The External Monitoring and Evaluation Report of ADB-funded Flood Management Sector Project

The External Resettlement Monitoring and Evaluation Report of

ADB-funded Hunan Flood Management Sector Project

No.2 Report

Changsha Xinghuan Water & Electricity Engineering Technology Development Co., April 2 2008

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 1

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Contents

1. Introduction ...... 3 2. Project Overview...... 3 3. Establishment of Resettlement Organization and its Function ...... 12 4. Progress of Civil Works Construction...... 26

5.The Resettlement Baseline Surveys...... 30

6. Resettlement Implementation Progress...... 43 7. The Affected Persons’ Appeal and Complaints...... 83 8. Support of the Vulnerable Groups...... 90 9. Public Participation, Consultation and Information Disclosure ...... 91 10. The existing Main Problems and Recommendation ...... 93 11. Conclusions and Recommendations...... 97

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 2

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 1. Introduction

On June 29 2006, Asian Development Bank (ADB) approved 200 million US Dollar from Ordinary Capitcal Resource( OCR) for Hunan Flood Management Sector Project. The first 8 subprojects were identified as the core subprojects, namely , Xinhua, Sangzhi, Wugang, , and Chenxi. The external resettlement monitoring and evaluation( M&E) work was commissioned to Changsha Xinghuan Water & Electricity Engineering Technology Development Co.,( CXWEETD). So far, the first resettlement M&E report had been prepared and submitted to ADB including the 4 subprojects, Loudi, Xinhua, Wugang and Sangzhi. Now, it’s the second round of the resettlement M&E. in all 36 subprojects, only 6 of 8 core subprojects had started the resettlement and land acquisition. They are Loudi, Xinhua, Wugang, Sangzhi, Huaihua and Yongzhou. and Chenxi subprojects had some small scaled civil works construction but no the resettlement and land acquisition were involved. Therefore, this M&E report is principally centered for the remaining 6 core subprojects. Since the Project implementation and the resettlement implementation in the relevant subprojects are at an early stage, little progress has been made in these regards. Therefore, the second M&E report will focus on the establishment of resettlement organizations, the complied resettlement policies and compensation standards, land acquisition and resettlement progress and resettlement fund raising and disbursement. Based on ADB’s requirement, the external monitoring and evaluation report is a consolidated one covering all the relevant subprojects. No separate M&E report is necessary for each individual subproject.

2. Project Overview

2.1 Project Scope

Hunan Flood Management Sector Project covers 35 counties with severe flood impact. The project area consists of 8 municipalities including , , Youzhou, Loudi, Chengzhou, , Huaihua and one autonomy prefecture, and 27 counties located in the 12 municipalities.

The 8 core subprojects are Loudi, Xinhua, Wugang, Sangzhi, Yongzhou, Leiyang,

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 3

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Huaihua and Chenxi. These subproject areas have comparatively developed economy. They are not only the county seat but also the local financial, communication, commercial and cultural center where a lot of agricultural, industrial and commercial activities concentrated. Although these cities have higher elevation above the sea with undulating topography and little flood impact from Dongting Lake and Four Rivers, they are prone to suffer from flash floods. The flash floods have the characteristics of quite rapid rise and large flow, causing substantive localized damage. Therefore, the Hunan Flood Management Sector Project has the great significance.

According to the engineering scopes and the designed flood protection standards, the structural measures of 8 core subprojects include flood control works, water-logging works, dredging and flood control roads. The total investment of 8 core subprojects is RMB 1.337907 billion Yuan including RMB 198.9377 million Yuan for resettlement cost. After the structural measures completion, the flood protection standards in municipalities will be raised to 1 in 50 year return period and the water logging standard will be raised to 1 in 20 year return period; the flood project standards in counties will be raised to 1 in 20 year return period and the water logging standards will be raised to 1 in 10 year return period. The Project will substantively reduce the flood suffering and damage. The engineering scope of each core subproject refers to table 2.1-1.

2.2 Project Resettlement Impact Summary

The scope of resettlement and land acquisition covers areas with land acquisition and areas where people’s production and their lives are unfavorably affected. According to the resettlement plans of 8 core subprojects, the total temporary land acquisition is 2666.75mu; the total permanent land acquisition is 3997.98 mu; the total affected population is 3734 households with 15396 persons; the total relocated population is 976 households with 3691 persons and the demolished house areas are 155519.8m2. The resettlement impact summary of 8 core subprojects refer to Table 2.2-1~2.2-4.

.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 4

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Table 2.1-1 8 Core subproject Key Characteristics City No. Loudi Xinhua Wugang Sangzhi Yongzhou Leiyang Huaihua Chenxi Name Construction of Construction of 11 sections of a new new earth dikes Construction of 15.485km long Chengbei, Construction of with the total a 13.385km flood control Chengzhong 5891m long length of long new earth embankments two protection flood control 25.979km; dike; including circles; wall in the Construction of Construction of 4.586km long Construction of main urban 4 sections of Construction of 9.64km long Chengbei 4 new area and the new masonry a new flood control embankment, embankments Gaoping flood flood control 12.342km long wall; Construction of 4.619 km long Construction of with the total control circle; walls with the dike including Construction of a new7.75km Chengbei a new 1220m length of 36.8 Construction of total length of 6.783 km long 13.385km long long Hongmiao long earth dike; km including 1400m long 8.75 km; dike in the masonry slope Chengdong embankment Construction of 30.90 km long earth and rock Strengthening main urban protection flood control and 6.28km gravity-typed Flood earth flood control of the 4 existing area (5,729km works; embankments; long Chengnan water-retaining Control embankment wall in the dikes with the long earth dike 23.025km long 1 Strengthening embankment; and works and 5.89km main urban total length of and 1.054km grass slope 4.5km long Rehabilitation of earth-retaining long earth and area; 10.14km; long flood protection Chengxi flood 0.75 km of wall with the rock Construction of Construction of control wall) works inside control existing dike; length of embankment; 1192m long 7 sections of and 5.559km and outside of embankments. Construction of 719.1m. 36.8km long earth concrete slope long earth the flood a new 0.95 km bank protection dikes;648.5m protection Shuidongjiang control dike; river channel works and long masonry works with the dike. Anti-seepage that will divert 16.684km long bank total length of treatment at flood waters riprap. protection 4.11km; 8 the foundation from the works in main sections of of dike with the Chuangcheng urban area. bank collapse length of River directly to rehabilitation 13.715km. the Nanshui with the total River length of

10.53km.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 3

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Construction of Construction of Construction of Construction of 16 sluice gates 10 new sluice 2 sections of Construction of 9 drainage including 15 gates; Construction of new open 4 new pumping gates in three gravity pumping Construction of 4 new sluice channels stations with flood stations and 1 Upgrading 4 4 flood gates; 1 new including 394m Construction of capacity of protection traffic gate; pumping diversion drainage long inlet open 19 sluice gates; 940kw/ 8 sets; circles; Construction of stations, with channels with station with channel and Construction of 12 drainage Construction of 6 pumping the designed the length of installed 813m long. Water 2 new water sluice gates, 1 2 electricity stations with capacity of 5.44km; capacity of outlet open Logging logging controlling gate, pumping installed 1370kw/14 Construction of 2 465kw; channel; Works pumping 1 flood control stations with capacity of sets; 7 sets of new Construction of Construction of stations with gates; the designed 1460kw; Construction of electricity 1 new diversion 1 new electricity capacity of construction of capacity of Construction of 5 new drainage drainage channel; pumping 1385kW a new 6km long 220KW in 1 flood sluice gates. pumping ; Construction of station; flood diversion three flood diversion stations with 3 buried gates. Construction of channel. protection channel with the designed 3 new sluice circles. the length of capacity of gates 1.3km. 395kw each.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 4

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Continued 2.1-1 8 Core subproject Key Characteristics City No Loudi Xinhua Wugang Sangzhi Youzhou Leiyang Huaihua Chenxi Name 26.2km long river channel Construction of dredging and new masonry disposal of Yudai Bridge gravity-typed spoil in and Tiyun water retaining Lianshui River Construction Bridge Hardening dike dam with the and Sunshui of flood Enlargement; crest surfacing height of 50m; River; Other control roads River with the length Construction of Construction 3 Works and river dredging in 4 of 23.025km; one new of flood cleaning-up. sand beaches River dredging Tuoping control and 2 in the urban overflow dam; command battures. Construction of system and a new 400m other relevant long tunnel. supporting

facilities.

The The The The The The The construction construction construction construction construction construction The construction period is period is period is period is period is period is construction period is planned 37 Project planned 48 planned 36 planned 49 planned 40 planned 48 period is planned 34 months with 4 Schedule months with months with months with months with months with 45 planned 18 months with 35 months 42 months for 24 months for 47 months for 38 months for months for months. 31 months for for major major works. major works. major works. major works. major works. major works. works.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 5

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

The total The total The total The total The total The total The total subproject subproject The total subproject subproject subproject subproject subproject investment is investment is subproject investment is cost is 95.60 investment is investment is investment is 387.4962 109.92.03 investment is 113.6 million million Yuan 243.5982 77.3730 196.7197 million Yuan million Yuan 113.6 million Project Yuan with including million Yuan million Yuan million Yuan including including Yuan including Cost 16.6043 15.2979 including including including 5 58.8907 16.0251 1.9 million Estimates million Yuan million Yuan 42.72 million 24.115 million 23.3847 million million Yuan million Yuan Yuan for for the for Yuan for the Yuan for Yuan for for for resettlement resettlement resettlement resettlement resettlement resettlement resettlement resettlement cost. cost. cost. cost. cost. cost. cost. cost.

The flood The flood The flood The flood control control The flood control control The flood standard will standard will control The flood standard will standard will control be raised to be raised to 1 standard will control be raised to 1 be raised to 1 standard will be The flood 1 in 20 year in 20 year be raised to 1 standard will in 20 year in 20 year raised to 1 in control return period return period in 20 year be raised to 1 return period return period 20 year return standard will from the from the return period in 20 year from the from the period from the be raised to 1 current 1 in 2 current 1 in 5 from the return period current 1 in 5 current 1 in 2 current 1 in 5 in 50 year year return year return current 1 in 10 from the year return year return year return return period; period; The period; The year return Project current 1 in 5 period; The period; The period; The The water water water logging period; The 6 Objectives year return water logging water logging water logging logging logging standard will water logging period; The standard will standard will standard will be standard will standard will be raised to 1 standard will water logging be raised to 1 be raised to 1 raised to 1 in be raised to 1 be 1 in 10 in 10 year be raised to 1 standard will in 10 year in 10 year 10 year return in 20 year year return return period in 10 year be raised to 1 return period return period period from the return period. period from from the return period in 10 year from the from the current natural the current 1 current from the return period. current 1 in 3 current 1 in drainage in 2-5 year natural current 1 in 3 year return 2-5 year conditions. return drainage return periods. period. return period. period. conditions.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 6

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Table2.1-2 Temporary Land Acquisition

City Loudi Xinhua Wugang Sangzhi Youzhou Leiyang Huaihua Chenxi Item 4 administrative 5 10 administrative 1 administrative 2 administrative 5 administrative 2 administrative 3 administrative villages in 3 administrative villages in 7 villages in 1 villages in 2 Administrative villages in 4 villages in 1 villages in 1 townships( residenti villages in a townships(residen township(residential township(residentia villages townships( resident development township al committees) township tial committees) committees) l committees ial committees) zone

Temporary 1243.66mu of 174.5mu of 127.38mu of 346.4mu of 359.82mu of Land 164.55mu of various 118.44mu of various 132mu of various various types of various types of various types various types of various types of Occupation types of land types of land types of land land land of land land land Area

Dry land Dry land 33.4mu; 139.59mu; Dry land Types of Timber forest Dry land10.23mu; Dry land Shrubbery 12.74mu; Dry land Dry land 40mu; Temporary 18.4mu; Timber forest 35mu;Shrubbery 434.94mu; Shrubbery 13.6mu;Shrubber Shrubbery Shrubbery 66mu; Land Shrubbery 54.88mu; Shrubbery 33.73mu;Wasteland Grassland 25.48mu; y 332.8mu Wasteland 26mu. Occupation 36.7mu and 99.44mu 49.71mu 669.13mu. Wasteland Grassland 86mu 89.16 mu

Average Land Acquisition 2 years 2 years 2 years 2 years 2 years 2 years 2 years 2 years Year

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 7

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Table 2.1-3 Permanent Land Acquisition

City Loudi Xinhua Wugang Sangzhi Yongzhou Leiyang Huaihua Chenxi Item 23 31 16 1 development Administrative 11 Administrative 3 Administrative 6 Administrative 11 Administrative zone and 6 villages in 4 Administrative villages Administrative Administrative villages in 5 villages in 2 sub- villages in 3 sub- Administrative townships villages in 1 (residential villages in villages townships districts. districts. villages ( residential townships committees) in one township. (residential committees) 2 districts and committees) 11 townships. Permanent 67.57mu of 47.37mu of 1589.55mu of 473.4mu of various 218.27mu of 914.24mu of 265.32mu of 422.26mu of Land various of various of various of land of land various of land various of land various of land various of land Acquisition land land Paddy field Paddy field 126.16mu; Dry 359.36mu; Dry land Paddy field land 222.96mu; Paddy field 245.49mu; 126.16mu; Dry Vegetable land Paddy field 134.9mu; Dry land Paddy field Paddy field Vegetable land 245.49mu; 179.05mu; 100.26mu;Dry 8.1mu; Vegetable 40.94mu; Dry 366.8mu; Dry land Dry land land 99.75mu; Vegetable land Orchard land land 13.70mu; land 53.2mu; Pond land 3.5mu; 95.94mu;Vegetable 0.57mu; Orchard land 99.75mu; 7.62mu; Fish Orchard land 28.5mu; Economic Pond 0.28mu; Including land 2mu;Rural Vegetable 22.3mu; Pond Orchard land pond 39.75mu; 6.04mu; Rural forest 4.5mu; Rural collective land residential plot land 11.1mu; 22.3mu; Pond Shrubbery residential plot Timber forest residential 8.65mu and 52.31mu; wet Timber forest 11.1mu; Timber 11.02mu; 8.10mu and 9.3mu; Rural plot 0.81mu Enterprise land land 1.65mu 87.49mu; forest 87.49mu; Timber forest Idle land residential plot and Idle land 20.64mu Rural Rural residential 81.68mu; Rural 61.64mu 4.05mu and Idle 1.84mu residential plot 23.7mu; Idle residential plot land 124.71mu plot 23.7mu land 129.7mu 4.59mu; Idle , land 622.69mu and Idle land 129.7mu

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 8

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Industrial land Urban Industrial land 30.11mu; Industrial land residential 14.63mu; Urban 8.32mu; Urban land Urban Industrial land residential residential land Housing plot Including 11.32mu; residential 21.4mu; Urban land 16.62 13.20mu;Urban 12.7mu national land Urban idle land 68.73mu; idle land and mu; Urban idle land and land and Urban idle other land 3.4mu Idle land and other land other land land and other other land 37.01mu 1.72mu land 85.19mu 14.1mu

Table 2.1-3 Project Affected Persons

City Loudi Xinhua Wugang Sangzhi Yongzhou Leiyang Huaihua Chenxi Subtotal

Per Pers Pers Pers Pers Pers Pers Pers Pers Items HH HH son HH HH HH HH HH HH HH ons ons ons ons ons ons ons ons s 201 1539 Total Population 782 4214 628 414 1978 60 472 759 2612 352 1521 684 2398 55 183 3734 8 6 Land Acquisition 176 without 631 1748 596 218 555 17 78 446 1491 257 1112 545 1916 49 152 2759 8816 4 resettlement Resettlement without land 113 352 6 39 193 782 41 193 301 1062 71 307 126 417 3 15 854 3167 Acquisition Land Acquisition 38 136 26 133 3 10 3 8 12 59 24 102 13 65 3 11 122 524 and Resettlement

Affected 1615 18 1808 4 82 11 595 8 291 33 7881 8 5284 8 210 90 Enterprises 1

Resettled 4 82 2 56 1 16 7 154 Enterprises

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 9

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Individual shops 94 170 22 36 8 40 11 17 3 7 1 3 2 5 141 278

Economic 1021 637 276 56 543 419 588 121 0 3661 Rehabilitation Resettlement with housing 151 488 32 172 196 792 37 176 313 1121 95 409 139 483 4 16 967 3657 construction Vulnerable 39 85 22 76 9 95 15 37 14 316 Groups

Affected Ethnic 139 139 Minority

Table 2.1-5 Area of Demolished Houses

City Unit Loudi Xinhua Wugang Sangzhi Yongzhou Leiyang Huaihua Chenxi Subtotal

Item

HH 151 32 196 44 313 95 139 6 974 House Demolition Perso 488 172 792 201 1121 409 482 26 3685 ns

incl HH 134 155 44 290 124 746 Urban Perso 421 621 201 1014 407 2664 ns

Rural HH 17 32 41 23 95 15 6 228

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 10

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Perso 67 172 171 107 409 76 26 1021 ns The Total Areas of m2 30723.26 5272 14486.48 16860.04 41619.35 21506.96 24232.24 819.44 155519.8 House Demolition

Urban m2 26260.92 10980.41 16860.04 33025.88 18574 105701.3 Incl Rural m2 4462.34 5272 3506.07 8593.47 21506.96 5658.24 819.44 49818.52

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 11

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

3. Establishment of Resettlement Organization and its Function

The relevant local governments have put high priority on the subproject resettlement and land acquisition and established the resettlement management organizations equipped with qualified staffs to ensure that the resettlement and land acquisition implementation go smoothly.

No resettlement and land acquisition were implemented in Leiyang and Chenxi. The external M&E work hasn’t been carried out yet.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 12

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Table3.1 Loudi Subproject Management Organization Setting Legal Basis Type of Name of Subordinate Total Full-time Part-time Location Timing Roles and Responsibility of the Organization Organization to person person person ( ) ( ) ( ) organization Subproject Loudi Leading and Overseeing Leading 2005-10-12 Municipal No.62 the subproject Decree by Subrpoject Group Government Loudi Management Subproject Subproject Muncipical Office Subproject day to day Management 2003-7-1 Leading Government Management Office Group

Loudi Land Loudi House Appraisal and House Acuqisition Municipal Verification of Employed by Organization Appraisal and Land Compensation Standards LPMO setting Agency Demolition Resources

Office Bureau

Resettlement Loudi Land Physical Indices Nominated and Land Acuqisition Confirmation,Resettlement by Loudi Acquistion and 2003-7-1 LPMO and Land Acquistion 4 Muncipical Implementation Demolition Agreement Signing Government Agency Office Audit on Project Account and Records concerning Nominated Loudi Supervision Municipal Civil Works Construction, by Loudi Municipal Agency Audit Bureau Resettlment and Land Muncipical Government Acquistion Government

Physical LPMO, Loudi Resttlement and Land Acquisition Office, village representatives and the affected persons jointly made the Indices phyisical indices survey and confirmation. LPMO is employed the Loudi Land Acquisition and Demolition Office to have an Organization 1 Survey and appraisal on state-owned land to be involved into resettlement and land acquisition and then disclose publicly the asset value Operation Confirmation and its corresponding compensation standards.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 13

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Land Acquisition After the confirmation of physical indices, LPMO directly have a negotiation with affected village committees and the relevant and affected persons about the land acquisition and demoliton agreements and sign with them respectively. The signed agreements 2 Demolition are kept in Loudi Land Resources Bureau and Loudi Land Acquisition and Demolition Office as reference. Agreement Signing

Once the agreements are signed and the compensation delivered to each affected person, the affected village committee and Demolition 3 the Land Acquisition and Demolition Office began to implementing land acquisition and demolition within the given timeframe. Implementing

The land compensation is delivered to the affected village committee by LPMO. The villiage committee then hold a village Compensation 4 meeting on discuss how to allocate the land compensation fund among the affected perons. The resettlement compensation is Fund delivery delivered directly to the affected persons by LPMO. The resettlement and land acquisition is completed in one affected town/township or for certain sections of embankment Financial 5 construction, the financial account recording the compensation fund delivery submits for aduit by Loudi Audit Bureau. Account Audit

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 14

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Table 3.2 Xinhua Subproject Management Organization Setting

Legal Basis Type of Name of Subordinate Total Full-time Part-time Location Timing Roles and Responsibility of the Organization Organization to person person person ( ) ( ) ( ) organization Subproject County Leading and Overseeing Leading 2007-5-11 Government the subproject Subrpoject Group The No.6 County Council Management Subproject Subproject Meeting in Office Subproject day to day Management 2007-5-11 Leading 2007 Management Office Group

Xinhua Land House Appraisal and House Acuqisition Xinhua Land Verification of Employed by Organization Appraisal and Resources Compensation Standards LPMO setting Agency Demolition Bureau

Office

Resettlement Xinhua Land Physical Indices and Land Acuqisition Xinhua Land Confirmation,Resettlement Nominated Acquistion and Resources and Land Acquistion 4 by County Implementation Demolition Bureau Agreement Signing Government Agency Office Audit on Project Account The Audit and Records concerning Office under Nominated Supervision Subproject Civil Works Construction, Subproject 2007-5-11 by County Agency Leading Group Resettlment and Land Leading Government Acquistion Group

Physical LPMO, Xinhua Resttlement and Land Acquisition Office, village representatives and the affected persons jointly made the Indices Organization phyisical indices survey and confirmation. LPMO is employed Xinhua Land Acquisition and Demolition Office to have an 1 Survey and Operation appraisal on state-owned land to be involved into resettlement and land acquisition and then disclose publicly the asset value Confirmation and its corresponding compensation standards.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 15

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Land Acquisition Xinhua Resttlement and Land Acquisition Office is responsible for implementing the land acquisition and house demolition. and 2 LPMO is responsible for signing the compensation agreement with the affected persons and send copies of the agreement s to Demolition County Land Resources Bureau for information Agreement Signing Once the agreements are signed and the compensation delivered to each affected person, the affected village committee and Demolition 3 the Land Acquisition and Demolition Office began to implementing land acquisition and demolition within the given timeframe. Implementing

The land compensation is delivered to the affected village committee by LPMO. The villiage committee then hold a village Compensation 4 meeting on discuss how to allocate the land compensation fund among the affected perons. The resettlement compensation is Fund delivery delivered directly to the affected persons by LPMO.

Financial The resettlement and land acquisition is completed in one affected town/township or for certain sections of embankment 5 Account Audit construction, the financial account recording the compensation fund delivery submits for aduit by Loudi Audit Bureau.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 16

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Table 3.3 Wugang Subproject Management Organization Setting

Legal Basis Type of Name of Subordinate Total Full-time Part-time Location Timing Responsibility of the Organization Orgnization to Person Person Person ( ) ( ) ( ) organization No.72 Document Subproject Municipal Leading and Overseeing 2007-5-1 of County Leading Group Government the subproject Government Subrpoject in 2005 Management Office No.146 Subproject Subproject Document Subproject day to day Management 2005-12-1 Leading of County Management Office Group Government in 2005 Shaoyang Municipal Organization House House Appraisal and Shaofang Real Employed Setting Appraisal Verification of Estate by LPMO Agency Compensation Standards Appraisal Company Wugang Land Resettlement Acuqisition and Physical Indices and Land Demolition Nominated Confirmation,Resettlement Acquistion Office with 2005-12-1 LPMO 10 by the and Land Acquistion Implementation Rettlement Government Agreement Signing Agency Division within LPMO Audit on Project Account and Records concerning Nominated Supervision City Audit City Civil Works Construction, by the Agency Bureau Government Resettlment and Land Government Acquistion

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 17

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

LPMO, Wugang Resttlement and Land Acquisition Office, village representatives and the affected persons jointly made the Physical phyisical indices survey and confirmation. LPMO is employed the Shaoyang Municipal Shaofang Real Estate Appraisal Indices Survey 1 Company to have an appraisal on state-owned land to be involved into resettlement and land acquisition and then disclose and publicly the asset value and its corresponding compensation standards Confirmation

Land Acquisition and After the confirmation of physical indices, LPMO sign the compensation agreements with affected persons and send copies of Demolition them to the Land Acuqisition and Demolition Office for information. the Land Acuqisition and Demolition Office is implementing 2 Agreement the land acquisition and demolition. Organization Signing Operation Demolition Once the agreements are signed and the compensation delivered to each affected person, the affected village committee and 3 Implementing the Land Acquisition and Demolition Office began to implementing land acquisition and demolition within the given timeframe

The land compensation is delivered to the affected village committee by LPMO. The villiage committee then hold a village Compensation 4 meeting on discuss how to allocate the land compensation fund among the affected perons. The resettlement compensation is Fund Delivery delivered directly to the affected persons by LPMO The resettlement and land acquisition is completed in one affected town/township or for certain sections of embankment Financial 5 construction, the financial account recording the compensation fund delivery submits for aduit by Wugang Audit Bureau. Account Audit

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 18

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Table 3.4 Sangzhi Subproject Management Organization Setting

Legal Basis Type of Name of Locatio Subordinate Total Full-time Part-time Timing Role and Responsibility of the Organization Organization n to Person Person Person ( ) ( ) ( ) organization No. 9 Subproject Subproject Project Management and County 〔2006〕 Management Management Sept.2006 Coordination Government County Office Office Meeting Minutes. House Hengtai House Appraisal and Employed Appraisal Appraisal Company Verification of Organization by LPMO Agency Compensation Standards Setting Resettlement Physical Indices Liyuan Township and Land County Confirmation,Resettlement County Government Acquistion Government and Land Acquistion Government

Implementatio Agreement Signing n Agency Audit on Project Account ; Records concerning Civil Nominated Supervision County Works Construction, County Audit Bureau by Agency Government Resettlment and Land Government Acquistion and Quality Control Physical Indices Survey LPMO, Liyuan Township Government, Financial Bureau, Land Resources Bureu and House Appraisal Agency jointly confirm Organization 1 and the physical indices. Zhangjiajie Hengtai House Appraisal Company has a house appraisal and discloses the confirmed Operation Confirmation physical indices.

Land Acquisition and After the confirmation of physical indices, LPMO sign the compensation agreements with affected persons and send copies Demolition 2 of them to Liyuan Township Government for information. Liyuan Township Government is implementing the land acquisition Agreement Signing and demolition.

Once the agreements are signed and the compensation delivered to each affected person, Liyuan Township Government 3 Demolition Implementing began to implementing land acquisition and demolition within the given timeframe.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 19

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

The land compensation is delivered to the affected village committee by LPMO. The villiage committee then hold a village Compensation Fund meeting on discuss how to allocate the land compensation fund among the affected perons. The resettlement compensation 4 Delivery is delivered directly to the affected persons by LPMO.

5 Financial Account Audit The resettlement and land acquisition is completed in one affected town/township or for certain sections of embankment construction, the financial account recording the compensation fund delivery submits for aduit by Sangzhi Audit Bureau

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 20

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Table 3.5 Huaihua Subproject Management Organization Setting

Type of Legal Basis Name of Subordinate Role and Total Full-time Part-time Organization Location Timing of the Organization to Responsibility Person Person Person ( ) ( ) ( ) organization No. 13 Subproject Subproject Leading Group and Document Municipal Project Management Management Management Office 2006.12 50 40 10 2007 Government And Coordination 〔 〕 Office Municipal Government

Organization House Huaihua Caifu Appraisal House Appraisal and Setting Appraisal Company and Verification of Agency Guangnian Appraisal Company Compensation Standards Land Acquisition Physical Indices Subproject Nominated And Resettlement Division under the Confirmation,Resettlement Leading by Leading Demolition Subproject Leading Group and Land Acquistion Group Group Implementing Agreement Signing Agency Supervision

Agency Acccording to the civil works scope, the Resettlement Division confirm the land acquistion and resttlement Areas. The Physical Indices Survey and 1 Appraisal Agency conducts the appraisal and disclose the appraisal results three times publicly. Confirmation

Land Acquisition and Demolition After the confirmation of physical indices, LPMO sign the compensation agreements with affected persons and send 2 Agreement Signing copies of them to Land Acqusition and Demoliton Office for information. Resettlement Division under the subproject Leading Group is implementing the land acquisition and demolition

Organization Once the agreements are signed and the compensation delivered to each affected person, Liyuan Township Government Operation 3 Demolition Implementing began to implementing land acquisition and demolition within the given timeframe

The land compensation is delivered to the affected village committee by LPMO. The villiage committee then hold a village 4 Compensation Fund Delivery meeting on discuss how to allocate the land compensation fund among the affected perons. The resettlement compensation is delivered directly to the affected persons by LPMO.

5 Financial Account Audit Audited by Municipal Audit Bureau.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 21

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Table 3.6 Yongzhou Subproject Management Organization Setting-Lengshuitan

Legal Basis Type of Name of Subordinate Total Full-time Full-time Location Timing Role and Responsibility of the Organization Organization to Person Person Person ( ) ( ) ( ) organization No. 91 Subproject 〔2005〕 Municipal Leading and Overseeing Management 2005.11.24 25 10 15 Document Government the subproject Office by Municipal Management Government Agency No. 1 Lengshuitan (2008) Subproject Subproject Project Implementation Area 2008.2 Management 10 6 4 Document Management Management Office by Office Municipal Water Organization Yongzhou Setting House House House Appraisal and Nominated Appraisal Demolition Municipal Verification of by Agency Office (only for Government Compensation Standards Government ) Land Acquisition Yongzhou Physical Indices Nominated And House Municipal Confirmation,Resettlement by Demolition Demolition Government and Land Acquistion Government Implementing Office Agreement Signing Agency Audit on Project Account ; Records concerning Civil Lengshuitan Nominated Supervision Municipal Works Construction, District Audit by Agency Government Resettlment and Land Bureau Government Acquistion and Quality Control Physical LPMO, the Resttlement and Land Acquisition Office, village representatives and the affected persons jointly made the phyisical Organization Indices Survey 1 indices survey and confirmation. Yongzhou House Demolition Office has an appraisal on houses and then disclose publicly the Operation and asset value and its corresponding compensation standards Confirmation

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 22

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Land Acquisition and After the confirmation of physical indices, LPMO sign the compensation agreements with affected persons and send copies of them to the House Demoliton Office for information. The House Demoliton Office is implementing the land acquisition and 2 Demolition Agreement demolition Signing Once the agreements are signed and the compensation delivered to each affected person, the Village Committee and to the Demolition 3 House Demoliton Office began to implementing land acquisition and demolition within the given timeframe. Implementing

The land compensation is delivered to the affected village committee by LPMO. The villiage committee then hold a village Compensation 4 meeting on discuss how to allocate the land compensation fund among the affected perons. The resettlement compensation is Fund Delivery delivered directly to the affected persons by LPMO The resettlement and land acquisition is completed in one affected town/township or for certain sections of embankment Financial 5 construction, the financial account recording the compensation fund delivery submits for aduit by Lengshuitan District Audit Account Audit Bureau

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 23

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Table 3.7 Yongzhou Subproject Management Organization Setting-Lingling District

Legal Basis Type of Name of Subordinate Total Full-time Part-time Location Timing Role and Responsibility of the Organization Organization to Person Person Person ( ) ( ) ( ) organization No. 91 Subproject 〔2005〕 Municipal Leading and Overseeing Management 2005.11.24 25 10 15 Document Government the subproject Office by Municipal Management Government Agency No. 40 Lingling 2006 Lingling 〔 〕 Subproject Area Project Implementation 2006.10.19 District 11 11 0 Document Management Management Government by Lingling Office District Government Organization Hunan Xiaoxiang Setting Real Estate House House Appraisal and Appraisal Employed Appraisal Verification of Company by LPMO Agency Compensation Standards (For Lingling District) Land

Acquisition Physical Indices Lingling District Lingling Nominated And Confirmation,Resettlement Land Acquistion District by Demolition and Land Acquistion and Demolition Government Government Implementing Agreement Signing Office Agency Audit on Project Account ; Records concerning Civil Lingling Nominated Supervision Lingling District Works Construction, District by Agency Audit Bureau Resettlment and Land Government Government Acquistion and Quality Control Physical Indices LPMO, the Resttlement and Land Acquisition Office, village representatives and the affected persons jointly made the Organization 1 Survey and phyisical indices survey and confirmation. Hunan Xiaoxiang Real Estate Appraisal Company has an appraisal on houses and Operation Confirmation then disclose publicly the asset value and its corresponding compensation standards

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 24

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Land Acquisition After the confirmation of physical indices, LPMO sign the compensation agreements with affected persons and send copies of and Demolition them to the Lingling Land Acquistion and House Demoliton Office for information. The Office is then implementing the land 2 Agreement acquisition and demolition Signing

Once the agreements are signed and the compensation delivered to each affected person, the Village Committee and to the Demolition 3 House Demoliton Office began to implementing land acquisition and demolition within the given timeframe. Implementing

The land compensation is delivered to the affected village committee by LPMO. The villiage committee then hold a village Compensation 4 meeting on discuss how to allocate the land compensation fund among the affected perons. The resettlement compensation Fund Delivery is delivered directly to the affected persons by LPMO The resettlement and land acquisition is completed in one affected town/township or for certain sections of embankment Financial Account 5 construction, the financial account recording the compensation fund delivery submits for aduit by Lingling District Audit Audit Bureau

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 25

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

4. Progress of Civil Works Construction

By February 2008, the 6 core subprojects have completed the bid process and contract awarding. Construction contractors and the supervision companies have been mobilized to the field. The implementation details are shown in Table 4-1.However due to various factors and constraints, the actual subprojects’ civil works progress lay behind the schedule.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 26

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Table 4.1 Progress of Civil Works Construction Made

Date of Name of Contract Investment Name of The Supervision Commence Progress Item Civil Works Price The Contractor Quantities Completed Completed City Company to Made Package (Yuan) (Yuan) Work

Civil works Hunan Water in the Hunan Water Resource and sections of Resource and Electricity Main works from Liangang No.2 Bridge to Loudi No.1 old city area 43.723 1 Hydro-power Engineering Bridge 45.69% of Chengbei Million General Construction Flood Company Supervision Protection Company Loudi Circle Civil works Hunan Water in Lishui Hunan Water Resource and Main Works at the Qingtan section at southern bank of sections of 59.279 Resource and Electricity 2 Lianshui River 51.29% Chengzhong Million Hydro-power Engineering

Flood No.1 Company Construction Protection Supervision Circle Company Loudi Water Hunan Water Resource and Resource and Chainage 0+000 3+000 slope protection and 12.50 1 Chengxi Hydro-power 2007.9.29 ~ 70% Hydro-power Construction embankment crest hardening; foundation grouting Million No.1 Company Supervision Xinhua Loudi Water Hunan Resource and Chainage 3+000 4+190 foundation excavation; Xinkang ~ Hydro-power 2 Chengdong Construction 2007.10.16 newly built 1 Huashan Pump station; repair and 2 million 15% Construction Company Ltd., upgrading 1 sluice; 800m long foundation grouting; Supervision backfill 1.5m. Company Shaoyang Kaituo Hunan Water Resource Construction 700m long dikes completed from Yudai Bridge to and Hydro-power Wugang 1 Chengbei Group 2007.1.11 Dongta; 1500m long dikes Tiyun Bridage upstream 7.2 million 40% Engineering Company Construction

Company

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 27

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Hunan Shaoyang Kaituo 500m long dikes completed from Xiaojiaba to Yudai Donggang Water Resource Bridge; 1500m long dikes Tiyun Bridage upstream 2 Chengnan Construction and Hydro-power 2007.1.11 7.9 million 45%

Development Engineering

Company Construction Company

Continued Table 4.1 Date of Name of Contract Investment Name of The The Supervision Commence Progress Item Civil Works Price Quantities Completed Completed City Contractor Company to Made Package (Yuan) (Yuan) Work Hunan Yuhui Water Water Resource Chainage A0+000~0+300 flood control wall; Main Urban 30.35 Resource and Hydro-power 1 2007.10.8 10million 30% Area million and Construction A0+800~1+390 flood control wall;C0+000~1+045 Hydro-power Consulting flood control wall Construction Company Saangzhi HunanC Water Hunan Jianghe Resource Water Resource 10.69 and and Hydro-power Chainage 0-120~0+326 flood control wall;Chainage 2 Gaojiaping 2007.4.1 9.60million 100% million Hydro-power Construction 0+326~0+911.38 earth embankment General Consulting Company Company Hunan Water Hunan Water Resource and Resource Electricity 23 and 50% of civil works completed; the foundation works Huaihua 1 Phase 1 Engineering 2007.3 12 million 50% million Hydro-power completed Construction Construction Supervision Company Company Hunan Hunan Water Xiangyu Resource and Lengshuitan Hdyro-power Electricity 10.23 District of 1 Hedong C9 Construction Engineering 2007.7 Chainage 0+000 2+800 earth embankment 15 million 100% million ~ Yongzhou Development Construction Company Supervision Company

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 28

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Hunan Water Hunan Water Resource Resource and and Electricity Chainage 1+921~3+481.74earth embankment; Hexi C10 27.13 2 Hydro-power Engineering 2008.3 2 million 10% Section Million Chainage11+448.42~13+370.91marsonary Machinery Construction embankment Construction Supervision Company Company Hunan Water Hunan Water Resource and Resource Electricity Hexi CW02 2.107 and 12.29 1 Engineering 2777m long concrete flood control wall 100% Section Million Hydro-power million Construction General Supervision Company Lingling Company District of Hunan Water Yongzhou Hunan Water Resource and Resource Electricity Hedong 30.3017 and 2 Engineering CW01Section Million Hydro-power Construction No.1 Supervision Company Company

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 29

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

5.The Resettlement Baseline Surveys

From end 2007 to the beginning of 208, Hunan Province, especially the project area had suffered 1in 100 years snow disaster, which had tremendous impact on the normal production and lives. The traffic, power supply and water supply were stopped. The provincial highway had been paralyzed almost 20 days. This natural disaster coincided with Chinese Spring Fesitival and thousands of travelers were stopped halfway. Under this circumstance, CXWEETD managed to finish the field surveys in Loudi, Xinhua and Wugang.However, the survey works for the other remaining 4 subprojects were forced to suspend due to harsh weather conditions.

Just after the Spring Festival, CXWEETD intended to intensify the effort in conducting the baseline survey for the remaining 4 subproject but only managed to have undertaken the field survey for the only one subproject-sangzhi because the subproject areas were reconstructing the snow-struck infrastructure and their own houses besides their routine spring farming activities. The baseline surveys for Huaihua and Youzhou subprojects had to been postponed to the next M&E period.

Therefore, the baseline survey this time only covered 4 subprojects, Loudi, Xinhua, Wugang and Sangzhi. The CXWEETD collected the scio-economic data and conducted the sampled household surveys. There were 193 sampling households in total including 70 households in Loudi, 60 in Xinhua, 42 in Wugang and 22 in Sangzhi.

Immediately after the completion of the field surveys, the CXXX collated the collected data and made the analysis. A baseline survey database was also established. The summary of baseline survey refers to Table 5-1.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 30

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Table 5.1 Resettlement Baseline Survey

Loudi Xinhua Wugang Sangzhi Item Unit No. % No. % No. % No. %

HH 70 60 42 22 Sampled Household Person 233 197 188 80 Non-agri Person 54 23% 31 16% 124 66% 65 76% Housing Area M2 13045 8481 4577 3685 Brick-concrete M2 12222 94% 4170 49% 1101 24% 3099 84.1%

Housing 2 Structural Brick-wood M 823 6% 4311 51% 3368 74% 317 8.6% Condition Wood and earth M2 108 2% 269 7.3% and wood Housing Area per capita M2 56 43 24 46 Farmland Mu 65.15 57.77 15.90 8.20 Paddy Field Mu 14.00 21% 49.10 85% 9.40 59% 0.00 Type Dry Land Mu 6.90 11% 6.10 11% 4.80 30% 0.00 Land Of Land Vegetable Land Mu 44.25 68% 2.57 4% 1.70 11% 8.2 100% Farmland per capita for Mu 0.36 0.35 0.25 0.55 Agricultural Population Income from Primary Sector Yuan 243420 25% 142931 19% 28280 3% 42000 12% From Rice Production Yuan 9890 1% 98482 13% 12220 2% 0% Vegetable Plantation Yuan 233530 24% 7749 1% 8500 1% 42000 12% Animal Husbandry Yuan 0 0% 36700 5% 3000 0.4% 0% Income from Secondary and Economic Yuan 737700 75% 592860 81% 781020 97% 295580 88% Tertiary Sector Income From migrant workers Yuan 505023 51% 302511 41% 234000 29% 295580 88% Total income of the all the sampled Yuan 981120 100% 735791 100% 809300 100% 337580 100% Households Income per capita Yuan 4211 3735 4305 4220 Net Income per capita Yuan 3850 3450 4250 3750 Vehicle (track) Set 6 9% 2 3% 1 2% 0 0% Tractor Set 3 4% 1 2% 0 0% 0 0% Motorcycle Set 47 67% 11 18% 18 43% 1 4% Bicycle Set 51 73% 13 22% 21 50% 2 8%

Family-owned TV set Set 77 110% 47 78% 46 110% 7 29% Production Computer Set 11 16% 3 5% 3 7% 0 0% And Living Facilities VCD Set 37 53% 15 25% 20 48% 0 0% And Equipment Refrigerator Set 40 57% 12 20% 18 43% 4 17% Washing Machine Set 47 67% 32 53% 33 79% 3 13% Water Heater Set 13 19% 5 8% 3 7% 2 8% Telephone Set 47 67% 19 32% 27 64% 5 21% Mobile Set 91 39% 45 23% 54 29% 27 34% High-class Furniture Set 8 11% 18 30% 1 2% 0 0%

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 31

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 5.1 Loudi

5.1.1 Living Conditions of the Affected Persons

According to the first resettlement baseline survey, there were 39 sample households in Loudi Subproject. Currently, the total housing areas of these households were 6213m2, including 5758 m2 brick-concrete structure, accounting for 93%, 455 m2 brick-wood structure, accounting for 7%. The average housing areas was 51 m2.

There are 70 sample households in Loudi Subproject. Currently, the total housing areas of these households are 13045m2, including 12222 m2 brick-concrete structure, accounting for 94%, 823 m2 brick-wood structure, accounting for 6%. The average housing areas is 56 m2, which is almost the same with the first M&E period.

As the subproject is distributed in a linear shape along Lianshui and Sunshui River, almost all of the affected persons live at the junction of urban and rural areas and very close to the riverine. They frequently suffered from the flooding damage and their living conditions are generally poor. Almost all the houses are old brick-concrete or brick-wood structures at the first or second floor. These houses were built in late 1980’s and in early 1990’s, some of which are already in poor conditions. Residents here hope to improve their living conditions soonest.

5.1.2 Production Conditions and Employment of the Affected Persons

According to the first resettlement baseline survey, the sampled 39 affected households had 29.1 mu farmlands in total including 6.2 mu paddy fields, accounting for 21%; 3.1mu dry land, accounting for 11%; 19.8 mu vegetable lands, accounting for 68%. The average farmland holding was 0.36 mu.

Based on the survey this time, the sampled 70 affected households have 65.15 mu farmlands in total including 14 mu paddy fields, accounting for 21%; 6.9mu dry land, accounting for 11%; 44.25 mu vegetable lands, accounting for 68%. The average farmland holding is 0.36 mu.

During the first M&E period, the typical affected households were selected for household surveys in each village. This time, more affected households were surveyed and the results showed that the average farmland per capita was the same with the previous because the land quantities are almost same in all the surveyed villages

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 32

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project whose land was contracted to each household.

As the subproject is distributed in a linear shape along the river, most of farmers only lost a small portion of their own lands.

The agriculture plantation in the subproject area is mainly vegetable and rice. The paddy fields grow vegetable, double-cropping rice and some single-cropping rice, soybean and oilseed. The dry lands grow grain, soybean, green pea, pea, sweet potato, potato, peanut, oilseed, vegetable and melon fruit etc.

The subproject area is located at the junction of urban and rural areas and the relevant infrastructures are comparatively good. Local farmers have more opportunities to get involved into non-agricultural activities. Most of rural surplus labor forces, especially young labor forces have been transferred to working in the secondary and tertiary sectors. They are migrant workers in coastal cities, such as Guangzhou. They are mainly involved into construction and service sectors.

5.1.3 Economic Income of the Affected Persons

According to the first resettlement baseline survey, the total income of 39 sample households was RMB 527,040 Yuan last year including RMB 110,040 Yuan from the primary sector, accounting for 21% of the total. The income from vegetable plantation was RMB 99,000 Yuan, accounting for 90% of the total income from the primary sector and also accounting for 19% of the total income generated from the three sectors. The income from the secondary and tertiary sector was RMB 417,000 Yuan, accounting for 79% of the total income. The salary income from the migrant workers in the secondary and tertiary sectors was RMB 246,600 Yuan, accounting for the 59% of the total income from these two sectors and also accounting for 47% of the total income from the above-mentioned three sectors. The average income per capita was RMB 3,980 Yuan.

According to the resettlement baseline survey this time, the total income of 70 sample households was RMB 981,120 Yuan last year including RMB 243,420Yuan from the primary sector, accounting for 25% of the total. The income from vegetable plantation was 233,530RMB Yuan, accounting for 96% of the total income from the primary sector and also accounting for 24% of the total income generated from the three sectors. The income from the secondary and tertiary sector was RMB 737,700 Yuan, accounting for

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 33

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 75% of the total income. The salary income from the migrant workers in the secondary and tertiary sectors was RMB 505,023Yuan, accounting for the 68% of the total income from these two sectors and also accounting for 51% of the total income from the above-mentioned three sectors. The average income per capita was RMB 3,850 Yuan.

The average income per capita is slightly lower than it in the first M&E period. The reason is that little land acquisition and house demolition is implemented during the second M&E period, which may not show the full picture of the impact on the affected persons’ economic income resulted from land acquisition and resettlement.

The income structure indicated that the income was mainly from vegetable plantation in the primary sector and the income generated from the agriculture plantation accounted for a small percentage of the total family income. The major income of the affected persons is from non-agricultural employment, especially the salary income of the migrant workers, which accounted for 50% of the total income. Therefore, land acquisition in the subproject only has minor impact on their production and lives.

5.1.4 Living Quality of the Affected Persons

The affected persons live very close to the river. Their houses are old buildings with brick-concrete or brick-wood structure, either stand-alone or two-storied. These buildings are frequently damaged by floods. Generally speaking, their living conditions are poor.

The subproject area is located at the junction of urban and rural areas and the infrastructure is good. Local people have good access to water, electricity, road, post and communication. It’s also convenient for them to see a doctor and for children go to school.

The sample household survey showed that every hundred households had 9 vehicles, 4 tractors, 67 motorcycles, 73 bicycles, 110 TV sets, 16 computers, 53 video players, 57 refrigerators, 67 washing machines, 19 water heaters, 11 sets of high-medium quality furniture and 67 telephone sets. 39 out of every 100 persons have mobile phones.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 34

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 5.2 Xinhua

5.2.1 Living Conditions of the Affected Persons

According to the first resettlement baseline survey, there were 39 sampling households in Xinhua subproject. Currently the total housing areas of these households were

5361m2,including 2820 m2 brick-concrete structure, accounting for 53% of the total,

2541m2 brick-wood structure, accounting for 47% of the total. The average housing area was 44m2.

Based on the resettlement baseline survey this time, there are 60 sampling households in Xinhua subproject. Currently the total housing areas of these households are

8481m2,including 4710 m2 brick-concrete structure, accounting for 49% of the total,

4311m2 brick-wood structure, accounting for 51% of the total. The average housing area is 43m2,which is almost same with it in the first M&E period.

The affected persons live along Zishui River in a linear shape. Almost all of the houses are old stand-alone or two-storied buildings with brick-concrete or brick-wood structures, which were built in 1980’s or 1990’s. Some of them are really in poor conditions. Residents there hope to improve their living conditions soonest.

5.2.2 Production Conditions and Employment of the Affected Persons

According to the first resettlement baseline survey, the sampled 39 households had 34.39mu farmland in total including 30.8 mu paddy field, accounting for 89% of the total; 2.59 mu dry land, accounting for 8% of the total; 1.0 mu vegetable land, accounting for 3%. The average farmland holding per agricultural person was 0.32mu.

Based on the resettlement baseline survey this time, the sampled 60 households have 57.77mu farmland in total including 40. 1 mu paddy field, accounting for 85% of the total; 6.1 mu dry land, accounting for 11% of the total; 2.57 mu vegetable land, accounting for 4%. The average farmland holding per agricultural person is 0.35mu.

The subproject is distributed along Zishui River in a linear shape. Most of the affected persons only lost a very small portion of their own lands in addition, the proposed land acquisition mainly cover the drawdown area of Zexi Reservoir, not counted as part of farmers’ own land. Therefore, land acquisition has minor impact on the affected

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 35

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project households.

Rice is one of major crops in the subproject area. Paddy fields grow double-cropping rice, some single-cropping rice, soybean, oilseed and vegetables. Dry lands grow corn, other types of grain, soybean, sweet potato, potato, peanut, vegetable and melon fruits etc. local farmers cultivated the drawdown area of Zexi Reservoir according to the local farming practices, crops’ growth cycle and Reservoir operation rules. They plant rice, oilseed, potato and vegetable at certain interval.

In recent years, the secondary and tertiary sectors have developed very fast. The subproject area has the favorable geographic location and its infrastructure is good. The local farmers have more opportunities to be engaged into the non-agricultural activities and a large portion of surplus rural labor forces have been transferred to working in the secondary and tertiary sectors.

5.2.3 Economic Income of the Affected Persons

According to the first resettlement baseline survey, the total income of 39 sampled households was RMB 394,890 Yuan last year including RMB 75,390 Yuan income from the primary sector, accounting for 19% of the total. The income generated from rice plantation was RMB 30,800 Yuan in the primary sector, accounting for 41% of the total income of the primary sector and also accounting for 8% of the total income from the three sectors. The income generated from animal husbandry was RMB 36,700 Yuan, accounting for 49% of the income of the primary sector and also accounting for 9% of the total income from the three sectors. The income from the secondary and tertiary sectors was RMB 319,500 Yuan, accounting for 81% of the total. The salary income earned by migrant workers in the secondary and tertiary sectors was RMB 205,700 Yuan, accounting for 64% of the total income in these two sectors and also accounting for 52% of the total income from the three sectors. The average annual income per capita was RMB 3,100 Yuan.

Based on the resettlement baseline survey this time, the total income of 60 sampled households was RMB 735,791Yuan last year including RMB 142,931Yuan income from the primary sector, accounting for 19% of the total. The income generated from rice plantation was RMB 98,482Yuan in the primary sector, accounting for 69% of the total income of the primary sector and also accounting for 13% of the total income from the

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 36

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project three sectors. The income generated from commercial vegetable is 7,749 Yuan, accounting for 5% of the total income of the primary sector and also accounting for 1% of the total income from the three sectors. The income generated from animal husbandry was RMB 36,700Yuan, accounting for 26% of the income of the primary sector and also accounting for 5% of the total income from the three sectors. The income from the secondary and tertiary sectors was RMB 592,860Yuan, accounting for 81% of the total. The salary income earned by migrant workers in the secondary and tertiary sectors was RMB 302,511Yuan, accounting for 51% of the total income in these two sectors and also accounting for 41% of the total income from the three sectors. The average annual income per capita was RMB 3,450 Yuan. The acquired land and demolished houses are small in the second M&E period. Last year, the grain production increased in Xinhua and the grain price increased, which may contribute to improving the farmers’ income.

The income structure indicated that the income from agriculture plantation and animal husbandry almost accounted for 50% of the total income in primary sector respectively. However, the income from the agriculture plantation only had a small share of the total family income. The major income of the affected households was from the non-agricultural activities, especially the salary income from migrant workers. Therefore, land acquisition had minor impact on production and lives and the affected persons.

5.2.4 Living Quality of the Affected Persons

The urban area of lies both sides of Zishui River. The whole city is divided into two parts: Chengxi and Chengdong. The left bank( Chengxi) is the old city area and the right bank( Chengdong) is the new development zone. The subproject area is located in the Meiyuan Development zone of Chengdong. It is distributed along the Zishui River in a linear shape, most of which is low-lying area and frequently flooded. The living conditions there were poor.

Generally speaking, the infrastructures in subproject area are good. Local people have good access to water, electricity, road, post and telecommunication. It’s convenient for them to see a doctor and for children to go to school.

The sample household survey showed that every hundred household had 3 vehicles, 2 tractors, 18 motorcycles, 22 bicycles, 78 TV sets, 5 computers, 25 video players, 20

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 37

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project refrigerators, 53 washing machines, 8 water heaters, 30 sets of high-medium quality furniture and 32 telephone sets. 23 out of every 100 persons had mobile phones.

5.3 Wugang

5.3.1 Living Conditions of the Affected Persons

There are 42 sampling households in Wugang. Currently, the total housing area of these households was 4577m2 including 1101m2 brick-concrete structure, accounting for 24% and 3368m2 brick-wood structure, accounting for 74% and 108m2 wood structure, accounting for 2%. The average housing area per capita was 24m2.

Wugang lies beside Nanshui River, in the upper stream of Zishui River. Nanshui River passes through the city. The topography in the city is flat and spacious. The affected houses were mostly built in 1970’s and 1980’s, the majority of which were stand-alone or two-storied brick-wood structures. Since these houses were built randomly and improperly designed, each of them had limited space and the average housing area per capita was small. In addition, the ventilation and lighting of these houses were poor. Most of them lived in the dark, humid and poor sanitary conditions. Therefore, residents there hope to improve their living standards soonest.

5.3.2 Production Conditions and employment of the Affected Persons

The 42 sampling households have 15.9 mu farmland in total including 9.4 mu paddy field accounting for 59% of the total, 4.8mu paddy field accounting for 30% and 1.7 mu vegetable land accounting for 11%. The average farmland holding of per agricultural person is 0.25 mu.

The subproject is aligned along Zishui River in a linear shape. Most of the affected households only lost a small portion of their land. Therefore, the land acquisition has minor impact on their production and lives.

The agricultural plantation was mainly double-cropping rice, vegetable, water melon and oilseeds. Paddy fields grow double-cropping and some single-cropping rice, wheat, oilseed and vegetable. Dry lands grow corn, other types of grain, green pea, pea, sweet potato, potato, peanut, oilseed, vegetable and melon fruit etc.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 38

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project The subproject area lies at the junction of urban and rural areas and its infrastructure is good. Local farmers have more opportunities to be involved into non-agricultural activities. A large proportion of rural surplus labor forces have been transferred to working in the secondary and tertiary sectors.

5.3.3 Economic Income of the Affected Persons

The total income of these 42 sampling households was RMB 809,300 Yuan last year including RMB 28,280 Yuan from the primary sector accounting for 3% of the total. The income from the secondary and tertiary sectors was RMB 781,020 Yuan accounting for 97% of the total. The salary income of migrant workers in secondary and tertiary sectors was RMB 234,000 Yuan, accounting for 30% of that from these two sectors and also accounting for 29% of the total from the above-mentioned three sectors. The salary income of non-agricultural population was RMB 273,520 Yuan, accounting for 34% of the total. The average annual net income per capita was RMB 4,248 Yuan.

The income structure indicated that the income generated from the primary sector had a very small proportion of the total family income. Their income mainly relied on non-farming activities. In addition, non-agricultural status population had a larger percentage (66%) and their salary income accounted for 1/3 of the total income. The income earned by migrant workers also accounted for 1/3 of the total income. Therefore, land acquisition had minor impact on their production and lives.

5.3.4 Living Conditions of the Affected Persons

The subproject area is low-lying, spacious and frequently flooded. The living conditions there were poor. Most of houses were built in 1980’s with stone-along or two-storied brick-concrete or brick-wood structures. Very few wooden structured houses existed. The average housing area per capita was quite limited.

The subproject area is located suburban and its infrastructure is good. Local people have good access to water, electricity, road, post and telecommunication. It’s convenient for them to see a doctor and for children to go to school.

The sample household survey showed that every hundred household had 2 vehicles, 43 motorcycles, 50 bicycles, 110 TV sets, 7 computers, 48 video players, 43 refrigerators, 79 washing machines, 7 water heaters, 2 sets of high and medium quality furniture and

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 39

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 64 telephone sets. 29 out of 100 persons had mobile phones.

5.4 Sangzhi

5.4.1 Living Conditions of the Affected Persons

According to the first resettlement baseline survey, there were 11 sampling households in Sangzhi Subproject. Currently their total housing area was 686m2 including 100 m2 brick-concrete structure accounting for 15% of the total, 416 m2 brick-wood structure accounting for 60% of the total and 170 m2 wooden structure accounting for 25% of the total. The average housing area per capita was 19 m2.

Based on the resettlement baseline survey this time, there are 22 sampling households in Sangzhi Subproject. Currently their total housing area was 3685 m2 including 3099 m2 brick-concrete structure accounting for 84.1% of the total, 317 m2 brick-wood structure accounting for 8.6% of the total and 269 m2 wooden structure accounting for 7.3% of the total. The average housing area per capita was 46 m2.

The incremental sampled households this time are households living at the suburban areas. Some of them are rich but some of them are very poor. Most of them live in the spacious brick-concrete houses but they are economically poor. More people live in the wooden structures than those in other subprojects.

The city seat of Sangzhi is located on the upper reach of Lishui River. The river gradient there is steep. When floods occur, the water level rises quickly and remains high. The houses were built at the grade I terrace alongside the Lishui and Youshui Rivers. The subproject area is generally low-lying, flat and spacious and most of it was frequently flooded. The houses of those affected persons were mostly built in 1980’s and the average housing area per capita was limited. The majority of these houses are stand-along or two storied old buildings with brick-wood and wood structures. The living conditions and auxiliary facilities were poor. Residents there hope to improve their living standards soonest.

5.4.2 Production Conditions and Employment of the Affected Persons

According to the first resettlement baseline survey, the 11 sampling households had 6.8 mu farmland in total and all of them grow vegetable. The average farmland holding per

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 40

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project agricultural person was 0.76 mu.

Based on the resettlement baseline survey this time, the 22 sampling households have 8.2 mu farmland in total and all of them grow vegetable. The average farmland holding per agricultural person is 0.55 mu.

The subproject is aligned along the Lishui and Youshui Rivers in a linear shape. Most of the affected households only lost a very small portion of their farmland and houses which are closely adjacent to the dikes.

The affected Liyuan Township will be in the future urban areas according to the county plan. The infrastructure there is quite good. Local farmers have more opportunities to be involved into non-agricultural activities. Most of local surplus labor forces have been transferred to working in the secondary and tertiary sectors. Especially young people went outside of their town and found employment in big cities, such as Guangdong, Wenzhou. They mainly work in the construction, timber processing, shoe-making and electronics sectors.

The agriculture plantation is mainly vegetable and rice.

5.4.3 Economic Income of the Affected Persons

According to the first resettlement baseline survey, the total income of these sampling households was RMB 93,700 Yuan last year including RMB 15,000 Yuan income from the primary sector accounting for 16% of the total. This income was all from vegetable selling. The income from the secondary and tertiary sectors was RMB 78,700 Yuan accounting for 84% of the total. The salary income earned by migrant workers in the secondary and tertiary sectors was RMB 48,000 Yuan accounting for 61% of the total income from these two sectors and also accounting for 51% of the total. The average annual net income per capita was RMB 2,391Yuan.

Based on the resettlement baseline survey this time, the total income of these sampling households was RMB 337,580Yuan last year including RMB 420,00Yuan income from the primary sector accounting for 12.1% of the total. This income was all from vegetable selling. The income from the secondary and tertiary sectors was RMB 295,580Yuan, which is from the salary income earned by migrant workers in the secondary and tertiary sectors, accounting for 85% of the total. The average annual net income per capita was

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 41

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project RMB 3,750Yuan,which is higher than the net income per capita (RMB 1,575.1Yuan) of rural people in 2007 Year Book of Liyuan Township but lower than RMB 6,500 Yuan of the disposable income per capita of urban people.

The incremental sampled households are urban ones, which is quite different from the sampled households in other subproject areas. However, the income per capita is only RMB 3750 Yuan, which is almost same with it in other subproject areas. Because the is national key poverty county and the economic development is comparatively backward than other subproject areas.

The income structure indicated that the income sources were simplex in the primary sector and all was from commercial vegetable selling. In addition, the income from the primary sector only accounted for tiny part of the total family income. The family income mainly relied on non-farming employment especially the salary income earned by migrant workers, which accounted for 50% of the total. Therefore, land acquisition had minor impact on their production and lives.

5.4.4 Living Quality of the Affected Persons

The houses of the affected persons were built adjacent to grade I terrace alongside the river. They were old stand-alone or two-storied buildings with brick-wood and wooden structures built in 1980’s but the average housing area was limited. These houses were frequently flooded. Generally speaking, their living conditions were poor.

The subproject area is located in the urban area and its infrastructure is quite good. Local people have good access to water, electricity, road, post and telecommunications. It’s convenient for them to see a doctor and for children to go to school.

The sample household survey showed that every hundred household had 4 motocycles, 8 bicycles, 29 TV sets, 17 refrigerators, 13 washing machines, 1 micro-waver, 8 water heaters, 21 telephone sets. 34 out of 100 persons had mobile phones.

5.5 Youzhou, Leiyang, Huaihua and Chenxi

Due to the bad weather condtions mentioned at the beginning of this chapter, Huaihua and Yongzhou subproject resettlement baseline survey was postponed to the next M&E period. Chenxi and Leiyang subproject didn’t start the external resettlement M&E yet.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 42

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 6. Resettlement Implementation Progress

6.1 Resettlement Implementation Schedule

6.1.1 Loudi According to Loudi Resettlement Plan endorsed by Chinese Government and ADB, the

Loudi resettlement implementation schedule is:Preparation works of resettlement implementation started on June 10 2005 and finished on August 18 2006; the preparation period was 14 months; resettlement implementation formally started on February 15 2006 and will finish on February 22 2008; the implementation period is 24 months.

6.1.2 Xinhua

According to Xinhua Resettlement Plan endorsed by Chinese Government and ADB, the Xinhua resettlement implementation schedule is:Preparation works of resettlement implementation started on June 10 2005 and finished on August 18 2006; the preparation period was 14 months; resettlement implementation formally started on February 15 2006 and will finish on December 28 2007; the implementation period is 22 months.

6.1.3 Wugang

According to Wugang Resettlement Plan endorsed by Chinese Government and ADB, the Wugang resettlement implementation schedule is:Preparation works of resettlement implementation started on June 10 2005 and finished on August 18 2006; the preparation period was 14 months; resettlement implementation formally started on February 15 2006 and will finish on May 16 2007; the implementation period is 15 months.

6.1.4 Sangzhi

According to Sangzhi Resettlement Plan endorsed by Chinese Government and ADB, the Sangzhi resettlement implementation schedule is:Preparation works of resettlement implementation started on June 10 2005 and finished on April 21 2006; the preparation

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 43

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project period was 10 months; resettlement implementation formally started on January 18 2006 and will finish on July 27 2007; the implementation period is 18 months.

6.1.5 Huaihua

According to Huaihua Resettlement Plan endorsed by Chinese Government and ADB, the Huaihua resettlement implementation schedule is:Preparation works of resettlement implementation started on June 10 2005 and finished on July 7 2006; the preparation period was 13 months; resettlement implementation formally started on September 15 2005 and will finish on March 11 2008; the implementation period is 30 months.

6.1.6 Yongzhou

According to Yongzhou Resettlement Plan endorsed by Chinese Government and ADB, the Huaihua resettlement implementation schedule is:Preparation works of resettlement implementation started on June 10 2005 and finished on August 17 2006; the preparation period was 14 months; resettlement implementation formally started on September 15 2005 and will finish on April 28 2008; the implementation period is 32 months.

However, due to various factors and constraints, the actual resettlement implementation progress is far behind the schedule, such as difficulties in resettlement fund raising, delayed resettlement fund payment, complicate land acquisition approval procedures. So far, none of the subprojects’ resettlement implementation is according to the original schedules and the actual resettlement implementation is slower than the schedule to various degrees. Therefore, the original schedules are no longer relevant and need to be updated

6.1.7 Chenxi and Leiyang

The land acquisition and resettlement didn’t started yet. The external resettlement M&E work didn’t start either.

6.2 Resettlement Policies and Compensation Standards

6.2.1 Loudi

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 44

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project The adopted resettlement and land acquisition policies and compensation standards are consistent with those stipulated in the Loudi Resettlement Plan. However, the affected are not willing to accept the compensation standards in the Resettlement Plan in fact and sign the resettlement and land acquisition agreement. Therefore, the actually applied standards are substantially higher than those in the Plan. The external resettlement-monitoring agency has reviewed the signed land acquisition and resettlement compensation agreements last time and this time, and confirmed some of the actual applied compensation standards. The relevant details refer to Table 6.2.1-1and Table 6.2.1-2. The actual applied compensation standards are land compensation and resettlement subsidies exclusive the tax and fees. The empty cases in the two tables mean that actual compensation standards remain unclear or the external monitor didn’t find out the exact examples.

Table6.2.1-1 Compensation Standards of Permanent Land Acquisition Comparison

Unit(Yuan/Mu)

The Planned The Actual Applied Land Ownership Land Types Compensation Compensation Standards Standards Paddy Field 15476 41850 Dry Land 10833 26700 Vegetable land 30476 65650 Orchard 15598 Collective Land Fish Pond 16221 Rural Residential Plot 11713 65000 Shrubbery 6373 Timber Forest 7242 Idle Land 1490 10500 Industrial Land 50000 58000 Residential Land 50000 National Land Allocated free of Other Land charge

Table6.2.1-2 Compensation Standards of Relocated Houses Comparison Disparity The Actual The Planned between the Types of Applied Structure Unit Compensation Planned houses Compensation Standards and the Standards Actual Urban Brick-concrete Yuan/m2 423 380~460 Houses Brick-wood Yuan/m2 347 320~380 Earth-wood Yuan/m2 256 240~280

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 45

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Sundry Yuan/m2 80 Houses Brick-concrete Yuan/m2 295 260~330 430~530 Brick-wood Yuan/m2 230 200~260 Rural Wood Yuan/m2 192 170~220 Houses Earth-wood Yuan/m2 150 130~160 Sundry Yuan/m2 60 80 Houses

6.2.2 Xinhua

Some land requested in the Xinhua Subproject had been acquired by the government due to construction of Zexi Reservoir and the relevant affected had been appropriately compensated in the past. However, because most of the affected areas have been farmed by local villagers, compensation as permanent land acquisition will be provided to the affected people. The land acquisition and resettlement policies and standards to be adopted are consistent with those in Xinhua Resettlement Plan in order to guarantee the interests of the affected. During the resettlement implementation, the actual compensation standards are higher than those in the Xinhua Resettlement Plan.

Table 6.2.2-1Compensation Standards of Permanent Land Acquisition Comparison

Unit(Yuan/Mu)

The Planned Compensation The Actual Applied Land Types Standards Compensation Standards Paddy Field 13393 21350 Dry Land 9375 12375 Vegetable Land 18393 25825 Rural Residential Plot 10373 25000 Enterprise Land 13393

There are two categories of house demolition and relocation: backward relocation and centralized relocation. The backward relocation adopts the compensation standards in the Resettlement Plan.

The centralized relocation will provide higher value of shop front housing plots to the relocated households free of charge. The land value of shopfront is much higher than it of housing plot within the original village group. The house compensation consists of two parts: high-valued land and the actual cash compensation.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 46

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 1. High-valued Land

The monitor checked the traded land prices in the land trade center of Xinhua County Land Resource Bureau. These lands are located in Meiyuan Development Zone and three plots of them are close to the resettlement sites.

Table 6.2.2-1 Land Traded Prices in Meiyuan Development Zone

Land The Purpose of Way of No. Reference Location Area m2 Iime of Trading Traded ( ) Land Use Trading No. Price Meiyuan 1 〔2007〕-4 Development 2004.5 Comprehensive 2007.5.16~2007.5.25 330 Public Zone Meiyuan 2 〔2007〕-27 Development 8917 Housing 2007.5.17~2005.5.18 580 Public Zone Meiyuan Commercial& 3 2007 -21 Development 3279 2007.5.19 2007.5.29 290 Public 〔 〕 Housing ~ Zone

Land price for the comprehensive purpose:3300000/2004.5=1646.3 元/m2

Land price for the commercial and housing purpose:5800000/8917=650.44 元/m2

Land price for the housing purpose:2900000/3279=884.42 元/m2

The land only for the housing purpose can satisfy the Xinhua Resettlement Plan but the land for comprehensive purpose is selected by the Xinhua Government. This kind of land is high-valued and traded freely. its average land price is 500~1000 yuan/ m2 higher than that of the land only for the housing purpose. The lower limit is at least 500 yuan/m2 2. Cash Compensation

Confirmed by the monitor, the cash compensation of the rural house is 220Yuan/ m2for brick-concrete, 180Yuan/ m2 for brick-wood and 100 Yuan/ m2 for sundry house respectively.

3. The Actual Implementing House Compensation Standards

According to “The Resettlement and Land Acquisition Implementing Methods for the Urban Planned Area in Xinhua County”,the eligible affected household is allocated 30m2 land for one person family, 30m2 for two person family. For the households with more than 2 persons, each incremental person is allocated each incremental 10m2 land.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 47

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project According to Xinhua Resettlement Plan, the housing demolition affects 32 households with 172 persons. The housing areas to be demolished are 5272m2. Taking the average 5 persons per household, the 172 affected persons need at least 2408m2 land with the value of 1.204 million Yuan. The average cost is 228 Yuan for dismantling1m2 house.

Therefore, the actual implementing compensation standard in Xinhua is at least as followed:

Brick-concrete:220+228=448Yuan/m2;

Brick-wood:180+228=408Yuan/m2;

Sundry House:100+228=328Yuan/m2.

The external resettlement monitors have reviewed the signed resettlement and land acquisition agreements kept in the County Land Resources Bureau and talked with the affected persons who had signed the agreements. The planned and actual compensation standards refer to Table 6.2.2-2. The empty cases in the two tables mean that actual compensation standards remain unclear or the external monitor didn’t find out the exact examples.

Table6.2.2-2The Housing Compensation Standards Comparison of the Centralized Relocation Disparity The Actual The Planned between the Housing Applied Structures Unit Compensation Planned Types Compensation Standards and the Standards Actual Brick-concrete Yuan/m2 327 295~360 448 Rural 2 Houses Brick-wood Yuan/m 270 245~300 408 Sundry Houses Yuan/m2 60 328

6.2.3 Wugang

The adopted resettlement and land acquisition policies and compensation standards are consistent with those stipulated in the Wugang Resettlement Plan. However, the affected are not willing to accept the compensation standards in the Resettlement Plan in fact and sign the resettlement and land acquisition agreement. Therefore, the actually

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 48

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project applied standards are substantially higher than those in the Plan. The external resettlement-monitoring agency has reviewed the signed land acquisition and resettlement compensation agreements this time, and confirmed some of the actual applied compensation standards. The relevant details refer to Table 6.2.3-1and Table 6.2.3-2.

Table 6.2.3-1Compensation Standards of Permanent Land Acquisition Comparison

Unit(Yuan/Mu)

The Planned The Actual Applied Land Ownership Types of Land Compensation Standards Compensation Standards Paddy Field 19013 Dry Land 15137 Collective Land Orchard 19132 Housing Plot 16262 Idle Land 1492 Industrial Land 106720 National Land Housing Plot 60030 Others Allocated free of charge Allocated free of charge

Table6.2.3-2 Compensation Standards of Relocated Houses Comparison Disparity The Actual The Planned Types of between the Applied Structure Unit Compensation houses Planned and Compensation Standards the Actual Standards 2 Brick-concrete Yuan/m 435 400~470 2 Brick-wood Yuan/m 363 340~400 2 Urban House Wood Yuan/m 313 290~340 2 Earth-wood Yuan/m 250 230~270 Sundry House Yuan/m2 80 2 Brick-concrete Yuan/m 292 270~330 288 2 Brick-wood Yuan/m 231 210~260 210~240 2 Rural House Wood Yuan/m 189 170~210 2 Earth-wood Yuan/m 145 130~160 2 Sundry House Yuan/m 60 60~120

6.2.4 Sangzhi at the second resettlement M&E period, the land acquire in Sangzhi is all stated-owned

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 49

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project and allocated for the embankment construction free of charge. No demolition occurred. The following is the summary from the first external M&E.

(1) Land Acquisition Compensation Standards

The resettlement and land acquisition compensation policies and standards to be adopted are consistent with those in the Resettlement Plan. However, the affected are not willing to accept those standards and signed the resettlement and land acquisition agreement during the resettlement implementation. Therefore, the actual compensation standards are higher than the planned in the Resettlement Plan.

(2) House Demolition and Relocation Compensation Standards

There are 4 households relocated in April 2005 and the adopted compensation standards are based on No.〔2004〕27 Document issued by Zhangjiajie Municipal

Government. However, the actual standards are lower than those stipulated in Sangzhi Resettlement Plan. After endorsement of the Resettlement Plan by the local government, house demolition and relocation compensation standards will fully comply with Resettlement Plan.

The external resettlement monitors have reviewed the signed resettlement and land acquisition agreement. The planned and actual compensation standards refer to Table 6.2.4-1 and Table 6.2.4-2. The empty cases in the two tables mean that actual compensation standards remain unclear or the external monitor didn’t find out the exact examples.

Table 6.2.4-1Compensation Standards of Permanent Land Acquisition Comparison

Unit(Yuan/Mu)

The Actual Applied The Planned Land Ownership Land Types Compensation Compensation Standards Standards Paddy Field 10678 45000 Dry Land 7474 45000 Collective Land Vegetable Land 15678 45000 Wet Land 4485 Residential Land 41354 National Land Other land Allocated free of charge

Table6.2.4-2 The Housing Compensation Standards Comparison

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 50

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Disparity Disparity between The Actual between The Planned House the Applied the Structures Unit Compensation Types Planned Compensation Planned Standards and the Standards and the Actual Actual

2 340 260 Brick-concrete Yuan/m 384 ~ 320 ~ 420 360 Urban 2 270~ 210~ Houses Brick-wood Yuan/m 314 220 330 250 Sundry Yuan/m2 80 100 Houses

6.2.5 Huaihua

The adopted resettlement and land acquisition policies and compensation standards are consistent with those stipulated in the Huaihua Resettlement Plan. However, the affected are not willing to accept the compensation standards in the Resettlement Plan in fact and sign the resettlement and land acquisition agreement. Therefore, the actually applied standards are substantially higher than those in the Plan. The external resettlement-monitoring agency has reviewed the signed land acquisition and resettlement compensation agreements this time, and confirmed some of the actual applied compensation standards. The relevant details refer to Table 6.2.5-1and Table 6.2.5-2. The actual applied compensation standards are land compensation and resettlement subsidies exclusive the tax and fees. The empty cases in the two tables mean that actual compensation standards remain unclear or the external monitor didn’t find out the exact examples.

Table 6.2.5-1Compensation Standards of Permanent Land Acquisition Comparison

Unit(Yuan/Mu)

The Actual Applied The Planned Land Ownership Land Types Compensation Compensation Standards Standards Collective Paddy Field 18569 37230 Land Dry Land 11737

Vegetable Land 25569 60000

Economic Forest 16656

Timber Forest 8775

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 51

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Housing Plot 14230

Pond 18059

Others 1530 1530

Housing Land 46690 National Land Others Allocated free of charge

Table 6.2.5-2 The Housing Compensation Standards Comparison

The Actual Disparity between the Type of Compensation Applied Structure Unit Planned and the House Compensation Standard Actual Standards

Brick-concrete Yuan/m2 434 391~477 400 Urban Brick-wood Yuan/m2 362 326 398 350 House ~ Sundry House Yuan/m2

Brick-concrete Yuan/m2 277~339 350

2 Rural Brick-wood Yuan/m 222~272 300 House Wood Yuan/m2 175~213 Sundry House Yuan/m2 140

6.2.6 Yongzhou

The adopted resettlement and land acquisition policies and compensation standards are consistent with those stipulated in the Yongzhou Resettlement Plan. The external resettlement-monitoring agency has reviewed the signed land acquisition and resettlement compensation agreements this time, and confirmed some of the actual applied compensation standards. The relevant details refer to Table 6.2.6-1and Table 6.2.6-2. The actual applied compensation standards are land compensation and

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 52

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project resettlement subsidies exclusive the tax and fees. The empty cases in the two tables mean that actual compensation standards remain unclear or the external monitor didn’t find out the exact examples.

Table 6.2.6-1Compensation Standards of Permanent Land Acquisition Comparison

Unit(Yuan/Mu)

The Planned The Actual Applied Land Ownership Type of Land Compensation Compensation Standards Standards Paddy Field 15040 15040 Dry Land 10688 10688 Vegetable Land 22040 22040 Orchard 14907 Collective Housing Plot 12624 12624 Land Timber Forest 6987 Shrubbery 6534 Pond 14507 Others 1600 Industrial Land 44080 Allocated free of charge National Housing Land 60030 Land Others Allocated free of charge Allocated free of charge

Table 6.2.6-2 The Housing Compensation Standards Comparison

The Actual Applied Type of Compensation Structure Unit Compensation House Standard Standards

Brick-concrete Yuan/m2 482 482

2 Urban Brick-wood Yuan/m 401 401 House Wood 362 362 Sundry House Yuan/m2 100 100 Brick-concrete Yuan/m2 331 331 Brick-wood Yuan/m2 263 263 Rural Wood Yuan/m2 231 231 House Earth-wood 172 172 Sundry House Yuan/m2 80 80

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 53

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 6.2.7 Leiyang and Chenxi

No progress was made so far.

6.3 Land Acquisition Progress

6.3.1 Loudi (1) Land Acquisition Progress

In the second M&E peroid, Loudi Subproject hasn’t implemented the land acquisition. The acquird land is shown as Table 6.3.1-1~6.3.1-2.

(2) Progress of Land Acquisition Approval Procedures

1) Land Acquisition Approval

The land acquisition approval procedures have been completed. The approval documents are Hunan Provincial Government National Construction Land Acquisition Approval Reports (LR: No780), (LR: No1088) and (LR: No1089).

2) Land Acquisition and Resettlement Entrusting Agreement Signing

Loudi PMO had signed the land acquisition and resettlement entrusting agreement with Loudi Municipal Land Acquisition and Resettlement Office.

3) Land Acquisition and Resettlement Agreement signing with the Affected Groups

Loudi PMO had signed land acquisition and resettlement agreement with the affected groups and the relevant fund had been allocated to the related villages, groups and communities. After the village and the village group meeting, the compensation was delivered to each affected person.

Table 6.3.1-1 Land Acquisition Implementation Progress

Unit ( Mu) The planned Land Acquisition The Actual Completed Land % of Completed Land Areas Acquisition Areas Acquisition Areas Item Collective National Collective National Collective National Subtotal Subtotal Subtotal Land Land Land Land Land Land Number 1589.55 1528.72 60.83 504.815 504.815 0 31.76% 33.02% 0 Remark

Table6.3.1-2 Land Acquisition Implementation Progress Statistics

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 54

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Acquired Land Total Nature of Relocated Fund No. Chainage Name of the Affected Groups Areas Fund Progress Land House Area Paid (Mu) (104 Yuan) 1 2+840~5+059 Maotang and Xinarenqiao Villages 138.768 Collective No 343.57 paid 100% 2 0+450~2+840 Maotang and Lianbin villages 185.124 Collective No implementation 1222.689 75% Land Mineral Trade 3 1+687 1+968 35 Collective No 203.93 Paid 100% ~ Reserve Center 4 2+896~4+290 Dui Cun village 124.816 Collective No implementation 742.019 Paid 100% 5 0+000~0+674 Daqiao Community 15.396 Collective No implementation 68.6 Paid 100% 6 0+000~0+674 Huashan Community 5.711 Collective No implementation 30.56 Paid 100% ubtotal 504.815 2611.37 Note: 75% of the affected groups have signed the land acquisition agreement in Chainage No.2.

6.3.2 Xinhua

(1) Land Acquisition Progress

The detailed land acquisition progress refers to Table 6.3.2-1 and Table 6.3.2-2.

Table 6.3.2-1 Land Acquisition Implementation Progress

unit(Mu)

The planned Land Acquisition The Actual Completed Land % of Completed Land Areas Acquisition Areas Acquisition Areas Timing Collective National Collective National Collective National Subtotal Subtotal Subtotal land Land land Land land Land 1st 177.428 0 177.428 37.48% M&E 473.4 473.4 0 2nd 205.112 205.112 43.33% M&E Some land requested in the Xinhua Subproject had been acquired by the government due to construction of Zexi Reservoir and the relevant affected had been appropriately compensated in the Remark past. However, because most of the affected areas have been farmed by local villagers, compensation as permanent land acquisition will be provided to the affected people

Table 6.3.2-2 Land Acquisition Implementation Progress Statistics

Relocated Total Fund Acquired Land Fund Paid Nature of House No. Chainage Name of the Affected Groups Areas 4 4 Progress Land Area (10 (10 (Mu) 2 (m ) Yuan) Yuan) Shangdu Sub-district 1 175.927 National 1267 366.83 366.83 100% Group 4 of Baisha Village Shangdu Sub-district 2 1.501 National / 3.2 3.2 100% Group 4 of Baisha Village Shangdu Sub-district 27.684 National / 62.7205 62.7205 100% Group 5 of Baisha Village

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 55

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Subtotal 205.112 1267 432.3 432.3 100% (2) Progress of Land Acquisition Approval Procedures

1) Land Acquisition Approval Procedures

The land acquisition pre-appraisal procedures were completed and the formal approval was under the way.

2) Land Acquisition and Resettlement Entrusting Agreement Signing

Arranged by Xinhua County Government, Xinhua PMO had signed the land acquisition and resettlement entrusting agreement with Xinhua County Land Acquisition and Resettlement Office.

3) Land Acquisition and Resettlement Agreement signing with the Affected Groups

Loudi PMO had signed land acquisition and resettlement agreement with the affected groups and the relevant fund had been allocated to the related villages, groups and communities. After the village and the village group meeting, the compensation was delivered to each affected person. The monitor checked this and found that every affected household had got the compensation.

6.3.3 Wugang

(1) Land Acquisition Progress

The detailed land acquisition progress refers to Table 6.3.3-1 and Table 6.3.3-2.

Table 6.3.3-1 Land Acquisition Implementation Progress

Unit(Mu)

The planned Land Acquisition The Actual Completed Land % of Completed Land Areas Acquisition Areas Acquisition Areas Item Collective National Collective National Collective National Subtotal Subtotal Subtotal land Land land Land land Land 1st 24.95 0 24.95 11.43% 42.63% M&E 218.27 159.74 58.53 2nd 112.21 87.26 24.95 51.4% 54.63% 42.63% M&E Remark

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 56

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Table 6.3.3-2 Land Acquisition Implementation Progress Statistics

Reloca Total Fund Acquired Natur ted Fund Paid Name of the Land Progre No Chainage e of House 4 4 Remark Affected Groups Area (10 (10 ss Land Area (mu) (m2) Yuan) Yuan) Yudaiqiao~ Allocated 3+781 Natio ~ Dongta 14.45 No No No 100% free of nal 1st 4+469 charge M&E Xiaojiaba~ Allocated 3+578 Natio ~ Yudaiqiao 10.5 No No No 100% free of nal 4+078 charge 1+929~ Yuanmenkou 2+957 Colle 69.544 Collective Subdistrict 30.6 No ctive 69.5442 100% Land 2nd 1+984~ Gexin Village 2 M&E 2+695 Yuanmenkou 1+636~ Colle 126.65 Collective Subdistrict 56.66 No ctive 126.6513 100% Land 3+136 Ziyuan Village 13 Subt 112.21 196.2 196.2 otal (2) Progress of Land Acquisition Approval Procedures

1) Land Acquisition Approval Procedures

The land acquisition pre-appraisal procedures were completed. The land acquisition approval was under the way.

2) Land Acquisition and Resettlement Entrusting Agreement Signing

Arranged by Wugang County Government, Wugang PMO had signed the land acquisition and resettlement entrusting agreement with Wugang Municipal Land Acquisition and Resettlement Office.

3) Land Acquisition and Resettlement Agreement signing with the Affected Groups

The land acquisition and resettlement agreements were signed and the relevant fund was allocated to the related villages, groups and communities. After the village and the village group meeting, the compensation was delivered to each affected person. The monitor checked this and found that every affected household had got the compensation.

6.3.4 Sangzhi

(1) Land Acquisition Progress

The detailed land acquisition progress refers to Table 6.3.4-1 and Table 6.3.4-2.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 57

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Table 6.3.4-1 Land Acquisition Implementation Progress Unit (Mu) The planned Land Acquisition The Actual Completed Land % of Completed Land Areas Acquisition Areas Acquisition Areas Item Collective National Collective National Collective National Subtotal Subtotal Subtotal land Land land Land land Land 1st 44.546 44.546 0 65.93% 81.69% M&E 67.57 54.53 13.04 2nd 110.31 44.55 65.76 163 81.69 504.3 M&E % % % Remark

Table 6.3.4-2 Land Acquisition Implementation Progress Statistics

Acquired Relocated Total Fund Name of the Affected Nature No. Chainage Land Area House Area Fund Paid Progress Groups Of Land (mu) (m2) (104 Yuan) (104 Yuan) 1st Gaojiaping 0+000 1+570 44.546 Collective 1239.19 204.68 204.68 100% M&E ~ Residential Committee 2nd Wuliqiao Residential Allocated free National No 100% M&E Committee 27.342 Of Charge Wenming Road Allocated free Residential National No 100% 38.4225 Of Charge Committee 合计 110.31 1239.19 204.68 204.69 (2) Progress of Land Acquisition Approval Procedures

1) Land Acquisition Approval Procedures

The land acquisition approval procedures have been completed. Some paperwork has to go through for those allocated national land.

2) Land Acquisition and Resettlement Entrusting Agreement Signing

Wugang PMO had signed the real estate entrusting agreement with Zhangjiajie Hengtai Real Estate Assessment Company and the real estate measure entrusting agreement with Sangzhi County Housing Measure Team.

3) Land Acquisition and Resettlement Agreement signing with the Affected Groups

The land acquisition and resettlement agreements were signed and the relevant fund was allocated to the related villages, groups and communities. After the village and the village group meeting, the compensation was delivered to each affected person. The monitor checked this and found that every affected household had got the compensation.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 58

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 6.3.5 Huaihua (1) Land Acquisition Progress

The detailed land acquisition progress refers to Table 6.3.5-1 and Table 6.3.5-2.

Table 6.3.5-1 Land Acquisition Implementation Progress Unit (Mu) The planned Land Acquisition The Actual Completed Land % of Completed Land Areas Acquisition Areas Acquisition Areas Item Collective National Collective National Collective National Subtotal Subtotal Subtotal Land Land Land Land Land Land Number 422.26 397.26 25.4 343.52 343.52 0 81.35% 86.47% 0 Remark

Table 6.3.5.-2 Land Acquisition Implementation Progress Statistics

Relocated Acquired Land Total Fund Nature of House No. Chainage Name of the Affected Groups Areas Fund Paid Progress Land Area (Mu) 2 (Yuan) (Yuan) (m ) Hutianqiao Village 292.19 Collective 20802508 20802508 100% Taipingxi Yingkou Town 26.647 Collective 1855266.4 1855266.4 100% Phase 1 Civil Works Xichong Village 17.543 Collective 1171437.8 1171437.8 100% Hongxing Village 7.145 Collective 437274 437274 100% 343.525 24266486.2 24266486.2 (2) Progress of Land Acquisition Approval Procedures

1) Land Acquisition Approval Procedures

The land acquisition approval procedures have been completed. The approval Number is No173(2006) document Sheet approved by Hunan Provincial Government.

2) Land Acquisition and Resettlement Entrusting Agreement Signing

Huaihua PMO had signed the agreement with the Resettlement Division under the Subproject Leading Group. The division is staffed from the Land Acquisition and Demolition Office under Huaihua Land Resource Bureau. . 3) Land Acquisition and Resettlement Agreement signing with the Affected Groups

The land acquisition and resettlement agreements were signed and the relevant fund was allocated to the related villages, groups and communities. After the village and the village group meeting, the compensation was delivered to each affected person. The monitor checked this and found that every affected household had got the compensation.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 59

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 6.3.6 Yongzhou (1) Land Acquisition Progress

The detailed land acquisition progress refers to Table 6.3.6-1 and Table 6.3.6-2.

Table 6.3.6-1 Land Acquisition Implementation Progress Unit (Mu) The planned Land Acquisition The Actual Completed Land % of Completed Land Areas Acquisition Areas Acquisition Areas Item Collective National Collective National Collective National Subtotal Subtotal Subtotal Land Land Land Land Land Land 190.82 Number 914.24 745.69 168.55 367.274 45.644 321.63 40.17% 6.12% % Remark

Table 6.3.6.-2 Land Acquisition Implementation Progress Statistics

Relocated Fund Acquired Land Total Paid Name of the Nature of House No. Chainage Areas Fund Progress Affected Groups Land Area ( (Mu) 2 (Yuan) (m ) Yuan) Lengshuitan Hexi Xiaoxiang Hdyro- Allocated National 20% 1+921~3+481.74 Power Station 120.7 Free Xiangjiang Lengshuitan Hexi Allocated Paper-making National 15% 11+448.42~13+370.91 Free Company Ltd 66 Yongzhou Lengshuitan Hedong Allocated Municipal National 100% 0+000~2+800 Free Government 134.93 Chaoyang Sub district Dongyuegong Collective 100% Of Linging District Community 45.644 1401254.19 1401254.19 Sub

Total 367.274 (2) Progress of Land Acquisition Approval Procedures

1) Land Acquisition Approval Procedures

The land acquisition pre-appraisal is under the way.

2) Land Acquisition and Resettlement Entrusting Agreement Signing

LPMO had signed the agreement with Yongzhou Land Acquisition and Demolition Office and Lingling Land Acquisition and Demolition Office respectively, who are responsible for implementing land acquisition and house demolition. 3) Land Acquisition and Resettlement Agreement signing with the Affected Groups

The land acquisition and resettlement agreements were signed and the relevant fund was allocated to the related villages, groups and communities. After the village and the

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 60

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project village group meeting, the compensation was delivered to each affected person. The monitor checked this and found that every affected household had got the compensation.

6.3.7 Chenxi and Leiyang The resettlement M&E didn’t start yet in these two subprojects.

6.4 House Demolition and Relocation Progress

6.4.1 Loudi (1) House Demolition Progress

The detailed house demolition progress refers to Table 6.4.1-1 and Table 6.4.1-2 against the Loudi Resettlement Plan.

Table 6.4.1-1 House Demolition Comparison with Resettlement Plan Item Unit Number Remark The Planned Demolished House 2 m 30723.26 Areas Planned The Planned Relocated HH 151 Household The Planned Relocated Persons Person 488 Only sundry The Actual Completed Housing 2 m 56.2 houses were Demolition Areas demolished Completed Only sundry During the The actual Relocated st HH 0 houses were 1 M&E Households demolished Period Only sundry The Actual Relocated Persons Person 0 houses were demolished % of % of the Completed House 0.18% completed Demolition Area During the % of the Completed Relocated st 1 M&E Household Period % of the Completed Relocated

Persons The Actual Completed Housing 2 Completed m 1382.52 During the Demolition Areas nd The actual Relocated 2 M&E HH 6 Period Households Accumulated The Actual Relocated Persons Person 21 % of % of the Completed House

completed Demolition Area 4.5% During the % of the Completed Relocated nd 2 M&E Household 4.0% Period % of the Completed Relocated Accumulated Persons 4.3%

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 61

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

(2)Relocation Progress

The relocation progress refers to Table 6.4.1-2。

Table 6.4.1-2 Relocation Progress Comparison with the Resettlement plan Town/Township Item Unit Number Remark ( sub-district) Total HH 151 Relocated Persons Persons 488 Lianbin and Cash HH 19 Huashan two Compensation sub-districts Relocation Persons 62 Planned Lianbin, HH 115 Huashan and Property Huangnitang 3 Adjustment Persons 359 sub-districts Dapu and Scattered HH 17 Huashan Backward Sub-district Relocation Persons 67 Completed No progress in the 1st M&E period Completed Lianbin, in the 2nd Huashan and Property The resettlement sites are under 0 0 The construction and the relocated M&E Huangnitang 3 Adjustment Households are in the transit period. period subdistricts

6.4.2 Xinhua

(1) House Demolition Progress

The detailed house demolition progress refers to Table 6.4.2-1.

Table 6.4.2-1 House Demolition Comparison with Resettlement Plan Item Unit Number Remark The Planned Demolished House 2 m 5272 Areas Planned The Planned Relocated HH 32 Household The Planned Relocated Persons Persons 172 Completed The Actual Completed Housing 2 All adopt the property m 1267 During the Demolition Areas adjustment relocation

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 62

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

1st M&E The actual Relocated method. HH 5 Period Households The Actual Relocated Persons Persons 23 % of the Completed House % of 24.03% Demolition Area Completed % of the Completed Relocated During the 15.63% st Household 1 M&E % of the Completed Relocated Period 13.37% Persons The Actual Completed Housing 2 Completed m 1955.93 During the Demolition Areas nd The Actual Relocated 2 M&E HH 8 Period Households Accumulated The Actual Relocated Persons Persons 38 % of % of the Completed House 37.1% Completed Demolition Area During the % of the Completed Relocated nd 2 M&E Household 25% Period % of the Completed Relocated

Accumulated Persons 22.1%

(2)Relocation Progress

The relocation progress refers to Table 6.4.2-2 against the Resettlement Plan.

Xinhua County Government has arranged 4 resettlement sites, namely Nongfeng Relocation Street, Baisha Relocation Site, Tangjialing Relocation site and Laiziling Relocation site. All of them are higher value of shop front houses close to the commercial areas. So far, all relocated households live in these 4 resettlement sites and become urban citizens.

Before the relocated households started to construct their new houses, the ground leveling and service of road, water and electricity had been completed. The new houses will follow the higher building standards and the compensation fund may not cover all the money needed to build the new houses. So the affected persons may have to find alternative sources of funding. There are two ways of construction new houses. For richer relocated households, they will build their new houses themselves. However, for the relocated households with limited financial capacity, they will build their new houses by cooperation with others. The relocated households provide the housing plots and the investors provide the money. The newly built houses will be shared between them according to the signed agreement beforehand. Since these shop fronts have great potential of appreciation, more and more investors are seeking the cooperation

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 63

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project opportunities with the relocated households. So far, the external monitor didn’t see any evidence showing that the relocated households are not able to build the new house due to lack of money.

The relocated households with the shop fronts don’t have reallocated farmland. Because the benefits from shop fronts are greater than those from farming, all relocated households are willing to live there.

Table 6.4.2-2 House Relocation Progress Comparison Village Item Unit Number Remark Meiyuan Relocated HH 32 Development Zone Households Persons 172 5 villages including HH 32 Planned Scattered Backward Shangdu, Ziyuan, Resettlement within Baisha, Zijiang and the Group Persons 172 Nongfeng Relocated HH 5 Completed Baisha Village Households Persons 23 In the 1st M&E HH 5 period Baisha Village Property Adjustment Persons 23 % of Completed Meiyuan Relocated HH(%) 15.63% st in the 1 M&E period Development Zone Households Persons(%) 13.37% Relocated Completed HH 8 Baisha Village Households In the 2nd M&E Accumulated Persons 38 period HH 8 Accumulated Baisha Village Property Adjustment Persons 38 % of Completed HH(%) 25% in the 2nd M&E Relocated Baisha Village period Households Persons(%) 22.1% Accumulated

6.4.3 Wugang

(1) House Demolition Progress The house demolition progress made refers to Table 6.4.3-1 against the Resettlement Plan.

Table 6.4.3-1 House Demolition Comparison with Resettlement Plan Item Unit Number Remark The Planned Demolished House 2 Planned m Areas 14486.48 The Planned Relocated HH Household 196

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 64

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

The Planned Relocated Persons Persons 792

The Actual Completed Housing 2 Completed m 0 Demolition Areas During the st The actual Relocated 1 M&E HH 0 Households Period The Actual Relocated Persons Persons 0 % of the Completed House % of Demolition Area Completed % of the Completed Relocated During the st Household 1 M&E % of the Completed Relocated Period Persons The Actual Completed Housing 2 Completed m 652.78 During the Demolition Areas nd The Actual Relocated 2 M&E HH 17 Period Households Accumulated The Actual Relocated Persons Persons 77 % of % of the Completed House

Completed Demolition Area 4.5% During the % of the Completed Relocated nd 2 M&E Household 8.7% Period % of the Completed Relocated

Accumulated Persons 9.7% (2)Relocation Progress

The relocation progress refers to Table 6.4.3-2 against the Resettlement Plan.

Table 6.4.3-2 House Relocation Progress Comparison

Town(Sub-district) Item Unit Number Remark Relocated HH 196

Person Person 792 Yingchunting HH 43 Cash And Yuanmenkou Sub Compensation Person 135 districts Planned Yingchunting HH 112 Property And Yuanmenkou Sub Adjustment Person 486 districts Scattered HH 41 Yuanmenkou Subdistrict Backward Anle Town Person 171 Resettlement Completed in the 1st M&E No period Completed in the 2nd M&E Yuanmenkou Cash HH 17 period Subdisctrict Compensation Accumulated Person 77 % of HH 8.7% Completed Cash nd During the 2 Yuanmenkou Compensation M&E Subdisctrict 安置 Person 9.7% Period Accumulated

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 65

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

6.4.4 Sangzhi

(1) House Demolition Progress

No progress was made in implementing house demolition in the 2nd M&E period. The detailed house demolition progress refers to Table 6.4.4-1.

(2) Relocation Progress

The relocation progress refers to Table 6.4.4-2.

Table 6.4.4-1 House Demolition Comparison with Resettlement Plan Item Unit Number Remark The Planned Demolished House 2 m 16860.04 Areas Planned The Planned Relocated Household HH 43 The Planned Relocated Persons Persons 201 The Actual Completed Housing 2 Completed in m 1239.19 Demolition Areas the 1st M&E The actual Relocated Households HH 4 period The Actual Relocated Persons Persons 12 % of the Completed House 7.35% % of Demolition Area Completed % of the Completed Relocated st 9.30% in the 1 Household M&E period % of the Completed Relocated 5.97% persons The Actual Completed Housing 2 Completed in m Demolition Areas 1239.19 the 2nd M&E period The actual Relocated Households HH 4 No progress Accumulated was made in The Actual Relocated Persons Persons 12 implementing % of the Completed House house % of Demolition Area 7.35% demolition in Completed in the 2nd M&E nd % of the Completed Relocated the 2 M&E period Household 9.30% period % of the Completed Relocated Accumulated persons 5.97%

Table 6.4.4-2 House Relocation Progress Comparison Residential Item Unit Number Remark Committee

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 66

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Relocated Liyuan Township HH 43 Households Persons 201 Wenming Road, Heping Cash HH 18 Planned Street and Wangjiaping Compensation Persons 88 Wenming Road, Heping HH 25 Property Road and Wenchang Adjustment Persons 113 Street Relocated HH 4 Liyuan Township Households Persons 12 Cash HH 4 Completed Heping Road Compensation Persons 12 Property HH

Adjustment Persons Relocated HH(%) 9.30%

Households % of Completed Persons(%) 5.97% Cash HH 22.22%

Compensation Persons 13.64% No progress was made in implementing house demolition and relocation in the 2nd M&E Remark period

6.4.5 Huaihua

(1) House Demolition Progress The house demolition progress made refers to Table 6.4.5-1 against the Resettlement Plan. Table 6.4.5-1 House Demolition Comparison with Resettlement Plan Item Unit Number Remark The Planned Demolished House 2 m Areas 24232.24 Planned The Planned Relocated Household HH 139 The Planned Relocated Persons Persons 483

The Actual Completed Housing 2 m Demolition Areas 3759.25 Completed The actual Relocated Households HH 27 The Actual Relocated Persons Persons 101 % of the Completed House

Demolition Area 15.51% % of % of the Completed Relocated Completed Household 19.42%

% of the Completed Relocated

persons 21% (2) Relocation Progress

The relocation progress refers to Table 6.4.5-2.

Table 6.4.5-2 House Relocation Progress Comparison

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 67

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Town/township Item Unit Number Remark (Subdistrict) Total HH 139 Relocated Person 483 Household Hongxing Subdistrict HH 124 Property Planned And its Administrative Offices Exchange Person 407

Scattered HH 15 Yingkou Town Backward Person 76 Resettlement Total HH 27 Relocated Person 101 Household Completed Hongxing Subdistrict and Property HH 14 Yingkou Town Exchange Person 57 Hongxing Subdistrict and Cash HH 13 Yingkou Town Compensation Person 44

6.4.6 Yongzhou (1) House Demolition Progress The house demolition progress made refers to Table 6.4.6-1 against the Resettlement Plan. Table 6.4.6-1 House Demolition Comparison with Resettlement Plan Item Unit Number Remark The Planned Demolished House 2 m Areas 40694.07 Planned The Planned Relocated Household HH 313 The Planned Relocated Persons Persons 1121

The Actual Completed Housing 2 m Demolition Areas 8558.8 Completed The actual Relocated Households HH 89 The Actual Relocated Persons Persons 303 % of the Completed House

Demolition Area 21% % of % of the Completed Relocated Completed Household 28.43%

% of the Completed Relocated

persons 27.03% (2) Relocation Progress

The relocation progress refers to Table 6.4.6-2.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 68

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Table 6.4.6-2 House Relocation Progress Comparison

Town/township Item Unit Number Remark (Subdistrict) Total HH 313 Relocated Person 1121 Household Xujiajing, Chaoyang, HH 290 Nanjingdu, Lingjiaoshan, Property Planned Yangjiaqiao, Xiaojiayuan Exchange Person 1014 Subdistricts

Scattered HH 23 Qilidian, Zhaoyang, Backward Nanjingdu and Maojiangqiao Person 107 Resettlement Total HH 89 Relocated Person 303 Household Completed Zhaoyang, Nanjingdu and Property HH 61 Maojiangqiao Exchange Person 211 Zhaoyang, Nanjingdu and Cash HH 28 Maojiangqiao Compensation Person 92

6.4.7 Chenxi and Leiyang The external resettlement M&E didn’t start yet for these two subprojects.

6.5 Enterprise and Government Agencies Relocation Progress

6.5.1 Loudi (1) Enterprise and Institution Relocation Plan

According to Resettlement Plan, there are 18 affected enterprises and institutions in the Loudi Subproject including 16 enterprises. Only management buildings or auxiliary production buildings are affected within these enterprises. Therefore, these enterprises didn’t need to be relocated totally. The subproject construction has minor impact on these enterprises’ production, operation and daily activities. In addition, there are 2 institutions affected in the subproject. However, only part of their buildings is affected and didn’t need to be relocated completely. The institutions can coordinate offices within themselves or construct the substitute buildings.

(2) The Completed Enterprise and Institution Relocation

No progress had been made in this regard.

6.5.2 Xinhua

(1) Enterprise and Institution Relocation Plan

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 69

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project According to Resettlement Plan, there are 4 affected enterprises and institutions in the Xinhua Subproject including 3 enterprises. All of these enterprises need to be relocated completely. The subproject construction will affect these enterprises’ production and operation. There is only one institution affected in the subproject and it needs to be relocated completely.

(2) The Completed Enterprise and Institution Relocation

No progress had been made in this regard.

6.5.3 Wugang

(1) Enterprise and Institution Relocation Plan

According to Resettlement Plan, there are 11 affected enterprises and institutions in the Wugang Subproject including 9 enterprises. 2 enterprises need to be relocated completely. Only management buildings or auxiliary production buildings are affected in the other remaining 7 enterprises. The subproject construction has minor impact on their production, operation and daily activities. There are 2 affected institutions affected in the subproject. The institutions can coordinate offices within themselves or construct the substitute buildings.

(2) The Completed Enterprise and Institution Relocation

Wugang Water Supply Company has relocated. It’s a state-owned enterprise and its main business is to supply water for the city. The total land occupation area is 18mu and the land is state-owned. The acquired land so far is 1.2mu and the demolished house areas are 865.31m2. The land acquisition and resettlement impact is slight. The compensation is delivered to the Company.

6.5.4 Sangzhi

(1) Enterprise and Institution Relocation Plan

According to Resettlement Plan, there are 8 affected enterprises and institutions in the Sangzhi Subproject including 2 enterprises. Only one of two enterprises needs to be relocated completely. For the other one, only management buildings or auxiliary production buildings are affected. The subproject construction has minor impact on their production, operation and daily activities. There are 6 affected institutions affected in the

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 70

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project subproject. The institutions can coordinate offices within themselves or construct the substitute buildings.

(2) The Completed Enterprise and Institution Relocation

One enterprise has relocated, that’s Sangzhi Ethnic Chinese Medicine Hospital. The hospital is state-owned and operated well. It has 350 full-time employees and about 50 temporary staffs. The original land area was 13mu and the land is state-owned. The acquired land is 13mu and the demolished house is 2000m2 and the affected persons are 400. Before its relocation, a new site was selected and a new hospital had been built. It was demolished in July 2005 and it was back to normal operation in July 2005.

6.5.5 Huaihua

(1) Enterprise and Institution Relocation Plan

According to Resettlement Plan, there are 8 affected enterprises and institutions. The total affected employees are 210 and the land occupation areas are 67mu. 4 of those enterprises are affected only residential buildings or auxiliary production buildings. Therefore, the subproject construction has little impact on their normal operation. 4 of those institutions are affected only residential buildings or auxiliary production buildings. None of them need to be relocated completely. They could have internal adjustment within their different offices or build new alternative buildings.

(2) The Relocated Enterprise and Institution

3 enterprises and institutions have relocated, namely the Metal Smelting Plant, Cotton Wool Processing Plant and Plastic Making Plant. These three plants are all collective nature. Their total employees are 47 and the land occupation areas are 8.1mu in total. The compensation fund is RMB 280,000 Yuan for them. They were relocated completely in May 2007 and new plants had been set up in the new relocation sites.

6.5.6 Yongzhou

(1) Enterprise and Institution Relocation Plan

According to Resettlement Plan, there are 32 affected enterprises and institutions. The affected employees are 7881 in total. The land acquisition areas are 2021.19mu in total.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 71

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project The total affected enterprises are 28 and their total employees are 7700. The land areas are 1863.29mu in total. The subproject construction only affected their administrative buildings or auxiliary production buildings, which have little impact on their normal operation. 4 of these institutions are affected whose total employees are 181. The total land occupation areas are 157.9mu. Only parts of their buildings are affected, so they need not to be relocated completely. They could have internal adjustment within their different offices or build new alternative buildings.

6.5.7 Leiyang and Chenxi

The resettlement M&E didn’t start yet.

6.5.8 the affected Individual Shops

According to the Resettlement Plan, the affected individual shops are shown in Table 6.5.8-1.

Table 6.5.8-1 The Affected Individual Shops

The Total Affected The Total The Total The Total Employees Worked Household Population Subproject Affected Affected Affected for % % Households Population Individual Shops These Shops

Loudi 151 488 94 170 62% 35%

Xinua 32 172 0 0 0% 0%

Sangzhi 43 201 8 40 19% 20%

Wugang 196 792 22 36 11% 5%

Huaihua 139 482 1 3 1% 1%

Yongzhou 313 1121 11 17 4% 2%

Leiyang 95 409 3 7 3% 2%

Chenxi 6 26 2 5 33% 19% The monitor noted that the affected individual shops were not treated as a standalone category when they were compensated in all subproject areas.

LPMO responded that the affected individual shops are all in small scale and serve only the local community such as shoe repairing, keys repairing, mat making, tailor, small restaurant and small general merchandises. Moreover, most of them are located in the margin area of the city and frequently flooded. When these shops are appraised by the

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 72

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project asset assessment agency, their commercial value has been taken into account and the additional preferable measurements are provided. It’s also the normal practice of the urban demolition.

The monitor had the sampled surveys on these groups of individual shops and found that they had been compensated for their business disruption. However, they were not satisfied with the relocation sites. They thought they were different from the common residents and they need the good places, namely shopfronts with convenient access so that they could start their business again. Actually they were treated same with the common affected households and no special relocation arrangement was made for them particularly.

The monitor has requested the LPMO to regard these affected individual shops as a standalone category when being compensated. The information relevant to the individual shop’s demolition and relocation should be kept separately. The special relocation method should also be made. The monitor will follow up this matter in the subsequent M&E report.

6.6 Resettlement Site Construction Progress

The monitor noted that the actual resettlement site constructions are quite different from what have designed in the Resettlement Plans. The monitor was told that the resettlement site selection and construction were closely relevant to the affected persons and the governments. They had to have discussions several times so that all parties were happy with the outcomes. The different resettlement sites have the implication of different land values, which is also the focal point of all parties concerned. The infrastructure at the resettlement sites is not the issue because the subprojects are largely located at the suburban areas or urban areas. Table 6.6-1 has a comparison between the actual resettlement site construction and the designed in the Resettlement Plan.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 73

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Table 6.6.-1 Resettlement Site Construction Progress Against the Designed in the Resettlement Plan

The Implementation Plan and the Progress Made

The Planned Implementation Sub- Resettlement Plan Resettlement Design Progress Remark project Date of Site Location Contractor Invest- Investment Physical Completion Name Scale ment Made Progress (104Yuan) (104Yuan) Measure of earth embankment Qingtan completed; Qingtan Residential 53mu signing the Committee It’s planned to build one centralized agreements Resettlement site called Maotang with the Loudi Resettlement Site. 16.62mu paddy field affected village will be leveled as the housing plot. Lianbing Lianbin 25mu Not started yet Village Village

Maotang Maotan 26mu Not started yet Village

It’s planned to relocate the affected Xinhua persons with scattered backward East end of Urban and Xinhu resettlement adjacent to the original Baisha Zijiang No.2 Development 80% 2007.12.30 village group Bridge Investment Company

Xinhua Urban and Tangjialing Xuefu Road Development 70% 2007.12.30 Investment Company

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 74

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Xinhua Urban and Lanziling Xuefu Road Development 100% 2008.3.1 Investment Company Xinhua Urban and Zijiang Zijiang Development 20% 2008.12.30 Village Investment Company Flood The planning It’s planned to build a centralized Group 2, 3 of Control Hunan and design resettlement site. It’s initially decided that Zijiang Embankment Donggang completed; Wugang the Fengrenmiao area is the new Village in 8Mu 50 20 Resettlement Construction land resettlement site for the property Yuanmenkou Site Company acquisition adjustment. Sub-district completed

The Implementation Plan and the Progress Made

Sub- The Planned Implementation Resettlement Plan Remark Project Resettlement Design Progress Date of Site Location Contractor Invest- Investment Completion Name Physical Scale ment Made Progress (104Yuan) (104Yuan) It’s planned that the Shangjiaping in Sangzhi Wenming Road Residential Committee Construction Group 2 of Sangzhi is the new resettlement site in the new Wanjiaping and 50mu 225 100% 2008.01 Wanjiaping location for property exchange. The Installation apartment is planned to build for all the Company

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 75

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Sangzhi Xiantian- Construction Xiaotianchong chong and 40MU 180 100% 2008.02 Group Installation Company Group 11 of Taipingxi It’s planned that the Yinyuan Community Tianqiao Project 169shop Implementing Huaihua is the new resettlement site for property Village in Resettlement fronts Demolition exchange Yingkou Site Township It’s planned that the Hedong Residential Lengshuitan Committee is the new resettlement site No District For property exchange Nanmenkou Resettlement Nanmenkou 80mu Community of Hedong Maojiangqiao Resettlement Risheng 70mu Community Avenue Of Hedong It’s planned that Huilongta Community Honglongta Lingling and Nanmenkou Community are the new Resettlement Huilongta District resettlement sites 60mu Community Road For property exchange Of Hedong Road North Network Pingyang North Construction Road Pingyang Company of 23mu 470 100% 470 2007.12 Resettlement Road Southern Community Railway Station

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 76

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

6.7 Resettlement Fund Delivery

So far, the major resettlement fund is used for land and building compensation. Since the types of land and houses are different, the resultant unit price is variable. Therefore, the table below didn’t have a comparative analysis on the unit price but presented a comparison on the planned resettlement fund and the actual spent resettlement fund.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 77

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Table 6.7 The Planned Resettlement Fund And The Actual Spent Resettlement Fund

Loudi Xinhua Wugang

Planned Actually Accumulated Spent Planned Actually Accumulated Spent Planned Actually Accumulated Spent Item The Total The Total The Total The Total Spent The Total Spent The Total Spent Planned % Planned Planned 4 4 % 4 % 4 (10 Yuan) 4 (10 Yuan) 4 (10 Yuan) (10 Yuan) (10 Yuan) (10 Yuan)

A. Resettlement Compensation 3997.29 2717.5 67.98% 959.64 477.7 49.78% 1205.63 223.15 18.51%

1. Land Compensation 1860.39 2611.37 140.37% 618.13 432.3 69.94% 354.86 196.2 55.29% 2.House and Auxiliary 1934.84 76.27 3.94% 264.1 45.4 17.19% 658.21 21.95 3.33% Facilities 3. Infrastructure 73.2 30.96 118.8 4. Relocation Transportation 29.28 10.32 31.68 Fee 5. Scattered trees 0.15 0.4 0.1 6. Compensation for Enterprises 51.22 29.86 58.30% 26.91 0.00% 27.87 5 17.94% And Institutions 7. Small shops 10.26 8.82 3.98 8. Vulnerable Group Subsidy 37.95 10.13 9. Tombs

B. Specialized Facilities 231.63 68.79 62.37 1.Transporation Facility 74.6 5 55.2 2. Transmission and 23.03 33.49 2.62 Transformation Facility 3. Water Resources Facility 129.5 21.9

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 78

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Loudi Xinhua Wugang

Planned Actually Accumulated Spent Planned Actually Accumulated Spent Planned Actually Accumulated Spent

4.Telecommunciation Facility 4.5 7 4.55 5. Cable TV 1.4

C. Others 410.76 102 24.83% 121.24 63.7 52.54% 141.88 78.08 55.03%

1. Cost for Survey, Design and 126.87 20 15.76% 30.85 30.85 100.00% 38.04 38.04 100.00% Scientific Research

2. Implementation Management Cost 126.87 80 63.06% 30.85 30.85 100.00% 38.04 38.04 100.00% 3. Implementation Agency Initiation Cost 73.6 39.31 40.75 4. Technical Training Cost 19.99 2 10.01% 4.8 2 41.67% 6.03 2 33.17% 5. M & E Cost 63.43 15.43 19.02

D. Basic Contingency Cost 463.97 114.97 140.99

E. Total Investment (exclude Tax and 5103.65 1575.01 30.86% 1264.64 541.4 42.81% 1550.87 301.23 19.42% fee)

F. The Relevant Tax and Fee 785.42 367.1 46.74% 337.87 0.00% 109.56 0.00% 1 Cultivated Land Occupancy Tax 276.83 53.86 33.63 2. Cultivation Fee of Cultivated Land 473.69 205.8 43.45% 284.01 0.00% 75.93 0.00% 3. Forest Vegetation Recovery Fee 34.9 4 Other tax and fees 161.3

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 79

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Loudi Xinhua Wugang

Planned Actually Accumulated Spent Planned Actually Accumulated Spent Planned Actually Accumulated Spent

G. Total Investment including Tax and 5889.07 1942.11 32.98% 1602.51 541.4 33.78% 1660.43 301.23 18.14% Fee

Sangzhi Huaihua Yongzhou

Planned Actually Accumulated Spent Planned Actually Accumulated Spent Planned Actually Accumulated Spent Item The Total The Total The Total The Total The Total The Total Planned Spent % Planned Spent % Planned Spent % (104Yuan) (104Yuan) (104Yuan) (104Yuan) (104Yuan) (104Yuan) A. Resettlement Compensation 1203.88 302.32 25.11% 1657.76 2564.85 154.72% 3046.12 883.48 29.00%

1. Land Compensation 91.47 204.69 223.78% 517.35 2426.65 469.05% 930.21 140.13 15.06% 2.House and Auxiliary 998.46 47.63 4.77% 1047.4 110.2 10.52% 1880.91 638.88 33.97% Facilities 3. Infrastructure 0.06 55.55 124.02 4. Relocation Transportation 26.4 16.91 37.91 Fee 5. Scattered trees 10.56 2.84 6. Compensation for Enterprises 63.63 50 78.58% 4.49 28 623.61% 38.82 104.47 269.11% And Institutions

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 80

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Sangzhi Huaihua Yongzhou

Planned Actually Accumulated Spent Planned Actually Accumulated Spent Planned Actually Accumulated Spent

7. Small shops 2.4 0.41 3.04 8. Vulnerable Group Subsidy 10.9 15.65 28.11 9. Tombs 0.26

B. Specialized Facilities 9.38 120.78 127.14 1.Transporation Facility 42.75 2. Transmission and 6.93 45.63 23.45 Transformation Facility 3. Water Resources Facility 1.7 2.8 47.04 4.Telecommunciation Facility 0.75 40.5 9 5. Cable TV 31.85 4.9

C. Others 128.68 74.8 58.13% 153.2 108.72 70.97% 340.06 192.4 56.58% 1. Cost for Survey, Design and 36.4 36.4 100.00% 53.36 53.36 100.00% 95.2 95.2 100.00% Scientific Research 2. Implementation Management Cost 36.4 36.4 100.00% 53.36 53.36 100.00% 95.2 95.2 100.00% 3. Implementation Agency Initiation Cost 31.66 20.4 102.69 4. Technical Training Cost 6.02 2 33.22% 8.29 2 24.13% 15.23 2 13.13% 5. M & E Cost 18.2 17.79 31.74

D. Basic Contingency Cost 134.19 193.17 351.33

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 81

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Sangzhi Huaihua Yongzhou

Planned Actually Accumulated Spent Planned Actually Accumulated Spent Planned Actually Accumulated Spent

E. Total Investment excluding Tax and 1476.12 377.12 25.55% 2124.91 2673.57 125.82% 3864.65 1075.88 27.84% fee

F. The Relevant Tax and Fee 53.67 0.00% 213.56 0.00% 407.2 0.00% 1 Cultivated Land Occupancy Tax 35.04 60.36 180.78 2. Cultivation Fee of Cultivated Land 18.63 0.00% 147.68 0.00% 191.41 0.00% 3. Forest Vegetation Recovery Fee 5.52 35.01 4 Other tax and fees

G. The total Investment including Tax 1529.79 377.12 24.65% 2338.47 2673.57 114.33% 4271.85 1075.88 25.19% and Fee

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 82

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

7. The Affected Persons’ Appeal and Complaints

The affected persons are entitled to rights and obligations endowed by the constitution and laws. The acting laws and regulations guarantee legal rights of all citizens not being infringed. Once infringed, the affected persons have rights to lodge appeals and protect their rights.

7.1 Appeal Channels

Land acquisition, house demolition and the subproject construction may arouse the affected persons’ dissatisfaction and complaints. There are many appeal channels. The affected person can lodge appeals to the resettlement management organizations at different levels, the mass medias and the relevant departments of the governments at different levels. The affected persons can also lodge appeals to the legal departments, such as Justice Departments. In addition, they also can turn to the external resettlement monitoring agencies.

7.2 Appreal Procedures

When the affected persons lodge an appeal, they can settle it with the local resettlement management organizations or local government first. If unsolved, they can go to the relevant agencies at upper levels. The affected person can communicate with the village committee first, then the village committee together with the affected persons settle it with the town/township government. Alternatively, the affected persons can lodge an appeal verbally or in written format to the resettlement management organizations at higher level directly. Upon receiving the appeal, the resettlement management organizations at higher level will work together with its subordinate agencies to find the solutions. If unsolved, the affected persons can lodge an appeal to the government departments under their jurisdictions according to Administrative Procedural Law of People’s Republic of China. If the affected persons still feel unsatisfied with the solutions, they can litigate it to the court.

7.3 The Affected Persons’ Appeals and Complaints

The external resettlement monitoring agency has visited some affected households

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 83

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project during the baseline survey and the sampling household survey. The external resettlement monitor had face to face communication with them to listen to their ideas. Currently, the majority of the affected persons supports the subproject construction and accepts the land acquisition and resettlement resulted from the subproject construction. Although the resettlement implementation organizations at different level have made lots of effort on the resettlement policies and compensation standards, some of the affected persons are still suspicious of the resettlement compensation standards. Some of them are worried about under-funded compensation fee and they can’t afford to buy new houses. Some are worried about their future incomes when their farmland is acquired. Some are worried about the inconvenient traffic conditions in the resettlement site. Some are worried about their deteriorating living standards after relocation. On the contrary, some have extra high expectation and want to get the compensation beyond the resettlement policies. If unsatisfied, they will refuse to relocate.

7.3.1 Loudi

A. Reply to the Issues and Requirements in the first M&E period. The replies to the issues and requirements raised by the affected persons in the first M&E period are summarized as below: (1) Xie Wenying from Hebian Group of Daqiao Community hope to be relocated within the original village and the housing plot should have good access to road. Reply: the Resettlement Plan should be followed. The original village doesn’t have the space to accommodate more people. The relocation method will adopt the property exchange. (2) Chen Guoguang and Chen Xinjun of Hebian Group of Daqiao Community hope that the housing compensation prices should be calculated based on the average housing price in Loudi City. Reply: the house compensation should follow the Resettlement Plan and the legal document regarding the house compensation standards. The houses in Hebian Group are rural houses and not urban houses. Therefore it will be compensated according to the house compensation standards for rural areas. (3) Liu Guilian and others of Hongqi Group in Qingtan Community hope to be relocated within the original village. The proposed housing plots should be confirmed before the house demolition and relocation. The housing compensation prices should be

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 84

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project calculated based on the latest average housing price in Loudi City. Reply: The village doesn’t have enough space to accommodate more people and the relocation method will adopt the property exchange. The houses in this Group are rural houses and will be compensated according to the house compensation standards for rural areas. (4) Peng Fanglian of Tongche Group in Lianbing village hopes to find employment for his children. In addition, the same areas of farmland with same quality as the previous one should be reallocated to him. Reply: Employment for his children hasn’t been found so far. (5) Yan Rupu of Xintang Group from Lianbing Village hopes to find employment for his son. The proposed housing plot should have good access to road and is adjacent to the commercial centers. Reply: Employment for his children hasn’t been found so far. The housing plot will be in a centralized place. (6) Li Qinglin of Tongche Group in Lianbing Village said that they were poor and hope to provide them with the living subsidies Reply: The local government is making the relevant policies to support the vulnerable groups. Currently one of measures taken is to include the affected persons in the urban minimum living subsidy program.

B. The major Issues and Requirement Raised in the 2nd M&E period.

(1) Zhou Riyi in Niu’e Group of Lianbin Village said that his family income was so low that it’s difficult to make a living. He hopes that the government could provide him with the living subsidy. (2) Peng Guisong in Lianbing Village complained that the entire land compensation fund should give him directly rather than the village group since his land was acquired. (3) Zhou Dongxiu in the Hebian Group of Daqiao Community asked the compensation policy for the individual shops. She said she would be happy with the compensation standards taking into account of the commercial value of her original shops. She also hopes that a new shop will be allocated to her in good locations and then she can continue the business. As a whole, the most concerned issues in Loudi subproject are compensation prices of land acquisition and resettlement, traffic conditions of housing plots, employment

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 85

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project opportunities and rehabilitation measures etc. the monitor suggested that the LPMO should intensify their efforts in disclosing the national and local relevant policies and standards concerning the land acquisition and resettlement and explain the entitlement enjoyed by the affected person. All these above-mentioned issues have been communicated with Loudi PMO. The external resettlement monitoring agency will follow up how these issues will be dealt with during the next monitoring phase.

7.3.2 Xinhua

A. Reply to the Issues and Requirements in the first M&E period. The replies to the typical issues and requirements raised by the affected persons are summarized as below: (1) Song Shuchang and others hope to be relocated near to their original houses. They prefer the relocation approach of property adjustment. Reply: the relocation method is the centralized relocation. Except this, his other requirement can be satisfied. (2) Zhu Chunyan, Zhu Manli and others hope to increase the compensation standards and to be relocated near to their original houses. Reply: the relocation method is the centralized relocation. Except this, his other requirement can be satisfied. (3) Cheng Guanghua of Shangdu Village said that the tuitions of their children were too high and they were unable to afford to build new houses. They hope to be regarded as the vulnerable groups and get the special subsidies. Reply: His family is not in the category of the vulnerable groups. (4) Li Binghua of Shangdu village said that he didn’t like relocation method of the cash compensation but the property adjustment. He wants to get a new house with the same area as the original one. Reply: The compensation policy and standards apply to all the affected households. (5) Sun Xudong of Baisha Village hopes to have a shop front house as his future income. Reply: OK. (6) Li Yunsong of Zijiang Village hopes to be relocated near to his original house. He wants to have a shop front house. Reply: Ok.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 86

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project (7) Li Yuansong of Zijiang Village said that the alternatives should be considered to try to avoid the land acquisition and resettlement. Reply: The government will hold the public hearing meeting to discuss the several options.

B. The major Issues and Requirement Raised in the 2nd M&E period.

(1) Li Jiuxiang in Baisha Village said, “ I heard that the government paid the bill for water supply and electricity in other places when the affected households were in the period of house demolition and new house construction. Why we have to pay the bills ourseleves? (2) Sun Shuhui in Baisha Village said, “ there is no a single tree in the relocation site currently but the government said before that a very good environment would be built here like a garden?” As a whole, almost all of the affected persons are willing to have shop front houses, because Xinhua County Government has developed many high values of shop front houses after its relocation. These shop fronts have good economic returns and attracted attentions of the affected persons. All these above-mentioned issues have been communicated with Xinhua PMO. The external resettlement monitoring agency will follow up how these issues will be dealt with during the next monitoring phase.

7.3.3 Wugang

A. Reply to the Issues and Requirements in the first M&E period. The replies to issues and requirements raised by the affected persons are summarized as below: (1) Luo Meigui and others of Yulong Community in Yuanmenkou Residential Committee said that they had known the information about the resettlement in 2000 but nothing had happened since then. But they have still been worried about this issue and haven’t had peaceful lives. Reply: it takes a long time to have land acquisition and the resettlement fund raising. (2) Lei Qingxi of Yulong Community of Yuanmenkou Residential Committee, Zeng Degui of Shuiyun Community and Peng Guimei of Shipaifang Community and others said that they were small business men (such as bamboo product maker, paper craftsman and tailors) and had established their business relationships with local people. If they are relocated, they will have to develop new customers. If they fail,

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 87

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project they may encounter difficulties in making a living. Reply: the Resettlement Plan should be followed. There are no separate compensation policies and standards tailored for the individual shops currently. (3) Chen liyan and Chen yusheng in Shipai Community of Yuanmenkou Residential Committee said that their current living conditions were good. They were worried about the low compensation standards and bad resettlement sites. Therefore they are reluctant to be relocated. Reply: The places where they are living now are subject to flooding frequently. The new resettlement sites are good in fact. (4) Xiao Shimin, Zhong Dingyuan and others in Yuanmenkou Residential Committee hope to be relocated near to their original places. Reply: the relocation approaches was discussed and agreed with the affected persons. Will consider their requirements. During the first M&E period, The affected households in Wugang subproject almost live in the several streets of the old city area alongside the river. Almost all of them are urban citizens but most of them are laid-off workers or unemployed without any benefits. Their average income is low. So the common concerns are the low compensation standards, limited financial capacity of constructing new houses, future income sources and relocation near to their original places. During the 2nd M&E period, the affected persons said almost the same things. All these above-mentioned issues have been communicated with Wugang PMO. The monitor suggested the LMPO hold the public meetings at the affected communities and answered the common questions and concerns from the affected persons.

7.3.4 Sangzhi

A. Reply to the Issues and Requirements in the first M&E period. The replies to the issues and requirements raised by the affected persons are summarized as below: (1) Xiong Chaodong of Gaojiaping Residential Committee (relocated already) and others said that it’s not easy to get the certificates for their new houses, such as land Certificate, House Certificate and House Construction Certificate. Reply: these certificates are ready.

(2) Xiang Chucai(relocated already) said that he had bought a new apartment but he

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 88

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project didn’t get used to living in the high buildings. He hopes that he could get another new housing plot. Reply: He can buy another new house in the resettlement site. (3) Wang Songhou, Xiang Zuojun and others hope that the local government can help their children with employment. Reply: the employment can’t be found so far for him. (4) Gu Guilian and others in Gaojiaping Residential committee said that the compensation standards are low. They hope that the special subsidies should provide to the vulnerable groups. Reply: The affected households were double-checked and some of them were provided with living subsidies by the Civil Affairs Bureau. B. The major Issues and Requirement Raised in the 2nd M&E period.

(1) Group 2 and Group 3 in Wenming Road said.” They enjoy the rural cooperative medical care when they are rural people; when they become urban citizens, they couldn’t afford to see the doctor if they don’t join in the urban cooperative medical treatment.” (2) Liu Wenzhi of Group 3 in Wenming Road said, “My houses is flooded every year and can’t live any more”. He requests to relocate as soon as possible. (3) Yuan Zhengzhu of Group 2 in Wenming Road said, “ I heard that the compensation standards are quite low and I prefer to stay but suffer the flooding rather than relocate to another place.” (4) Wang Weibi of Group 2 in Wenming Road said, “ my family has relocated once for the urban development. Now, we have to relocate again for the flood control embankment construction. We have sacrificed too much and we deserve the higher compensation standards.” (5) Xiang Chucai in Gaojiaping Residential Committee said,” the minimum living subsidy is only 50 Yuan/ month in Sangzhi County, which is too low.” (6) Zhang Xinlian in Weicaowan Group said, “ lot of people in the village are poor but not provided with the minimum living subsidy. It’s unfair.” As a whole, the most common concerns in the Sangzhi subproject are compensation standards, medical care and the minimum living subsidy. None of them mentioned the bias of ethnic minorities or ignorance of the minority customs. All these above-mentioned issues have been communicated with Sangzhi PMO. The external

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 89

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project resettlement monitoring agency will follow up how these issues will be dealt with during the next monitoring phase.

7.3.5 Yongzhou, Leiyang, Huaihua and Chenxi

Huaihua and Yongzhou subprojects have not undertaken the resettlement baseline surveys. The external resettlement M&E didn’t start in Leiyang and Chenxi

8. Support of the Vulnerable Groups

According to the Resettlement Plan, the subprojects all have adopted the relevant measures to support the vulnerable groups. These are summarized as followed: Those affected vulnerable group mainly include elderly living alone, women headed households, and extremely poor families. Besides the compensation standards provided by the project, the project would provide additional financial or physical assistance so that their rehabilitation and restoration of income and livelihood could be achieved as soon as possible. (1) The project will provide special allowance for the families under the poverty line to help them construct houses and maintain their original living level at least. The concrete measures are too provide the subsidy worth of RMB 3000 yuan/household and the subsistence subsidy of RMB 600 yuan/person to help them overcome the difficulties during the demolition. (2) After implementation of the project, the affected households could apply for loan from Rural Credit Cooperative, and local village collectivities could provide guarantees for such application. (3) During the course of implementation of the project, the village committee will help those vulnerable families including elderly living alone, disabled, and women headed households with selecting new housing site, rebuilding new houses, and transferring to new houses construction. The monitor noted that the each subproject government had the mature urban (rural) minimum living standards system. The easy way to define the vulnerable groups is to identify whether the household income is below the urban (rural) minimum living

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 90

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project standards or not. If so, the Civil Affairs Bureau will include these households into the urban (rural) minimum living subsidy and send them the subsidy monthly. The actually supported and the identified vulnerable groups in the Resettlement Plans are shown in Table 8-1 Table 8-1 Comparison of the Actually Supported and the Identified Vulnerable Groups in the Resettlement Plans

The Identified Vulnerable The Actually Groups in the Resettlement Supported Subproject The Support Measures Plan Vulnerable Groups (Person) (Person) Loudi 85 0 Included urban (rural) minimum living subsidy

Xinhua 0 0 Included urban (rural) minimum living subsidy Included urban (rural) minimum living subsidy; Wugnag 76 0 The house area less than 40m2 is compensated as the 40m2 house area. Sangzhi 9 7 Included urban (rural) minimum living subsidy Included urban (rural) minimum living subsidy; Yongzhou 95 8 Provide the cheap-renting house,50m2/household. Leiyang 37 Included urban (rural) minimum living subsidy; Huaihua 14 3 Provide more areas of housing plots than the original. Chenxi

Subtotal 316 18

9. Public Participation, Consultation and Information Disclosure

It’s very important to get support from the affected persons to ensure the resettlement implementation smoothly. During the process of resettlement, public participation, consultation and information disclosure are crucial. The common ways of public participation, consultation and information disclosure included: (1) Public Media. In each Subproject County or City, the subproject is the key project, which has been widely reported on the TV and new paper. The publics are aware of the subproject implementation progress. (2) Resettlement Information Booklet. Before the implementation of resettlement and land acquisition, the resettlement booklets are distributed among the affected

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 91

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project households, detailing the project, resettlement and land acquisition compensation policies and standards and the entitlement of the affected persons. (3) Public Hearing Meeting. Before the resettlement implementation, the resettlement management organizations of each subproject have several meeting with the affected persons to listen to their ideas and discuss about the resettlement sites and relocation approaches. (4) Village (group) Consultation. The village (group) leaders hold meetings with the affected households informing of the resettlement policies and the entitlements and also discussing the relocation site selection. These meetings normally hold just before the implementing the land acquisition and resettlement. (5) The Poster putting up. During the resettlement implementation, the resettlement management organizations will put up the posters, set up the bulletin board at the fixed public places and hold the group discussion in each subproject area to inform the affected persons of land acquisition, house demolition, compensation standards and resettlement site construction. (6) Public Notices of Compensation Standards and Physical Indices. The confirmation of physical indices will be published openly before the affected persons sign the agreement so that they are satisfied with them. Table 9-1 Public Participation, Consultation And Information Disclosure at Each Subproject

Public Notice Resettlement Public Public Village(Group) Poster of Subproject Information Hearing Media Consultation Putting-up Compensation Booklet Meeting Standards 1st M&E Completed Completed Completed Completed Completed Completed Loudi 2nd M&E Completed Completed Completed

1st M&E Completed Completed Completed Completed Completed Completed Xinhua 2nd M&E Completed Completed Completed

1st M&E Completed Completed Completed Completed Completed Wugang 2nd M&E Completed Completed Completed Completed

1st M&E Completed Completed Completed Completed Sangzhi 2nd M&E Completed

Huaihua 1st M&E Completed Completed Completed Completed

Yongzhou 2nd M&E Completed Completed Completed

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 92

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

10. The existing Main Problems and Recommendation

(1) The Slower Resettlement Implementation

Due to various factors and constraints, the resettlement and land acquisition implementation progress of each subproject is slower than the schedule to various degrees. In some subprojects, the resettlement and land acquisition have severely hindered the civil work construction. The factors affecting the resettlement implementation are:

Firstly it is insufficient resettlement fund. The resettlement fund is invested by the local government and isn’t from ADB loan. However, the investment is large and in urgent demand. Therefore, it increases difficulties of the local government to raise such a large amount of fund for resettlement and land acquisition.

Secondly some affected persons have extra high expectations. For instance, some of them ask for several times of higher compensation standards than those stipulated in the Resettlement Plan or the acting standards. This disparity has caused difficulties in agreement negotiation and consequently the resettlement implementation is slow.

Thirdly, some PMOs and local governments didn’t pay much attention to the resettlement. They think that the resettlement fund is the only issue to be considered. However, almost all of the subprojects will affect the suburban areas. People living there include mostly unemployed urban citizens and rural residents with little land or without any land. Most of them make a living by daily labor and small business. They don’t have the regular income and their living standards are low. Therefore, these groups of people attached great importance on their income sources after relocation. They are worried that they even couldn’t maintain the current living standards because they lack of skills to make a living. That’s why they constantly raise the requirement of increasing the compensation standards or finding the employment for their children. If their requirement is not satisfied, they will refuse to relocate and subsequently affect the resettlement and land acquisition implementation. Since the resettlement and land acquisition implementation is the major constraint of the civil works construction, ADB has paid much attention to it. The external

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 93

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project resettlement-monitoring agency recommended that the local governments and their relevant departments should take the appropriate measures to facilitate the resettlement and land acquisition implementation. Especially more effort should be made to raise enough resettlement funds, further explain the resettlement policies and compensation standards and speed up the construction of resettlement sites. All of them will ensure that the resettlement and land acquisition implementation matches with the civil works construction.

(2) Strengthening the Information Management

The local governments have put high priority on the subprojects and many government departments are involved into the subproject management. For instance, water resource bureaus are responsible for engineering aspects; financial bureaus are responsible for fund allocation; land resources bureaus and affected town/township governments are responsible for land acquisition and resettlement; audit bureaus are responsible for financial auditing. Such management mechanism makes the data relevant to land acquisition and resettlement to scatter within these bureaus. There is no systematic data management mechanism. The data collection, collation and consolidation at each subproject are slower than the actual resettlement and land acquisition progress. Therefore it’s difficult to know resettlement and land acquisition progress fully and genuinely. Without support of good information, it’s also hard for the relevant departments to make the right decisions.

The resettlement and land acquisition relate to every aspect of the society. They have complicate procedures with multi-department involvement. Such characteristics make the information flow huge, which is not easy to manage and keep records. Therefore, the information network construction should be strengthened via computer technology and internet. The technologies can help with the data collection and collation more effectively. With support of good information and information management system, it will be very easy for the relevant departments to make the right decisions.

The external resettlement monitoring agency recommended that the information management system should be set up at the early stage of the subproject implementation. More importantly, the qualified full-time IT personnel should be equipped to have data collection, collation and entry of database to ensure that the information management is synchronous with the resettlement implementation so that

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 94

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project the relevant people could understand the resettlement and land acquisition implementation fully and genuinely.

This issue was raised in the 1st M&E period but wasn’t seen any good sign in the 2nd M&E period.

(3) More Efforts on Resettlement Fund Raising

The resettlement fund is invested by the local government and isn’t from ADB loan. Sources of the resettlement fund include borrowings from Agriculture Development Bank and flood security funds. Currently the fund-raising is not as good as expected. The resettlement and land acquisition implementation at each subproject will be at the peak in the year of 2007 and 2008, which will have high demand of resettlement fund by then. Therefore, the external resettlement monitoring agency recommended that more efforts should be made to ensure the sufficient resettlement fund. Otherwise, the insufficient resettlement fund will hinder the resettlement and land acquisition implementation.

(4) Strengthening the Project Management

ADB has higher resettlement management requirement on its financed project. However, since the project is the first ADB-financed one, many resettlement management organizations at different levels lack sufficient resettlement experience. Therefore, the external resettlement monitoring agency recommended that the relevant experience should be summarized and lessons should be drawn from the past so as to regulate and guide the resettlement and land acquisition implementation in the future. In addition, relevant management regulations should be made, such as regular meeting regulation, coordinated meeting regulation, significant case reporting regulation, resettlement implementation reporting regulation, statistics reporting regulation and performance regulation.

This issue was mentioned in the first M&E period. The monitor noted that the resettlement management organizations had made some efforts. However, the results were not as good as expected due to lack of experience and shortage of full-time staffs.

(5) Slow Land Approval Process

The land acquisition approval process is to be involved into so many government agencies and it takes time to complete it. In some subprojects, the land was acquired

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 95

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project before the paperwork of the land acquisition approval was completed. This is not in compliance with the legitimate procedures. It also may delay the land acquisition progress. Therefore, this work should be expedited.

(6) Relocation of the Individual Shops

Resettlement Plans said,” the individual shops that operate the business in houseowners’ own houses will be relocated to the new shopfronts after the consultation with them at the crowded crossing area or both sides of major traffic roads to avoid the customer reduction and maintain the original operation.”

The individual shops in the subprojects were compensated for their business suspension, which the shop owners were satisfied with. However, there are no universal relocation approaches for the affected individual shops in all subprojects. Their relocation approaches were the same with the common affected households. The monitor noted that the individual shop owners had different requirements that their relocation approaches should be different from that for the common affected households. They should be relocated at the shopfronts with high commercial value and easy access to traffic. However, such shop fronts were often limited and have to decide their ownership by tossing the coin. If the shop owners were satisfied with the new shopfronts, the other common affected households were also unsatisfied with it.

The monitor explored some of reasons. To operate the small shops need little expertise and one shopfront is enough. Those shops have been compensated better than the houses. If new shops are provided, the other households affected by the house demolition may feel unhappy with it. It’s also difficult to provide the new shops for all the affected individuals.

All LMPOs are making efforts to solve this issue and hope to find a good solution which make all parties concerned happy.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 96

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

11. Conclusions and Recommendations

11.1 Conclusions The 8 core subprojects of Hunan Flood Management Sector Project are under the implementation. So far, Loudi, Xinhua, Wugang , Sangzhi, Huaihua and Yongzhou have concluded the resettlement M&E contracts with the external monitor..

The subproject PMOs and local governments have put high priority on the resettlement and land acquisition and all of them have established or strengthened the resettlement implementation agencies equipped with qualified staffs. Currently, they have made great efforts in resettlement promotion and awareness campaigns, physical indices confirmation, land acquisition and resettlement, resettlement fund raising and delivery. All these have made a good starting point. For each subproject, the resettlement and land acquisition implementation varies.

(1) Loudi

Currently the accumulative completed land acquisition is 504.815mu, accounting for 31.76% of the total land acquisition in Resettlement Plan. The acquired land has completed the approval procedures and the relevant compensation fund had been delivered. The accumulative completed house demolition areas are 1382.52m2, accounting for 4.5% of the total house demolition areas in the Resettlement Plan. There are 8 relocated households with 21 persons. The land acquisition of the resettlement is under the way.

The external resettlement monitoring agency has reviewed the signed land acquisition and resettlement agreements and found that the actual land acquisition and resettlement compensation standards are substantively higher than those in the Resettlement Plan. The Subproject PMOs said the affected persons had required higher compensation standards. If they were compensated according to the standards in Resettlement Plan, it’s very hard to reach agreements with the affected persons.

The resettlement investment completed accounted for 32.98% of the total resettlement

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 97

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project cost. The resettlement fund raising is not as good as expected. The completed or on-going embankment construction starts at areas with few house demolition and resettlement, so the resettlement fund delivered is only small amount. However, more resettlement fund will be needed with the more civil works construction. If this situation remains unchanged, it will hinder the subsequent civil works implementation.

The most concerned issues in Loudi subproject are compensation prices of land acquisition and resettlement, traffic conditions of housing plots, employment opportunities and rehabilitation measures etc. Generally speaking, most of the affected persons support the subproject construction and its associated land acquisition and resettlement. However, the subproject is at the early stage of implementation and the resettlement and land acquisition just initiated. Some affected persons have limited understanding of the resettlement policies and they are suspicious of the compensation standards. Their expectations on the compensation are much higher than those standards in the Resettlement Plan. In addition, their reluctant cooperation has affected the resettlement and land acquisition implementation to various degrees.

(2) Xinhua

Currently the accumulative completed land acquisition is 205.112mu, accounting for 43.33% of the total in the Resettlement Plan. The acquired land has completed the land pre-appraisal procedures and the land approval procedures are under the way. The relevant compensation fund has been delivered already. The accumulative completed house demolition areas are 1955.937m2, accounting for 37.1% of the total in the Resettlement Plan. The relocation of enterprises and institutions didn’t start yet. The external resettlement monitoring agency has reviewed the signed land acquisition and resettlement agreements and found that the actual land acquisition compensation standards are substantively higher than those in the Resettlement Plan..

Besides the relocation approaches in the Resettlement Plan, the local government has provided the alternatives. The affected person can choose to relocate in the 4 concentrated resettlement sites which had been developed for all the affected persons resulting from the urban constructions. The compensation consists of two parts: high-valued land and the cash compensation. Compared with the relocation approaches in the Resettlement Plan, the affected persons prefer this option. The relocated 8 households have all chosen to live in the concentrated resettlement sites. Currently, 3

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 98

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project out of 4 resettlement sites are close to completion and the other one has completed.

The resettlement investment completed accounted for 33.78% of the total resettlement cost. The resettlement fund raising is not as good as expected, which may hinder the subsequent civil works implementation.

The common concerns of the affected persons are having shop front houses and providing the special subsidies for the vulnerable groups etc. however, most of the affected persons support the subproject construction and its associated land acquisition and resettlement. They would like to relocate in the concentrated resettlement sites.

(3) Wugang

Currently the accumulative completed land acquisition is 24.95mu, accounting for 11.43% of the total. The acquired land has completed land pre-appraisal procedures. The house demolition and relocation of enterprises and institutions didn’t start yet. The resettlement sites are under the design.

The acquired land belongs to the state. Therefore, it’s hard to check the actual compensation standards of resettlement and land acquisition.

Checked the singed agreements by the monitor, the actual implementing compensation standards are higher or same with those stipulated in Resettlement Plan.

The subproject is at the initial stage of implementation and the required resettlement fund will be ready for delivery.

The common concerns are the low compensation standards, limited financial capacity of constructing new houses and future income sources etc. Generally speaking, most of the affected persons support the subproject construction and its associated land acquisition and resettlement. However, the subproject is at the early stage of implementation and the resettlement and land acquisition just initiated. Some affected persons have limited understanding of the resettlement policies and they are suspicious of the compensation standards. These showed that the public participation, consultation and information disclosure should be strengthened in Wugang Subproject to win more support from the affected persons during the short-terms.

(4) Sangzhi

Currently the accumulative completed land acquisition is 110.31mu, accounting for

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 99

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 65.93% of the total. The acquired land has completed the land approval procedures and the relevant compensation has been delivered. The accumulative completed house demolition areas are 1239.19m2, accounting for 7.35% of the total in the Resettlement Plan. Only one enterprise has been relocated, accounting for 13%. The resettlement site construction has completed.

The external resettlement monitoring agency has reviewed the signed land acquisition and resettlement agreements and found that the actual land acquisition compensation standards are substantively higher than those in the Resettlement Plan. However, the actual house compensation standards are lower with those in the Resettlement Plan because the house demolition and relocation happened earlier than the timing when Sangzhi Resettlement Plan was prepared. The adopted compensation standards were based on the Document (Reference No: [2004]27) issued by Zhangjiajie Municipal Government Administrative Office. The subsequent land acquisition and resettlement will follow the compensation standards stipulated in the Resettlement Plan.

The resettlement investment completed accounted for 24.65% of the total resettlement cost. The resettlement fund raising is not as good as expected. The completed or on-going embankment construction starts at Gaojiaping protection circle with few house demolition and resettlement, so the resettlement fund delivered is only small amount. However, more resettlement fund will be needed with the more civil works construction. If this situation remains unchanged, it will hinder the subsequent civil works implementation.

The most common concerns in the Sangzhi subproject are long and time-consuming procedures of applying the certificates, adaptation of new lives in the high buildings rather than tiled one-story house, expectation of high compensation standards and employment for children etc. Generally speaking, most of the affected persons support the subproject construction and its associated land acquisition and resettlement. However, the subproject is at the early stage of implementation and the resettlement and land acquisition just initiated. Some affected persons have limited understanding of the resettlement policies and they are suspicious of the compensation standards. They also complained about the insufficient support from local government.

(5) Huaihua

Currently the accumulative completed land acquisition is 343.525mu, accounting for

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 100

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project 81.35% of the total. The acquired land has completed the land approval procedures and the relevant compensation has been delivered. The accumulative completed house demolition areas are 3759.25m2, accounting for 15.51% of the total in the Resettlement Plan. There are 89 households with 101 persons relocated. Three enterprises have been relocated, accounting for 13%. The land acquisition of the resettlement sites is under the way.

Checked the singed agreements by the monitor, the actual implementing compensation standards are substantively higher than those stipulated in Resettlement Plan. It’s hard to adopt the standards in the Resettlement Plan according to LPMO.

The resettlement investment completed accounted for 32.98% of the total resettlement cost. The resettlement fund raising is not as good as expected. The completed or on-going embankment construction starts at the sections with few house demolition and resettlement, so the resettlement fund delivered is only small amount. However, more resettlement fund will be needed with the more civil works construction. If this situation remains unchanged, it will hinder the subsequent civil works implementation.

(6) Yongzhou

Currently the accumulative completed land acquisition is 367.274 mu, accounting for 40.71% of the total. The acquired land has completed the land approval procedures and the relevant compensation has been delivered. The accumulative completed house demolition areas are 8558.8m2, accounting for 21% of the total in the Resettlement Plan. There are 27 households with 303 persons relocated. Five enterprises and institutions have been relocated, accounting for 16%. The land acquisition of the resettlement sites is under the way.

Checked the singed agreements by the monitor, the actual implementing compensation standards are substantively higher than those stipulated in Resettlement Plan. It’s hard to adopt the standards in the Resettlement Plan according to LPMO.

The resettlement investment completed accounted for 25.19% of the total resettlement cost. The resettlement fund raising is not as good as expected. The completed or on-going embankment construction starts at the sections with few house demolition and resettlement, so the resettlement fund delivered is only small amount. However, more resettlement fund will be needed with the more civil works construction. If this situation

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 101

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project remains unchanged, it will hinder the subsequent civil works implementation.

(7) Leiyang and Chenxi

The external resettlement M&E didn’t start yet in Leiyang and Chenxi subprojects.

11.2 Conclusions

The resettlement management regulations should be made and improved. The resettlement implementation schedule should be updated regularly. Effective measures should be taken to promote the resettlement polices. More efforts should be made to increase the transparency of resettlement. sufficient resettlement fund should be raised in a timely manner. The house demolition and construction of resettlement sites should be accelerated. More efforts should be made to improve the rehabilitation measures to ensure that the affected person can resume their normal production and lives. Inter-agency cooperation should be strengthened. The information management should be improved including data collection, collation and management. High priorities should be paid on complaints of the affected persons and effective measures should be taken to solve them. More efforts should be made to communicate with affected persons thoroughly and effectively to eliminate the distrust and worries of the affected persons so as to win their more support for the subproject.

Changsha Xinhuan Water & Electricity Engineering Technology Development Co., 102

The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Changsha Xinhuan Water & Electricity Engineering Technology Development Co.,