CONTENTS

Page EXECUTIVE SUMMARY 1

MEETING LOCAL DEVELOPMENT SUSTAINABLY 3

DEVELOPING A BALANCED HOUSING MARKET 5

PROGRESS AGAINST LOCAL DEVELOPMENT FRAMEWORK 7 TARGETS PROGRESS ON ALLOCATED SITES 12 PROGRESS ON WINDFALL SITES 15 PROGRESS ON NEW LOCAL PLAN DRAFT ALLOCATIONS 16

LOCAL DEVELOPMENT FRAMEWORK – 5 YEAR SUPPLY 18

HEDNA BASED – FIVE YEAR SUPPLY – EMERGING LOCAL PLAN 19

ANNEXES:

ANNEX 1: HOUSING SUPPLY SUMMARY TABLE 24

ANNEX 2: ACTIVITY SUMMARY OF POST 2014 SITES 25

ANNEX 3: LDF ALLOCATED SITES 27

WINDFALL SITES BY SUBAREA

ANNEX 4: SUB AREA 32 ANNEX 5: SUB AREA 41 ANNEX 6: SUB AREA 55 ANNEX 7: STOKESLEY SUB AREA 67 ANNEX 8: SUB AREA 74

ADDITIONAL STUDIES

ANNEX 9: SCHEDULE OF DEMOLITIONS 2019/2020 89 ANNEX 10 : INTERIM PLANNING POLICY GUIDANCE SITES 90 ANNEX 11: PERMITTED DEVELOPMENT 91 ANNEX 12: APPEAL SUMMARY 2004 – 2020 92 EXECUTIVE SUMMARY

Development Plans and Targets

 The current development plan – the Local Development Framework (LDF) has a housing requirement for 6,540 dwellings up to 2026, the annual target was 330 dwellings (gross) up to 2008, then 290 dwellings per year thereafter or 280 dwellings per year net.  The emerging local plan as informed by the Housing and Economic Development Needs Assessment 2018 (HEDNA) has identified an annual housing requirement of 315 dwellings per year net. This gives a housing requirement to 2035 of 6,615 homes.  The government introduced a housing requirement under the Housing Delivery Test using the “Standard Method” which gives a housing requirement of 226 homes per year  On each of these Hambleton has exceeded the set requirements: o Against the LDF target, since 2004 there has been 5,482 completions against a target of 4,800 dwellings, averaging 343 homes per year. o Since 31st March 2014, the start date for the new local plan, in all 2,739 homes up to early March 2020 have been completed against a requirement of 1,890 dwellings. Completions have averaged 457 homes per year. Development Progress since 1st April 2019  From 1/4/19 to early March 2020 there have been 596 gross completions, this is the highest annual number of completions to date, when results for the full year are available, and the final total is expected to exceed 600, given the current levels of activity. During the period 2018/2019, the gross number of homes completed was 475.  Generally demolition numbers are very low for Hambleton. During 2019/2020 there were 23 notified demolitions of which only five sites saw loss of dwelling stock totalling 5 dwellings, see appendix 4, for details. Most demolitions were for replacement dwellings (which are excluded from HDC’s housing supply figures) or for other non-residential structures. Therefore, during the year 2019/2020 gross completions numbered 596 units, which equates to 591 net.  The LDF target is 55% completions on Brownfield land, in 2019/2020 just 13.2% were completed on Brownfield sites, compared to 23.2% in 2018/2019.  In 2019/2020, the total number of dwellings permitted on brownfield sites was 31% of the total. In 2018/2019, the figure was 37.6%.(Figure 2.1).  During 2019/2020, 326 dwellings were permitted, with 57 homes gaining permission on three LDF allocated sites and 269 dwellings were permitted on windfall sites. Yet supply showed significant an increase over the figure in the 2018/2019 Strategic Housing Land Availability Assessment as the draft local

plan allocations were added to the supply despite an increase in building tempo.  Major strategic sites allocated under the Local Development Framework are well underway in Northallerton and at Sowerby, Thirsk.  The North Northallerton scheme was submitted in May 2015, work started in March 2017, residential development was well underway by March 2020, with nearly 70% of phase 1 complete (208 units built out of 298 on site), permission for phase 2 was approved in February 2020 for a further 472 units, the link road is due for completion by October 2020.  Sowerby Gateway strategic site phases 1 & 2 saw 339 completions, phase 3 comprises 641 dwellings, to date 143 units have been built, with 86 so far during 2019/2020. In addition, a further 97 affordable units were approved at Planning Committee in October 2019, this scheme has yet to start. The total capacity for Sowerby Gateway is 1,077 dwellings.

 There were 118 (19.7% of the 2019/20 total) new build affordable homes completed in this monitoring period compared with 92 during 2018/2019 (see Figure 3.15). The target from the latest Housing and Economic Development Needs Assessment is to provide 55 affordable units per year.  Five Year Supply - Hambleton has a five year supply for the period ending 5th March 2020. o There were a potential total of 3,492 units expected to be delivered within the next 5 years to 2025, this equates to a 10.5 year supply (with a 5% buffer applied). o As at early March 2020 there are over 600 homes under construction, across over 400 active sites. o Supply for the next five years to 2025 comes from three sources: . 1,790 dwellings from LDF Allocations . 1,227 dwellings from known windfall sites (that is, sites with planning permission . 475 from proposed new draft allocations under the new local plan o Post 2025 there are a further 1,645 dwellings to be built.  Windfall permissions have remained healthy, in total, since 2004 the number of windfall dwellings permitted amounts to 6,954 dwellings, averaging 435 homes per year. This rate has the raised slightly since April 2014 the base date for the new local plan, 336 windfall homes have been permitted per year. Since 2004 windfall completions account for 61% of the total completions totalling 3,339 homes.  Work on establishing a “non-implementation” rate has shown that this is very low, averaging since 2004, about 3.0% of permitted units, totally just 320 units out of a potential 10,621 plots on sites with or which have had planning permission.

 In total, there are 880 dwellings to be provided across 377 identified sites of under 1ha. This will amount to 18% of the total supply as at March 2020 and 13.3% of the total housing requirement for the emerging local plan of 6,615 dwellings.

CHAPTER 1

MEETING LOCAL DEVELOPMENT NEEDS SUSTAINABLY

SUSTAINABLE DEVELOPMENT 1.1 Sustainable development has been at the heart of the development plan for many years; in the current adopted Core Strategy in Core Policy CP1 and now in the emerging Local Plan in Policy S 1.

1.2 A key part of achieving sustainable development is redevelopment of previously developed land (brownfield) in preference to the development of greenfield land. This aim is reflected in current development plan target in Development Policy DP12.

1.3 A key part of achieving sustainable development is redevelopment of previously developed land (brownfield) in preference to the development of greenfield land. This aim is reflected in current development plan target in Development Policy DP12.

1.4 Figures 1.1 and 1.2 below show respectively how many dwellings were granted planning permission and how many were completed on greenfield and previously developed land (brownfield) since 2004, the start of the LDF plan period.

Dwellings Permitted Year Total Brownfield Greenfield 2004/2005 226 76% 70 24% 296 2005/2006 473 95% 26 5% 499 2006/2007 510 90% 57 10% 567 2007/2008 265 87% 40 13% 305 2008/2009 127 70% 55 30% 182 2009/2010 72 71% 30 29% 102 2010/2011 156 86% 26 14% 182 2011/2012 388 85% 69 15% 457 2012/2013 138 12% 1049 88% 1187 2013/2014 470 70% 206 30% 676 2014/2015 55 16% 284 84% 339 2015/2016 35 3% 1268 97% 1303 2016/2017 141 10% 1255 90% 1396 2017/2018 148 30% 346 70% 494 2018/2019 204 38% 338 62% 542 2019/2020 101 31% 225 69% 326

Figure 1.1: Permissions Granted for Dwellings on Greenfield and Brownfield Land

1.5 Between 2004 and 2012 most of the permissions granted for residential development were on brownfield land. As LDF allocations came forward, greenfield permissions tended to dominate, so in 2015/2016 just 3% of dwellings were permitted on brownfield land. There has been an improvement in the brownfield permission rate since 2015/2016 seeing an increase it is holding steady over the past three years at around 30%. So far during 2019/2020 around 31% of dwellings gaining permission were on brownfield land.

Dwellings Completed Year Total Brownfield Greenfield 2004/2005 127 58% 91 42% 218 2005/2006 297 73% 108 27% 405 2006/2007 351 91% 36 9% 387 2007/2008 379 91% 39 9% 418 2008/2009 257 85% 46 15% 303 2009/2010 185 81% 42 19% 227 2010/2011 231 83% 49 18% 280 2011/2012 162 92% 15 8% 177 2012/2013 130 87% 20 13% 150 2013/2014 111 57% 83 43% 194 2014/2015 197 62% 120 38% 317 2015/2016 170 46% 197 54% 367 2016/2017 191 34% 376 66% 567

2017/2018 212 51% 205 49% 417

2018/2019 110 23% 365 77% 475

2019/2020 71 12% 525 88% 596

Figure 1.2: Gross housing completions on Greenfield and Brownfield Land

1.6 Figure 1.2 above shows that just 12% of completions in the monitoring period April 2019 to early March 2020 were on brownfield sites. The table above shows a steady reduction in brownfield completions from a peak rate of 92% in 2011/12. This reflects the low proportion of brownfield permissions in previous years.

CHAPTER 2

DEVELOPING A BALANCED HOUSING MARKET

THE SCALE OF NEW HOUSING DEVELOPMENT

2.1 Hambleton’s gross housing requirement as set out in the Local Development Framework (LDF) is 330 per annum for the period 2004 - 2008 and 290 per year for the period 2008 - 2026 (18 years). This provided a plan period target of 6,540 dwellings (gross). There is an indicative expected demolition rate of 10 homes per year. This produces net build rates of 320 and 280 per annum providing a total net completions requirement for 6,320 by 2026 (Figure 2.1 below). It should be noted that this period is longer than that covered by the Council’s Adopted Core Strategy (which is 2004 to 2021).

Annual Requirement Period net gross 2004-2008 (4 years) 320 330 2008-2026 (18 years) 280 290 Total 6,320 6,540 Figure 2.1: LDF Housing requirement – Hambleton

Sub Area LDF Homes Built LDF Windfall Anticipated Housing by Mar'20 Allocations Sites with Homes Requirement (Year 16 To be Built Permission to be To 2026 of LDF) to be Built Delivered by 2026 Bedale 987 767 339 178 1284 Easingwold 873 994 179 368 1541 Northallerton 2186 1497 813 177 2487 Stokesley 728 687 209 211 1107 Thirsk 1766 1537 250 428 2215 Totals 6540 5482 1790 1362 8634

Figure 2.2: Gross sub area split of LDF housing requirement: Allocations DPD with completions and anticipated homes to be built

2.2 Figure 2.2 shows progress against the LDF housing requirement split by sub area. By early 2020, 84% of the LDF requirement had been delivered, this despite a severe slowdown during the last recession. A further 1,790 dwellings are to be provided from LDF allocated sites and 1,362 from known windfall sites (those with planning permission). It is anticipated that in total 8,634 dwellings will be built by 2026, the majority of the outstanding homes are expected to be built within the next five years, in total this is 2,094 more homes that the LDF envisaged. With recent windfall permissions are coming forward at a rate averaging 336 per year, an extra 1,680 units could be added to the supply by 2026, this on top of known completions & commitments.

2.3 The Strategic Housing Market Assessment (SHMA) was published in January 2016 and updated in September 2016. The SHMA was updated in June 2018 with the publication of the Housing and Economic Development Needs Assessment (HEDNA).

2.4 This gave an overall housing requirement of 315 dwellings per year, 55 of which should be affordable. Over the plan period from 2014 to 2035 this equates to 6,615 homes. Completions - 2004/2005 - Up to mid 2020 Years run from April to March

7 8 9 0 5 6 7 8 9 0 1 2 3 4 6 0 1 1 1 00 00 00 00 01 01 01 015 01 0 01 02 2 20 2 2 20 20 2 2 2 2 2 201 tal / 2 / / / / / / / 2 / / /2 / /2 riod 4 5 7 8 1 2 3 5/ 6/ 7 8/ 9 0 06 0 0 09 10 1 1 14 To Pe 00 01 01 20 2 2 20 20 20 20 20 20 2 20 20 201 201 201 201 LDF Target Homes required = 330 330 330 330 290 290 290 290 290 290 290 290 290 290 290 290 4,800

Homes delivered = 218 405 387 418 303 227 280 177 150 194 317 367 567 417 475 596 5,498

Under/over supply = -112 75 57 88 13 -63 -10 -113 -140 -96 27 77 277 127 185 306 698 *** **** LDF Over Supply Between 2004/2005 & present, HDC gross completions averaged 344 per year , (the averaged annual LDF requirement was 300 per year - 4,800/16 = 300) Since 2014/2015 (the date for rebased SHMA) completions have averaged 457 per year

* - slight increase in published totals which came out in year end checking.

Figure 2.3: District Housing Provision Update 2004 – 2020

700

600

500

400

300

200

100

0

Homes delivered = LDF Target Homes required =

Completion Progress

2.5 The Council carried out survey work during the year 2019/20 to ascertain the likelihood of sites coming forward within the next five years.

2.6 Contact was made with owners, agents and developers with interests in allocated and larger windfall sites (those with 20 or more dwellings) including those with planning permission, seeking to understand when their sites were likely to be delivered.

2.7 In addition, a number of administrative sources were also used to assess what level of progress had been made :  North Building Control Partnership  Council Tax Returns & results of Council Tax surveys  Street Naming & Numbering information  National House Builders Confederation (NHBC) Monthly Returns  CIL Commencement & Completion Forms  Local estate agents, if sites were being marketed or sold

2.8 In reviewing sites additional evidence was gathered to indicate “intent” to proceed with development, this pre-development activity included:

 Amending / Discharging Planning conditions  The site has been “Street Named & Numbered” & added to the Local Land and Property Gazetteer  Site plans have been submitted and/or approved with Building Inspectors.  Whether the site been offered for sale or sold to a developer  Whether the applicant had undertaken pre- submission consultations.

Many of these activities have a significant cost for the developer and so show a serious intent to proceed.

Completions 1991 - 2020

700 600 500 400 342 300 200 100 0

Annual Net Completions Mean average per annum for the period 1991 - 2019 3 year rolling average

Figure 2.4: Net completions for the period 1991 to 2020

2.9 The net annual housing completion rates for the District since 1991 are illustrated in Figure 2.4 above. Overall, the annualised average completion rate over the long term is 342 dwellings per year. The recent trend from 2007/2008, the beginning of the recession, was for a decreasing number of completions to 2012/2013, with the start of

a recovery in 2013/2014, which has now consolidated over the last five years, with a particular surge in 2019/2020.

Windfall Sites

2.10 Details of windfall completions over the last 16 years are given in Figure 2.5 below. It should be noted that completions during the period 2008 to 2011 are all windfalls. This is because, in the absence of allocations in the former Local Plan and the adoption of the Allocations DPD (in December 2010), all approvals in this period took place on unallocated sites and hence are considered to be windfalls.

2.11 Of the completed dwellings since the start of the Plan period (2004/05), windfalls have accounted for 61% on average (209 dwellings per annum). The contribution from allocated sites has increased steadily from just 1% in 2011/2012 to 72% of all completions in 2016/2017. The percentage completions on allocated sites over the last two years has held steady at around 67% - 68%.

Losses by Total Allocated Windfall Conversion Total LDF Completions Completions Completions or Completions Running Year (gross) (gross) (gross) Demolition (net) Total 2004/05 218 24 11% 194 89% 17 201 201 2005/06 405 107 26% 298 74% 17 388 589 2006/07 387 42 11% 345 89% 54 333 922 2007/08 418 13 3% 405 97% 21 397 1319 2008/09 303 0 0% 303 100% 21 282 1601 2009/10 227 0 0% 227 100% 7 220 1821 2010/11 280 0 0% 280 100% 9 271 2092 2011/12 177 1 1% 176 99% 5 173 2265 2012/13 150 43 29% 107 71% 6 144 2409 2013/14 194 86 44% 108 56% 15 179 2588 2014/15 317 205 65% 112 35% 2 315 2903 2015/16 367 261 71% 106 29% 4 363 3266 2016/17 567 409 72% 158 28% 12 555 3821 2017/18 417 246 59% 171 41% 0 417 4238 2018/19 475 324 68% 151 32% 2 473 4711 2019/20 596 398 67% 198 33% 5 591 5302

AVERAGE 344 135 39% 209 61% 12 331

Figure 2.5 – Allocated & Windfall Completions 2004 2020

AFFORDABLE HOUSING

2.12 Affordable housing policies are contained in Core Policies CP9 and CP9A. The Strategic Housing Market Assessment (SHMA) (December 2011) demonstrated a revised affordable housing need of 320 dwellings per annum between 2011 and 20161. It is a key element of the LDF to ensure that more affordable housing is delivered. The overall amount of affordable housing sought by Core Strategy Policy CP9 is 43%, although the proportion within each sub area differs which is either set at 40% or 50%.

2.13 Recent work on affordable need in the June 2018 Housing and Economic Needs Assessment (HEDNA)13B in support of the emerging new local plan has identified a lower requirement of 55 affordable units per year. This is for the period 2016 to 2035, the end of the new local plan, the HEDNA envisages that 1,048 affordable units will be provided.

Dwellings completed which are Gross Affordable Completions Year Gross Percentage for year 2004/2005 22 10% 218 2005/2006 74 18% 405 2006/2007 104 27% 387 2007/2008 117 28% 418 2008/2009 70 23% 303 2009/2010 45 20% 227 2010/2011 92 33% 280 2011/2012 19 11% 178 2012/2013 43 29% 150 2013/2014 40 21% 194 2014/2015 111 35% 317 2015/2016 112 31% 367 2016/2017 172 30% 565 2017/2018 64 15% 416 2018/2019 92 19% 474 2019/2020 118 20% 596 Totals 1295 5495 Plan period 81 24% 343 average

Figure 2.6: Affordable Dwelling Completions 2004-2020

2.14 Figure 2.6 above shows that the number of new build affordable dwellings delivered in the monitoring year up to early March 2020 was 118, 26 more than in the previous year. There has been a particular surge in provision with 669 affordable units being provided between 2014 to 2020, on average of 112 affordable dwellings built during this period.

1 North Yorkshire SHMA Dec 2011, Appendix 2 Hambleton,p.120 13B HDC HEDNA June 2018.,section 6.23 p.56 Chapter 3

Site Progress – LDF Allocated Sites, Windfall and New Local Draft Allocations

Allocated Sites Progress 2019/2020

3.1 In all there were 44 sites allocated under the Local Development Framework for housing or as part of sites with a mix of uses.

3.2 The 2018/2019 SHLAA noted that some sites were identified as not currently being available to be delivered as allocated in the Plan, this remains the case as at mid March 2020. These sites are:  NH2 – Jewson Timber, Swain Court  NM1 – Northallerton Auction Mart  NM2 – Northallerton Auction Mart Car Park  NM4 – Fire Station Headquarters

3.3 Eighteen Allocated sites or part sites were completed prior to April 2019 :

Site Ref Site Name Date Completed

BM1 Bridge Street, Bedale January 2013

BH4 Former Abattoir, Aiskew March 2015

BH7 East of Hackforth Road, Little Crakehall July 2018

BM4 Leeming Lane, Leeming Bar September 2017

EH1 Former Ward Trailers site, Easingwold July 2015

EH6 South Back Lane, Stillington September 2017

Part EM1 Redrow Homes , Road Easingwold June 2016

Part EM1 Linden Homes, Stillington Road, July 2017 Easingwold NH5 North of A684,Morton-on-Swale September 2018

TH1 Former Cherry Garth Care Home Site June 2015

TH4 Former Turkey Factory, Dalton October 2013

TH5 Way, Carlton Miniott May 2016

TM2A Sowerby Gateway Extra Care October 2016

TM2A Phase 1 – Topcliffe Road / Gravel Hole November 2017 Lane TM2A Phase 2 – Sowerby Gateway – Taylor October 2017 Wimpey TM2A Phase 2 – Sowerby Gateway – Linden December 2018 Homes Source : HDC Planning Policy

3.4 During 2019/2020 the following additional allocated sites were completed :

Site Ref Site Name Date Completed NH1 Former York Trailers, Northallerton April 2019

SH3 “Waters Meet” – Broughton Grange Farm, November 2019 Great Broughton Source : HDC Planning Policy

3.5 There are 11 active allocated sites with construction under way and five allocated sites have planning permission, but no start on site made.

3.6 Progress during 2019/2020 has been rapid:

o BH6 - Land to west of Lyngarth Farm, Bedale – saw 42 dwellings completed out of the 79 permitted. o SH3 – “Waters Meet”, Great Broughton saw 24 dwellings built and site was completed. o NM5B & NM5D – North Northallerton Phase 1 has seen so far 101 units built. o SH1 – White House Farm is rapidly nearing completion with 48 dwellings built in the year with 30 units remaining to be built. o SH4 – Cleveland Lodge – 57 apartments were completed in March 2020. o Sowerby Gateway (TM2a) – has had 86 dwellings built by two developers. o Construction commenced on Persimmon’s part of EH2/EH3 in Easingwold during the summer 2017 and saw their first completions in March 2019, this year 33 were built.

3.7 Up to March 2020, an additional two LDF allocated sites gained permission:

Site Ref Site Name Date Decision Issued NH3 Danes Crest, Brompton – for 21 dwellings December 2019

NM5B / North Northallerton – Phase 2 – for 472 February 2020 NM5D dwellings Source : HDC Planning Policy

3.8 Also the following LDF site have been approved at planning committee and are awaiting their S106 agreements:

Site Ref Site Name Date Approved at Committee BH5 Wilberts Farm, Bedale – 116 dwellings October 2019 permitted Source : HDC Planning Policy

3.9 Out of the 44 Allocated sites, nine do not have planning permission, but on all these sites there has been some pre-decision activity, the sites are :

Site Site Name Current Activity Ref BH1 Masham Road, Bedale Application 19/01511/FUL for 14 units, refused; Extra care units refused Oct'19 - 19/02128/FUL Numbers revert to LDF allocation requirement, all post 5 years BH2 Pig Farm , Aiskew Pre application submitted in April 2016 for 82 units. New Pre-application Feb'20 - 90 units BH8 Hares of Snape Works, Snape Formal Pre-app received for 40 units - 5/8/2016 New Pre-application received 19/02167/PPP - again for around 40 units BM2 North East of Aiskew Pig Farm “Call for Sites” form submitted - North East part of site identified for up to 60 dwellings – no application yet Feb’20 some reported activity by owners EH7 Back Lane, Helperby Land owner had indicated that western part of the site could come forward – some developer interest NM5C North Northallerton – East of Initially 165 units under LDF site New Stokesley Road NM5C now draft allocation for 650 Local units – with site NM5C as first Plan phase. site Pre Application inquiry Jul’19 NOR1 Public Consultation event Sep’19 Screening application Feb’20 SH2 North of Sowerby Crescent, Follows on from SH1 – White New Stokesley House Farm; Outline application Local submitted – 19/00359/OUT in Plan Feb’19 site Committee Resolution to approve STK1 awaiting S106 TH2 Depots, Station Road, Thirsk Planning Application - 16/00950/FUL – for northern part of site refused – Oct’17 TH3 Rybeck Farm , Thirsk Agent pursuing this site as part of a larger “Call for Sites” scheme.

Hambleton Allocated Site Supply Summary

3.10 The table below indicates the previous and current supply from allocated sites within Hambleton:

Total Post 5 Site 5 Year Year Allocated Sites Supply Capacity Supply Supply

1st April 2019 based position 4,153 1,857 918

Mid March 2020 based position 4,788 1,788 1,093

Change During 2019/2020 635 -69 175 Source : HDC Planning Policy

3.11 Allocated sites accounted for 398 completions out of the 596 in 2019/2020; overall five year supply numbers have decreased by 69 units, the post 5 year supply has seen an increase of 175 units. Windfall Sites – Change – 2019/2020

Sources of Windfall Supply

3.12 Windfall development has three elements and is comprised of:

a. “Normal” Windfall – permissions granted in accordance with the development plan (within development limits or as a rural exception site). b. Change of use is possible under prior approval for the conversion of : i. Agricultural buildings to dwellings ii. Offices to dwellings iii. Shops to dwellings. c. Applications allowed on appeal. 3.13 In addition, the nature of windfall supply has changed since 2014, Hambleton introduced an Interim Policy Guidance Note (IPGN) which, following national policy outlined in the NPPF – see core document LDF05.1 – Interim Policy Guidance Note. This seeks to enable development of small-scale development sites, outside development limits of the secondary settlements and villages. 3.14 Since 2014, IPGN and permitted development applications have contributed an extra 607 dwellings to Hambleton’s housing supply. There has been only one major residential appeal allowed during the year up to March 2020, this was for a site at Stokesley Road, Northallerton. This was a full permission (17/01394/FUL) for 17 units. A further 8 minor residential applications were allowed on appeal yielding an extra 19 dwellings.

3.15 The Table below shows the windfall supply position as at March 2020 including expected completions for years 2020/21 to 2024/25:

Windfall Completions by Sub Area Summary : 2020 -2025

Sub Area Total on Site 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Total

Bedale 196 20 50 20 0 0 90 Easingwold 626 85 157 106 19 1 368 Northallerton 300 41 102 31 3 0 177 Stokesley 339 61 71 60 19 0 211 Thirsk 676 81 167 89 56 22 415

District 2137 288 547 306 97 23 1261 Windfalls

3.16 During 2019/2020 an additional 94 new windfall sites gained planning permission adding an extra 269 units to the supply. Windfall completions contributed 31% of all HDC completions in 2018/2019 – 147 in all.

3.17 A 10% non-implementation rate for smaller sites was applied because, larger windfall sites (most of the new windfall are accounted for by large sites that were granted on planning appeal prior to 2017) are more likely to come forward, smaller sites that are more likely to expire.

Smaller Sites Contribution

3.18 With Hambleton being a rural district smaller windfall sites make a significant contribution to supply and will continue to do so, there are 377 identified smaller sites with permission under 1ha in size.

3.19 For these smaller sites, permission was granted up to mid-March 2020, for 1,034 dwellings, in all 154 dwellings have been completed with 880 to be built.

Site Size No. of Sites % Sites 2.0.ha & Over 16 4.0% Sites between 2.0ha & 1.0 ha 9 2.2% Sites less 1.0 ha 377 93.8% District Total 402 100.0%

3.20 As can be seen in the table above on sites with planning permission, smaller sites dominate the housing supply in Hambleton in terms of the number of sites identified with planning permission. However, when looking at the future contribution of sites to housing numbers it is the sites over 2.00 ha that will make the most significant contribution.

Site Size Units to be Built % Sites 2.0.ha & Over 1746 63.4% Sites between 2.0ha & 1.0 ha 127 4.6% Sites less 1.0 ha 880 32.0% District Total 2753 100.0%

New Draft Local Plan Allocated Sites Summary

3.21 The following table lists all the proposed draft allocations for the emerging Local Plan with a short commentary on :  Expected delivery  Any Development progress – e.g. pre-application activity or planning application submitted  An approximate start & completion time

Total to be Total Total Totals to Potential Net Date of Ref Site Address Application No. Site Status Built by 2025 Years Years 2035 Notes Capacity Capacity Update Years 1 - 5 6 - 10 11 - 15 Year 15

Proposed New Local Plan Allocation Northeast of AIB1 18/02393/PPP Draft Allocation 85 85 80 5 0 85 04/03/2020 Pre Planning Enquiry - 18/02393/PPP - Ashgrove,Aiskew Nov'18 for larger site than allocation

Proposed New Local Plan Allocation South of Lyngarth AIB2 Draft Allocation 60 60 0 60 0 60 04/03/2020 No application activity - adjacent site Farm,Bedale BH6 active 100% affordable homes by Korban Homes West of Danes Crest, Application Pre application consultation Jun'19, Detailed BRO1 Brompton 19/01499/FUL 21 21 21 0 0 21 09/04/2020 on site late 2019 Permission approved Dec'19 19/01499/FUL approved for 21 affordable units Feb'20 Discharging conditions Mar'20 Proposed New Local Plan Allocation Sth.Part St Lamberts Drive, Part with pp Southern part of site - 5 dwellings BUR1 18/02364/OUT 25 25 25 0 0 25 04/03/2020 Draft Allocation permitted under 18/02364/OUT 19/02741/REM Reserved Matters submitted Dec'19 Proposed New Local Plan Allocation Developers propose 300 units CAM1 Land off Ripon Way Draft Allocation 55 55 55 0 0 55 04/03/2020 No indictive deliverability Pre Planning Application - 19/02471/PPP

Total to be Totals Total Total Potential Net Built by to Date of Ref Site Address Application No. Site Status Years Years Notes Capacity Capacity 2025 2035 Update 6 - 10 11 - 15 Years 1 - 5 Year 15 Proposed New Local Plan North of Crakehall Allocation CRK1 Water Mill,Little 20/00330/FUL Draft Allocation 17 17 17 0 0 17 02/03/2020 Full Planning Application Crakehall submitted Mar'20 for 21 units Northeast of Proposed New Local Plan Easingwold EAS1 19/01430/PPP Draft Allocation 125 125 70 55 0 125 04/03/2020 Allocation Community Primary Formal Pre-App - July 2019 School Easingwold Draft Allocation for 30 dwellings Land at Skottowe GTA1 Draft Allocation 30 30 30 0 0 30 30/03/2020 Agent: To be developed within 5 Crescent years Proposed New Local Plan Land to the rear of HUB1 Draft Allocation 28 28 28 0 0 28 04/03/2020 Allocation Huby Old Hall,Ruby Developer has 'live' option on site Proposed New Local Plan Harkness Drive , Allocation LEB1 Draft Allocation 85 85 50 35 0 85 04/03/2020 Leeming Agent - can be delivered in next five years Application for 16/00224/OUT approved May'16.Call for Sites 16/00224/OUT (13 submission for larger site at rear of South of units) - approved allocated (phase 2). Outline for Nth. LEB2 Northallerton Road, Reserved Matters 80 67 70 10 0 80 04/03/2020 Call for Sites - B/004/008/H part of site Leeming Bar submitted - Reserved matters submitted 19/01085/REM Jun'19 Proposed New Local Plan Site LEB2 - 80 units Church Commissioners : New Local Plan Site proposed allocation - Pre application NOR1 200 dwellings on NM5C - North activity Total capacity = 650 ; 165 Existing LDF allocation. Northallerton Area, Draft Allocation LDF site NM5C plus 485 for NOR1 Formal Pre- 650 485 170 350 130 650 02/03/2020 East of Stokesley Screening extended site. Application inquiry Road, Northallerton Request - Pre Planning Inquiry Jul'19 submitted Jul'19 20/00299/SCR Public Consultation event Sep'19 Screening request Feb'20

Total to be Totals Total Total Potential Net Built by to Date of Ref Site Address Application No. Site Status Years Years Notes Capacity Capacity 2025 2035 Update 6 - 10 11 - 15 Years 1 - 5 Year 15 Proposed New Local Plan Allocation Submitted under 2015 Call for Sites Beechfield, South SOT1 Draft Allocation 40 40 0 40 0 40 04/03/2020 - T/138/005/H Otterington No indicative deliverability No notified progress Proposed New Local Plan Allocation North of Stillington The developer hopes bring the site STI1 Draft Allocation 35 35 35 0 0 35 04/03/2020 Social Club, Stillington forward for development in the 0-5 year period. LDF Allocation SH2 for 100 dwellings Pre-app May'18. Public consultation being held SH2 - North of Detailed Committee Spring 2018 Sowerby Crescent, application - STK1 resolution to 205 100 140 65 0 205 04/03/2020 Build out rates amended Dec'18 Stokesley 19/00359/OUT - approve Outline application submitted STK1 submitted Feb'19 Feb'19 - still awaiting decision Mar’20 New Local Plan allocation STK1 - 205 in total Proposed New Local Plan Allocation TIS1 Station Road, Thirsk Draft Allocation 110 110 60 50 0 110 04/03/2020 No application activity application submitted Dec'19 - 64 TIS2 Back Lane Sowerby 19/02572/FUL Draft Allocation 50 50 50 0 0 50 04/03/2020 dwellings Proposed New Local Plan Allocation WST1 Bridge View Way Draft Allocation 11 11 0 11 0 11 04/03/2020 No application activity Total to be Totals Total Total Total Total Built by to Potential Net Years Years 2025 2035 Capacity Capacity 6 - 10 11 - 15 Years 1 - 5 Year 15 1,712 1,429 901 681 130 1,712

Future Build Rates

3.22 The expectation had been, that on large sites, the average yearly build rate was approximately 30 dwellings per year per developer. However, over the last six years within Hambleton individual site rates have exceeded this rate. In fact, during 2019/2020 build rates have increased, recent examples include:

Site Max Yearly Rate No. of Developers “Kings Park” - North 46 built during 2019/2020 1 Northallerton “Thurstan” Park” – North 55 built during 2019/2020 1 Northallerton SH1 – White House Farm 58 built during 2018/2019 1 TM2a – Sowerby Gateway 97 built during 2018/2019 2 Redrow Homes, Easingwold 48 built during 2014/2015 1 Former York Trailers Site 70 built during 2015/2016 2 28-34 Bedale Road, Bedale 41 built during 2015/2016 1 Ripon Way Carlton Miniott 40 built during 2015/2016 1 Former Abattoir Site, Aiskew 54 built during 2014/2015 1 EM1 – Linden Homes York Rd 43 built during 2016/2017 1 , Easingwold NH5 - North of A684, Morton- 41 built during 2017/2018 1 on-Swale Source :HDC Planning Policy

3.23 There are two large strategic sites – North Northallerton & Sowerby Gateway, Thirsk with 900 and 980 permitted units respectively; Sowerby Gateway since starting in August 2013 has contributed 399 completions. North Northallerton is now active having two developers on site – Persimmon & Taylor Wimpey; up to March 2020 there were 208 completions. Both these site will continue to make a significant contribution to completion rates in future years.

3.24 Two large sites at Easingwold and Stokesley that were granted permission on appeal will make a significant contribution to delivery rates, this coupled with a steady supply of “normal” windfall, IPGN and prior approval schemes will see rates being maintained.

3.25 A new set of allocated sites for the emerging local plan are likely to be developed before 2021.This will substantially contribute to housing supply and Hambleton will see a substantial increase in delivery of new housing.

Methodology & Data Revisions

3.26 As part of a quality review checks have been undertaken and extra retrospective completions identified, completions being added from 1st April 2004. This may lead to different completion totals than those previously published in older SHLAAs or Authority Monitoring Reports.

3.27 The SHLAA methodology has changed as a result of recent appeal decisions, these refinements include:

 A 10% non-implementation rate for windfalls; this applies to small sites only. For larger windfalls there is information on 5 year build out rates.

3.28 In previous SHLAAs a windfall allowance had been applied; following a review this has now been discontinued.

Chapter 4 Five Year Land Supply

Local Development Framework 4.1 The assessment provides details at district level of the housing supply covering the periods 1 April 2020 – 31 March 2025 (deliverable sites) and 1 April 2025 – 31 March 2026 (the end of the LDF Plan Period).

4.2 From 1 April 2004 to mid-March 2020, there is a surplus over the LDF requirement of 698 dwellings. A 5% buffer is applied to the gross LDF target of 290 units giving a requirement for 305 per year. 4.3 The table below shows that windfall permissions and allocated sites are expected to deliver 3,530 dwellings over the next five years (April 2020 to March 2025). Against a target of 1,523, this gives an oversupply of 2,007 units and therefore constitutes a deliverable five year supply.

LDF Based Supply - Allocated Sites & Windfall Permissions with Planning Permission to March 2020

Annual Supply Supply LDF Year Difference *1 requirement*2 Windfalls Allocations Total

1 2020/21 295 283 578 2 2021/22 618 289 907 Five Year Deliverable 3 2022/23 445 380 825 3,530 1,523 2,007 Supply: 2019-2024 4 2023/24 261 425 686 5 2024/25 128 406 534 Final Year of LDF - 6 2025/26 0 276 276 290 -14 Post 2026 Developable Supply 357 814 1,171 n/a n/a

TOTALS 2,104 2,873 4,977 1,813 1,993

*1 Note : Allocated totals include proposed new Local Plan Allocations *2 The LDF requirement = 290x5 = 1450 units plus 5% buffer=1523 dwellings over five years, there is no undersupply to be added

4.4 It should be noted that, there is no windfall allowance has been made in this assessment for future windfall permissions which will be granted (and many completed) during this five year period and there is no 10% non-implementation rate adopted for small windfall sites. 4.5 This can be broken down as follows:  The LDF requirement for next five years is 1,523 dwellings plus 290 for year 6, (the end of LDF plan period), giving a total requirement of 1,813, this equates to an average 302 per year up to 2026, the end of the LDF plan period.  Total Supply for the plan period is expected to be 3,806 dwellings, with 1,171 dwelling to be delivered after 2026.  This gives 12.6 years supply – that is, 3,806 / 302 equates to a 12.6 years’ worth of potential development over the next six years.  Looking at the five year supply to 2025, this amounts to 3,530 dwellings with a requirement based on 305 per year this is 11.6 years supply.

4.6 Based on the information in Table 2 a trajectory has been produced which shows the delivery expectations for the District to 2026.

1,000 LDF Based - District Wide Housing Trajectory 900 800 700 600 500 400

Dwellings 300 200 100 0

Year Completions LDF Housing Requirement

Graph 1: District Wide Housing Trajectory – LDF Requirement

Revised Housing Supply Scenarios – the Emerging Local Plan

4.7 The revised scenario described below reflects the situation following the publication in 2018 of the new Housing & Economic Development Needs Assessment (HEDNA). The supply situation is based on early March 2020 date. These give a new requirement comprised of:

 Housing need is based around a requirement for 315 dwellings per annum,  A 5% buffer is used, which gives a basic requirement to 331 per year, as completions have been in excess of the annual requirement.  For windfall completions a 10% non-implementation rate for small sites has been adopted.

HEDNA Based Supply - with 5% Buffer - LDF Allocated Sites, Windfall Permissions and New Local Plan Sites as at early March 2020 Annual Supply * HEDNA New based Year Local Plan Supply Difference Windfalls LDF requirement Draft Total ** Allocations with 5 % Allocations buffer

1 2020/21 283 283 5 571 Five Year 2 2021/22 506 209 120 835 Deliverable Supply: 2020- 3 2022/23 309 220 239 768 3,554 1,654 1,900 2025 4 2023/24 96 350 344 790 5 2024/25 22 233 335 590 Post Five Year Developable Supply 0 960 386 1,346 3,150 -1,804 2025-2035 TOTALS 1,216 2,255 1,429 4,900 4,804 96

* This is for 315 per year with 5% buffer = 315x5 = 1,575 plus the extra 5% giving 1,654, followed by a further 315 per year for next ten years of the new local plan to 2035, which equals a further 3,150. ** With 10% non-implementation rate for small sites

HEDNA Based - District Wide Housing Trajectory - 2020 to 2035 900 800 700 600 500 400 300 Dwellings 200 100 0

Year Supply HEDNA Based Housing Requirement 5% buffer

Housing Delivery Test Standard Method HEDNA Based Housing Requirement 10% buffer

Graph 2: HEDNA based District Wide Housing Trajectory to 2035

4.8 Table 3 above shows a surplus of 1,900 dwellings in the next five years to 2025. Post 2025 to 2035 there is a -1,804 unit deficit, according to the HEDNA Requirement.  The HEDNA requirement for next five years is 1,575 dwellings (315 per year) plus a 5% buffer which gives 1,654 dwellings to 2025. For the period 2025 to 2035, the end of new Local Plan , there is a requirement for a further 3,150 dwellings (at 315 dwellings per year). This gives an annual average requirement to 2035 of 320 per year.  Total Supply to 2035 is 4,900 dwellings  This gives 15.3 years supply – this equates to 4,900 / 320 giving 15.3 years of potential development.  Looking at five year supply to 2025, there are expected to be 3,554 dwellings built in the period, with a requirement based on 331 per year this is 10.7 years supply.

ANNEX 1 : Council - Housing Supply Summary as at 12/3/20 Expected Delivery Rates: Years run from April to March Total to be Total Homes Homes Total Total Potential Built by 2025 to be Allocation Site Site Status Built up to U/C - to 2020/21 2021/22 2022/23 2023/24 2024/25 Years Years Capacity Years 1 - 5 Built 5/3/2020 5/3/2020 6 - 10 11 - 15 By 2035 New LocalNew PlanRef.

No Developer BH1 - Masham Road, Bedale 18 0 0 0 0 0 0 0 0 18 0 18

BH2 - Pig Farm, Aiskew & part BH3 - The Linden Homes Hatchery 90 0 0 0 10 20 20 20 70 20 0 90

BH3 - South East of Aiskew Site Complete 100 100 0 0 0 0 0 0 0 0 0 0 BH4 - The Abattoir, Aiskew Site Complete 90 90 0 0 0 0 0 0 0 0 0 0 15/01240/OUT 18/02748/REM Reserved Matters approved at Committee BH5 - Wilberts Farm, Sandhill Lane, Aiskew Oct'19 116 0 0 0 30 30 30 26 116 0 0 116 "The Dales" 15/00006/FUL BH6 - Lyngarth Farm, Bedale Active 79 42 37 25 12 0 0 0 37 0 0 37

Site Complete BH7 - East of Hackforth Road, Little Crakehall 16 16 0 0 0 0 0 0 0 0 0 0

BH8 - Hares of Snape Works, Snape No Developer 20 0 0 0 0 0 10 10 20 0 0 0 BH9 - South of Northallerton Road, Leeming LEB2 No Developer Bar 80 0 0 0 0 6 7 10 23 57 0 57

Pre Application Activity "Call for Sites" submission (B/004/016) BM2 - North East of Aiskew Pig Farm, Aiskew 60 0 0 0 0 0 10 25 35 25 0 25

BM3 - Station Yard, West Tanfield Active - on site 42 4 5 10 10 10 8 0 38 0 0 38 BM4 - Leeming Lane, Leeming Bar Site Complete 82 82 0 0 0 0 0 0 0 0 0 0

EH1 - Ward Trailers, York Road, Easingwold Site Complete by October 2015 44 44 0 0 0 0 0 0 0 0 0 0 EH2 - East of Oxenby Place, Easingwold Site Complete 22 22 0 0 0 0 0 0 0 0 0 0 "The Weald" EH2 - Kellbalk Lane & EH3 - North of Meadow Active Spring Way, Easingwold 115 36 10 30 30 19 0 0 79 0 0 79

EH4 - Garage, Main Street, Shipton No Developer 7 1 0 0 0 0 0 0 0 6 0 6

EH5 - South of Prospect Cottages, Detailed Permission 20 0 0 0 0 10 10 0 20 0 0 0

EH6 - South Back Lane, Stilliington Site Complete 24 24 0 0 0 0 0 0 0 0 0 0

EH7 - Back Lane, Helperby 5 0 0 0 0 0 0 0 0 0 5 5

Site Complete EM1 - Stillington Road/York Road, Easingwold 141 141 0 0 0 0 0 0 0 0 0 0

EM1 - Stillington Road/York Road, Easingwold Outline 80 0 0 0 0 30 30 20 80 0 0 0 NH1 - York Trailers, Yarforth Road, Site Complete Northallerton 241 241 0 0 0 0 0 0 0 0 0 0

NH3 - West of Danes Crest, Brompton Application 19/01499/FUL approved BRO1 Dec'19 21 0 0 11 10 0 0 0 21 0 0 0

10/01716/FUL - Works started Jun'16, NH4 - Bungalow Farm, East Cowton New Application - 19/01779/OUT submitted Sep'19 45 0 0 0 0 10 20 15 45 0 0 45

Complete - Linden Homes NH5 - North of A684, Morton-on-Swale 48 48 0 0 0 0 0 0 0 0 0 0

NM1 - Northallerton Auction Mart 0 0 0 0 0 0 0 0 0 0 0 0

NM2 - Northallerton Auction Market - Car Park 0 0 0 0 0 0 0 0 0 0 0 0

NM5A & D - North Northallerton Area, West of Persimmon Northallerton - Middlesbrough Railway 150 102 20 48 0 0 0 0 48 0 0 48 "Thurstan Park" NM5B - North Northallerton Area, West of Taylor Wimpey Stokesley Road 148 111 35 37 0 0 0 0 37 0 0 37

"Kings Park" NM5D - North Northallerton Area, North Persimmon / Taylor Wimpey Northallerton - East of Darlington Road 472 0 0 30 100 100 100 100 430 42 0 0

NM5B - Residual Area West of Stokesley Planning Application refused Apr'18,allowed on appeal Jun'19 Road, Northallerton 17 0 0 0 7 10 0 0 17 0 0 0

NM5C - North Northallerton Area, East of No Developer 650 0 0 0 0 30 70 70 170 350 130 650 NOR1 Stokesley Road, Northallerton

NM5D - Residual Area East of Darlington Broadacres 72 0 0 0 0 0 20 20 40 32 0 72 Road (Sheepcote Close) SH1 - "Stokesley Grange" White House Farm & Crab Tree Farm, Active - Taylor Wimpey 30 0 0 0 0 30 0 0 30 Stokesley 178 148 31

SH2 - North of Sowerby Crescent, Stokesley STK1 Taylor Wimpey 0 20 40 40 40 140 65 0 205 STK1 205 0 0 "Waters Meet" SH3 - Broughton Grange Farm, Great Site Complete Brougton 26 26 0 0 0 0 0 0 0 0 0 0 "Fry Court" Active SH4 - Cleveland Lodge, Great Ayton 69 57 12 12 0 0 0 0 12 0 0 12

Detailed Permission SH5 - North of Garbutts Lane, Hutton Rudby 25 0 0 0 10 15 0 0 25 0 0 0

TH1 - Cherry Garth Care Home, Thirsk Site Complete 52 52 0 0 0 0 0 0 0 0 0 0

16/00950/FUL - for 25 bungalows - Highway access issues. "Call for Sites" TH2 - Depots, Station Road, Thirsk form submitted for north part of site for 25 dwellings - revised capacity now 50 - this element post five years. 50 0 0 0 0 0 0 0 0 0 50 50

TH3 - Rybeck Farm, Thirsk No Developer 45 0 0 0 0 0 0 0 0 0 45 45

TH5 - Ripon Way, Carton Miniott Site Complete 43 43 0 0 0 0 0 0 0 0 0 0

Site Complete - Phase 1 107 107 0 0 0 0 0 0 0 0 0 0

Site Complete by Sep'17 44 44 0 0 0 0 0 0 0 0 0 0 TM2A - South West Thirsk Area, West of Topcliffe Road, Sowerby Site Complete Dec'18 98 98 0 0 0 0 0 0 0 0 0 0 PHASE 3 - New Taylor-Wimpey / Linden Application for rest of site, 16/02269/REM - 641 units 641 146 66 50 50 50 50 50 250 245 0 495 TM2A - South West Thirsk Area, Westbourne Sowerby Extra Care - SITE COMPLETE - Oct'16 Farm, Sowerby 90 90 0 0 0 0 0 0 0 0 0 0 LDF Allocations Site Totals = 4,788 1,915 216 283 289 380 425 406 1,783 860 230 2,160 All Windfall Permissions up to Mar'2020 = 2,137 876 381 288 547 306 97 23 1,261 0 0 1,261 New Local Plan Draft Allocations 821 0 0 5 70 165 191 124 555 256 0 811 Less 10% Small Site Windfall Non-Implementation Rate 281 515 305 93 21 1,216 10.7 YEARS The supply equates to 1,783 units from LDF allocated sites + 1,216 dwellings from known windfalls (with a 10% loss from small sites) + Draft Allocated Local Plan sites - 555 ; 3,534 UNITS/ 331 PER YEAR as per HEDNA - June 2018 - (315 units per year with 5% buffer) giving a potential 3,534 completions by March 2025. Total Total 2020 / 2021 / 2022/ 2023/ 2024/ 5 Year Total Years Years 2021 2022 2023 2024 2025 Total to be Built 6 - 10 11 - 15 Expected Housing Supply 2020 - 2025 (Allocated Sites, Draft Local Plan Sites & Windfalls) = 569 874 850 709 551 3,554 1,116 230 4,900 P.24 HDC Hambleton Supply ver019e - Final Version - 2019-20 -2020-04-08.xlsx 3,554 4,900

ANNEX 2 - ACTIVITY SUMMARY OF POST 2014 SITES

 Monitoring of housing supply for the emerging Local Plan is undertaken in a spreadsheet all sites with planning permission after 1/4/14 or that were active at that date are included. This gives a total of 743 sites accounting for 7749 dwellings.  The the supply consists of three main sources: o LDF Allocated sites – among these are some draft emerging local plan sites which have been carried over into the new plan plus sites which have been extended where the initial phases are LDF allocations. o Sites which are totally new and are draft allocations in the new Local Plan o Windfall sites – these are grouped into the five sub-areas within Hambleton which are centred around the five principal market towns, which are: . Bedale . Easingwold . Northallerton . Stokesley . Thirsk  Progress of all sites is coloured coded to indicate progress, these categories are defined as:

Colour Site Type Code Explanation Sites with no activity where Expired planning application has lapsed Site with no planning permission but where formal pre-app Pre Application submitted or pre-app consultation undertaken Totally new site for the emerging New Local Plan Sites local plan - all yet to start

Outline Sites with outline permission only

Detailed Planning Sites with full detailed permission Permission

Sites with permission but post application activity undertaken i.e • discharging conditions Post Application Activity • street named & numbered • building regulation application submitted or approved

Active Sites with builders on site

Completed Sites Sites completely built out

25  The progress on each site is presented in the following series of Annexes in the following order : o LDF Allocations (those sites being carried over or extended in the emerging new local plan are indicated) o Totally new draft allocations for the emerging for the new Local Plan o Windfall sites by sub-area.

26 Annex 3 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 LDF Allocated Sites Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Application 19/01511/FUL for 14 units, refused; BH1 19/01511/FUL Extra care units refused Oct'19 - 19/02128/FUL BH1 - Masham Road, Bedale 02/03/2020 19/02128/FUL 18 0 0 0 0 0 0 0 0 018018 Numbers revert to LDF allocation requirement , all post 5 years

Pre application submitted (April'16) for Linden Homes - submitted pre-app - 16/00967/PPP. BH2 BH2 - Pig Farm, Aiskew & part 82 units. 04/03/2020 Aug'19 - contact owner possible outline to be BH3 - The Hatchery 90 0 0 0 0 10 20 20 20 70 20 0 90 New Pre-application submitted; New Pre-app 20/00242/PPP Feb'20 - 90 units

11/02543/FUL - 59 dwellings complete ; 14/01228/FUL - 41 ; 22 completions by Apr'17, total BH3 completions on site 81. BH3 - South East of Aiskew Site Complete 10/07/2017 100 100 0 0 0 0 0 0 0 0 0 0 0 14/01228/FUL FINISH BY APRIL'17 2016/2017 Summary - 38 completions Q1 2017/2018 - Last Three Completions

BH4 BH4 - The Abattoir, Aiskew Site Complete 90 90 0 0 0 0 0 0 0 0 0 0 0 17/09/2015 Site now complete

Reserved Matters submitted Jan'19 now 116 units 15/01240/OUT Street Naming & Numbering submitted Feb'19;Build 18/02748/REM out rate revised Sep'19 BH5 BH5 - Wilberts Farm, Sandhill Reserved Matters 16/10/2019 26 26/02/2020 Committee approval Oct'19 - No change Mar'20 Lane, Aiskew 116 0 0 0 0 30 30 30 116 0 0 116 approved at Committee Oct'19

15/00006/FUL -Decision Issued 21/12/16 Street Naming & Numbered Jan'19 BH6 "The Dales" 15/00006/FUL 05/03/2020 Persimmon undertaking site works - Nov'18 BH6 - Lyngarth Farm, Bedale Active 79 42 37 42 25 12 0 0 0 37 0037 50 starts by Jun'19 By early Mar'20 - 42 completions,37 u/c

Street Named & Numbered - June 2016; BH7 BH7 - East of Hackforth Road, Site Complete 05/09/2018 Little Crakehall 16 16 0 0 0 0 0 0 0 0 0 0 0 Final plot completed Jul'18

Pre-application received BH8 BH8 - Hares of Snape Works, Formal Pre App recieved 5/8/16 for 40x units. New 19/02167/PPP - again for 19/11/2019 Snape 20 0 0 0 0 0 0 10 10 20 000 pre app recieved Oct'19 around 40 units

Application for 16/00224/OUT approved May'16.Call for Sites submission for larger site at rear of Outline - Reserved BH9 BH9 - South of Northallerton allocated (phase 2). Matters submitted - 26/02/2020 LEB2 Road, Leeming Bar 80 0 0 0 0 0 6 7 10 23 57057 Call for Sites - B/004/008/H 19/01085/REM Reserved matters submitted Jun'19 Proposed New Local Plan Site LEB2 - 80 units

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 27 Annex 3 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 LDF Allocated Sites Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

This site follows from BH2 NE Part of Site now "Call for Site" submission Pre Application Activity BM2 BM2 - North East of Aiskew Pig (B/004/016) for 60 dwellings - "Call for Sites" 04/03/2020 Farm, Aiskew 60 0 0 0 0 0 0 10 25 35 25 0 25 Possible Outline to be submitted by owner plus submission (B/004/016) developer interest No change Feb'20

Jun'17 - S106 signed , decision issued Street Named & Numbered - Aug'17 BM3 BM3 - Station Yard, West 17/02311/MRC - Revised Site Layout Active - on site 07/01/2020 Tanfield 42 4 5 4 10 10 10 8 0 38 0 0 38 Active on Site - Private Inspector 7 units being marketed Sep'19 To Feb'20 - 4 completions

Summary 2016/2017 - 50 Completions , 32 under BM4 BM4 - Leeming Lane, Leeming Site Complete 12/11/2017 construction Bar 82 82 0 0 0 0 0 0 0 0 0 0 0 Q2 - Final Completions - 30 in total to end Sep'17

EH1 EH1 - Ward Trailers, York Road, HDC : By October 2015 site complete, last plot 39 Site Complete 29/04/2016 Easingwold 44 44 0 0 0 0 0 0 0 0 0 0 0 completed June 2015

EH2 - East of Oxenby Place, Summary 2016/2017 - 9 completions EH2 Easingwold Site Complete 22 22 0 0 0 0 0 0 0 0 0 0 0 02/10/2017 Last three plots completed 31/8/17 on VOA List dated 24/9/17

14/02285/FUL - Approved 12/11/15; 116 Dwellings "The Weald" in total EH3 EH2 - Kellbalk Lane & EH3 - Active Street Named & Numbered Mar'18 24/02/2020 North of Meadow Spring Way, 115 36 10 33 30 30 19 0 0 79 0 0 79 HDC Amended build out rate May'18 Easingwold 2018/2019 Completions - 3 built 2019/2020 Completions - 35 built Planning permission for 1 dwelling under 12/00322/FUL - granted June 2014 , Street Named & Numbered as Birchwood - Nov'17 EH4 EH4 - Garage, Main Street, Partly 09/03/2020 completed Feb'19 Shipton Active 7 1 0 0 0 0 0 0 0 0 6 0 6 Site now part of a larger 100 dwelling scheme (100 units) under Call for Sites - ALT/E131/018 No Change - Mar'20

14/02294/OUT - Permission granted 5/10/2015 ; Expires Oct'18 EH5 EH5 - South of Prospect Detailed Permission 18/11/2019 Reserved Matters application approved Apr'19 Cottages, Husthwaite 20 0 0 0 0 0 10 10 0 20 000 Contact with agent - viability issues - Nov'19,HDC slipped start by year.

Summary 2016/2017 - 21 Completions last three units remaining EH6 EH6 - South Back Lane, Site Complete 12/11/2017 Last plot (21 , 3 Thompsons Garth) now not Stilliington 24 24 0 0 0 0 0 0 0 0 0 0 0 showhome & complete on 29/9/17 - Source : Gazetteer Team

Site EH7 - East side - Problem with Highway access Pre Application Activity No progress by March 2019 - Post five year EH7 EH7 - Back Lane, Helperby Sep'19 - possible Outline 17/09/2019 5 0 0 0 0 0 0 0 0 0 0 5 5 completions application to follow Contact owner Sep'19 - possible outline application

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 28 Annex 3 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 LDF Allocated Sites Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

EM1 EM1 - Stillington Road/York Site Complete 11/01661/FUL - Redrow Homes - 93 All Built ; 06/09/2019 Road, Easingwold 141 141 0 0 0 0 0 0 0 0 0 0 0 Q1 - 2017/2018 Last Completion on 15/00175/REM

Jomast Development allowed on appeal 80 units Jun'17 EM1 EM1 - Stillington Road/York Outline 13/06/2017 27/02/2020 Call for Sites - E/041/032/M Road, Easingwold 80 0 0 0 0 0 30 30 20 80 0 0 0 Site being Marketed - Seeking to discharge conditions but no start to 2021 - Agent

59 Completions during 2016/2017, 101 to go. NH1 NH1 - York Trailers, Yarforth 2017/2018 Total Completions 55 Site Complete 19/11/2019 Road, Northallerton 241 241 0 3 0 0 0 0 0 0 0 0 0 2018/2019 - 39 completions Last 3 units built Apr'19

Dec'18 - Continuing pre - application discussions NH3 - West of Danes Crest, Application with Karban Homes- looks like 100% affordable. NH3 Brompton 19/01499/FUL approved 09/01/2020 Pre application consultation Jun'19, BRO1 21 0 0 0 11 10 0 0 0 21 000 Dec'19 19/01499/FUL approved for 21 affordable units Dec'19

10/01716/FUL - Works Siite works started so permission active. started Jun'16, NH4 NH4 - Bungalow Farm, East Survey 3/2/17 - demolition activity confirmed New Application - 18/11/2019 Cowton 45 0 0 0 0 0 10 20 15 45 0 0 45 Nov'18 - site being marketed 19/01779/OUT New application 19/01779/OUT - for 70 units submitted Sep'19

15/00741/FUL - 48 in total ; By Jan'17 - 35 units u/c Survey 2/2/17 - confirmed lots of activity but no NH5 NH5 - North of A684, Morton-on- Complete - Linden 04/10/2018 completions Swale Homes 48 48 0 0 0 0 0 0 0 0 0 0 0 March 2017 saw 1 completion. By Mar'18 - Just 6 units left, completed Sep'18

Owner indicated possible relocation of auction mart NM1 NM1 - Northallerton Auction ; both this site and the car park (NM2) could come Exclude from supply 17/05/2019 Mart 0 0 0 0 0 0 0 0 0 0 0 0 0 forward. Exclude from supply at present - No Change Mar'19

Contacted the owner - site could come forward; NM2 NM2 - Northallerton Auction Exclude from supply 17/05/2019 Dwelling numbers could increase. Market - Car Park 0 0 0 0 0 0 0 0 0 0 0 0 0 Exclude from supply at present - No Change Mar'19

Decision issued 5/12/16. Amended rates Nov'18 to 40 per year; Dec'18 now "Kings Park" 50 units per year NM5D NM5D - North Northallerton Active- Persimmon 24/02/2020 Survey Apr'18 - at least 15 starts Area, North Northallerton - East * 150 102 20 46 48 0 0 0 0 48 0048 by Sep'18 - 21 completions of Darlington Road by Dec'18 - 45 completions by Feb'20 - 102 Completions;

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 29 Annex 3 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 LDF Allocated Sites Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

By Jan'19 - 45 completed , 43 u/c "Thurstan Park" NM5B Nov'18 - build out rates revised to 50 per year NM5B - North Northallerton Active Taylor Wimpey 11/03/2020 148 111 35 55 37 0 0 0 0 37 0037 Total 2018/2019 completions 56 Area, West of Stokesley Road Total so far 2019/2020 - 55 Completions - Mar'20

This is a small residual part of the original allocation which is not part of the North Northallerton Planning Application NM5B NM5B - Residual Area West of permission. refused Apr'18,allowed 27/02/2020 Stokesley Road, Northallerton 17 0 0 0 0 7 10 0 0 17000 Application refused Apr'18 , allowed on appeal, on appeal Jun'19 Jun'19, Advert erected Jan'20 No BI record Jan'20 Church Commissioners : New Local Plan Site proposed allocation - NOR1 Pre application activity NM5C - North Northallerton Total capacity = 165 Existing site NM5C + 485 for NM5C/ Draft Allocation Area, East of Stokesley Road, 02/03/2020 extended site. Public Consultation event Sep'19 ; Pre Screening Request - 650 0 0 0 0 0 30 70 70 170 350 130 650 NOR1 Northallerton Planning Inquiry Jul'19, screening request Feb'20 20/00299/SCR

Application 18/02720/FUL - Resolution to approve Mar'19, phase 1; 72 units NM5D - Residual Area East of NM5D 18/02720/FUL Street Naming & Numbering application received Darlington Road (Sheepcote 09/09/2019 committee resolution to 72 0 0 0 0 0 0 20 20 40 32 0 72 Mar'19 Close) approve Demolition Notice for farm buildings - 19/00019/DEM - Mar'19

Dec'18 - Future build out rates amended upward to Awaiting S106 for both 100 per year (50 per builder) NM5A & D - North Northallerton phase 2 applications NM5D & NM5A Numbers on site 226 Taylor Wimpey; 246 for Area, West of Northallerton - Resolution to approve at 02/03/2020 472 0 0 0 30 100 100 100 100 430 42 0 42 Persimmon; a 130 unit reduction Middlesbrough Railway planning committee Total on site 472 Feb'20

Summary 2016/2017 - 17 completions with 33 under constructions SH1 - "Stokesley Grange" 2017/2018 - 27 Completions SH1 White House Farm & Crab Tree Active - Taylor Wimpey 178 148 31 48 30 0 0 0 0 30 0 0 30 24/02/2020 SHLAA 2018 update will complete by 2020. Farm, Stokesley 2018/2019 - 58 completions 2019/2020 to Feb'20- 46 completions

Pre-app May'18. SH2 SH2 - North of Sowerby Public consultation being held Spring 2018 Committee resolution to STK1 Crescent, Stokesley 18/11/2019 Outline application submitted Feb'19 - still awaiting approve 205 0 0 0 0 20 40 40 40 140 65 0 205 STK1 decsion Nov'19 New Local Plan allocation STK1 - 205 in total

Application 17/00941/FUL received Apr'17 - for 26 dwellings "Waters Meet" To start 9/4/18 - CIL Commencement Notice SH3 SH3 - Broughton Grange Farm, Site Complete 04/12/2019 Street Naming & Numbered recieved Apr'18 Survey Apr'19 Great Brougton 26 26 0 24 0 0 0 0 0 0 0 0 0 1st completion Jan'19 - 6 plots have been sold Last Plot Completed Nov'19 - Plot 1

Application - 17/01180/FUL - decision issued Sep'18 - 57 apartments & 12 bungalows "Fry Court" SH4 CIL Commencement Notice Oct'18 SH4 - Cleveland Lodge, Great Active 27/02/2020 69 57 12 57 12 0 0 0 0 12 0012 Tolent Construction on site - Dec'18 Ayton Street Naming & Numbering Jul'19 CT bringing in 57 flats - 13/3/20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 30 Annex 3 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 LDF Allocated Sites Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Application submitted for part of this site - 25 only 16/01836/FUL approved Oct'17 SH5 SH5 - North of Garbutts Lane, Detailed Permission 03/10/2017 27/02/2020 Site Works Started - Mar'18 Hutton Rudby 25 0 0 0 0 10 15 0 0 25 000 Builders Notice Board appeared Aug'19 No BI Record Feb'20

TH1 TH1 - Cherry Garth Care Home, SHLAA 2015 - Phase2 now complete, site finished in Site Complete 19/04/2016 Thirsk 52 52 0 0 0 0 0 0 0 0 0 0 0 June 2016

Planning Application (Southern half of site - Call for sites submitted. North 16/00950/FUL - 25 Part - site of Power Plastics 2018 expansion TH2 - Depots, Station Road, TH2 bungalows - Blue Oak 11/12/2019 approved May'18 - therefore northern part not Thirsk 50 0 0 0 0 0 0 0 0 0 05050 Homes (Yorkshire) Ltd - coming forward refused Oct'17 HIGHWAY ACCESS ISSUES moved to post 5yr period

Call for Sites Form submitted - allocated site part of TH3 much larger scheme. Allocated Site (now Site 2 ) to TH3 - Rybeck Farm, Thirsk Pre application activity 12/03/2020 45 0 0 0 0 0 0 0 0 0 04545 come forward for housing. No change by Mar'20

15/00904/FUL - 3 extra dwellings on site of TH5 allotments, now compound, granted 5/10/15. In all TH5 - Ripon Way, Carton Miniott Site Complete 09/06/2016 Survey Not Required 43 43 0 0 0 0 0 0 0 0 0 0 0 during 2015/2016 there were 40 completions; last 3 plots finished May'16.

2016/2017 Summary - 33 completions with just 24 dwellings to go. TM2A TM2A - South West Thirsk Area, Site Complete 18/12/2017 West of Topcliffe Road, Sowerby 107 107 0 0 0 0 0 0 0 0 0 0 0 At Nov'17 just two dwellings left , Plots 92 & 93, both completed

Taylor Wimpey on site; as at May'16 - 17 units u/c ; Feb'17 - 25 units complete. TM2A TM2A - South West Thirsk Area, 2016/2017 Summary - 34 Completions , 10 Under Site Complete by Sep'17 04/12/2017 West of Topcliffe Road, Sowerby 44 44 0 0 0 0 0 0 0 0 0 0 0 construction Q1 2017/2018 - 8 Completions Last two units completed Q2

2016/2017 Summary - 21 built, 36 under TM2A TM2A - South West Thirsk Area, Complete - Linden construction 04/01/2019 West of Topcliffe Road, Sowerby Homes 98 98 0 0 0 0 0 0 0 0 0 0 0 2017/2018 - 40 completions 2018/2019 - 37 completions Last Plot - Complete Dec'18

Application 16/02269/REM - Joint Linden / Taylor Wimpey scheme. TM2A TM2A - South West Thirsk Area, by Mar'19 - 78 U/C, 60 completions Active 11/03/2020 West of Topcliffe Road, Sowerby 641 146 66 86 50 50 50 50 50 250 245 0 495 by Sep'19 - 58 U/C, 117 completions 146 built by Mar'20 - but soon only 1 developer on site so reduced to 50 per year

Sowerby Extra Care - TM2A TM2A - South West Thirsk Area, Site Complete 0 Nov'16 SITE COMPLETE - Oct'16 Westbourne Farm, Sowerby 90 90 0 0 0 0 0 0 0 0 0 0

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 31 Annex 4 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Bedale Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

"Stable Cottage" - Stud Farm, Low Street, 27/02/2017 13/01687/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 Little Fencote 0 BI Plans approved, Start July 2015 BI completion Feb'17

New application submitted, will deliver in five year 15/00167/FUL 29 Northallerton Road Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 26/04/2016 period. HDC confirmed start 03/06/2015; complete Dec'15

Renewal of Permission - Dec'16 ; 12/00826/FUL & Land to the Rear of Street Farm Expired 0 0 0 0 0 0 0 0 0 0 0 0 18/12/2019 16/02320/FUL 0 No activity , No BI record Sep'19 Expired Dec'19

Site complete 9/7/2016 - see VOA List 28/8/2016 10/02851/FUL Pear Tree House, Church Street Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 03/05/2017 Known as The Old Byre

11/00372/REM Hurstleigh, well Bank Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 25/09/2015 HDC - Start August 2013,Completed Apr'16

Surveyed 15/2/17 - Under Construction - Roof Trusses being erected; at least 2 units on way 13/02559/FUL & "Pinkney Fields" - Complete 4 4 0 0 0 0 0 0 0 0 0 0 14/05/2018 15/01656/FUL Land adjacent 4-5 Brookside, Hackforth 0 Plots 3 & 4 completed Jan'18 Plot 2 Completed Feb'18 Plot 1 Complete & Site Mar'18

16/01618/FUL - Aprroved Jan'17 for five dwellings 13/02340/FUL BI Start - Plot 5 - Nov'17 Land To The South Of Ash Grove - (The 16/01618/FUL Active 5 0 5 0 2 3 0 0 0 0 0 5 02/03/2020 Bungalow), Hackforth 5 Survey 4/5/18 - Plots 3 & 5 under construction BI Start - Plot 1,2 & 4 - by Apr'19 Mar'20 all five dwellings still u/c

Renewal approved July'17 Street Named & Numbered Sep'18 14/02600/FUL CIL Commencement Notice Nov'18 Fencote Hall, Hergill Lane, Little Fencote Active 1 0 1 0 0 1 0 0 0 1 0 0 1 23/09/2019 17/00786/FUL No change Sep'19 REPLACEMENT ONLY????

Street Named & Numbered - Jan'16; NO CHANGE JAN'17 14/02501/FUL 2A Sussex Street, Bedale Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 20/11/2017 Q1 2017/2018 - 1 completion Q2 2017/2018 Second Plot Completed, 22/10/17 - VOA List 19/11/17

BI Initial Notice acknowledged Mar'16 - 14/02188/FUL Crakehall Methodist Church, The Green, Complete 1 1 0 0 0 0 0 0 0 0 0 0 10/07/2017 Crakehall 0 16/06783/IN, Land sold - Survey 2/2/17 - Not started BI Completion 30/6/17

14/01645/FUL 49 South End, Bedale Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Completed Jan'16

Development complete HDC : no confirmation of completion; plans 14/01615/FUL Post Office, Burneston Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 06/09/2018 submitted Sep'15 - 15/10446/OTH/A ; Survey 15/2/17 - Looks like no progress. No change Sep'18 - Expired

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 32 Annex 4 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Bedale Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

The Old Mill completed Oct'17 from application 09/02518/FUL 14/01531/FUL 14/01531/FUL a revised layout for remaining two Badger Farm, Carthorpe Active 3 1 2 0 1 1 0 0 0 2 0 0 2 26/11/2019 plots New BI application for Plot 3 - 18/18832/INC No change Nov'19

No activity - still a school; 14/01002/FUL Survey 15/2/17 - Looks like no progress school still in The Old School, Burneston Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 06/09/2018 use By April 2018 site expired, no change Sep'18

No Activity - expires Oct'17; Survey 15/2/17 - no 14/01829/MBN Cote House Farm Moor End Lane Burril progress nice looking barn Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 06/09/2018 l North Yorkshire DL8 1TR No evidence of a start - so expired by Dec'17, no change Sep'18

BI Plans Approved Oct'15. Survey 15/2/17 - access difficult but no signs of "The Milking Parlour" 14/01908/MBN activity Saltburn House Farm ,Carthorpe ,North Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 13/02/2020 Yorkshire, DL8 2LF Street Named & Numbered - May'17 New Initial Notice Aug'18 No change Dec'19

SHLAA15_13 - Work to start this year; BI Initial 14/01942/FUL "Garth View" Rookwith Complete 1 1 0 0 0 0 0 0 0 0 0 0 09/06/2017 Grange Rookwith North Yorkshire HG4 4AY 0 Notice Acknowledgement - 16/04190/IN Feb'16 Completed on 9/3/17

Street Named & Numbered Aug'16; Building Plans Approved Mar'16, possible construction activity The Stables 8A Emgate Bedale North 14/01955/FUL Complete 3 3 0 0 0 0 0 0 0 0 0 0 05/03/2018 Yorkshire DL8 1AL 0 2/2/17 Plots 2 & 3 completed Feb'18 Plot 1 completed Jan'18

Full application - 16/01002/FUL - refused & 15/00221/OUT dismissed on appeal 13th December 2016 Land To The North Of Springfield Station 18/02615/OUT Active 20/11/2019 2 0 2 0 2 0 0 0 0 0 0 2 17/01/2020 Road Scruton North Yorkshire 2 New Outline - 18/02615/OUT - approved Feb'19 19/01978/REM Reserved Matters Approved - Nov'19 CT start Jan'20

Street Named & Numbered Nov'18 15/00428/MBN Hook House Farm Planetree Lane Kirkby Plot 1 - Hook House Granary - Oct'18 Active 3 2 1 0 1 0 0 0 0 1 0 0 1 13/02/2020 Fleetham North Yorkshire DL7 0SS Plot 2 - The Byre - completed Nov'18 No change Nov'19; Survey 2020 - no progress Feb'20

Surveyed 2/2/17 - Not Started, BI Plans approved

"The Old Chapel" & June 2016 15/00683/FUL "Church House" Street Named & Numbered - Apr'18 Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 06/09/2018 Aiskew Methodist Church 20 Bedale Road Survey May'18 - construction activity Aiskew North Yorkshire DL8 1DD Church House - Built Mar'18 The Old Chapel - Built Jul'18

Street Named & Numbered; Survey 15/2/17 - 15/00847/MBN Sceptre Cottage Station Road Crakehall Complete 1 1 0 0 0 0 0 0 0 0 0 0 11/06/2018 North Yorkshire DL8 1TX 0 builders on site VOA Completion - 10/3/18

The Barn Hamhall Lane Scruton North Exclude from supply used as BI Plans approved - Apr'16 15/01035/MBN 0 0 0 0 0 0 0 0 0 0 0 0 15/03/2019 Yorkshire DL7 0RJ Holiday Accomodation 0

No Activity 15/01232/MBN Mill Bungalow Leeming North Yorkshire Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 06/09/2018 Expires July 2018 No BI activity therefore expired by Sep'18 DL7 9SZ HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 33 Annex 4 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Bedale Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

38 Leases Road Leeming Bar North 15/01469/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 14/01/2019 Yorkshire DL7 9DA 0 No Activity; expired September 2018

BI Plans approved, Oct'15, Query double count "Shire House" & " The Hay Barn" 14/01908/MBN ??? 15/01536/MBN Saltburn House Farm Carthorpe North Active 2 0 2 0 2 0 0 0 0 2 0 0 2 17/03/2020 Street named & Numbered May'17 Yorkshire DL8 2LF Commencement Notice - July'18 No change by Mar'20

Pre-App submitted June 2016 15/01543/OUT Land To The South West Of Prospect House Outline No change Feb'18 16/01501/PPP 1 0 0 0 0 1 0 0 0 0 0 1 11/12/2019 Great Fencote North Yorkshire DL7 0RX Reserved Matters submitted 1 18/01603/REM Reserved Matters validated Aug'18, decision still outstanding Dec'19

Full Application - 17/00731/REM - Approved May'17 - survey 15/2/17 photo for record "Stongarth" 15/01809/OUT Street Named & Numbered - June 2017 Land Opposite Rosedene Carthorpe North Complete 1 1 0 0 0 0 0 0 0 0 0 0 10/09/2018 17/00731/REM 0 Yorkshire CIL commencement Notice - May'17 Survey May'18 - well on way VOA Completion 1/6/18

Building Inspector start 20/1/2016, still no BI "Eight Days Mowing" - 15/01839/MBN Completion Building Adjacent Swale Cottage Burneston Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 06/09/2018 North Yorkshire DL8 2JH Street Named & Numbered Jun'18 Note Council Tax completion Jun'18

Farm Buildings Lumley Lane (North Of 15/01855/MBN New MBN submiitted May'19 - 19/01141/MBN - Melton Court) Kirkby Fleetham North Planning Permission 26/07/2019 1 0 0 0 0 1 0 0 0 0 0 1 09/03/2020 19/01141/MBN 1 Yorkshire Prior approval not Required expires Jul 2024

Survey : Land sold , full application approved 15/02116/OUT "Tilia House" 17/00696/FUL Oct'17 17/00696/FUL Cedar Garth Meadow Lane Snape North Post Application Activity 1 0 0 0 1 0 0 0 0 1 0 0 1 27/11/2019 Street Named & Numbered Mar'18 Yorkshire DL8 2TJ Building Inspectors Initial Notice - Mar'18 No reported change Nov'19

Full Permission - June'16 ; BI Initial Notice - 16/16787/IN 15/02189/OUT & Land East Of The Anchorage Lowfield Lane Expired 0 0 0 0 0 0 0 0 0 0 0 0 27/08/2019 16/00684/FUL Snape North Yorkshire 0 No CIL start by Mar'19 CT visited 16/8/19 - no sign of start , no new permission therefore expired

14/02378/FUL & "Silver Tree House " - Manor House HDC - Started Dec'15;complete Jun'16; Survey 15/02237/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 15/02/2017 Burneston North Yorkshire DL8 2HT 15/2/17 - photo took

Survey 15/2/17 - look largely complete - site safety 15/00124/MBN & Rear Of Rosedene Carthorpe North notices at site entrance but if any activity it looks 15/02240/MBN Site Complete by Sep'17 3 3 0 0 0 0 0 0 0 0 0 0 0 04/12/2017 Yorkshire DL8 2LH like finishing off. VOA Completion for Rosecroft (Plot 1) 17/1/17

17/01383/FUL, approved Sep'17, adds another two 17/01383/FUL plots to this scheme Land East Of Mustard Field House Church 15/02497/OUT Planning Application 3 0 0 0 0 1 2 0 0 0 0 3 17/03/2020 Wynd Burneston North Yorkshire 3 Survey April 2019 - no start Survey 2019 No BI record, Mar'20; expires Sep'20

15/02819/FUL & The Old Forge Exelby North Yorkshire DL8 Revised application 16/01787/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 31/07/2017 16/01787/FUL 2HD Aschilebi House - VOA completion 13/6/2017

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 34 Annex 4 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Bedale Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

16/00227/FUL Old Brew House Little Crakehall North 25/01/2017 C/U holiday accomodation to residential; VOA Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Yorkshire DL8 1JG a Completion 31/10/2016

No Activity, no BI plans etc expires May 2019 15/01668/FUL Village Farm The Green Crakehall North Expired 0 0 0 0 0 0 0 0 0 0 0 0 09/09/2019 Yorkshire DL8 1HP 0 Not Surveyed Expired May'19

Tanfield Mill Hydro Tanfield Mill West 15/02270/FUL Complete 3 3 0 0 0 0 0 0 0 0 0 0 01/02/2017 Tanfield North Yorkshire HG4 5LE 0 SITE VISIT - all three complete

Full permission granted Sep'16; Building regs application submitted;BI Plans Approved - 06/2/17; "Broomstick Cottage " Land Adjacent 15/02581/OUT & Street Named & Numbered 06/2/17 - Survey Fencote House Hergill Lane Little Fencote Complete 1 1 0 0 0 0 0 0 0 0 0 0 06/02/2018 16/01769/REM 0 North Yorkshire DL7 0RR 15/2/17 - No activity BI Commencement 18/4/2017 CT Completion Jan'18

Full application submitted Feb'17; 16/00219/OUT "Pooh Corner" CIL Commencement Notice - 8/6/17 & Land Adjacent To Village Hall Hackforth Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 04/03/2019 17/00292/REM North Yorkshire DL8 1PE Survey 4/5/18 - well underway - to roof CT Completion Jan'19 Street Named & Numbered as Mangold Garth; Building Inspectors Initial Notice Dec'16 - 16/00222/FUL "Mangold Garth" - Ash Brae Langthorne 16/30835/IN 18/00553/FUL Complete 1 1 0 1 0 0 0 0 0 0 0 0 31/01/2020 North Yorkshire DL8 1PQ 0 Note revised application - 18/00553/FUL - approved Jun'18 Non-material amendment approved Jul'19 CT Completion Dec'19

"Manor Garth " Building Regs Initial Notice 16/01308/FUL Land To The South Of Southfields Silver Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 31/07/2018 Survey 4/5/18 - largely complete Street Hackforth North Yorkshire Gazetteer Completion - Jul'18

1x replacement &1 new,permitted Sep'16 16/00887/FUL Rosedene Carthorpe North Yorkshire DL8 Revised application approved Jan'18 17/02086/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/09/2018 2LH Survey May 2018 - well on way VOA Completion 31/7/18

Outline granted Dec'16; Reserved Matters 22/7/17 16/02010/OUT "Amberleigh House" Street Named & Numbered - Sep'17 17/01222/REM Field House Farm Exelby Close Exelby Active 09/08/2018 1 0 1 0 1 0 0 0 0 0 0 1 16/01/2020 18/01247/REM 1 Revised application approved - Aug'18 - now a four North Yorkshire CT Survey Sep'19 bedroom dwelling CT report Utilities electric work, BI start Jan'20

Discharging conditions - Oct'17 Land To West Of Bedale Road Bedale Road Building Inspector Initial Notice - Oct'17 16/01444/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 11/02/2019 Well North Yorkshire CT Completion Dec'18

15/01055/OUT & Oak Dene Burneston Hargill Burneston Surveyed 15/2/17 - Started; 15/02804/REM Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 06/02/2018 North Yorkshire DL8 2JE Council Tax Completion Jan'18

Parr Cottage Snape North Yorkshire DL8 16/01472/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 27/02/2017 2TJ 0 Holiday Cottage to residential - complete

New Permission from Feb'17 Street Named & Numbered Nov'18 Plot 1 - The Old Barn - nearly complete Apr'19,CT 16/02242/FUL Goldswang Farm The Green Kirklington Complete 3 3 0 3 0 0 0 0 0 0 0 0 23/09/2019 18/00206/FUL North Yorkshire DL8 2ND 0 completion Jul'19 Plot 2 - The Old Brewery - CT completion,Jul'19 Plot 3 - Swan Barn - CT completion Aug'19

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 35 Annex 4 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Bedale Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15 Detailed Application - 18/01547/FUL -approved Dec'18;Detailed Application - 18/01546/FUL - 16/02514/OUT approved Dec'18 Land West Of Exelby Grange Exelby North 18/01547/FUL Post Application Activity 3 0 0 0 0 3 0 0 0 0 0 3 17/03/2020 Yorkshire Dec'18 3 Plot 1 - 18/01546/FUL - Street Named & Numbered - 18/01546/FUL Yanagh House No reported progress Mar'20

16/02750/FUL Rosedene Carthorpe DL8 2LH Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 11/12/2017 New Permission from Mar'17; Dec'17 Completion

New Permission from Mar'17 Land To The East Of Willow Proposed Call for Sites - ALT/B/004/025 16/02714/FUL Planning Permission 5 0 0 0 0 2 3 0 0 5 0 0 5 17/03/2020 Gardens Leeming Bar North Yorkshire No BI record Mar'20

Street Named & Numbered Aug'18 17/00403/FUL 18/00846/FUL - amended scheme refused & allowed 17/01614/FUL 5 Northallerton Road Leeming Bar North on appeal - still 5 flats, 18/00059/MRC Active 6 1 5 0 2 3 0 0 0 0 0 5 17/03/2020 Yorkshire DL7 9AA 5 18/00946/FUL Plot 1 started Jan'19 18/24698/OTH - BI No - 4 starts plots 2,3,4,5 - still u/c Mar'20

Oaklands 59B Leeming Lane Leeming Bar 16/02011/FUL Planning Permission -1 0 0 0 0 0 -1 0 0 0 0 -1 12/06/2017 North Yorkshire DL7 9RR -1 Missed - House to C2

Business Unit to Dwelling Adjacent application 17/00012/JPN office to 17/00013/PPN The Barns Gatenby North Yorkshire DL7 Active 2 0 1 0 0 1 1 0 0 0 0 2 17/03/2020 17/00012/JPN 9NG 2 dwelling allowed on appeal May'18 BI start for 17/00012/JPN Aug'19 No reported change Mar'20

Missed - Added June 2017; Street Named & "The Old Dairy" Numbered - June 2017 15/02057/FUL 11A Lumley Lane Kirkby Fleetham North Post Application Activity 1 0 0 0 0 1 0 0 0 1 0 0 1 17/03/2020 Yorkshire DL7 0SH New Initial Notice - 19/14591/IN - Aug'19 No reported change Mar'20

2 Aiskew Crossing Bedale Road Aiskew Expires 15/9/19 - no new permission , no building 16/01470/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 25/09/2019 North Yorkshire DL8 1DZ inspector record therefore expired by 25/9/19

"May-Zac" New Permission-Jun'17 16/02527/OUT Adj The Old Byre Street Named & Numbered Feb'18 17/01994/REM Church Street Complete 1 1 0 1 0 0 0 0 0 0 0 0 27/08/2019 18/00996/REM Well 0 18/00996/REM - Revised Reserved Matters DL8 2QA approved Jul'18 , expires Jun'22 CT completion Jul'19

New Permitted Development - Aug'17 Revised application 18/00174/MBN approved 17/01316/MBN Plump House Thirn North Yorkshire DL8 Mar'18 18/00174/MBN Post Application Activity 1 0 0 0 1 0 0 0 0 0 0 1 25/11/2019 1TL 1 (19/00416/FUL) Application 19/00416/FUl for new access road to serve development approved Apr'19 Street Named & Numbered Sep'19

New IPGN Site - Permitted Oct'17 17/01552/OUT Reserved Matters approved - 18/00585/REM - July Land Adjacent Northfield Bedale Road Well 18/00585/REM Post Application Activity 2 0 0 0 1 1 0 0 0 0 0 2 17/03/2020 North Yorkshire 2 2018 CT Survey May'19 BI Initial Notice - Nov'18 No reported progress Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 36 Annex 4 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Bedale Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

New IPGN Site - Permitted Oct'17 "Longwool" Building Inspector Initial Notice - Apr'18 17/01276/FUL Land Adjacent To Cumbrae Flask Lane Active 1 0 1 0 1 0 0 0 0 1 0 0 1 26/11/2019 Street Named & numbered May'19 Nosterfield Revised BI record with a Aug'19 start date - still u/c Nov'19

Snape Castle Dovecote / Snape Castle New IPGN Site - Missed PARS confirmed occupation 16/00491/MRC Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 12/12/2017 Mews Snape North Yorkshire DL8 2TJ Aug'17 - occupancy restriction removed

Retrospective application for the sub division of a Le Maison Sussex Street Bedale North 17/01834/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 21/05/2018 Yorkshire DL8 2AJ 0 dwelling to create a separate residential flat - therefore complete

New IPGN Permssion - Dec'17 Revised application approved Jan'19 - 18/02379/FUL 17/02175/FUL Land Adjacent To Elm House Hackforth now a 3 bedroom dwelling Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 01/02/2020 18/02379/FUL North Yorkshire DL8 1PA New BI Initial Notice - 19/09026/IN - May'19 Street Nmamed & Numbered - Sep'19 CT Completion - Feb'20

New Permission - Jan'18 Call for Sites submission - B/004/018 17/02422/OUT Land Adjacent To Peace Haven 93 Bedale Outline 17/01/2018 3 0 0 0 0 0 3 0 0 0 0 3 27/11/2019 18/02545/MRC Road Aiskew 3 18/02545/MRC | Variation of conditions 8 & 11 attached to planning permission 17/02422/OUT No full application by Nov'19

Permission Granted May'17 Building Regulation Application approved - May "The Granary" 2017 16/02411/FUL Old Hall Farm - Store At The Square Church Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 21/03/2019 Wynd Burneston North Yorkshire Part of Call for Sites "site" - B/021/003 Gazetteer Completion Mar'19

Subdivison of existing dwelling net gain 1 17/02249/FUL Old Hall Farm Burneston North Yorkshire New Permission - Jan'18 Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 25/09/2019 SURVEY 2019 DL8 2HX CIL Commencement Notice Nov'17 New electrical installation completed

The Old Forge,Exelby Outline 19/01/2018 3 0 0 0 0 0 3 0 0 0 0 3 17/03/2020 17/02334/OUT DL8 2HD 3 No full application by Mar'20

Street Named & Numbered - Mar'18 There appears to be a BI record for 1 dwelling this is "Dyson Croft & Crosby Garth" complete Oct'18 18/00027/FUL Land And Buildings To The North Of The Complete 2 2 0 1 0 0 0 0 0 0 0 0 0 31/07/2019 Rowans Exelby North Yorkshire Survey 2019 - 2nd plot well on way - 16/4/19 Plot 2 complete Jul'19

Conversion of former hall to form single almshouse 14/00999/FUL Almshouses Burneston North Yorkshire Detailed Permission 26/04/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 17/03/2020 No BI record at Mar'20 DL8 2HY

18/00105/FUL Oak Dene Burneston Hargill Burneston Post Application Activity 1 0 0 0 0 1 0 0 0 0 0 1 12/12/2019 Survey 2019 North Yorkshire DL8 2JE 1 New BI Initial Notice - 19/19117/IN - Nov'19

Ivy Cottage Cowling Road Burrill North 17/02319/FUL Yorkshire DL8 1RQ Detailed Permission 04/05/2018 1 0 0 0 0 1 0 0 0 0 0 1 17/03/2020 CT Survey Oct'19 1 No BI Record as at Mar'20

Reserved Matters approved Mar'19 "1 to 5 The Paddock" Discharging conditions Jul'19 Land To The East Of Fiji Villa Carthorpe Post Application Activity 07/06/2018 5 0 0 0 0 2 3 0 0 5 0 0 5 03/12/2019 BI Initial Notices Nov'19 18/00087/OUT North Yorkshire DL8 2LH 19/00132/REM Street Named & Numbered Nov'19

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 37 Annex 4 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Bedale Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

CIL Self Build Certificate 18/00767/FUL Firtrees Hackforth Road Little Crakehall BI Number - 19/04415/IN - Decision Date - 4/3/19 Active 08/06/2018 1 0 1 0 0 1 0 0 0 1 0 0 1 26/11/2019 North Yorkshire DL8 1HY CIl Commencement Notice 26/2/19 Street Named & Numbered Jul'19

Detailed application - 19/00988/FUL - Approved "Field House" 18/00352/OUT Jul'19 Land To The North Of Sheilings North Road Post Application Activity 29/07/2019 1 0 0 0 0 1 0 0 0 0 0 1 25/11/2019 19/00988/FUL 1 Hackforth North Yorkshire DL8 1NR Street Named & Numbered Aug'19 BI Initial Notice - Oct'19

Glebe Farm Low Street Kirkby Fleetham 18/00370/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 23/01/2019 North Yorkshire DL7 0SP 0 CT confirmed completion Jan'19

New Agricultural conversion "Granary Barn" & CIL commencement notice Apr'19 18/01164/MBN The Grange Flask Lane Nosterfield North Active 1 0 1 0 0 1 0 0 0 0 0 1 18/12/2019 19/01437/MBN 1 revised scheme under 19/01437/MBN Yorkshire DL8 2QU Street Named Numbered Aug'19 New Initial Notice Oct'19

Land Adjacent 91 Bedale Road Aiskew 18/00760/OUT Outline 10/08/2018 2 0 0 0 0 2 0 0 0 0 0 2 17/03/2020 North Yorkshire 2 New Outline - No full application by Mar'20

17/00744/OUT Land Between Rose Cottage And The Green New Outline - Expires 9/8/2021 Detailed Permission 16/12/2019 1 0 0 0 0 1 0 0 0 0 0 1 18/12/2019 Scruton North Yorkshire 1

Outline application with some matters reserved

"Mary Orchard Farm" The Myer (access included) for the construction of one 18/01545/OUT Burneston,North Yorkshire dwelling Post Application Activity 17/05/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 18/12/2019 19/00293/REM DL8 2HP Reserved Matters submitted 7/2/19, approved May'19;Street Named & Numbered Jun'19 New BI Plans submitted Oct'19

"Nightingale Cottage" Construction of a dwelling in rear garden 17/00087/FUL The Old Farmhouse 58 Bedale Road Aiskew Post Application Activity 1 0 0 0 0 1 0 0 0 1 0 0 1 17/03/2020 Street Named & Numbered Oct'18 North Yorkshire DL8 1DD No Bi record Mar'20

Outline planning (all matters reserved) for the construction of one detached dwelling 18/00964/OUT Field House Carthorpe North Yorkshire Detailed Permission 09/09/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 17/03/2020 19/01215/REM DL8 2LF Reserved Matters - 19/01215/REM - approved Sep'19 Bi Plans submitted on 17/3/20!

Demolition of commercial offices and warehouse 18/01575/FUL Whitegates Burneston North Yorkshire DL8 and construction of 2 no. dwellings Active 2 0 2 0 0 2 0 0 0 2 0 0 2 18/12/2019 2HX Bi Initial Notice - 19/15010/IN - Aug'19 CIL commencement Notice - Apr'19

10/01307/FUL Killerby Hall Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 09/09/2019 Expired - no building inspector record

11/02358/FUL "Keepers Cottage" - Hunter Hill, Hackforth Complete 1 1 0 0 0 0 0 0 0 0 0 0 Road, Little Crakehall 0 November 2018 completion

11/02620/REM Land Adjacent To Hall Cottage Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Site Complete Sep'15

12/00062/FUL The Horsefold, Well Bank Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Oct'15 Completion

12/01846/FUL Low Rookwith Farm Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Sep'15 Completion

13/01946/FUL Blacksmiths Cottage & East Cottage , Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Post 2015 Completion

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 38 Annex 4 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Bedale Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

14/00103/FUL Land To The Rear Of Rose View Ings Lane Complete 1 1 0 0 0 0 0 0 0 0 0 0 Snape North Yorkshire DL8 2TF 0 Post 2015 Completion

14/00370/FUL Scolars Court - Bedale Centre Benkhill Complete 14 14 0 0 0 0 0 0 0 0 0 0 Drive Bedale North Yorkshire DL8 2EA 0 Post 2015 Completion, six completions pre 2015

14/00751/FUL St Edmunds The Green Crakehall North Complete 1 1 0 0 0 0 0 0 0 0 0 0 Yorkshire DL8 1HP 0 Dec'14 Completion

14/00828/FUL 13 Forge Lane, Kirkby Fleetham Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Post 2015 Completion

14/01423/FUL Browns Buildings Tanfield Mill West Complete 1 1 0 0 0 0 0 0 0 0 0 0 Tanfield North Yorkshire HG4 5LF 0 Post 2015 Completion

14/02063/FUL The Manor House Snape North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 DL8 2TA 0 Post 2015 Completion

15/00639/MRC Courtyard Cottages 34 Bedale Road Aiskew Complete 1 1 0 0 0 0 0 0 0 0 0 0 North Yorkshire DL8 1BN 0 Post 2015 Completion

15/00864/FUL New Jersery Wool Shop 38 Market Place Complete 1 1 0 0 0 0 0 0 0 0 0 0 Bedale North Yorkshire DL8 1EQ 0 Post 2015 Completion

Common Room And Stores Tom Hall Court 15/00906/FUL Bedale North Yorkshire DL8 2DT Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Post 2015 Completion

12/00332/FUL Lowthorns, 59A Leeming Lane Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x completion Oct'14

12/00432/FUL G Dawkins And Son, 36 Emgate Complete 6 6 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'14 completion

12/02337/FUL Land Adjacent To Lowfield, Back Lane Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Nov'14 Completion

12/02457/FUL Building Adjacent To Beckside Lodge, The Complete 1 1 0 0 0 0 0 0 0 0 0 0 Bridge, Aiskew Bank 0 Jul'14 Completion

13/00457/FUL Street Farm Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Jun'14 completion

13/00670/FUL The Lodge Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Apr'14 completion

08/02434/FUL Street House Farm Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Jun'14 completion

09/01429/FUL 16 Low Street Complete 9 9 0 0 0 0 0 0 0 0 0 0 0 1x Completion post April 2014

Outline permitted Feb'19 18/02120/OUT Land Adjacent Green Dragon Inn Exelby Detailed Permission 16/12/2019 5 0 0 0 0 2 3 0 0 0 0 5 17/03/2020 19/02234/REM North Yorkshire 5 Reserved Matters approved Dec'19 No BI record Mar'20

West of Bancroft 9 Firby Road Bedale New Permission Feb'19 18/00016/FUL Detailed Permission 15/02/2019 2 0 0 0 0 2 0 0 0 2 0 0 2 17/03/2020 North Yorkshire DL8 2AT No BI record at Mar'20

New Permission Dec'17 17/01639/FUL The Coach House North End Bedale North Survey April 2019 - still nursery (19/01641/MRC) Complete 1 1 0 1 0 0 0 0 0 0 0 0 17/12/2019 Yorkshire DL8 1XA 0 Survey 2019 Modification of condition - Oct'19 CT Completion Dec'19

Land Between 11 And 17 Leeming Lane New Outline June'19 19/00281/OUT Outline 09/05/2019 2 0 0 0 0 0 2 0 0 2 0 0 2 12/12/2019 Leeming Bar North Yorkshire No detailed application submitted by Dec'19 Alterations and change of use of former first & second floor office space to provide 3 residential 18/02746/FUL First Floor 23 Market Place Bedale North Detailed Permission 17/04/2019 3 0 0 0 0 3 0 0 0 0 0 3 12/12/2019 CT Survey Sep'19 Yorkshire DL8 1ED 3 apartments No BI record at Dec'19

"The Millstones" 11/02154/FUL Complete 1 1 0 1 0 0 0 0 0 0 0 0 10/07/2019 Mount Pleasant Farm, Back Lane 0 VOA Completion May'19 - readded to schedule HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 39 Annex 4 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Bedale Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Construction of five dwellings and associated 19/00113/FUL Danby Cottage Nosterfield North Yorkshire Active 23/08/2019 5 0 5 0 2 3 0 0 0 0 0 5 28/01/2020 CT Survey Oct'19 DL8 2QP 5 garages All plots started Jan'20

Pear Tree House Church Street Well North 19/00131/FUL Complete 19/03/2019 1 1 0 1 0 0 0 0 0 0 0 0 03/10/2019 Yorkshire DL8 2QA 0 CT notifcation to VOA - completed Oct'19

New Permission Sep'19 19/01310/FUL Land Between Walnut House & Holmlea Post Application Activity 06/09/2019 2 0 0 0 0 1 1 0 0 0 0 2 12/12/2019 CT Survey Oct'19 Bedale Road Well North Yorkshire 2 CT access off B6267 created New BI Initial Notice - 19/23589/IN - Dec'19

Brookside Leyburn Road Crakehall North 19/02138/FUL Detailed Permission 19/12/2019 1 0 0 0 0 1 0 0 0 0 0 1 08/01/2020 Yorkshire DL8 1HR 1 sub-division of existing dwelling ; 1 net gain

Corner House Hotel 2 Leases Road Leeming Change of use of pub and hotel, including associated 19/01839/FUL Detailed Permission 07/01/2020 5 0 0 0 2 3 0 0 0 5 0 0 5 22/01/2020 Bar North Yorkshire DL7 9AN alterations, to 5no. flats

Arbutus House Cowling Road Burrill North Construction of a detached dormer bungalow & 19/00993/FUL Detailed Permission 10/01/2020 1 0 0 0 1 0 0 0 0 1 0 0 1 22/01/2020 Yorkshire garage Bedale SubArea Totals 196 106 30 11 20 50 20 0 0 90 0 0 90

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 40 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Full application approved Apr'16; 59 Uppleby, Easingwold / Building Regs Application approved 18/07489/IN - 13/00876/OUT & Bay Tree House 16/00332/REM Back Lane Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 17/12/2018 Apr'18; Easingwold Street Named & Numbered CT Completion - Dec'18

Street Named & Numbered - March '17; Approved 13/01570/FUL Amco House, Market Place, Easingwold Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/07/2017 BLPU 12/4/17

Development yet to commence 13/01203/OUT & "1 - 4 Shepherds Mews" 20/03/2017 All Four plots under construction from April/May 15/02543/FUL Rear of Shepherds Garth, 149 Long Street, Complete 4 4 0 0 0 0 0 0 0 0 0 0 0 Easingwold a 2016 - 16/07344/DOM BI Completion : All Built 17/3/17

189a Long Road - Built out plus SHLAA 2015 : Agent confirmed 1 dwelling built but 06/01549/FIUL 187 Long Street 07/03256/FUL Active 2 2 0 0 0 0 0 0 0 0 0 0 0 19/11/2019 HDC note that 2x conversions outstanding ; No change Nov'19 - looks like conversions unlikely to be built Forge Cottage' and 'Bakers Cottage' complete. Difficult to establish whether the remaining 3 07/03485/FUL G F Baker Ltd, Market Place Active 2 2 0 0 0 0 0 0 0 0 0 0 0 17/03/2020 dwellings are complete No Change Mar'20 excluded from 5 yr supply

10/01856/OUT & HDC - Reserved Matter application - 12/00804/REM Longfield Farm, North Moor Road Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/12/2018 12/00804/REM also start made 1/4/2014 VOA Completion Nov'18

Hutchinsons DIY and Stationary, Chapel 14/00854/FUL Street Complete 8 8 0 0 0 0 0 0 0 0 0 0 0 26/04/2016 Site Complete by Feb'16 24/7/15 12/01472/OUT & Land Adjacent to Diera Lodge, Back Lane 14/01295/REM Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 See 1x dwelling completed by Oct'15 the other Mar'16 SHLAA15_14

Work started see photo May'18

12/02590/FUL & New applications submitted Feb'19 - 15/02488/FUL 19/00407/FUL& 19/00408/FUL - approved Apr'19 Avenue Farm, Church Avenue Detailed Permission 17/04/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 17/03/2020 19/00407/FUL above identical applications except one with garage 19/00408/FUL / one with office No BI record Mar'20

Street Named & Numbered "St John - The Evangelist Cottage" - St 13/00293/FUL Johns Priory, 151B Long Street Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 14/09/2018 Building Inspector Notice accepted Oct'2016 No real evidence of a start - Expired Sep'18

09/00925/FUL Lund House Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 08/02/2017 Site Expired - no new application

SHLAA 2016 - New application 16/00750/FUL approved July'16., 13/00223/FUL & Sunnybank, High Street 16/00750/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 09/09/2019 Survey 3/3/17 - No Start

No new application, No BI record by Sep'19 - expired Development not commenced on site SHLAA2015 : Owned by Builder - did have 2013 start Land to the rear of the Bay Tree, South but now a new one for 16/12/15 - 12/00201/FUL Active 1 0 1 0 0 0 1 0 0 1 0 0 1 17/03/2020 Back Lane,Stillington 15/26971/dombn, no change Jan'17, Survey 3/2/17 - seemed to be limited progress No change Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 41 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Works yet to commence, can deliver within five year Rutland House, 4 the Gowans, Sutton on 20/01/2017 15/00127/REM Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 period; BI Initail Notice Acknowledgement; BI the Forest a Completion 10/1/2017

Site fenced off - Survey 5/5/17 New Application approved April 2018, 13/01394/FUL & 18/00293/FUL, for an extra unit.Street Named & 15/02536/FUL Land Between the Haycorns and Grasmere, 18/00293/FUL Stilliington Road Active 2 0 1 0 1 1 0 0 0 2 0 0 2 17/03/2020 Numbered Aug'18 New Initial notice - 19/06511/IN - Apr'19 - No change Mar'20

14/00799/FUL Permission renewed Mar'18 Badgers Rake, Newton Road Planning Permission 1 0 0 0 0 1 0 0 0 1 0 0 1 18/03/2020 18/00108/FUL No BI record -Mar'20

Land east of Fourways, Raskelf Road, 06/07/2016 SHLAA 2016 - Plot U/C as at 5/6/2016, complete 15/00422/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Easingwold a Nov'16

Reserved matters application received and works "Steerwood" recently commenced on site. HDC Check start - From 14/00046/OUT & Linton Wood Farm, Linton Woods Lane, 14/02416/REM Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 29/08/2017 BI - full electrical installation for new build at this Linton on Ouse location Apr'16 VOA Completion - 1/6/2017

13/01530/FUL Glendale, Sand Hole Lane, Shipton by HDC - 16/00532/MRC approved Feb'16; site Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 03/02/2017 16/00532/MRC Beningbrough complete

27/01/2017 15/00128/FUL Land to rear of 5 The Nurseries, Easingwold Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Completed Sep'16 a

Development started Mar'15 14/02548/FUL A and R Bentley, Tall Oaks Farm, Huby Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 12/02/2019 CT Completion Dec'18

HDC Gained permission 1/4/2015 - not started by 10/02158/FUL Royal Oak House, Long Street, Easingwold Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 14/09/2018 April 2018 therefore expired

McCarthy & Stone scheme Land at Stillington Road, Easingwold 27/01/2017 14/01120/FUL Complete 37 37 0 0 0 0 0 0 0 0 0 0 0 SHLAA2016 also survey : Commenced 27/3/15 , 36 (Mccarthy & Stone) a completed by Jan'17

SHLAA 2015 : Site being marketed & commence by 2017 ; No progress Jan'17 Feb'18 expiry - No new application - therefore 14/02497/FUL 122 Main Street, Stillington Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 10/05/2019 expired Not street named & numbered by Feb'18 No change therefore expired - Mar'19

Started April 2015 14/02345/FUL The Old School, Cherry Tree Avenue, Variation of conditions - 17/02064/MRC Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 27/02/2020 17/02064/MRC Newton on Ouse New Initial Notice - 19/16184/IN - Sep'19 DM confirmed complete by Nov'19

27/01/2017 14/01269/FUL Helperby House, Main Street, Helperby Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Building Inspector start 10/2/2016; finished 30/9/16 a Building Inspector start 22/4/15. 14/00741/FUL But no evidence of start; application 17/00173/FUL 60 Long Street, Easingwold Not Active 0 0 0 0 0 0 0 0 0 0 0 0 0 25/04/2017 17/00173/FUL seeks to revert to commercial use therefore exclude from supply

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 42 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15 HDC - April 2015 Permission. Building Plans Submitted Feb'16, conditionally approved Mar'17 14/00360/FUL No change May 2018 expiry date 1/4/2018 therefore Oak Cottage, Church Hill, Old application Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 14/09/2018 18/01472/FUL expired BUT revised application refused - 18/01472/FUL for new build dwelling

HDC - both started on 4/3/2015, split of existing Cherry Tree House Cherry Tree Avenue 12/01832/FUL Newton On Ouse York YO30 2BN Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 30/05/2018 dwelling therefore 1 net gain Approved BLPU by 31/3/18 therefore complete.

HDC - HM09/02950/OTH - Start on 5/10/2015 . Survey 3/2/17 : Located next to Stillington Fisheries - Crabtree Cottage , The Green , Stillington 13/02006/FUL YO61 1JX Active 1 0 1 0 0 0 0 1 0 1 0 0 1 18/03/2020 activity with scaffolding out front - roofing works Checked Council Tax - no progress, party wall dispute - Mar'20

SHLAA 2015 : Currently out to tender work to start Manor House Farm Carr Lane Sutton On 27/01/2017 14/01789/FUL Complete 5 5 0 0 0 0 0 0 0 0 0 0 0 late summer, ALL PLOTS UNDER CONSTRUCTION BY The Forest North Yorkshire YO61 1EB a NOV'15,all built by 1/12/16 HDC Estimate 17/17214/IN - Electronic Initial Notice Manor Farm Yeoman Course House Lane 14/01905/MBN Oulston North Yorkshire YO61 3RB Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 13/02/2020 Acknowledgement Expired Oct'19

0 0 0 Detailed Planning approval - 17-00519/REM - 27/Oct/17 "Hambleton Chase" 13/01703/OUT & Active on site from Feb'18 Land North of Stillington Road,Easingwold 17/00519/REM Active 175 43 17 42 45 45 42 0 0 132 0 0 132 24/02/2020 now Kier Living Ltd 50 starts by Apr'19, 1 completion By Feb'20- 43 completions

0 0 0 BI records - internal works completed - White Bear Cottage White Bear Farm 27/01/2017 14/01332/FUL South Back Lane Stillington North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 16/06899/NICEIC, April 2016 a Yorkshire YO61 1ND Linked to 17/02730/MRC Nine Acres Stillington Road Easingwold 14/01964/FUL 27/02/2017 5x dwellings complete by Jan'17, survey confirmed North Yorkshire YO61 3DZ Complete 5 5 0 0 0 0 0 0 0 0 0 0 0 a complete 2/2/17

15/00153/FUL & Village Farm Main Street Alne North 27/01/2017 1 under construction at 31/3/16 ; completed Complete 5 5 0 0 0 0 0 0 0 0 0 0 0 15/01176/FUL Yorkshire YO61 1RT a 5/4/2016 - 4x completed by Nov'16

Building Inspector start Dec'17 Rose Bower Garage Thirsk Road 15/00237/FUL Easingwold North Yorkshire YO61 3HN Active 1 0 1 0 0 0 1 0 0 1 0 0 1 19/03/2020 Breeze block now to 1st floor, still u/c Sep'18 Progress stalled for past year - no change Mar'20

15/00513/FUL Under Construction May'16 - Revised application - "The Garden House" - Birdforth House & Main Street Alne North Yorkshire YO61 1RS Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 07/11/2017 16/00858/FUL - Approved Jun'16 16/00858/FUL Complete Nov'17

Strawberry Cottage Gracious Street Huby 27/01/2017 15/00577/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Under Construction Sep'15, built 15/12/16 North Yorkshire YO61 1HR a

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 43 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Milestone Antiques Farnley House 101 No progress by Feb'18 , 15/00692/FUL Long Street Easingwold North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 14/09/2018 YO61 3HY Now on Council Tax from 1/6/18 - c/u completed

Street named & numbered - Gazetteer start May '16 Land Adjacent The Cottages Aldwark North Plot 1 - Melrose House - Completed May'17 15/00694/FUL Complete 3 3 0 0 0 0 0 0 0 0 0 0 0 14/09/2018 Yorkshire Plot 2 - Mulberry Lodge - Completed Nov'17 Plot 3 - High Fields - Completed Jul'18

BI Plans submitted Dec'16 - 16/31242/IN - Electronic Initial Notice Acknowledgement "Sentry Cottage" 15/00791/FUL & Start - foundations underway on air photo Mid'2017 Land South East Of Holmlea Skates Lane 16/00056/MRC Active 1 0 1 0 1 0 0 0 0 1 0 0 1 19/03/2020 Sutton On The Forest North Yorkshire Street Named & Numbered Sep'18,no reported progress Mar'20

Rowntree House Market Place Easingwold The Big Check - Feb'18 - CT Completion (Oct'16) - on 15/00840/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 09/02/2018 North Yorkshire YO61 3AG Map & Gazetteer

Start on 22/12/16 Highthorne Farm Highthorne Lane Described as "Holiday Cottage 2" but no pp for 15/01049/MBN Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 14/09/2018 Husthwaite North Yorkshire YO61 4PL holiday use therefore conversion completed Apr'18

15/01151/FUL Church Farm Myton On Swale North 11/04/2017 NOTE : Started 26/4/2016 Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Yorkshire YO61 2QY a VOA Completion Jan'17 - updated on 11/4/17

Revised application 17/01039/FUL - allowed on "Kwetu" 15/01184/MBN appeal Mar'18 Craven Farm Stillington North Yorkshire 17/01039/FUL Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 29/11/2019 YO61 1NX Street Named & Numbered - May'18 BI Start Oct'18, no change Nov'19. Street Named & Numbered - Sep'17 Plot 1 Completed Sep'17 15/01188/MBN 16/01223/FUL Plot 3 - Completed Jun'17 Springhead Farm Raskelf North Yorkshire 19/00072/MBN YO61 3LL Active 4 2 0 0 1 1 0 0 0 2 0 0 2 19/03/2020 Extra unit added 19/00073/MBN Mar'19 19/00073/MBN Street Named & Numbered May'19 19/01125/FUL No change Mar'20

15/01534/FUL February 2016 permission. Cobble Cottage Main Street Stillington 18/02396/FUL 11/02/2019 North Yorkshire YO61 1JU Detailed Permission 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020 New application - 18/02396/FUL - granted Feb'19 No BI record - Mar'20

144 Long Street Easingwold North 27/01/2017 15/01626/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Started 23/2/2016, complete 01/7/16 Yorkshire YO61 3JA a

Warren Hill High Moor Lane Shipton By BI Initial Notice - 18/12893/IN - Jul'18 15/01703/MBN Post Application Activity 1 0 0 0 1 0 0 0 0 1 0 0 1 19/03/2020 Beningbrough North Yorkshire YO30 1AS No change Mar'20

Not Started; discharging conditions Feb'16; Street Bielby House Raskelf North Yorkshire YO61 15/01785/FUL 3LF Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 08/02/2018 named & Numbered The Big Check Feb'18 - Approved BLPU Built Oct'17

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 44 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15 17/02190/FUL - for 5 dwellings ; Survey 2019 - Site cleared - April 2019 - New Street & 15/02162/MBN "Craven House" Numbering Nov'19 17/02190/FUL The Brick Barn Helperby North Yorkshire Active 4 0 4 0 0 2 2 0 0 4 0 0 4 19/03/2020 MBN not to be proceeded with - still net gain 4 ;CT YO61 2PL start,Sep'19;No reported change - Mar'20

Approved Jan'16 - Survey March 2017 - Site Fenced "1 - 3 Owl Cottages" off. 15/02377/MBN Goose Farm Goose Lane Sutton On The Post Application Activity 3 0 0 0 0 1 2 0 0 3 0 0 3 19/03/2020 Street Named & Numbered Oct'18 Forest North Yorkshire YO61 1ET Initial Notice - 18/21218/IN - Oct'18 No reported change Mar'20

Revised application 16/01226/MBN - Aug'16 "The Dovecote" CIL Commencement Notice 8/8/17 15/02435/MBN & Barn To The Rear Of Auburn Hill Flawith 16/01226/MBN Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/12/2018 BI Record - 17/05455/COND - BI start 8/9/17, North Yorkshire completed 20/9/2018

Black Bull Cottage The Nookin Husthwaite October 2016 permission 15/01474/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 19/11/2019 North Yorkshire YO61 4PY Expired Oct'19

Plot 1 - complete 5/1/18 "Blackwell Court" - Blackwell Ox Huby 15/00182/FUL & Plot 2 - started 10/3/17,complete 22/11/17 Road Sutton On The Forest North Yorkshire 15/01667/FUL Complete 4 4 0 0 0 0 0 0 0 0 0 0 0 06/02/2018 YO61 1DT Plot 3 - started 23/1/17,complete 22/11/17 Plot 4 - complete 5/1/18

Approved August 2016 Builiding Work started see BI Notice - 16/26200/COND - Jan'17 Laurence House Main Street Sutton On The 15/02069/FUL Forest North Yorkshire YO61 1DW Active 3 0 3 0 1 2 0 0 0 3 0 0 3 19/03/2020 Street named & Numbered Oct'19 Material Change - 19/02284/MRC Oct'19" Still u/c Mar'20

BI Start under Notice 16/26200/COND - Jan'17 "The Fold Yard" Street Named & Numbered Sep'18 - dwelling nearly 15/02697/FUL Woods Farm Main Street Sutton On The Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 15/10/2018 Forest North Yorkshire YO61 1DW complete CT Completion 27/9/18

Street Named & Numbered - Apr'16, Survey Apr'19 - No Progress 16/00166/FUL 16/00166/FUL - separate application - barn 18/01748/MRC The Stelling Active 1 0 1 0 0 1 0 0 0 1 0 0 1 19/03/2020 Back Lane Helperby North Yorkshire conversion Part of Call for Sites - E/063/002 CT start, no reported progress Mar'20 BI Number - 19/06720/IN - April 2019 Oct'19 many units nearing completion assume all Land Adjacent To Applegarth Cottages started Apr'19 16/00387/OUT Main Street Linton On Ouse North 18/01517/REM Active 5 1 4 1 2 2 0 0 0 4 0 0 4 19/03/2020 Street Named & Numbered Nov'19 Yorkshire 1st completion Dec'19, no reported change Mar'20

Street Named & Numbered - 28/9/17 "Orchard Barn" Discharging conditions - Nov'17 -16/00393/DCN 16/00393/FUL Pigeoncote Farm Raskelf North Yorkshire Active 1 0 1 0 0 1 0 0 0 1 0 0 1 19/03/2020 YO61 3LG CIL Commencement Notice - Jun'18 No change by Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 45 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15 Ref. No: 17/14576/DOM | Deposited: Thu 06 Jul 2017 | Decided: Fri 11 Aug 2017 | Status: Plans 2A Central Avenue Conditionally Approved 16/00410/FUL R/O 33 Crabmill Lane Easingwold North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 23/11/2018 BI Commencement 23/2/18 Yorkshire YO61 3DF Street Named & Numbered Mar'18 CT completion July 2018 Full Application approved Mar'18 Street Named & Numbered Sep'18 16/00411/OUT Land To Rear Of The Shieling York Road Plot 3 - Kennet House - complete Nov'18 Complete 3 3 0 0 0 0 0 0 0 0 0 0 0 18/03/2019 18/00099/FUL Easingwold North Yorkshire Plot 2 - Winterfell - BI Completion Dec'18 Plot 1 - Lancaster House approved Inspector Final Certifcate - 13/3/19

Convert disused farm buildings into three dwelling houses 16/00688/FUL Mill Farm Crayke Road Brandsby North New application - 18/00709/FUL - for a 4th unit Post Application Activity 4 0 0 0 0 0 0 3 1 4 0 0 4 19/03/2020 18/00709/FUL Yorkshire YO61 4RP approved Dec'18 New Initial Notice Jul'19, No reported progress Mar'20

16/00883/OUT Full application submitted,Dec'16 16/02722/REM Land South Of White Bear Farm South Back 17/02730/MRC Lane Stillington North Yorkshire Complete 6 6 0 0 0 0 0 0 0 0 0 0 0 07/05/2019 Discharging conditions - Nov'17 All six built by Mar'19

Building Inspector start Nov'16; Street Named & "Gable End" - The Old Post Office Main 16/00918/FUL Street Alne North Yorkshire YO61 1TB Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 29/08/2017 Numbered as Gable End 9/1/17 VOA Completion -1/6/17

Change of use of gallery space into single dwelling 16/00933/FUL Lund Gallery The Lund Easingwold North Planning Permission 1 0 1 0 1 0 0 0 0 1 0 0 1 19/03/2020 CT start - 2018; Yorkshire YO61 3PA No reported change Mar'20

Recent Planning Permmission - July'16; Survey 16/01050/FUL 3/2/17 - No Start 19/00545/FUL Church Farm House, Main Street Planning Permission 1 0 0 0 0 0 1 0 0 1 0 0 1 19/03/2020 Permission renewed May'19 No BI record at Mar'20

Street Named & Numbered 31/8/17 Alderside Thirsk Road Easingwold North 16/01241/FUL Yorkshire YO61 3HJ Site Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 06/09/2018 NHBC Start 15/8/17 Site Complete Aug'18

Electronic Initial Notice Acknowledgement - Nov'17 "Hall Garth House" CIL Commencement Notice- Aug'18 16/01396/FUL Land West Of Ings House Main Street Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 04/11/2019 Linton On Ouse North Yorkshire Street Named & Numbered Dec'18 BI Completion Oct'19

Reserved Matters submitted Oct'17,approved May'19 16/01477/OUT 16 Thornlands Easingwold North Yorkshire 24/05/2019 17/01936/REM YO61 3QQ Post Application Activity 2 0 0 0 0 1 1 0 0 2 0 0 2 19/03/2020 Discharging conditions Dec'19 /Jan'20 New BI Initial Notice Jan'20

"Plantation Barn" Street Named & Numbered Feb'18 16/01637/MBN Plantation Farm Sutton On The Forest Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 11/06/2018 BI Inspector start July'17 North Yorkshire YO61 1EG VOA Completion - 1/3/18

Street Named & Numbered Apr'18 "Mulberry House" Building Inspector - Electronic Initial Notice 16/01683/FUL Mayfield Youlton Lane Alne North Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 23/09/2019 Yorkshire YO61 1SB Acknowledgement Sep'17 CT completion Sep'19 HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 46 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Plots 1 & 2 BI Completions - 17/11/17 The Forge North End Raskelf North 16/01796/FUL Yorkshire YO61 3LF Complete 4 4 0 0 0 0 0 0 0 0 0 0 0 06/02/2018 Plot 4 - completed 17/12/17 Plot 3 - completed 2/1/18

Two dwellings - 1x replacement , both started Feb'17 - NHBC The Old Orchard Mitchell Lane Alne North 16/01841/FUL Yorkshire YO61 1RQ Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 06/02/2018 Demolition notice for old bungalow - 17/00026/DEM - 4/4/17 Site complete Jan'18

Wildon Hill Barn North Yorkshire 27/01/2017 16/02212/FUL YO7 2BU Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Restiricted Use removed therefore complete

New Permission from Feb'17 "Matthew Hatton Court" 16/02541/FUL Survey 31/3/17 - Buildings Down & Foundations in Fire Staon Sllington Complete 8 8 0 0 0 0 0 0 0 0 0 0 0 15/01/2018 Road Easingwold North Yorkshire YO61 3DY Dec'17 - Externals largely complete VOA all complete by Dec'17

16/01614/OUT New Permission from Jan'17 Land Adjacent Church House Church 19/01832/REM 20/12/2019 Wind AlneNorth Yorkshire Detailed Permission 2 0 0 0 0 2 0 0 0 2 0 0 2 19/03/2020 Reserved Matters approved Dec'19 No BI record Mar'20 Allowed on Appeal - 9/3/17 CIL Commencement Notice - Mar'18 "Byland" & "Farndale" Plot 1 - Street Named & Numbered - Oct'18 16/01593/FUL Land Between Acacia Lodge And Active 2 0 2 0 1 1 0 0 0 2 0 0 2 19/03/2020 Plot 2 - Street Named & Numbered - Nov'18 Stoneybroke Raskelf Road Easingwold No reported change Mar'20

Brafferton Manor Milking 02/05/2017 New Permission from Mar'17 16/02391/FUL Parlour Boroughbridge Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Road Brafferton North Yorkshire Assumed impliemented Mar'17

Total five dwellings - front part of site E/070/013 made under Call for Sites 16/02064/FUL Plot 1 - Duncan House - Mar'19, CT completion 16/02247/FUL Part OS 8471 And 9170 Gracious 17/01463/MRC Street Huby North Yorkshire YO61 1HR Active 5 1 0 1 2 2 0 0 0 4 0 0 4 19/03/2020 Oct'19 18/01669/FUL No further reported change Mar'20

Discharged conditions Oct'19 Holmfield Newton Road Tollerton North New Initial Notice - 20/02320/IN - Feb'20 16/02733/FUL Post Application Activity 30/03/2017 4 0 0 0 0 2 2 0 0 4 0 0 4 19/03/2020 Yorkshire YO61 1QT No further reported progress Mar'20

Missed - separate permission to 16/02733/FUL Holmfield Newton Road Tollerton North 18/02201/FUL 17/12/2018 Yorkshire YO61 1QT Post Application Activity 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020 New BI Initial Notice - 19/07110/IN - Apr'19 No reported progress Mar'20

New Permission from Mar'17 Reserved Matter application approved Oct'17 17/00005/OUT Street Named & Numbered - 7/11/17 Land To The East Of Flawith & Road Tholthorpe North Yorkshire Complete 3 3 0 0 0 0 0 0 0 0 0 0 0 16/10/2018 Daniel Gath Site - no 10% reduction applied 17/01849/REM CIL Commencement Notice for 27/11/17,BI Starts on all plots Breeze block nearly up to roof level - 25/1/18

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 47 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Reserved Matters 18/02467/REM approved Feb'19 16/01612/OUT R Thompson Joinery Limited South Back 16/09/2016 18/02467/REM Lane Tollerton North Yorkshire YO61 1PU Active 4 0 4 0 0 2 2 0 0 4 0 0 4 19/03/2020 Street Named & Numbered Jul'19 All plots started by Jul'19, no completions by Mar'20

Plot 1 Street Named & Numbered Apr'19 Land To The South Of Bravener Court Plots 2 & 3 - Street Named & Numbered - Jun'19 16/02127/FUL Newton On Ouse 18/00788/MRC North Yorkshire Active 3 2 1 2 1 0 0 0 0 1 0 0 1 19/03/2020 Plot 3 - CT Completion Aug'19 Plot 1 - CT completion Dec'19 No further progress reported Mar'20

New Permission from Apr'17 16/02803/OUT Reserved Matters approved Jan'18 Land To West Of Green Acres The Green 17/02536/REM Raskelf Active 3 3 0 3 0 0 0 0 0 0 0 0 0 23/09/2019 Street Named & Numbered - May'18

All 3 Plots completed Jul'19

New Permission from Apr'17 Survey May'18 - Not started 17/00144/FUL Land To The North Of Fold House Main Variation to Plot 2 approved - 17/01558/MRC - 17/01558/MRC Street Alne North Yorkshire YO61 1TB Post Application Activity 2 0 0 0 0 2 0 0 0 2 0 0 2 19/03/2020 Sep'17 Discharging conditions Dec'19 No BI record Mar'20

East Villa Main Street New Permission from Apr'17 Shipton By Beningbrough New BI initial Notice - Apr'19 - 19/08426/IN 17/00355/FUL Post Application Activity 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020 North Yorkshire Street Named & Numbered Nov'19 YO30 1AB No further progress reported Mar'20

17/02706/MRC - approved Mar'18 Survey 4/5/18 - Not started "Pasture House" - 17/00346/FUL Initial BI Notice - May'18 Land To The Rear Of Spring House Gale 17/02706/MRC Road Alne North Yorkshire Active 1 0 1 0 0 1 0 0 0 1 0 0 1 19/03/2020 Street name & Numbered Mar'19 CIL Commencement Notice Feb'19; No notified change Mar'19

Barn East Of Permitted Development - April'17 Thormanby Hall Farm 17/00195/MBN No BI record or CIL start - Dec'19 Thormanby 19/01199/MBN North Yorkshire Post Application Activity 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020 New Permitted development approved Jul'19 YO61 4NN New Initial Notice submitted Mar'20

The Old Stable Buildings Behind Stable New Permission - Apr'17 15/02421/FUL Cottage Main Street Helperby North Planning Permission 3 0 0 0 0 0 3 0 0 3 0 0 3 09/03/2020 No Bi record Mar'20 - Expires Apr'20 Yorkshire YO61 2PW CT Survey - no start 4/12/19

Hillside Wentworth Avenue Thormanby New Permission - Jul'17, Net Gain of 3 - 5 in total. 16/02262/FUL Planning Permission 3 0 0 0 0 1 2 0 0 3 0 0 3 19/03/2020 North Yorkshire YO61 4NN No BI record Mar'20

Street Named & numbered Apr'19 Follywood House Easingwold Road Huby So net gain of 1 for supply purposes 17/01088/FUL Active 1 0 1 0 1 0 0 0 0 1 0 0 1 19/03/2020 North Yorkshire YO61 1HJ New permission - Aug'17 BI start Nov'18; no notifed change Mar'20

Bailiffs House Myton Grange Myton on 17/00099/XXX Swale Y061 2QU Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 02/10/2017 Sep'17 VOA Completion but no PP

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 48 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

New Permission - July'17 17/01062/OUT Reserved Matters approved Mar'18 18/00157/MRC Land To The North West Of Foxholm House Plot 4 Street Named & Numbered Oct'18 17/02323/REM Flawith North Yorkshire Complete 4 4 0 2 0 0 0 0 0 0 0 0 0 10/07/2019 18/00157/MRC Plots 3 & 4 BI completion Feb'19 Plot 2 - Apr'19 completion Last plot - Spruce House completed Jun'19

New Permission - Sep'17 17/01532/OUT "Cart Shed House & Alder House" Reserved Matters validated Jul'18,approved Feb'19 18/01596/REM Land Off Back Lane Village Farm Main 19/01195/MRC Active 2 0 2 0 0 2 0 0 0 2 0 0 2 25/02/2020 was part of 15/00153/FUL Street Alne North Yorkshire YO61 1RT CIL commencement notice - Jul'19 Street Named & Numbered Feb'20

The Lodge The Hawkhills Estate Easingwold New Permission - Sep'17 16/02453/FUL Planning Permission 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020 North Yorkshire YO61 3EW No BI record as at Mar'20

New Permitted Development - Aug'17 Low Barn Croft Lane Carlton Husthwaite Street named & Numbered 22/9/17 17/01315/MBN Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 07/11/2019 North Yorkshire BI Application submitted - 18/15658/CONS - 7/9/18 BI start Feb'19,CT finish Nov'19

19/00027/DEM - Demolition Notice submitted - April 15/02638/OUT Former Hambleton District Council Depot 2019 17/01427/FUL Stillington Road Easingwold North 17/01688/DPN Post Application Activity 7 0 0 0 2 3 2 0 0 7 0 0 7 19/03/2020 New application - 19/00085/FUL - for 7 dormer Yorkshire YO61 3DY 19/00085/FUL bungalows approved Apr'19 No Building Regs record - Mar'20

New Permitted Development - Nov'17 Thrush House Sutton On The Forest North 17/01976/MBN Yorkshire YO61 1ED Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 05/02/2018 BI Start Oct'17 CT/Gazetteer completion 12/12/17

Andersons Unit 3 The Granary Far Shires Farm New Permitted Development 17/01810/JPN Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 09/12/2019 Forest Lane Complete Dec'19 Alne YO61 3EJ

New Permission - Jan'18 17/01102/OUT Call for Sites - E/141/004 Home Farm Mill Lane Stillington North 19/02540/REM 03/01/2018 Yorkshire YO61 1NG Post Application Activity 5 0 0 0 0 2 3 0 0 5 0 0 5 19/03/2020 Detailed application sumitted for Plot 3 Nov'19 Dropped Kerbs & plots marked out 19/02540/REM - withdrawn Feb'20

BI Start Plot 7 , 28/3/18; Street Named & Numbered Mar'18 17/00585/FUL Land West Of Paddock Close Tollerton By Oct'18 - Plots 3 & 7 complete 18/00550/MRC Complete 8 8 0 0 0 0 0 0 0 0 0 0 0 11/03/2019 Road Huby North Yorkshire Plots 2 & 4 completed Nov'18 Plots 5 & 6 completed Jan'19 ; Plot 1 completed & therefore site complete - 07/03/19 New Permission - Jan'18 Reserved Matters refused Nov'18 17/02409/OUT "Oakview House" New Reserved matters - 19/00388/REM - approved 18/01120/REM Wayside 1 Oulston Road Easingwold North Post Application Activity 1 0 0 0 0 1 0 0 0 1 0 0 1 16/12/2019 May'19 19/00388/REM Yorkshire YO61 3PR Street Named & Numbered - Jun'19 BI Initial Notice - 19/22069/IN - Nov'19

New Permission - Jan'18 IPGN & Call for Sites - ALT/E/122/003 17/02240/OUT Land North East Of The Cottage The Green 15/01/2018 19/00818/REM Raskelf North Yorkshire Active 4 0 4 0 2 2 0 0 0 4 0 0 4 25/02/2020 Details approved Dec'19 - 19/00818/REM CIL Commencement Notice Jan'20 Street Named & Numbered Feb'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 49 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

New Permission - Jan'18 The Garage Low Street Discharging conditions Dec'18 16/01987/OUT Husthwaite Detailed approved - 19/01328/REM - Sep'19 19/01328/REM Post Application Activity 24/09/2019 3 0 0 0 0 1 2 0 0 3 0 0 3 19/03/2020 North Yorkshire Garages demolished Nov'19 YO61 4QA No BI record Mar'20

Land North East Of Dove Cote New Permission - Jan'18 17/02358/OUT The Green Reserved Matters permitted 31/10/18 18/01041/REM Raskelf Post Application Activity 5 0 0 0 2 3 0 0 0 5 0 0 5 20/03/2020 North Yorkshire Survey April 2019 - No start YO61 3LE New BI Notice - 20/00321/DOM - submitted Jan'20

Discharging conditions 2014 Street Named & Numbered - Feb'18 "Gabion House" - Land To The Rear Of 11/01373/FUL Hilltop Cottage & Pinfold Cottage Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 07/01/2019 Variation conditions approved 18/00261/MRC - Apr'18 CT Completion Nov'18

Mulberry House 3 Chapel Court Chapel New Permission - Mar'18 18/00020/FUL Street Easingwold North Yorkshire YO61 Planning Permission 1 0 0 0 0 1 0 0 0 1 0 0 1 20/03/2020 3AE No change Mar'20

Appeal decision - May'18 "Mill View House" Reserved Matters validated Jul'18,approved Sep'18 17/01331/OUT Land at Bye Green, Low Street, 18/01381/REM Active 1 0 1 0 0 1 0 0 0 1 0 0 1 20/03/2020 Street Named & Numbered Sep'18 Husthwaite, North Yorkshire, YO61 4QA BI Start Oct'18 No reported change Mar'20

New Permission - Sep'17, discharging conditions Mar'18 "The Fig House" 17/01539/FUL Glencoe Thrintoft North Yorkshire DL7 0PL Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 16/12/2019 CIL commencement Notice - May'18 Street Named & Numbered Mar'19 Completed Dec'19

Change of Use of barn to self contained separate The Granary Stearsby North Yorkshire two bedroomed dwelling 17/00732/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 02/07/2018 YO61 4SA Allowed on Appeal Assumed Complete from decision date

HDC - a split one dwelling to two ; looks like extra The Croft Newton Road Tollerton North 14/01481/FUL Yorkshire YO61 1QT Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/05/2015 dwelling complete by February 2015 - net gain 1. 2014/2015 net completions +1

18/00053/FUL not implemented, superseded by application 18/02565/FUL - permitted Feb'19 which 18/00053/FUL Windross House Market Place Easingwold was for restaurant to offices Excluded from supply 0 0 0 0 0 0 0 0 0 0 0 0 0 16/12/2019 (18/02565/FUL) North Yorkshire YO61 3AB Confirmed completion of commercial conversion - 19/04361/OTH - on 13/12/19 so excluded from supply

Ashdale Gracious Street Huby North Outline Permission - Not counted in supply 18/00701/OUT Yorkshire YO61 Outline 29/06/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 20/03/2020 No detailed application submitted- Mar'20

Pond Corner 4 The Green Raskelf North Outline Permission - Not counted in supply 18/00060/OUT Yorkshire YO61 3LE Outline 06/04/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 20/03/2020 No detailed application submitted- Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 50 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Reserved Matters - 19/00883/REM - approved 18/00271/OUT Land West Of 6 The Green Hag Lane 05/09/2019 19/00883/REM Raskelf North Yorkshire Active 3 0 1 0 0 3 0 0 0 3 0 0 3 20/03/2020 Sep'19 2 plots started by Jan'20

The Laurels Main Street Outline Permission - Not counted in supply 16/00755/OUT Tollerton 18/10/2019 19/00936/FUL Detailed Permission 2 0 0 0 0 1 1 0 0 2 0 0 2 20/03/2020 Detailed application approved Oct'19 North Yorkshire No BI record by Mar'20 YO61 1QQ

Plot being marketed Dec'18 Material change approved Aug'19 17/02739/FUL The Croft South Back Lane Tollerton North (19/01370/MRC) Yorkshire YO61 1PU Active 1 0 1 0 1 0 0 0 0 1 0 0 1 25/02/2020 CIL Commencement Notice Sep'19 New Initial BI Notice - Oct'19 Street Named & Numbered Feb'20

Prior Notification for change of use of agricultural building to 3 dwellinghouses Forest Farm Tollerton North Yorkshire 17/02551/MBN 29/06/2018 YO61 1RA Active 3 0 1 0 1 2 0 0 0 3 0 0 3 25/02/2020 Discharging conditions - 17/02551/DCN - Oct'19 1st Plot started Feb'20

New Permission Aug'18 - conversion and extension 18/00559/FUL Hollins Grove Farm Easingwold North of remaining barns to form 2 dwellings Post Application Activity 2 0 0 0 0 2 0 0 0 2 0 0 2 20/03/2020 20/00498/LBC Yorkshire YO61 3ES CT land sold late 2019 New Listed Building Consent application - Mar'20

The Annex Change of use from a holiday cottage to a dwelling Highthorne Farm,Highthorne Lane and single storey front extension 18/01273/FUL Husthwaite North Yorkshire Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 18/12/2019 YO61 4PL Electoral Registration Jun'19 - confirmed complete by CT

"Brackenbury Croft" Field House Reserved Matters approved May'19 18/01449/OUT South Back Lane 31/05/2019 19/00502/FUL Stillington Post Application Activity 1 0 0 0 0 1 0 0 0 1 0 0 1 20/03/2020 Street Named & Numbered Aug'19 North Yorkshire No BI Record Mar'20 YO61 1ND

Note Oct'18 permission Street Named & Numbered. 16/02013/OUT Land Off Forge Lane Tollerton North 05/06/2019 19/00229/REM Yorkshire Active 20 1 14 1 0 10 9 0 0 19 0 0 19 19/03/2020 Reserved Matters approved Jun'19 12 starts Aug'19, 2 more starts Feb'20 1st Completion Mar'20

Change of use of doctors surgery to create a pair of 16/02054/FUL Tollerton Surgery 5 - 7 Hambleton View 08/10/2018 Tollerton North Yorkshire YO61 1QW Detailed Permission 2 0 0 0 0 2 0 0 0 2 0 0 2 19/03/2020 semi-detached bungalows No BI record Mar'20

Alterations and extensions to existing detached Annexe At Barn Cottage The Acorns Bell 18/00459/FUL 11/10/2018 Lane Huby North Yorkshire Detailed Permission 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020 dwelling to provide a 4-bedroom dwelling BI activity - Mar'20

The Old Station Yard Demolition of existing storage sheds and 18/00995/FUL Station Road Alne Station Detailed Permission 23/10/2018 5 0 0 0 0 2 3 0 0 5 0 0 5 19/03/2020 construction of five detached homes. North Yorkshire YO61 1TP No BI record Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 51 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Construction of two detached dwellings Discharging conditions - Feb'19 Land Adjacent To Beechcroft Farm OS 18/00209/FUL 22/10/2018 Field 7556 Aldwark North Yorkshire Post Application Activity 2 0 0 0 2 0 0 0 0 2 0 0 2 19/03/2020 BI Initial Notice - 19/05968/IN - accepted Mar'19 Street Named & Numbered May'19 No notified Change Mar'20

Outline planning application for up to 28 dwellings Land to East of Boroughbridge Road, 16/01142/OUT 27/11/2018 Brafferton YO61 2PD Outline 28 0 0 0 0 10 10 8 0 28 0 0 28 19/03/2020 Allowed on appeal Nov'18 No detailed permission submitted up to Mar'20

Outline application (all matters reserved) for the construction of 5no. Dwellings 18/01175/OUT OS Field 4442 Easingwold Road Huby 20/09/2019 19/01358/REM North Yorkshire Active 5 0 5 0 2 3 0 0 0 5 0 0 5 20/01/2020 Reserved matters approved Sep'19 Street Named & Numbered Nov'19 All Plots started Jan'20

Change of use and extension of existing building to Rear Of Thorntons Butchers Off Windross form a three bedroom dwellinghouse 18/02012/FUL Square Market Place Easingwold North Active 14/11/2018 1 0 1 0 1 0 0 0 0 1 0 0 1 10/02/2020 BI Start Nov'18 Yorkshire YO61 3AG No reported progress Feb'20

Construction of 4 bungalows New BI application Apr'19 18/01992/FUL Land South Of Bonny Croft Back Lane 06/12/2018 Raskelf North Yorkshire Active 4 1 3 1 2 1 0 0 0 3 0 0 3 24/02/2020 Street named & Numbered Apr'19 Survey April 2019 - Site Preparations - Drop Kerbs in All plots started by Jul'19; Plot 3 built Feb'20

Outline - residential development of 3 detached dwellings 18/01939/OUT Land To The West Of Scatterpenny The 28/06/2019 19/00687/REM Post Application Activity 3 0 0 0 0 0 1 2 0 3 0 0 3 19/03/2020 Reserved Matters approved Jun'19 Green Raskelf North Yorkshire YO61 3LE Street Named & Numbered Sep'19 3x BI Initial Notices Sep'19

New dwelling ; IPGN site "Calldecott House" BI Initial Notice deposited Sep'18 18/02555/FUL Pear Tree Cottage North End Raskelf North Active 1 0 1 0 0 1 0 0 0 1 0 0 1 19/03/2020 CIL Commencement Notice 10/4/19 - Self Build Unit Yorkshire YO61 3LF Street Named & Numbered - Nov'19 No reported change Mar'20

Framfield House (Outbuildings) Main Retrospective application for conversion of 18/00856/FUL Street Shipton By Beningbrough North Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 06/02/2019 Yorkshire YO30 1AD outbuilding to form two dwellinghouses

Material Change submitted Feb'19 - 19/00389/MRC 18/01929/FUL South Villa York Road Easingwold North Street Named & Numbered Mar'19 Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 26/11/2019 (19/00389/MRC) Yorkshire YO61 3ED BI Application Apr'19 CT completion Nov'19

Green Acres The Green Raskelf North 4x dwellings; Part of Call for Sites - E/122/001 18/02119/OUT Outline 14/01/2019 4 0 0 0 0 2 2 0 0 4 0 0 4 18/12/2019 Yorkshire YO61 3LD No detailed application submitted by Dec'19

13/01986/FUL Former Three Tuns Inn Raskalf Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 2 completions post Apr'15 , 1x before

13/02078/FUL Land to North of Linton Meadow, Linton on Ouse Complete 16 16 0 0 0 0 0 0 0 0 0 0 0 16 post Apr'15 completions Whenby Grange Whenby North Yorkshire 14/00528/FUL YO61 4SE 1 Complete-04-08.xls 1 0 0 0 0 0 0 0 0 0 0 0 1x post Apr'15 completion HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020 x HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 52 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

14/00630/FUL Clayhithe York Road Easingwold North 7 Yorkshire YO61 3ED Complete 7 0 0 0 0 0 0 0 0 0 0 0 All 7 completed post April 2015 14/00824/REM Land opposite and south of Field House,South Back Lane,Stillington Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x post Apr'15 completion Banks Farm 14/01294/MBN Oulston Road 1 Easingwold Complete 1 0 0 0 0 0 0 0 0 0 0 0 1x post Apr'15 completion North Yorkshire 15/01660/FUL The Old Garage Brandsby Street Crayke 1 North Yorkshire YO61 4TB Complete 1 0 0 0 0 0 0 0 0 0 0 0 1x post Apr'15 completion 18/00001/XXX Burtree House , Thormanby Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x CT Completion 09/00491/FUL Prospect Farm, Alne Road Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Jun'14 completion

09/03877/FUL Seconds To Go Main Street Huby North Yorkshire YO61 1HQ - Handley House Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Mar'15 completion 11/02770/FUL Holly House, The Nookin Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Sep'14 completion 12/02366/FUL Providence Pig Unit Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Jan'15 completion 13/01413/FUL St Crespin,York Road ,Easingwold ,YO61 Complete 4 4 0 0 0 0 0 0 0 0 0 0 0 Site complete by Mar'15 3ED 13/02214/FUL Park Close , Easingwold Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Jun'14 completion Cobblestones Main Street Huby YO61 1HQ 14/00615/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Aug'14 completion

Methodist Church Main Street Shipton By New Permission from Feb'19 - 1 net gain 18/02371/OUT Outline 11/02/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020 Beningbrough North Yorkshire YO30 1AA No detailed permission submitted by Mar'20

Land North Of Fold House Main Street Alne New Permission from Mar'19 18/02577/OUT Outline 08/03/2019 3 0 0 0 0 3 0 0 0 3 0 0 3 19/03/2020 North Yorkshire YO61 1TB No detailed application by Mar'20

"Number Five - Back Lane " New Permission from Feb'19 18/01354/FUL The Croft Main Street Alne North Yorkshire Active 15/02/2019 1 0 1 0 0 1 0 0 0 1 0 0 1 19/03/2020 Street Named & Numbered Jun'19 YO61 1RS BI start Jun'19, no change Mar'20

Prior Notification for Change of use of agricultural "The Old Dairy" building to a dwellinghouse 18/00076/MBN Low Shires Farm Alne North Yorkshire Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 16/10/2019 YO61 3PF Street Named & Numbered CT Completion Sep'19

"Birch Field" This missed in 2002 only added to CT in Apr'19 02/00292/FUL Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 14/06/2019 Land Adjacent Chalfonts Alne York Street Named & Numbered Aug'19

CT completion but appeal dismissed under Kirkstone Chapel Street Easingwold North 15/01821/FUL Yorkshire YO61 3AE Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 01/07/2019 15/01821/FUL but CT completions on both flats ; only 1 net gain

New Outline approved Jul'19 19/00973/OUT Rowan Brea Sutton Road Huby North 20/12/2019 19/02003/FUL Yorkshire YO61 1HF Detailed Permission 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020 Detailed application approved Dec'19 No BI record Mar'20

New detailed permission Aug'19 18/00916/FUL Land To The South And East Of Lynne Detailed Permission 15/08/2019 5 0 0 0 0 2 3 0 0 5 0 0 5 19/03/2020 House Carr Lane Sutton On The Forest No BI record Mar'20

Bank Cottage The Nookin Husthwaite New detailed permission Sep'19 19/01139/FUL Detailed Permission 20/09/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020 North Yorkshire YO61 4PY No BI record Mar'20

New detailed permission Oct'19 Daniel Gath Site - no 10% reduction applied Land Adjacent Ash Lea And Bellwood 18/00375/FUL 15/10/2019 Cottage Raskelf Road Easingwold Post Application Activity 11 0 0 0 3 3 3 2 0 11 0 0 11 19/03/2020 Demolition Notice - 19/00110/DEM - Loss of Bellwood Cottage, net gain 11 units - Nov'19 No BI record Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 53 Annex 5 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Easingwold Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Rural Exception Site - Broadacres - No 10% reduction New BI application approved Jan'20 Land South Of Robin Lane Huby North 18/02660/FUL 31/10/2019 Yorkshire Post Application Activity 12 0 0 0 3 3 3 3 0 12 0 0 12 19/03/2020 Discharging conditions Dec'19 Non-material amendment - 20/00500/NMC - Mar'20

Construction of four detached dwellings 18/00929/OUT Land East Of 22 To 28 Ings View South Back 22/10/2019 (19/02738/REM) Lane Tollerton Post Application Activity 4 0 0 0 0 2 2 0 0 4 0 0 4 19/03/2020 CT - Land sold Nov'19 Reserved Matters submitted Dec'19

New permission Nov'19 Land To The North Of Maple Lane Huby 18/02502/FUL 13/11/2019 North Yorkshire Active 7 0 7 0 2 2 3 0 0 7 0 0 7 19/12/2019 Street Named & Numbered Nov'19!!! 5 starts late Nov'19, Plots 6 & 7 start Dec'19

Alterations to existing domestic storage building to form a dwelling Rear Of Westfield Main Street Tollerton BI Initial Notice - 15/08278/IN - Apr'15 13/00803/FUL Post Application Activity 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020 North Yorkshire YO61 1QQ Street Named & Numbered - Sep'19 No repoprted change Mar'20

Missed - Change of use from 6 Letting Rooms to 2 Old Black Bull Inn North End Raskelf North dwellings 17/02676/FUL Complete 09/11/2018 2 2 0 2 0 0 0 0 0 0 0 0 0 19/12/2019 Yorkshire YO61 3LF 1st BI Completion by Jul'19 Site complete Dec'19

Prior Notification for Change of use of agricultural Owlwood House West Lane Stillington 17/00103/MBN North Yorkshire YO61 1LR Active 2 0 2 0 2 0 0 0 0 2 0 0 2 11/12/2019 building to two dwellinghouses BI Start Dec'19

Construction of 2 semi detached dwellings Grey Cottage Main Street Tollerton North 19/02391/FUL 09/01/2020 Yorkshire YO61 1QQ Post Application Activity 2 0 0 0 2 0 0 0 0 2 0 0 2 19/03/2020 Discharging conditions Mar'20 New Intial BI Notice Mar'20 Demolition of a single storey dwelling and construction of 2no detached two storey dwellings Pear Tree Cottage North End Raskelf North 19/01340/FUL 20/09/2019 Demolition Notice Mar'20 Yorkshire YO61 3LF Post Application Activity 1 0 0 0 0 1 0 0 0 1 0 0 1 19/03/2020

Easingwold Sub Area Totals 626 258 89 67 85 157 106 19 1 368 0 0 368

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 54 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

13/00708/FUL HDC : 15/00811/FUL approved June 2015; Land to the rear of Post Discharging conditions April 2016. Started 2/6/16 15/00811/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 02/10/2017 Cottage, The Green Survey : 8/3/17 - well on way Complete July 2017

Started 4/4/14; Variation to drawings 10/02534/FUL Land at Crawford Yard, The (14/01746/MRC) approved Oct'14 - (14/01746/MRC) Active 1 0 1 0 1 0 0 0 0 1 0 0 1 20/03/2020 Survey 14/2/17 - attempted Survey but no direct Green, Brompton access, no sign of activity No reported progress Mar'20

SHLAA 2015 : Agent notes that demolitions and site 12/01338/FUL "Yeoman Court" - The Close, works have commenced as at 24/7/15; 15/02350/LBC 58 Northallerton Road, Active 8 0 8 0 4 4 0 0 0 8 0 0 8 20/03/2020 Street Named & Numbered - Jul'17 Brompton New build at rear - roof works finished,work continuing - Mar'20

Detailed application approved Sept'15; Building 13/00548/OUT Southwood Farm, Danby Exclude from Supply Plans Deposited - May 2016 0 0 0 0 0 0 0 0 0 0 0 0 0 03/10/2017 15/01416/REM Wiske Agriculutral Dwelling BI Plans conditionally approved - Sep'16 No evidence of start expired 30/9/17

13/00588/REM The Oaks, Deighton Lane Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 26/04/2016 Reserved matters - expired on 23/3/2014

Pepper Arden Hall, Pepper 10/02891/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 05/04/2018 Site Expired Arden

10/00455/FUL Application Renewed,not started expired Nov'16; 13/00947/FUL Post Office,East Cowton Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 01/03/2017 Survey 1/3/17 confirmed no start therefore expired

"The Grain Store" 11/00712/FUL Started August 2013 , Honeyclose Farm, Great Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 24/01/2019 Street Named & Numbered , Apr'17 Langton CT completion Jan'19 SHLAA 2015 : Site sold in 2014,start made 13/00535/FUL Red House Farm, Great 07/05/2016, no change Mar'17 Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 14/03/2018 Langton Access poor not surveyed Gazetteer Completion Mar'18

Revised application now new build rather than 11/01797/FUL Bay Horse Inn (Black Bull), conversion - Jul'17 Complete 3 3 0 0 0 0 0 0 0 0 0 0 0 23/03/2018 Plot 1 - Malt Cottage completed Jan'18 16/01840/FUL Great Smeaton Plot 2 - Completed 7/3/18 Plot 3 - Completed 22/3/18

Started 2012 12/00316/FUL The Old Chapel, Kepwick Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 23/09/2019 Complete Jul'19

Site close to completion, internal works to complete Methodist Church, Church HDC - Building Inspector start on 13/7/15 ,still u/c 13/00622/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 25/01/2017 Lane April 2016; SHLAA 2015 site sold, Site Complete Nov'16

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 55 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Scheme revised from 9 units to 7, nothing started SHLAA 2015 : project about to commence; SHLAA Morton Auto-services, 25/01/2017 14/02612/FUL Complete 7 7 0 0 0 0 0 0 0 0 0 0 0 2016 ; all started; no completions to 1/4/16, 2 Morton-on-Swale completions May'16. Site Complete by Sep'16

The County Arms, 219A High Sep'18 - no progress - expired 15/01673/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 14/09/2018 Street No BI record by Sep'18 No access to site available Land to the rear of 231-233 No Confirmed Start - SHLAA 2015 : Agent notes work not commenced,July 13/00927/FUL 0 0 0 0 0 0 0 0 0 0 0 0 0 02/05/2017 High Street, Northallerton Expired 2015.no change Apr'16 Expired Site 12/00254/OUT Land Adjacent 1 Lees Lane, Outline Renewed 1/5/2015; No full application by & Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 07/02/2018 Northallerton Sep'18 therefore expired 15/00548/OUT Jasper House, 13/02076/FUL Boroughbridge Road, Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 07/06/2018 Site Expired Northallerton

13/02475/FUL Land Adj to 66 Ainderby Permission renewed Mar'18 Detailed Permission 1 0 0 0 0 1 0 0 0 1 0 0 1 20/03/2020 17/00315/FUL Road, Northallerton No movement by Mar'20

13/00914/FUL East End House, Morton on Permission renewed - 18/01730/FUL Active 1 0 1 0 0 1 0 0 0 1 0 0 1 20/03/2020 18/01730/FUL Swale Started Jun'19, no reported change Mar'20

141 Ashlands Road, Approved April 2015 12/01502/FUL Active 1 0 1 0 0 1 0 0 0 1 0 0 1 20/03/2020 Survey 14/2/17 - no start , no activity Northallerton BI Start - Jan'18, No reported change Mar'20

Arla Foods, Romanby Road, 15/01073/REM Northallerton Complete 25 25 0 0 0 0 0 0 0 0 0 0 0 04/10/2018 Site complete by Aug'18

14/02291/OUT Park View - Yafforth Hill Outline no development; NOW 15/00538/REM, 09/03/2017 & Farm, Mounstrall Lane, Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 confirmed start 30/7/2015, 15/00538/REM Yafforth Survey : 8/3/17 - Looked Complete

Building Inspector start Dec'16 - 16/23138/DOM. Survey 14/2/17 - site works , portaloo - breeze block 37B Northallerton Road, works to over 6ft; 14/02057/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 21/02/2018 Brompton Street named & Numbered 1/6/17 CT Inspection 20/2/18 - virtually finished cosmetics only

Outline no development - Scout Hut, Malpas Road, HDC - Actively marketed by Robin Jessop now sold 14/02028/OUT Exclude from Supply 0 0 0 0 0 0 0 0 0 0 0 0 0 12/06/2018 to Northallerton Auction mart for car park removed Northallerton from supply Expired April 2018

Golden Lion Hotel 114 High 14/00223/FUL Street Northallerton North Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 07/06/2018 Expired Aug'17 - no activity Yorkshire DL7 8PP

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 56 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Brookfields Farm Hornby 14/01515/MBN Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 07/06/2018 Expired Oct'17 - no activity North Yorkshire TS15 9PU

Manor Home Farm Waver Survey 1/3/17 : Viewed from Deighton Lane looks 14/01530/MBN Lane Deighton North Active 1 0 1 0 0 1 0 0 0 1 0 0 1 20/03/2020 like new structure there Yorkshire DL6 2SJ No reported change Mar'20

"Meadow View" Barn On North End Of, Land And Buildings On The North Survey 8/3/17 - Under Construction; 14/02106/MBN Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 18/12/2017 Street named & Numbered - June 2017 West Side Of Ainderby BI Completion 1/11/17 Steeple North Yorkshire "

Farm Buildings Opposite Deepdale Coage Low Moor Plot started 31/3/2016; still under construction 14/02112/MBN Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 02/03/2020 Lane East Harlsey North CT Completion Nov'16 Yorkshire

Plot 2 - Street Named & Numbered - Jun'18 14/02321/MBN "Arbour House / The Oak Plot 1 - Street Named & Numbered - Aug'18 15/00106/MBN Mill" CIL Commencement Notice 8/10/18 - structures Active 2 1 1 1 1 0 0 0 0 1 0 0 1 24/02/2020 16/00293/FUL Town End Farm East Harlsey already cleared North Yorkshire DL6 2DB 18/22243/IN - Initial Notice for 2 Plot Nov'18 Plot 2 - Arbor House built Dec'19 Rutson Hospital High Street HDC - Loss of one flat during 2015/2016 as site 14/01626/FUL Northallerton North Complete -1 -1 0 0 0 0 0 0 0 0 0 0 0 26/04/2016 redeveloped for retail Yorkshire DL7 8EN Holly Tree House Hailstone Allowed on Appeal. Not Started 14/01866/FUL Moor North Yorkshire DL6 Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 11/12/2018 Bi completion Mar'17 3QS

"Carr House Barns" Not Started; Private BI Inspector - initial notice Carr House Farm Little Street named & Numbered Feb'17 15/00429/MBN Active 2 1 1 0 1 0 0 0 0 1 0 0 1 10/01/2020 Carr House Barns VOA completion 21/6/17 Smeaton North Yorkshire Looks like Plot 2 still outstanding DL6 2HA No change Jan'20

57 South Parade 25/01/2017 2 completions 2015/2016 with remaining three 15/00705/FUL Northallerton North Complete 5 5 0 0 0 0 0 0 0 0 0 0 0 under construction, all completed by Jul'16 Yorkshire DL7 8SL "Old Beretun" Discharging conditions Sep'16 Swalefields Farm Morton May 2018 start 15/00780/MBN Active 1 0 1 0 0 1 0 0 0 1 0 0 1 20/03/2020 On Swale North Yorkshire Street Named & Numbered Jan'19 DL7 9RW Still u/c Mar'20

"Mulberry House" Reserved Matters Approved - 17/0396/REM - Feb'17 15/00869/OUT Oxmoor Barn Thrintoft Survey 8/3/17 - No Start 17/00396/REM Moor Lane Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 10/01/2020 CIL Commencement Certificate : 19/6/2017 Thrintoft North Yorkshire Street Named & Numbered - Oct'17 DL7 0PN Complete Oct'19

"Foxrush" Survey 1/3/17 - not started - photo 15/01032/MBN BI Plans submitted May'17 - 17/11404/IN Brindlewood East Harsley Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 22/01/2019 Street Named & Numbered Oct'18 North Yorkshire DL6 2DB Complete Nov'18

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 57 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Barn And Wheelhouse BI Plans Conditionally approved - Apr'18 15/01067/MBN Thorn Tree Farm Welbury Active 1 0 1 0 0 1 0 0 0 1 0 0 1 10/01/2020 BI start Jul'18 North Yorkshire DL6 2RZ Still u/c Jan'20

15/01090/OUT & Land Adjacent To West Full application approved Apr'17 16/02590/REM House Thrintoft North Post Application Activity 1 0 0 0 0 1 0 0 0 1 0 0 1 09/03/2020 New Reserved Matters submitted Feb'20 (20/00396/REM) Yorkshire DL7 0PL

"Greenview House" Land Adjacent To (the 15/01189/FUL Garden) 9 The Green BI Start 31/10/17 Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 07/01/2019 Street Named & Numbered North CT completion Sep'18 Yorkshire DL7 9QA

Street named & numbered - Gazetteer start Jan'16 15/01259/FUL Ivy Cottage West Rounton Survey 1/3/17 - no direct access but construction Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 04/12/2017 type deliveries (tradesmen) & neighbour confirmed North Yorkshire DL6 2LW u/c Building Inspector completion - Sep'17

15/01639/FUL Revised application for two dwellings - 17/01124/FUL The East House Great 17/01124/FUL - approved Mar'18 19/01830/PPP Smeaton North Yorkshire Post Application Activity 2 0 0 0 0 0 2 0 0 2 0 0 2 20/03/2020 Two pre-planning enquiries Mar'19 19/00668/PPP DL6 2EP No BI record up to Mar'20

Juana Stokesley Road 15/01661/MBN Work started 2/6/2016 Brompton North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 21/05/2018 Council Tax completion May'18 DL6 2TY

"Pennine View" New application for single 4 bedroom dwelling - 15/01838/OUT Land Adjacent Cat And aprroved Nov'17 & Discharging conditions Nov'17 Bagpipes Inn East Harlsey Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 22/02/2019 17/01521/FUL BI Start made - 22/1/18 Northallerton North Street Named & Numbered - Jan'18 Yorkshire CT Completion Nov'18

15/01889/MBN East Farm Little Smeaton Building reg plans approved, Jan '16 Post Application Activity 3 0 0 0 0 3 0 0 0 3 0 0 3 20/03/2020 Replacement Initial Notice - 18/15604/IN - Aug'18 North Yorkshire DL6 2HD No reported progress Mar'20

The Band Room Romanby no full application yet; Survey 14/2/17 - Passing door 15/01897/OUT - good potential site next door redeveloped as 3 Road Northallerton North Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 15/03/2019 storey town houses. Yorkshire DL7 8NG No change Mar'19 therefore expired Discharging Conditions Jan'16, work started May "High Croft House" 2016. 15/02139/FUL Survey 1/3/17 : This well on way roof on internals Bankside Farm East Harlsey Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 13/09/2018 progressing - photo North Yorkshire DL6 2DB Street Named & Numbered May'18 Site complete Jul'18

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 58 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

15/02311/OUT Land Between Bankside 19/00144/OUT - new outline submitted - Jan'19, 19/00144/OUT approved Apr'19 Farm And Hawthorn Cottage Detailed Permission 04/04/2019 2 0 0 0 0 2 0 0 0 2 0 0 2 20/03/2020 19/01745/FUL Detailed application refused 19/01745/FUL - for 2 East Harlsey North Yorkshire dwellings refused , appeal allowed Mar'20

Building Regulations - Plans Approved Feb'16; 15/02400/FUL & Community Health Council started July 2016, 16/01990/NMC approved Sep'16 14/02/2017 (16/01990/NMC) 32 High Street Northallerton Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Survey 14/2/17 - Skip in lane (full) , joiners & North Yorkshire DL7 8EE contractor vans in alley - work in progress, 32 looks domestic

Discharging Conditions - April 2016; Building 15/02407/FUL May Cottage East Harlsey Regulations : Initial Notice submitted; Street Named Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/07/2017 & Numbered - Sep'16; North Yorkshire DL6 2BL U/C from 6/5/2016, Q1 2017/2018 - Site Complete

15/02747/FUL 34 High Street Northallerton Building Regulations - Plans Approved May'16; U/c Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/07/2017 25TH July 2016, works being underatken Feb'17 North Yorkshire DL7 8EE Q1 2017/2018 - 1 built - site complete

Residential Split 1 dwelling to 2; 1 net gain; Street 15/02811/FUL 29 Water End Brompton DL6 15/02/2017 Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Named & Numbered, BI application made Jun'16 but 3HQ rejected, Completed July'16

13 South 25/01/2017 16/00011/JPN Parade Northallerton North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Site Complete - 21/12/16 Yorkshire DL7 8SE

Leake Lane Farm Leake Lane 21/06/2016 92/0986/FUL Nether Silton North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 BI Completion on 20/6/2016 Yorkshire YO7 4BL

Land Adjacent Dabs Bank Building Regs plans approved Oct'16 16/00033/FUL 16/02367/MRC submitted; granted 6/3/18 West Rounton North Active 1 0 1 0 0 1 0 0 0 1 0 0 1 20/03/2020 16/02367/MRC BI Start Jul'18 Yorkshire No further progress reported by Mar'20

16/00398/OUT Shorthorn Inn Hornby Road Reserved Matters Submitted 19/01481/REM - Jul'19 Demolition Notice - 19/00104/DEM - Nov'19 (17/00098/PPP) Appleton Wiske North Post Application Activity 11 0 0 0 0 6 5 0 0 11 0 0 11 20/03/2020 No BI record Mar'20 19/01481/REM Yorkshire DL6 2AL

"Sprocket Cottage" Street named & numbered - 9/1/17, BI plans 16/00528/FUL 14A Normanby Road approved Aug'16 - 16/15353/DOM Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 31/07/2018 BI Start 20/6/17 Northallerton North Survey 2018 - Externals look largely complete Yorkshire DL7 8RW Gazetter Completion July'18

"Poppys View" Full application approved Mar'17 16/00953/OUT Land Adjacent Sunnyside CIL commencement Notice - Sep'17 & Active 1 0 1 0 0 0 1 0 0 1 0 0 1 20/03/2020 Street Named & Numbered Aug'18 Welbury North Yorkshire 17/00014/REM Confirmed BI start Aug'19 DL6 2SE No reported progress Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 59 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

"Keillmore" Full application approved Jul'18 16/00602/OUT Glebe Farm Tofts Lane Street Named & Numbered Aug'18 Active 1 0 1 0 0 1 0 0 0 1 0 0 1 20/03/2020 CIL Commencement Notice Nov'18 18/00161/FUL Welbury North Yorkshire BI confirmed start Nov'18 DL6 2SE No further reported progress Mar'20 Antiques Former Methodist No progress by Mar'19 ; expires May 2019 - No BI 16/00662/FUL Chapel Morton On Swale Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 09/09/2019 record therefore expired - Sep'19 North Yorkshire DL7 9RF

Coach House - The East Permission Sep'16 - no activity yet No CIL commencement Noticeor BI Application - 16/01198/FUL House Great Smeaton North Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 04/11/2019 Dec'18 Yorkshire DL6 2EP No new application - expired Sep'19

Age Concern 33 High Street 16/02038/FUL New Permission Nov'16, Survey : Still an active office Northallerton North Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 02/03/2020 - Jan'20 Yorkshire DL7 8EE Expired

11/02034/FUL Mossa Grange,Danby Wiske 20/01/2017 Missed - allowed on appeal all 3 conversions Complete 3 3 0 0 0 0 0 0 0 0 0 0 0 complteted during 2016/2017

Thrintoft Grange Thrintoft Plot 1 Grange Lodge u/c 13/1/2017, completed 16/01391/FUL Active 4 1 0 0 2 1 0 0 0 3 0 0 3 20/03/2020 Nov'17 North Yorkshire DL7 0PL No reported progress Mar'20

New Permission from Feb'17 16/02681/OUT Hall Farm Hornby North Part of Call for Sites - N/067/001 Post application activity 06/02/2017 3 0 0 0 0 3 0 0 0 3 0 0 3 02/03/2020 20/00246/REM Yorkshire DL6 2JQ Reserved matters submitted - 20/00246/REM - 6/2/20 Land And Buildings On The West Side Of Brompton New Permission from Jan'17 16/02322/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 27/03/2018 Street Named & Numbered March'17 Road Northallerton North Gazetteer Completion - Mar'18 Yorkshire

14/02539/MBN "The Byres" Application 17/01347/FUL replaces 17/00744/FUL 17/00544/FUL Barn To The North East Of 17/01347/FUL Oxmoor Barn Thrintoft Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 19/12/2019 An IPGN Site 17/02624/MRC Moor Lane Thrintoft North 17/02624/MRC - approved Mar'18 Yorkshire CT Completion Oct'19

Land To The North East Of New Permission from Mar'17 16/02233/OUT East Harlsey Telephone Reserved Matters validated Aug'18,approved Oct'18 18/01690/REM Post application activity 1 0 0 0 0 1 0 0 0 1 0 0 1 20/03/2020 BI plans approved Nov'19 Exchange East Harlsey No further progress by Mar'20

The Village Store , Morton- Came through Street Naming & Numbering 17/00999/MISC Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 06/02/2018 on-Swale CT completions - Jan'18

16/00556/FUL Further application for 6 dwellings - 18/02278/FUL - Ship Service Station, Low submitted, approved April 2019 18/02278/FUL Active 6 0 6 0 0 2 2 2 0 6 0 0 6 20/03/2020 Worsall, Yarm TS15 9PH Looks like demolition proceeding Sep'19 Survey 2020 Survey 2020 - conversion well on way Mar'20

Call for Sites - N/008/003 Land And Buildings At 16/01700/OUT New Full Application approved Jul'18 - Village Farm Front Street Post Application Activity 13/07/2018 5 0 0 0 0 2 3 0 0 5 0 0 5 20/03/2020 18/00181/REM 18/00181/REM Appleton Wiske New Initial Notice submitted Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 60 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15 17/01800/REM - refused, allowed on Appeal "The Meadow" May'18;Street Named & Numbered Oct'18 16/01885/OUT Land Adjacent To Field View BI Start Nov'18 ; Apr'19 - well on way to 2nd 17/00920/REM Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 29/11/2019 storey,Jun'19 roof on House Hornby North 17/01800/REM Site Complete Oct'19 Yorkshire DL6 2JQ

Tunstall Barn School House Missed - added when Street Named & Numbered - June 2017 16/02071/MBN Farm West Rounton North Active 1 0 1 0 1 0 0 0 0 1 0 0 1 02/03/2020 Building Inspector Start - Dec'17 Yorkshire DL6 2LT No reported progess Feb'20

"Valentine House" - Colwell Reserved Matters approved - Nov'17 16/02254/OUT House Welbury North Street Named - Mar'18 Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 03/06/2019 Building Inspector Initial Notice - Apr'18 17/01993/REM Yorkshire DL6 2SG CIL Commencement Apr'18 April 2019 Completion

16/02124/OUT New Permission - 23/6/17 Land South Of Cricket 18/00755/REM BI Plans approved for Plot 2 - Mar'19 Ground Hornby Road Great Active 5 0 1 0 0 2 3 0 0 5 0 0 5 23/03/2020 Survey 2019 - Site started, foundations in - June 18/02607/REM Smeaton 2019;BI record for Plots 1 & 2 Survey 2019 Street Named & Numbered Oct'19

Land South Of Manor Close And Call For Sites 2015: N/098/002 16/02674/FUL Oct'19 - CT Survey - Initial ground works East Of Village Road Active 5 0 3 0 0 2 3 0 0 5 0 0 5 23/03/2020 Survey 2020 BI Initial Notice - 19/24696/IN - Dec'19 Low Worsall At least 3 under construction Mar'20

17/00811/OUT Peppergarth East Cowton New Permission - 23/6/17 Detailed Permission 23/06/2017 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 19/02577/FUL North Yorkshire DL7 0DF Full application approved 19/02577/FUL - 17/3/20

16/02735/OUT 2 net gain Little Hornby Farm Hornby 19/01919/FUL Demolition Notice - 18/00013/DEM - Demolition of Road Appleton Wiske North Post Application Activity 2 0 0 0 0 0 2 0 0 2 0 0 2 23/03/2020 Structures at 19/00689/FUL Yorkshire DL6 2AF Three detailed applications approved for all plots 19/01611/REM No further reported progress - Mar'20

Outline New permission - 17/00308/OUT - approved Little Hornby Farm Hornby 18/8/17 17/00308/OUT Reserved Matters - 19/00051/REM - approved Road Appleton Wiske North Active 2 0 1 0 0 2 0 0 0 2 0 0 2 23/03/2020 19/00051/REM Mar'19 Yorkshire DL6 2AF Plot 1 BI start Apr'19, still u/c Mar'20 Plot 2 Street named & Numbered Oct'19

New Permission - 9/6/17 Land To The North Of 25 17/00505/FUL BI Application - 18/22361/DOM - submitted - The Peppergarth Romanby Active 1 0 1 0 1 0 0 0 0 1 0 0 1 23/03/2020 Nov'18, conditionally approved Jan'19. CT Survey 2020 North Yorkshire Street Named & Numbered Jan'19 BI start Sep'19, up to roof line by Jan'20

Gate House 49 - 51 High New Permission - 19/07/2017 17/01142/FUL Survey work started, BI Start Mar'18 Street Northallerton North Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 12/09/2018 SURVEY 2018 By May 2018 work nearing completion Yorkshire DL7 8EG Note : June 2018 Completions

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 61 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Buildings At OS Field 4268 Danby Wiske North 14/01230/MBN Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 27/11/2017 Nov'17 - Gazetteer completion Yorkshire - Opposite Old Police House

D Oakley Limited 68 Reserved Matters approved - 18/02646/REM - 17/01059/OUT Romanby Road Feb'19 18/02646/REM Active 7 0 0 0 0 3 4 0 0 7 0 0 7 23/03/2020 Demolition notice -19/00032/DEM for structures - Northallerton North SURVEY 2019 Apr'19 Yorkshire DL7 8NQ Survey 2020 - well on roofs on Mar'20

Survey June 2018 : Construction well underway, to 1st floor level. Land To The East Of 15 Lead 17/00611/FUL Aug'19 - Plot 1 - Arncliffe House complete , Lane Brompton North Active 3 1 2 1 0 2 0 0 0 2 0 0 2 23/03/2020 Survey 2020 other 2 dwellings not started - Mar'20 Yorkshire

17/01624/FUL New Permission Nov'17 Land And Buildings To The Discharging IPGN Site Rear Of Swaledale Court Discharging Conditions - Nov'17 conditions - Active 1 0 1 0 1 0 0 0 0 1 0 0 1 23/03/2020 Morton On Swale North BI Start - Feb'18 Nov'17 Yorkshire Street Named & Numbered Mar'18 17/01624/DCN No notiified change by Mar'20

18/02134/REM - reserved matters application 17/01808/OUT validated Oct'18, approved Feb'19 OS Field 0051 Hornby North Survey 2019 - Site started , foundations in - June 18/02134/REM Active 22/02/2019 1 0 1 0 0 1 0 0 0 1 0 0 1 23/03/2020 Yorkshire 2019 Survey 2019 Street Named & Numbered Aug'19 No reported progress Mar'20 Barn At Street House Farm Deighton Lane 17/01555/MBN Brompton Was permitted development but new revised Planning Permission 13/02/2018 2 0 0 0 2 0 0 0 0 2 0 0 2 23/03/2020 application 17/01498/FUL - Feb'18 17/01498/FUL North Yorkshire No notified progress , no BI record Mar'20 DL6 2SP

Revised application approved Jul'19 for 8 units - Land East Of Ashlands 19/00087/FUL 17/01549/FUL House Bullamoor Road July 2019 - site access under way Active 01/07/2019 8 3 6 3 3 2 0 0 0 5 0 0 5 23/03/2020 Street named & Numbered Oct'19 19/00087/FUL Northallerton North Aug'19 - 8 BI starts, Three plots built by Mar'20 Yorkshire

Chilton House Low Worsall New Outline Permission - Jan'18 17/01514/OUT Outline 16/01/2018 3 0 0 0 0 3 0 0 0 3 0 0 3 23/03/2020 North Yorkshire TS15 9PJ No Detailed Application submitted up to Mar'20

Fieldhead Sandy Bank New Outline Permission - Feb'18 17/00810/OUT Northallerton North Outline 27/02/2018 2 0 0 0 0 2 0 0 0 2 0 0 2 23/03/2020 IPGN Site Yorkshire DL6 1AW No Detailed Application submitted up to Mar'20

White House Farm New Outline Permission - Mar'18 17/02720/OUT Bungalow West Rounton Outline 01/03/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 No Detailed Application submitted up to Mar'20 North Yorkshire DL6 2LW

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 62 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

New Permission - Apr'18 Street Named & Numbered - Apr'18 18/00211/FUL Rokeby House Mill Hill Lane Site clearance May'18 Complete 2 2 0 2 0 0 0 0 0 0 0 0 0 11/09/2019 SURVEY 2018 Northallerton DL6 1AP Both plots started by Jul'18 Plot 1 Completed Apr'19 Plot 2 Complete Sep'19 New care home with 26 extra care apartments - approved Apr'18 17/00584/FUL Land South Of Marston's 18/02050/MRC - increased no. of apartments to 31 18/02050/MRC Willow Beck Public House Active 31 0 31 0 15 16 0 0 0 31 0 0 31 23/03/2020 Foundations in, with steel work - Sep'19;Roofs going Survey 2020 Finkills Way on Mar'20

Demolition of Structures - 19/00002/DEM - Jan'19;BI Old Hall Farm Hornby Road 18/00096/FUL Start Plot 1 - April 2019 Appleton Wiske North Active 2 0 1 0 1 1 0 0 0 2 0 0 2 23/03/2020 Material Change submitted 19/02373/MRC - Nov'19 (19/02373/MRC) Yorkshire DL6 2AF Street Naming & Numbering Jan'20 No further progress Mar'20

BI Initial Notice submitted - 18/23635/IN "Dragonstone" Street Named & Numbered May'19 18/00414/FUL Land At Raby Lane East Plan Policy estimated start Jan'19 Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 24/02/2020 Survey 2019 Cowton CT - Apr'19 - up to roof line CT - Oct'19 roof on Plot complete Feb'20

Church View Nurseries Green Hills Lane Ainderby Not included as Annexe but CT identifed as self- 16/00741/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 11/04/2019 contained therefore added , nearly complete Aug'18 Steeple North Yorkshire DL7 BI Completion - 18/3/19 9JX

Land Adjacent To The BI start on all plots Nov'18 17/01095/FUL Golden Lion Ainderby Road Complete 06/04/2018 4 4 0 4 0 0 0 0 0 0 0 0 0 11/07/2019 Street named & Numbered Jan'19 Romanby All four dwellings complete Jun'19

Rose Villa East Harlsey New Outline - Expires 13/9/2021 18/01362/OUT Outline 13/09/2018 5 0 0 0 0 5 0 0 0 5 0 0 5 23/03/2020 North Yorkshire DL6 2DB No detailed application submitted by Mar'20

Crow Tree Farm Yafforth CIL Commencement Notice Jan'19 16/02168/FUL Road Romanby North Active 2 0 2 0 0 2 0 0 0 2 0 0 2 23/03/2020 CT Survey - well on way Oct'19 Yorkshire DL7 0PE No reported progress Mar'20

Land North And East Of New Permission Jul'18 18/00925/OUT Outline 30/07/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 Chapelgarth,Hornby No Detailed Application submitted up to Mar'20 North Yorkshire

The Treadmills East Road The Treadmills scheme - permitted Dec'18 18/01849/FUL Northallerton North Detailed Permission 04/12/2018 4 0 0 0 0 4 0 0 0 4 0 0 4 23/03/2020 No 10% reduction applied Yorkshire DL6 1NP Scheme started progress continuing - Mar'20 Construction of 5no. detached dwellinghouses Part on NH5 remainder windfall 18/01866/FUL Hatchend Morton On Swale Street Named & Numbered Sep'19 Active 14/12/2018 5 0 5 0 2 3 0 0 0 5 0 0 5 23/03/2020 CT survey 31/10/19 all on way Survey 2019 North Yorkshire DL7 9RG BI Initial Notice Jun'19 No reported progress Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 63 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Garden Cottage West Outline planning permission with some matters 18/02362/OUT Rounton North Yorkshire Outline 14/01/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 reserved (access) for the construction of a dwelling DL6 2LW No detailed application submitted by Mar'20

Land Adjacent Lyndale IPGN site - 1x bungalow 18/01133/OUT Welbury North Yorkshire Outline 17/01/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 20/03/2020 No detailed application submiitted by Mar'20 DL6 2SG

05/01501/FUL Birkby Grange Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion

09/00447/FUL Rear Of 219 High Street Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion

North Arch Cottage, 278 10/01077/FUL High Street Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion

12/00151/REM OS Field 8568, Moor Lane Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion

Old Tom’s Barn, Scholla 13/00265/FUL Lane, Northallerton, DL6 Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion 3QT

Parklands Coarse Fishery & 13/01880/REM Caravan Park,Yafforth Road, Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion Northallerton

Paddock Offices Elder Road 13/02288/FUL Northallerton North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion,1x pre Apr'15 Yorkshire DL6 1NH

14/00601/FUL 79A Ainderby Road Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion,1x pre Apr'15

Mill Farm 3 Water End 14/01115/FUL Brompton North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion DL6 2RN

Ground Floor Paddock Offices Paddock House Elder 14/02029/FUL Road Northallerton North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion Yorkshire DL6 1NH

The Post Office Front Street 15/00758/FUL Appleton Wiske North Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 2x Post Apr'15 Completion Yorkshire DL6 2AA

09/00031/FUL 57 Bullamoor Road Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Oct'14 Completion

Manor House Farm 09/01812/FUL Appleton Wiske Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Jul'14 Completion Northallerton North HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 64 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

10/02839/FUL The Coach House Complete 4 4 0 0 0 0 0 0 0 0 0 0 0 Jun'14 Completion

Station House, 4 11/01090/FUL Boroughbridge Road Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x post Apr'14

11/01297/FUL Otterington House Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Mar'15 Completion

Former Swaledale Arms 11/01506/FUL Morton On Swale North Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 2x post Apr'14 completions Yorkshire DL7 9RJ

11/01677/FUL 46A Water End Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Mar'15 Completion

11/01936/FUL Sun Appliances, 33 Malpas Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 May'14 Completion Road

Land To The North Of First 13/00490/FUL Fairholme Farm, Fairholme Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 May'14 Completion Lane

13/00819/FUL Ladybank House Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Mar'15 Completion

13/01862/FUL Elders Elder Road Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Sep'14 Completion Northallerton DL7 8QA

1ACastle Close 13/02215/FUL Northallerton North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Jun'14 Completion Yorkshire DL7 8DN

4, TWEDDLES YARD, 14/01004/FUL NORTHALLERTON, NORTH Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Jun'14 Completion YORKSHIRE, DL7 8QA

Hornby Methodist Church 14/01316/FUL Hornby North Yorkshire DL6 Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Jan'15 Completion 2JQ Ingram Grange Farm Outline granted Feb'19 18/02161/OUT Appleton Wiske North Outline 12/02/2019 2 0 0 0 0 2 0 0 0 2 0 0 2 20/03/2020 No detailed application submitted by Mar'20 Yorkshire DL6 2AW

Ivy House Farm Thrintoft Outline granted Mar'19 18/02416/OUT Moor Lane Thrintoft North Outline 12/03/2019 4 0 0 0 0 2 2 0 0 4 0 0 4 20/03/2020 No detailed appliction by Mar'20 Yorkshire DL7 0PW

18/02433/FUL Bank Top West Rounton New Permission Feb'19 Detailed Permission 1 0 0 0 0 1 0 0 0 1 0 0 1 20/03/2020 No BI record - Mar'20 CT Survey Oct'19 North Yorkshire DL6 2LW

Annexe The Cart Shed At Retrospective planning permission for creation of 18/02570/FUL Girsby Hall Farm Girsby Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 03/04/2019 two dwellings North Yorkshire DL2 1PP

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 65 Annex 6 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Northallerton Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

The Hollies Morton On New Outline granted Jun'19 18/02460/OUT Swale North Yorkshire DL7 Outline 25/06/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 20/03/2020 No detailed Permission at Mar'20 9QX

Land To West Of Smithy 19/00834/OUT Green Hornby Road New Outline granted Jun'19 Outline 28/06/2019 2 0 0 0 0 2 0 0 0 2 0 0 2 20/03/2020 CT Survey Oct'19 Appleton Wiske North No detailed Permission at Mar'20 Yorkshire

18/02135/OUT New Outline granted Feb'18 "The Roost" 19/01313/REM Reserved matters approved - 19/01313/REM - Land West Of The Paddocks Post application activity 12/08/2019 1 0 0 0 0 0 1 0 0 1 0 0 1 20/03/2020 Aug'19 CT Survey Oct'19 Hornby North Yorkshire Street Named & Numbered Feb'20 No further reported progress Mar'20

Orchard House Stobarts Application for outline planning permission with access to be considered (all other matters reserved) 19/01324/OUT Lane Low Worsall North Outline 23/08/2019 1 0 0 0 0 0 1 0 0 1 0 0 1 20/03/2020 for the creation of a detatched dwelling Yorkshire TS15 9PJ No detailed application Mar'20

19/01306/FUL Brindlewood East Harlsey New Permission Sep'19 Detailed Permission 20/09/2019 1 0 0 0 0 0 0 1 0 1 0 0 1 20/03/2020 CT Not started Oct'19 CT Survey Oct'19 North Yorkshire DL6 2DB BI Plans approved Nov'19, no start by Mar'20

Land South of Skelder 18/02717/OUT New dwelling allowed on Appeal Bungalow, Green Hills Lane, Outline 11/10/2019 1 0 0 0 0 0 1 0 0 1 0 0 1 20/03/2020 Detailed application 20/00446/REM submitted 20/00446/REM Ainderby Steeple Feb'20

Land Between Spring Terrace And Railway Line Allowed on Appeal 19/00363/OUT Outline 21/10/2019 1 0 0 0 0 0 1 0 0 1 0 0 1 20/03/2020 No detailed application by Mar'20 Springwell Lane Northallerton

Active site Romanby Court High Street Street Named & Numbered Nov'19 18/01113/FUL Northallerton North Active 05/09/2019 11 1 10 1 6 4 0 0 0 10 0 0 10 24/02/2020 There are only 11 new flats Yorkshire DL7 8PG 1st completion Feb'20

Notification For Prior Approval for a proposed Low Sober Farm Whin Lane Change of Use of Agricultural Building to a Dwelling 19/00295/MBN Warlaby North Yorkshire Post application activity 05/04/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 20/03/2020 House DL7 9JT Street Named & Numbered Oct'19 No reported progress Mar'20

The Bungalow West 19/02033/OUT Rounton North Yorkshire Outline 13/12/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 08/01/2020 new permission Dec'19 DL6 2LW

Northallerton Sub Area Windfalls 300 123 91 18 41 102 31 3 0 177 0 0 177

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 66 Annex 7 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Stokesley Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Works commenced on side extension SHLAA 2015 : Contacted Agent no info on progress. 12/02638/FUL Newton Rose, 46 Newton 01/03/2017 Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 Discharging conditions July'15, Both units built Road May'16 Survey 1/3/17 : Confirmed built

Holme Farm, 12 The Holme, 09/00105/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 19/02/2018 Completed March'17 Great Broughton

Albion House 73 Newton 10/01686/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 01/03/2017 10/01686/ful expired therefore removed Road Great Ayton

15/00533/OUT 15/00533/OUT - Expired May'18 110 High Street, Great Outline 19/00133/OUT - Renewal approved Apr'19 19/00133/OUT 04/04/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 Broughton Post Application Activity CT Note that land cleared Sep'19 No further reported progress Mar'20

No development, permission granted until October 13/01627/FUL 22 The Holme Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 11/12/2018 2018 - expired

13/01616/FUL Application for 1x dwelling & 1x Holiday let ;revised Revised application changed holiday let to dwelling; started Ayrshire Lodge, Nunthorpe Complete 2 2 0 2 0 0 0 0 0 0 0 0 0 14/06/2019 Application Dec'2013 - still U/C 15/00155/MRC Site Complete - CT Completions Jun'19

Started March 2013 Land Adjacent to Rosenda, 29/01/2017 12/00549/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 HDC - Built April 2016 - now called Rosenda - Station Road original dwelling renamed to Sandell Rise

13/01850/OUT Outline, HDC Reserved matter application approved & OS Field 0046, Seamer Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 12/02/2018 Dec'14; Not started by April 2016 - expires Dec'17 no 14/02157/REM activity

New Application approved April 2016 - 13/02342/FUL "Norfolk House" - 15/02775/FUL - discharging conditions ; Street Named & Numbered - Norfolk House; & Cranimoor Hill Road, Kirkby Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 22/10/2018 BI Plans approved Aug'16 15/02775/FUL in Cleveland CIL Commencement Notice - Jul'16 CT Completion Oct'18

"Lime Tree House" - 2A Survey 1/3/17 - looked complete , according to Hallgarth Great Broughton NYBCP photovoltaic system installed 14/02582/REM Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 13/06/2018 TS9 7EH June'18 - checked Gazetteer - CT completion . 20/10/16

Development commenced, no units delivered. Land west of Apple Tree Developer ESH Property Services. 01/03/2017 Complete SHLAA 2016: PARS All 16 units started,all complete 13/02666/FUL House, Garbutts Lane, 16 16 0 0 0 0 0 0 0 0 0 0 0 a Hutton Rudby May'16 Survey 1/3/17 indeed complete

14/02284/FUL & Crossways, 116 Newton Site cleared, no development Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 27/04/2016 SHLAA 2015 : PARS - Development started 7/7/15, 15/00685/FUL Road, Great Ayton CT Completion 14/3/16

Adjacent 13 Linden Road, Great Ayton 02/08/2016 U/C from Sep'15 - addressed as 45a Addison Road - 14/01918/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Address : (45A Addison a Completed 28/7/2016 Road)

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 67 Annex 7 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Stokesley Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

24a Addison Road, Great 14/00965/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 01/07/2015 Development complete - HDC CONFIRM Ayton The Barn The Plant Nursery Art Topiary The Nursery HDC Estimate;started Oct'14; still U/C Jan'17 14/01069/MBN Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 10/07/2019 Great Busby North Yorkshire BI Completion 1/4/19 TS9 7AS

The Granary & The Stables HDC - 2x conversion; Building Inspectors Notice Windy Hill Farm Stokesley submitted - Mar'15 14/01246/MBN Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 12/03/2019 Road Huon Rudby North Survey 1/3/17 - Not sure started - photo Yorkshire TS15 0JS No progress by Mar'19

Albion House 73 Newton HDC - Completed August 2014 14/01477/IAN Road Great Ayton North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 06/06/2016 Survey 1/3/17 : Still got shop front , completed?? Yorkshire TS9 6DT

HDC - not started - Jan'17 Peaton Carr Farm Stokesley no confirmed start since therefore expired in by 14/01659/MBN Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 03/10/2017 North Yorkshire TS9 5JS Oct'17 Later application 15/01538/MBN refused

This is a change of use - CT confirmed completion on 07/00158/FUL 64 Kirkby Lane Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 27/04/2016 1/4/2015

Application 16/02756/REM approved Jul'17, reduced 14/00337/OUT Land To The North And numbers by 1! & West Of Woodlands Walk Active 225 56 18 39 50 50 50 19 0 169 0 0 169 23/03/2020 1st starts Jan'18 16/02756/REM Tanton Road Stokesley 17 completions 2018/2019 - upped delivery rates 39 Completions - 2019/2020 to mid Mar'20

47A & 47B - Olivias Artisan Street Named & Numbered; Electrical works Bakery 47 High Street completed on 47A & 47B - Jun'15; no confirmed 15/00169/FUL Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 12/07/2017 finish underway but …. Stokesley North Yorkshire Survey 1/3/17 : Upper floors looked empty TS9 5AD VOA Completion - May'17

Not Started, 11 & 13 Bridge Street, Great Survey 1/3/17 : still warehouse/store 15/00597/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 15/03/2019 Ayton Looks like no progress - expired May'18 No CIL Commencement Notice - Apr'18

The Wheelhouse Primrose BI Plans submitted - Aug'16 - 16/17297/IN 15/01029/MBN Hill Farm Little Broughton Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 09/02/2018 The Big Check -on Gazetteer & Map completed by North Yorkshire TS9 5JR Feb'18

Building Notice acceptance - 20/12/2016; Demblin Ingleby Greenhow BI Start 31/1/17, survey confirmed start breeze 15/01060/MBN Active 1 0 1 0 1 0 0 0 0 1 0 0 1 23/03/2020 block well advanced on gable ends North Yorkshire TS9 6LH Enforcement Issues - still u/c Apr'19 No reported change Mar'20

Plot 1 - started 05/02/2016; plot 2 / 3 started Q1 2016/2017 Harland Hill Farm Easby Street Named & Numbered Sep'18 15/01102/MBN Active 3 2 1 0 1 0 0 0 0 1 0 0 1 23/03/2020 North Yorkshire TS9 6JD Plot 2 - CT Completion Dec'18 Plot 3 - BI Completion - Jan'19 No reported change Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 67 Annex 7 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Stokesley Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

15/01113/OUT "Sycamore Cottage" - Hill BI Plans approved Oct'16 under 16/18180/DOMIN BI Start 10/3/17 & Top East Side Hutton Rudby Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 07/01/2019 Street Named & Numbered 16/00812/FUL North Yorkshire TS15 0DB CT Completion Sep'18

"Stable Cottage" Hill House Stables Land Oct'17 - CIL Commencement Notice 15/01802/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 08/10/2018 Street Named & Numbered Sep'18 Adjacent To Village Hall CT Completion Jun'18 - but notified Oct'18 Ingleby Cross

Building plans submitted - 18/4/16, approved Meynell Hall Great May'16, 15/01820/MBN Broughton North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 12/09/2018 BI confirmed start 17/2/17 TS9 7EU Council Tax still under construction Mar'18 BI Completion 7/8/18 Land At The Old Orchard Survey 1/3/17 : Not started still garden land Call fo Sites - part of S/120/001 15/01823/FUL Cooper Lane Potto North Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 14/01/2019 NO CIL Commencement Notice - Apr'18 Yorkshire DL6 3HQ Expired

Approved Jan'16 Stonewold Stainton Road Survey 1/3/17 : Not started 15/01988/FUL Seamer North Yorkshire TS9 Active 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 BI Plans conditionally approved Jan'18 5NA BI Start 18/01/2019 No further change Mar'20

Completed 2/9/16 - 16/15297/IN, 8 High Street Great Ayton 29/01/2017 15/02572/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Survey 1/3/17 - looks complete , only one record at North Yorkshire TS9 6NJ No.8 which for residential shop use ceased in Oct'16 Halfway Barn, Road from Application to change from holiday to C£ use - 15/01376/MRC Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 13/09/2016 Harland Hill,Easby allowed on appeal Feb'16

April 2016 decision, expires April 2019 14/02578/OUT White House Farm Stokesley Variation on affordable housing submitted Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 15/04/2019 16/01138/S106, refused Nov'17 16/01138/S106 North Yorkshire TS9 5LE Survey 1/3/17 No new application submitted , therefore expired

16/02525/MRC - Variation in Plot sizes to Land And Buildings At Rear accommodate self-builders Of Kirkby House Farm Hill All plots u/c from Nov'17, since all started no 10% 15/02246/FUL Complete 5 5 0 3 0 0 0 0 0 0 0 0 0 08/10/2019 Road Kirkby In Cleveland reduction applied North Yorkshire Street Named & Numbered Feb'18 All Complete by Oct'19

June 2016 permission Pilly Hall Farm Easby North BI application - 18/21257/COND - approved - Nov'18 15/02726/MBN ACTIVE 1 0 1 0 1 0 0 0 0 1 0 0 1 23/03/2020 Yorkshire TS9 6JQ BI start Mar'19 No reported progress Mar'20

"Wesley House" - Great Broughton Methodist Street Named & Numbered; Survey 1/3/17 - Building Sold - no active works looks 16/00637/FUL Church High Street Great Site Complete - Jul'17 1 1 0 0 0 0 0 0 0 0 0 0 0 29/08/2017 exactly like chapel Broughton North Yorkshire VOA Completion 21/7/17 TS9 7EG Plot 1 Building work started 6/1/17, CT Inpsection finished Dec'18 Low House Farm Stainton 15/01294/MBN Plot 2 started Apr'18 Road Seamer North Active 2 1 1 0 1 0 0 0 0 1 0 0 1 23/03/2020 Associated application - 19/02581/FUL for garden & 16/00820/MBN Yorkshire TS9 5NB garage - Dec'19 No reported change Mar'20 HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 68 Annex 7 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Stokesley Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Applegrove Farm Apple 16/01588/MBN Discharging Conditions - Dec'17 Grove Farm Track Seamer Post Application Activity 08/04/2019 2 0 0 0 1 1 0 0 0 2 0 0 2 23/03/2020 Plot being marketed on Zoopla - Dec'18 19/00026/FUL North Yorkshire TS9 5NL No reported progress Mar'20

Completed no building work required. Loss of unit to 3 North Road Stokesley office use 16/01179/FUL Complete -1 -1 0 0 0 0 0 0 0 0 0 0 0 01/03/2017 Survey 1/3/17 - externally looks like a house , North Yorkshire TS9 5DU painting work being undertaken, linked to office at No.1 North Road

Blue Hall Cottage, 16 The 23/02/2017 Site thought to be expired but no confirmed start 10/02377/FUL Holme Great Broughton TS9 Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 VOA List 19/2/17 had a 20/1/17 completion date 7HF Moo Lodge The Meadows Kirkby Lane Kirkby In 02/03/2017 16/00872/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 C/U froom annexe to separate dwelling Cleveland North Yorkshire TS9 7AQ Call for Sites - S/128/007 Reserved Matters approved Jul'19 - now just two 16/02470/OUT OS Field 6300 Tame Bridge dwellings 19/00631/REM Active 05/06/2019 2 0 1 0 1 1 0 0 0 2 0 0 2 23/03/2020 Stokesley North Yorkshire Plot 1 start Jul'19 No reported progress Mar'20

Kitching Kneale And Co 81 16/00854/FUL High Street Great Ayton Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 25/04/2018 Conversion completed by Apr'17 North Yorkshire

Former Wesleyan Chapel BI Plans submitted - Sep'16 16/01222/FUL Ingleby Arncliffe North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 23/06/2017 Built July 17 Yorkshire DL6 3LN

BI Plans approved Jan'18 ; Call for Sites submission Highfield 12 Enterpen 16/01771/FUL S/073/003 Hutton Rudby North Post Application Activity 1 0 0 0 0 0 1 0 0 1 0 0 1 02/03/2020 DM Planning Officer site visit Mar'19 no start Yorkshire Initial Notice : 18/00751/IN - Jan'18 No reported progress Mar'20

First & Second Floors 45 High Street Stokesley North New Permission - April 2017 17/00095/FUL Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 12/06/2018 Yorkshire TS9 5AD BI completion - both flats May'18

109 High Street Great Broughton New Permission - June'17 BI Plans approved 16/02643/FUL North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 17/12/2018 Net Gain of 1 unit TS9 7HB CT Completion - Dec'18 Hill View Hill Road New Permission - May'17 17/00180/OUT Kirkby In Cleveland Call for Sites - S/082/002 Outline 2 0 0 0 0 0 2 0 0 2 0 0 2 23/03/2020 North Yorkshire No detailed application submitted - Mar'20 ; expires TS9 7AN Jun'20 The Dairy Easby Grove Farm New Permission - June'17 Easby Later application for Subsequent application - 19/00439/FUL - now 17/00847/MBN 0 0 0 0 0 0 0 0 0 0 0 0 0 14/05/2019 North Yorkshire holiday accomodation change of use to holiday cottage - therefore TS9 6JQ removed from supply

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 70 Annex 7 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Stokesley Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15 Hollygarth House Hollygarth Great Ayton New Permission - June'17 16/02683/FUL Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 18/12/2017 North Yorkshire 2x BI Completions Dec'17 TS9 6NG

White Post Farm Great Added - Sep'17 - VOA completion Jun'17 15/00232/MBN Broughton North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 25/09/2017 Street named & Numbered Jan'17 TS9 7HU

103-105 High Street Great Ayton Loss of two dwellings to A1/A3 use 17/01157/FUL North Yorkshire Active -2 0 -1 0 0 0 -2 0 0 -2 0 0 -2 23/03/2020 Dwelling to salon started Jan'19 TS9 6NB No further change Mar'20

Cringle Moor Thirsk Road New Application Sep'17 17/00360/FUL Stokesley North Yorkshire Planning Permission 2 0 0 0 0 0 2 0 0 2 0 0 2 23/03/2020 No progress - No Building Regulations application by TS9 5BP Mar'20

Free House Farm Land To New IPGN Application granted Nov'17 17/00878/FUL The Rear Of Crathorne Arms Call for Sites - S/033/001 Post Application Activity 5 0 0 0 3 2 0 0 0 5 0 0 5 25/02/2020 New Initial Notice submitted - 20/01692/IN - Feb'20 19/02712/MRC Crathorne North Yorkshire Material Change - 19/02712/MRC - now just 5 units - TS15 0BA Feb'20

Newby Grange Newby 17/02211/FUL New Permission - Nov'17 North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 12/09/2018 BI Start Feb'18 TS8 0AN July'18 - Complete

Stokesley Used Car Sales Tame Bridge New Permitted Development 17/00389/JPN Stokesley Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 21/10/2019 In Oct'19 , notifed of a CT completion in Apr'19 TS9 5LQ

Alterations and change of use from garage/store to Ground Floor 18 Levenside ground floor flat 17/01173/FUL Stokesley North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 15/03/2019 New Permission Jan'18 TS9 5BJ Street Named & Numbered Sep'18 Site Complete Dec'18 Brook House 21 Levenside New Permission - Feb'18 17/01570/FUL Stokesley North Yorkshire Planning Permission 09/02/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 No BI record by Mar'20 TS9 5AR

17/00305/OUT Springwell Nurseries New Permission - Feb'18 Call for Sites - S/128/001 - whole site has pp 19/02287/OUT Stainton Road Seamer North Outline 23/02/2018 5 0 0 0 0 2 3 0 0 5 0 0 5 23/03/2020 New Outline submitted Oct'19 - for 5 units Yorkshire TS9 5NA No change Mar'20

Annaclay Farm The Holme 17/02207/OUT New Permission - Feb'18 Great Broughton North Outline 22/02/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 No Detailed Application submitted up to Mar'20 Yorkshire TS9 7HF Building & Land North of 17/00812/PPN Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 11/05/2018 Post March 2018 completion A172 Swainby Hawthorns,Tame Bridge 18/01112/OUT Stokesley Outline application with details of access (all other matters reserved) for a bungalow 19/01017/REM North Yorkshire Detailed Permission 12/08/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 Reserved Matters approved Aug'19 TS9 5LQ CT no start Oct'19 , No BI record at Mar'20 HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 71 Annex 7 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Stokesley Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Detailed application approved for Plot 2 - 18/01602/OUT Outline - Details for part OS Field 2719 Stokesley 19/00302/FUL.Plot 4 approved - 19/01229/FUL - 19/00302/FUL of Site Road Hutton Rudby North 25/10/2018 5 0 0 0 0 2 3 0 0 5 0 0 5 23/03/2020 Jul'19 Street Named & 19/01229/FUL Plot 2 - Street Named & Numbered Nov'19 Yorkshire Numbered No reported progress Mar'20

10 Cooper Lane, Potto DL6 Allowed on appeal 17/01766/FUL Post Application Activity 15/11/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 CIL Self Build exception Feb'20 3HQ No BI record Mar'20

Hunter Hill Farm Lodge 18/02290/FUL Tanton Road Seamer North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 06/02/2019 Retrospective sub-division , 1 net gain Yorkshire TS9 5NG

Stonewold, Stainton Road, 09/01605/REM Seamer Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion

Rear of the Old Mill, 47 11/00054/FUL Levenside, Stokesley LEVEN Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion MEWS

13/00646/FUL Great Ayton Police Station, Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Completion Mar'15 Guisborough Road Stanley Grange Stud, Yarm 12/01414/FUL Lane Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion

12/02230/FUL 13 Allen Grove Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion, 1x Pre Apr'15 completion

13/02115/FUL North House, 5 North Road Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 2x Post Apr'15 Completion

15/09999/X 46 Hebron Road,Stokesley Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'15 Completion

Notification for prior approval for a proposed "Oak Tree View" change of use of agricultural building to a The Barn Faceby Fields dwellinghouse 18/02658/MBN Goulton Lane Carlton In Active 1 0 1 0 0 1 0 0 0 1 0 0 1 23/03/2020 Street Named & Numbered Apr'19 Cleveland North Yorkshire BI Commencement 2/10/19 TS9 7DS No change Mar'20

Ayton Firs Manor Green Proposed change of use of annex to independent dwelling 19/00369/FUL Lane Great Ayton North Complete 18/04/2019 1 1 0 1 0 0 0 0 0 0 0 0 0 11/12/2019 Annex already exists - retrospective complete at Yorkshire TS9 6JB Apr'19

14/02360/FUL Seamer Hill Farm Seamer Was holiday accomodation but Detailed Permission 1 1 0 1 0 0 0 0 0 0 0 0 0 10/06/2019 18/02614/MRC saw this changed to dwelling 18/02614/MRC North Yorkshire TS9 5NQ BI completion May'19

HSBC 25 High Street Change of use of First and Second floors from offices 19/01014/FUL Stokesley to 2No. Apartments Post Application Activity 22/07/2019 2 0 0 0 0 2 0 0 0 2 0 0 2 23/03/2020 Not started Sep'19 North Yorkshire BI Initial Notice Oct'19 TS9 5AD No reported change Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 72 Annex 7 : Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Stokesley Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

The Coach House Ayton Firs Subdivision of existing residential annex to form an 19/01312/FUL independent dwelling Green Lane Great Ayton Post Application Activity 19/08/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 BI Initial Notice DEC'19 North Yorkshire TS9 6JB No further reported progress Mar'20

Great Broughton Post Office Change of use of existing ground floor commercial 19/00560/FUL 50 High Street Great units to single apartment Detailed Permission 12/09/2019 1 0 0 0 0 0 1 0 0 1 0 0 1 23/03/2020 Broughton North Yorkshire BI Initial Notice DEC'19 TS9 7EG No further reported progress Mar'20

"Middle House" - Building 08/01976/FUL Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 22/10/2019 Notifed BI Completion Oct'19 Between 41-43 North End

Land Adjacent 24 Belbrough New permission Dec'19 19/02007/FUL Close Hutton Rudby North Detailed Permission 13/12/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 No reported progress Mar'20 Yorkshire TS15 0EH Ingleby Arncliffe Church Of 19/01448/OUT VC Primary School Outline 13/01/2020 4 0 0 0 2 2 0 0 0 4 0 0 4 22/01/2020 Outline application - 4 dwellings Ingleby Arncliffe DL6 3NA

Stokesley Totals 339 128 23 49 61 71 60 19 0 211 0 0 211

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 73 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Under development, will deliver in year 1 - 07/02387/FUL 16 Millgate Thirsk Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 29/09/2015 HDC site complete in August 2014 therefore to be removed Now Harland Builders both plots started 24/11/16 Update Feb'18 - Outside roofs well on , Street The Rowans (Plot 9-13) East Named & Numbered 09/01777/FUL Active 4 4 0 1 0 0 0 0 0 0 0 0 0 23/09/2019 Plot 2 completed May'18 of Estate Road Plot 3 & last plot completed Aug'19

No development and permission expired. HDC Survey 19/8/15 - No Progress therefore expired 09/03651/FUL 20B Station Road Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/07/2017 but PARS start May 2017 Completion

The Old Brewery, 93 Long 10/02627/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 29/01/2017 HDC permitted October 2013, expires October 2016. Street

One completion with works on site underway on Land to the rear of 5A to 5C 06/03/2017 final two plots; 11/02035/FUL Complete 3 3 0 0 0 0 0 0 0 0 0 0 0 Front Street a HDC has 2 completions 2015/2016 with Plot 3 commencing on 21/9/15, VOA completion Jan'17

Walkers Ground, Church 12/01093/FUL Plot for sale with no works commenced Street Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 10/03/2017 HDC no indication of activity; lapsed Jan'16 Survey confirmed no activity

Street named & Numbered Nov'15 12/01707/FUL Survey 8/3/17 - no start 15/01952/FUL West House, 1 Alexander Building Inspector plans submitted Mar'18 Detailed Permission 05/04/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 19/00116/FUL Close Revised application - 19/00116/FUL - approved April 2019 Land sold Nov'19,No start Mar'20

29/01/2017 HDC - 2x flats both started Nov'13 , 1 completion July 12/02365/FUL 87A Market Place Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 a 2014. CT completion of Flat 2 Jan'17

"Pear Tree House" Site under construction 12/02398/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 20/06/2016 20 Ingramgate HDC confirm July 2014 start, completed Mar'16

Land East of Common Lane, No development on site; April 2016 no change - 13/00078/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 29/01/2017 Carton Husthlewaite therefore expired

13/00377/FUL No development on site; varying conditions Jan'16; Greystones, Dalton Lane Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 20/09/2016 15/02260/MRC site expired Sep'16

Works nearing completion; 13/00503/FUL now "Beech Crest" 09/03/2017 HDC - Building Inspector start for 19/3/2015; Built Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 6 Hillcrest, Pickhill a 2/7/16 Survey 8/3/17

13/00975/FUL Two permissions for the site. One dwelling Land to the rear of North completed under permission 11/00640. 11/00640/REM Complete 5 5 0 0 0 0 0 0 0 0 0 0 0 10/09/2018 Lodge, Stockton Road HDC : Two complete under permission 13/00975/FUL, I completed 3/9/16

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 74 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

HDC Survey 19/8/15 : Plot2 now complete - cards in 13/01769/FUL Land North of Oak View Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 28/04/2016 window - Plot 1 still u/c site generally needs finishing off; Plot 1 finished Sept'15

Street Named & Numbered - 2017 13/02323/FUL Land off Catton Village Survey May 2018 - very active Active 6 4 2 2 2 0 0 0 0 2 0 0 2 23/03/2020 Plots 3 & 4 completed Mar'19 Street, Catton Plots 1 & 2 completed Apr'19 No further change Mar'20

Reserved Matters approved for 40 units, affordable 13/02397/OUT Land off End Street, St dwellings,Nov'18 Active 16/11/2018 40 0 40 0 10 10 10 10 0 40 0 0 40 10/03/2020 10 BI starts Mar'19 by Jul'19 all under construction 17/02448/REM Marys Close, Thirsk Street Named & Numbered Jul'19 No completions yet early March 2020

The Cottage, Spital Hill, York SHLAA 2015 : Agent - Almost Complete; PARS 13/02399/FUL Complete -1 -1 0 0 0 0 0 0 0 0 0 0 0 24/07/2015 Updated; 2 dwellings into 1 - Gazetteer confirmed Road complete 13/02560/REM Land to the north of The HDC - 12 completions 2015/2016; Revised Layout 16/00511/FUL Complete 43 43 0 0 0 0 0 0 0 0 0 0 0 29/03/2019 submitted - 16/00511/FUL extra 7 units site total Willows, Willow Bridge Lane now 43 2017/2018 - 13 built.

13/02588/OUT 09/05/2016 Reserved matters approved 14/01606/REM. Park Farm Holme on Swale Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 14/01606/REM a HDC confirmed start on 27/5/15,COMPLETE 22/4/16

Hawthorn Cottage, Long 13/02603/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 01/07/2015 HDC - Confirmed Completion on 31/7/2015 Street, topcliffe

Street Named & Numbered Mar'17; 16/01201/MRC 14/00004/FUL "Scots Dene" approved to change site area Revised Application submitted approved May'17 - 16/01201/MRC Land Adjacent Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 23/03/2018 technically expired for 2 months. 17/00470/FUL Pennington,Pickhill CIL Commencement Notice Served. Site Complete Mar'18

Revised application 17/00975/FUL - approved 14/00313/FUL Lyng Easthaugh, Main 3/8/17 17/00975/FUL Active 1 0 1 0 0 1 0 0 0 1 0 0 1 23/03/2020 BI Initial Notice - Nov'19 Street, Sessay Survey April 2019 - Well on way, 2nd storey No notified change Mar'20

HDC - Note numbers change : Change of use from a Abbeyfield Society, Mitchell nursing home to 7 one bedroom and 1 two bedroom 14/00755/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 26/04/2018 House, Gillings Court apartments No Change Jan'17 - expired May 2017

Outline permission, can deliver in five year period 14/00882/OUT Land adjacent to the New HDC : Full Application submitted 15/01852/FUL; BI & Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 11/09/2018 Plans submitted - April 2016 House, Catton 15/01852/FUL Survey 8/3/17 - Very active - see photo CT Completion - May'18

Manor Farm Balk North No activity - Jan'17 14/01134/MBN Planning Permission 0 0 0 0 0 0 0 0 0 0 0 0 0 26/04/2018 Yorkshire YO7 2AH expired

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 752 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15 HDC - Reserved Matter granted July 2015 - IPGN Site; BI Plans - Initial Notice served; Street Named & 14/01434/OUT "Thistledoo" Numbered - August 2016. & Redundant Pumping Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 29/03/2019 CT still ongoing Oct'17 15/01104/REM Station, Pickhill Survey 4/5/18 - Externals Finished Site Complete Feb'19

0 0 0

14/01523/FUL New application 17/00051/JPN for 25 flats approved Station Road Business Park & March 2017; Station Road Thirsk North Site Complete - Aug'17 30 30 0 0 0 0 0 0 0 0 0 0 0 04/12/2017 17/01193/JPN approved 17/7/17 now for 30 units. 17/00051/JPN Yorkshire YO7 1PZ Street Named & Numbered 2/6/17 17/01193/JPN All Complete by August 2017

Plot 1 - BI Start Nov'17 Salmon Hall Caon Lane Plot 2 - BI Start Feb'18 Plot 3 - Completed Jun'18 14/01917/MBN Topcliffe North Yorkshire Active 3 1 2 0 2 0 0 0 0 2 0 0 2 23/03/2020 Street Named & Numbered Jan'18 YO7 3SA Survey May 2018 - plenty of activity No notified change Mar'20 New Church Farm Church HDC confirmed start 14/5/2015; Completed 14/01961/FUL Lane Bagby North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/05/2016 Feb'2016 YO7 2PW

Known as "No. 3 & 4 Moorhouse Farm Cottages" 06/06/2016 These both confirmed CT completions - on 14/02610/MBN Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 Moorhouse Farm Felixkirk a 22/4/2016 North Yorkshire YO7 2EE

14/02081/FUL "Williams Court" HDC - sold to Palladian Homes - up to roof level. Emailed Palladian for details - 3rd party inspector & Thirsk Garage - 6 Complete 14 14 0 0 0 0 0 0 0 0 0 0 0 02/10/2017 Survey 8/3/17 - substantially complete 15/00636/FUL Ingramgate All complete July'17 HDC Estimate ; Works to extend building to improve internal layout of barn approved March 2015; this 14/02151/MBN Village Farm,Sinderby North plot 4 - other three holiday accomdodation - Initial Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 12/02/2018 15/00038/FUL Yorkshire YO7 4JD notice submitted,Feb'15 Survey 8/3/17 - Looked like not started - holiday accomodation looked active

Now known as 20a - 21 01/08/2016 SHLAA 2015 : Agent - Almost Complete; PARS 14/02500/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Hambleton Place, Thirsk a Updated; built 24/6/2016 Recent permission approved, no development on site. HDC Survey 19/8/15 - No Progress; no change Jun'16 15/00005/FUL 41 Station Road Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 06/04/2018 Survey 8/3/17 - Not started The Big Check Feb'18 - No progress expires Mar'18, no further applications therefore expired

Replacement of dwelling with a 2 storey dwelling and construction of a dormer bungalow. 20 Croft Heads Sowerby 09/02/2017 Complete Replacement ignored for supply purposes therefore 15/00310/FUL 1 1 0 0 0 0 0 0 0 0 0 0 0 a North Yorkshire YO7 1NG 1 net gain.; Plot 1 - Field View - (the new bungalow) started 12/10/2015,COMPLETE 8/2/17.

Land Adjacent to 147 No development, recently approved application 15/00357/FUL Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 11/09/2018 Checked Sep'18 no evidence of any completions Hambleton Place therefore expired

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 76 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

"Butter Hill View" Reserved Matters submitted Oct'16, approved Jul'17 15/00408/OUT Land North Of The Paddocks now 6 dwellings & Complete 6 6 0 0 0 0 0 0 0 0 0 0 0 16/03/2018 NOTE : Daniel Gath site therefore no 10% reduction Main Street Sessay North 16/02364/REM Plots 1,2,3 & 4 complete Feb'18 Yorkshire Plots 5 & 6 complete - Mar'18

28 Long Street Thirsk North Street Named & Numbered - Greengage Cottage; 15/00527/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 14/09/2017 Initial Notice from 06/7/2015 Yorkshire YO7 1AP Completion Sep'17

"The Shieling" Land Adjacent To 62 Back 07/06/2016 15/00681/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 Under Construction from Nov'15; finished May'16 Lane Sowerby North a Yorkshire YO7 1NQ 15/00905/OUT Street Named & Numbered Apr'19 17/00962/MRC Survey April 2019 - on site , 17/01935/REM "Rokesby Place" 19/00989/FUL - repositioned Plot 8 19/00989/FUL Chapel Farm Pickhill North Active 8 2 0 2 4 2 0 0 0 6 0 0 6 23/02/2020 19/00892/FUL - changes to Plots 1 & 2 , both 19/00892/FUL Yorkshire YO7 4JG approved Jul'19 19/01500/FUL 2 completions by Feb'20

Hall And Premises Norby 07/06/2016 Complete Conversion completed May'16 15/00907/FUL Estate Norby North 2 2 0 0 0 0 0 0 0 0 0 0 0 a Yorkshire YO7 1BG

15/01028/FUL Survey 8/3/17 - Not started. 18/02634/FUL The Old Chapel Pickhill Permission renewed under 18/02634/FUL Active 1 0 1 0 0 1 0 0 0 1 0 0 1 23/03/2020 (19/01005/MRC) North Yorkshire YO7 4JG Variation of Condition May'19 BI Start Aug'19, no further progress Mar'20

Additional application 16/02350/FUL - net gain 1x 15/01109/OUT dwelling , permitted Feb'17. Total net gain two The Hawthorns Main Street & dwellings Thornton Le Moor North Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 15/02/2019 16/00876/FUL Street Named & Numbered - 5/9/17 Yorkshire DL7 9DW BI Completion Plot 2 - Hedgerows - Dec'18 16/02350/FUL BI Completion Plot 1 - Jan'19 so site complete

Pickhill Engineers Ltd Street Expires July 2018 15/01118/OUT No Full Application approved byFeb'18, Survey Lane Pickhill North Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 16/04/2019 8/3/17 Yorkshire YO7 4JU Survey April 2019 - no change

Eldmire Hill Ox Close Lane No movement 15/01126/FUL Eldmire North Yorkshire Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 14/01/2019 Expired YO7 3JH

Building Plans submitted - April 2016; 2x starts Sandhill Farm Low Road 30/9/2016 15/01185/MBN Thirkleby North Yorkshire Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 15/10/2018 Street Named & Numbered May'18 YO7 2BE Plot 1 - complete Jun'18 Plot 2 complete Pentland House - Sep'18 "Honeyfield Lodge" Beechdene Carlton Road Street Named & Numbered ; plans approved; U/C 15/01207/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 14/02/2018 from 06-07-2016 Carlton Miniott North Gazetteer completion - Feb'18 Yorkshire YO7 4NJ

Westholme Skipton On Street Named & Numbered as "Meadow Lodge" - BI 10/03/2017 Complete start from 12/01/2016; Completed 15/11/16, 15/01349/FUL Swale North Yorkshire YO7 1 1 0 0 0 0 0 0 0 0 0 0 0 a 4SB Survey 8/3/17 : confirmed complete

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 77 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

"Greenfield House" Street Named & Numbered - "Greenfield House " ; BI 15/01355/FUL Land Adjacent Westwood Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 20/12/2018 Start April 2016 Bagby North Yorkshire CT Completion Dec'18

Montrose Main Street Plans approved, Jan'16 Survey 8/3/17 - no activity , site notice only 15/01446/FUL Sessay North Yorkshire YO7 Active 1 0 1 0 0 1 0 0 0 1 0 0 1 23/03/2020 BI Start - 16/00348/DOM - Plot 1 Start - Nov'18 3BE No change Mar'20

15/01499/OUT / Plot 1 Reserved Matters approval May'17 16/01677/MRC Land To The East Of Church Jan'18 new reserved matters for whole site - Active 5 1 4 1 2 2 0 0 0 4 0 0 4 27/02/2020 approved Apr'18 17/01242/REM Lane Bagby North Yorkshire Street Named & Numbered Sep'18 18/00124/REM Plot 3 complete Jul'19, no further reported progress

Reserved Matters approved - 18/02089/REM - "Hillside House" Feb'19 15/01542/OUT Land To The South Of Post Application Activity 06/02/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 Street Named & Numbered Aug'19 18/02089/REM Willow Garth No BI record Mar'20 North Yorkshire

Full application submitted 15/01559/OUT Village Farm Catton Village Survey 8/3/17 - No activity - site notice at site CIL Commencement Notice - Dec'17 & 16/02633/FUL Street Catton North Active 5 0 5 0 2 3 0 0 0 5 0 0 5 23/03/2020 Survey 2018 - Marked progress Yorkshire YO7 4SQ Street Named & Numbered Jul'17 No reported change Mar'20

Three Tuns Yard Chapel Street Named & Numbered , Building Inspector and 31/01/2017 Complete Gazetteer start 27/1/16, all three completed by 15/01787/FUL Street Thirsk North 3 3 0 0 0 0 0 0 0 0 0 0 0 a Yorkshire YO7 1LU Nov'16

15/02006/OUT BI Start April 2017, all 10 u/c by Sep'17, & New Application to split Wisteria House - 16/01420/REM 17/02496/FUL - giving a net gain of 11 units Wisteria Cottage, 21 Station Active 16/02185/REM 11 1 10 0 6 4 0 0 0 10 0 0 10 23/03/2020 Wisteria House split into 2 dwellings completed Road Site Started Apr'17 17/00493/FUL Mar'20 - work continues 17/02496/FUL

15/02034/FUL Felixkirk Church Hall Permission Renewed Sep'18 Post Application Activity 21/09/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 23/02/2020 No BI record at Mar'20 18/01398/FUL Felixkirk North Yorkshire Discharging conditions Feb'20 Hall Garth Fanny Lane No full Application approved by Sep'18 15/02061/OUT Knayton North Yorkshire Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 15/03/2019 Expired Feb'19 YO7 4AS

Agricultural Buildings 16/02084/MRC approved 17/11/16; 15/02158/MBN Maunby North Yorkshire Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 09/10/2019 BI start under 16/28078/conbns 17/11/16 YO7 4HA Gazetteer Completion Oct'19

15/02251/MBN "Stannum Barn" Survey April 2019 - externals work largely complete , 17/00486/PPP Land At Whitby internals progressing Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 06/02/2020 Street Named & Numbered Nov'19 17/01839/MRC Farm Lowfields CT Completion - Feb'20 Lane Pickhill North Yorkshire

84 St James Green Thirsk Not started 15/02496/FUL Planning Permission 0 0 0 0 0 0 0 0 0 0 0 0 0 15/03/2019 North Yorkshire YO7 1AJ Expired March 2019

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 78 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Land To The Rear Of The 15/02717/OUT Survey 4/5/18 - No Change Cottages Street Lane Pickhill Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 15/03/2019 No Full Application approved by Sep'18 North Yorkshire YO7 4JX Expires Mar'19; Call for Sites - T/118/001/H Foxs 18 - 20 Chapel Street 29/01/2017 Complete Both completed July'16 15/02732/FUL Thirsk North Yorkshire YO7 2 2 0 0 0 0 0 0 0 0 0 0 0 a 1LU Greystone Flatts Farm 15/02756/MBN Borrowby North Yorkshire Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 19/07/2017 Started 09/03/2016, site complete 17/7/17 YO7 4QY Approved Jun'16 Street Named & Numbered - Sep'17 Greenbank Farm Dalton BI Initial Notice Oct'17 14/01472/FUL Complete 2 2 0 1 0 0 0 0 0 0 0 0 0 29/07/2019 North Yorkshire YO7 3HY Plot 2 - Sycamore House CT completion Dec'18 Plot 1 - Oak Tree House CT Completion Jun'19

16/00724/OUT Little Acre Dalton North & Site Survey - 2/2/17 Breeze block nearly up to 1st Yorkshire YO7 3JD Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 05/11/2018 Floor 16/01942/REM CT Completion Aug'18

Demolition Notice for garages - 19/00067/DEM - July 16/00999/FUL 5 Silver Street Sowerby 2019 Active 2 0 1 0 0 0 1 1 0 2 0 0 2 23/03/2020 North Yorkshire YO7 1JU BI Start Plot 1 - Jul'19 Checked Mar'20 - no further change

No activity - Jan'17; revised application “Rosewood Grange” 16/01079/FUL 16/02801/MRC approved Mar'17 Land East Of Craddock Row CIL Commencement Notice 1/2/17 16/02801/MRC Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 16/10/2019 Sandhutton North Yorkshire BI Initial Notice - Apr'17 YO7 4RT Street Named & Numbered Apr'18 CT Completion Sep'19

16/01419/FUL The Old Post Office Sinderby Expired but new Expired Aug'19 application submitted 0 0 0 0 0 0 0 0 0 0 0 0 0 09/09/2019 Renewal 20/00003/FUL - Renewal of previous North Yorkshire YO7 4JD Jan'20 application recived - 2/1/20

CIL Commencement Notice - June 2017 as demolition Ainderby Hall Ainderby started 16/00373/FUL Survey May 2018 - no active construction Quernhow North Yorkshire Active 4 0 4 0 0 2 2 0 0 4 0 0 4 24/03/2020 Survey 2019 - confirmed site cleared no further YO7 4HZ activity - 5 dwellings with chapel conversion Survey 2020 - well on way, no change Mar'20 BI Initial Notice - 18/12083/IN - Jun'18 Land Adjacent Fren Dene Street Named & Numbered - Dec'18 16/01933/OUT And Primrose Hill Dalton Survey April 2019 - all five under construction - 18/00460/REM Complete 5 5 0 5 0 0 0 0 0 0 0 0 0 03/12/2019 externals largely finished North Yorkshire Private Inspector - under reported APPEAL SITE All Plots complete by Nov'19

No activity - Jan'17 16/01627/MBN Discharging Conditions - Jan'18 Discharging Manor Farm Pickhill North BI Approval - 18/06989/CONS Active 1 0 1 0 0 1 0 0 0 1 0 0 1 24/03/2020 Conditions Yorkshire YO7 4JR CIL commencement Notice - Feb'19 16/01627/DCN Checked Mar'20 no further change

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 79 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

No activity - Jan'17 16/01446/FUL Methodist Chapel Amended scheme - 17/01949/FUL approved Nov'17 Active 1 0 1 0 0 1 0 0 0 1 0 0 1 11/02/2020 17/01949/FUL Sandhutton North Yorkshire BI start - 18/22385/MULBN - Nov'18 Checked Feb'20 - no change

"Highfield" Outline 16/02150/OUT approved Nov'16 16/02150/OUT Schiehallion Stockton Road Reserved Matters approved Apr'17 , Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 12/09/2018 CIL start Jul'17, BI Start Jul'17 17/00207/REM South Kilvington North Street Named & Numbered - Nov'17 Yorkshire YO7 2NL CT completion 15/6/18

No activity - Jan'17 3 Belgrave Terrace Survey 8/3/17 - No activity 16/02086/FUL Discharging conditions - Nov'17 - 16/02086/DCN Mowbray Place Sowerby Active 2 1 1 1 1 0 0 0 0 1 0 0 1 24/03/2020 CIL Commencement Notice - start 31/1/18 North Yorkshire YO7 1RE Street Named & Numbered Plot 2 BI completion Sep'19 , no change Mar'20

Revised Application for 4 dwellings submitted - 15/02851/FUL 18/01409/FUL - refused Sep'18,allowed on appeal 17/01561/FUL 131 Long Street Thirsk North Jul'19 Active 22/07/2019 4 0 4 0 2 2 0 0 0 4 0 0 4 10/02/2020 18/01409/FUL Yorkshire YO7 1BB 19/21959/DOM - new BI Application Nov'19; no change Feb'20 All plots started Dec'19

16/00133/FUL New Permission 16/02304/FUL added extra 16/02304/FUL 2 Castlegate Thirsk North apartment , Total now 4 Active 4 3 1 0 1 0 0 0 0 1 0 0 1 24/03/2020 Three CT Completions for the flats - Plots 2,3,4 - Yorkshire YO7 1HL Mar'19 No further progress Mar'20

New Application - Oct'16 16/01913/FUL 9 Chapel Street Thirsk North 13/03/2017 Complete Survey 8/3/17 - conversion complete , for sale as 3 1 1 0 0 0 0 0 0 0 0 0 0 0 a Yorkshire YO7 1LU bed semi New Application - Nov'16 "Willows Mews" Survey 8/3/17 - Trial Pits & markers on site 16/01640/FUL Variation to Plot 1 under 17 01590/FUL & Land Off Bellingham Close Complete 4 4 0 0 0 0 0 0 0 0 0 0 0 19/11/2018 17/01583/MRC changes to 3 & 4 Thirsk North Yorkshire Street Named & Numbered - Aug'17 as "Willow Mews" Thirsk Service Station White 16/01711/FUL Horse Service Station 109 BI Plans approved Jan'17 Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 12/09/2018 Survey 8/3/17 - no activity Long Street Thirsk North BI completion 24/8/18 - both plots Aug'18 Yorkshire YO7 1BB 0 0 0 Undercro Garage Smiths New Permissiion from Feb'17 16/02740/FUL Survey 8/3/17 - Building work underway Row Chapel Street Thirsk Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 25/09/2017 Street named & numbered April'17 YO7 1TJ Complete Jul'17 - VOA Return

Demolition Notice : 17/00075/DEM - Site now active 16/01575/FUL The Bungalow Masonic Lane Street Named & Numbered - May 2018 Complete 5 5 0 0 0 0 0 0 0 0 0 0 0 20/03/2019 First 3 completions for Plots 1, 4, 5 occupied 2/1/19 Thirsk YO7 1PS but notified by CT 15/3/19 Final Plots 2 & 3 CT Completions 18/3/19

Additional unit approved under 16/02135/OUT - 16/00808/OUT "9 to 14 The Green" now 5 in total 16/02135/OUT Land East Of Amberleigh Full application 17/02615/FUL approved Mar'18 Complete 5 5 0 5 0 0 0 0 0 0 0 0 0 04/11/2019 17/02615/FUL House Lowfields Lane Part of Call for Sites T/118/002 Pickhill North Yorkshire Street Named & Numbered Oct'18 CT Notified completions Sep'19

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 80 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Reserved Matters application approved May 18 16/00712/OUT "Chapel House" Discharging conditions - 18/00363/DCN - Jun'18 18/00363/REM Hill Farm Skipton On Swale Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 11/07/2019 Start 2/7/18 North Yorkshire YO7 4SB Street Named & Numbered Aug'18 BI Completion Jun'19

Station Farm Pickhill YO7 New Permission - March 2017 16/02116/OUT Outline - Post application 4JG 03/03/2017 14 0 0 0 0 7 7 0 0 14 0 0 14 24/03/2020 Call for Sites - T/118/004 Activity 20/00353/REM Reserved Matters submitted Feb'20

Former Methodist Church New Permission - March 2017 16/02416/FUL Planning Permission 1 0 0 0 0 0 1 0 0 1 0 0 1 24/03/2020 New BI Initial Notice - 19/15104/IN - Aug'19 Ainderby Quernhow Main site started

Walkers GarageSouth 16/01511/FUL Oerington North Yorkshire Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 24/03/2020 Expired March 2020 DL7 9HT

Long Street Fisheries 62A 16/02787/FUL Long Street Thirsk North Expired 0 0 0 0 0 0 0 0 0 0 0 0 0 24/03/2020 No new pp submitted,therefore expired Mar'20 Yorkshire YO7 1AU "Melpasby Manor" Methodist Chapel Skipton Street Named & Numbered - approved BLPU on 06/00820/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/07/2017 On Swale Thirsk North 12/4/17 Yorkshire YO7 4SB

"Rymer Granary" - Rymer Two Bed Farm Conversion - Street Named & 17/00151/MBN House Farm Felixkirk North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 18/06/2018 Numbered - June 2017 Yorkshire YO7 2EF Site Complete Mar'18

New permission approved Aug'17 for 2 extra 16/01468/OUT West View Bagby Lane dwellings - now 5 in total 17/01223/OUT Bagby North Yorkshire YO7 Post Application Activity 5 0 0 0 0 2 2 1 0 5 0 0 5 24/03/2020 Call for Sites - T/009/004/H 19/00773/REM 2PH Reserved Matters approved Jun'19 - 19/00773/REM BI Initial Notice Jul'19, no noted progress Mar'20

New Permission - April 2017 White House 17/00196/FUL Plot 2 started Apr'18 CoageSinderby North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 28/11/2018 Street Named & Numbered - Apr'18 17/01743/MRC Yorkshire YO7 4JD Discharging conditions 17/01743/MRC CT Completion Nov'18 Hilltop Dalton North New Permission - Aprill 2017 17/00268/OUT Outline 28/04/2017 1 0 0 0 0 1 0 0 0 1 0 0 1 24/03/2020 YorkshireField YO7 3HSHouse No detailed permission submitted up to Mar'20 Main Street 17/00053/FUL Sessay New permission - June'17 Planning Permission 01/06/2017 1 0 0 0 0 1 0 0 0 1 0 0 1 24/03/2020 No BI record therefore no progress Mar'20 but 2018 (18/01347/PPP) North Yorkshire pre planning enquiry "TheYO7 Snuggle 3BE Up" The Paddock New permission - June'17 Sandhutton Street Named & Numbered - Jul'17 17/00794/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 10/09/2018 North Yorkshire BI Start 19/7/17 YO7 4RW VOA Completion 27/7/18 Survey April 2019 - up 2nd storey , roofs going on - but only outline permisssion 16/01594/OUT Nags Head Pickhill North Reserved Matters approved May'19 18/02627/REM Active 14/06/2017 3 0 3 0 0 3 0 0 0 3 0 0 3 24/03/2020 Note subject to enforcement action Yorkshire YO7 4JG Street Named & Numbered Aug'19 All 3 units stil u/c Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 81 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Howebridge 5 Blakey Lane New permission - 1/8/17 17/00982/OUT Sowerby North Yorkshire Outline 01/08/2017 1 0 0 0 0 1 0 0 0 1 0 0 1 04/12/2019 No Detailed Application submitted up to Dec'19 YO7 1JY

Hope Farm East Sandhutton New Permission - Aug'17 16/02529/OUT Outline 24/08/2017 1 0 0 0 0 1 0 0 0 1 0 0 1 04/12/2019 North Yorkshire YO7 4RW No Detailed Application submitted up to Dec'19

Street Named & Numbered - Jan'19 H Lee And Son Chapel Street 16/01139/FUL Plot 4 - 4 The Squires - completed - 29/3/2019 Thirsk North Yorkshire YO7 Complete 4 4 0 3 0 0 0 0 0 0 0 0 0 16/09/2019 Plot 3 completed May'19 1LU Plot 1 - 1,The Squires CT completion Aug'19 Plot 2 - 2 , The Squires CT completion Jul'19

Seven Lodge Post Office New Permission - Jun'17 - net gain of one unit 17/00624/FUL Lane North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 05/04/2019 BI Plans - Oct'17 Yorkshire YO7 4EP CT Completion Feb'19

Further application - 18/00859/FUL - now 5 Anchor Dykes Station Road dwellings approved Aug'18 17/00807/FUL Street named & Numbered Sep'18 Topcliffe North Yorkshire Active 5 3 2 3 2 0 0 0 0 2 0 0 2 04/12/2019 18/00859/FUL All plots underway Jun'18 YO7 3SQ Plot 5 - Completed Sep'19 3 plots completed by Nov'19

New Permission - Jul'17 Towlers (Thirsk) Ltd 66 - 68 BI Plans - Nov'17 BI Start May'18 17/01104/FUL Market Place Thirsk North Active 4 1 3 0 2 1 0 0 0 3 0 0 3 04/12/2019 Street Named & Numbered Aug'18 Yorkshire YO7 1LW Plot 2 complete - Mar'19 No notified progress since Mar'19

First And Second Floor 85 New Permission - Sep'17 BI plans approved - Dec'17 17/01278/FUL Market Place Thirsk North Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 29/11/2019 BI start - Oct'18 Yorkshire YO7 1ET CT Completion Nov'19

New IPGN Permission - Oct'17 Street Named & Numbered August 2018 Land East Of Bedlam Hill Google maps shows founmdation & access road - 17/00495/FUL Active 5 1 2 0 0 2 2 0 0 4 0 0 4 04/12/2019 Borrowby North Yorkshire summer 2018 Plot 4 started Oct'19,Plot 5 started Jun'19 Plot 1 Completed Mar'19

Street named & Numbered Jan'19 Land Adjacent To 2C 17/01717/FUL Survey May'19 - well on way to 2nd storey Barbeck Thirsk North Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 04/12/2019 Jun'19 - roof on , weather tight this week Yorkshire YO7 1DG Completed Nov'19

Three Tuns Garage Reserved Matters approved Oct'19 - 19/00925/REM 17/01247/OUT Brentwood House Demolition Notice submitted Apr'19 Active 11/10/2019 5 0 4 0 0 2 3 0 0 5 0 0 5 10/03/2020 19/00925/REM Sandhutton North Yorkshire Street Named & Numbered Nov'19 YO7 4RW Four Plots started Dec'19 - No change Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 82 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Call for Sites - T/037/003 ; 17/01872/OUT Land Adjacent Rose Cottage New IPGN Permission - Nov'17 Full permission approved Jul'18 18/00944/FUL Pit Ings Lane Dalton North Post Application Activity 5 0 0 0 0 2 3 0 0 5 0 0 5 04/12/2019 No BI Record Apr'19 Yorkshire Survey 2019 - No start April 2019 Street Named & Numbered Nov'19

New Permission Nov'17 Garages Opposite 26 No progress - Apr'18 Demolition Notice for Garages - 18/00052/DEM - 17/00263/FUL Sowerby Road Sowerby Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 01/04/2019 May'18 North Yorkshire Street named & Numbered Nov'19 CT completion Mar'19

Ingram House 1 Ingramgate 15/01191/FUL Thirsk / The Coach House 1A Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 18/12/2017 Site Completed - August 2017 The Crescent

New Permission - Jan'18 ; Net Gain of 1 7 Station Road Thirsk North 18/00008/DEM - 7 Station Road Thirsk - demolition 17/02253/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 08/03/2019 notice Yorkshire YO7 1PZ Boths Plots started - Mar'18 Plot 1 - 5d Station Road Complete Mar'19

Office Horseshoe Barns Balk 14/01755/JPN Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 12/02/2018 Site Completed - Feb'2018 North Yorkshire YO7 2AQ Outline granted Dec'17 17/01305/OUT Glebe Farm Stockton Road Reserved Matters application validated May'18,approved Sep'18 18/00943/REM South Kilvington North Post Application Activity 2 0 1 0 0 2 0 0 0 2 0 0 2 06/01/2020 BI Initial Notice Nov'18 Yorkshire YO7 2LZ Discharging conditions Feb'19 U/C - scaffolding to 1st storey - Dec'19

Glebe Farm Stockton Road 17/01306/OUT Outline Missed South Kilvington North Detailed Permission 30/04/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 11/12/2019 19/00433/REM No BI Record at Dec'19 Yorkshire YO7 2LZ

The Hollies Main Street Outline granted Jun'18 18/00591/OUT Thornton Le Moor North Outline 07/06/2018 2 0 0 0 0 2 0 0 0 2 0 0 2 11/12/2019 No Detailed Application submitted up to Dec'19 Yorkshire DL7 9DW

Land And Store Chapel 18/00001/FUL Street Thirsk North No BI application - no progress Dec'19 Detailed Permission 1 0 0 0 1 0 0 0 1 0 0 1 10/12/2019 Yorkshire YO7 1LU

"April Folly" BI Application Feb'19 Crosby Lodge (And Land To Street Named & Numbered - Mar'19 17/02613/FUL Active 1 0 1 0 0 1 0 0 0 1 0 0 1 17/12/2019 The Rear) South Otterington BI start Aug'19 North Yorkshire DL7 9HT No more progress Dec'19

OS Field 3146 Maunby Alternative Site : ALT/T/100/001 17/02114/OUT North Yorkshire May'18 decision,Pre Planning Inquiry July'19 Outline 04/05/2018 2 0 0 0 0 2 0 0 0 2 0 0 2 10/12/2019 (19/01492/PPP) No Detailed Application submitted up to Dec'19

Land North East Of 6 School Terrace Carlton Road June 2018 permission 18/00116/FUL Detailed Permission 3 0 0 0 0 3 0 0 0 3 0 0 3 11/12/2019 Carlton Miniott North No Bi Record Dec'19 Yorkshire- Final Vers HDC Hambleton Supply ver019e2 ion - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 83 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15 0 0 0 91/91A Long Street Thirsk Permission for 6 flats , demolition of 2 existing 17/02037/FUL Post Application activity 4 0 0 0 0 4 0 0 0 4 0 0 4 17/12/2019 houses so 4 net gain North Yorkshire YO7 1AS 18/00077/DEM - Demolition of Structures - Sep'18

"Bank Top House" New Permission Aug'18 18/00728/FUL Land Adjacent Swale Lodge Revised application approved Jul'19 Post Application activity 1 0 0 0 0 1 0 0 0 1 0 0 1 25/11/2019 19/00820/FUL Church Street Topcliffe BI Initial Notice Jul'19 North Yorkshire YO7 3PA Street Named & Numbered Aug'19

Maythorne 96 Long Street,Thirsk New Permission Jul'18 18/00736/OUT Outline 20/07/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 24/03/2020 North Yorkshire No Detailed Application submitted up to Mar'20 YO7 1AX Carlton House,Sandhutton 18/01176/OUT Lane New Permission Jul'18 19/01348/FUL Carlton Miniott,North Detailed Permission 10/02/2020 1 0 0 0 0 1 0 0 0 1 0 0 1 24/03/2020 Detailed application - 19/01348/FUL refused Oct'19 19/02630/FUL Yorkshire Later application 19/02630/FUL -approved Feb'20 YO7 4NJ De Mowbray Court Back Lane,Sowerby New Permission Sep'18 18/01412/FUL Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 29/07/2019 Initial BI Notice Nov'18 North Yorkshire,YO7 1ST CT completion Jun'19

Cinquecliff Grange Farm Permitted Development - Farm conversion Oct'18 18/01625/MBN Thirlby North Yorkshire YO7 Permitted Development 02/10/2018 2 0 0 0 0 2 0 0 0 2 0 0 2 24/03/2020 No notified progrtess Mar'20 2EA

Cinquecliff Grange Farm 18/01626/JPN Permitted Development - Farm office to dwelling Thirlby North Yorkshire YO7 Permitted Development 02/10/2018 1 0 0 0 0 1 0 0 0 1 0 0 1 24/03/2020 Oct'18 2EA No notified progrtess to Mar'20

"Furlong Park" Demolition Notice recieved - 18/00105/DEM - on Austin Reed Ltd 1/11/18 BI Initial Notice - 18/21209/IN - Oct'18 18/00331/FUL Station Road,Thirsk Active 26/10/2018 112 13 41 13 28 28 28 15 0 99 0 0 99 24/03/2020 Street Naming & Numbered - Jan'19 North Yorkshire, YO7 1QH Site cleared , foundations started Apr'19 By Mar'20 - 41 u/c, 13 built

Swaletree House Farm Back Works to refurbish and amalgamation of three 18/01858/FUL Lane Kirby Wiske North Active 26/11/2018 -1 0 -1 0 0 0 -1 0 0 -1 0 0 -1 24/03/2020 dwellings into two work started Feb'19 Yorkshire YO7 4EU No change Mar'20

Thornton Printers The Old Change of use and conversion of print works and Drill Hall 22 Chapel Street offices to 2no. residential town houses 18/00917/FUL Detailed Permission 18/12/2018 2 0 0 0 2 0 0 0 0 2 0 0 2 24/03/2020 Thirsk North Yorkshire YO7 No BI record Mar'20 1LU

09/01857/FUL The Works, Chapel Street Complete 5 5 0 0 0 0 0 0 0 0 0 0 0 Two Post Apr'14 completions

R/o 64 - 64a Market Place 10/00351/FUL Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Post Apr'14 completion (Nick Garth Yard)

10/01234/FUL Black Horse Inn Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Completion Mar'15

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 84 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

11/01498/FUL 144 Front Street Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Completion Jun'14

Land To South West Of, 12/00170/FUL Racecourse Mews Complete 6 6 0 0 0 0 0 0 0 0 0 0 0 6x completions Apr'15

12/00603/FUL 64A Market Place Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 2x Completions

12/00843/FUL 1 And 2 Grange Cottages Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x Completion Nov'14

12/01406/FUL 62 Topcliffe Road Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x completion Jun'14

13/00368/FUL Bagby Service Station Complete 2 2 0 0 0 0 0 0 0 0 0 0 0 2x Completions

13/00570/FUL 52 St James Green - 1-8 Complete 8 8 0 0 0 0 0 0 0 0 0 0 0 8x completions Jan'15 Little Green Mews 13/01892/REM Hill Farm Complete 3 3 0 0 0 0 0 0 0 0 0 0 0 1x completion post April 2014 Leake Greens Farm Long 14/01319/FUL Lane Borrowby North Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x completion Jun'15 Yorkshire YO7 4QF 18/0001/YYY Ewelands House Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x CT completion Jan'18 89/0387/EUC Crosskeys Farm, Borrowby Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 1x completion Oct'14 Land North-East Of Kingsley New Permission granted Mar'19 18/02733/OUT Cottage Sinderby North Outline 1 0 0 0 0 1 0 0 0 1 0 0 1 24/03/2020 No detailed application submitted up to Mar'20 Yorkshire YO7 4JD

The Gallery B & B 18 Change of use of bed and breakfast accommodation to residential dwelling 18/02622/FUL Kirkgate Thirsk North Detailed Permission 11/02/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 24/03/2020 New Permission - Feb'19 Yorkshire YO7 1PQ No BI record Mar'20

Demolition of fire damaged dwelling and construction of 2, two bedroom dwellings 18/02395/FUL 54 Long Street Thirsk North Net gain 1;19/00054/DEM - Demolition of Structures Active 1 0 1 0 0 1 0 0 0 1 0 0 1 24/03/2020 Yorkshire YO7 1AU - 13/5/19 Street Named & Numbered May'19 Both plots started Jun'19 -checked Mar'20 still u/c

Notification for prior approval for a proposed Cotcliffe Bank Farm Crosby change of use of an agricultural building to a 18/02735/MBN Active 1 0 1 0 0 1 0 0 0 1 0 0 1 24/03/2020 North Yorkshire dwelinghouse (Class C3) BI Start Apr'19, build progressing Mar'20

Prior Notification for the change of use of a building from an office (Class B1a) to 6no residential St James Lodge Masonic 16/02726/JPN apartments (Class C3 Lane Thirsk North Yorkshire Complete 6 6 0 6 0 0 0 0 0 0 0 0 0 19/12/2019 18/02659/JPN Application renewed Feb'19 YO7 1PS BI Number - 19/01106/IN - Initial Notice - Jan'19 All completed Nov'19

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 85 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Notification for Prior Approval for a proposed Foxhall Farm Knayton North change of use of agricultural building to a 18/02250/MBN Detailed Permission 1 0 0 0 0 1 0 0 0 1 0 0 1 24/03/2020 Yorkshire YO7 4BR dwellinghouse No BI Record Mar'20

Thistle Dhu Sandhutton Conversion of existing steel portal frame building to 18/00006/MBN create a two storey dwelling Lane Carlton Miniott North Active 1 0 1 0 0 1 0 0 0 1 0 0 1 24/03/2020 18/02237/MBN CIL Commencement Notice - 28/6/19, BI Start July Yorkshire YO7 4NH 2019,build still progressing Mar'20

Proposed change of use of an agricultural building into 3 dwellings and asssociated operational West Park Farm Sowerby 18/01740/MBN development Parks Sowerby North Post Application Activity 3 0 0 0 0 2 1 0 0 3 0 0 3 24/03/2020 Discharging conditions Jan'20 18/01740/DCN Yorkshire YO7 3AJ New BI Initial Notice - Jan'20

Notification for proposed change of use of a building First Floor Office 2B Millgate from Office use class B1(a) to a dwellinghouse class 18/02479/JPN Active 1 0 1 0 1 0 0 0 0 1 0 0 1 24/03/2020 C3 Thirsk North Yorks BI start Apr'18, building work ongoing Mar'20

Notification of prior aproval for a proposed change Oxfield Farm Felixkirk North of use of agricultural building to a dwellinghouse 19/00257/MBN Active 1 0 1 0 1 0 0 0 0 1 0 0 1 24/03/2020 Yorkshire YO7 2EF (Class C3) BI start Nov'19,building work ongoing Mar'20

Notification for Prior Approval for a proposed Greystone Flatts Farm change of use of agricultural storage building 18/00434/MBN Borrowby North Yorkshire Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 22/01/2020 (Building 3) to dwellinghouse YO7 4QY Initial BI Notice - 18/17006/IN - accepted Sep'18 BI Completion Jan'20

Wenvoe House Busby Stoop On Maps 010001289554 - Wenvoe House moved 14/00987/JPN Complete 1 1 0 0 0 0 0 0 0 0 0 0 0 from NNDR to CT on 31/7/15 therefore work North Yorkshire YO7 4EQ complete

Skipton Hall Skipton On Alterations and extension to dwellinghouse and 18/01663/FUL outbuildings to form two dwellinghouses Swale North Yorkshire YO7 Post Application Activity 08/04/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 20/00432/PPP Only 1 net gain;New Pre-app received by Mar'20 4SB No BI record Mar'20

Land To The North Of South Outline planning application with details of access 18/00952/OUT Kilvington Church Of (all other matters reserved) for five detached dwellings with associated infrastructure, a car park England VC Primary School Outline 30/04/2019 5 0 0 0 0 5 0 0 0 5 0 0 5 23/03/2020 and a Primary School sports field Stockton Road South No detailed application submitted by Mar'20 Kilvington

Change of use of office accommodation on part of Thirsk Properties 19 Market the first and second floor to form a 2 bedroom 19/00468/FUL Place Thirsk North Yorkshire Post Application activity 21/06/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 residential flat YO7 1HD BI Initial Notice - 19/17168/IN - Oct'19 No further progress Mar'20

1 Craddock Row Sandhutton Construction of a 3 bedroom bungalow 19/00245/FUL Post Application activity 27/06/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 BI Plans conditionally approved - DEC'19 North Yorkshire YO7 4RT No notified progress Mar'20

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 86 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15 Construction of one dwelling and conversion of former agricultural buildings to form three dwellings Southfields Fanny Lane Part of Call for Sites - T/088/002 18/02676/FUL Knayton North Yorkshire Post Application Activity 06/06/2019 4 0 0 0 0 4 0 0 0 4 0 0 4 23/03/2020 No BI Plans submitted Mar'20 YO7 4AS

Black Swan Main Street Alterations and extension to public house and construction of 3 dwellings 16/01871/FUL Thornton Le Moor North Post Application Activity 10/06/2019 3 0 0 0 0 3 0 0 0 3 0 0 3 23/03/2020 Demolition Notice - 19/00105/DEM - Nov'19 Yorkshire DL7 9DN No BI Record Mar'20

Construction of a two storey terraced block of seven Land West Of 8 Mowbray dwellings Houses Carlton Road Broadacres affordable units 18/02084/FUL Active 17/06/2019 7 0 7 0 7 0 0 0 0 7 0 0 7 23/03/2020 Carlton Miniott North Part of "Call for Sites" - T/025/014 Yorkshire Street Named & Numbered Nov'19 All plots started Sep'19,still u/c Mar'20

Topcliffe Methodist Church 19/00579/FUL New permission Jul'19 Church Street Topcliffe Detailed Permission 03/07/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 No BI record uo to Mar'20 North Yorkshire YO7 3PA

Construction of two dwellings and formation of an 19/00791/FUL Ivy House Dalton North access drive Post Application activity 27/07/2019 2 0 0 0 0 2 0 0 0 2 0 0 2 23/03/2020 Yorkshire YO7 3JA Initial Notice - for bungalow - 19/15674/IN - Sep'19 No further progress Mar'20

Agricultural Buildings Adjacent Penhill House Change of use of group of existing agricultural 18/01997/FUL Detailed Permission 31/07/2019 1 0 0 0 0 1 0 0 0 1 0 0 1 23/03/2020 buildings to create a four bedroom family dwelling Fanny Lane Knayton North No BI Application up to Mar'20 Yorkshire

Change of use of former office into a one bedroom 11 Westgate Thirsk North ground floor accessible flat 19/00484/FUL Active 07/05/2019 1 0 1 0 0 1 0 0 0 1 0 0 1 23/02/2020 Yorkshire YO7 1QR BI Start Jul'19 No notified change Mar'20

8 Stammergate Thirsk North 2005 application started but never completed till 05/01854/FUL Complete 1 1 0 1 0 0 0 0 0 0 0 0 0 18/10/2019 Yorkshire YO7 1BD now - BI Completion Oct'19 Land East Of Maythorn Outline Application 19/01483/OUT Cottage Sinderby North Outline 18/10/2019 2 0 0 0 0 2 0 0 0 2 0 0 2 23/03/2020 No Detailed Application submitted by Mar'20 Yorkshire YO7 4JD Land Adjacent To Single Detached Dwelling 19/01770/FUL Stoneydale Cemetery Road Detailed Permission N 1 0 0 0 0 0 1 0 0 1 0 0 1 23/03/2020 No BI record up to Mar'20 Thirsk Former Dispol Uk Ltd Residential development of 14 dwellings 19/01531/FUL Station Road Thirsk North Detailed Permission 03/12/2019 14 0 0 0 3 3 4 4 0 14 0 0 14 03/03/2020 No progress Feb'20 Yorkshire YO7 1QH Land off Frendene, Pit Ings 19/00099/FUL Detailed Permission 14/01/2020 4 0 0 0 2 2 0 0 0 4 0 0 4 22/01/2020 Allowed on appeal Jan'20 Lane, Dalton

Church Farm Sandhutton 19/01980/FUL Detailed Permission 10/01/2020 2 0 0 0 1 1 0 0 0 2 0 0 2 22/01/2020 Conversion of barn to create two dwellings North Yorkshire YO7 4RW

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 87 Annex 8: Housing Supply to March 2020

KEY Pre Application Planning Post Permission - S106/ Active Site Completed Expiry / Outline All active Allocated Sites plus windfall with permission PLUS New Local Plan Proposed Activity Application Street Named & Numbered Deactivated Permission New Local Plan Draft Allocations Allocation Formal Pre-Apps etc. Updated & Checked against PARS to : Mar'20 Windfall Sites with Permission - Thirsk Under Construction Actual Total to be Total Total Totals to Decision Potential Date of LDF / LP Ref.No Site Address Site Status Completions at Completions 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 Built by 2025 Years Years 2035 HDC Notes in Blue & Red Date Capacity Change /from Mar'20 2019/2020 Years 1 - 5 6 - 10 11 - 15 Year 15

Resolution to approve Land Off Topcliffe Road Oct'19 Proposed development for the construction of 97 19/00952/FUL Oct'19 97 0 0 0 0 25 25 25 22 97 0 0 97 28/01/2020 Sowerby North Yorkshire Part of LDF allocation affordable dwellings TM2A Sowerby , Thirsk

Thirsk Totals 676 261 148 52 81 167 89 56 22 415 0 0 415 WINDFALL SITES TOTALS 2137 876 381 197 288 547 306 97 23 1261 0 0 1261

HDC Hambleton Supply ver019e2 - Final Version - 2019-20 -2020-04-08.xlsx HAMBLETON DISTRICT COUNCIL - SHLAA - Mar 2020 - Page No. : 88 ANNEX 9 : - 2019/2020 Notifed Demolitions & Other Losses

Demolition Losses of Planning Date of Notices / CT Residential Location Application No. Notification Comment Notifications Stock

19/00027/DEM - Hambleton District Council Depot 19/00085/FUL 01/04/2019 Demo of structures / depot etc. 1 0 Stillington Road Easingwold 19/00040/DEM - 54 Long Street Thirsk 18/02395/FUL 13/05/2019 Demo damaged dwelling replace 1 0 with two dwellings - only 1 dwelling added to supply This has been accomodated within housing supply spreadsheet

19/00063/DEM - Wilberts Farm Sandhill Lane 15/01240/OUT 14/06/2019 No dwellings on site 1 0 19/00067/DEM - Garages at Silver Street, Sowerby 16/00999/FUL 11/07/2019 Garages only 1 0 via VOA List - Angram Grange,Husthwaite 18/00674/FUL 06/09/2019 via VOA List 21/7/19 - 1 0 replacement dwelling Lambert Medical Centre Thirsk 19/01007/FUL 01/08/2019 This is loss of apartment to D1 use 1 0 - needs confirmation of loss Building Inspector application submitted 19/2/20 - 20/02358/OTH - not started yet

19-00082-DEM - Ewelands House Felixkirk To Ewelands 19/00582/FUL 27/08/2019 Replacement dwelling 1 0 Hill Felixkirk North 19-00083-DEM - Northallerton Tyre And Battery Co 27/08/2019 Non-residential 1 0 Brompton Road Northallerton.pdf Westmoor Farm Green Lane West Sowerby 27/08/2019 Part of Sowerby Phase 3 1 1 19/00093/DEM 18/02032/FUL 16/10/2019 Linked to development of 1 2 1 & 2 The Bungalows Blind Lane Aiskew North Yorkshire carehome facility - 60 bedrooms DL8 but involves relocation from 1BW existing facilities Greenwell House (17) & Bedale Grange (16) 29 bedroom net gain of C2

19/00096/DEM - Motel Leeming Services 86 Bedale 15/02200/REM 21/10/2019 Demo of petrol station 1 0 Road Aiskew North Yorkshire DL8 1DT 19/00098/DEM - Garages 1 - 4 Chapel Garth Dalton No application - 28/10/2019 Demo of Garages 1 0 Thirsk YO7 3HU PPP only 19/00104/DEM - Shorthorn Inn Appleton Wiske 16/00398/OUT 12/11/2019 Demo of Pub - flat tied to pub no 1 0 housing loss 19/00105/DEM - Black Swan Main Street Thornton-le- 16/01871/FUL 12/11/2019 Demo of structures - pub 1 0 Moor alterations & 3 dwellings 19/00110/DEM - Bellwood Cottage Raskelf Road 18/00375/FUL 26/11/2019 Demo of cottage - 12 dwellings , 1 1 Easingwold Daniel Gath Oaklands Sutton Road Huby 11/11/2019 CT Notifcation - replacement 1 0 dwelling Dromonby Grange Farm,Stokesley 18/02061/FUL 31/01/2020 CT Notifcation - replacement 1 0 dwelling 105 High Street Great Ayton 17/01157/FUL 24/02/2020 Dwelling to café - "The Poor 1 1 House" Millhouse 56 North End Hutton Rudby 19/00175/FUL 13/02/2020 Replacement dwelling - no net 1 0 gain 20/00022/DEM - Picton Manor Cottage/The Flat Picton 19/01461/FUL 24/02/2020 Replacement dwelling - no net 1 0 Moor Track Picton TS15 0AF gain 20/00014/DEM - Exelby A19 Services A19 Northbound 09/04149/FUL 13/02/2020 Replacement shop , tank rroom 2 1 0 Services Ingleby Arncliffe 17/01792/MRC fuel stations 19/01411/MRC 20/00012/DEM- Ashwood Danby Wiske Village Street 18/02165/FUL 12/02/2020 Replacement dwelling - no net 1 0 Danby Wiske North Yorkshire DL7 0NQ gain Ewelands House Felixkirk North Yorkshire YO7 2DP / 19/00582/FUL 05/03/2020 Replacement dwelling - no net 1 0 Mowbray Hall - See 05-MAR-2020 CTAX.pdf gain

TOTALS 23 5

Notes : Replacement dwellings are excluded from supply, where 1 unit demolished & extra proposed then only net gain is counted toward supply

89 Annex 10 - Interim Policy Guidance Sites - The Summary in Numbers - 1/4/15 to 17/3/20

Overall the IPGN policy has contributed 459 units to HDC Housing Supply.

Of these 116 (25.2%) are complete,a further 77 (16.8%) are under construction, the remaining 51% (235 units) have no notified start and 31 units have expired. Distribution of IPGN Sites Distribution by Sub-Area

Completions / 75 Bedale Sub-Area Numbers % Starts 139 Bedale 75 16.3% 33 Easingwold Easingwold 131 28.5% 74 Northallerton Northallerton 83 18.1% 24 131 Stokesley Stokesley 31 6.8% 8 31 Thirsk Thirsk 139 30.3% 54 83 District Totals 459 100.00% 193

IPGN Dwellings by Application Type No. of Units by Application Type Application Type Numbers % 3 Outline 104 22.7% Outline Full 224 48.8% 104 128 Full Reserved Matters 128 27.9% Material Change (MRC) 3 0.7% Reserved Matters

District Totals 459 100.00% Material Change 224 (MRC)

House Type Provided (where Known) House Type Provided House Type Number % Detached 234 51.0% Semi-Detached 43 9.4% Detached Terrace / Courtyard 31 6.8% 106 Bungalow 45 9.8% Semi-Detached Flat 0 0.0% 0 45 234 Terrace / Unknown 106 23.1% Courtyard 31 Bungalow 43 District Totals 459 100.00%

Bedroom Size of Units

House Type Number % IPGN Units by Bedroom Size 1 Bedroom 2 0.4% 2 2 Bedrooms 47 10.2% 1 Bedroom 47 3 Bedrooms 148 32.2% 106 2 Bedrooms 4 Bedrooms 135 29.4% 5 & Over Bedrooms 21 4.6% 21 148 3 Bedrooms Unknown 106 23.1% 135 District Totals 459 100.00% 4 Bedrooms

Where bedroom size is known for 353 units just over half (55.8%) are of 1/2/3 bedroom size There are no further details on 106 units which are subject to "Outline" permission

Size of Site Size of Site No.of % Dwellings 53 Single Unit Sites Single Unit Sites 106 23.1% 106 Sites of 2 units 50 10.9% Sites of 2 units Sites of 3 units 55 12.0% Sites of 4 units 52 11.3% 143 50 Sites of 3 units Sites of 5 units 143 31.2% Sites 5 units & over 53 11.5% 55 Sites of 4 units 52 District Totals 459 100.0%

59 units have been given permission on sites proposed under "2016 Call for Sites"

Potential Expiries Potential Expires Expires up to Expires up to March 2020 31 39 31 March 2020 Between March 2020 - 31/3/21 77 Between March Between 1/4/21 - 31/3/22 65 2020 - 31/3/21 54 Between 1/4/22 - 31/3/23 54 77 Between 1/4/21 - After 1/4/23 39 31/3/22 65 Between 1/4/22 - Totals 266 31/3/23

Whilst there are 31 units on sites which have expired up to March 2020 this accounts for 7% of the IPGN total, a further 235 have no start date,however, starts are under reported of the 77 completions , 23 units have no start date , but are Council Tax completions.

90 Source : HDC Planning Policy - March 2020 Annex 11 ‐ Permitted Development ‐ The Summary in Numbers ‐ 1/4/15 to March 2020

Overall Permitted Development has contributed 149 units to HDC Housing Supply.

Of these 82 (55%) are complete,a further 24 (16%) are under construction. In all 71% of Permitted Development units have been built or started.

Distribution of Permitted Development Sites Distribution by Sub‐Area Completions /

Sub‐Area Numbers % Starts 20 Bedale 20 13.4% 12 Bedale Easingwold 23 15.4% 11 Easingwold 69 23 Northallerton17 11.4% 11 Northallerton Stokesley 20 13.4% 16 Stokesley Thirsk* 69 46.3% 56 17 Thirsk* * One application Thirsk accounted for 30 units 20 District Totals149 100.00% 106

Permitted Development Dwellings by Application Type No. of Units by Application Type Application Type Numbers % MBN Agricultural Conve 102 68.5% ‐ MBN ‐ Agricultural IAN ‐ Retail to Residential 1 0.7% Conversion JPN ‐ Office to Dwelling 44 29.5% 44 PPN ‐ Sotorage to Dwellin 2 1.3% IAN ‐ Retail to Residential District Totals 149 100.00% 1 102 JPN ‐ Office to Dwelling

House Type Provided House Type Provided House Type Number % Detached 40 26.8% Semi‐Detached 35 23.5% Terrace / Courtyard 20 13.4% Detached Bungalow 9 6.0% 5 40 Semi‐Detached Flat 40 26.8% 40 Unknown 5 3.4% Terrace / Courtyard Bungalow 9 District Totals 149 100.00% 35 20 Flat

Flats account for 37 units from three JPN applications

Bedroom Size of Units PD Units by Bedroom Size

House Type Number % 10 6 1 Bedroom 38 25.5% 38 1 Bedroom 14 2 Bedrooms 53 35.6% 2 Bedrooms 3 Bedrooms 28 18.8% 3 Bedrooms 4 Bedrooms 4 Bedrooms 14 9.4% 28 5 & Over Bedrooms 6 4.0% 5 & Over Bedrooms Unknown Unknown 10 6.7% 53 District Totals 149 100.00%

In all, 80% of Permitted Development units are smaller ‐ 119 units in 1/2/3 bedroom categories, there are only 20 units with 4 or more bedro There are no further details on 10 dwellings

Size of Site Size of Site No.of 0 Dwellings Single Unit Sites Single Unit Sites 67 36 Sites between 2 ‐ 5 units 46 Sites between 2 ‐ 5 67 units Sites with over 5 units 36 Sites with over 5 units Site size unknown 0 Site size unknown 46 District Totals 149

Source : HDC ‐ Planning Policy ‐ March 2020

91 ANNEX : 12 PLANNING APPEAL STATISTICS

Since the adoption of the LDF Core Strategy in April 2007 there have been 493 submitted appeals.

1 2 6 7

09 10 15 20 0 0 01 01 0 01 01 0 LS 2 2 2 2 2 rage /2 /2014 /2 /2019 /2 %

8 9/ 0/ 3 4 5/ 8 9 TA ve 16/ Numbers 01 01 0 A 2007/2008 200 200 2 2011/ 2012/2013 201 201 2 2 2017/2018 201 201 TO Average

Allowed 14 16 11 13 4 8 12 5 8 6 15 11 18 141 19.0 28.6% Dismissed 38 27 16 28 23 15 20 20 17 32 30 27 32 325 25.0 65.9% Withdrawn 7 4 0 5 1 0 2 1 1 4 0 2 0 272.15.5% Total 59 47 27 46 28 23 34 26 26 42 45 40 50 493 38 100.0%

With about 38 appeals being submitted per year since 2007, nearly three quarters are dismissed or withdrawn, leaving a little over one quarter being allowed.

Of the 50 appeals determined so far during 2019/2020, less than a third, 18 (28.5%), were allowed, 32 were dismissed and 0 appeals were withdrawn.

Allowed Dismissed Withdrawn Partial Approval Total 18 32 0 0 50

Of the 18 appeals allowed, there was only one major residential application for 17 dwellings at Stokesley Road, Northallerton (17/01394/FUL).

Of the remaining 17 appeals which were allowed for minor development, these included 8 residential applications yielding 19 dwellings, 5 householder applications, 2 replacement dwellings.

Of the 32 appeals that were dismissed there were two larger residential schemes for 44 units, these were:

 18/01519/OUT - Stockton Road, Thirsk, North Yorkshire for 34 dwellings  18/00820/OUT – Stillington Road, Huby, North Yorkshire for 10 dwellings

There were 17 smaller schemes accounting for a proposed 34 units also dismissed on appeal.

92 Civic Centre, Stone Cross, Rotary Way, Northallerton, North Yorkshire DL6 2UU 01609 779977 [email protected] hambleton.gov.uk

This information is available in alternative formats and languages

© Communications Unit HDC 2018