Barton Highway Duplication Preferred Road Corridor Boundaries Report NOVEMBER 2011

Total Page:16

File Type:pdf, Size:1020Kb

Barton Highway Duplication Preferred Road Corridor Boundaries Report NOVEMBER 2011 Barton Highway duplication Preferred road corridor boundaries report NOVEMBER 2011 RMS 11.116 ISBN 978-1-922040-05-3 Quality control Manidis Roberts Pty Ltd ABN 42 003 550 972 Our reference 09089 Level 9, 17 York Street, Sydney NSW 2000 | GPO Box 91, Sydney NSW 2001 Version number 8 T (02) 9248 9800 | F (02) 9248 9810 | [email protected] | www.manidisroberts.com.au Date November 2011 Contents 1 Introduction 1 1.1 Purpose of this report 1 1.2 Background to the project 1 1.2.1 Project overview 1 1.2.2 Why do this now? 2 1.3 Study corridor 2 1.4 Consultation history 4 1.4.1 Consultation documentation 4 1.4.2 General consultation 5 1.4.3 PEI consultation 5 2 Project objectives 7 2.1 Regional transport needs 7 2.2 Safety 7 2.3 Traffic capacity 7 2.4 Future growth 8 3 Corridor constraints 9 3.1 Engineering and design constraints 9 3.1.1 Tie–in with existing infrastructure 9 3.1.2 Current road design standards 9 3.1.3 Access and interchange arrangements 9 3.1.4 Constructability and operational considerations 10 3.2 Environmental constraints 10 3.2.1 Aboriginal heritage 10 3.2.2 Non-Aboriginal heritage 11 3.2.3 Noise 11 3.2.4 Soil and water 11 3.2.5 Ecology 11 3.2.6 Visual amenity/landscape 11 3.2.7 Socio-economic considerations 12 3.2.8 Contaminated land 12 3.2.9 Additional assessment 12 4 Decision making process 13 4.1 Process 13 4.2 Output 14 5 Recent consultation activities 15 5.1 Summary of issues raised during recent consultation 15 5.1.1 Public display and information sessions 15 5.1.2 One–on–one discussions with property owners 16 5.1.3 Discussions with Aboriginal knowledge holders 16 6 Design refinements 17 6.1 16.0km to 16.5km from Canberra – curve improvement 17 6.2 20.5km to 20.8km from Canberra – Rolfe Road boundary adjustment 17 6.3 20.5km to 23.5km from Canberra – median width adjustment 17 6.4 22.1km to 23.0km from Canberra – removal of service road 17 6.5 24.0km to 27.0km from Canberra – change to proposed new carriageway location 18 6.6 31.0km to 33.2km from Canberra – adjusted alignment 18 6.7 31.6km to 31.9km from Canberra – Gooda Creek Road boundary adjustment 19 6.8 33.3km to 33.8km from Canberra – Vallencia Drive intersection adjustments 19 6.9 33.4km to 34.3km from Canberra – west side service road adjustments 19 6.10 34.3km to 35.0km from Canberra – Euroka Avenue interchange adjustments 19 6.11 34.6km to 36.0km from Canberra – east side service road changes 20 6.12 34.6km to 41.5km from Canberra – median crossovers near Murrumbateman 20 6.13 37.3km to 37.7km from Canberra – Murrumbateman Road overpass adjustment 20 6.14 38.8km to 39.2km from Canberra – Hillview Road overpass adjustment 21 6.15 39.9km to 41.3km from Canberra – boundary adjustment 21 7 The refined highway corridor 22 7.1 Description of refined highway corridor 22 7.2 Where to from here? 22 Appendix A – Overview of proposed road corridor 23 Appendix B – Barton Highway decisions matrix 63 Appendix C – Submissions report 81 Figures Figure 1.1 Barton Highway study corridor 3 Tables Table 1.1 Overview of issues raised by government agencies during preparation of the PEI 5 1 Introduction 1.1 Purpose of this report The purpose of this report is to: • Provide an overview of investigations and consultation undertaken to determine the road corridor boundaries for the future duplication of the Barton Highway between the Australian Capital Territory (ACT) border and the existing dual carriageway just south of the Yass River. The road corridor boundaries were submitted to Yass Valley Council for inclusion in the development of the council Local Environmental Plan (LEP) on 29 April 2011. This document reflects investigations and consultation from May 2010 to 29 April 2011. • Document the process of evaluation in determining the road corridor boundaries for the future duplication of the Barton Highway. This includes identification of environmental constraints, community business and government stakeholder requirements, Aboriginal and European heritage issues and engineering considerations that have influenced the corridor selection process. • Clearly describe the outcomes of the evaluation process, including: – Identification of how the decision making process has considered issues raised by the community at or as a result of the public display of the proposed road boundaries and concept design held in late May 2010. – Identification of how the decision making process has considered issues raised by the community or other stakeholders throughout the planning process – Identification of how the decision making process has considered any environmental, heritage or other issues in determining the road corridor boundaries. – A description of the preferred road corridor boundaries for the future duplication of the Barton Highway. 1.2 Background to the project 1.2.1 Project overview The Australian Government is funding the planning process for the future duplication of the existing single carriageway sections of the Barton Highway between the ACT border and the dual carriageways north of Murrumbateman. The Roads and Maritime Services (RMS) is managing the planning process. In 2008, a 200 metre wide corridor was identified along which various studies and investigations would occur. The study corridor extends for about 32.5 kilometres from the ACT border to the southern extent of the Barton Highway’s existing dual carriageway arrangement about 7.4 kilometres southeast of Yass (refer to Figure 1.1). Within the study corridor the Barton Highway is a single carriageway facility (one lane in either direction). It connects the dual carriageway south of the ACT border to the dual carriageway approximately 8.5km south of the Hume Highway. It generally follows the existing highway except for the bypass of Murrumbateman and the Gounyan curves deviation. The Murrumbateman bypass follows the “outer eastern” route declared by the Australian Government in October 2001. Barton Highway duplication 1 Roads and Maritime Services In 2009, Aurecon Australia Pty Ltd was engaged to carry out a preliminary environmental investigation of the corridor. The information gained from investigations and preliminary environmental studies was used to propose which side of the existing highway a new carriageway should be built and where the road boundaries should be located. In 2010 the proposed road boundaries and concept design were placed on public display for comment. This community and stakeholder feedback has been used to refine the concept design and finalise the road corridor boundaries. 1.2.2 Why do this now? Determining road boundaries for future duplication of the Barton Highway is being undertaken for several reasons: • To allow the RMS to identify properties impacted by the proposed road corridor boundaries and thereby provide the owners of those properties with certainty around the requirements for property acquisition that would be necessary to secure the road corridor. • Give options to property owners directly affected by the project under the provisions of the Land Acquisition (Just Terms Compensation) Act 1991. • Provide for the integration of the road corridor boundaries into Yass Valley Council’s Local Environmental Plan (LEP). 1.3 Study corridor The 200 metre wide primary study corridor was defined at the public display in May 2008. The Preliminary Environmental Investigation (PEI) involved an initial desktop investigation area of 500 metres either side of the centre line of the study corridor. Targeted environmental investigations were subsequently undertaken at areas of environmental sensitivity within the primary study corridor. Figure 1.1 identifies the study corridor for the proposed future duplication. 2 Barton Highway duplication Roads and Maritime Services Figure 1.1 Barton Highway study corridor Barton Highway duplication 3 Roads and Maritime Services 1.4 Consultation history 1.4.1 Consultation documentation The future duplication of the Barton Highway has been the subject of various investigations over a number of years. Figure 1.2 provides an overview of the consultation undertaken regarding this proposed project. Communications material relating to the proposed future duplication of the Barton Highway is included on the RMS’s website: http://www.rms.nsw.gov.au Figure 1.2 Barton Highway future duplication consultation overview Item Timing Detail Your property and RMS January 2008 A general fact sheet that provides information regarding the process for projects acquisition of privately owned land by the RMS under the Roads Act, 1993 and the Land Acquisition (Just Terms Compensation) Act 1991 to provide new or better road infrastructure. NB. An updated version of this document was issued in April 2011 with minor changes to some document references where these have changed or been updated. Barton Highway Safety February 2008 A document outlining the results of a review of road safety on the Barton Review Highway between the ACT border and the Hume Highway. Display panel and flip May 2008 The display panel provided details of the study corridor for the proposed chart future duplication. The flip chart provided the same information with a more detailed scale. Information on the benefits of the proposed future duplication, upcoming planning activities, property acquisition process and timing and details of upcoming information displays were included. Frequently asked May 2008 This FAQ sheet answered commonly asked community questions about questions and answers the project including information on investigations being undertaken, the extent of the proposed study corridor, property acquisition process, commencement of construction works, commentary on noise attenuation measures and an overview of ‘where to from here’.
Recommended publications
  • New South Wales Class 1 Load Carrying Vehicle Operator’S Guide
    New South Wales Class 1 Load Carrying Vehicle Operator’s Guide Important: This Operator’s Guide is for three Notices separated by Part A, Part B and Part C. Please read sections carefully as separate conditions may apply. For enquiries about roads and restrictions listed in this document please contact Transport for NSW Road Access unit: [email protected] 27 October 2020 New South Wales Class 1 Load Carrying Vehicle Operator’s Guide Contents Purpose ................................................................................................................................................................... 4 Definitions ............................................................................................................................................................... 4 NSW Travel Zones .................................................................................................................................................... 5 Part A – NSW Class 1 Load Carrying Vehicles Notice ................................................................................................ 9 About the Notice ..................................................................................................................................................... 9 1: Travel Conditions ................................................................................................................................................. 9 1.1 Pilot and Escort Requirements ..........................................................................................................................
    [Show full text]
  • Barton Highway FAQ December 2020
    Barton Highway FAQ December 2020 Questions Answers Where is the Barton The Barton Highway is about 52 kilometres in length, connecting the Hume Highway near Yass and the Highway located? surrounding rural and residential areas to the ACT. The highway plays a strategically significant role at a national and local level. It forms one part of the Sydney-Canberra-Melbourne road corridor, allowing freight movements between the three cities. On a local level, the highway connects the townships of Yass and Murrumbateman in NSW and Hall in the ACT; and surrounding rural areas to employment, health and education resources in Canberra. How is the upgrade being The Australian and NSW governments have each committed $50 million over four years to upgrade the funded? Barton Highway to improve driver safety, ease congestion and boost freight productivity. The funding will be used to fund investment priorities nominated in the Barton Highway Improvement Strategy 2017, which includes duplicating the highway from the ACT border towards Murrumbateman, as well as future staged upgrades. Has further funding been A further $100 million of Australian Government funding was announced for the Barton Highway in the committed? 2018/19 Federal Budget in May 2018. The announced funding was under the Australian Government’s Roads of Strategic Importance initiative. The duplication business case, which has been forwarded to the Australian Government, will provide guidance as to where the additional $100 million will be best directed. Why is the Barton Highway The Barton Highway is being upgraded to improve road safety. The upgrade will improve journey reliability, being upgraded? ease congestion, improve driver safety and boost freight productivity.
    [Show full text]
  • Ace Works Layout
    South East Australian Transport Strategy Inc. SEATS A Strategic Transport Network for South East Australia SEATS’ holistic approach supports economic development FTRUANNSDPOINRTG – JTOHBSE – FLIUFETSUTYRLE E 2013 SEATS South East Australian Transport Strategy Inc. Figure 1. The SEATS region (shaded green) Courtesy Meyrick and Associates Written by Ralf Kastan of Kastan Consulting for South East Australian Transport Strategy Inc (SEATS), with assistance from SEATS members (see list of members p.52). Edited by Laurelle Pacey Design and Layout by Artplan Graphics Published May 2013 by SEATS, PO Box 2106, MALUA BAY NSW 2536. www.seats.org.au For more information, please contact SEATS Executive Officer Chris Vardon OAM Phone: (02) 4471 1398 Mobile: 0413 088 797 Email: [email protected] Copyright © 2013 SEATS - South East Australian Transport Strategy Inc. 2 A Strategic Transport Network for South East Australia Contents MAP of SEATS region ......................................................................................................................................... 2 Executive Summary and proposed infrastructure ............................................................................ 4 1. Introduction ................................................................................................................................................. 6 2. Network objectives ............................................................................................................................... 7 3. SEATS STRATEGIC NETWORK ............................................................................................................
    [Show full text]
  • Roads to Riches: Better Transport Investment
    April 2016 Roads to riches Better transport investment Marion Terrill Roads to riches: better transport investment Grattan Institute Support Grattan Institute Report No. 2016-5, April 2016 This report was written by Marion Terrill, Grattan Institute Transport Program Founding Members Program Support Director. Owain Emslie and Brendan Coates provided extensive research Higher Education Program assistance and made substantial contributions to the report. Thornton McCamish and Lucille Danks also assisted in its preparation. We would like to thank the members of Grattan Institute’s Transport Program reference group and a number of other industry experts, researchers and officials for their helpful comments on the report. We would also like to thank Grattan Institute’s Public Policy Committee. The opinions in this report are those of the authors and do not necessarily Affiliate Partners represent the views of Grattan Institute’s founding members, affiliates, individual Google board members reference group members or reviewers. Any remaining errors or Origin Foundation omissions are the responsibility of the authors. Medibank Private Grattan Institute is an independent think-tank focused on Australian public Senior Affiliates policy. Our work is independent, practical and rigorous. We aim to improve policy outcomes by engaging with both decision-makers and the community. EY PwC For further information on the Institute’s programs, or to join our mailing list, The Scanlon Foundation please go to: http://www.grattan.edu.au/ Wesfarmers This report may be cited as Terrill, M., Emslie, O. and Coates, B. 2016, Roads to riches: better Affiliates transport investment, Grattan Institute ISBN: 978-1-925015-84-3 Ashurst Corrs All material published or otherwise created by Grattan Institute is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 3.0 Unported License.
    [Show full text]
  • Kairos Conf Brochure
    Kairos Prison “I was in Prison Ministry and you visited me” Australia (Matthew 25:36) Kairos Prison Ministry Australia PO Box 169, Hornsby, NSW, 1630 Phone: (+61 2) 9987 2016 Fax: (+61 2) 9476 6258 Email: [email protected] Web: www.kairos.org.au ABN 55 081 496 175 “That We May Be One” ACCOMMODATION OPTIONS Come along and enjoy a GETTING THERE wonderful time of fellowship with + Eaglehawk Ibis Styles other delegates from all over Australia as we mingle and ROAD: CONFERENCE VENUE From Sydney – Hume Highway then Federal Web page:http://www.accorhotels.com/gb/hotel- worship together. Highway - Eaglehawk is on the highway just 9271-ibis-styles-canberra-eaglehawk Phone: 02 6123 0100 or Email to: Throughout the weekend our work in before the ACT border. [email protected] From Melbourne – follow the Hume Highway the ministry will be improved by the and turn onto Barton Highway at Yass then Conference rates: sharings and during turn north and head towards Sydney. Queen room (1 queen bed) $145.00 per room presentations and workshops. per night Superior Double (2 double beds) $165 per room RAIL: Canberra Railway Station is There will also be an per night located in Kingston, ACT, 20 km from venue. Family Room (5 Guests) $205 per room opportunity to meet our new CEO. Local Kairos volunteers may be able to pick up per night (bedding available: King bed plus as there is no public transport to the venue. 3 singles or 5 singles) Registrations to: To obtain conference rates, the code BUS: Canberra bus station is located in the CONF3 must be used city, 20 km from venue.
    [Show full text]
  • Murrumbateman Evolving from a Village to a Unique and Sustainable Town
    Murrumbateman Evolving from a village to a unique and sustainable town Hillview Tapping into the strengthened economic triangle MURRUMBATEMAN EVOLVING FROM A VILLAGE TO A UNIQUE AND SUSTAINABLE TOWN MEETING THE CHALLENGE OF DEVELOPMENT PRESSURES • Protecting agricultural land and minimising loss of pastoral land to urban development • Ensuring urban development is sympathetic to the natural environment • Balancing population growth with the capacity of infrastructure and services to support it, particularly ensuring access to clean and secure water supplies • Developing innovative solutions to manage environmental impacts MURRUMBATEMAN EVOLVING FROM A VILLAGE TO A UNIQUE AND SUSTAINABLE TOWN MEETING THE CHALLENGE OF DEVELOPMENT PRESSURES • Expanding local employment lands to create new local jobs • Enhancing tourism opportunities • Maintaining the township atmosphere • Developing local employment and social opportunities to encourage young people to stay • Ensuring affordable housing and improved transportation options are provided MURRUMBATEMAN EVOLVING FROM A VILLAGE TO A UNIQUE AND SUSTAINABLE TOWN MURRUMBATEMAN • Protecting the growing wine industry from land use • Protecting visual amenity of surrounding farmland conflict • Recognising the opportunities of large parcels of • Developing opportunities from the upgrade of the land in single ownership to the north of the village Barton Highway and the potential for affordable housing • Tapping into new commercial, retail and industrial land opportunities MURRUMBATEMAN EVOLVING FROM A
    [Show full text]
  • Barton Highway/Gundaroo Drive/ William Slim Drive Roundabout Upgrade
    Barton Highway/Gundaroo Drive/ William Slim Drive roundabout upgrade Background Site constraints Roundabouts provide a safe, simple form of Prior to 2010, preliminary works looking traffic management at intersections, especially at options to improve the Barton Highway/ where the flows are balanced on each leg Gundaroo Drive/William Slim Drive intersection entering the intersection. examined ways to develop the site to reduce traffic delays and congestion and improve The roundabout at the intersection of the safety. Key constraints identified in these Barton Highway, Gundaroo Drive and preliminary investigations include: William Slim Drive provides practical traffic control outside peak traffic periods. However, • the layout of the roundabout, with wide with traffic growth generated from the separation of the dual carriageway developing Gungahlin region and beyond, approaches on the Barton Highway the existing intersection has become heavily • Ginninderra Creek immediately to the congested in the peak periods. Unbalanced north-west of the intersection and conflicting traffic flows, heading to and from • substantial bridge structures over the city during the peak periods, create lengthy Ginninderra Creek on both the Barton queues and delays on the heavily trafficked Highway carriageways which is in close legs. The result of these delays is an increase proximity to the intersection in the frequency of crashes. • the hill in the southern quadrant of the, intersection adjacent to Giralang (between The Barton Highway/Gundaroo Drive/William the Barton Highway northbound and William Slim Drive roundabout will be upgraded to Slim Drive) incorporate additional lanes and traffic signal • the boundary of the nature reserve in the control on all four approaches.
    [Show full text]
  • APPENDIX 1 APPROVED 4.6 METRE HIGH VEHICLE ROUTES Note: The
    APPENDIX 1 APPROVED 4.6 METRE HIGH VEHICLE ROUTES Note: The following link helps clarify where a road or council area is located: www.rta.nsw.gov.au/heavyvehicles/oversizeovermass/rav_maps.html Sydney Region Access to State roads listed below: Type Road Road Name Starting Point Finishing Point Condition No 4.6m 1 City Road Parramatta Road (HW5), Cleveland Street Chippendale (MR330), Chippendale 4.6m 1 Princes Highway Sydney Park Road Townson Street, (MR528), Newtown Blakehurst 4.6m 1 Princes Highway Townson Street, Ellis Street, Sylvania Northbound Tom Blakehurst Ugly's Bridge: vehicles over 4.3m and no more than 4.6m high must safely move to the middle lane to avoid low clearance obstacles (overhead bridge truss struts). 4.6m 1 Princes Highway Ellis Street, Sylvania Southern Freeway (M1 Princes Motorway), Waterfall 4.6m 2 Hume Highway Parramatta Road (HW5), Nepean River, Menangle Ashfield Park 4.6m 5 Broadway Harris Street (MR170), Wattle Street (MR594), Westbound travel Broadway Broadway only 4.6m 5 Broadway Wattle Street (MR594), City Road (HW1), Broadway Broadway 4.6m 5 Great Western Church Street (HW5), Western Freeway (M4 Highway Parramatta Western Motorway), Emu Plains 4.6m 5 Great Western Russell Street, Emu Lithgow / Blue Highway Plains Mountains Council Boundary 4.6m 5 Parramatta Road City Road (HW1), Old Canterbury Road Chippendale (MR652), Lewisham 4.6m 5 Parramatta Road George Street, James Ruse Drive Homebush (MR309), Granville 4.6m 5 Parramatta Road James Ruse Drive Marsh Street, Granville No Left Turn (MR309), Granville
    [Show full text]
  • Putting Hume First James Harker-Mortlock
    PUTTING HUME FIRST JAMES HARKER-MORTLOCK – INDEPENDENT CANDIDATE FOR HUME STATEMENT IN REGARD TO BARTON HIGHWAY DUPLICATION 12th December 2012 James Harker-Mortlock, independent candidate for the seat of Hume, stated today : ‘The saga of the duplication of the Barton Highway has been going on for too long. Too often people are injured or even killed on the Highway. Between 2009 and 2011, 16 people lost their lives and more than 160 were injured. Now is the time for action. I have made obtaining the funding for the completion of the Barton Highway my number one policy in my campaign for the seat of Hume. Unfortunately, the Barton Highway duplication appears to have been forgotten by the major parties. The Coalition completed some work at the Canberra end of the highway in the early 2000s and promised $264 million in the federal election campaign in 2007 to complete the duplication. The ALP Government has completed improvements on the Capricorn Corner and Gounyan Curves and has announced the installation of a right hand turning lane at Murrumbateman Road and the straightening of a one kilometre section of the Highway to its south. Whilst these improvements are much appreciated they are not enough. Not nearly enough. In a Report released in 2007 by the Australian Road Assessment Program (AusRAP), the NSW section of the Barton Highway was shown to be the worst section of AusLink-funded road in NSW. The report gave a two-star (out of five stars, with five being the safest) rating to 43 per cent of the NSW section of the road, with three stars for the remaining 57 per cent.
    [Show full text]
  • Barton Highway Duplication Business Case October 2019 Contents
    Barton Highway Duplication Business Case October 2019 Contents 1. Executive summary 3 4. Duplication assessment 13 1.1 Purpose 3 4.1 Value management workshop 13 1.2 Barton Highway Improvement Strategy 3 5. Scope 15 1.3 Case for duplication 3 1.4 Traffic, congestion and safety 4 6. Costs 15 1.5 Regional connectivity 4 1.6 Community expectations 4 7. Environmental and sustainability impacts 15 1.7 Duplication objectives 5 8. Project management and delivery 16 2. Overview 6 9. References 16 2.1 Transport demand 6 2.2 Traffic and congestion 7 Appendices 17 2.3 Driver behaviour 8 Appendix – A Traffic 17 2.4 Road safety 9 Appendix – B Duplication assessment 22 2.5 Community expectations 10 Appendix – C Design requirements 25 Appendix – D Economic assessment 26 3. Benefits 11 Appendix – E Stakeholder engagement 33 Barton Highway Duplication Business Case 2 1. Executive summary 1.1 Purpose Transport for NSW has prepared this business case on the staged duplication of the Barton Highway on behalf of the Australian Government. During this process, Transport for NSW consulted the Barton Highway Duplication Steering Committee, comprising stakeholders from: • Department of Infrastructure, Transport, Cities and Regional Development • Transport for NSW • Yass Valley Council. The Barton Highway is a strategically important rural highway linking the southern and western areas of NSW to the ACT. This business case for staged duplication of the highway will deliver the safety improvements and increased capacity required to meet current and future traffic demands. It will also support the continued economic growth and connectivity commitments as identified in the Barton Highway Improvement Strategy (2017).
    [Show full text]
  • Road Number and Name Changes in NSW
    Road number and name changes in NSW A better way to navigate NSW roads A25 Barton Highway The current route marking system in NSW is 30 years old and needs an overhaul. From early 2013, we will introduce a new road numbering system and new names for some important routes across the state network. The system will include a combination of a letter - either an M (motorway), A (route of national significance) orB (route of state significance) - and a umbern from 1 to 99. This factsheet details the changes across NSW. To Brisbane (Queensland) QUEENSLAND To Goondiwindi To Cunnamulla To Hebel (Queensland) To Warwick Woodenbong Tweed Heads (Queensland) (Queensland) A39 (Queensland) M1 A71 A55 A15 B91 Casino B62 B60 ay A39 u hw Western Tenterfield Br xner Hig B55 A1 Hig A15 B91 ir hw Moree wyd B76 ay B71 G G Summerland wy di B76 Way r y F Highwa o Brewarrina s B76 s y Grafton i a c Glen Innes k w e B76 Walgett h r r g s s y Bourke i A1 a H C w h a Coffs Narrabri g s B95 i t l l l W H Harbour e y M e r a d B78 a i e w t n y c e y a W a Armidale W h N a l g l y e l rfa h e a ll ng Wat B87 A39 E w w h n n B55 e ig a B71 ay N H H w H y High A15 m le ig i x g O d O i h w h A1 USTRALIA x K a w B56 Gunnedah le y a y c y fi Tamwor th i c Port B51 a Cobar B56 H P ighway Macquarie y A32 A32 Nyngan hwa Hig Quirindi Northern rier A32 Bar A32 SOUTH A ighwa A15 H y N olden Taree G e Broken Hill w B84 B84 E n A32 Dubbo M g H i la S i tc n i g h lv h d To Adelaide e e w H r B87 l A1 l a i (South Australia) C g y y h i w t A39 ay y H B55 i B75 A43 y g A32 a h C
    [Show full text]
  • VINCI Construction Wins Motorway Contracts in Australia
    Rueil-Malmaison, 5 October 2020 VINCI Construction wins motorway contracts in Australia • Upgrades to a stretch of the M1 Pacific motorway, the main motorway connection along the east coast of Australia • Upgrades to Barton Highway, a major route used to transport goods between New South Wales, Canberra, and Victoria • Two contracts worth a total €200 million Seymour Whyte, a VINCI Construction subsidiary based in Australia, has won two motorway upgrade contracts worth a total 330 million AUD (about €200 million). The first contract, worth 270 million AUD (€165 million), is for the third upgrade package on the M1 Pacific Motorway between Varsity Lakes and Tugun near the border between Queensland and New South Wales. Following on from the first package won by Seymour Whyte in June 2020, this contract involves widening a 5km section of the motorway to three lanes in both directions, upgrading motorway bridges and slip roads, building a new service road and preserving the corridor for a possible future rail extension. This work, which also includes integrating smart motorway technologies, will help to reduce travel times for the 90,000 motorists who use this section each day. The second contract, worth 60 million AUD (€37 million), will be carried out by an alliance chosen by Transport for NSW, between Seymour Whyte (responsible for the construction, 94%) and SMEC (tasked with the design, 6%). It involves upgrading a stretch of the Barton Highway between the Australian capital Canberra and Murrumbateman 280 km south west of Sydney in New South Wales. The package includes a new two-lane northbound carriageway, modifications to the existing Barton Highway, intersection upgrades, drainage works and relocation of services and utilities, as well as landscaping work.
    [Show full text]