Development of an Action Plan to Address Primary Mercury Mining in Kyrgyzstan
Mercury Waste Partnership Meeting for UNEP Global Mercury Partnership Tokyo, 12 March 2009
Craig Boljkovac, UNITAR Overview of presentation
z Nature of the project and project objectives
z Project activities and Implementation
z Consultations with government agencies in Bishkek/field visit to the Khaidarkan mining area
z Indicative timeline
z Future plans 2 Nature of the project
z Mercury in the international context
z Based on results of UNEP/GRID-Arendal within the Environment and Security Initiative to assess the environmental and health risks from Khaidarkan's Hg plant tailings (REHRA project) and Chemicals Management National Profile
z Project partners are UNEP, UNEP/GRID-Arendal and UNITAR with financial support of the Government of Switzerland and US EPA
z Guidance materials have been/are being developed
3 Project objectives (1)
z Assess the mercury mine and smelter, including environmental, technical and socio- economic aspects
z Develop an action plan to address identified gaps and challenges including options to replace the present mercury mining operations in the area by environmentally less harmful initiatives
4 Project objectives (2)
z Raise awareness of the local as well as donor community about currently ongoing primary mercury mining in the country
z Through its catalytic nature and approach, stimulate investments for possible follow-up
5 Project activities (1)
z Technical assessment
z Socio-economic assessment
z Generation of an action plan with options
6 Preparatory Implementation Activities Activities National Advisory Committee
Technical Site Assessment* Final Action Draft Action Plan National Plan and With Options*** Forum*** International Socioeconomic Forum*** Assessment**
Methodology Development International Advisors
•National execution with support from UNEP ** National execution with support from UNITAR • *** National execution with support from UNEP and UNITAR Project Implementation
z National Lead Agency/National Coordinator appointed
z National Advisory Committee established
z Group of international advisers (USEPA, Swiss Government, international organizations and other interested stakeholders) 8 Consultations with government agencies in Bishkek (1)
z State Agency on Environmental Protection and Forestry
z State Agency on Geology and Mineral Resources
z Management of Khaidarkan Mining
z Ministry of Industry, Energy and Fuel Resources
9 Consultations with government agencies in Bishkek (2)
z Fund of State Property
z Ministry of Foreign Affairs
z Government Office
z Institute of Chemistry (National Academy of Sciences)
10 Consultations with government agencies in Bishkek (3)
z State Inspection of Industrial Security and Mountain Control (Ministry of Emergencies)
z Ministry of Labour and Social Development
z State Sanitary- Epidemiological Surveillance (Ministry of Health)
z Ministry of Finance
11 Report on the field visit to Osh and the Khaidarkan mining area (1)
z Osh-Batken Regional Environmental Department
z Osh Department of State Inspection of Industrial Security and Mountain Control
z Batken District Environmental Department
z South Geological Expedition
12 Report on the field visit to Osh and the Khaidarkan mining area (2)
z Khaidarkan Smelter
z Khaidarkan Refining Factory
z Khaidarkan Mining
z Tailings
13
Indicative Timeline (1)
Field Missions UNITAR October 2008 (SEA) UNEP-GRID- Arendal (TA) Desk Assessment UNEP-GRID- Draft made available in Arendal July 2008
Technical Analysis UNEP-GRID- Draft made available in Report Arendal September 2008 January 2009 (final) Socio-Economic UNITAR Draft made available to Methodology SEA experts in September 2008
24 Indicative Timeline (2)
Socio-Economic Kyrgyzstan Early 2009 Assessment Action Plan Training UNITAR/ October 2008 Kyrgyzstan
Action Plan Draft Kyrgyzstan Mid 2009
Public Awareness UNITAR/ Mid 2009 Workshop and National Kyrgyzstan Consultations
25 Indicative Timeline (3)
Informal Donor UNEP/UNITAR/ April 2009 Consultations Kyrgyzstan meeting National Forum Kyrgyzstan/ May 2009 UNITAR
International Forum UNITAR/UNEP September 2009
26 Indicative Timeline (3)
z Формирование Национального Комитета
z Координация проекта
z Социально-экономическая оценка
27 Key issues for discussion
z Outcomes of last mission to Kyrgyzstan
z “Pending” issues (formation of the National Committee; status of Government Office decree, socio- economic assessment (SEA); project coordination)
28 For more information
www.unitar.org/cwm [email protected]