WestPlan Delivery Programme Prògram Lìbhrigidh a’ Phlana Shiar

March 2021 This constitutes the Action Programme for the West and Islands Local Development Plan (WestPlan)

www.highland.gov.uk This Delivery Programme sets out the infrastructure and development required to support the implementation of the West Highland and Islands Local Development Plan (WestPlan). As a result it constitutes the Action Programme which is a statutory requirement of the local development plan making process.

The purpose of the Delivery Programme is to provide information for identifying, monitoring and implementing the actions for delivering future growth in the area. It will be used to help identify which infrastructure projects will be subject to developer contributions requirements and as a tool for coordinating investment in development and infrastructure. We will revise and amend it as infrastructure is delivered, opportunities for new development are presented and as pressures change over time.

Developer contributions towards the delivery of the infrastructure projects shown in this Delivery Programme may be required from sites located within and outwith these settlements. For secondary school and community facility projects, developer contributions will typically be sought on a secondary school catchment area basis. Therefore, please check the relevant Main Settlement(s) to identify developer contribution requirements.

The Delivery Programme is split into the following sections: Page 1. Strategic Infrastructure Improvements - sets out the major investments 3 within the WestPlan area wh0ich will support regional and national growth; 2. Economic Development Areas (EDAs) - sets out the steps for enabling 6 major employment generating development within the EDA sites identified in WestPlan. 3. Fort William 2040 - sets out actions for maximising benefit from 7 investment and development in Fort William and (see FW2040 webpage for more information). 4. Main Settlements – outlines the actions for delivering growth in each of 8 the Main Settlements included within WestPlan and identifies which infrastructure projects will be subject to developer contributions requirements. 5. Other Areas - sets out the actions for delivering growth in areas outwith 21 the Main Settlements.

Please contact the Development Plans team should you have any questions regarding the content of the Delivery Programme by emailing [email protected] or on 01349 886608. 1. Strategic Infrastructure Improvements

ACTIONS FUNDING DELIVERY Topic Action Lead and Council Supporting Timescales Total Cost Capital Status/Actions Delivery Budget Partners A890 Stromeferry (rockfall area) No timescale Options range Item no longer The Highland Scottish Transport Bypass identified at this from £35M - funded Council (THC), Appraisal Guidance Remedy to "lifeline" road closure issue stage. £109M scheme in Scottish (STAG) assessment THC Capital Government, completed but still at Programme Network Rail, Hi- route options stage. Trans. Corridor A890 Stromeferry (rockfall area) Bypass safeguards in Plan. Councillor Working Group established 2019. Fort William Further Scottish Investment to THC. Discussions Intention first, to

t Improvements & Wider Transport Transport be with Transport undertake further STAG r

o Appraisal Appraisal confirmed but , Hi- appraisal work as part p

s Transport interventions to ease peak time congestion Guidance (STAG) one of the Trans, and local of STPR2 (second n

a within the Fort William urban area. appraisal work to potential interests Strategic Transport r

T be schemes, Projects Review) to progressed early Link Road assess optimum within the Plan initially transport interventions. period. estimated at Corridor safeguards in £35M - £50M. Plan. Corran Narrows Strategic Transport No timescale Investment to Listed but THC, Hi-Trans Scottish Transport Appraisal and Potential Fixed Crossing identified at this be confirmed unfunded item Appraisal Guidance Provision of a more reliable "lifeline" crossing stage. but initially in THC (STAG) assessment estimated at Capital underway. Feasibility of £22M - £30M. programme fixed crossing across Corran Narrows being investigated. Replacement ferry initially estimated at

2 £5M. Reference to land safeguards in WestPlan. Uig Harbour Expected start on £30M+ THC Transport Planning application for Upgrade of harbour facilities, including new terminal site in Spring 2020. contributing Scotland, elements of works building, to accommodate new ferry vessel. Programme and £1.5M Caledonian outwith the Harbour funding to be towards Maritime Assets Revision Order lodged confirmed by essential Ltd (CMAL), July 2019. Transport maintenance CalMac Ferries Scotland. works to the Ltd (CFL), THC, pier. HIE, Hi-Trans A890 Balnacra to Lair Not known Initially Item no longer THC. Discussions Reference in WestPlan 6km new dual track road to improve existing single track estimated at funded with Network Rail, strategy. Item no longer section. £12M scheme in SNH, SEPA and funded scheme in THC THC Capital local interests. Capital Programme. Programme Detailed scheme design completed and full planning permission Feb 2017. Ashaig Airport Progress Expected cost Hi-Trans, THC, Technical advice from Airstrip improvements to accommodate reintroduction of dependent on £1.53M - HIE, SNH and Highlands and Islands scheduled air services funding availability. £1.77M SEPA. Technical Airports Limited. advice from £170K of THC Cap Prog Highlands and committed in May 2019 Islands Airports for further engagement Limited with statutory bodies and preparation work.

Skye Cycle Way - Establish a safe cycle path from N/A 2020 onwards Early high BSCC, Skye Around 200km of Kyleakin and Armadale to Broadford, Portree and Uig level costings Connect, network have been indicate an Edinbane CT, surveyed to date. estimated SUSTRANS, £44million to HlTRANS, design and Transport construct a Scotland, THC, network of Landowners around 230km. £96k has been secured from SUSTRANS

3 to deliver a strategic plan & feasibility study A832 Twin Tracking Slattadale to First Phase 0.6km Final stage Scheme not THC, SNH, SEPA Preliminary assessment Gairloch completed. TBC funded in work underway for final Two phases to twin track remaining single track section of Final phase 5km to THC Capital section but firm cost / A832. Charlestown. Programme schedule to be confirmed Next Generation and Superfast Broadband Next Generation: Next £Nil Scot Gov, HIE, Roll out has reached Delivery of improved digital connectivity 2013-2017 Generation: BT, Other Public 86% of premises in Superfast: By 2021 £146M (across Sector Bodies Highlands and Islands. whole of HIE area) Superfast: TBC Local Full Fibre Networks (Fort William, , Contract for the £7.149M The 5 public UK Government Currently less than 1% Thurso and Wick) 152 connections sector (DCMS), HIE, of properties in the Strategic aim is to increase the footprint of full fibre finalised in January partners are UHI, SNH, NHS, region can get these, networks in the region. Successful partnership bid to the 2019. capitalising THC, Capita, with the figure for the UK Government’s Local Full Fibre Network (LFFN) Construction will savings and CityFibre UK around 7%. s

e programme for £4.3m to install open access, gigabit start late 2019 for making an i t i l capable networks in each of the 4 settlements that will completion by upfront The project is currently i t provide connections to 152 public buildings. As they are March 2021. payment. in a detailed planning U open access, engagement with the telecoms market is Savings will phase, due for continuing to secure interest in building these out to be realised completion in October businesses and domestic properties. over 20 years 2019 at which point we from network will start construction. rights of use provided to each of the 152 sites. This funding will total £2.849m.

4 2. Economic Development Areas

DELIVERY

ACTIONS TIMESCALES FUNDING Lead and Supporting Status Delivery Partners

Ashaig Airstrip Progress Expected cost Hi-Trans, THC, HIE, SNH Technical advice from Highlands and Islands 42ha of land safeguarded for enhancement of the dependent on £1.53M to and SEPA. Technical Airports Limited. £170K of THC Cap Prog airstrip and provision of associated facilities to allow funding availability. £1.77M advice from Highlands and committed in May 2019 for further engagement with the reintroduction of scheduled air services. Islands Airports Limited statutory bodies and preparation work.

Glencoe Ski Centre Base Station Not known Not known Operator led proposal 4ha of land safeguarded for expansion of outdoor recreational activities

Inverlochy Castle Estate Not known Not known ICMI (owner) 31ha of land safeguarded for expansion and diversification of tourism facilities

Kishorn Port & Dry Dock Ongoing Not known Kishorn Port Ltd, HIE, Masterplan planning permission updated 2018. 67ha of land safeguarded for development servicing Applecross Trust, Crown Downsizing & recycling of MV Kaami; preservation offshore energy industry, particularly renewables, oil Estate Scotland, Scottish & maintenance of Voyageur Spirit FPSO and and gas sectors and decommissioning, as well as Development International support to Banff FPSO all took place in 2020. aquaculture sector. (SDI) Expansion of aquaculture tenants' activities also took place in 2020. Future port developments are being progressed (dry dock extension; 9ha of laydown land and deep water quay). Nevis Forest and Mountain Resort Ongoing Up to £25M Forestry Enterprise Masterplan (Aug 2015) covering 109ha is a 20 year 112ha of land safeguarded for provision/expansion Scotland, Forest Holidays vision for improving the economic benefits through of outdoor recreational facilities and tourist Ltd, HIE, Visit Scotland, setting out a range of development and investment accommodation. SDI opportunities of Scotland’s Forests and Land for Lochaber. Forest Holidays Ltd submitted a Proposal of Application Notice in Aug 2019 (19/02871/PAN).

5 3. Fort William 2040

This section will display the latest version of the FW2040 Delivery Programme. For more information on the project please see the FW2040 webpage.

6 4. Main Settlements

ACTIONS TIMESCALES COST and DELIVERY FUNDING Type Infrastructure Projects Developer contributions Lead and Supporting Status required towards Delivery Partners infrastructure project Settlement BROADFORD Name • 107 homes allocated • 50 ha employment land allocated

Community Creation of new All housing development Prioritised to be TBC THC, HLH, Broadford Business case has been Facilities community hub as part of within Portree High delivered within 5 and Strath Community prepared. Preparation underway new primary school with School catchment may years but subject Company (BSCC) for planning application enhanced sports provision be required to contribute to securing submission. and relocation of library at standard Community Scottish and other council services Facility rates. Government including service point, funding. social work. Development Community asset transfer N/A Not known Not known BSCC, Broadford and Community Council and the of public toilets and car Strath Community Community Company have park - Relocate toilets and Council, THC lodged expression of interest in enhancement of facilities. acquiring the sites. Energy Opportunity identified for N/A N/A Costs identified THC, Developer Detailed assessment of heat district heat network in in Assessment network opportunities currently Broadford Report. out alongside WestPlan. The report will help assist delivery of heat network proposals. Health New community hospital to N/A 2021 £15M NHS Highland Planning application consented Services serve Skye, Lochalsh and for replacement hospital in Apr South Wester Ross. To be 2019 (18/04539/FUL). Currently located on land adjoining under construction. existing health centre.

7 Schools Broadford Primary School All housing development TBC TBC THC - 1 classroom extension within school catchment required to contribute at 1 classroom extension rates. Schools Replacement of existing N/A 2027 £11.6M THC, Scot Gov Included as part of the THC 2021 Broadford Primary School capital programme review. to address condition and suitability issues.

Transport Skye Cycle Way - N/A 2022-23 £3.5M BSCC, Transport Route identified, feasibility and Establish a safe cycle path Scotland/Sustrans, concept design complete. between Broadford and THC Sustrans supporting Kyle of Lochalsh using the development of detailed old road. proposals. Planning application submitted (20/03669/FUL) and access negotiations in train. BSCC working in partnership with THC on Breakish section. Settlement DUNVEGAN Name • 42 homes allocated • 18 ha employment land allocated

Community Dunvegan Sports Pitch - Not at present because Not known Not known North West Skye Dunvegan Primary is identified Facilities Provision of outdoor sports the means for delivering Sports and Recreation as immediate priority for the next facilities (potentially the project remain Association, THC, tranche of Schools for the Future associated with the uncertain. Work is LSHA funding. Investment decision will creation of the new school underway to link the be dependent on outcome of in Dunvegan) sports pitch, school and funding application. housing as one project.

Schools Replacement of existing N/A £3M investment £3M committed THC, Scot Gov Replacement school - Identified Dunvegan Primary School expected by in THC Cap by THC as Years 1-5 Priorities to address condition and 2023. Prog 2019 for for future funding bid. suitability issues. Replacement of ELC provision Investment decision will be school and dependent on outcome of dependent on enhancement funding application. outcome of of other Enhancement of ELC provision

8 funding facilities. and other facilities - Part of application. Replacement of Capital Programme approved school Jun 2019. dependent on outcome of funding application. Settlement FORT WILLIAM Name • 895 homes allocated • 220 ha employment land allocated

Community Provision of community All housing development Not known Not known Lochaber Community Lochaber Community Facilities space in Upper Fort within Lundavra Primary Partnership Partnership exploring options William catchment to contribute and feasibility of Upper at standard Community Achintore. Facility rates. Community Visitor Centre - All housing development TBC £850k HLH Facilities Expansion of the visitor within Lochaber High centre, provision café and School catchment at additional car parking, standard Community covered outdoor Facility rates towards educational classroom eligible components of wider project. Community Extension of Lochaber All housing development 2022 £1.5M HLH Ongoing development of Facilities Leisure Centre to provide within Lochaber High business case a larger gym and new School catchment at studio, strength and standard Community conditioning Facility rates. Community Need for new/ enhanced All housing development Not known New indoor HLH, THC, Community Facilities multi-purpose spaces within Lochaber High facility indoor and outdoor School catchment at estimated at catering for sports and arts standard Community £3M. which may involve the Facility rates. replacement/major refurbishment of Nevis Centre. Energy Opportunity identified for 4 N/A N/A Costs identified THC, Developer Detailed assessment of heat district heat network areas: in Assessment network opportunities currently A) Fort William and Report. out alongside WestPlan. The Achintore, B) Inverlochy, report will help assist delivery of C) Blar Mhor, D) Caol. heat network proposals.

9 Planning Fort William Town Centre N/A Ongoing Not known Community, THC Policy Action Plan - highlights a range of proposals and opportunities identified by the community and stakeholders that can deliver regeneration in Fort William town centre. Schools Land safeguarded for a Contributions towards TBC Not known THC potential new school at land costs may be sought Blar Mhor. if new school is shown to be required. Schools Inverlochy Primary - 1 All housing development Dependent upon TBC THC Part of pan-Highland capital Classroom extension within school catchment rate of programme commitment to required to contribute at 1 development. address anticipated future classroom extension Expected years capacity issues resulting from rates. 2-5 based on forecasted levels of housing SRF. development. Schools Bun-Sgoil Ghàidhlig Loch N/A TBC £450K THC Part of Capital Programme Abar - 2 classroom approved Jun 2019. extension Schools Lundavra Primary - Major All housing development Dependent upon TBC THC, Developers Part of pan-Highland capital extension within school catchment rate of programme commitment to required to contribute at development. address anticipated future major extension rates. Expected years capacity issues resulting from 2-5 based on forecasted levels of housing SRF. development. Schools Lochaber High School - N/A TBC £250K THC Improvements to grass playing fields (currently out of use) Settlement GAIRLOCH Name • 77 homes allocated • 17 ha employment land allocated

Energy Opportunity identified for N/A N/A Costs identified THC, Developer Detailed assessment of heat district heat network in in Assessment network opportunities currently Gairloch Report. out alongside WestPlan. The

10 report will help assist delivery of heat network proposals.

Planning Gairloch and Loch Ewe N/A Commenced Aug N/A GALE (local Policy Planning For Real - 2019 community group) Preparation of new Community Action Plan Schools Gairloch Primary School - N/A Investment in £350K THC Additional ELC unit ELC committed for accommodation - ELC original Scottish accommodation Government in 2019 update timescales were to THC Capital Aug 2020. Prog. Settlement GLENCOE Name • 10 homes allocated • 2.3 ha employment land allocated

Community Replacement of existing TBC TBC TBC Community Facilities Glencoe Village Hall with new community facility on allocation GC03, north of Primary School. Settlement LOCHCARRON Name • 78 homes allocated • 11 ha employment land allocated

Community Lochcarron Leisure Centre Not at present as the Not known Not known Community led - Planning permission granted Facilities - Provision of new means for delivering the Lochcarron Leisure (16/05404/PIP) in May 2017 for community and sports project remain uncertain. Centre Company sports facility/café at Kirkton. facilities. (LLCC), Lochcarron Summer 2019: Community Community groups in the process of updating Development Business Plan with a view to Company (LDCC) approaching potential major funding agencies post Brexit.

11 Development Kirkton Woodland - N/A Not known Not known HSCHT, Lochcarron Community owned forest Community and potential future Development residential area adjacent Company to village. Aspirations for affordable housing in partnership with HSCHT, community event space, allotments, and tourism accommodation and facilities. Schools Lochcarron Primary N/A Investment in £900K THC School - Additional ELC ELC committed for and replacement primary accommodation - ELC units original Scottish accommodation Government in 2019 update timescales were to THC Capital Aug 2020. Prog. Transport Potential safeguarding of N/A Not known Not known Not known land for the Lochcarron Bypass Route as identified in WestPlan (2019). Settlement Name • 15 homes allocated • 5 ha employment land allocated

Settlement KYLE OF LOCHALSH Name • 66 homes allocated • 12 ha employment land allocated

12 Community The Plock - Develop the All housing development Former toll Kyle and Lochalsh Business plan and masterplan Facilities area as an activity and within Plockton High building Community Trust finalised in Jun 2018. KLCT took community hub for School catchment may conversion (KLCT) ownership of The Plock in 2019. residents and visitors. be required to contribute estimated at Short term: conversion of at standard Community £50K+. Path former toll building to Facility rates. network works community meeting space, estimated at including accessibility £100K+. Plock improvements. Medium Hub building term: enhancement and estimated at extension of path network. £1.5M+. Long term: creation of new community hub building and event space. Planning Potential Lochalsh-wide N/A N/A N/A Community groups Policy Community-led Action Plans

Schools Kyle Primary School - N/A Investment in £350K THC Additional ELC unit ELC committed for accommodation - ELC original Scottish accommodation Government in 2019 update timescales were to THC Capital Aug 2020. Prog. Transport Limited availability of TBC TBC TBC THC, Developers Car parking for recent parking may require long development at Main Street/A87 term solution to be was accommodated at swimming delivered. pool. Settlement KYLEAKIN Name • 28 homes allocated • 23 ha employment land allocated

Community Kyleakin Connections - All housing development Not known Not known Kyleakin Connections Kyleakin Connections are in Facilities Extension of current facility within Plockton High process of getting asset transfer to increase capacity and School catchment may of the building from THC. enhance the range of be required to contribute Planning permission services. at standard Community (18/05346/FUL) granted in Jan Facility rates. 2019 for creation of an additional building.

13 Development Creation of a new fish feed N/A 2016 - 2020 £100M Marine Harvest Opened in early 2019. Work is plant at former Allt Scotland (Mowi) ongoing at present. Anabhaig quarry near Kykeakin. Green Enhancement of existing All housing development Not known Not known Kyleakin Community Infrastructure play park and/or creation within Kyleakin may be Hall Committee of a new playpark. required to contribute where on-site provision is not possible. Transport Skye Cycle Way - N/A 2022-23 £3.5M BSCC, Transport Route identified, feasibility and Establish a safe cycle path Scotland/Sustrans, concept design complete. between Broadford and THC Sustrans supporting Kyle of Lochalsh using the development of detailed old road. proposals. Planning application submitted (20/03669/FUL) and access negotiations in train. BSCC working in partnership with THC on Breakish section. Settlement Name • 65 homes allocated • 25 ha employment land allocated

Community Mallaig Pool and Leisure - All housing development TBC Estimated at Community led - Facilities Major refurbishment of within Mallaig High £1.1M. £310K Mallaig Pool and sports facilities and School catchment raised so far. Leisure. enhancement of other required to contribute at facilities to establish it as a standard Community community hub. Facility rates. Planning Mallaig Harbour N/A Short, Medium Not known Mallaig Harbour Policy Masterplan (2017) - and Long Term Authority, THC Detailed plan for the priorities have enhancement and been identified expansion of harbour facilities Settlement NORTH , GLENACHULISH AND SOUTH BALLACHULISH Name • 20 homes allocated • 6 ha employment land allocated

14 Community Ballachulish South, Adjoining housing site TBC TBC TBC Provision made within the Plan Facilities Community park and only required to for land to be transferred to the habitat improvements contribute at standard community at nil cost. along the river. Community Facility rates. Settlement POOLEWE Name • 23 homes allocated • 2.4 ha employment land allocated

Settlement PORTREE Name • 366 homes allocated • 65 ha employment land allocated

Community Portree, Fingal Centre - All housing development Prioritised to be £500K HLH, THC Outline business case has been Facilities Expansion to provide new within Portree High delivered within prepared fitness suite School catchment may the HLH's 5 year be required to contribute capital at standard Community programme. Facility rates. Development Public Sector Co- N/A Not known Cost Not HIE, THC, Public & 3rd location/Asset Review Known. Sector Partners Feasibility work being funded by HIE Energy Opportunity identified for N/A N/A Costs identified THC, Developer Detailed assessment of heat district heat network in in Assessment network opportunities currently Portree Report. out alongside WestPlan. The report will help assist delivery of heat network proposals. Schools Bun-Sgoil Ghaidhlig Phort N/A TBC TBC THC Righ

Schools Portree Primary School - 1 All housing development Dependent upon TBC THC classroom extension within school catchment rate of required to contribute at 1 development. classroom extension rates.

15 Schools Portree Primary School - N/A Investment in £250K THC Refurbishment of ELC ELC provision - committed for accommodation; funding in original Scottish ELC and place to refurbish vacated Government primary space in Primary School timescales were accommodation Aug 2020. in 2019 update to THC Capital Prog. Transport Completion of Portree Link Contributions may be Not known Initial estimate THC, Lochalsh and No funding assigned in THC's Road which involves required from any new of £1.2M (part Skye Housing Capital Programme (March 2018) connection and improved development in Portree funded by Association, Highland junction onto the A855. Settlement Development developer Housing Alliance, other Area as shown in contributions - landowners/developers WestPlan. See WestPlan specific amount for more details. not yet confirmed) Transport Extensions to the Portree Contributions may be Not known Not known THC, developers, Link Road northwards with required from any new landowners a single connection onto development in Portree the A87 Trunk Road Settlement Development Area as shown in WestPlan. See WestPlan for more details. Transport Improve public car parking Developer contributions Initial outline Not known THC, landowners Parking options appraisal and coach/bus drop-off may be required where costs are prepared in 2018. provision within the village proposals are unable to estimated at centre and encourage meet on-site parking £750k relocation of longer stay requirements needs to more peripheral locations Transport Reclaim land for Car Park Developer contributions Not Known Initial estimate THC, Portree & Braes Parking options appraisal and Amenities may be required where of £2.6M Community Trust, prepared in 2018. proposals are unable to (Funding not landowners meet on-site parking yet known) requirements Settlement SLEAT Name • 114 homes allocated • 16 ha employment land allocated

16 Development Kilbeg Village N/A Ongoing Not known. Sabhal Mòr Ostaig Phase 1 delivered which includes Development Project - Community Development Trust, new Academic, Research, Approved masterplan Campervan Sabhal Mor Ostaig Knowledge Transfer and which includes a mix of Facilities UHI, Scot Gov, THC, Enterprise building. housing, commercial, costed at HIE educational and leisure £256k. Funding development. application for £121k submitted to RTIF for consideration on 15 Dec 2020. Transport Review of Harbour N/A TBC Not known CMAL, MHA, THC and RSTAG report expected to be Infrastructure at Armadale key local stakeholders issued late 2019. and Mallaig - CMAL in a Steering Group leading on undertaking a STAG. Schools Bun-Sgoil Shleite - 2 All housing development Dependent upon TBC THC classroom extension within school catchment rate of required to contribute at 2 development. classroom extension rates. Schools Bun-Sgoil Shleite - ELC N/A TBC TBC THC Scope of works still to be agreed. extension and refurbishment Settlement AND ROY BRIDGE Name • 110 homes allocated • 3 ha employment land allocated

Schools Spean Bridge Primary - 2 All housing development Dependent upon TBC THC classroom extension within school catchment rate of required to contribute at 2 development. classroom extension Expected years rates. 2-5 based on SRF. Settlement STAFFIN Name • 10 homes allocated • 1.5 ha employment land allocated

17 Development Creation of 6 affordable N/A 2021 £1.6M in total. Staffin Development Planning permission homes and two business Funding Trust, Lochalsh and (17/01699/FUL) granted in March units, one of which will secured for Skye Housing 2018. Currently under serve as the new NHS design work, Association (LSHA), construction. Highland GP surgery, at planning Staffin Community Stenscholl Common application and Council, Highlands Grazing land. purchase of the Small Communities land. Funding Housing Trust yet to be (HSCHT) secured for development. Funding Package complete 6/7/20 Development Staffin Slipway N/A TBC Total project Staffin Development Development cost Trust, THC, HIE £3,230,000. Funding secured to date £969,000 from the Regeneration Capital Grant Fund Settlement Name • 55 homes allocated • 5 ha employment land allocated

Community Strontian, Community Park Housing development TBC TBC Community TBC Facilities within Strontian to provide developer contributions towards the provision of a central community park. Settlement UIG Name • 44 homes allocated • 13 ha employment land allocated

18 Transport Uig Harbour - Major N/A Expected start £30M+ (THC THC, Transport Planning application for elements upgrade and enhancement on site in July contributing Scotland, CMAL, of works outwith the Harbour of harbour facilities, 2021. £1.5M towards CalMac Revision Order lodged July 2019. including new terminal Programme and essential Tenders expected to go out in building, to accommodate funding to be maintenance late 2019. Construction to start new ferry vessel. confirmed by works to the July 2021 depending on funding. Transport pier). Scotland.

Water Expansion of water supply N/A Not known Not known Scottish Water Yield study being undertaken by capacity to serve future Scottish Water into capacity of demand. existing water supply. Settlement ULLAPOOL Name • 85 homes allocated • 30 ha employment land allocated

Community Ullapool, Lochbroom All housing development 2024 £850K HLH Facilities Leisure Centre. New within Ullapool High exercise studio and School catchment may extended fitness suite. be required to contribute at standard Community Facility rates. Development Creation of new waterfront N/A Not known Not known Community, Ullapool promenade, including Harbour Trust, THC widening Shore Street and improved access to the harbour. Energy Opportunity identified for N/A N/A Costs identified THC, Developer Detailed assessment of heat district heat network in in Assessment network opportunities currently Ullapool Report. out alongside WestPlan. The report will help assist delivery of heat network proposals. Schools Ullapool Primary School - N/A Investment in £1.15M THC Contract awarded. Nursery extension linked ELC provision - committed for to school original Scottish ELC Government accommodation timescales were in 2019 update Aug 2020. to THC Capital Prog.

19 5. Other Areas

ACTIONS DELIVERY

Developer COST and Lead and contributions TIMESCALES Settlement/ Infrastructure Supporting Type required towards FUNDING Status Location Projects Delivery infrastructure Partners project Schools Acharacle Primary - 1 All housing Classroom extension development within school catchment required to contribute at 1 classroom extension rates. Development Achiltibuie Community purchase N/A Not known Not known Coigach Options Appraisal and redevelopment of Community Report completed Old Dornie and Development Nov 2013. Badentarbet piers. Company Planning , Potential community N/A Not known Not known The Achnacarry, Policy Bunarkaig and led land use plan Bunarkaig and Clunes Clunes Community Group Planning Applecross “Plan It Applecross” - N/A Completed Summer £32k Applecross Completed. Not Policy Community land use 2019. Endorsed as Community planned to be plan Planning Material for Company, PAS, approved as Consideration in THC, HIE, Scot Supplementary November 2019. Gov, Applecross Guidance. Trust

20 Development Applecross Creation of 3 Expected completion £528k Applecross Planning permission affordable homes in date Sept 2021. Community (20/02786/FUL) Camusterrach. Company, Scot granted Sept 2020. Gov

Development Applecross Purchase of hydro Land purchase by Unknown Applecross Planning pre-app field for 8 affordable March 2021. Community (20/01279/PREAPP) housing and 2 Development 3-5 Company, Scot granted May 2020. business workshops. years Gov

Schools Auchtertyre Auchtertyre Primary All housing Dependent upon School - 1 classroom development within rate of development. extension school catchment required to contribute at 1 classroom extension rates. Development Claigan Redevelop and N/A Apr-21 Cost TBC. Funded SGRPID, THC Land purchase extend existing car by SGRPID & THC underway by park and construct SGRPID. Design & new toilets, all to build cost in process improve tourism of being finalised infrastructure. along with planning application. Development Elgol Build new toilets, N/A Apr-21 Application Broadford & Planning permission develop additional submitted to RTIF Strath (20/03990/FUL) Disabled Parking and for consideration Community granted 26/11/2020. construct a path and decision on the Company Funding Application down to the harbour 15th December submitted. area, all to improve 2020, total cost tourism infrastructure. £224,229. Funding applied for £168,172 with match funding of £56,057 Planning Fairy Pools, Improved car parking N/A 2018-2019 Phase 1 was Minginish Phase 1 completed Policy Glenbrittle and transport facilities £660K (funding Community Hall in Dec 2018 which to serve visitors to the included: £300K Association, included creation of Fairy Pools Scot Gov, £200K Outdoor Access new 120 car park LEADER, £100K Trust for and parking areas

21 THC, £50K HIE, Scotland, and for larger vehicles. £10K local funding Phase 2 includes fundraising) partners. roadside bollards, toilet facilities, pay and display machines and small retail outlet. Development Flodigarry Ionad Throndairnis, N/A Not known Not known Ionad Land buyout for the development of a Throndairnis centre completed. cultural & heritage Feasibility study centre, including café updated April 2020. and accomodation Planning Glendale Potential community N/A Not known Not known Glendale Trust Policy led land use plan

Planning Inverie () - Potential community N/A Expected to be Not known Knoydart Policy As part of ongoing led land use plan complete by end of Foundation stewardship of 2020 Knoydart, the Knoydart Foundation is in the process of developing a strategic document for the area, including a planning framework. Development Isle of Canna Community-led N/A 2022-23 Not known IoCCDT, Feasibility work housing - 3No. Communities underway, SLF affordable rented Housing Trust, supported units Scot. Gov.

22 Development Isle of Canna Coroghan Barn N/A 2023-24 Not known IoCCDT, NTS, Feasibility work redevelopment HES underway, AHF supported

Development Isle of Canna Canna Pier Hub N/A 2024-25 Not known IoCCDT, THC, Feasibility concept NTS, stage

Development Isle of Raasay Isle of Raasay N/A Not known Not known Raasay The project has pontoon, Development been invited to toilet,shower and Trust submit a stage 2 laundrette project. application to the RCGF. Planning Isle of Rum Isle of Rum N/A Area 1: Major For new housing Isle of Rum Progress in 4 of 10 Policy community-led land Shorebase Feasibility: £10k Community Character Areas. use plan (finalised commercial via Awards for All Trust (IRCT) First two areas 2015) - Priorities are development (let by £5k mowi Scottish include significant based around 10 IRCT to Mowi) New House build: Government departures from Character Areas £450k Scottish Mowi Plan (These options Area 4: completion Government not available to June 2020 of 4 £180k Mowi Trust in 2014/15 and accommodation (mostly in-kind) so not considered at units (let by IRCT to £35k Crerar Trust that time). Mowi). Now all let £45k IRCT as of Nov20 ?£100k loan

Area 7: decrofting of development land and proposals underway to allow letting of vacant crofts

Area 9: installation in 2019 of 10 public moorings, 3 commercial moorings; all tides

23 pontoon for public and commercial use.

Planning Shieldaig Potential community N/A Not known Not known Shieldaig Shieldaig Housing Policy led land use plan Community Needs Reports Association published in July 2017.

Schools Shieldaig Shieldaig Primary - 1 All housing Dependent upon Classroom THC Classroom extension development within rate of development. extension TBC and conversion of school catchment Expected years 4-15 Schoolhouse vacant schoolhouse required to contribute based on SRF. conversion £100K to ELC at 1 classroom accommodation. extension rates.

24