PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

PRE – FEASIBILTY REPORT OF Rough Stone, Jelly and Gravel

OVER AN EXTENT 3.99.0 HECTARES AT S.F.NoS.35/4A, 35/4B, 35/4C, 35/4D, 35/4E, 35/4F, 35/4G, 35/4H and 35/4I of Maruthamputhur Part-1 Village, Alangulam Taluk, District, State.

LESSEE: G.Karuppasamy

1

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY LEASE APPLIED AREA FOR OVER AN EXTENT OF 3.99.0Ha IN MARUTHAMPUTHUR PART-1 VILLAGE, ALANGULAM TALUK, AND TAMILNADU OF THIRU.G.KARUPPASAMY, (Under the Guidelines of Ministry of Environment and Forest in terms of the provisions of EIA notification 2006 and specifically in circular No J- 12022/41/2006-IA.II (I) dated 20th December, 2020) 1.1 Executive Summary of the project The total extent of the Area is 3.99.0Ha, Patta land in Maruthamputhur Part-1 Village of Alangulam Taluk, Tirunelveli District. The category of project is B2. The lease applied area exhibits almost plain topography. The quarry operation is proposed to carry out with open cast semi mechanized mining with 5.0m vertical bench width of the bench is not less than bench height. Quarrying operation is carried out Splitting of rock mass of considerable volume from the parent rock mass by jackhammer drilling and blasting, hydraulic excavators are used for loading the Rough Stone from pithead to the needy crushers/other buyers for road project and construction works for filling and leveling of low lying areas. Occasionally hydraulic excavators are attached with rock breakers for fragmentation to avoid secondary blasting. The quarry operation is proposed up to depth for 72m below the ground level. Geological Resources is estimated at 25,82,125m3 of Rough stone, 1,98,625m3 of Weathered Rock and 79,450m3 of gravel formation. Mineable Reserves is estimated at 6,77,950m3 of Rough Stone, 1,36,500m3 of Weathered Rock and 55,932m3 of gravel formation after leaving necessary safety distance from the lease boundary as indicated in the precise area letter and relevant mining laws in force. Production Schedule is proposed an average production of 6,77,950m3 of Rough Stone, 1,36,500m3 of Weathered Rock and 55,932m3 of gravel formation for the period of Five years only. Mining license applied for period of Five years only. The Mining plan period proposed for the period of Five years only

2

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

The project area does not fall in ‘HACA’ region. There is no interstate boundary within the radius of 10Kms. The project area does not fall in CRZ zone within the radius of 10km from project area. There is no Western Ghats within the radius of 10Kms from project area. There are no Bird sanctuaries, wild life sanctuaries as per Wild life protection Act 1972, within the radius of 10Kms. There is no Habitation situated within 300mts in the project area. No Other existing pit situated within the radius of 500mts. 0.3KLD of water for labor drinking and domestic purpose will be available from near by village through package drinking water vendors. 0.3KLD and 0.4KLD for dust suppression in haul roads and Green belt during the course of quarrying will be taken from the existing Borehole on near the quarry. The project cost (Fixed assert cost + EMP cost + Operational cost) is about Rs. 74,46,000/- Seventy four lakhs and forty six thousand only) The EMP cost is around Rs. 4,50,000/- (Four Lakhs and fifty thousand rupees only) 2.0 INTRODUCTION OF THE PROJECT OR BACKGROUND INFORMATION The Rough Stone, Jelly and Gravel is proposed to excavate by opencast semi mechanized method in Maruthamputhur Part-1 Village, Alangulam Taluk, Tirunelveli District over an extent of 3.99.0Ha. The Category of project-’B2’ (i) Identification of project and project proponent: In case of mining project, a copy of mining lease/letter of intent should be given I. The quarry lease was applied at the date of 16.06.2017. II. The letter was issued by the District Collector, Tirunelveli letter vide Rc.No. M1/24418/2017, dated 06.09.2018. III. The Mining Plan was approved by the Deputy Director, Department of Geology and Mining, Tirunelveli vide Rc.No. M1/24418/2017, dated 09.10.2018. Owner name and address of the Project Proponent: Name of owner : Thiru.G.Karuppasamy,

Address : S/o.Gurusamy,

No.249, Sivanthinagar,

Kuthukkal Valasai, Tenkasi Taluk,

Tirunelveli District.

3

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

Pincode : 627811

Phone no : 6380546131 Email Address : [email protected] Owner Location of the Lease applied Area: Name of the quarry : Maruthamputhur Part-1 Rough Stone, Jelly and Gravel quarry, S.F.No s : 35/4A, 35/4B, 35/4C, 35/4D, 35/4E, 35/4F, 35/4G, 35/4H and 35/4I, Extent : 3.99.0 Ha, Village : Maruthamputhur Part-1, Taluk : Alangulam, District : Tirunelveli, State : Tamil Nadu, Ownership : Private individual, It is patta land jointly registered in the name of Thiru.Pannerselvan, Thiru.Jeyasundar, Thiru.Raju, Applicant (Karuppasamy) and Thiru.Niraikulathan vide patta no.1828, The Co-Pattadhars is given consent for quarrying. Please refer annexure no. IV & VII. (ii) Brief description of nature of the project The Rough Stone, Jelly and Gravel quarrying operation is proposed to carry out by opencast Semi mechanized method by formation of benches. Fifteen benches are proposed with a height of 5m on Rough Stone, Jelly and Gravel. The area applied for quarry lease exhibits almost plain topography covered by Gravel formation. The massive Charnockite formation is noticed below 2m (Avg) Gravel and 5m weathered rock formation and sloping towards Southeastern side of the area, the altitude of the area is above 126m (maximum) from MSL. The total quantity of Mineable reserve is estimated at 6,77,950m3 of Rough Stone, 1,36,500m3 of Weathered Rock and 55,932m3 of gravel formation for a period of Five years only. The excavated rough stone will be directly loaded into tipper to the needy crushers/other buyers for road project and construction works for filling and leveling of low lying areas. The quarrying operation is proposed up to a depth of 72m below the ground level. The quarrying Rough Stone, Jelly and Gravel of irrespective of sizes has a good market at present scenario.

4

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

(iii) Need for the project and its importance to the country and or region The Rough Stone, Jelly and Gravel is important building material to our country and Region, it’s a vital material for construction industries and the Rough Stone, Jelly and Gravel quarrying project falls in the area of Tirunelveli District, where plenty of Road widening projects are been carried being under massive development hence a lot of Rough Stone, Jelly and Gravel is required for (Granular sub base GSB) and also for the culverts and bridges, Besides catering domestic construction projects. Other infrastructure projects like building, Bridges are also under progress hence there is a huge demand of Rough Stone, Jelly and Gravel for public sector companies and local private sector projects also. The earning source in the targeted area is limited, most of the people in and around the area depend upon the seasonal agriculture and much of the people migrate to nearby towns where good industries and factories are growing up. Through this project will give employment opportunities to 19 employees directly and 9 employees indirectly. Mineral Industries of the state of Tamil Nadu provides employment opportunities for the people of the state as well as in the specific project area. The Quarrying is one among the major core sector for industries, which plays a vital process of country’s economic development. (iv) Demand and supply gap There is a huge demand of Rough Stone, Jelly and Gravel in Tirunelveli District as many National Road projects is under massive development for its widening and strengthening operation apart from this many bridges and fly over’s are also being under construction. There is a huge demand of Rough Stone, Jelly and Gravel for infrastructure development of the state; hence the project is significant to the state. The Railway line is also under progress where huge Demand of Rough Stone, Jelly and Gravel is required as Ballast. Other internal panchayat Roads, State Highway roads and Major District Roads are also under progress, besides all these public works projects the Rough Stone, Jelly and Gravel is widely used for domestic construction project like Hospital, School, Government Building and Housing, Construction. It is worth mentioning that the Rough Stone, Jelly and Gravel of Tirunelveli District. (v) Imports vs indigenous production There is no import of Rough Stone, Jelly and Gravel at present in .

5

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

(vi) Export Possibility There are no possibilities for export. (vii) Domestic/Export Markets After obtaining the lease the applicant will fetch a domestic market as mentioned earlier. It is propose to the excavated rough stone will be directly loaded into tipper to the needy crushers/other buyers for road project and customers for road project and construction works for filling and leveling of low lying areas. (viii) Employment Generation (Direct and Indirect) due to the project It is proposed to deploy about 19 directly and 9 persons will be indirectly benefited. The tentative man power required for the proposed Rough Stone, Jelly and Gravel quarry shall be as follows. a. Skilled labors Operator : 8 Mechanic : 1 Mines Manager/mate : 1 b. Semi-skilled Driver : 4 c. Unskilled- helper Musdoor/Labours : 5 Total : 19 The above man power is adequate to meet out the production schedule and the machinery strength envisaged in the mining plan and also to comply with the stationary provisions of quarry safety regulation. It is been ensured that the labours will not be deployed less than 18 years, No Child labours will engaged or entertained for any kind of quarrying operations. All the labours engaged for quarrying operations will be insured till the end of life of quarry. 3.0 PROJECT DESCRIPTION (i) Type of project including interlinked and interdependent projects, if any There is no interlinked & interdependent project. This is a quarrying project for production of 6,77,950m3 of rough stone of 1,36,500m3 of weathered rock formation and 55,932m3 of Gravel formation for a period of Five years only. The quarry operation is proposed depth for 72m (below ground level). The project is site specific. The entire rough stone will be directly loaded into tipper to the needy crushers /other buyers for road project and construction works for filling and leveling of low lying areas.

6

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

(ii) Location (map showing general location, specific location, and project boundary & project site layout) with coordinates  It is patta land jointly registered in the name of Thiru.Pannerselvan, Thiru.Jeyasundar, Thiru.Raju, Applicant (Karuppasamy) and Thiru.Niraikulathan vide patta no.1828, The Co-Pattadhars is given consent for quarrying. Please refer annexure no. IV & VII.  The area is mentioned in GSI Toposheet No. 58 H /09.  The Latitude between of 08°49'11"N to 08°49'19"N  The Longitude between of 77°31'22"E to 77°31'31"E WGS 1984 datum.  The Altitude is 126m (Maximum) from MSL. (iii) Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted There is no alternative sites are examined, The entire rough stone will be directly loaded into tipper to the needy crushers/other buyers for road projects and Gravel to needy customers for road project and construction works for filling and leveling of low lying areas. (iv) Size or magnitude of operation The total area of the project is about 3.99.0Ha. It is proposed to excavate 6,77,950m3 of Rough Stone, 1,36,500m3 of Weathered Rock and 55,932m3 of gravel formation for a period of Five years. The quarry proposed depth for 72m by open cast semi mechanized quarrying by deploys jackhammer drilling and blasting, hydraulic excavator attached with bucket are used for loading and unloading the Rough Stone, Jelly and Gravel from pithead to needy crushers/other buyers for road project and construction works for filling and leveling of low lying areas. Table-1:

Rough Stone Weathered Description Gravel (m3) (m3) Rock (m3) Geological Resources 25,82,125 1,98,625 79,450 Available Mineable reserves 6,77,950 1,36,500 55,932 Five year plan period As in the 6,77,950 1,36,500 55,932 approved mining plan (v) Project description with process details (a schematic diagram/flow chart showing the project layout, components of the project etc. should be given): The reserves and resource are arrived based upon the Geological investigation

7

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

 REMOVAL OF GRAVEL BY EXCAVATORS AND DIRECLTY LOADED INTO TIPPERS.  REMOVAL OF ROUGH STONE, JELLY AND GRAVEL BY EXCAVATORS BY DRILLING AND BLASTING.  SHALLOW DRILLING WITH JACKHAMMER 32-36 mm Dia.  MINIMUM BLASTING WITH CLASS 2 EXPLOSIVES.  LOADING OF ROUGH STONE, JELLY AND GRAVEL BY EXCAVATORS INTO TIPPERS.  TRANSPORTATION BY TIPPERS TO NEEDY CRUSHERS/OTHER BUYERS FOR ROAD PROJECT AND CONSTRUCTION WORKS FOR FILLING AND LEVELING OF LOW LYING AREAS. (vi) Raw material required along with estimated quantity, likely source, marketing area of final products, Mode of transport of raw Material and Finished Products This is a quarrying project for exploiting Rough Stone, Jelly and Gravel; hence, there is no requirement for raw material. The final product of Rough Stone, Jelly and Gravel irrespective of sizes will be sold to needy crushers/other buyers for road project and construction works for filling and leveling of low lying areas. (vii) Resource optimization/recycling and reuse envisaged in the project, if any, should be briefly outlined No optimization/Recycling and Reuse envisaged in the proposed Rough Stone, Jelly and Gravel quarry. (viii) Availability of water its source, Energy/power requirement and source should be given This Rough Stone, Jelly and Gravel and quarry project does not require huge water and Electricity for the project. WATER BALANCE CHART

WATER (1 KLD)

0.3KLD of Drinking water & Domestic 0.3 KLD for Dust suppression purpose 0.4 KLD for Green belt development

Used only for drinking purpose for operational workers Dust Suppression in the Haul Roads to prevent

Dust emission and pollution.

8

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

Table-2 Purpose Quantity Sources Drinking & Domestic 0.3KLD Approved Packaged Drinking water Purpose vendors available in Maruthamputhur village which is about 1.5km on Northwestern side of the area. Dust suppression 0.3KLD From Existing Borehole on nearby the quarry. Green belt 0.4 KLD From Existing Borehole on nearby the quarry.

Energy Electricity for Mines office and Lights only at nights (working is restricted on day time only between 9Am to 5Pm with 1pm to 2pm as lunch break). Diesel (HSD) will be used for quarrying machineries around 4,16,550 liters of HSD will be used for the entire project life. Diesel will be brought from nearby diesel pumps. No power is required for the project. Lightings on the Night will be taken from nearby electric poles after obtaining permission from concerned authorities. For Gravel Per hour Excavator will consume = 10 liters / hour Per hour Excavator will excavate = 60 m3 of Gravel For 55,932m3 = 55,932m3/60 = 932hours Diesel consume 932working hour = 932hours x 10 liters = 9320 liters of HSD for the excavation of Gravel. For weathered Rock Formation Per hour Excavator will consume = 10 liters / hour Per hour Excavator will excavate = 20 cbm of Rough Stone For 1,36,500Cbm = 1,36,500/20 = 6825 hours Diesel consume 6825 working hours = 6825 hours x 10 litres = 68250 liters of HSD for the excavation of Rough Stone. For Rough Stone Per hour Excavator will consume = 10 liters / hour Per hour Excavator will excavate = 20 cbm of Rough Stone For 6,77,950Cbm = 6,77,950/20

9

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

= 33898 hours Diesel consume 33898 working hours = 33898 hours x 10 litres = 338980 liters of HSD for the excavation of Rough Stone. Diesel consumption for Gravel = 9320Liters Diesel consumption for Weathered rock = 68250Liters. Diesel consumption for Rough Stone = 338980Liters. Total diesel consumption = 4,16,550 Liters of HSD Will be utilized for Entire project life. (ix) Quantity of wastes to be generated (liquid and solid) and scheme for their management/disposal The entire quarried Rough Stone, Jelly and Gravel of irrespective of sizes will be consumed to the needy crusher/other buyers as even the dust is sold nowadays as M sand. Hence, there is no waste in this quarrying operation. There is no toxic effluent expected to generate in the form of solid or liquid and gases and the no requirement of treatment of waste. (x) Schematic representations of the feasibility drawing which give information of EIA purpose

Form – 1

Along with pre-feasibility report & Approved Mining plan with Annexure

To Submit DEIAA

Final Presentation

4.0 SITE ANALYSIS (i) Connectivity  There is an existing road from the area leads to Maruthamputhur- Odaimarichan village road on Western side of the area.

10

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

 The Nearest Railway line is Tirunelveli to Tenkasi line which is about 15.5Km on Western side of the area.

 The National Highway (NH-208) Tirumangalam – Tenkasi is about 31.5km on Northwestern side of the area.

 The State Highway (SH-39) Tirunelveli - Alangulam is about 3.5Km on Northern side of the area.

(ii) Land Form, Land use and Land ownership

The entire project area is about 3.99.0Ha, which is Non irrigated and devoid of Vegetation and Habitations. Table-2

District Taluk Village S.F No Area Classification 35/4A, 35/4B, Tirunelveli Alangulam Maruthamputhur 35/4C, 35/4D, 3.99.0Ha It is patta land Part-1 35/4E, 35/4F, vide patta no- 35/4G, 35/4H and 1828, 35/4I

(iii) Topography (along with map) 1. The area applied for quarry lease exhibits almost plain topography covered by Gravel formation. The massive Charnockite formation is noticed below 2m (Avg) Gravel and 5m weathered rock formation and sloping towards Southeastern side of the area, the altitude of the area is above 126m (maximum) from MSL. 2. No major river is found nearby the applied area. 3. Water table is found at a depth of 80m in summer and 77m in rainy seasons. 4. Temperature of the area is reported to be 180C to a maximum of 420C during summer. 5. Rainfall of this area is about 800mm to 900 mm during the both NE & SW monsoons. (iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including area under CRZ), shortest distances from the periphery of the project to periphery of the forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from the HFL of the river), CRZ. In case of notified industrial area, a copy of the Gazette notification should be given.

The Quarry Lease Area is almost plain topography. The area is a dry barren land devoid of Agriculture and Habitations. The land is not used for any specific vegetation. The massive Charnockite formation is clearly inferred followed by the 2m (Avg) Gravel

11

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY and 5m weathered rock formation. The Ground water occurrence in this area is 80m depth. The quarrying is restricted up to depth 72m below the ground level; hence the quarry operation will not be affected by the ground water. The region experiences semi – humid climate and there is scanty growth of vegetation in and around the lease area (seasonal vegetation is mostly practiced). No Major water bodies within the radius of 10km. No CRZ within the radius of 10km No Forest within the radius of 10km No Interstate boundary within the radius of 10km No Western Ghats within the radius of 10km No National park, wild life sanctuary, eco sensitive area within the radius of 10km (v) Existing Infrastructure This is a Rough Stone, Jelly and Gravel quarry project hence there is no existing infrastructure in the proposed quarry area. (vi) Soil Classification The Rough Stone is clearly visible below 2m (Avg) Gravel and 5m weathered rock formation. This land does not sustain any type of vegetation or Agriculture (vii) Climatic data form secondary sources The area receives rainfall of about 800mm to 900mm/per annum and the rainy season is mainly from Oct - Jan during North East, monsoon. The summer is hot with maximum temperature of 42C and winter encounters a minimum temperature of 22C. (viii) Social infrastructure available There is no social infrastructure within the radius of 1Km like schools, universities, hospitals, prisons and community housing etc. 5. PLANNING BRIEF (i) Planning Concept (type of industries, facilities, transportation etc) Town and Country Planning/Development authority Classification Opencast Semi Mechanized mining is adapted to in the Rough Stone, Jelly and Gravel. The excavated Splitting of rock mass of considerable volume from the parent rock mass by jackhammer drilling and blasting, the removed mass is manually dressed into small stones and then loaded manually into tippers for transportation to

12

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY the needy crusher/other buyers. Facilities such as power, Transportation and commodities infrastructure facilities are locally available near the project site. There are no habitations or villages en-route between the quarry and crushing site the loaded vehicles are allowed to move only below 40Kms per hour on the roads. The haul roads are sprinkled periodically to prevent dust. Transportation  There is an existing road from the area leads to Maruthamputhur- Odaimarichan village road on Western side of the area.

 The Nearest Railway line is Tirunelveli to Tenkasi line which is about 15.5Km on Western side of the area.

 The National Highway (NH-208) Tirumangalam – Tenkasi is about 31.5km on Northwestern side of the area.

 The State Highway (SH-39) Tirunelveli - Alangulam is about 3.5Km on Northern side of the area.

The total area of the project is about 3.99.0Ha. Open cast semi mechanized method of quarrying by deploys jackhammer drilling and blasting, air driven compressor, and excavators attached with buckets are used for loading and unloading the Rough Stone, Jelly and Gravel Splitting of rock mass of considerable volume from the parent rock mass by jackhammer drilling and blasting, The removed mass is manually dressed into small stones and then loaded manually into tippers for transportation to the needy crusher/other buyers. The project land is devoid of vegetation and lies in the backward town of Tirunelveli District. There are no specific industries or factories in and around the project area. The Mineable Reserves is estimated at 6,77,950m3 of Rough Stone, 1,36,500m3 of Weathered Rock and 55,932m3 of gravel formation, the applicant proposed to carry out 6,77,950m3 of Rough Stone, 1,36,500m3 of Weathered Rock and 55,932m3 of gravel formation for the period of Five years only. (ii) Population projection There are no habitations within 500m radius. There are few villages located in this area within 10 km radius of quarry site; the approximate distance and population are given below. Table – 4

13

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

Approximate distance Name of the Approximate S.No & Direction from lease Village population applied area 1. Keela Karumpuliyuthu 3.5km - NE 200 2. Maruthamputhur 1.5km - NW 2000 3. Udayampuli 3.0Km – SE 500 4. Thalaiyuthu 5.0Km – SW 400 Basic human welfare Amenities such as Health Center, Schools, Communication Facilities, and Commercial Centers etc are available at Alangulam at a distance of 5.5km on the NW side of the area. (iii) Land use planning (breakup along with green belt etc.) The land use planning of the quarry area of the total extent of 3.99.0Ha is given below. Table-5 Present Area Area in use during the Sl. No. Land Use (Hect) quarrying period (Hect)

1. Quarrying Pit Nil 2.80.0

2. Infrastructure Nil 0.01.0

3. Roads Nil 0.01.0

4. Green Belt Nil 0.15.0

5. Unutilized 3.99.0 1.02.0

Total = 3.99.0 3.99.0

(iv) Assessment of Infrastructure Demand (Physical & Social) The existing road facilities are already available which shall be used and maintained. The labors requirement is drawn from the nearest villages. The labors will be brought by jeeps and vans to the quarry site, Medical facilities are available near the project site, Government and private hospitals and other basic amenities and infrastructure facilities like communication centres, school supermarket, and bus stand are also available in Alangulam distance of 5.5km (NW). This quarry project will provide employment for about 19 persons directly and 9 peoples indirectly. (v) Amenities/Facilities The simple methods adopted and the limited scale of activities involved in Rough Stone, Jelly and Gravel quarrying does not require High Tension Electric Power supply

14

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY or huge worship facilities. The quarrying work is restricted to one general shift during daytime 9.00am to 5.00pm with 1.00pm - 2.00pm lunch break. Major Machinery repair works are attended at Alangulam distance of 5.5km (NW) minor repairs are carried out by the nearby mechanics. All facilities and amenities are available in Alangulam distance of 5.5km (NW) side of the area. Packaged drinking water will be brought from approved vendors. Mine office, storeroom, toilet and first-aid room will be provided on permanent structures within the lease area after the grant of lease. 6. PROPOSED INFRASTRUCTURE (i) Industrial Area (Processing area) There is no processing area proposed within the lease area. (ii) Residential area (Non processing area) There is no residential area within 500m of the lease area. (iii) Green Belt All along the boundary barrier is selected for Green belt development by planting and maintaining native species. The total area for proposed for Green belt is around 0.10.0Ha Ha out of 3.99.0Ha. (iv) Social infrastructure About 19 employees will be directly benefited and 9 persons will be indirectly benefited, the lease ensure to share all responsible for special benefits like water, health care, Education benefits, and promotion of socio cultural activities of the nearby villages. (v) Connectivity (traffic and transportation road/ Rail/ Metro/ Water ways etc.,)  There is an existing road from the area leads to Maruthamputhur- Odaimarichan village road on Western side of the area.

 The Nearest Railway line is Tirunelveli to Tenkasi line which is about 15.5Km on Western side of the area.

 The National Highway (NH-208) Tirumangalam – Tenkasi is about 31.5km on Northwestern side of the area.

 The State Highway (SH-39) Tirunelveli - Alangulam is about 3.5Km on Northern side of the area.

(vi) Drinking Water management (Source & Supply of water) This proposed Rough Stone, Jelly and Gravel quarry project does not require huge water either for beneficiation or processing. Water required for domestic

15

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY consumption for labors is around 1.0 KLD. The packaged Drinking water for this will be brought from approved water vendors. 1. Drinking Water & Domestic purpose – 0.3 KLD (source: through approved packaged water vendors) 2. Dust Suppression – 0.3 KLD (source: from existing borehole on near by the quarry) (vii) Sewerage System Toilets will be constructed on permanent structure and sewage will be discharged once in a months. The sewage waste will be collected in soak pit and discharged as manure after treatment for the Green belt development. (viii) Industrial Waste Management No industrial waste will be generated from the project. (ix) Solid Waste Management The waste generated during quarrying activity is negligible rock mass during handling and re handling. Hence, there is no waste in this quarrying operation. There is no solid waste generation during the quarrying operation. (x) Power Requirement & Supply / source The proposed Rough stone quarrying does not required any power supply for the quarrying operation. It is proposed to operate in day time only from 9 Am to 5Pm with 1 Hour lunch interval between 1Pm to 2Pm. 7.0 REHABILITATION AND RESETTLEMENT (R & R PLAN) (i) Policy to be adopted (Central/State) in respect of the project affected persons including home ousters, langoustes and landless laborers (a brief outline to be given) It is patta land jointly registered in the name of Thiru.Pannerselvan, Thiru.Jeyasundar, Thiru.Raju, Applicant (Karuppasamy) and Thiru.Niraikulathan vide patta no.1828, The Co-Pattadhars is given consent for quarrying. Please refer annexure no. IV & VII. Hence there is no Rehabilitation and resettlement is involved. The deployed labours will be insured as per the Government norms till the end of the life of the quarry. Periodical medical test will be conducted for the labors to monitor the occupational disease. The salaries and benefits will be paid as specified by the instruction given by the labor enforcement officers

16

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

8. PROJECT SCHEDULE & COST ESTIMATES (i) Likely date of start of construction and likely date of completion (Time schedule for the project to be given) The proposed quantity is around 6,77,950m3 of rough stone of 1,36,500m3 of weathered rock formation and 55,932m3 of gravel formation for the period of Five years only (ii) Estimated project cost along with analysis in terms of economic viability of the project A. Fixed Asset cost: Land cost = Rs. 15,96,000/- Labours shed = Rs. 1, 00,000/- First aid room & Accessories = Rs. 1, 00,000/- Sanitary facilities = Rs. 1, 00,000/- Total Fixed Asset cost = Rs. 18,96,000/- B. Operational cost: Machineries = Rs. 50, 00,000/- Fencing cost = Rs. 1, 00,000/- Total operational cost = Rs. 51, 00,000/- (I). EMP Estimation: Air Quality Sampling = Rs. 40, 000/- Water quality sampling = Rs. 40, 000/- Noise monitoring = Rs. 20, 000/- Ground vibration test = Rs. 20, 000/- Total EMP Estimation cost = Rs. 1,20,000/- (II). Expenditure and maintenance:  Drinking water facility for the labors = Rs. 1,00,000/-  Sanitary arrangement = Rs. 25,000/-  Safety kits = Rs. 50,000/-  Water sprinkling = Rs. 1,00,000/-  Afforestation cost = Rs. 30,000/-  Cost towards charity = Rs. 25,000 Total Expenditure and maintenance cost = Rs.4,50,000/-

Total EMP cost and Expenditure cost The project cost: Total cost of Project (A+B+C) = Rs.74,46,000/- (The total cost of the project including EMP cost is about Rupees Seventy four lakhs and forty six thousands only)

17

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY Population Benefit The social responsibilities like providing School Note books, Uniforms to the Students below poverty level beside if the villages require any borehole for public use it will ensure to do so. As a part of corporate social responsibility it is ensured to take part and contribute the native cultural activities in the nearby villages. During summer seasons packaged drinking water will be kept will be kept in the village for public and for tresspallers. MINE CLOSURE PLAN: Steps proposed for phased restoration, reclamation of already mined out areas: After the exploitation the Gravel Bund and fencing will be constructed around the pit to prevent inherent entry of public. The quarried pit will be allowed to collect rain and seepage water which will act as a Reservoir which will enhance the Ground water level of the nearby wells. There is no proposal for back filling, reclamation and re habitation. The quarry pit will be fenced to prevent inherent entry of public. The green belt development will be maintained. Measures to be under taken on mine closure as per Act & Rules: Measure will be taken as per Act & Rules. Mitigation measure to be undertaken for safety and restoration / reclamation of the already mined out area: Drilling will be carrying out by wet drilling to control the dust into the air. Blasting will be carrying out on limited scale. Mist spray on haul road will be proposed to prevent the dust propagation into the air. The plantation will be carried out on the safety barriers to prevent Noise, besides wet drilling will be practiced to prevent dust. All the machineries will be maintained in good conditions as per RTO and TNPCB Norms to prevent Noise, Smoke and vibration. Machineries will be periodically maintained by experienced mechanic to minimize noise, Smoke and ground vibration.

18

PRE FEASIBILITY REPORT OF MARUTHAMPUTHUR PART-1 ROUGH STONE, JELLY AND GRAVEL QUARRY UNDER EIA NOTIFICATION 2006 THIRU.G.KARUPPASAMY

9. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) (i) Financial and social benefits with special emphasis on the benefit to the local people including tribal population, if any, in the area There are no tribal populations in and around the area about 19 personas directly and 9 persons indirectly will be benefited by these projects, besides the government. Will get good revenue by taxes, seinerage fees etc. The socio - Economic conditions of the village and distance will enhance due to the project, hence the project should be allowed after considering all the parameters.

Signature of the Applicant

G.Karuppasamy

Signature of the Recognized qualified person

C.Natarajan, M.Sc.,M.Phil., RQP/MAS/004/87/A

Place : Salem Date :

19