PROFORMA FOR REPORTING TO THE DELIVERY MONITORING UNIT- DMIC PROJECTS.

Department of Industrial Policy & Promotion Reporting Period: Status as on 31st December, 2018.

Sl. Particulars Report No.

1. Name of the Scheme/Project Delhi – Mumbai Industrial Corridor (DMIC) Project

2. Number of MoUs1 signed/yet MoUs signed with all the DMIC States -- to be signed with name of the of Uttar Pradesh, Haryana, Rajasthan, States , Madhya Pradesh and Maharashtra 3a. Early Bird Projects (EBPs) - EBPs finalized for all the DMIC States. -- Indian side

3b. Early Bird Projects (EBPs) - EBPs announced; currently at an early These EBPs are in the States of UP, Haryana, Rajasthan, Delhi and Maharashtra. Japan side stage of implementation; progress monitored regularly.

4a. Master Planning Consultants All the Master Planning Consultants -- appointed/ yet to be appointed appointed. M/s Scott Wilson for overall DMIC region M/s Halcrow for Gujarat Investment Region (IR)

M/s Lea Associates for MP IR

M/s Jurong Consultants for Haryana

IR

M/s AECOM for Maharashtra IR and Dighi Port industrial area. M/s Kuiper Compagnons BV for Rajasthan IR M/s Halcrow for UP IR Overall DMIC Gujarat Madhya Pradesh Haryana Maharashtra Rajasthan Uttar Pradesh

region

4b. Reports submitted so far Perspective The Final The Final The State Two nodes have been The Final Concept The Planning of the Development Plan Development Plan Government has taken up in Plan for the Government of overall DMIC for Dholera for the Pithampur- accorded its Maharashtra: Shendra Investment Uttar Pradesh region completed Special IR (DSIR) Dhar-Mhow administrative – Bidkin-Industrial Region was has given their and approved. and final Pre- Investment Region approval to the Park and Dighi Port approved by the concurrence on feasibility studies has already been Concept Master Industrial Area. State Government the following Meetings with have been approved by the Plan of MBIR and in its Steering consultants of completed. The State Government has forwarded the The Concept Master Committee Delineation DMIC project Final pre- and is in the final Development Plan Plans and meeting held on of Dadri Noida were conducted feasibility studies stage of to the Deptt. of Development Plans 18th June 2012. Ghaziabad under the for Renewable notification. Town and Country for Dighi Port The State Investment chairmanship of Energy, Integrated Planning, Industrial Area and Government Region CEO & MD, Housing for Secretary, DIPP has Government of Shendra Bidkin Mega notified on 26th (DNGIR); DMICDCP on Industrial requested Chief Haryana for further Industrial Park have May 15th, 16th 17th and Workers, Flood Secretary, Madhya necessary action been approved by the 2013 the master Approval of 18th December, management for Pradesh vide his with regard to the State Government. plan for Site and way 2014 regarding Phase 1 letter dated 3rd notification. The consultant has Shahjahanpur- forward for the system and development of August, 2015 to further submitted the Neemrana-Behror Multi Modal processes in DSIR, Rail resolve all the DMICDC had a design basis report Urban Complex Logistics Hub, other cities infrastructure at pending issues to meeting on 8th and the same has 2041 which also Dadri; across the world DSIR and Water enable DMICDC to April 2013 with been submitted to included the Approval of and adoption of management move forward with Chief Town State Government for master plan of Site and way International system for Phase 1 the implementation Planner of the State their comments. Khuskhera- forward for Bench Marks, development of of the Project. of Haryana to Secretary, DIPP vide Bhiwadi Boraki Railway Standards and DSIR have been discuss and his letter dated 22nd Neemrana Station; best practices for completed. Secretary, DIPP incorporate the July, 2016 has Investment creation for vide his letter dated suggestions of requested the Chief Region. nd Inclusion of Smart and 2 March, 2016 has Government of Secretary, High Speed Sustainable Cities requested the Chief Haryana in the Government of During the Seamless across DMIC Secretary, development plan. Maharashtra to meeting held on Connectivity Region. The Government of The concerns raised resolve the pending 22nd July, 2014, between Delhi- infrastructure Madhya Pradesh to were duly addressed issues relating to Government of Greater sectors for which resolve the pending and the modified Shendra Bidkin Rajasthan (GoR) the issues for moving drawings along with informed that the Industrial Park and Noida and benchmarking forward with the the requisite State Government Dighi Port industrial Faridabad; frameworks were DMIC Project documents were Area for moving is in process of expeditiously. discussed during submitted by forward drafting new Act Approval to the above DMICDC to the expeditiously. under which take up Pre meetings are Chief Secretary, State Government. Additional Secretary, implementation of Feasibility roads and utilities Government of DIPP alongwith DMIC project will Study for : (1) and Madhya Pradesh In the above CEO & MD, be taken up in Greater Noida transportation along with meeting, the DMICDC visited the Rajasthan. Hi Tech systems, water CEO&MD, institutional site at Shendra to supply storm DMICDC reviewed structure proposed review the progress The State Township, (2) water drainage the status of DMIC for the MBIR was of activities on 11th Government has Solid waste and sewer projects in Madhya also discussed at August, 2016. approved the management of systems, power Pradesh on 15th length and it was Additional Secretary, following five Noida and and solid waste June, 2016 at decided that Ministry of Finance projects for Greater Noida management Bhopal. Government of visited the site of conducting the and systems etc. The Haryana would Shendra on 19th pre – Feasibility consultants were Secretary, DIPP revert with revised August, 2016 to Study: (3) Reuse of directed to take vide his letter dated model within the review the progress waste water in into account the 26th July, 2016 has regulatory of project activities. - Waste Water Noida and international requested the Chief framework of the CEO of Maharashtra Conveyance Greater Noida. standards, Secretary, State. Industrial System form DJB The delineated specifications Government of development (Okhla Treatment map of the IR and benchmarks Madhya Pradesh to In the meeting held Corporation (MIDC) Plant) th was submitted and best resolve the pending on 28 October, visited the site at - Integrated to GNIDA for practices, while issues for moving 2013 followed by Shendra on 22nd Multimodal inclusion in the preparing their forward with the the meeting held on September, 2016 to th Passenger Hub UP sub-region respective DMIC Project 29 November, review the progress of NCR. deliverables and expeditiously. 2013, it was of project activities. - High Tech tender packages confirmed by the Fifty (50) number of Agriculture/ Food In the meeting for The process of State Government plots have been Cluster - Water held on 20th implementation notification of that the allotted to industries Management for March, 2013 in of trunk Development Plan development plan in the Shendra Phase – 1 - Public DMICDC with infrastructure of Pithampur- for MBIR and its Industrial Area. Transportation for the State projects. Dhar-Mhow Institutional Hyosung Corporation IR. Government, Investment Region structure will be is the First Anchor the draft has been initiated finalized Investor in Shendra The Consultant concept master with the publishing expeditiously. A Industrial Area (land has initiated the plan was of Development meeting was held allotted – 100 acres) nd preliminary presented. The Plan by the State on 2 June, 2015 with a Total assessment of the draft report Government on under the investment proposed st projects. Draft incorporating 21 August, 2017 to Chairmanship of of Rs. 3111 crore. Pre – feasibility the suggestion obtain comments/ Secretary, DIPP in reports for all the of GoUP on views from the the presence of Joint MD., CFO above projects Concept Master public. Secretary, DMICDC and Joint Shareholders‟ Government of CEO of MIDC were submitted by Plan for the Agreement (SHA) Haryana and visited the Shendra the consultant and Investment and State Support another meeting and Bidkin site on under review by region was Agreement (SSA) with PS(Industries) 18.03.2018. DMICDC and the submitted to for the node/ city in DMICDC office State State level SPV has been where it was CEO & MD, Government. Government executed. Land informed by the DMICDC visited the for their acquisition by the State Government site to review the Detailed Plan for comments and State Government officials that the progress of activities Phase 1 of the approval. for the node needs development plan on 28th September, Khuskhera to be initiated. of MBIR will be 2018. The Bhiwadi In the meeting notified shortly. contractors were Neemrana IR held on 3rd instructed to expedite (Greenfield March 2013 in Secretary, DIPP completion of interior Township Project) Uttar Pradesh, vide his letter dated and finishing works. was prepared and the institutional 11th September, a draft report on structure and 2015 has requested Hon‟ble CM of same has been Share Holder the State Maharashtra and submitted to the Agreement/Stat Government to Hon‟ble Commerce State Government e Support resolve the pending & Industry Minister for their Agreements issues for all the with top management comments. were discussed projects under of AITL and and the State DMIC Project in DMICDC visited Second Node in Government of Haryana. AURIC-Bidkin site, Rajasthan: Uttar Pradesh is Development Plan Aurngabad Jodhpur – Pali – in the process for Manesar Bawal (Mharashtra) and Marwar of drafting a Investment Region ground breaking Industrial Area new legislation. has been notified ceremony was The State by the State conducted on 21st A meeting was Government has th Government of April,2018. held on 20 identified the Haryana on 5th May, 2014 November, 2015 Early Bird between Projects for the GNIDA and Secretary DIPP node and tentative the consultants vide letter dated location of the regarding 21st September, Industrial Area draft/final 2017 has requested and the same has report on Chief Secretary, been shared with Concept Master Government of DMICDC. The Plan for Dadri Haryana to expedite consultant Noida the pending matters appointed in May Ghaziabad with regard to 2012 for Investment implementation of preparation of Region. DMIC Project in Master Plan, GNIDA issued the State of Development Plan minutes for the Haryana. and Early Bird meeting. The Projects consultant was The progress of the directed to DMIC Project in consultant had incorporate the the State of comments/sug Haryana was submitted the Site gestions of reviewed during the Identification and GNIDA. 6th Board Meeting Market of the project Assessment A meeting was SPV‟s i.e. DMIC Reports for the held on 11th Haryana Global July, 2014 City Project Ltd., Industrial area between DMIC Haryana which are under GNIDA and Multi Modal review of the consultants Logistic Hub DMICDC. Site regarding Project Ltd. and delineation for the Concept Master DMIC Haryana IR has been Plan for MRTS Project Ltd. approved by the DNGIR. The held on 7th State. A meeting draft concept October, 2017. under the master plan chairmanship of prepared by the A review meeting Additional Chief consultant was was held on 22nd Secretary was held approved by th May, 2018 under on 17 April 2013 GNIDA. The the chairmanship of in Jaipur, wherein final concept ACS, Industries, various master plan is Government of options/design currently under Haryana to review concepts on preparation and the status of DMIC Concept Master shall be projects in the State Plan were submitted to and expedite the discussed. It was the State resolution of decided that the Government pending issues conceptual design shortly. pertaining to the of the master plan implementation of would be decided A meeting was these projects. in the Chief convened under Secretary‟s the A meeting was held meeting. The chairmanship of on 24th July, 2018 alternative Chief Secretary, under the conceptual design Government of chairmanship of for the Master Uttar Pradesh Hon‟ble Industries Plan of industrial on 10th April, Minister to review area submitted by 2015 at the DMICDC the consultant on Secretariat, Projects in 17th June 2013 to Lucknow Haryana. DMICDC was wherein various Concerned shared with the issues related to Departments were State Government Dadri Noida directed to expedite for their Ghaziabad the project related comments. Investment activities and land Region and IIT, acquisition for the The comments of Greater proposed Freight the State NOIDA were Village. Government on discussed. The the Draft minutes of the Development Plan meeting has have been been issued by received. State Government CEO&MD, vide their letter DMICDC vide his dated 5th May, th letter dated 14 2015 October, 2015 has requested the CEO&MD, State Government DMICDC vide for expeditious letter dated 18th approvals once June, 2015 has the revised requested State development plan Government of is submitted to the UP for State approval of Government. Techno- Economic The draft Master Feasibility Plan for Jodhpur- Study reports Pali-Marwar submitted by Industrial Area the DNGIR‟s has been consultant on published in three Early Bird public domain on Projects. 6th April, 2016 for obtaining Secretary, DIPP comments / has requested suggestions from Chief Secretary, the stakeholders/ Government of general public Uttar Pradesh before final vide his letter notification of the dated 21st July same. 2015 to intervene and The final Master resolve all Plan for Jodhpur- pending issues Pali-Marwar related to Industrial Area is notification of in the process of Master Plan of finalization after DNGIR, land obtaining acquisition for comments/ the investment suggestions from region and early the stakeholders/ bird projects, general public. review of land The Master Plan is allotment of likely to be Rivaz notified by the Township and end of July, 2016. finalization of village list CEO&MD, submitted by DMICDC vide his consultant. letter dated 18th June, 2016 has A meeting was requested the convened under State Government the to finalise the chairmanship of dates for Chief Secretary, conducting the Government of public hearing. Uttar Pradesh on 7th August, As the process of 2015 at notification of Secretariat, Master Plan is Lucknow presently wherein various underway, the issues related to proposal for Dadri Noida extension of Ghaziabad validity of the Investment Terms of Region and IIT, Reference (ToR) Greater Noida for JPMIA has were discussed. been sent to MoEF&CC vide CEO & MD, DMICDC‟s letter DMICDC vide dated 30th July, his letter dated 2016. 24th November, 2015 has The proposal for requested the extension of the State validity of the Government to ToR was enlisted identify and in the 162nd make the land Meeting of the available for Expert Appraisal taking forward Committee (EAC) the DMIC held on 30th Project in the August, 2016. State of Uttar The proposal has Pradesh. been approved by the EAC. Secretary, DIPP vide his letter Special Legislation dated 2nd for DMIC in March, 2016 Rajasthan has requested the Chief At the request of Secretary, the State Government of Government, a Uttar Pradesh Special legislation to resolve the for DMIC in pending issues Rajasthan was for moving drafted by forward with DMICDC and the DMIC provided to them Project for further action expeditiously. regarding enactment. Secretary, DIPP vide his letter dated 26th July, 2016 has requested the Chief Secretary, Government of Uttar Pradesh to resolve the pending issues for moving forward with the DMIC Project expeditiously.

Secretary, DIPP vide his letter dated 16th November, 2016 has requested the Chief Secretary, Government of Uttar Pradesh to resolve the pending issues for moving forward with the DMIC Project expeditiously.

4d. Status of initiating The consultant The Development The Final A meeting was held Land acquisition is in DMICDC had The Final implementation has submitted Plan for Dholera Development Plan on 9th September process by the State submitted the land report on the Special for the Pithampur- 2013, between Government. At details of the Concept Master Investment region Dhar-Mhow Commerce & Dighi, the area under infrastructure Plan for Dadri Environment has been approved Investment Region Industry Minister possession is 7.64 sq. component for NOIDA Impact by the State has been approved and Hon‟ble Chief km. Land notified is phase 1 to the Ghaziabad Assessment Cabinet. by the State Minister of 129.04 sqkm and State Investment (EIA) Study Government of Government. Haryana, wherein it land under Government. The Region has report in local Gujarat has Madhya Pradesh was assured by notification is 120.96 State Government been submitted language to transferred 70,430 Investment Region Government of sqkm. had initiated the to State respective State acres of land to Development and Haryana that In the case of process of land Government of RDA (Regional Management Act, Manesar Bawal Shendra, notifications acquisition and Uttar Pradesh Pollution Development 2003 was enacted Investment Region were issued for 84 sq issued section 4 for their Control Board, Authority) for by the State in Master Plan will be km. for phase 1A comments and District Phase-I April, 2013. The notified within next The area under (15.06 sqkm) of approval. Administration implementation of State Govt is 30 days. The possession is 32 sqkm the proposed GNIDA vide and Nodal the project. currently in the approval on the and 8 sqkm is likely development. its letter dated agency for process of drafting Development Plan to be acquired Further, Section 30th January, initiating the DMICDC has also rules. for the Manesar shortly. 5a had been 2015 has shared signed an MoU Bawal Investment issued. Public its comments process of Public with Gujarat The State Region is awaited The consultants had hearing was and the same hearing for the Government for Government is from the State started the survey conducted and has been following 5 implementation of taking financial Government. work and letters were Land Acquisition forwarded to nodes:- various support from sent to CEO – MIDC Officer (LAO) the consultant infrastructure HUDCO to fund As per the to appoint a nodal had submitted the for Dighi Port projects. land acquisition at directions of officer for the Site final report to incorporation in Industrial Area, Betma cluster Government of surveys, preparation State the reports. Maharashtra The entire DSIR (Phase-1) and early Haryana and the and finalization of Government. The area is divided into bird projects. The observations made maps and plans for The Manesar - State Government 6 TP Schemes. Consultant has in the State Level Dighi Industrial Area Consultants Bawal had issued Section TP1 and TP2 already submitted Committee on the and Shendra – Bidkin have submitted Investment 6 for 1425.36 (combined area- the report on Development Plan, Industrial Park. Pre-Feasibility Region, Haryana hectare of land on 152 sqkm) which development of suitable 13th March 2013. study for caters to the The Development Khushkhera – Betma region. Total modifications have Section 4 for the Integrated Solid planning for Phase Control Regulation Bhiwadi – area being taken up been made by the additional area Waste I (105 sqkm) of (DCR) to be adopted Neemrana in Phase I is 10.42 technical consultant within phase 1A Management Investment Ahmedabad sq. km. Out of 2.38 for the proposed in development plan was issued. CEO for Noida and Region, Dholera sq. km. of Investment Region. for Shendra Bidkin & MD, DMICDC Greater Noida Rajasthan Investment Government land, The Reports have Industrial Park have appraised and the same Region and the 1.38 sq. km. has been submitted to been notified by the Principal Secretary has been shared Pithampur- Mega Industrial been transferred, State Government State Government. DMIC (GoR) with State Dhar-Mhow Park (45 sqkm) remaining is Forest of Haryana for during a meeting Government Investment within Phase 1). land. Notifications approval. The contract has been on 5th June, 2014, for comments. Region, Madhya All the six draft u/s 4 and 6 issued signed between about the progress Pradesh Town Planning for 8.04 sq. km. A meeting was held DMICDC and the of DMIC in the A meeting was (TP) Schemes for private land. Large on 29th November selected consultant State. It was convened under - Dholera Special numbers of writ 2013 between for the preparation of decided that the Dholera Investment petitions have been Secretary, DIPP the preliminary design comments on the chairmanship of Investment Region have been filed by the land and Chief Secretary, for the roads and reports submitted Chief Secretary, Region, Gujarat. sanctioned by the owners challenging Govt. of Haryana services/utilities and by DMICDC to Government of State Authority. the notification for to discuss the status „CBD‟ for Phase-I the State Govt. Uttar Pradesh Environment land acquisition. of DMIC projects (8.5 sq. km) of will be provided on 7th clearance has Rapid This is being in Haryana and its Shendra –Bidkin by the respective November, been obtained Environment contested by the way forward. In the Industrial Area in Government 2014 at for Khuskhera Impact State. meeting, State Maharashtra. A departments Secretariat , Bhiwadi Assessment Government of meeting was taken by within a month‟s Lucknow Neemrana (EIA) study for An Empowered Haryana, has stated CEO&MD, time. On 22nd wherein various Investment Dholera Special Committee Meeting that they are ready DMICDC on 22nd July, 2014, issues with Region in Investment chaired by Chief to move forward March, 2014 to CEO&MD, regard to Rajasthan, Region (DSIR) is Secretary was held with the acquisition review the current DMICDC had a DMIC Project Manesar Bawal complete and has on 1st September, of land required for status of the projects meeting with in Uttar Investment been reviewed by 2012 to discuss the creating trunk and issues involved Additional Chief Pradesh were Region in DMICDC. status of land infrastructure in the therein. Secretary discussed. It Haryana, acquisition and Phase-I (Infrastructure) , was decided Ahmedabad It has been other related issues development of the The RfP document Govt. of that necessary Dholera Special informed that the for development of Manesar Bawal for selection of Rajasthan to amendments Investment land for road Investment Region Investment Region. PMNC for Shendra – review the that are Region in demarcation and Early Bird Bidkin Industrial Area progress of DMIC required to be Gujarat and process for TP -3, Projects. The As per the was sent to the State project in carried out in Shendra Mega 4, 5 and 6 forming Empowered directions of Government for their Rajasthan. In the the Uttar Industrial Park. part of Phase 2 & Committee was Government of comments and meeting, it was felt Pradesh 3 of Dholera SIR provided their Haryana and the observations. The that the two Industrial area For Haryana will be made comments on the observations made comments were DMIC nodes in development (Manesar available by SHA and SSA. for in the State Level received from the Rajasthan are Act 1976 will be Bawal December 2013. review and Committee on the State Government being planned on expedited. Investment incorporation by Development Plan, and the same were the concept of Region) Principal Secretary DMICDC. Hon‟ble suitable incorporated. The Smart Cities and Minutes of the MoEF vide its (Industries & Chief Minister, modifications have RFQ cum RfP concerned efforts meeting have letter dated 23rd Mines Madhya Pradesh, been made by the document for are required to been issued. September, 2014 Department has reviewed the status Technical appointment of steer the project in CEO & MD, has accorded advised DMICDC of Investment consultant for the Programme Managers its implementation DMICDC vide final to initiate the Region and Early proposed for Phase – I (24 sq. phase. During the its letter dated Environmental preparation of Bird Projects along Investment Region. km) of Shendra- meeting, it was 23rd January, Clearance to the Detailed Project with the status of The reports have Bidkin Industrial Area discussed that to 2015 has project. Report (DPR) for land acquisition. In been submitted to was issued. The last kick start requested Chief projects in the meeting, State Government date of submission of development of Secretary, Uttar A review meeting Dholera Special consultant has been of Haryana for bid proposals was 4th smart cities in Pradesh to was held on 23rd Investment advised to approval. March, 2014 which Rajasthan, there is convene a November, 2015 Region and has reconfigure the land DMICDC has also was then extended to a need to meeting under with Principal agreed that the use of knowledge submitted the final 25th March, 2014. expeditiously his Secretary, expenditure city. In the meeting pre-feasibility Only two bids were procure/set apart Chairmanship Industries, incurred towards convened by Chief reports for the received by an area close to to discuss and Government of cost of Secretary of the projects namely: DMICDC on 25th 1000 acres. resolve all Haryana to preparation of State on 17th March 2014. In the pending issues review the DPR will be November, 2012, 1. Pre-Feasibility meeting held on 15th SIPP requested of the DMIC progress of considered as the the State has report for April, 2014 under the Chief Secretary, project in Uttar DMIC Project in equity from assured that affordable/low cost Chairmanship of Rajasthan vide Pradesh. Haryana DMIC Trust in decision on housing project SIPP, it was letter dated 14th followed by the city level SPV notification of communicated by the October, 2014 to SIPP has another meeting after its formation. development plan 2. Pre-Feasibility Principal Secretary, convene a meeting requested Chief held on 16th RfP for selection for investment report for Industries, under his Secretary of December 2015 of PMNC has region would be Education & Maharashtra, that an Chairmanship in Uttar Pradesh under the been issued to the conveyed Medical Hub area of 40.42 sq km order to discuss vide letter dated Chairmanship of seven empanelled immediately. In the of land should be and resolve all the 11th February, 3. Pre-Feasibility PS to CM, consultants and meeting with considered from an pending issues for 2015 to report for Haryana. letter of Award Additional Chief earlier area of 32.03 taking forward convene a Integrated Multi and Work order Secretary on sq km for Phase-1 of DMIC Project in meeting under Model Passenger CEO&MD, issued by December 29, Shendra Bidkin Rajasthan. his Hub DMICDC vide DMICDC to the 2012, Government Industrial Area and chairmanship th his letter dated consortium of of Madhya Pradesh accordingly all project On 17 October to discuss and TH 4. Pre-Feasibility rd 24 November, M/s AECOM provided details of development 2014 and 3 resolve all report for 2015 has Asia Company available land for activities should be November 2014, pending issues developing requested the Ltd. All the Phase I undertaken by CEO &MD, relating to Gurgaon-Bawal State preliminary development. In DMICDC. DMICDC had a DMIC project Mass Rapid Transit Government to documents for the the meeting held on meeting with in the State of identify and development of 6th May, 2013, the The RFQ-cum-RFP Principal make the land infrastructure at State Govt. has System document for the Secretary, DMIC, Uttar Pradesh. available for Dholera SIR have assured that the selection of Government of taking forward been handed over Development Plan 5. Pre-Feasibility Programme managers Rajasthan to A meeting was the DMIC the PMNC will be notified by report for for Phase-1 (40.42 sq review the held under the Project in the consultant and the the Town & Freshwater km) of Shendra- progress of DMIC Chairmanship State of Haryana. consultant has Country Planning (conveyance) from Bidkin Industrial Area project in of Principal been directed by Department by Tajewala was issued. However, Rajasthan. Secretary A review meeting DMICDC to June, 2013. Headworks due to inadequate (Industries), was held on 15th initiate CEO, DMICDC response, DMICDC Govt. of UP on January, 2016 implementation of vide his letter dated All the pre- had initiated a fresh 5th February, under the projects at the 17th September, Feasibility reports bid process for The Tenth State 2016 followed Chairmanship of earliest. In a 2013 had requested have been finalized selection of Steering by another Chief Minister, meeting held on the State Programme Managers Committee on meeting under incorporating the Government of 12th April, 2013 at Government to for Phase-1 (40.42 DMIC project was the comments/ th Haryana to DMICDC with expedite the Sq.km) of Shendra- held on 11 Chairmanship suggestion/ review the the Programme notification of Bidkin Industrial December, 2014 of CEO, progress of Managers Development Plan Area. On the last date in Jaipur. GNIDA to observation of the DMIC Project in (PMNC) and the and framing of of submission i.e. discuss the way State Government Secretary, Haryana and to officials of GIDB, rules under the new 22nd September, 2014, forward for the of Haryana. Industrial Policy discuss the way PMNC has been Act. Proposal for three bids have been project. forward. and Promotion advised to initiate inclusion of the MoEF vide its letter received. The (SIPP) vide letter A meeting was the process of new node i.e. rd evaluation of bids is dated 23 dated 13th May, Further meeting procuring the Proposal for under process. held under the th September 2014 2015 has was held on 11 consultants for inclusion of the Chairmanship has accorded final requested Chief February, 2016 detailed design for new node i.e. The Programme of Principal Environmental Secretary, Govt. to discuss the roads (total length Shahjapur-Dewas Managers for Phase – Secretary Clearance for of Rajasthan to way forward of approximately Industrial Area was I (40.42 sq.km) of (Infrastructure Manesar Bawal expedite the based on the 550 km) along placed for seeking Shendra-Bidkin and Industrial Investment Region. enactment of the decisions taken with the utility approval from the Industrial Area have Development), in the aforesaid Special Government of corridor including DMIC Trust in the SIPP has requested been appointed and meeting. Investment Uttar Pradesh Power, Water, meeting held on 6th Additional Chief have started working Region Act. The on 16th March ICT, Sewer, Storm December, 2013. Secretary, Haryana on the assignment. Secretary, DIPP comments on 2016 regarding Water Drainage After due vide his letter dated vide his letter The consultant Draft Special the pending etc. for Town deliberations in the 14th October, 2014 dated 2nd March, appointed for the Investment issues relating Planning 1 and 2 meeting, the same to convene a 2016 has preparation of the Region Act have to DMIC (TP1) and (TP2). was deferred and meeting under the requested the preliminary design for been forwarded by project. PMNC has been would be placed Chairmanship in Chief Secretary, the roads and DMICDC to the advised to review before DMIC Trust order to discuss and Government of service/utilities and State GNIDA has the DPR prepared after receipt of resolve all the Haryana to provided the by the Gujarat additional „CBD‟ for Phase – resolve the State Road information from pending issues for (8.5 sq, km) of Government. list of 15 pending issues Development the State taking forward Shendra – Bidkin villages to be for moving Corporation Government. The DMIC Project in Industrial Area The Program included in forward with the (GSRDC) for S.H. same was from the Haryana. (SBIA) in Manager tender DNGIR in lieu DMIC Project 36 and DPR State Government Maharashtra, had document for of 10 villages expeditiously. prepared by and are under A meeting was submitted the KBNIR was forming part of WAPCOS for examination. convened under the inception report and issued and the Rivaj Hitech For Rajasthan Flood Detailed Chairpersonship of the same was proposal due date Township. A (Kushkhera vulnerability on information Chief Secretary approved. was 2nd January revised list of Bhiwadi priority basis. The regarding land Haryana on 20th 2015 Three (3) the villages is Neemrana State department infrastructure from February 2015 to The consultant has bids have been being prepared Investment has confirmed to the State discuss the pending further submitted the received by the and will be Region node) execute the Government is issues and way technical assessment proposal due date provided to project only after awaited. forward for DMIC report and is currently and the same were GNIDA soon. MoEF has incorporation of projects in Haryana. working on evaluated. As two accorded final observations of A meeting was held preliminary designing out of three Environmental PMNC on these under the CEO & MD, of trunk bidders were not Clearance to the two projects. chairmanship of DMICDC vide infrastructure and qualified at the th project. PMNC has also Chief Secretary, letter dated 11 Master planning technical stage been advised to Government of May, 2015 has alternative for 50 itself, it was Gujarat explore the Madhya Pradesh on requested Chief acres of CBD. decided to (Ahmedabad- possibilities of 16th July, 2014 to Secretary, retender the Dholera undertaking the discuss the issues Government of Meetings were held assignment. Investment potable water related to the Haryana for under the co- Region) project from project. In the attending a meeting chairmanship of SIPP has The application Periaj reservoir meeting, it was under the Principal Secretary requested Chief for the public and industrial informed that chairmanship of (Industries), Secretary, hearing for water from Town & Country Secretary, DIPP to Government of Rajasthan vide its Environment th municipal waste Planning discuss the progress Maharashtra and letter dated 11 Clearance was water of Department will of DMIC project in CEO&MD, February, 2015 to submitted by th Ahmedabad notify the Draft the State of DMICDC on 20 convene a meeting DMICDC to Municipal master Plan after Haryana. October, 2014 and under his Gujarat Pollution th Corporation on the approval of 13 January, 2015 to Chairmanship in Control Board A meeting was held PPP basis. RfP for Dept. of Urban review the progress order to discuss (GPCB). on 2nd June, 2015 selection of Development. In and the way forward and resolve all the Extension of under the consultant to the meeting, MD, for DMIC project in pending issues for validity of Terms Chairmanship of prepare the MPTRIFAC was Maharashtra. taking forward of References Secretary, DIPP in preliminary design directed to take DMIC Project in has been the presence of The project report for for the roads and necessary action for Rajasthan. accorded by the Chief Secretary, the proposed Water services/utilities formation of expert Appraisal for Town city/node level SPV Government of Supply Scheme for CEO & MD, Committee of Planning (TP2) for taking forward Haryana to discuss SBIA was received DMICDC vide its MoEF. The Scheme has been the development of the pending issues from MIDC and has letter dated public hearing issued. the investment relating to the been shared with the 3rdFebruary 2015 for Environment Approximately 50 region. DMIC projects in consultant. has requested for Clearance has sq km of land area the State of support from been conducted which constitutes SIPP has requested Haryana. The Special Advisory State Government successfully on the area on the Chief Secretary, Panel of DMICDC, in addressing the 03rd January, eastern side of Madhya Pradesh in its meeting held on pending issues 2014 by Gujarat TP2 with around vide hid letter dated 19th August, 2014 had with regard to the Pollution 170 km of roads is 14th October, 2014 reviewed the current implementation of Control Board proposed for to convene a status and issues the DMIC project (GSCB). The development in meeting under his related with in Rajasthan. final EIA report the RfP Chairmanship in preliminary design for has been document. order to discuss and the roads and A review meeting submitted to Letter of Award resolve all the services/utilities and was held on 9th DSIRDA. The for Consultancy pending issues for „CBD‟ for Phase – I March 2015 under final EIA & Services for taking forward (8.5 sq. km.) of SBIA. the Chairmanship EMP Report has Preparation of DMIC Project in of Additional been submitted Madhya Pradesh. A meeting was held Chief Secretary to MoEF on Letter of Award under the co- (DMIC Project) 20th May 2014 for Consultancy Shareholders‟ chairmanship of Government of and was Services for Agreement and CEO&MD, Rajasthan at appraised by Preparation of State Support DMICDC and CEO, Jaipur. nd Expert Appraisal Preliminary Agreement for the MIDC on 22 Committee of Design Report for nodal / city level August, 2014 to CEO&MD, MoEF in its Roads and SPV has been discuss the issues and DMICDC has 136th Meeting Services/Utilities executed. the way forward for requested Chief held on 30th July, of Town Planning DMIC Project in Secretary,

2014. The Scheme – 2 (East) Maharashtra. Rajasthan vide his th committee has and Town letter dated 8 RfP cum RfQ recommended Planning Scheme June, 2015 to document for the proposal for – 2 (West) were expedite the Preliminary environmental issued to the enactment of the Engineering of Bidkin Special clearance. MoEF selected Industrial Park of 32 has issued a consultants. The Investment sq.km. had been formal letter of consultants have Region Act and issued on 28th approval dated mobilized the execution of November, 2014. 19th September, team. The Shareholders The bid process was 2014 in this consultants Agreement (SHA) regard. appointed for the annulled and & State Support CRZ clearance is Preliminary DMICDC has Agreement (SSA). important for Design Report for initiated a fresh EIA clearance of Roads and bidding process, The A meeting was Dholera SIR and Services/Utilities RFP-cum-RFQ held under the is being pursued of Town Planning document for the chairmanship of by the State Scheme – 2 (East) project was issued on Chief Secretary, Government. and Town 11th March, 2015 Rajasthan on 27th

For the same, Planning Scheme Pre-Bid meeting was July 2015 to th discuss all the CEO-DSIRDA – 2 (West) have held on 20 March, made a submitted their 2015 and the last date inter- presentation to inception reports for submission of the Departmental Gujarat Pollution after incorporating proposal is on 16th issues involved in control Board DMICDC‟s April, 2015.Five bids the proposed (GPCB) and comments. The have been received till Rajasthan Inv- Gujarat Coastal consultants for the proposal due date estment Region Zone both Town and the same are (SIR) Ordinance, Management Planning Scheme- under evaluation. 2015. Authority 2(East) and Town

(GCZMA) on Planning Scheme - The progress of CEO & MD, 20th March, 2014. 2(West) have phase-1 of Shendra- DMICDC has

Further Details further submitted Bidkin Industrial Park requested Chief in Maharashtra was Secretary, were sought the Draft from DSIRDA Architectural informed to the Rajasthan vide his letter dated 23rd with respect to design drawing Board of Trustees of the infrastructure report (3rd DMIC Project October, 2015 to proposed to be deliverable) DMIC Implementation Trust expedite the land developed in the and the same has Fund in its 8th acquisition and areas coming been approved Meeting held on 25th enactment of the under CRZ September, 2014. Special regulations in Preliminary Investment DSIR. DSIRDA Design for Roads Consultant appointed Region Act. has submitted and services / for conducting Site CEO&MD, the necessary Utilities of Town Survey works for DMICDC has details vide their Planning Scheme Shendra Bidkin requested Chief letter dated 17th – 2 (East) and Industrial Area is Secretary, April, 2014. Town Planning moving forward with the demarcation of Rajasthan vide his For Madhya Scheme – 2 (West) letter dated 23rd Pradesh is currently 8.5 sq. km. i.e., November, 2015 (Pithampur- underway. The Shendra Industrial Dhar-Mhow Town Planning Area. Contour to resolve the Investment Scheme 2 (West) Surveys for the pending issues Region) Design Basis Bidkin Industrial Area with regard to A district level Report was is under progress. DMIC Project in coordination submitted by the the State of meeting among design consultant The Shareholders Rajasthan. stakeholders was and has been Agreement and State convened at approved. Support Agreement CEO & MD,

Indore on 14th for incorporation of DMICDC vide his The Design Basis the SPV between letter dated 24th May 2014 under the chairmanship reports (4th DMIC Trust and the November, 2015 of Principal deliverable) have State Government of has requested the Secretary been reviewed and Maharashtra were State Government (Commerce, comments on the executed. to identify and Industry & same have been make the land Employment) shared with the Node/ city level SPV available for Government of consultant. for between DMICDC taking forward the Madhya Pradesh incorporation the and Govt. of DMIC Project in regarding the same by the Maharashtra has been the State of th way forward for consultant. incorporated on 19 Rajasthan. public hearing December, 2014 by for EIA of The design the name A meeting was consultant for “Aurangabad held under the Pithampur - Dhar – Mhow TP2 East has Industrial Township Chairmanship of submitted the Limited” with an Chief Secretary, Investment Region, Madhya draft preliminary initial authorized Rajasthan on 2nd th Pradesh. design report (4 capital of Rs.10 crore December, 2015 deliverable) which and paid up capital to resolve the The ToR has been reviewed of Rs.1 crore. The pending issues clearance for the and commented first Board Meeting with regard to Shendra and upon. of Aurangabad DMIC Project in Bidkin Industrial Industrial Township the State of Park has been The comments are Limited (AITL) was Rajasthan. It was granted by being held on 19th decided that the

MoEF. The EIA incorporated by December, 2014 to State Government studies for the consultant. discuss the way will finalise the

Shendra and forward for DMIC SIR Act before The 3rd Meeting of Bidkin Industrial project in 31st December, Special Advisory Park based on Maharashtra. This 2015. Panel of the ToR was followed by obtained from DMICDC was Extra Ordinary Secretary, DIPP MoEF is under convened on 19th General Meeting vide his letters progress. August, 2014 to wherein the dated 2nd March DMICDC has review the current authorized share 2016 and 26th submitted the status and issues capital has been July, 2016 has Draft EIA report on MRTS Project increased to Rs.6200 requested the for Shendra between crore. Chief Secretary, Industrial Area Ahmedabad and Government of to Maharashtra Dholera Special Government of Rajasthan to Maharashtra has Pollution Investment resolve the Control Board Region (DSIR) transferred the land pending issues for (MPCB) for and Preliminary to the SPV and moving forward conducting Design of Roads DMIC Trust has with the DMIC Public Hearing. and Services. released its initial Project equity to SPV. expeditiously. The Public A meeting was Hearing was held on 31st SIPP vide its letter A meeting was conducted on October, 2014 dated 6th May, 2015 held on 9th 30th October, under the has requested Chief August, 2016 2014 in Shendra, Chairmanship of Secretary, under the Aurangabad. CEO&MD, Government of Chairmanship of

Final EIA report DMICDC with Maharashtra to Addl. Chief has been TCE to review the transfer the balance Secretary, DMIC, prepared and progress of land to the SPV so Government that tender document submitted to preliminary design MoEF through study for TP-2 for trunk of Rajasthan to online portal and West. infrastructure discuss the status the same has component can be of various projects been accepted. To kick start the floated soon after the to be developed Further, development, an approval of CCEA on under DMIC DMICDC has Activation Area of the final note. project in also submitted 22 sq km has been Principal Secretary, Rajasthan. the hard copies identified which Government of of the EIA would act as Maharashtra has Secretary, DIPP report to MoEF. catalyst for further responded vide letter vide his letter The project investments. The dated 7th May, 2015 dated 16th would be taken project was placed requesting for November, 2016 before the Board infusion of equity has requested the up in the Expert Appraisal of Trustees in the matching to the value Chief Secretary, committee meeting held on of land admeasuring Government of meeting which is 10th March, 2014 8.39 sq. k. by the Rajasthan to likely to be held for investment Government of India. resolve the shortly. The approval. pending issues for EIA study for However, it was MIDC vide its email moving forward Bidkin Industrial decided that dated 21st October, with the project Area is under DMICDC/DIPP 2014 forwarded the expeditiously. progress. will analyze the revised Articles of DMICDC has matter and inform Association of the requested that why a low proposed node/city level SPV. A extension of equity base model Terms of for node/city level confirmation was sent

Reference SPV and the by the DMICDC vide validity to MoEF transfer of its email dated 27th through online Government of October, 2014 on the revised Articles of portal and the India‟s same has been contribution in Association. accepted. tranches (project Formation of SPV is Further, wise) will not be being taken forward DMICDC has feasible to take by the State also submitted forward the Government of the hard copies development of Maharashtra. The of ToR to new Industrial proposal for formation of MoEF. Both the Cities. In this proposals were regard, DIPP has node/city level SPV taken up in the sent a letter to was placed before the 147th Expert DEA explaining Board of Trustees in

Appraisal why release of the meeting held on 10th March, 2014 and Committee funds in tranches meeting held on (project wise) will the same was 24th April, not be feasible. In approved with 51% 2015.The Expert this regard, participation from Appraisal matters related to State Govt. and 49%

Committee allocation of funds participation of (EAC) has were discussed by DMIC Trust with an recommended the DMIC Trust initial capital base of Rs.10 crore. Steps the Environment in its meeting held Clearance for on 25th June, have already been

Shendra Mega 2014. It was initiated for the Industrial Park decided in the formation of and extension of meeting that the node/city level SPV the validity of node/city level for Shendra Bidkin Bidkin Mega SPVs may be Industrial Park in Industrial Park formed for the Maharashtra. TOR till 26th above node-level February 2016. project with an To kick start the initial equity development in

Revised contribution of Shendra Bidkin Environmental Rs.250 crores by Industrial Area in

Clearance is the DMIC Trust. Phase I comprising of being obtained 32.30 sqkm has been The remaining for Shendra part of Trust‟s identified which Mega Industrial equity will be would act as catalyst Park. released in for further tranches based on investments. The Ministry of the expenditure project was placed Environment, phasing of funds before the Board of Forest and released earlier. Trustees in the Climate Change meeting held on 10th vide letter dated It the meeting March, 2014 for 10th June, 2015 held on 8th investment approval. has informed August, 2014 However, it was

DMICDC that under the decided that the validity of Chairmanship of DMICDC/DIPP will

ToR for Bidkin Additional Chief analyze the matter Mega Industrial Secretary, and inform that why a Park has been Industries, low equity base th extended till 26 Institutional model for node/city February, 2016. Framework for level SPV and the Ahmedabad transfer of Revised Dholera Special Government of Environmental Investment India‟s contribution Clearance is Region was in tranches (project being obtained discussed and it wise) will not be for Shendra was decided that a feasible to take

Mega Industrial team will be sent forward the Park for revised to DMICDC development of new master plan. The office to take the Industrial Cities. In proposal of matter forward. this regard, DIPP has DMICDC for sent a letter to DEA issuance of MoEF has explaining why Addendum to accorded release of funds in EC was Environment tranches (project considered by Clearance for wise) will not be EAC of Ahmedabad feasible. MoEFCC in its Dholera Special 153rd meeting Investment In this regard, matters held on 20th Region vide its related to allocation November, letter dated 19th of funds were

2015.The same September, 2014. discussed by the DMIC Trust in its has been recommended by Further, a meeting held on 25th the EAC as per meeting was held June, 2014. It was minutes of the on 15th October, decided in the meeting. 2014 with State meeting that the Nodal Agencies node/city level SPVs The proposal for and DMICDC to may be formed for extension of discuss the the above node-level validity of ToR Institutional project with an initial for Environment Framework and equity contribution of Clearance of Shareholders‟ Rs.250 crore by the JPMIA was Agreement (SHA) DMIC Trust. The considered by and State Support remaining part of EAC of Agreement (SSA) Trust‟s equity will be

MoEFCC during for formation of released in tranches th their 157 node/city level based on the meeting held on SPV. Revised expenditure phasing 28th March, 2016. draft SHA and of funds released The Ministry has SSA has been sent earlier. approved the by DMICDC vide extension of its email dt.27th SIPP requested validity of the October, 2014 to Principal Secretary ToR for a further the State (Industries), period of one Government of Maharashtra vide his year up to 11th Gujarat for letter dated 14th

November, 2016. comments/concur October, 2014 to rence. convene a meeting

Draft EIA report under his for Bidkin mega SIPP has Chairmanship in

Industrial Park requested Chief order to discuss and has been Secretary, Gujarat resolve all the submitted to vide his letter pending issues for Maharashtra dated 6th May, taking forward DMIC Pollution 2015 to confirm Project in Control Board the availability of Maharashtra. for conducting the land Public hearing admeasuring 22.5 SIPP vide its letters for the project. sq.km for the dated 12th December Public Hearing development of 2014 and 11th has been trunk February 2015 had th requested Chief completed on 5 infrastructure in February, 2016. the activation area Secretary of and the same Maharashtra The would be regarding approval Environment transferred to the and notification of Clearance SPV immediately Development Control proposal for after its Regulation (DCR) Bidkin incorporation so and for resolution of Industrial area that RFQ cum pending issues with was considered RFP for the trunk regard to DMIC by the Expert infrastructure can project in Appraisal be floated soon Maharashtra.

Committee after the approval (EAC), CEO & MD, of CCEA on the MoEF&CC final note. The DMICDC vide his th letter dated 6th during its 159 same has been meeting held on confirmed by January, 2015 has 30th May, 2016. chief Secretary of requested Principal The EAC Gujarat vide his Secretary (Industries) recommended to letter dated 13th for transfer of land to study the best May, 2015. the SPV along with practices adopted the exemption from in the developed SIPP has further payment of stamp countries and requested Chief duty on the same. emerging Secretary, Gujarat economies vide its letter MIDC will be internationally dated 12th May, submitting a formal for assessing the 2015 followed by proposal to the Town and Country Planning pollution loads another letter from such kind dated 1st June, Department for of large industrial 2015 to Additional notification of Plan of hubs and to Chief Secretary, 8.39 sq.km. of present the Gujarat to issue Shendra Industrial information on necessary Park by the the issues in the directions to Government of next meeting of expedite the Maharashtra. EAC. The processes with desired details regard to The Development have been execution of Control Regulation submitted to Shareholders (DCR) to be adopted in development plan MoEF&CC by Agreement (SHA), DMICDC vide State Support for Shendra Bidkin its letter dated Agreement (SSA) Industrial Park has 20th July,2016. and the been approved by incorporation of Hon‟ble Chief The node/ city level Minister of Environment SPV for Maharashtra and the Clearance Ahmedabad notification process proposal for Dholera Special for the same is in Bidkin Industrial Investment region progress.

Area has been in Gujarat along approved by the with transfer of The Consultant

Expert Appraisal entire land to the appointed for the Committee preparation of the node/ city level (EAC), SPV. preliminary design for the roads and MoEF&CC during its 164th Government of services/ utilities and meeting held on Gujarat vide its „CBD‟ for Phase – 1 1`st December, letter dated 3rd (8.39 sq. km) of 2016. June, 2015 has Shendra-Bidkin, in informed that Industrial Area The Industrial & Mines (SBIA) in Environment Department, Maharashtra has Clearance for Government of submitted the design Bidkin Industrial Gujarat has issued basis report and draft

Area was a Governmental Preliminary Design obtained by Resolution Reports and the same

MoEF&CC vide authorizing have been sub mitted letter dated 21st to State Government DSIRDA for February, 2017. transferring 5205 for their comments. Ha land as equity The 2nd Board ToR Clearance participation in meeting of the for Jodhpur- the proposed SPV Aurangabad industrial Pali-Marwar for Dholera. Township was held Industrial Area on 27th March, 2015. has been State Government accorded by the of Gujarat has The public hearing

Expert Appraisal informed that the was conducted on Committee of State Cabinet has 30th October 2014 in

MoEF and EIA given „in principle‟ Shendra, Aurangabad. approval with Final EIA report has study is under progress. regard to node/ been prepared and city level SPV submitted to MoEF A meeting was formation and through online portal taken by draft Shareholders and the same has CEO&MD, Agreement subject been accepted. DMICDC on to mutual Further, DMICDC 24th March, 2014 acceptance and has also submitted to review the most importantly the hard copy of the current status of the land parcels to EIA report to MoEF. EIA studies, be transferred to The EIA study for public hearings the city level SPV, Bidkin Industrial area and submission pending paper is under progress. of final EIA work formalities. .DMICDC has reports to requested extension DMIC Trust in its MoEF. of Terms of 10th meeting held Reference validity to th The proposal for on 19 March, MoEF through online extension of 2015 has portal and the same validity of ToR approved the has been accepted. for Environment Shareholders‟ Further, Clearance of Agreement (SHA), JPMIA was State Support DMICDC has also considered by Agreement (SSA) submitted the hard EAC of for execution copy of ToR to MoEFCC during between DMIC MoEF.Both the their 157th Trust and State proposals were taken meeting held on Nodal Agency . up in the 147th Expert 28th March, Further, MOA Appraisal Committee

2016. and AoA along meeting held on 24th with the The Ministry has formation of April 2015. approved the node/ city level extension of SPV have also The Expert Appraisal validity of the been approved by committee (EAC) has ToR for a further the DMIC Trust. recommended the period of one Environment year up to 11th The issues related clearance for Shendra November, 2016. with the provision Mega Industrial Park

The proposal for of transmission and extension of the and distribution of validity of Bidkin validity of the Terms (TOR) power within Mega Industrial Park, th for JPMIA for DSIR was TOR till 26 another period discussed with February, 2016. of one year i.e. Power Grid for validity till Corporation of Ministry of 11th November, India Limited Environment, Forest 2017 has been (PGCIL) and and Climate Change, th sent to DMIC in the vide letter dated 10 MoEF&CC vide meetings June, 2015 has letter dated 30th convened on 12th informed DMICDC July, 2016. September, 2014 that the validity of

and 5th February, ToR for Bidkin Mega The proposal for 2015. Industrial Park has extension of the been extended till 26th CMD, PGCIL February, 2016. validity of the ToR was enlisted stated that wire The proposal of in the 162nd business frame Meeting of the work DMICDC for Expert Appraisal authorization is in issuance of Committee the pipeline of Addendum to EC (EAC) held on electricity reforms was considered by 30th August, and is expected to EAC of MoEFCC in rd 2016. The take upward of 2 its 153 meeting held th proposal has years before the on 20 November, been approved law is passed and 2015. The same has by the EAC. SERCs are ready been recommended

to take it forward. by the EAC as per The revised EIA Therefore, the minutes of the report after keeping in view of meeting. incorporating the DSIR schedule, changes as per CMD, PGCIL Draft EIA report for the Notified suggested that Bidkin mega Development DSIR may engage Industrial Park has Plan has been with local Transco been submitted to sent to the State (GETCO) and Maharashtra Pollution Discom (GUVCL) Pollution Control

Control Board, for sourcing of Board for conducting Rajasthan vide power to DSIR. Public hearing for the letter dated 19th project. Second workshop December, 2016 for seeking an on ICT with the Public Hearing for early date for industry players Bidkin EIA conducting was conducted on conducted on 5th Public hearing. 13th December, February, 2016. 2014 and based on DMICDC has The Public the discussions/ submitted all hearing was inputs, steps have documentation to conducted on been initiated for MoEF&CC for grant 15th March, 2017 the appointment of final environment at Rohat. of the ICT clearance on 12th consultant before April, 2016.

The proposal for moving forward grant of with the The DMIC Trust in

Environment appointment of its 15th meeting held Clearance for the on 26th July, 2016 has the Master Jodhpur Pali Systems approved the Marwar Integrator. proposal for Industrial Area development of trunk (JPMIA) project DMICDC infrastructure in Rajasthan was conducted a components in the approved in the meeting on Power Bidkin industrial Area 171st meeting of Strategy and (approx.32 sq.km.) as the Expert Renewable Energy Phase – II Appraisal on 13th April 2015 development of the Committee with all the Shendra Bidkin (EAC) held on Consultants and Industrial area (SBIA)

12th May, 2017. AECOM Global near Aurangabad, The EAC has expert presented Maharashtra with an recommended the approach to estimated value of the Environment be followed for Rs.6414.21 crore. Clearance for the making smart and The Cabinet project as per the sustainable power Committee on Minutes of the system for DSIR. Economic Affairs meeting issued. (CCEA) approved the SIPP has Development of The validity of requested Chief Trunk Infrastructure the Terms of Secretary, Gujarat Components as part Reference (ToR) vide his letter of Phase – II for Dighi Port dated 14th development of Industrial Area October, 2014 to Shendra Bidkin (DPIA), convene a meeting Industrial Area in Maharashtra & `under his Maharashtra under Pithampur - Chairmanship in Delhi Mumbai Dhar -Mhow order to discuss Industrial Corridor Investment and resolve all the (DMIC) Project on Region pending issues for 15th November, 2016 (PDMIR), taking forward with an estimated Madhya Pradesh DMIC Project in cost of Rs.6,414.21 has expired on Gujarat. crore 27th May 2014. DMICDC has Based on various The Environment requested MoEF rounds of Clearance proposal for extension of Industry for Bidkin Industrial the ToR through consultation, it has Area was approved by been decided that letter dated 28th the Expert Appraisal April, 2014 for the ICT Committee (EAC), PDMIR, Madhya Consultant will be MoEF&CC during its Pradesh and appointed for 164th meeting held on letter dated 29th laying down 1st December, 2016. April, 2014 for detailed BoQs for DPIA, various hardware Letter of Award has Maharashtra. and software been issued to the DMICDC has components. selected consultant been following Draft RFQ cum for Preliminary up with MoEF RFP has been Engineering of Bidkin on the above uploaded on Industrial Park of 32 matter through a DMICDC‟s sqkm. website and due letter dated 22nd May, 2014 and date of submission The Consultant has of bid is 13th completed 80% of 26th May, 2014. April, 2015. the topographical survey. A letter from CEO&MD, MoEF has been DMICDC vide his The proposal of received in letter dated 23rd DMICDC for response to the January, 2015 has issuance of letters from requested CEO, Addendum to EC DMICDC GIDB to convene was considered by wherein it is a meeting in order EAC of MoEFCC in directed to apply to discuss and its 153rd meeting held afresh to obtain resolve all the on 20th November, fresh ToR along pending issues for 2015. with filled in taking forward Form -1 as DMIC Project in Proposal for funding prescribed in Gujarat. and issuance of EIA notification tenders for creation 2006 of MoEF. A meeting was of five (5) trunk The fresh held between infrastructure application along Secretary, DIPP components for with filled in and Additional phase 1 (8.390 Form-1 for both Chief Secretary, sq.km.) of Shendra projects has been Gujarat on 31st Bidkin Industrial Park submitted to July, 2015 to in Maharashtra have

MoEF vide letter discuss the been submitted to th pending issues DMIC Trust vide dated 27 June, 2014. The including the letter dated 13th proposals for matter of February, 2015. two nodes viz. execution of SHA, Dighi Port SSA, transfer of The tender Industrial Area in land delineated in documents along with Maharashtra and Survey No.18/1 Preliminary Design Pithampur-Dhar- to the SPV etc. Report for Roads and Mhow Services, Rail Over Investment Further, Secretary, Bridges/ region in DIPP has Administrative Rajasthan were requested Chief building. Water considered for Secretary, Gujarat Treatment Plant extension of ToR vide its letter (WTP)/ Sewerage th in the 136th dated 12 August, Treatment Plant Expert Appraisal 2015 to decide on (STP)/ Common Committee the cost of the Effluent Treatment meeting of land to be Plant (CETP) and MoEF held on transferred to SPV Landscaping were 30th July, 2014. and to get the stay approved by the The Committee order of the DMIC Trust in its has finalized the Hon‟ble High 10th meeting held on additional ToRs Court vacated March 19, 2015. afresh for immediately. carrying out EIA Additional Chief Cabinet Committee on Economic Affairs studies. Secretary, Government of (CCEA) in its th The application Gujarat clarified meeting held on 30 for approval of the key points May, 2015 has Terms of including the cost approved the five (5) Reference (ToR) of land, to trunk infrastructure for carrying out Secretary, DIPP packages in the area the EIA study vide his letter of 8.39 Sq.Km as part for the proposed dated 15th of phase – 1 IIT, Greater September, 2015. development of Noida project Shendra Bidkin has been Further, CEO & Industrial Park in submitted to MD, DMICDC DMIC project. State Expert had requested Shri

Appraisal Arvind Agrawal, RfQ cum RfP document for Committee Additional Chief (SEAC) on 12th Secretary, selection of ICT October, 2016. Industries and Consultant for SBIA Mines, (8.39 sq.km) has been The Terms of Government of issued on 29th June, Reference (ToR) Gujarat vide his 2015. for carrying out letter dated the EIA study 22.9.2015 to Pre-bid meeting was th for the proposed confirm whether held on 13 July, IIT, Greater the activation area 2015. Corrigendum

Noida project of 22.5 sq.km. for along with employer has been which the responses to queries approved in the approval of Union has been uploaded on 298th meeting of the website and Cabinet has been the State Expert obtained by DIPP Proposal submission Appraisal for the date has been Committee development of extended from 14th (SEAC) held on trunk September 2015 to 5th 25th November, infrastructure October, 2015. 2016. The EIA components in report has been DSIR is ready for Two bids have been uploaded to transfer to the received by the

MoEF&CC on SPV, as State proposal due date and 9th June 2017. Government‟s the same are under

matching equity. evaluation. The ICT The Terms of Consultant for SBIA Additional Chief Reference (TOR) Secretary, (8.39sq. km) has been for carrying out Government of appointed and the the EIA study Gujarat, in letter of award has for the proposed response to the been issued. Bhiwadi above letter has International confirmed vide his Kick off meeting Airport, District letter dated conducted with ICT Alwar, Rajasthan 24.09.2015 that consultant at was considered the State Govt. Programme office in by the Expert can transfer about Aurangabad and Appraisal 1086 hectare issued ICT Master

Committee Government land Plan and relevant (Infra-2) in its drawings to ICT in Activation Area 19th meeting held to the SPV. He Consultant. The th Consultant has on 28 June, has further 2017. informed that the submitted the State Cabinet Inception report on The approval for 24th April, 2016. Environment exemption of Meetings with various Clearance for the Stamp Duty, data service providers Jodhpur –Pali transfer fees etc. is were held on 24th Marwar expected soon all May, 2016 to discuss Industrial Area the procedures for the business model (JPMIA) project the same have for delivery of data in Rajasthan has been done. been granted by and communication the MoEF&CC The Board of service. vide letter dated Trustees in their In accordance with 14th July, 2017. meeting dated 14th the decisions of the October, 2015 Final EIA report were apprised of 11th Trust meeting of Integrated the status of land held on 29th June, Industrial in the Activation 2015 additional equity Township Area in Dholera of Rs.352.8 crore has Project at Special been released to the Greater Noida Investment node/ city SPV on has been Region and the 22nd July, 2015. The submitted and proposal for State Government of the matter has release of equity transferring the land been placed for with regard to the matching to the the consideration available land was equity of DMIC of Expert considered by the Trust. Appraisal Trustees. and the Committee same was Tender documents (EAC) in its approved. for Package I (Roads meeting and Services) have scheduled on Shareholder‟s been issued on 7th 12th September, Agreement (SHA) August 2015. 2017. and State Support Agreement (SSA) Bid submission date The Terms of have been has been extended to

Reference (TOR) executed between 20th November, for carrying out DMIC Trust and 2015. the EIA study DSIRDA on 18th 4 (four) bids have for the proposed November, 2015 Bhiwadi and 28th March, been received on 20th November, 2015. International 2016 respectively.. Airport, District Technical Evaluation Alwar, Rajasthan A Special Purpose is under process. has been issued Vehicle by the Secretary, DIPP vide by the MoE&CC name “Dholera his letter dated 4th vide letter dated Industrial City March, 2016 has 17th August, Development requested the Chief 2017. Public Limite0d Secretary, hearing for the (DICDL)” has Government of project was held been incorporated Maharashtra to on 12th for the development of resolve the pending September, 2018. Dholera SIR. The issues for moving The equity share of forward with the Environment DMIC Trust has DMIC Project Clearance for been released and expeditiously. Integrated land has been Industrial transferred to the Secretary, DIPP vide Township SPV by the State his letter dated 4th Project at Government. March, 2016 has

Greater Noida requested the Chief was considered Secretary, DIPP Secretary, and vide his letter Government of dated 2nd March, Maharashtra to recommended by the Expert 2016 has resolve the pending Appraisal requested the issues for moving Committee Chief Secretary, forward with the (EAC) in its Government of DMIC Project meeting held on Gujarat to resolve expeditiously. 12th September the pending 2017. issues for moving The Environment forward with the Clearance for Bidkin The DMIC Project Industrial Area was Environment expeditiously. received by the Clearance for MoEF&CC vide

Integrated The Additional letter dated 21st Industrial Secretary, DIPP February, 2017.

Township alongwith CEO&MD, CEO&MD, Project at Greater Noida DMICDC visited DMICDC along with Shri P.K. Dash, has been granted the site at Dholera by the to review the Independent Director MoEF&CC vide progress of of DMICDC visited letter dated activities on 12th the site to review the th 27.11.2017 August, 2016.In progress on 13 addition, 527 Ha February, 2017. Power Projects of land has been transferred to the EPC Contractor for Project SPV on 12th AURIC HALL: development September, 2016 The RfQ cum RfP activities for 5 and additional for Selection of EPC Gas Based equity of Contractor for Power Projects Rs.303.87 crore as Design Construction with capacity of share of DMIC 1000-1200 MW Trust has been of Administrative each have been released to the Building (AURIC taken up by SPV on 23rd HALL) for Shendra DMICDC at the September, 2016. was issued on 23rd following sites: July, 2016.The Pre- Meeting was held bid meeting was held

1. Chainpura under the on 19th August, 2016 Industrial Area, chairmanship of and the last date of

Distt. Guna, ACS, Department submission of Madhya Pradesh. of Industries, proposals was 13th 2. - MIDC Indapur Government of September, in Dist. Pune in Gujarat on 19th Maharashtra 2016.Only one bid September, 2016 was received by the 3. - MIDC Ville to review the Bhagad, Dist. bid due date. Due to Raigad in progress of low responses, the Maharashtra activities of the SPV (Aurangabad ad 4. - Vaghel, Distt. DMIC projects in Industrial Township Patan, Gujarat Gujarat. Another Limited (AITL)) has 5. - Rajpur- meeting was held reissued the tender on

Shahpur, Distt. under the 19th September, Mehsana, chairmanship of 2016.

Gujarat Additional Chief A sixth project Secretary The foundation stone was also under (IMD),Governme of Auric Building was consideration, nt of Gujarat on laid by Chief Minister but was not 1st October, 2016 of Maharashtra on pursued due to on allocation of 9th ovember,2016 shortage/ lack of 100 MLD potable availability of water to DSIR. EPC contractor for domestic gas for Package I (Roads and these projects. Secretary, DIPP Services) has been vide his letter appointed and For the first 4 dated 16th roadway excavation, sites, Detailed November, 2016 embankment and Project Reports has requested the subgrade filling is in have been Chief Secretary, progress along with prepared, No Government of activities relating to Objection Gujarat to resolve physical Certificates have the pending issues implementation. The been obtained relating to following works are from Airports Dholera Special under progress; Authority of Investment India (AAI) for Region for  Laying of DI pipes Power Plant moving forward and HDPE pipes for chimney height. expeditiously. potable and recycled Water allocation water networks. has been tied up Review meetings  Excavation of with State Govts. on the progress of trenches and bed and implementation of preparation for the projects in Environmental residential and Clearance from DSIR were held industrial sewer the MoEF has on 19th networks; been obtained. November, 2016,  Construction of RCC th 27 December manholes for th For Rajpur- 2016 and 14 residential sewer and Shahpur, site February, 2017 installation of HDPE investigations under the manholes for have been chairmanship of industrial sewer; completed, NOC CEO & MD,  Construction of walls has been DMICDC. and columns for received from potable water UGSR; AAI for Power Shri P.K. Dash,  Construction of walls plant chimney Independent and columns for height and TOR Director of recycled water for DMICDC had UGSR; Environmental visited the site on th  Construction of Clearances has 14 February, been approved 2017 to review the culverts/ minor by MOEF. EIA progress of bridges; studies would be construction  Delivery of DWC initiated after activities on site. pipes for residential getting sewer; confirmation Officials of  Pre-casting of RCC about the DMICDC SPV ducts for 132 KV allocation of gas visited the site on line and laying of st for other 31 July, 2018 and ducts. th projects. 29 August, 2018 to review and EPC contractor for

Project monitor the Road over-Bridges development progress of (RoB)-Package II- the activities for 5 infrastructure Contractor has been Gas Based works on site. appointed. The Power Projects The contractor following works are with capacity of was directed to under progress: 1000-1200 MW complete the each had been works as . Foundation works on taken up by scheduled and a 32 piers out of the 36 DMICDC at complete quality piers for ROB1; following sites: check was . The form work and conducted. reinforcement for 1. Chainpura CEO&MD, pier column works is Industrial DMICDC visited ongoing and 1st lift Area, Distt. the site on 23rd concreting of 16 Guna, November, 2018 columns completed Madhya to review and and 13 columns are Pradesh; monitor the completed below pier 2. MIDC progress of cap level; Indapur in infrastructure . Casting of RE wall District Pune works on site. panels for ROB-1 is

to The contractor ongoing and 27% Maharashtra; was directed to completed and

3. MIDC Ville complete the erection of the casted Bhagad, works as panels has been District scheduled and a started; Raigad; in complete quality . Excavation and PCC Maharashtra; check was for minor bridge 4. Vaghal, conducted. completed and base District Patan The equity share raft works; in Gujarat; of NICDIT has ROB 2 work has 5. Rajpur- been released started in the Shahpur, and 3027.97 Ha. available area and 13 District of land has been footings have been

Mehsana, transferred to the excavated and PCC Gujarat. SPV by the State with annular filling

Government. concrete is Project specific completed on 7 SPVs have been Activation Area footings. established and Implementation: land is being The draft EPC Contractor for taken from State preliminary design Package IV (Auric Government/ report submitted Building) Industrial by the design Development consultant for M/s Shapoorji Corporations in Town Planning Pallonji Co. Ltd. these SPVs. Scheme-2 (East) (SPCL) has been selected as the EPC Project specific of Dholera Special contractor for SPVS have been Investment Design, construction established and Region (DSIR). of Administrative land is being has been reviewed Building (AURIC taken from State by PMNC and the HALL) for Shendra Government / comments of State on 6th December, Industrial Governments 2016. Kick off Development have been meeting was held on Corporations in incorporated in 4th January 2017 with these SPVs. the preliminary the contractors of the design report.. project. (1) Chainpura Industrial In a review LOA issued to Area in meeting held on Shapoorji Pallonji Guna 8th August, 2014, Co. Ltd. on 8th District, MP the storm water October, 2018 for – 89.874ha drainage proposal EPC contract for allotted by with open channel Shendra Landscape IIDC, in the middle of works and kick off Gwalior; Activation Area meeting was held on (2) MIDC has been given „in- 22nd October, 2018. Indsapur principle‟ approval Industrial as the same was M/s SPCPL has Area, Pune considered as an submitted the various Dist., MH – economical and utilities design and 79.77 ha of optimal option. drawings for Auric land allotted GIDB has building for approval. by MIDC; requested for (3) MIDC Ville funding from The structural Bhagad DMICDC for the drawings have been Industrial SBC pipeline approved till 4th Area, Raigad feasibility and Floor. Auric city hall Dist., MH – DPR study; and schematic designs 64.3 ha of deep aquifer have been finalized land allotted testing study and the work has by MIDC. relating to ground begun on site on the water desalination same lines. The Development of project. The above building is designed these gas based studies will be for the Indian Green power projects implemented by Building Council were taken up as GICC. (IGBC) gold rating. pre-emptive Auric City Hall measure towards The process of Building received two meeting the activation area in awards for the best power Ahmedabad- Office Building and requirements in Dholera for the Best architect the DMIC Investment area in by the National region. Due to Gujarat was Awards for the the non- informed to the Design Excellence. availability of Board of Trustees domestic gas, the of DMIC Project RfQ cum RFP for projects have Implementation Preparation of become non- Trust Fund in its Detailed Design for viable. The 8th Meeting held Landscape Works for DMICDC Board on 25th AURIC – Shendra in its meeting September, 2014. Industrial Area under held on 16th Aurangabad November, 2016 SIPP has Industrial Township decided that requested Chief Limited (AITL) was DMICDC will Secretary, Gujarat floated on 30th May, initiate steps to vide his letter 2016.Three bid return the land to dated 14th proposals were the State October, 2014 to received and the Industrial convene a meeting evaluation was Development `under his completed in the Corporations Chairmanship in month of August, and refund the order to discuss 2016. The tender has money paid to and resolve all the been re-issued on 7th them in this pending issues for October, 2016. Four regard. taking forward bids have been DMIC Project in received by the bid (i) Model Solar Gujarat. due date on 16th Project in November, 2016. Neemrana, RFQ for Roads & Rajasthan: Services has been M/s Terracon MoU signed on issued on 17th Ecotech Pvt. Ltd. has 30th April 2012 November 2014, been selected for with NEDO pre-Bid meeting preparation of (Japan), MNRE, was held on 8th Detailed Design for Ministry of December, 2014, Landscape Works for Finance and pre-bid queries AURIC – Shendra DMICDC. have been Industrial Area. uploaded on 16th Tender documents Japanese December, 2014 for selection of EPC consortium to and 13(thirteen) contractor for mobilize bids were received landscaping works in technology and on February 16, Shendra Industrial resources for 2015 .Out of 13 Area was issued on Implementation. bids received 22.12.2017.Pre-bid against RFQ for meeting was held on The planned Roads & Services, 17the January, 2018. project has six firms have The bid opening date following been shortlisted was scheduled on features: for the RFP stage. 05.03.2018. The bid opening date has 5.00 MW Solar CEO, GIDB has been extended to Power Project informed CEO & 05.04.2018. Feeding Power MD, DMICDC to the vide his e-mail Tender documents Commercial Grid dated 7th July, for selection of EPC 2015 that issues contractor for 1 MW Solar landscaping works in related to Power Project Shendra Industrial confirmation of and 2.00 MW Area was re-issued on SSNNL canal st Diesel Generator 31 May, 2018. Pre- network passing Integrated with bid meeting was held through TP 2 &4 on 6th June, 2018 and Smart Micro area have been the bid submission Grid Feeding th discussed with date was on 25 June Power to 2018. Two bids have Chief Engineer, Industrial been received and the SSNNL. On the Consumers in evaluation is being basis of Neemrana finalized. discussion, they The LOA has been Industrial Park have in principle issued on 17th agreed to modify January, 2017. The The Japanese their planning for Consultant has consortium will canal network. presented Concept be mobilizing Accordingly, master plan. The RfQ cum RfP for Selection technology and CEO, GIDB has of Contractor for resources for suggested Construction of implementation. DMICDC to Landscape Works for continue the Lake-3 and all allied DMICDC had Activation Area works including approached planning in TP 2 Operation and RIICO for land & 4 of DSIR as maintenance for 18 months at AURIC allotment and per schedule. Shendra Industrial RIICO has Area was issued on allotted 30 acres The RFP for 19th July, 2017. No of land to Roads and bids have been DMICDC at services has been received by the due Japanese Zone, issued to six firms date, i.e. 29th August Neemrana. shortlisted at the 2017. RFQ stage on 20th RfQ cum RfP for Bidding process July, 2015,pre-bid Selection of for selection of meeting was Consultant for Project conducted on 19th preparation of Development & August 2015and Detailed Master Plan Implementation the 2nd pre-bid for Bidkin Industrial supervision was scheduled for area was issued on consultants is 29th September 2nd March 2016. underway 2015. The due Due to inadequate date of submission response, the tender The Detailed was 2nd December was re-issued on 7th Project Report 2015. July, 2016. The last submitted to date for submission DMICDC was The RFQ cum of proposals was 3rd placed before the RFP for design August, 2016. DMIC Trust for and construction consideration of ABCD Building Five bid proposals and investment was floated on 3rd have been received by approval. After August 2015, pre- the bid due date on deliberating on bid meeting 3rd August, 2016. the matter, the M/s Haskoning Board of was floated on 3rd DHV Nederland BV Trustees August 2015, pre recommended to bid meeting was has been selected. revise the DPR conducted on 9th after including September 2015. Letter of Award has the cost of The due date of been issued to M/s Japanese submission was Haskoning DHV component 10th December Nederland BV for which is coming 2015. Three bids preparation of as grant to the have been Detailed Master Plan project. Revised received by the for Bidkin Industrial DPR submitted bid due date. Area on 8th by the consultant September, 2016. to DMICDC. EPC contractor The proposal of for Roads and The consultant has investment Services and submitted draft approval in the ABCD Building Detailed Master Plan project has been has been for Bidkin Industrial posed for appointed. The Area and is being approval of construction of reviewed. The DMIC Trust in roads & detailed plot level its meeting held underground plan is under on 18/ 19, services work finalization. March, 2013. It started on the RfQ cum RFP for has been decided major arterial selection of System that DMIC Trust roads inside Integrator for Design may hold 49% Activation Area. Development stake in the Almost 60% of Implementation, proposed SPV the total drawings Integration, Testing, and the balance have been commissioning and 51% stake may approved.. support for AURIC be given to a Embankment soil City‟s e-land Public Sector filling for the management system undertaking like identified priority was floated on 30th BHEL. The roads (C-7, G7, June, 2016. The pre- decision was G4, A6, H1, F3A, bid meeting was held communicated to E2) is under on 8th August 2016. NEDO, progress (Total Two (2) nos. of bid Government of quantity proposals have been Japan. completed is 34000 Cum). received by the bid The Cabinet Laying of concrete due date on 29th Committee for storm water drain, August, 2016. Economic ICT & power Affairs in its ducts and other Letter of Award has meeting held on utilities (HDPE been issued to M/s 20th January, pipe laying) on the CSM Technologies 2014 has priority roads G-4, Ltd. on September 9, approved the C7 is in progress 2016 as System proposal of (industrial effluent Integrator for design, DIPP for pipe laying development, implementation approx.18733 M Implementation, and operation of completed). Integration, Testing, Model Solar Testing of piles Commissioning and Project at (10 piles) with support for AURIC Neemrana, revised design for City‟s e-land Rajasthan ESR location at management system. through a 100% R8 & R9 has been subsidiary of executed. Out of The application has DMICDC. The 8 nos. of major been launched on Board of bridges, 28th November, Directors of excavation and 2016. The DMICDC in its PCC works of 4 applications received meeting held on nos., foundation via the application is 24th February, works of 3 nos., about 600 for the 49 2014 has substructure of 2 number of plots open approved the nos. and for allotment. incorporation of superstructure of The RfQ cum RfP 100% SPV of 1 no. are for Design, DMICDC for completed and 2nd Construction, the project. bridge in progress. Testing, Accordingly, a Commissioning and company with EPC Contractor Operation & the name of for ABCD Maintenance of “DMICDC Building has been Infrastructure Works Neemrana Solar appointed. for Roads, Drains, Power Limited” Design drawings Culverts, Minor and has been are under approval Major Bridges, Water incorporated and (362 drawings Supply, Sewerage, DMIC Trust has approved) Power systems released its share Architectural including Sewage and of equity to the drawings and project SPV. structural design Common Effluent for foundation of Treatment Plants for Further, compound wall Sector A, Phase – II DMICDC vide has been in AURIC Bidkin letter dated 15th approved. Industrial Area, May, 2015 has Comprehensive Aurangabad, received a (LEED report is Maharashtra on EPC confirmation under review Basis (Package –I) has from Ministry of &discussions with been issued on 17th New and the contractor February, 2017. LoA Renewable design team. has been issued on Energy (MNRE) Construction of 20th June, 2017 to that NVVN can SPV building has M/s L&T Ltd.(INR sign PPA with been completed - 1223 crore) DMICDC/ up to casting of 1st DNSPL floor slab is M/s Idam completed. Infrastructure Performance Preparation of 2nd Advisory Pvt. Ltd. Bank Guarantee Floor slab casting has been selected for has been is in progress. „Providing assistance submitted to Grade slab in preparation and NVVN for completed. submission of License signing the PPA Application and the PPA has Piling work of (Distribution) and been signed on utility building has support in related 5th June, 2015. been started. matters in the course Construction of of processing The consultant 21 piles (17%) out applications by has submitted of 121 piles is Maharashtra draft Power completed in the Electricity Regulatory Purchase utility building. Commission (MERC) Agreement. The Earth filling for till issuance of license draft Power external area under the AITL”. Purchase development near The letter of Award Agreement was to completion. will be issued shortly. forwarded to Pile work (132 NTPC Vidyut nos.) for The RFP for Vyapar Nigam compound wall “Empanelment of Ltd (NVVN) on has been Consultants as th 16 April, 2014. completed. Transaction Managers The consultant Subgrade for all and advisors for land has also internal roads allotment at Shendra submitted the completed GSB – Bidkin Industrial draft Power under Area at Aurangabad Purchase construction for was issued on 7th Agreement to be 24 m road. 70% October, 2016. The entered into with pile work pre-bid meeting was end-user completed for held on 18th companies. compound wall. October, 2016. MNRE has 100 m length (only Three (3) bids have accorded its Column work) for been received by the approval for the compound wall bid due date on 17th execution of completed. 100% November, 2016 PPA with pile work NVVN at completed for Consultants have Rs.8.77/- per fencing. been empaneled as unit for purchase Transaction Managers of power from The RfQ cum RfP and advisers for land the 5MW grid of EPC allotment at Shendra for 25 years Contractor for – Bidkin Industrial subject to DIPP Water Treatment area at Aurangabad. ensuring that the Plant (WTP) was entire profit on floated on 7th The draft RfQ cum the project will March, 2016. The RfP document for be separately pre-bid meeting appointment of accounted for by was held on 18th Master System DMICDC and April, 2016 and Integrator for Supply, spent on BPL the bid due dated Implementation, families via Solar was 21st June, Operations and Home Lighting 2016.Eight bids Maintenance of Smart Systems. have been City ICT Secretary, DIPP received and the Infrastructure at vide letter dated evaluation is in Shendra Area of 26.11.2014 progress. AURIC has been requested submitted by ICT Chairman and M/s SPML Infra consultants to the Managing has been selected SPV and the same is Director, NTPC as the EPC being reviewed. to expedite the Contractor for Consultant appointed signing of PPA Water Treatment at the tariff of Plant (WTP) and for Preliminary Rs. 8.77 per unit. the land for Engineering of Bidkin Revised PPA construction work Industrial Park of 32 after has been handed sqkm is finalising the incorporating the over to the draft tender comments of contractor on 6th documents for NVVN and December, 2016. Package – I of Sector certain The kick-off A-Bidkin Industrial modifications as meeting with the Area and per the contractor was Package II requirement of held on 21st (STP&CETP). the project has December, 2016. RfQ cum RfP for been resubmitted Preparation of the appointment of to NVVN on civil GAD and Master System 18th December structural Integrator (MSI) for 2014. drawings are Supply, under progress. Implementation, SIPP has Stage-wise Integration, requested CMD, approvals of all Operations and NTPC vide its the drawings are Maintenance of smart letters dated 24th in progress. 17% city ICT components February 2015 to of drawings are at Auric-Shendra was approved. Site issued on 4th expedite the development February, 2017. Pre- signing of PPA works have been bid meeting was held for taking started. on 20th February, forward the Solar 2017.Two bids were Project at The RfQ cum RfP received by the bid Neemrana in of EPC contractor due date on 6th April, Rajasthan. for Sewage 2017. The two bids Treatment Plant were found CEO & MD, (STP) was floated unresponsive in the DMICDC vide on 4th April, 2016 pre-qualification his letters dated and the pre-bid evaluation. The RfQ 1st January, 2015, meeting was held cum RfP has been re- 23rd January, on 11th May, 2016 issued on 26th April, 2015 and 17th and the bid due 2017 March, 2015 has date was 11th July, A review meeting was also requested 2016. Four (4) held on 16th May, NVVN to bids have been 2017 to review the expedite the received. Letter progress of work by signing of PPA.. of Award has the ICT consultant been issued to M/s IBI at DMICDC A meeting was M/s L&T Pvt. office, New Delhi. held on 9th April Ltd. as EPC The bid submission 2015 with Contractor for date has been NVVN for STP on 26th extended to 5th June, discussing the September, 2016. 2017 from 22nd May, issues of signing 2017. of PPA. to M/s L&T Pvt. Ltd Three bid proposals NVVN vide has been were received till the Based on appointed as the last date of sub discussions in the EPC Contractor mission and bid meeting, the for STP and the proposals are under revised draft of land has been evaluation. PPA has been handed over on The consortium led forwarded to 21st December, by M/s Honeywell NVVN vide 2016. has been appointed as letter dated 21st the Master System April, 2015. The RfQ cum RfP Integrator (MSI) for for Consultancy Supply, A meeting services of Implementation, between Employer‟s Integration, CEO&MD, Engineer for Operations and DMICDC, WTP, STP and Maintenance of smart Chairman, CETP was floated city ICT components th Rajasthan on 27 April, at Auric-Shendra and Electricity 2016 The pre-bid letter of award is Regulatory meeting was held being issued. th Commission and on 25 May, 2016 The “ Expression of Secretary, and the bid due Interest (EoI) for Department of date was 9th Appointment of Energy, Govt. of August, 2016. Telecom Service Rajasthan was One (1) bid was Providers for Leasing nd held on 22 July, received by the of Dark Fibre for 2014. for bid due date. Due Offering Triple Play discussing the to low response, Services at Shendra way forward on the tender was re- Area of AURIC” has the project issued on 2nd been issued on 21st September, 2016. Dec.,2017 and the The first batch of Six (6) bids have pre-bid meeting was Solar Panels been received. held on 10th January, from Japan have M/s STUP 2018. The last date arrived on Nava Consultants have of submission has Sheva Port on been appointed been extended upto 25th October, for Consultancy 05.04.2018. 2014.Solar Panels services of for 5 MW have Employer‟s RFP for selection of reached the Engineer for contractor for “ project site. WTP, STP and Consultancy Design, Periodic CETP. LoA was Build and meetings are awarded on 3rd Commissioning of 5 being held to January, 2017.The MLD Sewage monitor the Consultant has Treatment Plant progress of the mobilized and (CETP) based on project. started working on Membrane Bio site. Reactor (MBR) RERC vide their Technology on EPC letter dated 25th The RfQ cum RfP basis with 5 years August, 2014 for Consultancy Operation and opined that as services of Maintenance at per the provision Preliminary Shendra (Package- of the Electricity Design of ABCD III)‟ was issued on Act 2003, Building Phase II 27th February 2018 generating –Command Pre-bid meeting was company may Control Centre held on 12th March, supply electricity was floated on 2018 Two bids have to any consumer 27th April, 2016 been received by the subject to open and the pre-bid bid submission date, access meeting was held i.e. 5th May, 2018 regulations on 31st May, 2016 Letter of Award framed by the and the bid due issued to M/s Commission u/s date was 22nd July, Passavant Energy & 42(2) of the Act. 2016. Two (2) Environment India In other words, bids have been Pvt. Ltd. on 8th June if a generating received. Financial 2018 for company wants bids have been “Consultancy Design, to supply opened on 20th Build and electricity in September, 2016. Commissioning of 5 accordance with The letter of MLD Sewage section 10(2) it award has been Treatment Plant need not obtain a issued to M/s (STP) and 6 MLD license u/s 14 of HCP Design, Common Effluent the Act. Planning and Treatment Plant Provisional Management Pvt. (CETP) based on Implementation Ltd. for Membrane Bio Document has Consultancy Reactor (MBR) been finalized services of Technology on EPC with NEDO. Preliminary basis with 5 years Design of ABCD Operation and RERC vide letter Building Phase-II Maintenance at dated 6th April, – Command Shendra (Package- 2015 has clarified Control Centre on III). An agenda item that as the 13th October for the approval of generating 2016. the bid was proposed company will not in the adjourned be utilizing the Common Effluent Board meeting of infrastructure of Treatment Plant AITL on 28th June, the existing (CETP) of 2018. distribution capacity 20 MLD company and the has been proposed RFP for “Selection of objective of this to be developed Managed Service demonstration for the Dholera Provider (MSP) for providing cloud and project is to Industrial in next managed services for promote 5-10 years. The Auric” was issued on renewable energy tenders for 17th March 2018. in the State construction of Pre-bid meeting was through cutting the CETP was held on 26th March edge technology, issued in June, 2018. Three bids have the generating 2016 and three been received by bid submission date on company may proposals have 19th April 2018. supply electricity been received.  ESDS Software directly to the Consent to Solutions Private identified set of dispose the RO Limited has been consumers reject from the selected as without CETP at upstream contractor-Managed obtaining a of the proposed Service Provider distribution Kalpsar Dam as (MSP) for providing Cloud and Managed license u/s 14 of per terms and Services for Auric. the Electricity conditions Letter of Award was Act2003. stipulated by issued on 18th July, Narmada, Water 2018. EPC contractor Resources, Water  RFP for Selection of has been Supply & Kalpsar Contractor for “Relocation of 132 appointed for Department, has KV EHV overhead implementation been applied and transmission line of 6.00 MW being rigorously network to Model Solar followed upon. underground cable Power Project at Until the including Design, Neemrana approvals are Supply, Installation, Industrial Area obtained, the bid testing and commissioning at on turnkey basis finalization AURIC Shendra and process has been Industrial Area, on comprehensive kept on hold and Item Rate Basis operation & the bidders have under AITL” was Maintenance for been requested to issued on 1st a period of 10 extend the bid December,2018. years. validity upto 22nd Pre-bid meeting was held on 7th September, 2017. The kickoff December, 2018. A meeting was Five bids have been meeting with the held on 11th July, received and the EPC contractor 2017 to discuss evaluation is under was held in the issue at the progress. DMICDC on level of Chief  RFP for th 7 October, Secretary, appointment of Master System 2014. Government of Subsequently, Integrator (MSI) for Gujarat with all Supply, meetings were the concerned Implementation, th held on 15 stakeholders and Integration, th October and 28 officials. Operations and October, 2014 Maintenance of between M/s L&T has Smart City ICT DMICDC, the been selected as components at Auric Bidkin was EPC contractor the successful issued on 4th and Japanese bidder for the December, 2018. officials for project. Letter of Pre-bid meeting finalizing the Award issued on was held on 13th technical aspects 23rd February, December, 2018 and and the way 2018. bid submission date th ahead for is 8 January, 2019. implementing the D.R.Agrawal  RFP for selection of project. Infracon Pvt. Ltd EPC Contractor for has been selected Design, The EPC as the successful Construction, Testing, contractor has bidder for Commissioning and initiated the site construction of Operation & grading and 10MLD short Maintenance of fencing work at term water supply Additional project site. The works from Pipli. Infrastructure work for Plant LOA will be Works for Roads, Levelling, Plant issued shortly. Drains, Culverts, Fencing, Water Supply,  RFP for Sewerage, Power Transformer Empanelment of systems in AURIC Foundation and Transaction Shendra Industrial Watch Tower Advisors for Area was issued on Foundation has DICDL has been 14th December, been completed. issued on 4th 2018. Pre-bid The work meeting was held Jan,2018 and the th construction of on 7 January, 2019 bid due date is and bid submission control room, 2nd February, date is 28th January, switchyard and 2018. One (1) bid 2019. array lighting at has been received  site is under and bid  As per the new progress. The evaluation is in Government progress of the progress Regulations, all the works related to project was  RFP for selection reviewed by procurement of cloud of Public services have to be CEO & MD, Relations (PR) executed by DITM DMICDC in the agency for (Directorate of meetings held on DICDL has been Information th 11 May, 2015 issued on Technology, th Maharashtra), SPV- and 12 June, 04.01.2018 and 2015. AITL is in the the bid due date process of submission is 09.02.2018. The Connectivity of all these Letter of Award documents to DITM of the Plant with issued to M/s panel for further the Grid has Ventures process. been completed Advertising on  on 24th July, 22.03.2018 for  RFP Selection of 2015. The Consultant for progress of the Public Relations Preparation of proposal is being (PR) agency for Concept Landscape reviewed on DICDL. Master Plan for Bidkin Industrial regular basis. Area and Detailed Three bids Landscape work for Secretary, DIPP received and bid Sector A vide his letter evaluation is in Development was dated 21st July, progress. issued on 21st 2015 followed by December 2018. another letter The tender Bid submission rd from CEO & documents along date is 23 January 2019. MD, DMICDC with Preliminary dated 7th Design Report for September, 2015 Roads and Other activities: have requested Services in Chairman, Activation Area CEO & MD, NEDO for ABCD building DMICDC vide his expeditiously for Dholera SIR letter dated 29th identifying the and for Water March, 2016 has Japanese Treatment Plant requested Chairman, Companies for (WTP) were NHAI to take up the sale of 1 MW approved by the DPR preparation integrated solar work for various road power. DMIC Trust at projects in th the 9 meeting Maharashtra on On the basis of held on February priority basis. The the fixed tariff, 6, 2015. feasible alignments NEDO has have been inspected The Preliminary identified M/s initially after a joint Design Report MIKUNI India visit with NHAI on (PDR) for Private Limited 13th May, 2016. and the PPA Sewerage between M/s Treatment Plant NHAI had floated MIKUNI India (STP) and the tender for Private Limited Common Effluent selection of and M/s Treatment Plant consultant for DNSPCL for 1 (CETP) alongwith preparation of DPRs MW has been the tender for various executed. The document were connecting road 2nd extension of approved by the projects. However, MoU upto DMIC Trust in its due to low response, August, 2019 10th meeting held the tender is being re- between NEDO, on March 19, issued by NHAI. Japan, 2015. Cabinet Department of Committee on Secretary, DIPP vide Economic Economic Affairs letter dated 17th Affairs, Ministry (CCEA) in its August, 2016 had of Finance and meeting held on requested the Ministry of New 30th May, 2015 has Secretary MoRTH to & Renewable approved the five start the works of Energy has been trunk DPR preparation on executed on 11th infrastructure the road connectivity May, 2016. packages in the project in Shendra area of 22.5 Sq. Bidkin Industrial Area Secretary, DIPP km. as part of (SBIA) under the and CEO&MD, Phase – 1 proposed Bharatmala DMICDC visited development of Pariyojana. the 5 MW Solar DSIR in Gujarat Plant at in DMIC project. CEO& MD, Neemrana DMICDC has Industrial area on The RFQ cum requested Secretary, 8th May, 2016 to RFP for MoRTH vide letter review the Employer‟s dated 15th progress of work Engineer for September, 2016 to at site. Roads and take up the Services and development of CEO & MD, ABCD Building in Aurangabad-Pathan DMICDC visited Activation area Section for four- the 5 MW Solar has been floated laning under Plant at on 17th August, MoRTH/ NHAI Neemrana to 2015 and pre-bid project which is very review the meeting was critical for road progress of conducted on 14th connectivity of the projects and September, 2015. Shendra-Bidkin other works at Extended due date Industrial area site on 25th June, for submission (SBIA). 2016. was 30th December, CEO& MD, The Data 2015.Six (6) bids DMICDC had Purchase have been requested Principal Agreement for received by the Secretary (Industries), sharing the bid due date. The Government of construction and bid process was Maharashtra vide installation data annulled as the letter dated 15th relating to 1MW applicants failed to September 2016 to Micro-Grid Solar meet the eligibility take up with Power Project requirements. Maharashtra State has been Further, the RFQ Road Development executed on 13th cum RFP was Corporation Ltd. September, 2016 floated again on (MSRDC) to expedite between 22nd February, the work of DMICDC 2016. The pre-bid preparation of DPRs Neemrana Solar meeting was for the roads Power Company conducted on 10th connecting Shendra Ltd. (DNSPCL) March, 2016. to Bidkin. and M/s Hitachi Ltd for sharing M/s WS Atkins Secretary, DIPP vide the construction (India) Pvt. Ltd. his letter dated 16th and installation In JV with November, 2016 has data relating to 1 Feedback requested the Chief MW Micro-Grid Ventures has been Secretary, Solar Power appointed for Government of Project. undertaking the Maharashtra to Consultancy resolve the pending CEO & MD, services of issues relating to DMICDC visited Preliminary Shendra-Bidkin the 5MWp Solar Design Report for Industrial Area Power Plant, roads and services (SBIA) for moving Neemrana on / utilities of TP forward expeditiously. 30th September Scheme 1 Area. 2016 to review The Consultant A Joint site visit to the progress of has submitted the Bidkin was organized work. technical with Chief Engineers, Assessment Superintendent The expected report. Engineers and date of testing & Executive Engineer trial run/ M/s Yooshin- teams of MSETCL & commissioning Multimedia in MSDISCOM, M/s the 1 MW Micro association with AECOM and the Grid Solar Power M/s Satra has PMNC Electrical Project is 1st been appointed as team to finalise the June, 2017. the employer‟s route of incoming Engineer for feeder‟s line and The RFQ cum Roads and location of MRSS at RFP for selection services and Bidkin. of “Engineering, ABCD Building in Procurement and Activation Area. A design review meet Construction The Kick-off was organized on (EPC) meeting was held 11th& 12th January, Contractor for on 15th July, 2016 2017 by PMNC with 1.00 MW Model and the Small and Medium Solar Power Consultant was Enterprises (SMEs) Project at mobilized on site and the Utilities Neemrana and started design team of M/s Industrial Area working. SPCPL to explain on Turnkey Basis about the short fall in and RfQ cum RfP Water, Storm Water Comprehensive document for and Structural Operation & selection of ICT Designs submitted Maintenance for Consultant for after proof checking a period of 10 Dholera Special by the Proof years at Investment Consultants. Neemrana Region (22.5 Industrial Park, sq.km) was issued A meeting was held Japanese Zone, on 14th December, on 17th January, 2017 Neemrana, 2015. with NHAI Project Rajasthan has Director and PMNC been issued on Two bids were SME on the 23rd September, received and after development of 2016. Single bid the financial connectivity to Bidkin was received by opening WIPRO and ROW clearance the bid due date is the successful for Laying of Raw on 7th bidder. Water Pipeline from November, 2016. Jaikwadi Dam to The process of M/s WIPRO has Bidkin. selection was been appointed as annulled due to the ICT Dighi Industrial Area: high financial Consultant for RFQ cum RFP for quote by the Dholera Special Investment selection of single bidder. Region (22.5 consultants for sq.km). The preparation of The RfQ cum Consultant is detailed master RfP for Package- working on the planning and I – Engineering, design of systems preliminary Procurement and and conducting engineering for Construction international Dighi Industrial (EPC) services benchmark studies Area was issued on for 1.00 MW for the project. A 9th March, 2018. Model Solar review meeting Four bid proposals Power Project at was held on 16th have been received by Neemrana May, 2017 to the bid submission Industrial Area review the date of 28th May, on turnkey basis progress of work 2018. M/s EGIS and Operation & by the ICT India has been Maintenance of consultant, M/s appointed as 1.00 MW Solar WIPRO at consultant for PV plant DMICDC office, preparation of integrated with New Delhi. detailed master DG & Micro planning and Grid, Operation In addition to the preliminary of DG sets for a five trunk engineering for Dighi period of 10 infrastructure Industrial Area. years has been packages, Letter of Award floated on 23rd (LOA) was awarded November, 2016 RFQ cum RFP of on 22nd August, 2018. Last date of the following The kick off meeting submission of works have also was held on 27th proposal is 14th been issued by September, 2018 with December, 2016. GICC: the project consultants under the (1) Preliminary The RfQ cum chairmanship of MD, design of raw RfP for Package- AITL. II – Supply, water installation, transmission Marketing: commissioning line from & maintenance Road shows have of 5x500 KVA Branch Canal to been held in Engineered DSIR was Aurangabad for Diesel Generator issued on 23rd promotion / Power System at February 2015. marketing of AITL Neemrana Nine (9) bids during December, Industrial Area at were received 2016. Further, road Neemrana for RFQ cum shows are being Industrial Park, RFP for planned in the cities Japanese Zone, Preliminary of Mumbai and Pune Neemrana, design of raw during January, 2017. Rajasthan has water been floated on transmission Materials for 25th November, line from marketing in various 2016. Last date Saurashtra international of submission of Branch Canal to languages have been proposal is 16th DSIR and prepared and December, 2016. four Applicants circulated to the have been potential investors. The EPC qualified for contractor (M/s Technical First green Evaluation. Contactor (M/s The financial First green bids were Consulting Pvt. opened on 1st Ltd) has been September, appointed for 2015.Letter of Engineering, Award was Procurement and issued on Construction 28.09.2015. (EPC) services The Kick-off and for meeting was Operation & held on 28th Maintenance for October, 1.00 MW Model 2015.First Solar PV plant progress review integrated with meeting was DG & Micro conducted on Grid for a period 23rd November of 10 years at 2015. Route Neemrana Alignment Industrial Area. Report was Letter of Award submitted by has been issued the Consultant. on 17th Steering December, 2016. Committee meeting was The contractor conducted on (M/s Sterling 20th January, and Wlson 2016 and the Powergen Pvt. Consultant has Ltd) has been been directed to appointed for revise the report Supply based on the Installation, comments of Commissioning the Committee. and Maintenance The second for 10 years of meeting of 5x500KVA Steering Engineering Committee was Diesel Generator held on 4th Power System at February, 2016 Neemrana, where the intake Rajasthan. Letter location at of Award has Bhaskarpura been issued on and the 27th December, alignment along 2016. Vallabhipur Branch Canal Replacement of (VBC) is Damaged finalized. Module at 5 MW (2) Detailed design Solar Power for Flood Plant Purchase protection order for 1350 works along nos. of 170 Wp Adhiya River is Solar Frontier issued on 4th Modules has March, 2015. been placed to Five (5) bids M/s Array Tech have been Technologies received by the Pvt. Ltd., proposal Bengaluru on submission due th 30 January date i.e. 26th 2017. The same May, 2015.Two will be delivered Applicants had at 5MW Solar qualified for Power Plant, Technical Neemrana within Evaluation. 6 to 8 weeks. Letter of award was issued on Civil Mechanical 7th October, and Electrical 2015. The kick- drawings of off meeting was 1MW Solar EPC held on 29th and 5x500 KVA October, 2015. DG Sets have Consultant has been finalized. been appointed for detailed EPC contractor design for and the DG Flood supplier have protection started civil works along Construction Adhiya. work at the Concept design 1MW Solar report has been Power Project approved by site. State Agencies. Preliminary CEO & MD, Design Report DMICDC visited is submitted by the site on 1st the consultant April 2017, 13th and review May, 2017, 23rd comments were June, 2017 and given to the 29th July, 2017 to Consultant for review the their progress of compliance. activities. The first Steering The 1 MW Committee Micro-Grid Solar meeting on Power project preliminary has been design report commissioned was held on and the supply of 15th March, power to Mikuni 2016. has been started (3) Consultancy from 10th July, services for 2017. drilling of six tube wells in The 6 MW Activation area model project is issued on 23rd (5MWp solar February, power plant 2015.The which uses thin proposal due film technology date was 23 and feeds power June, 2015. directly to the Two bids have State grid and a been received 1MWp plant that and the bid uses poly process has crystalline been annulled. technology with 2MW Diesel (4) RFQ cum RFP Generator Set for selection of integrated with a agency for Smart Micro Desilting of Grid feeding Adhiya River power to has been floated Japanese on 26th August, industrial 2015. The pre- consumers in the bid meeting was Neemrana conducted on Industrial Park 22nd September, was inaugurated 2015 and the on 11th August, due date of 2017 by submission was Secretary, DIPP 21st October, in the presence 2015. of the Nine (9) bids Ambassador of have been Japan to India, received. and senior Consultant for Government Desilting of officials and Adhiya River business heads has been from both the appointed. countries. Letter of Award has been issued. The Contractor has Commissioning started the Certificate of 5 survey work. MW Solar Power The RfQ cum RfP Plant has been for issued by implementation of Rajasthan bunding along Renewable Adhia River in Energy Phase – I (south Corporation side bunding for Limited immediate (RRECL) on 3rd protection) was September, 2017. floated on 17th The power is October, 2016. being supplied to The pre bid State Grid (i.e. meeting was held 220 KV GSS on 27th October, Neemrana) at the 2016. M/s agreed tariff of Jugalkishore Ram Rs.8.77/- per Kishan Agrawal unit. Infrastructure Pvt. Ltd. has been As part of the selected as the CSR initiative of contractor for the DMICDC work. Neemrana Solar LoA was issued Power Co., an e- on 6th January, learning facility 2017. The kick- at Government off meeting was Girls Sr. held on 24th Secondary January, School at Behror 2017.Total was inaugurated excavation of by District 110000 cum for Collector Shri embankment is Prakash completed. Toe- Rajpurohit, in wall construction the presence of of 900 m is CEO&MD, completed. DMICDC on The RfQ cum RfP 6.10.2018. The for Selection of Lab. is equipped contractor for with latest construction of 10 computers, e- MLD short term learning water supply modules, works from Pipli projector, has been issued on scanner etc. 12th July 2017. No bids were received by the bid due date i.e.. 3rd October, 2017. The tender was re- issued on 18th October, 2017. The bid submission date is 5th December, 2017.

The RFQ cum RFP for ICT Consultant was issued on 26th February, 2015 and pre-bid meeting was held on 12th March, 2015.The responses to the queries and Corrigendum-1 has been uploaded on DMICDC website. The proposal due date has been extended till 4th June, 2015.Only two bids were received. Hence the bid process has been cancelled. RFP has been revised and rebidding is scheduled in the first week of September, 2015. The topographical survey is under progress for Town Planning Scheme – 2 of DSIR.

The RFP for topographical survey for Town Planning Scheme - 1 has been issued by DSIRDA on 6th April, 2015 and pre-bid meeting was held on 15th April, 2015. The bids evaluation is complete and LoA to be issued.

The current process is annulled by GICC and is proposed to be re-bid.

The fresh RfP for topographical survey for Town Planning

Scheme -1 has been re-issued by DSIRDA.

Six bids were received and evaluation is in progress.

RFQ cum RFP for consultancy services for providing assistance to Town Planning Officers (TPOs) for finalizing the TP Schemes was issued on 1st

April, 2015 by GIDB. The bids evaluation is complete and LoA to be issued. Consultant for providing assistance to TPDS for finalizing the TP schemes has been appointed. Secretary (DIPP) alongwith CEO & MD, DMICDC visited DSIR and reviewed the progress of the project on 27th May, 2016.

The topographical survey is completed for Town Planning Scheme – 1 and 2 of DSIR.

During the 15th meeting of DMIC Trust held on 26th July, 2016, the proposal of release of additional equity to the SPV in lieu of the Government of Gujarat transferring additional land parcel of 527 Ha was deliberated. DMIC Trust accorded its approval for the release of additional equity.

CEO&MD DMICD visited the site on 21st Novermber,2017 to review the progress of Infrastructure construction activities.

CEO&MD, DMICDC reviewed the progress of the on-going project activities during the meeting held on 22.12.2017.

CEO&MD, DMICDC reviewed the progress of the on-going project activities during the meeting held on 25th January, 2018.

Hon‟ble Chief Minister of Gujarat unveiled the logo of Dholera Smart city and land laid the foundation of water supply system and CETP in Dholera on April 22, 2018. Further, following two new projects were announced during the occasion by Hon‟ble Chief Minister : (a) Development of World‟s largest Solar Park of 5000 MW, and (b) Skill development centre to provide employment to local people in Dholera.

CEO&MD, DMICDC reviewed the progress of construction activities at site on 12th May, 2018. The contractors were instructed to engage more manpower & equipments to complete the activities as per scheduled timelines.

The Dholera road show was successfully held on 13.10.2017 in Mumbai and 09.01.2018 in Delhi and 3rd April 2018 in Pune. DICDL participated in Defence Expo 2018 held at Chennai from 11 th to 15th April,2018.

GETCO had issued the tender for erection, commissioning and charging of the transmission line from Fedra to Activation Area, DSIR and its associated network like the Bay at the transmission end at Fedra substation to be completed by March 2019. The contract is awarded to Associated Power Structures Ltd. on March 15, 2018. The contractor has carried out the initial survey and submitted profile survey for part alignment of transmission line to GETCO for approval. Detailed survey activities are under progress for transmission line within DSIRDA notified area (8.2 km)

New Concept Interiors has been appointed as contractor for Construction of Additional Facilities at BEC (Business and Exhibition Centre) building. The interior works have been initiated, wall paneling, HVAC ducting, firefighting pipe line works are under progress. GERC has issued power distribution license to Torrent Power Limited on 14th August, 2018 for DSIR. DICIDL is in discussions with Torrent Power regarding the options to build 66 / 11 kV substation on priority. Plots have been allotted to Torrent Power (20.78 acres – 05 plots) and Hindustan Petroleum Corp. Ltd. (5.93 acres – 02 plots) for setting up of Power distribution substation and a fuel station. M/s Enarch Consultants has been appointed for Interior Design of ABCD Building Ph-I. The Consultant has submitted the BEC building design and it is approved. Draft design report for SPV building has been finalized. RfQ cum RfP for selection of Master System Integrator (MSI) was issued on 24th August, 2018. The pre-bid meeting was held on 24th September, 2018 and the submission due date has been extended upto 21st December 2018. No bids have been received by the due date. The tender will be re-issued shortly.

RfQ cum RfP for canal front development including land fill, civil, MEP and landscape was issued on 22nd November, 2018 and the bid due date was 27th December, 2018. Four bids have been received and evaluation is under progress.

4e. Status of feasibility study of Overall DMIC Gujarat Madhya Pradesh Haryana Maharashtra Rajasthan Uttar Pradesh EBPs region

Six lane Water Supply Early Bird Project - Final report for Khushkhera - Dadri Noida expressway from Project: Exhibition cum Transportation and Bhiwadi – Ghaziabad Ahmedabad to convention Centre Tele-communication Neemrana Investment Dholera In the meeting at Panchgaon network, final TEFR Investment Region between DMICDC Chowk for Mega Industrial Region (KBNIR) (DNGIR) Gujarat State and the officials of Park at Shendra- Road MP Govt. held on The Techno- Bidkin Region and During the A meeting was Development 11th January, 2012, economic feasibility the final TEFR for meeting held on convened on Corporation was it was decided that Study has been Dhule Mega 17th October, May 7, 2012 entrusted with the there will be a approved by the Industrial Park (MIP) 2014, chaired by the responsibility for onetime VGF State Government. were submitted to the Government of Chief Secretary, the project contribution of For Land state. Rajasthan (GoR) Government of development and 20% by both acquisition, award informed that the Uttar Pradesh, implementation of Centre and State so was announced in Exhibition cum State Government to discuss the 6 – Lane as to make the April 2011 but stay convention Centre at is in process of site delineation Expressway project was given by Aurangabad finalizing the new options for connecting commercially Supreme Court. Land is in MIDC‟s Act under which Dadri-Noida- Ahmedabad to doable. It was also State Government possession. Provision implementation of Ghaziabad Dholera. agreed that AKVN needs to get the of last mile DMIC project will Investment will ensure ban on Stay order vacated connectivity to the be taken up in Region The State extraction of as early as possible. project site by the Rajasthan. During (DNGIR) along Government had ground water, will State Government the State Steering with Early Bird earmarked provide guarantee Early Bird Project agencies is also Committee Projects on approximately Rs for a minimum of pending. meeting held on Boraki Railway 2,200 Crore for 25 MLD water Integrated Multi 1st December Station, Multi the project from demand and initiate Modal Logistics Based on the meeting 2014, the State Modal Logistics its budget, which immediate action Hub Project at convened by Chief Government has Hub at Dadri is now being for obtaining NOC Rewari Minister, a notice was approved the and raised to Rs.2800 for laying the water issued by Urban Development plan International The Techno- Crore. The pipeline & Development of KBNIR and Airport at economic feasibility process for land construction of Department of the Integrated Jewar. The Study was approved acquisition has treatment plant and State soliciting Greenfield Dadri Noida by the State been started by other allied works. suggestions and Township Project. Ghaziabad Government. the GSRDC. These actions are observations of all Investment Section 4 Draft Feasibility awaited. concerned with The Committee Region has Notification was report has been respect to the Global also approved the been notified issued on 4th July received by FSI of 1.5 that was following pre- on 29th August, 2011 for Land GIDB. accorded to the 50 feasibility report 2017 by the acquisition. It needs Chief Secretary, The revised RFQ, acre area for the submitted by Government of to be expedited by Government of RFP and Draft project. The project Uttar Pradesh. the State Gujarat in a Concession components had the consultants: Government. meeting held on Agreement for been revised on that Multi Modal DMICDC and (1)Waste Water 30th January, 2016 Water Supply basis and included as Logistics Hub Government of Conveyance directed the design Project were „CBD‟ – Central (MMLH) at Haryana have System from Consultant and submitted to State Business District in Dadri agreed in principle Okhla STP (DJB) GSRDC to Government for the RfQ cum RfP to form a Joint to KBNIR. explore the approval of state document for o The comments Venture for possibility of PPP committee. selection of of GoUP on implementation of (2) Integrated reducing the Section 4 and 5 was consultant to prepare draft report of IMLH project. The Multimodal proposed ROW completed for land the preliminary design Techno- comments of the passenger from 100 m to acquisition of 0.68 for the roads and Economic State Government Hub(IMPH) 60m. Ha of land required services/utilities for Feasibility on Joint Venture A meeting was for construction of Phase – I (8.5 sq. Study of Agreement and (3) High-Tech held under the treatment plant and Km) of Shendra- MMLH at Share Holder Agriculture & Chairmanship of other allied works. Bidkin Industrial Dadri were Secretary, DIPP The RFP for Agreement were Area. The consultant Food Cluster incorporated to on March 15, selection of received. Revised had submitted three finalize the 2016 and it was Transaction shareholders alternative concept (4)Water report. Site decided that Advisor for Bid agreement after master plans for the Management for details were NHAI will take up Process incorporating the CBD, which are Phase 1 of overlaid on expressway by Management of the comments was sent presently being KBNIR revenue maps acquiring 100 m project was to the State on 13th reviewed. of the identified RoW which will approved by the February, 2013. (5) Public site and also accommodate State Government. The revised Joint The Techno – Transportation for submitted to MRTS Row of Letter was sent to Venture Agreement Economic Feasibility KBNIR. GoUP. 30 m. the State was forwarded to Report for the project DMICDC Secretary, DIPP NHAI is Government on HSIIDC. SHA was revised as per through its vide his letter undertaking the 27th October 2012, revised again and communication dated 10th July project under the wherein immediate forwarded to the the global FSI of 1.5 dated 4th March 2015 has Bharatmala decisions related to State for approval. accorded by the State 2013 requested requested Chief scheme (upto water withdrawal Government and in DFCCIL to Secretary, centre of DSIR- charges, State‟s The shareholder‟s accordance with review the Rajasthan to road stretch of VGF contribution, agreement is alignment of the changed expedite the 110 km). M/s fixation of water currently being the spur line coordinates of the formation of SMEC (India) Pvt. tariff, banning of finalized. that is proposed site. The project node/ SPV level Ltd. has been ground water from Western proposal was placed for KBNIR. He selected for extraction, water The project had DFC Yard before the DMIC has also requested project purchase agreement been placed as part towards Trust meeting held on State Government preparation of with industries and of the agenda item proposed th 18-19th March, 2013. to expedite the Feasibility study/ municipal area were for the 4 meeting MMLH site. A It was decided that land acquisition Detailed Project sought. In the of Board of meeting was th project would be proceedings so as Report (DPR) by meeting convened Trustees on 10 held on 10th brought to Trust to kick start the NHAI of Road by Chief Secretary September, 2013 May 2013 under along with the DMIC stretches selected of the State on 17th for seeking the comprehensive first development in for DMICDC as Nov.2012, the State Investment chairmanship of phase of Shendra the State. informed by assured that approval and the Principal Industrial city NHAI on 6th decisions on the DMIC Project Secretary development. The RfQ and RfP September, 2016. above issues would Implementation Industries, A meeting was held document for the CEO & MD, be conveyed Trust Fund Government of on 22nd August, 2014 appointment of DMICDC had immediately. accorded „in Uttar Pradesh in Mumbai under the PMNC for requested principle‟ approval and CEO, co-chairmanship of KBNIR was re- Secretary, Government of to the project. The Greater Noida CEO&MD, issued on 10th MoRTH vide Madhya Pradesh joint Venture Industrial DMICDC and CEO, June, 2015, pre- letter dated 15th given an additional Agreement has also Development MIDC to review the bid meeting held September, 2016 proposal to been finalized in Authority with to initiate the DMICDC for consultation with progress of the on 22nd June, Director, acquisition of land providing water to the State Nodal project. It was also 2015. Four bids Dedicated for the project and Pithampur Agency. decided the MIDC have been Freight declare it as a Industrial Area. will shortly finalise received by Corridor National Highway. Instead of the water In the meeting held one of the three proposal due date, Corporation MoRTH has supply project from on 28th October, options of the i.e. 20th July, 2015 India Limited requested the Mahi Dam, a 28 km 2013 followed by alternative concept and bid evaluation to discuss the details fo the pipeline was the meeting held on master plan for CBD. is in progress. above issue and finalised alignment proposed from 29th November,  A presentation was it was suggested of the proposed Narmada - Shipra 2013, it was decided made by the In the meeting that DMIC expressway to Simhastha link for that the land consultant to held under the consultants may NHAI vide letter providing 90 MLD acquisition process MIDC Chairmanship of take the inputs dated 23rd water to Pithampur. for the project will Aurangabad on Chief Secretary, of DFCCIL September, 2016 The proposal was be expedited by the 12th September Rajasthan on 2nd while finalising in order to take examined by State Government 2014, wherein December, 2015, the alignment in further action on DMICDC and the along with the MIDC has it was decided that regard to the the same. The shortcomings in the formation of the provided inputs on RIICO will make spur. Consultant has same were Project SPV. the alternative available the funds Techno- submitted the communicated to concept master for disbursing the Economic DMIC Trust, in its draft Inception the Government of plan and suggested award declared by Feasibility study meeting held on report to NHAI. Madhya Pradesh for a stakeholders the State for “Multi 25th June, 2014, A meeting was with a request to meeting which was Government for Modal Logistic approved an held on 20th submit the revised also organized on acquisition of 14 Hub at Greater allocation of Rs.450 January, 2017 proposal. In the 19th September sq.km. land for Noida near crore as the equity under the meeting held on 2014 at phase – I Dadri” was contribution for chairmanship of 13th April, 2013 Aurangabad. The development of completed and IMLH Rewari CEO & MD, between DMICDC consultant is the node before approved by Project. st DMICDC with and the State further 31 December, the State NHAI officials Government, the incorporating the 2015. Government. HSIDC vide its and the issues with respect inputs received The DMIC letter dated 14th State Government consultants to to the Design, from various Project February 2015 has has informed that review the Costing, Structuring stakeholders and Implementation requested for they have declared progress of of the project etc. taking the prelim Trust Fund survey of alternate the award for the preparation of were discussed in design study accorded „in site for DMIC 14 sq. km. land DPR for the detail and AKVN forward. The principle‟ Projects. A joint and they are in the Expressway and (Indore) was consultant approval to the visit along with process of the mode for requested to submit presented the project in its HSIIDC officials arranging long acquisition of land the revised Master plan meeting held on has been conducted term loan for for the same. proposal. Revised options for Central 10th September, by DMICDC on NHAI vide letter proposal was paying the 2013. dated 17th March, submitted by 26th February 2015. Business District compensation to Shareholders 2017 has informed AKVN (Indore) on Based on the (CBD) to District the project agreement was that the ROW 21st May, 2013 and meeting between Collector, affected people. finalized with required for after reviewing the CEO & MD, Aurangabad, the State Nodal Expressway is 90 same, the State DMICDC with MIDC on 21st CEO & MD, Agency. A spur M and has Government was Principal Secretary October, 2014 DMICDC vide his line from DFC initiated the land requested to revise (Industries), followed by a letter dated 22nd Yard to the acquisition DPR again after Haryana on 30th presentation to March, 2016 has proposed accordingly. addressing the March,2015. Site Principal Secretary forwarded the MMLH is CEO & MD, issues with respect visits were (Industries), tender document planned. The DMICDC vide to project supply conducted on6th Government of for selection of alignment letter dated 27th area, projected April, 2015 and 8th Maharashtra on consultants for details of the March, 2017 has water demand, April, 2015 along 22nd October, preliminary spur-line from requested the allocation of water with State 2014 to review and engineering and the DFC Yard Joint Secretary for industrial use, Government finalise one of the design works for to the proposed (MoRTH) to project structuring, officials from options of master the phase – I in MMLH project expedite the land etc Irrigation and plans for CBD at KBNIR. The were furnished acquisition for the Power Shendra. State Government by DMICDC to proposed The project had departments to Government of has been DFCCIL on Expressway and been placed for ascertain existing Maharashtra has requested to 20th February, MRTS project seeking investment situation on the finalized the most comment / 2013 for review from Ahmedabad approval in the proposed sites. preferred option for approve the and approval. to Dholera. meeting of Board The site report has development of the tender document DFCCIL vide A review meeting of Trustees on 10th been submitted to CBD vide letter dated and also their letter was held on 28th September, 2013 State Government 22nd October, 2014 incorporate the dated 31st March 2017 and the DMIC on 18th April, 2015 and the consultant land details in the January, 2014 under the Project by DMICDC. has been directed to document. communicated chairmanship of Implementation work on the preferred that alignment CEO &MD, Trust Fund In the meeting held option. The State of DFC near DMICDC accorded on 2nd June, 2015 Proposal for funding Government has Dadri/Boraki wherein the investment under the and issuance of provided the land was under progress of approval to the Chairmanship of tenders for creation details pertaining finalization. activities under project. CEO, Secretary, DIPP to of District to development of They also the project was DMICDC vide his discuss the issues Administrative Phase-I in KBNIR requested the discussed. NHAI letter dated 23rd related with DMIC Building (DAB) in to DMICDC. detailed plan to finalise the September, 2013 Project in Haryana, CBD of Shendra The tender along with DPR and initiate had requested the it was decided that Bidkin Industrial Park document is being feasibility report the land State Government the projects at the in Maharashtra has finalized. to examine the acquisition to expeditiously new identified sites been approved by technical Secretary, DIPP process to complete the land at Atheli and DMIC Trust in its feasibility of the DMICDC. acquisition of the Nangal Chaudhary 10th meeting held on and CEO&MD, proposed CEO&MD, Right of way for can be undertaken 19th March 2015 DMICDC visited alignment and DMICDC vide the project. The after establishing followed by CCEA in Neemrana the same has letter dated 3rd shareholders the feasibility. its meeting held on Industrial Area on been submitted July 2017 has Agreement for Accordingly, in 30th May, 2015. 8th May, 2016 and to DFCCIL for requested constitution of the discussion with the reviewed the their Chairman, NHAI project SPV was State Government, Multi – Modal progress of comments/sug to expedite the finalized with the it was decided to Logistics Park Khushkhera gestions. finalisation of State Nodal Agency take up project (MMLP): Bhiwadi DPR for the and was forwarded development Initial location at Neemrana DFCCIL had project. A by DIPP to activities for Karla was finalised in Investment provided their meeting was held Department of Law development of discussion with State, Region in comments on on 24th July 2017 for their IMLH at Nangal based on which the Rajasthan being the report vide at NHAI to concurrence. Chaudhary. The Techno-Economic developed in their letter review the RFQ-cum-RFP Feasibility Study was Phase-1 of DMIC dated 17th progress of DPR The project was document for completed. But later Project in April, 2014, preparation officially selection of on DMICDC was Rajasthan. which were activities for the inaugurated by consultant to advised to shift the incorporated by project. Chief Minister of prepare Techno- project to Talegaon CEO&MD, the consultant. CEO&MD, Madhya Pradesh Economic by the State DMICDC has DMICDC vide jointly with Feasibility Study Government. requested the The State letter dated 28th Minister of (TEFS) Report for DMICDC completed State Government Government July, 2017 has Commerce and IMLH at Nangal the reconnaissance of Rajasthan to had informed requested NHAI Industry, Chaudhary has survey for the new expedite the that the land to initiate the land Government of been shared with site and submitted its process of land admeasuring 21 acquisition for the India on 13th State Government report with the acquisition for the hectares is proposed September, 2013 at for their comments. finding that the new nodes, taking up already under Expressway and Bhopal. DMIC State Government site was also suitable loan from possession and MRTS projects Trust approved the has shared their for the development HUDCO, the land together. formation of SPV comments and the of a MMLP. approval of the acquisition A review meeting for this project in same are under MIDC also suggested SHA&SSA and process for the was held on 10th partnership with review. a new site for MMLP formation of the remaining land October, 2017 State Government which was near SPV. was initiated by under the of Madhya Pradesh CEO & MD, Aurangabad. the State chairmanship of on 6th December, DMICDC vide his DMIC Trust in its A Review meeting Government. A Secretary, 2013. The letter dated 14th meeting held on 10th was held on 15th review meeting MoRTH to Shareholders October, 2015 has March, 2014 accorded July 2016 with was held on th discuss the Agreement for the requested the State its approval for the ACS (Industries), 11 July, 2014 progress of project between Government to substitution of earlier Rajasthan to between project activities DMIC Trust and select anyone site identified location at discuss the way DMICDC and and way forward. the State Nodal for undertaking the Karla in Maharashtra forward. The GNIDA. The The DPR is Agreement was feasibility study. by near State Government final Techno- being finalised executed and the Shendra Bidkin has initiated the Economic by NHAI. project SPV with A review meeting Industrial Area in land acquisition Feasibility Dholera Special the name of was held on 23rd Maharashtra and process for Phase Study for the Investment “Pithampur Jal November, 2015 approved – I development project, Region Prabandhan with Principal appointment of of 338 Ha. In incorporating Development Company Limited” Secretary, consultant for this regard, the the comments Authority was incorporated. Industries, carrying out project State Government of the GNIDA, (DSIIRDA) vdie The share of DMIC Government of development is in the process was submitted their letter dated Trust towards the Haryana to discuss activities. of finalizing the on 1st August, 31.12.2018 have equity of this the pending loan agreement 2014. Further, communicated company was identification of the A meeting was held with HUDCO for GNIDA vide to NHAI released on 31st site for the project under the paying the its letter dated regarding March, 2014. The and it was decided chairmanship of compensation to 30th January handover of land progress of project that the same shall Secretary, DIPP on the land owners. 2015 has shared falling within was reviewed by the be taken in the 15th April 2014 to its comments DSIIR boundary State Empowered meeting of the review the progress During the and the same for the Committee chaired Hon‟ble Chief of DMIC project in meeting held on has been Expressway. by Chief Secretary Minister of Maharashtra. It was 9th August, 2016 forwarded to Metro in its 15th Meeting Haryana. Further, decided that the under the the consultant connectivity held on 29th April, CEO&MD vide his revised RFQ-cum- Chairmanship of for between 2014. e-mail dated 22nd RFP documents will Addl. Chief incorporation in Gandhinagar to December, 2015 be forwarded to Secretary, DMIC, the reports. Ahmedabad In the meeting the requested the State MIDC for Government of For Phase I of Committee directed Government to confirmation of the Rajasthan, the A meeting was Metro MPAKVN, Indore identify the site for extended area / site State Government held on 8th connectivity for fixation of the project details. has informed that December 2014 between minimum raw water expeditiously to it is in the first at Dedicated GandhinagaSPV - charges in take the project The final bid instance arranging Freight Metro Link discussion with development document for funds for Corridor Express between Narmada Valley activities forward. selection of acquisition of 532 Corporation of Gandhinagar and Development consultant for Ha of land out of India Ltd. Ahmedabad Authority / Water Another review preparation of the total 1425 Ha (DFCCIL) to (MEGA). For Resources meeting was held Techno – Economic identified for discuss the way Phase I, SPV is Department. on 15th January, Feasibility Study Phase-I forward for acquiring the 2016 under the (TEFS) for Multi – development. MMLH Dadri Right of Way, The Board meeting Chairmanship of Modal Logistics Park project vis-à-vis while for Phase II for “Pithampur Jal Chief Minister of at Karmad, after A meeting was final alignment (between Prabandhan Haryana to review incorporating held between of DFC passing Ahmedabad to Company Limited” the progress of the comments and Additional Chief through the Dholera), land is was also held on project. During the observations from Secretary area. On the being acquired 16th July, 2014 to meeting, it was State Govt., has been (Industries), request of along with discuss the way decided that the issued and pre-bid Government of DFCCIL, a acquisition of land forward for the project will be meeting with Rajasthan and JS, copy of final for 6 lane project. located at a suitable prospective bidders DIPP to discuss Techno- expressway. location close of was conducted on various pending Economic Consultant for In the meeting held Nizamgarh junction 24th September, 2014. issues relating to Feasibility preparation of under the in Nangal The last date of DMIC projects in report (TEFR) Detailed Project Chairmanship of Chaudhry abutting submission of bid Rajasthan on 19th has been Report for Chief Secretary of the dedicated proposal was on 27th December, 2016. forwarded to MRTS/RRTS Madhya Pradesh on freight corridor rail October, 2014. DFCCIL for options between the 16th July, 2014. track. It was However, on the A meeting was their reference AKVN Indore was further decided that basis of requested held on 14th July, and Ahmedabad and directed for fixation effective steps from several 2017 between coordination Dholera Special of raw water tariff would be taken by prospective bidders, CEO and MD, purpose. Investment and execution of the Haryana bid submission date DMICDC and Region. The Water Purchase Government for has been extended to ACS, Industries & Further, the interim report Agreement with providing 1000 17th November, 2014. DMIC, Chairman, consultant has highlighting key Narmada Valley acres of land to the RIICO, submitted the issues like MRTS Development SPV being Three bid proposals Government of Revised Final alignment, traffic Authority at the incorporated for were received till the Rajasthan to Techno – assessment and earliest. DMICDC the purpose. due date and the discuss the way Economic system selection has forwarded the same are being forward of the Feasibility etc, was submitted revised draft of State Government evaluated. project. This was Study for the by the consultant. RFQ-cum-RFP has been requested followed up by a project and the The interim report document for to provide the site State Government meeting on 20th same has been submitted by selection of details to move vide its letter dated July, 2017 under shared with the consultant was consultant for forward with the 19th January, 2015 has chairmanship of state been approved by review of Detailed project informed that JNPT ACS Industries & Government the State Project Report, Bid development has decided to build a DMIC, Chairman, for their Government in Process activities at the Dry Port round 40 RIICO, comments and the meeting held Management and earliest. Kms from SBIA and Government of suggestions. on 20th May, 2014 Construction requested to review Rajasthan with all at Gandhinagar. Supervision for the RfQ cum RfP has the master plan of the stakeholders In-principle The consultant project to the State been issued for SBIA and large of the State approval has has also started Govt. for approval. undertaking the portion allocated to Government to been obtained the engineering feasibility study. MMLP may be put to discuss the project for the project surveys along the The Board meeting Due date for industrial use. related activities by the finalized MRTS for “Pithampur Jal submission of bids alignment for Prabandhan is 5th May, 2016. Thirty three (33) and way forward. Authority. preparation of Company Limited” number of plots have Detailed Project was held on 20th A meeting was held been allotted to CEO&MD, A meeting was Report (DPR). November, 2014 on 17th May, 2016 industries in the DMICDC vide held under the The consultant wherein after under the joint Shendra Industrial letter dated 3rd Chairmanship reported detailed chairmanship of Area. August, 2017 to of Shri H.D. encountering deliberations the CEO&MD, ACS, Government Gujrati, public resistance tender packages for DMICDC and MD, of Rajasthan have Director while carrying out appointment of HSIIDC to review requested to (Operations & the engineering consultant for DPR the progress of initiate the land Business surveys. The State review, bid process activities under the acquisition Development), Government was management and project and to process for the Dedicated requested by construction expedite the same. node and also the Freight DMICDC to supervision for incorporation of Corridor resolve the issue at executing the A meeting was held the node level Corporation of the local level. project have been under the SPV. India Limited Further, the approved. Chairmanship of (DFCCIL) on consultant has Shri H.D. Gujrati, Road Link 25TH May, 2016 submitted route The tender Director Connecting to discuss the alignment design, document for (Operations & Bhiwadi – current status Station Area „Selection of Business Tapokara of Multi Model Plans, Civil and Consultant for Development), Industrial Logistics Hub Structural GADs Review of detailed Dedicated freight Complex via at Dadri and and Draft Project Report, Bid Corridor Ajarka to the possibility Environmental Process Corporation of Neemrana of developing Plan and Social Management and India Limited railway siding The Final Techno Impact Report as Construction (DFCCIL) on 25th from the DFC Economic the next scheduled Supervision” has May, 2016 to to the proposed Feasibility report milestone of the been issued on 14th discuss the current site. for the Project DPR. During the January, 2015 and status of Integrated was approved by follow up the last date for Multimodal The MMLH the State meetings, the submission which Logistics Hub project Government in its observations of all was 24th February, IMLH) at Nangal proposal was Steering the stakeholders 2015had been Chaudhary and the deliberated at Committee on 3rd deliverable extended to 11th possibility of length during meeting held on submitted by the March 2015. Six developing a the last meeting 18th June 2012. To consultant were bids have been railway siding from NICDIT held take the project concluded and the received . The the DFC to the on 23rd August, further the land consultant has process has been proposed site. 2017 wherein it details along the ensured that these annulled on was decided would be account of none of RfQ cum RfP was approved that more incorporated in the bidder issued for alignment was options may be the next qualifying the undertaking the shared with the worked out to deliverable i.e. minimum Techno -economic State increase the draft DPR. qualification feasibility study for Government. The overall viability The State Govt. criteria. Development of State Government of the project has provided their Integrated has to initiate the and the observations and Revised tender Multimodal process of land proposal may suggestions and document for Logistics Hub acquisition for the be placed again the same are being “Selection of (IMLH) at Nangal proposed with the Multi incorporated. Consultant for Chaudhary and development. Modal The project was Review of detailed M/s RITES has Transport Hub placed before the Project Report, Bid been appointed for State Government (MMTH). Board of Trustees Process the same. has appointed in the meeting Management and Urban A meeting was held on 17th Construction The DMIC Project Development & held on 19th January, 2014 for Supervision” has Implementation Housing (UDH) September 2017 considering been issued on 13th Trust Fund (DMIC Department as for the review inclusion in JICA July, 2015.The pre- Trust) has nodal agency for on project rolling plan for bid meeting for the approved the implementation of activities of DMIC Project. It same was held on incorporation of this project. Freight Village was decided in the 4th August, project SPV in Taking the project and MMTH meeting that the 2015.Nine bids partnering with the forward, UDH, under the project should have been received Government of GoR has initiated chairmanship of again be brought by the proposal due Haryana and the land CEO & MD, before the DMIC date, i.e. 10th execution of Joint acquisition DMICDC. Trust once the September, 2015. Venture Agreement process and issued alignment and Pre-Qualification for the project in its Section 4 for part DMICDC vide th broad financials proposals are under 14th Trust Meeting of road length letter dated 9 are completed. evaluation. held on 26th April, (35Kms). Section October, 2017 Meetings were 2016. 4 and Section 6 have held between Consultant for for part of road communicated GIDB, DSIRDA, Review of Detailed The Joint Venture length (35km) has regarding the GSRDC, GICC, Project Report, Bid Agreement was been issued. “in-principle” PMNC Dholera Process executed on 16th approval and DPR Management and June 2016 and the In the meeting obtained by the consultant to Construction project SPV in the held under the Board of IIT- discuss technical Supervision has name of “DMIC Chairmanship of GNL for issues like route been finalized. Haryana Multi Chief Secretary, sharing the cost nd alignment, design Letter of award to Modal Logistic Rajasthan on 2 for HT Lines at intersections the Consultant has Hub Project December, 2015, shifting in and interchanges, been issued. Limited” has been it was decided that Greater Noida station location, incorporated on the UDH will take for the MMLH station planning, Consultant for 27th July, 2016. immediate project. ridership forecasts Review of Detailed necessary action and system Project Report, Bid A meeting was held with regard to CEO&MD, technology. The Process on 8th July 2016 land acquisition DMICDC vide coordination Management and with Principal for the road link letter dated 17th strategy between Construction Secretary October, 2017 design of Supervision has (Industries) on Development of have requested Ahmedabad- been appointed and status of DMIC Aerotropolis CEO, GNIDA Dholera work is in progress. projects in Haryana to expedite the expressway and The Consultant has to review the The Techno – survey and Ahmedabad- submitted the progress of various Economic finalise the land Dholera MRTS Revised Final DPR activities. Feasibility Report details for the was also to the SPV. was approved by MMLH and discussed. The Various rounds of the State MMTH project interface options A review meeting meetings have been Government in its between MRTS was held on 30th held in DFCCIL to Steering A joint site visit and MEGA April, 2016 under discuss the current Committee was conducted th network were the Chairmanship status of IMLH at meeting held on on 29 th discussed. of CEO & MD, Nangal Chaudhary 18 June 2012. October, 2017 DMICDC to and the possibility to the MMLH Based on the Issues related to review the progress of developing a and MMTH by technical study, Ahmedabad- of the project. The railway siding from the Chief the site for the Dholera metro tenders for the DFC to the Transport Airport was project were selection of EPC proposed site. A Planning approved by State discussed and its contractor is likely letter has been Manager, North Government. progress was to be floated received dated 18th Central Further, reviewed in the shortly. August 2016 from Railways with DMICDC had Special Advisory DFCCIL regarding officials of During the Review submitted the Committee the “in-principle” DMICDC and Meeting on Status application for meeting held at approval sought for the SPV-IIT- of implementation setting up of 12th September, the development of GNL. of DMIC Projects proposed 2014 at DMICDC a railway siding at under the Aerotropolis to In the meeting office. The the proposed site Chairmanship of Ministry of Civil with CEO, technical for IMLH. Chief Secretary on Aviation and Greater Noida consultant has 15th June, 2016 at A meeting was held Ministry of Industrial presented fare Bhopal, it was on 1st August, 2016 Defence. A no Development structure and results of financial decided to expedite under the co- objection was Authority on model. Based on the process of chairmanship of received from the 23rd June 2016, inputs received by signing of the CEO &MD, Ministry of it was decided DMICDC, the Water Allocation DMICDC and MD, Defence, but to initiate steps consultant revise Agreement with Haryana State MoCA clearance to take the the financial Narmada Valley Industrial & is awaited. Land IMTH and structure and Development Infrastructure details for the MMLH options of funding Authority (NVDA) Development approved location projects would also be to meet the water Corporation Ltd. were sent to the forward in close detailed out. requirement of the (HSIIDC) on status State and Land coordination project by the SPV. of DMIC projects Acquisition with dedicated The consultant in Haryana to Process to be Freight has submitted the The tenders for review the progress initiated by the Corridor Draft DPR (4th selection of EPC of various activities. State. Application Corporation of deliverable) for contractor for the for site clearance India Ltd. the project and water Supply A meeting was held was submitted by (DFCCIL). A PMNC has project has been on 3rd August, DMICDC to joint survey was provided floated on 7th July, 2016 in Ministry of Airport Authority also conducted observation/ 2016. The pre-bid Railways under the of India. A on 28th June, comments to meeting was held Chairmanship of meeting on way 2016 with the consultant. on 12th July, 2016 Member (Finance), forward for officials of A review meeting and the proposal Railways wherein it establishment of DFCCIL, was held on 6th submission date was decided that Aerotropolis was GNIDA, Nov. 14 under the was 2nd September, DFCCIL may held under the Ministry of chairmanship of 2016. Three (3) participate in the chairmanship of Railways and CEO & MD, nos. of bid SPV formed Secretary, MoCA, DMICDC in DMCIDC. proposals have between HSIIDC on 18th January, this regard. A workshop was been received by and DMIC Trust as 2013 with conducted with the bid due date equity partner with representative of A meeting was Additional Chief and the bids are the approval of AAI, DIPP, held under the Secretary under evaluation. their Board. DMICDC, Govt. chairmanship of (Industries), of Rajasthan and CEO&MD, Government of M/s L&T +Pvt. A review meeting Consultants. DMICDC on Gujarat & CEO- Ltd. has been was held under the Application for 25th October, GIDB on 11th selected as EPC chairmanship of site clearance was 2016 to review December 2014 to contractor for the CEO&MD, submitted by the progress of discuss the Water Supply DMICDC on 16th DMICDC to spatial survey deliverable 3&4 project. The kick March, 2017 to Airport Authority work carried for the off meeting was discuss the progress of India. AAI is out by the assignment. held on 15th of activities under carrying out site consultant M/s Further, the November, 2016. the project with the suitability study Skylark Ltd. for Consultant has consultant M/s for the airport. the sites and to submitted Final The “Raw Water RITES and Maps of Survey of check the DPR on 30th Nov Purchase representatives of India (SOI) for feasibility of ember, 2014 and Agreement” the SPV. the site clearance providing a new PMNC has between DMIC have been railway provided the Pithampur Jal CEO&MD, procured from platform at the observations and Prabandhan Ltd. DMICDC visited SOI for provision existing rail site. comments on (DMIC-PJPL) and the site at Nangal to AAI. Land Final DPR. Narmada Valley Chaudhary on 1st identified for the RfQ cum RfP Development April, 2017 proposed project for selection of CEO &MD, Department alongwith the shall be notified consultant for DMICDC vide (NVDD) has been representatives of by the State preparation of letter dated 7th executed on 22nd State Government. Government after DPR for Multi- January, 2015 has June, 2017. The DFCCIL vide its the site clearance Modal Logistic requested CEO, physical progress of letter dated 25th from AAI. AAI Hub and Multi- GIDB to convey construction April, 2017 have officials made site Modal final approval of activities is about proposed to sign an visit to the Transport Hub the State 20% upto 31st July, MoU with proposed airport at Dadri, Uttar Government on 2017. Government DMICDC for site and carried Pradesh has the Detailed of Madhya Pradesh development of out due diligence been issued on Project Report vide letter dated Multi-modal of the site 25th July,l 2016. (DPR) for the 20th July, 2017 have Logistics Parks / features, nearby The last date project. requested SIPP to Hubs in providing developments, for submission The consultant grant “in principle seamless transport topography, of proposals after incorporating approval” for the logistics solutions habitation etc. A was 26th the comments proposal to acquire and expressed in- formal report August, 2016. from the 49% equity share principle from AAI related Stakeholders has holding of DMIC willingness to join to the airport site Pre-bid meeting submitted the Pithampur Jal hands for is awaited. In the was held on 8th revised draft Prabandhan Ltd. development of meeting held on August, 2016. Detailed Project held by NICDIT. proposed (IMLH) 4th April 2013 The bid report on 9th being developed by along with the submission date March, 2015. The matter was DMICDC and builders‟ guild, was 3rd MRTS project was accordingly State Government CREDAI Bhiwadi October, 2016. considered in the deliberated in the of Haryana near in the office of Four bids have meeting of DMIC NICDIT meeting Nangal Chaudhary. CTP NCR, Jaipur rd been received Trust held on held on 23 under the by the bid February 6, 2015 August, 2017. MoU was signed by chairmanship of submission date and it was decided DMICDC and Principal Secretary that Department The proposal DFCCIL for the UDH, Govt. of on 3rd of Economic submitted by the development of Rajasthan, it was October, Affairs vide its State Government Integrated Multi- decided that any 2016.M/s PWC letter dated 23rd on 20.7.2017 to modal Logistics permissions for has been February, 2015 acquire 49% equity Hub at Nangal building activities awarded the had included the share holding of Choudhary, in the influence consultancy project in the DMIC Pithampur Haryana on 5th area of Airport services for JICA Special Jal Prabandhan Ltd. May,2017. Site shall be given preparation of Rolling Plan for held by NICDIT by the State DPR for Multi- DMIC Project. has been approved. The project Government only Modal Logistic SIPP has consultants have after guidelines are Hub and Multi- requested Chief Multimodal submitted the final framed by State in Modal Secretary, Gujarat Logistic Hub master plan along consultation with Transport Hub vide letter dated Project: with broad cost DMICDC and the at DadrI, Uttar 1st June, 2015 to estimates. report/recommen Pradesh and the issue necessary Land acquisition dations provided LoA direction for for the project is at The first meeting of by AAI as per the has been issued formal approval an advanced stage. the co-ordination site clearance on 15th on the final DPR Out of the total group constituted report. AAI December, along with the area of 1.78 sqkm, between DFCCIL, submitted to 2016. initiation of Govt. land of 0.158 State Government DMICDC the site necessary activities Square km was of Haryana and clearance report A kick off for securing the transferred and DMICDC was held for the proposed meeting was ROW for the possession taken. on 18th July 2017 Aerotropolis held on 6th project. For Private land of to review the status project, which was January 2017 Secretary, DIPP 1.6214 Square Kms, fo the project. shared with the with the has requested Sections 4 & 6 State consultants for The project Chief Secretary, notifications were Government. AAI the status of consultants have Gujarat vide his issued, and action has proposed various projects submitted the final letter dated 2nd u/s 9 was also carrying out an with the master plan July, 2015 to completed. Obstacle consultant alongwith broad resolve issues with Rs.86.92 Cr was Limitation under the cost estimates. regard to provided to Surfaces (OLS) chairmanship of The project was availability of Collector, Dhar for Survey around the CEO & MD, placed for ROW for the compensation by site before taking DMICDC. consideration of development of the State any final decision NICDIT in its Ahmedabad Government. Six on the proposed A meeting was meeting held on Dholera MRTS petitions have been site. The State scheduled on 23rd August, 2017 th project. filed in the Government was 25 January and the same has 2nd workshop for Honorable High requested by 2017 at approval of final court of Indore been approved. DMICDC to carry DMICDC DPR of against land Government of out the same. office with the Ahmedabad acquisition and Haryana has further project Dholera MRTS court had ordered been requested to RfP for consultants, Project was to maintain status complete the land undertaking the survey conducted on 10th quo. The State acquisition for the Impact consultant and August 2015 and Government had project. Assessment of Railways the concerned moved for the proposed consultant. stakeholders vacation of the The application for Greenfield airport DMICDC provided their status – quo. grant of Terms of near Bhiwadi on along with inputs on the Reference (ToR) Indira Gandhi officials from study. The consultant for the project has International IITGNL to sort A review meeting submitted the been submitted to Airport, New out issues w.r.t. was held on 10th revised PPP MoEF&CC. Delhi was issued the rail November, 2015 structuring for the on 23rd May, 2013. alignment and under the project. After A joint site visit drawing relating Chairmanship of acquisition of land, was conducted by Obstacle to the survey. CEO & MD, the project would the officials of Limitation DMICDC to be taken up for DMICDC and Surfaces (OLS) Project review resolve the issues bidding. In the DFCCIL on 11th survey of the meeting for regarding the meeting on 16th January, 2018. proposed site was DMIC IITGNL alignment of DFC July, 2014 held carried out by the was held on Cabinet Committee and MRTS under the State Government 19th January of Economic corridors in the Chairmanship of and the same was 2017 at Affairs (CCEA) in region and the Chief Secretary, submitted to AAI. GNIDA office the meeting held Consultant has MP, the industries In view of the in Greater on 16th May, 2018 been directed to department was OLS survey, the Noida wherein has accorded its submit the final directed to utilize State Government the consultants approval for the DPR for MRTS at appropriate part of has also proposed presented the project. the earliest based the land, which was an alternate site status of on the discussions made available to for the activities under Site visit was held in the Ministry of Heavy development of the project. conducted on 19th meeting. Industries for Airport. Site visit June 2018 by Chief Secretary, NATRIP project of the alternate Project update Hon‟ble Industries Government of near Pithampur, for proposed site was meetings were and Commerce Gujarat during a locating the undertaken on held on 23rd Minister, th meeting held on proposed the 19 June 2013 by March, 2017 Government of th 30th January, 2016 IMLH Project since senior officials & and 29 March, Haryana. directed the the NATRIP representatives of 2017 to discuss Discussions were PMNC and Project could not the State the rail Design Consultant be implemented as held regarding Government, alignment to explore the proposed. expediting the land DMICDC and between the possibility of DMICDC was acquisition. AAI. If the consultant M/s reducing the asked to examine alternative site is PwC, M/s proposed ROW the feasibility of A meeting was held found suitable by Skylark (DGPS from 50m to 30m this new location under the AAI, DMICDC Consultant), and also to work for IMLH vis-à-vis chairmanship of shall file new Advisor out an alternative connectivity aspects CEO & MD, application with Railways, route along Botad- with respected to DMICDC AAI for site DMICDC and Dhanduka-Arnej- the Indore-Dahod alongwith State clearance. In the the Dholka-Bhavla- railway line being officials on 29th meeting held on representatives Ahmedabad meter constructed by August, 2018 to 17th June 2013, from DMIC gauge line and Western Railways. review the status of DMICDC IITGNL on perform an DMICDC was the project and way requested AAI to 23rd March, analysis of the examined the new forward. appoint an 2017 at option and further location from the independent DMICDC. compare it to aspect of rail A meeting was held consultant of building an connectivity and under the international A review elevated MRTS found the site non- chairmanship of repute through meeting was along the current suitable for the rail CEO&MD, International Civil held on 10th alignment and in connectivity. MP, DMICDC Aviation April, 2017 the reduced 30 m TRIFAC was alongwith State Organization under the th ROW. informed about the officials on 26 (ICAO) which chairmanship of Secretary, DIPP same vide September, 2018 to shall be acceptable CEO&MD, vide his letter DMICDC‟s letter review the status of to all stakeholders DMICDC to dated 3rd March, dated 27th August, the project and for carrying out discuss the 2016 has 2014. discuss the way the study progress of the requested the forward. The suggested by project Chief Secretary, Knowledge City concerned officials MoCA in meeting activities Government of Project.: were instructed to held on 18th alongwith the Gujarat to make report the progress January 2013, State the land available The total planned as per the decisions namely, “Impact Government for the project area is 4.42 sqkm, periodically. Assessment Study representatives. expeditiously. comprising of proposed Out of total 886.78 A meeting was Government land Greenfield airport A review acres required for held under the of 2.18 sqkm. and near Bhiwadi on meeting was the project, State th Chairmanship of private land of 2.24 existing IGI held on 8 Government has Secretary, DIPP sqkm. Of the Airport”. May, 2017 transferred 6.39 on March 15, Government Accordingly, the under the acres to the 2016 and it was portion 2.06 sqkm RfP floated by chairmanship of decided that was transferred, project SPV and DMICDC for the CEO &MD, NHAI will take up and remaining is in matching equity above study was DMICDC to expressway by progress. For the of Rs.191.67 crore withdrawn. discuss the acquiring 100 m private portion, has been released progress of the RoW which will notification was by NICDIT. DMICDC had project also accommodate issued u/s 4 and 6 requested the activities with MRTS RoW of and action u/s 9 is Pre-Feasibility State Government the DPR 30m. Land being completed Study (PFS) on to carry out the consultant M/s acquisition to be for 2.08sqkm; for Mass Rapid OLS survey of the PwC. taken up by remaining Transit System alternate site NHAI and State 0.16sqkm, Section 4 (MRTS) between which was carried M/s PwC has Government will notification was Gurgaon and out and submitted submitted the reimburse issued. Award for Bawal: to AAI for their Market acquisition cost to village Karchha review. AAI Assessment NHAI. land (0.3374 sqkm) Approval of the appointed the Report along DPR prepared by completed, final alignment and consultant to carry with the consultant has compensation PFS is awaited out impact Preliminary been approved by being distributed. from the State assessment study Design Report the State Rs.50.77 Cr Government. The of the proposed for MMLH Government in provided to Government of greenfield airport MMTH at the review Collector, Ujjain for Haryana had, near Bhiwadi on Greater Noida meeting held on compensation. meanwhile, given the existing IGI on 21st June, 16th May, 2016 Four petitions were its approval to the airport. The 2017. under the filed in Honorable creation of a Special consultant Review Chairmanship of High court of Purpose Vehicle for initiated the study meetings were Additional Chief Indore for the project. It was and the report held under the Secretary, 0.27SqKm of land. also requested to would be chairmanship of Industries and The State initiate the land submitted shortly. CEO&MD, Mines, Government has acquisition process Further, DMICDC on Government of filed a counter. for MRTS project. DMICDC 30th June, 2017 Gujarat. DMICDC is received a site and 13th July CEO&MD, During the meeting planning to start clearance for 2017 with all DMICDC vide of 31st May, 2012, it the DPR/Detailed establishment of concerned to letter dated 28th was agreed that Engineering Greenfield Airport expedite the July, 2017 has after the land Studies. Talks have near Bhiwadi from preparation of requested NHAI acquisition, the been initiated with AAI. As per the DPR for the to initiate the land development of the JICA for Japanese Greenfield Airport project. acquisition for the initial infrastructure long tenor, soft Policy of Ministry Railway Board proposed i.e. access road, loan. The project of Civil Aviation, has granted “in Expressway and construction of can only move DMICDC has principle MRTS projects boundary wall, forward with the initiated the approval” for together. water & power line support of key process of construction of Mega Industrial to the site should stakeholders- GoJ obtaining “in the Multi Model Park: be initiated. and GoR, who principle” Transport Hub Final report on Hon‟ble Chief need to finalise the approval for the (MMTH) at techno-economic Minister, Madhya alignment and make same. Based on Boraki which feasibility is being Pradesh, reviewed the land available. the discussion includes finalized in the status of In the meeting with Secretary, construction of consultation with Investment Region held on 12th June MoCA held on long distance the State and Early Bird 2012 under the 18th January, 2013, passenger Government. Projects along with chairmanship of DMICDC is terminal. Draft RfP for the the status of land Chief Secretary, required to carry DMICDC has preparation of acquisition. In the Government of out a study to requested Detailed meeting, consultant Haryana, it was assess the impact Ministry of Engineering was advised to suggested that a proposed Railways to Report for internal reconfigure the land detailed project Greenfield airport allow the Infrastructure was use of knowledge report needs to be near Bhiwadi on development as sent to the State city. prepared while existing IGI a Common Government for finalising the MRTS Airport. In order User facility review and RFP for inviting route alignment and to make this study under 1997 approval. The bids from concluding the land acceptable to all Policy of the observations of consultants for acquisition process. the stakeholders, Ministry of the State detailed DMICDC prepared DMICDC Railways and to Government were Engineering and the Draft Request requested AAI to waive off received and they Transaction for Proposal for appoint an Railway charges have provided an advisory services appointing the independent on area of 14 sq. km was approved by consultant to consultant of development of to be considered the State prepare the international Boraki Station for Detailed Government. Detailed Project repute through vide letter dated Engineering. State Report. The draft International Civil 25th July 2017. Government was M/s Tata RFP was shared Aviation A meeting with requested to Consulting with the State Organization North Central consider entire 45 Government. The (ICAO). The Railways Engineers Pvt. Ltd. sq. km of the comments received consultant was Allahabad was appointed for Mega Industrial from the State appointed and the regarding the undertaking Park for the Government were report finalized rail alignment detailed engineering Detailed incorporated and and forwarded to for MMTH of internal and Engineering. the RfP issued on all the project external 11th February, 2013. stakeholders with proposed at infrastructure of the Water Evaluation of eight a request to Boraki was held Desalination project. bids received in Secretary, MoCA on 28th July, Project, Dahej response to the RfP to hold a 2017. (EBP from The feasibility document issued by stakeholders Japanese side)) report was DMICDC was meeting for taking Details relating submitted by the completed and the the project to proposed A SPV, namely consultant. letter of Award has forward. connectivity Swarnim been issued to the plan requested Dahejspring After several selected consultant. Further, MoCA by Ministry of Desalination Pvt. rounds of Consultant was asked DMICDC Railways has Ltd., formed by interactions and appointed for to move ahead been sent vide the Japanese deliberations with preparation of and seek necessary DMICDC‟s consortium the State Detailed Project clearances from letter dated 21st members (Hitachi, Government Report. Inception the Steering August, 2017. Hyflux and officials and their report was Committee. Itochu) signed the consultants, the submitted by the Accordingly, A review Co-Development DPR was finalized. consultant and the DMICDC applied meeting was st Agreement with The project was same was for the grant of held on 31 Dahej SEZ placed for seeking forwarded to the “site clearance” August 2017 to Limited on March investment State Govt. for for the project by discuss the 22, 2012. The approval in the their review and MoCA and „No project term sheet for the meeting of Board observations. Objection timelines. Water Purchase of Trustees on 10th Certificate‟ from Agreement (WPA) September, 2013 Field investigation the Ministry of A reminder th between the SPV and the DMIC surveys are being Defence for the dated 12 and Dahej SEZ Project undertaken jointly proposed site. September 2017 Limited was also Implementation by the State Based on the has been sent to finalized during Trust Fund Government inputs received Railway Board the same time. accorded officials and the from Ministry of in this regard. WPA was investment consultants Defence, Further, the executed on 11th approval to the appointed by DMICDC has engineering January, 2013 in project. CEO, DMICDC for sent the desired drawings of the the presence of DMICDC vide his finalizing the route document to MMTH project Chief Minister, letter dated 24th alignment. The Ministry of has been shared Gujarat and Vice- September, 2013 consultant defence for with the Minister, METI, had requested to submitted the obtaining No Railway Board Government of the State Inception Report Objection vide letter dated Japan. The project Government to and the details of certificate.DMIC 14.11.2017. proposal for expeditiously land to be acquired DC has issued a equity investment complete the land for the project to letter dated 22nd A review in the project was acquisition for the State December, 2014 posed for widening the Government. The to MoCA to meeting under approval of approach road of interim report expedite the Site the DMIC Trust in its 9.5 Km length from highlighting key clearance. CEO chairmanship of meeting held on 7m ROW to 30m issues like MRTS & MD, vide letter CEO & MD, 18/19 March, ROW for meeting alignment, traffic dated 7th January, GNIDA and 2013. In Principle future requirements assessment and 2015and 2nd CEO & MD, Approval was and also vacation of system selection February, 2015has DMICDC held granted to take stay orders in order etc. was submitted again requested on 23.11.2017 15% Equity at par, to take remaining by the consultant Secretary, MoCA to review the the same was 27.06ha of land in and is currently for site clearance. Preliminary communicated to its possession. The under review. DMICDC has also Design report METI. shareholders requested MoD for the MMLH Dholera Agreement for The project was vide letter dated and MMTH as International constitution of the placed before the 8th January 2015 submitted by Airport project SPV was Board of Trustees to expedite the the project also finalized with in the meeting held issuance of No consultant‟s A SPV called“ the State Nodal on 17th January, Objection M/s PwC. Dholera Agency. The 2014 for Certificate for the International project was considering project site. A review Airport Ltd.” was officially inclusion in JICA meeting was formed by the inaugurated by rolling plan for Ministry of conducted with Government of Chief Minister of DMIC Project. It Defence has the officials of Gujarat. Project Madhya Pradesh was decided in the issued the No SPV consultant implementation jointly with meeting that the Objection and DMICDC framework will be Minister of project should Certificate for the on 5th finalized after the Commerce and again the brought Aerotropolis December, environmental Industry, before the DMIC project on 11th 2017 to finalise clearance. Land Government of Trust once the February 2015. the land details for the project was India on 13th alignment and DMICDC has for the project September, 2013 at broad financials are received the Site site. earmarked by the Bhopal. The completed. The Clearance for Government of consultant State Government establishment of The North Gujarat. EIA for submitted the DPR communicated to Greenfield Airport Central the site carved out for external DMICDC vide near Bhiwadi from Railways vide from the existing infrastructure letter their dated MoCA vide their their letter nd site was which is being 9th April, 2014, letter dated 18th dated 22 undertaken by reviewed by the that a Special November, 2015. December, AAI. State Government. Purpose Vehicle in 2017 have CEO&MD, the name of A meeting was communicated Airports Authority DMICDC & MD, Haryana Mass held with the regarding the of India (AAI) MP TRIFAC Rapid Transport officials of AAI “in-principle” entrusted with the reviewed the Corporation for preparation of approval for the responsibility of project in the (HMRTC) was Detailed Project project of undertaking the meeting held on incorporated for Report and development of DPR and 14th Nov., 2013. implementation of accordingly details MMTH at Environment DMIC Trust mass rapid of the project Boraki. Clearance for the approved the transport projects have been DMICDC vide Project and the proposal on 6th in Haryana and, it forwarded vide letter dated 5th fee payable by December, 2013 has been decided to email dated 15th February, 2018 DMICDC will be for subscribing to transfer the MRTS May, 2015. has responded considered as the shares of the project from to the DMICDC‟s equity SPV for this project HSIIDC to Airport Authority observations in the Project. in partnership with HMRTC. of India (AAI) sent by NCR. DPR for State Government vide its letter of Madhya Pradesh. A meeting of the dated 11th June, DMICDC vide Greenfield DMICDC Special Advisory 2015 has informed letter dated 16th International requested State Panel of DMICDC DMICDC that February, 2018 Airport near Government of was held on 16th AAI shall take up has proposed to Dholera was Madhya Pradesh to May, 2014 to the preparation of execute the prepared by the expeditiously move review the status DPR for Memorandum Airport Authority ahead with the and issues involved Greenfield airport of of India (AAI). execution of in the MRTS at Kotakisam Understanding Ministry of Shareholders project. Tehsil in Alwar (MoU) between Defence has agreement. State Interactions have District, Ministry of issued No Government/ also been started Rajasthan. The Railways and Objection Nodal agency is with JICA team for matter is being NICDIT/DMI Certificate. seeking necessary the MRTS project. taken forward. CDC/GNIDA Dholera approvals for the /DMIC International execution of SHA. A letter was sent SIPP vide his IITGNL for Airport from CEO&MD, letter dated 1st clarification of Corporation The project was DMICDC to October, 2015 the Limited submitted placed for Member Secretary, followed by observations a request to investment NCRPB requesting another letter made by NCR Ministry of Civil approval by the for the final DPR from CEO & and for Aviation for an Cabinet Committee for Delhi-Rewari- MD, DMICDC expediting the „in-Principle‟ for Economic Alwar RRTS vide his letter project approval. Affairs (CCEA) in corridor on the dated 26th activities its meeting held on basis of which the October 2015 has related to the DMICDC has 20th January, 2014 alignment for requested the development requested Ministry and CCEA MRTS Gurgaon- Ministry of Civil of the MMTH of Civil Aviation accorded their Bawal could be Aviation to issue project. After for expediting the investment finalized to harness of formals site discussions with „In-Principle‟ approval for the the synergies of two clearance for the Railway Board approval vide its project. The projects. A formal project. on 10th letter dated 11th Shareholders request for April,2018, the April, 2015. Agreement for the approval of Based on the draft MoU was project between finalized route decisions taken in revised Site clearance DMIC Trust and alignment has been the meeting held regarding the approval for the State Nodal sent separately on 2nd December, ownership of setting up a Agencies has been from Secretary, 2015 under the land for the greenfield airport executed. State DIPP and Chairmanship of Terminal was given to Governments of CEO&MD, Chief Secretary, station. The GIDB by Ministry Madhya Pradesh DMICDC to the Government of revised MoU of Civil Aviation vide its order dated State Govt. of Rajasthan, was shared with vide letter dt. 6th 22nd March, 2014 Haryana. In this Railways Board June, 2014. has issued regard, a meeting DMICDC is in on 17th April, directions for was held under the the process of 2018 and DIACL had transfer of land to chairmanship of awarding the work comments on meeting with the project SPV Chief Secretary, of DPR the same are MOEF along with “Madhya Pradesh Govt. of Haryana preparation to the awaited. The representative Vikramaditya to review the Airport Authority final from AAI and Knowledge City progress of the of India (AAI) confirmation their consultant (Ujjain) Ltd.”. A project. The State after including the on the MoU st on 1 July, 2014. letter from Govt. officials were scope of getting was received by Secretary, DIPP directed to finalise Environment DMICDC on The ToR was was sent to Chief the alignment at the Clearance from 10th July, 2018 discussed and Secretary, earliest. Ministry of vide letter dated MOEF also Government of Environment, 29th June, 2018. reviewed Madhya Pradesh on HMRTC vide their Forest and The MoU proposed Airport 21st May, 2014 letter dated 17th Climate Change between Indian Master Plan. regarding the July, 2014 intimated (MoEFCC) on Railways and Subsequently, a transfer of land to that after the behalf of the SPV DMIC revised Master the project SPV. decision in the proposed SPV. IITGNL for plan was meeting held on The cost to be the submitted to The Project SPV 30th June, 2014 incurred by development of MOEF and TOR taken the under the DMICDC in the MMTH has approval has been possession of Chairmanship of preparation of been approved accorded by 217.78 Ha of Chief Secretary, DPR will be by the Board of MOEF. Government land Haryana, the State treated as Ministry of and 197.42 Ha of Govt. approved the DMICDC‟s equity Railways and Consultant has private land route alignment of contribution in the will be executed commenced EIA transferred for MRTS Gurgaon- proposed SPV. shortly. study. The DPR Vikram Bawal. The route submitted AAI Udyogpuri alignment The first draft of Based on the has been reviewed (formerly proposed to be the SHA & SSA “In Principle” by PMNC and Knolowlege City, routed through has been shared Approval from comments on the near Ujjain) Central Peripheral with the State North Central same have been Road (CPR) instead Government for Railways for communicated by The State of project of their approval. PMNC on 28th Government DMICDC as MMTH Boraki, January, 2015. further issued the planned earlier. DMICDC has a meeting was notification for paid the first conducted on DIACL and exemption of stamp As the connectivity instalment 9th March, 2018 PMNC had with duty on transfer of to Global City towards the at NCR WAPCOS and the land to the Project Project is necessary preparation of Headquarters, scope related to SPV on 23rd May, for both the DPR for the Allahabad with Flood study for 2014. An amount projects to take-off project to AAI. the officials of the Airport and of Rs. 55.93 crore and it was initially The preparation NCR and aviation area was was released as agreed by HSIIDC, of the DPR has DMICDC. discussed. PMNC equity in the SPV as a letter was sent to been initiated and Letter to NCR had prepared DMIC Trust‟s Haryana State a site visit was regarding the technical notes on share on 20th June, Government with a made by the meeting was the „Flood Study 2014. request to convene officials of AAI, sent on and mitigation a meeting for final Government of 27.03.2018. plan‟ requirement The Board meeting decision on the Rajasthan and along with for “Madhya approved alignment DMICDC on DMICDC vide th preliminary ToR Pradesh from the 22nd March, 2016 letter dated 9 and submitted to Vikramaditya perspective of in this regard. February, 2018 DIACL for their Knowledge City holistic responded to review. (Ujjain) Ltd.” was connectivity. To review the the letter from held on 16th July, present status and DFCCIL PMNC had 2014 to discuss the HMRTC on request further course of regarding started preparing way forward for the of DMICDC action for Payment of document for project. appointed a nodal proposed Application fees submission to person for better Greenfield Airport as Private MoCA for the „in- The bid documents coordination for near Bhiwadi, a Freight principle‟ for external this project. meeting was held Terminal approval, based infrastructure was on 21st April, Policy. on the revised prepared and A meeting was held 2016 under the DPR submitted by submitted by at DMRC office on Chairmanship of The consultant AAI in the month consultant. 17th September, CEO & MD, has submitted of June, 2014. DMICDC given its 2014 to discuss the DMICDC with the Preliminary comments and the interchange option the officials of Design report The final DPR same was sent to of connectivity Government of for the MMLH was submitted by the State Govt. for between DMRC Rajasthan and and MMTH AAI to DIACL in approval. yellow line and Airport Authority and the same is December 2014. MRTS Gurgaon of India. being reviewed Parallely, JICA A meeting was held Bawal at HUDA by the SPV. through the under the city centre. During A review meeting appointed chairmanship of the meeting, one was held on 21st A meeting was consultants has Chief Secretary, integration option July, 2016 under conducted carried out an Government of was considered by the Chairmanship under the independent M.P. on 16th July, Director-BD and of CEO & MD, chairmanship of study. The draft 2014 to discuss the the consultant was DMICDC with CEO & MD, final report of the issues related to the directed to work the officials of the DMICDC and same has been project. In the out and submit the Government of CEO & MD, submitted and meeting, AKVN details of this Rajasthan and GNIDA with discussed with Ujjain was directed integration option Airport Authority officials of DIACL on 14th to submit the to DMICDC and of India. GNIDA, December, 2014.A details of DMRC for further DMIC IITGNL comparative ROW/ROU approval of the A joint site visit and the analysis of both clearance for lying operations was held on 20th consultants on the studies is down of trunk main department. October, 2016 by 5th January, being prepared. & land acquisition the officials of 2018. The The Final DPR is proposal for Secretary, DIPP. DMICDC, AAI, Preliminary awaited from widening of LAO, Design Report JICA study team. approach road of Secretary, DIPP , in Government of (DPR) for the 9.5 km length to his letter dated 14th Rajasthan and project was In the 21st Collector, Ujjain. October, 2014 to M/s RITES to approved in the Meeting of State Government review the survey joint review Steering The Detailed of Haryana, had and investigation meeting and the Committee held Project Report also highlighted the work. consultants on 8th July, 2015 (DPR) for external connectivity to have been for Greenfield and internal Global city among A review meeting directed to airports, the infrastructure was the list of pending was held on 6th undertake the Committee approved by the issues of DMICDC December, 2016 preparation of recommended State Government. projects to be under the DPR. that in respect of The consultant addressed by the chairmanship of setting up of an submitted the State Government CEO&MD, The letter dated airport at Dholera, composite tender on urgent basis. DMICDC to 10th January, DIACL may get package comprising Issue of the MRTS review the 2018 from the necessary of both external connectivity progress of work DFCCIL inputs from &internal envisaged for the w.r.t. preparation regarding the WAPCOS before infrastructure proposed Global of the DPR by deposit of approaching the components and city project was AAI and the amount Steering the same was discussed in the status of land pertaining to committee for “in- forwarded to the meeting held under acquisition by the cost of principle” State Govt. for the chairmanship of State shifting the HT approval. DIACL approval. Principal Secretary, Government. lines in Greater may in the Industries & Noida for meantime, also The project was Commerce, Another meeting MMLH Project pursue its case for also reviewed in the Government of was held on 22nd has been environment Special Advisory Haryana on 15th December, 2016 forwarded to clearance. The Committee meeting November, 2014. to discuss about DMIC IITGNL committee also held at 12th the possibility of (SPV) vide asked AAI to September, 2014 at The topographical developing Multi letter dated 17th offer their specific DMICDC Office surveys, Modal Logistics January, 2018 comments in and the tender environmental and Hubs in proximity for necessary respect of packages were social surveys along to the proposed action. proposed airport discussed in detail. the approved route Aerotropolis. at Dholera within alignment have A meeting was 150 k.m. vis-à-vis The Board meeting been completed. Further, a meeting conducted with factors i.e. for “Madhya The Geo-tech was held on 30th the consultant commercial Pradesh surveys started and January, 2017 with PwC in the viability sharing of Vikramaditya presently under the officials of presence of traffic etc. Knowledge City progress along the AAI and Railways (Ujjain) Ltd” was alignment. DMICDC to Adviser for The proposal of held on 24th discuss the DMICDC Environment September, 2014 The Alignment & passenger traffic regarding the Clearance of wherein detailed Station Area Plans and cargo design for Dholera deliberations were and draft potential for the Freight Village International held on the tender Environmental Airport and the and MMTH, Airport was packages. Detailed Management Plan possibility of Greater Noida considered by the discussions were & Social Impact developing Multi on 14th May, Environment held with MP Report is under Modal Logistics 2018. Appraisal TRIFAC from 25th finalization and Hubs in proximity Subsequently, Committee in its to 28th September, shall be submitted. to the proposed another 150th meeting held 2014 on finalise the Aerotropolis. meeting was on 30th July, 2015. tender documents. The revised interim convened with The Environment The revised tender report submitted by Review meeting DFCCIL on Clearance for the document along the consultant was was held on 6th 18th May, 2018 Project has been with the revised reviewed. Request February, 2017 regarding the recommended by document for was sent to the under the traffic the Environment appointment of State Government Chairmanship of movement and Appraisal Programme regarding approval CEO & MD, operation plan Committee of Managers was of interim report to DMICDC with for the Freight MoEFCC. Formal forwarded to the enable DMICDC to the officials of Village. The letter dated 27th State Government move forward to AAI, Government consultants November, 2015 of Madhya Pradesh the next stage of of Rajasthan on were instructed from MoEFCC for perusal and the DPR the project. to submit the has been received. approval. assignment. In a revised final review meeting held A meeting was DPR within A Steering A meeting was held at DMICDC on held on 19th June, two weeks after Committee on 31st October, 24th November, 2017 between incorporating Meeting held on 2014 under the 2014, the CEO and MD, the changes. 28th December, chairmanship of preliminary DMICDC and 2015 under the CEO&MD, financial analysis MD, RIICO cum A meeting was Chairmanship of DMICDC with was reviewed and Commissioner, conducted with Secretary, Ministry TCE to review the necessary directions Department of Noida Metro of Civil Aviation progress of this were issued to DMIC, Rail (MoCA). MoCA project. consultant. The Government of Corporation on have granted “in consultant has been Rajasthan to 18th June, 2018 principle” The Board meeting asked to submit discuss the way regarding the clearance to the for “Madhya draft Business plan forward of the extension of Project. Pradesh for MRTS project. Noida Metro Vikramaditya Gurgaon, Bawal at from Delta The RfQ cum RfP Knowledge City the earliest. CEO&MD, Station in for Selection of (Ujjain) Ltd” was DMICDC vide Greater Noida Transaction held on 14th The project was letter dated to the proposed Advisors for January, 2015 placed before the 20.11.2017 have Multi Modal Development of wherein the tender Board of Trustees requested ACS, Transport Hub International packages for the in the meeting held Industries, Govt. at Boraki. It Airport at Dholera trunk infrastructure on 17th January, of Rajasthan to was decided in Gujarat under and tender for 2014 for expedite the land that the SPV DMIC Project has appointment of considering acquisition and would examine been issued on PMC has been inclusion in JICA formation of SPV the proposal 19th May, 2016. approved for rolling plan for for the project. and initiate the The pre-bid issuance. DMIC Project. It process of meeting was held was decided in the CEO& MD obtaining on 30th May 2016. The tender meeting that the DMICDC vide approvals from The RfQ cum RfP document for project should letter dated 6th GNIDA and for Selection of “Selection of again be brought December, 2017 the State Transaction Construction before the DMIC has requested Government. Advisors for agency for the Trust once the Govt. of Development of development of alignment and Rajasthan to A meeting was International Infrastructure broad financials are expedite the land conducted with Airport at Dholera Work for Vikram completed. acquisition and DFCCIL on 6th in Gujarat under Udyogpuri in formation of SPV July, 2018 to DMIC Project was Ujjain” was issued A meeting was held for the project. discuss the level issued on 19th on 4th February, under the of Rail Flyover May, 2016. Four 2015. Six (6) bids chairmanship of A meeting was (RFO) from (4) nos. of have been received Chief Secretary, held between WDFC yard at proposals have by the last date for Haryana on 23rd Chief Secretary, Dadri to DMIC been received by submission, i.e. 30th December, 2014 to Govt. of Freight Village. the bid due date April, 2015 . discuss the MRTS Rajasthan and The RFO levels on 29th July, 2016. alignment options CEO&MD, were finalized. Letter of Award has to connect the DMICDC on 5th M/s PwC have been issued to the proposed Global February, 2018 to Draft DPR has been selected as selected EPC City project with discuss the been submitted the Transaction contractor for the MRTS Gurgaon- progress of by the Advisors for development of Bawal project .In project activities consultants for Development of Infrastructure this meeting, there and to expedite the Freight International Work for Vikram was a broad the land Village and th Airport at Dholera Udyogpuri in Ujjain consensus that acquisition and MMTH on 17 in Gujarat under Project MRTS alignment formation of SPV July, 2018. The DMIC Project. Management may be routed for the project. same is under The kick off Consultant for the through the Global A meeting was review by the meeting was held project has been City for overall held between SPV. on 17th shortlisted and the benefit of the Additional Chief A meeting was September, 2016. Letter of Award has region. For the Secretary, Govt. conducted on been issued. The purpose of serving of Rajasthan and 31st August, A meeting was contractor has the sectors in the CEO&MD, 2018 with the held on 11th mobilized on the vicinity of Global DMICDC on 18th consultant in November, 2016 site. City, an additional April, 2018 to the presence of at DMICDC station is also discuss the representative office to review .The public hearing proposed to be progress of of Railways and the progress of for EIA clearance considered before project activities Adviser for activities being has been conducted Global City. A and to expedite st DMICDC carried out under successfully on 21 formal approval on the land regarding the January, 2015 at the alignment is acquisition and the project. Ujjain. The Final awaited from the formation of SPV design for EIA reports after State Government. for the project. Freight Village Another meeting incorporation of CEO&MD, (FV) and Multi was held on 8th comments received CEO&MD, DMICDC vide Modal December, 2016 during the public DMICDC vide letter dated 31st Transport Hub letter dated 8th at DMICDC hearing has been May, 2018 have (MMTH), January, 2015 has office to review th submitted on 5 requested State requested ACS Greater the progress of May, 2015 to Government of Industries & NOIDA. activities being Madhya Pradesh Haryana for formal DMIC, carried out under State Environment approval on MRTS Government of Meetings with the project. impact Assessment alignment passing Rajasthan to Land Authority. through Global city provide the land Department of as discussed in the Further the details for R&R GNIDA were meeting dated 23rd project was The Presentation held on December, 2014. package for the reviewed at the before the State The Alignment & project and initiate 26.9.2018 and level of ACS Appraisal Expert Station Area Plans the activities 16.10.2018 to (Industries), Committee was and Draft related to conduct review the Government of th made on 4 July, Environmental the public hearing status of land Gujarat in the 2015 and minutes Management Plan for obtaining acquisition for Board meeting of of the meeting was & Social Impact Environment the project. the SPV (Dholera issued on the same Report and draft Clearance for the International A follow up day. On the basis business plan have project. Airport Company meeting was of the deliberations, been submitted by The Terms of Ltd.) held on 27th held on 14th State Appraisal the DPR consultant Reference (TOR) December, 2016 November, Expert Committee and the same are for carrying out at Gandhinagar. 2018 with has asked to submit being reviewed. the EIA study for officials of additional The reports have the proposed Review meetings DFCCIL, information and the also been sent to Bhiwadi were held on 23rd DMICDC and consultant has the State International January, 2017 and consultants to already provided Government for Airport, District 6th February,2017 discuss the the same. Further, their comments and Alwar, Rajasthan under the project design proposal was observations. DPR has been issued by Chairmanship of th basis report. considered on 8 Consultant has the MoEF^CC CEO&MD, September, 2015 submitted Draft vide letter dated DMICDC Follow-up and the State Level DPR of 17 th August, 2017. wherein the meetings were Environment the project on 18th The public hearing project held on Impact Assessment April, 2015.The was held on 12th consultants 7.12.2018 & Authority (SEIAA) same has been September, 2018. presented the 17.12.2018 with had recommended forwarded to the The application current project officials of Environment for Grant of activities and clearance for the State Government Environment DFCCIL & deliverables under Project has been for their comments Clearance for the consultants to the project. obtained. and observations. project has been discuss the submitted to project A review meeting Project A kick-off meeting MoEF&CC on connectivity was held on 7th Management with regard to JICA 29th November, with WDFC. April, 2017 under Consultant for the preparatory survey 2018. the chairmanship project has been for Gurgaon-Bawal CEO, GNIDA of CEO&MD, appointed and MRTS Project was Development of vide his letter DMICDC mobilized on the held at DMICDC the Knowledge dated 8.10.2018 wherein the site. The under the City have project contractor has Chairmanship of communicate d consultants initiated work on CEO&MD, The Final Techno regarding the presented the the site. DMICDC on 23rd Economic completion of current project January, 2015. In Feasibility report 80% land activities and The public hearing this meeting, the for Knowledge acquisition for deliverables under for EIA clearance study work plan of City was approved the project. the project. has been conducted JICA team and data by the State successfully on 21st and other Government in its Boraki A review meeting January, 2015 at information Steering Railway was held on 8th Ujjain. The Final required by the Committee Station: May, 2017 under EIA reports after JICA study team meeting held on the chairmanship incorporation of was discussed. 18th June, 2012. Site details were of CEO&MD, comments received JICA team was Moving ahead overlaid on DMICDC during the public ensured of all DMICDC also revenue maps wherein the hearing has been possible assistance submitted the land of the identified project submitted on 5th by DMICDC and details to the State site and consultants May, 2015 to Haryana State Government. submitted to presented the Madhya Pradesh Government for Section 4 the State based various models of State Environment completion of this notification for uponnte the project impact Assessment study. land acquisition of revised structuring. Authority. Phase 1 of the alignment The JICA Knowledge City provided by A proposal on The Presentation Preparatory survey (3.26 sqkm) was Dedicated “Bundling of before the State team discussed issued as part of Freight Dholera Airport Appraisal Expert issues related to the Phase 1A of the Corridor with Ahmedabad Committee was MRTS project with node. Corporation of Airport” was sent made on 4th July, HMRTC, the State India Limited. by Principal 2015 and minutes nodal Agency for Further, Section Draft Techno- Secretary of the meeting was this project on 15th 5a had been Economic (Industries & issued on the same April, 2015 at issued. Public Feasibility Mines), day. On the basis HMRTC office at hearing was Study was Government of of the deliberations, Chandigarh. conducted and submitted to Gujarat to State Appraisal Land Acquisition State Secretary, Ministry Expert Committee DMICDC vide Officer (LAO) Government of of Civil Aviation, has asked to submit letter dated 21st submitted the final Uttar Pradesh GOI vide letter additional May, 2015 has sent report to State for their review dated 19th June, information and the the replies to the Government. The and comments. 2017. consultant has observations State Government already provided highlighted in the had issued Section The comments Principal Secretary the same. Further, letter from 6 for the area. of the State (Industries), proposal was HMRTC. Govt. on draft Government of considered on 8th report were Gujarat vide letter September, 2015 CEO & MD, received on dated 8th and the State Level DMICDC vide Integrated Water 25thJune, 2014. th September, 2017 Environment letter dated 13 resource In the meeting have requested Impact Assessment May, 2015 has Management dated 20th AAI to participate Authority (SEIAA) requested NCRPB Plan March, 2013 as the equity has recommended to share the the consultant The consultant partner for the the Environment feasibility report of made a detailed appointed for project in the joint clearance for the proposed RRTS presentation on preparation of an venture company. Project. project with JICA the proposed A meeting was study team. A joint Integrated Water layout plan and held on 3.11.2017 A meeting was held meeting with JICA Resources costs. The to discuss about on 26th October, study team and Management Plan consultant was the proposal on 2015 under the M/s AECOM was and DPR for advised to equity Chairmanship of held on 13th May, alternative sources incorporate the participation by CEO & MD, 2015 to discuss the of water for the suggestions of AAI for the DMICDC followed progress of the KBNIR against GoUP and project in the joint by another meeting study. the RfP issued on submit the st venture company. held on 7th 1 June, 2013. The report at the November, 2015 CEO & MD, consultant earliest. The Principal Secretary under the DMICDC vide submitted the observations th (I&M), Govt. of Chairmanship of letters dated 18 Inception Report, made by GoUP Gujarat vide his Secretary, DIPP to May, 2015 has Situation Analysis were letter dated review the progress requested NHAI, Report and the incorporated 6.12.2017 and of the work done Department of report on System and DMICDC 01.01.2018 has by the EPC Town and country Wide Decision submitted the requested Contractor and the Planning, Support Model draft report to Chairman, Airport PMC and the way Government of Based Framework State Authority of forward. Haryana and & Evaluation Government of India(AAI) for Dakshin Haryana Criteria and Field Uttar Pradesh equity Review of the Bijli VitranNigam Investigation Plan. vide its letter participation by progress of to share the specific The reports are dated 8th April AAI in the project construction works details/ report with under review by 2013 for company. on site was held on JICA study team. DMICDC and the comments. 8.4.2016 and State Nodal A meeting was 15.6.2016. The A meeting was held Agency. In the steering held on preparatory on 15th June, 2015 committee 21.03.2018 under activities for the under the The Progress of meeting held on the chairmanship project have been Chairmanship of the project was 11.05.2013 of Chairman, AAI completed. CEO & MD, reviewed by between to review the DMICDC to CEO&MD, DMICDC and proposal by State During the Review discuss various DMICDC on 14th Government of Govt. of Gujarat. Meeting on Status issues related with August, 2014. The Uttar Pradesh, of implementation the MRTS project. State Government it was decided AAI has given in- of DMIC Projects The meeting was provided its that Greater principle under the attended by comments on the Noida approval for its Chairmanship of Principal Secretary, first four Industrial equity Chief Secretary on Industries deliverable/report Development participation in 15th June, 2016 at alongwith the s submitted by the Authority the Dholera Bhopal, it was representatives consultant. The (GNIDA), shall Airport. Various decided to expedite from State consultant resolve the meetings were the process of Government of submitted the matter of the conducted during signing of the Haryana. JICA compliance to the DFC alignment the month (25th Water Allocation Study team, comments at the earliest and 26th April Agreement with HMRTC and the received, which taking into 2018) with the Narmada Valley DPR consultant. have further been consideration consultants PwC, Development communicated to the local site DIACL, Authority (NVDA) In a letter dated the State Govt. by conditions and WAPCOS, to meet the water 19th June, 2015 to DMICDC for consulting with Irrigation Dept., requirement (11 Chief Secretary, final approval of the local PMNC and SPV- MLD) of the Government of the reports. community. DICDL to project by the SPV. Haryana, Secretary, The final discuss the way DIPP has requested A stakeholders decision in this forward on flood The physical to initiate the land meeting chaired regard is mitigation and progress of the acquisition for by the Secretary, awaited from Airport site project achieved so 10km of Right of DMIC, Government of development. far is 26%. The Way for MRTS Government of Uttar Pradesh. Survey, Gurgaon – Bawal Rajasthan was Principal Investigation, project between held on 21st It was also Secretary (I&M), construction of IMLH Location to October, 2014 to suggested to Government of boundary wall and the Bawal town, discuss the move forward Gujarat vide their design works are in which was earlier analysis carried on formation of letter dated 22nd progress. notified under the out by the the SPV May, 2018 to old Land consultant, between Chairman, A meeting was held acquisition Act but comments from DMICDC and Airport Authority on 4th August, presently denotified stakeholders and Greater Noida of India (AAI) 2016 to review the by the State the way forward Industrial have progress of work Government. for the project. Development communicated on site by the Drilling of Corporation for the agreement of officials of A meeting has been exploratory bore the project Government of DMICDC and SPV held on 27th July, wells for studying based on Gujarat on the alongwith the PMC 2015 under the water availability suitable equity following: and EPC chairmanship of has been partnership  1426 Ha. of contractor. Chief Secretary, completed by the structure. land will be Government of consultant. Secretary, DIPP made available Haryana to discuss As per letter and CEO&MD, on lease rent various issues The consultant dated DMICDC visited of Rs.1 per related to MRTS has submitted 13.11.2013, the site at Vikram annum for 30 Project and the Situation Analysis received from Udyogpuri on 23rd years further decisions regarding Report for Surface Infrastructure October, 2016 to expandable to approval of route water, Ground & Industrial review the progress another 30 alignment etc. water and Development of work. years; pending on part of Reclaimed water. Commissioner,  An additional the State Interim Integrated Government of A review meeting Government. Water Resources Uttar Pradesh, land 5 to 6% was held on 15th of land for Management Plan with regard to November, 2016 by A review meeting commercial and Draft survey the officials of was held on 23rd development Detailed Project conducted by DMICDC, SPV i.e. November, 2015 of city side of Reports of various DFCCIL for Vikram Udyogpuri with Principal the airport will alternatives for the proposed Ltd. wherein the Secretary, be provided; MBIR, The same Eastern DFC progress of work Industries, has been alignment at the  Various was presented by Government of forwarded to the subject site, the utilization like the PMNC and Haryana to finalize State Government negotiations power EPC contractor. the alignment for for their with the local connection, the project and it comments on the farmers were water Officials from was decided that same. Comments completed and connection DMICDC visited the same shall be on Situation the State and drainage the site to monitor taken in the Analysis Report Government is system shall be the progress of meeting of the for Surface Water, facilitating the provided up to activities on site by Hon‟ble Chief Ground Water process. the point of the PMC and EPC Minister of and Reclaimed airport contractor on 2nd Haryana. Water has been The land premises. March, 2017. received from measuring an Concessions/ Another review Public Health approximate exemptions A review meeting meeting was held Engineering area of 150 will be was held under the on 16th December, Department and acres for the provided to chairmanship of 2015 under the Water Resources integrated local property CEO& MD, Chairmanship of Department, transport hub tax; DMICDC to Principal Secretary Government of project is  Flood review the physical to CM, Rajasthan and already under mitigation progress of Government of consultant has the possession outside the construction Haryana. submitted their of the State airport activities at site on Accordingly, the compliance on the Government of boundary shall 24th March, 2017. DPR has been same. Uttar Pradesh be the submitted to the and the land The agreement on responsibility State4 Government During the State acquisition “Supply of water of the State. for comments / steering process for the from Water supply A meeting was approval vide letter Committee remaining land pipeline from th held under the dated 24 meeting held on was initiated. Ujjayini to Ujjain st chairmanship of December, 2015. 1 December, Industrial area Various Chairman, AAI on 2014, the Vikram Udyopuri Next review meetings have 14th June, 2018 to consultants Ltd. in Ujjain” has meeting was held been held with discuss the revised apprised that the been signed on 15th January, Ministry of DPR alongwith total water between with 2016 under the Railways the roadmap/ demand for Narmada Valley Chairmanship of representatives timelines of KBNIR would be Development Chief Minister of to explain about important 463 MLD till year Authority (NVDA) Haryana to review the project milestones till the 2014\\40 and 260 and Vikram the progress of the planning and ground-breaking MLD till 2020. Udyogpuri Ltd. on project. During the support ceremony. The They highlighted 24th May, 2017 to meeting, it was required from revised DPR hs that augmentation meet the water decided that the them. The brief been shared with of external surface requirement (11 final DPR will be project note AAI and it was water source MLD) of the approved by was submitted directed to would be required project. HSIIDC for their review. expedite the to meet the water immediately. Also, As per the letter finalization of the demand \for CEO & MD, the project will be development of dated same. DMICDC visited implemented in a KBN IR. They 13.12.2013 of the site on 27th phased manner, also appraised Ministry of A review meeting April, 2018 along first phase being about their Railways, the was conducted on with the officials of from HUDA City findings on the proposal 3rd July, 2018 with the SPV and Centre Gurgaon to necessity of submitted by NHAI and SPV reviewed the Panchgaon sourcing water DMICDC was DICDL and progress of trunk junction. supply from examined by NHAI informed infrastructure Chambal river them and the that DPR will be activities at site. Accordingly, the (near Dholpur) suggestions of completed by State Government and the same was MoR are being August 2018 and Officials from has given approval endorsed by the incorporated in land acquisition DMICDC visited on the Detailed Committee. the Techno will start by the site to monitor Project Report Economic October, 2018. the progress of (DPR)vide its letter The Consultant Feasibility activities on site by dated 11TH has submitted Report for the Follow-up meeting the PMC and EPC February, 2016. Draft Integrated project. was held on 26th contractor on 27th Water resources October, 2018 May, 2017. It was DMICDC has Management In the meeting with AAI, SPV- observed that the requested DIPP for (IWRM) plan for held on 7th DIACL and the construction of taking up the KBNIR and the April, 2014 at consultants roads, utilities and matter of inclusion same has been North Central presented the the administrative of the project in shared with the Railways revised outcomes building is in JICA Rolling Plan State Government (NCR), of the DPR and progress. The for DMIC Project on 12th January, Allahabad, compliance of the physical progress with DEA, MoF 2015 for wherein the comments. reported by vide letter dated comments and project was th contractor was 24 February, 2016. suggestions. appraised and The AAI Board in 42%. various The DMIC Project its meeting held on State Government technical issues Implementation 30th October, 2018 CEO&MD, vide its letter related to the Trust Fund (DMIC th have approved the DMICDC vide his dated 5 February project were Trust) has DPR and proposal letter dated 24th 2015 has discussed. It approved the of equity July, 2017 has submitted the was further incorporation of participation in the requested the MD, comments on the discussed that project SPV in Project. VUL to expedite Draft detailed the possibility partnering with the the physical project report on to start early State Government The proposal for construction sustainable operations and of Haryana and extension of in- activities to meet integrated water provisions of a execution of Joint principle approval the deadline of the resource western link for Venture Agreement of MOCA for management plan centre and Dholera Airport project. for the project in its and preparation of south bound was presented 14th Trust Meeting detailed project trains to come during the Steering CEO & MD, held on 26th April, report for into the facility Committee DMICDC visited 2016. Alternative water needs to be meeting held on the site on 29th source for explored. 26th November, September, 2017 to A meeting was held Khushkhera – 2018. review the progress on 17th May, 2016 Bhiwadi – A project note of construction under the joint Neemrana containing yard Railway line activities on site chairmanship of Investment region plans and rail from Bhimnath along with the CEO & MD, (KBNIR), connections for to Dholra:. officials of the SPV DMICDC and Rajasthan IMTH Boraki / State MD, HSIIDC to (Deliverable – 7). was submitted The DMIC Trust Government. review the progress to Railways for fund accorded the of activities under The Consultant in-principle investment CEO&DMICDC the project and to has incorporated approval. The approval to the vide letter dated expedite the same. the comments and modified yard project as 14.11.2017 has The Joint Venture has submitted the plan and construction of requested Principle Agreement was compliance report. drawings new rail line from Secretary, Govt. of executed on 16th The same has prepared in Bhimnath to Madhya Pradesh June, 2016 and the been forwarded to concurrence Dholera Special for early resolution project SPV in the the State with DFCCIL Investment of the pending name of “DMIC Government for alongwith a Region in Gujarat issues w.r.t. water Haryana MRTS approval. project note on in the 4th meeting and Power for the Project Limited‟ has IMTH Borkai of the Board of project. been incorporated The consultant was shared to Trustees on 10th on 27th July, 2016. has submitted NCR for September, 2013. Site visit was Draft Integrated approval vide DMIC Trust conducted on A meeting was held Water resources DMICDC‟s approved the 27.12.2017 by on 8th July, 2016 Management letter dated 10th formation of SPV officials of with Principal (IWRM) plan for July, 2014. In for Railway line DMICDC and SPV Secretary KBNIR the meeting Project from to review the (Industries) on (Deliverable -8) held on 11th Bhimnath to progress of status of DMIC and the same has July, 2014 Dholera in construction projects in Haryana been shared with between partnership with activities. to review the the State DMICDC and State Government progress of various Government on Grater Noida Review meetings of Gujarat on 6th activities. 12th January, 2015 Industrial were conducted on December, 2013. for comments and Corridor 17th and 27th A meeting was held suggestions. The Authority, the August 2018 among DMICDC on 1st August, 2016 Consultant has consultant requested State officials of Vikram under the co- incorporated the highlighted that Government of Udyogpuri Limited chairmanship of comments has in order to Gujarat to (VUL), DMICDC, CEO&MD, submitted the maintain the expeditiously PMC and DMICDC and MD, compliance report. smooth flow of move ahead with Contractor at site to Haryana State The same has traffic for the the execution of review the status of Industrial & been forwarded to MMTH project Shareholders water and power Infrastructure the State a connection of agreement and connectivity and it Development Government for 60m ROW incorporation of was decided to Corporation Ltd. approval road, liking the SPV. State expedite the (HSIIDC) on status Multi-Modal Government/ process of of DMIC projects The consultant Transfer Hub Nodal agency appointment of in Haryana to has submitted the to 105m ROW sought approvals ICT Consultant and review the progress Dynamic Road through for the execution contractor for ETP. of various activities. Operating Model the Ansal Hi- of SHA and Framework tech township formation of SPV. RFQ cum RFP for A meeting was held (deliverable – 9) – is needed. Ministry of Selection of ICT on 16th August and Final GNIDA Railways (Railway consultant has been 2016 with Integrated water confirmed that Board) accorded issued on 6th Additional resource the issue will be „in principle‟ September, 2018. Secretary, DEA for management resolved after approval for inclusion of the discussing with undertaking the Expression of project in JICA (Deliverable – 10), the private project and asked Interest (EOI) Special Rolling the same has been developer. The DMICDC to document has been Plan.As a follow-up shared with the NCR was prepare and floated for inviting of that meeting, State Government shared their th submit the applications for Detailed Project on 6 February comments and detailed cost allotment of Report (DPR) has 2015 for observations on estimates and industrial land. been forwarded to comments and the above DPR for the MoUD vide suggestions. project note 01 plot has been above project. The DMICDC‟s letter and yard plan allotted to State Government RFP document dated 16th drawing, which Panchmahal vide its letter was reviewed by September, 2016. are being District Co- dated 30th April Advisor-Railways Further, a meeting addressed by operative Milk and 6th May, 2015 in the meeting was held under the the consultant. Producers Union have shared their with PMNC chairmanship of Ltd. (12 acres). comments for Dholera on 9th Additional A meeting was deliverable 9 and December, 2014 Secretary, DIPP on held on 8th Development of deliverable 10 and after minor 29th September, December, Industrial respectively. The corrections, the 2016,wherein it was 2014 at Township at Consultant has same has been agreed by all the Dedicated finalised. The Polaykala near stakeholders that as incorporated the freight Corridor RFP document Dewas MRTS and RRTS comments and has Corporation of shall be issued to will meet difference submitted the India Ltd. the empaneled During the Chief sets of passengers, compliance report. (DFCCIL) to consultants of Secretary‟s meeting there is no The same has discuss the Western Railways held on 15th June, duplication between been forwarded to issues related (WR). The list of 2016, it was decided MRTS and RRTS the State with Integrated empaneled that MPAKVN will projects rather Government for Transport Hub, consultants of prepare and submit these projects will approval. Boraki in Western Railways the proposal on complement each Greater Noida has been received. development of other through The Consultant vis-à-vis final industrial township different number of has submitted the alignment of The State on identified stoppages and Deliverable No.11 DFC passing Government has Government land catchment area etc. Draft Project through the been requested to of about 477 Ha at report and term area. The expedite the Polaykala near Subsequently, a sheets for Techno- execution of SHA Dewas. Further, review meeting was identified projects Economic for Bhimnath- DMICDC will take held on 18th under IWRM Plan Feasibility Dholera Rail line up the project for October, 2016 and the same has Report (TEFR) project and special approval under the been submitted to for MMTH formation of SPV from DMIC Trust, chairmanship of the State Boraki has been for the project. as the proposed CEO & MD, Government for submitted by node do not form DMICDC in comments and the consultant In the meeting part of the presence of JICA suggestion. and same has th held on 15 June, approved nodes of officials so as to been sent to 2015 with Ministry DMIC Phase –I. discuss the future State Government State of Railways, activities and vide its letter Government th DMICDC has Economic associated dated 14 May for their review requested Corridor: timelines. 2015 have shared and comments. Railways to take their comments GNIDA vide The strategy for up development With respect to the for deliverable 11. its letter dated development of the of Bhimnath- queries of Ministry The Consultant 30th January economic corridor Dholera rail of Urban has incorporated 2015 has shared taking into account connectivity Development on the comments and its comments various alongwith the the proposal of has submitted the and the same implementation Gauge Conversion inclusion of MRTS compliance report. has been models was work of Botad- project in the JICA The same has forwarded to discussed in the Ahmedabad. This Rolling plan, a reply been forwarded to the consultant Empowered will help has been received the State for Committee meeting DMICDC for in DIPP from Government for incorporation in early held on December DMICDC. approval. the reports. development of 7, 2011 at Bhopal. this much-needed 0.97sqkm was During 1st meeting In the meeting Inclusion of strategic identified for 75m of National held under the High Speed connectivity to ROW of the road Industrial corridors Chairmanship of Seamless take-off corridor, development Chief Secretary, Connectivity development of comprising &Improvement Rajasthan on 2nd between DSIR. Government land Trust (NICDIT), December, 2015 it Delhi-Greater of 0.1962 sqkm and held on 13th was decided that Noida and Secretary, DIPP Private land of January, 2017, it the comments / Faridabad: has requested 0.7803 sqkm. was decided to approval will be Chief Secretary, Administrative approve the provided by the In the meeting th Gujarat vide his approval of the inclusion of MRTS State Government held on 20 letter dated 2nd State Government Project from on the final March, 2013, July, 2015 to for land acquisition Gurgaon to Bawal deliverable before the consultant resolve issues with / transfer for the in JICA Special 31st December, made a detailed regards to 75 m ROW was Rolling Plan under 2015. presentation on execution of SHA accorded on 11th DMIC Project. the proposed and formation of January, 2012, Jodhpur Pali alignment project SPV for which was For MRTS- Marwar Industrial options. The Bhimnath Dholera forwarded to Gurgaon Bawal Area (JPMIA) consultant was Rail Connectivity Collector, Indore project, DIPP vide advised to th The State meeting Project for necessary letter dated 29 incorporate the Government in action. Regarding March, 2017 have comments of the State Steering Secretary, DIPP acquisition of 300m sent the duly filled GoUP and committee held on has requested width on either side “Proforma for carry out the 25th July, 2013 Chairman, Railway of the Corridor, a Preparation of detailed study approved the Board vide his decision is being Preliminary Project considering the st concentric radial letter dated 21 taken by the State Report for Bilateral suggestions. city design July, 2015 to to acquire land by Financial The report on concept for the expedite the gauge adopting the land Cooperation” to providing preparation of conversion work pooling model. In DEA. DEA to Seamless Concept Master of Ahmedabad – the meeting on 16th take further Connectivity Plan of Jodhpur Botad MG line July, 2014 held necessary action for was submitted Pali Marwar IA. and convey under the inclusion of the to State Based on the consent for chairmanship of project in JICA Government decision taken the execution of chief Secretary, Special Rolling for their consultant Bhimnath – DSIR M.P., AKVN Plan.DIPP vide its approval. th submitted the new rail link. In Indore was directed letter dated 26 Draft Concept The project was response to the to take up land April, 2017 has same, Ministry of acquisition for the forwarded the Plan. discussed in the Railways vide its project using land request from DEA Steering letter dated 23rd pooling model. The to get the Further, committee September, 2015 rules in this regard Proforma for DMICDC meeting held on has agreed to take are being framed by Preparation of received the 11.05.2013 up the Bhimnath the State Govt. of Preliminary Project comments on the between – DSIR new rail Madhya Pradesh. Report (PPR) for draft concept plan DMICDC and link with full Bilateral from the State Government of funding support Cooperation signed Govt. and the Uttar Pradesh from DMICDC. by the Project SPV same was shared wherein it was It has further been i.e. DMIC Haryana with the suggested to requested to MRTS Project Ltd. consultant. After integrate the deposit Rs.28 lakh instead of incorporating the project with for final location DMICDC Ltd. comments existing survey to Accordingly the received from planned/propo determine the DPR duly signed by DMICDC and sed Urban alignment. Shri Manoj Pal State Transport Singh, Director, Government, the systems. In this regard DMIC Haryana Consultants DMICDC had MRTS Project submitted the final A meeting was sought a Limited. has been concept plan held on confirmation from sent to DIPP. report. The 31.07.2013 the State DIPP submitted consultant under the Government for the same to DEA submitted the Chairmanship moving with the on 16th May, 2017 Draft of Secretary, above model. with the request to Development Plan Ministry of State Government take further of JPMIA, which Urban has confirmed the necessary action for was shared with Development same vide their inclusion of the the State to apprise them letter dated 28th project in JICA Government for about the October, 2015. Special Rolling their comments project Plan. and suggestion. Concept, the DMICDC has planning done deposited Rs.28 DEA vide its letter During the State so far, mode of lakh to Ministry of dated 29th May, Steering implementation Railways for Final 2017 had intimated Committee of the project Location Survey that the MRTS meeting held on etc. All the to determine the project has been 1st December, stakeholders alignment. included in the 2014, the namely MoUD, JICA Rolling plan Committee Ministry of A meeting was for DMIC Project. approved the final Railways, NCR held under the concept master Planning Board, Chairmanship of A meeting was held Plan of JPMIA. DMRC, State Secretary, DIPP on 21st June, 2017 Committee also Government of on 15th March, under the decided that Uttar Pradesh 2016 and it was chairmanship of necessary steps fully supported decided that the CEO&MD, should be taken to the project. It project will be DMICDC with notify the JPMIA was stated that implemented officials of DMRC urban areas and this project will under Non- and project directed the provide Government consultants to consultant to connectivity for Railway Model review the status of move ahead with the movement (NGR) with State the project and the preparation of of workers. Government deliberate on future Master taking forward the course of activities. Development Plan A meeting was process of land for the JPMIA. held on 22nd acquisition of DMRC vide letter October, 2013 th RoW once the dated 26 July, DMICDC got in- with DMRC Final Location 2017 have given principle clearance officials to align Survey (FLS) is their concurrence for ToR from the study with completed. FLS is on the DPR and Ministry of the ongoing under progress by recommended to Environment and DMRC projects Indian Railways move forward with Forest (MoEF) for in the influence (IR) and is the implement the Industrial area. A meeting expected to be ation of the project Area. The was held completed by related activities consultant has between the August 2016. under JICA moved ahead with CEO Greater assistance. the study and Noida DMICDC has DMICDC vide its Draft Industrial deposited Rs.28 letter dated 28th Environmental Development lakh to Ministry of July, 2017 has impact Authority and Railways for Final requested Assessment along CEO&MD, Location Survey Department of with the baseline DMICDC to to determine the Economic Affairs report for the discuss the alignment. The to request JICA to project has been options FLS is completed. reinitiate their submitted to State suggested by Land acquisition activities related to for their DMRC for the plans and yard preparatory surveys comments and alignment. The plans have been for the project. suggestion. joint survey of prepared and Further the the Technical submitted for Discussions have consultant has consultant with approval by been initiated with also submitted the Greater Noida Western Railways. JICA for re- Environmental Industrial Detailed estimates initiating the baseline report for Development are prepared and Preparatory Survey the Pali-Sojat Authority submitted for work. Support of Bypass, Mass (GNIDA) approval of Government of Rapid Transit representatives, Railway Board by Haryana / HSIIDC System and Multi for the the Western is being sought. Modal Logistic suggested Railways. Hub. alignment A meeting was option was DMICDC vide its held on 15th June, The State conducted on letter dated 22nd 2018 under the Government has 11th Nov 2013. December, 2016 chairmanship of identified the The alignment have requested the Hon‟ble Chief following Early of the surveyed Dholera Special Minister of Haryana Bird Projects for route was Investment to review the status carrying out submitted to Region of the project. Techno Economic GNIDA for Development Feasibility Study: approval. The Authority Site visit was project was th (DSIRDA) conducted on 19 - Development of placed before June, 2018 by Airport near the Board of To expedite the Hon‟ble Industries Jodhpur Trustees in the land acquisition and Commerce meeting held of -Development of process for the Minister, 17th January, Sojat – Pali By - Right of Way Government of 2014 for Pass road (RoW). It has Haryana. considering further requested inclusion in A meeting ws held -Development of Western Railways JICA rolling under the Multi Modal to expedite the plan for DMIC chairmanship of Logistic Hub approval process Project. It was CEO&MD, of the Final decided in the DMICDC along - Water supply Location Survey meeting that with State officials and Waste Water (FLS) vide letter the project th on 29th August, Management in dated 26 should again be 2018 to review the Jodhpur - Pali – December, 2016. brought before status of the project Marwar Industrial the DMIC A joint meeting and way forward. Area Trust once the was held on 16th - Mass Rapid alignment and March, 2017 Pre-Feasibility broad financials between DICDL Study for Water Transit System are completed. and Western Supply (from In the review Railways to Tajewala): According to the meeting held on discuss the rail line minutes of the 25th March, alignment at State has advised review meeting by 2014, the Gandhinagar. that the DPR State nodal agency consultant was should be prepared held on 11th June asked to DMICDC vide before they 2014, the State coordinate with letter dated 28th approve the Government had various March, 2017 have project, but requested the stakeholders requested the DMICDC‟s view is consultant to like DMIC, Western Railways that State should at move ahead with DMRC, (Mumbai least approve the the studies and GNIDA etc. Division) to „concept‟ before seek environment for concurrence convey the final further studies are clearance. State on the final approval of the undertaken. Government vide alignment and FLS survey and its letter dated 18th other issues like share the copy so In the meeting of May 2015 has institutional th as to enable to 18 March 2013, requested integration etc. take forward the DMICDC Legal DMICDC to project consultants made a provide the copy A meeting was development detailed of the village map held on 9th activities. presentation along with all May, 2014, physical features between DMICDC vide on the queries such as water Advisor- letter dated 28th raised by State bodies, Railway Railways March, 2017 have Haryana are line etc. under DMICDC and requested the Government. The JPMIA node of MD, DMRC to Western Railways comments/ Rajasthan. discuss the (Ahmedabad suggestions DMICDC has High Speed Division) to furnished by State submitted the Connectivity convey the current Government of desired documents Project in UP status of the being reviewed by to the State and its possible Botad – Bhimnath DMICDC. Pre bid Government vide integration with Gauge Conversion meetings were held its letter dated proposed nd project and on 22 March and 22nd May, 2015. DMRC rd expedite the 23 April, 2013. network. implementation Clarifications were CEO&MD, related works. issued to the DMICDC has In the review prospective bidders requested meeting by the Further, during and the last date for Additional Chief Special Advisor the follow-up submission of Secretary project Panel of meeting held on proposals was (DMIC) vide its DMICDC held 12th April, 2017 extended upto 25th letter dated 4th on 16th May, between Western May, 2013. June, 2015 to 2014 at Railways, intervene and DMICDC, it Ahmedabad Global City at resolve all the was decided Division and Gurgaon: pending issues to that another DICDL, the enable the meeting with alternative Proposal for implementation of Delhi Metro alignment of the undertaking project the project and Rail rail link inside development contract in a time Corporation DSIR was activities for Global bound manner. (DMRC) would discussed and City Project was be scheduled to agreed to suit the placed before the The comments of discuss the development of DMIC Trust in its the State possibilities of th DSIR. Western meeting held on 6 Government on integration Railways has December, 2013 & the Draft between the submitted the which was Development Plan projects of DPR and approved by the have been DMRC, NMRC estimates for trust. received vide letter and DMICDC. sanction to the dated 1st October In this regard a The Consultant Railway Board on and the meeting was submitted the Draft 26th May, 2017. Consultant has held on 30th Pre-Feasibility been directed to May, 2014 Reports for A meeting was incorporate the between MD, Education and held on 3rd same. DMRC, CEO Medical Hub, Low August, 2017 &MD, Cost Housing and between Western CEO & MD, DMICDC and Integrated Railways and DMICDC vide his Advisor- Multimodal DMICDC letter dated 14th Railways Passenger Hub at (represented by October, 2015 has DMICCDC to Panchgaon Chowk. Project Managers requested the discuss the The comments – M/s AECOM) State Government integration of received from the and Government for expeditious this project State Government of Gujarat approvals once with the DMRC through its letter (represented by the revised network. st the SPV), wherein dated 21 July development plan it was discussed 2012 were is admitted to the DMICDC that project will be incorporated in State requested implemented by order to finalise the Government. DMRC to the SPV to be reports. prepare a created as Joint MoEFCC has supplementary Venture between The State been requested to DPR for DMICDC and Government had consider the integrated Government of requested for 50% proposal for connectivity Gujarat. contribution from extension of between Boraki The Board of SPV DMIC Trust for validity of ToR for to Indira has approved the acquisition of land Environment Gandhi estimated cost of in the project Clearance of International the project as specific SPV to JPMIA. Airport, which finalized by fund the cost of will include the Western Railways land (approx. In the meeting MRTS during the Rs.1500 crore) for held under the connectivity meeting held on this project. In the Chairmanship of proposed by 6th September, meetings held on Chief Secretary, DMICDC. The 2017. The project 25th June, 2014, 30th Rajasthan on 2nd traffic demand will be June, 2014 and 4th December, 2015, and route implemented the July, 2014 and it was decided that alignment study SPV created as a keeping in view that the approval on report has been joint venture there was lack of final feasibility and finalized and between NICDIT clarity as to whether various pre- submitted by and Government the proposed feasibility studies the consultant. of Gujarat and Global City Project will be provided The same was project cost will was to be treated as by the State sent to DMRC be funded by an „Early Bird Government by for reference 100% equity. The Project‟ or a „City 31st December, and assistance RFP document level project‟ and 2015. in preparation for preparation of also that the DPR of The proposal for DPR for detailed for the Global City supplementary extension of the design for the rail Project was yet to DPR. validity of the link project was be ToR for the issued on April 10, prepared/finalized, A meeting was Jodhpur Pali-Pali- 2018 and the pre- it was decided that held at DMRC Marwar Industrial bid meeting was this proposal would office on 17th Area (JPMIA) was held on April 20, be taken up September, approved in the 2018. Two bids separately. 2014 to discuss 162nd Meeting of were received by the way forward the Expert the bid due date The consultant was on the project. Appraisal on May 10, 2018. appointed for The aspects The bid process undertaking Committee (EAC) related to was annulled and Feasibility Report held on 30th speed, further the tender has and master August, 2016. connectivity to been re-issued on planning the Global The Ministry has GT Road May 31, 2018 and City Project. approved the beyond Boraki, the last date for extension of the train capacity submission of bids The consultant has current ToR till etc. were was July 13, 2018. submitted the 11th November, discussed. The Three bids have Inception Report, 2017. consultant was been received. which was sent to asked by State Govt. for The Final DMRC to Letter of Award their comments. Development Plan update the was issued on 21st The kick-off for JPMIA has ridership August 2018 to meeting for this been notified by forecast and Aarvee project was held on the Government broad costing consultants for 26th September, of Rajasthan on of the line. preparation of 2014 under the 2nd November, DMICDC was DPR for detailed chairmanship of 2016. also shared design for the rail MD, HSIIDC. technical details link project. The The revised EIA required by consultant has Various issues report after DMRC in this submitted the related to the incorporating the regard. Inception Report Global City project changes as per the and Base line were discussed in Notified Review schedule and site the meeting held Development Plan meetings were surveys have been under the has been sent to held with the initiated. chairmanship of the State officials of Principal Secretary, Polllution Control DMRC on 10th Multi-modal Industries & Board, Rajasthan October, 2014, Logistics Park Commerce, vide letter dated 30th Cctober, (MMLP) and its Government of 19th December, 2014 and 25th connectivity at Haryana on 15th 2016 for seeking November, Sanand:- November, 2014 an early date for 2014 to discuss conducting Public the issues DMIC Trust in The project was hearing. relating to its meeting held discussed in detail traffic demand th on 10 March, in the meeting held The public hearing forecasting and 2014, accorded its under the was held on 15th alignment of approval for the chairmanship of March, 2017 at the MRTS and way substitution of Minister, Industries SDM office, Multi Modal & Commerce, Rohat in Pali forward. Logistics Park at Government of District. Ahmedabad- Haryana on 11th The Techno- Dholera, Gujarat December 2014. The proposal for Economic at Sanand it the grant of Feasibility district of Repeated reminders Environment Report (TEFR) Ahmedabad in have been sent by Clearance for the for MMTH Gujarat and CEO & MD, Jodhpur Pali Boraki has been approved DMICDC and also Marwar Industrial submitted by appointment of by SIPP for Area (JPMIA) the consultant consultant for expediting approval project in and same has carrying out on the inception Rajasthan was been sent to project report of the approved in the State development Global City Project 171st meeting of Government activities. finalization of site the Expert for their review boundary and Appraisal and comments. The bid nomination of a Committee (EAC) documents for dedicated officer as held on 12th May, DMRC vide its selection of the nodal point of 2017. The EAC letter dated 23rd consultant to contact Response has recommended December, prepare Techno- from the state the Environment 2014 has Economic Government of Clearance for the submitted the Feasibility Study Haryana is still project as per the report on the (TEPS) for Multi awaited. Minutes of the DMICDC‟s – Modal Logistics meeting issued. request of Park at Sanand During the meeting running high was prepared. The held on 2nd June, The Environment speed trains bid document for 2015 under the Clearance for the between selection of Chairmanship of JPMIA project has Greater Noida consultant for Secretary, DIPP, been granted by and IGI Airport preparation of the Chief Secretary, the MoEF&CC sharing the Techno – Government of vide their letter same tracks Economic Haryana had dated 14th July, with DMRC Feasibility Study assured that State 2017. normal metro (TEFS) for Multi Government will trains – Modal Logistics get the issues with Development of Park at Sanad, regard to Natural Sojat – Pali By - A meeting was th after incorporating Conservation Zone Pass road: held on 5 comments and (NCZ) sorted out January, 2015 at The consultant observations from with NCR Planning DMRC Office State Govt. was Board in next 15 submitted the site to discuss the issued and a pre- days. HSIIDC will delineation report two options bid meeting with also send the and in the State proposed by prospective comments on the Steering DMRC in their bidders was held inception report committee report with on 24th along with the meeting held on regard to the September, 2014. details relating to 25th July, 2013, the MRTS The last date of the final site State Government alignment and submission of bid boundary. approved the its integration proposal was 27th alignment already with existing October, 2014. A meeting was held proposed by the and proposed Four (4) bid under the Public Works line of DMRC. proposals had Chairmanship of Department, It was discussed been received. Principal Secretary Government of that proposal of Letter of Award to Chief Minister of Rajasthan. extension of has been issued to Haryana on 28th Airport Express the selected September, 2015 During the State line from New consultant for wherein it was Steering Delhi to Mayur preparation of informed that land Committee Vihar Phase – I Techno – parcel identified for meeting held on till DNGIR Economic Global City project 1st December, may be taken Feasibility Study does not fall under 2014, the up as part of (TEFS) for Multi the NCZ or under Committee has DMIC project – Model Logistics eco sensitive zone approved the subject to the Park at Sanand. and the matter has Market Analysis, approval of been resolved. gap assessment Ministry of The consultant Further, a Chief and concept plan. Urban has submitted the Town Planner DMICDC has Development. inception report (CTP) has been received the Subsequently, and the same is appointed as the comments on another being shared with nodal officer for draft feasibility meeting was the State the project. The report from the held on 8th Government for State Government state Government January, 2015 their comments/ has given their and the same has under the approval. comments on the been incorporated Chairmanship Inception Report by the Consultant. of Secretary, A review meeting and the consultant Final Feasibility Ministry of th was held on 18 has been directed to report has been Urban April 2016 under incorporate the sent to state Development the Chairmanship same and take the Government for regarding of CEO & MD, project forward. comments and approval on DMICDC to suggestion. extension of discuss the A review meeting The consultants existing progress of the was held on 23rd have submitted MMLP Sanand November, 2015 final Environment Airport Express Project with the with Principal Impact link from New representatives of Secretary, Assessment report Delhi to Mayur the Project Industries, for the project. Vihar Phase –I Consultants and Government of Further, Final and then State Haryana to discuss Feasibility report further to Government. the way forward for has been sent to DNGIR to the project and it State Government provide faster The preparation was decided that and the same has connectivity to of techno – the same shall be been approved. the region with economic taken in the an additional feasibility study is meeting of the Development of option of under progress by Hon‟ble Chief Airport near system the Consultants. Minister of Jodhpur: integration with Haryana. Airport metro During the review Accordingly, a State Government line. meeting held on review meeting was has proposed 19th September, held on 15th expansion of GNIDA vide 2016 under the January, 2016 under existing Jodhpur its letter dated th chairmanship of the Chairmanship airport and 30 January ACS, Department of Chief Minister of develop it as an 2015 has shared of Industries, Haryana to discuss Early Bird Project. its comments Government of the way forward for In the State on the Gujarat, it was the project. Steering Alignment and also discussed that Committee traffic demand the State The way forward meeting held on study and the Government may for the project was 1st December, same has been expedite the discussed during 2014, the send to the process of land the meeting held on Committee Consultants for th acquisition for the 11 February, 2016 approved the site its project. assessment report incorporation. The DMIC Project submitted by the A follow-up Implementation DMICDC vide consultants. review meeting Trust Fund (DMIC letter dated 13th was held on 27th Trust) has April, 2015 has Additional land September, 2016 approved the requested State parcels have been under the incorporation of identified near the Government of chairmanship of project SPV in existing airport, Uttar Pradesh CEO & Managing partnering with the which are to provide Director, Government of currently under confirmation DMICDC to Haryana and the possession of for 50% cost discuss the execution of Joint Indian Air Force. sharing towards progress of the Venture Agreement For obtaining the preparation of MMLP Sanand for the project in its NOC, UDH DPR proposed Project with the 14th Trust Meeting Department, GoR to be prepared representatives of held on 26th April, had referred this by DMICDC. the Project 2016. matter to Ministry Consultants and of Defence, GoI. CEO & MD, State A meeting was held In the meeting DMICDC vide Government. The on 17th May, 2016 held on 22nd July, his letter dated preparation of under the joint 2014 under the 11th May, 2015 techno-economic chairmanship of Chairmanship of has requested feasibility study is CEO & MD, Additional Chief Secretary, under progress by DMICDC and MD, Secretary MoUD to the Consultants. HSIIDC to review (Infrastructure), convene a the progress of Govt. of meeting under On 24th October activities under the Rajasthan, it was his 2016, the project and to appraised that chairmanship to consultant M/s expedite the same. Govt. of discuss and PwC conducted Rajasthan is finalise various meetings with the A meeting was held required to project officials of GIDB on 8th July, 2016 transfer land to development and CICC at with Principal Airport Authority activities Ahmedabad to Secretary of India (AAI) and including discuss the (Industries) on the Ministry of preparation of findings on the status of DMIC Defence (MoD). DPR. land area projects in Haryana During the assessment for the and to review the Review meeting Secretary, DIPP proposed facility. progress of various held on 15th July, vide letter dated th CEO & MD, activities. Various 2016, it was 8 June, 2015 DMICDC vide rounds of meetings informed that a has requested letter dated 7th have been held „No Objection‟ Secretary, December, 2016 between the project has been received MoUD to have requested for consultants and the from the Ministry convene a a meeting to be Chief Town of Defence on the meeting under convened at the Planning officers of proposal of his chairman level of Chief Government of extension of ship with Secretary, Haryana for existing Jodhpur officials from Government of discussing various Airport. The State DMRC, Gujarat wherein development Government GNIDA and the consultant will options. officials will share NCT OF Delhi present models on a copy of NOC to discuss the land acquisition, The Joint Venture with DMICDC way forward equity models etc. Agreement was and also indicate relating to the for taking forward executed on 16th further steps that DPR the project. June, 2016 and the may be taken in preparation of project SPV in the order to take the MRTS CEO&MD, name of “DMIC project forward. connectivity DMICDC vide Haryana Global city DMICDC has between Delhi letter dated 30th project Limited” requested the and DNGIR. January, 2017 have has been State Government requested Chief incorporated on to provide the The final TEFR Secretary, 22nd July, 2016. copy of the „No for high speed Government of Objection‟ seamless Gujarat to A meeting was held received from the connectivity expedite the under the Ministry of between Delhi matter of land chairmanship of Defence vide to Greater acquisition for the Hon‟ble Minister, letter dated 18th Noida has been project. Industries, October, 2016 and submitted by Government of indicate the the consultant A review meeting Haryana on 10th further course of on 16th June, rd was held on 23 September, 2016 to action to be 2015 and same January, 2017 review the progress undertaken for the has been under the of the project. The project. forwarded to chairmanship of consultants State CEO&MD, presented the three Development of Government of DMICDC options for Master Multi Modal UP for their wherein the Plan of Global City. Logistic Hub comments and project The first option for approval. consultants Master Plan was The consultant presented the preferred to be the submitted the In-principle current project most appropriate revised site approval has activities and for Global City. delineation report been obtained deliverables under and in the State for the project the project. Another review Steering by the meeting was held committee held on CEO&MD, on 14th October, 25th July, 2013, the Authority DMICDC vide 2016 under the State Government letter dated 22nd chairmanship of approved the A meeting swas March, 2017 have Hon‟ble Industries development of held under the requested PS to Minister, Multi Modal Chairmanship Chief Minister, Government of logistic hub near of Shri Mukund Government of Haryana to review Rohat. Kumar Sinha, Gujarat to the project OSD (UT), expedite the progress. Other During the State Ministry of matter of land stakeholders were Steering Urban acquisition for the also present from Committee development project. HUDA, Delhi meeting held on (MoUD) Transco, NHAI 1st December, regarding A meeting was and BBMB. 2014 the MRTS held under the Committee has connectivity chairmanship of The Government approved the between IGI MD, GIDC on of Haryana has Market Analysis, Airport in Delhi 13th April, 2017 approved the gap assessment and Dadri regarding the land Financial Model of and concept plan. Noida acquisition models the project on 21st Further, Final Ghaziabad of the project and December, 2016 Feasibility report Investment and the Master Plan has been sent to Region in way forward for is being finalized. State Government Greater Noida the same. and the same has under Delhi CEO&MD, The RfQ cum RfP been approved. Mumbai DMICDC for selection of Industrial reviewed the Consultant for Water supply Corridor progress of Preparation of and Waste Water Project on 5th project activities Preliminary Design Management in April, 2016. with the Report for Roads & Jodhpur - Pali – consultant on 8th Services / Utilities Marwar A meeting was May, 2017. for Global City Industrial Area held on 23rd CEO&MD, Project at Haryana June, 2016 DMICDC vide under DMIC The consultant under the letter dated 30th Project was issued submitted the chairmanship of May, 2017 have on 17th February revised report and Secretary cum requested the 2017.Four bids had recommended Commissioner Principal Secretary have been received Rajiv Gandhi lift (Transport) (Industries & by the submission canal as a source Government of Mines), date on 11th April, for potable water NCT, Delhi in Government of 2017 and the demand for which the Gujarat to evaluation is under Jodhpur – Pali – Government of expedite the land progress. Marwar Industrial NCT, Delhi acquisition for the area. was requested project. A meeting was held to provide „in- on 23rd February, The State principle CEO&MD, 2017 under the Government in ‟approval for DMICDC vide his chairmanship of the State Steering preparation of letter dated 11th Hon‟ble Minister of committee DPR. July, 2017 has Industries, meeting held on Government of again requested PS Government of 25th July, 2013 NCT, Delhi (industries & Haryana to review approved for Rajiv was also Mines) the project master Gandhi lift Canal requested to Government to plan. as a source for make initiate the land potable water in provisions of acquisition for the The Government JPMIA. The RoW through project. of Haryana have consultant was the accorded „in- advised Government MD, GIDC vide principle‟ approval accordingly. owned land TH letter dated 6 on the Master P lan DMICDC has parcels so as to September, 2017 of the project vide received the minimize the th has requested letter dated 7 comments on land acquisition DMICDC to March, 2017. draft feasibility of private land. provide last mile report from the connectivity to the A review meeting State Government Other th identified site at was held on 19 and the same has projects: Sanand – III April,. 2017 under been incorporated (Khoraj) estate for the chairmanship of by the Consultant. Greater Noida development of Hon‟ble Industries Hi Tech the Multi-modal Minister, Further, Final Township Logistics park. In Government of Feasibility report (changed to response to the Haryana to review has been sent to Integrated letter, CEO & the project State Government Industrial MD, DMICDC progress. Other and the same has Township vide letter dated stakeholders were been approved. (earlier Hi- 22nd September, also present from Tech City) 2017 have HUDA, Delhi Mass Rapid Project, requested for the Transco, NHAI Transit System Greater Noida. State Government and BBMB. to commit on the The consultant Secretary, DIPP availability of land A review meeting carried out the site has requested and participate in was held on 12th delineation study Chief Secretary, the equity May, 2017 under for the Government of structure of the chairmanship of Development of Uttar Pradesh DMIC project as Hon‟ble Industries MRTS. Based on vide his letter approved by the Minister, their analysis, Bus dated 21stJuly Cabinet. Government of Rapid Transit 2015 to provide Haryana to review System along NH- support for MD, GIDC vide the project 65 between ensuring the letter dated progress. Other Jodhpur and Pali Environment 22.11.2017 has stakeholders were was suggested as a Clearance for committed to also present from short term the IIT, Greater provide support in HUDA, Delhi measure and a Noida project terms of land for Transco, NHAI Commuter Trains in a time the project at the and BBMB. System between bound manner. identified site at Jodhpur – Pali IA Further, Khoraj (Sanand). The earlier bidding as a long term DMICDC has The Techno- process for solution. In the also requested economic selection of State Steering CEO, GNIDA feasibility report is consultant for committee to expedite the under preparation Preparation of meeting held on same vide their by the project Preliminary Design 25th July, 2013, letter dated 29th consultants. Report for Roads & State Government July, 2015. Services/ Utilities approved the CEO&MD, for Global city above suggestions. CEO, GNIDA DMICDC and Project was vide his letter MD, GIDC annulled due to During the State dated 23rd July, conducted a joint insufficient Steering 2015 has site visit to the response and Committee requested Chief identified project revised tender meeting held on Secretary, Uttar site at Khoraj document was 1st December, Pradesh for the (Sanand) on issued on 8th June, 2014 the recommendatio 22.12.2017. 2017. Committee had n on the approved the modified CEO&MD, Four bid proposals Market Analysis, Greater Noida DMICDC vide his have been received gap assessment Master Plan – letter dated till the last date of and concept plan. 2021. 26.12.2017 has submission i.e. 21st requested GIDC July, 2017. DMICDC has Site delineation to initiate the received the for the steps of formation M/s Egis India comments on proposed Hi of Project SPV as Consulting Draft Feasibility Tech Township per the approved Engineers Private Report from the at Greater institutional Limited has been State Government Noida area structure for selected for the and the same has proposed to be industrial corridor Preparation of been incorporated developed as projects. The Preliminary Design by the Consultant. Township was Techno-economic Report for Roads identified by feasibility report is and Services/ Further, Final DMICDC. The under preparation Utilities for Global Feasibility report land details by the project City, Haryana. has been sent to along with the consultants. State Government Khasra CEO&MD, and the same has numbers were The draft DMICDC vide his been approved. sent to the State SHA/SSA for the letter dated 4th for approval. project has been August, 2017 have Pre-Feasibility The Concept prepared and requested Study: Report was shared with the Government of submitted to During the 10th nodal agency Haryana to expedite GoUP for State Steering GIDC vide letter the pending matters comments. dated 21st May, with regard to Committee 2018 for review. implementation of Meeting, the The RfQ cum DMIC Project in consultants were RfP for A meeting was the State of asked to prepare undertaking the held on 31st July, Haryana. the Pre-feasibility preliminary 2018 with the report on the design of the consultants State Government following: Integrated wherein Rail vide its letter dated Industrial City Connectivity 5th September, 2017  Skill was issued. options were has informed that Development presented before „in principle‟ center. DMIC Trust the officials from approval has been  ROB on approved the DMICDC and accorded for re- Railway line formation of State Government designation of near Rohat SPV for this GIDC, the nodal Global City Site as Railway project in agency, is „Special Zone‟ in Station. partnership examining the the published Final  Dedicated with State connectivity Development Plan, Freight Road Government of options and the Gurgaon Manesar from JPMIA Uttar Pradesh Urban Complex to NH-12 on 6th report. (GMUC) 2031 AD parallel to December, with a provision of railway Line. 2013. The DMICDC vide FAR of 3.00. The  Conservation Shareholders letter dated 16th master plan will be and Agreement for August, 2018 has finalized after promotion of incorporation provided the inviting comments/ traditional of the SPV proposed rail suggestions from water between DMIC connectivity the public and management Trust and the options for the publication of system State MMLP project to revised Final including Government of Ministry of Development Plan attenuation Uttar Pradesh Railways and for GMUC – 2031. ponds was executed. Dedicated Freight  Waste water Corridor Meetings were held recycling The Cabinet Corporation of under the plant for Committee for India Limited chairmanship of industrial Economic (DFCCIL) for Additional Chief effluent as Affairs review and further Secretary, Power, common accorded their necessary action. Govt. of Haryana facility. investment and Principal The above approval for the DMICDC vide Secretary, mentioned reports project in its letter dated 31st Industries, Govt. of have been meeting held on October, 2018 th Haryana on submitted by the 20 January, have submitted 28.11.2017 and consultant and the 2014. the details of the 03.01.2018 to same have been proposed rail The appointed review the status of shared with the connectivity consultant the project and to State Government option for the submitted the discuss the pending for their MMLP project to inception report matter related to comments/ DFCCIL for and conducted shifting of HT/LT suggestions. review and further required data lines. Comments of the necessary action. collection State Government A meeting was held /surveys. In have been Marketing: on 9th February, accordance with received on Skill 2018 at DMICDC the approval, a Development M/s Target office to finalize the SPV with the Centre and the Exhibitions Ltd. Layout Plan & name of same are being has been Final Urban Design “Integrated incorporated by appointed as guidelines for the Industrial the Consultant. Exhibition Agency Township for Vibrant project. Pre-feasibility Greater Noida Gujarat Summit reports on the Limited” was 2016-17 scheduled A review meeting other four projects incorporated on 10-13th was held under the have been with equal January, 2017. chairmanship of approved by the equity The agency is CEO&MD, State participation of responsible for DMICDC and Government. DMIC Trust pavilion and Principal Secretary, and GNIDA. preparing standees Industries, Govt. of GNIDA further , hoardings, Haryana on 2nd vide its letter kitbags, radio February, 2018 to dated 25th jingles and review the status of March, 2014 designing Dholera the DMIC projects requested to booth for Vibrant in Haryana. undertake to transfer the Gujarat exhibition. The application for land to the SPV grant of Terms of at the earliest RfQ cum RfP has Reference (ToR) and in this been issued for for the project has regard moved a Creative and been submitted to proposal to the Branding agency MoEF&CC. State Govt. of th on 15 December, UP for A meeting was held 2016. Three (3) exemption of on 2nd August, 2018 bids have been stamp duty. under the received by the DMICDC was chairmanship of bid due date , i.e. informed that th Additional Chief 6 February 2017. the exemption Secretary (Power), from the Letter of Award Government of payment of has been issued to Haryana to review stamp duty was M/s. Vyas the status of the accorded by the Giannotti Creative project and tyo State Pvt. Ltd. in JV deliberate the issues Government. with Integrated related to shifting Design of HT/ LT power Lease deed for Consultancy on lines. the transfer of th 14 March, 2017 land to the A meeting was as Creative and Project SPV held on 14th Branding Agency was executed December, 2018 on 9th for DICDL. under the September, chairmanship of 2014. RfP for Additional Empanelment of Secretary, DIPP Secretary, DIPP Consultants as to review the had sent a letter Transaction status of the to Chief Managers and project and to Secretary, Advisors for Land deliberate on the Government of Allotment of pending issues. Uttar Pradesh Dholera Industrial on 21st May City Development Integrated Water 2014 regarding Limited (DICDL) Resources the completion has been issued on Management of land transfer 26th December, Plan: to the project 2016 and three SPV. bids have been On the directions received by the of the State An amount of bid due date on Government of Rs.617.20 crore 17th January, 2017. Haryana, the was released as Evaluation is equity in the under progress. representative of SPV as DMIC Singapore Water Trust‟s share on Social media Co. gave a 20th June, 2014. marketing is in presentation on the progress to GNIDA has promote Dholera scope of work for provided its on Twitter, undertaking comments on Facebook, You Techno Economic bid documents Tube and other feasibility study and the same such platforms. have been regarding The first edition incorporated. augmentation of of monthly e- water supply in the newsletter named The consultant “Dholera Smart has sub mitted MBIR. Wire” is circulated the revised final Accordingly, the in December 2016 pre-feasibility draft RFP for to all the report for IIT preparation Government Greater Noida and the same departments and of Integrated Water has been shared potential Resource investors. Management Plan with the State for MBIR was Government prepared in for their consultation with comments & the State suggestions. Government. A meeting was Consultant was held on 1st appointed for the August, 2014 project and have between mobilized the team. GNIDA, The appointed DMICDC and consultant has the consultants submitted the regarding inception report as project per milestone and progress. The required data progress was collection/ also reviewed in surveys/ the third stakeholder meeting of consultations are in Special progress. The Advisory Panel reports including held on 19th the Inception August, 2014. Report, Situation Analysis, Field The progress of Investigation Plan the project was and Decision further Support Model reviewed by have been reviewed CEO&MD, by DMICDC and DMICDC in State Irrigation the meeting Department. held on 15th Consultant October 2014 submitted the between compliance report DMICDC and to the observations the consultants of Irrigation followed by Departments. The another review State Irrigation meeting on 31st Department October, 2014 accepted these with TCE. reports vide their letter dated 14th The project was August, 2014. discussed in detail in the An integrated meeting held stakeholder‟s under the workshop for chairmanship of sustainable Chief Secretary, integrated water Government of resource Uttar Pradesh management plan on 7th for Manesar Bawal November Investment Region 2014 at was also held on Secretariat, 12th June, 2014 at Lucknow. Panchkula to discuss and The progress of disseminate the the project was initial findings further related with reviewed by availability and CEO & MD, reliability of existing DMICDC in water resources for the meeting MBIR. held on 8th December, The consultant 2014 between submitted DMICDC and deliverable No.6 consultants i.e., IWRM Plan for followed by MBIR and the same another review was forwarded to meeting on 11th the State Govt. for December, their comments on 2014. the same. The meeting of The work of the State Expert drilling of Appraisal exploratory bore Committee wells for studying (SEAC) was water availability held on 13th was completed by December, the consultant. 2014, wherein proposal for Interim Integrated issuance of Water Resources Terms Management Plan of Reference (deliverable No.6) (TOR) for and Draft Detailed carrying out Project Reports EIA studies for (deliverable No.7) IIT Greater of various Noida was alternatives for discussed. MBIR was submitted by the Minutes of the consultant and is meeting have being reviewed by been issued and DMICDC and the the Committee State Government. has desired for an approval The Situation layout plan for Analysis Report for ToR clearance. Surface Water, Ground Water and CEO & MD, Reclaimed Water, DMCIDC vide Interim Integrated letters dated Water Resource 15th January, Management Plan, 2015 and dated 22nd January, Draft detailed 2015 requested Project Reports of CEO, GNIDA various alternatives regarding for MBIR, Draft expediting of Integrated Water the approval Resource process for site Management Plan, master plan / Dynamic Operating layout plan. Model Framework, Further, CEO Final Integrated &MD Water Resources DMICDC vide Management Plan its letter dated and Detailed 23rd January, Project Report and 2015 to Chief Term Sheet for the Secretary, Identified projects Government of under IWRM Plan Uttar Pradesh has been submitted has requested to the State to expedite the Government for same. their observations/ approvals. A meeting was held at GNIDA .The State on 17th Government vide December, its letter dated 6th 2014 followed February 2015 has by another provided its meeting on 30th observation on the December, deliverables No.5 2014 to discuss ie. Situation the Floor Space Analysis Report for Index (FSI) Potential Ground issue for the Water, Surface project. Water and Recycled Water and Based on the deliverable 6 ie. discussions, Integrated Water compliance Resource report on the Management Plan comments of the project. shared by DMICDC and The project was GNIDA has discussed in detail been submitted in the meeting held by the under the Consultant and Chairmanship of the same has Minister, Industries been shared & Commerce, with the State Government Government for approval of the reports. of Haryana on 11th Further, on 30th December, 2014. January, 2015 GNIDA shared The progress of the its comments project was on Final reviewed by CEO Detailed Site & MD, DMICDC Master Plan, th on 17 January, Urban design 2015. Framework report and The consultant has Business Plan. submitted The comments deliverable No.9, have been i.e. Dynamic shared with the Operating Model Consultant for Framework and its deliverable No.10 incorporation i.e. Final Integrated and the same Water Resources has been Management Plan. submitted by The same has been the consultant. forwarded to the State Govt. for A meeting was their comments held on 18th vide letter dated February under th 12 January, the co- 2015.The chairmanship of consultant has also Chairman& submitted CEO, Greater deliverable No.11 Noida i.e. Detailed Project Industrial Report and Team development Sheet for the Authority identified projects (GNIDA) and under IWRM Plan. CEO & MD, The same has been DMICDC to forwarded to the discuss the state Government progress of the for their comments Integrated vide letter dated 5th Industrial February, 2015. Township (IIT) project and Draft detailed other issues Project Reports of related to various alternatives DNGIR of MBIR investment (Deliverable -7), region. Draft Integrated Further, to water Resource resolve all the Management Plan pending issues (Deliverable -8), of DNGIR, Dynamic Operating SPV Board Model Framework meetings were (Deliverable –(9), held on 3rd Final Integrated February, 2015, Water Resources 26th February, Management Plan 2015 and 19th (deliverable -10) March, 2015. and Detailed Project Report and The master plan term Sheet for the for IIT Greater identified projects Noida has been under IWRM Plan approved by (Deliverable – 11) the Board of have been GNIDA. submitted to the State Government The consultant for their has submitted observations / the draft approvals. Preliminary Government of design report. Haryana has Tender provided their documents and observations / Technical comments on schedules for deliverables 6 to 10 the project. on 6th April, 2015. The progress of The consultant has the project was submitted the reviewed by compliance to the CEO & MD, observations on 8th DMICDC in May, 2015, which the meeting have been held on 3rd forwarded to state March, 2015 Government for between approval. DMICDC and the consultants A Stakeholder followed by Workshop was another review conducted under meeting on 20th the Chairmanship March, 2015. of Chief Secretary, Government of CEO & MD, Haryana on 28th DMICDC vide May, 2015. its letter dated 18th May 2015 As directed by has requested Chief Secretary, Principal Government of Secretary, Haryana, a sub- Power committee under Department, the chairmanship of Government of Chief Engineer Uttar Pradesh (LCU), Irrigation & to give their Water Resource consent on the Department with following to representative of enable the IIT other concerned Greater Noida departments/organi project forward: zations reviewed reports / finding of  Power the IWRM plan in allocation of the meetings held 182 MVA for on 3rd June, 2015 IIT Greater and 18th June, 2015 Noida followed by another  Confirmation meeting held on 6th on power sources – October, 2015. 400/220 KV substation located at Pali and Chholas Village (two feeders from each source may be confirmed)  Construction power of 10 MVA by double circuit overhead line.

CEO & MD, DMICDC vide its letter dated 18th May, 2015 has requested Principal Secretary, Irrigation and Water Resources Department, Government of Uttar Pradesh to provide their confirmation regarding allocation of 7 MLD of potable Ganga water from Mat branch.

During the meeting held on 10th April 2015 under the chairmanship of Chief Secretary, Uttar Pradesh, consultants were asked to submit the power supply details to UPPTCL and the same has been shared to the concerned department on 20th April, 2015. The progress of the project was reviewed by CEO & MD, DMICDC in the meeting held on 24th April, 2015, 8th May 2015 and 18th May, 2015.

Further Board Meeting of the SPV was held on 18th May, 2015. Minutes of the meeting are awaited.

CEO&MD, DMICDC vide letter dated 18th June, 2015 has requested State Government of UP regarding availability of State Government officials for presentation on Single Window Clearance Mechanism for IIT Greater Noida project proposed by DMICDC.

CEO & MD, DMICDC vide letter dated 24th August, 2015 had requested Principal Secretary (Industries) for approval of master plan, so that the process of environmental clearance could be expedited.

A meeting was held on 26th October, 2015 under the Chairmanship of CEO & MD, DMICDC in the presence of CEO, GNIDA to review the progress of the project and the way forward.

The tender document for selection of Programme Manager for implementation of Integrated Industrial Township project has been issued and Pre- bid meeting was held on 7th July 2015.

Tender document for selection of EPC Contractor for the construction of Trunk Infrastructure components has been issued on 9th July, 2015and pre- bid meeting was held on 18th August 2015.

The tender for selection of Programme Manager for implementation of Integrated Industrial Township project has been issued on 31st March 2016.

EPC Contractor for implementation of Trunk infrastructure components has been appointed. Work has been initiated on the ground.

Secretary, DIPP has reviewed the progress of the project on 1st April, 2016 followed by the site visit.

M/s Rodic consultants have been selected as the Project Management consultant (PMC) for the project.

The application for approval of Terms of Reference (ToR) for carrying out the EIA study for the proposed IIT, Greater Noida project has been submitted to state Expert Appraisal Committee (SEAC) on 12th October, 2016.

The Terms of Reference (ToR) for carrying out the EIA study for the proposed IIT, Greater Noida project has been approved in the 298th meeting of the State Expert Appraisal Committee (SEAC) held on 25th November, 2016. Officials of DMICDC reviewed the progress of activities at the site on 27th March, 2017.

The RFQ cum RFP for selection of contractor for installation of 33 and 11kV Power Distribution Works for Integrated Industrial Township, Greater Noida, Uttar Pradesh was issued on 14th February, 2017. The pre- bid meeting was conducted on 6th March, 2017.The last date of bid submission was 15th May, 2017 and no bids were received by the due date.

The tender was reissued on 4th July, 2017. The bid submission date has been extended up to 3rd October, 2017.

Three bids have been received by the bid submission date and the evaluation is under progress.

M/s Siemens has been appointed as the EPC contractor for installation of “33 and 11kV Power Distribution Works for Integrated Industrial Township, Greater Noida, Uttar Pradesh.

Review meetings were conducted on the project site on 20th & 27th July, 2018 and on 3rd & 10th August, 2018 by DMICDC to monitor the progress of works by contractor.

A meeting was conducted on 30th July, 2018 under the chairmanship of CEO & MD, DMICDC with Siemens regarding progress of works. It was directed to expedite the works and complete the project in a time bound manner.

CEO & MD, DMICDC visited the project site to review the progress of construction activities on 27.03.2018. CEO&MD, DMICDC vide letter dated 28.03.2018 have requested the Authority, Greater Noida Industrial Development Authority to expedite the handover of land for the project to the EPC ontractor.

RfQ cum RfP for Selection of Information and Communication Technology Consultant for IIT Project at Greater Noida was issued on 13th November 2017 and the due date for bid submission was 5th January, 2018. The bid opening was scheduled on 11th January, 2018. Since only 01 ( one) bid was received, the process has been annulled and will be re- tendered shortly.

Pre-bid meeting for the same was conducted on 22nd November 2017.

RfQ cum RfP for Selection of Systems Integrator for e- LMS for IIT Project at Greater Noida was issued on 14th November 2017and the due date for bid submission was 22nd January, 2018. Three bids have been received and the evaluation is under process.

Pre-bid meeting for the same was conducted on 23rd November 2017. Due date for bid submission is 22.01.2018

The Environment Clearance for Integrated Industrial Township Project at Greater Noida has been granted by the MoEF&CC vide letter dated 27th November, 2017.

A meeting was held on 23rd June, 2017 with Shri Alok Sinha, Principal Secretary, Industries, Government of UP and CEO&MD, DMICDC at Greater Noida Industrial Development Authority to discuss the issues and progress of project activities.

CEO&MD, DMICDC visited the site of IIT-GNL on 29th June 2017 to review the progress of construction works. The construction of roads and services, administrative building and compound wall of site is under progress. The estimated physical progress of construction activities on site is about 42.2%

A meeting was held on 9th August, 2017 with Chief Secretary, Government of Uttar Pradesh and CEO&MD, DMICDC at Lucknow to discuss the issues and progress of the DMIC projects in the State.

CEO&MD, DMICDC vide letter dated 20.03.2018 have requested Additional Chief Secretary, Infrastructure & Industrial Development, GoUP for expediting the approval on designation of DMIC IITGNL as Special Planning Authority.

Reminder letter dated 20th April, 2018 in this regard has been sent to ACS, Govt. of U.P.

A separate follow-up/ reminder letter was sent on 14th September, 2018 to Chief Secretary, Government of UP in this regard.

Secretary, DIPP vide his letter dated 14th May, 2018 has requested Chief Secretary, Government of UP to expedite the approval on designation of DMIC IITGNL as Special Planning Authority.

CEO & MD, DMICDC vide his letter dated, 25th May, 2018 has requested Principal Secretary (Energy), Government of U.P. regarding expediting of works of UPPTCL in IITGNL.

Meetings were held on 8th May, 2018 and 19th May, 2018 at the site to review the progress of trunk infrastructure works. Greater Noida Industrial Development Authority (GNIDA) was requested to expedite the transfer of balance land to the Contractor. Further, the contractor was instructed to complete the major works by end of July 2018 to meet the overall timelines.

CEO&MD, DMICDC attended the meeting held on 8th June, 2018 under the chairmanship of Additional Chief Secretary of Uttar Pradesh to discuss the matter regarding designation of DMIC IITGNL as “Special Planning Authority”. It was directed to expedite the process of designating the SPV as “Special Planning Authority” by the Government of Uttar Pradesh. A follow up letter dated 23rd July 2018 has been sent by SIPP to CS, UP as a reminder for the same.

CS, UP has further been requested to appoint CEO of DMIC, IITGNL for a tenure to 3 years.

RfQ cum RfP for Selection of Information and Communication Technology Consultant for IIT Project at Greater Noida was re-issued on 05.03.2018.

Two bids have been received by the due date on 10th April, 2018 and the evaluation of bids was annulled by DMIC IITGNL on 26th July 2018. The RfQ cum RfP will be reissued shortly.

The Master Plan of IITGNL was revised and approved by the Board f the SPV on 14th August, 2018.

CEO&MD, DMICDC vide his letter dated 6th September, 2018 to CEO, DMIC IIT- GNL have requested to expedite the EPC works.

LOA has been issued to CSM Technologies for Systems Integrator for e- LMS for IIT Project at Greater Noida on 2nd May, 2018.

Allotment of land to 3 applicants/ companies (Haier, Satkriti Comm. & Forme) to set up units in IIT- GNL has been approved in the Board meeting of SPV held on 31st August, 2018.

Land has been allotted to 3 applicants/ companies (Haier, Satkriti Comm. & Forme) to set up units in IIT- GNL. DMICDC vide letter dated 8.10.2018 have requested GNIDA regarding expediting the completion of construction works around the plots already allotted to industries.

CEO & MD, DMICDC vide his letter dated 9.10.2018 have requested the CS, Government of Uttar Pradesh to resolve the pending issues w.r.t. IIT GNL project.

Officials of DMICDC alongwith the SPV visited the site on 25.10.2018 and 20.11.2018 to monitor the progress of construction works by the contractor.

RfQ cum RfP for Selection of ICT Consultant was issued on 14.12.2018. The Pre-bid meeting was held on 28.12.2018 and bid submission due date is 28.1.2019.

Solid waste management of Noida and Greater Noida

The project was forwarded to the State Government on 14th March, 2014 and the comments are still awaited.

Re-use of waste water in Noida and Greater Noida:

Secretary, DIPP has requested Chief Secretary, Government of Uttar Pradesh vide his letter dated 21st July, 2015 to intervene and resolve all pending issues related to approval of State Govt. on Pre-feasibility study for water recycling and re-use strategy.

The draft Pre- feasibility report of the project was forwarded to the State Government on 2nd January, 2013 for comments. In the meeting held on 11th July, 2014 between DMICDC and GNIDA it was informed that the report is currently under review by the State Govt. and subsequently the comments shall be furnished to DMICDC at the earliest.

5 Status of JBIC loan for PDF Loan documents in respect of JBIC loan for DMIC project signed on 28th December 2009 between IIFCL and JBIC with sovereign guarantee from Government of India (Ministry of Finance).

6. Details of annual allocation/ Year 2009-10 2010 -11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 releases to DMIC-PDF / DMIC Project Implementation Allocation (in (BE) 50.00 75.00 BE 175.00 411.40 207.80 643.00 1199.99 1399.99 1031.79 Fund to be set up as Trust Crore) (RE) 0.01 RE 87.00

Releases (in 7.00 75.00 87.00 411.40 303.80 643.00 1176.06 499.86 744.00 Crore)

7. Indo – Japan Task Force 15 meetings held so far. Last meeting held on 27.10.2016 in New Delhi. Meetings – Number of meetings held so far/ decision in the last meeting

8. Eco-Cities in DMIC Region (ii) Smart Community/Eco Cities

In addition to the studies being conducted at the 4 sites of Dahej, Changodar, Shendra, Manesar, 2 more locations, namely, Neemrana and Haryana SEZ at Jhajjar have recently been taken up in discussion with METI, Japan. Several Pilot Projects have emerged from these studies for implementation.

CEO & MD, DMICDC vide its email dated 6th May, 2015 has sought cooperation and support of New Energy and Industrial Technology Department Organization (NEDO) on (a) Sustainable energy road map/ master plan and strategy for a green field industrial cities and engineering solutions, and (b) Strategy for transmission & distribution of power within cities under DMIC region.

A meeting has been held on 18th and 19th June, 2015 between METI, DMICDC and DIPP to discuss on Smart Community Project.

Dahej Ecocity, Gujarat (Hitachi, Itochu, Hyflux Consortium):

A SPV, namely Swarnim Dahejspring Desalination Pvt. Ltd., formed by the consortium members signed the Co-Development Agreement with Dahez SEZ Limited on March 22, 2012. The term sheet for the Water Purchase Agreement between the SPV and Dahej SEZ Limited (DSL) was finalized during the same time. The Co – development Agreement between Swarnim Dahej Spring Desalination Pvt. Ltd. (a SPV formed by the consortium members) and Dahej SEZ, was extended for another 3 months. The WPA between the SPV and DSL was executed on 11th January, 2013 in the presence of Chief Minister, Gujarat and Vice Minister, METI, Government of Japan. The project proposal for equity investment in the project has been posed for approval of DMIC Trust in its meeting held on 18/19 March, 2013. A meeting was held under the chairmanship of Additional Chief Secretary, Government of Gujarat on all the pending issues related to the project on 18th June, 2015. The meeting was also attended by the representatives of METI and the consortium led by M/s HITACHI. State Government vide their email dated 20th July, 2015 has forwarded the Minutes of the meeting held on 18th June, 2015. It has been informed that the details of Water Purchase Agreement (WPA) and proposed water Sales Agreement (WSA) were discussed at length and the financial implication thereof was also discussed. GIDC is supplying water at the rate of Rs. 27.04 per kilo liter and the proposed rate of desalinated water works about 73.00 per kilo liter which is too high and none of the industry shall be ready to pay such high water rate. GIDC and OPaL are not able to get a single buy- back agreement for the desalinated water. In the absence of buy-back commitment from end-users, It is impossible for GIDC or OPaL to take the desalination project forward. It was affirmed by Additional Chief Secretary, Gujarat that under the present circumstances it is not possible for GIDC or OPaL to take the burden of take or Pay agreement of the desalinated water.

Other emerging pilot projects being undertaken include solar roof top and Waste management.

 The feasibility report for other pilot projects is expected to be submitted soon. State Government issued the letter of comfort on 22nd January, 2014 for Seawater Desalination Project at Dahej. Equity Structure is being deliberated between Japanese consortium, JBIC and DMICDC.  CEO & MD, DMICDC has requested CEO, GIDB vide its letter dated 12th May, 2015 to provide an update on extension of validity of Water Purchase Agreement (WPA) for water supply project at Dahej, Gujarat.  SIPP vide his letter dated 22nd May, 2015 has requested Chief Secretary, Government of Gujarat to convene a joint meeting under his chairmanship along with other stakeholders to resolve pending issues related to Dahaj Desalination Project.

CEO&MD, DMICDC has requested for a meeting under the Chairmanship of Addl. Chief Secretary, Industries inviting all the stakeholders for discussion the outstanding issues including tariff, water quality parameters, water sales etc. and take the project forward vide letter dated 15th September, 2014. Responses in this regard is awaited. A reminder letter dated 23rd April, 2015 has been sent to State Government for a meeting alongwith all the Stakeholders to resolve pending issues. Confirmation for the meeting is awaited from the State Government of Gujarat. Secretary, DIPP vide letter dated 9th December, 2014 followed by DMICDC‟s letter dated 22nd December, 2014 has requested the State Government for a meeting along with other Stakeholders to resolve pending issues.

CEO & MD, DMICDC vide letter dated 1st January, 2015 has requested PMO to convene a meeting with all the stakeholders for early resolution of pending issues. CEO & MD, DMICDC vide letter dated 23rd April, 2015 has requested the State Government for a meeting along with all the stakeholders to resolve pending issues.

Sanand- Changodar Region, Gujarat (Mitsubishi consortium)

The emerging projects include Water Solutions system, Consolidated Solar Power, Dual Mode Transportation (at an alternative location with adequate demand). In a meeting held on 27th Feb 2013 with CEO, DMICDC, Mitsubishi Consortium shared their preliminary findings on the following projects:

(a) Coal Gasification project (b) Urban Mass-transportation Project (c) Lithium Battery Life Time cycle Business (d) Waste to Energy project Shendra Ecocity, Maharashtra (JGC Consortium):

 The consortium had a detailed meeting with DMICDC officials during March 5-6, 2012 on various proposed pilot projects viz. Drinking Water Supply, Waste Water service, Water Recycle Service, Electric Vehicle and Photovoltaic Cells. The discussion included aspects like tariff for various services, priority of projects, fund mobilization, role of DMICDC etc.  Decentralized smart service Multi infrastructure station is being taken up as a pilot project.  The feasibility report for these pilot projects is expected to be submitted soon

Manesar-Bawal Ecocity, Haryana (Toshiba Consortium):

Energy management system with high efficient gas cogeneration system is being evolved by Toshiba as a pilot project. Toshiba Consortium is in discussion with GAIL for allocation of domestic natural gas and met with local industries for „high quality‟ and „stable‟ electricity supply. TOSHIBA Consortium in a meeting held on 20th September 2012 explained that they are taking forward the project structuring. Meetings were held in January 2013 with IOCL and BPCL to discuss the gas pricing issue. TOSHIBA Consortium filed a petition to Haryana Electricity Regulatory Commission (HERC) seeking permission to sell electricity directly to the industries. HERC had subsequently sought views from DMICDC in this regard. The same was provided. The matter was heard by HERC on 2nd April, 2013 and HERC will be formulating some guidelines in this regard. The order was issued on 29th July, 2013. Japanese consortium is examining the order of HERC. Various rounds of meetings have been held with GAIL to discuss the availability of gas at reasonable prices. A meeting was held on 2nd December, 2013 with Secretary, MoPNG to discuss the availability of gas at reasonable prices. A self-contained proposal has been sent to MoPNG stating the gas requirements in the phased manner. During the Indo Japan Task Force Meeting held on 20th August, 2014, the representative of MoPNG stated that the recommendation for the allocation of gas for power projects will be made by the Ministry of Power based on the priority of the projects. Various rounds of discussions have been held between Toshiba and DHBVNL to see the possibility of out of court settlement and in this regard M/s Toshiba has already forwarded a draft MoU to the lawyers of M/s DHBVN to agree on the out of court settlement and for withdrawing their appeal from APTEL. Meanwhile, HERC issued the orders dt. 29th May, 2014 for increasing the cross subsidy surcharge (CSS) and additional surcharge (AS):- CSS AS Total (Rs./KWH) 2013-14 0.53 0 0.53 2014-15 2.02 0.5 2.52 Various meetings have been held in this regard. DHBVNL during a joint meeting held on 2nd March, 2015 informed that settlement issues can only be taken up after all necessary business approvals (SPV establishment and gas/ users/ land agreement under the name of the SPV) have been assured by Toshiba. SIPP vide letter dated 7th April, 2015 has requested Chairman, DHBVNL for intervention and facilitation for signing of MoU between Toshiba and DHBVNL. APTEL has dismissed the appeal filed by Dakshin Haryana Bijli Vitran Nigam Limited (DHBVN) and has upheld the orders earlier issued by Haryana Electricity Regulatory Commission (HERC).CEO & MD, DMICDC vide its letter dated 16th June, 2015 has requested Ministry of Power to make adequate allocation of domestic gas for the project.

M/s Toshiba has re-assessed the feasibility of the project and informed the following:- i. Power demand volume at expected power selling price has drastically decreased; ii. The ratio of consumers who utilize the grid power as the main power source is gradually increasing; iii. Liberalisation of power trading by launch of open access scheme has enabled the consumers to purchase electricity from power traders at cheaper price than grid tariff; iv. Grid power outage has been improved. v. Internal Rate of Return (IRR) will still be negative (Target IRR is 16%) and operations will be in deficit and therefore the project will not be economically viable. In view of the above, M/s Toshiba has proposed that the project may be kept on hold unless the business can be self-sustainable & provide adequate return on investment. The same has been informed to Secretary, DIPP vide DMICDC‟s letter dated 14th October, 2015.

Logistic Data Bank – DMIC Region: Jhajjar – Manesar region, Haryana:

NEC Corporation and Mitsui are working on the Logistics Data Bank business plan, and had a detailed discussion with DMICDC on the subject in the third wee of May 2012. They also had a meeting with Jawaharlal Nehru Port Trust about the Logistics Data Bank Concept and possible implementation strategy. The NEC Corporation is meeting logistic companies and large manufacturing companies to finalize implementation strategies for the Logistic Databank project. The NEC Consortium had given a presentation to DMICDC and apprised that a regulatory framework from DGFT for data sharing by all the logistics players will be necessary to ensure the viability of this project. In a meeting held on 28th Sept. 2012 the proof of concept on Logistics Data bank Project was presented to Secretary, Department of Commerce, who advised the consultant to work out the options for providing an affordable technological solution. A number of meetings were conducted by DMICDC with NEC Consortium in January 2013 to finalise the projects. The project proposal for equity investment in the project was posed for approval of DMIC Trust in its meeting held on 18/19 March, 2013. The trust had decided to implement the project through a SPV jointly (50:50) owned by DMIC Trust and NEC from Japan, who has developed the project. Regulatory framework for charging mandatory user charges is being discussed with DGFT and M/o Shipping and data sharing by all the logistics players will be necessary to ensure the viability of Logistics Data Bank (LDB) project. In this regard a meeting was held under the chairmanship of Secretary, Shipping with all the concerned stakeholders on 13th march, 2014.

In the meeting, it was decided that Jawaharlal Nehru Port Trust (JNPT) will make a proposal to Tariff Authority for Major Ports (TAMP) for including the mandatory user charges for LDB Project. TAMP will finalise the JNPT proposal and subsequently M/o Shipping can examine and issuing a common direction when the scheme is extended to major ports. Other concerned ministries will also issue necessary instructions and share the technical details. Meeting with Chairman, JNPT, TAMP & Joint Secretary, Shipping was held on 14th June, 2014 to move further on the proposal and take into consideration the inputs of private terminal operators of JNPT. A proposal was sent to JNPT for onward forwarding to TAMP vide letter dated 7th July, 2014 for issuance of notification for levy and collection of Mandatory User Charges (MUC) for DMICDC‟s Logistics Data Bank (LDB) project. Through this proposal, DMICDC is seeking support for exemption of MUC for LBD collected by Port terminal Operators, provision of area for setting up of kiosks of LDB operation at ports and to for allowing the SPV to deploy operations team for tagging and de-tagging of RFID tags. A meeting was held under the co-chairmanship of CEO&MD, DMICDC and Chairman, JNPT on 22nd August, 2014 to discuss the way forward for the project which was followed by a discussion at the level of Joint Secretary, Ministry of Shipping on 25th August, 2014. A joint hearing was held by Tariff Authority For Major Ports (TAMP) on 20th October, 2014 for fixation of Mandatory User Charges from JNPT for Logistics Data Bank project. Tariff Authority For Major Points has passed an order on 14th November 2014 for levy of Mandatory User Charges for Logistics data Bank project. This was communicated to DMICDC by TAMP vide their letter dated 14th November, 2014. CEO&MD, DMICDC, vide letter dated 15th December, 2014, has requested Railways and various port terminal operators for providing necessary authorization to DMICDC-LDB team to study and develop the necessary electronic interface with FOIS data for retrieving the container related information. Jawaharlal Nehru Port Trust vide letter dated 12th February 2015 has authorized LDB Team to study the terminal operating system and EDI interface for LDB Project. Discussion has been initiated with NEC team for the Shareholders Agreement (SHA) and incorporation of the project SPV. A joint meeting was held on 15th January, 2015 with NEC team and their legal consultants to discuss the term sheet received from NEC Team vide their e-mail dated 26th December, 2014. CEO&MD, DMICDC vide letter dated 23rd January, 2015 has requested METI to discuss the matter related to SHA & formation of SPV with NEC and issue necessary directions to expedite the same. DMICDC vide letter dated 9th February 2015 has requested METI to issue necessary direction to NEC for execution of SHA & formation of SPV for LDB Project. Various rounds of discussions have been held with the NEC Team on the draft Shareholder‟s Agreement (SHA). The matter was also deliberated at length during the Smart Community working group meeting held on 18th June, 2015. Secretary, DIPP vide his letter dated 25th June, 2015 has requested Vice Minister, METI to look into the matter and finalise the SHA at the earliest. Shareholders‟ Agreement (SHA) has been executed with NEC.The SPV for the project has been incorporated. Port Operator Agreement has been executed with Jawaharlal Nehru Port Trust. Additional equity of Rs.8.04 crore with 50-50 contribution from DMIC Trust and NEC, Japan has been received on 28th April, 2016. The work for supply of RFID Readers for Logistics Data Bank Project was awarded on 2nd May, 2016 and for Supply of RFID Tags on 14th May, 2016. Logistics Data Bank (LDB) Services Agreement has been executed with NEC India Pvt. Ltd. on 15th June, 2016. All the four kiosks have been set up at JNPCT, NSICT, APM to support operations at truck gate and rail sidings. Around 159 operators have been deployed at Ports to conduct the operations of tagging and de-tagging. Out of the total 49 locations which have been planned for FY 2016-17, about 32 locations have been covered, in which RFID installations is complete. The project has been launched and services have started at all the terminals of JNPT Port with effect from 1st July, 2016. About 12,151,419 containers have been tagged and de-tagged till the end of December, 2018. The System has been integrated with the ICE gate system of Department of Customs. 4 Port Terminals, 12 toll plazas and 34 CFS/ICDs are currently operational. All 50 locations which have been planned for FY 2016, have been covered in which RFID installations have been completed. Agreement with APSEZ signed on 3rd April, 2017 and LDB service has now extended to EXIM containers of Mundra & Hazira Port Terminals, Gujarat. DMICDC Logistics Data Bank Services (DLDS) has successfully launched the LDB Project across all container terminals at APSEZ Mundra (Adani Port Special Economic Zone) & AHPPL Hazira (Adani Hazira Port Pvt. Ltd.) in Gujarat from 1st May, 2017. With this expansion to Ports in Mundra & Hazira (Gujarat) as well as coverage of EXIM traffic of JNPT Mumbai, LDB service would now be providing visibility service to approximately 70 % of EXIM containers of India.4 Port Terminals at Mundra & 1 Port Terminal at Hazira are now operational for providing container tracking services through LDB Portal. With the coverage of Mundra and Hazira Port terminals, DLDS would be able to provide container tracking services to approximately 70% of the container traffic in India. Discussions have been initiated with Southern ports to expand the services of the project. DLDS LDB team visited the Container Port terminals in Katupalli, Krishnapatnam & Chidambaranar in South India and had meetings with the respective stakeholders for extending the LDB Services. Integration of Freight Operations Information System (FOIS) system of railways with LDB System has been successfully completed and users are now able to have the visibility of in-transit rail container movement. A meeting was held on 23rd August, 2017 with Indian Port Association (IPA) for discussions on the proposal of extending Logistics Data Bank (LDB) services to other Major ports in India. The Project was discussed during joint meeting between Prime Ministers of India & Japan in September 2017. DLDS has won the 11th Express, Logistics & Supply Chain Leadership Awards (ELSC Awards) in the Best-in-class Supply Chain Visibility category.

DLDS has launched the Pan India Operations of LDB Project on 18th December 2017 with the execution of agreements to extend the LDB service to New port terminal at JNPT i.e. Bharat Mumbai Container Terminals Private Ltd (BMCTPL) of PSA International, Krishnapatnam Port in Andhra Pradesh, Kattupalli and Ennore Ports in Tamil Nadu.

LDB Operation at Bharat Mumbai Container Terminal Private Limited (BMCTPL) has been started from 1st April, 2018.

DLDS issued the RFP for procurement of RFID readers for pan-India expansion of the LDB project on 25th July, 2018. The pre-bid meeting was held on 31st July, 2018. Meeting with Traffic Manager , Cochin Port Trust was held on 4th July, 2018 to discuss the expansion of Logistics Data Bank Project to Cochin Port Terminal. LDB Operations have been operational at Chennai, Krishnapatnam, Vizhakhapatnam, Cochin Ports, Haldia International Container Terminal (HICT) and Kolkata Port Trust (KOPT) from 1st November, 16th November and 1st December 2018 respectively.

Neemrana Ecocity, Rajasthan

 Efficient and stable supply of high-quality electricity in an industrial park – Mitsui & Kansai Ministry of P&NG has informed that as far as requirement of 2.8 mmscmd of RLNG for the Smart Community Projects in Rajasthan and Haryana is concerned, the same will be made at the price of RLNG applicable at the time of supply of gas in 2014. METI has been requested to finance the implementation of the pilot projects. 9. Any other issue related toa) Related to Financing & Implementation DMIC Project On 28th July 2011, an appraisal meeting was held under the chairmanship of Hon‟ble Finance Minister wherein various issues related to DMIC project were discussed and deliberated.

The final Memorandum of EFC was circulated to all concerned Ministries/Departments on 9th September, 2011. The EFC under the chairmanship of Secretary (Expenditure) in its meeting held on 17th October, 2011 recommended additional allocation of Rs.175 crore for carrying out project development activities. Draft note for the Cabinet Committee on Economic Affairs (CCEA) regarding financial support for carrying out DMIC project development activities, as approved by the Minister for Commerce, Industry and Textiles, forwarded to the Ministry of Finance with endorsement to the Cabinet Secretariat and PMO on 9th December, 2011. The CCEA in its meeting held on 24th January, 2012 has accorded its approval for the proposal.

The Cabinet on 15th September, 2011 has accorded approval for the financial and institutional structure for the development of industrial cities in the DMIC and formation of DMIC implementation fund of Rs.17,500 crore and project development fund of Rs.1000 crore for DMIC Project. The process of setting up of the Trust as per the Cabinet approval was initiated. The Deed of Public Trust for DMIC Project Implementation Trust Fund was signed in the presence of Hon‟ble Minister for Commerce, Industry and Textile on 27th September, 2012. In the existing equity of DMICDC, 41% held by IL&FS and 10% held by IDFC have been taken over by IIFCL and LIC respectively as per the Cabinet decision. As approved by the Cabinet, the Board of DMICDC had approved the increase in the authorized capital of the company from Rs.10 crore to Rs.100 crore.

Meeting of the Monitoring Committee for DMIC Project was held under the Chairmanship of Principal Secretary to PM on 13th December, 2011. A meeting was held under the chairmanship of Principal Secretary to PM on 20th December, 2011 to discuss allocation of gas and coal for DMIC power projects. A meeting under the Chairmanship of Secretary, DIPP was held on 10th October, 2011 to discuss the way forward. Meetings of the Monitoring Committee were held under the Chairmanship of Principal Secretary to Prime Minister on 29th October 2012 and on 24th May, 2013 and directions were given to concerned stakeholders to take appropriate action for swift implementation of various policy/ projects.

The Cabinet in August, 2012 accorded approval for revised equity structure of DMICDC with Government of India equity retained at 49% and Japan Bank for International Cooperation (JBIC) and Government owned financial institutions equity kept at 26% and 25% respectively. In pursuance of the above approval, the distribution of 25% shareholding in DMICDC among Government owned Financial Institutions was decided at 19.9% for Housing and Urban Development Corporation Ltd. (HUDCO), 4.1% for India Infrastructure Finance Company Ltd. (IIFCL) and 1% for Life Insurance Corporation of India (LIC); and the Share Holders Agreement with all the stakeholders, namely, Government of India, Japan Bank for International Cooperation (JBIC) and Financial Institutions owned by the Government of India was finalized after vetting by Ministry of Law and justice and executed on 28th March, 2013. The Board of Directors of DMICDC in its meeting held in April, 2013 approved the allocation of shares to GoI, JBIC and HUDCO.

A meeting was held on 26th June, 2012 under the Chairmanship of Secretary, DIPP to discuss DMIC related issues in National Capital Region and the meeting was attended by the representatives of National Capital Region Planning Board (NCRPB), State Governments of Rajasthan and Uttar Pradesh and DMIC Development Corporation.

A list of prospective projects in the infrastructure sector under the Government of Japan US $ 4.5 bn facility (JBIC and JICA) has been put together for carrying out Pre- Feasibility Studies/ Feasibility Studies and subsequent steps. The list was discussed in the Indo Japan Task Force meeting held on 19th October, 2012. A copy of the list was forwarded to the Department of Economic Affairs on 26th October, 2012 with the request to take appropriate action so that the list could be finalized at the earliest. In the meeting held in the Department of Economic Affairs on 1st November, 2012, it has been decided that DIPP/DMICDC would quickly provide concept notes/ preliminary project reports/ detailed project reports as are available in respect of all the identified 19 project proposals. It has also been stated that tentative cost of all the project proposals would also be indicated and the same would be forwarded to DEA after obtaining the approval of the Commerce & Industry Minister. DEA would examine the proposals and finalize the rolling plan of projects for the US $ 4.5 billion JBIC/JICA assistance after placing the list of projects before the DMIC Trust for approval. „In principle‟ approval of the Hon‟ble Minister of Commerce, Industry and Textile for the list of 19 prospective projects for Japan‟s USD 4.5 billion facility has been conveyed to the Department of Economic Affairs on 3rd January, 2013. Four projects have been posed by DEA to JICA under Rolling Plan. DEA has been requested to include these transportation projects.

A Consultative Mechanism/ Committee under the chairmanship of Secretary, Department of Economic Affairs (DEA) was set up and the issues regarding relaxation of capital regulations were taken up with the Reserve Bank of India. The issues regarding priority sector lending, relaxation of restrictions on foreign currency borrowing, opening of Japanese bank branches in metropolitan areas, expatriates in foreign banks and alternative option of financing have been resolved. Consultations are going on in respect of other outstanding issues related to relaxation of capital regulations.

Incorporation of City / Nodal level SPVs in accordance with the implementation framework approved by the Union Cabinet: Shareholder‟s Agreement and State Support Agreement for the states of Maharashtra and MP were finalized. New law has been drafted for DMIC in Rajasthan at the request of the State Government. DMICDC has also been in discussion with the respective State Governments for finalization of the SHAs and SSAs. DMICDC has received observations of Financial Department of Government of Maharashtra on SHA & SSA and the issues raised in the letter have been addressed by DMICDC in its reply to the State. SHA‟s/SSA‟s for the node/city level SPV of Maharashtra and Madhya Pradesh have been finalized with the State nodal agencies and the same were approved by the Board of Trustees in meeting held on 6th December, 2013. Approval / concurrence and comments are awaited from other States. The State Government of Uttar Pradesh is in the process of drafting a new legislation. The Shareholders Agreement (SHA) and State Support Agreement (SSA) would be finalized in accordance with the new legislation.

DMICDC has also empaneled two companies as Project Management Consultants (PMC) who will work as an extended team of DMICDC.

 Appointment of Detailed Engineering Consultants for Phase 1 of the nodes. PMNC will finalise the TOR and undertake bid process management for selection of detailed engineering consultants. b) Project Development Activities (other than the 7 nodes, Power projects and smart communities) Road and Rail based Spur Connectivity to the new cities: Proposals have been submitted by DMICDC to the concerned Central Ministries. Rigorous follow up is being done by DMICDC to priorities their development. MoRTH vide OM no. 15014/1/2011/P&M dated 20th October 2011 agreed to undertake the construction of 4-6 lane highway ahead of demand to enable the viability of DMIC nodes in Maharashtra and Rajasthan. Railway Board has agreed to undertake the Technical Studies for the development Rail Infrastructure for Phase – I of Dholera SIR on joint sharing basis with DMICDC. A meeting on the Road connectivity required for DMIC Project was held under the Chairmanship of Secretary, Ministry of Road Transport and Highways on September 21, 2011. The Technical Studies for the development of Rail Infrastructure for Phase – I of Dholera SIR is complete and has been sent to Railway Board for their comments and observations.

The matter has been pursued by DIPP vide their letter dated June19, 2013. Ministry of Road Transport and Highways (MORTH) vide their letter dated 8th July, 2013 has informed that Ministry of Commerce & Industries will have to arrange for necessary funding out of their budgetary resources in order to develop p these road projects. However, any technical support required will be provided by MORTH.

Secretary, MoRTH vide his letter dated 15th October, 2014 to Secretary, DIPP has reiterated that due to the paucity of funds the proposal of road connectivity could not be taken forward. The matter of connecting Dighi Port Industrial Area of DMIC Project was also discussed in the Trust meeting held on 25th September, 2014 and it was decided that DEA will take up the matter with MoRTH. Secretary, DIPP vide his letter dated 12th January 2015 requested Secretary, Ministry of Finance for provision of adequate funds to MoRTH for the development of priority road projects for connectivity in the DMIC Region. DMICDC vide letter dated 20th April, 2015 has requested Ministry of Railways for development of rail connectivity spurs under DMIC region. A meeting was held on 15th June, 2015 in Ministry of Railways to discuss the rail-based connectivity spurs to the new cities of DMICDC. Various proposals which were earlier submitted by DMICDC to Ministry of Railways were discussed at length. The minutes of the meeting have been received. CEO & MD, DMICDC vide his letter dated 29th March, 2016 has requested Chairman, NHAI to take up the DPR preparation work for various road projects in Maharashtra on priority basis.  Logistics Hubs at select locations across the Dedicated Freight Corridor: In the meeting held under the Chairmanship of Chairman, Railway Board on 25th April, 2013 to apprise him about the DMICDC‟s proposed Multi – Modal Logistics Hubs (MMLH) at Rewari, Dadri, Sanand and in Maharashtra and to seek the support of Ministry of Railways for a favorable policy regime to promote and develop Multi-Modal Logistics Hub, DMICDC has been requested to submit detailed proposal regarding their request to bring the MMLP policy under the policy on port terminals.

Feasibility studies have been completed for Greater Noida, Rewari & Pithampur. DMICDC is conceiving similar facilities at select locations in Gujarat and Maharashtra, in the proximity of junction stations on the Dedicated Railway Freight Corridor. These projects need the support of key stakeholders i.e. the State Governments who will make the land available. DMIC Trust in its meeting held on 10th March 2014 has approved the selection of consultants for preparation of Techno-Economic Feasibility Study (TEFS) for the logistics hub project at Karmad in Maharashtra and Sanand in Gujarat. Letter of Award has been issued to the selected consultant for preparation of TEFS for Multi-Modal Logistics Park at Sanand.

Water Availability: In pursuance of the decisions taken in the meetings of the Monitoring Committee for the DMIC Project held on 18th November 2009 and 22nd June 2010, the Department of Industrial Policy and Promotion,0 with the concurrence of the Ministry of Water Resources, has constituted a Committee on 13th August 2010 under the chairmanship of Secretary, Ministry of Water Resources to look into the availability of water in the DMIC region. First meeting of the Committee held on 16th September 2010 and second meeting held on 18th August, 2011. In the 3rd meeting of the Water Committee held under the Chairmanship of Secretary, Ministry of Water Resources (MoWR) on November 06, 2012 on the availability of water in DMIC Region, Secretary, MoWR requested the State Governments to arrange water supply to the proposed new industrial cities in DMIC and suggested that State Governments may consider plans for the efficient use/management of water in irrigation sector where 80% of the water resources are used. DMICDC is getting an „Integrated Water Resources Management Plan‟ prepared for its nodes in Haryana and Rajasthan. The bidding process is complete. Work orders to the shortlisted consultants will be issued after getting approval of DMIC Trust. The consultants have been appointed for preparation of an Integrated Water Resource Management Plan and DPR for alternative sources of water for the KBNIR & MBIR.

India International Convention and Expo Centre (IICC)

(Exhibition cum Convention Centre – Integrated Freight Complex at Dwarka, Delhi):

The Exhibition-cum-Convention facility has been conceived as a world class state-of-the-art facility for India. The project has been benchmarked against the world‟s best facilities and will consists of high quality iconic sustainable architecture, design and includes smart technologies, underground parking, transit oriented and integrated development. The ECC will be an internationally recognized, architectural icon with an innovative design and novel green building concept.

Extensive discussions have been carried out for deciding on the way forward for the ECC & ACC project between the important stakeholders such as DDA, Ministry of Urban Development (MoUD), DIPP, DMICDC and the Prime Minister‟s Office (PMO). „In-principle approval‟ of DDA was communicated by the Vice Chairman, DDA on 24th November, 2010 for establishment of a world class ECC at Dwarka, New Delhi.The Union Cabinet, while approving the financial & institutional structure for DMIC on 15th April, 2011, approved the establishment of the ECC at Delhi / Haryana as one of the Early Bird Projects. Subsequently DMICDC appointed M/s AECOM to undertake the preparation of the Master Plan, and carry out associated feasibility studies. During the meeting held under the chairmanship of Lt. Governor of Delhi on 23rd May, 2012 it was decided that DIPP would develop both ECC and IFC facilities and all the land for ECC and IFC project shall be transferred by DDA to DIPP on Government to Government transfer policy. The rates shall be decided as per existing DDA regulations for transfer of land to Government Departments. Subsequently, Ministry of Urban Development vide its Letters dated 19th December, 2012 and 24th January, 2013 directed Vice-Chairman, DDA to transfer the land to DIPP at the rates applicable to Government Departments. In the meeting held in PMO on 24th May, 2013, the Vice Chairman, DDA stated that land would be transferred by DDA to DIPP at Government to Government rates within a period of six weeks along with the permission to undertake mixed use development of the project components as an integral component of the Master Plan. A meeting was held on 1st November, 2013, under the chairmanship of the Principal Secretary to Prime Minister, to review the status updates on projects including the ECC project. It was decided that DDA will communicate the Government to Government rates for transfer of land to DIPP within two weeks under intimation to PMO. Thereafter DIPP will structure the project and move a note to CCEA for necessary approvals to the project. Even after the above discussions, the land was not transferred to DIPP by DDA. Therefore the PMO directed DIPP to move a Cabinet Note for transfer of the project site to DIPP. On this basis, a Cabinet Note was prepared with the proposal for transfer of land to DIPP, by DDA, at a nominal sum of Re.1. The subject was listed before the Cabinet on 25th April, 2014, but the item was deferred.

Subsequently, it has been decided to explore the option of DDA providing the land on long term lease (99 years) along with the required changes in land use to a Special Purpose Vehicle company (SPV) for implementing the ECC & ACC project. The SPV will be a 100% subsidiary of DMICDC and will further have all rights to sub-lease the land parcels, sub-contract project components, grant long term concessions to private developers, fix lease rentals etc. On the above basis, the project structuring option has been broadly developed for the ECC & ACC project.

In the meeting dated 7th February, 2015 in the PMO, it was decided that land for this project will be provided for the project. In this regard, a note for seeking the approval of Cabinet will be circulated by Department of Industrial Policy and the same is under process.

In the meeting held on 28th May, 2015 under the chairmanship of Hon‟ble Prime Minister, certain action points have been decided for the project. On the request of DIPP, DMICDC vide its e-mail dated 16th June 2015 has submitted its inputs on the action points. Further DIPP had requested for recommendation with regard to the availability of water for the project and the same was requested from Delhi Jal Board vide DMICDC letters dated 27th July, 2015 and 12th August, 2015.

Delhi Jal Board has given its inputs vide letter dated 24th August, 2015 and same has been forwarded to DIPP vide letter dated 25th August 2015. Further action is underway in DIPP. A status note giving point-wise replies to the issues raised during the meeting on 28.05.2015 has been sent to Prime Minister‟s office vide DIPP‟s Note dated 15.9.2015. A meeting was held on 21st December, 2015 under the Chairmanship of Hon‟ble Prime Minister of India to review the progress of the project. As per decisions taken during the above meeting, DIPP circulated a draft Cabinet Note on the subject for inter-ministerial consultation on 19.01.2016.Five copies of the Final Cabinet Note were sent to Cabinet Secretariat alongwith a copy to PMO vide DIPP‟s OM dated 11.02.2016. The Cabinet has approved the proposal of DIPP for transfer of land for the project to DIPP in its meeting held on 23.3.2016. The follow up action is underway in DIPP.

The Project Steering Committee constituted to oversee the ECC planning gave its approval to the implementation model on 26th May, 2016.

The Concept Master plan and feasibility report was carried out for the complete land parcel measuring 114 Ha including EIA and the concept architectural plan was prepared for an area of 970,000 sqm. The preliminary cost estimates for the complete development of the project has been finalised.

The RFQ cum RFP for Publ; Selection of Programme Manager has been issued on 20th July 2016.Three (3) nos. of bid proposals was received by the bid due date ie.29th August, 2016.

Stakeholders consultation meet for the project was held on 25th July 2016 for deliberations on the model for development and identification of the best suited model of implementation.

A meeting of the Committee of Secretaries (CoS) was held on 17th August, 2016 under the Chairmanship of Cabinet Secretary to review the progress of activities of the project.

The letter of Award has been issued to M/s AECOM as the Programme Manager for ECC on 22nd September, 2016.

The consortium of M/s AECOM India Pvt. Ltd. and M/s AECOM Asia Company Ltd. has been appointed as the Programme Manager for ECC.

A meeting was held under the chairmanship of Secretary, DIPP to review the progress of works under the project on 10th October, 2016.

The Delhi Development Authority (DDA) has transferred over 89.5832 Ha land (excluding 0.1368 Ha of the acquired land) to the Department of Industrial Policy and Promotion (DIPP) in Sector 25, Dwarka, New Delhi for creation of ECC on 6th September, 2016.

The revised demand note for the Infrastructure Development for Water and Sewerage Supply to the complex has been submitted by Delhi Jal Bard on 20th July, 2017.

Accordingly, DMICDC has requested DDA for carrying out the realignment of existing electrical power lines passing through the site. Also, DMICDC had sent a letter to DDA requesting to provide entry from western and southern boundaries to site via arterial roads (Sector – 25, Dwarka) and demarcate the same in the Final Master Plan.

DDA has provided an NOC for tree cutting/ afforestation in accordance with Delhi Preservation of Trees Act, 1994 in the 89.72 Ha of land in Sector – 25, Dwarka proposed as the ECC project site vide their letter dated 15th November, 2016. A Survey agency has been appointed as 3rd party surveying agency to conduct topographical survey for the project site. An application to Department of Forest & Wildlife seeking permission for felling of trees has been submitted. The permission for felling trees has been granted on August 16, 2017 subject to deposit of fee for compensatory plantation.

The MoEF&CC has granted the Environmental Clearance for the project vide letter dated 29th August, 2017.

Delhi Metro Rail Corporation Ltd. (DMRC) have agreed “in principle” to prepare the Detailed Project Report (DPR) to assess the feasibility of Metro connection to the proposed ECC site at Sector – 25, Dwarka. DMRC has submitted a Brief Report on “Extension of Delhi Metro from Sector -21, Dwarka to proposed Exhibition-cum-Convention Centre at Sector 25, Dw2arka vide their letter dated 22nd September, 2016.

As the project lies in proximity to the IGI Airport, an application has been sent to Airports Authority of India (AAI) seeking max. allowable building heights in the proposed site.

Survey of India has been appointed to conduct physical site survey for supply of coordinates and AMSL height of project site on 11thNovember, 2016. NHAI has been requested to construct an interchange along the Dwarka expressway which in any case is proposed to be constructed by NHAI on 8th November, 2016. DMICDC has requested Transco to provide uninterrupted power supply and source of transmission line to the project site to meet the expected demand on 17th November, 2016. An interactive session was conducted with Indian and International O&M operators on 16th December, 2016 to seek inputs and suggestions on the development of competitive project proposal. The 2nd meeting of Project Steering Committee for ECC Dwarka under the chairmanship of Secretary, Department of Economic affairs was held on 16th December, 2016. The project master plan was approved by the Steering Committee. Delhi Jal Board has agreed to make available 5 MLD water starting with 3 MLD by April, 2018. As decided in the Steering Committee meeting proposed to revise norms of ground coverage to 45% from existing 40% and built-up area for Exhibition, Convention and Meeting spaces to 35% from the existing 40% was submitted to DDA on 5th January, 2017. DDA has taken up the matter of realignment of existing HT lines passing through the site with BSES for 11 KV HT line and Haryana Vidyut Prasaran Nigam Ltd. (HVPNL) for 66kV HT line. BSES has submitted tentative estimate for shifting of 11 kV HT line and the survey has been conducted on 3rd December, 2016. Delhi Transco Ltd. (DTL) will set up the 3rd 220 KV substation by September, 2018 to make available enough power supply to meet expected demand of 110 MW for ECC. DDA has agreed to provide connectivity for 2 out of 3 arterial roads from the Western side with 24 mt RoW and they have invited tenders for the construction of the same by 9th January 2017. A letter has been sent to DDA requesting to provide connectivity for all three arterial roads to address voluminous traffic expected during mega events in ECC facility on 5th January, 2017. DDA has been requested (letter dated 5th January, 2017 and proposal letter highlighting the impact on financial viability dated 9th March 2017) for the provisions in the Delhi Master Plan 2021 notification regarding permissible percentage of Exhibition, Convention & Meeting space with respect to commercial spaces to 35%(EC):65%(Commercial) from existing 40%(EC):60%(Commercial) in order to achieve more economic and functional viability for the ECC facility. During the meeting of the Steering Committee held on 16th December, 2016, Delhi Jal Board has agreed to make available 5 MLD water starting with 3 MLD by April 2018. The Project Master Plan & Schematic Layouts submitted for Water Distribution Scheme respectively to Delhi Jal Board (DJB). DDA has provided NOC for cutting of trees existing within the project premises. Tree count and Tree classification for the project site has been obtained Joint inspection has been carried out with Deputy Conservator of Forests and an application to Department of Forest & Wildlife seeking permission for felling of trees has been submitted. Survey of India has completed physical site survey and submitted the coordinates of the site and Above Mean Sea Level Certificate on 21st December, 2016. A meeting was conducted with Member, NHAI on 29th December 2016 during which the proposed entry / exit points to EECC site were discussed and they were requested to take up the same for approval. NHAI has been requested to expedite the matter. As directed by DPCC, the application for Environmental clearance and request for seeking TOR has been submitted on MoEFCC web portal on 24th February, 2017. Application for Environmental clearance and approval of Terms of Reference (ToR) was submitted to the Ministry of Environment & Forest on 24th February 2017.Expert Appraisal Committee (EAC) reviewed the proposal on 14th April 2017 and granted ToR. Environmental Impact Assessment (EIA) Study has been completed at the site. Expert Appraisal Committee (EAC) reviewed the proposal for the grant of Environmental Clearance on 28th July 2017. Delhi Metro Rail Corporation Ltd (DMRC) have agreed “in principle” to the proposed configuration in master plan containing a metro station in the middle of the site with three entry / exit points in the project premises. DMRC has submitted the proposed alignment in master plan containing a metro station in the middle of the site with three entry/ exit points in the project premises on 27th January, 2017. Delhi Metro Rail Corporation Ltd. (DMRC) have submitted the updated Detailed Project Report (DPR) on 6th March, 2017 with updated costs as directed by CoS during the meeting held on 17th February 2017 & proposed alignment for the “Extension of Delhi Metro from Sector 21, Dwarka to the proposed Exhibition-cum-Convention Centre at Sector 25, Dwarka. DPR submitted by DMRC has been approved by DIPP on 31st March, 2017.

Delhi Metro Rail Corporation (DMRC) has appointed construction agency to undertake the extension of Metro link to IICC Dwarka and the work has been started at site.

A scheme for dedicated entry / exit points for ECC facility has been prepared by M/s AECOM (PMC) in consultation with NHAI and same has been submitted to NHAI for approval. AAI has provided NOC as per maximum permissible building heights for individual building blocks of the ECC Complex. A meeting was held under the Chairmanship of Cabinet Secretary on 17th February, 2017 to review the progress of the project. A stakeholders‟ meeting was held under the chairmanship of Secretary, Department of Industrial Policy and Promotion on 28th February, 2017 to review the status of statutory approvals required from the stakeholders and any issues thereof. The Project Master Plan has been submitted to DDA & DUAC for statutory approval on 9th February, 2017. The Project Master Plan & Schematic Layouts for Electrical and Water Distribution Scheme have been submitted to Delhi Tansco Limited (DTL) & Delhi Jal Board (DJB) respectively for statutory approval on 9th February, 2017. A scheme for dedicated entry / exit points for ECC facility has been prepared by M/s AECOM (PMC) in consultation with NHAI and same has been submitted to NHAI for approval. RfP cum RfQ for Selection of Commercialization, Planning & Transaction Advisor has been issued on 10th March, 2017. A consortium of M/s IDOM and M/s CP Kukreja Architects has been appointed as Preliminary Engineering and Architectural Consultant. The LOA was issued on 21st March, 2017. A Standing Committee of South Delhi Municipal Corporation (SDMC) has approved the layout plan of ECC project during the meeting on 23rd February, 2017. The approved layout plan duly signed by SDMC officials has been sent to DMICDC on 20th March, 2017. M/s Boston Consulting Group has been appointed as Commercialization, Planning & Transaction Advisor. DUAC reviewed the proposal on 31st March 2017 and zoning plan was approved on 7th April, 2017 with some observations. The response to the observations has been sent vide DMICDC letter dated 25th April, 2017. Based on the meeting held on 3rd May, 2017, DUAC has provided its approval on the urban design layout. The Project Master Plan & Schematic Layouts have been submitted to BSES Rajdhani Power Limited (BRPL) and SWS Division, SDMC for approval on 25th April, 2017. DDA has provided its approval on the Master Plan as per the project development proposal submitted in accordance to the MPDC-2021 guidelines. Electrical Distribution Scheme has been submitted to BSES Rajdhani Power Limited (BRPL) on 25TH April, 2017. An estimate for the Electrical Distribution has been received from BSES which will be included as a part of EPC Contract.

Haryana Vidyut Prasaran Nigarm Ltd. has appointed Adeco Energy Pvt. Ltd. to execute the shifting of HT lines passing through the site and the work has been started. Architectural design as finalized was presented to the members of CoS in the meeting held under the Chairmanship of Cabinet Secretary on 8th June 2017. Public Investment Board/ Committee of Establishment Expenditure (PIB/CEE) during its meeting dated 4th May, 2017 has recommended the formation of SPV with initial paid up capital of INR 5 cr. as equity and Additional Budgetary Support of INR 1500 crore. 5 copies of Final Cabinet note were sent to Cabinet Secretariat on 22.9.2017. The architectural design was also presented to Hon‟ble Prime Minister on September 28, 2017. United Traffic and Transportation Infrastructure (Planning & Engineering Centre (UTTIPEC) during its 42nd Working Group – IIA meeting held on 3.10.2017 recommended the road connectivity scheme to the Governing Body for approval and uploaded the same for community feedback. The Consent to Establish (CTE) has been issued by Delhi Pollution Control Committee vide letter dated 25th October, 2017.

Tender documents for selection of EPC contractor for Exhibition halls with associated Foyer, Convention Centre & Trunk Infrastructure and operator and maintenance agency have been issued on 16th October, 2017. The pre-bid meeting was held on 5th November, 2017.

The Union Cabinet in its meeting held on 10th November, 2017 has accorded its approval for development of Exhibition cum Convention Centre and allied infrastructure in PPP and non-PPP mode (including Exhibition & Convention spaces, arena, trunk infrastructure, Metro/NHAI connectivity, hotels, office and retails spaces, etc.).The progress of the project was reviewed by the Project Steering Committee in its 4th meeting held on 16th November, 2017.Steps have been initiated for incorporation of the project SPV.

A new Government company as a Special Purpose Vehicle(SPV) titled as India International Convention & Exhibition Centre Limited was incorporated on December 19, 2017 for the development and implementation of the project. The contract for EPC works for detailed design, construction, testing and commissioning of Phase-I components is under progress.

1st Board Meeting of the Company was held on 12th January, 2018. Larsen & Toubro has been appointed to undertake the detailed design, construction, testing and commissioning of Phase-I components on EPC basis. Larsen & Toubro Limited has been awarded the contract for Detailed Design, Construction, and Testing & Commissioning of IICC Dwarka Phase-I component on an EPC basis. The EPC agreement has been executed on January 30, 2018 and approx.. 188 acres (76.13) of land has been handed over to EPC Contractor. Construction works have been started at site.

The lease agreement has been executed between DIPP and India International Convention & Exhibition Centre Ltd on 08.03.2018 and further the deed got registered with the office of Sub-Registrar IX, Kapashera, New Delhi on 12.03.2018. Approx. 188 acres (76.13 Ha) of land has been handed over to EPC for undertaking construction activities at site. Land has been handed over to EPC Contractor for taking up the construction activities. Major excavation works have been completed and Plain Cement Concreting work is going on in full swing at site.

RfP for the selection of Operator for Exhibition and Convention Centre has been issued on March 22, 2018. A total of 03 bids were received till the last date of bid submission, i.e. May 7, 2018 and the evaluation process of the bids has been completed.

RfQ cum RfP for selection of Financial Advisor for raising loans for IICC has been issued on March 23, 2018. A total of 07 bids were received till the last date of bid submission, i.e. April 30, 2018 and the evaluation process of bids has been completed. A meeting under the chairmanship of Secretary, DIPP was held on May 25, 2018 to review the progress of EPC works and issues related to the project implementation. All the stakeholders were requested to cooperate to complete the project activities as per the timelines. Permission for felling of 1961 trees at site has been granted by Departments of Forest & Wildlife, Government of NCT of Delhi.

An MoU has been signed with Delhi Metro Rail Corporation (DMRC) for Extension of Airport Express line to IICC project on 22nd June, 2018 and the construction work is going on in full swing at site.

Operator Services Agreement for a term of 20 years from Commercial Operation date has been signed on 24.7.2018 for the consortium of Korea International Exhibition Centre and eSang Networks Company, who has been appointed as operator for Exhibition and Convention Centre.

RfP for selection of Developer for Hotels in IICC Project has been issued on 29th June, 2018 and the selection will be conducted via e-Auction. MSTC website has been engaged to conduct the e-Auction process for the same. The pre-proposal meeting was conducted on 19th July, 2018. DMRC has taken over the possession of remaining 0.1368 Ha land parcel after making due payment to the land owners on 18th July, 2018. The RfP process has been annulled. L&T has been directed to take up the construction activities in that portion.

South Delhi Municipal Corporation (SDMC) has granted approval on the building layout Plans for Phase-I development on 6th July, 2018. Consent to operate for two batching plants (120 cum/hr + 60 cum/hr) have been obtained from Delhi Pollution Control Committee on 27th August, 2018. As per the revision made in the site layout and built-up area, the application has been submitted to SDMC for revised layout plan approval on 6th August, 2018. Hon’ble Prime Minister of India laid the Foundation stone for the project on 20th September, 2018.

Development of Industrial Park Encompassing Logistics Centre at Silvassa in U.T. of Dadra & Nagar Haveli

In the meeting dated 17th December, 2014 between CEO & MD, DMICDC and Hon. Administrator, Union territories of Daman & Diu and Dadra & Nagar Haveli, it was decided to include world class Integrated Exhibition cum Convention Centre at Diu and Industrial park project at Silvassa for undertaking various project development activ0ities under DMICDC. Accordingly, tender document for “Selection of Consultant for Preparation of Techno-Economic Feasibility Report for Development of Industrial park Encompassing Logistics Centre at Silvassa” has been issued on 1st April, 2015.Four (4) bids have been received by the last date for submission of bid proposals, i.e. 25th May, 2015. The evaluation of bids is in progress.

The process has been annulled on account of no confirmation on the availability of land.

Exhibition Cum Convention Centre (ECC), Diu in U.T. of Daman & Diu

In the meeting dated 17th December, 2014 between CEO & MD, DMICDC and Hon. Administrator, Union Territories of Daman & Diu and Dadra & Nagar Haveli, it was decided to include world class Integrated exhibition cum Convention centre at Diu and Industrial park project at Silvassa for undertaking various project development activities under DMICDC. Accordingly, tender document for “Selection of Consultant for Preparation of Techno-Economic Feasibility Study Report for Exhibition Cum Convention Centre (ECC) at Diu has been issued on 1st April 2015. Five (5) bids have been received by the last date for submission of bid proposals, i.e. 25th May, 2015. The evaluation of bids is in progress.

The process has been annulled on account of no confirmation on the availability of land.

Skill Development centers: DMICDC has already selected the Transaction Advisor for the development of 7 Skill Development Institutes in the DMIC nodes to be developed in Phase 1A. To further strengthen the skill development initiative, DMICDC has also initiated the process of selection of Technical Skill Provider whose main task will be to identify the skill gap in the region and accordingly suggest and devise the courses in consultation with existing and proposed industries to reduce the skill gap on continuous basis. 4 bids were received in response to the RfP for selection of Technical Service provider.

The RfQ cum RfP for selection of consultant for providing technical consultancy for establishment of advanced Skill Development Institutions (SDI) in DMIC region was issued as well as Letter of award was issued to the selected consultant for providing Technical Service for establishment of Skill Development Centres. The team has been mobilized by the consultant. Project kick off meeting was conducted on 20th January, 2014. The appointed consultant has submitted the inception Report and Training Need Analysis report, other required data collection/surveys are in progress. The selected consultant for providing Technical Services for establishment of Advanced Skill Development Centres in DMIC region has submitted the draft Training Need Analysis reports for each of the six DMIC States. The consultant has submitted third deliverable i.e. Technical Report and fourth deliverable i.e. draft Detailed Project Report (DPR). DMICDC has reviewed the reports and provided their comments. The deliverables have been shared with the respective State Governments/Nodal Agencies for their comments/observations. The Government of Gujarat has provided their consent and approval to third, fourth and fifth deliverable i.e. Training Needs Assessment Report, Technical Report and Detail Project Report submitted by Technical consultant vide letter dated 14th August, 2014.

The Transaction Advisor (TA) has submitted the Inception report along with the Site appraisal report. DMICDC is in discussion with respective State Governments for formalizing the arrangements of provisioning of the proposed site for establishing advanced skill development institute. The TA consultant has submitted the revised Inception report along with the Site appraisal report for establishing advanced skill development institute in DMIC states (except UP). In a meeting held on 16th April, 2013 the TA made a detailed presentation to CEO, DMICDC on the way forward and models for the development of Skill Institutes. The development with respect to the same is as follows: Maharashtra: Shendra - The Site for the proposed Skill Development Institute has been proposed at Shendra Industrial Area, Aurangabad, Maharashtra by MIDC. The proposed site is a part of land parcel earmarked for amenities / utilities within the industrial area and it admeasures 30,000 sq m. The site is suitable for the development as Skill Development Institute.

Dighi Port - The Site for the proposed Skill Development Institute has been proposed at Ville Bhagad industrial Area, Raigad district by MIDC. The proposed site is a part of land parcel earmarked for amenities / utilities within the industrial area and it admeasures 30,000 sq m. The site is suitable for the development as Skill Development Institute.

Madhya Pradesh: The proposed site is located at Pithampur Industrial Area No. 3 , Dhar District and is part of land parcel earmarked for amenities. Madhya Pradesh Audyogik Kendra Vikas Nigam Ltd. (MPAKVN), Indore proposes to provide land measuring 20,000 sq m. The site is suitable for the development as Skill Development Institute. A meeting was held on 13th January 2014 with Principal Secretary, Department of Technical Education and Skill development, Government of Madhya Pradesh to discuss skill development issues.

Gujarat: The proposed site is located in Dhandhuka, Ahmedabad district. The proposed site has a building and land which currently is under the ownership of Gujarat Infrastructure Development Corporation (GIDC). The building was designed to accommodate a training centre and thus has all the required utilities such as power, water etc available at the site. Principal Secretary (Industries), Gujarat has been requested to consider extending the lease of the site to 30 years as the site is available for a period of 3-5 years only.

Rajasthan: The TA in consultation with state nodal agency had shortlisted two sites for setting Advanced Skill Development Center at Government Polytechnic college campus Neemrana and at Daulatsingpura, Neemrana. Both of these sites has connectivity issue and are parts of State Government vocational institutes. A request is being made to the State Government for providing green field site near Neemrana Industrial Park on long term basis as the transfer of the shortlisted sites on long term seems to be difficult. A meeting on establishment of advanced skill development centers in Rajasthan was held on 21st October, 2014 to update on the progress and receive the comments and feedback of the State Government. The comments of Government of Rajasthan on the deliverables have been received vide letter dated 7th November, 2014.

Haryana: In a meeting held on 3rd January 2013, Government of Haryana proposed a site located at Government Polytechnic college complex Manesar, The site/land parcel identified is under ownership of Manesar „Gram Panchayat‟ and has been leased to Department of Technical Education, Haryana. However, there is no clear demarcation of boundaries and the State Government is being requested to provide the boundary of the proposed site. A stakeholder meeting on establishment of advanced skill development centre in Haryana was held on 30th June, 2014 to update the progress and to receive feedback of the State Government. The Minutes of the meeting have been received from the State Government. It has been directed in this meeting to involve Department of Industrial Training, Govt. of Haryana. Accordingly, another meeting of key stakeholders including DMICDC and Consultants was held under chairmanship of DG, Industrial Training Department on 11th August, 2014 regarding the progress of the project. The State Government of Haryana has provided their comments/suggestions on the Technical Report and Draft Detail Project Report vide letter dated 2nd September, 2014. A meeting was held on 20th February, 2015 with Chief Secretary, Government of Haryana to discuss skill development issues . The State Government of Madhya Pradesh has provided their comments/suggestions on the study vide letter dated 2nd September, 2014. The comments of Haryana Industrial Training Directorate have also been received vide letter dated 20th November, 2014.

HSIIDC vide letter dated 16th April, 2015 has requested DMICDC and its consultant (M/s Accenture) to make a detailed presentation regarding the final DPR to HSIIDC. Industrial Training Department and Technical Education Department, Haryana. The consultant has been directed to schedule the same expeditiously.

A stakeholder meeting for DNGIR node in UP was held on 3rd July, 2014 and on 4th July, 2014 in Mumbai for Shendra Bidkin Industrial Area to discuss the way forward for the project. The State Government of Maharashtra has provided their comments/suggestions on the study vide letter dated 12th August, 2014. On 10th September, 2014, CEO&MD, DMICDC had a meeting with consultant providing technical services for Establishment of Advanced Skill Development Centres and Transaction Advisor to review the progress of the project. GNIDA has provided its comments / suggestions on third, fourth and fifth deliverables i.e. training Needs Assessment Report, Technical Report and Detailed Project Report submitted by Technical consultant vide email dated 30th January, 2015. The same has been shared with the consultant for incorporating in the respective revised reports. The selected consultant has submitted the fifth deliverable i.e. Final Detailed Project Report (DPR). The deliverables have been shared with the respective State Governments/Nodal Agencies for their comments/ observations. The State Government of Rajasthan has provided their comments/ suggestions on the Final Detailed Project Report (DPR) vide letter dated 18th June, 2015 and same have been forwarded to the consultant for the incorporation of the same. A meeting was held on 21st July, 2015 under the Chairmanship of Joint Secretary, Ministry of Skill Development and Entrepreneurship (MSDE) to discuss the synergies that can be drawn from the work that is being done by MSDE and DMICDC in the area of Skill Development. A meeting was held on 22nd April, 2016 with the Secretary, Ministry of Skill Development and entrepreneurship to discuss the way forward for skill development in DMIC nodes / cities. A meeting was held on 23rd June, 2016 with the Joint Secretary, Ministry of Skill Development and Entrepreneurship to discuss the next steps for skill development in DMIC nodes.

Information & Communication Technology (ICT) Master Planning for new cities being developed in DMIC Region:

In addition to the physical master planning activity, the ICT Master planning is being undertaken for the following nodes being developed in the DMIC Region: a) Ahmedabad Dholera in Gujarat; b) Dighi Port Industrial Area in Maharashtra; c) Shendra – Bidkin Industrial Park City in Maharashtra; d) Khushkhera Bhiwadi Neemrana Investment Region; and e) Manesar Bawal Investment Region in Haryana. The objective is to dovetail the physical master plan with the ICT Master Plan so that over a period of time, the real time control and governance of the city can be done by sitting in one command/ control centre. Final ICT report for the Dighi Port Industrial Area in Maharashtra has been submitted by the consultant. The reports for Ahmedabad Dholera Special Investment Region in Gujarat and Shendra – Bidkin Industrial Park in Maharashtra have been submitted by the consultant and accepted by the State Government. In a meeting held on 18th April 2013, the consultant had made a presentation on the final stage report. The final ICT Master Plans for Khushkhera Bhiwadi Neemrana Investment Region in Rajasthan and Manesar Bawal Investment Region in Haryana have been submitted by the consultant and the same have been submitted to State Government for their comments/suggestions. Comments of State Government of Rajasthan have been received and are being incorporated in the reports. The draft RfQ-cum-RfP for ICT Master Systems Integrator for implementation of Smart City Components at DSIR has been uploaded for the purpose of inviting suggestions/comments from potential applicants. The last date of receipt of comments was 15th May, 2014. The progress of the ICT in DMIC Region was reviewed by CEO&MD along with experts from IIT, Hyderabad on 30th May, 2014. A workshop was held on 23rd June, 2014 to discuss the comments on RFQ cum RFP for ICT Master System Integrator for implementation of Smart City components at DSIR with the perspective bidders. 27 companies participated in the workshop. The comments received are being compiled. A review meeting was held between DMICDC and State Government on 8th August, 2014 to discuss the way forward. EO&MD, DMICDC and Chairman, Telecom Regulatory Authority of India (TRAI) discussed regulatory issues relating to the implementation of ICT master plans in DSIR in Gujarat during the meeting held on 8th July, 2014. Later, DMICDC shared a self-containing note related to issues during the meeting with TRAI. TRAI vide their letter dated 13th August, 2014, has nominated two officers to address issues related to the ICT development in DSIR. A follow up meeting was held with the officials of TRAI on 12th September, 2014 to discuss the way forward and it was decided that SPV can own dark fiber within the current regulatory framework and this would require for an IP-I (Infrastructure Provider 1 Registration/License). It was also informed that since WiFi (2.4 and 5.8 GHz) is a non-regulated service hence SPV may own and operate WiFi infrastructure within DSIR. It was agreed that issues raised by DMICDC vide letter dated 23rd July, 2014 will be examined by TRAI and a meeting will be convened shortly to discuss the same. The minutes of the meeting held on 12th September, 2014 have been issued by TRAI addressing the queries raised by DMICDC vide the letter dated 23rd July, 2014. A meeting was held on November 12, 2014 in Gandhinagar with Telecom service Providers (TSP) to collect their views and expectations regarding technical aspects and operational issues related to the ICT project in Dholera Special Investment Region. The Second workshop on ICT with the industry players and based on the discussions/inputs, steps have been initiated for the appointment of the ICT consultant before moving forward with the appointment of the Master Systems Integrator. Based on various rounds of Industry Consultation, it has been decided that the ICT Consultant will be appointed for laying down detailed BoQs of various hardware and software components. RFQ cum RFP has been uploaded on DMICDC‟s website and the proposal due date has been extended till 4th June, 2015. CEO & MD, DMICDC vide its letter dated 14th May, 2015 and 5th May, 2015 has requested CEO, MIDC to send their comments / suggestions on the draft RFQ cum RFP for selection of ICT consultant for implementation of smart city components in Shendra Bidkin Industrial Area. The RFQ cum RFP for ICT Consultant for activation area in Dholera Special Investment Region was issued. Two bids have been received by the proposal due date and the evaluation of these bids is in progress. RfQ cum RfP document for selection of ICT Consultant for Shendra Bidkin Industrial Park (SBIA) (8.39 sq.km) has been issued on 29th June, 2015.Pre- bid meeting was held on 13th July, 2015. Revised document after carrying out modifications has been issued. Proposal due date was 5th October, 2015.Two bids have been received by the bid due date. ICT Consultant for Shendra Bidkin Industrial Park (SBIA) (8.39 sq.km) has been appointed. Letter of award has been issued. Kick off meeting conducted with ICT consultant at Programme office in Aurangabad and issued ICT Master Plan and relevant drawings to ICT Consultant. RfQ cum RfP document for selection of ICT Consultant for Dholera Special Investment Region (22.5 sq.km) was issued on 14th December, 2015.Two bids were received and after the financial opening, WIPRO is the successful bidder. The letter of award is being issued.

Investment opportunities for Infrastructure Development: The Memorandum of Understanding (MoU) was signed between DMICDC and India Infrastructure Finance Company Ltd. (IIFCL) on 26th August, 2016 to set forth their mutual intention to enhance investment opportunities to develop the India Infrastructure and relevant activities.

Marketing and Promotion of DMIC project: Senior officials of DMICDC are regularly holding meetings and discussions with banks, foreign delegates and resident missions to create awareness and promote various business. Investment opportunities in the DMIC Region. Recently the meetings have been held with Department of Electronics and Information Technology for setting up of electronic manufacturing clusters, with Ministry of Small, Medium and Micro Enterprises, Ministry of Food Processing etc. In addition, conferences and seminars are also being organized in association with various business forums- and Chambers of Commerce. DMICDC is actively participating in various conferences and seminars. State SPVs have also been requested to increase the investors outreach to start the allotment of land to the anchor investor. The Land Allotment Policy of four cities where the construction activities are underway has been finalized and process of land allotment has been initiated. A workshop was held on 20th September 2017 with the participation of officials from Ministry of Electronics & Information Technology, GoI and stakeholders of the industry on the development of DMIC projects and availability of land in the nodes.

Delegations from GIC Singapore, Canadian Commercial Corporation with focus on Defence & MRO and Yuwanta Securities from Taiwan have visited DMICDC and the Project SPVs during the month.

DMICDC Logo has been registered under the Trademarks Act, 1999.

DMICDC had participated in the 4th Defence Export Control and Acquisition Conference in New Delhi on 04-December, 2017 which was organised by the US-India Business Council. Deliberations were held with various key market players and stakeholders for considering DMIC smart cities as their future manufacturing destinations for Aerospace and Defence equipments.

DMICDC set up a pavilion at the 50th Skoch Summit promoting Dholera Special Investment Region among potential investors as a promising investment destination. DSIR also won Skoch Order-of-Merit award at the summit. DMICDC set up a pavilion at „Magnetic Maharashtra‟ event held in Mumbai from 18th to 23rd February, 2018 to showcase the project to probable investors. DMICDC organized a seminar with representatives of Pharma and medical devices sector on 21.03.2018. DMICDC in association with JBIC organized a seminar with Japanese companies on 20th June, 2018. Out of Home digital campaigns in the form of Airport Translites is active and running at Delhi and Mumbai Airports from November 2018 for industrial corridor projects. The campaign is receiving positive feedback and encouraging response from various target audience. Stakeholders/ Investors consultation seminar was organized by DMICDC along with the officials of SPV on 15th December, 2018 for the marketing and promotion of projects under DMIC.

1 MoUs are signed between DMICDC and the concerned state nodal agency for master planning and development of identified EBPs.

*************