ROAD TRAFFIC REGULATION ACT 1984 - SECTION 14(1) (LOCK’S LANE, ROAD AND ROAD) (TEMPORARY RESTRICTION OF TRAFFIC) ORDER 2019

1. The Council hereby give notice that to facilitate a programme of carriageway resurfacing to be undertaken in Lock’s Lane, London Road and Streatham Road, they have made an Order, the effect of which will be to temporarily restrict vehicular traffic in those roads and in Eveline Road, Graham Avenue, Graham Road and Lavender Avenue.

2. During the works, no person will cause or permit any vehicle to:- (a) enter, proceed in, or wait in any of the roads or lengths of roads specified in column 1 of Schedule 1 to this Notice; (b) turn left into Graham Road from Streatham Road during Phases 1 or 3 of the works; (c) turn right into Graham Road from Streatham Road during Phases 1 or 3 of the works; (d) turn left in Lock’s Lane from Streatham Road during Phases 1 or 2 of the works; (e) turn right into Lock’s Lane from London Road during Phases 1 or 2 of the works; (f) access Eveline Road or Lavender Avenue from London Road or vice –versa during Phase 4 of the works; (g) access Graham Road or Graham Avenue from Streatham Road or vice-versa during Phases 1A or 3A of the works; (h) access Lavender Avenue from London Road or vice-versa during Phase 3 of the works.

3. During Phase 4 of the works:- (a) the one-way working in Eveline Road will be suspended and two-way working will be permitted, no access from London Road; (b) waiting and parking will be prohibited in the lengths of Eveline Road specified in Schedule 2 to this notice.

4. Any designated parking place situated in any of the roads or lengths of roads specified in column 1 of Schedule 1 to this Notice will be suspended for the duration of the works in those roads or lengths of roads.

5. Alternative routes for diverted traffic will be indicated by advance warning and diversion signs on the roads affected when the works are in progress but will likely be those diversion routes specified in column 2 of Schedule 1 to this Notice.

6. The restrictions will apply only during such times and to such extent as will from time to time be indicated by traffic signs prescribed by the Traffic Signs Regulations and General Directions 2016.

7. Any vehicle that is in contravention of any waiting restrictions imposed by the Order may be removed under the provisions of the Removal and Disposal of Vehicles Regulations 1986.

8. Nothing in the Order will apply to: - (a) any vehicle being used in connection with the execution of the said works or any public service or utility vehicle; or (b) anything done with the permission or at the direction of a police officer in uniform or police community support officer in uniform; or (c) emergency service vehicles, subject to site conditions at the time of any emergency.

9. Nothing in sub-paragraph 2(a) above will apply to any person requiring vehicular access to properties adjacent to the prohibited roads or lengths of roads insofar as access is reasonably practicable without interference with the said works.

10. The Order will come into force on Monday 2nd December 2019 and the anticipated works dates and times are specified in Schedule 1 to this Notice. However, the Order will remain in operation for a maximum period of 18 months and its provisions will be re-introduced during those 18 months should further works be required.

Dated: 19 November 2019.

Paul McGarry Head of futureMerton London Borough of Merton Merton Civic Centre London Road SM4 5DX

SCHEDULE 1 ROAD CLOSURES FOR CARRIAGEWAY RESURFACING WORKS

Length of Road Closure Diversion Route Anticipated Times of Works 1. 2. 3. PHASE 1 Four way traffic lights will be in operation. 9pm on Monday Streatham Road, the south-westbound Diversion 1. Via Road, Grove Road, Tamworth 2nd December lane(s) between a point 25 metres north-east Lane, Cedars Avenue, Commonside West, Upper Green 2019 until 4am the of the north-eastern kerb-line of Graham East, London Road, Raleigh Gardens, Way and following day. Road and its junction with London Road. London Road. Lock’s Lane, between its junction with Diversion 2. Via London Road, Holborn Way, Upper London Road and a point 10 metres south- Green West, Commonside East, Cedars Avenue, east of its junction with Proctor Close. Tamworth Lane, Grove Road and Eastfields Road. London Road, the south-westbound lane(s), Diversion 3. Graham Road access via Graham Avenue from its junction with Streatham Road to a and Fernlea Road. point 20 metres south of its junction with Diversion 4. Via Streatham Road, Southcroft Road, Lock’s Lane. Road and London Road. PHASE 2 Four way traffic lights will be in operation. 9pm on Tuesday Streatham Road, the south-westbound Diversion 1. Via Eastfields Road, Grove Road, Tamworth 3rd December lane(s) between the south-western kerb-line Lane, Cedars Avenue, Commonside West, Upper Green 2019 until 4am the of Graham Road and its junction with London East, London Road, Raleigh Gardens, Holborn Way and following day. Road. London Road. Lock’s Lane, between its junction with Diversion 2. Via London Road, Holborn Way, Upper London Road and a point 10 metres south- Green West, Commonside East, Cedars Avenue, east of its junction with Proctor Close. Tamworth Lane, Grove Road and Eastfields Road. London Road, the south-westbound lane(s), Diversion 3. Via Streatham Road, Southcroft Road, from its junction with Streatham Road to the Mitcham Road and London Road. south-western kerb-line of Bond Road. PHASE 3 Four way traffic lights will be in operation. 9pm on Thursday London Road, the southbound lane Diversion 1. (No access to London Road from Lavender 5th December between the northern kerb-line of Lavender Avenue) Via Western Road, Holborn Way and London 2019 until 4am the Avenue and the south-westbound lane of Road following day. Streatham Road Diversion 2. (No access to Lavender Avenue from Streatham Road, between the north-eastern London Road) Via London Road, Longley Road, kerb-line of Graham Road and its junction High Street, High Street , Christchurch with London Road Road and Western Road Lavender Avenue, from its junction with Diversion 3. Graham Road access via Graham Avenue London Road westward for ten metres. and Fernlea Road. PHASE 4 Four way traffic lights will be in operation. 9pm on London Road, the northbound lane(s) Diversion 1. (No access to London Road from Eveline Wednesday 4th between its junction with Bond Road and the Road or Lavender Avenue) Via Western Road, Holborn December 2019 northern kerb-line of Lavender Avenue. Way and London Road until 4am the Diversion 2. (No access to Eveline Road or Lavender following day. Avenue from London Road) Via London Road, Longley Road, Tooting High Street, High Street Colliers Wood, Christchurch Road and Western Road. PHASE 3A Two way traffic lights will operate on Streatham Road 9pm on Monday Streatham Road, the north-eastbound lane, Diversion (No access to Graham Road or Graham 9th December between Graham Road and the common Avenue from Streatham Road and vice-versa) Via Sandy 2019 until 4am the boundary of Nos. 43 and 45 Streatham Lane and Fernlea Road. following day. Road. PHASE 1A Two way traffic lights will operate on Streatham Road 9pm on Tuesday Streatham Road, the south-westbound lane, Diversion (No access to Graham Road or Graham 10th December between Graham Road and the common Avenue from Streatham Road and vice-versa) Via Sandy 2019 until 4am the boundary of Nos. 43 and 45 Streatham Lane and Fernlea Road. following day. Road. PHASE 5 Diversion via Streatham Road, Southcroft Road, Mitcham 9pm on London Road, full width of road between its Road and London Road. Wednesday 11th junction with Lavender Avenue and its December 2019 junction with Victoria Road. until 4am the following day.

SCHEDULE 2 Eveline Road, (a) the north side, (i) from its junction with London Road westward for a distance of 125 metres; (ii) from its junction with Mortimer Road eastward to a point opposite the western kerb-line of Plummer Lane; (b) the south side, from a point 125 metres west of its junction with London Road westward for a distance of 95 metres.