NABARD RIDF XXIV –WSS to Seethathode& area in panchayath of district- Phase II packageI- Laying 508 mm MS raw water pumping main to P, laying 508 mm MS clear water pumping Name of Work main from TP to sump I, sump I to sump II, sump II to sump III, sump III to OHSR at Nilakkal, construction of sumps and OHSR’s, supplying and laying distribution mains, supply and erection of pump sets, transformer substations, automation of pumping systems

This project aiming water supply to Nilackal base camp of , Seethathode panchayath and Plappally, Laha, Attathode, Kisumam and in Perunad panchayath. This package includes Construction of 6.00 LL capacity Sump cum Pump House at Thathakkamani , Sump cum Pump House at S- valavu, in -Plapally Road, 6 LL Sump cum Pump Description House & 3.5 LL OHSR at Plapally, OHSR - 3 nos of 20 LL Capacity each at Nilakkal base camp of Sabarimala,Supplying and Laying 508 mm M.S Clear Water Pumping Mains,Construction of Steel Pipe Bridge for Pumping main ,Automation of Treatment Plant, Pumping stations etc,Supply and erection of Pump Sets,630 KVA Transformer substation at TP site,315 KVA Transormer substations at clear water pump houses, Supplying and laying distribution mains from OHSRs at Nilakkal,Construction of RCC Retaining wall and compound wall for Sumps Administrative Sanction G.O(Rt) No. 107/2019/WRD dated TVPM 21.2.2019 AS Amount (Rs) 1200000000 Technical Sanction TS/2019-20/2018/13798 dt. 27.6.2019 for Rs. 754500000 Agreement No. 9/SE/PHC/TVLA/2019-20 dated 22.11.2019 Name of Contractor Annai Infra Developers Ltd. Accepted PAC 565179165 Site Handing over date 4.12.2019 Duration of Project One year Scheduled date of Completion 21.11.2020 Expected Date of Completion 30.9.2021 Total Bill Submitted (Rs) 69096000 Total Bill Paid (Rs)

PROJECT COMPONENTS 1 Construction of 6.00 LL capacity Sump cum Pump House at Thathakkamani in Angamoozhy- 2 Construction of 6.00 LL capacity Sump cum Pump Houseat S- valavu in Angamoozhy-Plapally Road 3 Construction of 6.00 LL capacity Sump cum Pump House & 3.5 LL OHSR at Plapally 4 Construction of 20 LL Capacity OHSR No.1 Near Devaswam Board Water Tank or BSNL tower 5 Construction of 20 LL Capacity OHSR No.2, Near Palliyarakkavu Devi Temple (Old KSRTC) at 6 Construction of 20 LL Capacity OHSR No.3 Near Cattle shed at Nilakkal 7 Supplying and Laying 508 mm M.S Raw Water Pumping Mains fromWell to TP 8 Supplying and Laying 508 mm M.S Clear Water Pumping Mains from TP to OH tank at Nilackal 9 Construction of Steel Pipe Bridge for Pumping Line 10 Automation of Treatment Plant, Pumping stations etc, 11 Supply and erection of Pump Sets, 630 KVA Transformer substation at TP site,315 KVA Transormer 12 Supplying and laying distribution mains from OHSRs at Nilakkal 13 Construction of RCC Retaining wall and compound wall for Sump 1,Sump 2 & Sump 3 between Issues

Wild trees at boosting stations are not auctioned and removed by forest department, Road cutting 16.12.2020 permission from PWD not obtained for laying RWPM from Seethathode well to TP and for laying CWPM from Seethathode TP to Angamoozhy and from Plappally to Nilackal. DAILY WORK PROGRESS Date Works Remarks Pipeline laid- today 60 m, total 1714 m, For piling of OH tank near BSNL tower 17.12.2020 reached machineries

508 mm MS pipe supplied- 8764 m, Lining of MS pipe completed- 2556.00 m, Earth work excavation of pipe line between Angamoozhy and Plappally road- 1938 m, 16.12.2020 Pipeline laid- 1654 m, Pressure tested- 479.50 m, OH tank near Palliyarakkavu temple at Nilackal- Excavation for footing in progress, OH tank near BSNL tower at Nilackal- Existing water supply line of TDB shifted and realigned, OH tank near Cattle shed at Nilackal- Submitted design for approval, Boosting stations- Soil investigation done, SCADA - Casing pipe laid along with pipeline Pipe line laid- Today 74.00 m, total 1788.00 m, OH Tank near BSNL Tower - (1). 18.12.2020 Primary setting out of pile points completed. (2). Bar bending started.