Alberta Power Industry Consortium & University of Alberta Professional Development Course
Power System Grounding – Industry Experiences
Organized By Alberta Power Industry Consortium & University of Alberta AESO AltaLink ATCO Enmax Epcor FortisAlberta
Instructed By
Joseph Kuffar & Dennis Peters, Enmax Nerkez Lalic, Epcor Dennis Rasmusson, AltaLink Wilsun Xu, University of Alberta
May 28 & 30, 2013
Calgary & Edmonton, Alberta, Canada
Abstract
Power system grounding is probably one of the most confusing subjects in the field of power engineering. It covers a wide range of topics, such as short‐circuit responses of power networks, electric field distributions of grounding structures, and implications to safe work practice. This course is a continuation of the 2012 APIC course on power system grounding. Building on the fundamental theories taught last year, the current course will share actual industry practices, experiences, investigations of the APIC companies. Relevant technical concepts and theories behind the practices will also be explained to facilitate learning. This course will mainly focus on grounding related electrical safety issues. A few cases involving the grounding performance of power systems will also be discussed.
1 1 Confidentiality Requirement
This course material was prepared by the University of Alberta for the ultimate benefit of the Alberta Power Industry Consortium members (hereinafter called “SPONSORS”). It may contain confidential research findings, trade secrets, proprietary materials (collectively called “Proprietary Information”). The term Proprietary Information includes, but is not limited to, plans, drawings, designs, specifications, new teaching materials, trade secrets, processes, systems, manufacturing techniques, model and mock-ups, and financial or cost data.
The document is made available to the sponsors only. The Sponsors will use all reasonable efforts to treat and keep confidential, and cause its officers, members, directors, employees, agents, contractors and students, if any, (“Representatives”) to treat and keep confidential, and Proprietary Information in the document and the document itself. This course material shall not be disclosed to any third party without the consent of the Alberta Power Industry Consortium.
Disclaimer
This document may contain reports, guidelines, practices that are developed by the University of Alberta and the members of the Alberta Power Industry Consortium (APIC).
Neither the APIC members, the University of Alberta, nor any of other person acting on his/her behalf makes any warranty or implied, or assumes any legal responsibility for the accuracy of any information or for the completeness or usefulness of any apparatus, product or process disclosed, or accept liability for the use, or damages resulting from the use, thereof. Neither do they represent that their use would not infringe upon privately owned rights.
Furthermore, the APIC companies and the University of Alberta hereby disclaim any and all warranties, expressed or implied, including the warranties of merchantability and fitness for a particular purpose, whether arising by law, custom, or conduct, with respect to any of the information contained in this document. In no event shall the APIC companies and the University of Alberta be liable for incidental or consequential damages because of use or any information contained in this document.
Any reference in this document to any specific commercial product, process or service by trade name, trademark, manufacture, or otherwise does not necessarily constitute or imply its endorsement or recommendation by the University of Alberta and/or the APIC companies.
2 2 About the Alberta Power Industry Consortium:
The Alberta Power Industry Consortium consists of six Alberta utility companies (AESO, AltaLink, ATCO, Enmax, Epcor and FortisAlberta) and the University of Alberta. Established in the fall of 2007, its goal is to bring Alberta power companies together, with the University of Alberta as the coordinating organization, to solve technical problems of common interest, to produce more power engineering graduates, to support the professional development of current employees, and to promote technical cooperation and exchange in Alberta’s power utility community.
3 3 About the instructors:
Mr. Joseph Kuffar is a 2004 graduate of Electrical Engineering from the University of Saskatchewan. Joseph has 9 years technical engineering experience. His work experience includes system planning, distribution system design, material standards and QC, and asset management (distribution & network). He is currently holds a position with ENMAX as Supervising Engineer, T&D Asset Management. Joseph is a registered professional engineer in the province of Alberta.
Mr. Nerkez Lalic is a 1972 graduate of Electric Power Engineering Faculty from the University of Sarajevo, Bosnia & Herzegovina. He worked for international equipment manufacturing, engineering and consulting companies on the design, construction, testing, commissioning and EPC management of high voltage substation and overhead/underground transmission line projects. He has been with EPCOR for nine years and currently holds the position of Senior Manager, Transmission Projects. Mr. Lalic has a special interest in improving EPC processes of complex engineering projects, focusing on implementation of COAA standardized engineering contracts in practice and safety standards improvement, coordination and implementation during execution of complex construction works. Mr. Lalic is a registered professional engineer in the province of Alberta.
Mr. Dennis Peters is a 2008 graduate of Electrical Engineering from the University of Saskatchewan. Dennis worked for ENMAX upon graduation and has 5 years of engineering experience. His work experience includes network secondary distribution customer and system design and recently network and distribution asset management. He has special interest in network secondary distribution material specifications and material QC and QA. Dennis currently holds a position with ENMAX as T&D Asset Management Engineer. Dennis is a registered professional engineer in the province of Alberta.
Mr. Dennis Rasmusson is a 1972 graduate of Electrical Engineering Technology from NAIT in Edmonton. Upon graduation Dennis spent the first 10 year of his career in the field in the area of protection and control. He spent the next 17 years in various positions in management in both transmission and distribution. During this time his roles included Manager of Substation Construction and Operations, Regional Transmission Maintenance Manager, Area Manager of Sherwood Park, and Director of Asset Management. During the last 15 years his main focus was on safety and held roles of Safety Manager and Director of EH&S. He has been working in the electrical utility industry for 42 years. In 2010 Dennis started his retirement by working as a safety specialist on a reduced work week and plans on retiring late 2013.
Dr. Wilsun Xu obtained a B.Sc. degree from China in 1982 and PhD from UBC in 1989. He worked in BC Hydro from 1989 to 1996. He joined the University of Alberta as a faculty member in 1996 and is currently a research chair professor at the U of A. Dr. Xu has extensive engineering and research experiences in the area of power quality. His research work on multiphase power system analysis has helped him to formulate a methodology to analyze faulted power systems with complex grounding configurations. In recent years, Dr. Xu has used the methodology to investigate several issues related to power system grounding. Dr. Xu is a registered professional engineer in the province of Alberta.
4 4 Course Outline
1. Review: Basic concepts of power system grounding Performance grounding versus safety grounding Basics of safety grounding Basics of performance grounding
2. Grounding and safe work practice Theory: Equipotential bonding and grounding transmission lines Case: Working on isolated transmission facilities – Altalink practice Case: Deep grounding‐well method for improving Epcor substation grounding Theory: Characteristics of GPR as affected by grounding arrangements
3. Grounding performance of power systems Theory: measurement of grounding resistances Case: Distribution grounding system assessment and replacement program of Enmax Case: Bonding feeder and substation neutrals – pros, cons, and ATCO practice Case: Does improving grounding help to reduce telephone interference?
5 5 Alberta Power Industry Consortium & University of Alberta Professional Development Course Power System Grounding - Industry Experiences
by Wilsun Xu, Professor [email protected] Department of Electrical & Computer Engineering University of Alberta
May 2013 6
Background of this course
• The 2012 APIC course covered various concepts & theories of power system grounding; • The course feedback indicates that there is an interest to learn actual cases and industry experiences on grounding; • This course is developed as a continuation of the last year’s course, with a focus on industry applications and experiences; • Key theories will also be reviewed to enhance learning; • Industry speakers are invited to share their experiences
7
Background of this course Industry instructors & cases
Joseph Kuffar, Supervising Engineer, T&D Asset Management, Enmax Dennis Peters, Engineer, T&D Asset Management, Enmax
• Case: Distribution grounding system assessment and replacement program of Enmax
Nerkez Lalic, Senior Manager - Transmission Projects, Epcor
• Case: Deep grounding-well method for improving Epcor substation grounding
Dennis Rasmusson, Safety Specialist, AltaLink
•Theory: Equipotential bonding and grounding transmission lines •Case: Working on isolated transmission facilities – Altalink practice
Case: Bonding feeder and substation neutrals – ATCO practice Case: Grounding and telephone interference – U of A findings
8
Course Outline
Part I - Review: basic concepts of power system grounding • Performance grounding versus safety grounding • Performances of networks versus grounding structures
Part II - Grounding and safe work practice • Theory: Equipotential bonding and grounding transmission lines • Case: Working on isolated transmission facilities – Altalink practice • Case: Deep grounding-well method for improving Epcor substation grounding • Theory: Characteristics of GPR as affected by grounding devices
Part III - Grounding performance of power systems • Theory: measurement of grounding resistances • Case: Distribution grounding system assessment and replacement program of Enmax • Case: Bonding feeder and substation neutrals – pros, cons, and ATCO practice • Case: Does improving grounding help to reduce telephone interference?
9
Part I Quick Review of Last Year’s Material
• When performing short-circuit analysis, you encounter If-1ph>If-3ph. What does it mean? If this is a concern, what can you do?
• What is temporary overvoltage (TOV)? What is the impact of grounding on TOV?
• What is GPR and what is the profile or distribution of GPR?
• What is the step voltage?
• Why grounding through a feeder neutral is better than grounding through a temporary grounding rod?
10
1. Introduction
Grounding means connecting a network point (node) to the ground directly or through an impedance. It also means connecting unenergized elements of equipment to ground.
De-energized Transformer: G line
Generator: G
a b Enclosure Line neutral: c N
Load:
11
1. Introduction Why ground?
We classify grounding practices into two broad types:
1. Safety (protective) grounding • Grounding is made primarily for safety reasons • The grounding element is normally unenergized
• Example: trip grounding for workers
2. Performance grounding • Grounding is used to improve power system performance • The grounding element is normally energized • Example: grounding of transformer neutral point • Performance considerations include reducing equipment insulation requirements, improving service reliability, mitigating interference etc.
12
1. Introduction Why ground?
Example of safety (protective) grounding:
Example of performance grounding:
a a b b
c c N
Solidly grounded system Multi-grounded neutral (MGN) system
13
1. Introduction How to ground?
From the system perspective, grounding is just a node connected to ground ( ). In reality, it is realized using ground structures/devices
Sample grounding devices
Mesh (grid) Rod Buried wire Buried plate
Main concerns for grounding devices: Performance issue
• Effectiveness to provide a ground: grounding resistance
• Voltage rise and distribution when a current flows into it Safety issue
Ground potential rise (GPR) Surface potential
14 Ground surface 1. Introduction System performance
Issues of concern for performance grounding: Under perfect balanced system condition, the grounding points have zero voltage, so grounding does not affect normal system operation. It affects a system when the system becomes unbalanced due to faults or loads.
1. Temporary overvoltage (TOV) 2. Fault current 3. Protection 4. Reliability These are the most important concerns affecting the selection of grounding schemes. 5. Power quality Economic issue. 6. Signal interference 7. … 15
1. Introduction Summary
There are, therefore, two aspects on grounding practices
Aspect 1: Network performance consideration Aspect 2: Safety considerations Aspect 1: IEEE C62.92 - Guide for the Application of Neutral Grounding in Electrical Utility Systems Part I – Introduction Part II - Grounding of Synchronous Generator Systems Part III- Generator Auxiliary Systems Part IV- Distribution Part V- Transmission Systems and Subtransmission Systems
Aspect 2: IEEE Std. 80 - Guide for Safety in AC Substation Grounding IEEE Std. 81 - Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System
16 This course mainly deals with safety grounding issues 2. Review – Safety (Protective) Grounding
Worksite Safety Measures:
Barricade - reduce electric contact
Insulation (mat, glove, boots) – reduce current flow to workers
Grounding – reduce hazard duration and GPR
Equipotential zone – reduce voltage differences in the site
May also related to grounding
Each measure shall work independently
17
2. Review – Safety (Protective) Grounding
The hemispherical electrode at the surface of earth
Iground Network Perspective
(grounding resistance)
Safety perspective (GPR)
VGPR
x
18
2. Review – Safety (Protective) Grounding
Grounding resistance (R1 or R2) determines V1 or V2 (i.e. GPR at the grounding spot)
Grounding device However, the distribution of ground potential I depends on the type of electrodes
V1=I*R1 Different type of electrodes V2=I*R2
Similar type of electrodes
19
2. Review – Safety (Protective) Grounding
a) Interfering Electrode
Vtotal
If the electrodes are close to each other, the total grounding resistance
is greater than the parallel of the two electrodes, i.e. Ra ≠ 0 20
2. Review – Safety (Protective) Grounding
Other important concepts:
1. Touch and step voltages 2. Electrical model of human body 3. Human response to electricity
These concepts will be reviewed in more detail in the next presentation
21 3. Review – Performance Grounding
Two key performance concerns:
1. Fault current carrying capability of power equipment
It is desirable for all types of fault currents (1φ, 2φ faults etc.) to be
less than the three-phase fault current. If3φ generally defines the equipment fault current carrying capability. I Index: Current raio = f 1Φ I f 3Φ
2. Over-voltage withstand capability of power equipment
It is desirable that the fault-caused voltage rise is not excessive due to the concerns on equipment insulation cost
Vduring− fault Which is also called Index: Voltage ratio = “earth fault factor” V − faultpre 60Hz-component 22
3.1 Impact of grounding Define performance indices
Impedance Ratio
The degree of grounding of a network point can be characterized approximately using the following impedance ratio K
Z Impedance ratio K = 0 Z1
Look into the system from here
(Z1 & Z0)
This ratio varies with locations in a system
23
3.1 Impact of grounding
Consider cases of R0=R1=0, i.e. Z0&Z1 have reactive parts only:
If K=0 (i.e. Z0=0, this is an unrealistic case): Iratio= 1.5, Vratio=61% (V drop)
If K=1 (i.e. Z0=Z1, ZN=0, fully grounded): Iratio=1.0, Vratio=100%
If K=3 (i.e. Z0=3Z1, boundary case): Iratio=0.6, Vratio=125%
If K=∞ (i.e. Z0 = ∞, ungrounded): Iratio=0.0, Vratio=173%
Conclusions:
1) If and TOV can be changed by changing K, i.e. the degree of grounding
2) Reducing If will always lead to increasing TOV or vice versa. The two indices can not be reduced simultaneously Various grounding schemes are used to achieve a different level of
24 compromise between If and TOV 3.1 Impact of grounding IEEE Definition
Coefficient of grounding (COG)
Vmax toline −−− ground (During fault) V (During fault) V COG = = = ratio V −− linetoline Pre fault)( V Pre fault 3)(3
If COG does not exceed 80%, i.e. the phase-to-ground voltage rise is less than 80% of rated line voltage, the location is called effectively grounded (This is equivalent to less than 138% voltage swell or voltage increase < 38%)
If any location in a particular part of a system satisfies the above condition, that part is called effectively grounded
COG<80% is approximately equivalent to the following condition X R 0 ≤ 3 & 0 ≤ 1 roughly |K|<3 X1 X1 25
3.2 Performance of typical grounding schemes Comparison
Effective Grounding Non-effective Grounding
Ground - Some neutrals Ungrounded Resonant Ground with every - Ground with ground large R neutral small R If Very large Small (arcing ≈ zero 10 ~ 200A large current) TOV Low Low(<125%) High Mild Mild
Line trip Yes Yes No No No (reliability) Fault easy easy hard hard Okay detection Application UHV EHV MV MV MV (≥220kV) [110 ~ 220kV] (industrial)
MGN 26
Equipotential Bonding and Grounding Transmission Lines May, 2013
27 Welcome To Worker Protective
28 Grounding Basics 2 AGENDA 1. Why do we bond and ground? 2. Hazards: • Induction and line energization • Touch and Step potential • Ground Potential Rise (GPR) 3. Methods of grounding • Bracket grounding • Equipotential Bonding and Grounding (EBG)
29 3 1. Why do we bond and ground?
1) To protect linemen and substation workers from harmful voltages and currents that exit on power system
2) Isolating power lines or equipment to work on them is not sufficient to protect workers from harmful voltages and currents
3) Bonds and grounds are applied to reduce voltages and currents to a safe level
30 4 2. The Hazards
31 5 Range of Tolerable Current
Effects of an electric current passing through the vital parts of a human body depend on: • Duration of the current flow, • Magnitude of the current flow, and • Frequency of this current
Ventricular fibrillation = immediate arrest of blood circulation
32 6 Effects of Current Magnitude on the Body
• < 1 mA No sensation • 1 – 8 mA Sensation of shock, but not painful • 8 – 15 mA Painful shock, “let go value” • 15 – 20 mA Painful shock, loss of muscle control • 20 – 50 mA Severe muscle contractions • 50 – 200 mA Heart failure possible • > 200 mA Severe burns and heart failure
IEEE 80 Reference 33 7 Relationship of Electrical Current and Shock Duration
34 8 Sources of Harmful Currents: Primary sources of currents on isolated lines: 1. Accidental energization • Switching error, failed isolation switch, human error • Lightning • Wildlife • Back feed – customer generators, testing • Potential rise on ground grids, neutral or shield wire from a fault on an adjacent circuit.
2. Induction
35 9 Induction • Induction comes from two sources: • Voltage source – capacitive coupling
• Current source – magnetic induction
Together these form Electromagnetic Induction
36 10 Electric Field Induction - first type Electric field from an energized line will charge a conductive object • Adjacent power line • Fence • Vehicle • Ungrounded line hardware • Person
37 11 C1
C2
38 12 39 13 40 14 Magnetic Induction – second type • When there is a current flow in a conductor there will be a magnetic field developed around that conductor • This magnetic field will expand and collapse at the same frequency as the AC power system feeding the conductor • When magnetic lines of force cut a conductor there will be a voltage produced in the isolated conductor Transformer action
41 15 Magnetic Induction (cont’d)
42 16 Magnetic Induction (cont’d)
• Magnetic induction on power lines can be considered an air core transformer • The amount of magnetic induced voltage and current will be directly proportional to the current on the energized line, the separation between the lines and the length of the two parallel lines
43 17 There will be no current flow if the isolated line remains isolated and ungrounded (open circuit)
44 18 If there is only one ground on the secondary of a transformer there will not be any magnetic induced current flow
45 19 46 20 Magnetic Induction (cont’d) • The magnetic induced voltage on a power line will increase as you move away from the portable protective grounds • This is called open-end voltage
47 21 48 22 Magnetic Induction Summary • When you install a 2nd set of personal protective grounds there will be a current flow between the 2 sets of grounds • The amount of current that will flow in this circuit will depend on the current flowing on the energized line, the separation between the lines, the distance between the grounds and the total impedance of the circuit • This includes the impedance of the line and the resistance of the grounds • This circulating current is normally much higher than the steady state current flow from capacitive induction
49 23 50 24 Static Induction – third type
51 25 Hazards of Step & Touch Potentials
• When there is a voltage difference between your hands and your feet, it is called touch potential • When there is a voltage difference between your feet, it is called step potential
52 26 Touch Voltage
53 27 Step Potential
54 28 Step Potential
55 29 Step Potential
56 30 3. Grounding and Bonding • Bracket grounding • Equipotential Grounding and Bonding
57 31 No Grounds Installed
58 32 Equipotential Bonding
But no grounding 59 33 • Trip ground • It is connected with sole purpose of tripping an accidentally energized circuit • Should measure no more than 10 Ω to ground • Can be located anywhere on isolated line
60 34 Equipotential Bonding and Grounding
61 35
Bracket Grounding
Voltage = 80kv phase-to-ground RW = 1000 ohms RP1= RP2 = RP3 = 2200ohms RC1 = RC2 = RC3 = RC4 = 0.01 ohms RJ1 = RJ2 = _ 0.0025 ohms Rr1 = Rr2 = 3 ohms R = R = R = R = R = 7 g1 g2 g3 g4 g562 ohms 36 To mitigate the hazard around the base of the pole: Ⓐ Open the downlead on the structure at the work site OR Ⓑ Use bond mats and an insulated platform, maintain a safe distance away from the area, or enter and exit the area 63 quickly 37
To mitigate the hazard around the base of the pole: Ⓐ Open the downlead on the structure at the work site OR Ⓑ Use bond mats and an insulated platform, maintain a safe distance away from the area, or enter and exit the area 64 quickly 38
Overhead Shield Wire (OHSW) • Include OHSW in EB&G • Ground resistance of trip ground is reduced because multiple parallel down leads
65 39 In a complex grounding situation where human error may increase the likelihood of a hazard being created through an error in applying or removing grounds in wrong sequence: Addition of: • Two bleed grounds will lower hazard of induction and • Grounds should not be more than 1 to 1 1/2 spans from worksite
66 40 Optional protection from induction • Two bleed grounds will lower hazard of induction • Grounds should not be more than 1 to 1 1/2 spans from worksite
67 41 Questions
68 42 Question 1 • What are the two primary hazards safety grounding is addressing?
► Line energization
► Induction
69 Question 2 • The effect of current passing through the body depend on what factors? • Duration of the current flow, • Magnitude of the current flow, and • Frequency of this current
70 Question 3 • What the primary purpose of a trip ground?
► To provide a low ohms circuit to ground to cause the protection to clear the fault as fast as possible.
71 Question 4 • What is the primary purpose of bonds?
► To protect a worker by creating a equipotential zone and limiting the voltage across a workers body.
72 Question 5 • What is bracket grounding and what is it main limitation?
► It placing grounds on all sources of energy and the worker works between the grounds.
► Bracket grounding does not protect the worker from line energization.
► Bracket grounding does trip the circuit and clears the fault.
73 Working on Isolated Transmission Facilities May, 2013
74 AGENDA 1. AltaLink Work Methods: • EBG - Lines and Substations • No Bond Zone • Live Line Methods • Modified No Bond Zone Method 2. Grounding Process • Eliminating human error during grounding
75 2
Why do we bond and ground?
1) To protect linemen and substation workers from harmful voltages and currents that exit on power system 2) Isolating power lines or equipment to work on them is not sufficient to protect workers from harmful voltages and currents 3) Bonds are applied to reduce voltages and currents to a safe level 4) Grounds are applied to result in faster fault clearing
76 3 Working Safely on Isolated Transmission Lines
There are 4 ways that we can safely work on lines: 1. Equipotential Bonding and Grounding 2. No Bond Zone 3. Modified No Bond Zone 4. Live Line Method
77 4 1. Equipotential Bonding and Grounding
Applying Bonding • Equipotential bonding methods must be used when the equipment being worked on can become energized
• Only the application of bonds in a EB&G zone can protect a worker from harmful currents
78 5 Applying Bonds (cont’d): • All conductive paths must be bonded together to form an equipotential zone. To ensure you maintain equipotential zones the phases, neutrals, shield wires, guy wires and steel winch lines etc. must be bonded together.
79 6 Trip Ground Locations • Permanent trip ground structures locations
► Engineered to be used in high fault zones
► Typically have a resistance less than 10Ω • Steel Structures
► Attach a ground to the grounding lug at the bottom of the tower • Concrete Structures
► A downlead runs the length of the structure; this is same for wooden structures • Heath probes must not be used as a trip ground
► Heath probes can be used as a marshalling point for ground chains. However, they must be barricaded because they create serious step and touch potential hazards
80 7 OHSW as a Trip Ground • Generally has a resistance in the range of 3-6Ω in good soils • Downleads (#2 ACSR or larger) must be electrically connected to the 5/16” or larger OHSW • OHSW may be used as trip grounds inside single fault level zones • Only use the OHSW as a trip ground in a double fault zone when there is an engineering study that confirms it can be used safely
81 8
Location for Trip Ground for Lines with Distance Protection
82 9 Bonding Guy Wire and Anchors
• Guy wires are not to be used in tripping circuits
► Preforms could fail under fault conditions • Guy wires are to be bonded into zone if required • Anchors may be use in a tripping circuit if they have been meggered to less than 10 ohms
83 10 Problems With The Placement of Grounds
Substation 1 Substation 2
84 11 85 12 Housekeeping Hazards • Do not coil grounds
Creates a high impedance • Use correct grounds
Must be equal lengths and as short as possible • Secure and place grounds properly
Place out of the way for work to occur
May be tied down but not coiled
86 13 Installing Parallel Grounds • Ensure both sets are of exact length
► Share fault current equally • Install both grounds on one phase before moving to next phase
► When only one ground is on, it is at risk of failure under fault condition
87 14 Mobile equipment without a boom • If a vehicle must be parked in the ground potential rise zone and is not likely to contact the primary:
► Vehicle should not be bonded into the zone
► Workers are still at risk of touch potential but to a lesser degree • Use of a bond mat attached to the vehicle mitigates the touch potential problem
88 15 Mobile Equipment - with an Aerial Device • Insulated boom
► Bond bucket into EB&G
► Do not bond or ground at ground level
► Freely contact truck
• Non-insulated boom ► Bond the bucket (mandatory) ► Bond the chassis ► Maintain safe distance, use mat and platform, or enter/exit quickly
89 16 Protecting People on the Ground General Practices • Apply trip grounds or ground rods away from work site • Install grounds or bonds with an insulated stick • Flag/barrier equipment and work sites in urban areas
90 17 Protecting Workers around Mobile Vehicles • Remove items you need from the vehicle • Use bond mats or insulated platforms • Stay 5 meters (16’ 5”) away from vehicles or equipment that is tied into EB&G zone • To access a bucket truck, either move boom out harms way and remove truck chassis ground, or enter/exit quickly
91 18 Protecting Workers around Mobile Vehicles • To access a truck hoisting a load, either remove grounds and move load, or enter/exit quickly • Disconnect the truck when the truck is no longer needed in EB&G zone • Remove ground-rod end first and then remove ground from truck chassis
92 19 Bond Mats • Bond mats are to be used to bond a person to an EB&G zone • Must not be used as a grounding mat
► Bond mats are not designed for fault current
► Only use a bond mat when there is a trip grounding on the circuit
93 20 Using Bond Mats
• Mitigate step and touch potential • Stand on mat and then connect the mat to equipment with an insulated stick
94 21 Using Bond Mats To step off bond mats, do one of the following: • Use an insulated platform between mat and area outside GPR Zone Or • Move quickly in and out of the area
95 22 Bond mats in parallel
Preferred Method
Connecting Bond Mats
Bond Mats in Series
96 23 Grounding in a substation • Substations are different from lines in two ways:
► Substation ground grid along with all permanent conductive objects in the substation are grounds to the grid. This creates basically an EBG zone
► Insulating gravel and ground grid protects workers on the ground
97 24 Substation Ground Grid
Typical Substation Grid Substation Grid In Poor Soil Conditions
98 25 Substation Ground Grid
Ideal ground grid Practical substation grid
99 26 Touch and Step Potential Hazards
100 27 Typical Grounding in a Substation
Bucket bond is part of the EBG zone for the worker in the bucket
trip ground
Ground the truck is in case boom contacts primary buss
Insulating gravel protects workers on the ground
101 28 Typical Grounding in a Substation
Grounds are required to be isolated from the station equipment for most maintenance equipment tests
102 29 Typical Grounding in a Substation
‘Method A’ has less movement of the ground leads under fault conditions (during a balance fault)
103 30 2. No Bond Zone Method • When it not practical to use EBG method • Often used after a storm when significant amount of conductor is on the ground • A No Bond Zone is defined as a zone where there is an additional separation point in addition to the Guarantee of Isolation (GOI) point and there is NO possible way that section of line can become energized
104 31 No bond zone requirements: • Second set of barriers in addition to ACC GOI isolation points • Conductor must be physically isolated • Bleed ground
► Bleeds off static induction
► Install within sight of the work whenever practical • No induction
► In induction corridors, all parallel circuits must be de- energized
► Line crossings must be near perpendicular to ensure magnitude of induction is not harmful
► Second barrier must be created at the crossing to
protect against accidental energization 105 32 No Bond Zone
106 33 Second barriers at line crossings: ► Install splash ropes when fallen conductor could encroach on MAD
107 34 3. Live Line Method
• The line is isolated and grounded (trip ground) • Workers treat it as a live line and use live line tools and techniques • Assume line voltage to be line nominal voltage rating
108 35 4. Modified No Bond Zone • Is a method that combines elements of no bond zone and live line method • Often used when ‘no bond zone’ cannot be used due to the presence of induction
► The line is isolated with second open points (open spans) [This eliminates re-energization of the line]
► Induction is managed live line techniques at a reduce voltage level (permits the use of Class 4 rubber gloves)
109 36 Grounding Practices Process 1. Is grounding complex or non-complex?
► Complex grounding occurs at more than one work site or involves more than one work crew 2. Create a project grounding plan
► Outlines hazards and mitigations for all sites
► Required for complex grounding only
► Signed by project grounding leader 3. Review the project grounding plan
► Signed by competent second set of eyes
110 37 Grounding Practices Process cont’d 4. Communicate the project grounding plan ► At start-up meeting ► Participants sign attendance sheet 5. Create a site grounding plan ► Outlines electrical hazards and mitigations for one site ► Required for complex and non-complex grounding ► Use Safe Work form in Safety and Health Library ► Signed by site grounding leader
111 38 Grounding Practices Process cont’d
6. Review the site grounding plan
► Signed by competent second set of eyes 7. Communicate the site grounding plan
► At tail-board meeting
► On-site workers sign Safe Work Plan
112 39 Grounding Practices Process cont’d 8. Execute grounding according to the site grounding plan ► Minimum two workers ► Third person as safety observer (optional) ► Before each step, read out and repeat ► If changes required, stop work, revise, communicate 9. Submit all grounding plans for review ► External contractor crews return to AltaLink project manager ► AltaLink crews return to your manager
113 40 Questions
114 41 Question 1 • What are the four methods used by AltaLink to work on isolated transmission lines?
► EBG
► No Bond Zone
► Live Line Methods
► Modified No Bond Zone
115 Question 2 • If the center section of a line is the ideal location for a trip ground, when would you place the trip ground in a substation?
► If you can not find a good low ohms ground location. i.e. in mountains
116 Question 3 • Why would you ground a truck chassis?
► To protect the truck. It does not protect the workers on the ground.
117 Question 4 • How do you protect workers on the ground?
► Keep them away from the GPR zone (ribbon off area)
► Bond mats or insulated platform
► Remove fault current injection point (if possible)
118 Question 5 • What are two primary difference affecting grounding in a substation versus transmission line?
► Substation ground grid – all non energized conductive objects are connected to ground grid. Basically a EGB zone
► Insulating gravel.
119 Deep-ground-well method used for improving the grounding resistance of HV substation grounding system
Alberta Power Industry Consortium (APIC) Grounding Seminar Calgary, May 28th, 2013; Edmonton, May 30th, 2013, Presenter: Nerkez Lalic, P.Eng. Senior Manager Transmission Projects, EPCOR DTI
1 120 1. Introduction Achieving low resistive earth grounding of a substation grounding system (electrode) is primarily in function of: • Resistivity of earth the grounding electrode is placed in • Relative size of the grounding system itself. In most cases, we as engineers have no control over the available size of the substation, and we certainly have no control of the soil / earth conditions at the site.
As such, we need to evaluate the most effective method of achieving low resistive earth grounding of a substation grounding system in order to control Earth Potential Rise / Ground Potential Rise outside substation area.
2 121 2. Earth Potential Rise (EPR) / Ground Potential Rise (GPR) . Earth Potential Rise (EPR) also called Ground Potential Rise (GPR) occurs when a large current flows to earth through grounding system resistance / impendence. . Ground Potential Rise or Earth Potential Rise (as defined by IEEE Standard 80-2000) is the maximum electrical potential that a (substation) grounding grid may reach with reference to a distant grounding point - potential of remote earth. This voltage - GPR, is equal to the maximum grid current times the grid resistance.
3 122 2. Earth Potential Rise (EPR) / Ground Potential Rise (GPR)
. The change in voltage over distance (potential gradient) may be so high that a person could be injured due to the voltage developed between two feet, or between the ground on which the person is standing and a grounded metal object.
. Probably the most commonly noted Ground Potential Rise or Earth Potential Rise event involves the death of cows in a field during a lightning strike.
4 123 2. Earth Potential Rise (EPR) / Ground Potential Rise (GPR)
5 124 2. Earth Potential Rise (EPR) / Ground Potential Rise (GPR) • Transferred potential through any conducting object connected to the substation earth ground is a hazard to people and equipment outside the substation.
• Earth potential rise (EPR) is caused by electrical faults that occur at electrical substations, generating stations, or high-voltage transmission lines.
6 125 2. Earth Potential Rise (EPR) / Ground Potential Rise (GPR)
• The potential rise can cause hazardous voltage, many hundreds meters away from the actual fault location.
7 126 2. Earth Potential Rise (EPR) / Ground
Potential Rise (GPR)
Number of factors determine the level of potential rise, including: . Magnitude of fault current, . Earth type, . Earth moisture, . Ambient and earth temperature, . Underlying rock layers . Clearing time to interrupt a fault.
8 127 2. Earth Potential Rise (EPR) / Ground Potential Rise (GPR)
Earth potential rise is a SAFETY ISSUE.
An EPR event at a site such as an electrical transmission and distribution substation may expose personnel, users, public and properties to dangerous voltages.
9 128 2. Earth Potential Rise (EPR) / Ground Potential Rise (GPR)
10 129 2. Earth Potential Rise (EPR) / Ground
Potential Rise (GPR) Comment on figure “Potential Gradient Area”: • If the potential gradient area, having diameter A-B, is within substation fence dangerous potentials can be controlled by creating equipotential zones, insulating equipment (PPE), and restricted work areas as described below. • If potential gradient area, having diameter A-B, is outside substation fence dangerous potentials are in the public zone and that can be mitigated by improving grounding resistance (impedance). i.e. reducing EPR (Ue) and reducing diameter of potential gradient area to within substation fence. 11 130 3. Step, Touch Potential and Ground Potential Difference (GPD)
• "Step potential" is already discussed and there is no need to repeat. • "Touch potential" is already discussed and there is no need to repeat. • "Ground Potential Difference (GPD)" is a factor calculated when a grid of grounding conductors is installed. GPD potential is the difference between the metallic object connected to the grid, and the potential of the soil within the grid. This can be a problem if equipotential zone is poorly designed and installed.
12 131
4. MITIGATION
The grounding grid is one of the most challenging aspects in design of new and safe operation of in-service substations.
An engineering analysis of the power system under fault conditions can be used to determine whether or not hazardous step and touch voltages will develop.
The result of this analysis can show the need for protective measures and can guide the selection of appropriate precautions.
13 132
4. MITIGATION Several methods may be used to protect employees from hazardous ground-potential gradients:
•The creation of an equipotential zone will protect a worker standing within it from hazardous step and touch potentials. Equipotential zones will not, however, protect employees who are either wholly or partially outside the protected area.
•Bonding conductive objects in the immediate work area can also be used to minimize the potential between the objects and between each object and ground.
14 133 4. MITIGATION •The use of insulating Personal Protective Equipment (PPE), such as rubber gloves, can protect employees handling grounded equipment and conductors from hazardous touch potentials.
•Restricting employees from areas where hazardous step or touch potentials could arise can protect employees not directly involved in the operation being performed.
15 134
4. MITIGATION
•It is common practice to cover the surface with a high- resistivity layer of crushed stone or asphalt. The surface layer provides a high resistance between feet and ground grid and is an effective method to reduce the step and touch potential hazard. •Improve grounding resistance/impedance – by increasing ground grid (substation) size and / or application of low resistive earth grounding, considering that magnitude of fault current is determined with fixed number of amperes. The only variable that can be changed is earth resistance (impedance) of grounding system.
16 135 4. MITIGATION
A well designed grounding grid can eliminate Step and Touch potential hazards regardless of how high the Ground Potential Rise voltage is. Just like how a bird can land on a power line without being electrocuted properly designed equipotential zones inside substation can do the same thing.
17 136 5. Deep well grounding – effective method of improving grounding resistance (impedance):
Background: In the middle of eighties a number of studies were done to determine the most effective method of installing low resistive earth grounding. Various grounding methods and materials were evaluated. The majority of the standard methods were rejected for practicality or cost reasons. New methods of using chemical rods and soil conductivity improvement materials looked promising but left unanswered questions as to environmental impact and liabilities. There is concern about ground water contamination from the chemicals.
18 137 5. Deep well grounding – effective method of improving grounding resistance (impedance):
Based on the studies it was determined that deep driven ground rods would offer the best solution for low resistive earth grounding if full rod contact with surrounding earth could be achieved and maintained. In achieving full rod contact with surrounding earth use of hydrated sodium bentonite of specific electric conductance and sealing characteristics has given excellent results.
19 138 5. Deep well grounding – effective method of improving grounding resistance (impedance):
As substation space is limited, realistically the only remaining way to improve earth resistance and reduce GPR to the acceptable values is to drive deep electrodes. It is not uncommon to see 100-meter (300+ ft) deep electrodes at some sites. The advantages of deep driven electrodes are:
20 139 5. Deep well grounding – effective method of improving grounding resistance (impedance):
• economical to install, • maintain low resistance over time, • maintenance free, • no environmental concerns.
With new technologies a new processes are developed for installing deep driven ground rods. This processes overcomes the problems associated with installing deep ground rods.
21 140 5. Deep well grounding – effective method of improving grounding resistance (impedance):
22 141 5. Deep well grounding – effective method of improving grounding resistance (impedance):
23 142 5. Deep well grounding – effective method of improving grounding resistance (impedance):
Construction of ground well with modern equipment: two 60m deep wells per day
24 143 6. Ground System Design
A good ground system design demands computer modeling that can simulate the effects of an electrical fault on a 3D model of substation, taking into account such factors as conductor spacing and depth, X/R, soil resistivity, human fibrillation currents, ground coverings, etc.
25 144 7. CASE STUDY
EPCOR Poundmaker POD 240/25kV, 3x75MVA substation grounding grid design installation testing and commissioning utilizing deep well grounding (nine wells 60 meters - 200 feet each) to improve substation grounding system resistance
26 145 7. CASE STUDY- Poundmaker substation
Poundmaker, 189St-105Av, Edmonton: Energized in September 2012
27 146 Energized in September 2012
28 147 Title
Substation site, August 2010
29 148 Soil Investigation Report
30 149 Soil Resistivity Test Report
31 150 First excavations: Soil Layers
August 2011 32 151 Grounding Study & Detailed Design The EPCOR Poundmaker substation grounding grid was designed by: CANA High Voltage Ltd #31, 4511 Glenmore Trail SE Calgary, AB T2C 2R9 Phone: 403-451-6408 Fax: 403-247-4729 The soil resistivity test and fall of potential data were used to develop SES - CDEGS Software Package (Current Distribution, Electromagnetic Fields, Grounding and Soil Structure Analysis) model of the substation site. The substation grounding configuration, insulating gravel, seasonal soil models, touch and step voltages were reviewed to evaluate safety at the site.
33 152 Grounding Study & Detailed Design
It was clear that challenging soil electrical characteristics and limited fenced area of substation will require more extensive than usual grounding system.
34 153 Grounding Study – Design Criteria & Results of Safety Analyses
• Fault Level = 15.3kA + 5kA(safety margin) = 20.3kA • Clearing Time = 0.35 sec • Safety Threshold Evaluation = IEEE 80 criteria • Insulating Gravel = or > 5000 Ohm – m • Calculated GPR values were 6,977V in the summer; 7,518V in the spring and 8,026V in the winter • This GPR values exceeds the recommended 3000V limit as in AEUC – Division B, Cl 6-008)
35 154
Grounding Study – Design Criteria & Results of Safety Analyses • For calculated GPR values corresponding ground resistance values are: 0,345 Ohm in the summer; 0,370 Ohm in the spring and 0,395 Ohm in the winter • For AEUC allowed GPR value calculated ground resistance value is 0.147 Ohms • To achieve required safety threshold limits combination of ground grid, ground rods and ground wells were required.
• Calculated well resistance needs to be less than 3.25 Ohm if the well is tested without the rest of the grid in place
36 155 Grounding Study – Soil Model
37 156 Ground Grid Detail Design Model Top View Sketch
38 157 Ground Grid Detail Design Model 3D Sketch
39 158 Ground grid detailed design - layout
40 159 Fall of Potential calculated-expected results Ground Well Testing
41 160 Fall of Potential test results Single Ground Well – Tested May 6, 2013
42 161 Overall Ground Grid Soil Resistance Test Results Tested August 18, 2012
43 162 Substation Ground Grid Resistance Vs Single Grounding Well Resistance Comparison
44 163 Grounding Well Construction Photo
45 164 Grounding Well Construction Photo
46 165 Grounding well construction photo – ground electrode 4/0 Cu conductor + grounding rod
47 166 Questions to you!
48 167 Are you:
• Inspecting and maintaining grounding system at your substations? • When required, improving resistance of substations grounding system ? • Controlling GPR in public areas outside fence of your substations? • Having experience in installing deep grounding wells on your substations ?
49 168 ALBERTA Electrical Utility Code, 3rd Edition 2007: Section 12, Clause 7.7 Maintenance of Grounding System: “Grounding system shall be periodically tested for resistance and periodically inspected and maintained to ensure that the grounding system comply with the requirements of this Code”
50 169 References:
. Paper: DEEP EARTH GROUNDING vs SHALLOW EARTH GROUNDING by Martin D. Conroy and Paul G. Richard, Computer Power Corporation, Omaha, Nebraska
. Westinghouse: Electrical Transmission and Distribution Reference Book
. IEEE- 80, Guide for Safety in AC Substation Grounding
. IEEE – 81, Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System
. IEEE – 81.2, Guide for Measurement of Impendance and Safety Characteristics of Large, Extended or Interconnected Grounding System
. IEEE – 367, Recommended Practice for Determining the Electric Power Station Ground Potential Rise and Induced Voltage From Power Fault
.AEUC – Alberta Electrical Utility Code
. Fluke 1625 and Megger DET-2-2 tester’s manuals
. CANA – HTI : EPCOR Poundmaker Substation Grounding Study Report
51 170
Thank you !
52 171 Case Study
Characteristics of GPR as Affected by Grounding Structures
by Wilsun Xu University of Alberta May 2013
1 University of Alberta Problems to clarify
1. What are the roles of each grounding element in a substation? • Grounding mesh, • Ground rod, and • Gravel
2. What are the true benefits of grounding a worksite?
• Reduce ground potential rise? • Shorten the duration of energization?
3. Exercise and discussion: analyzing a portable grid 1. Substation grounding grid
Substation grounding grid consists of three components: mesh, rod and gravel.
Substation Mesh Rod Grounding grid
GPR (surface potential) Gravel (insulating layer) Vtouch
Vstep
Max surface potential Case C Case B (lower step V, high GPR) (higher step V, lower GPR)
What are the roles played by the mesh and the rod structures? 1. Substation grounding grid
Three cases are used to find the role of each element:
1. “Mesh+Rod”, which corresponds to the actual substation grid 2. “Mesh Only”, which corresponds to a mesh (horizontal) structure 3. “Rod Only”, a hypothetical case corresponding to a vertical rod structure
Zsystem Vs
Rg
The following factors are also studied:
1) The depth of the structure 2) The soil resistivity 1. Substation grounding grid Comparing single vertical and horizontal rods
100 t=0m Z t=0.5m 90 Y t=1m Vertical Rod t=1.5m 80 t=2m Vx (x,0,0) X 70 t t=0m 60
(0,0,z) dz 50 t=0.5m
(0,0,-L/2-t) 40 t=1m
L Voltage Potential t=1.5m 30 t=2m
20 d 10
0 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 Distance [m] Z 100 t=0.01m Y t=0.5m 90 X Vx (x,0,0) t=1m t=1.5m 80 x Horizontal Rod t=2m t 70 t=0.01m 60
50 t=0.5m (0,0,-t) 40 t=1.0m Voltage Protential t=1.5m L/2 30 L 20
10 t=2m
0 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 Distance [m]
1) GPR profiles are comparable, 2) close to surface will result in higher GPR and Vstep 1. Substation grounding grid Compare grounding structures
50 Mesh&Rod 48 Mesh Ground potential distributions Rod due to different structures 46 44
42
40 Main conclusions: 38 Surface Potential [V] 36 Depth=1.0m 1) The difference among the 34
3 structures is small 32
30 2) They shall be buried deep -60 -40 -20 0 20 40 60 Length [m] to achieve better performance
3) Mesh and rod structures 50 Mesh&Rod 48 Mesh interfere with each other a lot Rod 46
44 I=100A 42
ρ=100Ω∙m 40
Grid size: 100mx100m, 38
Mesh size=10x10m Surface Potential [V] 36 Depth=0.1m Rod size:11x11, L_rod=5m 34 Conductor sizes d=19.1mm 32
30 -60 -40 -20 0 20 40 60 Length [m] 1. Substation grounding grid Impact of soil
100 Mesh&Rod Impact of soil resistivity Mesh 90 Rod 80 Main conclusions: 70 60 Rod helps the grounding grid 50 Uniform soil resistivity
to access low resistivity soil, 40
• Flatten the GPR profile Surface Potential [V] 30 ρ=200Ω∙m
• Lower the GPR due to 20 smaller grounding R 10
0 -60 -40 -20 0 20 40 60 Length [m]
100 Mesh&Rod Mesh 90 Rod I=100A 80 Two layers of resistivity Grid size: 100mx100m, 70 Mesh size=10x10m 60 Top layer: Depth=2 meter, ρ=200Ω∙m Rod size:11x11, L_rod=5m 50 Second layer: ρ=20Ω∙m Conductor sizes d=19.1mm 40 Structure depth=0.5m Surface Potential [V] 30 20
10
0 -60 -40 -20 0 20 40 60 Length [m] 1. Substation grounding grid Lay mesh on surface
60 Mesh laid on surface Mesh&Rod Mesh Rod 55 Depth=0.5m Uniform soil resistivity Main conclusions: 50
Bring the structures 45 (mesh, rod or combined)
Surface Potential [V] 40 to surface will lead to higher step voltages & GPR 35
30 -60 -40 -20 0 20 40 60 Length [m]
60 Mesh Rod Mesh&Rod I=100A 55 ρ=100Ω∙m Grid size: 100mx100m, 50
Mesh size=10x10m 45 Rod size:11x11, L_rod=5m 40 Conductor sizes d=19.1mm Surface Potential [V] Depth~0m Structure depth=0.5m 35 Top thin layer has high resistivity to represent surface 30 -60 -40 -20 0 20 40 60 Length [m] 1. Substation grounding grid Summary of findings
Main findings: The vertical (rod) and horizontal (mesh) structures are almost equally effective. However, the rod structure can reach deep soil with lower resistivity, leading to more significant reduction on GPR and step voltages;
The depth of grounding structure has a significant impact on the surface potential, in the form of GPR and step voltage. If the structure is closer to the surface, higher GPR and step voltage will result;
The vertical (rod) and horizontal (mesh) structures interfere with each other heavily. Combined use of the two structures does not double the performance. They act more like backups to each other; 2. The benefits of grounding a structure
If a working object is grounded through Rg, can the touch voltage be lowered?
ZsystemP=R+jX h a s e L in e Phase Line
25kV N e u tr a l Neutral If 3
V Additional touch grounding V V to u c h X touch X R I mat I Rg Fmat Rg Frod Rg V 50Ω V s te p S tif fle g s step 15Ω
(a) Ungrounded scheme (b) Grounding to temporary rod CaseU 1 n g r o u n d GroundingCase to Temp. 2 Rod Phase Line Phase Line Neutral Neutral This is equivalent to asking: can we lower the ground potential at point X?
V touch Vtouch
Rg V Rg V 15Ω step 15Ω step
(c) Grounding to Perm. to system Rod rod (d) GroundingGrounding to system to Neutral neutral 2. The benefits of grounding a structure
Zsystem=R+jX 25kV If X 3 Zsystem Vsys Additional E E grounding Rmat Rg Vmat Rmat IFmat IFrod Rg Vmat
The supply voltage E is divided between Vsys and Vmat. We want to lower Vmat by using Rg
Zsys=1.5 ohm Rmat=10 ~ 200 ohm, Rg=5 ~ 30 ohm, Rmat//Rg= 4 ~ 30 ohm
One can easily see that most of the supply voltage E will be “consumed” by Vmat. So Vmat≈E and it cannot be lowered significantly with Rg.
There is a larger fault current since the total circuit Z is reduced with Rg;
Some of the current originally going through Rmat could be diverted to Rg 2. The benefits of grounding a structure
P h a s e L in e Phase Line
N e u tr a l Neutral X Zsystem E Rg V V to u c h touch X
Rg Rg V 50Ω V s te p S tif fle g s step 15Ω
(a) Ungrounded scheme (b) Grounding to temporary rod U n g r o u n d Grounding to Temp. Rod Phase Line Phase Line Neutral Neutral
Similarly, the voltage at point X cannot be lowered significantly since the
V system impedance is generally much smaller than the grounding resistance touch Vtouch
Rg V Rg V 15Ω step Cases15Ω ofstep very small Rg may exist if the grounding is created through a neutral or shield wire. Also, the substation ground has very small Rg (c) Grounding to Perm. to system Rod rod (d) GroundingGrounding to system to Neutral neutral 2. The benefits of grounding a structure
Main findings: Grounding does not guarantee a significant reduction on the GPR, since the grounding resistance is often higher than the system impedance. A large portion of the system voltage will impose on the grounding resistance; The energizing source behaves as a voltage source.
Grounding can help to reduce GPR if the grounding resistance approaches the level of system impedance, examples are ground to system neutral or substation; The energizing source behaves as a current source.
Grounding, however, can result in a larger fault current, leading to fast fault clearing and reduced GPR duration;
Grounding can divert some fault currents from a structure, making the structure experience reduced fault current; 3. Exercise & discussion: portable grid
Like the substation grid, a portable grid (mat) is used to create an equipotential zone.
Cable for trip grounding Portable grid Vtouch (a separate practice)
Vstep
Bonding cable
Requirement on portable grid: Vtouch V touch safety limit () Duration Vstep V step safety limit () Duration
Discussion items: Q1: Will grounding connection lower the touch and step voltages? Q2: Are we likely encounter unacceptable touch and step voltages using the mesh?
3. Exercise & discussion: portable grid Analyze Q2
Ideal case
Ideal grid Cable for trip grounding Vtouch (Metal plate) (a separate practice)
Vstep
Bonding cable
Actual case
Vtouch
Vstep
1.5 meters (a). Two feet stand on ground surface (b). One foot stands on ground surface (Touch potential concern). (Touch or step potential concern).
3. Exercise & discussion: portable grid Analyze Q2
Condition: Vs=14.4kV, If=8kA, Overall grid 1.4mX1.4m, mesh size 0.2m, rod length 0.5m
Main findings: • The mesh structure works well when buried deep inside soil But it cannot perform when laid on ground surface • Rods are needed to “flatten” the surface potential 3. Exercise & discussion: portable grid Q3
Compare two other work scenarios
Grounding rod Mat Grounding rod Conductors
1m 1m
(a) With mesh-conductor-based mat (b) Without mesh-conductor-based mat (Vstep=7.7 kV) (Vstep= 952V)
Question 3:
If the grid is covered by a layer of (insulating) fabric, Should the fabric layer be placed on top or bottom?
Fabric on top Fabric on bottom 3. Exercise & discussion: portable grid Analyze Q3
Fabric layer on top
Rbody Zsystem R E fabric Equal-
potential Rg Increases the body resistance, helps to zone reduce body current. Useful to improve safety
Fabric layer on bottom
IF IF
IF IF
The bottom insulation layer will concentrate IF current to the weakest spot to the ground. As result, having an bottom insulation layer is not helpful. Theory
Measurement of Grounding Conditions
by Wilsun Xu University of Alberta May 2013
190 University of Alberta Outline
• Measurement of grounding resistance
• Measurement of soil resistivity
• Measurement of touch and step voltages
• Factors affecting grounding resistance and GPR
• Online monitoring of substation grounding grid
191
1. Measurement of grounding resistance
V & I Earth surface V RR = g I Temporary rod
Main challenges
1. How to determine V, a voltage referred to remote earth? 2. The current I must pass through a remote point to be valid
192 Invalid I Valid I 1. Measurement of grounding resistance
Additional challenge for substation Rg measurement
Neutral and shield wires can affect the measurement results
Impact of neutral and shield wires
193
1. Measurement of grounding resistance Basic method
“Fall-of-Potential” method (for all grounding structures)
V For substation grid: Distance
~61.8% of XE-C XEC > 1.5~5 times of the diameter of the grid Surface potential
194
1. Measurement of grounding resistance Other methods
Direct measurement by simulating a fault condition
• Using a transmission line as a current injection line • Measure substation voltage to a remote ground
195
1. Measurement of grounding resistance Other methods
Potential difference method
Voltage sensors
Potential difference
Potential
Potential Use multiple potential difference difference data to estimate this curve
Distance 196
1. Measurement of grounding resistance Other methods
Practical methods
a) Measure Rg of MGN neutral
b) Use other structure as the remote ground
197
1. Measurement of grounding resistance ATCO results
Statistics of grounding resistances of permanent grounding structures
Histogram Measurement events Rg
Cumulative distribution
0.8 means 80% % % Measurement events
198 Rg 9 2. Measurement of soil resistivity Wenner method
I source
V 1 meter 2
d d d
Total potential (V1+V2)
199
3. Measurement of step/touch voltages
Step voltage sensor
1) Up to 100A, several hours, dedicated source 2) Several kA, 0.1 to 0.2 sec, short circuit
IB RB RB IB
RF RF RF RF
Touch voltage sensor Step voltage sensor
200
4. Factors affecting Rg Factors affecting Rg
1. Characteristics of the soil
2. Moisture and salt content
3. Temperature
4. Seasonal change
201
5. On-line monitoring technique
1) Active current injection 2) Step/touch sensor network
202 3) Trend monitoring 6. Summary
• Grounding condition measurement is still difficult to perform, due to 1) the need for multiple independent electrodes, 2) the impact of various natural factors
• The existing measurement methods just provide a snapshot of the grounding condition. Interpretation of the grounding performance under other conditions is needed
• On-line, continuous monitoring approaches seem to be the future for ground condition monitoring
203
Distribution Grounding System Program – Assessment and Replacement
Simon Chan Joseph Kuffar
204 Outline
Background Drivers Ground Testing Program Grounding Replacement Program
205 Background
In 2004, UMS Group reviewed EPC Proactive Asset Replacement Program. Study compared EPC to North American utility industry as well as global best practices. Recommended EPC to initiate a Ground Integrity Testing program
206 Background..
Practice of the time….. Initial Installation test Maintenance test – Proactive – In conjunction with Pole Testing and Treatment Program (O/H system only) – Reactive – abnormal report (both O/H and U/G) Grounding replacement – Reactive replacement - abnormal report – Pole replacement program Paper records
207 Drivers
Equipment Protection To provides a low resistance path ground as well as discharge path for lightning energy To allow proper operation of protective equipment during the fault Personnel Safety To Maintains equipment and other grounded structures at the potential of earth To Minimize the risks of step and touch potential Regulatory compliance
208 Drivers..
Regulatory Requirements: . the 2003 Alberta Electric Utilities Act (Section 105 (1)): – The owner of an electric distribution system has the following duties: – “(c) to operate and maintain the electric distribution system in a safe and reliable manner”.
. the 2007 Alberta Electrical and Utility Code Section 12 Grounding : Clause 7.6 Corrosion of Grounding System (2) If the cross section area or mass of the grounding system equipment has been reduced by corrosion to less than 80% of the amount required by this Code the equipment shall be replaced. – Clause 7.7 Maintenance of Grounding System Grounding systems shall be periodically tested for resistance and periodically inspected and maintained to ensure that the grounding systems comply with the requirements of this Code.
209 Drivers…
CSA – C22.3 No.1 Overhead System 9.1.2.1 Multi-grounded Systems Where a single electrode resistance exceeds 25 ohms, up to two additional electrodes connected in parallel or up to two deep-driven electrodes shall be used unless it is clear that additional electrodes will not significantly reduce the resistance.
210 2006 Grounding Testing Program
EPC initiated a 3 year grounding test program Work performed by consultant Purpose – Establish an accurate overall ground rod condition for both O/H and U/G system – Create a centralized database for record keeping – Implement a structured maintenance program
211 Fall 2006 Testing
Tested the grounding systems for 39 distribution feeders (randomly selected). Sample selection as per ANSI/ASQ Z1.4 Standard Test limited to O/H and U/G dead-front equipment Pass/Failure Value of 25 ohms was used Started late Sept 2006 and completed Nov 2006 Data captured and stored in CMMS
212 Fall 2006 Testing - Tool
Ground Tester (AEMC 3731)
213 Fall 2006 Testing - Results
1099 of 7351 Distribution Ground Rods Tested 332 Failed (30%) 30% Pass/Fail Criteria – 17 Feeders failed Most failures were on old installations - 20 years plus
214 Fall 2006 Testing - Results ..
Questions 1. What is our typical Soil Condition? 2. How bad (severity of Deterioration)? 3. Should we change the approach? 4. What is the mode of failure (connectors or rods)? 5. Should we established a pass/fail criteria based on the actual soil condition?
215 Fall 2006 Testing -Recommendation
Collect Soil Conditions/Resistivity Data with each ground rod resistance measurement Determine the mode of failure - field Verification Test the remaining ground rods on feeders that failed
216 Outcome
Revised approach 2007 -2008 Testing based on age Work issued by city section Test area selected covered most areas of the city Measurements included Soil resistivity and grounding resistance Test sites selected as per ANSI/ASQ Z1.4 Standard
217 Soil Resistivity Measurement
Wenner’s Method Tool -Fluke 1625 GEO Earth Ground Tester
218 2007-2008 Results
Soil in Calgary area generally has low resistivity. Certain areas have Corrosive soil condition A single ground rod can achieve a ground resistance of 25 ohms or less Estimated 25% of sites have deteriorated beyond the limit set in the AEUC Systems installed prior to 1990 are particularly in poor condition. Replacement of all existing deficient ground systems could be over $30 Million.
219 2007-2008 Results -Key Understanding
- Understand typical soil conditions in Calgary - Identify areas with corrosive soil - Establish a pass/failure based on soil condition - Project the level of deterioration for field verification - Prioritize the replacement program
220 2007-2008 Results
2006-2008 Sampling Test Results 70%
60%
50%
40%
30% Rate Failure 20%
10%
0% Unknown 1950's 1960's 1970's 1980's 1990's 2000's Vintage
221 Field Trial 2009-2011
Objectives: – Small scale project to assess and determine the course of addressing the entire EPC grounding system. – Further refine the number of deficient sites – Assess the replacement costs per site – Verify the projected level of deterioration – Identify any resource or other concerns likely to occur in a full scale replacement program
222 Field trials – Projected deterioration
Calculated grounding resistance and projected levels of deterioration based measured soil resistivity
% Length Electrode Soil Rod Calculated Length (ft) Resistivity Diameter Resistance (Ohm-m) Value (single rod)
10% Length 8 47 0.75 143
20% Length 8 47 0.75 82
30% Length 8 47 0.75 59
40% Length 8 47 0.75 47
50% Length 8 47 0.75 39
60% Length 8 47 0.75 33
70% Length 8 47 0.75 29
80% Length 8 47 0.75 26
100% 8 47 0.75 21 Length
223 Field Trial - Results
Field Verification Showed more deterioration than initially projected No issues with the connector Most Ground rod penciled at approx 4ft below ground
224 Results- Field Trial …
225 Grounding Replacement Program
In 2012, ENMAX Initiated grounding replacement program. – Targeting areas with high failure rate – Priority given to areas with UJKT Cables – Installation based on current standard – Hydrovac excavation
226 Overhead Grounding Standard
227 Padmount Grounding Standard
TOP VIEW 228 Padmount Grounding Standard
FRONT VIEW
229 Current Practice..
Current Maintenance practice Initial Installation test Maintenance test – O/H- In conjunction with Pole Testing and Treatment Program (10-year Cycle) – UG – in conjunction with Line inspection Maintenance record captured in CMMS system
230 Current Practice….
Replacement Upgrade the grounding when – Section of cable is replaced – Old equipments are replaced – High resistance grounds are identified – Other system upgrades program Sections with high failure rate are targeted for proactive replacement program
231 Challenges
Equipments on Private Property (backyard…) Equipment in less accessible areas Equipment on paved lanes Easement Encroachment - fences, garages & etc Resources Customer Complaints
232
233
234
235 Reference
Alberta Electrical Utility Code, 3rd Edition 2007 CSA – C22.3 No.1 Overhead System ANSI/ASQ Z1.4 Standard Fluke 1625 User manual
236 Questions
237 Theory & Case Study
Connecting Substation and Feeder Neutrals: Pros, Cons and ATCO Practice
by Wilsun Xu University of Alberta May 2013
238 1 University of Alberta 1. The issue of concern
Equivalent circuit of Upstream ends Substation
138 kV 25 kV Distribution side Customer side Transmission side
///
MGN
Should one connect the substation neutral to the feeder neutral?
Q1: If connecting the neutrals, the substation GPR may transfer to feeder neutral. How bad can it be?
Q2: If not connecting the neutrals, what are the negative consequences?
239 2. GPR transfer from substation to feeder Fault scenarios to consider
Distribution Substation
Distribution side-25 kV Transmission fault MGN
Distribution fault
GPRT − fault = sub IR −Tf
GPRD− fault = sub IR −Df
Neutral If Neutral If If If Grounding grid Grounding grid
240 Outside sub Inside sub 2. GPR transfer from substation to feeder Method to estimate
Substation GPR: Propagation of GPR to outside: A B C Substation
Z’geq N Neutral
IN Ineutral Zn X Z X Ig n VN VN Rsub
Z' Z' GPR V == geq V = geq GPR GPRsubstation N ≈= IRV faultsub neutral−max X N substation n + ZZ 'geq n + ZZ 'geq
Ratio of GPR transfer:
Z'geq k = GPRneutral−max / GPRsubstation = n + ZZ 'geq
241 2. GPR transfer from substation to feeder Sample results
16
14
12 Z’geq 10 ZN ZN ZN 8
6 Z’geq Zgn Zgn Zgn
Equivlent imped. [ohm] 4
2
0 0 0.5 1 1.5 2 Neutral length [km]
S=50m S=100m (base case) S=250m S=500m 1
0.9 K [ / ] 0.8
0.7 7 15( base case) 30 Grounding resisatnce [Ω] Ratio of GPR transfer 242 2. GPR transfer from substation to feeder Sample results
Observation GPR transfer Max NPR Corresponding system ratio k per kA condition (V/kA)
High end value 0.95 129 Rgn 30 S, =Ω= 50 m
Typical value 0.91 124 Rgn 15 =Ω= 1S, 00 m
Low end value 0.76 108 Rgn 7 S, =Ω= 500 m
NPR – neutral potential rise = GPRneutral
243 2. GPR transfer from substation to feeder NPR at customer location
Neutral voltage rise (NPR) at other points
Customer #1 Customer #2 NPR NPRmax NPR 2 N Z Zn Zn Zn Znnn Zn
GPR Rgn Rgn Rgn Rgn Rgn
NPR =k ×NPR NPR1 =NPRmax =k×GPR NPR21 =k ×NPR 1 ….. i+1 i i
n NPRn =k ×GPR
Corresponding Max NPR NPR per kA at 2 NPR per kA at 5 km system condition per kA km (V/kA) (V/kA)
Rgn 30 S, =Ω= 50 m 129 24 3.4
Rgn 15 =Ω= 1S, 00 m 124 22 3.2
Rgn 7 S, =Ω= 500 m 108 46.4 12
244 3. ATCO Practice Decide if two neutrals shall be connected
Ground potential
Substation neutral
First grounding point outside fence (neutral connection point)
600V threshold
Hazard zone Should not happen in public area
i.e. if it happens in the public area, No. of grounding points Neutrals shall not be connected from substation
245 3. ATCO Practice
Why use 600V as the threshold?
V0 0.116 Ibody ≤ Step Voltage ts
0.116 Vstep <×1000 V0 ts 0.5m
V0 is the NPR IEEE Std.80 (t=0.5s) Simplified (t=0.5s) 50 kg 726.0 V 453.8 V 70 kg 982.6 V 614.1 V
Rod=1.5m
246 3. ATCO Practice
O/H Does the O/H line have Next Slide a neutral leaving the substation? No
Concern Is the feeder O/H or U/G?
U/G Is there a M.G.N on the riser pole?
Please refer to Is the pole located in an isolation manual area frequently travelled by the public?
Connection from the concentric neutral to the substation ground is approved
247 3. ATCO Practice
Calculated by Excel
Are the first 6 grounding points Please refer to isolation manual YES (Ground Rods, Pull Boxes, etc.) …. located in areas frequently travelled by the public?
Connection from the concentric neutral to the substation ground is approved
User Input Data
Enter your fault level (amps): 500000 Enter your sub ground resistance: 0.15 Select Cable Leaving Substation: 500 MCM Select System Neutral or U/G system Cable 1/0
248 3. ATCO Practice
Calculation of neutral voltage rise at every neutral point. The NPR shall be < 600V
k - The maximum ratio of NPR to GPR PR = 1500 Ground Pt. k1 0.98355496 1 NPR1 = 1475 1 k2 0.97131637 2 NPR2 = 1457 2 k3 0.94345550 3 NPR3 = 1415 3
k4 0.89010828 4 NPR4 = 1335 4 k5 0.79229275 5 NPR5 = 1188 5 k6 0.62772780 6 NPR6 = 942 6 k7 0.39404219 7 NPR7 = 591 7 k8 0.15526925 8 NPR8 = 233 8 K9 0.02410854 36 9 K10 0.00058122 1 10 K11 0.00000034 0 11 K12 0.00000000 0 12 K13 0.00000000 Calculation for K1 0 13 K14 0.00000000 0 14 U/G Cable Impedance per meter Z equivalent Distance from Sub to Riser or Pull Box Impedance of Neutral K1 #1 AL 0.00066380 6 300 0.1991400 0.967876189 350 MCM 0.00046000 0.1380000 0.977517107 500 MCM 0.00033440 0.1003200 0.983554961 750 MCM 0.00022000 0.0660000 0.989119683 1/0 0.00063000 0.1890000 0.969461949 266.8 0.00035800 0.1074000 0.982414776 477 0.00029270 0.0878100 0.985576094
249 4. Not connecting the neutrals: negative consequence
I
I
Neutral V = Neutral GPR |GPR| Islanded neutral
Net GPR profile
GPRX= I N Z total
Will the GPR close to the first pole become unacceptable if the neutral is not connected?
250 4. Not connecting the neutrals: negative consequence
a) Fault current IF causes induced voltage en at each grounding interval:
IF Phase-neutral Mutual (coupling) Z X en znn en znn en znn F znn znn znn Y + - + - + -
Rgn Rgn Rgn Rgn Rgn Rgn Rgn ezn= mn × I F Induced V
b) Each induced voltage en can be converted into a current source IN:
IN IN IN zmn X znn znn znn F znn znn znn Y IINF= znn
Rgn Rgn Rgn Rgn Rgn Rgn Rgn Self Z of the neutral
251 4. Not connecting the neutrals: negative consequence
c) The current sources can be merged into one.
zmn IINF= znn
X zn n zn n zn n F z nn z nn zn n Y
R gn R gn R gn R gn R gn R gn R gn
d) The series current source can be further represented using two shunt sources
V NX zn n zn n zn n V NF zn n zn n zn n Y
IN IN R gn R g n Rg n R g n R g n R g n R g n A B
This model makes it much easier to analyze the GPR case
252 4. Not connecting the neutrals: negative consequence
e) The voltage profile along the neutral can be established using superposition
V NX zn n zn n zn n V NF zn n zn n zn n Y
IN IN R gn R g n Rg n R g n R g n R g n R g n A B
ZtotalA ZtotalB-up ZtotalB-down
Parallel Zone
VNX= IZ N totalA
Caused by source A Neutral V
Caused by source B VNF= I N (Z totalB-up //Z totalB-down )≈ 0.5IN Z totalA
253 4. Not connecting the neutrals: negative consequence
IF
X en znn en znn en znn F znn znn znn Y + - + - + -
Rgn Rgn Rgn Rgn Rgn Rgn Rgn
Parallel Zone
Caused by source A Neutral V 2km (neutral) Caused by 1km (shield) source B
Net GPR profile Neutral V Magnitude
254 X F 4. Not connecting the neutrals: negative consequence
V NX zn n zn n zn n V NF zn n zn n zn n Y
IN IN R gn R g n Rg n R g n R g n R g n R g n A B
ZtotalA ZtotalB-up ZtotalB-down
V NX Z≈ ZR IN ZtotalA totalA nn gn A
zmn GPRmax = GPRat-X = z nn .R gn ×= IF ZItransfer F znn
Typical value of Ztransfer for Alberta distribution line is about 0.34 ohm. For example if a fault current is 1kA, the maximum GPR is 340 V.
255 4. Not connecting the neutrals: negative consequence If neutrals are connected:
Observation GPR transfer Max NPR Corresponding system ratio k per kA condition (V/kA)
High end value 0.95 129 Rgn 30 S, =Ω= 50 m
Typical value 0.91 124 Rgn 15 =Ω= 1S, 00 m
Low end value 0.76 108 Rgn 7 S, =Ω= 500 m
GPRmax=0.124IF
If neutrals are not connected:
There may be a concern GPR max =ZItransfer F = 0.34 IF (Note that the IF’s are different)
Summary: more investigations are needed to find the best compromise
256 Case Study
Does improving grounding help to reduce telephone interference ?
by Wilsun Xu University of Alberta May 2013
257 1 University of Alberta 1. A telephone interference problem
East Industry 12E IT numbers shown here Sub. 11SU are probe-wire IT 21SU 12SU
Telephone Line IT = 1000 (Dec. 2005) IT = 1800 (March 2006) IT = 2300 (Sept. 2009) IT = 3500 (Nov.19th 2010) IT = 500 (Nov. 29th 2010) Summerside ACCEPTABLE IT LEVEL Sub.
Telephone Cabinet 41 Ave. 75 St. 91 St. 66 St. 17 St. 127 St. 101 St. IT = 5000 (Nov. 29th 2010) NOT ACCEPTABLE IT LEVEL
258 1. A telephone interference problem
The 9th harmonic voltage is the main contributor (around 70%) to telephone noise.
259 1. A telephone interference problem
Source of telephone interference East Industry 12E Sub. 21SU Telephone Line 12E
21SU Summerside Sub.
Telephone Cabinet 41 Ave. 75 St. 127 St. 66 St. 17 St. 91 St. 101 St.
Parallel zone of interference 260 2. Basics of telephone interference
B Power conductors
A C
Neutral (N)
M-field produced Total M-field by N
Case 1: no neutral, Iabc in positive sequence M-field produced
Case 2: no neutral, Iabc in zero sequence by A, B & C
Case 2: with neutral, Iabc in zero sequence
261 2. Basics of telephone interference
B C Phase conductors A Power conductors A B Neutral (N) C Neutral N
Telephone cable sheath S Core (T) T Phone conductors ∆V Telephone cable core Sheath (S) A
Transformer analogy T
T TT T +=∆ TAIZIZV A
T TA A TB B TC C TN N TS S +++++=∆ TT IZIZIZIZIZIZV T Self Z Mutual Z 262 2. Basics of telephone interference
Phase conductors A Impact of B ∆= power current C VT ZI TT T +()ZI ++ ZI ZI Neutral N TA A TB B TC C
− ()ZITN N Telephone cable sheath S − ()ZITS S Impact of T Telephone cable core neutral current ∆VT Impact of sheath current Power influence on telephone:
T − power ( TA A TB B TC C −++=∆ TN IZIZIZIZV N )()
≈ZTA( I A ++ I B I C )( − ZI TN N ) Harmonics dominated by zero sequence =ZI − ZI TA0 TN N component: ≈−ZITA()0 I N 3, 9, 15
Neutral current reduces Zero sequence current interference causes interference
Ideas to reduce telephone interference: reducing I0, increasing IN to I0. The same concept is applicable to the analysis of induced voltages on pipelines 263 3. Factors Effecting Telephone Interference Level a) Bad Grounding Rods
1) The rods connecting the neutral to ground are subject to corrosion (i.e., the neutral grounding resistance increases). 2) To determine the impact of above on telephone interference, the rods along the neutral circuit in parallel with the telephone line are gradually removed 3) Results show bad grounding rods do not affect the induced voltage. voltage (V) voltage Telephone line total induced
Poor grounding (percentage of telephone line) 264 3. Factors Effecting Telephone Interference Level a) Bad Grounding Rods
1) Neutral current due to load imbalance
Phone line
Load
Substation Neutral IN N 3I0
Rgl
IN Conducted current Increased grounding resistance
Distance
The return load current, IN, is bypassed by the grounding rods, When it reaches the parallel zone, its magnitude has become
very small so IN does not help to reduce telephone interference. Improved grounding is actually not good in this case. 265 3. Factors Effecting Telephone Interference Level a) Bad Grounding Rods
2) Neutral current due to induction
Phone line
Load Substation + – + – + – + – IN + – + – + – N 3I0 Neutral Rgl
Loop current I I1 I2 x Voltage induced by phase currents
Since I1=I2=..=Ix due to similarities among the circuit segments, The currents entering the ground (through the rods) are almost zero in the parallel zone, so changing the grounding resistance of the rods has no impact on the neutral current, i.e. telephone interference.
Applicable for long neutral
266 3. Factors Effecting Telephone Interference Level a) Bad Grounding Rods
Summerside 21SU Feeder Sub.
Location 4 Location 3 Location 1 Location 2 Telephone Line
Neutral current due to loads In the parallel zone, the has “disappeared” when it reaches these points neutral only contains induced current
267 3. Factors Effecting Telephone Interference Level b) Broken Neutral
• The broken neutral causes a decrease of the neutral current close to the broken point, which, in turn, increases the telephone inferences: Neutral Broken
In In In In In
In Neutral Current Profile
Summerside Impact of Broken neutral on the Induced 9th Harmonic Voltage 21SU Feeder 60% Sub. 9.5 8.5 27% 22% 7.5 8% 6.5 5.5 4.5 3.5 Voltage (V) Voltage Location 4 2.5 Location 3 1.5 0.5 Location 1 -0.5 Base Case Broken at Broken at Broken at Broken at Location 2 (No Broken) Location 1 Location 2 Location 3 Location 4 Cases Telephone Line
Broken neutral has a significant impact on telephone interference level. However, if the broken point is 1.5km or more away from the telephone line, the negative impact is negligible.
268 3. Factors Effecting Telephone Interference Level c) Load balance
Load balancing does not affect the flow of 3rd, 9th and 15th harmonic currents significantly, which are dominated by the zero sequence component
Since the telephone interference is mainly caused by these harmonics, load balancing is not very effective to reduce telephone interference
Load balance can reduce the impact of 11th and 13th harmonics, which are not a major contributor to telephone interference (at least in this case)
269 3. Factors Effecting Telephone Interference Level c) Load balance
I0 A
B
Source C
N
3rd, 9th, and 15th harmonics behave as zero sequence current sources
I0=IA+IB+IC
Load balance cannot change I0, so it has no impact on telephone interference
270 3. Factors Effecting Telephone Interference Level Summary of findings
• Improving grounding resistance rarely reduces telephone interference (depending on the length of the neutral);
+ – + – + – + – + – + – + – Cannot be Cannot be too large too large Loop current I I1 I2 x
• Improving load balancing will not help reducing telephone interference in general; • Ensure neutral continuity in the parallel zone will help reducing telephone interference
271 4. Review exercise
1) Which case causes more interference?
Phase Phase Neutral Neutral
Telephone Telephone
Grounded overhead neutral Ungrounded overhead neutral
2) Which case will benefit from improved grounding resistance?
Phase Phase Neutral Neutral
Islanded neutral Telephone Telephone 272 Alberta Power Industry Consortium
Grounding Issues 2009-2010 Project #1.1
Draft Report
Substation GPR Transfer to Feeder Neutral Points
Project Leader
Wilsun Xu
Project Team Members
Khaled Alawasa Janak Acharya
Department of Electrical & Computer Engineering University of Alberta Edmonton, AB, T6G 2V4 Phone: 780-492-5965 [email protected]
November, 2009
273
NOTICE
This report was prepared by the University of Alberta for the ultimate benefit of the Alberta Power Industry Consortium members (hereinafter called “SPONSORS”), who do not necessarily agree with the opinions expressed herein.
Neither the SPONSORS, the University of Alberta, nor any other person acting on their behalf makes any warranty, expressed or implied, or assumes any legal responsibility for the accuracy of any information or for the completeness or usefulness of any apparatus, product or process disclosed, or accept liability for the use, or damages resulting from the use, thereof. Neither do they represent that their use would not infringe upon privately owned rights.
Furthermore, the SPONSORS and the University of Alberta HEREBY DISCLAIM ANY AND ALL WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING THE WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE, WHETHER ARISING BY LAW, CUSTOM, OR CONDUCT, WITH RESPECT TO ANY OF THE INFORMATION CONTAINED IN THIS REPORT. In no event shall the SPONSORS and the University of Alberta be liable for incidental or consequential damages because of use or any information contained in this report.
Any reference in this report to any specific commercial product, process or service by tradename, trademark, manufacturer or otherwise does not necessarily constitute or imply its endorsement or recommendation by the University of Alberta or the SPONSORS.
1
274
Table of Contents
1. Introduction ...... 2 2. System Configurations and Parameters ...... 2 3. Analytical Study...... 3 3.1 Substation GPR ...... 3 3.2 Neutral potential rise due to substation GPR ...... 5 3.3 NPR transfer to customer ...... 7 3.4 Representative values ...... 8 3.5 Summary...... 10 4. Case Study Results ...... 10 4.1 Effect of neutral grounding resistances...... 10 4.2 Effect of neutral grounding interval ...... 11 4.3 Effect of neutral length ...... 12 4.5 Effect of customer grounding resistance ...... 12 5. Summery and Conclusions ...... 14 Appendix A: MGN configurations...... 15 Appendix B : Equivalent impedance of MGN ...... 15
i
275
1. Introduction
The objective of this project is to investigate the neutral potential rise (NPR) of the MGN feeders due to short-circuit within substation boundaries. When such a fault occurs, the substation neutral will experience a GPR. This GPR propagates to distribution feeders through their MGN neutral, resulting in the neutral voltage rise. The project has determined key factors affecting the GPR transfer and developed a practical NPR estimation method for APIC member companies.
This project first employs analytical method to show the production of NPR and to establish simplified equations for its estimation. Case studies are then conducted to provide typical values expected in Alberta system. Finally, the case NPR transfer to the loads is studied.
2. System Configurations and Parameters
Figure 2.1 illustrates the general layout of the system used in this project. A distribution feeder with a multi-grounded neutral (MGN) is supplied by a substation transformer. The upstream transmission system is represented by its equivalent circuit.
Equivalent circuit of Upstream ends Substation
138 kV 25 kV Distribution side Customer side Transmission side
/// I f MGN
Z Z Z Z n n n n Z n R sub Rgn Rgn Rgn Rgn Rgn
Figure 2.1 A distribution feeder with MGN and equivalent transmission system.
The interest of this study is to demonstrate how the GPR transfers to the neutral and to the customer load. The following cases have been identified and investigated: Fault locations: T-side or D-side, inside the substation or just outside it. The connections of substation transformer windings (Delta or Y, grounded or ungrounded). The MGN configurations (full-neutral or islanded-neutral). The impedance of the substation transformer neutral.
The MGN that is islanded from the substation will not experience any GPR transfer through the neutral conductor (see Appendix A). Therefore, the study is restricted to the MGN that is essentially connected to the substation.
The study presented in this report make the following assumptions: The shield wire is assumed to be connected with the ground grid of substation under study and the upstream transmission substation.
2
276