BAGBY STREET IMPROVEMENT PROJECT OPEN HOUSE DECEMBER 6, 2018 OPEN HOUSE AGENDA

• Welcome • Team Introduction • Project Background • Project Overview • Corridor Design • Block-by-Block Plans and Renderings • Next Steps • Tabletop Discussions Project Management DESIGN TEAM Civil & Electrical Design 27% MWSDBE Landscape Architecture

Lighting Design (WBE)

Structural Investigation & Design (MBE/SBE/DBE)

Modal Concepts & Review

Topographic Survey & SUE (MBE/SBE/DBE)

Utility Design (MBE/DBE, Hire First)

Geotechnical Investigation (MBE/DBE)

TAS Review& Inspection (WBE/DBE)

CCTV Inspection (MBE/SBE/DBE) 03 04 HOUSTON BIKE PLAN

05 THEATER DISTRICT MASTER PLAN

06 PLAN DOWNTOWN

07 PLAN DOWNTOWN

08 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT

09 WESTERN DOWNTOWN FACILITIES MASTER PLAN Study Area

Scope

• Location analysis • Facilities assessment • Opportunity identification • Establish actionable framework for long-term transformation

Team

10 BAGBY STREET | TRAFFIC IMPACT ANALYSIS

Consultants: Phase I

Traffic Engineers, Inc.

Lockwood Andrews Newnam, Inc.

C.N. Koelh Urban Forestry, Inc.

CJ Hensch & Associates, Inc. 11 TRAFFIC OPERATIONS | SELECTED ALTERNATIVE

EXISTING | A.M. PEAK EXISTING | P.M. PEAK

PROPOSED | A.M. PEAK PROPOSED | P.M. PEAK

12 BAGBY STREET IMPROVEMENT PROJECT

13 STREET OF CIVIC & CULTURAL FACILITIES

14 STREET OF PARKS

15 STAKEHOLDER COORDINATION

I A. City Hall & Hermann Square [MOSE, GSD, HPARD] B. Central Library & Barbara Bush Literacy Plaza [HPL, GSD] K H C. Park K [MOSE, GSD, HPARD, Heritage Society] D. Tranquillity Park & Little Tranquillity Park E L [HFC, GSD, HPARD] E. Hobby Center & Wortham Theater G [HFC, Houston Ballet, Houston Grand Opera] F. Margaret Alkek Educational Building D F E [TUTS] G. D [The Cordish Companies] H. Downtown Aquarium [Landry’s] C A I. Post HTX K B [Lovett Commercial] J. & DoubleTree Hotel J K [Brookfield] J K. Western Downtown Facilities Master Plan [GSD] L. North Houston Highway Improvement Project [TxDOT] 16 COORDINATION AT CITY HALL & HERMANN SQUARE

BAGBY

CITY

KINNEY HALL

C

M WALKER

SMITH 17 DESIGN PRINCIPLES

• Develop Bagby Street . . . Existing • as the gateway to Western Downtown • to adapt for daily and civic activities • as new type of multi-modal corridor • to accommodate short- and long-term needs • Establish unified corridor aesthetic • Hardscape & landscape materials • Lighting • Special moments Proposed • Upgrade subsurface features • Design to budget

18 CORRIDOR HARDSCAPE

BAGBY STREET

BAGBY ST. STREET BUFFER/ CYCLE TRACK PEDESTRIAN PLANTING ZONE 10’ WIDTH w/ ZONE 4’ TO 6’ WIDTH 1’ ACCENT BAND WIDTH VARIES EACH SIDE 19 TYPICAL STREET CORNERS

CURB

BAGBY STREETLIGHT

STREET BUFFER/ PLANTING ZONE COBBLE

CYCLE TRACK 8” HEX., DARK GRAY FIELDS, LIGHT GRAY LANE MARKERS

ACCENT BAND 6”x12” SOLIDER COURSE, LIGHT GRAY DETECTABLE DOMES

PEDESTRIAN ZONE 4”x8” HERRINGBONE, MED., LT., & DK. GRAY MIX

20 CORRIDOR LANDSCAPING

21 CORRIDOR LIGHTING

WIDTH 4’ to 6’ VARIES TYP. 4’ to 6’ TYP. WIDTH VARIES

TYPICAL LIGHTING SECTION

22 CORRIDOR UTILITIES

23 BAGBY STREET IMPROVEMENT PROJECT

24 BAGBY | CLAY TO LAMAR

GARAGE DALLAS HERITAGE SOCIETY LAMAR

A B

BAGBY

B’ A’ DOUBLETREE HERITAGE PLAZA

SECTION B-B’ SECTION A-A’ 25 BAGBY | LAMAR TO WALKER

SAM HOUSTON PARK CITY HALL ANNEX C

D

BAGBY

D’ C’ LIBRARY

CITY HALL

LAMAR

WALKER MCKINNEY

ELEVATED CONCRETE BOARDWALK

SECTION C-C’ SECTION D-D’ 26 CENTRAL LIBRARY LOOKING NORTH EXISTING 27 CENTRAL LIBRARY LOOKING NORTH PROPOSED 28 LOOKING NORTH EXISTING 29 SAM HOUSTON PARK LOOKING NORTH PROPOSED 30 CITY HALL ANNEX & CITY HALL LOOKING NORTH EXISTING 31 CITY HALL ANNEX & CITY HALL LOOKING NORTH PROPOSED 32 BAGBY | WALKER TO CAPITOL

HOBBY CENTER E

BAGBY F

E’

F’ WALKER TRANQUILLITY PARK LITTLE TRANQUILLITY PARK

SECTION E-E’ SECTION F-F’ 33 HOBBY CENTER & TRANQUILLITY PARK LOOKING NORTH EXISTING 34 HOBBY CENTER & TRANQUILLITY PARK LOOKING NORTH PROPOSED 35 LITTLE TRANQUILLITY PARK LOOKING SOUTH EXISTING 36 LITTLE TRANQUILLITY PARK LOOKING SOUTH PROPOSED 37 BAYOU PLACE LOOKING SOUTH EXISTING 38 BAYOU PLACE LOOKING SOUTH PROPOSED 39 BAGBY | CAPITOL TO PRAIRIE

AQUARIUM

BAYOU PLACE

G H

BAGBY DECK DECK REPLACEMENT REPLACEMENT

H’ G’ BAYOU PLACE

SECTION G-G’ SECTION H-H’ 40 BAGBY | PRAIRIE TO FRANKLIN

AQUARIUM K

J

K’

J’ PRESTON

SECTION J-J’ SECTION K-K’ 41 NEXT STEPS

• December 6, 2018 _ Public Meeting • February 2019 _ 90% Plan Submission • April 2019 _ 100% Plan Submission, Final Plan Approvals, Permitting • May 2019 _ Contractor Procurement • June 2019 - June 2021 _ Construction

42 BAGBY STREET IMPROVEMENT PROJECT

PROJECT CONTACT: LONNIE HOOGEBOOM, Director of Planning & Design [email protected]