<<

Annual Environmental Report

For Waste Water Discharge Licence D0208-01

Dungloe Agglomeration

Licensee County Council

Contents;

1.0 Introduction and Summary

2.0 Monitoring Report

3.0 Operational Report

4.0 Infrastructural Assessment and Programme for Improvements 5.0 Environment Liability and Financial Provision

6.0 Licence Specific Reports

7.0 Certification and Sign Off

Appendix Environmental Liability Risk Assessment 1.0 Introduction and Summary

Dungloe is a coastal town in west Donegal on the N56 linking and . Wastewater from Dungloe catchment is currently treated to primary stage by an existing septic tank which discharges to Dungloe bay at the mouth of the Dungloe river. This septic tank was built in 1930 and has not had any major refurbishment since. There are a number of smaller septic tanks serving a small number of dwellings outside the normal catchment area of the main septic tank.

There is only one primary discharge point from the existing septic tank, discharging into the estuary of Dungloe river as it enters the sea. The tank is desludged annually.

The sewers consist of 150mm diameter and 225mm diameter laid mostly along the streets of the town, while short lengths of 100mm connect to small housing estates. There are surface water drains of 300mm and 450mm diameter also on the main street. There is one pumping station in the catchment, located on Quay road, with an emergency overflow discharging into Dungloe bay. This pump station is visited daily by the Waterwork’s Inspector and inspected for operation. There is a duty/standby arrangement in place. There is very little effective treatment of the wastewater in the septic tank due to the current loading of 1600pe. Settlements of some solids, grit and heavier materials is all that can be achieved.

Dungloe Sewerage Scheme is listed in the Department of the Environment, Water Services Investment Programme, 2010-2012 as a contract to start (see below). According to the Preliminary Report for the Sewerage Scheme, the 20 year design population for the scheme is 2400pe. This will cater for current and future development outside the existing catchment boundary.

The main objectives of the scheme are summarised as follows: • To provide wastewater treatment capacity for the catchment area for a planning horizon of 20 years. • To comply with current E.U. Directives relating to wastewater treatment discharges from urban agglomerations. • To make adequate provision of vital infrastructure to facilitate overall growth and development of the town.

CONTRACTS TO START 2010 - 2012 Donegal / Sewerage Schemes · Network S 150,000 / Regional Water Supply Scheme · Water Treatment Plant - DBO W 6,000,000 Bridgend Sewerage Scheme (G/SLI) · Wastewater Treatment Plant & Network S 500,000 Donegal (Group B) Sewerage Schemes 1 · Wastewater Treatment Plants - DBO S 25,000,000 Donegal (Group B) Sewerage Schemes 1 · Networks S 5,000,000 Scheme Name Contract Name W/S Estimated Cost Scheme Name Contract Name W/S Estimated Cost 29 Water Services Investment Programme 2010-2012 Donegal Town Sewerage Scheme (SLI) · Network (Brookfield) S 103,000 Glenties/Dungloe Sewerage Schemes · Wastewater Treatment Plants - DBO S 7,000,000 Gweedore Sewerage Scheme · Network S 8,500,000 Gweedore Sewerage Scheme · Wastewater Treatment Plant S 2,900,000 Sewerage Scheme · Contract 2 (Main Pumping Station & Outfall) S 16,500,000 Sewerage Scheme (G) · Wastewater Treatment Plant - DBO S 25,000,000 Water Conservation Stage 3 Works · Watermains Rehabilitation Project Phase 1 W 3,100,000 TOTAL 121,033,000 1 , Killybegs, Convoy and Glencolumbcille

2.0 Monitoring Report

As licences were not granted until Dec 2011, we only have results for BOD, COD and SS in accordance with the requirements of the Urban Wastewater Regulations. None of the extra testing in compliance with Schedule B of the licence has been tested for 2011; however since 2012 sampling is underway in accordance with the schedule.

Quality Results by Date Location Lab Ref Date Northing Easting pH BOD COD SS (mg/l) (mg/l) (mg/l)

Dungloe no. 1 - inlet 112501510 16/02/2011 411418 176788 7.4 86.2 210 66 Dungloe no. 1 - outlet 112501511 16/02/2011 411419 176778 7.46 77.8 227 82

Dungloe no. 1 - inlet 112502426 14/04/2011 411418 176788 7.47 80.9 209 18 Dungloe no. 1 - outlet 112502427 14/04/2011 411419 176778 7.41 111.3 286 54

Dungloe no. 1 - inlet 112503296 09/06/2011 411418 176788 7.04 38.4 118 30 Dungloe no. 1 - outlet 112503297 09/06/2011 411419 176778 7.06 28.4 110 42

Dungloe no. 1 - inlet 112504079 21/07/2011 411418 176788 7.47 149.6 302 150 Dungloe no. 1 - outlet 112504080 21/07/2011 411419 176778 7.29 122.4 286 112

Dungloe no. 1 - inlet 112505 290 27/09/2011 411418 176788 6.85 <10 161 70 Dungloe no. 1 - outlet 112505291 27/09/2011 411419 176778 7.04 <10 174 22

Dungloe no. 1 - inlet 112506504 07/12/2011 411418 176788 7.41 36.94 146 35 Dungloe no. 1 - outlet 112506505 07/12/2011 411419 176778 7.41 36.1 136 20

Quality Results

Location Lab Ref Date pH BOD COD SS (mg/l) (mg/l) (mg/l)

Dungloe no. 1 - inlet 112501510 16/02/2011 7.4 86.2 210 66 Dungloe no. 1 - inlet 112502426 14/04/2011 7.47 80.9 209 18 Dungloe no. 1 - inlet 112503296 09/06/2011 7.04 38.4 118 30 Dungloe no. 1 - inlet 112504079 21/07/2011 7.47 149.6 302 150 Dungloe no. 1 - inlet 112505290 27/09/2011 6.85 <10 161 70 Dungloe no. 1 - inlet 112506504 07/12/2011 7.41 36.94 146 35

Dungloe no. 1 - outlet 112501511 16/02/2011 7.46 77.8 227 82 Dungloe no. 1 - outlet 112502427 14/04/2011 7.41 111.3 286 54 Dungloe no. 1 - outlet 112503297 09/06/2011 7.06 28.4 110 42 Dungloe no. 1 - outlet 112504080 21/07/2011 7.29 122.4 286 112 Dungloe no. 1 - outlet 112505291 27/09/2011 7.04 <10 174 22 Dungloe no. 1 - outlet 112506505 07/12/2011 7.41 36.1 136 20

Influent

Location Lab Ref Date Northing Easting pH BOD COD SS (mg/l) (mg/l) (mg/l)

Dungloe no. 1 - inlet 112501510 16/02/2011 411418 176788 7.4 86.2 210 66 Dungloe no. 1 - inlet 112502426 14/04/2011 411418 176788 7.47 80.9 209 18 Dungloe no. 1 - inlet 112503296 09/06/2011 411418 176788 7.04 38.4 118 30 Dungloe no. 1 - inlet 112504079 21/07/2011 411418 176788 7.47 149.6 302 150 Dungloe no. 1 - inlet 112505290 27/09/2011 411418 176788 6.85 <10 161 70 Dungloe no. 1 - inlet 112506504 07/12/2011 411418 176788 7.41 36.94 146 35

Effluent

Location Lab Ref date Northing Easting pH BOD COD SS (mg/l) (mg/l) (mg/l)

Dungloe no. 1 - outlet 112501511 16/02/2011 411419 176778 7.46 77.8 227 82 Dungloe no. 1 - outlet 112502427 14/04/2011 411419 176778 7.41 111.3 286 54 Dungloe no. 1 - outlet 112503297 09/06/2011 411419 176778 7.06 28.4 110 42 Dungloe no. 1 - outlet 112504080 21/07/2011 411419 176778 7.29 122.4 286 112 Dungloe no. 1 - outlet 112505291 27/09/2011 411419 176778 7.04 <10 174 22 Dungloe no. 1 - outlet 112506505 07/12/2011 411419 176778 7.41 36.1 136 20

3.0 Operational Report

Donegal County Council has assigned a Waterwork’s Inspector to maintain the existing sewerage infrastructure in Dungloe.

The pumping station on Quay road is inspected daily for evidence of malfunction, overloading or blocking. The “Amps” reading indicates whether the pump is running freely or requires cleaning due to a build up of matter. There is an automatic changeover in place so if a pump trips or blocks, the second pump kicks in automatically. Every two to three weeks, the pumps are lifted using a block and tackle, cleaned and greased and maintained as necessary. An electrician and fitter also assist with this work. The overflow pipe is also checked to see if it has been operational and the non return flap at end in place. Generally both pumps are not down at the same time and the overflow is not used.

Other operational work on sewer network involves ensuring all sewers are running freely and without any build up of debris. Dates when specialist jetting equipment has been used are listed.

20 th July Main sewer line jetted out and flushed in Dungloe

18 th July Jetting and flushing of main sewer on main street and Chapel road

12 th July Emptying and Cleaning out sewage pumping station on quay road.

4th July Jetting out blocked sewer.

7th August Cleaning out blocked sewer main Street

4.0 Infrastructural Assessment and Programme for Improvements

The existing septic tank serving Dungloe provides an insufficient level of treatment to deal with the wastewater generated in the catchment. Settlement of some solids, grit and heavier materials is all that can be achieved.

Dungloe Sewerage Scheme and Glenties Sewerage Scheme are listed together in the Department of the Environment, Water Services Investment Programme, 2010-2012 as a combined design, build, operate scheme.

According to the Preliminary Report for the Sewerage Scheme, the 20 year design population for the scheme is 2400pe. This constitutes a 44% increase on the existing population and corresponds to a medium growth rate. This will cater for current and future development outside the existing catchment boundary.

Dungloe and Glenties Sewerage Schemes.

It is intended to deliver the project under two main contracts. 1. Design-Build and Operate Contract. This contract will involve the construction of a Main Transfer Pumping Station and Waste Water Treatment Works in both Dungloe and Glenties. It will also include for all pipe works between the pump station and the treatment works and associated outfalls. It is also proposed to include for an outlying pump station on the Mill Road in Dungloe. This contract will include for a 20 year operation phase. 2. Network Upgrade and Rehabilitation Contract. This contract will involve the improvement, rehabilitation and cleaning of the existing network in both Dungloe and Glenties.

Contract documents for the DBO Contract were submitted to the DoEHLG on the 9 th April 2009 and approved early 2011. A Contract Notice was published in the Official Journal of the European Union and on e-tenders requesting the submission of expressions of interest for contractors wishing to undertake the DBO project. Eight submissions were received by the closing date and the assessment of these submissions is nearing completion. The Consulting Engineers, Nicholas O’Dwyer are currently incorporating the necessary network improvements into the DBO documents as design and build elements only. DCC has had to re-negotiate the purchase of a right of way to allow access to the site of the new pumping station in Glenties. Agreement has been reached on the route of the new right of way, however in order to provide certainty of access in line with the contract programme it is anticipated that a CPO process will commence shortly. This will also necessitate a revised part 8 application for part of the route, which will be run in parallel with the CPO process.

5.0 Environmental Liability and Financial provision

DoEHLG funding of €7,000,000 is required to construct the necessary infrastructure to deal with the sewerage from the existing agglomeration and allow for future growth. A portion of the €7m will have to be raised by from own resources. The DoEHLG have not given approval to tender the project as yet. Donegal County Council does not carry specific Environmental Liability Insurance

6.0 Licence Specific Reports

Complaints summary The number of complaints relating to the Dungloe Sewerage Scheme relate to the number of blockages in the network. In 2011 there were five complaints.

Documented Emergency Response Procedures

The Waterworks Inspector position is a seven day, 52 week commitment to looking after Dungloe sewerage infrastructure. Assistance is available from Supervisor, Fitter, Electrician, and Engineer as necessary.

In the event of an emergency such as sewer blockage, pump down or smell outside of normal office hours, Donegal County Council has a Call Centre in place where members of the public can notify of incidents. The call centre then notifies the Inspector for follow up. The Inspector responds, discusses with supervisor and deals with emergency. Specialist equipment suppliers such as jetting, suction, dewatering are available inside and outside office hours. Donegal County Council staff has contact details for these suppliers in addition to contact details for:

• Doctor • Fire service • Ambulance

Staff are also familiar with and has had training on the Water & Environment Services, Safety and Health Plan, “The Blue Folder”.

The Donegal Local Authority, “Major Emergency Plan” is also available.

Pollutant Release

No known industrial discharges or dangerous substance emissions. No discharges to air or noise.

Public Awareness and Communication

Members of the public can access environmental information and other information relating to Dungloe Sewerage Scheme in Dungloe Public Service Centre by visiting or phoning Water & Environment section on 07495-61300. Discharge results are available.

Every two months a Glenties Electoral Area meeting is held between elected representatives and Executive staff from Donegal County Council. The press are also in attendance. Dungloe Sewerage Scheme is part of this agenda

Donegal County Council

Environmental Liability Risk Assessment & Statement of the Measures

For

Dungloe WWTP

2011

Urban waste Water Discharge Licence No. D0208-01

Revision History Version Status Author Reviewed Description Date By (Grade)

Table of Contents;

1.0 Introduction

2.0 Environmental Sensitivity of receiving waters

3.0 Groundwater protection

4.0 Protected Ecological sites and Species (Shortest distance from any Discharge)

5.0 Human Health

1.0 Introduction

This Environmental Liability Risk Assessment relates to the agglomeration of Dungloe and Environs. This report has been prepared in compliance with Licence D0208-01

2.0 Environmental Sensitivity of receiving waters

Using the EPA Sensitivity Assessment Excel sheet the Sensitivity Rating for this agglomeration is 1.

The EPA Dream system identifies the Risk Category as A2 with a risk Score of 12.

3.0 Groundwater Protection

Not applicable

4.0 Protected Ecological Sites and Species ( Shortest distance from any Discharge

Possible impacts – none Determined by Dream.

5.0 Human Health

There is no appreciable risk to human health from this discharge.

DREAM Risk Assessment

Dream Risk Category Enforcement Risk Score Category

A2 A2 12

Dungloe Table 1 Environmental Sensitivity Assessment Environmental Attribute Attribute Designated Comment Data Sources Score Score Sensitivity of Receiving Water EPA Maps Class A (Q5, Q4-5, Q4) 3 Shellfish Areas Class B (Q3-Q4) 2 2008 Bathing Water Map Class C (Q3, Q2-3) 1 Class D (Q2, Q1-2, Q1) 0 discharge is to sea Designated Costal & 2 0 Estuarine Waters Potentially Eutrophic 1 0 Coastal & Estuarine Groundwater Protection Regionally Important 2 Aquifer Locally Important Aquifer 1 Poor Aquifer 0 0

Vulnerability Rating - 3 Extreme Vulnerability Rating - High 2 Vulnerability Rating - 1 Moderate Vulnerability Rating - Low 0 0 Protected Ecological Sites and Species (Shortest distance from any discharge) Discharge within or 2 directly bordering a designated site <1km 1 >1km 0 0 Human Health Discharge within or directly bordering a designated shellfish area

0 - 5 km 1 1 Dungloe Shellfish Area >5 km 0

Designated Bathing Water The appropriate Officer should sign the Programme of Measures

WITHIN 0-5 km 1 >5 km 0 0

Drinking Water Source Within 0-10 km 1 >10km 0 0 Environmental Sensitivity Score 1 This value to be stated in your ELRA

Table 2 Risk Assessment Form Risk ID Process* Potential Environmental Severit Basis of Oc Basis of Risk Hazards effect y Severity cur Occurrence Score Rating ren ce Rat ing

1 Large inflow due to High BOD, COD, poor effluent 3 Dilution will 4 High rainfall in 12 high stormwater Increased SS quality occur winter during periods of heavy rainfall

2 flooding of existing High BOD, COD, poor effluent 3 large dilution 2 tank located 6 tank due to high sea Increased SS quality beside coast levels

3 Pump failure/trip Discharge to sea poor effluent 4 poor dilution of 2 Duty Standby 8 quality effluent pump standby in place

Table 5 Risk Classification Table – Severity

Rating Severity

Category Description Cost of Remediation 1 Trivial No damage or €1,000 negligible change to the environment. 2 Minor Minor €5,000 impact/localised or nuisance 3 Moderate Moderate €10,000 damage to environment 4 Major Severe damage €100,000 to local environment 5 Massive Massive damage €1,000,000 to a large area, irreversible in medium term

Table 6 Risk Classification Table – Occurrence The appropriate Officer should sign the Programme of Measures Rating Occurrence

Category Description Likelihood of Occurrence (%) 1 Very Low Very low chance 0 – 5 (0-5%) of hazard occurring in 30 yr period * 2 Low Low chance (5- 5 - 10 10%) of hazard occurring in 30 yr period 3 Medium Medium chance 10 - 20 (10-20%) of hazard occurring in 30 yr period 4 High High chance (20- 20 - 50 50%) of hazard occurring in 30 yr period 5 Very High Greater than >50 50% chance of hazard occurring in 30 yr period

Table 3 Risk Matrix V. 5 High

High 4 1

Occurren Mediu 3 ce m

Low 2 2 3

V. Low 1

Trivial Minor Moderate Major Massive

1 2 3 4 5 Severity

These are considered to be high-level risks requiring priority attention. These risks have the Summary of Table 2 Risk potential to be catastrophic and as such should be addressed quickly. Assessment Form These are medium-level risks requiring action, but are not as critical as a red coded risk. Risk ID Severit Occurr Risk y ence Score Rating Rating Green (light and dark green) – These are lowest-level risks and indicate a need for 1 3 4 12 continuing awareness and monitoring on a regular basis. Whilst they are currently low or minor risks, some have the potential to increase to medium or even high-level risks and must therefore be regularly monitored and if cost effective mitigation can be carried out to reduce the risk even further this should be pursued. 2 3 2 6

3 4 2 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Table 4 Statement of Measures

Risk I.D. Risk Score Mitigation measure to be Outcome Action Date for Owner/Contact taken completion Person 1 12 New Wastewater treatment plant 2 6 New Wastewater treatment plant 3 8 Duty/Standby in place Maintain duty standby