The World Bank Report No: ISR11924

Implementation Status & Results Medium Cities Infrastructure Project (P099992)

Operation Name: Liaoning Medium Cities Infrastructure Project (P099992) Project Stage: Implementation Seq.No: 10 Status: ARCHIVED Archive Date: 28-Oct-2013 Country: China Approval FY: 2006

Public Disclosure Authorized Product Line:IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 27-Jun-2006 Original Closing Date 31-Dec-2011 Planned Mid Term Review Date Last Archived ISR Date 24-Jun-2013 Public Disclosure Copy Effectiveness Date 05-Jan-2007 Revised Closing Date 31-Oct-2013 Actual Mid Term Review Date 30-Sep-2011

Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the Project is to assist the Borrower's Project Cities in enhancing: (i) the performance and quality of their existing urban transport infrastructure in terms of mobility, access, and safety; (ii) the efficiency and effectiveness of their urban public transport and road maintenance services; and (iii) the responsiveness of their urban transport systems to the needs of population without access to private motorized vehicles. Has the Project Development Objective been changed since Board Approval of the Project?

Public Disclosure Authorized Yes No

Component(s)

Component Name Component Cost Road Infrastructure and Reconstruction 330.93 Secondary Road Rehabilitation and Road Maintenance Equipment 113.40 Traffic Safety and Traffic Management 22.18 Public Transport 14.45 Institutional Development 4.85

Overall Ratings Previous Rating Current Rating Public Disclosure Authorized Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating Low Low

Public Disclosure Copy Implementation Status Overview After seven years of implementation, the project is due to close on October 31, 201. The project was implemented in six project cities of Liaoning provinces, namely , ,

Page 1 of 6 Public Disclosure Authorized The World Bank Report No: ISR11924

Jinzhou, , , and . All cities completed their project activities successfully, except Benxi, which was not able to complete the Benxi Bridge due to difficulties in coordinating construction schedule with the Ministry of Railway on a planned railway construction program crossing the bridge. Because of the priority given to railways, the Benxi Bridge construction had to be delayed. However, Benxi has now resumed the construction using its own funds, and expects to complete the bridge by mid-2014. The development objective of the project was achieved. Most of the outcome indicators were met. An Implementation Completion Report (ICR) is currently under preparation by the Bank and the Borrower. The ICR will carry out a full assessment of the achievement of the project objectives and implementation experience.

Locations Country First Administrative Division Location Planned Actual China Liaoning Panjin Shi

China Liaoning Liaoyang Shi

Public Disclosure Copy China Liaoning Shi

China Liaoning Fushun Shi

China Liaoning Dengta Shi

China Liaoning Benxi Shi

Results

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target I4. Number of traffic accident fatalities/1000 Text Value Benxi 3.8 , Fushun 5.97, Benxi 2.5, Fushun 1.89, Percentage of Reduction by motor vehicles Jinzhou 4.3, Liaoyang 14.8, Jinzhou 2, Liaoyang 3, Panjin city: Benxi 15% , Fushun Panjin 5.7 1.69 15% , Jinzhou 15% , Liaoyang 15% , Panjin 15% Date 13-Apr-2006 30-Apr-2013 01-Oct-2013 Comments 2005 data All indicators were achieved End target postponed to 2013 the targets. due to loan closing date extension I5. Use of open competitive bidding methods Text Value outside Fushun no real Benxi N/A, Fushun N/A, 10% reduction in at least one on a pilot basis to award maintenance competitive bidding Jinzhou 0.84, Liaoyang N/A, city contracts Panjin 0.89 Date 13-Apr-2006 30-Apr-2013 01-Oct-2013 Comments 2005 data These indicators were difficult End target postponed to 2013 to be achieved. due to loan closing date extension Public Disclosure Copy

Page 2 of 6 The World Bank Report No: ISR11924

I8. Improved level of bus service measured by Text Value Benxi: (i) 1440, (ii) 27.6; Benxi: (i) 2126, (ii) 32.6; % increase: Benxi: (i) 20%, (i) number of bus passengers and (ii) vehicle Fushun: (i) 3200, (ii) 144; Fushun: (i) 3400, (ii) 155; (ii) 15%; Fushun: (i) 20%, (ii) km of revenue service in at least one project Jinzhou: (i) 7600, (ii) 25.2; Jinzhou: (i) 10463, (ii) 24.52; 15%; Jinzhou: (i) 1 5%, (ii) city Liaoyang: (i) 5200, (ii) 24.1; Liaoyang: (i) 7760, (ii) 31.5; 15%; Liaoyang: (i) 15%, (ii) Panjin: (i) 2800, (ii) 12.3 Panjin: (i) 8917, (ii) 38 15%; Panjin:(i) 10%, (ii) 10% Date 13-Apr-2006 30-Apr-2013 01-Oct-2013 Comments 2005 data All indicators were partially or End target postponed to 2013 fully achieved the targets. due to loan closing date extension I9. Network coverage of public transport, Text Value Benxi 1.35, Fushun 2.58, Benxi 2.2, Fushun 2.86, increase by city: Benxi 10%, measured in route km per square km Jinzhou 1.74, Liaoyang 1.47, Jinzhou 1.7, Liaoyang 2.01, Fushun 5%, Jinzhou 10%,

Public Disclosure Copy Panjin 2.34 Panjin 3.91 Liaoyang 10%, Panjin 5% Date 13-Apr-2006 30-Apr-2013 01-Oct-2013 Comments 2005 data Target reached for most cities End target postponed to 2013 except Jinzhou. due to loan closing date extension I6. Satisfaction levels with public transport Text Value Benxi 3.1, Fushun 2.8, Benxi 3.05, Fushun 3, 15% increase services, expressed by a panel of public Jinzhou 2.7, Liaoyang 2.8, Jinzhou 4.3, Liaoyang 2.97, participants. See attached Jan. 3, 2007 note Panjin 3.0, Dengta 3.6 Panjin 2.95, Dengta N/A for calculations of Baseline values. Date 13-Apr-2006 30-Apr-2013 01-Oct-2013 Comments Some cities achieved the End target postponed to 2013 targets except Benxi Panjin due to loan closing date and Dengta. extension I7. Competitive award of bus route franchises Text Value Benxi 0%, Fushun 34%, Benxi N/A, Fushun N/A, Benxi 20%, Fushun no to multiple independent operators on a pilot Jinzhou 0%, Liaoyang 0%, Jinzhou N/A, Liaoyang N/A, Target, Jinzhou 20%, basis Panjin 0% Panjin N/A Liaoyang 20%, Panjin 20% Date 13-Apr-2006 30-Apr-2013 31-Dec-2011 Comments 2005 data Franchising was not pursued as part of national policies in China but some cities organized contracting within public transport companies. I3. Travel time (minutes) (calculated Text Value Benxi 19.6, 21 Fushun 39.6, Benxi 16, 18.5; Fushun 22.3, Reduction by city: Benxi 10%, speratedly for autos, buses and bycycles, and 7.4 Jinzhou 20.3, 20.5 21.6; Jinzhou 12.3, 18; 10% Fushan 15%, 5% averaged weighting by mode share) Liaoyang 11.1, 27.6 Panjin Liaoyang 11.7, 15.8; Panjin Jinzhou 10%, 10% Liaoyang 39.9, 37.9 Dengta 32.5, 28 30.2, 26.3, Dengta N/A, N/A 5%, 10% Panjin 15%, 15% Dengta 15%, 10% Date 13-Apr-2006 30-Apr-2013 01-Oct-2013 Comments 2005 data All indicators were partially or End target postponed to 2013 Public Disclosure Copy fully achieved the targets. due to loan closing date extension

Page 3 of 6 The World Bank Report No: ISR11924

I1. Satisfaction levels with transport facilities Text Value Benxi 3.1; Fushun 2.8, Benxi 3.2; Fushun 3.6, 15% increase (mobility, access, safety) expressed by a panel Jinzhou 2.7, Liaoyang 2.8, Jinzhou 4.3, Liaoyang 3.3, of public participants. See attached Jan. 3, Panjin 3; Dengta 3.6 Panjin 3.8; Dengta 3.3 2007 note for Baseline values. Date 13-Apr-2006 30-Apr-2013 01-Oct-2013 Comments All indicators were partially or End target postponed to 2013 fully achieved the targets due to loan closing date except Dengta. extension I10. Adoption of effective bus priority Text Value 10% reduction in travel time measures(as measured by difference in the Date 20-Jul-2005 30-Apr-2013 01-Oct-2013 operating speeds along priority sections). Comments Priority Public Transport End target in 2013 due to loan Corridors are being closing date extension Public Disclosure Copy implemented in Liaoyang and Benxi. Measurements to take place after a year of operations. Partially achieved targets. Roads in good and fair condition as a share of Percentage Value 50.00 79.60 79.00 total classified roads Date 13-Apr-2006 30-Apr-2013 30-Sep-2013 Comments Benxi 55%, Fushun 52%, Benxi 71%, Fushun 80%, Benxi 80%, Fushun 85%, Jinzhou 42%, Liaoyang 41%, Jinzhou 85%, Liaoyang 75%, Jinzhou 80%, Liaoyang 80%, Panjin 60%, Dengta 45% Panjin 87%, Panjin 80%, Dengta 70% All indicators were partially or fully achieved the targets. Size of the total classified network Kilometers Value 2075.00 2282.00 2290.00 Sub Type Supplemental

Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Completion of the works - Road Infrastructure Text Value 0 90 100 and Reconstruction Date 13-Apr-2006 09-Sep-2013 01-Oct-2013 Comments completed Target postponed to 2013 Completion of the works and successful Text Value 0 90 100 procurement of goods - Secondary Road Date 13-Apr-2006 09-Sep-2013 01-Oct-2013 Rehabilitation and Road Maintenance Equipment Comments Completed Target postponed to 2013

Completion of the works - Public Transport Text Value 0 90 100 Public Disclosure Copy

Page 4 of 6 The World Bank Report No: ISR11924

Date 13-Apr-2006 09-Sep-2013 01-Oct-2013 Comments Completed Target postponed to 2013 Completion of the works and successful Text Value 0 90 100 procurement of goods - Traffic Safety and Date 13-Apr-2006 09-Sep-2013 01-Oct-2013 Traffic Management Comments All contracts were completed. Target postponed to 2013 Completion of studies, training and study tours Text Value 0 90 100 - Institutional Development Date 13-Apr-2006 09-Sep-2013 01-Oct-2013 Comments International training will not Target postponed to 2013 be conducted due to recent domestic policy. Public Disclosure Copy Roads constructed, non-rural Kilometers Value 0.00 17.40 20.00 Date 01-Dec-2006 09-Sep-2013 01-Oct-2013 Comments completed Target postponed to 2013 Roads rehabilitated, Non-rural Kilometers Value 0.00 80.60 83.00 Date 01-Dec-2006 09-Sep-2013 01-Oct-2013 Comments completed Target postponed to 2013

Data on Financial Performance (as of 02-Aug-2013)

Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P099992 IBRD-48310 Effective 27-Jun-2006 18-Oct-2006 05-Jan-2007 31-Dec-2011 31-Oct-2013

Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P099992 IBRD-48310 Effective USD 218.00 218.00 0.00 171.33 46.67 79.00

Disbursement Graph Public Disclosure Copy

Page 5 of 6 The World Bank Report No: ISR11924 Public Disclosure Copy

Key Decisions Regarding Implementation ICR mission is planned in November 2013.

Restructuring History Level two Approved on 18-Sep-2011

Related Projects There are no related projects. Public Disclosure Copy