Downtown Boise Implementation Plan August 2013

Ta ble of Contents INTRODUCTION This document provides an overview of the DBIP development and summa- ries the key findings and outcomes. It is organized in the following sections: INTRODUCTION...... 1 The Downtown Boise Implementation Plan (DBIP) is a joint effort between the Ada County Highway District (ACHD), City of Boise, and Capitol City De- ▪▪Process – Discussion of the development of the DBIP, PROCESS...... 3 velopment Corporation (CCDC) to establish a blueprint for the implementa- Public Involvement – Details regarding the public outreach PUBLIC INVOLVEMENT...... 4 tion of transportation and streetscape improvements within the Downtown ▪▪ Boise core (study area shown in Figure 1). Downtown Boise is an employ- and involvement which shaped the decisions and guidance for RECOMMENDATIONS & OUTCOMES...... 7 ment and commercial hub for the Treasure Valley containing approximate- improvements within downtown Boise, ly 32,000 jobs. Between workers, residents, and visitors, what happens in SEQUENCING & COORDINATION...... 19 Downtown Boise impacts a large portion of the Ada County population. ▪▪Outcomes – Recommendations based on feedback collected from With a significant amount of required street maintenance overlays, planned the public and decisions made by the Project Management Team DBIP GIS TOOL...... 20 streetscape improvements, planned utility upgrades, and the desire for an (PMT), enhanced bicycle and circulation network, the DBIP effort was undertaken FINAL CONSIDERATIONS...... 20 to create a coordination plan so that the planned activities within the next Sequencing & Coordination – The sequencing of projects five to seven years can: ▪▪implementation within downtown between 2014 and 2019, List of Appendices ▪▪Be completed in coordination to minimize impacts for businesses GIS Tool – Details of the geodatabase developed during the and travelers, ▪▪course of the project as well as its capabilities and applications, Appendix A – Public Involvement Meeting #1 and Get the most return possible out of mobilizing efforts, Appendix B – Public Involvement Meeting #2 ▪▪ ▪▪Additional Considerations – Planned coordination efforts as well Appendix C – Bike Users Map Shorten the timeframe in which all envisioned downtown projects as areas for additional investigation. ▪▪are brought to fruition, and Appendix D – Two-Way Street Concepts Be sequenced in a logical and effective manner that maintains Appendix E – 13th Street VISSIM Modeling ▪▪circulation and access within downtown. Appendix F – ACHD DBIP Cost Estimates The DBIP effort also included close collaboration with the Downtown Boise Appendix G – DBIP Geodatabase Memorandum Association and Valley Regional Transit along with robust public outreach and involvement activities to hear from and incorporate the ideas and desires of downtown business owners, residents, workers, and visitors.

This report summarizes the key outcomes from the DBIP effort which are: A compilation of currently planned overlay and maintenance ▪▪work, intersection improvements, streetscape and sidewalk improvements, key planned developments, and utility improvements within the downtown core;

A refined downtown bicycle plan for improvements to the bicycle ▪▪facilities, networks, and routes within the downtown core;

Recommendations for the conversion of existing one-way streets ▪▪to two-way traffic flow; Downtown Boise Bike Corral A sequencing guidebook for the next five to seven years that ▪▪identifies work to be done, sequence of work, and how to coordinate efforts between agencies; and

An interactive GIS database that is a consolidated location for ▪▪all project information and allows users to query information by location to examine what projects are associated with it and near its vicinity, to outline all projects identified within a certain timeframe, and to establish if there are additional parallel efforts to be undertaken (such as water or sewer lines).

Downtown Boise Implementation Plan | 1

Downtown Boise Implementation Plan August 2013

N 30TH ST W THATCHER ST

N 4TH ST

N 7TH ST N 19TH ST

N 27TH ST N 26TH ST

N 29TH ST W UNION ST N 12TH ST N W ST

N 28TH ST

N 25TH ST N 24TH ST

N 6TH ST

N 23RD ST N 22ND ST N 18TH ST

N 11TH ST N5TH ST

N 17TH ST N VA HOSPITAL LOOP

N 16TH ST W HAYS ST N 10TH ST N 15TH ST W WASHINGTON ST S 30TH ST N 14TH ST W FRANKLIN ST

N 13TH ST N 12TH ST

S 23RD ST

S S 22ND ST S S 27TH ST

S 17TH ST S 17TH ST W IDAHO ST N 11TH ST E MOUNTAIN COVE RD

S S 25TH ST

W ARK ST S 18TH ST Downtown Family YMCA

W FAIRVIEW AVE S 24TH ST N 7TH ST N FRONT ST S 16TH ST W MAIN ST INTERSTATE 184 INTERSTATE 184 W GROVE ST

S 17TH ST N 10TH ST N 12TH ST

N 9TH ST W WASHINGTON ST N COLLINS RD W FORT ST S AMERICANA BLVD S 15TH ST Idaho Capitol Building N 5TH ST S 12TH ST W MAIN ST

W SPA ST W GRAND AVE N ROBBINS RD S 11TH ST N SCOUT LN W SHORELINE DR W STATE ST W FRONT ST N 8TH ST

S 10TH ST W JEFFERSON ST E SANTA MARIA DR

W IRVING ST N 6TH ST W BANNOCK ST E GARRISON RD N MOUNTAIN COVE RD E ALDAPE COVE RD S 14TH ST S 13TH ST N FORT PL

N CAPITOL BLVD N AMERICANA BLVD W RIVER ST

N HOUSTON RD W BORAH ST N SAN JUAN DR S 12TH ST The Grove E RESERVE ST E FORT ST S 9TH ST N MARSHALL ST W MILLER ST

W LEE ST N 4TH ST N 2ND ST W GROVE ST E JEFFERSON ST E KRALL ST W BROAD ST N 3RD ST E LOGAN ST E FLORAL LN

S ASH ST W MAIN ST Post Office N 1ST ST

N SAN FELIPE DR

S 6TH ST E KRALL ST N AVENUE N EAVE S 10TH ST S 5TH ST St. Luke's Boise Medical Center W BROAD ST AVENUEN AVE D

S 8TH ST AVENUE N AVE H W EMERALD ST E MCKINLEY ST S 2ND ST E FRANKLIN ST W MYRTLE ST S 3RD ST

E WASHINGTON ST S CAPITOL BLVD

N FLUME ST

W MEADOW DR S 4TH ST E REDWOOD CT E STATE ST W ROYAL BLVD Ada County Courthouse N BRUCE AVE

W CRESCENT RIM DR N ELM AVE

Ann Morrison Park N STRAUGHAN AVE S 2ND ST

S 9TH ST E FRONT ST N WALNUT ST N PACIFIC ST N MAPLE AVE S LA POINTE ST

N ATLANTICN ST S DALE ST

E BANNOCK ST N LOCUST ST W MORRIS HILL RD W ISLAND AVE S AVENUE A AVE W JULIA DAVIS DR

N LATAH ST S LUSK ST S 9TH ST E WARM SPRINGS AVE S BRUCE LN N PIERCE ST E MYRTLE ST E LEWIS ST

N ARCADIA ST W SHERWOOD ST S STRAUGHAN AVE

N ATLANTICN ST E HOLLY ST

W TULARA DR N OWYHEE ST N HAINES ST

N PICARDY PL

S S BROADWAY AVE E PARK BLVD E LEWIS ST

W KIPLING RD S LOIS AVE S EARLE ST

S WALNUT ST W CESAR CHAVEZ LN S VILLA PL S BRADY ST

W BOISE AVE W ALPINE ST S LUSK PL W BOISE AVE

S PIERCE PL S MIKE ST Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, and the GIS UserS HAINES PL Community

Civic Downtown Family YMCA St. Luke's Boise Medical Center STUDY AREA Figure Park Post Office The Grove 1

Boise State University Study Area Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG1_studyarea.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study; CCDC Streetscape Project Listings

2 | Kittelson & Associates, Inc.

PROCESS DBIP Development The DBIP was initiated by ACHD. Both the City of Boise and CCDC were col- The development of the DBIP recommendations and this final plan fol- laborators in the effort given their interests and work within downtown lowed the process summarized in Exhibit 1. The project started with compil- Boise. The plan covers the downtown core area between Broadway Street- ing existing conditions and current plans for the study area. This included Avenue B and 16th Street and to the east and west and between State Street reviewing and incorporating previous work that has been completed for and the Boise River north and south. Again, the study area map is provided improvements to the downtown bicycle network (ACHD’s Roadways to Bike- in Figure 1. ways Plan, counts and information from the Ada County Bicycle Alliance) and on two-way street conversions (CCDC’s Two-Way Conversion Study). The stakeholder and public outreach helped identify other needs and con- Project Management Team cerns not already included in previous study. All this information was then compiled and reviewed to create specific recommendations for the bicycle The DBIP effort was overseen by a Project Management Team (PMT). The network, two-way street conversions, and other transportation enhance- PMT was comprised of representatives from: ments. The public was provided the opportunity to review and comment on ACHD Planning & Projects, the draft recommendations. Finally, the recommendations were confirmed, ▪▪ a detailed sequencing and phasing plan was developed for project imple- mentation over the next five to seven years. ▪▪ACHD Traffic Engineering, ▪▪ACHD Development Services, ▪▪ACHD Pavement Maintenance, Stakeholder ▪▪City of Boise, Input ▪▪Capital City Development Corporation, ▪▪Downtown Boise Association, and ▪▪Valley Regional Transit. Develop The PMT was responsible for providing current plans and needs within the Idenity Other Needs: Recommendations: study area, reviewing technical analysis, reviewing public input and com- ▪Bicycle Network ment, and developing recommendations. Identify Existing ▪Bicycle Network Consolidate Current Establish Sequencing ▪Two Way Street Public Involvement Conditions & Compile ▪Two Way Street Plans & Additions & Implementation In addition to the coordination and collaboration between the various agen- Converstions cies on the PMT, the DBIP process also included extensive public outreach Current Plans Converstions Needs Plan and involvement activities. These activities included two Public Open -Hous ▪Intersection es, a project web site, web-based interactive commenting abilities, and a ▪Intersection Stakeholder Workshop for businesses, utility providers, developers, and Improvement other parties directly influencing or impacted by work in the downtown Improvement core. Additional details on the public outreach and involvement activities ▪ Implementation are provided in the next section of this report. Strategies

Public Public Input Input

E xhibit 1: DBIP Process

3 | Kittelson & Associates, Inc. Downtown Boise Implementation Plan | 3

PUB LIC INVOLVEMENT Coordination of utility work and the establishment of a Puce bli Op n House #1 ▪▪notification system for utility identification, Outreach to partnering agency staff, downtown stakeholders, and the gen- The first public open house for the DBIP effort was held on February 13th, eral public was a key component of the DBIP effort. Given the broad nature Implementation of adaptive lanes/signal timing for major events 2013 for citizens to provide input on the process. At the meeting, citizens all who travel, work, and live in downtown Boise, outreach to these groups ▪▪and traffic management, and were presented with information related to the plan through four informa- was an important element of developing the plan recommendations. This tion stations: outreach included specific meetings, a project web site, interactive web- Evaluation of current downtown parking rates and subsidization. based commenting, and project information and mailers. ▪▪ ▪▪Project Introduction (purpose, outcomes, schedule), Stakeholders were also asked to identify ideas to help implementation and ▪▪Planned Roadway Projects & Roadway Needs, coordination of downtown projects. Through this exercise, stakeholders rec- Existing & Proposed Bicycle Facilities, and ommended: ▪▪ Information on Two-Way Street Conversion & Mini-Roundabouts. ▪▪Improving the disclosure and availability of information, ▪▪ Improving disclosure and communication with who owns various Each station allowed for citizens to provide comments referenced by num- ▪▪rights-of-way in downtown, bered dots on either an aerial map poster or through an interactive web- site. Public input comment sheets were provided to citizens at the meeting Providing guidance for the contacts needed for work downtown, and could also be accessed via a survey on line for two weeks following the ▪▪ meeting. Based on the meeting sign in sheet, a total of 103 people attended Developing “joint trench notification” system for alleys with a 30- the second open house and a total of 309 different comments or items of ▪▪day notice, input were received either at the meeting or in the weeks following. BICYCLE IMPROVEMENTS Creation of a centralized information system including private ▪▪interests, The public meeting provided the opportunity for citizens to locate and com- ment on bicycle-specific concerns they have within downtown. Citizens were Semi-annual coordination meetings with agencies, utility also able to provide information regarding their preferred bike routes and Example of Interative Map ▪▪providers, event coordinators, and emergency service providers, connections within the study area. Input was gathered on the type of trips St akeholder Meeting made by cyclists, which improvements participants would like to see, and Increasing the allowable construction time windows in downtown what deterrents cyclists have to riding downtown. The feedback indicated As one of the first outreach efforts for the DBIP, a stakeholder meeting was ▪▪so work can be completed in a shorter number of days and, that the bicycle network in downtown should be developed to accommo- held on February 13th, 2013 that included representatives from a variety of date and provide appropriate facilities for a diverse range of bicycle users public services and private stakeholders within the downtown area. There Maintaining the database established as part of this effort current and levels of rider capability (from confident and experienced frequent adult were over 60 attendees including business owners, agency staff, utility pro- ▪▪and available to stakeholders. riders to more recreational and infrequent riders and families). viders, realtors and developers, downtown organization representatives, and elected officials. The stakeholder meeting was a facilitated session The most desired type of bicycle improvements indicated by people who where stakeholders worked in small groups to: provided input were designating bike routes on lower traffic streets. The least commonly selected improvement, wayfinding, may be attributed to ▪▪Identify currently programed projects and plans within the study the participants who took the survey (i.e., people who are already familiar area, with the downtown area). The input also indicated that the most evident deterrent to bicycling within downtown is the volume and/or speed of ve- Identify additional areas of concern or projects desired for hicular traffic in the downtown area. To encourage bicycling within down- ▪▪downtown, and town, addressing this issue (such as designating lower volume streets as bike routes or providing separated bicycle facilities on high volume roads) should Develop ideas to facilitate project coordination and be considered. Specific input received on downtown bicycle improvements ▪▪implementation across organizations. can be found in Appendix A to this report as part of the detailed Public Open House #1 summary. As part of the meeting, stakeholder’s identified what they considered the top priority projects for downtown Boise. Those identified by the The Open House also provided a “Show Us Your Preferred Bike Routes” ac- stakeholders were: tivity that allowed participants to use yarn to show continuous bike routes Stakeholder Meeting used on an aerial map poster. This information was then coded in geograph- Improved bicycle connectivity, safety, and parking, ic information system (GIS) database on a block-by-block basis to determine ▪▪ the most heavily used routes. This information is detailed in Figure 2. What Enhanced pedestrian and bicycle crossings, is evident from this activity is the emphasis of main corridors, notably that ▪▪ 8th Street and 10th Street serve as the primary north-south corridors and the use of Warm Springs Avenue as the main access to downtown from the ▪▪Conversion or study the conversion of existing one-way streets to east. While Figure 2 does not detail the full reality of heavily used biking two-way traffic flow, routes, it reinforces the expectations of commonly used bike routes.

Stakeholder Meeting

4 | Kittelson & Associates, Inc.

Downtown Boise Implementation Plan August 2013

N 30TH ST W THATCHER ST

N 27TH ST N 26TH ST N 19TH ST W WASHINGTON ST W UNION ST W IDAHO ST N 12TH ST W FORT ST N

N N 24TH ST

N N 29TH ST

N 28TH ST

N N 25TH ST

N 22ND STN 22ND N 23RD ST N 23RD N 18TH ST N 11TH ST E MOUNTAIN COVE RD N 17TH ST W HAYS ST N VA HOSPITAL LOOP W MAIN ST N 16TH ST N 10TH ST S 30TH ST N 15TH ST W FRANKLIN ST N 14TH ST W IDAHO ST N 6TH ST N 13TH ST W FAIRVIEW AVE

N GARDEN ST S 17TH ST S 27TH ST S 23RD ST S 17TH ST

S 24TH ST S

S 25TH ST S N 11TH ST

N 7TH ST

INTERSTATE 184 S 16TH ST W FLETCHER ST N 10TH ST W STATE ST W GROVE ST INTERSTATE 184 S 15TH ST W BANNOCK ST S 17TH ST W WASHINGTON ST N 12TH ST

N COLLINS RD S AMERICANA BLVD W SHORELINE DR

W MAIN ST N 6TH ST S 12TH ST W GRAND AVE N 8TH ST W SPA ST N 9TH ST N ROBBINS RD

N SCOUT LN E SANTA PAULA DR

S 14TH ST N CAPITOL BLVD N 5TH ST

W FRONTS 10THST ST W JEFFERSON ST E SHAW MOUNTAIN RD N MOUNTAIN COVERD E GARRISON RD S 13TH ST N 4TH ST N HOUSTON RD N HAPPY DR N FORT PL W RIVER ST N AMERICANA BLVD W BORAH ST S 11TH ST E RESERVE ST

N MARSHALL ST E FORT ST W MILLER ST S CAPITOL BLVDW GROVE ST W LEE ST E FLORAL LN W BROAD ST E LOGAN ST N 3RD ST S PIONEER ST E JEFFERSON ST S ASH ST

N 2ND ST W MAIN ST N SAN FELIPE DR

W LEE ST S 9TH ST N 1ST ST E KRALL ST N SAN JOSE DR S 6TH ST S 4TH ST E BANNOCK ST E IDAHO ST

S 5TH ST S 8TH ST W BROAD ST AVE E AVENUE N

W EMERALD ST AVE D AVENUE N E MCKINLEY ST E FRANKLIN ST W MYRTLE ST

E WASHINGTON ST

S CAPITOL BLVD S 3RD ST

W MEADOW DR E REDWOOD CT N FLUME ST E STATE ST

W CRESCENT RIM DR N BRUCE AVE W ROYAL BLVD E BANNOCK ST N ELM AVE S 2ND ST

N STRAUGHAN AVE E FRONT ST S 9TH ST

N PACIFIC ST N PACIFIC N MAPLE AVE W ANN MORRISON PARK DR W MORRIS HILL RD N LOCUST ST

S DALE ST W JULIA DAVIS DR W CESAR CHAVEZ LN E MYRTLE ST E WARM SPRINGSN WALNUT AVE ST E LEWIS ST S LUSK ST N PIERCE ST N LATAH ST N LATAH S LA POINTE ST S BRUCE LN W SHERWOOD ST S 9TH ST

S STRAUGHAN AVE

W CAMROSE LN N ATLANTICN ST E HOLLY ST

W TULARA DR N OWYHEE ST N HAINES ST E PARK BLVD W KIPLING RD

S LOIS AVE S EARLE ST S VILLA PL S BROADWAY AVE S BROADWAY S WALNUT ST W ALPINE ST S BRADY ST E LEWIS ST S LUSK PL

W BOISE AVE

Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP,S PIERCEand PL the GIS User Community

Number of Routes PREFERRED BICYCLE ROUTES Figure 1 4 7 Study Area INTERACTIVE OPEN HOUSE EXERCISE 2 5 8 2 3 6 9 Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG2_PIM_bikeroutes.mxd Source: Downtown Boise Implementation Plan Open House, February 13, 2013

Downtown Boise Implementation Plan | 5

TWO-WAY STREET CONVERSION AND MINI-ROUNDABOUTS Puce bli Op n House #2 BICYCE L NETWORK IMPROVEMENTS

The Open House asked citizens to locate and comment on the possibility of A second public open house was held on June 6th, 2013 as another oppor- The open house and comment surveys provided the opportunity for citizens converting existing one-way streets to two-way traffic flow within down- tunity for citizens to provide input on the DBIP. At the meeting, citizens were to comment on the recommended bicycle network and bicycle users’ map. town. This station also provided citizens the opportunity to comment on the presented with information related to the plan through four information The bicycle network map showed the draft recommendations for bicycle potential use of mini-roundabouts as intersection treatments within down- stations: improvements in downtown based on the comments from the first open town. house and the PMT’s recommendations. The “Bicycle Users’ Map” was a ▪▪Project Introduction (purpose, outcomes, schedule), new graphic, intended to help people plan a bike route through downtown The majority of input was in favor of using mini-roundabouts where ap- based on their biking comfort, that was presented to get feedback regarding propriate for traffic control, traffic calming, and to enhance the character ▪▪Bicycle Facilities Concepts, the map’s relevance and if the presentation was understandable. of downtown. The input also showed generally positive support for the conversion of existing one-way streets to two-way traffic flow. The main ▪▪Two-Way Conversion Concepts, and The following notes summarized the general feedback for the bicycle net- reasons for this support were derived from the idea that circulation and work and bicycle users’ map: navigation would be simplified downtown and that the elimination of one- Project Implementation Concepts. way streets would be beneficial for businesses. Several comments on the ▪▪ The majority of respondents agreed with the proposed bicycle two-way conversion mentioned that the current configuration (the combi- ▪▪network or agreed with the network with the exception of the nation of one-way and two-way streets) is confusing and difficult to navi- Again, each station allowed for citizens to provide comments referenced resulting parking impacts at one or two locations, gate and, therefore, any conversions should be done to simplify the system. by numbered dots on either an aerial map poster or through an interactive Those who opposed changing existing one-way streets primarily stated the website. Public input comment sheets were provided to citizens at the meet- The addition of bicycle lanes on 5th Street, 6th Street, and expense of the conversion being wasteful (particularly since people remem- ing and could also be accessed via a survey on line for two weeks following ▪▪Broadway-Avenue B were indicated as the improvements that bered when the streets were converted from two-way to one-way) and that the meeting. Based on the meeting sign in sheet, a total of 72 people -at most respondents felt were most important, traffic would increase substantially on those streets. Participants were also tended the second open house and a total of 117 comments were received asked to prioritize which streets they thought should be the priorities for either at the meeting or in the weeks following. The following sections sum- marize comments received from written comments, map comments, and Most respondents indicated that the Bicycle User’s Map was clear converting to two-way traffic (based on those initially screened in the previ- ▪▪and useful in planning a bicycle route, and ous Downtown Two-way Conversion Study). The results to this question in- the general comment survey. dicated that 13th Street was the street the most respondents felt should be To support the bicycle network, additional public bicycle parking the priority for two-way traffic conversion (for better connectivity between ▪▪was the amenity most respondents would like to see. the I-184 connector and the North End neighborhoods). Why is a Bike Network Important? ROADWAY IMPROVEMENTS & GENERAL AREAS OF CONCERN TWO-WAY STREET CONVERSIONS & MINI ROUNDABOUTS Creating a complete and connected bike network has many benefits for our community, especially in Downtown. Finally, the first open house provided opportunity for citizens to locate and Investing in bicycle improvements can: The open house also provided the opportunity for citizens to comment on comment on general roadway projects and areas of concerns regarding • Improve traffic congestion and air quality by getting people out of their the draft recommendations for two-way street conversions and mini round- cars transportation within downtown Boise. They were asked to identify their • Enhance the vibrancy and activity on a street for businesses and economic about locations in downtown Boise. Approximately 50% of the respondents development top concern with transportation construction in the downtown area. The • Strengthen our ability to attract quality industry, businesses, and were in favor of the proposed two-way street conversions with another 20% most frequent response to this question was closure of streets/travel lanes employees in favor of the conversions with the exception of removing all parking on • Create active street scenes that make Downtown vibrant and fun identifying that vehicular navigation and mobility were viewed as the great- • Help improve the health of our community through active lifestyles certain blocks of Jefferson Street. Related to mini roundabouts, almost 60% est detriment during construction downtown. This suggests that coordina- Why Mini-Roundabouts? of the respondents agreed with the proposed mini roundabout locations. tion of project phasing should emphasize maintaining traffic flow and route Mini roundabouts can be used at intersections instead of traffic signals or stop signs to minimize potential impacts to options (if possible). When prompted about the highest priority (i.e. where on-street parking. PARKING REMOVAL focus and funding should be prioritized) for downtown projects the most What is a mini roundabout? • A small roundabout (inner circle less than 75 feet) common responses were: • Has a traversable central island Finally, the open house also provided the opportunity for citizens to com- • Most commonly used in low-speed urban environments ment on the potential locations where on-street parking would need to be • Motorists must yield to pedestrians Improving traffic flow, and bicycles as well as other vehicles ▪▪ already in the circle removed to accommodate the two-way conversion or the addition of bike How do I use a mini-roundabout? lanes. The respondents identified a primary concern with the potential park- Pedestrians use the crosswalks around the Implementing improvements to bicycle facilities, and; perimeter of the mini-roundabout. ing removal on Jefferson Street. To address this concern, additional options ▪▪ Bicyclists can either navigate the mini- roundabout in the roadway or dismount and (such as maintaining parking on one side of the street) were evaluated for Beautification and enhancement projects. use the crosswalks and ramps as a pedestrian. Jefferson Street and an additional outreach meeting for the residents and ▪▪ businesses along Jefferson was held.

Appendix B to this report provides the detailed summary of Public Open House #2. The input received from all of these outreach efforts was incorpo- rated in the project team’s discussions and evaluation of improvements and priorities. The resultant outcomes and recommendations for the DBIP are presented in the next section.

6 | Kittelson & Associates, Inc.

R ECOMMENDATIONS & OUTCOMES is acceptable as long as there are reasonable parallel routes that provide Developing 3rd Street as a bicycle boulevard, all cyclists with connectivity to complete a comprehensive bicycle network. ▪▪ The resultant recommendations for the DBIP, have been developed based The key bicycle routes established as part of the DBIP are listed in Table 1. ▪▪Providing double sharrow markings along the Main Street/Idaho on input and comment from stakeholders and the public and the PMT’s Street couplet on the outer lanes, and Table 1. Key Bicycle Routes evaluation. The guiding principals in developing the DBIP recommendations Upgrading the existing bike lanes along 15th Street and 16th have been: MJ A OR EAST/WEST MAJOR NORTH/SOUTH ▪▪Street to accommodate full width bike lanes and parking. BICYCLE ROUTES BICYCLE ROUTES ▪▪Coordinating public works and investments to the greatest extent practicable to minimize impacts to the public, gain efficiencies Jefferson Street – provides Broadway Avenue/Avenue B The proposed downtown bicycle network is shown in Figure 5. In addi- in the expenditure of public funds, and create opportunities not ▪▪ ▪▪ tion to the planned network, Figure 5 shows several facilities (detailed as key east-west connectivity 3rd Street gained through unilateral efforts; east of Broadway-Avenue ▪▪ “Shared Space”) which are intended to note areas within downtown that B and west of 16th Street ▪▪5th Street/6th Street Couplet will serve both bicycles and pedestrians. These areas include: Expanding and improving the bicycle network, through improved (which Bannock does not) 8th Street the Greenbelt, ▪▪connections between downtown and surrounding areas, ▪▪ ▪▪ Main Street/Idaho Street Capitol Boulevard (northbound expansion of both exclusive and shared facilities, and upgrade ▪▪Couplet ▪▪ the Grove Plaza, existing facilities where feasible; and between the Capitol Boulevard ▪▪ ▪▪Grove Street Bridge and Grove Street) ▪▪the Boise High School pedestrian/bicycle path, 11th Street – provides key Improving access, simplify the road network, and increase route River Street ▪▪ the pathway connection between 3rd Street and the Greenbelt, ▪▪options for road users by expanding the two-way network ▪▪ north-south connectivity north ▪▪ wherever feasible of State Street and south of the proposed connection between the south of 5th Street and Front Street/Myrtle (which 10th ▪▪Julia Davis Park, and Street does not) The planned projects are primarily a combination of ACHD, CCDC, and ITD the proposed Pioneer Pathway. construction or maintenance projects within the existing right-of-way. The ▪▪15th/16th Street Couplet ▪▪ bicycle network, two-way street conversions, and the intersection improve- ments were derived from both public opinion captured during the public Some of the major components of the bicycle network within the down- involvement process and the evaluations and discussions within the Project town core include: Management Team. ▪▪Installing two-way bike lanes along the full extents of Jefferson C tuRRen ly Planned Projects Street, The current projects planned within the downtown study area mostly refer ▪▪Installing a one-way bike lane couplet on 6th Street (southbound) to planned roadway maintenance and streetscape projects. Roadway main- and 5th Street (northbound), tenance projects (e.g. overlays and rebuilds) are scheduled within ACHD’s Five-Year Workplan and ITD’s Idaho Transportation Investment Program ▪▪Installing bike lanes on Avenue B and Broadway from Jefferson (ITIP). A summary of these projects as part of the DBIP are shown in Figure Street to south of the Broadway Bridge, 3. ▪▪Providing a northbound bike lane on Capitol Boulevard between Currently planned streetscape (sidewalk, landscaping, street lighting) proj- the Capitol Boulevard Bridge and Grove Street (where cyclists can ects within downtown are managed by CCDC and are summarized in Figure use the signalized crossing to connect to either the Grove Street, 4. if they need to travel east-west, or 8th Street, if they need to travel north-south, bike routes), Dwntowno Bicycle Network ▪▪ North of Grove Street, providing exclusive bicycle lanes becomes more challenging at this time and would require The downtown bicycle network created as part of the DBIP is a refinement transition treatments with the right-turn trap lane at Main Rendering of shared lane markings on Idaho Street to the downtown Boise component of the 2009 Roadways to Bikeways Plan Street. Continue the bike lanes north of Main Street would adopted by ACHD. The refined network for the downtown was developed also require impacts to either the existing loading zone (on Improvements shown in Figure 5, but not currently scheduled for comple- to establish a comprehensive and connected bicycle system within down- the west side of Capitol) or on-street parking (on the east tion relate to the facilities within Julia Davis Park including the shared lane town as well as appropriate connections to that system from areas outside side of Capitol) between Main Street and Idaho Street. These markings from S. Capitol Boulevard to W. Myrtle Street, and the planned of downtown. The plan identifies east/west and north/south bicycle routes considerations can be reviewed in more detail if it is desired connection extending 5th Street from Myrtle Street into the park. as well as other connections and supporting infrastructure for bicyclists. to extend the bicycle lane in the future. Even in the near- In addition to the bicycle network, a Bicycle User’s Map was created as term, cyclists can continue on Capitol north of Grove Street a tool to help cyclists plan their route to and through downtown based In creating the recommended downtown bicycle network it was recognized if desired and shared-lane makings will provided to indicated that not all roadways need to serve all types of cyclists or need to have on their level of experience and comfort. The Bicycle User’s Map for the to drivers that they are to share the travel lane with bicycles downtown area is provided in Appendix C. physical bike lanes. There are many ways to accommodate cyclists in addi- when present. tion to bike lanes and the most appropriate treatments will depend on the Proposed bicycle improvements and two-way conversions will require the specific roadway context and traffic volumes. There may be roadways on Converting 10th Street to shared lanes and establishing 11th ▪▪Street as the more favorable north-south bike route, removal of some street parking on 5th, 13th, 15th and Jefferson Streets. which vehicles are prioritized and may only be comfortable to confident and ACHD and the City of Boise will continue to work with affected parties on assertive cyclists (such as 9th Street, Front Street, and Myrtle Street). This solutions to mitigate parking impacts in these areas.

Downtown Boise Implementation Plan | 7

Downtown Boise Implementation Plan August 2013

N 30TH ST W THATCHER ST

N 4TH ST

N 7TH ST N 19TH ST

N 27TH ST N 26TH ST

N 29TH ST W UNION ST N 12TH ST N W IDAHO ST

N 28TH ST

N 25TH ST N 24TH ST

N 6TH ST N 23RD ST

N 22ND ST N 18TH ST

N 11TH ST N5TH ST N 17TH ST N VA HOSPITAL LOOP

N 16TH ST W HAYS ST N 10TH ST N 15TH ST W WASHINGTON ST S 30TH ST N 14TH ST W FRANKLIN ST

N 13TH ST N 12TH ST

S 23RD ST

S S 22ND ST S S 27TH ST

S 17TH ST S 17TH ST W IDAHO ST E MOUNTAIN COVE RD

S S 25TH ST N 11TH ST W ARK ST S 18TH ST

W FAIRVIEW AVE S 24TH ST N 7TH ST N FRONT ST S 16TH ST W MAIN ST INTERSTATE 184 W STATE ST INTERSTATE 184 W GROVE ST N 10TH ST N 9TH ST

S 17TH ST N 12TH ST W WASHINGTON ST

W BANNOCK ST N COLLINS RD

W FORT ST S AMERICANA BLVD S 15TH ST N 6TH ST S 12TH ST W MAIN ST

W SPA ST W GRAND AVE N ROBBINS RD

N SCOUT LN

W SHORELINE DR N 5TH ST N 8TH ST

S 11TH ST S 10TH ST W FRONT ST E SANTA MARIA DR

W JEFFERSON ST N MOUNTAIN COVE RD W IRVING ST E GARRISON RD E ALDAPE COVE RD S 14TH ST S 13TH ST N 4TH ST N FORT PL

N CAPITOL BLVD N AMERICANA BLVD W RIVER ST

N HOUSTON RD W BORAH ST N SAN JUAN DR S 12TH ST E RESERVE ST

E FORT ST S 9TH ST N MARSHALL ST W MILLER ST W LEE ST E KRALL ST W BROAD ST W GROVE ST N 3RD ST E LOGAN ST E FLORAL LN

S ASH ST W MAIN ST S PIONEER ST E JEFFERSON ST

N SAN FELIPE DR

N 2ND ST N 1ST ST W LEE ST S 6TH ST E KRALL ST E BANNOCK ST

E IDAHO ST N AVENUE N EAVE

S 5TH ST N AVENUEN AVE D

S 8TH ST N AVENUE N AVE H W EMERALD ST W BROAD ST E MCKINLEY ST S 2ND ST E FRANKLIN ST W MYRTLE ST N AVENUE C AVE

S CAPITOL BLVD E WASHINGTON ST S 3RD ST

N FLUME ST

W MEADOW DR E REDWOOD CT E STATE ST W ROYAL BLVD S 4TH ST N BRUCE AVE

W CRESCENT RIM DR N ELM AVE S 2ND ST N STRAUGHAN AVE

S 9TH ST E FRONT ST N WALNUT ST N PACIFIC ST N MAPLE AVE S LA POINTE ST

N ATLANTICN ST S DALE ST

E BANNOCK ST N LOCUST ST W MORRIS HILL RD W ISLAND AVE

S AVENUE A AVE W JULIA DAVIS DR

N LATAH ST S LUSK ST S 9TH ST E WARM SPRINGS AVE S BRUCE LN N PIERCE ST E MYRTLE ST E LEWIS ST

N ARCADIA ST W SHERWOOD ST S STRAUGHAN AVE

N ATLANTICN ST E HOLLY ST

W TULARA DR N OWYHEE ST N HAINES ST

N PICARDY PL

S S BROADWAY AVE E PARK BLVD E LEWIS ST

W KIPLING RD S LOIS AVE S EARLE ST

S WALNUT ST W CESAR CHAVEZ LN S VILLA PL S BRADY ST

W BOISE AVE W ALPINE ST S LUSK PL W BOISE AVE

S MIKE ST Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, andS PIERCE the PL GIS UserS HAINES PL Community

Road Work Intersection Work Flexible Schedule 2014 2014 2015 Study Area ROAD/INTERSECTION WORK Figure 2016 2015 (2014 - 2018) 2017 2016 3 2018

2019 or later 2017 Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG3_maintenance.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study; CCDC Streetscape Project Listings

8 | Kittelson & Associates, Inc.

Downtown Boise Implementation Plan August 2013

N 30TH ST W THATCHER ST

N 4TH ST

N 7TH ST N 19TH ST

N 27TH ST N 26TH ST

N 29TH ST W UNION ST N 12TH ST N W IDAHO ST

N 28TH ST

N 25TH ST N 24TH ST

N 6TH ST

N 23RD ST N 22ND ST N 18TH ST

N 11TH ST N5TH ST

N 17TH ST N VA HOSPITAL LOOP

N 16TH ST W HAYS ST N 10TH ST N 15TH ST W WASHINGTON ST S 30TH ST N 14TH ST W FRANKLIN ST

N 13TH ST N 12TH ST

S 23RD ST

S S 22ND ST S S 27TH ST

S 17TH ST S 17TH ST W IDAHO ST E MOUNTAIN COVE RD

S S 25TH ST N 11TH ST W ARK ST S 18TH ST

W FAIRVIEW AVE S 24TH ST N 7TH ST N FRONT ST S 16TH ST W MAIN ST INTERSTATE 184 W STATE ST INTERSTATE 184 W GROVE ST N 10TH ST N 9TH ST

S 17TH ST N 12TH ST W WASHINGTON ST

W BANNOCK ST N COLLINS RD W FORT ST S AMERICANA BLVD S 15TH ST N 6TH ST S 12TH ST W MAIN ST

W SPA ST W GRAND AVE N ROBBINS RD

N SCOUT LN

W SHORELINE DR N 5TH ST N 8TH ST

S 11TH ST S 10TH ST W FRONT ST E SANTA MARIA DR

W JEFFERSON ST N MOUNTAIN COVE RD W IRVING ST E GARRISON RD E ALDAPE COVE RD S 14TH ST S 13TH ST N 4TH ST N FORT PL

N CAPITOL BLVD N AMERICANA BLVD W RIVER ST

N HOUSTON RD W BORAH ST N SAN JUAN DR S 12TH ST E RESERVE ST

E FORT ST S 9TH ST N MARSHALL ST W MILLER ST W LEE ST E KRALL ST W BROAD ST W GROVE ST N 3RD ST E LOGAN ST E FLORAL LN

S ASH ST W MAIN ST S PIONEER ST E JEFFERSON ST

N SAN FELIPE DR

N 2ND ST N 1ST ST W LEE ST S 6TH ST E KRALL ST E BANNOCK ST

E IDAHO ST N AVENUE N EAVE

S 5TH ST N AVENUEN AVE D

S 8TH ST N AVENUE N AVE H W EMERALD ST W BROAD ST E MCKINLEY ST S 2ND ST E FRANKLIN ST W MYRTLE ST N AVENUE C AVE

S CAPITOL BLVD E WASHINGTON ST S 3RD ST

N FLUME ST

W MEADOW DR E REDWOOD CT E STATE ST W ROYAL BLVD S 4TH ST N BRUCE AVE

W CRESCENT RIM DR N ELM AVE S 2ND ST N STRAUGHAN AVE

S 9TH ST E FRONT ST N WALNUT ST N PACIFIC ST N MAPLE AVE S LA POINTE ST

N ATLANTICN ST S DALE ST W MORRIS HILL RD W ISLAND AVE E BANNOCK ST N LOCUST ST

S AVENUE A AVE W JULIA DAVIS DR

N LATAH ST S LUSK ST S 9TH ST E WARM SPRINGS AVE S BRUCE LN N PIERCE ST E MYRTLE ST E LEWIS ST

N ARCADIA ST W SHERWOOD ST S STRAUGHAN AVE

N ATLANTICN ST E HOLLY ST

W TULARA DR N OWYHEE ST N HAINES ST

N PICARDY PL

S S BROADWAY AVE E PARK BLVD E LEWIS ST

W KIPLING RD S LOIS AVE S EARLE ST

S WALNUT ST W CESAR CHAVEZ LN S VILLA PL S BRADY ST

W BOISE AVE W ALPINE ST S LUSK PL W BOISE AVE

S PIERCE PL S MIKE ST Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, and the GIS UserS HAINES PL Community

Planned Streetscape Projects Study Area 2014

2015 STREETSCAPE PROJECTS Figure 2016 (2014 - 2019) 2017 4 2018

2019 Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG4_streetscape.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study; CCDC Streetscape Project Listings

Downtown Boise Implementation Plan | 9

Downtown Boise Implementation Plan August 2013

N 30TH ST W THATCHER ST

N 4TH ST

N 7TH ST N 19TH ST

N 27TH ST N 26TH ST

N 29TH ST W UNION ST N 12TH ST N W IDAHO ST

N 28TH ST

N 25TH ST N 24TH ST

N 6TH ST

N 23RD ST N 22ND ST N 18TH ST

N 11TH ST N5TH ST

N 17TH ST N VA HOSPITAL LOOP

N 16TH ST W HAYS ST N 10TH ST N 15TH ST W WASHINGTON ST S 30TH ST N 14TH ST W FRANKLIN ST

N 13TH ST N 12TH ST

S 23RD ST

S S 22ND ST S S 27TH ST

S 17TH ST S 17TH ST W IDAHO ST E MOUNTAIN COVE RD

S S 25TH ST N 11TH ST W ARK ST S 18TH ST

W FAIRVIEW AVE S 24TH ST N 7TH ST N FRONT ST S 16TH ST W MAIN ST INTERSTATE 184 W STATE ST INTERSTATE 184 W GROVE ST N 10TH ST N 9TH ST

S 17TH ST N 12TH ST W WASHINGTON ST

W BANNOCK ST N COLLINS RD W FORT ST S AMERICANA BLVD S 15TH ST N 6TH ST S 12TH ST W MAIN ST

W SPA ST W GRAND AVE N ROBBINS RD

N SCOUT LN

W SHORELINE DR N 5TH ST N 8TH ST

S 11TH ST S 10TH ST W FRONT ST E SANTA MARIA DR

W JEFFERSON ST N MOUNTAIN COVE RD W IRVING ST E GARRISON RD E ALDAPE COVE RD S 14TH ST S 13TH ST N 4TH ST N FORT PL

N CAPITOL BLVD N AMERICANA BLVD W RIVER ST

N HOUSTON RD W BORAH ST N SAN JUAN DR S 12TH ST E RESERVE ST

E FORT ST S 9TH ST N MARSHALL ST W MILLER ST W LEE ST E KRALL ST W BROAD ST W GROVE ST N 3RD ST E LOGAN ST E FLORAL LN

S ASH ST W MAIN ST S PIONEER ST E JEFFERSON ST

N SAN FELIPE DR

N 2ND ST N 1ST ST W LEE ST S 6TH ST E KRALL ST E BANNOCK ST

E IDAHO ST N AVENUE N EAVE

S 5TH ST N AVENUEN AVE D

S 8TH ST N AVENUE N AVE H W EMERALD ST W BROAD ST E MCKINLEY ST S 2ND ST E FRANKLIN ST W MYRTLE ST N AVENUE C AVE

S CAPITOL BLVD E WASHINGTON ST S 3RD ST

N FLUME ST

W MEADOW DR E REDWOOD CT E STATE ST W ROYAL BLVD S 4TH ST N BRUCE AVE

W CRESCENT RIM DR N ELM AVE S 2ND ST N STRAUGHAN AVE

S 9TH ST E FRONT ST N WALNUT ST N PACIFIC ST N MAPLE AVE S LA POINTE ST

N ATLANTICN ST S DALE ST W MORRIS HILL RD W ISLAND AVE E BANNOCK ST N LOCUST ST

S AVENUE A AVE W JULIA DAVIS DR

N LATAH ST S LUSK ST S 9TH ST E WARM SPRINGS AVE S BRUCE LN N PIERCE ST E MYRTLE ST E LEWIS ST

N ARCADIA ST W SHERWOOD ST S STRAUGHAN AVE

N ATLANTICN ST E HOLLY ST

W TULARA DR N OWYHEE ST N HAINES ST

N PICARDY PL

S S BROADWAY AVE E PARK BLVD E LEWIS ST

W KIPLING RD S LOIS AVE S EARLE ST

S WALNUT ST W CESAR CHAVEZ LN S VILLA PL S BRADY ST

W BOISE AVE W ALPINE ST S LUSK PL W BOISE AVE

S PIERCE PL S MIKE ST Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, and the GIS UserS HAINES PL Community

Recommended Improvements Existing Bike Facilities Other Bike Lane Bike Lane Planned Connection Figure Bike Route/Shared Route Bike Route/Shared Shared Space DOWNTOWN BICYCLE NETWORK Contraflow Bike Lane Contraflow Bike Lane Study Area 5 Improve Existing Bike Lane Multi-Use Path

Convert to Shared Route Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG5_bike_network.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study; CCDC Streetscape Project Listings

10 | Kittelson & Associates, Inc.

Downtown Boise Implementation Plan August 2013

N 30TH ST W THATCHER ST

N 4TH ST

N 7TH ST N 19TH ST

N 27TH ST N 26TH ST

N 29TH ST W UNION ST N 12TH ST N W IDAHO ST

N 28TH ST

N 25TH ST N 24TH ST

N 6TH ST

N 23RD ST N 22ND ST N 18TH ST

N 11TH ST N5TH ST

N 17TH ST N VA HOSPITAL LOOP

N 16TH ST W HAYS ST N 10TH ST N 15TH ST W WASHINGTON ST S 30TH ST N 14TH ST W FRANKLIN ST

N 13TH ST N 12TH ST

S 23RD ST

S S 22ND ST S S 27TH ST

S 17TH ST S 17TH ST W IDAHO ST E MOUNTAIN COVE RD

S S 25TH ST N 11TH ST W ARK ST S 18TH ST

W FAIRVIEW AVE S 24TH ST N 7TH ST N FRONT ST S 16TH ST W MAIN ST INTERSTATE 184 W STATE ST INTERSTATE 184 W GROVE ST N 10TH ST N 9TH ST

S 17TH ST N 12TH ST W WASHINGTON ST

W BANNOCK ST N COLLINS RD W FORT ST S AMERICANA BLVD S 15TH ST N 6TH ST S 12TH ST W MAIN ST

W SPA ST W GRAND AVE N ROBBINS RD

N SCOUT LN

W SHORELINE DR N 5TH ST N 8TH ST

S 11TH ST S 10TH ST W FRONT ST E SANTA MARIA DR

W JEFFERSON ST N MOUNTAIN COVE RD W IRVING ST E GARRISON RD E ALDAPE COVE RD S 14TH ST S 13TH ST N 4TH ST N FORT PL

N CAPITOL BLVD N AMERICANA BLVD W RIVER ST

N HOUSTON RD W BORAH ST N SAN JUAN DR S 12TH ST E RESERVE ST

E FORT ST S 9TH ST N MARSHALL ST W MILLER ST W LEE ST E KRALL ST W BROAD ST W GROVE ST N 3RD ST E LOGAN ST E FLORAL LN

S ASH ST W MAIN ST S PIONEER ST E JEFFERSON ST

N SAN FELIPE DR

N 2ND ST N 1ST ST W LEE ST S 6TH ST E KRALL ST E BANNOCK ST

E IDAHO ST N AVENUE N EAVE

S 5TH ST N AVENUEN AVE D

S 8TH ST N AVENUE N AVE H W EMERALD ST W BROAD ST E MCKINLEY ST S 2ND ST E FRANKLIN ST W MYRTLE ST N AVENUE C AVE

S CAPITOL BLVD E WASHINGTON ST S 3RD ST

N FLUME ST

W MEADOW DR E REDWOOD CT E STATE ST W ROYAL BLVD S 4TH ST N BRUCE AVE

W CRESCENT RIM DR N ELM AVE S 2ND ST N STRAUGHAN AVE

S 9TH ST E FRONT ST N WALNUT ST N PACIFIC ST N MAPLE AVE S LA POINTE ST

N ATLANTICN ST S DALE ST W MORRIS HILL RD W ISLAND AVE E BANNOCK ST N LOCUST ST

S AVENUE A AVE W JULIA DAVIS DR

N LATAH ST S LUSK ST S 9TH ST E WARM SPRINGS AVE S BRUCE LN N PIERCE ST E MYRTLE ST E LEWIS ST

N ARCADIA ST W SHERWOOD ST S STRAUGHAN AVE

N ATLANTICN ST E HOLLY ST

W TULARA DR N OWYHEE ST N HAINES ST

N PICARDY PL

S S BROADWAY AVE E PARK BLVD E LEWIS ST

W KIPLING RD S LOIS AVE S EARLE ST

S WALNUT ST W CESAR CHAVEZ LN S VILLA PL S BRADY ST

W BOISE AVE W ALPINE ST S LUSK PL W BOISE AVE

S PIERCE PL S MIKE ST Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, and the GIS UserS HAINES PL Community

Two-way Conversion RECOMMENDED TWO-WAY Figure STREET CONVERSIONS 6 Study Area Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG6_two-way.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study; CCDC Streetscape Project Listings

Downtown Boise Implementation Plan | 11

Tww o- ay Street Conversions Street is converted (such as a relief to existing traffic congestion on south- The current street network in downtown has been criticized as confusing bound 9th Street at Front Street) but those were not specifically reviewed due to the combination of one-way and two-way streets, and more spe- in this analysis. cifically only certain blocks being one-way. The DBIP sought to identify which existing one-way streets would help improve wayfinding and traffic Considering no significant operational impacts were identified for convert- circulation without compromising mobility or intersection traffic opera- ing 13th Street, the project team reviewed other considerations with the tions. Based on the evaluation completed and input received, the following conversion besides just traffic operations. These considerations give both streets have been designated for the one-way to two-way conversion: pros and cons for the two-way conversion. To inform the decision process, Table 2 lists these other factors for consideration. 3rd Street (State Street to Main Street) ▪▪ Table 2 – Other Considerations for 13th Street Two-Way Conversion 4th Street (State Street to Main Street) ▪▪ Advantages Disadvantages ▪▪8th Street (Jefferson to Bannock Street) There are no significant impacts to Will require the removal of on- ▪▪ Note that in addition to enhancing vehicular circulation, traffic operations street parking between Jefferson the conversion of this section of 8th Street allows for bike Street and Idaho Street (on the west lanes to be provided in both directions (northbound and side) and between Idaho Street and southbound) to connect the new Jefferson Street bike Main Street (on the east side) to ac- facilities with the heavily utilized 8th Street bicycle corridor. commodate needed turn lanes Converting this block to two-way travel may require Conversion will improve overall con- Will require the construction of an reconfiguration of the signal at the 8th Street/Bannock nectivity within this portion of the exclusive southbound right turn Street intersection and the alignment of southbound 8th downtown network lane at Front Street Street will have to be maintained through that intersection. However, providing bike lanes in the same direction of travel Conversion will provide a simpler, There is limited curb to curb width less confusing environment since so, while two-way flow will accom- as vehicles is a preferred solution to a contraflow bike lane Pedestrians and cyclists on 8th Street given the potential conflicts of that lane with on-street the full extents of 13th Street will modate cyclists in the regular travel parking. be two-way lane, there is not enough space to provide exclusive bike lanes while ▪▪11th Street (State Street to Main Street) maintaining on-street parking 12th Street (State Street to Front Street) Conversion will provide another There will likely be restrictions on ▪▪ continuous north/south route left-turns on to 13th Street from 13th Street (State Street to Main Street) through downtown and to access westbound State Street during the ▪▪ key destinations (such as the PM peak period since an exclusive Connector) left-turn lane cannot be provided ▪▪14th Street (State Street to Main Street) Based on balancing all these considerations and the significant public sup- ▪▪Jefferson Street (1st Street to 16th Street) port for the conversion of 13th Street, the project team ended with a rec- ommendation to include the conversion of 13th Street as a project within The proposed two-way conversions are shown in Figure 6. Detailed geo- the DBIP. The detailed assessment of the 13th Street two-way conversion is metric conceptual layouts of these streets in two-way configuration are provided as Appendix E to this report. provided in Appendix D to this report. Proposed bicycle improvements and two-way conversions will require the T- WO WAY CONVERSION OF 13TH STREET removal of some street parking on 5th, 13th, 15th and Jefferson Streets. ACHD and the City of Boise will continue to work with affected parties on The recommended two-way conversion of 13th Street was only reached solutions to mitigate parking impacts in these areas. after careful consideration between the impacts and benefits that were expected to result. Given its connection to I-184 (the Connector) and to residential areas within the North End, the impact to traffic operations and traffic routing was evaluated in detail including simulation modeling of -traf fic operations along 13th Street if it were converted to two-way operation. The results of this detailed evaluation indicated that the conversion of 13th Street to two-way operations would not result in any significant impacts to traffic operations provided certain intersection and signal timing improve- ments were included. From a purely traffic operations perspective, there is no presiding argument for or against the conversion of 13th Street to two- Pedestrians on 9th and Bannock way traffic flow. No significant traffic operational impacts were identified but neither were any significantly traffic operational benefits. There may be other traffic operational benefits that will be seen in the network if 13th

12 | Kittelson & Associates, Inc.

Ite n ers cTION Improvements Intersection On-Street Parking Impacts Other Considerations/ SEU Q ENCING & COORDINATION Notes With the implementation of all the previous projects mentioned, the in- Proper coordination and sequencing of the projects identified becomes the tersections affected by each will require attention to accommodate these 11th Street/ Loss of 4 parking spaces Current westbound ▪▪(1-2 on the north, south, ▪▪right-turn lane (from principal guidance of this effort. Downtown Boise was examined on a block changes. Many will involve minor changes such as changes to signing or Grove Street by block basis to combine projects from different agencies to be worked pavement markings, however some of the more major improvements and west legs for splitter Grove to 11th) would not island and pedestrian be needed with a mini- on during the same construction period. This coordination aimed to bring involve signal installation or conversion to a mini-roundabout. Candidate ramps) roundabout and could be together planned roadwork and maintenance schedules from ACHD, mini-roundabout locations were initially determined from intersection vol- replaced with 2 on-street streetscape projects from CCDC, and utility work within the right-of-way. umes and lane configurations. A field investigation of the mini-roundabout Elimination of the parking spaces With those projects serving as a base, elements of the bicycle network and candidate locations was conducted to identify potential parking impacts ▪▪ westbound right-turn Current diagonal two-way conversions would occur on those same blocks. All of the projects as well as other challenges or considerations for their implementation. The lane could result in two ▪▪intersection width is identified in the DBIP are planned to be completed between ACHD’s Fiscal candidate mini-roundabout locations and findings from the field review are additional 2 parking approximately 98’ (mini- Year 2014 and 2019. shown in Table 3. spaces on the west leg roundabout would fit (north side of Grove within this area without Sequencing was planned based on logical implementation of projects, The intersection at 3rd Street/Bannock Street is anticipated to be the first Street) to off-set the additional width needed) identified priority needs, minimizing disruptions and impacts on an area conversion to a mini-roundabout in 2014. This project to serve as a pilot above loss basis, and funding availability and allocation. Key considerations in devel- test for how drivers and cyclists will interact with the new intersection 12th Street/ Loss of 6 to 7 parking Potential lamp post oping the sequencing plan were: type. Intersection improvements are further detailed in the Sequencing & Grove Street ▪▪spaces (1-2 on each leg ▪▪impacts on NW corner Coordination Section and in Appendix D. for splitter island and West side of 12th ▪▪Completing work on Capitol Boulevard prior to the Broadway pedestrian ramps) ▪▪Street (Grove Street to Bridge improvement project so that both river crossings would Table 3 – Candidate Mini-roundabout Locations Front Street) curb to be not be under construction at the same time, Intersection On-Street Parking Impacts Other Considerations/ examined for setback Notes Current diagonal ▪▪Having fewer overall downtown roadway projects occurring ▪▪intersection width is in 2015 when the Broadway Bridge improvement project is 3rd Street/ ▪▪Loss of 8 to 10 parking ▪▪Current intersection approximately 78’ (mini- underway, Jefferson Street spaces (approximately diagonal width is only 59’ roundabout would fit 2-3 on each leg for Roundabout within this area without Holding improvements and maintenance work on Broadway- increased width, splitter ▪▪implementation would additional width needed) ▪▪ islands, and pedestrian Avenue B until 2016 after the Broadway Bridge project is require curb adjustments completed (it is recommended this be reviewed again once it is ramps) to provide enough width 14th Street/ ▪▪Loss of 6 to 7 parking ▪▪Driveway challenges at for an 80’ inscribed circle Grove Street spaces (1-2 on each leg SW, SE, and NE corners determined if the Broadway Bridge project will fully close the for splitter islands and (will require further bridge or if traffic will be maintained across the bridge during 3rd Street/ Loss of 4 parking spaces May require tree removal pedestrian ramps) examination to ensure construction), Bannock Street ▪▪(1 to 2 on each leg for ▪▪on SE, SW, and NE parking circulation and splitter islands and corners for pedestrian access is maintained) pedestrian ramps) ramps ▪▪Completing projects associated with areas of CCDC streetscape ▪▪Current diagonal improvements prior to 2017 (CCDC’s central district sunset), and ▪▪Tree removal could intersection width is be mitigated with approximately 80’ (mini- Focusing work on State Street later within the five to sevenyear adjustments to crosswalk roundabout would fit ▪▪ placement within this area without time period once two-way conversions and other circulation improvements have been completed. Current diagonal additional width needed) ▪▪intersection width is 12th Street/ Loss of 6 to 8 parking There are opportunities approximately 83’ (mini- Bannock Street ▪▪spaces (1-2 on each leg ▪▪for access modifications The identified sequencing of projects is summarized in Figures 7 through 11 roundabout would fit for splitter islands and on the east leg to with each graphic highlighting a year of projects within the downtown study within this area without pedestrian ramps) minimize on street area. Figure 12 shows and details the parking impacts anticipated as a result additional width needed) parking loss and improve of the projects shown in Figures 7 through 11. Cost estimates for the ACHD 10th Street/ Loss of 6 parking Current diagonal circulation portion of the work outlined over the five to seven year implementation Grove Street ▪▪spaces (1-2 on each leg ▪▪intersection width is Current diagonal period is provided in Appendix F. for splitter island and approximately 84’ (mini- ▪▪intersection width is pedestrian ramps) roundabout would fit approximately 83’ (mini- within this area without roundabout would fit It is possible that additional width needed) within this area without ▪▪approximately 2 parking additional width needed) spaces could added on Grove Street with consolidation of existing underutilized curb cuts

Downtown Boise Implementation Plan | 13

Downtown Boise Implementation Plan August 2013

N 30TH ST W THATCHER ST W WASHINGTON ST

N 19TH ST

N 27TH ST N 26TH ST 26TH N

N 29TH ST W UNION ST N 12TH ST W FORT ST N

W IDAHO ST ST 24TH N N 25TH ST 25TH N

N 22ND ST N 22ND N 28TH ST 28TH N N 23RD ST 23RD N N 18TH ST N 11TH ST E MOUNTAIN COVE RD N 17TH ST N VA HOSPITAL LOOP W HAYS ST W MAIN ST N 16TH ST N 10TH ST S 30TH ST N 15TH ST W FRANKLIN ST N 14TH ST N 6TH ST

N 13TH ST N 12TH ST

S 22NDS ST S 27TH ST 27TH S

S 23RDS ST W IDAHO ST G S 17TH ST SSL

S 25TH ST 25TH S BL S 24TH ST 24TH S SL W ARK ST S 18TH ST G N 7TH ST W FAIRVIEW AVE SL N FRONT ST BL S 16TH ST INTERSTATE 184 G INTERSTATE 184 W GROVE ST SL G N 10TH ST W WASHINGTON ST BL W JEFFERSON ST SL S 17TH ST G G BL SL N COLLINS RD S AMERICANA BLVD G W SHORELINE DR S 15TH ST SL BL N 9TH ST BL S 12TH ST N 10TH ST N 4TH ST W SPA ST W GRAND AVE SL N ROBBINS RD N 8TH ST SSL BL BL N 5TH ST S 14TH ST N 3RD ST SL N 6TH ST E SANTA MARIA DR W FRONT SST 10TH ST W STATE ST SSL SL BL SL E ALDAPE COVE RD BL E GARRISON RD N MOUNTAIN COVERD S 13TH ST N FORT PL

N HAPPY DR N HOUSTON RD W RIVER ST SL SSL BL SL N SAN JUAN DR N AMERICANA BLVD W BORAH ST E SHAW MOUNTAIN RD

S 12TH ST SL SSL E FORT ST E RESERVE ST SL M W BANNOCK ST W MILLER ST SSL BL SL SL SSL W GROVE ST E LOGAN ST SL W BROAD ST G SSL E JEFFERSON ST S ASH ST BL S PIONEER ST SL SL N FELIPE SAN DR SL W LEE ST G E KRALL ST S 6TH ST E BANNOCK ST S 9TH ST BL N 2ND ST SL

SL AVE E AVENUE N

W BROAD STS 5TH ST E IDAHO ST N AVENUE D AVE D AVENUE N S 8TH ST SL N 1ST ST W EMERALD ST BL E MCKINLEY ST E FRANKLIN ST SL S 2ND ST W MYRTLE ST SL BL E WASHINGTON ST

SL

N FLUME ST E STATE ST W MEADOW DR S 4TH ST E REDWOOD CT SL N BRUCE AVE W CRESCENT RIM DR ROADWAY IMPROVEMENTS N ELM AVE S CAPITOL BLVD S 2ND ST M - Mini-roundabout W ROYAL BLVD S 3RD ST N STRAUGHAN AVE BL E FRONT ST G - Signal Installation/Modification S 9TH ST N WALNUT ST N MAPLE AVE SSL - Sigining/Striping/Lighting ST PACIFIC N W MORRIS HILL RD N LOCUST ST S DALE ST S LA POINTE ST W JULIA DAVIS DR E WARM SPRINGS AVE W CESAR CHAVEZ LN E MYRTLE ST E BANNOCK ST

S LUSK ST BIKE IMPROVEMENTS ST N LATAH S BRUCE LN N PIERCE ST BL - Install Bike Lanes W SHERWOOD ST SL - Install Shared Lane Markings S STRAUGHAN AVE S 9TH ST CBL - Install Contraflow Bike Lane E HOLLY ST

N ATLANTIC STATLANTIC N

N OWYHEE ST IBL - Install ImprovedW TULARA Bike DRLane CSL - Convert to Shared Lane Markings E PARK BLVD E LEWIS ST

W KIPLING RD S EARLE ST

S LOIS AVE AVE BROADWAY S S WALNUT ST

S BRADY ST W ALPINE ST S LUSK PL

W BOISE AVE Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, and the GIS User Community

Road Work/Maintenance Intersection Improvement DOWNTOWN PROJECT SEQUENCING Figure Streetscape Study Area 2014 PROJECTS 7 Two-way Conversion Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG7_sequencing_2014.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study; CCDC Streetscape Project Listings

14 | Kittelson & Associates, Inc.

Downtown Boise Implementation Plan August 2013

N 30TH ST W THATCHER ST

N 19TH ST

N 27TH ST N 26TH ST 26TH N

N 29TH ST W UNION ST N 12TH ST W FORT ST N

W IDAHO ST ST 24TH N N 25TH ST 25TH N

N 22ND ST N 22ND N 28TH ST 28TH N N 23RD ST 23RD N N 13TH ST N 18TH ST N 14TH ST N 11TH ST E MOUNTAIN COVE RD N 17TH ST N VA HOSPITAL LOOP W IDAHO ST W HAYS ST W MAIN ST N 16TH ST W FRANKLINN 10TH ST ST G S 30TH ST N 15TH ST M

N 6TH ST

N 12TH ST SL G

S 22NDS ST

S 27TH ST 27TH S SSL

S 23RDS ST

S 17TH ST SL

S 25TH ST 25TH S G S 24TH ST 24TH S G N 11TH ST W ARK ST S 18TH ST SL N 7TH ST W FAIRVIEW AVE M N FRONT ST G S 16TH ST G INTERSTATE 184 SL INTERSTATE 184 N 9TH ST G N 10TH ST M SL W STATE ST N 6TH ST S 17TH ST W GROVE ST N 12TH ST SL W JEFFERSON ST N COLLINS RD BL N 5THW STWASHINGTON ST S AMERICANA BLVD W SHORELINE DR SL S 15TH ST BL W MAIN ST S 12TH ST W BANNOCK ST W SPA ST W GRAND AVE SL BL BL N ROBBINS RD N 8TH ST BL S 14TH ST SL E SANTA MARIA DR S 11THW ST FRONT SST 10TH ST BL BL SL BL E ALDAPE COVE RD E GARRISON RD N MOUNTAIN COVERD S 13TH ST N 4TH ST N FORT PL BL N HAPPY DR N HOUSTON RD BL SL N CAPITOL BLVD BL N SAN JUAN DR N AMERICANA BLVD W BORAH ST E SHAW MOUNTAIN RD N 3RD ST E RESERVE ST S 12TH ST W MAIN BLST SL E FORT ST BL W MILLER ST W GROVE ST SL W BROAD ST BL N 2ND ST E LOGAN ST BL E JEFFERSON ST S PIONEER ST S ASH ST SL

N FELIPE SAN DR

W RIVER ST BL N 1ST ST E KRALL ST W LEE ST S 4TH ST SL

S 9TH ST BL E BANNOCK ST N AVENUE E AVE E AVENUE N

S 8TH ST BL AVE D AVENUE N BL W BROAD ST W EMERALD ST SL E MCKINLEY ST S 2ND ST E FRANKLIN ST W MYRTLE ST BL N AVENUE C AVE E WASHINGTON ST

S CAPITOL BLVD S 3RD ST

N FLUME ST E STATE ST W MEADOW DR E REDWOOD CT S 4TH ST N BRUCE AVE W CRESCENT RIM DR ROADWAY IMPROVEMENTS N ELM AVE S 2ND ST M - Mini-roundabout W ROYAL BLVD N STRAUGHAN AVE E FRONT ST G - Signal Installation/Modification S 9TH ST N WALNUT ST N MAPLE AVE SSL - Sigining/Striping/Lighting ST PACIFIC N W MORRIS HILL RD N LOCUST ST S DALE ST S LA POINTE ST W JULIA DAVIS DR E WARM SPRINGS AVE W CESAR CHAVEZ LN E MYRTLE ST E BANNOCK ST

S LUSK ST BIKE IMPROVEMENTS ST N LATAH S BRUCE LN N PIERCE ST BL - Install Bike Lanes W SHERWOOD ST SL - Install Shared Lane Markings S STRAUGHAN AVE S 9TH ST CBL - Install Contraflow Bike Lane E HOLLY ST

N ATLANTIC STATLANTIC N

N OWYHEE ST IBL - Install ImprovedW TULARA Bike DRLane CSL - Convert to Shared Lane Markings E PARK BLVD E LEWIS ST

W KIPLING RD S EARLE ST

S LOIS AVE AVE BROADWAY S S WALNUT ST

S BRADY ST W ALPINE ST S LUSK PL

W BOISE AVE Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, and the GIS User Community

Road Work/Maintenance Intersection Improvement DOWNTOWN PROJECT SEQUENCING Figure Streetscape Study Area 2015 PROJECTS 8 Two-way Conversion Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG8_sequencing_2015.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study; CCDC Streetscape Project Listings

Downtown Boise Implementation Plan | 15

Downtown Boise Implementation Plan August 2013

N 30TH ST W JEFFERSON ST W THATCHER ST

N 19TH ST

N 27TH ST N 26TH ST 26TH N

N 29TH ST W WASHINGTON ST W UNION ST N 12TH ST W FORT ST N

W IDAHO ST ST 24TH N G N 25TH ST 25TH N

N 22ND ST N 22ND N 28TH ST 28TH N N 23RD ST 23RD N BL N 11TH ST N 18TH ST E MOUNTAIN COVE RD N VA HOSPITAL LOOP G W HAYS ST W MAIN ST BL N 10TH ST N 17TH ST S 30TH ST SSL W FRANKLIN ST

N 6TH ST BL N 16TH ST G

S 22NDS ST S 27TH ST 27TH S S 23RDS ST BL N 15TH ST S 17TH ST SSL

N 11TH ST

S 25TH ST 25TH S S 24TH ST 24TH S S 18TH ST BL W ARK ST N 14TH ST G N 7TH ST W FAIRVIEW AVE N 10TH ST N FRONT ST BL S 16TH ST N 13TH ST INTERSTATE 184 G W STATE ST W GROVE ST INTERSTATE 184 BL

G BL W IDAHO ST W BANNOCK ST S 17TH ST BL N 12TH ST CSL

BL N COLLINS RD W WASHINGTON ST BL S AMERICANA BLVD BL N 5TH ST W SHORELINE DR CSL S 15TH ST M BL

W SPA ST W GRAND AVE G M CSL W MAIN N ST 9TH ST N ROBBINS RD BL S 14TH ST G M N 8TH ST BL E SANTA MARIA DR CSL BL E ALDAPE COVE RD S 11TH ST E GARRISON RD N MOUNTAIN COVERD S 13TH ST N 6TH ST N 4TH ST N FORT PL N HAPPY DR N HOUSTON RD M W RIVER ST W FRONT ST N CAPITOL BLVD N SAN JUAN DR N AMERICANA BLVD W BORAH ST BL E SHAW MOUNTAIN RD

S 12TH ST E FORT ST E RESERVE ST BL W MILLER ST CBL

W BROAD ST N 2ND ST BL E LOGAN ST SL N 3RD ST S PIONEER ST S ASH ST E JEFFERSON ST

N FELIPE SAN DR SL W MAIN ST N 1ST ST E KRALL ST S 6TH ST S 4TH ST E BANNOCK ST S 9TH ST E IDAHO ST SL BL

S 10TH ST S 5TH ST AVE E AVENUE N N AVENUE D AVE D AVENUE N S 8TH ST W EMERALD ST W BROAD ST E MCKINLEY ST E FRANKLIN ST BL W MYRTLE ST E WASHINGTON ST

S CAPITOL BLVD S 3RD ST BL

N FLUME ST E STATE ST W MEADOW DR E REDWOOD CT S 4TH ST N BRUCE AVE W CRESCENT RIM DR ROADWAY IMPROVEMENTS N ELM AVE S 2ND ST M - Mini-roundabout W ROYAL BLVD N STRAUGHAN AVE E FRONT ST G - Signal Installation/Modification S 9TH ST N WALNUT ST BL N MAPLE AVE SSL - Sigining/Striping/Lighting ST PACIFIC N W MORRIS HILL RD N LOCUST ST S DALE ST S LA POINTE ST W JULIA DAVIS DR W CESAR CHAVEZ LN S AVENUE A AVE E WARM SPRINGS AVE E MYRTLE ST E BANNOCK ST

S LUSK ST BIKE IMPROVEMENTS ST N LATAH S BRUCE LN BL N PIERCE ST BL - Install Bike Lanes W SHERWOOD ST SL - Install Shared Lane Markings S STRAUGHAN AVE S 9TH ST E HOLLY ST CBL - Install Contraflow Bike Lane E PARK BLVD

N ATLANTIC STATLANTIC N

N OWYHEE ST IBL - Install ImprovedW TULARA Bike DRLane CSL - Convert to Shared Lane Markings E LEWIS ST

W KIPLING RD BL S LOIS AVE S EARLE ST S WALNUT ST

S BRADY ST W ALPINE ST S LUSK PL

W BOISE AVE Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, and the GIS User Community

Road Work/Maintenance Intersection Improvement DOWNTOWN PROJECT SEQUENCING Figure Streetscape Study Area 2016 PROJECTS 9 Two-way Conversion Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG9_sequencing_2016.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study; CCDC Streetscape Project Listings

16 | Kittelson & Associates, Inc.

Downtown Boise Implementation Plan August 2013

N 30TH ST W THATCHER ST

N 19TH ST

N 27TH ST N 26TH ST 26TH N

N 29TH ST W WASHINGTON ST W UNION ST N 12TH ST W FORT ST N

W IDAHO ST ST 24TH N N 25TH ST 25TH N

N 22ND ST N 22ND N 28TH ST 28TH N N 23RD ST 23RD N N 18TH ST N 11TH ST E MOUNTAIN COVE RD N 17TH ST G N VA HOSPITAL LOOP W HAYS ST W MAIN ST N 16TH ST N 10TH ST S 30TH ST N 15TH ST W FRANKLIN ST

N 6TH ST

N 13TH ST G

S 22NDS ST S 27TH ST 27TH S

S 23RDS ST

S 17TH ST W IDAHO ST

N 14TH ST S 25TH ST 25TH S

S 24TH ST 24TH S N 11TH ST W ARK ST S 18TH ST W STATE ST N 7TH ST W FAIRVIEW AVE N FRONT ST S 16TH ST INTERSTATE 184 W GROVE ST INTERSTATE 184 N 10TH ST

W BANNOCK ST S 17TH ST W WASHINGTON ST N 12TH ST SL N COLLINS RD S AMERICANA BLVD W SHORELINE DR S 15TH ST SL W MAIN ST S 12TH ST W SPA ST W GRAND AVE N 9TH ST SL N ROBBINS RD

S 14TH ST N 5TH ST SL N 8TH ST N 6TH ST E SANTA MARIA DR S 11THW ST FRONT SST 10TH ST G W JEFFERSON ST SL E ALDAPE COVE RD E GARRISON RD N MOUNTAIN COVERD S 13TH ST

N HAPPY DR N HOUSTON RD W RIVER ST N CAPITOL BLVD SL N SAN JUAN DR N AMERICANA BLVD W BORAH ST E SHAW MOUNTAIN RD S 12TH ST W MAIN ST E RESERVE ST

N 4TH ST SL W MILLER ST W GROVE ST

W BROAD ST E LOGAN ST N 3RD ST S PIONEER ST S ASH ST

SL N FELIPE SAN DR N 2ND ST W LEE ST N 1ST ST E KRALL ST S 6TH ST S 4TH ST E BANNOCK ST

S 9TH ST E IDAHO ST N AVENUE E AVE E AVENUE N

S 5TH ST AVE D AVENUE N S 8TH ST W EMERALD ST W BROAD ST E JEFFERSON ST E MCKINLEY ST S 2ND ST E FRANKLIN ST W MYRTLE ST N AVENUE C AVE E WASHINGTON ST

S CAPITOL BLVD S 3RD ST

E STATE ST W MEADOW DR E REDWOOD CT S 4TH ST

N BRUCE AVE W CRESCENT RIM DR ROADWAY IMPROVEMENTS N ELM AVE S 2ND ST M - Mini-roundabout W ROYAL BLVD N STRAUGHAN AVE E FRONT ST G - Signal Installation/Modification S 9TH ST N WALNUT ST N MAPLE AVE SSL - Sigining/Striping/Lighting ST PACIFIC N W MORRIS HILL RD N LOCUST ST S DALE ST S LA POINTE ST W JULIA DAVIS DR E WARM SPRINGS AVE W CESAR CHAVEZ LN E MYRTLE ST E BANNOCK ST

S LUSK ST BIKE IMPROVEMENTS ST N LATAH S BRUCE LN N PIERCE ST BL - Install Bike Lanes W SHERWOOD ST SL - Install Shared Lane Markings S STRAUGHAN AVE S 9TH ST CBL - Install Contraflow Bike Lane E HOLLY ST

N ATLANTIC STATLANTIC N

N OWYHEE ST IBL - Install ImprovedW TULARA Bike DRLane CSL - Convert to Shared Lane Markings E PARK BLVD E LEWIS ST

W KIPLING RD S EARLE ST

S LOIS AVE AVE BROADWAY S S WALNUT ST

S BRADY ST W ALPINE ST S LUSK PL

W BOISE AVE Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, and the GIS User Community

DOWNTOWN PROJECT Figure Road Work/Maintenance Intersection Improvement SEQUENCING 2017 PROJECTS Streetscape Study Area 10 Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG10_sequencing_2017.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study; CCDC Streetscape Project Listings

Downtown Boise Implementation Plan | 17

Downtown Boise Implementation Plan August 2013

N 30TH ST W THATCHER ST W WASHINGTON ST

N 19TH ST

N 27TH ST N 26TH ST 26TH N

N 29TH ST W UNION ST N 12TH ST W FORT ST N

W IDAHO ST ST 24TH N N 25TH ST 25TH N

N 22ND ST N 22ND N 28TH ST 28TH N N 23RD ST 23RD N N 18TH ST N 16TH ST IBL N 11TH ST E MOUNTAIN COVE RD N 17TH ST N VA HOSPITAL LOOP W HAYS ST W MAIN ST N 10TH ST IBL S 30TH ST IBL W FRANKLIN ST N 14TH ST N 6TH ST

N 13TH ST N 12TH ST IBL

S 22NDS ST S 27TH ST 27TH S

S 23RDS ST

S 17TH ST N 15TH ST

S 25TH ST 25TH S IBL

S 24TH ST 24TH S N 11TH ST W ARK ST S 18TH ST N 7TH ST W FAIRVIEW AVE N FRONT ST IBL INTERSTATE 184 N 10TH ST W STATE ST W GROVE ST INTERSTATE 184 IBL

W BANNOCK ST S 17TH ST W WASHINGTON ST N 12TH ST S AMERICANA BLVD N COLLINS RD IBL

W SHORELINE DR IBL S 15TH ST IBL S 12TH ST N 10TH ST W SPA ST W GRAND AVE W MAIN NST 9TH ST N ROBBINS RD

S 14TH ST N 5TH ST N 8TH ST N 6TH ST E SANTA MARIA DR S 11THW ST FRONT SST 10TH ST W JEFFERSON ST W IDAHO ST E ALDAPE COVE RD E GARRISON RD N MOUNTAIN COVERD S 13TH ST N FORT PL

N HAPPY DR N HOUSTON RD W RIVER ST N CAPITOL BLVD N SAN JUAN DR N AMERICANA BLVD W BORAH ST E SHAW MOUNTAIN RD

S 12TH ST E FORT ST E RESERVE ST

W MILLER ST N 4TH ST SL W MAIN ST W GROVE ST E LOGAN ST N 3RD ST E JEFFERSON ST S PIONEER ST S ASH ST SL

N FELIPE SAN DR N 2ND ST W LEE ST N 1ST ST E KRALL ST S 9TH ST SL S 6TH ST E BANNOCK ST E IDAHO ST

S 5TH ST AVE E AVENUE N S 8TH ST SL AVE D AVENUE N W EMERALD ST E MCKINLEY ST S 2ND ST E FRANKLIN ST W MYRTLE ST SL N AVENUE C AVE E WASHINGTON ST

S CAPITOL BLVD SL S 3RD ST

N FLUME ST E STATE ST S 4TH ST E REDWOOD CT W MEADOW DR SL

N BRUCE AVE W CRESCENT RIM DR ROADWAY IMPROVEMENTS N ELM AVE S 2ND ST M - Mini-roundabout W ROYAL BLVD N STRAUGHAN AVE E FRONT ST G - Signal Installation/Modification S 9TH ST N WALNUT ST N MAPLE AVE SSL - Sigining/Striping/Lighting ST PACIFIC N W MORRIS HILL RD N LOCUST ST S DALE ST S LA POINTE ST W JULIA DAVIS DR E WARM SPRINGS AVE W CESAR CHAVEZ LN E MYRTLE ST E BANNOCK ST

S LUSK ST BIKE IMPROVEMENTS ST N LATAH S BRUCE LN N PIERCE ST BL - Install Bike Lanes W SHERWOOD ST SL - Install Shared Lane Markings S STRAUGHAN AVE S 9TH ST CBL - Install Contraflow Bike Lane E HOLLY ST

N ATLANTIC STATLANTIC N

N OWYHEE ST IBL - Install ImprovedW TULARA Bike DRLane CSL - Convert to Shared Lane Markings E PARK BLVD E LEWIS ST

W KIPLING RD S EARLE ST

S LOIS AVE AVE BROADWAY S S WALNUT ST

S BRADY ST W ALPINE ST S LUSK PL

W BOISE AVE Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, and the GIS User Community

DOWNTOWN PROJECT Road Work/Maintenance SEQUENCING Figure Study Area 2018 PROJECTS Streetscape 11 Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG11_sequencing_2018.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study; CCDC Streetscape Project Listings

18 | Kittelson & Associates, Inc.

Downtown Boise Implementation Plan September 2013

N 30TH ST W THATCHER ST

N 4TH ST

N 7TH ST N 19TH ST

N 27TH ST N 26TH ST

N 29TH ST W UNION ST N 12TH ST N W IDAHO ST

N 28TH ST

N 25TH ST N 24TH ST

N 6TH ST

N 23RD ST N 22ND ST N 18TH ST

N 11TH ST N5TH ST

N 17TH ST N VA HOSPITAL LOOP

N 16TH ST W HAYS ST N 10TH ST N 15TH ST W WASHINGTON ST S 30TH ST N 14TH ST W FRANKLIN ST

N 13TH ST N 12TH ST

S 23RD ST

S S 22ND ST S S 27TH ST

S 17TH ST S 17TH ST W IDAHO ST E MOUNTAIN COVE RD

S S 25TH ST N 11TH ST W ARK ST S 18TH ST

W FAIRVIEW AVE S 24TH ST N 7TH ST N FRONT ST S 16TH ST W MAIN ST INTERSTATE 184 W STATE ST INTERSTATE 184 W GROVE ST N 10TH ST N 9TH ST

S 17TH ST N 12TH ST W WASHINGTON ST

W BANNOCK ST N COLLINS RD W FORT ST S AMERICANA BLVD S 15TH ST N 6TH ST S 12TH ST W MAIN ST

W SPA ST W GRAND AVE N ROBBINS RD

Parking Impacts N SCOUT LN W SHORELINE DR N 5TH ST N 8TH ST

S 11TH ST S 10TH ST Street From To Block Side No. Spaces Space Type(s) W FRONT ST E SANTA MARIA DR

W JEFFERSON ST N MOUNTAIN COVE RD W IRVING ST E GARRISON RD E ALDAPE COVE RD 5th Myrtle Broad east 12 time-limitedS 14TH ST S 13TH ST N 4TH ST N FORT PL N AMERICANA BLVD N CAPITOL BLVD 5th Broad Front east 8 unlimited W RIVER ST N HOUSTON RD W BORAH ST N SAN JUAN DR 5th Front Grove east 9 metered (+loading zone) S 12TH ST E RESERVE ST E FORT ST S 9TH ST N MARSHALL ST W MILLER ST 5th Grove Main east 7 metered (+loading zone) W LEE ST E KRALL ST W BROAD ST W GROVE ST N 3RD ST E LOGAN ST E FLORAL LN

S ASH ST W MAIN ST 5th Main Idaho east 9 metered S PIONEER ST E JEFFERSON ST

N SAN FELIPE DR

N 2ND ST 5th Idaho Bannock east 10 metered N 1ST ST W LEE ST S 6TH ST E KRALL ST E BANNOCK ST E IDAHO ST 5th Bannock Jefferson east 5 metered AVENUE N EAVE

S 5TH ST N AVENUEN AVE D

S 8TH ST N AVENUE N AVE H W EMERALD ST 13th Main Idaho east 7 time-limited W BROAD ST E MCKINLEY ST S 2ND ST E FRANKLIN ST W MYRTLE ST 13th Idaho Bannock west 8 unlimited (+loading zone) N AVENUE C AVE

S CAPITOL BLVD E WASHINGTON ST S 3RD ST

13th Bannock Jefferson west 3 unlimited (time-limited) N FLUME ST W MEADOW DR E REDWOOD CT E STATE ST 15th Bannock Jefferson east 7 unlimited W ROYAL BLVD S 4TH ST N BRUCE AVE

15th Jefferson State eastW CRESCENT RIM DR 4 unlimited N ELM AVE S 2ND ST Jefferson N STRAUGHAN AVE B 1st north 19 time-limited S 9TH ST E FRONT ST N WALNUT ST N PACIFIC ST N MAPLE AVE S LA POINTE ST Jefferson B 1stATLANTICN ST south 3 unlimited S DALE ST W MORRIS HILL RD W ISLAND AVE E BANNOCK ST N LOCUST ST

Jefferson 1st 2nd north 12 time-limited S AVENUE A AVE W JULIA DAVIS DR

N LATAH ST S LUSK ST S 9TH ST E WARM SPRINGS AVE S BRUCE LN N PIERCE ST Jefferson 2nd 3rd north 12 time-limited E MYRTLE ST E LEWIS ST Jefferson 3rd 4thN ARCADIA ST north 13 unlimited W SHERWOOD ST S STRAUGHAN AVE

Jefferson 5th 6thATLANTICN ST north 12 metered E HOLLY ST

Jefferson 6thW TULARA Capitol DR northN OWYHEE ST 8 metered N HAINES ST

N PICARDY PL

S S BROADWAY AVE Jefferson 14th 15th north 13 unlimited E PARK BLVD E LEWIS ST

W KIPLING RD S LOIS AVE S EARLE ST Jefferson 15th 16th north 11 unlimited W CESAR CHAVEZ LN S WALNUT ST S VILLA PL S BRADY ST

W BOISE AVE W ALPINE ST S LUSK PL Total Spaces 192 W BOISE AVE

S PIERCE PL S MIKE ST Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, and the GIS UserS HAINES PL Community

On-Street Parking Impacts Study Area PARKING IMPACTS DUE TO Figure Due to bike lanes TWO-WAY STREET CONVERSIONS Due to two-way street conversion AND BIKE LANES 12 Mini roundabout locations Downtown Boise Implementation Plan H:\projfile\13091 Downtown- Boise ImplementationPlan\gis\figs\DBIP_Report_Figs\13091_DBIP_FIG12_parking_impacts.mxd Source: ACHD GIS Database; ACHD Five-Year Work Plan; ITD Projects; CCDC Downtown Boise Two-Way Conversion Study

Downtown Boise Implementation Plan | 19

COORDINATION OPTIONS DBIP GIS TOOL There are several coordination options that exist for project implementa- As part of the work previously presented, the DBIP produced a GIS (geo- tion where multiple agencies are involved. Of the recommendations in this graphic information system) geodatabase. This geodatabase serves as a plan, the most common coordination will be between ACHD and CCDC on compilation of geographically accurate information that: roadways where both streetscape and other improvements are planned. In these situations, the following coordination options exist: serves as a consolidated location for all project information, can ▪▪be used as a mapping tool; Keep ACHD and CCDC projects separate (i.e., have different ▪▪contacts) but ensure work is coordinated through collaboration organizes downtown into block lengths and allows relationships and oversight ▪▪to be determined, and; allows users to query information for a particular street extent ▪▪ In this example, ACHD would have a contract for the street ▪▪and see what projects are associated with it, all projects that maintenance or roadway improvement work and CCDC would are programmed, or all projects identified within a certain time have a contract for the streetscape improvement work and the frame; and shows all projects identified for parallel efforts (such two project managers would work collaborative to integrate as water or sewer lines). the work. Have one agency oversee all of the work (i.e., have it occur under All figures shown in this document were created with this GIS tool. ▪▪one contract) with the other agency serving as a project team member and with a cost sharing agreement in place The geodatabase can be used to superimpose information on a map to simultaneously show projects and their relationship to other projects and ▪▪ In this example, either ACHD or CCDC would have the contract other aspects of the downtown environment. The content of this geodata- for the entire scope of work (street maintenance, roadway base includes: improvements, and streetscape) and would oversee all the ACHD/ITD Projects (2013-2018), work under that contact. There would be a cost sharing ▪▪ Contraflow bike lane on 8th and Main Street agreement in place for the other agency to contribute the ▪▪ Planned roadway maintenance costs for their portion of the work and they would be closely ▪▪ Planned intersection improvements involved with the day-to-day project proceedings as a project team member. ▪▪CCDC Projects (2013-2018), The best option for coordination will be determined on a project-by- ▪▪Existing/proposed bicycle facilities, project basis depending on the scope of the work, the breakdown of work between agencies, and staff resources and availability. ▪▪Two-way street conversions, ▪▪Major downtown events, ▪▪Major land use and development projects, ▪▪Parking facilities, ▪▪Parks, ▪▪Land uses and zoning, ▪▪Roadway block information, ▪▪Transit stops and routes, ▪▪Major utilities, and ▪▪Public feedback from the public involvement process. The geodatabase contains all data presented in this document and is fur- Open house signage on 8th and Bannock ther detailed in Appendix G. The value and usefulness of this geodatabase is dependent upon keeping the information within it up to date as projects are completed and as new projects are identified over time.

20 | Kittelson & Associates, Inc. FL INA CONSIDERATIONS The recommendations and sequencing included in the DBIP were based on the best information available at the time of plan creation and possible within the project’s budget and timeframe. It is expected that the recom- mendations here may evolve over the five year horizon as project come on line, if new projects develop, or if funding opportunities change.

In addition, there are other on-going activities or items raised through this process that could not be addressed within the plan’s timeframe and scope that may influence, add to, or modify the recommendations that have been developed to this point. These include: Implementing wayfinding and signage along with the ▪▪implementation of the downtown bicycle network,

Reviewing existing traffic signal progression and traffic signal ▪▪timing plans within downtown Boise for opportunities to slow traffic and lower the progression speeds (potentially down to 20 miles per hour) on certain roadways where bicycles and multi- modal travel is encouraged, especially on Main Street and Idaho Street.,

Further evaluation of parking impacts associated with two-way ▪▪street and bicycle network recommendations and working the affected parties on parking management solutions (e.g. Jefferson Bicycle air station outside Whole Foods on Myrtle Street and Broadway Avenue Street),

Evaluating further two-way conversion and/or additional bicycle ▪▪improvements on particular routes (such as Idaho and Main Streets) (on-going as part of the City of Boise’s commissioned work with consultant Jeff Speck), and

Identifying opportunities for Low Impact Development ▪▪(LID) stormwater treatments with future downtown project implementation which will result with coordination and consolidation of work. These opportunities may present themselves with the overlap of major efforts between ACHD and CCDC such as the work proposed on State Street.

Cyclist on Jefferson Street and 10th Street Kittelson & Associates, Inc. 101 South Capitol Blvd, Suite 301 Boise, Idaho 83702 ph. 208.338.2683 Kittelson.com