NGT WORKS District as on 8/3/21 Funding Expected date Progress Project Work Sl No. Project Name Executing Office AS Amount [Rs] AS Date TS Date Agency of completion Percentage Status State Plan- 2018-19 - TSS -Construction of RCC manholes at various 1 places under Sewerage Section II, Kuriathy GOK Sewerage Dn 2400000. 20-08-2018 27-08-2019 100 Completed State Plan- 30-2018-19- TSS - Rehabilitation of sewer main - Supplying and laying sewer line and Manholes from Karamana Jn to Karamana LP 2 School of Thalial Road GOK Sewerage Dn 4200000. 20-08-2018 21-02-2019 100 Completed State Plan 30- 2018-19- TSS- Raising of manhole covers under tarred surface and replacement of damaged concrete slabs with CI covers 3 under Sewerage Section Sasthamangalam. GOK Sewerage Dn 2500000. 20-08-2018 04-11-2018 100 Completed

State Plan 30- 2018-19- TSS- Rehabilitation and extension of sewer line 4 in Easwara Vilasom Residence Association (EVRS306-310, 407-410) GOK Sewerage Dn 900000. 20-08-2018 04-11-2018 100 Completed

State Plan 2017-18 : Increasing the capacity of 100mm Sw pipe to 5 150mm and constructing RCC manholes at Champakkada NPP lane GOK Sewerage Dn 500000. 05-10-2017 08-02-2018 100 Completed State plan 2017-18- Interconnecting and Laying 150mm SW pipe at Ashramom lane, Sasthamangalam, Under sewerage section 6 Sasthamangalam. GOK Sewerage Dn 437000. 05-10-2017 20-11-2018 100 Completed State Plan -2017-18- T S S - Replacement of existing 150mm SW line with 200mm Sw pipe and reconstruction of manholes(8Nos) for a length 7 of 250M in Hari Nagar,Marappalam -Muttada -TKD road. GOK Sewerage Dn 2160000. 05-10-2017 08-02-2018 100 Completed State Plan 2017-18Renovation of Grit chamber and well at 8 Mudavanmughal GOK Sewerage Dn 760000. 05-10-2017 15-02-2018 100 Completed Plan-30-2017-18-Re-constructing damaged brick manholes with RCC manholes at Ambalamukku- area under sewerage section, 9 . GOK Sewerage Dn 840000. 05-10-2017 100 Completed Plan-30-2017-18-Re-constructing damaged brick manholes with RCC manholes at Jawahar Nagar and Vellayambalam area under sewerage 10 section, Sathamangalam. GOK Sewerage Dn 963000. 05-10-2017 100 Completed Plan-30-2017-18-Raising of manholes and MH covers under section 11 No.II, Kuriathy GOK Sewerage Dn 2000000. 05-10-2017 100 Completed Plan -30-2017-18-Reconstructing damaged brick manholes with RCC manholes at Lenin Nagar in West RC area under sewerage section 12 sasthamangalam GOK Sewerage Dn 918000. 05-10-2017 100 Completed

TSS-Block J -Supplying and laying,joining Testing and comissioning of 450mm DIK9 Pumping main from Akkulam pumping station to Pulayanarkotta and alled works chamberSupplying and laying,joining Testing and comissioning of 450mm DIK9 Pumping main from Akkulam 13 pumping station to Pulayanarkotta and alled works chamber AMRUT Project Division 22800000. 02-11-2017 14-02-2018 100 Completed AMRUT- Supplying and laying 350mm DI K9 pumping main from Karimanal pumping station to stilling chamber at Bypass junction Block J 14 Kuzhivila AMRUT Project Division 13000000. 02-11-2017 20-03-2018 100 Completed MLA-SDF-2018-19-Vattiyoorkavu LAC- TSS- Rehabilitation of sewer line 15 from Kairali Lane towards MRA138 at Moolavilakom Jn in Pattoor GOK Sewerage Dn 230000. 26-11-2018 27-08-2019 19-01-2021 0 Ongoing State Plan 2018 - 2019 TSS Plan - 30 - Construction of well and Grit Chamber with Supplying and Installing 3 No's submersible Pump set etc. 16 at Thaliyal Pump House. GOK Sewerage Dn 16000000. 06-02-2019 27-07-2019 09-04-2020 87 Ongoing State Plan 2018 - 2019 TSS Rehabilitation of Collection Well and Pump House, Providing 3 No's of Wet Well non clog Submersible Pump set at 17 Aranoor Pump House GOK Sewerage Dn 7700000. 06-02-2019 22-08-2019 21-05-2020 37 Ongoing

18 State Plan:2018-19 - TSS- Rehabilitation of sewer line at Sridevi Nagar GOK Sewerage Dn 2900000. 06-02-2019 27-08-2019 0 Ongoing

19 State Plan 2018-19 - TSS - Supply of new pump sets at Mudavanmughal GOK Sewerage Dn 1300000. 06-02-2019 03-05-2019 25-02-2021 42 Ongoing 20 State Plan- 2018-19 - TSS - Supply of new pump sets at Enchakkal GOK Sewerage Dn 1000000. 06-02-2019 11-06-2019 25-02-2021 80 Ongoing State Plan 30 - 2018-19 - TSS- Rehabilitation of Exisitng Sewerline near 21 Thaliyal Pump house to avoid sewage overflow to Killi river GOK Sewerage Dn 10300000. 06-02-2019 03-01-2021 0 Ongoing

State Plan 2017-18: Rehabilitation of sewer line at Palace view lane and reconstruction of damaged manholes and raising manholes in 22 Mudavanmugal, Poojapura area GOK Sewerage Dn 2000000. 26-03-2018 30-10-2019 18-11-2021 12 Ongoing State Plan 2017-18 : TSS - Rehabilitation of damaged 400mm sewer line and reconstruction of dilapidated manhole in the sewer line between 23 Thakaraparampu Malloor road GOK Sewerage Dn 1900000. 26-03-2018 20-09-2020 31-05-2021 0 Ongoing Plan 30 - 2017 -18 TSS-D Block Zone II- Laying 700 mm dia RCC NP3 pipe sewer Trunk main II from Murinjapalam towards Kannammoola Ch. 24 342 M to 952 M GOK Sewerage Dn 29100000. 26-03-2018 0 Ongoing State Plan 2019 - 2020 TSS - Supplying and Installation of Diesel Genarators for Sewerage Pump Houses at 25 Pattoor,Plamoodu,Murinjapalam & Kannammoola. GOK Sewerage Dn 5600000. 14-06-2019 12-11-2019 04-02-2021 63 Ongoing

State Plan 2019-20: Supplying and installation of Diesel generators for 26 Sewage Pump Houses at Kuriathy, Mudavanmugal GOK Sewerage Dn 3000000. 14-06-2019 23-11-2019 25-09-2021 80 Ongoing PLAN 30- 2018-19- TSS- Rehabilitation of sewer line in Nandavanam to 27 Paris lane road, Bodheswaran Road and Link Road GOK Sewerage Dn 4867000. 20-08-2018 0 Ongoing State Plan 2017-18 : Reconstruction of damaged MH and sewer lines in 28 Enchackal - Pettah Aksharaveedi area GOK Sewerage Dn 800000. 05-10-2017 24-02-2020 18-03-2021 0 Ongoing State Plan 2017 18 Reconstructing damaged brick manholes with RCC manholes at Kannamoola in West RC area under sewerage section 29 sasthamangalam GOK Sewerage Dn 900000. 05-10-2017 26-10-2020 16-04-2021 53 Ongoing Plan-30-2017-18-TSS- E Block Zone II - Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole ch 512m to 30 785m GOK Sewerage Dn 19000000. 05-10-2017 0 Ongoing Plan-30-2017-18-TSS- Zone II- Laying 600 mm dia RCC NP3 pipe sewer main towards Edappazhanji Chithranagar(IV-Reach) Ch. 2738 to 2908 M 31 in connection with the commissioning of Jagathy - Koottamvila scheme GOK Sewerage Dn 14250000. 05-10-2017 0 Ongoing Plan-30-2017-18-TSS- E Block Zone II -Inter connection of 700mm dia CI pipe between Jagathy Chadiyara sewer main and parallel main across Killi river and constructing 450 mm dia bored cast in situ piles inside of 32 river and connected works.Ch.649M to 679M GOK Sewerage Dn 4000000. 05-10-2017 0 Ongoing Plan-30-2020-21-TSS-Laying of 400mm RCC pipe line instead of damaged existing sewer line in KSRTC Bus terminal, Thampanoor under Sewerage Section II, Kuriathy (already arranged due to NGT priority 33 work) GOK Sewerage Dn 3764000. 08-10-2020 17-03-2020 19-03-2021 10 Ongoing State Plan - 2016-17- T S S - Construction of Manholes and laying 150 mm SW sewer line from Pattom Marapalam Road near Balasubramaniya 34 temple lane,Iswarya lane and Bund road GOK Sewerage Dn 2105000. 16-11-2016 20-10-2018 07-12-2019 0 Ongoing State Plan 2017-18: Procurement of sewer cleaning machines and safety equipments for sewer maintenanace (Auto mounted desilting machine- 3no,medium vehicle mounted high pressure jetting machine-2No, heavy vehicle mounted high pressure jetting cum sucking machine 1No, vacuum operated suction machine-1No, self priming potable diesel dewatering pump set 4No, safety equipments for labourers-15set, other 35 safety equipments-9set. GOK Sewerage Dn 31700000. 20-12-2017 25-09-2020 0 Ongoing

AMRUT-Project 2015-16-Design,construction and commissioning of 5 36 MLD sewage treatment plant (STP) at Medical College , TVM AMRUT Project Division 191600000. 23-02-2017 25-09-2018 30-04-2021 81 Ongoing AMRUT – TSS – Design, Construction, Commissioning & Maintenance of 37 Pumping Station and Allied Works at Edathara AMRUT Project Division 82100000. 23-02-2017 17-09-2018 31-12-2021 1 Ongoing

AMRUT-Projects 2015-2016, Improvements to TSS -Supply and laying 38 600 mm pumping main from Edathara pumphouse to STP Muttathara AMRUT Project Division 172900000. 23-02-2017 16-12-2017 31-03-2021 50 Ongoing AMRUT -Providing Sewer trunk from Kazhakoottam area toPumping station of I Block through the bank ofThettiyar Thodu - Collection and Conveyance system. and pumping station, pumps and 39 electricalinstallation, Pumping mains (Block I)-(4 packages) AMRUT Project Division 105600000. 02-11-2017 06-03-2018 30-09-2021 25 Ongoing

AMRUT TSS- Laying Transmission main and sewer networks in Block J 40 (Karimanal) Collection and Conveyance system- ( 3 packages) AMRUT Project Division 150200000. 23-10-2017 26-03-2018 31-08-2021 11 Ongoing 41 Construction of Pumping station at Karimanal ( Block J) AMRUT Project Division 40000000. 02-11-2017 22-03-2018 31-05-2021 47 Ongoing Supplying and erection of pumpsets , transformers and electrical 42 accessories in the Block L Edathara Pumping Station AMRUT Project Division 40000000. 02-11-2017 28-05-2019 0 Tendered Supplying and erection of pumpsets ,transformer and electrical 43 accessories in the Akkulam Pumping station Block K AMRUT Project Division 18000000. 02-11-2017 21-08-2019 0 Estimate recasted Supplying & laying Transmission block K( Akkulam) to connect stilling chamber at By pass junction to pumping station at Akkulam-Collection and conveyance system supplaying laying testing and commissioning of 710 mm &630 mm dia HDPE sewer line through Akkulam bypass road from Kuzhivilla stilling chamber to Pumping station at Akkulam by HDD 44 method AMRUT Project Division 70000000. 02-11-2017 26-03-2018 31-03-2021 37 Ongoing 45 Laying transmission main and sewer networks in L block (Edathara) AMRUT Project Division 299400000. 02-11-2017 16-06-2018 31-05-2021 11 Ongoing TSS Design Construction Commissioning & Maintenance of pumping station and allied works at Akkulam-well cum pump house manhole 46 laying pipe for interconnection work etc AMRUT Project Division 40000000. 02-11-2017 27-02-2018 31-05-2021 22 Ongoing AMRUT TSS -Supplying and erection of pumpsets, Transformer and 47 electrical accessories in the karimanal pumping station ( Block J) AMRUT Project Division 15000000. 02-11-2017 09-08-2019 31-08-2021 0 Retendered