The World Bank Report No: ISR6127

Implementation Status & Results ET: Agricultural Growth Program (P113032)

Operation Name: ET: Agricultural Growth Program (P113032) Project Stage: Implementation Seq.No: 3 Status: ARCHIVED Archive Date: 28-Mar-2012 Country: Ethiopia Approval FY: 2011

Public Disclosure Authorized Product Line:IBRD/IDA Region: AFRICA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 30-Sep-2010 Original Closing Date 30-Sep-2015 Planned Mid Term Review Date 01-May-2013 Last Archived ISR Date 07-Sep-2011 Public Disclosure Copy Effectiveness Date 16-Feb-2011 Revised Closing Date 30-Sep-2015 Actual Mid Term Review Date

Project Development Objectives ET: Agricultural Growth Program (P113032) Project Development Objective (from Project Appraisal Document) The PDO is to increase agricultural productivity and market access for key crop and livestock products in targeted woredas with increased participation of women and youth. Has the Project Development Objective been changed since Board Approval of the Program?

Public Disclosure Authorized Yes No

Component(s)

Component Name Component Cost 1.1 Institutional Strengthening and Development 36.70 1.2 Scaling Up Best Practices 28.20 1.3 Market and Agribusiness Development 50.80 2.1 Small-scale Agricultural Water Development and Management 80.30 2.2 Small-scale Market Infrastructure Development and Management 51.10 3.1 AGP Management at the Federal, Regional, Zonal, and Woreda levels 11.40 3.2 Monitoring and Evaluation 6.70 Public Disclosure Authorized Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory

Public Disclosure Copy Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating High

Page 1 of 8 Public Disclosure Authorized The World Bank Report No: ISR6127

Implementation Status Overview The overall progress for the first 6 months of Ethiopian Fiscal Year 2004 (July 8, 2011 to January 7, 2012) was well below the plan for this period. Total use of funds (of all Government-implemented parts) in the first 2 quarters of EFY04 was reported to be ETB61.9 million or 18 percent of the target for the reporting period. Significant differences exist between various implementing agencies, regions, and woredas, and between project components and activities. While achievement compared with the plan is low, the significant progress made during the past six months is recognized. The plan was unrealistic and a faster implementation would have led to low implementation quality. Fund use is expected to accelerate further over the next months. Overall Implementation Progress is rated Moderately Satisfactory, i.e., satisfactory with moderate shortcomings mainly related to weak planning.

Locations Country First Administrative Division Location Planned Actual Ethiopia SSNPR Sidama Awraja Public Disclosure Copy Ethiopia Regional State Jarso

Ethiopia Oromia Regional State Giyon

Ethiopia SSNPR Guraghe Zone

Ethiopia Oromia Regional State Arsi Kifle Hager

Ethiopia Oromia Regional State Oromiya Kilil

Ethiopia SSNPR Southern Nations, Nationalities, and People's Regional State Ethiopia Oromia Regional State Sakka

Ethiopia Not Entered Decha

Ethiopia Oromia Regional State Hidabu Abote

Ethiopia Oromia Regional State Yaya Gulelena Debre Liban

Ethiopia Oromia Regional State Dendi

Ethiopia Oromia Regional State Ambo

Ethiopia Oromia Regional State Becho

Ethiopia Oromia Regional State Wonchi

Ethiopia Oromia Regional State Ada'a Chukala

Ethiopia Oromia Regional State Gimbichu

Public Disclosure Copy Ethiopia Oromia Regional State Leka

Ethiopia Oromia Regional State Guduru

Page 2 of 8 The World Bank Report No: ISR6127

Country First Administrative Division Location Planned Actual Ethiopia Oromia Regional State Gechi

Ethiopia Oromia Regional State Bedele

Ethiopia Oromia Regional State Didessa

Ethiopia Oromia Regional State Gomma

Ethiopia Oromia Regional State Gera

Ethiopia Oromia Regional State Sherka

Public Disclosure Copy Ethiopia Oromia Regional State Munesa

Ethiopia Oromia Regional State Adaba

Ethiopia Oromia Regional State Dodola

Ethiopia Oromia Regional State Kofele

Ethiopia Oromia Regional State Sinanana Dinsho

Ethiopia Oromia Regional State Gaserana

Ethiopia Oromia Regional State Agarfa

Ethiopia Oromia Regional State Walmara

Ethiopia Tigray Regional State Alamata

Ethiopia Tigray Regional State Raya Azebo

Ethiopia Tigray Regional State Ofla

Ethiopia Tigray Regional State Endamehoni

Ethiopia Tigray Regional State

Ethiopia Tigray Regional State Wolqayt

Ethiopia Tigray Regional State Kafta Humera

Ethiopia Tigray Regional State Tahtay Adiyabo

Ethiopia The State of Amhara Jabi Tehnan

Public Disclosure Copy Ethiopia The State of Amhara Bahir Dar Zuria

Ethiopia The State of Amhara Dejen

Page 3 of 8 The World Bank Report No: ISR6127

Ethiopia The State of Amhara Enemay

Ethiopia The State of Amhara Ankesha

Ethiopia The State of Amhara Guangua

Ethiopia The State of Amhara

Ethiopia The State of Amhara

Ethiopia The State of Amhara

Ethiopia The State of Amhara Public Disclosure Copy Ethiopia The State of Amhara Dera

Ethiopia The State of Amhara

Ethiopia The State of Amhara Antsokiyana Gemza

Ethiopia The State of Amhara

Ethiopia The State of Amhara

Ethiopia Not Entered Chena

Ethiopia Not Entered Enemorina Eaner

Ethiopia Not Entered Shebedino

Ethiopia Not Entered Bule

Ethiopia Not Entered Yem

Ethiopia Not Entered Basketo

Ethiopia Not Entered West

Ethiopia Oromia Regional State East Shewa Zone

Ethiopia Oromia Regional State East Wellega Zone

Ethiopia The State of Amhara West Gojam

Ethiopia The State of Amhara East Gojam

Ethiopia The State of Amhara Awi Public Disclosure Copy Ethiopia The State of Amhara North Gonder

Page 4 of 8 The World Bank Report No: ISR6127

Ethiopia SSNPR Siltie Zone

Ethiopia Not Entered Dawuro

Not Entered Not Entered Not Entered

Ethiopia Not Entered Gedeo

Results

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Public Disclosure Copy Percentage increase in total real value of Number Value 7126.00 8731.00 marketed agricultural products (including Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 livestock) per household (in ETB). Comments Value from 'rapid' baseline, to No further survey was be updated. undertaken since rapid Percentage increase in agricultural yield Percentage Value 9.90 11.50 (basket crops and livestock products). Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments Value from 'rapid' baseline, to No further survey was be updated. undertaken since rapid baseline.

Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Market infrastructure (roads and markets) Percentage Value 0.00 80.00 sustainably managed one year after the Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 investment is completed. Comments Users satisfied with the quality of market Percentage Value 66.20 76.00 infrastructure (roads and markets). Date 31-Mar-2010 30-Sep-2015 Comments No further survey was undertaken since 'rapid baseline'. Decrease in time for farmers to travel to Percentage Value 52.00 49.00 nearest market center. Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments Increase in areas treated under sustainable Percentage Value 45.00

Public Disclosure Copy land management (in hectares). Date 31-Mar-2010 15-Nov-2010 30-Sep-2015

Page 5 of 8 The World Bank Report No: ISR6127

Comments Baseline not yet available. No further survey was undertaken since 'rapid baseline'. Area under irrigation (percent of cultivated Percentage Value 4.50 6.10 land) Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments No further survey was undertaken since 'rapid baseline'. Infrastructure (for agricultural water) used 1 Percentage Value 0.00 80.00 year after the investment is completed. Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments

Public Disclosure Copy Implementation has not yet started. Farmers benefiting from the investments of Number Value 0.00 72.00 sub-component 2.1 (in 1000). Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments Implementation has not yet started. Sales value of key selected value chain Percentage Value commodities supported at the end-of-the-value- Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 chain. Comments Baseline not yet available. No survey was undertaken yet. Sub-projects fully operational and sustainably Number Value 0.00 50.00 managed 2 years after initial investment (in Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 1000). Comments No survey was undertaken yet. Farm households with innovative best practices Number Value 0.00 126.00 (in 1000). Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments No survey was undertaken yet. Farm households who are members of Percentage Value 36.00 40.00 functional farmer organizations. Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments No further survey was undertaken since 'rapid baseline'. Farmers satisfied with quality of extension Percentage Value 79.00 87.00 services provided. Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Public Disclosure Copy

Page 6 of 8 The World Bank Report No: ISR6127

Comments No further survey was undertaken since 'rapid baseline'.

Data on Financial Performance (as of 06-Mar-2012)

Financial Agreement(s) Key Dates Project Loan No. Status Approval Date Signing Date Effectiveness Date Closing Date P113032 IDA-47830 Effective 30-Sep-2010 19-Oct-2010 16-Feb-2011 30-Sep-2015 P113032 IDA-H6000 Effective 30-Sep-2010 19-Oct-2010 16-Feb-2011 30-Sep-2015 P113032 TF-99729 Effective 12-Jul-2011 18-Jul-2011 18-Jul-2011 30-Sep-2015 Public Disclosure Copy

Disbursements (in Millions) Project Loan No. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P113032 IDA-47830 Effective USD 108.40 108.40 0.00 9.46 103.45 9.00 P113032 IDA-H6000 Effective USD 41.60 41.60 0.00 6.25 36.96 15.00 P113032 TF-99729 Effective USD 6.20 6.20 0.00 5.77 9.71 93.00

Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation

Page 7 of 8 The World Bank Report No: ISR6127

The Mission strongly encourages a focus on the quality of the investments rather than fund use and strong focus on the planning for Ethiopian Fiscal Year 2005.

Restructuring History There has been no restructuring to date.

Related Projects P127507-Agricultural Growth Project - Additional Financing Public Disclosure Copy Public Disclosure Copy

Page 8 of 8