Nil (7 KLD) @100% (80% of 2 KLD)

Total Wastewater (8.8KLD ~9 KLD)

Septic Tank

Figure 2 :- Water Balance Diagram: Non rainy Season

The water balance diagram during the rainy season is shown below in Figure3:

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 22 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Total Water Requirement (9 KLD)

ment (50 KLD) Fresh Water (9 KLD)

Domestic Water=2 Flushing Horticulture KLD (7 KLD) (0 KLD)

Waste water from Wastewater domestic=1.8 KLD Nil (7 KLD) @100% (80% of 2 KLD)

Total Wastewater (8.8 ~9 KLD)

Septic Tank

Figure 3: Water Balance Diagram: Rainy Season

Approximately 8.8 KLD of wastewater will be generated from the project which will be managed by septic tank 2.2What is the capacity (dependable flow or yield) of the proposed source of water?

During the non rainy season; it is estimated that the total water demand during the operation phase will be approx. 45 KLD. The fresh water requirement for the logistic park is estimated to be approx. 45 KLD including horticulture, flushing and domestic. 2.3 What is the quality of water required, in case; the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality)

The water supply will be met through private water tanker which conforms to IS : 10,500. 2.4 How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities, sources and usage).

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 23 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Approx 8.8 KLD of wastewater will be generated from the project which will be managed by septic tank. 2.5 Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption).

No, there is no diversion of water from other users. Rise in water demand is a local phenomenon but the project would have limited regional impact on water reserves. 2.6 What is the incremental pollution load from wastewater generated from the proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity).

Approx 8.8 KLD of wastewater will be generated from the project which will be managed by septic tank. 2.7 Give details of the water requirements met from water harvesting? Furnish details of the facilities created.

Water Harvesting: The harvesting water will help in raising the ground water table. During the monsoon months, the storm water runoff could be stored and used for internal activities within premises. The proposed rainwater harvesting system would need to be based on environmental and sustainable concepts. Table 7: Rain Water Harvesting Potentials Rain Water Harvesting Potential Runoff Rainfall Particulars Area (Sq. m.) Discharge (Run Off) m3/hr coefficient (m)

Roof Area 35,851.62 0.9 0.045 1,451.99 Considering 20 min Retention Period =1,451.99/3 RWH Pit dimension; Diameter = 3.5 m, depth =5 m 3.14 x 1.753 x 1.75 x 5 =484 m /hr The volume of the single pit ~48.08 m3

Total number of pits proposed =484/48.08 ~10 =10.07

Hence as per the requirement, 10 rain water harvesting pits are proposed for logistic park.

Run off from green area and road /paved area shall be collected under Kuccha pond. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 24 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

No adverse impacts are envisaged due to the project on the runoff characteristics of the area as adequate arrangements will be made to trap the rainwater and suitable storm water drainage system will be provided. Runoff from the project will not allow standing or entering into the roadside or nearby drain. Adequate measures will be taken to collect such run off and either reused. No problem of flooding and water logging will envisage as excess run-off will drain to ground water. 2.9 What are the impacts of the proposal on the ground water? (Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent).

The project site is in a safe zone as pr CGWA classification, ground water recharge is proposed, however it will be collected in a tank and utilized as and when required during operational phase. Water requirement will be reduced by recycling of treated water. 2.10 What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts).

To prevent degradation and maintain the quality of the water source, adequate control measure will be proposed to check the surface run-off. Following management measures will be suggested to protect the water quality for the further construction phase: -  Avoiding excavation during monsoon season. Care will be taken to avoid soil erosion. The storm water disposal system for the logistic park shall be self-sufficient to avoid any collection/ stagnation and flooding of water. Maximum harvesting will be done within the site. 2.11 How is the storm water from within the site managed? (State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels).

The project site level is plain. Adequate storm water channel will be provided at the site to provide proper drainage facilities and to avoid flooding at the site and in area. A storm drainage system will be laid. The storm drains collects, convey and dispose to Natural Drainage system.

During the monsoon months, the storm water runoff could be stored and used for internal activities within premises. The proposed rainwater harvesting system would need to be based on environmental and sustainable concepts. 2.12 Will the deployment of construction laborers particularly in the peak period lead to unsanitary conditions around the project site (Justify with proper explanation).

EnvironmentNo, the deploymentAplinka of construction Solutions & Technologies labours will Pvt.not Ltd, led Noida to any Uttar unsanitary Pradesh conditions as all the 25 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

necessary precautions will take including provision of mobile toilet. During construction phase  the facilities will provide at the labour camp include the following:  Mobile toilet. To check any possibility of unsanitary conditions around the project site  Regular segregation and disposal of solid waste generated by workers as per local practices  Proper housekeeping First aid and medical facilities for all the concerned people working on the site. 2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal).

During operation, approximately 8.8 KLD of wastewater will be generated from the project which will be managed by septic tank. 2.14. Give details of dual plumbing system if treated waste is used for flushing of toilets or any other use.

There is a no provision of dual plumbing system for use of water for different applications. For flushing of toilets project will be used fresh water. 3. VEGETATION 3.1 Is there any threat of the project to the biodiversity? (Give a description of the local ecosystem with its unique features, if any).

No, threat on bio-diversity will envisage due to project. No forest land exists in its vicinity and no ecologically important habitats are observed in the study area (2 km from the project site) of the project. 3.2 Will the construction involve extensive clearing or modification of vegetation? (Provide a detailed account of the trees & vegetation affected by the project).

The site is devoid of trees only small shrubs and herbs are present at site. Only seasonal shrubs will clear off prior construction. 3.3 What are the measures proposed to be taken to minimize the likely impacts on important site features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc. along with a layout plan to an appropriate scale?).

Extensive plantation and green area and landscape development in the area of 11,921.49 sq. m will be developed. Local plants will plant all around the periphery of the project; as per the Guidelines for the development of Greenbelt by CPCB. Plantation will be of flowering, evergreen, Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 26 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

broadleaf trees that provide adequate shade. The following species will be planted within premises of the logistic park as given Table 8.

Table 8 (a): Trees for Greenbelt Development S. No.S. Family area (sqm) area Crownshape Leaf Leaf sqc)Area Crownsurface StomatalIndex CommonName Binomial Name Height (Meters)Height Regeneration By Vernacular Name FloweringSeason Sensitive/Tolerant Bauhinia purpurea

Caesalpi Butterfly Through Sept.- Oblo 107. 1 CassiaLinn. siamea naceae. tree wal T 7m seeds Nov. ng 625.2 3 23.58 Iron Minjr Caesalpi wood i(Ben 10- Aug - Oblo 3927. 138. 2 CitrusLamk naceae tree g.) T 12m By Seeds May ng 36 32 21.2 aurantium Roun By d/ Limb cutting, Sept - Oblo 20.2 3 Linn Rutaceae Lemon u T 5m Grafting Nov ng 494.9 3 35.81 Callistemon Throu citrinus scarl gh the et year (Curti Myrtace Bottle bottle By Seeds. esp- Coni 45,99 214. 127.4 4 Cassias)Stapf fistula ae brush, brush T 5m Cutting .April cal 7.20 01 9 Golden Caesalpi Showers Amla By seeds, Mar - Roun 2957. 130. 5 linn naceae , tas T 12m Suckers May d 11 51 20.4 Spre adin Delonix regia g/ Flat Erythrina Caesalpi Flamboy Gulm By seeds, April- topp 44209 358. 6 variegata(Bojer) Rafin naceae ant ohur S 15m cuttings June ed .23 32 14.38 Indian By seeds, Coral Dada Stem Feb- Oblo 22903 168. 7 Linn Fabaceae tree p T 10m cutting May ng .7 94 31.76 Morus alba By Seeds, Cutting, Moracea grafting, Feb.- Oblo 1047. 285. 8 Linn. e Tuti Tut S 8m budding June ng 62 3 17.4 Source: Guidelines for Developing Greenbelts, CPCB, 2007

Table 8(b): Shrubs Suggested For Development Of Greenbelts S. No. Family Season Flowering area (sqm) Crown shape Leaf AreaLeaf sqc) Crown surface Stomatal Stomatal Index Common Name BinomialName Height (Meters) RegenerationBy Vernacular Name Sensitive/ Tolerant

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 27 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Murraya paniculata By Rutacea March Seeds, June - Roun 1354. 35. 10. 1 Linn e ula T 5m Cutting Oct. d 61 3 31 Nerium Throug Oblo indicum Pink By hout ng / Tabernaemon Apocyn oleande Seeds, the Roun 5747. 32. 15. 2 atana Mill aceae r Kaner T 5m Cutting year d 63 62 7 divaricata Throug Thevetia Apocyn By h the Roun 128.6 47. 30. 3 peruvianaLinn aceae Tagar T 3m Cutting Year d 7 81 2 Yellow By Roun Apocyn oleande Pila seeds, d/Ob 21775 11. 27. 4 Tecoma(Pers.)Merrill. Stans aceae r Kaner T 6m cutting long .22 08 8 By Bougainvillea Bingnon Seeds, Feb - Oblo 43. 23. 5 spectabilisLinn. iaceae T 5m cutting April ng 61.23 7 8 Throug Oblo Nyctagi Bougai Kagji By h the ng/R 939.2 33. 32. 6 HameliaWilld nvillea nvillea Phul T 8m cuttings year ound 5 15 53 patens By Rubiace Scarlet Seeds, Oct.- Roun 824.0 47. 19. 7 LawsoniaJacq ae bush T 3m cuttings Jan d 6 2 07 inermis By Source: Guidelines forLythrac Developing Greenbelts,Mehen CPCB, 2007 Seeds, April - Roun 77. 8 Linn eae Henna di T 5m Cutting July d 71.85 8 17 4. Fauna 4.1 Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details.

No displacement of fauna will envisage due to the logistic park. The project site is free of nesting, roasting foraging habitat of wild animals further there is no proposal of creation of any barrier for terrestrial or aquatic fauna, hence it can be inferred that the logistic park is not going to disturb the movement of fauna. 4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.

No direct impact on avifauna will envisage. However, after the commissioning of the project the better environmental conditions may provide a better habitat to the avifauna of the area. There may be some indirect impact to avian fauna; however that will be minimized by adopting proper waste management, controlling noise pollution and bird friendly lightening. 4.3 Prescribe measures such as corridors, fish ladders etc. to mitigate adverse impacts on fauna.

No interface with the fisheries activity and/or fauna will envisage. 5. AIR ENVIRONMENT

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 28 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

5.1 Will the project increase atmospheric concentration of gases & result in heat islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions).

Vehicular emissions and DG sets emission will be major sources of air pollution from the logistic park. During post construction phase, Ground Level Concentration of pollutants (as added by the project) will depend upon the following:  Emission of pollutants from additional traffic on the roads due to the project.  Meteorological conditions. Emission sources from D.G. Sets. , 2 2 PM NO , SO and CO will be the main pollutants of primary concern released from traffic movement and DG sets. Assuming that under cross wind condition perpendicular to the road, the dispersion of vehicular emissions would be confined within limited distance from the road and concentration will decrease with the increase in distance from road. It is anticipated that the contribution of vehicular emissions from the exhaust in ambient air quality will be marginal as Pollution under Control (PUC) Certified vehicles and branded make operated vehicle with low sulphur diesel will be used. Ground Level Concentration (GLC) of pollutants is found to be well within the stipulated National Ambient Air Quality Standards due to traffic movement and vehicles used inside the premises. 5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters.

There is burning of fuel through D.G. sets, traffic movements, operation of construction machines/equipment and domestic activities at site. 2 2 Construction activities lead to dust generation, emission of NO , SO and PM. The impacts on the ambient air quality phase is during construction temporary and reversible in nature (for short duration) and restricted to only a small area. During operation phase, there will be development of green-area and maintenance of vehicles, all these efforts will reduce the impact. 5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site.

Table 9 : Adequate provisions have been made for vehicle parking at the project site so as to allow smooth movement at the site. The provision of parking at the site is shown in the

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 29 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Table -9: Parking Area Statement

Total surface Parking Area 7,000 Sqm Number of 2 wheelers 606 Number of Cars 16 Number of trucks 20 5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category.

The logistic park is adjacent to NH-91 adjacent to the project site in SW. The internal road connects the site to the connecting road. 22 m wide road have been maintained around the logistic park to easy movement of heavy vehicles and fire tenders. Also the entry road is much wide to avoid traffic congestion near to entrance. During operation vehicles move on circular path, from one point they enter and from other point they exit from the logistic park premises. 5.5 Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures proposed for mitigation of the above.

There will be a marginal increase in the traffic noise; the sources are due to traffic movement within the project area. The horns will be prohibited inside the project site. The traffic movement will be only in daytime during the construction phase. In operational phase, only visitor’s vehicles will come inside the project boundary. The pollution will be in very small quantity and it will be further minimized by plantation on the sides and around the periphery of whole project. The major sources of noise during the operational phase are DG sets, compressor, internal traffic, external traffic since project is near to NH-91. The DG sets will be procured with acoustic enclosure and the other compressors and pumps will also be acoustically covered. The traffic during operation will be planned in a manner such that there are least idling and bottle necks. Moreover, greenbelt development in and around the site results in reducing noise level effectively. 5.6 What will be the impact of D.G. sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details.

DG Sets will be used for power back-up. So, D.G. set will be the main source of air and noise 2 2 pollution. Gaseous pollutants like NO , SO and PM shall be generated from activities like burning of fuel through D.G. sets. HSD diesel will be used with low sulphur.

During operation, vehicular movement and operation of D.G. sets are the major sources of noise pollution. Both these activities – D.G. sets and vehicular movement will not have any significant impact on the area. Since D.G. sets will not be operational continuously and moreover it will be placed enclosed with suitable enclosures, hence no or minimal impact will be anticipated. It is envisaged that the movement of the motor vehicles will be restricted to designated roads only.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 30 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Impacts on Air Quality

Impacts on ambient air quality during operation due to emissions from the stacks attached to D.G. sets would be very less. However suitable mitigation measures will be adopted. Mitigation Measures for Impacts of DG Sets on Ambient Air Quality:   D.G. sets will be used only during power failure  D.G. sets will comply with the applicable as per emission norms.  Adequate stack height for D.G. sets will be provided as per C.P.C.B. norms. During operation stage, monitoring of emissions from D.G. sets and ambient air quality will be carried out as per norms. 6. AESTHETICS 6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents?

The project site does not have any scenic amenity or landscaping in its surroundings so there is no possibility of obstruction of above-mentioned conditions. The project will not in any way results in the obstruction of a view scenic amenity or landscapes. The present project itself is planned with provisions of landscaping and green area development and afforestation. This will surely enhance the aesthetic beauty of the area. 6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account?

The development in the entire project area is as per the provisions of National Building Code. Hence; there were no adverse impacts on the existing structures in this area. 6.3 Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out.

The development in the entire project area is as per CLU which will be allotted by Sub District Magistrate, Sikandrabad and the construction has been carried out as per the UP Building Bye Laws 6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any other significant features in the vicinity of the proposed site have been considered

There are no anthropological or archaeological sites or artifacts in the vicinity of the project, hence not considered. 7. SOCIO-ECONOMIC ASPECTS

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 31 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

7.1 Will the proposal result in any changes to the demographic structure of local population? Provide the details.

During operation phase; the project will have the facilities for 300 staff and 20 visitor within logistic prk. So, it will also provide direct and indirect employment to the local people from the 7.2surroundingGive detailsareas. of the existing social infrastructure around the proposed project.

The site is located near to Sikandrabad Dehat Village, District Bulandshahr, and Uttar Pradesh. NH-91 is adjacent to project site in SW. The infrastructures are easily accessible by intra city public transport and intermediate public transport.Details of these social infrastructures are given below in Table 10: Table 10: Existing social infrastructure around the project

S. Description Surrounding Features Aerial Distance & Direction No. from the Project Site  

1 Nearby Place of worship  Bhajan Lal Mandir  Approx 1.5 km in SW  Markaz Wali Masjid  Approx. 2 km in SW  Devi Mandir  Approx. 2 Km in E

2 Nearby Hospital  Rana Hospital  Approx 2 km in SE  Ivory Hospital  Approx 17 Km in West

3 Nearby School/ college Prem Inter College Approx 8 km in East  Baral 

Source: Satellite Imagery of Project Area, Google earthI. P. College Inc, USA Approx 8 km in SE

7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed?

No adverse impact is anticipated on local communities. There are no sacred or cultural sites near the development site. So no question arises of disturbing them. Many local people may get jobs as per their skill. Security requirement will also be met from the local private agencies. 8. BUILDING MATERIALS 8.1 May involve the use of building materials with high-embodied energy. Are the construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency).

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Conventional construction material will be used. Energy efficient building materials will be32used Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

as specified in the Energy Conservation Building Code.The major materials will use for the construction of the project were steel, cement, bricks, metal, flooring tiles/stones, sanitary and hardware items, electrical fittings, water etc. 8.2 Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts?

Construction activities especially related to handling of loose material causes generation of fugitive dust that adversely impacts the air quality of the surrounding area of the project site. To minimize the impact, loose material were transported with proper covering. 8.3 Are recycled materials used in roads and structures? State the extent of savings achieved?

Yes, the recycled material will be used in the logistic park to the extent possible. The possibilities will be searched and if feasible following recyclable material will be used in construction.

1. Fly ash Bricks 2. Clean wood 3. Recycled Gypsum Wallboard, and cardboard 4. Portland cement 5. Particle boards or other fiber-boards 8.4 Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of the project.

kg per day The total solid waste generated from the project will be mainly domestic waste and estimated quantity of the waste is approx. 79 (@0.25 kg per capita per day for staff, @0.15 kg per capita per day for visitors andTable landscape 11: Solid wastes Waste @ Estimation 0.2 kg/acre/day. S. No Category No. Waste generated Waste generated (kg/day) (kg per capita per day)

2 Staff 300 0.25 75 3 Visitors 20 0.15 3 Landscape waste 0.2 kg/acre/day 0.588 (2.94TOTAL acre) SOLID WASTE GENERATED 78.588 kg/day ~ 79 kg/day (Source: For Waste Collection, Chapter 3, Central Public Health & Environment Engineering Organization, Ministry of Urban Development, (Government of India, May 2000)

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 33 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Following arrangements will be made at the site in accordance to Solid Wastes Management Rules, 2016.  Collection and Segregation of waste

1. A collection system will be provided for collection of waste in colored bins for separate blocks 2. The local vendors will be hired to provide separate colored bins for dry recyclables and Bio- Degradable waste. 3. Adequate number of colored bins will be provided at the suitable locations of the project site. 4. Litter bin will also be provided in open areas like parks etc.  Treatment of waste 

Bio-Degradable wastes 1. Bio-degradable waste will be manage by organic waste converter 2. Horticultural Waste is proposed to be composted and will be used for gardening purposes. Grass Recycling Recyclable wastes i. – The cropped grass will be spread on the green area. It will act as manure after decomposition. ii. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclables.  Disposal

Recyclable and non-recyclable wastes will be disposed through Govt. approved agency. Hence, the Municipal Solid Waste Management will be conducted as per the guidelines of Solid Wastes Management Rules, 2016. A Solid waste management Scheme is depicted in the following figure for the project. 9. ENERGY CONSERVATION 9.1 Give details of the power requirements, source of supply, backup source etc. What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption?

The estimated load for the project will be approx. 1000 KVA which will be supplied by Paschimanchal Vidyut Vitran Nigam Limited. Details of D.G Set

There is provision of 4 DG sets of total capacity 380 kVA (1X 80+3X 300 kVA). The DG sets has been equipped each with acoustic enclosure to minimize noise generation and adequate stack height to minimize the emission. Energy Conservation Measures & Management Plan:

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 34 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

In the operational phase, appropriate energy conservation measures and management plan will be adopted in order to minimize the consumptions of non-renewable fuel. The following measures are adopted:

 The orientation of the building has been done in such a way that maximum daylight is available.  Passive solar designs refer to use suns energy for heating and cooling of living species. Lesser opening provided on west facing walls. Landscape and green area will be spaced so as to cool the surrounding environment, which reduces energy consumption.

Following measures have been adopted to reduce the energy consumption of electrical installations:  Use of L.E.D in common areas. Using energy efficient light fixtures with good photometric properties. 9.2 What type of and capacity of, power back-up to you plan to provide?

Details of D.G Set

There is provision of 4 DG sets of total capacity 380 kVA (1X 80+1X 300 kVA). The DG sets has been equipped each with acoustic enclosure to minimize noise generation and adequate stack height to minimize the emission. 9.3 What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation?

Suitable thickness of glass depending upon the panel size to keep the U value as per the requirement of ECBC. 9.4 What passive solar architectural features are being used in the building? Illustrate the applications made in the proposed project?

 The orientation of the building has been in such a way that maximum daylight is available.  The orientation of the building has been done in such a manner that most of glazed areas in north and east. Landscape and green areas are well spaced so as to cool the surrounding environment, which reduces energy consumption.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 35 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details.

Orientation in such a manner so that surface of the building cuts direct radiation of critical hours and thus building will be less affected with the heat. Building units will be made environment friendly with optimum use of solar radiations. Feasibility for installation of solar photovoltaic cells for street lighting will be assessed. There will be the provision of solar hot water system. 9.6 Is shading effectively used to reduce cooling / heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?

The shading has been effective to reduce the cooling loads. The following techniques will be adopted:  For walls on of the building, a maximum of 10% window to wall ratio minimizes solar radiation, which further helps minimizes cooling/ventilation costs.  Shading be used to increase cooling effect in the buildings. Promoting awareness on energy conservation.  Training of staff on methods of energy conservation and to be vigilant to such opportunities.  Passive solar architectural measures are adopted to provide shading devices for windows and roof, which would effectively reduce heating up of building envelope. Roofs painted with reflective, aluminum based paints with solar reflectance ranging from 0.3 - 0.6. This results in less absorption of sunlight causing 40% back reflection and less heating of building structures during summer seasons. 9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications.

The design of the building will be such that maximum use of natural lighting can be achieved. The walls, roofs and opening will be designed that influx of heat is minimum. The design also incorporates the optimal and judicious use of natural lighting. Energy Efficient Features:   The orientation of the building is in such a way that maximum daylight is available.  Landscape and greens areas are well spaced so as to cool the surrounding environment, which reduces energy consumption. Use of LED in common areas. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 36 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

9.8. What are the likely effects of the building activity in altering the micro-climates? Provide a self- assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects?

The building uses energy efficient and environmental friendly design that controls the formulation of heat island effect. There is also green cover at the site to reduce formation of heat island. Passive design concepts have been used to minimize energy consumption and maximize the energy efficiency.  Due to the project there would be insignificant emission of air pollutants by vehicular movements and occasional use of D.G sets, hence no heat island effect is envisaged. To reduce the heat load reflective insulated glass are used in fenestrations to cut on heat loads and subsequently capital & operating cost of air conditioning. 9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration? Give details of the material used and the U-values or the R-values of the individual components.

The building envelope for external walls made of bricks, concrete and steel. Proper roof insulation will be provided to achieve desired thermal comfort. The entire building envelope, opening between conditioned and non-conditioned spaces will be gasketed, provided with air curtains or sealed with sealants. Bricks, concrete & Glass will be used as construction material. 9.10 What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans.

In case of emergency, immediate steps will be taken to raise alarm and stop fire. The Fire Protection System would be based on the regulations of National Building Code, 2016 and local fire norms.  Provision of water sprinklers.  Provision of separate fire hydrant pipe.  Provision of Overhead water storage tank. There is provision of firefighting pumps. Optical type smoke detectors shall be used in most areas. 9.11 If you are using glass as wall material provides details and specifications including emissivity and thermal characteristics.

No Glass has been used as wall materials. 9.12 What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 37 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

All care towards improving energy efficiency due to poor rate of infiltration has been taken while designing the building w.r.t to its envelope to ensure enough air circulation around the building by natural wind movement. NBC and ECBC guidelines/specifications have been adhered to mitigate the effect of air infiltration. 9.13 To what extent the non-conventional energy technologies are utilized in the overall energy consumption? Provide details of the renewable energy technologies used.

Non-conventional energy technologies have been used to save overall energy consumption. Following technologies have been used in order to conserve energy: Introducing electric meters with timer. Renewable energy technologies have been promoted in the form solar water heating. 10. ENVIRONMENT MANAGEMENT PLAN Introduction

The Environment Management Plan (EMP) is a site specific plan developed to ensure that the project is implemented in an environmental sustainable manner where all contractors and subcontractors, including consultants, understand the potential environmental risks arising from the project and take appropriate actions to properly manage that risk. EMP also ensures that the project implementation will carried out in accordance with the design by taking appropriate mitigation actions to reduce adverse environmental impacts during its life cycle. The plan outlines existing and potential problems that may adversely impact the environment and recommends corrective measures where required. Also, the plan outlines roles and responsibility of the key personnel and contractors who will be in-charge of the responsibilities to manage the project site. The Environment Management Plan (EMP) would consist of all mitigation measures for each component of the environment due to the activities increased during the operation and the entire life cycle to minimize adverse environmental impacts resulting from the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the sites including fire. Objectives 

Actions/ activities required to comply with rules and requirements of the environmental  clearance, consent to establish, consent to operate and other NOC from Govt. Departments.  To ensure that the logistic park is operated in accordance with the approved design. Provide personnel with systems, procedures and documentation necessary to undertake  the construction meeting with environmental requirements and to minimize the impact on the natural environment. A plan that ensures remedial measures is implemented effectively in a planned way. EMP includes four major elements

Environment Aplinka Solutions & Technologies: Pvt. Ltd, Noida Uttar Pradesh 38 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Commitment & Policy: The management will strive to provide and implement the  Environmental Management Plan that incorporates all issues related to air, water, land and noise.  Planning: This includes identification of environmental impacts, legal requirements and setting environmental objectives. Implementation: This comprises of resources available to the developers, accountability  of contractors, training of operational staff associated with environmental control facilities and documentation of measures to be taken. Measurement & Evaluation: This includes monitoring, counteractive actions and record keeping. EMP for Air Operation Phase

To mitigate the impacts of pollutants from DG set and vehicular traffic during the operational phase; following measures are recommended for implementation: Adequate stack height is maintained to disperse the air pollutants generated from the  operation of DG set to dilute the pollutants concentration within the immediate vicinity. Hence, no additional emission control measures have been suggested.  During construction, vehicles will be properly maintained to reduce emission. As it is an education institution, vehicles will be generally having “PUC” certificate. Adequate footpaths and pedestrian ways will be provided at the site to encourage non-  polluting methods of transportation. Increased vegetation in the form of greenbelt is one of the preferred methods to mitigate air and noise pollution. Plants serve as a sink for pollutants, act as a barrier to break the wind speed as well as allow the dust and other particulates to settle on the leaves. It also helps to reduce the noise level at large extent. EMP FOR NOISE Operation Phase

To mitigate the impacts of noise from diesel generator set during operational phase, the following measures are recommended: DG set will be housed in a suitable acoustic enclosure so that noise level at a distance of  1 m does not exceed 75 dB(A) as per CPCB standards or is meeting the local standard (whichever is higher). It would be ensured that the manufacturer provides acoustic enclosure as an integral part along with the diesel generators set. Further, enclosure of the services area with 4 m high wall will reduce noise levels and ensure that noise is at a permissible limit for residents and staff of the project and surrounding receptors. EMP FOR WATER: Operation Phase

In the operation phase of the project, water conservation and development measures will be Environmenttaken. FollowingAplinka Solutionsmeasures & Technologieswill be adopted: Pvt. Ltd, Noida Uttar Pradesh 39 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

  Minimizing water consumption. Promoting reuse of water after treatment and development of closed loop systems for different water streams. Water Conservation

The water conservation is the need of the hour and consumption of fresh water will be minimized by combination of water saving devices and other domestic water conservation measures. Further, to ensure ongoing water conservation, an awareness program will be introduced for the workers. The following section discusses the specific measures, which shall be implemented: Domestic Usage 

Use of water efficient plumbing fixtures (low flow sinks, water efficient dishwashers and  washing machines). Water efficient plumbing fixtures uses less water with no marked reduction in quality and service  Leak detection and repair techniques.  Sweep with a broom and pan where possible, rather than hose down for external areas.  Meter water usage: Implies measurement and verification methods. Monitoring of water uses is a precursor for management. Horticulture 

 Plants with similar water requirements grouped on common zones to match precipitation heads and emitters.  Use of low-angle sprinklers for lawn areas.  Select controllers with adjustable watering schedules and moisture sensors to account for seasonal variations and calibrate them during commissioning. Place 3 to 5 inches of mulch on planting beds to minimize evaporation. Storm Water Management

Most of the storm water produced on site will be harvested reuse by storing in an underground water tank of suitable size. Thus, proper management of water resource is a must to ensure that it is free from contamination. Contamination of Storm Water is possible from the following sources:  Diesel and oil spills in the diesel power generator and fuel storage area  Waste spills in the solid / hazardous waste storage area  Oil spills and leaks in vehicle parking lots  Silts from soil erosion in gardens Spillage of sludge from sludge drying area of sewage treatment plant Storm water management plan will incorporate best management practices which will include following: Regular inspection and cleaning of storm drains Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 40 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Clarifiers or oil/separators will be installed in all the parking areas. Oil/grease separators installed around parking areas and garages will be sized according to peak flow guidelines. Both clarifiers and oil/water separators will be periodically pumped in order to keep discharges within limits  Covered waste storage areas  Avoid application of pesticides and herbicides before wet season  Secondary containment and dykes in fuel/oil storage facilities  Conducting routine inspection to ensure cleanliness Provision of slit traps in storm water drains EMP FOR WASTE: Operational Phase

R R R R The philosophy of solid waste management at the logistic park will be to encouraging the four R’s of waste i.e. eduction, euse, ecycling and ecovery (materials & energy). Regular public awareness meetings will be conducted to involve the staff in the proper segregation and storage techniques. The Environmental Management Plan for the solid waste focuses on three major components during the life cycle of the waste management system i.e., collection and transportation, treatment or disposal and closure and post-closure care of treatment/disposal Collection and Transportation facility.

During the collection stage, the solid waste of the project will be segregated into biodegradable waste and recyclable waste. Biodegradable waste and recyclable waste will be collected in separate bins. Biodegradable waste will be treated in the project premises by organic waste converter. The recyclable wastes will be sent off to recyclers. Proper guidelines for segregation, collection and storage will be prepared as per Solid Waste Management Rules, 2016. To minimize littering and odour, waste will be stored in well-designed containers/ bins  that will be located at strategic locations to minimize disturbance in traffic flow. Care would be taken such that the collection vehicles are well maintained and generate minimum noise and emissions. During transportation of the waste, it will be covered to avoid littering.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 41 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Solid Waste

Biodegradable waste Non- Biodegradable (Domestic waste, Waste horticulture waste)

Green Bins

Recyclable waste Non- Recyclable (Solid Waste, Plastic Waste, Waste (Inert Disposal to the Govt. and Hazardous Waste Waste) approved vendor as per the provisions of Solid Waste Management Rules, 2016

White Bins Black Bins

Disposal to the Govt. approved vendor as per the provision of

Solid waste Management Rules, 2016 Hazardous and Other Waste (Management and Transboundary Movement) Rules 2016 Plastic Waste Management Rules, 2016

Figure 4: Waste Management Flow Diagram

Disposal

With regards to the disposal/treatment of waste, the management will take the services of the authorized agency for waste management and disposal of the same on the project site during its operational phase. EMP FOR ECOLOGY & BIODIVERSITY Operation Stage

 Improvement of the current ecology of the project site will entail the following measures:  Plantation and Landscaping Green Belt Development

The section below summarizes the techniques to be applied to achieve the above objectives: Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 42 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Plantation and landscaping

Selection of the plant species would be done on the basis of their adaptability to the existing geographical conditions and the vegetation composition of the forest type of the region earlier found or currently observed. Green Belt Development Plan

The green belt will be developed as per the guidelines for developing green belt by CPCB, 2007. The plantation matrix adopted for the green belt development includes pit of 0.3 m × 0.3 m size with a spacing of 2 m x 2 m. In addition, earth filling and manure may also be required for the proper nutritional balance and nourishment of the sapling. It is also recommended that the plantation has to be taken up randomly and the landscaping aspects could be taken into consideration. Plantation comprising of medium height trees (7 m to 10 m) and shrubs (5 m height) are proposed for the green belt. Plant Species for Green Belt Development

The selection of plant species for the development depends on various factors such as climate, elevation and soil. The plants would exhibit the following desirable characteristics in order to be selected for plantation 1. The species should be fast growing and providing optimum penetrability. 2. The species should be wind-firm and deep rooted. 3. The species should form a dense canopy. 4. As far as possible, the species should be indigenous and locally available. 2 2 5. Species tolerance to air pollutants like SO and NO should be preferred. 6. The species should be permeable to help create air turbulence and mixing within the belt. 7. There should be no large gaps for the air to spill through. 8. Trees with high foliage density, leaves with larger leaf area and hairy on both the surfaces. 9. Ability to withstand conditions like inundation and drought. 10. Soil improving plants (Nitrogen fixing rapidly decomposable leaf litter). 11. Attractive appearance with good flowering and fruit bearing. 12. Bird and insect attracting tree species. 13. Sustainable green cover with minimal maintenance. EMP for Socio-Economic conditions

The social management plan will be designed to take proactive steps and adopt best practices, which are sensitive to the socio-cultural setting of the area. The Social Management Plan for the logistic park focuses on the following components: Health Care:

The workers will be provided with facilities such as safe drinking water and mobile toilet. They will provid with medical aids at site. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 43 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Traffic Management

During operation phase proper traffic management and adequate parking facilities will be provided to mitigate the traffic noise. The logistic park is near to NH-91. EMP FOR ENERGY CONSERVATION

Energy conservation program will be implemented through measures taken both on energy demand and supply.

Figure 5: Energy Conservation measures

Energy conservation will be one of the main focuses for the logistic park during planning and  Architectural design operation stages. The conservation efforts would consist of the following:  Maximize the use of natural lighting through design.  The orientation of the buildings will be done in such a way that maximum daylight is available. The green areas will be spaced, so that a significant reduction in the temperature can  Energy Saving Practices  take place.  Use of LED instead of GLS lamps for Common Areas.  Achievement of U value of external envelope for air conditioned building as per perspective requirement of ECBC. Energy efficient motors in pumps and energy efficient chillers for HVAC with VFD control ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING PLAN

For the effective and consistent functioning of the complex, an Environmental Management Environmentsystem (EMS) wouldAplinka be established Solutions & Technologies at the site. ThePvt. Ltd,EMS Noida would Uttar include Pradesh the following: 44 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

  Environmental management cell.  Environmental Monitoring.  Personnel Training.  Regular Environmental audits and Correction measures. Documentation – standards operation procedures Environmental Management Plan and other records. ENVIRONMENTAL MANAGEMENT CELL

Apart from having an Environmental Management Plan, it is also complied to have a permanent organizational set up charged with the task of ensuring its effective implementation of mitigation measures and to conduct environmental monitoring. The major duties and responsibilities of Environmental Management Cell are as given below:  To implement the environmental management plan.  To assure regulatory compliance with all relevant rules and regulations.  To ensure regular operation and maintenance of pollution control devices.  To minimize environmental impact of operations as by strict adherence to the EMP.  To initiate environmental monitoring as per approved schedule. Review and interpretation of monitored results and corrective measures in case  monitored results are above the specified limit.  Maintain documentation of good environmental practices and applicable environmental laws for a ready reference.  Maintain environmental related records.  Coordination with regulatory agencies, external consultants, monitoring laboratories. Maintenance of log of public complaints and the action taken. Structure of Environmental Management Cell

Normal activities of the EMP cell would be supervised by a dedicated person who has been reporting to the site manager/coordinator of the logistic park. The hierarchical structure of suggested Environmental Management Cell is given in following Figure 6.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 45 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Rep from Corporate Site Corporate Environmental Manager Planning group Division

Site Environmental Coordinator

Turbo Bio-reactor Landscape Dev. Operator Incharge

Figure 6: Environnent Management Cell Structure

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 46 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Table 12: SUMMARY OF MANAGEMENT MEASURES AND RESPONSIBILITY S. No. Environmental Potential Impacts Potential Source Management Responsibility Issues (Direct/ Indirect) of Impact Measures Execution/ Civil Work Supervision   1. Ground Water Ground Water Operation Phase All the waste water Management Project Proponent Quality Contamination No Discharge will be treated by (SHE division) from the septic tank  project  2. Ground Water Ground Water Operation Phase Awareness Management Project Proponent Quantity Depletion The source of Campaign to reduce (SHE division) water during the water operation consumption. phase is private water  tanker  3. Surface Water Surface water Operation Phase Waste water will Management Project Proponent Quality contamination No Discharge be managed by septic (SHE division) of domestic tank wastewater.   4. Air Quality Emissions of PM, Operation Phase Use of low sulphur Management Project Proponent 2 2  SO , NO and CO Power diesel if available (SHE division) generation by Green belt have DG Set during been developed Environment Aplinka Solutionspower & Technologies failure Pvt. Ltd, Noida Uttar Pradesh with specific 47 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

Emission from species to help to vehicular reduce pollution traffic in use level Use of equipment fitted with silencers Proper maintenance of equipment. 5. Noise  Environment  Operation Phase Green Belt cover Management Project Proponent  Noise from provided. (SHE division) vehicular Provision of noise  movement shields near the heavy construction Noise from operations and DG set acoustic enclosures operation for DG set. DG sets are equipped with  acoustic enclosures  6. Land Soil contamination Operation Phase The solid waste Management Project Proponent Environment Generation of generated will be (SHE division)  municipal managed as per solid waste Solid Waste Environment Aplinka Solutions & Technologies ManagementPvt. Ltd, Noida Uttar Rules, Pradesh Used oil 48 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

 generated 2016. from D.G. set Collection, segregation, transportation and disposal will be done as per Solid Waste Management Rules, 2016 by the authorized agency. Used oil generated will be sold to authorized  recyclers.  7. Biological Displacement of Operation Phase Suitable green Management Project Proponent Environment Flora and Fauna on Increase in belts have been (SHE division) (Flora and site green covered developed as per Fauna) area landscaping plan in and around the site using local flora   8. Socio-Economic Population Operation Phase Project Management Project Proponent Environment displacement and Site operation Proponent will (SHE division) loss of income provide employment opportunities to the Environment Aplinka Solutions & Technologies localPvt. Ltd, people Noida in Uttar terms Pradesh 49 Consultant Project Name FWS Logistic Park Project M/s VRY Logistic Park LLP 8(a) Proponent Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Form I Project Address Sirondhan More, District Bulandshahr, Uttar Pradesh A

of labor during construction and service personnel (guards, securities, gardeners etc) during operations Providing quality-Integrated  infrastructure.  9. Traffic Pattern Increase of Operation Phase Vehicular Management Project Proponent vehicular traffic Traffic due to movement will be (SHE division) visitors and regulated inside the staff once the project with project is adequate roads and operational parking lots in the project.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 50 Consultant Project Name FWS Logistic Park Project Proponent M/s VRY Logistic Park LLP 8(a) Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Sirondhan Form I Project Address More, District Bulandshahr, Uttar Pradesh A

ENVIRONMENTAL MONITORING

The purpose of environmental monitoring is to evaluate the effectiveness of implementation of Environmental Management Plan (EMP) by periodic monitoring. The important environmental parameters within the impact area are selected so that any adverse effects are detected and time action can be taken. The project proponent will monitor ambient air Quality, Ground Water Quality and Quantity, and SoilTable Quality13: Environmental in accordance withMonitoring an approved Plan – Constructionmonitoring schedule. Phase Source Monitoring Location Parameters to be Frequency Monitored

Once in three month Ambient Air At 1 location at boundary 2.5 10 2 2, PM , PM , SO ,NO CO Quality of the project site.

At 1 location at boundary Day and night Once in three month Ambient Noise of the project site. equivalent noise level At 1 location nearest to the Once in three month Ground water As per standards project site. At 1 location outside the Once in three month Soil As per standards project site. Table 14: Environmental Monitoring Plan – Operation Phase Source Monitoring Location Parameters to be Frequency Monitored

Twice in a year or as per the DG set 2 2 condition of Environmental DG stacks PM, SO , NO emissions Clearance or as per requirement of SPCB Twice in a year or as per the At 0.5 m distance from condition of Environmental DG set noise Noise level enclosure Clearance or as per requirement of SPCB Twice in a year or as per the 2.5 10 2 2, Ambient Air PM , PM , SO ,NO condition of Environmental At 3 locations Quality CO Clearance or as per requirement of SPCB Twice in a year or as per the Day and night condition of Environmental Ambient Noise At 3 locations equivalent noise level Clearance or as per requirement of SPCB. At 1 location nearest to Twice in a year or as per the Ground water As per standards the project site. condition of Environmental Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 51 Consultant Project Name FWS Logistic Park Project Proponent M/s VRY Logistic Park LLP 8(a) Gata No. 847&848, Village Sikandrabad Dehat, Gulaothi Road, Near Sirondhan Form I Project Address More, District Bulandshahr, Uttar Pradesh A

Clearance or as per requirement of SPCB Awareness and Training

Training and human resource development is an important link to achieve sustainable operation of the facility and environment management. For successful functioning of the project, relevant EMP would be communicated to: Staff/Visitors and Contractors

Staff/visitors must be made aware of the importance of waste segregation and disposal, water and energy conservation. The awareness can be provided by periodic integrated meetings. They would be informed of their duties. Environmental Audits and Corrective Action Plans

To assess whether the implemented EMP is adequate, periodic environmental audits will be conducted by the project proponent’s Environmental division. These audits will be followed by Correction Action Plan (CAP) to correct various issues identified during the audits. DETAILS OF ENERGY CONSERVATION MEASURES Energy Conservation Measures & Management Plan:   Passive Solar designs refer to the use of Sun’s energy for the heating and cooling of living spaces.  The orientation of the logistic park will be done in such a way that maximum daylight is available.  The orientation of the logistic park would be done in such a manner that most of glazed areas in  north and east. Lesser opening will be provided on the west facing walls.  Landscape and greens areas will be so spaced so as to cool the surrounding environment, which will reduce energy consumption. Green belt in the site will be maintained by the project proponents, which would have an overall cooling effect on the surroundings. Following measures have been proposed to reduce energy consumption for Electrical installations:

In the operational phase, appropriate energy conservation measures and management plan will be adopted in order to minimize the consumptions of non-renewable fuel. The following measures are suggested to be adopted:  Use of LED instead of GLS lamps for Common Areas. Solar water heater arrangements Achievement of U value of external envelope for air conditioned Industrial/Logistic/Assembling Park as per perspective requirement of ECBC.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 52 Consultant