96944 Metropolitan Services Improvement Project (NaMSIP) Procurement Plan

I. General The following procurement plan has been developed for project implementation during the period May Public Disclosure Authorized 2015 to April 2016 and provides the basis for the procurement methods and Bank prior/post review thresholds. The plan will be updated when need arises to reflect the actual project implementation needs. It covers the three categories, namely, Works; Consultancies; and Goods. 1. Project information: Country / Borrower: Republic of Project: Nairobi Metropolitan Services Improvement Project (NaMSIP) IDA Credit No. 51020-KE Project Implementing Agencies: Directorate of Nairobi Metropolitan Development

Public Disclosure Authorized (MoNMED), Ministry of Land, Housing, and Urban Development. 2. Bank’s approval Date of the Revised Procurement Plan: April 29 2015 3. Date of General Procurement Notice: 3rd April, 2012 4. Period covered by this procurement plan: May 2015 to April 2016

II Thresholds for Prior Review - after December 4, 2014 Goods, Works, Non Consulting Services, Consulting Services

Public Disclosure Authorized The Table below summarizes the New Risk Based Prior Review Threshold (with effect from January 2015) for which Procurement Decisions are subject to Prior Review by the Bank are as stated in Appendix 1 to the Guidelines for Procurement.

Prior Review Thresholds Procurement Category in current PROCYS Procurement Category Estimated Contract Cost in US Dollars in new Matrix (millions)

Risk Level - Substantial (i) Design, Build & Operate Solid Waste facility Works, Turnkey and

Public Disclosure Authorized (ii) Output and Performance- based Road Contracts S&I of Plant and >=10 (iii) Plant Design, Supply, and Equipment Installation (iv) Works (i) Goods (ii) Health Sector Goods Goods >=1 (iii) Textbooks (i) Information Systems IT Systems, and Non- (ii) Non-Consulting Services >=1 (iii) Procurement of Consulting Services Management Services Prior Review Thresholds Procurement Category in current PROCYS Procurement Category Estimated Contract Cost in US Dollars in new Matrix (millions)

Risk Level - Substantial Consultant Services - Firm Consultant Services >=0.5

Works, Turnkey >=0.1 and S&I of …. All Direct Contracting and Single-Source Goods >=0.1 Contracts with IT Systems….. >=0.1 Consultant (Firms) Consultants >=0.1 Services…..

Consultant Services-Individual Individual Consultants (Single-Source Consultants >=0.1 Contracts)

Individual Consultants (Based on >=0.2 Comparison of CVs)

In addition, all Terms of Reference will be subject to prior review. III Procurement Packages with Methods and Time Schedule (Summary)

A: WORKS

Estimated/ Review Bid Actual Procurement by Bank No Contract Description Status Submission Comments Cost in method (Prior/ & Opening USD Post)

Construction of Sewerage Planned 25,000,000 ICB Prior 5-Nov-12 System (trunk sewer system and W001 reticulation and a waste water treatment plant) Actual 23,476,780 ICB Prior 5-Dec-12 Supply Installation and Commissioning of Street and Planned 1,200,000 NCB Post 14-Sep-14 W002 Security Lighting in , and Ruiru Actual NCB Post 3-Sep-14

Construction of NMT facilities Planned 25,000,000 ICB Prior 16-Nov-15 W003 in the 13 selected urban areas Actual Improvement of Drainage System in storm water drainage Planned 8,500,000 NCB Post 4-May-15 in Nairobi City (Dagoretti, W004 Langata, CBD and Embakasi), Thika (CBD and west of CBD), Mavoko and Actual

township Construction of model fire Planned 5,000,000 NCB Post 16-Jul-15 W005 station in Thika, and Nairobi Actual

Rehabilitation of Power Planned 1,000,000 NCB Post 16-Oct-15 Generation Plant at Chania Falls W006 for Thika Water & Sewerage Actual Company W007 Construction of Kikuyu Road Planned 1,600,000 NCB Prior 1-Feb-14 Estimated/ Review Bid Actual Procurement by Bank No Contract Description Status Submission Comments Cost in method (Prior/ & Opening USD Post)

2km Road leading to Railway Actual 3,100,000 NCB Prior 7-Feb-14 Station Construction/Rehabilitation Planned 1,000,000 NCB Post 16-Nov-15 W008 Works of Market in Ruiru Actual

Construction of loop road Planned 1,000,000 NCB Prior 1-Feb-14 W009 1.6km in Ruiru going past the Ruiru Hospital (see Comp. 3) Actual 1,350,000 NCB Prior 29-Jan-14

Construction of Road Planned 76,000,000 ICB Prior 15-Sep-15 (Tala)-Kenol, Kenol-Kangundo Road (Koma) and Katumani- W010 Road and Rehabilitation of Kenol- Actual Town-Katumani Link Road Construction of 3 Boreholes Planned 400,000 NCB Post 30-Jul-15 W011 within the three fire stations in Actual

Construction of Access Road Planned 6,000,000 ICB Prior 2-Dec-13 W012 and NMT to Imara Daima Railway Station Actual 4,721,686 ICB Prior 10-Dec-13 Rehabilitation of Market in Planned 2,400,000 NCB Post 20-Nov-15 W014 Muthurwa Actual

Rehabilitation of Market in Planned 4,800,000 NCB Post 20-Nov-15 W015 Kangemi Actual

Rehabilitation of Market on Planned 4,800,000 NCB Post 20-Nov-15 W016 Jogoo Road Actual

Rehabilitation of Market in Planned 2,400,000 NCB Post 20-Nov-15 W017 Karandini Actual

Rehabilitation of Outfall Drain Planned 2,000,000 NCB Post 27-Feb-14 W018 and Drainage Infrastructure in Manyani Roads Actual NCB Post 30-Jan-14

Planned 2,200,000 NCB Post 1-Nov-14 Access Road to Railway W019 1,407,305 Station Actual NCB Post 22-Aug-14

Construction of Juja Circuit Planned 1,000,000 NCB Post 15-Jul-15 W020 Road leading to Railway Station Actual (3.5km) (see Comp. 3) Supply Installation and Planned 720,000 NCB Post 14-Sep-14 Commissioning of Street and W021 Security Lighting in Kiambu and Actual 677,778 NCB Post 3-Sep-14 Supply Installation and Planned 700,000 NCB Post 14-Sep-14 Commissioning of Street and W022 Security Lighting in Limuru and Actual 652,222 3-Sep-14 Kikuyu Supply Installation and Planned 270,000 NCB Post 14-Sep-14 Commissioning of Street and W023 Security Lighting in Tala and Mavoko Actual NCB Post 3-Sep-14

Supply Installation and Planned 700,000 NCB Post 14-Sep-14 Commissioning of Street and W024 Security Lighting in , Ngong and Ongata Rongai Actual 713,333 NCB Post 3-Sep-14

Supply Installation and Planned 860,000 NCB Post 14-Sep-14 Commissioning of Street and W025 Security Lighting Lot 1 Nairobi County Actual NCB Post 3-Sep-14 Supply Installation and W026 Planned 440,000 NCB Post 14-Sep-14 Commissioning of Street and Estimated/ Review Bid Actual Procurement by Bank No Contract Description Status Submission Comments Cost in method (Prior/ & Opening USD Post)

Security Lighting Lot 2 Nairobi Actual 560,000 NCB Post 3-Sep-14 County Supply Installation and Planned 620,000 NCB Post 14-Sep-14 Commissioning of Street and W027 Security Lighting Lot 3 Nairobi County Actual NCB Post 3-Sep-14 Construction/Rehabilitation of Planned 1,000,000 NCB Post 16-Nov-15 W028 Market in Ongata Rongai Actual

Construction/Rehabilitation of Planned 1,000,000 NCB Post 16-Nov-15 W029 Market in Juja Actual

Construction/Rehabilitation of Planned 1,000,000 NCB Post 16-Nov-15 W030 Market in Kiambu Actual

Construction/Rehabilitation of Planned 1,500,000 NCB Post 23-Nov-15 W031 Market in Thika (Madaraka) Actual

Construction/Rehabilitation of Planned 1,000,000 NCB Post 23-Nov-15 W032 Market in Actual

Construction/Rehabilitation of Planned 1,500,000 NCB Post 23-Nov-15 W033 Market in Kihara Actual

Construction/Rehabilitation of Planned 2,000,000 NCB Post 30-Nov-15 W034 Market in Kikuyu Actual

Construction/Rehabilitation of Planned 1,000,000 NCB Post 30-Nov-15 W035 Market in Kitengela Actual

Construction/Rehabilitation of Planned 1,000,000 NCB Post 30-Nov-15 W036 Market in Ngong Actual

Construction/Rehabilitation of Planned 1,000,000 NCB Post 04-Dec-15 W037 Market in Tala/Kangundo Actual

Construction/Rehabilitation of Planned 1,500,000 NCB Post 6-Aug-15 W038 Kikuyu Bus Park Actual

Kiambaa Public Parks Planned 61,000 NCB Post 6-Aug-15 W040 Improvement Actual

Rehabilitation of Limuru Planned 1,000,000 NCB Post 28-Sep-15 W041 Sewerage Works Actual Investment in Traffic Management and flow in Thika, Planned 4,000,000 NCB Post 14-Sep-15 W042 Kiambu, , Ongata Rongai and Kitengela towns Actual

Planned 10,000,000 ICB Post 14-Feb-16 W043 IUWM Demonstrative Projects Actual Construction of Imara Daima Planned 1,300,000 NCB Post 04-Dec-15 W044 Footbridge Actual Construction of Makadara Planned 1,800,000 NCB Post 04-Dec-15 W045 Footbridge Actual

Rehabilitation of existing 2 No. Planned 360,000 NCB Post 5-Sep-15 Fire stations along Tom Mboya W046 Street and Enterprise Road in Actual Nairobi County

Construction of NMT Facilities Planned 2,000,000 NCB Post 11-Dec-15 W047 in Nairobi County Actual

Construction Works of Market Planned 2,000,000 NCB Post 11-Dec-15 W048 in Kikuyu Actual

W049 Construction Works of Kikuyu Planned 1,500,000 NCB Post 16-Oct-15 Estimated/ Review Bid Actual Procurement by Bank No Contract Description Status Submission Comments Cost in method (Prior/ & Opening USD Post)

Bus Park Actual

Planned 2,500,000 NCB Post 14-Jul-15 W050 Ruiru Station Quick wins Actual Construction/Rehabilitation Planned 1,500,000 NCB Post 18-Nov-15 W051 Works of Thika (Madaraka) Actual Market Construction Works of Githurai Planned 1,000,000 NCB Post 18-Nov-15 W052 Market Actual

Construction/Rehabilitation Planned 1,000,000 NCB Post 18-Nov-15 W053 Works of Kiambu Market Actual

Construction Works of Kiambaa Planned 1,500,000 NCB Post 27-Nov-15 W054 Market Actual

Improvement to Public Gardens Planned 61,000 NCB Post 16-Oct-15 W055 Kiambu Actual

Construction/Rehabilitation Planned 1,000,000 NCB Post 27-Nov-15 W056 Works of Juja Market Actual

Construction of Juja Circuit Planned 4,000,000 NCB Post 16-Jul-15 W057 Road leading to Railway Station (3.5km) (see Comp. 2) Actual Planned 2,000,000 NCB Post 15-Jun-15 W058 Access to Thika Railway Station Actual Construction of Juja & Thika Planned 42,000,000 ICB Prior 28-Jun-15 Sewerage System (trunk sewer W059 system and reticulation and a Actual waste water treatment plant) Construction/Rehabilitation Planned 800,000 NCB Post 07-Dec-15 W060 Works of Ongata Rongai Market Actual

Construction/Rehabilitation Planned 800,000 NCB Post 07-Dec-15 W061 Works of Kitengela Township Actual Market Construction/Rehabilitation Planned 800,000 NCB Post 07-Dec-15 W062 Works of Ngong Market Actual

Storm Water Drainage Works in Planned 700,000 NCB Post 12-Sept-15 W063 Ongata Rongai Actual

Modern Bus Park in Ngong Planned 350,000 NCB Post 10-Jun-15 W064 Town Actual

Modern Bus Park in Ongata Planned 350,000 NCB Post 10-Jun-15 W065 Rongai Actual

Modern Bus Park in Kitengela Planned 200,000 NCB Post 10-Jun-15 W066 Town Actual

Parking Bays, Bicycles and Planned 200,000 NCB Post 12-Jun-15 W067 Pedestrian Pathways in Ngong Actual Township Parking Bays, Bicycles and Planned 300,000 NCB Post 12-Jun-15 W068 Pedestrian Pathways in Ongata Actual Rongai Township Parking Bays, Bicycles and Planned 500,000 NCB Post 12-Jun-15 W069 Pedestrian Pathways in Actual Kitengela Township Estimated/ Review Bid Actual Procurement by Bank No Contract Description Status Submission Comments Cost in method (Prior/ & Opening USD Post)

Construction of Jua Kali sheds Planned 250,000 NCB Post 15-Jun-15 W070 in Ngong Township Actual

Investments in disaster Planned 120,000 NCB Post 15-Jun-15 W071 preparedness in Mavoko Actual

Construction of storm water Planned 220,000 NCB Post 15-Jun-15 W072 drainage in Mavoko Actual

Bridge and Approaches Planned 1,600,000 NCB Post 19-Jun-15 W073 Construction for Mavoko Quarry Actual Road Investments in disaster Planned 150,000 NCB Post 19-Jun-15 W074 preparedness in Tala/Kangundo Actual

Construction of market in Planned 825,000 NCB Post 14-Dec-15 W075 Tala/Kangundo Actual

Construction of approx. 4Km Planned 2,500,000 NCB Post 10-Jun-15 W076 Road in Tala/Kangundo Actual

Development of selected roads Planned 1,000,000 NCB Post 16-Jul-15 W077 in Muranga Town Actual

Development of selected roads Planned 1,000,000 NCB Post 16-Jul-15 W078 in Kenol Town Actual

Construction of Storm Water Drainage in Nairobi City Planned 10,500,000 ICB Prior 29-Jun-15 (Dagoretti, Langata, CBD and W079 Embakasi), Thika (CBD and west of CBD), Mavoko and Actual Ongata Rongai township) Construction of Kikuyu Planned 8,000,000 NCB Post 15-Jul-15 W080 Sewerage System Actual

Rehabilitation and Construction Planned 1,000,000 NCB Post 15-Jul-15 W081 of Mavoko Sewerage System Actual

Construction of Thika Storm Planned 25,000,000 ICB Prior 27-Jul-15 W082 Water System Actual

Construction of Muhuri Road Planned 6,000,000 NCB Post 15-Jul-15 W083 Nairobi Actual

Construction of 9 composite Planned 2,000,000 NCB Post 7-Sep-15 W084 plants in Nairobi Actual

B: GOODS

Bank Estimated/ Submission of Procurement Review No Contract Description Status Actual Cost bids & Bid Comments Method (Prior/ in USD opening Post)

G001 Purchase of office equipment Planned 30,209 Shopping Post 29-Jul-15 (desktop computer, laptops, camera, scanner) Actual

G002 Purchase of office furniture Planned 29,900 Shopping Post 29-Jul-15 (conference table, desks, chairs, Actual Shopping Post bookshelves) G003 Purchase of fire-fighting Planned 6,000,000 ICB Prior 19-Apr-13 Equipment for existing fire stations in Nairobi and 13

selected urban areas (a) 10,000 Actual 5,147,132 ICB Prior 27-Jun-13 litres 7 No. (b) 5,000 litres 7 No G004A Purchase and Installation of Planned 300,000 NCB Post 22-Oct-15 GIS Equipment and Software at NMED Actual

G004B Purchase and Installation of Planned 300,000 NCB Post 22-Oct-15 GIS Equipment and Software in Selected Counties Actual G005 Purchase of operation vehicles for PCT (6 No. (a) 4x4 double Planned 440,477 NCB Prior 20-Jun-13 cabin pick up 3 No. (b) Utility Vehicles 2 No. and (c) 9 seater mini bus 1 No. Actual 168,151 NCB Prior 26-Jun-13 G006 Purchase of 3 Water Bowsers Planned 400,000 NCB Post 18-Mar-15 to serve the 3 Fire Stations

within Nairobi Actual NCB Post 6-Mar-15 G007 Supply and Delivery of Planned 70,000 NCB Post 4-Mar-15 Vehicles for NCC Project Management Unit (1 No. (a) 4x4 double cabin pick up 1 No. Actual NCB Post 6-Mar-15 and (b) 9 seater mini bus 1 No.) G008 Exhauster Truck for Kikuyu Planned 240,000 NCB Post 13-Jul-15 and Kiambaa (10,000l)

Actual G009 Supply and Delivery of Vehicle Planned 40,000 NCB Post 3-Feb-15 for Project Management Unit (1 No. (a) 4x4 double cabin pick up 1 Actual NCB Post 31-Oct-14 No.) G010 Supply and Delivery of Planned 40,000 NCB Post 3-Feb-15 Vehicles for Project Management Unit (1 No. (a) 4x4 double cabin pick Actual NCB Post 31-Oct-14 up 1 No.) G011 Street Address Supporting Planned 350,000 NCB Post 29-Jun-15 Infrastructure & Equipment for 5 Counties Actual

G012 Supply and Delivery of Vehicle Planned 40,000 NCB Post 3-Feb-15 for County Project Management Unit (1 No. (a) 4x4 double cabin pick up 1 Actual NCB Post 31-Oct-14 No.) G013 Supply and Delivery of Vehicle Planned 40,000 NCB Post 3-Feb-15 for Project Management Unit (1 No. (a) 4x4 double cabin pick up 1 Actual NCB Post 31-Oct-14 No.)

C: CONSULTANCY SERVICES

Estimated/ Review by RFP S Actual Selection Bank Consultancy Description Status submission Comments No. Cost in Method (Prior/ & Opening USD Post)

Planned 180,000 ICS Prior 2-Aug-11 1 Assistant to Program Coordinator Actual 80,974 ICS Prior 6-Sep-11 Planned 450,000 ICS Prior 18-Feb-14 1a Assistant to Program Coordinator Actual ICS Prior 8-Apr-15 Interdisciplinary Land Use and Planned 600,000 QCBS Prior 21-Feb-13 2 Transport Analysis including selected detailed designs Actual 1,353,358 QCBS Prior 11-Sep-13 Carrying out Feasibility Studies and Preparation of Detailed Designs and Planned 230,000 QCBS Prior 26-Nov-13 Tender Documents for Non-Motorized 3 Transport (NMT) Facilities in Area 1 - Nairobi, Tala-Kagundo, Juja, Thika, Ruiru, Kiambu and Karuri within the Actual QCBS Prior 4-Jul-14 Nairobi Metropolitan Region Preparation of feasibility studies, final designs and bidding documents for Planned 500,000 QCBS Prior 20-Oct-11 4 integrated solid waste management and infrastructural development for Nairobi Actual 501,681 QCBS Prior 12-Nov-13 Metropolitan Region Preparation of feasibility studies, final designs and bidding documents for Planned 170,000 CQS Post 31-Oct-11 5 security/street lighting for selected 13 urban centres within the NMR Actual 183,212 CQS Post 22-Nov-11 Preparation of feasibility studies, final designs and bidding documents for Planned 180,000 CQS Post 23-Nov-12 6 disaster preparedness and response systems Actual 187,081 CQS Post 23-Nov-12 Preparation of feasibility studies, final designs and bidding documents for Planned 700,000 QCBS Prior 30-Aug-12 storm water drainage in Nairobi City 7 (Dagoretti, Langata, CBD and Embakasi), Thika (CBD and west of Actual 311,000 QCBS Prior 29-Aug-12 CBD), Mavoko and Ongata Rongai township Preparation of Feasibility Study, Design and Bidding Documents for Energy Planned 150,000 QCBS Post 15-Aug-14 8 Audit in the Five Counties in the Nairobi Metropolitan Region Actual QCBS Post 19-Sep-14

9 Environmental & Social Management Planned 43,000 ICS Prior 1-Feb-11

(Plan) Framework (ESMF) Actual 43,000 ICS Prior 2-Jun-11 Planned 41,250 ICS Prior 9-Jun-11 10 Resettlement Policy Framework Actual 41,250 ICS Prior 13-Apr-11 Planned 44,000 ICS Prior 28-Jan-11 11 Preparation of Operational Manual Actual 44,000 ICS Prior 5-Dec-11 Preparation of waste pickers development plan and its Planned 150,000 ICS Post 1-Nov-15 12 implementation for selected 13 urban centres within the NMR Actual

Analysis of human resources capacity Planned 250,000 QCBS Post 14-Sep-15 13 needs associated with the new county Actual mandates within the NMR Preparation of asset inventory of key basic infrastructure in each of the three Planned 250,000 QCBS Post 5-Nov-15 14 counties, Kiambu, Machakos and Kajiado Actual

Preparation for detailed design of Planned 2,000,000 QCBS Prior 6-Dec-15 15 public infrastructure around commuter rail stations Actual Estimated/ Review by RFP S Actual Selection Bank Consultancy Description Status submission Comments No. Cost in Method (Prior/ & Opening USD Post)

Preparation of a Communications 170,000 ICS Post 17-Oct-12 Strategy for the Nairobi Metropolitan Planned 16 Service Improvement Project (NaMSIP) 166,756 ICS Post 21-Aug-13 Actual Supervision of installation of street Planned 300,000 QCBS Post 7-Oct-15 17 lighting for selected 13 urban centres within NMR Actual Planned 300,000 ICS Post 6-Sep-12 18 Environmental Consultant Actual 35,100 ICS Post 28-Aug-13 Preparation of feasibility studies, final designs and bidding documents for Planned 700,000 QCBS Prior 10-Aug-15 storm water drainage in Kiambu (Juja, 19 Limuru, Ruiru-Gatong’ora and Githurai ), Machakos (Tala and Syokimau), Kajiando (Kitengela and Actual Muranga (Kenol) Preparation of an Integrated Urban Planned 500,000 QCBS Prior 12-Dec-12 20 Water Management Plan for the Nairobi Metropolitan Region Actual 21-Aug-13 Preparation of Revenue Enhancement studies for 4 selected counties Planned 450,000 QCBS Prior 29-Dec-13 21 (Machakos, Kiambu, Kajiado and Muranga) Actual QCBS Prior 1-Aug-14 Carrying out ICT and GIS Needs and ICT Assessment in MoNMED and Planned 400,000 QCBS Prior 8-Sep-12 22 Counties within Nairobi Metropolitan Region (NMR) Actual 389,412 QCBS Prior 4-Dec-13 Consultancy Services for Preparation of Feasibility Studies, Detailed Designs Planned 210,000 QCBS Post 26-Oct-12 and Tender Documentation for 23 Effecting Alternative Traffic Management in Thika, Kiambu, Athi Actual QCBS Post 19-Dec-14 River, Ongata Rongai and Kitengela towns Preparation of Integrated Strategic Urban Development Plans for 12 Planned 3,000,000 QCBS Prior 9-Oct-12 24 Towns in 4 Clusters within the Nairobi Metropolitan Region Actual 1,731,548 QCBS Prior 18-Dec-13

Consultancy for Establishment of a Planned 1,200,000 QCBS Prior 9-Oct-12 25 Physical Street Address System for Nairobi City Actual 1,112,162 QCBS Prior 18-Dec-13

Consultancy on GIS Based Mass Planned 2,000,000 QCBS Prior 8-May-15 26 Valuation System for Nairobi City County Actual QCBS Prior

Consulting Services for Design Review Planned 200,000 QCBS Post 4-Nov-15 27 and Construction Supervision of Kikuyu Sewerage project. Actual Preparation of Feasibility Studies, Planned 300,000 QCBS Prior 5-Sep-13 Development of Project Designs, 28 Bidding Documents and Supervision of Markets in Ongata Rongai, Juja, Actual QCBS Prior 13-Jun-14 Kiambu and Ruiru town. Planned 250,000 ICS Post 2-Mar-13 29 Procurement Consultant Actual 45,500 ICS Post 17-Jul-13 Design Review and Construction Supervision of storm water drainage in Planned 700,000 QCBS Prior 22-Jun-15 Nairobi City (Dagoretti, Langata, 30 Embakasi), Thika (CBD and west of CBD), Mavoko and Ongata Rongai Actual township Consultancy Services for Preparation of 31 Planned 300,000 QCBS Post 4-Oct-15 Feasibility Studies, Detailed Designs, Estimated/ Review by RFP S Actual Selection Bank Consultancy Description Status submission Comments No. Cost in Method (Prior/ & Opening USD Post)

Tender Documents and Supervision of Sewerage System in Ngong Town and Actual Ongata Rongai Preparation of Preliminary and Detailed Engineering Designs, Specifications, Planned 2,250,000 QCBS Prior 14-May-13 Bills of Quantities, Bidding Documents 32 and Carrying out Construction Supervision of Tala-Mombasa Road Actual 2,322,109 QCBS Prior 19-Dec-13 and Kenol-Koma Rock link roads. Consultancy Services on Identification, Planned 300,000 CQS Post 4-Oct-14 Design and Supervision of 33 Rehabilitation Works at the Limuru Actual CQS Post 19-Dec-14 Sewerage Treatment Plant Carrying out Feasibility Studies and Preparation of Detailed Designs and Planned 230,000 QCBS Prior 26-Nov-13 Tender Documents for Non-Motorized 34 Transport (NMT) Facilities in Area 2 - Limuru, Kikuyu, Mavoko, Kitengela, Ngong and Ongata Rongai within the Actual QCBS Prior 11-Jul-14 Nairobi Metropolitan Region. Consultancy for Establishment of a Planned 1,500,000 QCBS Prior 12-Aug-13 35 Physical Address System for Thika, Kiambu and Machakos Actual QCBS Prior 18-Dec-13 Consulting Services for Preparation of Planned 450,000 QCBS Post 4-Oct-15 Feasibility Studies, Detailed Designs and Tender Documents of Sewerage 36 Systems in Kenol Muranga, Ongata Rongai, Ngong, Kitengela (Kajiado), Actual Syokimau (Machakos) and Limuru, Thika North (Kiambu) Consulting Services For Integrated Planned 800,000 QCBS Prior 11-Nov-13 Action Plan for the Preparation of 37 Konza-Kenol-Kangundo-Tala, Komarock-Ruai Actual QCBS Prior 20-Jun-14 Technical Assistance (Urban Sector) for 300,000 ICS Prior 18-Oct-13 the Implementation of World Bank- Planned 38 Financed Projects at the Nairobi City ICS Prior 5-Nov-13 County Actual Consultancy Services for Feasibility Planned 2,000,000 QCBS Prior 25-Oct-13 Study and Formulation of an Urban 39 Renewal Spatial Plan for Nairobi Eastlands Actual QCBS Prior 12-Sep-14 Consulting Services For Preparation of Planned 2,500,000 QCBS Prior 26-Nov-13 Integrated Strategic Development Plan 40 for Muranga and Kiambu Counties within the Nairobi Metropolitan Region Actual QCBS Prior 8-Aug-14 Conducting Environmental & Social Planned 1,000,000 QCBS Prior 27-Nov-13 41 Impact Assessment for NaMSIP Sub- Projects Actual QCBS Prior 27-Apr-14

Technical Assistance for the 300,000 ICS Post 29-Aug-14 Implementation of World Bank- Planned 42 Financed Projects at the Kiambu County ICS Post 2-Dec-14 Actual Preparation of Feasibility Studies, Development of Project Designs, Planned 300,000 QCBS Prior 22-Jan-14 43 Bidding Documents and Supervision of Markets in: i. Thika (Madaraka), ii. Actual QCBS Prior 13-Jun-14 Githurai, iii. Kihara and iv. Kikuyu Preparation of Feasibility Studies, Development of Project Designs, Planned 300,000 QCBS Post 22-Jan-14 44 Bidding Documents and Supervision of Markets in: i. Kitengela, ii. Ngong, iii. Actual QCBS Post 18-Jul-14 Tala/Kangundo and iv. Muthurwa

45 Consulting on RAP on NaMSIP sub- Planned 2,600,000 QCBS Prior 27-Nov-13 Estimated/ Review by RFP S Actual Selection Bank Consultancy Description Status submission Comments No. Cost in Method (Prior/ & Opening USD Post)

projects Actual QCBS Prior 5-Sep-14 Consultancy for Development of a Framework for the Establishment of a Planned 350,000 QCBS Prior 31-Mar-14 46 Solid Waste Management Authority in Selected Counties within the Nairobi Actual QCBS Prior 18-Jul-14 Metropolitan Region (NMR)

Re-Planning the Nairobi Railway Planned 2,500,000 QCBS Prior 8-Jul-15 47 Station and surrounding areas Actual Consultancy Services for Preparation of Feasibility Studies, Detailed Designs, Planned 2,500,000 QCBS Prior 14-Nov-14 Tender Documents and Supervision of 48 Selected Roads and a Green Mall Street Bus Station in the Nairobi Railway Actual QCBS Prior 6-Feb-15 Station and its Surroundings Preparation of Feasibility Studies, Development of Project Designs, Planned 300,000 QCBS Post 17-Nov-14 49 Bidding Documents and Supervision of Markets in: i. Karandini, ii. Jogoo Actual QCBS Post 21-Nov-14 Road, and iii. Kandgemi

Planned 77,500 CQS Post 7-Oct-15 Improvement of Drainage System in 50 Southern Zone for Nairobi County Actual

Improvement of Drainage System in Planned 60,000 CQS Post 7-Jun-15 Southern Zone – Construction 51 Supervision Services for Nairobi Actual County

Supervision of Construction of NMT Planned 60,000 CQS Post 14-Oct-15 52 Facilities in Nairobi County Actual

Consultancy Services to assist the Nairobi City County in developing and Planned 2,000,000 QCBS Prior 14-Aug-15 implementing a 3 “R” and Intermediate 53 Treatment Plan, through promotion of Waste Reduction, Recovery of Actual QCBS Prior Resources, Reuse, Recycling and Intermediate Treatment

Consultancy Services For Design Planned 450,000 QCBS Post 1-Nov-15 54 Review and Works Supervision for Juja and Thika Sewerage Project Actual

Planned 200,000 QCBS Post 1-Nov-15 Consulting Services for Support of 55 Solid Waste Management in Kibera Actual

Consulting Services for Design Review and Construction Supervision of Sewer Planned 100,000 QCBS Post 1-Nov-15 56 Rehabilitation and Extension in Actual Mavoko Preparation of a Storm Water Master Plan, Detailed Designs, Tender Planned 2,000,000 QCBS Prior 10-Aug-15 57 Documents and Operations and Maintenance Manuals for the Nairobi Actual City County

Design Review and Construction Planned 200,000 QCBS Post 1-Nov-15 58 Supervision of Kikuyu Sewerage Works Actual

Consultancy Services for Monitoring & Planned 2,000,000 QCBS Prior 27-Jul-15 59 Evaluation of NaMSIP Projects Actual QCBS