I5 TRUNNION REPLACEMENT PROJECT HAMILTON CONSTRUCTION HISTORY

• Founded in 1939 by Harry Hamilton. Started as a small firm installing concrete and road irrigation systems.

Harry Hamilton was the concrete foreman on the Rogue River Bridge (above)

Hamilton crew circa 1940 (right) What we do.

Bridge Heavy civil contractors Design-Build Highway Interchange CMGC Design-Bid-Build Transit

Divisions Rail Pacific Northwest – & Mountain West – Colorado & Wyoming Marine Hamilton Construction Alaska Co. Hamilton Rail Concrete structural components MOVEABLE BRIDGE EXPERIENCE

• 2000: Old Youngs Bay Bridge • 2003: I5 Interstate Bridge • 2009: US101 Siuslaw River Bridge • 2009: Broadway Bridge • 2012: UPRR ( Crossing) • 2015: Broadway Bridge • 2016: • 2017: • 2017: Isthmus Slough • 2018: I5 interstate Bridge Trunnion Replacement ESTIMATING

• Advance Project Listings • Example ODOT 12 month outlook • https://www.oregon.gov/odot/Business/Procurement/Pages/Letting_Schedu les.aspx • Targeting work ESTIMATING

• Invitation to bid ESTIMATING

• Scoping work and Soliciting Subs ESTIMATING

• What is the selection criteria? Bidders Experience ESTIMATING

• Breaking it Down ESTIMATING ESTIMATING ESTIMATING ESTIMATING Estimating Activities ESTIMATING

• Scheduling ESTIMATING

• Putting it all together ODOT Bid Results ESTIMATING

• Estimating to Construction Pass-off CONSTRUCTION & F ABRICATION

• Fabrication • Done out of State by G&G Steel of Russelville Alabama • Specialty Fabrication • Coordination of fabrication and inspection • Delivery CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION

• Construction • 2 year long project (Fabrication the largest portion of this). • Onsite work limited to 3 month period of time. Aprox 6 weeks pre-closure, and approx. 6 weeks post closure. • Lots of time to develop plans and systems, not a lot of time to react to issues once on-site. • Fire Impact • Closure delayed due to wildfire and need to leave evacuation routes open. • Traffic Staging • Very Complex traffic staging, dealing with both directions of I5 at once. • Work could not start until traffic staging was complete • Continual monitoring and twice daily shifts during closure. • Daily Stakeholder meetings (lots of meetings) • So many different stakeholders, the meetings were endless. • Closure Schedule • Around the clock operations through completion CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION

• Questions??? CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION CONSTRUCTION & F ABRICATION