STORM WATER DRAINS on SEASIDE ECR After NGT ORDER Dt 27Th Oct 2020, GCC Started Construction of SWD in These Areas: • 30Th Oct 2020 :Dr
Total Page:16
File Type:pdf, Size:1020Kb
STORM WATER DRAINS ON SEASIDE ECR After NGT ORDER Dt 27th Oct 2020, GCC started construction of SWD in these areas: • 30th Oct 2020 :Dr. Rajan Gardens, Uthandi. • 2nd-4th Nov 2020: Rajiv Avenue , Injambakkam. • 6th Nov 2020: Karl Marx Road, Uthandi. • 6th Nov 2020: Juhu Beach, Uthandi • 16th Nov 2020: Sea Shore Town, Pannayur • 16th -17th Nov 2020: VGP layout , Injambakkam • 16th Nov 2020 : VGP layout , Phase 1,Uthandi • 16th Nov 2020: Palkalai Nagar, Palavakkam • 17th Nov 2020: Juhu Beach, Uthandi • 19th Nov 2020: Blue Beach Road, Neelangarai. • 19th Nov 2020: Nainarkuppam,Uthandi. • 20th Nov 2020: Copper Beach , Panaiyur • 30th Nov 2020: Nainarkuppam, Uthandi • 1st Dec 2020: Jagjivan Ram Avenue, Injambakkam Work stopped at all placed because of people protest and local communities like Neelangarai Kuppam,Pannaiyur Kuppam, Rajiv Gandhi Nagar and Chinandikuppam. IMD data of rainfall on November 26th, 2020 Rainfall recorded at Sholinganallur : 22 cm 24th to 26th NOV. 2020 CYCLONE NIVAR BROUGHT HEAVY RAINFALL TO SEA SIDE ECR. ALL AREAS WELL DRAINED EXCEPT WHERE SWD WAS CONSTRUCTED Blue Beach Road, Neelankarai VGP Layout Phase 1 - Uthandi Karl Marx Road - Uthandi Marakayar Nagar, 1st and 2nd Street, Neelankarai VGP Layout Phase 1 - Uthandi Karl Marx Road - Uthandi Marakayar Nagar, 3rd and 4th Street, Neelankarai VGP Layout Phase 1 - Uthandi Karl Marx Road - Uthandi Marakayar Nagar, 5th and 6th Street, Neelankarai VGP Layout Phase 1 - Uthandi Karl Marx Road - Uthandi Marakayar Nagar, 7thStreet, Neelankarai VGP Layout Phase 1 - Uthandi Bharathi Avenue, Injambakkam Seshadri Avenue, Injambakkam Karl Marx Road, Uthandi, November 26, 2020 7.00 am Swastik Avenue, Injambakkam Raja Nagar, 1st and 2nd Main Road, Neelankarai VGP Layout Phase 1 - Uthandi Karl Marx Road - Uthandi Raja Nagar, 1st Cross Street, Neelankarai VGP Layout Phase 1 - Uthandi Karl Marx Road - Uthandi Copper Beach, Pannaiyur, November 26, 2020 VGP Layout Phase 1 - Uthandi Karl Marx Road - Uthandi VGP Layout 3rd Avenue, Injambakkam, November 26, 2020 VGP Layout Phase 1 - Uthandi Karl Marx Road - Uthandi Seashore Town 5th and 6th Avenue, Panaiyur, November 26, 2020 VGP Layout Phase 1 - Uthandi Karl Marx Road - Uthandi Seashore Town 2nd and 11th Avenue, Panaiyur, November 26, 2020 VGP Layout Phase 1 - Uthandi Karl Marx Road - Uthandi Sea Cliff, Akkarai, November 26, 2020 VGP Layout Phase 1 - UthandiWater logging Karl Marx due Roadto - Uthandi SWD Juhu Beach, Uthandi, November 26, 2020 VGP Layout Phase 1 - UthandiWater logging Karl Marx due Roadto - Uthandi SWD Juhu Beach, Uthandi, November 26, 2020 Water logging due to SWD Juhu Beach, Uthandi, November 26, 2020 – flooding due to SWD construction near the beach VGP Layout Phase 1 - UthandiWater logging Karl Marx due Roadto - Uthandi SWD VGP Layout Phase 1 – 3rd Main Road, Uthandi, November 26, 2020 VGP Layout Phase 1 - UthandiWater logging Karl Marx due Roadto - Uthandi SWD VGP Layout Phase 1 – 2nd Main Road, Uthandi, November 26 and 27, 2020 This is theVGP lowest Layout point Phase in 1the - Uthandi layout and flows to the WaterPhotograph logging Karl onMarx due the Roadto 27th November- Uthandi with water sea. Obstruction by encroached compound wall and SWDCompletely drained filling of sand to raise level is preventing natural flow of water Rajiv Avenue, Injambakkam, November 26, 2020 VGP Layout Phase 1 - UthandiWater logging Karl Marx due Roadto - Uthandi SWD VGP Layout Phase 1, Uthandi, December 02, 2020 VGP Layout Phase 1 - UthandiWater logging Karl Marx due Roadto - Uthandi SWD VGP Layout Phase 1, Uthandi, December 02, 2020 VGP Layout Phase 1 - UthandiWater logging Karl Marx due Roadto - Uthandi SWD VRS Salai, Uthandi, December 02, 2020 Juhu Beach, Uthandi, December 02, 2020 Palkalai Nagar, Pallavakkam, December 02, 2020 7.00 am WATER STAGNATION IN FEW LOW LYING AREAS OR DUE TO BEACH ROADS OR ENCROACHMENTS DO NOT NEED FOUR SIDED BOX CONCRETE DRAINS SUSTAINABLE URBAN DRAINAGE IS THE SOLUTION GCC New Systems in SWD Project to Recharge Groundwater PVC Pipe installed at bottom slab of SWD to drain water. Not recharging water GCC New Systems in SWD Project to Recharge Groundwater Silt catch pit with RWH VGP Layout Phase 1 - UthandiWater logging Karl Marx due Roadto - Uthandi SWD Eco blocks at the end of SWD. Not required in sandy soil Times of India, December 02, 2020 Dinamalar, December 1, 2020.