PROPOSALS FOR THE APPROACH TO AND THE SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT AND ENVIRONMENTAL STATEMENT IN SUPPORT OF THE DEVELOPMENT CONSENT ORDER APPLICATION UNDER THE PLANNING ACT 2008 FOR THE DIVERSION OF THE RAILWAY AT WHITWELL QUARRY, DERBYSHIRE
Report reference: LAF/WT/SPS/1550/02 July 2010
Baddesley Colliery Offices, Main Road, Baxterley, Atherstone, Warwickshire, CV9 2LE Tel. (01827) 717891 Fax. (01827) 718507
pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
CONTENTS
1. Introduction
2. Description of the quarrying activities at Whitwell Quarry
3. Planning history of the operations at Whitwell Quarry
4. The proposed operations
5. The scope of the Environmental Impact Assessment
6. The structure of the Environmental Statement
TABLES
Table 1 Summary of the work undertaken as part of the ROMP application and work that will be undertaken for the DCO application for the railway diversion
FIGURES
Figure 1 Site location (drawing reference LAF/WT/11-09/15265)
Figure 2 Boundary of the Whitwell Quarry Complex (drawing reference LAF/WT/07-10/15654)
Figure 3 Plan showing the planning consent boundaries and limits of extraction (drawing reference LAF/WT/10-09/15244)
Figure 4 Plan showing the land ownership boundaries (drawing reference LAF/WT/07-10/15664)
Figure 5 Proposed Development Consent Order application boundary (drawing reference LAF/WT/07-10/15662)
Figure 6 Proposed development details (drawing reference LAF/WT/07-10/15663)
LAF/WT/SPS/1550/02 i July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
APPENDICES
Appendix A Consultation bodies under the Infrastructure Planning
(Environmental Impact Assessment) Regulations 2009
Appendix B Copy of the ROMP conditions (Code No: R5/0705/13)
Appendix C Copy of the ROMP submission dated July 2005
Appendix D Proposed contents list of the Environmental Statement
LAF/WT/SPS/1550/02 ii July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
1. Introduction
1.1 Whitwell Quarry complex operated by Lafarge Aggregates Limited is located in
Derbyshire approximately 20m south of Whitwell village and 300m north east of
Creswell (Figure 1). The site includes the main quarry, the northern extension
together with five additional extensions, a processing plant area and Whitwell Lime
Works located to the east of the main workings. The whole quarry site occupies
approximately 204ha. The northern part of the site is crossed by the Robin Hood
Railway Line that runs between Nottingham and Worksop. The railway runs
through a tunnel at the site (Figure 2). The high purity dolomitic limestone extracted
at the quarry is burnt in the kilns of the lime works for use in refractory products and
steel manufacture. There are only two quarries in the UK that produce limestone
which is suitable for these specialist uses and both quarries are recognised sources
of national importance of the mineral. Limestone present at the quarry which is not
suitable for use in the kilns is used principally to produce agricultural lime and
aggregates.
1.2 The quarrying activities at the site are the subject of a Review of Old Mineral
Planning Permissions (ROMP) consent which includes the diversion of the section
of the Robin Hood Railway that runs through the site. The Environment Act 1995
introduced the requirement for Mineral Planning Authorities (MPA) to undertake an
initial review and update of all mineral planning permissions granted between
30 June 1948 and 22 February 1982 and thereafter to operate a programme of
periodic review of minerals planning permissions more than 15 years old. This
process allows the MPA to ensure that conditions attached to mineral planning
permissions remain up to date and relevant. The ROMP consent for the site
LAF/WT/SPS/1550/02 1 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
includes conditions relating to the quarrying of the mineral resource around and
forming the railway tunnel.
1.3 In order to extract the mineral resource around and forming the railway tunnel it is
necessary to divert the railway. The permanent diversion of the railway is subject to
the provisions of the Planning Act 2008 and a Development Consent Order (DCO)
application shortly will be submitted in accordance with the Act. The proposed
development is a Schedule 2 development under the Infrastructure Planning
(Environmental Impact Assessment) Regulations 2009 and as the proposals have
the potential for environmental impacts it is considered likely that an Environmental
Impact Assessment is necessary to accompany the DCO application.
1.4 MJCA are commissioned by Lafarge Aggregates Limited to undertake the
Environmental Impact Assessment for the diversion of the railway in support of the
DCO application. The purpose of this scoping document is to explain the
background to the development and to set out the proposed scope for the
Environmental Impact Assessment. The objective of this scoping exercise is to
agree the approach to and the scope of the Environmental Impact Assessment and
Environmental Statement which will accompany the DCO application. Based on the
Environmental Impact Assessment an Environmental Statement will be prepared in
accordance with the Infrastructure Planning (Environmental Impact Assessment)
Regulations 2009.
1.5 In accordance with the Regulations which prescribe the bodies who must be
consulted as part of the Environmental Impact Assessment process a list of
consultees with whom it is suggested that this scoping report and the Environmental
Statement is circulated is presented at Appendix A. The list of consultees includes
LAF/WT/SPS/1550/02 2 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
those meeting the definition of ‘consultation bodies’ under Regulation 2(1) of the
Regulations together with other relevant local stakeholders.
LAF/WT/SPS/1550/02 3 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
2. Description of the quarrying activities at Whitwell Quarry
2.1 Quarrying at the site commenced in 1958. The majority of the area of the quarry to
the south of the railway tunnel has been excavated and is occupied by backfilled
quarry waste and kiln dust together with aggregate stockpiles (Figure 2). The
majority of the mineral to the north of the railway tunnel has been extracted and the
remainder will be quarried to a standoff of 40 yards from the tunnel. The standoff
will be maintained to protect the trains and train users under current arrangements.
2.2 In the five extensions to the main quarry extraction has been completed in the north
western extension, the south eastern and north eastern extension areas are
partially extracted and extraction operations have commenced in the southern
extension. It is anticipated that extraction will commence in the eastern extension
later in 2010.
2.3 Approximately 1.1 million tonnes of dolomitic limestone is extracted from Whitwell
per annum. Whitwell Quarry is one of only two quarries in the UK at which high
quality dolomitic limestone is extracted and processed hence the quarry is of
recognised national importance. The site produces materials used in refractory
applications for use in the steel and iron manufacturing industry, and all fines
generated at the end of the process are sold and used for agricultural applications.
Dolomite is also used for the manufacture of glass. Rotary kilns are used at the
Lime Works to manufacture various grades of dolomite product by burning the rock
at high temperatures.
2.4 Variation in chemical composition and hardness of dolomite and dolomitic limestone
and product requirements means that in order to provide an appropriate blend of
stone quarrying takes place at several faces concurrently. The faces generally are
LAF/WT/SPS/1550/02 4 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
worked in three benches by drilling and blasting. The top two benches are
generally suitable for kiln feed and the bottom bench is suitable for use as
aggregate. Extracted aggregate grade material is crushed, screened and graded
before it is transported from site.
2.5 The main reserves remaining in the Main Quarry comprise the reserves associated
with the railway tunnel. In accordance with the ROMP and associated agreed
schemes careful blasting and monitoring has resulted in agreement for the
extraction of mineral up to 40 yards from the outer face of the tunnel. In order to
extract the remaining 3.9Mt of mineral located close to and beneath the tunnel it is
necessary to divert the section of the railway that runs through the tunnel in
accordance with the scheme which is approved through the ROMP. In accordance
with the approved scheme it is intended that the railway is diverted to the south of
the current route as shown on Figure 2.
LAF/WT/SPS/1550/02 5 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
3. Planning history of the operations at Whitwell Quarry
3.1 Planning consent reference CLO/1156/3 granted on 5 March 1957 permitted the
extraction of limestone from land south of the railway line and includes the plant
site. On 27 November 1984 planning consent reference BOL/1082/484 was issued
for the extraction of mineral across and to the north of the railway. Planning
permission reference CM5/598/7 for five extensions of the quarry comprising areas
north east, north west, east, south and south east of the quarry was granted on 7
July 2004. As shown on Figure 3 the 2004 consent does not include the entire area
the subject of the 1957 and the 1984 consents. In particular the 2004 consent does
not include the aggregates plant and lime works or the area around the railway
tunnel.
3.2 In accordance with the provisions of the Environment Act 1995 it was necessary for
Derbyshire County Council to review the conditions of the 1957 and 1984 consents
for Whitwell. An Environmental Statement in support of the ROMP was submitted
to Derbyshire County Council in July 2005. The conditions for the ROMP were
issued on 7 July 2006 (Code No R5/0705/13).
3.3 In February 2006 an application supported by an Environmental Statement was
submitted for permission to operate without compliance with Condition 10 of the
planning permission Code No: CM5/598/7 to vary the working sequence of the
approved quarry extension area to enable earlier working of the south eastern and
north eastern extension areas and planning permission CM5/0206/178 for the
revised extraction sequence and timing was granted on 23 October 2006. The
boundaries of the planning consents for the site together with the associated
LAF/WT/SPS/1550/02 6 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
extraction boundaries are shown on Figure 3 and the land ownership at and around
the site is shown on Figure 4.
3.4 The extraction and restoration operations at the site are currently controlled by
Code No R5/0705/13 and planning permission reference CM5/0206/178. The
operations in the ROMP area which include the current railway line land together
with the land for the proposed diversion are controlled by Code No R5/0705/13. A
copy of the ROMP conditions is presented at Appendix B to this report.
3.5 Condition 9 of Code No R5/0705/13 states that:
‘Scheme of operations: The progressive extraction of minerals
(including working the railway tunnel area) and restoration of the site
shall be carried out in accordance with the details in Part II and plan
reference LAF/WT/05-05/12212 (Figure 7) and the phased
operations specified at Appendix M and in the ‘Romp Working Detail’
Plans Phases A to L inclusive of the submitted Environmental
Statement, except as otherwise required by other conditions to this
permission, or such variations as may otherwise have received prior
written approval of the Mineral Planning Authority in consultation with
Network Rail.’
Note 5(b) of the notes to applicants states that:
‘5(b) Network Rail: Advice and Requirements Relating to the
Proposed Railway Diversion
i) The permanent diversion of a railway is subject to the
provisions of the Transport and Works Act 1992 and an
LAF/WT/SPS/1550/02 7 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
application for the proposed diversion should be made at an
early stage.
ii) To achieve the proposed alignment of the diversion, within
acceptable safety tolerances, Network Rail may require the
alteration and/or reconstruction of the existing rail
overbridges.
iii) The proposed diversion must be constructed in accordance
with Network Rail specifications for all aspects of the works
including linespeed, levels, alignment, gauge, signalling etc.
iv) All existing railway crossings, connections and rights must be
maintained.
v) A possible alternative to diverting the railway to be considered
by Network Rail and Lafarge Aggregates, could be to
maintain the existing alignment of the railway and remove the
tunnel during a blockade with subsequent working of the new
cutting sides.
3.6 The ROMP ‘Working Detail Plans’ show the phases of the extraction of the mineral
from the area the subject of the ROMP together with the diversion of the railway to
facilitate extraction of the mineral from the tunnel and beneath the tunnel. The
Environmental Impact Assessment which was carried out to support the ROMP
included an assessment of environmental impacts associated with the diversion of
the railway and the extraction of the mineral at and around the tunnel.
LAF/WT/SPS/1550/02 8 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
4. The proposed operations
4.1 The proposed quarry operations to accommodate the railway diversion are shown
in detail on Drawings A to L inclusive in the ROMP application and the principles of
the approach will remain the same as proposed in the ROMP application presented
at Appendix C to this report. As at early 2010 the quarry is working close to the
circumstances depicted in Plan C in that series. Rock will be worked to a position
as close to the tunnel as is possible by conventional means comprising drilling,
blasting and haulage by dump truck. Working towards the tunnel is a continuous
process which will be carried out in close liaison with Network Rail entailing detailed
blast design and extensive monitoring of ground vibrations generated by blasting
activity.
4.2 On the south side of the tunnel the working face in the lower level of rock in the
quarry will be stopped at a position 80 metres from the centre line of the tunnel in
order to allow the future rail diversion line to be created on undisturbed rock. The
upper kiln feed faces will continue to be worked towards the tunnel subject to the
controls referred to above.
4.3 At a point of approach where conventional quarry working provides insufficient
control and predictability for the proximity to the tunnel, rock will continue to be
worked either by a substantially altered blasting regime involving much smaller
weights of explosives or by mechanical means involving a rock planer. Rock over
the top of the tunnel will certainly be worked using a planer. This technique is
proven and widely used in surface mines around the world and has been used
successfully at Whitwell in order to create the underpass in the south eastern part of
the quarry beneath the public road on the eastern boundary.
LAF/WT/SPS/1550/02 9 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
4.4 When the body of rock around the tunnel has been minimised an underpass will be
created from the south through the rock-bench on which the railway will run. The
railway line will then be put in place as described below and made operational.
Rock surrounding the now disused tunnel will be worked by conventional means
where possible, subject to safety monitoring and inspection processes agreed with
Network Rail in respect of the diverted line. The rock from around the tunnel will be
transported through the underpass beneath the diverted line to the quarry
processing plant.
4.5 The primary stages of diverting the railway will be as follows:
1. The surface of the native rock platform will be prepared.
2. A bridge will be constructed over the quarry underpass.
3. Rail ballast will be placed over the major section of new line length with the
exception of the connection areas.
4. Rail tracks will be laid over the major central section of diversion
accompanied by appropriate signalling infrastructure.
5. A second volume of ballast will be placed between the slopes and temped
in place.
6. Short line possessions of typically less than 24 hours will be secured to
enable connection at each end of the new route to the existing route.
7. Rail traffic will immediately operate on the new line.
8. The disused tunnel will be sealed to prevent trespass and to prevent
colonisation by bats and other protected species.
LAF/WT/SPS/1550/02 10 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
9. Demolition of the tunnel lining and removal of the old rails will commence
in accordance with a scheme agreed with Network Rail.
10. Remaining rock will be worked until the rock faces are in their final
positions.
11. A water drainage network will be established for the restored land on either
side of the diverted railway and linked as necessary into track bed
drainage.
4.6 During working of the portals and once the railway is diverted on to the lower bench
there is a risk of fly rock associated with blasting. The risk of fly rock is minimised
by standard blasting procedure and blasting away from the sensitive receptor. A
stone protection bund will be constructed between the quarry face and the railway.
As a precaution it is proposed that Lafarge Aggregates Limited will organise
blasting times to ensure that blasting does not take place when the line is in use.
The Company will communicate with the signal box to ensure that no trains pass
during blasting. Netting will be installed on the portal cutting faces and rock trap
fences will be constructed along the edge of the railway. An inspection of the line
will be undertaken after blasting to ensure that there are no obstructions or damage
prior to confirming with the signal box that train traffic may be released.
4.7 The boundary of the Development Consent Order application area is shown on
Figure 5 together with the proposed line of the diverted railway. A limit of deviation
of 25m either side of the diverted railway is shown for most of the length. More
detailed design drawings of the proposals for the diversion of the railway will be
included in the plans and sections for the DCO application and in the Environmental
Statement as appropriate.
LAF/WT/SPS/1550/02 11 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
4.8 The footpaths in the vicinity of the DCO application area are shown on Figure 5.
Footpath 20 runs around the southern edge of the western railway tunnel portal and
then runs along the line of the railway tunnel. Footpath 74 runs around the northern
edge of the western railway tunnel portal and joins FP20 at the top of the tunnel.
Footpath 72 joins FP20 to the east of the eastern railway tunnel portal and runs
parallel with the railway for a short distance before turning to the north west. In
accordance with the ROMP it will be necessary to divert and temporarily stop up
footpaths FP20 and FP74. The application for temporarily stopping up and
diversion of the footpaths will form part of the DCO application. The approximate
route of the diverted footpath following completion of the works is shown on
Figure 6.
LAF/WT/SPS/1550/02 12 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
5. The scope of the Environmental Impact Assessment
5.1 A full Environmental Impact Assessment (EIA) accompanied the ROMP submission
in July 2005. A copy of the ROMP submission is presented at Appendix C to this
scoping report. As explained in section 4 of this report the EIA for the ROMP
included the assessment of the environmental impacts associated with the
extraction of the mineral around the tunnel and the mineral in the northern area of
the quarry and detailed working schemes were submitted showing the proposed
route for the diversion of the railway. The findings of the EIA were accepted by the
Planning Authority and the ROMP was issued. It is considered that the majority of
the environmental impact assessments that were carried out as part of the ROMP
EIA remain valid and it is not necessary to repeat the valid assessments that were
undertaken as part of the ROMP EIA submission.
5.2 The ROMP EIA has been reviewed to identify the issues that are relevant to the
railway diversion, to confirm the environmental impact assessments that were
carried out as part of the EIA and to determine their current validity. Gaps in the
assessment of the environmental impacts associated with the diversion of the
railway as part of the ROMP EIA have been identified. It is considered that the EIA
necessary for the DCO application will comprise the ROMP EIA together with
additional environmental impact assessments which are identified as necessary.
5.3 The baseline environment of the quarry is well established and is described in the
ROMP EIA. Where it is considered that the relevant baseline has changed
materially since the ROMP EIA was carried out the changes have been identified in
this scoping review. The environmental issues which it is necessary to review are
blasting and vibration, noise, water resources, ecology and landscape and visual
LAF/WT/SPS/1550/02 13 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
impact. A summary of the relevant aspects of the work undertaken as part of the
Environmental Impact Assessment that accompanied the ROMP application is
presented in Table 1.
Blasting and vibration
5.4 As part of the ROMP EIA a detailed blasting and vibration impact assessment was
undertaken with regard to the impact of blasting on the railway tunnel and the
surrounding area as the proposed scheme of working progressed. The impact
assessment report is summarised at Section 22 and presented at Appendix O2 of
the ROMP submission. Section 8 of R5/0705/13 includes conditions in relation to
the control of explosives. Condition 37 of R5/0705/13 relates to blasting at Whitwell
Tunnel and Condition 38 of R5/0705/13 relates to the monitoring of ground vibration
and air overpressure. The continued operations at the quarry will be carried out in
accordance with these conditions.
5.5 The ROMP EIA did not include an assessment of the impacts of vibration resulting
from the removal of the tunnel on the diverted railway and on the slopes of the
proposed cutting, overbridge and underpass including the potential impacts of
flyrock. It will be necessary to review the impacts from vibration associated with the
diverted railway and tunnel removal activities on the quarry operations and the
nearest sensitive properties. As part of the additional EIA assessments will be
undertaken to establish the impacts resulting from vibration and flyrock and where
necessary special protective measures or mitigatory schemes will be identified and
their impact will be assessed.
LAF/WT/SPS/1550/02 14 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
Dust
5.6 As part of the ROMP EIA a semi quantitative dust impact assessment was
undertaken and is presented at Section 23 of the EIA. The dust assessment
includes the whole ROMP area including the tunnel area and the proposed route for
the diverted railway and a dust action plan is presented at Appendix K1 to the
ROMP submission. Specific dust prevention and control measures are outlined in
Condition 28 of R5/0705/08. Operations at the site will continue to be undertaken in
accordance with the dust control schemes specified in the planning consent for the
five extensions and the ROMP. It is considered that it is not necessary for any
further assessments to be carried out of the environmental impacts associated with
dust.
Noise
5.7 The noise impact assessment summarised in Section 24 and presented at
Appendix J1 of the ROMP EIA included the effect of noise generated from the day
time, night time and temporary operations at the site. The activities included in the
noise assessment are activities associated with the mineral extraction operations
such as rock drilling and blasting together with the loading and transportation of
material within the quarry, limestone processing, concrete batching and placement
of kiln dust together with temporary operations such as soil and overburden
stripping, the stockpiling of material, mound formation and final restoration. The
noise assessment in the ROMP EIA does not include the impacts associated with
the noise generated by the diversion of the railway line, the removal of the tunnel
and the diverted railway. The impact of noise on the users of the railway is not
assessed.
LAF/WT/SPS/1550/02 15 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
5.8 As part of the additional EIA it will be necessary to assess the impact of noise from
the diversion works and from the diverted railway on nearby dwellings and to
assess the impacts of noise on railway users. In order to ensure that appropriate
background noise data are used it is proposed that background noise monitoring is
undertaken at up to 5 potentially noise sensitive locations surrounding the site over
a representative period during the daytime, evening and night time as necessary to
cover all periods when trains are likely to run. Wherever possible all measurements
will be undertaken in accordance with BS 7445: 2003. A noise assessment will be
carried out to determine the impact of the realignment of the railway line on nearby
sensitive receptors taking into consideration the fact that a section of the line will no
longer be screened by the tunnel. The assessment will consider the additional
quarrying operations in the footprint of the tunnel. The predicted noise levels will be
assessed against the noise limits in the current planning permission together with
the relevant standards. On-site noise monitoring will be carried out to determine
noise levels from the current plant and operations and will determine typical noise
levels from passing trains at a suitable location on the Nottingham to Worksop Line.
Water resources
5.9 As assessment of the impact of quarrying on water resources was undertaken and
summarised at Section 25 and presented at Appendix H of the ROMP EIA. The
effects of the quarrying and restoration works on the quality of surface water, the
effects of dewatering on the flow in the watercourses, the effects on groundwater
quality and effects on groundwater abstractions are all assessed. Section 9 of
R5/0705/13 includes conditions with respect to the protection of water quality,
quarry discharge strategies and the monitoring of flows in the surrounding
watercourses. As these conditions will continue to be applicable for the duration of
LAF/WT/SPS/1550/02 16 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
the operations at Whitwell Quarry it is considered that it is not necessary to assess
further the impacts on water resources as part of this submission.
5.10 It is considered that an assessment of the impacts on surface water drainage
associated with the diverted railway route will be necessary in the additional EIA.
Following the restoration of the quarry the diverted railway route will comprise a
cutting and it will be necessary to ensure that appropriate surface water drainage is
provided to manage the surface water runoff from the adjacent restored areas
together with the groundwater which will be drained through the underpass which
will run below the diverted railway. It is proposed that the principles only of the
drainage scheme are presented in the designs and the EIA and that detailed
drainage designs and capacity calculations will be carried out at the detailed design
stage once the DCO order has been granted.
Soil resources
5.11 The remaining soil resources in the ROMP area were assessed as part of the
ROMP EIA. The report of the assessment is presented at Appendix G and
summarised at Section 26 of the ROMP EIA. Condition 59 of R5/0705/13 specifies
the methodology that will be used for stripping, storing and placing the soils at the
site. This condition is applicable to the proposed diversion route together with the
area of the tunnel. The proposed diversion route was stripped of soil prior to the
commencement of quarrying operations. The soils located above the tunnel area
will be stripped in accordance with the approved methodology. It is considered that
it is not necessary to assess further soil resources.
LAF/WT/SPS/1550/02 17 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
Ecology
5.12 Ecological surveys and an ecological impact assessment were undertaken as part
of the ROMP EIA. The results of the survey are summarised at Section 27 and
presented at Appendix F1 of the ROMP EIA. The ecological surveys and the
assessment presented in the ROMP EIA cover the area that is likely to be affected
by the proposal to divert the railway line. As the ecological surveys were
undertaken in 2004 for the ROMP submission it is considered that it is necessary to
undertake a site walkover to update the Phase 1 habitat survey and land use map.
The site walkover will include an assessment of the habitat for protected and BAP
species and a search for signs of use by such species, relevant to the season. The
2004 data will be updated particularly with regard to bats. Should the survey
identify any potential issues which need further investigation the relevant surveys
will be undertaken.
5.13 There is one Local Wildlife Site at the western railway tunnel portal. The location of
the Butchers Wood Railway Site is shown on Figure 5. The impacts of the
development on Butchers Wood were assessed in the ROMP application and the
loss of the calcareous grassland will be mitigated in the overall restoration of the
quarry. Based on the site walkover ecological survey an assessment will be made
of whether there have been any changes since the ROMP EIA was undertaken and
any additional impacts or mitigation measures that are necessary.
5.14 The main issue that will be assessed in the additional EIA will comprise the
potential use of the tunnel by roosting or hibernating bats. There is a small
probability that the tunnel is used currently by bats and it is possible that the tunnel
will be used by bats once trains no longer are running in the tunnel but before it is
LAF/WT/SPS/1550/02 18 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
removed. At Whitwell the potential for the presence of bats potentially is particularly
significant given the proximity of the site to Creswell Crags and the known
importance of the Crags for bats. Dusk and dawn bat swarming will be monitored
around the tunnel portals. Swarming occurs mainly in autumn but also in spring
around intended hibernation sites.
5.15 The results of the ecological impact assessment presented in the ROMP EIA will
be updated and amended where necessary to reflect changes in the baseline
ecology or additional habitats or protected species that are now present in the areas
associated with the railway diversion. Any mitigation measures that are considered
necessary with regard to the diversion of the railway or the tunnel removal will be
presented and assessed.
Landscape and visual impact
5.16 A landscape and visual impact assessment was undertaken as part of the ROMP
EIA. The assessment is summarised at Section 28 and presented at Appendix E of
the ROMP EIA. The landscape and visual impact assessment considered the
landscape and visual impacts associated with the removal of the tunnel together
with the diversion of the railway to the proposed alignment. As the landscape and
visual impact assessment was undertaken in 2004 it is considered that it is
necessary to determine whether the baseline against which the assessment was
carried out has changed and to update the impact assessment where necessary.
For the additional EIA the relevant local receptors and site vegetation and features
will be reviewed and the assessment of the impact of the removal of the tunnel and
diversion of the railway will be carried out where necessary.
LAF/WT/SPS/1550/02 19 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
Transport network
5.17 A transport and traffic impact assessment was undertaken as part of the ROMP EIA
and is summarised at Section 29 and presented at Appendix D1 of the ROMP EIA.
The diversion of the railway will not result in any change in the number of vehicle
movements including the proposals for the importation of track ballast. The vehicle
movements associated with the extraction of the mineral from the tunnel area are
included in the transport assessment undertaken as part of the ROMP EIA. It is
anticipated that following construction of the diverted railway line it will be necessary
for the railway line to be closed overnight on two weekends to make the
connections from the current line to the diverted line. The closure on each weekend
will be from 10pm on Saturday until 10am on Sunday. The impact of this closure on
railway users will be assessed in the Environmental Impact Assessment. It is
considered that it is not necessary to carry out any further assessment of the impact
on the transport network.
Archaeology
5.18 An assessment of the impact on the archaeological heritage at and in the vicinity of
the site was undertaken as part of the ROMP EIA and is presented at Appendix L1
and summarised at Section 30 of the ROMP EIA. The majority of the ROMP area
except for the railway line has already been extracted and any notable
archaeological features found have been recovered. It is stated in Section 30 that it
is likely that any further archaeological material in the ROMP area is of low priority.
Under Condition 49 of R5/0705/13 it is stated that all development shall be
undertaken in compliance with the implementation of a programme of
archaeological work in accordance with the written scheme of investigation dated
LAF/WT/SPS/1550/02 20 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
10 July 2003 which is presented at Appendix L2 and L3 of the ROMP submission.
Appendix L2 is the scheme that is relevant to the railway tunnel area. In the scheme
it is stated that a watching brief must be conducted when soil stripping is
undertaken. If archaeological or associated palaeoenvironmental remains are
discovered that warrant further work additional steps will be undertaken. The
potential impacts on archaeology due to the diversion of the railway are assessed in
the ROMP EIA therefore no additional assessment is necessary.
Alternatives
5.19 The alternatives to the proposal for the railway diversion are addressed at Section
20 of the ROMP EIA. The alternatives relate to alternative sources of the mineral.
It is stated that there are no known new sites that could supply the unique mix of
products which are manufactured from the stone at Whitwell. It is not considered
necessary to undertake any further assessment of alternatives with respect to the
availability of the mineral.
5.20 It is proposed that alternative layouts for the line of the diverted railway are
assessed in the Environmental Statement.
Conclusions
5.21 The Environmental Statement that will be submitted with the DCO application will
comprise the Environmental Statement submitted with the ROMP application
together with the additional environmental impact assessments that are identified as
necessary in this scoping report. The additional environmental impacts that will be
assessed will relate to the identified aspects of vibration, noise, surface water
drainage, ecology and landscape and visual impact as presented in Table 1.
LAF/WT/SPS/1550/02 21 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
Summaries of the assessments undertaken for the ROMP application will be
presented where necessary and a complete copy of the Environmental Statement
that accompanied the ROMP submission will be provided as an Appendix.
LAF/WT/SPS/1550/02 22 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
6. The structure of the Environmental Statement
6.1 The proposed contents list for the Environmental Statement which will accompany
the DCO application is presented at Appendix D. The Environmental Statement
which accompanied the ROMP together with detailed technical reports in support of
the submission will be presented as appendices to the Environmental Statement. A
summary of the Environmental Statement in non-technical language will be
produced.
6.2 The Environmental Statement will comprise three parts. Part 1 of the
Environmental Statement will provide an introduction to the proposals together with
a detailed description of the current planning permissions at the site. The approach
to the Environmental Statement will be outlined together with a summary of the
scoping responses. The site location will be described including the properties,
populations and public rights of way in the vicinity of the site.
6.3 In Part 2 a description of the current and proposed operations at the quarry together
with the development proposals will be presented. In Part 3 the baseline conditions
for the detailed assessments will be described to define the environmental context
of the site. Sufficient detail will be provided to facilitate the assessment of the
impacts.
6.4 The text will be supported by plans. The plans that will be presented will include an
up to date topographical survey of the quarry and the land in the immediate vicinity
of the quarry, plans showing the working scheme for the area together with the
detailed design drawings for the proposed railway diversion.
LAF/WT/SPS/1550/02 23 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
TABLES
LAF/WT/SPS/1550/02 July 2010 pl14014.doc LAFARGE AGGREGATES LIMITED WHITWELL RAILWAY DIVERSION
Table 1
Summary of the work undertaken as part of the ROMP application and work that will be undertaken for the DCO application for the railway diversion
Assessment Blasting and Landscape and Transport Dust Noise Water resources Soil resources Ecology Archaeology Alternatives What was vibration Visual Impact network covered Assessed in the ROMP
A detailed blasting and A semi An assessment of vibration impact An assessment quantitative dust An assessment of An assessment of Phase 1 habitat A landscape and the impact on the assessment was with regard to impact the impacts of the remaining survey was visual assessment A transport and archaeological What was undertaken with Operations in the alternative assessment was quarrying on soils within the undertaken was undertaken traffic assessment heritage at and in assessed? regard to the ROMP area. sources of the undertaken for water resources ROMP area was across the whole for the ROMP was undertaken. the vicinity of the impact of blasting mineral was the ROMP was undertaken. undertaken ROMP area area site was on the railway assessed. operations. undertaken. tunnel and the surrounding area.
Did the baseline The report cover the tunnel covered the N/A N/A and proposed tunnel area only. diverted route?
Did the The report assessment cover covered the x N/A N/A the removal of the tunnel area only. tunnel?
Did the assessment cover x x x x x N/A N/A the diverted line? Necessary work Blasting and Dust Noise Water resources Soil resources Ecology Landscape and Transport Archaeology Alternatives vibration Visual Impact network It will be No additional It is necessary to It is considered No additional It is necessary to It is necessary to The closure of the No additional No additional necessary to assessment is assess the that an assessment is undertake a determine whether railway for a short assessment is assessment is review the necessary. impact of the assessment of the necessary. Phase 1 habitat the baseline time to connect necessary. necessary with impacts from diversion works impacts on survey together against which the the diverted line respect to the vibration on the nearest surface water with autumn and impacts were will be assessed sources of the associated with sensitive drainage spring emergence assessed has in terms of impact mineral. the diverted receptors associated with surveys for bats changed and on the users of railway and tunnel together with the the diverted update the the railway removal activities impacts on railway route will assessment where network. An assessment in the quarry railway users be necessary. necessary. will be carried operations and during the works out of the the nearest and after the The assessment alternative sensitive railway has been will include the layouts for the properties diverted. impact on footpath diverted railway. together with the users of the potential impacts footpath diversion from flyrock. proposals.
LAF/WT/SPS/1550/02 1 July 2010 pl14014 table 1.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
FIGURES
LAF/WT/SPS/1550/02 July 2010 pl14014.doc N
0m 500 1000 1500 2000 2500m
Key / Notes
Approximate boundary of Whitwell Quarry Complex Final KR SPS LH 28/07/10 Draft KR SPS LH 06/11/09
Rev Status Drn App Chk Date
Site WHITWELL QUARRY Client
Title Site location
Figure 1 Scale 1:50,000@A4 Drawing Ref LAF/WT/11-09/15265 Baddesley Colliery Offices, Reproduced scale mapping by permission of Ordnance Main Road, Baxterley, Atherstone, Warwickshire, CV9 2LE. Survey R on behalf of The Controller of Her Majesty's Telephone : 01827 717891 Stationery Office. C Crown copyright 2006. All rights reserved. Technical advisers on environmental issues Fax : 01827 718507 Licence number 100017818. N
0m 100 200 300 400 500m
Key / Notes
Approximate boundary of Whitwell Quarry Complex Final KR SPS LH 29/07/10 Draft KR SPS LH 21/07/10 Proposed railway diversion Rev Status Drn App Chk Date
Site WHITWELL QUARRY Client
Title Boundary of the Whitwell Quarry Complex
Scale Figure 2 1:10,000@A3 Drawing Ref LAF/WT/07-10/15654 Baddesley Colliery Offices, Reproduced scale mapping by permission of Ordnance Main Road, Baxterley, Atherstone, Survey R on behalf of The Controller of Her Majesty's Warwickshire, CV9 2LE. Telephone : 01827 717891 Stationery Office. C Crown copyright 2006. All rights reserved. Technical advisers on environmental issues Fax : 01827 718507 Licence number 100017818. N
North Northern area eastern Phase 2a Phase 2b extension
North western extension Phase 1
Eastern extension
Main Quarry
South eastern extension
Southern extension
0m 100 200 300 400 500m
Key / Notes
Boundary of the land the subject Boundary of the land the Boundary of the land the of the ROMP permission subject of planning consent subject of planning consent Final KR SPS LH 28/07/10 R5/0705/13 dated 7 July 2006 reference BOL/1082/484 reference CM5/0206/178 dated 27th November 1984 dated 23 October 2006 Draft KR SPS LH 06/11/09 (The Northern Extension, Rev Status Drn App Chk Date Boundary of the land the subject Phase 1 and Phase 2) of planning consent reference Extraction limit the subject Site CLO/1156/3 dated 5th March of planning consent WHITWELL QUARRY 1957 (The Main Quarry) Extraction limit the subject reference CM5/0206/178 Client of planning consent dated 23 October 2006 reference BOL/1082/484
Extraction limit the subject of dated 27th November 1984 Title planning consent reference (The Northern Extension, Plan showing the planning consent boundaries CLO/1156/3 dated 5th March Phase 1 and Phase 2) and limits of extraction 1957 (The Main Quarry)
Scale Figure 3 1:10,000@A3 Drawing Ref LAF/WT/10-09/15244 Baddesley Colliery Offices, Reproduced scale mapping by permission of Ordnance Main Road, Baxterley, Atherstone, Survey R on behalf of The Controller of Her Majesty's Warwickshire, CV9 2LE. Telephone : 01827 717891 Stationery Office. C Crown copyright 2006. All rights reserved. Technical advisers on environmental issues Fax : 01827 718507 Licence number 100017818. 11 line of posts line of posts 108
376100N 5 15
11
21 87.2m
12 24 116 BRIDGE CLOSE
El 1
Sub 2
N Sta
Whitwell FP20 Whitwell Whitwell FP18 Whitwell BM Whitwell FP72 90.82m Gas Gov 376000N
Southfield Villas
FP65 1 Whitwell Whitwell FP73
Ep Ep Ep Ep MP 150.5 Ep
SANDY LANE Whitwell FP20 Ep Ep Ep Ep
Ep Ep Ep 8
Ep 375900N
Ep
Ep Ep Whitwell Ep FP72 Ep
Ep
375800N P L A N T I N G
geo 4
Whitwell FP20
375700N P L A N T I N G
BM BM 7 7 3
NO.8
375600N
10.5 Existing Railway Line and Tunnel 2
3654
375500N
GEO
BM Whitwell FP18 BM 6 0.91m RH Ward Bdy
Whitwell FP74 375400N
FW
3636
Er Whitwell FP20 BM 5LC Er 9 5 BM 0.91m RH
EXPLOSIVE STORE
Und PHASTLIME BUILDING
Def 375300N
8 SUMP
Elmton FP3 6
375200N
Elmton FP1 FINES TIPPING 10
375100N FINES TIPPING
33
4108
A 616 SP
BM 82.12m MP 149.75 4500 5200
375000N Allotment Gardens 453200E 82.0m Ward Bdy A 616 4500 0m 25 50 75 100 125m Def 452400E 452500E 452600E 452700E 452800E 452900E 453000E 453100E Allotment
Key / Notes
OWNERSHIPS Lafarge Aggregates Limited FH - Surface & 10 Owned by Welbeck 5 Mineral Welbeck Estates Surface & Mineral Surface Lease only to Lafarge Aggregates Limited 1 Part tenanted by Mr M Palmer Ownership boundaries Final KR SPS GT 29/07/10 Option to Purchase Surface issued to Lafarge Remainder tenanted by Mr S J Carr Aggregates Limited from Welbeck Estates Rev Status Drn App Chk Date 6 Agricultural tenancy in place with Mr S J Carr. Footpaths Lafarge Aggregates Limited have the right to Lafarge Aggregates Limited FH - Surface Site pass to rail undertaker. WHITWELL RAILWAY DIVERSION Welbeck FH Mineral - Leased to Lafarge 2 Client Aggregates Limited Tenant Mr M Palmer Pt0491 Chatsworth Surface & Welbeck Mineral leased 7 to Lafarge Aggregates Limited Tenant Mr M Palmer Pt2560 Lafarge Aggregates Limited FH - Surface Title Welbeck FH Mineral - Leased by Lafarge Plan showing the land ownership boundaries 3 Aggregates Limited Network Rail Part tenanted by Mr M Palmer 8 Note: Figure 4 Scale 9 Lower Mill Farm. Owned by Chatsworth Footpaths taken from Derbyshire Partnership Mapping 1:2,500@A2 4 Surface owned by EMDA Portal V3.2 Drawing Ref LAF/WT/07-10/15664
Baddesley Colliery Offices, Reproduced scale mapping by permission of Ordnance Survey R Main Road, Baxterley, Atherstone, on behalf of The Controller of Her Majesty's Stationery Office. Warwickshire, CV9 2LE. Telephone : 01827 717891 C Crown copyright 2006. All rights reserved. Licence number Technical advisers on environmental issues Fax : 01827 718507 100017818. 11 line of posts line of posts 108
376100N 5 15
11
21 87.2m
12 24 116 BRIDGE CLOSE E:452500
El 1 Sub 2
N Sta
Whitwell FP20 Whitwell Whitwell FP18 Whitwell BM Whitwell FP72 90.82m Gas Gov 376000N
Southfield Villas
FP65 Whitwell Whitwell FP73
Ep Ep Ep Ep MP 150.5 Ep
SANDY LANE Whitwell FP20 Ep Ep Ep Ep
Ep Ep Ep
Ep 375900N
Ep
Ep Ep Whitwell Ep FP72 Ep
Ep
375800N P L A N T I N G
geo
Whitwell FP20
375700N P L A N T I N G
BM BM 7
NO.8
375600N
Existing Railway Line and Tunnel10.5
Railway Diversion (Indicative only)
375500N
GEO
BM Whitwell FP18 BM 6 0.91m RH Ward Bdy
Whitwell FP74 375400N
FW
Er
BM 5 LC Er Whitwell FP20 BM
0.91m RH
EXPLOSIVE STORE
Und PHASTLIME BUILDING
Def 375300N
SUMP
Elmton FP3
375200N
Lower Mill Farm
Elmton FP1 FINES TIPPING
375100N FINES TIPPING
33
4108
A 616 SP
BM 82.12m MP 149.75 4500 5200
375000N Allotment Gardens 453200E 82.0m Ward Bdy A 616 4500 0m 25 50 75 100 125m Def 452400E 452500E 452600E 452700E 452800E 452900E 453000E 453100E Allotment
Key / Notes
Proposed Development Consent Order application boundary Final KR SPS GT 29/07/10
Footpaths Rev Status Drn App Chk Date
Site Butchers Wood Railway WHITWELL RAILWAY DIVERSION Local Wildlife Site Client
Limit of deviation Title Proposed Development Consent Order application boundary
Note: Scale Figure 5 Footpaths taken from Derbyshire Partnership Mapping 1:2,500@A2 Portal V3.2. Drawing Ref LAF/WT/07-10/15662
Baddesley Colliery Offices, Reproduced scale mapping by permission of Ordnance Survey R Main Road, Baxterley, Atherstone, on behalf of The Controller of Her Majesty's Stationery Office. Warwickshire, CV9 2LE. Telephone : 01827 717891 C Crown copyright 2006. All rights reserved. Licence number Technical advisers on environmental issues Fax : 01827 718507 100017818. 11 line of posts line of posts 108
376100N 5 15
11
21 87.2m
12 24 116 BRIDGE CLOSE
El 1
Sub 2
N Sta
Whitwell FP20 Whitwell Whitwell FP18 Whitwell BM Whitwell FP72 90.82m Gas Gov 376000N
Southfield Villas
FP65 Whitwell Whitwell FP73
Ep Ep Ep Ep MP 150.5 Ep
SANDY LANE Whitwell FP20 Ep Ep Ep Ep
Ep Ep Ep
Ep 375900N
Ep
Ep Ep Whitwell Ep FP72 Ep
Ep
375800N P L A N T I N G
geo
Whitwell FP20
375700N P L A N T I N G
BM BM 7
NO.8
375600N
10.5
Existing Railway Line and Tunnel
3654 Proposed Underpass
Railway Diversion (Indicative only) 375500N
GEO
BM Whitwell FP18 BM 6 0.91m RH Ward Bdy
Whitwell FP74 375400N
FW
3636
Er
BM 5LC Er Whitwell FP20 BM
0.91m RH
EXPLOSIVE STORE
Und PHASTLIME BUILDING
Def 375300N
Proposed Footbridge SUMP
Elmton FP3
375200N
Elmton FP1 FINES TIPPING
375100N FINES TIPPING
33
4108
A 616 SP
BM 82.12m MP 149.75 4500 5200
375000N Allotment Gardens 453200E 82.0m Ward Bdy A 616 4500 0m 25 50 75 100 125m Def 452400E 452500E 452600E 452700E 452800E 452900E 453000E 453100E Allotment
Key / Notes
Proposed Development Consent Order application boundary Final KR SPS GT 29/07/10 Footpaths Rev Status Drn App Chk Date
Site Disturbed footpaths WHITWELL RAILWAY DIVERSION Client
Final diverted route of the footpath
Title Proposed development details
Scale Note: Figure 6 1:2,500@A2 Footpaths taken from Derbyshire Partnership Mapping Drawing Ref Portal V3.2. LAF/WT/07-10/15663
Baddesley Colliery Offices, Reproduced scale mapping by permission of Ordnance Survey R Main Road, Baxterley, Atherstone, on behalf of The Controller of Her Majesty's Stationery Office. Warwickshire, CV9 2LE. Telephone : 01827 717891 C Crown copyright 2006. All rights reserved. Licence number Technical advisers on environmental issues Fax : 01827 718507 100017818. LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
APPENDICES
LAF/WT/SPS/1550/02 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
APPENDIX A
CONSULTATION BODIES UNDER THE INFRASTRUCTURE PLANNING (ENVIRONMENTAL IMPACT ASSESSMENT) REGULATIONS 2009
LAF/WT/SPS/1550/02 July 2010 pl14014.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
APPENDIX A
CONSULTATION BODIES UNDER THE INFRASTRUCTURE PLANNING (ENVIRONMENTAL IMPACT ASSESSMENT) REGULATIONS 2009
Note: This first list is taken from Schedule 1 of The Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009. Where consultees listed in Schedule 1 to the Regulations are not relevant to this application they are shown as struck out. The second list is of the local authorities specified in section 43 of The Planning Act 2008. The third list is of additional relevant local stakeholders.
Column 1: Consultee Column 2: Circumstances when that person must be consulted about a proposed application The Welsh Ministers All proposed applications likely to affect land in Wales The Scottish Executive All proposed applications likely to affect land in Scotland The relevant Northern Ireland All proposed applications likely to affect land Department in Northern Ireland Responsible Regional Authority All proposed applications likely to affect land in England and Wales
East Midlands Development Agency and East Midlands Leaders’ Board The Health and Safety Executive All cases The relevant Strategic Health All proposed applications likely to affect land Authority in England and Wales
East Midlands Strategic Health Authority The relevant Health Board(18) All proposed applications likely to affect land in Scotland Natural England All proposed applications likely to affect land in England The Historic Buildings and All proposed applications likely to affect land Monuments Commission for England in England The relevant fire and rescue authority All cases Derbyshire Fire and Rescue Authority The relevant police authority All cases Derbyshire Police Authority The relevant parish council, or, where All cases the application relates to land Wales or Scotland the relevant community Whitwell Parish Council council Elmton with Creswell Parish Council
LAF/WT/SPS/1550/01 1 July 2010 pl14014consultees.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
Column 1: Consultee Column 2: Circumstances when that person must be consulted about a proposed application The Environment Agency All proposed applications likely to affect land in England and/or Wales The Scottish Environment Protection All proposal applications likely to affect land Agency in Scotland The Commission for Architecture and All proposed applications likely to affect land the Built Environment in England The relevant Regional Development All cases Agency East Midlands Development Agency The Equality and Human Rights All proposed applications likely to affect land Commission in England and Wales The Scottish Human Rights All proposed applications likely to affect land Commission in Scotland The Commission for Sustainable All cases Development AONB Conservation Boards All proposed applications likely to affect an AONB that is managed by a Conservation Board Royal Commission on Ancient and All proposed applications likely to affect the Historical Monuments of Wales historic environment in Wales The Countryside Council for Wales All proposed applications likely to affect land in Wales The Homes and Communities Agency All proposed applications likely to have an effect on its areas of responsibility The Joint Nature Conservation All proposed applications likely to affect the Committee marine environment The Commission for Rural All proposed applications likely to affect Communities rural communities in England Scottish Natural Heritage All proposed applications likely to affect land in Scotland The Maritime and Coastguard Agency All proposed applications likely to affect the maritime or coastal environment, or the shipping industry The Marine and Fisheries Agency All proposed applications likely to affect the marine area in England and Wales The Scottish Fisheries Protection All proposed applications likely to affect the Agency fisheries industry in Scotland The Civil Aviation Authority All proposed applications relating to airports or which are likely to affect an airport or its current or future operation
LAF/WT/SPS/1550/01 2 July 2010 pl14014consultees.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
Column 1: Consultee Column 2: Circumstances when that person must be consulted about a proposed application The Highways Agency All proposed applications likely to affect road or transport operation and/or planning on roads for which the Secretary of State for Transport is the highway authority. Integrated Transport Authorities All proposed applications likely to affect (ITAs) and Passenger Transport transport within, to or from the relevant Executives (PTEs) integrated transport area of the ITA or PTE South Yorkshire ITA and South Yorkshire PTE The relevant Highways Authority All proposed applications likely to have an impact on the road network or the volume of traffic in the vicinity of the proposal Transport for London All proposed applications likely to affect transport within, to or from Greater London The Passengers Council All proposed applications likely to affect rail (now Passenger Focus) passenger transport or road passenger transport services or facilities The Disabled Persons Transport All proposed applications likely to affect Advisory Committee access to transport for disabled people The Coal Authority All proposed applications that lie within areas of past, present or future coal mining. The Office of Rail Regulation and All proposed applications likely to affect the approved operators rail transport industry Network Rail Infrastructure Ltd Network Rail (CTRL) Ltd The Gas and Electricity Markets All proposed applications likely to affect gas Authority and electricity markets The Water Services Regulation All proposed applications likely to affect the Authority water industry in England and Wales The Water Industry Commission of All proposed applications likely to affect the Scotland water industry in Scotland The relevant waste regulation All proposed applications likely to affect authority waste infrastructure The relevant internal drainage board All proposed applications likely to increase the risk of flooding in that area or where the proposals relate to an area known to be an area of flood risk The British Waterways Board All proposed applications likely to have an impact on inland waterways or land adjacent to inland waterways
LAF/WT/SPS/1550/01 3 July 2010 pl14014consultees.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
Column 1: Consultee Column 2: Circumstances when that person must be consulted about a proposed application Trinity House All proposed applications likely to affect navigation in tidal waters The Health Protection Agency All proposed applications likely to involve chemicals, poisons or radiation which could potentially cause harm to people The relevant local resilience forum All cases
Derbyshire Local Resilience Forum Relevant statutory undertakers All proposed applications likely to affect their functions as statutory undertakers Central Networks (in respect of an overhead line crossing the application site) The Crown Estate Commissioners All proposed applications likely to impact on the Crown Estate The Forestry Commission All proposed applications likely to affect the protection or expansion of forests and woodlands
Local authorities specified in section 43 of the Planning Act 2008
Districts/Boroughs East Staffordshire Bolsover Staffordshire Moorlands Rotherham Stockport Bassetlaw Tameside Mansfield Oldham Ashfield Amber Valley Counties/Unitaries North East Derbyshire Derbyshire Chesterfield Nottinghamshire High Peak Leicestershire Derbyshire Dales Staffordshire South Derbyshire Cheshire East Erewash Derby Kirklees Barnsley Sheffield Broxtowe Rushcliffe North West Leicestershire National Parks Lichfield Peak District National Park
LAF/WT/SPS/1550/01 4 July 2010 pl14014consultees.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
Other relevant stakeholders who it is recommended should be consulted Consultee Contact details
Whitwell Quarry Liaison Committee Mr P Stubbs Derbyshire County Council Shand House Darley Dale South Matlock DE4 3RY Mr W G Elliott Clerk to Elmton with Creswell Parish Council The Social Centre Elmton Road Creswell Clowne Derbyshire Mr R Slaney Whitwell Parish Representative 13 Fox Road Whitwell Worksop S80 4SA Mrs P Richardson Parish Representative 52 Wood Avenue Creswell Worksop S80 4EG Cllr S Smith Elmton with Creswell Parish Council 17 West Street Creswell Worksop S80 4DT Principal Environmental Health Officer (Commercial) Bolsover District Council Sherwood Lodge Bolsover Chesterfield S44 6NF Cllr D McGregor Bolsover District Council 31 Eyre Street Creswell Worksop Notts Cllr Ken Stevenson Derbyshire County Council 5 Claylands Place Bakestone Moor
LAF/WT/SPS/1550/01 5 July 2010 pl14014consultees.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
Other relevant stakeholders who it is recommended should be consulted Consultee Contact details
Whitwell Worksop S80 4QS Cllr V Mills Bolsover District and Whitwell Parish Councils 27 Sunnyside Whitwell Worksop S80 4SR Mr B Woodcock Clerk to Whitwell Parish Council Whitwell Community Centre The Square Whitwell Worksop S80 4QR Cllr R Turner Bolsover District Council 106 Elmton Road Creswell Worksop Mr Gerald Plant Creswell Parish Representative Woodbourne Bungalow Wood Lane Creswell Worksop S80 4EA Miss V Webb Derbyshire County Council Shand House Darley Dale South Matlock DE4 3RY Creswell Heritage Trust Crags Road Welbeck Nr Worksop S80 3LH
Tel: 01909 720378 Welbeck Estate Mr E T Tennant Coke Turner & Co The Millyard Rowsley Matlock DE4 2EB Chatsworth Estate Mr E T Tennant Coke Turner & Co The Millyard
LAF/WT/SPS/1550/01 6 July 2010 pl14014consultees.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
Other relevant stakeholders who it is recommended should be consulted Consultee Contact details
Rowsley Matlock DE4 2EB Limestone Journeys Crags Road Welbeck Nr Worksop S80 3LH
E-mail: Limestone.journeys@creswell- crags.org.uk Tel: 01909 720378 South Yorkshire & North East Derbyshire Secretary – Mr David Gadd Area Ramblers 5 Wong Lane Tickhill Doncaster DN11 9NH
E-mail: [email protected] Tel: 01302 745611 Peak and Northern Footpath Society Taylor House 23 Turncroft Lane Offerton Stockport SK1 4AB
Tel: 0161 480 3565 Network Rail John McCormick Senior Commercial Scheme Sponsor Floor 4a George Stephenson House Toft Green York
Tel: 01904 383161 E-mail: [email protected] Derbyshire Wildlife Trust East Mill Bridge Foot Belper Derbyshire DE56 1XH
Tel: 01773 881188 Steetley Dolomite Limited Southfield Lane Whitwell Worksop Nottinghamshire S80 3LJ
Tel: 01909 726100
LAF/WT/SPS/1550/01 7 July 2010 pl14014consultees.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
Other relevant stakeholders who it is recommended should be consulted Consultee Contact details
Network Rail Consultees Adrian Caltieri Head of Operations Development East Coast East Coast House 27 Skeldergate York YO1 6DH Andy Wylie Track Access Manager First Group Rail division 131-151 Great Titchfield Street London W1W 5EB James Shuttleworth West Coast Railway Company Steamtown Warton Road Carnforth LA5 9HX Kevin Crane Track Access & Performance Manager First GB Railfreight 11 Goodman Close Great Gonerby Grantham NG31 8PX Matthew Crump Train Planning Manager Serco Railtest Ltd West Wing Derwent House Railway Technical Centre Business Park, London Road Derby DE24 8UP Pawel Nowak Rail Network Manager DB Schenker Rail (UK) Limited Wembley Depot Pendolino Way London NW10 0RP Peter Hoare Operations Standards Manager Balfour Beatty Rail Services Manor Lane Hither Green London SE12 0UA
LAF/WT/SPS/1550/01 8 July 2010 pl14014consultees.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
Other relevant stakeholders who it is recommended should be consulted Consultee Contact details
Simon Taylor Head of Train Planning and Access East Midlands Trains Midland House Nelson Street Derby DE1 2SA Andrew McCall Rail Standards Manager Colas Rail Plant Depot Mill Road Rugby Warwickshire CV21 1BE Andrew Wijeyewardena Track Access Manager Freightliner Heavy Haul Ltd 3rd Floor, The Podium 1 Eversholt Street London NW1 2FL Chris Hext Safety & Standards Director Grant Rail Carolina Court Lakeside Doncaster DN4 5RA Lanita Masi Track Access and Network Change Manager East Midlands Trains Midland House Nelson Street Derby DE1 2SA Nigel Walker Rail Plant Manager Carillion Rail Rail Plant Depot Mill road Rugby CV21 1BE Steven Alderson Operations Manager DfT Rail Service Delivery 3/33 Great Minster House 76 Marsham St London SW1P 4DR
LAF/WT/SPS/1550/01 9 July 2010 pl14014consultees.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
Other relevant stakeholders who it is recommended should be consulted Consultee Contact details
Robin Nelson Train Planning Manager Freightliner Ltd The Podium 1 Eversholt Street London NW1 2FL Tom Jones (email only) Senior Rail Strategist Freightliner Group Basford Hall Gresty Road Crewe CW2 5AA [email protected] Andrew McLaren First Engineering Ltd Ground Floor Kintail House 3 Lister Way Hamilton International Blantrye G72 0FT Billy Bairstow Head of Train Operations Jarvis Fastline Holbeck Depot Ninevah Road Leeds LS11 9QG David Smith Head of Rail Planning Support Association of Train Operating Companies 3rd Floor, 40 Bernard St London WC1N 1BY John Gribble Rail Operations Assurance Manager Amey Infrastructure Services Ltd Sutton Courtenay Abingdon Oxon OX14 4PP Kevin Eccleston Access Planning Manager Direct Rail Services Ltd Gresty Bridge Depot Gresty Road Crewe CW2 5AA
LAF/WT/SPS/1550/01 10 July 2010 pl14014consultees.doc LAFARGE AGGREGATES LIMITED WHITWELL QUARRY RAILWAY DIVERSION
Other relevant stakeholders who it is recommended should be consulted Consultee Contact details
Paul Orchard Operational Planning & Performance Manager Fastline Ltd Fastline Freight 6th Floor St Ledger House Frenchgate Centre St Sepulchre Gate Doncaster DN1 1SW Valentine Licata Operations & Safety Executive Office of Rail Regulation One Kemble Street London WC2B 4AN Robin Hood Line Consortium Partners: All councils except Gedling Borough Council are specified under Section 43. The contact Nottinghamshire County, Derbyshire details for Gedling Borough Council are: County and Nottingham City Councils, Bassetlaw, Bolsover, Ashfield and Civic Centre Mansfield District Councils and Gedling Arnold Hill Park Nottingham Borough Council NG5 6LU
E-mail: [email protected]
Tel: (0115) 901 3971
LAF/WT/SPS/1550/01 11 July 2010 pl14014consultees.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
APPENDIX B
COPY OF THE ROMP CONDITIONS (CODE NO: R5/0705/13)
LAF/WT/SPS/1550/02 July 2010 pl14014.doc
LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
APPENDIX C
COPY OF THE ROMP SUBMISSION DATED JULY 2005
LAF/WT/SPS/1550/02 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
APPENDIX D
PROPOSED CONTENTS LIST OF THE ENVIRONMENTAL STATEMENT
LAF/WT/SPS/1550/02 July 2010 pl14014.doc LAFARGE AGGREGATES WHITWELL RAILWAY LIMITED DIVERSION
APPENDIX D
PROPOSED CONTENTS LIST OF THE ENVIRONMENTAL STATEMENT
PART 1 – INTRODUCTION TO THE PROPOSALS
1. INTRODUCTION
2. APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT
3. SCREENING AND SCOPING
4. SITE LOCATION AND DESCRIPTION
5. PROPERTIES AND POPULATION
6. PUBLIC RIGHTS OF WAY
PART 2 – THE PROPOSED DEVELOPMENT
7. PRINCIPLES OF THE DEVELOPMENT
8. CURRENT SITE OPERATIONS
9. PROPOSED SITE OPERATIONS
10. SEQUENCE OF WORKING
11. RESTORATION
12. ALTERNATIVES
PART 3- BASELINE AND ASSESSMENT OF ENVIRONMENTAL EFFECTS
13. BLASTING AND VIBRATION
14. DUST
15. NOISE
16. WATER RESOURCES
17. SOIL RESOURCES
18. ECOLOGY
19. LANDSCAPE AND VISUAL IMPACT
20. TRANSPORT
21. ARCHAEOLOGICAL IMPACT
22. CONCLUSIONS
THE ROMP ENVIRONMENTAL STATEMENT WILL BE PROVIDED AS AN APPENDIX
LAF/WT/SPS/1550/02 1 July 2010 pl14014.doc