LAND SURVEYORS APPENDIX 1 DETAILS OF PROFESSIONAL EXPERIENCE NAME OF APPLICANT : MUGALU GERALD NAME OF SUPERVISOR : ASIIMWE DENIS No. Project Title and Period on the Location within Brief of key Supervisors Description project country assignment on the project 1. Sub division of plot 303 block 80 kyadondo September, Wakiso The major RSU 2018 assignments in this Asiimwe project were; - Denis -Verify an acre that (Surveycom was subdivided if Surveyors) the area was correct

-to open boundaries and identify the corner mark stones -to plant new mark stones as per the kibanja of the client and locate its position within Plot 267 -to prepare a job record jacket (JRJ) for purposes of acquiring deed prints 2. Subdivision of Plot 1637 Block 78 kyadondo September, Wakiso The major RSU 2018 assignments in this Asiimwe project were;- Denis -to open boundaries (Surveycom and identify the Surveyors) corner mark stones -to subdivide off one plot -to prepare a job record jacket (JRJ) for purposes of acquiring deed prints 3. Topographic survey of Plot 2350 Busiro Block 489 August, 2018 Wakiso The major RSU at Mpumudde, Wakiso assignments I Asiimwe performed on this Denis project were;- (Surveycom -to open boundaries Surveyors)) of the Plot such that I pick all the necessary details within it -to carry out a topographic survey -to determine the highest and lowest point on the site -to produce a topographic map

4. Sub division of plot 26 block 224-02 busiro October, 2018 Wakiso The major RSU 2/10/2018 assignments on this Asiimwe project were: Denis -to retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing mark stones on the subject plot. -to subdivide plot 26 into four Plots measuring one acre each -to prepare detailed a CAD drawing -to prepare a Job Record Jacket for purposes of processing deed prints. 5. Sub division of plot 99 block 294 busiro October,2018 Wakiso The major RSU assignments on this Asiimwe project were: Denis -to retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing mark stones on the subject plot. -to subdivide off one plot -to prepare detailed a CAD drawing -to prepare a Job Record Jacket -to process deed prints and Certificate of Titles 6. Sub division of plot 658 block 119 Mawokota January, 2018 Mpigi The major RSU assignments on this Asiimwe project were: Denis -to retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing mark stones on the subject plot. -to subdivide of 0.90 acres -to prepare detailed a CAD drawing -to prepare a Job Record Jacket 7. Sub division of plot 1263 block 224 kyaggwe under June, 2018 Mukono The major RSU I/S MA/Y/1/1046 at Nazigo assignments on this Asiimwe project were: Denis -to retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing mark stones on the subject plot. -to subdivide off two plots. -to prepare detailed a CAD drawing -to prepare a Job Record Jacket -to process deed prints and Certificate of Title -to transfer the new Certificate of Title 8. Subdivision of Plot 243 Block 56 Bulemezi August, 2018 Luwero The major RSU assignments on this Asiimwe project were: Denis -to retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing mark stones on the subject plot. -to subdivide of 0.067 acres -to prepare detailed a CAD drawing -to prepare a Job Record Jacket 9. Subdivision of Plot 76 Busiro Block 441 May, 2018 kyaggwe The major RSU assignments in this Asiimwe project were:- Denis -to open boundaries (Surveycom and identify old Surveyors) corner mark stones -to subdivide off 4.0 acres -to prepare a Job Record Jacket (JRJ) 10. Boundary opening of Plot 1452 block 24 Kyadondo September, Rubaga, The major RSU 2018 assignments on this Asiimwe project were: Denis -To open the (Surveycom boundaries of the Surveyors) plot and to determine the total area of the plot. -To re-fix the missing corner mark stones -To establish whether the plot is free of any encroachments. -To prepare a survey report detailing the tasks performed, methodology and findings of the survey. -To prepare a detailed CAD drawing. 11. Subdivision of Plot 621 Block 56 Bulemezi September, Luwero The major RSU 2018 assignments in this Asiimwe project were:- Denis -to open boundaries (Surveycom and identify old Surveyors) corner mark stones -to subdivide off 2.0 acres -to prepare a Job Record Jacket (JRJ) -to process deed prints and Certificate of Title -to transfer the new Certificate of Title 12. Subdivision of Plot 1637 Kyadondo Block 78 April, 2018 Kyadondo My major RSU assignments on this Asiimwe project were;- Denis -to open boundaries (Surveycom so as to retrace the Surveyors) old corner markstones -to subdivide Plot 1637 into 4 Plots each measuring 0.046 ha -to prepare a Job Record Jacket (JRJ) -to process deed prints and the Certificate of Titles of each plot 13. Subdivision of Plot 377 Busiro Block 62 January, 2018 Wakiso The major RSU assignments on this Asiimwe project were: Denis -to retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing mark stones on the subject plot. -to subdivide off 0.46 acres -to prepare detailed a CAD drawing -to prepare a Job Record Jacket -to process deed prints and Certificate of Title -to transfer the new Certificate of Title 14. Subdivision of Plot 5 Block 481-482 Busiro July, 2018 Wakiso The major RSU assignments in this Asiimwe project were:- Denis -to open boundaries (Surveycom and identify old Surveyors) corner mark stones -to subdivide off 0.13 acres -to prepare a Job Record Jacket (JRJ) -to process deed prints 15. Transfer of precise Levels to all the new Standard January to The major RSU Guage Railway Project monuments. April 2018 assignments on this Magemeso project were: Ibrahim. -To carry out levelling from a FBM to all SGR monuments -To compile and process the data collected. 16. Establishment of geodetic Controls for Standard November Uganda The major RSU Railway Project (Eastern route). 2017 assignments on this Magemeso project were: Ibrahim. -To carry out GNSS observations on all the new monuments for SGR -To compile and process the data collected and results obtained.

17. Extension of Controls for Standard Railway Project November Uganda The major RSU Eastern route. 2017 assignments on this Magemeso project were: Ibrahim. -To carry out GNSS observations on all the new monuments for SGR -To compile and process the data collected and results obtained.

18. Boundary Opening of plot 1252 Block 242 November Bukasa, Wakiso The major RSU Kyadondo ,2016 assignments on this Magemeso project were: Ibrahim. -To retrace old boundary lines of the plot and find the existing beacons on the subject plot. -To establish any encroachment -To verify the area on ground whether it tallies with that on the Certificate of Title -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings 19. Boundary Opening of plot 4 Block 917 Busiro April ,2018 Kyaliwajala, The major RSU Wakiso assignments on this Magemeso project were: Ibrahim. -To retrace old boundary lines of the plot and find the existing beacons on the subject plot. -To establish any encroachment -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings 20. Boundary Opening of plot 50-54 Barkely road May ,2018 , Wakiso The major RSU Entebbe assignments on this Magemeso project were: Ibrahim. -To retrace old boundary lines of the plot and find the existing beacons on the subject plot. -To establish any encroachment -To verify the area on ground whether it tallies with that on the Certificate of Title -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings 21. Boundary Opening of plot 6 Block 520 Singo July ,2018 Mityana The major RSU assignments on this Magemeso project were: Ibrahim. -To retrace old boundary lines of the plot and find the existing beacons on the subject plot. -To establish any encroachment -To verify the area on ground whether it tallies with that on the Certificate of Title -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings 22. Survey of Kitubulu Central forest reserve May, 2018 Entebbe, Wakiso The major RSU assignments on this Magemeso project were: Ibrahim. -to survey the forest reserve -to find out whether there is any encroachment. -to prepare detailed report on the findings.

23. Boundary Opening of plot 627 Block 628 Busiro November Kyaliwajala, The major RSU ,2016 Wakiso assignments on this Magemeso project were: Ibrahim. -To retrace old boundary lines of the plot and find the existing beacons on the subject plot. -To establish any encroachment -To verify the area on ground whether it tallies with that on the Certificate of Title -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings 24 Boundary opening of Plot 1128,1129 and 1131 November, Bulindo, Wakiso The major RSU kyadondo 2017 assignments on this Magemeso project were: Ibrahim. -To retrace old boundary lines of the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 25. Boundary opening of Plot 658 Block 193 Busiro November, Wakiso The major RSU 2017 assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 26 Subdivision of Plot 21 Block 144 Mawokota December, Mpigi The major RSU 2017 assignments on this Asiimwe project were: Denis -to retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing mark stones on the subject plot. -to subdivide Plot 91 into three Plots with a proper access road -to prepare detailed a CAD drawing -to prepare a Job Record Jacket -to process deed prints and Certificate of Title -to transfer the new Certificate of Title 27 Survey of a Kibanja at Busunjju, Mityana District December, Mityana The major RSU 2017 assignments on this Asiimwe project were: Denis -to measure the (Surveycom kibanja and Surveyors) ascertain its area -to identify the plot in which the kibanja falls 28. Subdivision of Plot 1420 Block 313-320 Busiro October, 2017 Wakiso My major RSU assignments in this Asiimwe project were;- Denis -to open boundaries (Surveycom so as to retrace old Surveyors) mark stones -to subdivide 5 plots off Plot 14220 depending on how the occupants boundaries are -to prepare a Job Record Jacket (JRJ) -to follow up the processing of deed plans and Certificate of Title 29. Subdivision of Plot 14 Block 67 Busiro October, 2017 Wakiso The major RSU assignments on this Asiimwe project were: Denis -to retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing mark stones on the subject plot. -to subdivide 2 plots off Plot 1759 -to prepare detailed a CAD drawing -to prepare a Job Record Jacket -to process deed prints and Certificate of Title -to transfer the new Certificate of Title 30. Boundary opening of Plot 17 Block 133 Kyadondo October, 2017 Kampala The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To establish any encroachment on the subject Plot -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 31. Topographic survey of plot 7261 block 203 October, 2017 Namungona, The major RSU Kyadondo for National housing Kampala assignments on this Asiimwe project were: Denis -To carry out a (Surveycom topographic survey Surveyors) of the project site. -To prepare a topographic map of the site. 32. Subdivision of a kibanja at Kakindu,Entebbe October, 2017 Entebbe, Wakiso The major RSU assignments in this Asiimwe project were:- Denis -to measure the (Surveycom kibanja and Surveyors) determine its acreage -to plan (subdivide) the kibanja into plots and set them out on ground 33. Subdivision of Plot 75 Block 273 Busiro October, 2017 Wakiso The major RSU assignments in this Asiimwe project were:- Denis -to open boundaries (Surveycom and identify old Surveyors) corner mark stones -to subdivide off 0.84 acres -to prepare a Job Record Jacket (JRJ) 34. Boundary opening of Plot 104 Block 4 Kyadondo October, 2016 Rubaga The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 35. Boundary opening of Plot 8136 Block 265 July, 2016 Waksio The major RSU Kyadondo at Bunamwaya assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 36. Sub division of plot 1220 block 600 under I/S January, 2017 Maya Bujasi The major RSU MA/Z/7/5290 busiro assignments in this Asiimwe at Maya Bujasi project were: - Denis -to open boundaries (surveycom and identify old Surveyors) corner mark stones -to subdivide off 0.121 acres -to prepare a Job Record Jacket (JRJ) 37. Boundary opening of Plot 8136 Block 265 July, 2016 Kampala The major RSU Kyadondo assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 38. Sub division of plot 1512 block 474-475 Busiro March, 2016 Wakiso The major RSU under I/S MA/Z/6/3599 assignments in this Asiimwe at Maya project were:- Denis -to open boundaries (surveycom and identify old Surveyors) corner mark stones -to subdivide off 2 plots -to prepare a Job Record Jacket (JRJ) -to process deed prints 39. Subdivision of Plot 155 Block 224 Kyaggwe April, 2016 Kyaggwe The major RSU Mukono assignments in this Asiimwe project were:- Denis -to open boundaries (Surveycom and identify old Surveyors) corner mark stones -to subdivide off 0.054 ha -to prepare a Job Record Jacket (JRJ) -to process deed prints and Certificate of Titles -to transfer the new Certificate of Title 40. Boundary opening of Plot 3591 Block 82 Busiro May, 2016 Matuga, Wakiso The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To ascertain the area on ground -To establish if there any encroachments -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 41. Setting out of a four story building at Muyenga August, 2016 Kampala The major RSU assignments in this Kibuule project were:- Joseph (SIM -to set out the Engineering corners of the Limited) building 42. Sub division of plot 189 block 600 busiro I/S December, Maya, The major RSU MA/Z/6/5838 2016 Wakiso assignments I Asiimwe performed on this Denis project were: (Surveycom -A boundary Surveyors) opening survey on the plot and to find existing mark stones. -I subdivided off two plots and demarcated the plot with a proper access road as per instructions of the client. -I prepared a Job Record Jacket (JRJ) for the field observations made. -Followed up the processing of deed plans and Certificates of Title for the new plot. 43. Subdivision of Plot 155 Block 224 Busiro April, 2016 Wakiso The major RSU assignments in this Asiimwe project were:- Denis -to open boundaries (Surveycom and identify old Surveyors) corner mark stones -to subdivide off 0.049 ha -to prepare a Job Record Jacket (JRJ) -to process deed prints and Certificate of Titles 44. Boundary opening of plot 873 block 413-414 Busiro May, 2016 Wakiso The major RSU wakiso 19/05/2016 assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 45. Boundary opening of Plot 294 Block 170 Kyadondo August, 2016 Kampala The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 46. Boundary opening of Plot 1045 Block 82 Kyadondo March, 2016 Kungu, Wakiso The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 47. Boundary opening of Plot 9 second ring road Luzila February, 2016 Wakiso The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 48. Boundary opening of Plot 1421 Block 167 May, 2015 Mukono The major RSU Kyadondo assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To establish any encroachment -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 49. Boundary opening of Plot 11 Bell Avenue east October, 2015 Jinja town The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 50. Resurvey and Subdivision of Plot 4959 block 306 July, 2015 Wakiso The major RSU Busiro Block 474-476 Busiro assignments in this Asiimwe project were;- Denis -to resurvey and (Surveycom subdivide off one Surveyors) plot from plot 4959 -to prepare a job record jacket (JRJ) for purposes of acquiring deed prints 51. Subdivision of Plot 245 Block 474-476 Busiro July, 2015 Wakiso The major RSU assignments in this Asiimwe project were;- Denis -to open boundaries (Surveycom and identify the Surveyors) corner mark stones -to plant new mark stones as per the kibanja of the client and locate its position within Plot 245 -to prepare a job record jacket (JRJ) for purposes of acquiring deed prints 52. Subdivision of Plot 245 Block 474-475 Busiro June, 2015 Wakiso The major RSU assignments I Asiimwe performed on this Denis project were: (Surveycom -A boundary Surveyors) opening survey on the plot and to find existing mark stones. -I subdivided off 0.23 acres and demarcated the plot with a proper access road as per instructions of the client. -I prepared a Job Record Jacket (JRJ) for the field observations made.

53. Subdivision of Plot 55 Block 165 Busiro January, 2015 Kakili, Wakiso The major RSU assignments in this Asiimwe project were;- Denis -to open boundaries (Surveycom and identify the Surveyors) corner mark stones -to plant new mark stones as per the kibanja of the client and locate its position within Plot 245 -to prepare a job record jacket (JRJ) for purposes of acquiring deed prints 54. Subdivision of Plot 245 Block 474-476 Busiro July, 2015 Wakiso The major RSU assignments in this Asiimwe project were;- Denis -to open boundaries (Surveycom and identify the Surveyors) corner mark stones -to plant new mark stones as per the kibanja of the client and locate its position within Plot 245 -to prepare a job record jacket (JRJ) for purposes of acquiring deed prints 55. Subdivision of Plot 245 Block 474-476 Busiro July, 2015 Wakiso The major RSU assignments in this Asiimwe project were;- Denis -to open boundaries (Surveycom and identify the Surveyors) corner mark stones -to plant new mark stones as per the kibanja of the client and locate its position within Plot 245 -to prepare a job record jacket (JRJ) for purposes of acquiring deed prints 56. Subdivision of Plot 245 Block 474-476 Busiro July, 2015 Wakiso The major RSU assignments in this Asiimwe project were;- Denis -to open boundaries (Surveycom and identify the Surveyors) corner mark stones -to plant new mark stones as per the kibanja of the client and locate its position within Plot 245 -to prepare a job record jacket (JRJ) for purposes of acquiring deed prints 57. Subdivision of Plot 245 Block 474-476 Busiro July, 2015 Wakiso The major RSU assignments in this Asiimwe project were;- Denis -to open boundaries (Surveycom and identify the Surveyors) corner mark stones -to plant new mark stones as per the kibanja of the client and locate its position within Plot 245 -to prepare a job record jacket (JRJ) for purposes of acquiring deed prints 58. Boundary opening of Plot 183 Busiro Block 469 July, 2015 Wakiso The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare detailed CAD drawings. 59. Subdivison of Plot 69 Block 130 Bugerere January, 2015 Kayunga The major RSU assignments I Asiimwe performed on this Denis project were: (Surveycom -A boundary Surveyors) opening survey on the plot and to find existing mark stones. -I subdivided off 0.25 acres and demarcated the plot with a proper access road as per instructions of the client. -I prepared a Job Record Jacket (JRJ) for the field observations made. -Followed up the processing of deed plans and Certificates of Title for the new plot. 60. Subdivison of Plot 1626 Block 44 Mawokota July, 2015 Mpigi The major RSU assignments I Asiimwe performed on this Denis project were: (Surveycom -A boundary Surveyors) opening survey on the plot and to find existing mark stones. -I subdivided off 0.45 acres and demarcated the plot with a proper access road as per instructions of the client. -I prepared a Job Record Jacket (JRJ) for the field observations made. -Followed up the processing of deed plans and Certificates of Title for the new plot. 61. Boundary opening of Plot 45 Block 4 Kyadondo July, 2015 Rubaga The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 62. Subdivison of Plot 6851 Block 185 Kyadondo October, 2015 Najera, Wakiso The major RSU assignments I Asiimwe performed on this Denis project were: (Surveycom -A boundary Surveyors) opening survey on the plot and to find existing mark stones. -I subdivided off 0.40 acres and demarcated the plot with a proper access road as per instructions of the client. -I prepared a Job Record Jacket (JRJ) for the field observations made. -Followed up the processing of deed plans and Certificates of Title for the new plot. 63. Topographic survey of plot 190 block 345/6 Busiro January, 2015 Kampala, The major RSU assignments on this Asiimwe project were: Denis -To carry out a (Surveycom topographic survey Surveyors) of the project site for purposes of preparation of architectural building plans. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare a topographic map and plans of the plot. 64. Subdivison of Plot 19 Block 41 Singo August, 2015 Mubende The major RSU assignments I Asiimwe performed on this Denis project were: (Surveycom -A boundary Surveyors) opening survey on the plot and to find existing mark stones. -I subdivided off 4.0 acres and demarcated the plot with a proper access road as per instructions of the client. -I prepared a Job Record Jacket (JRJ) for the field observations made. -Followed up the processing of deed plans and Certificates of Title for the new plot. 65. Amalgamation of plot May, 2015 The major assignment RSU 1018,640,871,694,693,532,870,639,506 and 1016 I performed on this Asiimwe block 33 Kyadondo project were;- Denis -I carried out the field (Surveycom work Surveyors) -I prepared Job record jackets having obtained the Instruction to Survey -Followed up the processing of the deed plans and Certificate of Titles 66. Topographic survey of Kashaka-Mitoma January, 2015 Mitoma District The major RSU assignments on this Asiimwe project were: Denis -To produce a strip (Surveycom map for the road Surveyors) -To prepare a topographic map for the road. -To prepare longitudinal profile for the road. 67. Topograhic survey of two acres of land at Mbarara March, 2015 Mbarara The major RSU Joyce university for Uganda Cancer institute assignments on this Gunze project were: Habaasa -To carry out a (Terrain topographic survey Consult) of the project site. -To prepare a topographic map of the site. -To identify the points with highest and lowest elevation 68. Boundary Opening of plot 2321 Block 195 December,2014 Kampala The major RSU Joyce Kyadondo assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of Consult) the plot and find the existing beacons on the subject plot. -To establish any encroachment -To verify the area on ground whether it tallies with that on the Certificate of Title -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings 69. Boundary opening of Plot 1055 Block 12 Kyadondo January, 2014 Rubaga The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 70. Subdivision of Plot 498 Block 271 Busiro September, , Wakiso The major RSU 2014 assignments in this Asiimwe project were;- Denis -to open boundaries (Surveycom and identify old Surveyors) corner mark stones -to subdivide off 0.405 ha -to prepare a Job Record Jacket (JRJ) -to process deed prints and Certificate of Titles -to transfer the new Certificate of Title 71. Area verification of a Kibanja at Katwe, Busiro October, 2014 Wakiso The major RSU County, Wakiso assignments on this Asiimwe project were: Denis -To measure the (Surveycom area occupied by the Surveyors) kibanja holder -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 73. Boundary opening of Plot 386 Block 22 Kyadondo February, 2014 Busega, Kampala The major RSU Asiimwe assignments on this Denis project were: (Surveycom The major Surveyors) assignments on this project were: -To retrace old boundary lines of the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 74. Boundary opening of Plot 257 Block 448 Busiro October, 2014 Wakiso The major RSU assignments on this Asiimwe project were: Denis -To retrace old (Surveycom boundary lines of Surveyors) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 75. Completion of Land Acquisition along Kampala- July, 2013 Kampala The major assignment RSU Northern by-pas I performed on this Kiwanuka project were;- Dathan -Survey of the road reserve. -I prepared Job record jackets for the affected plots. -Followed up the processing of the deed plans and Certificate of Titles 76. Boundary opening of Plot 2746 Block 208 July, 2014 Bunamwaya, The major RSU Joyce Kyadondo Wakiso assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 77. Boundary opening of Plot 1070 Block 5 Kyadondo December, Mulago, The major RSU Joyce 2014 Kampala assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 78. Subdivision of Plot 58 Block 70 Kyadondo January, 2014 Wakiso The major RSU Joyce assignments I Gunze performed on this Habaasa project were: (Terrain -A boundary consult) opening survey on the plot and to find existing mark stones. -I subdivided off 0.083 ha with a proper access road as per instructions of the client. -I prepared a Job Record Jacket (JRJ) for the field observations made. -Followed up the processing of deed plans and Certificates of Title for the new plot. -Later transferred the new Certificate of Title 80. Boundary opening of Plot 15 Block 97 Bulemezi October, 2014 Luwero The major RSU Joyce assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -to establish any encroachment -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 81. Boundary opening of Plot 655 Block 600 Kyadondo July, 2014 Maya, Wakiso The major RSU Joyce assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 82. Boundary opening of Plot 252 and 257 Block 448 November, Nkozi Mpigi The major RSU Joyce Mawokota 2014 assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 83. Subdivision of Plot 89 Block 126 Bugerere September, Mukono The major RSU Joyce Mukono. 2014 assignments in this Gunze project were:- Habaasa -to open boundaries (Terrain and identify old consult) corner mark stones -to subdivide off 0.078 ha -to prepare a Job Record Jacket (JRJ) -to process deed prints and Certificate of Title -to transfer the new Certificate of Title 84. Boundary opening of Plot 291 Block 21 Kibuga March, 2014 Kampala The major RSU Joyce assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -To ascertain the area on ground -To establish if there any encroachments -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 85. Boundary opening of Plot 113 Block 328 Mawokota February, 2014 Lwela, Mpigi The major RSU Joyce assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -To ascertain the area on ground -To establish if there any encroachments -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 86. Resurvey of Plot 28 Block 79 Kyaggwe November, Mukono The major RSU Joyce 2014 assignments in this Gunze project were:- Habaasa -to open boundaries (Terrain and identify old consult) corner mark stones -to subdivide off 0.50 acres -to prepare a Job Record Jacket (JRJ) -to process deed prints and Certificate of Title -to transfer the new Certificate of Title 87. Subdivision of Plot 15 Block 385 singo January, 2013 Kampala The major RSU Joyce assignments I Gunze performed on this Habaasa project were;- (Terrain -to open the consult) boundaries of Plot 483 to identify all the corner mark stones -to subdivide 4.0 acres and distribute the residue amongst the beneficiaries -to prepare a Job Record Jacket

88. Boundary opening of Plot 619 Block 4 Kyadondo November, Kampala The major RSU Joyce 2013 assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 89. Topographic survey of plot October, 2013 Kampala District The major RSU Joyce 174,642,694,693,639,870,532,524,506,526,527,176 assignments I Gunze block 33 Kibuga performed on this Habaasa project were;- (Terrain -to carry out a consult) topographic survey -to determine the highest and lowest point on the site -to produce a topographic map -to produce a longitudinal profile 90. Boundary opening of Plot 275 and 268 Block 265 August, 2013 Bunamwaya, The major RSU Joyce Busiro Wakiso assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -To ascertain the area on ground -To establish if there any encroachments -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 91. Boundary opening of Plot 728 Block 24 Kibuga June, 2013 Lungujja, The major RSU Joyce Kampala. assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -to establish any encroachment -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings. 92. Boundary opening of Plot 4850 and 4851 Kyadondo November, Wakiso The major RSU Joyce 2013 assignments on this Gunze project were: Habaasa -To retrace old (Terrain boundary lines of consult) the plot and find the existing beacons on the subject plot. -To ascertain the area on ground -To establish if there any encroachments -To prepare a survey report detailing the tasks performed, methodology and results obtained. -To prepare detailed CAD drawings.