WESTERN REGION TRANSMISSION Public Disclosure Authorized () PRIVATE LIMITED

Social Safeguard Due Diligence Report

December 2010

Public Disclosure Authorized

CONTENTS

PAGE NO.

LIST OF ANNEXURES……………………………………………………………. 2

ABBREVIATIONS………………………………………………………………… 3

Social Safeguar d Due Diligence 1.0 Introduction…………………………………………………………………. 4 1.1 Background…………………………………………………………………. 4 1.2 Objective of Social Safeguard Due Diligence……………………………… 6 1.3 Project description………………………………………………………….. 6 2. Alternative analysis of the alignment……………………………...... 9 3. Methodology………………………………………………………………... 9 4 Social Impact Study of the project…………………………………...... 11 4.1 Impact on structure………………………………………………...... 11 4.2 Impact on Land……………………………………………………………... 11 4.3 Impact on Indigenous People………………………………………...... 11 4.4 Local employment………………………………………………………….. 11 4.5 Impact on livelihood and Crop Compensation ……………………………. 12 4.6 Accident Safety (Compensation for loss of life or Injury)………...... 13 5. Implementation Arrangement and Process………………………...... 13 6. Community Development Activities ………………………………………… 13 7. Conclusion and Recommendation………………………………………….. 13 8. Proposed monitoring by IIFCL……………………………………………... 14

TABLES

1.1 Project Highlights ………………………………………………………………. 4 1.2 Sub-project transmission lines………………………………………………… 6 1.3 Project Scope of Work………………………………………………………….. 7 1.4 Substation Details………………………………………………………………. 8 1.5 Sub-Project Construction Status……………………………………………….. 8 3.1 Availability of Social safeguard documents………………………………… 10

FIGURE 1.1 Western Region System Strengthening Scheme (WRSSS)-II…………….. 5

India Infrastructure Finance Company Limited Page 1

ANNEXURE

Annexure 1 List of Villages ………………………………………………………….. 15 Annexure 2 Justification of alignments …………………………………………….. 24 Annexure 3 License under Section 164 of The Electricity Act 2003…………… 26 Annexure 4 Crop Compensation Calculation ……………………………………... 30 Annexure 5 Crop production ………………………………………………………... 31 Annexure 6 Status of Crop compensation payment ……………………………… 32 Annexure 7 Formal Public consultation details …………………………………… 33 Annexure 8 Copy of 7/12 records ………………………………………………….. 36 Annexure 9 Copy of Notices issued to the affected landowners ……………….. 37 Annexure 10 Copy of Cheque issued to the affected landowners ……………….. 38 Annexure 11 Status of Community Development Activities ………………………. 39 Annexure 12 Summary of findings …………………………………………………. 40

India Infrastructure Finance Company Limited Page 2

ABBREVIATIONS

CEA Central Electricity Authority CRR Compliance Review Report CSR Corporate Social Responsibility ESPP Environment and Social Policy and Procedures IIFCL India Infrastructure Finance Company Limited IPTC Independent Private Transmission Company LIE Lender’s Independent Engineer PGCIL Power Grid Corporation of India Limited PIM Project Information Memorandum RAP Resettlement Action Plan ROW Right of Way SDD Social Due Diligence SIA Social Impact Assessment WB World Bank WRSSS Western Region System Strengthening Scheme WRTGPL Western Region Transmission (Gujarat) Private Limited WRTMPL Western Region Transmission (Maharashtra) Private Limited

India Infrastructure Finance Company Limited Page 3

SOCIAL SAFEGUARD DUE DILIGENCE

1.0 INTRODUCTION

1.1 Background: 1. To meet the growing power demand in the Western Region of India, a number of power transmission projects are coming up in this region. The State of Maharashtra is part of the Western Regional Electricity Grid comprising the States of Gujarat, Maharashtra, Madhya Pradesh and Goa. As part of strengthening of the Western Grid, new transmission strengthening proposed to be implemented under Western Region System Strengthening Scheme (WRSSS)-II, which comprises of 4 projects namely A, B, C and D as shown in Fig 1.1 . Project B and C that are coming up in the states of Maharashtra and Gujarat shall be developed by Independent Private Transmission Company (IPTC) through 100.00% private participation route. Power Grid Corporation of India Ltd. (PGCIL) carried out necessary bidding process in selecting the IPTC and entrusted the implementation of project B and C to Reliance Power Transmission Ltd (RPTL). RPTL then formed a wholly owned project specific “Special Purpose Vehicle” (‘SPV”) for implementing the Project B and C. Accordingly Western Region Transmission (Maharashtra) Private Limited (“WRTMPL”) and Western Region Transmission (Gujarat) Private Limited (“WRTGPL”) were formed to undertake the Project B and C respectively. The transmission project in Maharashtra involving development of 1031.3 km 400kV line. The project highlights are given in table 1.1 :

Table 1.1: Project Highlights

Project Name - Western Region System Strengthening Scheme - II, Project B

Total length - 1031.2 km

Location - Beed, Ahmednagar, Pune, Aurangabad, Sholapur, Osmanabad, Latur, Sangli and Kolhapur districts in Maharashtra and Bijapur district in Karnataka

Beneficiaries - MP Power Trading Company Ltd, Gujarat Urja Vikas Nigam Ltd, Maharashtra State Electricity Distribution Company Ltd., Chhattisgarh State Power Distribution Co. Limited, Electricity Department Govt. of Goa, Electricity Department Administration of Daman & Diu, Electricity Department Administration of Dadra & Nagar Haveli and MP Audyogik Kendra Vikas Nigam Ltd.

Project Cost - Rs 912 crores

India Infrastructure Finance Company Limited Page 4

2. The objective of the project is to:

• Provide adequate transmission system for reliable transfer of power to constituents of Western region; • Maintain system stability, security of the western grid under all operating conditions; and, • Increase the power transmission capacity of National Grid

.

Fig 1.1: Western Region System Strengthening Scheme (WRSSS) -II

3. WRTMPL has signed the Common Loan Agreement on 24 th April 2009 with the lenders 1 including India Infrastructure Finance Company Ltd. (IIFCL). IIFCL as part of its infrastructure scheme has approved Rs 124 crores to WRTMPL out of the total project cost of Rs 912. crores. Out of the approved Rs 124 crores, IIFCL has already disbursed Rs 15.65 crores to WRTMPL. 4. World Bank has sanctioned US$ 1,195 million line of credit to IIFCL to encourage flow of private investments into infrastructure. The sub-project has been considered for retroactive financing out of the above line of credit from World Bank. In order to be eligible for funding from the WB loan facility, Compliance Review Report (CRR) need to be prepared for the sub-projects which includes (i) Finance; (ii) Procurement; (iii) Environment and (iv) Social aspects. The Present report on Social Safeguard Due Diligence is part of the CRR.

1 The lenders of the project include State Bank of India (SBI), IIFCL, Vijaya Bank, Bank of Mysore and State Bank of Bikaner and Jaipur (SBBJ.).

India Infrastructure Finance Company Limited Page 5

1.2 Objective of Social safeguard Due Diligence 5. Social Safeguards due diligence study is carried out to assess the adequacy of the project with the applicable National and World Bank Social Safeguard policies. The main objective of this Social Due Diligence (SDD) is, • To assess the likely social impacts of the project with respect to land acquisition and involuntary resettlement, ascertain adverse impacts, if any, on the people, in terms of displacement, loss of incomes, and community links. • To ascertain, in case of any adverse impact, if appropriate mitigation measures have been taken during the project planning, designing and frameworks established for carrying out safeguard measures during the implementation stage to minimize and mitigate such any adverse impacts. • To confirm if other critical social issues have been addressed in compliance with the National and World Bank Social Safeguard Policies.

1.3 Project Description: 6. As part of strengthening of the Western Grid, new power transmission lines are proposed under WRSSS-II. Under this scheme 1031.2 km 400kV line is proposed to be developed in the state of Maharashtra. The sub-project transmission lines passes through Beed, Ahmednagar, Pune, Aurangabad, Sholapur, Osmanabad, Latur, Sangli and Kolhapur districts in Maharashtra and Bijapur district in Karnataka. The sub-project details are given in table 1.2 . Table 1.2: Sub-project transmission lines Sl. No. Name of Transmission Name of Tehsil/ Approx . No. of towers Lines District Line Length to be footed (Km) 1 Parli – Pune 400kV D/C Parli/Beed to 323.00 886 line Pune/Pune 2 Pune-Aurangabad 400kV Pune/Pune to 236.00 623 D/C line Aurangabad 3 Parli-Solapur 400kV D/C Parli/Beed to 136.00 355 line Solapur/Solapur 4 Solapur (Limdi chincholi)- Solapur to 219.00 575 Kolhapur, 400KV D/C Line Kolhapur

5 LILO of Lonikhand-Kalwa Lonikhand 1.20 8 400Kv D/C Line at Pune Kalwa/Thane 6 LILO of Solapur-Karad Solapur/Solapur 116.00 298 400kV S/C line at Solapur

Total 1031 .20 274 5 Source: Lenders Independent Engineer (LIE) report, 4 th Quarterly Report

7. The scope of work of WRTMPL as part of the project include only gantry to gantry connection and the major construction activities include (i) construction of tower foundation; (ii) tower erection and (iii) stringing of wires. The interconnection facilities like sub-stations and associated equipments are supported by PGCIL. WRTMPL has entered into an EPC

India Infrastructure Finance Company Limited Page 6

contract with Reliance Infra. The scope of work of WRTMPL, PGCIL and Reliance Infra is summarized in table 1.3 as given below: Table 1.3: Project Scope of Work Sl. Scope of Work Primary Secondary No. Responsibility Responsibility 1 Detailed survey with respect to route Reliance Infra WRTMPL alignment, optimization of tower locations, soil resistivity, etc. 2 Design and testing of various Reliance Infra WRTMPL families of tower for different wind zones through which the transmission lines are passing. 3 Fabrication and supply of all types Reliance Infra WRTMPL of towers, tower accessories and line materials. 4 Selecting different types of Reliance Infra WRTMPL foundations for different towers and casting for foundation for tower footings including river crossing towers. 5 Erection of towers, painting of Reliance Infra WRTMPL towers and supply and erection of span markers, obstruction lights, fixing of insulator string, stringing of conductors and earth wire along with all necessary line accessories. 6 Testing and commissioning of Reliance Infra WRTMPL respective transmission lines. 7 Maintenance of Right of Way. WRTMPL 8 Crop compensation. WRTMPL 9 Statutory clearances from Govt. WRTMPL authorities. 10 Interconnection facilities (like PGCIL WRTMPL (to obtain substation, gantries etc) necessary permission for charging) Source: Project Information Memorandum for Project B and Implementation Agreement

8. According to the Implementation agreement (IA) between PGCIL and WRTMPL, PGCIL shall provide all the necessary interconnection facilities to WRTMPL. The interconnection facilities include substations/switch stations. The substation facility for the present sub- project shall be provided by PGCIL from the existing sub-stations as detailed in table 1.4 .

India Infrastructure Finance Company Limited Page 7

Table 1.4: Substation Details S.No. Transmission Li ne Name of Substation 1 Parli-Pune 400kV D/C line 400kV substation at Parli 400KV Substation at Pune 2 Pune-Aurangabad 400kv D/C line 400 KV substation at Pune 400 KV substation at Aurangabad 3 Parli- Solapur 400kv D/C Line 400 kV substation at Parli 400kV substation at Solapur 4 Solapur-Kolhapur, 400kV D/C 400kV substation at Solapur Line 400kV substation at Kolhapur 5 LILO of Lonikhand-Kalwa 400kV 400kV substation at Pune D/C line Pune

6 LILO of Solapur-Karad 400kV 400kV substation at Solapur S/C line at Solapur

9. Lenders Independent Engineer (LIE) has been appointed by State Bank of India to monitor the progress in construction activities. The status of construction activities as per the LIE report is given in table 1.5 . Table 1.5: Sub-Project Construction Status Sl. Name of Length Activities Progress up No. transmission Line (km) to 30.11.10

Total Unit 1 Parli-Pune 400kV 323 Detailed 323 Km Completed D/C line Survey Foundations 886 Nos. 471 Erection 886 Nos. 108 Stringing 323 Km 0 2 Pune-Aurangabad 236 Detailed 236 Km 212 400kv D/C line Survey Foundations 623 Nos. 323 Erection 623 Nos. 44 Stringing 236 Km. 0 3 Parli- Solapur 400kv 136 Detailed 136 Km Completed D/C Line Survey Foundations 355 Nos. 118 Erection 355 Nos. 44 Stringing 136 Km 0 4 Solapur-Kolhapur, 219 Detailed 219 Km Completed 400kV D/C Line Survey Foundations 575 Nos. 227 Erection 575 Nos. 59

India Infrastructure Finance Company Limited Page 8

Sl. Name of Length Activities Progress up No. transmission Line (km) to 30.11.10

Stringing 219 Km 0 5 LILO of Lonikhand – 1.2 Detailed 1.2 Km Completed Kalwa 400kV D/C Survey line at Pune Foundations 8 Nos. 4 Erection 8 Nos. 0 Stringing 1.2 Km 0 6 LILO of Solapur- 116 Detailed 116 Km Completed Karad 400kV S/C Survey line at Solapur Foundations 298 Nos. 298 Erection 298 Nos. 298 Stringing 116 Km 115 Total for Project Detailed 1031 .2 Km 1007 Survey Foundation 274 5 Nos. 1441 Erection 274 5 Nos. 553 Stringing 1031 .2 Km 115 Source: Information as received from WRTMPL

2.0 ALTERNATIVE ANALYSIS OF ALIGNMENTS 10. The project transmission line passes through two states namely Maharashtra and Karnataka, covering 10 districts and 345 revenue villages (Annexure 1) . A comprehensive route justification criterion has been followed towards route selection (Annexure-2) . A detailed alternative study of various options has been done before finalization of the alignment. 11. The visiting team held discussions with the site engineers of the Developer, who explained the long and diligent process through which the transmission line alignment is fixed after all necessary measures to minimize impact on habilitations, trees and to reduce inconvenience to the farmers. First the alignment is drawn using topo sheet and then detail alignment is fixed based on field survey, which helps in avoiding impact on villages, forests, any other sensitive zones/ points. The preparatory process starts with OD survey which involves making straight lines on topo sheet (1:50,000); three alternative routes are marked and the best route is chosen based on minimum line length and obstructions. The sensitive spots avoided include National and State Highways, rivers, drainage systems, forests, human settlement, major development works; route lengths are also considered. No human settlement area is being affected due to the project. 3.0 METHODOLOGY

12. Social due diligence for the project was initiated by IIFCL after review of Project Information Memorandum (PIM) to understand the salient features of the project and various social and resettlement concerns. For better understanding, following key social safeguard documents were requested/ received from the Developer, and reviewed by the IIFCL Social Safeguard team, the status of which is given below:

India Infrastructure Finance Company Limited Page 9

Table 3.1: Availability of documents

Sl. No. Key Social Safeguard Availabi lity Remark documents requested Status 1 Social Impact Not An initial social study of the Assessment (SIA) or Available project suggested that no sections of feasibility involuntary resettlement and report containing SA rehabilitations issues are involved in the project. The project alignment has been so selected that it does not pass through any settlement area. No land acquisition issue is involved as part of the project.

2 Resettlement Action Plan Not Since no resettlement impact, Applicable Resettlement Action Plan (RAP) is not required to be prepared for the project.

3 Tribal Development Plan Not The route does not pass through (if Required) Applicable any settlement area. The Developer has also confirmed that no tribal population is found on the corridor till date. Thus no Tribal Development Plan required.

4 Lenders Engineer Terms Available The scope of work of LIE include of Reference – Observe and determine whether the social measures are in place.

13. In absence of any social study report, following relevant documents were collected for assessing likely social risks and impacts of the project in order to prepare the social safeguard DDR:

• Lender’s Independent Engineer’s report, August 2010; and, • Information pertaining to justification of alignment selection; • Information regarding the methodology adopted for crop compensation; • Information regarding formal public consultation and information disclosure that are being adopted. • Consultation with developer

14. Relevant information has also been collected during the Lender’s site visit (including LE meet), from 13 th April – 15 th April 2010, by IIFCL representative. A site visit was jointly conducted by World Bank, IIFCL and project Developer during June 9-10, 2010.

India Infrastructure Finance Company Limited Page 10

4.0 SOCIAL IMPACT STUDY OF THE PROJECT

4.1 Impact on structure 15. The finalization of the design has been done by consideration the route selection criteria (Annexure 2 ) to minimize resettlement impact if any. With the analysis of various alternatives, the final route has such been selected that the transmission lines are not passing through any settlement areas and thus there is no adverse impact on residential; or commercial or any other structures along the proposed alignment. 4.2 Impact on land 16. As per section 164 of The Electricity Act 2003 and Indian Telegraph Act 1885, part III, section 10 to 19, the appropriate Government has the authority to place and maintain transmission lines under, over, along or across and posts in or upon any immovable property. Indian Telegraph Act 1885, Part III, Section 10 (b) prohibits acquisition of any right other than that of use only. Land for towers and right of way is not acquired and agricultural activities are allowed to continue. The developers have received clearance from Ministry of Power under section 68 and section 164 of Electricity Act 2003 which is a mandatory requirement for execution of new transmission lines ( Annexure 3 ). 17. Project does not require any land acquisition for erection of tower under the Telegraph Act. The standard tower base area is of a dimension of 12 m. x 12 m. The flooring of each Stub or leg of the tower has a dimension of 400 mm x 400 mm (approx.). Apart from the land used for tower, a larger periphery of land will be required to be cleared temporarily to carry out the construction activities to erect the tower. The area to be temporarily affected varies for different locations, but on an average 40m x 40m. of land is affected temporarily to carry out the tower erection work. The land is temporarily excavated for the pit area which is then filled back and rehabilitated to allow continuation of normal agricultural activities. Moreover, land would also be affected for creating access roads for bringing in the material and the mobile machinery. 18. The impact on land is therefore temporary and the ownership status of the land remains with the landholder. Since the project does not involve setting up of any new sub-stations, thus no land acquisition is required for the project. 19. The substations for these transmission lines are not a part of this project and as per Implementation Agreement shall be facilitated by Power Grid Corporation of India Limited (PGCIL). PGCIL is an entity which has a corporate level Environment and Social Policy and Procedures (ESPP) endorsed by the World Bank according to which Social Due Diligence for these sub-stations has been conducted by PGCIL (http://www.powergridindia.com/PGCIL_NEW). 4.3 Impact on Indigenous people 20. As per the Census of India 2001 data, the percentage of Schedule Tribe population in the affected districts is very low. Moreover, the criteria followed towards route selection indicate that the proposed route does not pass through any settlement area. And thus it does not disturb any tribal settlement and does not have any adverse impact or create any threat to the survival of any tribal community along the alignment.

4.4 Local employment 21. The project provides limited employment opportunities to the local people during the construction stage, especially with respect to unskilled labor. As informed during the site visit, the nature of work requires specialized skill for the highly technical work such as

India Infrastructure Finance Company Limited Page 11

erecting or stringing. Local people normally do not have such experience. Thus, the contractors working for tower erection have their own gang of skilled labour who are trained in similar activities. As confirmed by the developer, no local labour has been employed for the Maharashtra section. 4.5 Impact on Livelihoods and Crop compensation 22. In total 2748 numbers of towers is being erected under the project. For each tower an average area of 40 m x 40 m land is being temporarily cleared for carrying out the construction activities. Approximately 439.68 Ha of land will be temporarily affected due to the construction activities. Moreover, additional land would also be affected for creating access roads for bringing in the material and the mobile machinery. As per the electrical clearance, if there are losses to the trees on the tower location and as well as on the line corridor, then the trees are to be removed completely below the conductor and / or lopped for the balance corridor area. Any damage for the loss of crops or any other temporary impacts due to the activities involved in tower erection and access roads during the construction stage is mitigated by providing adequate compensation.

23. The crop compensation procedure for the loss of crops is done in three steps. First step: Identification/ measurement of the exact area, extent of crop damaged and the type of the standing crop during execution. Second Step: Finding out the yield of the crop with the help of Agricultural University. In the process of crop damage assessment and calculation of compensation, the Agricultural University also refers to daily market price of the crops as published in the local newspaper. Third step: Calculation of the crops compensation amount is done by using the area, yield and the rate. It can be shown as below,

Crop compensation= Area x Yield x Rate of crop

An example of crop compensation calculation and yield chart is attached as Annexure 4 and Annexure 5 respectively.

24. The compensation for the temporary losses is paid three times during the whole construction stage. At first it is paid during the laying of Foundation of the tower, second time during the tower Erection and lastly during the Stringing stage. As per the 4th Quarterly LIE report of August 2010, the expenditure towards crop compensation till 30.11.2010 is Rs. 3.65 Crores. Refer Annexure 6 for details of the affected landholders and the progress of crop compensation till November 2010.

25. During the site visit, the team interacted with some affected farmers and their families in one village along the transmission alignment and found that compensation was transparently determined and distributed; those doing multiple cropping (the number is very small as these are dry land areas) perceived that the compensation is almost close or equal to their crop loss. However they all verified that all the affected farmers were duly identified and compensated. It was found that farmers those who raise limited or no crop also received minimum compensation, which is generally more than what they lose in terms of crop damage. The visiting team did not notice any opposition to the project and people were found to have been cooperative, and that any grievances regarding entitlement were duly addressed.

India Infrastructure Finance Company Limited Page 12

4.6 Accident Safety (Compensation for Loss of Life or Injury due to the Project)

26. As per Project Information Memorandum, WRTMPL has issued and REL Infra has accepted Letter of Award along with term sheet for the engineering, procurement and construction of the transmission lines under this project. The key terms of the proposed EPC contract entered into between WRTMPL and REL Infra includes that the Contractor shall provide insurance for Worker’s Compensation for any untoward incidents. Moreover, Reliance has Health & Safety policy which gives specific instructions to the contractors regarding the various health and safety issues that has to be taken into consideration during the project implementation stage. 5.0 IMPLEMENTATION ARRANGEMENTS AND PROCESS 27. As per the implementation arrangement, people are informed by a notification published in newspaper about the project and the tentatively affected villages ( Annexure 7). As per the procedure, any individual/ organization can file their observation/ reservation to the authorized executive within 60 days of the notification. After which, a detailed land survey is done after the alignment has been finalized on the revenue map. Based on land records (called 7/12) available with the Tehsildar, plot numbers and their owners are identified. A list of Titleholder is prepared based on the 7/12 records (r efer Annexure 8) and notices ( Annexure 9 ) are served personally to each of the land owner after measurement of the area of crop loss. A copy of the receipted notice is kept as records by the Developer for all future purposes. The rightful owner then submits a copy of its ownership paper which is then confirmed with the Revenue department. Local farmers and representatives from the local government authorities (Sarpanch) are involved in the distribution process by way of identifying the entitled farmer and testifying in case of change in names. 28. The crop compensation amount is estimated by the developer as per the above mentioned crop compensation calculation methodology. Compensation amount is paid by Demand draft/Cheque to the affected landholders by the Developer ( refer Annexure 10 ). The compensation data are maintained and the process of compensation payment is monitored at the site office level by the site engineers. They have no social scientist, but the process is well understood and managed by the site engineers. The grievances, if any, are addressed by senior executives of Developer or Project Incharge.

6.0 COMMUNITY DEVELOPMENT ACTIVITY

29. It was reported that Community welfare activities such as eye camps, blood donation camps etc, is organized by the contractor on ad hoc basis. The details of the same as conducted till the last quarter has been attached as Appendix-11 .

7.0 CONCLUSIONS AND RECOMMENDATIONS

30. The sub-project has been prepared by WRTMPL with adequate social safeguard consideration. Various alternative alignments have been considered as part of the project to minimize the impact on settlements, forests and tribal groups. The selected alignment has been approved by Central Electricity Authority (CEA) and the Developer has already been granted license under sections 14 and 15 of the Electricity Act 2003. The justifications towards route selection indicate that the proposed route of transmission line does not create any threat to the survival of any tribal community.

India Infrastructure Finance Company Limited Page 13

31. No land acquisition is involved in the project. The damage to the crops during the construction stage has been adequately compensated to the landholders. The details of such payments have been provided by the Developer. The checklist briefing the findings of SDD is attached as Annexure 12 . 32. It can be summarized that apart from the loss of crops, the project does not involve any major social safeguard issues. 8.0 PROPOSED MONITORING BY IIFCL 33. IIFCL has taken up the monitoring of various social issues such as crop compensation status and CSR activities undertaken by the Developer and the villages benefitted under such activity. The details of the same are attached as Annexure 6 and 11 . 34. IIFCL shall further undertake site visits to carry out checks and review compliance in terms of distribution of compensation and community development activity undertaken by the developer and shall include such details in the IIFCL’s report to the Bank.

India Infrastructure Finance Company Limited Page 14

ANNEXURE 1 Western Region Transmission (Maharashtra) Pvt. Ltd. List of villages and affected districts

Sl. No. State District Taluk/ Tehsil Village Name 1 Maharashtra Beed, Ambejogai, Kaiij, Pimla 2 Ahmadnagar, Beed, Patoda, Morewadi Pune, Ashti, 3 Aurungabad, Ahmadnagar, Chanai 4 Sholapur, Parner, Shirur, Sanegaon 5 Osmanabad, Ragurunagar Umrai 6 Latur, Sangil, (Khed), Vadgaon Lade Vadgaon Kolhapur (Mawal), Shirur, 7 Lkala Amba Parner, Rahuri, 8 Nevasa, Mulegaon 9 Gangapur, South Chandan Sawargaon 10 Sholapur, Barshi, Kanadi Mali 11 Paranda, Umeri Renapur, Latur, 12 Osmanabad and Kothi 13 Tuljapur, Massa Jog 14 Mangalwedha, Sarola 15 Jath, Jhola Kavathemahanke, 16 Dhawanjewadi Mirajghat, Shirol, 17 Hathakanangale Pandherwadi 18 Chakurwadi 19 Vaitagwadi 20 21 Masewadi 22 Limba Ganesh 23 Saudana 24 Soni 25 Bhayal 26 Sawargaon 27 Balewadi 28 Bensur 29 Tale Pimpalgaon 30 Jakalka 31 Yewlewadi 32 Bhurewadi 33 Sautada 34 Matkuli 35 Pokhri

India Infrastructure Finance Company Limited Page 15

36 Wadgaon 37 Kare Pandhri 38 Hajipur 39 Aashti 40 Bamhagaon 41 Shindewadi 42 Radhapur 43 Jalgaon 44 Chola Nimgaon 45 Kanudi Khura 46 Pimpalgaon 47 Dani 48 Parodi 49 Borodi 50 Mathepimprl 51 Ganwadi 52 Deulgaon 53 Sidhi 54 Ghonsapura 55 Babherwadi 56 Sarasgaon 57 Apdhupa 58 Narayan Ghavhan 59 Jategaon 60 Kandelwadi 61 Annapur 62 Nimgaon Dude 63 Nimgaon Boghi 64 Sone Sanghvi 65 Vaghale 66 Varude 67 Chinchoti 68 Khairwadi 69 Hiware 70 Thidewadi 71 Nimgaon 72 Rethewadi 73 Kharpudi Khuurd 74 Vaki Badrukh 75 Chandus 76 Koregon

India Infrastructure Finance Company Limited Page 16

77 Shelu 78 Warle 79 Shinde 80 Thakuewadi 81 Vasuli 82 Umbre 83 Navlakh 84 Umbre Navlakh 85 Shinde 86 Vasuli 87 Varate 88 Shelu 89 Koregaon 90 chandus 91 Shiroli 92 Waki Badrukh 93 Thakurwadi 94 Kendur 95 Thintewadi 96 Khairnagar 97 Kanhur 98 Lakhewadi 99 Mitgulwadi 100 Maithan 101 Ranadewadi 102 Dongaran 103 Mhase Budrule 104 Gunhore 105 Jarale 106 Nighoj 107 Pimpri Jaisen 108 Wadjhire 109 Jadhavwadi 110 Hatal Khindi 111 Karandi 112 Diksal 113 Jamgaon 114 Shangaon 115 Kallup 116 Wadgaon Anali 117 Milkup

India Infrastructure Finance Company Limited Page 17

118 Bhalwani 119 Bhalwani 120 Nimgaon Ghana 121 Khatgaon takali 122 Hingagaon 123 Bothegaon 124 Nagapur 125 Wadagaon Gupta 126 Pimpalgaon malwa 127 Vilad 128 Dehare 129 Shigave 130 Dhanori 131 Lkhadwa 132 Kukkudmedha 133 Umbrae 134 Pimpil 135 Awachad 136 Brahmini 137 Shilegaon 138 Kendal 139 Khurd 140 Pimpri Walane 141 karajgaon 142 Amalner 143 Banjulwadi 144 Nimbari 145 Tilapur 146 Goigaon 147 Panchegaon 148 Jaygudge Arawadha 149 Belpandhari 150 bel Pimpalgaon 151 Suregaon 152 Mevergaon 153 Bagadi 154 Agarkanadgaon 155 Nababpur 156 Gangapur 157 Sidhapur 158 Ambawnadi

India Infrastructure Finance Company Limited Page 18

159 babargaon 160 Bhangaon 161 Bolegaon 162 Kalegaon 163 Jinlethan 164 Kasoda 165 Jogeshwari 166 Shirpunj 167 Ranjangaon 168 Limbdi Chincholi 169 Rampur 170 Wudgain 171 Kardehalli 172 Dhotri 173 Darshanhalli 174 Sangdari 175 Bormani 176 Tandulwadi 177 Kasari 178 Mizanpur 179 Raulgaon 180 Bhalgaon 181 Ambergaon 182 Hatji 183 Malegaon 184 ratanjan 185 Ladole 186 Bhanegaon 187 Sakat 188 Pimpri 189 Panegaon 190 Kalambwadi 191 Dadshinge 192 Kavhe 193 Kasarwadi 194 Khandawi 195 Uplai 196 Khadaki 197 Dhotri 198 Katgaon 199 Pimpla Badrukh

India Infrastructure Finance Company Limited Page 19

200 Devkurali 201 Pimpla Khurd 202 Godhalwadi 203 Malumba 204 Masala 205 Pangdharwadi 206 Pimplawadi 207 Saranwadi 208 Brahmagaon 209 Wasgaon 210 Rui 211 Asu 212 Bavachi Pimpla 213 Magarwadi 214 Dastagirwadi 215 Pokhri 216 Selu 217 Saigan 218 Daitna 219 Mulegaon 220 Akola 221 Morwad 222 Chategaon 223 Motgaon 224 Wagandari 225 Panjakheda 226 Gandwad 227 Pimpri Amba 228 Shirala 229 Bhorgaon 230 Nivali 231 Kond 232 Kondwadi 233 Nitil 234 Ghugi 235 Lasona 236 Kanegaon 237 Samudrawani 238 Borgaon 239 Bombli 240 Vittalwadi

India Infrastructure Finance Company Limited Page 20

241 Umergaon 242 Baramgaon 243 Bamani 244 Bamniwadi 245 Khandala 246 Karala 247 Halora 248 Barul 249 Tirth (Budruk) 250 Devsingha 251 Bijanwadi 252 Arati (Hurd) 253 Arali (Budruk) 254 Yevata 255 Kalegaon 256 Dindegaon 257 Khanapur 258 Tandulwadi 259 Musti 260 Sangdari 261 Dhotri 262 Wadgaon 263 Rampur 264 Dindur 265 Limbi 266 Chincholi 267 Limbi Chincholi 268 Hanamgaon 269 Shinadgaon 270 Achegaon 271 Auj 272 Nilehal 273 Alergaon 274 Ratnapur 275 Aherwadi 276 Bankalgi 277 Badalagi 278 Sanjwad 279 Chincholi 280 Auradh 281 Nandani

India Infrastructure Finance Company Limited Page 21

282 Malkavathe 283 Kurghot 284 Takali Chinchpur 285 Karkal 286 Lavangi 287 Soddi 288 Shivangi 289 Sagar Budrukh 290 Lavangi 291 Maroli Nigadi Khurd 292 Bobald 293 Lakdewadi 294 Tonewadi 295 Sanwadi 296 Nurale 297 Wayphal 298 Nigadi Khurd 299 Gholeshwar 300 Achkanhalli 301 Revnal 302 Tipehalli 303 Birnal 304 Bagewadi 305 Kanthi 306 Baj 307 Belunki 308 Basappachiwadi 309 Ranjani 310 Shinganapur 311 Dhulagaon 312 Lonarwadi 313 Sarathi 314 Kuktoli 315 Kongnail 316 Kadamwadi 317 Belanki 318 Payappachiwadi 319 Shipur 320 Eerandali 321 Bolwad 322 Bedag

India Infrastructure Finance Company Limited Page 22

323 Mirajghat 324 Dharati 325 Arjunwad 326 Ghalwad 327 Malwadi 328 Bhanguti 329 Nandani 330 Janbali 331 Haroli 332 Yadrav 333 Takwade 334 Shiradwad 335 Rangoli 336 Hupari 337 Talandage Umbre 338 Navlakh 339 Karnataka Bijapur Indi Takli 340 Umrani 341 Hattali 342 Nivaragi 343 Havinal 344 Hathalli 345 Chadchan

India Infrastructure Finance Company Limited Page 23

ANNEXURE 2

India Infrastructure Finance Company Limited Page 24

India Infrastructure Finance Company Limited Page 25

ANNEXURE 3

India Infrastructure Finance Company Limited Page 26

India Infrastructure Finance Company Limited Page 27

India Infrastructure Finance Company Limited Page 28

India Infrastructure Finance Company Limited Page 29

ANNEXURE 4

India Infrastructure Finance Company Limited Page 30

ANNEXURE 5

India Infrastructure Finance Company Limited Page 31

ANNEXURE 6

WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED

Crop compensation details till November 2010

S.No. T/Line Description No. of Cases Amount in Rs.

1 Solapur - Karad (LILO) 16,693,872 1628 2 Parli - Pune 7,843,121 732 3 Pune - Aurangabad 7,820,511 444 4 Solapur - Parli 1,402,744 130 5 Solapur - Kolhapur 2,764,511 254 Sub Total 36,524,759 3188

India Infrastructure Finance Company Limited Page 32

ANNEXURE 7

India Infrastructure Finance Company Limited Page 33

India Infrastructure Finance Company Limited Page 34

India Infrastructure Finance Company Limited Page 35

ANNEXURE 8

India Infrastructure Finance Company Limited Page 36

ANNEXURE 9

India Infrastructure Finance Company Limited Page 37

ANNEXURE 10

India Infrastructure Finance Company Limited Page 38

ANNEXURE 11

WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED

Community Development Activity details for the period of April 10 to June 2010

Type of Date of the Budget Community Number of Project section programme/ allocated (in Development villages benefited activity Rs.) Activity Purchase of two oxen for a WRTM Ambajogai Office 1 8th April 2010 Rs. 10,000/- physically challenged farmer WRTM Pune Office at Free for all 5 23 rd April 2010 Rs. 1,50,000/- ‘Kiwale’ Village ‘Medical Camp’ Throughout the WRTM Blood Donation - - year

India Infrastructure Finance Company Limited Page 39

ANNEXURE 12 Findings of Social Due Diligence

The below table briefs the findings of the Due Diligence and the remarks by IIFCL.

Sl. Social Safe Findings Remark No. Guard Issues 1. Impact Various alternative alignments have Justification towards route Minimization been considered as part of the selection indicates that utmost Measures project. The selected alignment has care is taken to avoid congested been approved by Central Electricity inhabitant areas, villages and Authority (CEA). towns wherever possible at the time of route alignment. 2. Census and No such survey has been carried out Since no resettlement issues are Socio- involved therefore such surveys Economic are not envisaged as part of the Survey project. 3. Land No land acquisition for the project. Adequate compensation is Acquisition Land is used only during the being provided for the loss of Plan construction stage and the crops and any other temporary ownership of the land remains with losses. the landholders.

4. Entitlement The Calculation of the crop The methodology of crop Matrix compensation amount is done by compensation is well in place using the area, yield and the rate. and a sample document showing a few cases of crop The yield of the crop is decided with compensation calculation is the help of Agricultural University. attached as Annexure 4 and 5. In the process of crop damage assessment and calculation of compensation, the Agricultural University also refers to daily market price of the crops as published in the local newspaper.

5. Public As part of obtaining authorization People have been adequately consultation for the selected alignment from notified through paper and disclosure Ministry of Power under section 164 advertisement. No public of the Electricity Act 2003 and observation/reservation on obtaining license under sections 14 project scheme was received and 15 of Electricity Act, 2003, within a notice period of two these processes have already been months. The relevant document carried out. towards the public notification and information disclosure is

India Infrastructure Finance Company Limited Page 40

enclosed in Annexure -7.

6. Impact on The proposed alignment passes As informed by the Developer, tribal people mainly through villages and semi- no tribal population is found on urban to urban limits. The the corridor till date. IIFCL has justification towards route selection advised the Developer to adopt (refer Annexure-2) indicate that the appropriate mechanism to proposed route of transmission line minimize the inconvenience to does not create any threat to the the Schedule Tribe people if survival of any tribal community. any.

7. Alternative No resettlement is involved as part No structure will be affected as resettlement of the project. part of the project and hence sites alternative resettlement is not required.

8. Socio- Adequate compensation is being economic provided for any damage to crops rehabilitation and any other temporary losses. measures

9. Implementation There is project implementation The grievances, if any, are Arrangement arrangement. WRTMPL is addressed by senior executives responsible for : of Developer or Project - Crop Compensation Incharge. - Reporting and mitigating the complaints received for the crop loss and any other temporary losses. - Right of Way

10. Corporate Apart from compensating the Social affected people with adequate responsibility compensation, Developer is also (CSR) engaged in various CSR activities activities which are solely done for the community development. In this respect, the Developer has been organizing free Eye check-up camps for the local people.

India Infrastructure Finance Company Limited Page 41