200 Kv DC Extruded Cables Crossing the San Francisco Bay

Total Page:16

File Type:pdf, Size:1020Kb

200 Kv DC Extruded Cables Crossing the San Francisco Bay 21, rue d’Artois, F-75008 PARIS B1_105_2010 CIGRE 2010 http : //www.cigre.org 200 kV DC extruded cables crossing the San Francisco Bay M. BACCHINI T. WESTERWELLER N. KELLEY R. GRAMPA (*) Siemens, Prysmian Power Cables M. MARELLI Germany and Systems, Prysmian Powerlink, Italy U.S.A. SUMMARY In the Bay of San Francisco, in California, there is the first case in the world of commercial transmission of electrical energy in direct current at 200 kV with Multilevel VSC technology and cables with extruded insulation: it is the “Trans Bay Cable” (TBC) project. The innovative submarine HVDC link consists of two cables in bipolar configuration and has the capability to transmit 400 MW over a length of 55 miles i.e. 88 km. The connection between converter station in Potrero - in San Francisco - and Pittsburg - in the East Bay - allows the closure of the loop of the already existing “Greater Bay Area” transmission system, thus reinforcing the power flow directed to the center of San Francisco. This will decrease transmission grid congestion in the East Bay and will also avoid the need of building additional power plants in the City of San Francisco. Cables are manufactured by Prysmian in a factory close to Naples, in Italy, which is fully dedicated to submarine cables. Design for this specific project includes a copper conductor with a cross section of 1100 mm2, extruded insulation, lead sheath and armour of steel wires. The two HVDC cables (+/- 200 kV) are laid in bundle and buried at a depth of 6 ft (1.8 m), in a safe corridor separate from any existing AC cables. Laying operations are carried out by two different vessels: the “Giulio Verne” (one of the largest cableships in the world) for most of the route and a suitably equipped barge for the very shallow waters in the East Bay. The use of extruded insulation cables in the HVDC links showed a large increase during last years, due to some advantages that polymeric insulation can offer in comparison to traditional laminated mass impregnated cables and since the large technological progress happened, which involved materials, manufacturing process, system integration. KEYWORDS HVDC – VSC – Submarine cable – Extruded Cable – Multilevel converter – Interconnection. (*) Corresponding author Renato Grampa [[email protected]] PROJECT BACKGROUND The Trans Bay Cable Project (TBC Project) is a 400 MW, ±200 kV, submarine-based, point-to-point, DC transmission system which transmits power from the generation resource-rich area of Pittsburg, California to the City and County of San Francisco load-pocket (as shown in Figure X). The Project was developed by Trans Bay Cable, LLC and it will be owned by the Pittsburg Power Company upon Commercial Operation. Extruded DC and AC cable systems were provided by Prysmian and voltage-source DC converter stations were provided by Siemens as consortium partners under an engineer-procure-construct (EPC) contract. Commercial Operation is expected to be achieved during the first quarter of 2010. The benefits of the Project are many. The electric capacity and energy delivered by the Project to the City and County of San Francisco load-pocket improves power supply reliability and provides for future load-growth needs. In addition, overall electric system losses are substantially reduced. This focus of this paper is the 200 kV extruded DC submarine cable technology and installation provided by Prysmian. PROJECT DESCRIPTION AND INTERFACES The Project is integrated into the California ISO Control Area and interconnects with the Pacific Gas & Electric (PG&E) Pittsburg 230 kV Substation in Pittsburg, California and the PG&E Potrero 115 kV Substation in San. Francisco, California. A basic scheme of the link is reported in Figure 1. a.c. d.c. a.c. transmission transmission transmission 115 kV 200 kV 230 kV Fig. 1 Basic layout of the whole connection Specifically, the Project components include the: Pittsburg 230 kV Extruded AC Cable System which interconnects the Pittsburg Converter Station with the PG&E System at the PG&E Pittsburg Substation; Pittsburg Converter Station based upon Siemens’ Modular Multi-level Converter HVDC Plus Converter Technology; Land and Submarine ±200 kV Extruded DC Cable Technology which interconnects the Pittsburg Converter Station with the Potrero Converter Station; Potrero Converter Station based upon Siemens’ Modular Multi-level Converter HVDC Plus Converter Technology; and Potrero 115 kV Extruded AC Cable System which interconnects the Potrero Converter Station with the PG&E System at the PG&E Potrero Substation. 1 HVDC SYSTEM AND PLUS TECHNOLOGY A new modular multilevel converter (MMC) topology has been introduced by Siemens into HVDC applications during recent years. The concept of this topology is based on the converter arms acting as controllable voltage sources with a high number of possible discrete voltage steps. This allows for forming an approximate sine wave in terms of adjustable magnitude of the voltage to the AC terminal. This principle is shown in Figure 2. Each of these variable voltage sources is designed with a number of identical but individually controllable sub-modules. Each sub-module is a two-terminal component which can be switched Fig. 2 - Converter in Modular Multilevel topology and control principle between a state with full module voltage and a state with zero module voltage in both current directions. Dependent on the current direction, the capacitor can be charged or discharged. Besides auxiliary components and electronics, each sub-module consists of an IGBT half bridge and a capacitor unit. By serially connecting many modules an +U /2 d elegant multilevel topology can be constructed. It is possible to individually and selectively control each of the individual sub-modules in a converter arm. The total voltage of the two converter arms in one phase unit equals the DC voltage, and by adjusting the ratio of the converter arm voltages in one phase -Ud/2 module, the desired sinusoidal voltage at the AC terminal can be achieved. See Fig. 3 - AC and DC Voltages controlled by Converter Module Voltages Figure 3. DEVELOPMENT OF EXTRUDED CABLES FOR HVDC TRANSMISSION The TBC Project makes use of a new generation of HVDC cables, which are insulated with an extruded synthetic compound. If compared to traditional mass impregnated or oil filled cables, extruded cables generally provide several advantages. For DC application, they comprise use of simpler manufacturing technologies, a lower production cost, and possibility to operate cables at higher temperature than mass impregnated. These facts have been the main drivers which led to a large increase of the use of extruded insulation cables in the HVDC links during last years. Prysmian’s first stages of research was done at the end of years ‘90s on several polymeric insulating materials and included life test under increasing electrical stress, definition of coefficient of life (N, defined by using the very well known Weibull distribution law), investigation of space charge 2 distribution by applying PEA technology (Pulsed Electroacustic Analysis) to flat models of different polymeric insulating materials. Electrical conductivity of polymeric materials was investigated as well, by using flat models at different temperatures and electrical stresses. The second part of the study was done on model cables, insulated with most promising materials; the extensive test program consisted of: - d.c. dielectric strength, cold and hot conditions (from 20 to 90°C); - L.I. test (cold and hot) and L.I. superimposed onto HVDC of opposite polarity (cold and hot) - HVDC life test with step voltage increasing up to breakdown, with thermal cycles at 70°C; - HVDC life test as above, with daily polarity reversals. Eventually, the third part of the development project considered the best combination of semi- conductive and insulating materials. A full-size 200 kV 630 mm² cable and relevant accessories (flexible factory and repair joint, rigid repair joint, terminations) was submitted to a long-term test, following recommendation included in Cigré Technical Brochure 219 for DC VSC cable systems. The knowledge acquired during previous years and the very positive outcome of all development tests suggested to continue with development of HVDC extruded cables and a further pre-qualification started at increased voltage. A test protocol was prepared and implemented to allow a full qualification with and without polarity reversal, thus allowing use of DC extruded cables for both LCC and VSC converter technologies. Full system, including cable and accessories, has been subject to the following voltages, with thermal cycles in accordance to mentioned Cigré TB 219: - VSC System, U0 = 300 kV: o Voltage Cycle test: 435 kV, 70°C o Up2,S = 640 kV o Up2,O = 360 kV - LCC System, U0 = 250 kV: o Voltage Cycle test: 365 kV, 70°C o Polarity reversal: 315 kV, 70°C o Up1 = 500 kV (impulse superposed to DC at opposite polarity) Full test was successfully completed thus confirming that the applied materials and technology are fit for use for HVDC transmission: Additionally it further proved the importance of extensive development programs to move towards to industrial application with reasonable confidence. CABLE MANUFACTURING AND TESTING The most significant cable part of the TBC Project is the ±200 kV DC submarine cable. The power rating of the connection is 400 MW, which is considered as increased by 5% at sending point thus giving a nominal rated current of 1050 A. Specific environmental and installation conditions led to design a copper conductor size of 1100 mm2, which is of a compacted circular design, constructed from annealed plain copper wires and filled with water blocking compound to limit water propagation in case of cable severance. The insulation system consists of an inner semi-conducting screen layer, the insulation compound and an outer semi-conducting insulation screen, extruded simultaneously. The insulation is composed of a cross-linked polyethylene suitable for HVDC application.
Recommended publications
  • Trans Bay Cable LLC Docket No. ER13-2412-000
    145 FERC ¶ 61,151 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller, John R. Norris, Cheryl A. LaFleur, and Tony Clark. Trans Bay Cable LLC Docket No. ER13-2412-000 ORDER ACCEPTING AND SUSPENDING PROPOSED TARIFF CHANGES AND ESTABLISHING HEARING AND SETTLEMENT JUDGE PROCEDURES (Issued November 21, 2013) 1. On September 20, 2013, Trans Bay Cable LLC (Trans Bay) filed revisions to its transmission owner tariff (TO Tariff) increasing its transmission revenue requirement (TRR) from $132,500,000 to $139,134,000. In this order, we accept Trans Bay’s proposed TRR subject to refund; establish settlement judge and hearing procedures to determine, among other things, the discounted cash flow (DCF) range of reasonable returns for Trans Bay’s return on equity (ROE); and find that the resulting ROE should be set at the upper end of that range, not to exceed 13.5 percent, as discussed below. I. Background 2. Trans Bay owns a 53-mile, 400 MW high-voltage, direct-current submarine transmission line buried beneath the San Francisco Bay, with converter stations at each end (Project). The Project provides direct electric transmission between Pacific Gas and Electric Company’s (PG&E) Pittsburg and Potrero substations, both located in San Francisco, California. Trans Bay states that in 2012, the Project delivered power to approximately 57 percent of San Francisco’s load. As a participating transmission owner member of the California Independent System Operator Corporation (CAISO), Trans Bay recovers its high voltage TRR through CAISO’s transmission wheeling access charge pursuant to CAISO’s open access transmission tariff.
    [Show full text]
  • Hazards, Safety and Noise
    CHAPTER 4 HAZARDS, SAFETY AND NOISE Issues and topics related to health, safety, and noise within the Planning Area Topics: are addressed in this chapter. Some of these hazards may be naturally 4.1 Hazardous Materials and induced, such as wildfire hazards. Other health and safety hazards may be the Waste result of natural hazards, which are exacerbated by human activity, such as 4.2 Emergency Response and development in areas prone to flooding. Additional hazards are entirely Evacuation Routes human-made, including airport crash hazards and exposure to hazardous materials. For seismic and geologic hazards in the Planning Area, see Section 4.3 Air Traffic 5.4 (Geology, Soils, and Seismicity). 4.4 Fire Hazard 4.5 Flooding 4.6 Noise 4.0 HAZARDS, SAFETY AND NOISE 4.1 HAZARDOUS MATERIALS AND WASTE A hazardous material is a substance or combination of substances which, because of its quantity, concentration, or physical, chemical, or infectious characteristics, may either (1) cause or significantly contribute to an increase in mortality or an increase in serious, irreversible, or incapacitating irreversible illness; or (2) pose a substantial present or potential hazard to human health and safety or the environment when improperly treated, stored, transported, or disposed of. Hazardous materials are mainly present because of industries involving chemical byproducts from manufacturing, petrochemicals, and hazardous building materials. Hazardous waste is the subset of hazardous materials that has been abandoned, discarded, or recycled and is not properly contained, including contaminated soil or groundwater with concentrations of chemicals, infectious agents, or toxic elements sufficiently high to increase human mortality or to destroy the ecological environment.
    [Show full text]
  • HSC Minutes 11-2014
    Harbor Safety Committee of the San Francisco Bay Region Thursday, November 13, 2014 San Francisco Exploratorium, Observatory Pier 15, The Embarcadero San Francisco, CA Capt. Lynn Korwatch (M), Marine Exchange of the San Francisco Bay Region (Marine Exchange), Chair of the Harbor Safety Committee (HSC); called the meeting to order at 10:15. Alan Steinbrugge (A), Marine Exchange, confirmed the presence of a quorum of the HSC. Committee members (M) and alternates (A) in attendance with a vote: Capt. Esam Amso (M), Valero Marketing and Supply Company; Mary Brown (M), Horizon Lines; Michelle Connolly (A), Chevron Shipping Corp.; MGR Adam Czekanski, (M), US Army Corps of Engineers; Jeff Ferguson (M), NOAA; Aaron Golbus (M), Port of San Francisco; Bob Gregory (M), Foss Maritime; Capt. Bruce Horton (M), San Francisco Bar Pilots; Bill Needham (A), National Boating Federation; Jeff Robbins (A), General Steam Ship; Linda Scourtis (A), Bay Conservation and Development Commission; Deb Self (M), San Francisco Bay Keeper; Capt. Ray Shipway (M), Int’l Org. of Master, Mates & Pilots; Capt. Greg Stump (M), United States Coast Guard; Greg Zeligman (A), Starlight Marine Services. The meetings are always open to the public. Approval of the Minutes- A motion to accept the minutes of the October 9, 2014 meeting was made and seconded. The minutes were approved without dissent. Comments by Chair- Capt. Lynn Korwatch Welcomed the committee members and audience. Thanked the Exploratorium for hosting this month’s meeting. Mary Miller, San Francisco Exploratorium, welcomed the HSC and highlighted the partnerships the Exploratorium has with NOAA, UC Davis, USCG, Bar Pilots and the HSC among others.
    [Show full text]
  • Appendix C Trans Bay Cable LLC Preliminary Transmission Owner Tariff
    Draft Trans Bay Cable LLC Transmission Owner Tariff Appendix C Trans Bay Cable LLC Preliminary Transmission Owner Tariff January 13, 2006 Sheet No. 1 Draft Trans Bay Cable LLC Transmission Owner Tariff Table of Contents Section Page 1. Preamble .....................................................................................................................7 2. Effective Date............................................................................................................. 7 2.1 Termination..................................................................................................... 7 3. Definitions................................................................................................................... 7 3.1 Access Charge................................................................................................. 7 3.2 AGC ................................................................................................................ 7 3.3 Ancillary Services........................................................................................... 7 3.4 Applicable Reliability Criteria........................................................................ 8 3.5 Available Transfer Capacity ........................................................................... 8 3.6 Base Transmission Revenue Requirement...................................................... 8 3.7 Black Start....................................................................................................... 8 3.8 Business Day..................................................................................................
    [Show full text]
  • HSC Minutes 10-2014
    Harbor Safety Committee of the San Francisco Bay Region Thursday, October 9, 2014 Port of Richmond, Harbormaster’s Office, 1340 Marina Way South, Richmond, CA John Berge (M), Pacific Maritime Shipping Association, Vice-Chair of the Harbor Safety Committee (HSC); called the meeting to order at 10:15. Alan Steinbrugge (A), San Francisco Marine Exchange, confirmed the presence of a quorum of the HSC. Committee members (M) and alternates (A) in attendance with a vote: Jim Anderson (M), CA Dungeness Crab Task Force, Capt. Atanas Atanasov, Nation Cargo Bureau; John Berge (M), Pacific Maritime Shipping Association; Jessica Burton Evans, (A), US Army Corps of Engineers; Capt. Mike Day (A), United States Coast Guard; Capt. Tom Dougherty (M), Blue & Gold Fleet; Aaron Golbus (M), Port of San Francisco; Jim McGrath (M), Bay Conservation and Development Commission; Bob Gregory (M), Foss Maritime; Capt. Griffin Patrick (A), Tesoro Refining and Marketing; Deb Self (M), San Francisco Bay Keeper; Janie Singleton (M), Port of Richmond; Rich Smith (M), Westar Marine Services; Alan Steinbrugge (A), San Francisco Marine Exchange. The meetings are always open to the public. Approval of the Minutes- A motion to accept the minutes of the September 11, 2014 meeting was made and seconded. The minutes were approved without dissent. Comments by Chair- John Berge Welcomed the committee members and audience. Coast Guard Report- Capt. Mike Day Advised that mediation is ongoing regarding damage to the Trans Bay Cable caused by anchor fouling during a September 5 LOP incident. The Coast Guard is reviewing procedures. Advised of a September 21 stowaway case in which an American was caught on board a vessel departing for Asia.
    [Show full text]
  • Appendix a – Engineering Methodology, Environmental Engineering, and Permitting
    Appendix A – Engineering Methodology, Environmental Engineering, and Permitting Introduction Methodology This appendix presents the details of the engineering analyses completed to prepare the Technical Memorandum. Alignment engineering, environmental engineering, tunneling engineering, and geotechnical engineering disciplines provided input to the analysis of landings and corridors. The engineering analyses examined the locations of landings for the five categories of rail geometry, geotechnical conditions, environmental risks, constructability risks, and construction impacts. That table was presented in the main text. Then, the analyses focused on selected horizontal and vertical alignments within the corridors to examine potential fatal flaws with a San Francisco Bay (Bay) crossing. This appendix presents the regional setting for the study, then our compilation and commentary on geotechnical data and the regulatory environment. It then presents details associated with the two considered tunnel technologies, immersed tube tunnel (ITT) and mined tunnel. Study Area Since the scope of the initial engineering studies is only related to a new transbay tunnel, stakeholder agencies were limited to Bay Area Rapid Transit (BART) and regional and state rail providers. The study area considered in this memo is limited to crossings of the Bay and approximately one block inland on each side of the Bay. The vicinity of the study area is shown on Figure A1. In San Francisco, landing sites from Fisherman’s Wharf to Pier 70 were considered. In the East Bay, landing sites from Emeryville to Alameda Island were considered. The onshore alignment component of each landing was checked for its viability considering existing development and planned transit lines, but the development of onshore alignments is beyond the scope of this task.
    [Show full text]
  • Health & Safety Plan TBC‐HS‐103
    Health & Safety Plan TBC‐HS‐103 Fire Prevention Plan Annex A Wildfire Mitigation Plan TBC‐HS‐103: Annex A Wildfire Mitigation Plan Table of Contents 1. Persons Responsible for the Execution of the Plan .............................................................................. 6 1.1 Verification .................................................................................................................................... 6 2. Metrics and Underlying Data ................................................................................................................ 6 2.1 Lessons Learned ............................................................................................................................ 7 2.2 Recent Performance on Progress Metrics – Last 5 Years .............................................................. 8 2.3 Recent Performance on Outcome Metrics – Last 5 Years ............................................................. 9 2.4 Description of Additional Metrics ............................................................................................... 12 2.5 Description of Targets ................................................................................................................. 13 2.6 Detailed Information Supporting Outcome Metrics ................................................................... 13 2.7 Mapping Recent, Modelled, and Baseline Conditions ................................................................ 15 3. Baseline Ignition Probability and Wildfire Risk Exposure ..................................................................
    [Show full text]
  • LPI San Francisco Program Report (2009)
    Local Power, Inc. 35 Grove St. #118 San Francisco, CA 94102 (510) 451-1727 Community Choice Aggregation Program Report Submitted to: San Francisco Local Agency Formation Commission Final Version - February 28, 2009 (San Franciscans Use Mirrors to Reflect the Sun onto the City Hall Dome at Community Choice Rally, May 2006). Local Power Inc. 1 CCA Program Report February 28, 2008 San Francisco LAFCO Contents 1. Background and Introduction p. 3 2. Major Conclusions p. 12 3. Hetch-Hetchy p. 14 4. Projects Identified p. 18 a. Golden Gate Tidal Project p. 18 b. CCSF Solar Photovoltaics Programs p. 27 c. Wind Turbines p. 36 d. Cogeneration p. 43 e. In-City Grid Reliability Projects p. 60 f. General Zoning & Permitting Issues p. 68 5. SFDOE/PG&E Energy Efficiency Partnership p. 78 6. Trans-Bay Cable Project p. 81 7. Ongoing In-City Distribution Developments p. 86 8. Smart Grid and Emerging Technology p. 90 9. Best Practices Survey p.106 10. Recommendations p.118 Attachments Local Power Inc. 2 CCA Program Report February 28, 2008 San Francisco LAFCO 1. Background and Introduction On August 20, 2008 the San Francisco Local Agency Formation Commission (SFLAFCO) directed Local Power Inc. to begin work on this Community Choice Aggregation (CCA) Program Report. The purpose of this report is to outline and recommend a course of action regarding ongoing energy developments, public and/or private, that might be adapted to augment San Francisco’s CCA and H Bond Program (CCA Program) as approved in Ordinances 146-07 and 147-07 in 2007, as well as the original CCA Ordinance 86-04 in 2004.
    [Show full text]
  • U.S. Department of Homeland Security United States Coast Guard
    U.S. Department of Homeland Security United States Coast Guard LOCAL NOTICE TO MARINERS District: 11 Week: 52/19 CORRESPONDENCE TO: COMMANDER DISTRICT ELEVEN (DPW) COAST GUARD ISLAND BUILDING 50-2 ALAMEDA, CA 94501-5100 REFERENCES: COMDTPUB P16502.6, Light List Volume VI, 2017 Edition, U.S. Chart No.1 12th Edition, and Coast Pilot Volume 7 49th Edition. These publications, along with corrections, are available at: https://nauticalcharts.noaa.gov/ BROADCAST NOTICE TO MARINERS - Information concerning aids to navigation and waterway management promulgated through BNM HB-0024-19, SF-0137-19, LA-0202-19, and SD-0109-19 have been incorporated in this notice, or will continue if still significant. SECTION I - SPECIAL NOTICES This section contains information of special concern to the Mariner. SUBMITTING INFORMATION FOR PUBLICATION IN THE LOCAL NOTICE TO MARINERS A complete set of guidelines with examples and contact information can be found at http://www.pacificarea.uscg.mil/Our-Organization/District- 11/Prevention-Division/LnmRequest/ or call D11 Waterways Management Branch at 510-437-2980 or e-mail [email protected]. Please provide all Local Notice to Mariners submissions 14 days prior to the start of operations. BRIDGE INFORMATION- PROJECTS, DISCREPANCIES, CORRECTIONS & REGULATORY For all bridge related issues, including lighting, operation, obstructions, construction, demolition, etc. contact the Eleventh Coast Guard District Bridge Administrator 24 hour cell phone at 510-219-4366. Flotsam may accumulate on and near bridge piers and abutments. Mariners should approach all bridges with caution. A vessel delay at a drawbridge may be reported to the District Bridge Administrator by telephone, or by using the Delay_Report_11-2017.pdf included in the Enclosures section of this Local Notice to Mariners.
    [Show full text]
  • BEFORE the PUBLIC UTILITIES COMMISSION of the STATE of CALIFORNIA Order Instituting Rulemaking to Implement Electric Utility
    BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Implement Electric Utility Wildfire Mitigation Plans Rulemaking 18-10-007 Pursuant to Senate Bill 901 (2018) (Filed October 25, 2018) TRANS BAY CABLE LLC’S (U934-E) SUBMISSION OF ITS WILDFIRE MITIGATION PLAN Lenneal Gardner Corporate Counsel for Trans Bay Cable LLC One Letterman Dr., Suite C5-100 San Francisco, CA 94129 Phone: (415) 291-2300 Facsimile: (415) 651-9500 Email:[email protected] February 6, 2019 1 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Implement Electric Utility Wildfire Mitigation Plans Rulemaking 18-10-007 Pursuant to Senate Bill 901 (2018) (Filed October 25, 2018) TRANS BAY CABLE LLC’S (U934-E) SUBMISSION OF ITS WILDFIRE MITIGATION PLAN I. INTRODUCTION In accordance with the Administrative Law Judge’s Rule on Wildfire Mitigation Plan Template, and Adding Additional Parties as Respondents, Trans Bay Cable LLC (“TBC”) respectfully submits is Wildfire Mitigation Plan. II. BACKGROUND In response to the recent catastrophic wildfires in California, the state senate passed Senate Bill 901 (“SB 901”). SB 901 requires utilities operating in California to adopt wildfire mitigation plans subject to the review and approval of the California Public Utilities Commission (the “Commission”). The Commission instituted the above captioned rulemaking proceeding on October 25, 2018, providing guidance regarding the framework, details, content and deliverables of the wildfire mitigation plans to be with the Commission by February 6, 2019. On January 17, 2019, the assigned Administrative Law Judge issued a Ruling, naming 2 TBC and three other independent transmission owners as additional respondents with instructions to file a wildfire mitigation plan with the Commission by February 6, 2019.
    [Show full text]
  • MEMORANDUM February 21, 2007 TO
    MEMORANDUM February 21, 2007 TO: MEMBERS, PORT COMMISSION Hon. Ann Lazarus, President Hon. Kimberly Brandon, Vice President Hon. Rodney Fong Hon. Michael Hardeman FROM: Monique Moyer Executive Director SUBJECT: Informational presentation regarding the environmental review and energy policy considerations related to the proposal by Trans Bay Cable LLC (“TBC”) to install an electricity transmission line at 23rd Street and the San Francisco Bay and proposed terms of the proposed Port-TBC agreements. DIRECTOR’S RECOMMENDATION: INFORMATIONAL ONLY; NO ACTION REQUIRED Introduction Trans Bay Cable LLC (“TBC”) proposes to install a 400 MW high voltage direct current transmission line (“Project”) beneath the Bay, between the cities of Pittsburg and San Francisco. The subject of this report is the environmental review and approval process for the Project, the role the Project will play in the City and County of San Francisco’s transmission grid and related energy policy considerations, and draft terms of the proposed Port-TBC license agreements, subject to further negotiation. Port staff made an informational presentation to the Port Commission on December 12, 2006 regarding the Project. Background The Project sponsor is a wholly-owned subsidiary of Babcock & Brown LP, a San Francisco-based company, in cooperation with Pittsburg Power Company, a municipal utility. The primary goal of the Project is to transmit electrical power from the East Bay, which has excess electricity-generation capacity and to reduce transmission grid congestion to the distribution facilities in San Francisco. The California Independent System Operator (CAISO) approved the Project as the preferred long- term transmission alternative to address the identified electric reliability concerns in San Francisco and northern San Mateo County beginning in 2012 and supports an earlier date of operation.
    [Show full text]
  • U.S. Department of Homeland Security United States Coast Guard
    U.S. Department of Homeland Security United States Coast Guard LOCAL NOTICE TO MARINERS District: 11 Week: 43/18 CORRESPONDENCE TO: COMMANDER DISTRICT ELEVEN (DPW) COAST GUARD ISLAND BUILDING 50-2 ALAMEDA, CA 94501-5100 REFERENCES: COMDTPUB P16502.6, Light List Volume VI, 2017 Edition, U.S. Chart No.1 12th Edition, and Coast Pilot Volume 7 49th Edition. These publications, along with corrections, are available at: https://nauticalcharts.noaa.gov/ BROADCAST NOTICE TO MARINERS - Information concerning aids to navigation and waterway management promulgated through BNM HB-0013-18, SF-0160-18, LA-0145-18, and SD-0105-18 have been incorporated in this notice, or will continue if still significant. SECTION I - SPECIAL NOTICES This section contains information of special concern to the Mariner. SUBMITTING INFORMATION FOR PUBLICATION IN THE LOCAL NOTICE TO MARINERS A complete set of guidelines with examples and contact information can be found at http://www.pacificarea.uscg.mil/Our-Organization/District- 11/Prevention-Division/LnmRequest/ or call BM1 Silvestre Suga at 510-437-2980 or e-mail [email protected]. Please provide all Local Notice to Mariners submissions 14 days prior to the start of operations. BRIDGE INFORMATION- PROJECTS, DISCREPANCIES, CORRECTIONS & REGULATORY For all bridge related issues, including lighting, operation, obstructions, construction, demolition, etc. contact the Eleventh Coast Guard District Bridge Administrator 24 hour cell phone at 510-219-4366. Flotsam may accumulate on and near bridge piers and abutments. Mariners should approach all bridges with caution. A vessel delay at a drawbridge may be reported to the District Bridge Administrator by telephone, or by using the Delay_Report_11-2017.pdf included in the Enclosures section of this Local Notice to Mariners.
    [Show full text]