FORM –1

“Park Xpress”

“RESIDENTIAL & COMMERCIAL DEVELOPMENT”

At

Survey No. 5, 18 &19, at Balewadi, ,

By

M/s. Shriniwas Pride Purple Properties LLP

APPENDIX - I

(See paragraph - 6) FORM 1

(I) Basic Information Sr.No. Item Details 1. Name of the project “Park Xpress ” “Residential & commercial Development” 2. S. No. in the schedule 8 (B2) 3. Proposed Total Plot Area: 59,779.99 m2 capacity/area/length/tonnage to be Deduction (D. P.Road + Amenity area): 11,378.78 m2 Net Plot area : 48,401.21 m2 handled/command area/lease 2 area/number of wells to be drilled FSI : 74,878.16 m Non FSI: 65,704.68 m2 Total : 1,40,583.0 m2 Project Proposal: BUILDING NO. OF NO.OF NO. OF TYPE BUILDINGS FLOORS FLATS/ SHOPS Existing Wing A-B 1 ST+8 128 & C-D Wing E-F 1 ST+14 108 Wing G-H 1 ST+8 128 & Wing I- J Wing K-L 1 ST+14 108 Wing M-N 1 ST+14 108 Wing O-P 1 ST+14 108 IT building 1 G+ 7 96 1 IT building 1 G+ 7 88 1 Club house 1 G+1 0 Total 8 Total buildings residential tenements 688 & commercial 184 Proposed Wing A-B 1 P+8 128 & CD Wing E-F 1 P+11 86 Wing G-H 1 P+8 128 & Wing I- J Wing K-L 1 B+P+13 104 Wing M-N 1 B+P+13 104 Wing O 1 B+P+13 52 Club house 1 G+1 0 Wing A 1 G+P1+19 50 Wing B 1 G+P1+19 50 Wing C 1 G+P1+19 57 Wing D 1 G+ Loft 15 (Shops) Club house 1 Ground 0 Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Sr.No. Item Details Total Total residential tenements 759 & shops15

4. New/Expansion/Modernization Expansion 5. Existing Capacity/ Area etc. Earlier EC vide letter No.: SEAC-2009/CR.12/TC.2 dated 17.11.2009 was obtained for Total BUA area: 1,41,357.87 m2 out of which 1,20,380.5m2 has been constructed. Attached as Enclosure 1. 6. Category of project i.e.’ A’ or ‘B’ 8 (B2) 7. Does it attract the general Not Applicable condition? If yes, please specify. 8. Does it attract the specific Not Applicable condition? If yes, please specify. 9. Location Balewadi Plot/Survey/Khasra No. S. No. 5,18 &19 Village Balewadi Tehsil Haveli District Pune State Maharashtra 10. Nearest railway station Pune railway station : 11.0 Km Nearest airport : 15 Km 11. Nearest Town, city, Pune city District headquarters Along with distance in kms. 12. Village Panchayats, Zilla Pune Municipal Corporation Parishad, Municipal Corporation, Local body (complete postal address with telephone nos. to be given) 13. Name of the applicant M/s.Shriniwas Pride Purple Properties LLP. 14. Registered Address Pride House, 5th Floor, Near Pune University Circle, Pune. 15. Address for correspondence Pride House, 5th Floor, Near Pune University Circle, Pune. Name Mr. Sunil Popatlal Nahar Designation(Owner/Partner/CEO) Partner Address Pride House, 5th Floor, Near Pune University Circle, Pune. Pin Code 411032 E-mail [email protected]

Telephone No. 020-67091000/01 Fax No. 67091099 16. Details of Alternative Sites No examined, if any. Location of these sites should be shown on a topo-sheet. 17. Interlinked Projects Not applicable 18. Whether separate application of No interlinked project has been submitted? 19. If yes, date of submission Not applicable Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Sr.No. Item Details 20. If no, reason Not applicable 21. Whether the proposal involves approval/clearance under: if yes, details of the same and their Not applicable status to be given. (a) The Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (c) The C.R.Z Notification, 1991? 22. Whether there is any Government Not applicable Order/Policy relevant/ relating to the site? 23. Forest land involved (hectares) Not applicable 24. Whether there is any litigation No pending against the project and/or land in which the project is propose to be set up? (a) Name of the Court (b) Case No. (c) Order /directions of the Court, if any and its relevance with the proposed project.

(II). Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Details thereof (with approximate quantities Sr. Information/Checklist Yes /rates, wherever possible) with source of No. confirmation / No information data 1.1 Permanent or temporary change No Project site is in residential zone as per DP in land use, land cover or remarks. topography including increase DP remarks are attached as Enclosure 2 in intensity of land use (with respect to local land use plan) 1.2 Clearance of existing land, No -- vegetation and building? 1.3 Creation of new land uses? No --

1.4 Pre-construction investigation Yes Geotechnical Investigation has been carried out. e.g. bore houses, soil testing? 1.5 Construction works? Yes Residential Development with convenient shopping.

1.6 Demolition works? No -

Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Details thereof (with approximate quantities Sr. Information/Checklist Yes /rates, wherever possible) with source of No. confirmation / No information data 1.7 Temporary sites used for Yes Temporary labour camp for construction construction works or housing workers on site with security of construction workers? 1.8 Above ground building, structures Yes Excavation material & construction waste or earthworks including linear material shall be partly reused and remaining structures, cut and fill or disposed to the authorized land fill site. excavations. 1.9 Underground works including No. -- mining or Tunneling? 1.10 Reclamation works? No --

1.11 Dredging? No --

1.12 Offshore structures? No --

1.13 Production and manufacturing No -- processes? 1.14 Facilities for storage of goods or Yes During construction phase temporary storage materials? facilities will be created to store the construction raw material. 1.15 Facilities for treatment or Yes  STP for treatment of sewage disposal of solid waste or liquid  Segregation of solid waste into non- effluents? biodegradable and biodegradable garbage  Biodegradable waste shall be treated in OWC.  Segregation of Non-biodegradable waste into recyclable & non-recyclable.  Recyclable waste: To recyclers  Non-Recyclable waste: To PMC.  Dried sludge from STP : As manure 1.16 Facilities for long term housing No -- of operational workers? 1.17 New road, rail, or sea traffic No -- during construction or operation? 1.18 New road, rail, air waterborne No -- or other transport infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing No -- transport routes or infrastructure leading to changes in traffic Movements? 1.20 New or diverted transmission No -- lines or pipelines? 1.21 Impoundment, damming, No -- culverting, realignment or other change to the hydrology of watercourses or aquifers? Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Details thereof (with approximate quantities Sr. Information/Checklist Yes /rates, wherever possible) with source of No. confirmation / No information data 1.22 Stream crossings? No -- 1.23 Abstraction or transfers of water No -- from ground or surface waters? 1.24 Changes in water bodies or the Yes By considering the runoff prior to development land surface affecting drainage and runoff after development there is some or run-off? increment in runoff of storm water. Incremental Runoff = 273m3/hr 1.25 Transport of personnel or Yes Transport of construction materials. materials for construction, Precautions taken to reduce the impact of the operation or decommissioning? vehicular movement by trying to avoid the vehicular trips during peak hours. 1.26 Long-term dismantling or No -- decommissioning or restoration works? 1.27 Ongoing activity during No -- decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in Yes There will be influx of people in proposed either temporarily or project, which includes permanently? Existing + Proposed : Fixed – 3795 and floating 45 population. 1.29 Introduction of alien species? No --

1.30 Loss of native species or genetic No -- diversity? 1.31 Any other actions? No --

2.0 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Sr. Information/checklist Yes Details thereof (with approximate quantities No. confirmation / No /rates, wherever possible) with source of information data 2.1 Land especially undeveloped or Yes Total Plot Area under development = 59,779.99 m2 agricultural land (ha) 2.2 Water (expected source & Yes During construction: Potable water shall be competing users) unit : KLD supplied as per requirement. During Construction Phase for worker From: potable water tanker 2 - 5 KLD (Depending upon the activity) During Operation: Quantity of water: About 342 m3/day Fresh from PMC :342 m3/day Recycled : 216 m3/day (171 m3/day for Flushing and 45 m3/day for gardening) 2.3 Minerals (MT) No --

Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Sr. Information/checklist Yes Details thereof (with approximate quantities No. confirmation / No /rates, wherever possible) with source of information data 2.4 Construction material – stone, Yes Quantity : As per requirement aggregates, and / soil (expected Stone aggregates demand will be met from the source – MT) clay/soil generated after excavation and from open market Sources: The material required for construction activities shall be procured from company’s authorized / approved vendors only. The vendor’s performance will be monitored periodically. In case of urgency or non-availability of materials from authorized/approved vendors, it will be procured from the open market. 2.5 Forests and timber (source – MT) Yes Timber required for doors sourced from local suppliers. 2.6 Energy including electricity and Yes During Construction Phase - fuels (source, competing users) From Maharashtra State Electricity Distribution Unit: fuel (MT), energy (MW) Company Limited (MSEDCL): 148 KW D.G. Sets: As per requirement During Operational Phase – Source – MSEDCL Connected Load : 5767 KW as per 75W/sq.mt circular Maximum demand: 2931 kw Number and capacity of the DG sets to be used – 320 KVA (1 no.), 250 KVA (1 no.) &300 KVA( 1 no.) 2.7 Any other natural resources (use No -- appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Sr. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data 3.1 Use of substances or materials, No -- which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of No -- disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. No -- by changing living conditions? 3.4 Vulnerable groups of people No -- Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Sr. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data who could be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No --

4. Production of solid wastes during construction or operation or decommissioning (MT/month):

Details thereof (with approximate quantities / Sr. Information/Checklist Yes / rates, wherever possible) with source of No. confirmation No information data 4.1 Spoil, overburden or mine No -- wastes 4.2 Municipal waste (domestic Yes During Construction Phase: and or commercial wastes) Total quantity of solid waste = 63 kg/day (Biodegradable and Non-biodegradable) During Operation Phase: The total quantity of solid waste: 1708 Kg /day. (Biodegradable and Non biodegradable) 4.3 Hazardous wastes (as per Yes Waste oil generated from D.G. shall be stored at Hazardous waste Management separate location duly marked and will be sold to Rules) the authorized recyclers. 4.4 Other industrial process wastes No -- 4.5 Surplus product No -- 4.6 Sewage sludge or other sludge Yes Dried sludge from STP will be used as manure for from effluent treatment. the plants. 4.7 Construction or demolition Yes Construction waste material shall be partly reused wastes. and remaining disposed to the authorized land fill site. 4.8 Redundant machinery or No -- equipment. 4.9 Contaminated soils or other No -- materials. 4.10 Agriculture wastes. No -- 4.11 Other solid wastes. No --

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sr. Information/Checklist Yes / No Details thereof (with approximate No. confirmation quantities/rates, wherever possible) with source of information data 5.1 Emissions from combustion of Yes CPCB approved D.G. Sets will be used during fossil fuels from stationary or power failure. mobile sources 5.2 Emissions from production No -- processes

Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Sr. Information/Checklist Yes / No Details thereof (with approximate No. confirmation quantities/rates, wherever possible) with source of information data 5.3 Emissions from materials Yes Fugitive dust emission due to handling and handling including storage or loading-unloading activities is envisaged during transport construction. Frequent water sprinkling will be done to minimise the fugitive emissions. 5.4 Emissions from construction Yes/ The project may cause rise in dust levels during activities including plant and Marginal construction phase. Precautions would be taken equipment to reduce dust generation by water sprinkling at regular intervals. 5.5 Dust or odours from handling Yes Dust generation controlled as described above. of materials including For odour control: Proper ventilation shall be construction materials, sewage provided around STP and solid waste and waste management facilities 5.6 Emissions from incineration of No -- waste 5.7 Emissions from burning of No -- waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other No -- sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sr. Information/Checklist Yes / Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 6.1 From operation of equipment Yes but For control of noise following measures shall be e.g. engines, ventilation plant, negligible adopted: crushers.  Regular noise monitoring to be scheduled to maintain the noise level within the levels prescribed by CPCB during day and night time  Provision of ear plugs to workers  Use of good efficiency mufflers  No noise polluting work in night shifts  Provision of barricades along the periphery of the site. 6.2 From industrial or similar No - processes. 6.3 From construction or Yes Noise levels may increase due to operation of demolition. machinery as well as transportation vehicles. This may cause nuisance to the nearby area. Following precautions shall be taken to control noise pollution:  High noise generating construction activities would be carried out only during day time  Installation, use and maintenance of mufflers on equipment  Workers working near high noise construction machinery would be supplied with ear

Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Sr. Information/Checklist Yes / Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data muffs/ear plugs  Provision of barricades along the periphery of the site  Plantation of trees Acoustic enclosure for DG sets 6.4 From blasting or piling. No - 6.5 From construction or Yes During Construction phase: operational traffic.  Proper traffic management for the construction vehicles  Regular maintenance of vehicles with suitable enclosures and intake silencers  Planning and ensuring effective implementation of the waste movement plan for loading and offsite movement in non-traffic hours. During Operation Phase :  Install traffic control measures to regulate the flow of traffic  Assign traffic wardens to regulate flow of project traffic during peak hours

6.6 From lighting or cooling No -- systems. 6.7 From any other sources. No --

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea :

Sr. Information/Checklist Yes / Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 7.1 From handling, storage, use or No -- spillage of hazardous materials. 7.2 From discharge of sewage or No During Construction Phase: other effluents to water or the Disposal of sewage to municipal sewer line land (expected mode and During Operation Phase: place of discharge). The treated sewage will be reused for flushing and gardening within the premises. Excess treated sewage will be disposed to sewer line 7.3 By deposition of pollutants No Dust will be generated during construction phase emitted to air into the land or from earthworks and movement of vehicles. into water. Appropriate fugitive dust control measures, including watering, water sprinkling of exposed areas and dust covers for trucks, will be provided to minimize any impacts. DG exhaust will be discharged at stipulated height by providing adequate stack height to the DG sets. 7.4 From any other sources. No --

Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Sr. Information/Checklist Yes / Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 7.5 Is there a risk of long term No -- build up of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment :

Sr. Information/Checklist Yes / Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 8.1 From explosions, spillages, No -- fires etc from storage, handling, use or production of hazardous substances 8.2 From any other causes. No -- 8.3 Could the project be affected Yes Landslides are not expected in the area. by natural disasters causing Management plan for flood and earthquake is as environmental damage (e.g. follows : floods, earthquakes, Flood : landslides, cloudburst)?  Minimizing the incremental runoff from the site with the help of rain water harvesting pits  Level of ground water table:6 to 8 bgl  No of recharge pit: -20 Nos.  Proper management of channelization of storm water from site by using proper internal SWD system and discharge points of adequate capacity  Use of screens and silt traps to SWD  Proper maintenance of storm water drainage to avoid choking of drains and flooding on site  Ensure discharge of storm water from the site is clear of sediment and pollution Earthquake : The structure of the building is designed as per IS codes for zone III. Disaster Management Plan is attached as Enclosure-3

Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality:

Sr. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data 9.1 Lead to development of supporting

Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Sr. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data facilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: •Supporting infrastructure (roads, No Supporting infrastructure is already in existence. power supply, waste or waste water treatment, etc.) Yes Residential & commercial Development • housing development • extractive industries • supply industries • other 9.2 Lead to after-use of the site, which No -- could have an impact on the environment 9.3 Set a precedent for later Yes Will create job opportunity in construction and developments operation phase with support staff like security, maintenance, household workers, shop keepers etc. 9.4 Have cumulative effects due to Yes Impacts on water availability, storm water proximity to other existing or drainage, availability of electricity, traffic planned projects with similar congestion etc. effects

(II) Environmental Sensitivity Sr. Areas Name/ Aerial distance (within 15 km.) No. Identity from Proposed project location boundary 1 Areas protected under international – Approx:6.0 conventions, national or local reserved legislation for their ecological, landscape, cultural or other related Reserved forest Beyond 5km toward North and value NW 2 Areas which are important or Approx. 0.66 km sensitive for ecological reasons - Approx. 4.0 km Wetlands, watercourses or other Mula Muth River Approx. 9.80 km water bodies, coastal zone, Ram River Approx. 4.80 km biospheres, mountains, forests Vishrantwadi Lake Approx. 11.00 km Lohgaon Lake Approx. 13.20 km Lake Approx. 3.90 km Manas Lake Approx. 9.0 km Bhugaon Lake Approx. 8.60 km Khadakwasla Dam Approx. 14.30 km Kusegaon Dam Approx. 12.70 km Bord valley lake Approx.9.50km Shahu maharak Approx. 9.0 km lake Peshve park lake Approx. 11.0 km Approx. 8.25 km Upper lake

Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Sr. Areas Name/ Aerial distance (within 15 km.) No. Identity from Proposed project location boundary Sumanath sarovar Approx. 8.0 km

3 Areas used by protected, important or Yes 3.5 sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or Mula river Approx. 0.66 km underground waters Pavana River Approx. 4.0 km Mula Muth River Approx. 9.80 km Ram River Approx. 4.80 km Vishrantwadi Lake Approx. 11.00 km Lohgaon Lake Approx. 13.20 km Pashan Lake Approx. 3.90 km Manas Lake Approx. 9.0 km Bhugaon Lake Approx. 8.60 km Khadakwasla Dam Approx. 14.30 km Kusegaon Dam Approx. 12.70 km Bord valley lake Approx.9.50km Shahu maharak Approx. 9.0 km lake Peshve park lake Approx. 11.0 km Approx. 8.25 km Upper lake

Sumanath sarovar Approx. 8.0 km

5 State, National boundaries No -- 6 Routes or facilities used by the public NH 4 Approx- 0.30 km. for access to recreation or other tourist, pilgrim areas 7 Defence installations cantonment Within 13 Km 8 Densely populated or built-up area Pune Approx. – 4 Km 9 Areas occupied by sensitive man- School- made land uses (hospitals, schools, 1. Sanskruti Approx. 0.94 Km places of worship, community School facilities) 2. The orchid Approx 1.15km 3. VIBYOG high Approx 1.92km College – Approx. 1.57 Km 1. Symbiosis College information Approx. 4.43 Km technology 2. Symbiosis College Arts,

Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Sr. Areas Name/ Aerial distance (within 15 km.) No. Identity from Proposed project location boundary commerce and Approx. 8.10 Km science Approx. 8.70 Km 3. MIT college

10 Areas containing important, high No -- quality or scarce resources (Ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution No -- or environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard No -- which could cause the project to present environmental problems (Earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) Proposed Terms of Reference for EIA studies: Not applicable

Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”

Form1 ‐ “PROPOSED RESIDENTIAL DEVELOPMENT”