Toronto Transit Commission / City of Toronto EGLINTON CROSSTOWN LIGHT RAIL TRANIST TRANSIT PROJECT ASSESSMENT ENVIRONMENTAL PROJECT REPORT
APPENDIX J –CONSOLIDATED TRAFFIC REPORT
Toronto Transit Commission (TTC)
TRANSIT PROJECT ASSESSMENT STUDY - CONSOLIDATED TRAFFIC REPORT
REPORT
FEBRUARY 2010
REPORT REPORT
Toronto Transit Commission (TTC) TRANSIT PROJECT ASSESSMENT STUDY - CONSOLIDATED TRAFFIC REPORT
TABLE OF CONTENTS INTRODUCTION
This report describes the preliminary traffic assessment of the future Light Rail Vehicle (LRV) operation along Eglinton Avenue, as part of the Eglinton Crosstown Light Rail Transit (ECLRT) INTRODUCTION ...... 1 Transit Project Assessment Study process. This assessment was completed in stages as the Transit Project Assessment Study progressed, based on consultation with Transit City Department SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY – OVERALL TRAFFIC and other Toronto Transit Commission staff, the Technical Advisory Committee, other stakeholders, ANALYSIS ...... 1-1 and the public. The analysis described in this report is the foundation for future preliminary and detailed design. SECTION 2: TRANSIT PROJECT ASSESSMENT STUDY – U-TURN TRAFFIC ANALYSIS ...... 2-1 The traffic analysis reports described in this report are organized into 4 sections:
SECTION 3: TRANSIT PROJECT ASSESSMENT STUDY – KEELE STATION BUS Section 1: Overall Traffic Analysis TERMINAL TRAFFIC ANALYSIS ...... 3-1 Section 2: U-Turn Traffic Analysis Section 3: Keele Station Bus Terminal Traffic Analysis SECTION 4: TRANSIT PROJECT ASSESSMENT STUDY – AIRPORT EXTENSION FEASIBILITY STUDY TRAFFIC ANALYSIS ...... 4-1 Section 4: Airport Extension Feasibility Study Traffic Analysis
The contents of each report can be summarized as follows:
Section 1: Transit Project Assessment Study – Overall Traffic Analysis The overall traffic analysis encompassed the ECLRT alignment along Eglinton Avenue for the original limits of the project from Renforth Drive to the west to Kennedy Road to the east. This report describes the initial traffic analysis conducted for existing conditions and future conditions with LRT implementation using Synchro 6.0 Traffic Signal Coordination Software package by Trafficware. This analysis consisted of two steps: an analysis of existing and future conditions to identify critical signalized intersections, followed by a detailed analysis of the critical signalized intersections.
Six critical signalized intersections were identified as follows:
Eglinton Avenue at Martin Grove Road; Eglinton Avenue at Kipling Avenue; Eglinton Avenue at Jane Street; Eglinton Avenue at Black Creek Drive; Eglinton Avenue at Wynford Drive; and Eglinton Avenue at Victoria Park Avenue.
This traffic analysis introduced the potential alternative design of prohibiting left turns at some major intersections. The left turns would then be re-routed to downstream “u-turn signals”.
The initial traffic analysis can be found in Section 1 – Transit Project Assessment Study – Overall Traffic Analysis.
It is important to note that since the analysis of the areas described in this report was superseded by further analysis, the recommendations presented in this specific report do not represent the final recommendations. Furthermore, a complete description of the analysis conducted at the intersection of Eglinton Avenue at Black Creek Drive is presented in Appendix M of the Environmental Project Report. Subsequent u-turn traffic analyses are described in Section 2.
February 2010 Page 1
February 2010 Page i. REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) TRANSIT PROJECT ASSESSMENT STUDY - CONSOLIDATED TRAFFIC REPORT TRANSIT PROJECT ASSESSMENT STUDY - CONSOLIDATED TRAFFIC REPORT
Section 2: Transit Project Assessment Study – U-Turn Traffic Analysis After completing the initial alignment studies, and holding early meetings with stakeholders, five alternatives were selected for further refinement and development. The route illustrated in Exhibit Following the completion of the initial overall traffic assessment, Transit City Group reviewed the 1 was recommended, as the evaluation process concluded that two major factors governed this feedback from TTC staff, the TAC, other stakeholders, and the public. The feedback indicated that selection: there was need for more detailed analysis of the signalized intersections that were candidates for the addition of “u-turn signals” or other mitigating measures. Therefore, detailed traffic analysis was This route offers the best benefit in terms of connection and transfer convenience to conducted to quantify the advantages and disadvantages of these mitigating measures. The ten Mississauga/GO BRT and LBPIA; and locations identified for potential changes were the intersections of Eglinton Avenue at: It has the fewest challenges in implementation, including shortest guideway span across Highway 401 and with no impacts to existing on/off ramps. Martin Grove Road Jane Street Kipling Avenue Victoria Park Avenue Exhibit 1: Recommended Airport Link Alignment Islington Avenue Pharmacy Avenue Royal York Road Warden Avenue Scarlett Road Birchmount Road
A detailed traffic-traveller analysis was conducted at the ten intersection study areas, comparing operation of traditional left turns to various left turn rerouting scenarios, with consideration to truck routing and high left turn volumes. The scenarios were compared based on the projected delays experienced by the LRVs, cross-street transit vehicles, general traffic, and pedestrians, to determine a most preferred scenario at each location.
The details of the u-turn analysis at each of these locations can be found in Section 2 - Transit Project Assessment Study – U-Turn Traffic Analysis.
Section 3: Transit Project Assessment Study – Keele Station Bus Terminal Traffic Analysis A bus terminal at the Keele Street Station was added to the project. The purpose of evaluating various Keele Street bus terminal scenarios was to select a preferred scenario to be used for preliminary design that efficiently progressed buses into and out of the terminal area. There are primarily two treatments for stops at this location, namely; on-street stop locations, and off-street Following the selection of the preferred route, and endorsement of the preferred route by all stops within the bus terminal. stakeholders, a number of stakeholders’ concerns remained to be addressed. Three sections of Route 1 were identified as areas requiring further refining of the alignment of the LRT and special Five (5) scenarios were selected for analysis, which were evaluated based on: transit service traffic studies. These special traffic studies have been completed and are organized in the following impacts (efficiency), local traffic impacts, pedestrian and sidewalk impacts, property impacts and ), sections: construction impacts. Section 4.1: Special traffic study at the Eglinton Avenue/ The East Mall Intersection; Based on the above factors, the recommended scenario locates an off-street bus terminal in the southeast quadrant of the intersection of Trethewey Drive at Yore Road. Section 4.2: Special traffic study centred on the Eglinton Avenue/ Commerce Boulevard Intersection; and Further details on scenarios and the evaluation can be found in Transit Project Assessment Study – Keele Station Bus Terminal Traffic Analysis, which is included in Section 3. Section 4.3: Special traffic study at the Convair LRT station.
Section 4: Transit Project Assessment Study – Airport Extension Feasibility Study – Traffic Analysis In 2008, the TTC investigated the feasibility of extending the ECLRT project to include a link to the Lester B. Pearson International Airport (LBPIA). The original project limits were subsequently extended to the west, and the ECLRT – Airport Extension Feasibility Study report covering the link to LBPIA, was commenced. The purpose of the feasibility study was to determine if there was a logical and feasible connection, and if so, to recommend a preferred alignment.
February 2010 Page 2 February 2010 Page 3 REPORT
TABLE OF CONTENTS
1. INTRODUCTION AND BACKGROUND ...... 1-1
1.1 Background ...... 1-1
1.2 Study Area ...... 1-2
1.3 Project Description ...... 1-3
1.4 Study Objectives ...... 1-4
2. TRAFFIC ANALYSIS ...... 1-4 Toronto Transit Commission (TTC) 2.1 Overall Methodology ...... 1-4
2.2 Study Horizons ...... 1-5
2.3 Traffic Data ...... 1-5 SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - 2.4 Analysis Parameters ...... 1-5 OVERALL TRAFFIC ANALYSIS 2.4.1 Capacity and Level of Service ...... 1-5 2.4.2 Queue Lengths ...... 1-5
3. EXISTING CONDITION ...... 1-6
3.1 Existing Transportation Systems ...... 1-6
3.1.1 Transit Services in the Study Area ...... 1-6 3.1.1.1 Routes Directly Along ECLRT Alignment ...... 1-6 3.1.1.2 Intersecting Routes ...... 1-7 3.1.2 Road Network ...... 1-7 3.2 Assessment of Existing Traffic Operations ...... 1-8
4. FUTURE CONDITIONS ...... 1-9
4.1 Future Transportation Systems ...... 1-9
4.1.1 Transit Services in the Study Area ...... 1-9 REPORT 4.1.2 Road Network ...... 1-9
FEBRUARY, 2010 4.2 Assessment of Future Traffic Operations ...... 1-9
5. OVERALL TRAFFIC IMPACTS RESULTS ...... 1-10
5.1.1 Traffic Capacity Reduction ...... 1-15 5.1.2 Impacts to Unsignalized Intersections ...... 1-15
5.1.3 Left Turn Prohibitions ...... 1-17
February, 2010 Page1- i. REPORT REPORT
TABLE OF CONTENTS (CONT’D) TABLE OF CONTENTS (CONT’D)
6. DETAILED TRAFFIC STUDIES ...... 1-19 6.6.3 Background ...... 1-36 6.6.4 Proposed Scenarios ...... 1-36 6.1 Martin Grove Road and Eglinton Avenue West ...... 1-19 6.6.5 Recommendations ...... 1-37
6.1.1 Study Purpose ...... 1-19 6.1.2 Site Traffic Issues...... 1-19 LIST OF EXHIBITS 6.1.3 Background ...... 1-20
6.1.4 Proposed Scenarios ...... 1-20 Exhibit 1-1: Toronto Transit City Light Rail Plan ...... 1-1 Exhibit 1-2: Study Area ...... 1-2 6.1.5 Recommendations ...... 1-20 Exhibit 1-3: Typical Cross Section and Rendering of the LRT ...... 1-3
6.2 Kipling Avenue and Eglinton Avenue West ...... 1-22 Exhibit 5-1: Traffic Assessment Summary (West Alignment: Renforth Drive to Keele Street) ...... 1-11 Exhibit 5-2: Traffic Assessment Summary (East Alignment: Laird Drive to Kennedy Road) ...... 1-13 6.2.1 Study Purpose ...... 1-22 Exhibit 5-3: Existing and Future Movements at Unsignalized Intersections ...... 1-16
Exhibit 5-4: Re-routed Left Turns (AM Peak) ...... 1-17 6.2.2 Site Traffic Issues...... 1-22 Exhibit 5-5: Re-routed Left Turns (PM Peak) ...... 1-18 6.2.3 Background ...... 1-23 Exhibit 6-1: The Martin Grove Road and Eglinton Avenue West Study Area ...... 1-20 Exhibit 6-2: Martin Grove Road and Eglinton Avenue West - Preferred Scenario: Vehicle 6.2.4 Proposed Scenarios ...... 1-23 Routing ...... 1-21 6.2.5 Recommendations ...... 1-24 Exhibit 6-3: Martin Grove Road and Eglinton Avenue West - Preferred Scenario Road Configuration Alternatives ...... 1-22 6.3 Jane Street and Eglinton Avenue West ...... 1-25 Exhibit 6-4: The Kipling Avenue and Eglinton Avenue West Study Area ...... 1-23 Exhibit 6-5: Kipling Avenue and Eglinton Avenue West - Scenario 2 - Vehicle Routing ...... 1-25 6.3.1 Study Purpose ...... 1-25 Exhibit 6-6: The Jane Street and Eglinton Avenue West Study Area ...... 1-26
6.3.2 Site Traffic Issues...... 1-25 Exhibit 6-7: Jane Street and Eglinton Avenue West - Preferred LRT Interface Option ...... 1-28 Exhibit 6-8: Jane Street and Eglinton Avenue West - Preferred Scenario: Vehicle Routing ...... 1-28 6.3.3 Background ...... 1-26 Exhibit 6-9: The Black Creek Drive and Eglinton Avenue West Study Area ...... 1-29 Exhibit 6-10: Summary of Loading Scenarios ...... 1-31 6.3.4 Proposed Scenarios ...... 1-26 Exhibit 6-11: Black Creek Depot – Preferred Scenario LRT Loading/Unloading Diagram ...... 1-32 6.3.5 Recommendations ...... 1-27 Exhibit 6-12: Wynford Road and Eglinton Avenue East Study Area...... 1-33 Exhibit 6-13: Proposed Geometric Configuration for DVP - Off Ramps ...... 1-35 6.4 Black Creek Drive and Eglinton Avenue West ...... 1-29 Exhibit 6-14: Victoria Park Avenue and Eglinton Avenue West Study Area ...... 1-36
Exhibit 6-15: Victoria Park Avenue and Eglinton Avenue - Scenario 1...... 1-37 6.4.1 Study Purpose ...... 1-29 Exhibit 6-16: Victoria Park Avenue and Eglinton Avenue - Scenario 2...... 1-37 6.4.2 Site Traffic Issues...... 1-29 Exhibit 6-17: Victoria Park and Eglinton Avenue East - Preferred Scenario: Vehicle Routing ...... 1-38
6.4.3 Background ...... 1-29
6.4.4 Proposed Scenarios ...... 1-30 LIST OF APPENDICES 6.4.5 Recommendations ...... 1-30 Appendix I: Traffic Assessment Summary: Existing and Future Conditions 6.5 Wynford Drive and Eglinton Avenue East ...... 1-32 Appendix II: Graphic Summary of Traffic Operations: Existing and Future Conditions 6.5.1 Study Purpose ...... 1-32 Appendix III: Eglinton LRT – Eglinton Avenue at Martin Grove Road Synchro Assessment 6.5.2 Site Traffic Issues...... 1-33 Appendix IV: Eglinton LRT – Eglinton Avenue at Kipling Avenue Synchro Assessment Appendix V: Eglinton LRT – Eglinton Avenue at Jane Street Synchro Assessment 6.5.3 Background ...... 1-33 Appendix VI: Eglinton LRT – Black Creek Report Analysis 6.5.4 Proposed Scenarios ...... 1-34 Appendix VII: Eglinton LRT – Eglinton Avenue at Wynford Drive Synchro Assessment 6.5.5 Recommendations ...... 1-34 Appendix VIII: Eglinton LRT – Eglinton Avenue at Victoria Park Avenue Synchro Assessment 6.6 Victoria Park Avenue and Eglinton Avenue East ...... 1-35
6.6.1 Study Purpose ...... 1-35 6.6.2 Site Traffic Issues...... 1-35
February, 2010 Page1- ii. February, 2010 Page1- iii. REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
1. INTRODUCTION AND BACKGROUND The ECLRT is one of seven light rail lines proposed in the Transit City plan. Metrolinx, the Province’s agency responsible for the regional transportation plan, has adopted this plan in its 1.1 Background entirety in September 2008. The core objective of the Transit City Plan calls for the development of a network of light rail transit lines across the City of Toronto that offer seamless interconnection This report describes the traffic analysis completed as part of the Eglinton Crosstown Light Rail between each other, with the City’s existing and proposed rapid transit lines, and with regional Transit (ECLRT) Transit Project Assessment Study process. transit services.
During the past decade, the Toronto Transit Commission (TTC) in conjunction with the City of 1.2 Study Area Toronto has been examining high-quality and reliable transit technology and routes that would cross the City, culminating in the Toronto Transit City – Light Rail Plan. Released in March 2007, Transit City is high-level plan for a Light Rail Transit (LRT) network for the City of Toronto and consolidates The ECLRT alignment runs along Eglinton Avenue from Renforth Drive in the west to Kennedy various light rail plans and studies undertaken by the City and the TTC during this period. Exhibit Road in the east. Exhibit 1-2 shows the ECLRT routing and study area. 1-1 shows a map of the proposed LRT lines in the Toronto Transit City Light Rail Plan. Exhibit 1-2: Study Area Exhibit 1-1: Toronto Transit City Light Rail Plan
February, 2010 Page 1-1 February, 2010 Page 1-2 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
1.3 Project Description north-west transit infrastructure to provide a convenient transit alternative for travel within and across the City of Toronto. Light Rail Transit (LRT) – electrically powered “light rail” vehicles are the preferred technology of The proposed alignment of the ECLRT is as follows: choice for the ECLRT. Where the proposed LRT will operate at-grade, it will mostly operate in the centre of the roadway. Exhibit 1-3 shows a typical roadway cross section with the proposed LRT. Eglinton Avenue (West Alignment) – the ECLRT will travel at-grade in the centre of the roadway, from Renforth Drive to Emmett Avenue, where it will continue to run at- grade on the north-side of Eglinton Avenue until a point east of Jane Street, where it Exhibit 1-3: Typical Cross Section and Rendering of the LRT will return to the centre of the roadway until a point east of Black Creek Drive where it will transfer underground;
Eglinton Avenue (Central Alignment) – the ECLRT will travel underground from a point east of Black Creek Drive to Laird Drive where it will return to an at-grade centre of roadway alignment; and
Eglinton Avenue (East Alignment) – the ECLRT will travel in the centre of the roadway, from Laird Drive to Kennedy Road. 1.4 Study Objectives
The primary objectives of the traffic analysis are to conduct a preliminary assessment of the future Light Rail Vehicle (LRV) operation, and to determine impacts to traffic operations and land use. Ultimately, the results of the traffic analysis will be used to guide and advance the design of the ECLRT from the preliminary to the final design. Therefore, the analysis conducted in this report is the foundation for future preliminary and detailed design.
2. TRAFFIC ANALYSIS 2.1 Overall Methodology
Existing intersection capacity analyses were undertaken using the Highway Capacity Manual (HCM) methodology, and specifically the Synchro 6.0 Traffic Signal Coordination Software package by Trafficware. The Synchro analysis consisted of two steps, namely:
1. An analysis of existing and future conditions to identify problematic locations, or “Hot Spots”; and
2. A detailed analysis of Hot Spot locations to develop an effective LRV operation for the Hot Spot areas that will be refined during preliminary and detailed design.
To evaluate LRV operation in transit right-of-ways, a priority scheme was developed and employed The approximate length of the entire ECLRT alignment is 27 km and its average width is 7.3m. At at signalized intersections. The priority scheme ensures that a safe transportation system is in proposed stop locations, a 3m platform is required, which will be placed on the far side of the place for all roadway users including pedestrians, cyclists, transit (bus and LRV) and traffic. The intersection in the shadow of the existing left-turn lane, thereby requiring no additional right-of-way priority scheme consists of the following measures: width. Throughout the entire alignment, a minimum of two through traffic lanes will be maintained 1. Ensure high quality LRT operations (i.e. speed, reliability); The ECLRT will run from Renforth Drive in the west to the Yonge-University-Spadina Subway line in the centre to the Bloor-Danforth Subway line at Kennedy Station in the east. It will function as a 2. Facilitate the movement of pedestrians; high-quality transit option for east-west travel and integrate with the 3. Facilitate bus operation and where passengers transfer between bus and LRT, prioritise equivalent to 2; and
February, 2010 Page 1-3 February, 2010 Page 1-4 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
4. Facilitate the movement of vehicles at the signalized intersections. Critical queue lengths were identified as movements that surpassed the estimated length of the existing left-turn or right-turn storage bay, or extended through to the upstream signalized 2.2 Study Horizons intersection.
Two study horizons were analyzed as part of the overall ECLRT traffic analysis: 3. EXISTING CONDITION
Existing Condition – Current 2008 condition in which the analysis is based on 3.1 Existing Transportation Systems existing roadway/intersection configurations, signal timing plans and turning movement counts. The ECLRT will be located entirely within the City of Toronto. It will integrate directly with the Spadina Subway, the Yonge Subway, the Bloor-Danforth Subway, and the Scarborough Rapid – Future Condition Assumes a future time period in which the ECLRT is in place and Transit (RT), surface bus routes, and a grid network of major arterial roadways. The ECLRT will fully operational. The analysis is based on revised roadway/intersection configurations, also accommodate direct transfer with the proposed Jane Street LRT, Don Mills Road LRT, and modified signal timing plans and existing turning movement counts (assumes roadway Scarborough/Malvern LRT lines. A potential connection to the proposed Mississauga Bus Rapid is at or near capacity during existing condition). Transit (BRT) facility is under investigation1. A description of these elements is provided in the following. 2.3 Traffic Data 3.1.1 TRANSIT SERVICES IN THE STUDY AREA Morning and afternoon peak hour traffic turning movement counts and signal timings of traffic at all signalized intersections along the preferred alignment were provided by the City of Toronto. A brief description of transit services operating in the Study Area is provided below. At Kennedy Station (Eglinton Avenue East and Kennedy Road), the ECLRT will connect with the east-west 2.4 Analysis Parameters Bloor-Danforth Subway, the Scarborough Rapid Transit lines and the proposed Scarborough Malvern LRT. There are many bus routes that travel partially along or intersect with the proposed The City of Toronto’s Guidelines for Using Synchro Software v.5.0 was consulted for the base ECLRT alignment. parameters of this study. 3.1.1.1 Routes Directly Along ECLRT Alignment 2.4.1 CAPACITY AND LEVEL OF SERVICE Bus Routes that operate within the Study Area include the following: An intersection’s overall operating conditions are typically characterized by two standard measures: the volume to capacity ratio (V/C) and the level of service (LOS). Taken together, they provide an Route 32: Eglinton West – TTC Route 32 is an east-west bus route that operates indication of delay and the number of vehicles that can be accommodated through an intersection. between Renforth Drive in the east and Eglinton Subway Station in the west. There are The V/C ratio is an indication of the volume of traffic attempting to make a specific movement five variants of Route 32 operating on Eglinton Avenue West: through an intersection (i.e., northbound left, westbound straight through), versus the theoretical capacity of that movement given the lane configurations, operating conditions and signal timings Route 32: Eglinton Station to Renforth Drive (the main branch); provided at the intersection. A V/C ratio of 1.0 represents a condition where all available capacity for a particular movement is being used. Route 32A: Eglinton Station to Renforth Drive & Skymark;
The level of service (LOS) of the overall intersection or a particular movement is a measure of the Route 32B: Eglinton Station to Airport Corporate Centre; average vehicle delay experienced by the motorists attempting to travel through the intersection. LOS is measured from “A” to “F” with peak hour LOS in the “A” to “D” range being considered Route 32C: Eglinton Station to Jane & Lawrence via Trethewey Drive; and acceptable by most, and a LOS of F representing unacceptable delays.
Route 32D: Eglinton West Station to Jane Street & Emmett Road. Critical movements were identified as those operating with a volume-to-capacity (V/C) ratio of 0.85 or higher and/or the poorest level of service (LOS). Route 34: Eglinton East – TTC Route 34 is an east-west bus route that operates 2.4.2 QUEUE LENGTHS between Eglinton Subway Station and Kingston Road via Eglinton Avenue East with TTC Route 34C operating between Eglinton and Kennedy Subway Stations. In the th The Synchro 6.0 Traffic Signal Coordination Software measures both the 50th percentile and 95 vicinity of the Study Area, Route 34 buses operate from Eglinton Station via north on percentile maximum queue lengths. The 50th percentile queue (the median) is the maximum queue Duplex Avenue, east on Eglinton Avenue East and through to Kennedy Station. length during a typical traffic cycle. The 95th percentile queue is the maximum queue length during a typical traffic cycle with 95th percentile traffic volumes.
1 Summary of Existing and Future Conditions Report, Eglinton Crosstown LRT, Preliminary Planning for a Transit Project Assessment Study, LGL Limited, Sowel Kang, M.E.S & Grant N.Kauffman, M.E.S.
February, 2010 Page 1-5 February, 2010 Page 1-6 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
3.1.1.2 Intersecting Routes westbound travel lanes with a centre median that becomes a shared left-turn lane at points east of Victoria Park Avenue. At most major and minor signalized intersections, Bus routes that intersect the proposed Study Area include the following: there are exclusive left-turn lanes and some exclusive or channelized right-turn lanes. Route 112: Renforth Drive; Route 7: Bathurst Street; 3.2 Assessment of Existing Traffic Operations Route 111: The East Mall; Route 33: Spadina Road; The assessment of existing traffic operations followed these prescribed steps: Route 46: Martin Grove Road; Route 14: Chaplin Crescent; 1. Turning movement, pedestrian and bicycle data were compiled for 37-study area Route 45: Kipling Avenue; Route 61: Avenue Road; intersections.
Route 405: Widdicombe Hill Blvd; Route 5: Oriole Parkway; 2. Along Eglinton Avenue East at intersections where there are HOV lanes, existing eastbound and westbound through volumes were reduced to account for HOV traffic. Route 37: Islington Avenue; Route 97: Yonge Street; Spot counts along Eglinton Avenue East in the AM and PM peak period were used to confirm the percentage of eastbound and westbound HOV traffic along Eglinton Route 73: Royal York Road; Route 103, Route 74: Mount Pleasant Avenue. Road; Route 79: Scarlett Road; 3. Lane configurations along Eglinton Avenue East were adjusted to account for the Route 11: Bayview Avenue; removal of HOV traffic in the existing condition. Route 32D: Emmett Avenue; Route 56: Laird Drive; 4. Traffic volume adjustments were made to intersection movements in which volumes Route 35: Jane Street; did not appear consistent with other intersections. Route 51, Route 54: Leslie Street; Route 89: Weston Road; 5. A map of the study area alignment was developed in Synchro 6.0 for the existing Route 25, Route 403 Don Mills Road; condition AM and PM peak hours and all required data was entered. Route 171, Route 71, Route 32C: Trethewey Drive; Route 100: Wynford Road; 6. The lengths of turning lanes/bays were measured using Google Earth. Route 41: Keele Street; Route 91: Bermondsey; 7. The results of the existing condition Synchro 6.0 HCM analysis and Synchro 6.0 queue Route 47: Caledonia Road; Route 24: Victoria Park Avenue; length analysis were summarized for each intersection.
Route 29: Dufferin Street; Route 70: O‘Connor Drive; 8. For each intersection movement, the following thresholds were classified as impacts:
Route 90: Vaughn Road; Route 67: Pharmacy Avenue; A Volume to Capacity Ratio (V/C) ≥ 0.85;
Route 63: Oakwood Avenue Route 68: Warden Avenue; A Level of Service (LOS) = E or F; and
Route 109: Marlee Avenue; Route 17: Birchmount Road. A 95th percentile queue length for a turning bay/lane that exceeds its measured length.
3.1.2 ROAD NETWORK 9. A series of existing condition summary tables and traffic hot spot maps were created for the AM and PM peak hours. Eglinton Avenue West is a major east-west arterial that connects to Highway 407 in Mississauga and Yonge Street in Toronto. From Renforth Road to Black Creek Drive, Eglinton Avenue West generally operates with two eastbound and two westbound travel lanes with a shared centre left-turn lane. At most major and minor signalized intersections, there are exclusive left-turn lanes and some exclusive or channelized right-turn lanes.
Eglinton Avenue East is a major east-west arterial that connects to Yonge Street in Toronto and Kingston Road in Toronto (Scarborough). From Laird Drive to Kennedy Road, Eglinton Avenue East generally operates with three eastbound and three
February, 2010 Page 1-7 February, 2010 Page 1-8 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
4. FUTURE CONDITIONS 6. For each intersection movement, the same impact threshold movements used in the existing condition analysis following thresholds were classified as impacts:
4.1 Future Transportation Systems A Volume to Capacity Ratio (V/C) ≥ 0.85;
A Level of Service (LOS) = E or F; and 4.1.1 TRANSIT SERVICES IN THE STUDY AREA
The implementation of the ECLRT will result in changes to existing transit services in the Study A 95th percentile queue length for a turning bay/lane that exceeds its measured Area: length.
Route Elimination – Some existing TTC bus routes such as Route 32: Eglinton West 7. A series of future condition summary tables and traffic hot spot maps were created for (between Eglinton Station at Yonge Street and Eglinton West Station at Allen Road) the AM and PM peak hours. will be replaced by the ECLRT; and 5. OVERALL TRAFFIC IMPACTS RESULTS Route Modification – Some existing TTC bus routes such as Route 32D: Eglinton West to Eglinton Station – looping at Emmett Avenue and Jane Street, will be shorted The results of the of the exiting and future condition traffic analysis are summarized in Exhibit 5-1 and/or re-routed to interface with the ECLRT. and Exhibit 5-2, for the west and east sections of Eglinton Avenue, respectively. Table rows highlighted in orange were included in Section 6: Detailed Traffic Studies. Detailed results of the Future transit operation plans have not been finalized by the TTC. traffic analysis can be found in Appendix I and Appendix II, for Existing Conditions and Future Conditions. 4.1.2 ROAD NETWORK
No new roadways are projected to be added to the Study Area. There will be changes to existing roadway configurations such as the removal of traffic lanes and some geometric modifications to major intersections (i.e. Eglinton Avenue West and Don Mills Road) to accommodate the ECLRT. 4.2 Assessment of Future Traffic Operations
The assessment of future traffic operations followed these prescribed steps:
1. Turning movement, pedestrian and bicycle volumes were assumed to remain the same in the future LRT condition. The signalized intersection of Eglinton Avenue East and Kennedy Road has been analyzed as part of the Scarborough Malvern LRT study area.
2. Eastbound and westbound through HOV volumes that were reduced at intersections along Eglinton Avenue East (existing condition) were added back.
3. Lane/roadway configurations along the entire study area alignment were adjusted to conform to the future roadway layout with the ECLRT right-of-way in place. Along the entire ECLRT alignment, two lanes of through traffic and one dedicated left-turn lane are assumed at all signalized intersections. At signalized intersections, no lane/roadway configuration changes were made to streets that intersect the LRT alignment.
4. A map of the study area alignment was developed in Synchro 6.0 for the future condition AM and PM peak hours and all required data was entered.
5. The results of future condition Synchro 6.0 HCM analysis and Synchro 6.0 queue length analysis were summarized for each intersection.
February, 2010 Page 1-9 February, 2010 Page 1-10 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
Exhibit 5-1: Traffic Assessment Summary (West Alignment: Renforth Drive to Keele Street) Traffic Impacts Traffic Impacts Signalized Vehicle Capacity Level of Service 3 Signalized Vehicle Capacity Level of Service 3 Inter- 1 2 Turning Queues Inter- 1 2 Turning Queues Intersection (V/C) Ratio (LOS) Intersection (V/C) Ratio (LOS) No. section No. section With Eglinton AM PM AM PM AM PM With Eglinton AM PM AM PM AM PM Approach Approach Avenue West Peak Peak Peak Peak Peak Peak Avenue West Peak Peak Peak Peak Peak Peak Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu East East West West 11 Royal York Road 1 Renforth Drive North North South South East East West Matheson Boulevard West 12 Scarlett Road 2 North East North South South East East West West 13 Jane Street 3 The East Mall North North South South East East West Hwy. 401/427 West 14 Weston Road 4 North Interchange North South South East East West West 15 Black Creek Drive 5 Martin Grove Road North North South South East East West Widdicombe Hill / West 16 Bricknell Avenue 6 North Lloyd Manor Road North South South East East Trethewey Drive / West West 17 7 Kipling Avenue Keele Street North North South South 1. One or More Movements In Approach Have a V/C Ratio ≥ 0.85 East 2. One or More Movements In Approach Have a LOS E or F Wincott Drive / West 8 3. Left-Turn or Right-Turn Queue Exceeds Turning Bay Length Bemersyde Drive North South East West 9 Islington Avenue North South East Russell Road / West 10 Eden Valley Drive North South 1. One or More Movements In Approach Have a V/C Ratio ≥ 0.85 2. One or More Movements In Approach Have a LOS E or F 3. Left-Turn or Right-Turn Queue Exceeds Turning Bay Length
February, 2010 Page 1-11 February, 2010 Page 1-12 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
Exhibit 5-2: Traffic Assessment Summary (East Alignment: Laird Drive to Kennedy Road) Traffic Impacts Traffic Impacts Signalized Vehicle Capacity Level of Service 3 Inter- 1 2 Turning Queues Intersection (V/C) Ratio (LOS) Signalized Vehicle Capacity Level of Service 3 No. section Inter- 1 2 Turning Queues With Eglinton Intersection (V/C) Ratio (LOS) Approach AM PM AM PM AM PM No. section Avenue West With Eglinton Peak Peak Peak Peak Peak Peak Approach AM PM AM PM AM PM Avenue West Peak Peak Peak Peak Peak Peak Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu Ex Fu East West East 63 Eglinton Square North West 53 Laird Drive South North South East West East 64 Pharmacy Avenue North West 54 Brentcliffe Road South North South East West East 65 Lebovic Avenue North West 55 Leslie Street South North ------ South East West East 66 Warden Avenue North West 56 Don Mills Road South North South East West East 67 Prudham Gate North Don Valley Pkwy. SB West 57 South (West) North ------ South East West East 68 Sinnott Road North Don Valley Pkwy. NB West 58 South (East) North South ------East West East 69 Birchmount Road North West ------59 Wynford Drive South North South ------East West East 70 Rosemount Drive North Swift Drive / West 60 South Credit Union Drive North South East West East 71 Ionview Road North Sloan Avenue / West 61 South Bermondsey Road North South East West East 72 Kennedy Road North West 62 Victoria Park Avenue South North South 1. One or More Movements In Approach Have a V/C Ratio ≥ 0.85 2. One or More Movements In Approach Have a LOS E or F 1. One or More Movements In Approach Have a V/C Ratio ≥ 0.85 3. Left-Turn or Right-Turn Queue Exceeds Turning Bay Length 2. One or More Movements In Approach Have a LOS E or F
3. Left-Turn or Right-Turn Queue Exceeds Turning Bay Length
February, 2010 Page 1-13 February, 2010 Page 1-14 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
The implementation of the ECLRT is projected to result in the following traffic impacts:
Left-turn prohibitions from existing unsignalized street and entrances (i.e. right-in and right-out movements allowed only) throughout the Study Area. Exhibit 5-3: Existing and Future Movements at Unsignalized Intersections
Some left-turn prohibitions at specific major signalized intersections to ensure efficient LRT operations (speed, reliability, safety).
Reduced roadway capacity due to the removal of one travel lane in each direction at some locations along Eglinton Avenue.
Increased delays for vehicular traffic, particularly for left-turn movements, due to the introduction of separate left-turn and U-turn traffic signal phases in order to accommodate ECLRT service through the intersection.
Some of these impacts are discussed in further detail below:
5.1.1 TRAFFIC CAPACITY REDUCTION
The ECLRT will allocate some roadway space to a dedicated transit right-of-way. At some locations along Eglinton Avenue, one travel lane will be reduced, which in turn will reduce the overall traffic carrying capacity of the Study Area.
5.1.2 IMPACTS TO UNSIGNALIZED INTERSECTIONS
At existing unsignalized intersections and driveway entrances along the entire ECLRT alignment, left-turn in and left-turn out movements will be prohibited and only right-turn in and right-turn out movements will allowed (Exhibit 5-3). In the recommended design for the ECLRT, each unsignalized and driveway location is provided with either one or both of the following:
A local alternative route; and
A signalized intersection upstream has a U-turn movement.
February, 2010 Page 1-15 February, 2010 Page 1-16 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
5.1.3 LEFT TURN PROHIBITIONS Exhibit 5-5: Re-routed Left Turns (PM Peak)
During the development of the recommended design, ten intersections were identified where traffic Cycle E-W Thru- N-S Thru- Volume Cross Street U-Turns @ movements could cause potential ECLRT operational concerns (i.e. regarding the speed and Length Green Green EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Kipling/Widdicombe Hill, reliability of the transit vehicle, pedestrians, and vehicular traffic). A detailed transit-traffic analysis Kipling 120 54 38NB, 28SB 218 1534 39 150 1304 60 113 828 151 75 654 62 was conducted for each location and specific design recommendations were made to ensure Kipling/Byland efficient and safe ECLRT operations. This resulted in the design recommendation to prohibit left- Islington/LaRose, Islington 120 63 27 Islington/First Driveway 156 1582 63 104 1246 48 69 822 110 48 709 74 turns and re-route the movements at the identified intersections. Exhibit 5-4 and Exhibit 5-5 show S. of Eglinton the signal timings, traffic volumes, and recommended re-distribution of left turns at the identified intersections for the AM and PM peak, respectively. Royal York/LaRose, Royal York 120 55 37 Royal York/Second 128 1446 118 145 1713 63 72 656 65 66 600 108 Driveway S. of Eglinton Scarlett/Richview, Scarlett 110 39 34 112 1177 176 102 1035 277 180 710 125 134 451 52 Exhibit 5-4: Re-routed Left Turns (AM Peak) Scarlett/Fontenay New u-turn signals on Eglinton (1), Jane (1); Cycle E-W Thru- N-S Thru- Volume Jane 100 32 41NB, 29SB 175 1118 145 104 1295 156 169 1030 117 40 885 252 Cross Street U-Turns @ Eglinton/Emmet, Length Green Green EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Jane/Lambton Kipling/Widdicombe Hill, Kipling 120 60 33NB, 23SB 185 1475 72 129 1247 34 127 644 125 46 592 32 New u-turn signals on Kipling/Byland Eglinton; Don Don Mills 120 31 41 294 1289 271 285 881 197 209 1553 302 406 1266 309 Islington/LaRose, Mills/Wynford, Don Islington 112 56 27 Islington/First Driveway 70 1163 69 172 1208 48 44 775 62 48 752 65 Mills/St. Dennis S. of Eglinton Pharmacy/First Driveway N. of Eglinton, Royal York/LaRose, Pharmacy 120 47 32NB, 45SB 365 1825 89 60 1024 124 126 552 101 97 370 136 Royal York 112 44 40NB, 30SB Royal York/Second 91 1272 101 71 1204 89 102 702 68 75 543 110 Eglinton/First Driveway Driveway S. of Eglinton E. of Pharmacy Scarlett/Richview, Scarlett 100 29 34 39 1240 250 83 1008 159 153 545 140 183 581 61 Warden/First Driveway Scarlett/Fontenay Warden 120 47 32 N. of Eglinton, 53 1755 206 182 1330 46 358 109 246 58 106 29 New u-turn signals on Warden/Civic Eglinton (1), Jane (1); Jane 1 100 34 39NB, 29SB 214 1045 161 82 984 25 225 885 119 64 732 191 Eglinton/Emmet, Birchmount/First Jane/Lambton Driveway N. of Eglinton, Birchmount 120 45 37NB, 47SB 252 1671 199 167 1109 255 213 1360 257 99 933 234 New u-turn signals on Birchmount/First Eglinton; Don Driveway S. of Eglinton Don Mills 2 120 34 39 282 1032 324 327 1169 108 250 1062 231 376 1348 200 Mills/Wynford, Don Mills/St. Dennis Kennedy/Treverton, Kennedy 120 42 38 222 2064 108 190 1145 199 138 692 169 258 519 190 Kennedy/Transway Pharmacy/First NOTES Driveway N. of Eglinton, 1 All left turns redistributed to through, u-turn, right turn movements. New u-turn signals at Eglinton/east of Jane and Jane/north of Eglinton Pharmacy 3 120 44 33NB, 48SB 134 831 91 52 1881 64 104 684 71 109 503 344 Eglinton/First Driveway 2 E-W left turns redistributed to new u-turn signals downstream Don Mills in each direction E. of Pharmacy 3 North-south left turns permitted at Pharmacy Avenue. Re-routing required for east-west left turns only.
Warden/First Driveway Warden 120 50 32 N. of Eglinton, 188 1006 107 133 1599 75 187 955 150 253 1121 254 Warden/Civic
Birchmount/First Driveway N. of Eglinton, Birchmount 120 53 37 160 750 75 197 1995 119 77 621 72 117 943 184 Birchmount/First Driveway S. of Eglinton
Kennedy/Treverton, Kennedy 120 44 36 123 624 52 180 2120 131 126 456 77 213 655 194 Kennedy/Transway NOTES 1 All left turns redistributed to through, u-turn, right turn movements. New u-turn signals at Eglinton/east of Jane and Jane/north of Eglinton 2 E-W left turns redistributed to new u-turn signals downstream Don Mills in each direction 3 North-south left turns permitted at Pharmacy Avenue. Re-routing required for east-west left turns only.
February, 2010 Page 1-17 February, 2010 Page 1-18 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
6.1.3 BACKGROUND 6. DETAILED TRAFFIC STUDIES Exhibit 6-1 shows the study area and signalized intersections that were analysed. Detailed traffic studies were undertaken at seven “hot spot” locations identified in the Existing and Future Condition traffic analysis. Exhibit 6-1: The Martin Grove Road and Eglinton Avenue West Study Area Martin Grove Road and Eglinton Avenue West;
Kipling Avenue and Eglinton Avenue West;
Jane Street and Eglinton Avenue West;
Black Creek Drive and Eglinton Avenue West;
Wynford Drive and Eglinton Avenue East;
Victoria Park Avenue and Eglinton Avenue East; and
Each of these detailed traffic and transportation impact studies are summarized below. The final reports are presented in Appendix III through VIII, respectively. 6.1 Martin Grove Road and Eglinton Avenue West
6.1.1 STUDY PURPOSE Legend
A detailed Synchro traffic analysis was conducted at the Martin Grove Road and Eglinton Avenue Signalized Intersection for Scenario 1 and 2 West hot spot. The purpose of the analysis was to conduct a preliminary assessment of the future ECLRT operations, and to determine the impacts to traffic operation and the surrounding land use. The findings from the study were used to advance the initial design of the ECLRT and provide a foundation for future preliminary and detailed design. 6.1.4 PROPOSED SCENARIOS The full Eglinton LRT - Eglinton Avenue at Martin Grove Road Synchro Assessment report can be found in Appendix III. Due to the uncertainties of the road and operating characteristics for general traffic with the LRT in service, the following scenarios were developed and analysed: 6.1.2 SITE TRAFFIC ISSUES Future Conditions – There are no restrictions for general traffic at the intersection of There are several site traffic issues associated with the Eglinton Avenue West and Martin Grove Eglinton Avenue West and Martin Grove Road; Road hot spot: Scenario 1 – Left turns are prohibited at the intersection of Eglinton Avenue West and LRT merging into and out of the Right Of Way (ROW) and the potential for LRT Martin Grove Road, and U-turns are permitted on adjacent intersections along Martin conflicts with eastbound traffic; Grove Road; and
High volumes at the Martin Grove Road at Eglinton Avenue West intersection, Scenario 2 – Implementation of a half diamond exchange. specifically in the east and west directions; 6.1.5 RECOMMENDATIONS Excessive eastbound queues and associated queue spillback; The analysis has shown that left turns should be considered for removal at the intersection of Proximity to Hwy 401 and Hwy 427. Eglinton Avenue West and Martin Grove Road. By doing so, cycle lengths can be shortened, and signal timing plans simplified. Scenarios 1 and 2 reflect the traffic operations with the removal of the left turns.
February, 2010 Page 1-19 February, 2010 Page 1-20 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
The analysis has demonstrated better traffic operation results for Scenario 1 and 2 over the Exhibit 6-3: Martin Grove Road and Eglinton Avenue West - Preferred Scenario Road base scenario (Future Conditions) in terms of LRT operational and traffic delays. These two Configuration Alternatives scenarios are both viable options from a traffic operations perspective for implementation. However, the major concern with Scenario 1 is the capacity of the roadways to accommodate further increase in future traffic volume because the majority of left turn and U-turn movements are operating close to capacity. Under Scenario 2, with the additional roads, traffic operations at the intersection of Eglinton Avenue West and Martin Grove Road have significantly improved (Refer to Exhibit 6-2). However, there are significant costs and property impacts under Scenario 2. Both Scenario 1 and Scenario 2 have design challenges that need to be investigated during preliminary and detailed design.
Exhibit 6-2: Martin Grove Road and Eglinton Avenue West - Preferred Scenario: Vehicle Routing
Legend 6.2 Kipling Avenue and Eglinton Avenue West EB WB NB SB 6.2.1 STUDY PURPOSE
A detailed Synchro traffic analysis was conducted at the Kipling Avenue and Eglinton Avenue West hot spot. The purpose of the analysis was to conduct a preliminary assessment of the future ECLRT operations, and to determine the impacts to traffic operation and the surrounding land use. The Under Scenario 2, two roadway configurations were considered. Exhibit 6-3 illustrates these findings from the study were used to advance the initial design of the ECLRT and provide a alternatives. The estimated costs of the alternatives are $3.17 million and $2.39 million for foundation for future preliminary and detailed design. Alternatives 1 and 2, respectively. The higher costs estimates for the implementation of Alternative 1 can be attributed to the land acquisition costs for the northeast roadway and the road construction The full Eglinton LRT - Eglinton Avenue at Kipling Avenue Synchro Assessment report can be costs for the southwest roadway. found in Appendix IV.
6.2.2 SITE TRAFFIC ISSUES
There are several site traffic issues associated with the Eglinton Avenue West and Kipling Road hot spot:
Large through volumes at Eglinton Avenue at Kipling Road, specifically the eastbound traffic in the AM and the westbound traffic in the PM; and
February, 2010 Page 1-21 February, 2010 Page 1-22 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
Wide intersection leading to increased pedestrian crossing time, increased cycle length Scenario 3 – Prohibited left turns at Eglinton Avenue West/Kipling Avenue with u-turns and consequently more east-west vehicle and LRT delay. at all downstream intersections on Eglinton Avenue West and Kipling Avenue;
Scenario 4 – Prohibited left turns at Eglinton Avenue West/Kipling Avenue with left 6.2.3 BACKGROUND turns distributed to u-turn at downstream intersections on Kipling Avenue and to Widdicombe Hill; and
Exhibit 6-4 shows the Kipling Avenue and Eglinton Avenue West Study Area shows the study area Scenario 5 - Prohibited left turns at Eglinton Avenue West/Kipling Avenue with left with the five signalized intersections included in the analysis. Of the five intersections shown, a new turns distributed to u-turn at downstream intersections on Kipling Avenue and new signalized intersection is proposed to be implemented at the Kipling Avenue and Byland Road (east midblock signals on Eglinton Avenue West. leg) intersection. In addition, each scenario was analysed under three different iterations of traffic operations:
Exhibit 6-4: The Kipling Avenue and Eglinton Avenue West Study Area Iteration 1 – Existing cycle lengths with one-stage pedestrian crossings;
Iteration 2 – Existing cycle lengths with two-stage north-south pedestrian crossings at Eglinton Avenue West West/Widdicombe Hill and Eglinton Avenue West West/Wincott Drive;
Iteration 3 – 80 second cycle lengths with two-stage north-south crossings on all Eglinton Avenue West crossings; and
Iteration 4 – Adjusted Parameters as defined by the TTC within the interim analysis period, including modified peak hour factors, reduced pedestrian crossing distance, analysis using Highway Capacity Manual (HCM) parameters, and increased pedestrian volumes at the intersection of Eglinton Avenue West and Kipling Avenue.
6.2.5 RECOMMENDATIONS
Based on the analysis of the four iterations, and applying five traffic distribution scenarios, Iteration 1 was most promising, along with:
Legend Left-turn movements prohibited at Eglinton Avenue West/Kipling Avenue and redistributed as recommended in Scenario 2; = Study Area Intersections Evaporated through volumes and left turn volumes at a maximum rate of 31%; and
Traffic signal coordination along Eglinton Avenue West for uninterrupted LRT operations.
6.2.4 PROPOSED SCENARIOS In summary, the analysis has shown that left turns should be considered for removal at the intersection of Eglinton Avenue West and Kipling Avenue. Scenarios 2 to 5 in all iterations reflect Due to the uncertainties of the road and operating characteristics for general traffic with the LRT in traffic operations with the removal of the left turns. Scenario 2 and Scenario 5 are both viable service, five scenarios were analyzed. The scenarios are: options for implementation. However, Scenario 2 provides the least capacity restraints without the addition of midblock traffic signals along Eglinton Avenue West (refer to Exhibit 6-5). Scenario 1 – Future conditions with permitted left turns at Eglinton Avenue West/ Kipling Avenue, east-west left turns operating under protected phases only;
Scenario 2 – Prohibited left turns at Eglinton Avenue West/Kipling Avenue with northbound and southbound u-turns at Kipling Avenue/Widdicombe Hill and Kipling Avenue/Byland Road, respectively;
February, 2010 Page 1-23 February, 2010 Page 1-24 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
Exhibit 6-5: Kipling Avenue and Eglinton Avenue West - Scenario 2 - Vehicle Routing 6.3.3 BACKGROUND
Exhibit 6-6 shows the study area with the four signalized intersections included in the analysis. The proposed signalized intersection on Eglinton Ave West, east of Jane Street will accommodate u- turns under Scenarios 1 and 2. The proposed signalized intersection on Jane Street, north of Eglinton Avenue West will accommodate u-turns under Scenario 2.
Exhibit 6-6: The Jane Street and Eglinton Avenue West Study Area
Avenue e Emmett Ave nu Eglinton
Street Jane
6.3 Jane Street and Eglinton Avenue West
6.3.1 STUDY PURPOSE
A detailed Synchro traffic analysis was conducted at the Jane Street and Eglinton Avenue West hot
spot. The purpose of the analysis was to conduct a preliminary assessment of the future ECLRT Legend operations, and to determine the impacts to traffic operation and the surrounding land use. The Existing Signalized findings from the study were used to advance the initial design of the ECLRT and provide a Intersection pton Avenue Lam foundation for future preliminary and detailed design. Proposed Signalized Intersection The full Eglinton LRT – Eglinton Avenue at Jane Street Synchro Assessment report can be found in Appendix V. 6.3.4 PROPOSED SCENARIOS
In consultation with City of Toronto and TTC staff, Synchro analysis was conducted to evaluate the 6.3.2 SITE TRAFFIC ISSUES LRV operation for two intersection configuration scenarios, and three LRT interface options. The two scenarios are: There are several site traffic issues associated with the Eglinton Avenue West and Jane Street hot spot: Scenario 1- Prohibited left turns at Eglinton Avenue West and Jane Street and redistribute to adjacent Eglinton Avenue West signals; and Challenges in interfacing the Jane LRT and Eglinton LRT, including the transfer of LRTs from Eglinton to Jane; Scenario 2 – Prohibited left turns at Eglinton Avenue West and Jane Street and redistribution to adjacent Eglinton Avenue West signals and Jane Street signals. High left turn volumes on all approaches; The three LRT interface options are: Wide intersection leading to increased pedestrian crossing time, increased cycle length and consequently more LRT delay; and Option 1 – Eglinton Crosstown LRT (ECLRT) and Jane LRT (JLRT) at-grade in centre of roadway; Anticipated pedestrian volume increases by 750% (166 to 1250 in the AM; 195 to 1462 in the PM) and the need to facilitate safe pedestrian transfer. Option 2 - ECLRT at-grade north of roadway and JLRT at-grade in centre of roadway; and
Option 3 - ECLRT at-grade north of roadway and JLRT at-grade west of roadway.
February, 2010 Page 1-25 February, 2010 Page 1-26 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
6.3.5 RECOMMENDATIONS Exhibit 6-7: Jane Street and Eglinton Avenue West - LRT Interface Option 3
Based on the analysis results, Option 3 best accommodates the pedestrian transfers between the Jane LRT and the Eglinton LRT, which is expected to increase by 750% to as much as 1462 pedestrians/hour.
Option 3 is to implement all of the following (refer to Exhibit 6-7):
Provide the capacity on Eglinton Avenue West east and west of Jane Street to integrate the ECLRT from north of Eglinton Avenue West into the centre of the roadway.
Provide the capacity on Jane Street north and south of Eglinton Avenue West to integrate the JLRT from west of Eglinton Avenue West into the centre of the roadway.
Modify the Eglinton Avenue West and Jane Street signalized intersection to allow the ECLRT to cross Jane Street north of the intersection, and the JLRT to cross Eglinton Avenue West west of the intersection.
Of the traffic redistribution scenarios considered, Scenario 2 is less disruptive to the Eglinton Avenue West and Emmett Avenue intersection than Scenario 1, under interface Option 3.
Scenario 2 is to implement all of the following (refer to Exhibit 6-8):
Four phase signal operation at Eglinton Avenue West and Jane Street with prohibited east-west and north-south left turn movements; Exhibit 6-8: Jane Street and Eglinton Avenue West – Scenario 2 90 second cycle length at Eglinton Avenue West and Jane Street;
Minimum of 26 seconds for the ECLRT phase on a through movement;
A new signalized intersection on Eglinton Avenue West east of Jane Street with the capacity to accommodate eastbound u-turns;
e A new signalised intersection on Jane Street north of Eglinton with the capacity to Street accommodate northbound u-turns; Emmett Avenue Eglinton Avenu
Jane Provide the accommodation for westbound u-turns at the Eglinton Avenue West and
Emmett Avenue intersection; and
Provide the accommodation for southbound u-turns at the Jane Street and Lambton Avenue intersection.
Legend
ue Existing Signalized Intersection pton Aven Lam Proposed Signalized Intersection
February, 2010 Page 1-27 February, 2010 Page 1-28 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
6.4 Black Creek Drive and Eglinton Avenue West North Access Driveway 6.4.1 STUDY PURPOSE Carhouse Depot A Light Rail Transit (LRT) depot is proposed on Eglinton Avenue West, just west of Black Creek Drive and east of the CN Rail track. A detailed analysis was conducted at this hot spot. The purpose of the analysis was to conduct a preliminary assessment of the future ECLRT operations, and to determine the impacts to traffic operation and the surrounding land use. The findings from the study were used to advance the initial design of the ECLRT and provide a foundation for future preliminary and detailed design.
The full Eglinton LRT - Black Creek Depot Analysis report can be found in Appendix VI.
6.4.2 SITE TRAFFIC ISSUES
There are several site traffic issues associated with the Eglinton Avenue West and Black Creek Photography Drive Access Drive hot spot:
Anticipated need to service four lines (Pearson Airport, Kennedy Station, Jane Street, and St Clair Avenue);
LRT merging into and out of the Right Of Way (ROW) and the potential for LRT 6.4.4 PROPOSED SCENARIOS conflicts with east-west traffic; To asses the traffic impact of the Back Creek Depot on the signalized intersections in its immediate vicinity, three approaches were considered for depot activity, namely: 6.4.3 BACKGROUND Scenario 1: A four-track system is constructed that will allow for two LRV to Exhibit 6-1 illustrates the proposed location of the Black Creek depot, along with the two proposed simultaneously enter, and two LRV to simultaneously exit from the Black Creek depot LRV access driveways. The first, referred to as the North Access Driveway, will be located on the at the Eglinton Avenue West at North Access Driveway signalized intersection (i.e. two north side of Eglinton Avenue, between Black Creek Drive and the CN Rail tracks. The second, tracks in and two tracks out). referred to as the Photography Access Driveway, will be located along Photography Drive, and will intersect Black Creek Drive at Photography Drive. It is anticipated that the North Access Scenario 2: A two-track system is constructed that will allow for one LRV to enter and Driveway will be the primary source for loading/offloading LRV, while the Photography Access one LRV to exit from the Black Creek depot at the Eglinton Avenue West at North Driveway will act as a relief point if the North Access Driveway movements become restricted or Access Driveway signalized intersection (i.e. one track in, one track out). schedule delays occur.
Four signalized intersections are within the study area, namely: Eglinton Avenue West at North Scenario 3: Two LRV are allowed to exit the depot at the Eglinton Avenue West at Access Driveway, Eglinton Avenue West at Black Creek Drive, Eglinton Avenue West and Black North Access Driveway signalized intersections. For this scenario, the impact of a Creek Drive at Photography Drive. four-track system and a two-track system were analyzed (as in Scenario 1 and 2).
6.4.5 RECOMMENDATIONS Exhibit 6-9: The Black Creek Drive and Eglinton Avenue West Study Area The analysis results, along with the feasibility of the scenarios and iterations considered, are presented in Exhibit 6-10.
February, 2010 Page 1-29 February, 2010 Page 1-30 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
Exhibit 6-10: Summary of Loading Scenarios Scenario 3 Iteration 7 and 8 are preferred, provided that two LRV can be serviced during the LRV phase at the Eglinton Avenue West at North Driveway Access. This option Scenario/ Cycle Length Feasible Comments provides left turn phasing at Eglinton Avenue West at Black Creek Drive. Iteration (seconds) (Y/N) Scenario 3 requires an intersection spacing of 200 metres or more between Eglinton Scenario 1 – Dual tracks Avenue West at North Driveway Access and Eglinton Avenue West at Black Creek Drive to store LRV. The storage space is necessary because multiple LRV may not be able to clear Iteration 1 75 Y No left turns at Eglinton Avenue at Black Creek. the signalized intersection of Eglinton Avenue West at Black Creek Drive in one cycle.
Iteration 2 90 Y No left turns at Eglinton Avenue at Black Creek. Scenario 3 Iteration 7 is preferred over Scenario 3 Iteration 8 from an LRV operations perspective since it offers the most flexibility in terms of LRV access. However Scenario 3 Iteration 3 102 Y Pedestrians not serviced and southbound phase truncated Iteration 8 is the most cost-efficient alternative. when LRV serviced. Recovery time available. Overall the preferred alternative is Scenario 3, Iteration 7 (refer to Exhibit 6-11). This 120 N Left turn omitted when LRV serviced. No recovery time configuration presents the most flexibility for LRV operation. A more cost-efficient available configuration is Scenario 3, iteration 8.
133 N No recovery time available Exhibit 6-11: Black Creek Depot – Preferred Scenario LRT Loading/Unloading Diagram Scenario 2 – Single tracks North Access Driveway Iteration 4 53 N Cycle length too short at North Access Driveway (Based on 15 minute peak)
Iteration 5 67 N Cycle length too short at North Access Driveway (Based on 1 Eglinton Avenue hour peak) 39 15 Automobile 14 53 lanes Iteration 6 113 Y WB Track (Even loading) EB Track 14 Automobile 29 lanes Scenario 3 – Back-to-Back LRV Clearance in One Cycle
Iteration 7 120 Y (Four-track System) Iteration 8 120 Y 6.5 Wynford Drive and Eglinton Avenue East (Two-track system 6.5.1 STUDY PURPOSE
The results displayed in Exhibit 6-10 illustrate that: A detailed Synchro traffic analysis was conducted at the Wynford Drive and Eglinton Avenue East hot spot. The purpose of the analysis was to conduct a preliminary assessment of the future ECLRT The Eglinton Avenue West at North Driveway Access is the primary LRV access, and that operations, and to determine the impacts to traffic operation and the surrounding land use. The the Black Creek Drive at Photography Drive will mostly likely act as a “relief” driveway used findings from the study were used to advance the initial design of the ECLRT and provide a during incidents. foundation for future preliminary and detailed design.
The full Eglinton LRT - Eglinton Avenue at Wynford Drive Synchro Assessment report can be found in Appendix VII.
February, 2010 Page 1-31 February, 2010 Page 1-32 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
6.5.2 SITE TRAFFIC ISSUES 6.5.4 PROPOSED SCENARIOS
There are several site traffic issues associated with the Eglinton Avenue East and Wynford Drive As part of this preliminary assessment the current road network of Eglinton Avenue East from the hot spot: DVP West Ramp to Wynford Drive was assessed using the future volumes. In this scenario, Wynford Drive was operating as a half signal. From this analysis, traffic conditions appeared to be Implications of the reconfiguration of Eglinton Avenue at Wynford Drive to an at-grade operating at a good level of service for most movements. However, queuing concerns were signalized intersection; observed at both the DVP ramps during both peak periods. As a result of the potential queuing concerns, future scenarios were developed to mitigate this concern. The future scenarios Capacity reduction on Eglinton Avenue from three east-west lanes to two east-west developed were as follows: lanes Scenario 1 – LRT Line with 120 second cycle length; Managing queue spillback onto the Highway at the Eglinton Avenue at DVP Ramps; Scenario 2 – LRT Line with 90 second cycle length; and Accommodating Queue jump lanes/phase for GO Bus from DVP to Eglinton; and Scenario 3 – LRT Line with 120 second cycle length and DVP Ramp modifications. 6.5.3 BACKGROUND 6.5.5 RECOMMENDATIONS This report documents the Synchro traffic analysis completed on Eglinton Avenue East from the Don Valley Parkway (DVP) West Ramp to the Wynford Drive signalized intersection. Exhibit 6-1 Scenario 3 is the preferred alternative since it incorporates physical geometric improvements that shows the study area with the three signalized intersections included in the analysis. As part of the favour LRV operations, pedestrian transfers, cycling operation, GO operations, and DVP queuing new alignment on Eglinton Avenue East, the intersection of Eglinton Avenue East and Wynford concerns. Drive will be modelled as an at-grade full signalized intersection. The purpose of Scenario 3 is to maintain traffic operations at a 120 second cycle length, and reduce the queuing experienced on both DVP ramps by implementing geometric ramp Exhibit 6-12: Wynford Road and Eglinton Avenue East Study Area modifications to both ramps. The high volume of right turning vehicles is the main cause of queuing. As a result, an additional right turn lane is proposed at both DVP ramp approaches to resolve this concern. It should be noted that due to this lane configuration, right-turn-on-red movements are now prohibited for safety concerns due to high through traffic, cyclist and pedestrian volumes. Also, under this Scenario, the GO Transit bus transfers are improved through the use of a centre platform for bus boarding and alighting. There is also the potential for a GO bus queue jump lane on the DVP off ramp. Exhibit 6-13 illustrates the ramp geometrics for both off ramps.
February, 2010 Page 1-33 February, 2010 Page 1-34 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
Exhibit 6-13: Proposed Geometric Configuration for DVP - Off Ramps Creating land development opportunities.
6.6.3 BACKGROUND
This report documents the Synchro traffic analysis completed on the Eglinton Avenue East at the Victoria Park area road network, which includes the following signalized intersections:
Eglinton Avenue East and Victoria Park Avenue;
Eglinton Avenue East and Eglinton Square;
Eglinton Avenue East and Pharmacy Avenue;
Eglinton Square and Victoria Park Avenue. LRT Exhibit 6-14 illustrates the study area and the above locations. edestrian Crossing
P Exhibit 6-14: Victoria Park Avenue and Eglinton Avenue West Study Area
6.6 Victoria Park Avenue and Eglinton Avenue East
6.6.1 STUDY PURPOSE
A detailed Synchro traffic analysis was conducted at the Victoria Park Avenue and Eglinton Avenue East hot spot. The purpose of the analysis was to conduct a preliminary assessment of the future ECLRT operations, and to determine the impacts to traffic operation and the surrounding land use. The findings from the study were used to advance the initial design of the ECLRT and provide a foundation for future preliminary and detailed design.
The full Eglinton LRT - Eglinton Avenue at Victoria Park Avenue Synchro Assessment report can be found in Appendix VIII.
6.6.2 SITE TRAFFIC ISSUES 6.6.4 PROPOSED SCENARIOS There are several site traffic issues associated with the Eglinton Avenue East and Victoria Park Due to the uncertainties of the road and operating characteristics for general traffic with the LRT in Avenue hot spot: service, the following scenarios were developed and analysed: Close signal spacing along Eglinton Avenue East; Scenario 1 - This scenario assumes prohibited eastbound/westbound left turns at Eglinton Avenue East at Victoria Park Avenue. Note that northbound and southbound Intersections already operating near or at capacity; left turns at this location are already prohibited. Exhibit 6-15 presents the rerouted paths of the eastbound/westbound left turn vehicles under Scenario 1. Capacity reduction on Eglinton Avenue from three east-west lanes to two east-west lanes; and
February, 2010 Page 1-35 February, 2010 Page 1-36 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
Scenario 2 - This scenario builds on the same assumptions as Scenario 1, with the Upgrades for the eastbound approach at Jonesville Crescent and Victoria Park Avenue addition of prohibited eastbound/westbound left turns at Eglinton Avenue East at to separate left turning vehicles from through/right turning vehicles; and Pharmacy Avenue, and a half signal on Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue to allow U-turns. Exhibit 6-16 presents the proposed Recalibration of traffic signal timing plans to allow for a 90 seconds cycle length along rerouting paths for the prohibited left turn vehicles under Scenario 2. this corridor section.
Traffic Analysis of the Final Scenario reveals that the expected traffic impacts on the network are Exhibit 6-15: Victoria Park Avenue and Eglinton Avenue - Scenario 1 mitigated to some extent.
Exhibit 6-17: Victoria Park and Eglinton Avenue East - Preferred Scenario: Vehicle Routing
Jonesville Crescent Victoria Park Avenue Avenue VictoriaVictoria Park Park
Eglinton Avenue East Avenue Avenue Pharmacy Pharmacy
Exhibit 6-16: Victoria Park Avenue and Eglinton Avenue - Scenario 2
Eglinton Square ’Connor Drive O
6.6.5 RECOMMENDATIONS
The Final Scenario derived from the iterative analysis incorporates the following road network modifications and upgrades (refer to Exhibit 6-17):
Prohibition of eastbound/westbound left turns on Eglinton Avenue East at Victoria Park Avenue, and Eglinton Avenue East at Pharmacy Avenue;
Signalization (half signal) of the intersection of Eglinton Avenue East and Jonesville to allow for eastbound left turns;
A new U-turn signal on Eglinton Avenue East between Pharmacy Avenue and Lebovic J:\24649_trnst_cityEA\10.0 Reports\Synchro Reports\TTR_ECLRT-Overall Report_TCG Format_2009-05-19-Ena.doc\2010-03-02\R Avenue which will also allow for pedestrian crossings;
February, 2010 Page 1-37 February, 2010 Page 1-38 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
Traffic Assessment Summary of Existing and Future Conditions (West Alignment: Renforth Drive to Keele Street) INTERSECTION EXISTING / TYPE EXISTING FUTURE FUTURE PROPOSED INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRANSIT LRT STOP? UNSIGNALIZED CONDITION TRANSIT CONDITION / DRIVEWAY) SERVICE AM PEAK HOUR EXISTING (Peak Hour / IMPACTS Daily Ridership) V/C: West Approach TTC Route 112 A/C/D NEW AM PEAK LOS: West Approach (367 / 7,663) HOUR IMPACTS Queues: North Miss. Transit 17 (N/A) V/C: None Approach Miss. Transit 89 (N/A) LOS: None Signalized Miss. Transit 109 (N/A) Queues: None Renforth Drive Minor Arterial PM PEAK HOUR Road IMPACTS FUTURE NEW PM PEAK V/C: East, West & Miss. Transit service to HOUR IMPACTS South Approaches Renforth Drive would V/C: None LOS: East, West & replace TTC 32A/B LOS: None South Approaches Queues: None Queues: East APPENDIX I Approach AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK IMPACTS Daily Ridership) HOUR IMPACTS V/C: None V/C: None LOS: None FUTURE LOS: None Queues: None SUMMARY OF TRAFFIC ASSESSMENT: Queues: None Matheson Signalized
PM PEAK HOUR Boulevard East Local Road NEW PM PEAK EXISTING AND FUTURE CONDITIONS IMPACTS HOUR IMPACTS V/C: South Approach V/C: None LOS: None LOS: None Queues: North Queues: None Approach AM PEAK HOUR EXISTING (Peak Hour / IMPACTS Daily Ridership) NEW AM PEAK V/C: South Approach TTC Route 111 (332 / HOUR IMPACTS LOS: South Approach 6,057) V/C: West Approach Queues: West LOS: West Approach Signalized Approach FUTURE Queues: None The East Mall Collector Road PM PEAK HOUR NEW PM PEAK IMPACTS HOUR IMPACTS V/C: West Approach V/C: None LOS: West Approach LOS: None Queues: West Queues: None Approach AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK IMPACTS Daily Ridership) HOUR IMPACTS V/C: None TTC Route 111 (332 / V/C: West Approach LOS: None 6,057) LOS: West Approach Queues: West Signalized Queues: None Hwy. 401/427 Approach FUTURE
Provincial Interchange NEW PM PEAK Expressway PM PEAK HOUR HOUR IMPACTS IMPACTS V/C: West Approach V/C: North Approach LOS: None LOS: North Approach Queues: None Queues: None
February, 2010 Page 1-I-1 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
INTERSECTION EXISTING / INTERSECTION EXISTING / TYPE EXISTING FUTURE FUTURE TYPE EXISTING FUTURE FUTURE PROPOSED PROPOSED INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRANSIT INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRANSIT LRT STOP? LRT STOP? UNSIGNALIZED CONDITION TRANSIT CONDITION UNSIGNALIZED CONDITION TRANSIT CONDITION / DRIVEWAY) SERVICE / DRIVEWAY) SERVICE AM PEAK HOUR EXISTING (Peak Hour / EXISTING (Peak Hour / NEW AM PEAK IMPACTS Daily Ridership) Daily Ridership) HOUR IMPACTS V/C: All Approaches TTC Route 46 (284 / TTC Route 405 (N/A) V/C: East Approach NEW AM PEAK AM PEAK HOUR LOS: East, North & 8,609) LOS: East & West HOUR IMPACTS IMPACTS South Approaches TTC Route 111 (332 / FUTURE Approaches V/C: None V/C: South Approach Queues: North & 6,057) Queues: East LOS: West Approach LOS: South Approach South Approaches Approach Signalized Queues: None Wincott Drive / Queues: None Martin Grove FUTURE Signalized
Major-Minor Yes PM PEAK HOUR Bemersyde Yes NEW PM PEAK Road NEW PM PEAK Local Road PM PEAK HOUR Arterial Road IMPACTS Drive HOUR IMPACTS HOUR IMPACTS IMPACTS V/C: East & West V/C: East & West V/C: None V/C: None Approaches Approaches LOS: None LOS: South Approach LOS: East & West LOS: East & West Queues: None Queues: None Approaches Approaches Queues: East Queues: East & West Approach Approaches AM PEAK HOUR EXISTING (Peak Hour / EXISTING (Peak Hour / NEW AM PEAK AM PEAK HOUR IMPACTS Daily Ridership) Daily Ridership) HOUR IMPACTS IMPACTS V/C: East Approach TTC Route 405 (N/A) NEW AM PEAK TTC Route 37/A/C/D V/C: West & North V/C: South Approach LOS: East & North HOUR IMPACTS (535 / 16,241) Approaches LOS: North & South Approaches FUTURE V/C: West Approach TTC Route 405 (N/A) LOS: East & West Approaches Queues: East & North LOS: West Approach Approaches Queues: None Widdicombe Hill Approaches Queues: None Signalized FUTURE Queues: East
/ Signalized Approach Islington Avenue Major Arterial Yes PM PEAK HOUR Yes PM PEAK HOUR NEW PM PEAK Lloyd Manor Collector Road Road IMPACTS IMPACTS HOUR IMPACTS NEW PM PEAK Road V/C: West & North V/C: East, West & V/C: None HOUR IMPACTS Approaches North Approaches LOS: None V/C: East Approach LOS: West, North & LOS: East, West & Queues: West LOS: East Approach South Approaches North Approaches Approach Queues: East Queues: None Queues: East & North Approach Approaches EXISTING (Peak Hour / NEW AM PEAK AM PEAK HOUR EXISTING (Peak Hour / Daily Ridership) HOUR IMPACTS IMPACTS Daily Ridership) AM PEAK HOUR V/C: None V/C: East, North & TTC Route 45/A/E (735 IMPACTS FUTURE LOS: East & West NEW AM PEAK South Approaches / 18,461) V/C: None Approaches HOUR IMPACTS LOS: East, North & TTC Route 405 (N/A) LOS: None Queues: West V/C: West Approach South Approaches Russell Road / Queues: None Approach LOS: West Approach Signalized Queues: None FUTURE Signalized Queues: None Eden Valley Yes Local Road PM PEAK HOUR NEW PM PEAK Drive Kipling Avenue Major Arterial Yes PM PEAK HOUR IMPACTS HOUR IMPACTS NEW PM PEAK Road IMPACTS V/C: None V/C: West Approach HOUR IMPACTS V/C: East, West & LOS: None LOS: East & West V/C: None South Approaches Queues: None Approaches LOS: None LOS: East, West & Queues: East & West Queues: None South Approaches Approaches Queues: East AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK Approach IMPACTS Daily Ridership) HOUR IMPACTS V/C: East Approach TTC Route 73/A/B/C V/C: West Approach LOS: None (429 / 8,850) LOS: East & West Queues: None Approaches Signalized Royal York FUTURE Queues: None Minor Arterial Yes PM PEAK HOUR TTC: ECLRT Road Road IMPACTS GO: NEW PM PEAK V/C: East & West Other: HOUR IMPACTS Approaches V/C: None LOS: East & West LOS: None Approaches Queues: East & West Queues: None Approaches
February, 2010 Page 1-I-2 February, 2010 Page 1-I-3 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
INTERSECTION EXISTING / INTERSECTION EXISTING / TYPE EXISTING FUTURE FUTURE TYPE EXISTING FUTURE FUTURE PROPOSED PROPOSED INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRANSIT INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRANSIT LRT STOP? LRT STOP? UNSIGNALIZED CONDITION TRANSIT CONDITION UNSIGNALIZED CONDITION TRANSIT CONDITION / DRIVEWAY) SERVICE / DRIVEWAY) SERVICE EXISTING (Peak Hour / EXISTING (Peak Hour / NEW AM PEAK Daily Ridership) Daily Ridership) HOUR IMPACTS Unsignalized TTC Route 73B (429 / AM PEAK HOUR TTC Route 71B (275 / V/C: East Approach Mulham Place Yes N/A 8,850) N/A IMPACTS 2,547) LOS: None Local Road V/C: None Queues: East FUTURE LOS: None FUTURE Approach Signalized Black Creek Queues: None New GO Station on AM PEAK HOUR EXISTING (Peak Hour / Major Arterial Yes Georgetown Line NEW PM PEAK Drive IMPACTS Daily Ridership) Road PM PEAK HOUR HOUR IMPACTS V/C: West TTC Route 73B (429 / NEW AM PEAK IMPACTS V/C: East & West Approaches 8,850) HOUR IMPACTS V/C: None Approaches LOS: West TTC Route 79/B (590 / V/C: East Approach LOS: None LOS: East & West Approaches 7,382) LOS: None Queues: None Approaches Signalized Queues: None Queues: None Queues: East & West Scarlett Road Major-Minor Yes FUTURE Approaches Arterial Road PM PEAK HOUR NEW PM PEAK EXISTING (Peak Hour / NEW AM PEAK IMPACTS HOUR IMPACTS AM PEAK HOUR Daily Ridership) HOUR IMPACTS V/C: West V/C: East Approach IMPACTS V/C: None Approaches LOS: East Approach V/C: None FUTURE LOS: None LOS: West Queues: None LOS: None Queues: East Signalized Approaches Bricknell Queues: None Approach Queues: None Collector-Local No Avenue EXISTING (Peak Hour / Road PM PEAK HOUR NEW PM PEAK Unsignalized Daily Ridership) IMPACTS HOUR IMPACTS Emmett Avenue Yes N/A N/A V/C: None V/C: None Collector Road FUTURE LOS: None LOS: None Queues: None Queues: West EXISTING (Peak Hour / Approach AM PEAK HOUR Daily Ridership) AM PEAK HOUR EXISTING (Peak Hour / IMPACTS NEW AM PEAK TTC Route IMPACTS Daily Ridership) V/C: East & North HOUR IMPACTS 35A/B/C/D/E (954 / V/C: East, West & TTC Route 41/B (557 / Approaches V/C: West Approach 40,731) South Approaches 22,765) NEW AM PEAK LOS: East, North & LOS: West Approach LOS: East & West HOUR IMPACTS South Approaches Queues: East FUTURE Approaches FUTURE V/C: None Signalized Queues: None Approach Jane LRT (ridership @ Queues: East & South New 32 Trethewey bus LOS: None
Jane Street Major Arterial Yes Eglinton Ave. W) Trethewey Drive Signalized Approaches route would be Queues: None PM PEAK HOUR NEW PM PEAK Road - AM Peak Hour NB: shortened and operate IMPACTS HOUR IMPACTS / Major Arterial Yes 1,000-1,100 PM PEAK HOUR from Jane Street and NEW PM PEAK V/C: East, West & V/C: None Keele Street Road - AM Peak Hour SB: IMPACTS Lawrence Avenue to HOUR IMPACTS North Approaches LOS: None 1,500-1,900 V/C: West, North & Keele Street and V/C: East Approach LOS: East, West & Queues: West TTC Route 35 South Approaches Eglinton Avenue over LOS: East Approach South Approaches Approach Eliminated LOS: West & North existing 32C branch Queues: None Queues: None Approaches routing AM PEAK HOUR EXISTING (Peak Hour / Queues: East & South NEW AM PEAK IMPACTS Daily Ridership) Approaches HOUR IMPACTS V/C: East, West & TTC Route 71B (275 / V/C: North Approach South Approach 2,547) LOS: West Approach LOS: East & South TT Route 89 (516 / Queues: None Approach 12,987) Signalized Queues: East NEW PM PEAK Weston Road Minor Arterial Yes Approach FUTURE HOUR IMPACTS Road New GO Station on V/C: West Approach PM PEAK HOUR Georgetown Line LOS: East & West IMPACTS Approaches V/C: None Queues: East LOS: None Approach Queues: None
February, 2010 Page 1-I-4 February, 2010 Page 1-I-5 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
INTERSECTION EXISTING / TYPE EXISTING FUTURE FUTURE PROPOSED INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRAFFIC LRT STOP? Traffic Assessment Summary of Existing and Future Conditions UNSIGNALIZED CONDITION TRANSIT CONDITION (East Alignment: Laird Drive to Kennedy Road) / DRIVEWAY) SERVICE EXISTING (Peak Hour / INTERSECTION EXISTING / Daily Ridership) TTC Route 51 (197 / TYPE EXISTING FUTURE FUTURE 3,363) PROPOSED NEW AM PEAK INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRAFFIC TTC Route 54/A/E (863 / AM PEAK HOUR HOUR IMPACTS LRT STOP? 33,846) UNSIGNALIZED CONDITION TRANSIT CONDITION IMPACTS V/C: West TTC Route 100 (754 / / DRIVEWAY) SERVICE V/C: East & South Approach 15,535) Approaches LOS: West EXISTING (Peak Hour / LOS: East Approach Approach Daily Ridership) Signalized FUTURE Queues: East Approach Queues: None TTC Route 51 (197 / TTC Route 51 operates Leslie Street Major Arterial Yes 3,363) between Donlands Road PM PEAK HOUR NEW PM PEAK TTC Route 54/A/E (863 / Station and Leslie & 33,846) IMPACTS HOUR IMPACTS AM PEAK HOUR NEW AM PEAK Eglinton TTC Route 56/B (160 / V/C: East Approach V/C: West IMPACTS HOUR IMPACTS TTC Route 54 operates 3,527) LOS: None Approach V/C: East, West & South V/C: North from Don Mills & Eglinton TTC Route 100 (754 / Queues: None LOS: None Approaches Approach to Lawrence Avenue 15,535) Queues: None LOS: East, West & South LOS: North East
Approaches Approach TTC Route 100 operates FUTURE Queues: East & North Queues: None from Broadview Station Signalized TTC Route 51 operates Approaches and Don Mills & Eglinton between Donlands Laird Drive Major Arterial- Yes NEW PM PEAK EXISTING (Peak Hour / Collector Rd Station and Leslie & AM PEAK HOUR Daily Ridership) PM PEAK HOUR HOUR IMPACTS NEW AM PEAK Eglinton IMPACTS TTC Route 25/D (938 / IMPACTS V/C: West HOUR IMPACTS TTC Route 54 operates V/C: All Approaches 41,823) V/C: East & North Approach V/C: None from Don Mills & Eglinton LOS: All Approaches TTC Route 100 (754 / Approaches LOS: West LOS: None to Lawrence Avenue Queues: East & South 15,535) LOS: East & North Approach Queues: None East Signalized Approaches Approaches Queues: West TTC Route 56 operates FUTURE Queues: North Approach Approach Don Mills Road Major Arterial Yes NEW PM PEAK between Donlands PM PEAK HOUR Don Mills LRT (ridership Road HOUR IMPACTS Station and Laird & IMPACTS @ Eglinton Ave. E) V/C: None Eglinton V/C: All Approaches - AM Peak Hour NB: LOS: None TTC Route 100 operates LOS: All Approaches 1,700-1,800 Queues: East & from Broadview Station Queues: South - AM Peak Hour SB: West Approaches and Don Mills & Eglinton Approaches 1,700-2,000 EXISTING (Peak Hour / TTC Route 25 Eliminated Daily Ridership) EXISTING (Peak Hour / TTC Route 51 (197 / Daily Ridership) 3,363) Unsignalized TTC Route 100/A/D (754 TTC Route 54/A/E (863 / Gervais Drive / Collector-Local Yes N/A / 15,535) N/A 33,846) Ferrand Drive Road AM PEAK HOUR TTC Route 56B (160 / FUTURE IMPACTS 3,527) V/C: East & West TTC Route 100 (754 / NEW AM PEAK Approaches 15,535) HOUR IMPACTS AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK LOS: East & West V/C: None IMPACTS Daily Ridership) HOUR IMPACTS Approaches FUTURE LOS: None V/C: South Approach V/C: None Signalized LOS: South Approach FUTURE LOS: None Queues: West Approach TTC Route 51 operates Queues: None Don Valley Signalized Brentcliffe Road Minor Arterial- Yes between Donlands Queues: None Queues: None Pkwy. SB Municipal No Collector Rd PM PEAK HOUR Station and Leslie & NEW PM PEAK IMPACTS Eglinton HOUR IMPACTS (West) Expressway PM PEAK HOUR NEW PM PEAK V/C: East & West TTC Route 54 operates V/C: None IMPACTS HOUR IMPACTS Approaches from Don Mills & Eglinton LOS: None V/C: South Approach V/C: None LOS: East & West to Lawrence Avenue Queues: None LOS: South Approach LOS: None Approaches East Queues: South Approach Queues: None Queues: None TTC Route 56 operates between Donlands Station and Laird & Eglinton TTC Route 100 operates from Broadview Station and Don Mills & Eglinton
February, 2010 Page 1-I-6 February, 2010 Page 1-I-7 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
INTERSECTION EXISTING / INTERSECTION EXISTING / TYPE EXISTING FUTURE FUTURE TYPE EXISTING FUTURE FUTURE PROPOSED PROPOSED INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRAFFIC INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRAFFIC LRT STOP? LRT STOP? UNSIGNALIZED CONDITION TRANSIT CONDITION UNSIGNALIZED CONDITION TRANSIT CONDITION / DRIVEWAY) SERVICE / DRIVEWAY) SERVICE AM PEAK HOUR EXISTING (Peak Hour / AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK IMPACTS Daily Ridership) NEW AM PEAK IMPACTS Daily Ridership) HOUR IMPACTS V/C: West & North HOUR IMPACTS V/C: East, West & TTC Route 24/A/B/D V/C: None Approach FUTURE V/C: None North Approaches (716 / 22,718) LOS: None LOS: North Approach LOS: None LOS: East & West TTC Route 70A (340 / Queues: None Don Valley Signalized Queues: None Queues: None Signalized Approaches 7,960) Victoria Park Queues: East Approach NEW PM PEAK Pkwy. NB Municipal No Major Arterial Yes (East) Expressway PM PEAK HOUR NEW PM PEAK Avenue FUTURE HOUR IMPACTS IMPACTS HOUR IMPACTS Road PM PEAK HOUR V/C: None V/C: East & North V/C: None IMPACTS LOS: None Approach LOS: None V/C: All Approaches Queues: East LOS: North Approach Queues: None LOS: East, West & Approach Queues: None South Approaches AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK Queues: None IMPACTS Daily Ridership) HOUR IMPACTS AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK V/C: None TTC Route 100/A/D (754 V/C: None IMPACTS Daily Ridership) HOUR IMPACTS LOS: None / 15,535) LOS: None V/C: None TTC Route 70A (340 / V/C: None Signalized Queues: None TTC Route 144 (270 / Queues: None LOS: None 7,960) LOS: None Wynford Drive Major-Minor Yes 573) Queues: None Queues: None Arterial Road PM PEAK HOUR NEW PM PEAK Signalized FUTURE IMPACTS FUTURE HOUR IMPACTS Eglinton Square Major Arterial No PM PEAK HOUR NEW PM PEAK V/C: East Approach New GO Station on V/C: None Road IMPACTS HOUR IMPACTS LOS: East Approach Richmond Hill Line LOS: None V/C: West Approach V/C: East Queues: None Queues: None LOS: None Approach EXISTING (Peak Hour / NEW AM PEAK Queues: None LOS: West AM PEAK HOUR Daily Ridership) HOUR IMPACTS Approach IMPACTS V/C: None Queues: None V/C: East & West FUTURE LOS: None AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK Approaches New GO Station on Queues: West IMPACTS Daily Ridership) HOUR IMPACTS Swift Drive / Signalized LOS: West Approach Richmond Hill Line Approach V/C: East & West TTC Route 67/A (315 / V/C: None Queues: East Approach Approaches 4,537) LOS: None Credit Union Local-Collector Yes NEW PM PEAK LOS: East & West Queues: None Drive Road PM PEAK HOUR HOUR IMPACTS Signalized Approaches FUTURE IMPACTS V/C: None Pharmacy Queues: East & North NEW PM PEAK Minor Arterial Yes V/C: East Approach LOS: West Avenue Approaches HOUR IMPACTS LOS: East Approach Approach Road V/C: None Queues: None Queues: East PM PEAK HOUR LOS: West Approach IMPACTS Approach AM PEAK HOUR EXISTING (Peak Hour / V/C: East Approach Queues: None IMPACTS Daily Ridership) LOS: East Approach V/C: East & West TTC Route 91/C/F (370 / Queues: East Approach NEW AM PEAK Approaches 4,949) AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK HOUR IMPACTS LOS: East & West IMPACTS Daily Ridership) HOUR IMPACTS V/C: None Approaches FUTURE V/C: West Approach V/C: None LOS: None Queues: West & North LOS: None FUTURE LOS: East & West Queues: None Sloan Avenue / Signalized Approaches Queues: None Approaches
Queues: None Bermondsey Minor Arterial Yes NEW PM PEAK PM PEAK HOUR Signalized PM PEAK HOUR Road Road HOUR IMPACTS IMPACTS Lebovic Avenue Yes IMPACTS NEW PM PEAK V/C: None Collector Road V/C: East & West V/C: East & West HOUR IMPACTS LOS: None Approaches Approaches V/C: None Queues: East LOS: East & West LOS: East & West LOS: None Approach Approaches Approaches Queues: None Queues: East, West & Queues: West North Approaches Approach
February, 2010 Page 1-I-8 February, 2010 Page 1-I-9 REPORT REPORT
Toronto Transit Commission (TTC) Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
INTERSECTION EXISTING / INTERSECTION EXISTING / TYPE EXISTING FUTURE FUTURE TYPE EXISTING FUTURE FUTURE PROPOSED PROPOSED INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRAFFIC INTERSECTION (SIGNALIZED / TRAFFIC CONNECTING TRAFFIC LRT STOP? LRT STOP? UNSIGNALIZED CONDITION TRANSIT CONDITION UNSIGNALIZED CONDITION TRANSIT CONDITION / DRIVEWAY) SERVICE / DRIVEWAY) SERVICE AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK IMPACTS Daily Ridership) HOUR IMPACTS IMPACTS Daily Ridership) HOUR IMPACTS V/C: All Approaches TTC Route 68/B (625 / V/C: None V/C: None V/C: West LOS: East, North & 16,442) LOS: West LOS: None FUTURE Approach South Approaches Approaches Queues: None LOS: East & West Signalized Queues: East, North & FUTURE Queues: None Approaches Warden Avenue Major Arterial Yes South Approaches Rosemount Signalized PM PEAK HOUR Queues: East & NEW PM PEAK No IMPACTS West Approaches Road PM PEAK HOUR HOUR IMPACTS Drive Collector Road V/C: East Approach IMPACTS V/C: None LOS: None NEW PM PEAK V/C: All Approaches LOS: None Queues: None HOUR IMPACTS LOS: All Approaches Queues: West V/C: None Queues: East & North Approach LOS: East & West Approaches Approaches AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK Queues: None IMPACTS Daily Ridership) HOUR IMPACTS AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK V/C: None V/C: West IMPACTS Daily Ridership) HOUR IMPACTS LOS: None FUTURE Approach V/C: None V/C: West Queues: None LOS: East & West LOS: None FUTURE Approach Approaches Queues: None LOS: East & West PM PEAK HOUR Queues: None Approaches Signalized Prudham Gate No IMPACTS PM PEAK HOUR Queues: East & Collector Road V/C: None NEW PM PEAK Signalized IMPACTS West Approaches LOS: None HOUR IMPACTS Ionview Road Yes V/C: None Queues: None V/C: East Collector Road LOS: None NEW PM PEAK Approach Queues: None HOUR IMPACTS LOS: East & West V/C: East Approaches Approach Queues: South LOS: East & West Approach Approaches AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK Queues: East & IMPACTS Daily Ridership) HOUR IMPACTS West Approaches V/C: None V/C: West AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK LOS: None FUTURE Approach IMPACTS Daily Ridership) HOUR IMPACTS Queues: None LOS: West V/C: West Approach TTC Route 43/B (498 / V/C: East Approach LOS: East & West 14,624) Approach Signalized PM PEAK HOUR Queues: West Approaches TTC Route 113 (201 / LOS: None Sinnott Road No IMPACTS Approach Queues: East & South 4,183) Queues: West Collector Road V/C: East & West Signalized Approaches Approach Approaches NEW PM PEAK Kennedy Road Major Arterial Yes FUTURE LOS: West Approach HOUR IMPACTS PM PEAK HOUR NEW PM PEAK Queues: None V/C: None Road IMPACTS HOUR IMPACTS LOS: East V/C: East, West & V/C: None Approach South Approaches LOS: None Queues: None LOS: East, West & Queues: West AM PEAK HOUR EXISTING (Peak Hour / NEW AM PEAK South Approaches Approach IMPACTS Daily Ridership) HOUR IMPACTS Queues: East & South V/C: West, North & TTC Route 17/A/C (451 V/C: East Approaches South Approaches / 10,137) Approach LOS: All Approaches LOS: None Queues: East, North & FUTURE Queues: West Signalized Birchmount South Approaches Approach Major-Minor Yes Road Arterial Road PM PEAK HOUR NEW PM PEAK IMPACTS HOUR IMPACTS V/C: East Approach V/C: West LOS: East & West Approach Approaches LOS: None Queues: None Queues: East & West Approaches
February, 2010 Page 1-I-10 February, 2010 Page 1-I-11
REPORT
Toronto Transit Commission (TTC) SECTION 1: TRANSIT PROJECT ASSESSMENT STUDY - OVERALL TRAFFIC ANALYSIS
APPENDIX II
GRAPHIC SUMMARY OF TRAFFIC OPERATIONS:
EXISTING AND FUTURE CONDITIONS