for PROPOSED EXPANSION OF “UDDIPA" (RESIDENTIAL COMPLEX)

at Premises No. 1, Kashinath Dutta Road, , Dag. No. 921 to 925, JL No. 8, P.S: Baranagar, District North 24 Parganas, -700 036

SUBMITTED TO STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, GOVT. OF

Project Proponent

Square Four Housing & Infrastructure Development Pvt. Ltd. (previously M/s. Overflow Tradelink Pvt. Ltd.) 238A, A.J.C. Bose Road, 2nd Floor, Suit – 2B, Kolkata – 700020

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, , Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

FORM 1

(I) Basic Information Sl. Item Details No. Vertical Expansion of “UDDIPA” Residential 1 Name of the project/s Complex 2 Sl. No. in the schedule Sl. No. 8 (a) Project scenario as per EC granted by SEIAA, West Bengal, as well as the revised scenario after expansion are tabulated:

As per Environmen tal clearance

already Total Project received Expansion Project Details (memo No. Project Scenario 2331 / EN / T-II-1 / 071 / 2015 dated 21.10.2016) Proposed capacity/area/length/ tonnage to be 3 Blocks Block 3 Blocks 3 Blocks 3 handled/ command area/lease area/number of (2 Additional details (B+G+18) (B+G+20) wells to be drilled Floors) Built Up 37444.12 3502.816 40946.936 Area sqm sqm sqm 9696.94 9696.94 Land Area - sqm (Vertical sqm Land Left 812.186 Expansion 812.186 for Road shall takes sqm. sqm. Widening place in the Net Land 8884.754 same 8884.754 Area sqm. premises) sqm. Nos. of 324 36 360 flats Project 98 crores 7 crores 105 crores Cost

4 New /Expansion/Modernization Vertical Expansion Project Only piling work has started at the site. No work 5 Existing Capacity/ Area etc. related to super-construction has yet started for the project. 6 Category of project i.e. ‘A’ or ’B’ Category B Does it attract the general condition? If yes, 7 No please specify. Does it attract the specific condition? If yes, 8 No please specify. Premises No. 1, Kashinath Dutta Road, Dag. No. 921 to 925, JL No. 8, Baranagar 9 Location Municipality, P.S: Baranagar, District North 24 Parganas, Kolkata -700036.

FORM 1 Page 1

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

Site Co-ordinate: Latitude - 22° 37' 55.44" N Longitude - 88° 22' 37.70" E. Plot/Survey/Khasra No. Dag. No. 921 to 925, J L No. 8 Village Khatian No. 549 Tehsil Baranagar District 24 Paraganas (N) State West Bengal Railway Station (Junction) – 2.1 km Nearest railway main station/airport along with from project site. 10 distance in kms. Netaji Subhash Chandra Bose International Airport, Kolkata – 6.4 km from project site. Nearest Town, City District Headquarters 11 Within Kolkata city along with distance in kms. Baranagar Municipal Office, Village Panchayats, Zilla Parishad, Municipal 87, Deshbandhu Road (East) Corporation, Local body (complete Kolkata-700035 12 postal addresses with telephone nos. to be Phone No. - (033) 2577-6595 / 0012, given) Fax No:- 033-25771071 email Id: [email protected] Square Four Housing & Infrastructure 13 Name of the applicant Development Pvt. Ltd. (Previously M/s. Overflow Tradelink Pvt. Ltd.) 238A, A J C Bose Road, 2nd Floor, Suit No. - 14 Registered Address 2B, Kolkata – 700020 Address for correspondence: Name Somnath Samanta Designation (Owner/Partner/CEO) Director 238A, A J C Bose Road, 2nd Floor, Suit No. - Address 15 2B, Kolkata Pin Code 700020 E-mail [email protected] Telephone No. (033) 2290 3179/3185 Fax No. (033) 2290 3179 Details of Alternative Sites examined, if any. 16 Location of these sites should be shown on a NA topo sheet. 17 Interlinked Projects No Whether separate application of interlinked 18 No project has been submitted? 19 If yes, data of submission NA 20 If no, reason NA

FORM 1 Page 2

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given. 21 No (a) The Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (c) The CRZ Notification, 1991? Whether there is any Government 22 NA Order/Policy relevant/relation to the site? 23 Forest land involved (hectares) No Whether there is any litigation pending against No the project and /or land in which the project is propose to be set up? 24 (a) Name of the Court (b) Case No. (c) Orders/directions of the Court, if any and its relevance with the proposed project.

* Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease area and production capacity for mineral production, area for mineral exploration, length for linear transport infrastructure, generation capacity for power generation etc.)

FORM 1 Page 3

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sl. Information/Checklist Yes/ Details thereof (with approximate quantities /rates, No. confirmation No wherever possible) with source of information data The proposed project site measuring 8884.754 sqm (after Permanent or temporary gifting 812.186 sqm for road widening purpose) is in Premises change in land use, land No. 1, Kashinath Dutta Road, Dag. No. 921 to 925, J. L. No. cover or topography 8, P.S. - Baranagar, Dist. North 24 Parganas, Kolkata. A few 1.1 including increase in No dilapidated structures were present at the project site, which intensity of land use (with have been demolished and the demolition debris are being respect to local land use used for site development activities. This is a vertical plan) expansion project of Residential Complex. As per area Master Plan, this land is earmarked for such development. A few dilapidated structures were present at the project site, which have been demolished and the demolition debris are being used for site development activities. There are 28 nos. Clearance of existing land, 1.2 Yes existing trees within the project site. 15 nos. of trees shall be vegetation and buildings? felled. 13 nos. of trees shall be retained. Permission for felling of trees has already been obtained from the competent authorities. The proposed site is earmarked for the development of Creation of new land Residential Complex. The proposed project will be developed 1.3 No uses? as per the Development / Master Plan of the area and following the local building by-laws. Pre-construction Soil testing has already been conducted for foundation 1.4 investigations e.g. bore Yes design. The test results are found to be satisfactory. houses, soil testing? During expansion (Phase-2): 2 floors shall be added above the 3 Blocks of B+G+18 1.5 Construction works? Yes configuration. Thus, after the vertical expansion, the 3 Blocks shall be of B+G+20 configuration. A few dilapidated structures were present at the project site, which have been demolished and the demolition debris are 1.6 Demolition works? Yes being used for site development activities. For the vertical expansion part, no demolition work is necessary. Piling work has started at the project site for the Phase – 1 of the project for which EC vide memo. No. 2331/EN/T-II- 1/071/2015 dated 21.10.2016 and Consent to Establish (NOC) vide Memo No. 806-2N-70/2015(E) dated 14.12.2016 Temporary sites used for has already been obtained. Local workers, to the tune of 150 construction works or 1.7 Yes nos. will be employed for the construction activities. No housing of construction temporary labour hutment is proposed. Restrooms and proper workers? sanitation facilities are being provided. Septic tank is being maintained at site. All the construction activity including storing of raw materials has been confined within the project site only. Above ground buildings, The civil works for the construction and development of the 1.8 Yes structures or earthworks proposed project include earthwork excavation, foundation for

FORM 1 Page 4

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

Sl. Information/Checklist Yes/ Details thereof (with approximate quantities /rates, No. confirmation No wherever possible) with source of information data including linear structures, buildings and structures, construction of internal roads, cut and fill or excavations pavements, parking area, water storage tanks, storm water drain, water supply and sewer/drainage network, landscaping and security fencing, etc. The entire construction activities will be carried out under the guidance and supervision of experienced engineers and architects. Since all such construction activities will be confined within the project premises, there will be no physical changes outside the project boundary. Underground works 1.9 including mining or Yes The 3 Blocks of Residential buildings shall have basements. tunneling? 1.10 Reclamation works? No - 1.11 Dredging? No - 1.12 Offshore structures? No - It is a construction project and there will be construction of Production and 1.13 No residential towers; hence no production / manufacturing manufacturing processes? process is involved. Majority of the construction materials are being stored in the godown. Sand, stone chips etc. are being stored in covered place earmarked for the purpose, within project area. Cement Facilities for storage of 1.14 Yes is being stored under cover in bales. Bricks, stone chips and goods or materials? steel have been laid in open. Other miscellaneous items (like wood, wires, plumbing materials, paints, glass etc.) will be stored in covered areas. 1.15 Facilities for treatment or Yes Construction Phase disposal of solid waste or liquid effluents? Solid Waste:

Construction debris including bricks, gravel, rubbish, waste of plaster, concrete debris, metal tiles, etc. will be used within the project site for land filling activities, road work, etc. Other wastes like, pieces of steel, cement bags, waste paper and cardboard packing material will be sold off to recyclers. MSW generated by the construction workers would be 30 kg/day (150 persons @ 0.2 kg/day) which would be stored at a place within the site (VAT). From there it be collected, transported, treated and disposed off by Baranagar Municipality.

Operation Phase

Solid Waste:

Solid waste during operational phase in general will be of domestic nature. Garbage will be segregated at source for biodegradable, in-organic recyclables and in-organic inert material during operational phase (92.5 kg/day) (Phase – 2). Total MSW will be stored at a place within the site. Organic

FORM 1 Page 5

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

Sl. Information/Checklist Yes/ Details thereof (with approximate quantities /rates, No. confirmation No wherever possible) with source of information data component will be managed in house by installing mechanical composter, inorganic recyclables will be sold to vendors and inorganic inert material will be stored at a place within the site (VAT). From there it be collected, transported, treated and disposed off by Baranagar Municipality as per MSW (M&H) Rules, 2000.

Liquid Waste:

During construction phase wastewater originating from labour huts will be diverted to septic tank followed by soak pit by a temporary connection to Baranagar Municipality sewer drain.

The wastewater will be collected through a well-designed sewer network leading to STP. The proposed STP will be based on FAB (Fluidized Aerobic Bio-reactor) technology followed by tertiary treatment and UV radiation for disinfection. Treated water, meeting the relevant norms will be used in non-critical purposes within the complex. Surplus treated wastewater will be disposed of into the Baranagar Municipality sewer system.

Concurrence letter from Baranagar Municipality for providing infrastructural support such as water supply, discharge of sewage and storm water and disposal of solid waste has already been obtained. 1.16 Facilities for long term No Attempts will be made to use local people in different housing of operational operational activities of the project. As such, housing facilities workers? for operational workers have not been considered for the project. 1.17 New road, rail or sea Yes Internal roads will be constructed within the complex. traffic during construction or operation? 1.18 New road, rail, air No Not applicable. waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of No Not applicable. existing transport routes or infrastructure leading to changes in traffic movements? 1.20 New or diverted No Not applicable. transmission lines or pipelines?

FORM 1 Page 6

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

Sl. Information/Checklist Yes/ Details thereof (with approximate quantities /rates, No. confirmation No wherever possible) with source of information data 1.21 Impoundment, damming, culverting, realignment or No impoundment, damming, culverting, realignment or other other changes to the No changes to the hydrology of surface water courses is hydrology of water envisaged. courses or aquifers? 1.22 Stream crossings? No Not applicable 1.23 Abstraction or transfers of There will not be any abstraction of ground water as daily water from ground or Yes freshwater will be supplied by Baranagar Municipality water surface waters? supply system. Changes in water bodies The project proponent will adopt well-planned construction or the land surface practices that will ensure minimum interruption of the natural 1.24 No affecting drainage or run- drainage pattern of the area. Surface drainage will not be off? affected due to construction & operation of the project. The vehicle to be used for transportation of materials will have a valid Pollution Under Control (PUC) certificate. Transport of personnel or Overhaul truck will be cleaned before leaving the site. Speed materials for construction, of the vehicle will be maintained at 10-15 km/hr. The overhaul 1.25 Yes operation or trucks to be used for carrying the raw materials will be decommissioning? covered with tarpaulin to minimize the loss through spillage. Most of the personnel associated with the project will use public transportation system. Long-term dismantling or 1.26 decommissioning or No Not applicable. restoration works? 1.27 Ongoing activity during decommissioning which No Not applicable. could have an impact on the environment? 1.28 About 150 nos. construction workers will be working on the project during the peak construction stage (temporary phase). Influx of people to an area

in either temporarily or Yes During the operational phase there will be about 1680 permanently? (Phase-1: 1512 + Phase-2: 168) permanent residents and temporary population of about 323 (Phase-1: 289 + Phase-2: 34) within the residential complex. 1.29 Introduction of alien No Not applicable. species? 1.30 Loss of native species or As the project site is already developed, so there is no No genetic diversity? question of any loss of native or genetic diversity.

FORM 1 Page 7

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

Sl. Information/Checklist Yes/ Details thereof (with approximate quantities /rates, No. confirmation No wherever possible) with source of information data 1.31  Ensuring that walking surfaces or boards at height are of sound construction and are provided with safety rails or belts.  Provide protective equipment; helmets etc.  Maintaining hoists and lifts, lifting machines, chains, ropes, and other lifting tackles in good condition. Any other actions? Yes  Raw materials will not be dumped around the public roadside.  Adequate emergency first aid system will be provided at project site.  Fire extinguishers and buckets of sand to be provided in the fire-prone area and elsewhere.

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Sl. Information/checklist Yes/No Details thereof (with approximate quantities /rates, No. confirmation wherever possible) with source of information data 2.1 Land especially No The proposed project site is a flat land within the urban area. undeveloped or Total Land area is 9696.940 sqm (2.396 acres). Net land agricultural land (ha) area for development is 8884.754 sqm (after gifting 812.186 sqm for road widening purpose). 2.2 Water (expected source Yes Estimated Total Water Demand is 293.63 kld (Phase-1: & competing users) unit : 268.5 kld + Phase-2: 25.13 kld). The Fresh Water KLD Requirement is 188.21 kld (Phase-1: 172.5 kld + Phase-2: 15.71 kld) which will be sourced from Baranagar Municipality water supply system. A portion of the treated wastewater from STP (105.42 kld) (Phase-1: 96 kld + Phase-2: 9.42 kld) would be used for flushing, irrigation & car washing purposes. Rest of the treated wastewater (133.46 kld) (Phase-1: 123 kld + Phase-2: 10.46 kld) shall be discharged into Baranagar Municipality drain. 2.3 Minerals (MT) No Not Applicable 2.4 Construction material – Yes stone, aggregates, Material Quantity Source sand / soil (expected Bricks 31,44,000 pcs Brick field source – MT) Cement 5840 T From reputed manufacturer Sand 730000 CFT Birbhum Stone chips 444000 CFT Pakur Steel 2110 Tons From reputed manufacturer

Material are being supplied by local agencies. Fly ash bricks would be used as an ingredient for concrete and PSC/PPC would be used for plaster.

FORM 1 Page 8

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

Sl. Information/checklist Yes/No Details thereof (with approximate quantities /rates, No. confirmation wherever possible) with source of information data 2.5 Forests and timber Yes Use of timber shall be as less as possible. Timber will be (source – MT) supplied by bonafide local agencies mainly for door frames. Flush door shutters would be procured from reputed suppliers. 2.6 Energy including Yes Electricity will be supplied by CESC. The connected load will electricity and fuels be about 1425 kVA (Phase – 1 + 2). DG sets - 1 no. 320 (source, competing kVA & 1 no. 380 kVA will be installed for backup power but users) Unit: fuel (MT), not to full extent. The emission from DG sets will be energy (MW) discharged through stack of height 3.6 meter for 320 kVA DG set and 3.9 meter for 380 kVA DG set above the roof of the DG building. Fuel (low sulphur diesel) required for DG set will be about 112 litre/hr. 2.7 Any other natural No Not applicable. resources (use appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Sl. Information/Checklist Yes/ Details thereof (with approximate quantities/rates, No. confirmation No wherever possible) with source of information data 3.1 Use of substances or Yes No use and storage of hazardous chemicals (as per MSIHC materials, which are rules) during operational phase is anticipated. However there hazardous (as per MSIHC may be some handling of spent oil, for backup DG sets. rules) to human health or Suitable management practices shall be adopted for the environment (flora, collection, storage and disposal of such spent oil. HSD (low- fauna, and water sulphur variety) shall be used for DG sets. supplies) 3.2 Changes in occurrence of No During construction & operational phase disinfectant will be disease or affect disease used as and when necessary to control insects. No such vectors (e.g. insect or changes will take place which would create breeding grounds water borne diseases) for water borne pathogens or insects. 3.3 Affect the welfare of No The proposed development would create direct & indirect people e.g. by changing employment, thereby helping in the economic growth & shall living conditions? improve living conditions of the people. 3.4 Vulnerable groups of No - people who could be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No -

FORM 1 Page 9

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Sl. Information/Checklist Yes/ Details thereof (with approximate quantities/rates, No. confirmation No wherever possible) with source of information data 4.1 Spoil, overburden or mine No - wastes 4.2 Municipal waste Yes Construction Phase (domestic and or commercial wastes) Solid Waste:

Construction debris including bricks, gravel, rubbish, waste of plaster, concrete debris, metal tiles, etc. will be used within the project site for land filling activities, road work, etc. Other wastes like, pieces of steel, cement bags, waste paper and cardboard packing material will be sold off to recyclers. MSW generated by the construction workers would be 30 kg/day (150 persons @ 0.2 kg/day) (Phase – 2) which would be stored at a place within the site (VAT). From there it be collected, transported, treated and disposed off by Baranagar Municipality.

Operation Phase

Solid Waste:

Solid waste during operational phase in general will be of domestic nature. Garbage will be segregated at source for biodegradable, in-organic recyclables and in-organic inert material during operational phase (1040.5 kg/day) (Phase-1: 948 kg/day + Phase-2: 92.5 kg/day). Total MSW will be stored at a place within the site. Organic component will be managed in house by installing mechanical composter, inorganic recyclables will be sold to vendors and inorganic inert material will be stored at a place within the site (VAT). From there it be collected, transported, disposed and treated by Baranagar Municipality as per MSW (M&H) Rules, 2000.

4.3 Hazardous wastes (as Yes Mostly non-hazardous type of materials shall be handled, per Hazardous Waste stored and used as construction material. The hazardous Management Rules) wastes will mainly be generated from centering oil, grease, water proofing compounds, paints, wood dust from treated wood, discarded lube oil, etc. Special care shall be taken to prevent spillage so that the hazardous solid wastes shall not be mixed with non-hazardous wastes. Hazardous solid wastes shall be stored in HDPE container as per Hazardous Waste (Management, Handling and Transboundary Movement) Rules 2008 and its subsequent amendments and finally shall be sold to authorized vendor of MoEF. 4.4 Other industrial process No Not applicable. wastes 4.5 Surplus product No Not applicable.

FORM 1 Page 10

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

4.6 Sewage sludge or other Yes During operational phase 25.13 kld of waste water shall be sludge from effluent generated which shall be treated in an STP based on FAB treatment technology. 9.42 kld of the treated waste water shall be recycled for landscaping, car washing & toilet flushing and the rest 10.46 kld shall be discharged into Baranagar Municipality drain. 4.7 Construction or Yes 426 MT of solid waste shall be generated during the demolition wastes construction phase. Construction waste will be used in the site and road preparation work. 4.8 Redundant machinery or No Not Applicable equipment 4.9 Contaminated soils or No Hazardous wastes originating from centering oil, grease, other materials water proofing compounds, paints, discarded lube oil etc. shall be stored in HDPE containers to prevent soil contamination. 4.10 Agricultural wastes No Not Applicable

4.11 Other solid wastes Yes Packing materials, hard board etc. will be segregated and sold to the vendors.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sl. Information/Checklist Yes/ Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 5.1 Emissions from Yes (i) Use of low sulphur content ultra pure diesel reduces combustion of fossil fuels SO2, NOx and PM emissions from the DG sets. from stationary or mobile Electricity will be supplied by CESC. DG sets - 1 no. 320 sources kVA & 1 no. 380 kVA will be installed for backup power. The emission from DG sets will be discharged through stack of height 3.6 meter for 320 kVA DG set and 3.9 meter for 380 kVA DG set above the roof of the DG building. Fuel (low sulphur diesel) required for DG set will be about 112 litre/hr. The emission from DG sets will be maintained as per the norms of CPCB given below

PM < 0.3 G/kw-hr CO < 3.5 G/kw-hr HC < 1.3 G/kw-hr NO2 < 9.2 G/kw-hr

(ii) The vehicle to be used for transportation of materials will have a valid Pollution Under Control (PUC) certificate. 5.2 Emissions from No Not applicable production processes 5.3 Emissions from materials No Fugitive dust will be generated from the material handling handling including areas. Water sprinkling arrangement will be made to minimize storage or transport the dust generation. All vehicles to be used for transportation of materials will have valid Pollution under Control (PUC) certificate. 5.4 Emissions from Yes Nominal quantities of fugitive dust will be emitted during construction activities excavation, back filling & hauling operations as well as

FORM 1 Page 11

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

including plant and transportation during construction period. equipment 5.5 Dust or odours from Yes During construction phase, sewage after treatment in Septic handling of materials Tank – soak pit system will be discharged into Baranagar including construction Municipality sewer line. materials, sewage and waste Dust is likely to be generated during excavation, back-filling and hauling operations along with transportation activities during the construction phase. Water sprinkling system and tarpaulin cover will be provided over stored raw material to reduce the dust emission. 5.6 Emissions from No Not applicable. incineration of waste 5.7 Emissions from burning No Open burning of biomass/ other material will be avoided. of waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other No Not applicable. sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sl. Information/Checklist Yes Details thereof (with approximate quantities/rates, No. confirmation /No wherever possible) with source of information data 6.1 From operation of No (i) Possible source is from DG sets. DG sets will have equipment e.g. engines, acoustic enclosure as per norms. ventilation plant, crushers (ii) From construction machines. But the vibration and noise will be confined within the premises. 6.2 From industrial or similar No processes 6.3 From construction or Yes Equipment used for demolition and construction work demolition generates noise and the anticipated noise levels are tabulated below. Equipments Typical Noise levels DB(A) 50 ft from source Air Compressor 81 Compactor 82 Concrete Mixer 85 Concrete pump 82 Concrete vibrator 76 Jack Hammer 88 Paver 89 Pile driver 96-101 Pump 76 Shovel 82 Mobile Crane 83 Roller 74 Source : Transit Noise and Vibration Impact Assessment, Final report, 1995 by US Department of Transportation

But this will not cause any disturbance to the neighboring

FORM 1 Page 12

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

areas. 6.4 From blasting or piling Yes There shall be no blasting activity. During piling operation, latest pile installation techniques are being adopted to have negligible effect due to vibration, etc. 6.5 From construction or Yes During construction phase it is being ensured that vehicles operational traffic must have valid Pollution Under Control (PUC) certificate for transportation of construction materials. The vehicles carrying construction materials will ply during non - peak hours.

During operational phase the vehicles to be used by the residents will have valid PUC certificate.

Traffic movement inside the premises will be controlled by the security personnel and the average speed will be maintained at 10-15 km/hr. 6.6 From lighting or cooling No systems 6.7 From any other sources No

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Sl. Information/Checklist Yes Details thereof (with approximate quantities/ rates, No. confirmation /No wherever possible) with source of information data 7.1 From handling, storage, Yes Non-hazardous type of materials shall mostly be handled, use or spillage of stored and used as construction material. The hazardous hazardous materials wastes shall be generated from centering oil, grease, water proofing compounds, paints, wood dust from treated wood, discarded lube oil, etc. Special care shall be taken to prevent spillage so that the hazardous solid wastes shall not be mixed with non-hazardous wastes. Hazardous solid wastes shall be stored in HDPE container as per Hazardous Waste (Management, Handling and Transboundary Movement) Rules 2008 and its subsequent amendments and finally sold to authorized vendor of MoEF. 7.2 From discharge of sewage No The treated wastewater around 133.46 kld (Phase – 1+2) will or other effluents to water be collected through a well designed sewer network for final or the land (expected discharge to Baranagar Municipality combined sewer line in mode and place of front of the project site. So, there is no risk of contamination discharge) of water and land. 7.3 By deposition of pollutants No Dust will be generated during construction phase from emitted to air into the land earthwork excavation, movement of vehicles and by wind or into water erosion of areas cleared of vegetation. Appropriate fugitive dust control measures, including watering, water sprinkling of exposed areas and dust covers for trucks, shall be employed to minimize any such impacts. Thus, no significant air quality impacts from fugitive dust emissions are anticipated during construction and operation phase of the project. 7.4 From any other sources No Not applicable

FORM 1 Page 13

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

7.5 Is there a risk of long term No Not applicable build up of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

Sl. Information/Checklist Yes Details thereof (with approximate quantities /rates, No. confirmation /No wherever possible) with source of information data 8.1 From explosions, spillages, No This is a construction project and does not involve use of fires etc from storage, hazardous substances as construction materials. Hence, handling, use or production chances of explosions, spillages, fire etc. are minimal. of hazardous substances During construction all the labourers shall be provided with suitable personal protective equipment (PPE) as required under the health & safety norms. Training and awareness about the safety norms shall be provided to all supervisors and labourers involved in the construction activities. An agreement shall be signed with the contractor, which shall clearly deal with the safety aspects during construction.

No major hazardous substances shall be stored within the project site. No industrial or process activity is involved in this project hence, chances of chemical hazards and accidents are minimal. However, suitable firefighting measures shall be provided. 8.2 From any other causes No 8.3 Could the project be No The area under study falls in Zone-III according to the Indian affected by natural Standard Seismic Zoning Map. Suitable seismic coefficients disasters causing in horizontal and vertical directions respectively, shall be environmental damage adopted while designing the structures. There are no chances (e.g. floods, earthquakes, of floods and landslide. landslides, cloudburst etc)?

FORM 1 Page 14

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Sl. Information/Checklist Yes Details thereof (with approximate quantities/rates, No. confirmation /No wherever possible) with source of information data 9.1 Lead to development of Yes Internal road will be constructed by the project proponent. supporting facilities, Electricity will be supplied by CESC. Usable/ recyclable solid ancillary development or wastes from construction activities will be sold off to development stimulated recyclers. Unusable materials will be used for land by the project which could development activities. Unusable material, if in excess have impact on the will be disposed off in consultation with the concerned environment e.g.: Authority.

•Supporting infrastructure Wastewater will be collected through a well-designed (roads, power supply, sewer network leading to STP in the operational phase. waste or waste water treatment, etc.) In the operational phase, treated wastewater to the tune of 105.42 kld (Phase-1: 96 kld + Phase-2: 9.42 kld) will be used for non- critical purposes viz. for toilet flushing, car • housing development washing, irrigation purpose etc. within the Complex. Treated wastewater, in excess (133.46 kld) (Phase-1: 123 kld + Phase-2: 10.46 kld) will be disposed of into the public drainage system.

Operation phase solid waste will comprise of biodegradable and non- biodegradable fractions. The non-biodegradable – recyclables wastes will be sold to recyclers and the in-organic inert materials & the bi-

degradable solid wastes will be disposed off in consultation

with the concerned Civic Body on regular basis.

NA • extractive industries

NA • supply industries

• other NA 9.2 Lead to after-use of the No site, which could have an impact on the environment 9.3 Set a precedent for later No developments 9.4 Have cumulative effects No Other housing complexes coming up in the vicinity will also due to proximity to other help local area development. existing or planned projects with similar effects

FORM 1 Page 15

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

(III) Environmental Sensitivity

Sr. Areas Name/Identity Aerial distance (within 15 No. km.) Proposed project location boundary 1 Areas protected under international None - conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or River Hooghly 1.3 km from the Project site in sensitive for West Direction ecological reasons - Wetlands, East Calcutta Wetland Boundary in SE Around 9 km watercourses or direction w.r.t the Project site. other water bodies, coastal zone, biospheres, mountains, forests 3 Areas used by None - protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, None - marine or underground waters 5 State, National None - boundaries 6 Routes or None - facilities used by the public for access to recreation or other tourist, pilgrim areas 7 Defense Military Camp (Training Center) Within 0.5 km distance from the installations project site.

FORM 1 Page 16

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

Sr. Areas Name/Identity Aerial distance (within 15 No. km.) Proposed project location boundary 8 Densely The Project Site is within Kolkata City. The project site is located at populated or Densely populated area is around the Kashinath Dutta Road, built-up area project site. Baranagar Municipality, Dist. North 24 Parganas, Kolkata. The site is surrounded by well- developed residential and commercial area. 9 Areas occupied by School: sensitive man- 1) Narendranath Bidyamandir  0.4 km from Project site made land uses 2) Baranagare Ramkrishna Mission  0.5 km from Project site (hospitals, schools, School places of worship, 3) R. B. T. School  0.5 km from Project site community 4) Mahun Girls High School  0.6 km from Project site facilities) 5) Baranagar Netaji High School  0.7 km from Project site 6) B.T. Road Govt. Spond. H.S. School  0.7 km from Project site 7) Bharati Girls High School  0.7 km from Project site 8) Sree Adarsha Hindi High School  0.8 km from Project site 9) Ramkrishna Sangha  1.1 km from Project site Bidyamandir for Girls 10) Sinthee Sikshayatan Boys' High  1.3 km from Project site School 11) Baranagore Rameswar High  1.5 km from Project site

School 12) Baranagore Victoria High School  1.5 km from Project site 13) Rajkumari Memorial Girls’ High  1.5 km from Project site School 14) Mata Monmohini School  1.5 km from Project site 15) Delhi Public School  2.3 km from Project site

College: 1) The North Suburban College of  0.6 km from Project site Commerce 2) Indian Statistical Institute  1.7 km from Project site 3) Prasanta Chandra Mahavidalaya  1.9 km from Project site 4) Chakpara Womens’ College  2.9 km from Project site 5) Bhairab Ganguly College  3.1 km from Project site 6) R. G. Kar Medical College  3.1 km from Project site 7) Motijheel College of Commerce  3.1 km from Project site 8) Hiralal Womens’ College  3.2 km from Project site 9) Maharaja Manindra Chandra College  3.5 km from Project site 10) Kashiwari College  3.5 km from Project site

University: 1) University of Calcutta – B. T. Road  0.5 km from Project site Campus 2) Rabindra Bharati University  0.6 km from Project site 3) Ramkrishna Mission Vivekananda  2.5 km from Project site University

FORM 1 Page 17

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

Sr. Areas Name/Identity Aerial distance (within 15 No. km.) Proposed project location boundary Hospital: 1) North Suburban Hospital  0.6 km from Project site 2) Baranagar State General Hospital  0.8 km from Project site 3) Binayak Hospital  1.0 km from Project site 4) Neebda Hospital  1.3 km from Project site 5) R. G. Kar Medical College & Hospital  3.1 km from Project site 6) Sanjeevani Hospital  3.3 km from Project site 7) Khudiram Hospital  3.5 km from Project site 8) Matri Sadan Hospital, North Dum  3.6 km from Project site Dum 9) Patipukur TB Hospital  3.6 km from Project site 10) Belur State General Hospital  3.8 km from Project site 11) Municipality  3.9 km from Project site Hospital

12) Municipality  4.0 km from Project site Hospital 13) ESI Hospital,  5.0 km from Project site 14) Belur ESI (TB) Hospital, Chandmari  5.3 km from Project site 15) Deshbandhunagar Hospital  5.4 km from Project site 16) Calcutta Medical College & Hospital  6.7 km from Project site 17) Eden Hospital  6.8 km from Project site 18) General Hospital  7.2 km from Project site 19) Nilratan Sarkar Medical College  7.6 km from Project site 20) Muragacha Hospital, Sodpur  8.3 km from Project site 10 Areas containing important, high River Hooghly 1.3 km from the Project site in quality or scarce West Direction resources (ground water resources, East Calcutta Wetland Boundary in SE Around 9 km surface direction w.r.t the Project site. resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already None - subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded)

FORM 1 Page 18

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

Sr. Areas Name/Identity Aerial distance (within 15 No. km.) Proposed project location boundary 12 Areas susceptible None - to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

(IV). Proposed Terms of Reference for EIA studies

As the built-up area of this project is less than 1,50,000 sqm. separate EIA study is not required.

FORM 1 Page 19

Square Four Housing & Expansion of "Uddipa" Residential Complex at Premises No. – 1, Infrastructure Kashinath Dutta Road, Baranagar Municipality, Dag No. – 921 to 925, J.L. Development Pvt. Ltd. No. – 8, P.S. – Baranagar, Dist. – 24 Paraganas (N), West Bengal

I hereby give the undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.

Date: 26.06.2017

Place: Kolkata

Somnath Samanta (Director)

Address: Square Four Housing & Infrastructure Development Pvt. Ltd. 238A, A.J.C. Bose Road, 2nd Floor, Suit 2B, Kolkata – 700020

Note :

1. The projects involving clearance under Coastal Regulation Zone Notification, 1991 shall submit with the application a C.R.Z map duly demarcated by one of the authorized agencies, showing the project activities , w.r.t. C.R.Z (at the stage of TOR) and the recommendations of the State Coastal Zone Management Authority (at the stage of EC). Simultaneous action shall also be taken to obtain the requisite clearance under the provisions of the C.R.Z Notification, 1991 for the activities to be located in the CRZ.

2. The projects to be located within 10 km of the National Parks, Sanctuaries, Biosphere Reserves, Migratory Corridors of wild animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis the project location and the recommendations or comments of the Chief Wildlife Warden thereon (at the stage of EC).

3. All correspondence with the Ministry of Environment & Forest including submission of application for TOR/Environmental Clearance, subsequent clarification, as may be required from time to time, participation in the EAC Meeting on behalf of the project proponent shall be made by the authorized signatory only. The authorized signatory should also submit a document in support of his claim of being an authorized signatory for the specific project.

FORM 1 Page 20