Strategic Housing Land Availability Assessment “ – a great place to live, Mainwork and Report visit” March 2013 Important Notice – Disclaimer

In relation to the information contained within the Allerdale Borough Council Strategic Housing Land Availability Assessment (SHLAA), the Council makes the following disclaimer without prejudice:

• The SHLAA only identifies sites with future development potential. It does not allocate sites to be developed. The Council will decide the allocation of sites for future housing development through the Site Allocations process.

• The identification of potential housing sites within the SHLAA does not imply that the Council would necessarily grant planning permission for residential development on these sites. Any applications would be considered against the appropriate policies in the relevant development plan documents and having regard to any other material considerations.

• The inclusion of potential housing sites within the study does not prevent them from being considered for other purposes.

• The boundaries of sites are based on the information available at the time. The SHLAA does not limit an extension or contraction of these boundaries for the purpose of a planning application.

• The fact that a site is not included in the study does not preclude the possibility of planning permission for residential development being granted on it. It is acknowledged that sites will continue to come forward that may be suitable for residential development that have not been identified in the SHLAA.

• The categorisation of sites in terms of whether they are considered deliverable or developable is based on an assessment at the time of the study. Circumstances or assumptions may change which may mean that sites could come forward sooner or later than originally envisaged.

• The housing capacity of site included in the SHLAA has been estimated using a benchmark of 30 dwellings per hectare. However this does not mean that this density is appropriate for each individual site, which would need to be assessed through the planning process when a planning application is submitted.

• The information included in the SHLAA is ‘snapshot’ based on information that was available at the time of the study, and is therefore unable to take account of any changes in circumstances. It is important to recognise that:

• There may be additional constraints on some sites that were not identified at the time of the assessment • Constraints identified on some sites may now have been addressed • Sites identified in the document may have secured permission since the information was compiled and published. Applicants are therefore advised to carry out their own analysis of sites to identify any constraints or other information for the purpose of a planning application and not rely solely on the findings of the SHLAA. 1 Introduction 1

2 Methodology 3

3 Identifying Future Housing Requirements 8

4 Gross capacity of SHLAA sites 13

5 5 year supply of deliverable sites 15

6 List of deliverable sites 17

7 List of developable sites 21

Settlement hierarchy A1 25

A2 Deliverable and developable site maps 26 Allerdale Evidence Base Local Plan

1 Introduction

National planning policy requirements in strategy/target for housing growth and delivery relation to housing supply and also the general geographic distribution of This Strategic Housing Land Availability development within the Borough. Assessment (“SHLAA”) has been prepared by Before the emerging Local Plan can be Allerdale Borough Council (“the Council”) to formally adopted by the Council it must provide an assessment of the amount of land successfully pass an examination in public available for housing development both and be found ‘sound’. One of the key tests of currently and in the future. soundness is that the housing strategy/target is deliverable. A top priority for Government is to ensure that land availability is not a constraint on the In order to demonstrate that the housing delivery of new housing. The new National strategy/target is deliverable, the Council must Planning Policy Framework (“NPPF”) states provide evidence that there is: that local planning authorities should prepare (i) An adequate supply of housing land to SHLAAs to establish realistic assumptions fulfil the overall target set out in the plan. about the availability, suitability and the likely (ii) Enough housing land within each of the economic viability of land to meet the key settlements and tiers of settlement identified need for housing during the plan hierarchy to deliver the spatial strategy period. (iii) Sufficient ‘deliverable’ sites in order to

Purpose of this SHLAA document provide a supply for the first five years of the plan The Council are in the process of preparing an new Local Plan (“The emerging Local Plan”) This SHLAA document forms part of the will eventually replace the current Local Plan evidence base to demonstrate that that was adopted in 1999. requirements (i), (ii) and (iii) can be fulfilled. The emerging Local Plan sets out the Council’s long-term vision for the Borough for the period 2011-2028. This includes the

1 SHLAA: Main Report Evidence Base Allerdale Local Plan

Document format Chapter 7: provides a list of developable sites within those settlements included within the The subsequent chapters of the document settlement hierarchy comprise of the following: Appendix A1: Illustrates the settlement Chapter 2 describes the methodology which hierarchy as set out in the emerging Local was followed in the preparation of this Plan Assessment. Appendix A2: Includes maps of those Chapter 3 sets out the future housing settlements included within the settlement requirements for the Allerdale Borough in hierarchy that contain sites that are terms of numbers and geographical considered to be developable/deliverable in distribution, as set out in the emerging Local the SHLAA. Plan

Chapter 4 identifies the gross capacity of all sites included in the SHLAA and compares this against the housing target set out in the emerging Local Plan

Chapter 5: identifies the gross capacity of the deliverable SHLAA sites and compares this against the housing requirement for the first 5 years as set out in the emerging Local Plan

Chapter 6: provides a list of deliverable sites within those settlements included within the settlement hierarchy

SHLAA: Main Report 2 Allerdale Evidence Base Local Plan

2 Methodology

Core Requirements of the Assessment Land Availability

• The West Employment Land & The SHLAA Practice Guidance states that, as Premises Study a minimum a SHLAA should provide the following core outputs to identify opportunities • Submissions to the Council from local for housing development: residents proposing residential land for inclusion in the next Local Plan (i) A list of sites, cross-referenced to maps

showing locations and boundaries of Stage 2 - Call for Sites specific sites (ii) The potential quantity of housing that Landowners, developers and other interested could be delivered on each identified site parties were invited to submit sites for inclusion in the SHLAA , which they (iii) Any potential constraints on the considered to have the potential to be deliverability of identified sites developed as housing. Two call for sites have (iv) An indication of when each identified site been undertaken: the first in June 2008 and is likely to be developed the second in July 2011.

Identifying sites to be considered in the Assessing Site Suitability SHLAA Information was gathered on each site to Stage 1 - Desk top study assess their suitability. This involved This involved using existing information consulting the following organisations: sources to identify sites with the potential to • United Utilities (gas/water/electric/sewage deliver housing. These included: constraints) • Registers of land owned by public sector • Cumbria Highways (access/highway organisations capacity) • The National Land Use Database (NLUD) • Environment Agency (flooding issues) • ’s Employment • Natural (biodiversity/landscape

3 SHLAA: Main Report Evidence Base Allerdale Local Plan

issues) fair or good based on the number of services that could be accessed via each mode of • English Heritage (historic environment constraints) transport.

• Allerdale Borough Council Discounting sites (contamination/mining constraints) The first sieve involved discounting those sites Each site has been assessed by planning which were considered to be unsuitable for officers in order to obtain a detailed housing development. assessment on the location characteristics of each site including topography, surrounding Sites were discounted if: uses, potential landscape impact and means • In a location detached from any of access. settlement included in the settlement hierarchy identified in the emerging Local From these surveys, any potential on-site Plan constraints were recorded and supplemented • Located wholly within Flood Zone 3 by information included in the Council’s • The means of access was considered existing Local Plan evidence base: substandard and/or dangerous, or • Strategic Flood Risk Assessment significant highway capacity constraints • Open Space Audit & Needs Assessment have been identified

• Cumbria Biodiversity Database • Planning permission for development has been granted • Cumbria Landscape Character Guidance • Subject to severe utilities infrastructure • Local Geodiversity Action Plan for constraints Cumbria • Below 0.3ha in area Each SHLAA site has been assessed in terms • Development would adversely affect the of accessibility. This was undertaken using a interest of a protected site (e.g. Site of modelling system that rated each site poor,

SHLAA: Main Report 4 Allerdale Evidence Base Local Plan

Special Scientific Interest [SSSI]) For those sites that were identified by the Council, ownership details were obtained from • Development would have a harmful impact upon a Historic Asset (e.g. listed building, the Land Registry. The owners were then Scheduled Ancient Monument, sensitive contacted to see whether they would consider archaeological area) releasing the land for housing.

• Development would have harmful Sites were considered unavailable and landscape impact therefore discounted at this stage, if:

• Topography rendered it unsuitable for • The Land Registry was unable to provide development ownership data

• No response from the owner was received Assessing site availability following an approach from the Council.

The NPPF states that one of the key tests to • Following an approach from the council determine whether a site can be considered to the owner indicated that they did not want be deliverable or developable is whether it is to develop the site available for development. Those sites fulfilling the first sieve criteria were subject to an Assessing site achievability availability assessment to determine whether the owner of a site was willing to allow it to be Those sites deemed to be available were then developed as housing in the future. assessed in terms of their achievability. This was essentially an assessment as to the It was assumed that those sites that had been economic viability of the site and the whether submitted to the Council by landowners and the site would yield a enough profit to make agents acting on their behalf has indicated their development a realistic proposition. willingness to release the land for housing. A strategic viability model was used for this Therefore these sites were deemed to have exercise. Sites were classified in terms of: automatically fulfilled this test. • Size: large, medium or small,

• Type: brownfield or greenfield

5 SHLAA: Main Report Evidence Base Allerdale Local Plan

• Market value: high, medium or low (based Assessing site deliverability on average house prices at parish level) Those sites considered to be both available and Taking into account the location (in terms of achievable were then assessed in terms of the land value/market attractiveness), area (in likelihood of when they would be developed. terms of the number of dwellings that could be The assessment was based on deductive delivered) and the need for remediation (in reasoning taking into account the economic terms of brownfield land) sites were then given viability of the site, the level of demand for a rating of viable, marginal or unviable. housing in the locality and any identified constraints that would need to be addressed The difficult housing market conditions caused before the site could be brought forward. by the economic downturn has been factored into the assessment in order to avoid an overly Based on a combination of these factors sites conservative approach. In some cases the were then classified into two categories: viability rating has been adjusted taking into account both historical trends and local • Deliverable (A realistic prospect that knowledge of the housing market (e.g. demand housing will be delivered on the site within and/or desirability of areas/settlements). 5 years) • Developable (There is a reasonable Given the timeframe of the Allerdale Local Plan prospect that housing will be delivered on (2011-2028) it is likely that housing market will the site later in the plan period within the improve. Therefore it was considered essential 6-15 year timeframe) to allow for a certain level of flexibility within our viability assessments. Estimating housing capacity of SHLAA sites

Only the most constrained and unviable sites Potential housing capacity of SHLAA sites has were discounted at this stage. been estimated based on assumptions in relation to:

• Density

SHLAA: Main Report 6 Allerdale Evidence Base Local Plan

• Net developable area (“NDA”)

In relation to density, the proposed density standard set out in the emerging Local Plan, of 30 dwellings per hectare, has been used.

With regards to NDA, assumptions were made in relation to the percentage of the area of the site that would be taken up by infrastructure (roads, hard standing) and open space:

• Sites > 3 hectares: 75% NDA • Sites 2-3 hectares: 80% NDA • Sites 1-2 hectares: 85% NDA • Sites <1 hectare: 90% NDA

7 SHLAA: Main Report Evidence Base Allerdale Local Plan

3 Identifying future housing requirements

Establishing the level of future housing Proposed settlement hierarchy growth for the Borough The emerging Local Plan also sets out how One of the principal roles of the emerging future housing growth will be managed and Local Plan is to establish the target for the distributed throughout the Borough. A map number of houses that will need to be illustrating the proposal spatial strategy and delivered in the Borough over the next plan geographical dispersal of settlements is period (2011-2028). included in Appendix A1.

Based on up-to-date population, household It is proposed that these dwellings will be formation and economic forecasting the distributed within a proposed settlement Council has arrived at a proposed housing hierarchy comprising of: growth target of 5167 dwellings, which Principal Service Centre (“PSC”): equates to a requirement to deliver 304 dwellings per annum. Workington (including High Harrington, Seaton, Siddick and Stainburn) In addition to statistical forecasting the Council has also considered the following additional Workington has been identified as the criteria/considerations: Principal Service Centre in recognition of it role as the main housing, employment and • Potential land availability and known retail centre. infrastructure capacity. Key Service Centres (“KSC”): • Past levels of house completions (which

give some guide to the capacity of the Cockermouth construction industry to deliver and the Silloth level of market demand) Wigton • The need to maximise the delivery of affordable housing and to respond to and Key Service Centres have been designated on support growth in the local economy. the basis that they are the recognised urban

SHLAA: Main Report 8 Allerdale Evidence Base Local Plan

centres in the plan area and offer a good Greysouthern Hayton range of services. Ireby Kirkbampton Langrigg Little Bampton Local Service Centres (“LSC”): Little Clifton Mawbray

Abbeytown Allonby Mockerkin Newton Arlosh Brigham Broughton Oulton Broughton Moor Papcastle Pardshaw Flimby Great Clifton Parsonby Plumbland Kirkbride Prospect Port Skinburness Thursby Tallentire Torpenhow Ullock Waverton The Local Service Centres have been Westnewton selected on the basis of having a shop, school and public transport. It was considered that Rural Villages have been identified by taking these services were core facilities for a the settlements designated as either a limited community and a good basis to build future growth village or an infill village in the current sustainability. Local plan and applying an additional requirement for each settlement to be located Rural Villages (“RV”): within 2.5 miles from a primary school. The aim of this approach is to try and ensure that Anthorn Blencogo the smaller rural settlements are retained in Blennerhasset Blitterlees the hierarchy to allow small scale Bolton Low Houses Bothel infill/’rounding off’ development that can Bowness on Solway Branthwaite contribute to the sustainability of these Bridekirk Broughton Cross communities. Camerton Crosby Crosby Villa Dean Proposed distribution of housing growth Deanscales Dovenby Eaglesfield Fletchertown The Local Plan seeks to ensure that the Gilcrux Glasson majority of development will be located in the

9 SHLAA: Main Report Evidence Base Allerdale Local Plan

existing urban centres that provide the best Using the proposed distribution of housing range of services, employment opportunities growth set out in the Local Plan, the bulk of and access to public transport. This is housing development would be located within considered to be the most sustainable the main towns of Aspatria, Cockermouth, approach as it makes the most use of existing Maryport, Silloth, Wigton and Workington. physical, utility and social infrastructure and also reduces the need to travel. Proposed housing targets

However it is considered that the smaller rural Based on the proposed distribution of the settlements should have the opportunity to overall housing target, Table 2 sets out the accommodate small-scale infill/rounding off Total Annual development where appropriate. This is essential if they are to remain sustainable and Principal Service centre (PSC) 1808 106 to address some of the local need for housing Key service centres (KSC) 2015 119 and employment outside the main centres. Local service centres (LSC) 1034 61 Rural villages (RV) 310 18 Table 1 illustrates how the Council proposes TOTAL 5167 304 to distribute future housing growth between

Table 2: Housing growth targets for each tier of the % settlement hierarchy. Principal Service centre (PSC) 35% numbers for each tier of the settlement Key service centres (KSC) 39% hierarchy Local service centres (LSC) 20% Rural villages (RV) 6% Therefore the Council must demonstrate that Table 1: Distribution of housing target between each tier of is enough land can be provided to meet: the settlement hierarchy. • A gross housing target of 5167 dwellings each tier of the hierarchy. over the plan period and the numbers required at each tier of the settlement hierarchy:

SHLAA: Main Report 10 Allerdale Evidence Base Local Plan

• PSC: 1808 dwellings Housing • KSC: 2015 dwellings Numbers • LSC: 1034 dwellings • RV: 310 dwellings a Total 5168 b Annualised Target (a/17) 304 Establishing the housing target for the first c 5 Year Target (bx5) 1520 five years of the Plan d 5 Year Target + buffer ((cx0.2)+c) 1824 The NPPF requires that local planning e Annualised Target + buffer (d/5) 364

authorities identify annually sufficient Table 3: Methodology for the 5 year land supply calculation deliverable sites to provide five years worth of based on the housing target set out in the emerging Local Plan housing against their housing requirements.

Local planning authorities with a record persistent under delivery of housing are Based on the proposed distribution of the expected add a buffer of 20% to their five year overall housing target, the following 5 year target. Based on historic rates of housing supply targets are set for each tier of the delivery, the Council considers itself to be a settlement hierarchy: 20% buffer authority. 5 Year Supply Target Based on a target of 5167 dwellings to be Total 1824 delivered over a 17 year period (2011-2028), Principal Service Centre 638 the annualised requirement is 304 dwellings. This gives a 5 year supply target of 1520 Key Service Centre 711 dwellings. However when the 20% buffer Local Service Centre 365 required by the NPPF is added, this increases Rural Villages 110 the 5 year supply target to 1824 dwellings. Table 4: 5 year land supply target numbers for each tier of the settlement hierarchy set out in the emerging Local Table 3 illustrates this calculation: Plan

11 SHLAA: Main Report Evidence Base Allerdale Local Plan

Table 4 illustrates that in order to demonstrate a 5 years supply of deliverable sites the Council must establish that there is:

• An adequate supply of deliverable SHLAA site that will provide 1824 dwellings during the first 5 years of the plan and the numbers required at each tier of the settlement hierarchy:

• PSC: 638 dwellings • KSC: 711 dwellings • LSC: 365 dwellings • RV: 110 dwellings

SHLAA: Main Report 12 Allerdale Evidence Base Local Plan

4 Gross capacity of SHLAA sites

Meeting the housing growth target set out in the emerging Local Plan to be found sound, in the Allerdale Core Strategy it must be also be demonstrated that there are enough sites of sufficient capacity of located in The emerging Local Plan sets out housing right places. The Council must to establish growth target for the Borough of 5167 that the spatial strategy and the proposed dwellings over the plan period 2011-2028. distribution of housing growth identified in the

emerging Local Plan is achievable. No. Dwellings Local Plan housing target 5167 SHLAA Local Plan Site Target Total capacity of SHLAA sites 9099 Capacity Table 5: Comparison of the cumulative capacity of SHLAA sites against the housing target set out in the Principal Service emerging Local Plan 2433 1808 Centre Key Service Centres 3466 2015 Table 5 illustrates that based on the Maryport 1183 620 assumption in relation to density and NDA, the sum of the capacity of the sites included in the Cockermouth 653 517 SHLAA considered to have potential for Wigton 982 517 residential development is 9099 dwellings . Aspatria 592 207

The cumulative capacity of the SHLAA sites Silloth 56 155 exceeds the proposed housing target set out Local Service Centre 2150 1034 in the emerging Local Plan. Therefore it can be demonstrated that sufficient land has been Rural Villages 1050 310 identified to fulfil it. TOTAL 9099 5167 Table 6: Comparison of the capacity of SHLAA sites against Meeting the housing targets for each tier the housing target for each tier in the settlement of the proposed settlement hierarchy hierarchy set out in the emerging Local Plan

In order for the housing strategy/target set out

13 SHLAA: Main Report Evidence Base Allerdale Local Plan

Table 6 illustrates that based on the total capacity SHLAA sites within each tier of the settlement hierarchy exceed the target set out in the emerging Local Plan.

In terms of the larger settlements in the hierarchy which have their identified growth targets, with the exception of Silloth, there is sufficient land to meet this requirement over the plan period. In the specific case of Silloth, sites have been identified in the adjacent villages of Blitterlees and Skinburness which could be used to offset this deficiency if required.

The results of the SHLAA demonstrate that the proposed housing strategy contained within the Core Strategy is deliverable at a strategic level:

• The gross capacity of sites included exceeds the proposed housing target for the plan period

• The gross capacity of sites included exceeds the housing targets identified for each tier of the proposed settlement hierarchy

SHLAA: Main Report 14 Allerdale Evidence Base Local Plan

5 5 year supply of deliverable sites

Ensuring a supply of deliverable housing land during the first five years of the Core Establishing the housing target for the first Strategy five years of the Plan

A sufficient number of SHLAA sites have been As set out in Table 3, based on a target of 5168 identified to demonstrate that there is a dwellings to be delivered over a 17 year period sufficient amount of land for housing to fulfil the (2011-2028), the annualised target is 304 proposed housing target set out in the emerging dwellings. This gives a 5 year supply target of Local Plan and that the distribution of this 1520 dwellings. However when the 20% buffer growth, is achievable. required by the NPPF is added, this increases the 5 year supply target to 1824 dwellings. The final test that must be fulfilled in order for the Council to establish that the housing Therefore in order for the Council to strategy/target set out within the emerging Local demonstrate a supply of deliverable housing Plan is sound is to demonstrate a supply of land during the first five years of the emerging deliverable land for the first five years of the Local Plan it must be established that there are plan. sufficient deliverable sites identified in the SHLAA to meet the supply target of 1824 The NPPF requires that local planning dwellings authorities identify annually sufficient deliverable sites to provide five years worth of Table 7 illustrates that there is an adequate housing against their housing requirements. supply of deliverable SHLAA sites within each tier of the hierarchy to support the delivery of Local planning authorities with a record the housing strategy during the first five years of persistent under delivery of housing are the plan. expected add a buffer of 20% to their five year target. Based on historic rates of housing delivery, the Council considers itself to be a 20% buffer authority.

15 SHLAA: Main Report Evidence Base Allerdale Local Plan

Deliverable 5 Year SHLAA site Target capacity

Total 1824 3157 Principal Service Centre 638 1010 Key Service Centre 711 1091 Maryport 218 432 Cockermouth 182 0 Wigton 182 337 Aspatria 73 266 Silloth 55 56 Local Service Centre 365 498 Rural Villages 110 558 Table 7: Comparison of the capacity of deliverable SHLAA sites against the 5 year housing target for each tier in the settlement hierarchy set out in the emerging Local Plan

There are insufficient deliverable site identified within settlement of Cockermouth. This is due to capacity problems at the wastewater treatment works (“WwTW”) serving the town. In this case it is proposed to phase housing delivery in the town to the back end of the plan period to allow the necessary upgrades to the WwTW to be implemented.

SHLAA: Main Report 16 Allerdale Evidence Base Local Plan

6 SHLAA - List of deliverable sites

Principal Service Centre SHLAA Ref Location Settlement Site Site Area capacity EXWK27 Land off Woodville Way Harrington Workington 3.6 82 EXWK20 Land at Main Road (c) Harrington Workington 4.7 107 EXWK28 Land at Northfield Avenue Harrington Workington 0.4 11 EXWK21 Land off Stainburn Rd Stainburn Workington 1.6 43 EXWK08 Land at Whitestiles Seaton Workington 1.3 33 EXWK11 Land off St Andrews Road Stainburn Workington 1.0 26 N11.WK08 Land off Ashfield Road Ashfield Road Workington 10.0 225 EXWK22 Land at Eastlands Farm Harrington Workington 1.5 38 EXRU19 Land at Whitestiles, Seaton Seaton Seaton 2.7 65 AAWK35 Land off Barnett Drive Seaton Seaton 0.6 18 N11.WK19 Land opposite Yearl Rise Seaton Seaton 7.3 164 N11.WK18 Land at Derwent Avenue Seaton Seaton 1.4 36 EXWK33 Land off Seaton Road Seaton Workington 7.2 162 TOTAL 1010

Key Service Centres SHLAA Ref Location Settlement Site Area Site capacity EXAS03 Land adj. Aspatria RUFC Aspatria 2.6 62 EXAS06 Land at Harriston Road Aspatria 9.05 204 EXMP05 Land at Netherhall Road Maryport 7.82 176 N11.MP01 Land adj White Croft Maryport 11.39 256 AASL20 Land off Fell View Silloth 0.74 20 AASL18 Port of Silloth Silloth 1.09 28 AASL01 Rear of Epsom Green Silloth 0.3 8 EXWG07 Land at Syke Road Wigton 3.11 70 EXWG16 Land at Lowmoor Road Wigton 2.07 50 EXWG25 Land off West Road Wigton 8.3 187 EXWG13 Land at Bushgill Head Farm Wigton 0.5 14 AAWG04 Land at Standingstone Heights Wigton 0.61 16 TOTAL 1091

17 SHLAA: Main Report Evidence Base Allerdale Local Plan

Local Service Centres SHLAA Ref Location Settlement Site Area Site capacity

EXRU221 Land at Abbey Farm Abbeytown 2.93 70 RU66 Land Near Christ Church Allonby 0.77 21 EXRU130 Land at Croft House Allonby 0.31 8 RU17 Land at South Terrace Broughton 1.03 26 EXRU15 Land at South Terrace Broughton 0.66 18 EXRU127 Land at Rose Farm Broughton 1.9 48 EXRU185 Land at Rose Farm Broughton 1.2 31 EXRU128 Land at Meetinghouse Lane Broughton 0.5 12 EXRU161 Land at Broughton Moor Broughton Moor 1.6 41 EXRU24 Land at West Lane Flimby 3.1 70 EXRU04 Land to south of Great Clifton Great Clifton 6.78 153 TOTAL 498

Rural Villages SHLAA Ref Location Settlement Site Area Site capacity

N11.SL04 Blitterlees Blitterlees 1.6 41 EXRU96 Land at Bothel Bothel 1.3 33 RU58 Grange farm Bridekirk 1.14 29 EXRU222 Land at Bridekirk Bridekirk 1.73 44 EXRU160 Land at Birkby Lodge Crosby 0.6 16 EXRU85 Land at Crosby Crosby 0.42 11 RU55 Land nr Midcroft Court Dean 0.52 14 EXRU208 Land nr Mellfield Dean 0.43 12 AARU128 Land at Well Head Farm, Dean Dean 0.6 16 EXRU11 Home Farm Deanscales 0.72 19 EXRU170 Dovenby Hall (a) Dovenby 0.59 16 EXRU144 West End Farm Eaglesfield 0.46 12 RU20 Land Eaglesfield Eaglesfield 2.3 62 EXRU21 Land at Gilcrux Gilcrux 0.72 19 EXRU77 Land at Gilcrux Gilcrux 0.75 20 EXRU189 Retreat Farm Gilcrux 0.58 16 EXRU108 Land at Hayton Hayton 0.6 16 EXRU194 Land at Sun Croft Ireby 0.8 22 RU44 Land nr School Kirkbampton 0.53 14 EXRU111 Land at Kirkbampton Kirkbampton 0.63 17 EXRU121 Land at Kirkbampton Kirkbampton 1.04 27 EXRU65 Land East of Seaview Tallentire 0.43 12 EXRU92 Land at Tallentire Tallentire 0.39 11 EXRU154 Land at Tallentire Tallentire 0.73 20 EXRU231 Land at North Lodge Tallentire 0.7 19 EXRU06 Land near Solway View Tallentire 0.3 8 EXRU101 Land at Westnewton Westnewton 0.46 12 TOTAL 558

SHLAA: Main Report 18 Allerdale Evidence Base Local Plan

7 SHLAA - List of developable sites

Principal Service Centre SHLAA Ref Location Settlement Site Site Area capacity EXWK35 Land adjoining Little Croft Harrington Workington 0.8 22 EXWK13 Land at Stocks Hill Harrington Workington 0.4 9 N11.WK12 Northside Pumping Station Harrington Workington 0.3 8 N11.WK03 Former Garth School Coronation Drive Workington 0.5 14 N11.WK10 Fire Station Frances Croft Workington 0.5 12 N11.WK02 Town Hall Oxford St Workington 0.3 8 AAWK05 Site adj Town Quay Stanley Street Workington 0.4 10 AAWK22 Land at Mossbay Road Workington Workington 2.5 59 EXWK30 Land off Woodville Way (b) Harrington Workington 3.7 84 AAWK23 Former Corus Steel Works Derwent Road Workington 25.2 567 EXWK24 Land at Stoneyheugh Stoneyheugh Workington 15.4 346 EXWK23 Land adj Eddycroft Workington 0.6 16 AAWK47 Millburn Croft, Low Seaton (b) Millburn Croft Seaton 0.7 19 AAWK36 Land at Sunnyside Sunnyside Seaton 0.3 9 AAWK32 Land off Park Avenue Park Avenue Seaton 0.7 18 EXWK34 Land at Derwent Close Derwent Close Seaton 2.4 58 EXWK04 Land at Lowca Lane Lowca Lane Seaton 3.6 81 EXWK31 Land near Coachman Inn Seaton 3.73 83 TOTAL 1423

19 SHLAA: Main Report Evidence Base Allerdale Local Plan

Local Service Centre SHLAA Ref Location Settlement Site Area Site Capacity AAAS02 Land at Station Road Aspatria 0.9 23 AAAS11 Land off Pringle Aspatria 0.4 10 AAAS05 Aspatria Car Park Aspatria 0.5 12 EXAS05 Land at Brayton Road Aspatria 1.8 46 AAAS03 Land at Outgang Road Aspatria 1.2 31 EXAS06 Land at Harriston Road Aspatria 9.05 204 EXCK13 Land off Castlegate Drive Cockermouth 4.9 109 EXCK10 Land off Strawberry How Road (b) Cockermouth 11.6 263 EXCK14 Land off Strawberry How Road (a) Cockermouth 4.1 92 EXCK11 Land off Lorton Road Cockermouth 1.4 36 N11.CK02 Fire Station Cockermouth 1.1 27 EXCK04 Land at Lorton Road Cockermouth 5.6 126 AAMP19 Land at Mulgrew Close Maryport 0.4 10 AAMP04 Maryport Harbour (a) Maryport 1.5 38 AAMP05 Maryport Harbour (b) Maryport 0.9 24 EXMP01 Land adj Parkside residential care home Maryport 1.4 35 AAMP29 Land at Glasson Industrial Estate Maryport 2.4 58 EXMP07 Land to the rear of Brooklands (Rose Vale) Maryport 2.7 65 EXMP04 Land adj to Rose Vale Maryport 1.7 42 N11.MP04 Land to rear of Ellenfoot Drive Maryport 9.2 207 N11.MP03 Land adj Ewanrigg Hall Maryport 6.7 151 EXMP03 Land at Ellenborough Maryport 1.2 31 RU07 Land opp Borriskill (Rose Vale) Maryport 4.0 90 AAWG23 Land at The Oaks Wigton 0.5 15 EXWG08 Land at Kirkland Road Wigton 3.9 88 AAWG06 Land off Redmayne Close Wigton 0.8 23 EXWG27 Park Square Wigton 3.8 86 EXWG33 Land at Highmoor Park Wigton 8.9 200 N11.WG05 Land adjacent to Brookside Centre Wigton 0.3 8 EXWG28 Land adjoining auction mart Wigton 3.0 68 EXWG23 Land at Standingstone Heights Wigton 3.1 70 EXWG24 Land at Station Hill Wigton 3.9 87 TOTAL 2375

SHLAA: Main Report 20 Allerdale Evidence Base Local Plan

Local Service Centre SHLAA Ref Location Settlement Site Area Site capacity

EXRU186 Land at Abbeytown Abbeytown 3.5 78 EXRU78 Land at School Brow Brigham 0.8 22 EXRU84 Land at Lawson Garth Brigham 0.9 23 EXRU157 Land at Spring Croft Close Brigham 0.3 9 EXRU150 Land to the rear of Kirklea Broughton 0.7 18 AARU125 East Elms Farm Broughton 0.3 8 RU27 Land at Derwent Park Broughton 0.4 10 EXRU38 Land at Heatherfields Broughton Moor 2.2 54 EXRU45 Land adj Wilsons Terrace Broughton Moor 0.4 12 EXRU211 Newlands Park Dearham 3.7 84 RU64 Land adj Craika Farm Dearham 3.7 84 RU36 Land to the rear of Pow Hall Dearham 2.1 50 EXRU124 Land at Dearham Dearham 3.4 77 EXRU47 Land at Dearham Dearham 1.7 44 AARU93 Mid Town Farm Dearham 1.3 33 EXRU123 Land at Dearham Dearham 1.5 38 EXRU181 Land at Dearham Dearham 0.4 11 AARU94 Land at Midtown Dearham 0.3 8 RU15 Land at Grange Farm Flimby 0.5 13 AARU130 Land at Risehowe Industrial Estate Flimby 1.9 49 EXRU71 Land at William Street Great Clifton 0.6 16 EXRU224 Land at William Street Great Clifton 0.4 11 EXRU118 Land at Great Clifton Great Clifton 1.7 44 RU05 Land at Lowther Street Great Clifton 1.0 24 AARU21 Land off Moor Road Great Clifton 1.0 26 EXRU39 Land at Moor Road, Great Clifton 0.3 8 RU63 Land off Chestnut Grove Kirkbride 0.6 16 RU62 Land off West Lane Kirkbride 2.0 47 AARU64 Land near Bridge Hill Kirkbride 1.7 43 RU28 Land to the rear of Bank End Prospect 1.2 30 EXRU42 Field to rear of Greenbank Close, Prospect 1.6 42 RU32 Land adj The Steadings Thursby 5.1 115 EXRU106 Land adj Stonehouse Park Thursby 1.0 26 EXRU146 Land at Matty Lonning Thursby 12.4 279 RU30 Land nr How End Farm Thursby 6.7 150 AARU135 Land at Thursby Glebe Thursby 1.0 26 AARU95 Land at Old Vicarage Thursby 0.4 10 AARU102 Land south of Green Close Thursby 0.5 14 TOTAL 1652

21 SHLAA: Main Report Evidence Base Allerdale Local Plan

Rural Villages

SHLAA Ref Location Settlement Site Area Site capacity

AARU105 Land near Blencogo School Blencogo 0.4 10 RU26 Land adj Ravenswood Blencogo 0.3 8 AARU106 Land opposite Blencogo Farm Blencogo 0.4 11 N11.SL06 Land nr Blitterlees Farm Blitterlees 0.6 16 EXRU178 Garage at Brough Hill Bolton Low Houses 0.7 19 RU71 Land adj Brookside Bolton Low Houses 0.6 15 EXRU180 Land at Bothel Parks Bothel 0.5 14 EXRU227 Land at Bothel Bothel 0.4 11 AARU36 Land at Bothel Parks Bothel 0.8 22 AARU35 Land off School Lane (a) Bothel 0.4 11 EXRU18 Land at Broughton Cross Broughton Cross 0.5 13 EXRU66 Land at Broughton Cross Broughton Cross 1.9 49 AARU16 Land off Lonsdale Close Crosby Villa 0.6 16 EXRU164 Land at Gilcrux Gilcrux 0.6 17 AARU29 The Garth Gilcrux 0.3 8 EXRU156 Fish Farm Gilcrux 3.0 68 AARU113 Land off Mill Road Glasson 0.6 16 RU47 Midtown Farm Kirkbampton 0.3 8 RU14 Land at Scots Croft Little Clifton 1.8 46 EXRU151 Land at West End Farm Newton Arlosh 0.9 24 EXRU12 Land at Sunny Bank Newton Arlosh 0.5 14 RU59 Land near the Joiner's Arms Newton Arlosh 0.5 12 EXRU114 Land at Oulton Oulton 0.8 21 EXRU54 Land adj Rectory Farm House Parsonby 0.6 15 AARU122 Land at 270 Skinburness Road Skinburness 0.5 12 EXRU37 Land at The Beeches, Waverton Waverton 0.6 16 TOTAL 492

SHLAA: Main Report 22 Allerdale Evidence Base Local Plan

A1 Appendix 1: Spatial distribution of settlements

23 SHLAA: Main Report Evidence Base Allerdale Local Plan

A2 Appendix 2: Maps of deliverable and developable sites

Principle Service Centre:

Workington (including Harrington, Seaton, Siddick and Stainburn)

Key Service Centres:

Aspatria Cockermouth Maryport Silloth Wigton

Local Service Centres:

Abbeytown Allonby Brigham Broughton Broughton Moor Dearham Flimby Great Clifton Kirkbride Prospect Thursby

Rural Villages:

Anthorn* Blencogo Blennerhasset* Blitterlees Bolton Low Houses Bothel Bowness on Solway * Branthwaite* Bridekirk Broughton Cross Camerton* Crosby Crosby Villa Dean Deanscales Dovenby Eaglesfield Fletchertown Gilcrux Glasson Greysouthern* Hayton Ireby Kirkbampton Langrigg* Little Bampton* Little Clifton Mawbray* Mockerkin* Newton Arlosh Oughterside* Oulton Papcastle* Pardshaw* Parsonby Plumbland* Port Carlisle* Skinburness Tallentire Torpenhow* Ullock* Waverton Westnewton

* No developable/deliverable sites have been identified in these rural villages

SHLAA: Main Report 24 Allerdale Evidence Base Local Plan

Principal Service Centre

Workington

Deliverable and Developable Sites

Deliverable Developable

25 SHLAA: Main Report Evidence Base Allerdale Local Plan

Workington (North)

SHLAA: Main Report 26 Allerdale Evidence Base Local Plan

Workington (South)

27 SHLAA: Main Report Evidence Base Allerdale Local Plan

Harrington

SHLAA: Main Report 28 Allerdale Evidence Base Local Plan

Seaton

29 SHLAA: Main Report Evidence Base Allerdale Local Plan

Stainburn

SHLAA: Main Report 30 Allerdale Evidence Base Local Plan

Key Service Centres

Maryport Cockermouth Wigton Silloth Aspatria

Deliverable and Developable Sites

Deliverable Developable

31 SHLAA: Main Report Evidence Base Allerdale Local Plan

Maryport (North)

SHLAA: Main Report 32 Allerdale Evidence Base Local Plan

Maryport (South)

33 SHLAA: Main Report Evidence Base Allerdale Local Plan

Cockermouth (West)

SHLAA: Main Report 34 Allerdale Evidence Base Local Plan

Cockermouth (East))

35 SHLAA: Main Report Evidence Base Allerdale Local Plan

Wigton (North)

SHLAA: Main Report 36 Allerdale Evidence Base Local Plan

Wigton (South)

37 SHLAA: Main Report Evidence Base Allerdale Local Plan

Silloth

SHLAA: Main Report 38 Allerdale Evidence Base Local Plan

Aspatria

39 SHLAA: Main Report Evidence Base Allerdale Local Plan

Local Service Centres

Abbeytown Allonby Brigham Broughton Broughton Moor Dearham Flimby Great Clifton Kirkbride Prospect Thursby

Deliverable and Developable Sites

Deliverable Developable

SHLAA: Main Report 40 Allerdale Evidence Base Local Plan

Abbeytown

41 SHLAA: Main Report Evidence Base Allerdale Local Plan

Allonby

SHLAA: Main Report 42 Allerdale Evidence Base Local Plan

Brigham

43 SHLAA: Main Report Evidence Base Allerdale Local Plan

Broughton

SHLAA: Main Report 44 Allerdale Evidence Base Local Plan

Broughton Moor

45 SHLAA: Main Report Evidence Base Allerdale Local Plan

Dearham

SHLAA: Main Report 46 Allerdale Evidence Base Local Plan

Flimby

47 SHLAA: Main Report Evidence Base Allerdale Local Plan

Great Clifton

SHLAA: Main Report 48 Allerdale Evidence Base Local Plan

Kirkbride

49 SHLAA: Main Report Evidence Base Allerdale Local Plan

Prospect

SHLAA: Main Report 50 Allerdale Evidence Base Local Plan

Thursby

51 SHLAA: Main Report Evidence Base Allerdale Local Plan

Rural Villages

Blencogo Blitterlees Bolton Low Houses Bothel Bridekirk Broughton Cross Crosby Crosby Villa Dean Deanscales Dovenby Eaglesfield Fletchertown Gilcrux Glasson Greysouthern Hayton Ireby Kirkbampton Little Clifton Newton Arlosh Oulton Parsonby Skinburness Tallentire Waverton Westnewton

Deliverable and Developable Sites

Deliverable Developable

SHLAA: Main Report 52 Allerdale Evidence Base Local Plan

Blencogo

53 SHLAA: Main Report Evidence Base Allerdale Local Plan

Blitterlees

SHLAA: Main Report 54 Allerdale Evidence Base Local Plan

Bolton Low Houses

55 SHLAA: Main Report Evidence Base Allerdale Local Plan

Bothel

SHLAA: Main Report 56 Allerdale Evidence Base Local Plan

Bridekirk

57 SHLAA: Main Report Evidence Base Allerdale Local Plan

Broughton Cross

SHLAA: Main Report 58 Allerdale Evidence Base Local Plan

Crosby

59 SHLAA: Main Report Evidence Base Allerdale Local Plan

Crosby Villa

SHLAA: Main Report 60 Allerdale Evidence Base Local Plan

Dean

61 SHLAA: Main Report Evidence Base Allerdale Local Plan

Deanscales

SHLAA: Main Report 62 Allerdale Evidence Base Local Plan

Dovenby

63 SHLAA: Main Report Evidence Base Allerdale Local Plan

Eaglesfield

SHLAA: Main Report 64 Allerdale Evidence Base Local Plan

Gilcrux

65 SHLAA: Main Report Evidence Base Allerdale Local Plan

Glasson

SHLAA: Main Report 66 Allerdale Evidence Base Local Plan

Hayton

67 SHLAA: Main Report Evidence Base Allerdale Local Plan

Ireby

SHLAA: Main Report 68 Allerdale Evidence Base Local Plan

Kirkbampton

69 SHLAA: Main Report Evidence Base Allerdale Local Plan

Little Clifton/Bridgefoot

SHLAA: Main Report 70 Allerdale Evidence Base Local Plan

Newton Arlosh

71 SHLAA: Main Report Evidence Base Allerdale Local Plan

Oulton

SHLAA: Main Report 72 Allerdale Evidence Base Local Plan

Parsonby

73 SHLAA: Main Report Evidence Base Allerdale Local Plan

Skinburness

SHLAA: Main Report 74 Allerdale Evidence Base Local Plan

Tallentire

75 SHLAA: Main Report Evidence Base Allerdale Local Plan

Waverton

SHLAA: Main Report 76 Allerdale Evidence Base Local Plan

Westnewton

77 SHLAA: Main Report