CALUMPIT WATER DISTRICT a pro-active, self-reliant, dynamic and highly competitive water institution with utmost concern on environmental protection and gearing towards the realization of the government’s goals for national development is fully committed to provide safe, adequate, potable and affordable water supply not just in the whole municipality of Calumpit but together with its adjoining areas (Capalangan and Sulipan , Longos , some part of Dampol , San Francisco, Caduang Tete, Candelaria, Pampanga) with compliance and satisfaction of customer and other interested parties including statutory and regulatory body of the district. The district is committed in maintaining process excellence with consistency by delivering Quality Management System (QMS) requirements in combination with continuous process improvement achieving it through CWD’s Quality Objectives.

A. LIST OF COMPLETED AND ON-GOING GOVERNMENT/PROJECTS/ACTIVITIES (PPA)

COMPLETED PROJECTS

Name of Project Project Cost Beneficiaries (Php)

1. Installation of waterline at Phase II, 2,416,727.00 Residents of Iba O Este Northville IX Relocation Site, Calumpit, Bulacan at Iba O Este, Calumpit, Bul.

2. Interconnection of waterline at Sitio 1 Sapang 733,278.00 Residents of Sitio 1 Bayan and Sto. Niño Highway, Calumpit,Bul. Sapang Bayan and Sto. Niño Highway,Calumpit, Bulacan

3. Construction of Meysulao”Riverside” Pumping 5,879,965.00 Residents of Meysulao Station at Purok4, Bgy. Meysulao and and San Miguel,Calumpit, Installation of Transmission Line from Meysulao Bulacan to San Miguel

4. Construction of Iba Este Pumping Station at 5,908,199.41 Residents of Iba Este, Bgy. Iba Este, Calumpit, Bulacan Calumpit, Bualacan

5. Construction of Perimeter Fence at Central 401,373.00 Residents of Balungao Balungao Pumping Station, Calumpit, Calumpit,Bulacan Bulacan

6. Installation of new lateral pipeline at Sitio Centro 59,217.00 Residents of Sitio Centro Bgy. Sto. Niño, Calumpit, Bulacan to. Niño, Calumpit Bulacan

7. Installation of parallel pipeline from San Jose 1,056,555.00 Residents of Metro San Pumping Station to Calumpit-Hagonoy Boundary Jose, Calumpit, Bulacan

8. Drilling of one (1) production well at bgy. Gatbuca, 2,445,900.00 Residents of Frances, Calumpit, Bulacan Gatbuca, Poblacion, Balungao, Corazon, and Sucol,Calumpit, Bulacan

9. Quality Management System (QMS) 616,000.00 CWD Concessionaires ISO 9001:2015 Certification

ON-GOING PROJECT

Name of Project Project Cost Beneficiaries (Php)

1. Installation of new transmission line 2,572,874.00 All Calumpiteños from Labangan Bridge No.1 to 6 (bgy.Iba O Este to Caniogan,Calumpit, Bulacan)

B. CWD SOCIAL ADVOCACY

Activities completed to promote corporate social responsibility:

• CWD employees abled to donate less than 40 bags of different type of blood to Philippine Red Cross during Blood Letting activity on October 1 as part of the CWD’s 36th Anniversary celebration.

• Participated in Mangrove Tree Planting Activity on September 23, 2016 in Obando, Bulacan spearheaded by the Bulacan Association of Water Districts (BAWD) which aims to preserve and protect the environment.

• Conducted Buhay Kyut Program (Kalusugang Yaman Ugnay sa Tubig) in coordination with LWUA at F. Mendoza Memorial Elementary School on August 12, 2016. This is to promote health and proper hygiene, solid waste management, water conservation and environmental protection among pupils, teachers and parents in elementary.

• Provides free flowing water to all fire hydrants in Calumpit for the needs of Bureau of Fire-Calumpit Station for fire suppression and flushing of debris brought by flood in Public Elementary schools and other government and private establishments in Calumpit.