STORMWATER MANAGEMENT CREDIT APPLICATION REPORT CREDIT VALLEY CONSERVATION
December 2016 TABLE OF CONTENTS
CONTENTS 1.0. INTRODUCTION ...... 4 1.1. SITE DESCRIPTION ...... 6 1.1.1. General ...... 6 1.1.1.1. Meadowvale Conservation Area: ...... 7 1.2. PRE-DEVELOPMENT CONDITIONS ...... 11 2.0. INTEGRATED WATER MANAGEMENT (IWM) ...... 12 2.1. BUSINESS OBJECTIVES ...... 12 2.1.1. Integrated Water Management (IWM) ...... 13 2.2. MISSISSAUGA STORMWATER CRITERIA ...... 15 2.3. EXISTING CONDITIONS ...... 15 2.3.1. Geotechnical Investigation ...... 18 2.4. STORMWATER DRAINAGE SYSTEM ...... 19 2.4.1. Minor System ...... 19 Parking Lot 2 ...... 20 Parking Lot 3 ...... 20 Roof Drainage - Buildings A & B ...... 21 2.5. Stormwater Best Management Practices ...... 25 2.5.1. Rainwater Harvesting System (RWH) for Building A ...... 25 2.5.2. Permeable Pavement Parking Lots ...... 29 2.5.2.1. Paver Type and Thickness ...... 30 2.5.2.2. Bedding Layer and Thickness ...... 30 2.5.2.3. Granular Base Material and Thickness ...... 31 2.5.2.4. Underdrain System ...... 33 3. Vegetated Swales ...... 36 3.1.1.1. Wet Weather Drainage Patterns ...... 38 3.2. Major System ...... 39 3.0. HYDROLOGIC MODELLING ...... 40 3.1. STORMWATER CRITERIA ...... 46 3.2. Peak Flow Reduction ...... 46 3.3. WATER QUALITY TREATMENT ...... 47 3.3.1. Permeable Pavement ...... 48 3.3.2. Vegetated Swales ...... 49
2
3.4. RUNOFF VOLUME REDUCTION ...... 51 4.0. CREDIT REQUEST ...... 53 5.0. SYSTEM OPTIMIZATION ...... 55 Figure 28 : Stylized ADS enhanced swale design (Source: Advanced Drainage Systems (ADA) Canada) ...... 55 5.1. CREDITS FOR OVER CONTROL ...... 56 6.0. OPERATION & MAINTENANCE PLANS ...... 56 6.1. RAINWATER HARVESTING SYSTEM OPERATIONS AND MAINTENANCE MANUAL ...... 56 6.1.1. Introduction ...... 56 6.1.2. Rainwater Harvesting System Description ...... 56 6.1.3. RWH System Components ...... 57 6.2. CVC PERMEABLE PAVEMENT OPERATIONS AND MAINTENANCE PLAN ...... 83 Results ...... 83 7.0. ENGINEER’S CERTIFICATION & OPERATION ...... Error! Bookmark not defined. 7.1. CERTIFICATION THAT ALL BMPS HAVE BEEN CONSTRUCTED IN ACCORDANCE WITH THE SUBMITTED DRAWINGS AND THAT THEY ARE OPERATIONAL...... Error! Bookmark not defined. 7.2. CONFIRMATION OF THE DATE(S) THAT ALL THE BMPS WERE IMPLEMENTED INTO SERVICE ...... Error! Bookmark not defined. 8.0. APPENDICES ...... Error! Bookmark not defined.
3
1.0. INTRODUCTION
CVC has implemented a variety of innovative stormwater management best management practices on their property to reduce impacts to municipal stormwater infrastructure by controlling the quantity and quality of stormwater leaving the site.
The purpose of this report is to support an application for a stormwater credit for the Credit Valley Conservation (CVC)-owned property located at 1255 Old Derry Road in Mississauga. In 2016, CVC will have been assessed with a stormwater charge of $9,180.00 based on an impervious area of 24,506.2 m 2, which constitutes 91.8 billing units (Figure 1).
Figure 1 Annual Charge for CVC property (04439200)
Figure 2 shows the CVC-owned lands identified within the stormwater fee calculator tool. The area hatched in red represents lands that the City of Mississauga is currently leasing from CVC. While the area without hatching represents the lands associated with CVC’s administration office.
4
Figure 2 Total impervious cover across the CVC property
CVC has also measured the surface area of existing impervious surfaces which was found to be 23,810 m2. Table 1 provides a breakdown of the impervious cover for the entire CVC property.
5
Table 1 Breakdown of Impervious Cover
Land Use Area (m 2) Type Buildings 2,291 Gravel 8,206 Parking Lot 1,989 Paved Trail 80 Pervious Parking 3,866 Road 3,066 Sidewalk 1,204 Trail 3,108 Total 23,810
1.1. SITE DESCRIPTION
1.1.1. General
Located on the north side of Old Derry Road and west of the Credit River in Mississauga, the CVC property is located close to the heritage conservation district known as the Village of Meadowvale. The site is bounded by existing residential developments and centered within the Credit River valley. The property lies within the limits of Credit River Subwatershed No. 9.
CVC’s Administration Office is located on the west side of the Credit River while the property on the east side of the river is managed by the City of Mississauga. The east side of the property is the Meadowvale Conservation Area and includes the Glassford and Culham Trails which traverse the property and connect it to surrounding parks and neighbourhoods.
Figure 3 illustrates the parcel boundaries for the entire CVC property.
6
Figure 3 Meadowvale Conservation Area 1.1.1.1. Meadowvale Conservation Area:
The entrance to this section of the property is at 7250 2nd Line W. The main facilities for the conservation area include a washroom structure, a gravel parking lot, and gravel trail (Glassford Trail). A small section of the Glassford Trail is paved. The site is completely openly drained with no storm sewers or catchbasins.
7
Figure 4 Boundary of Meadowvale Conservation Area
8
The entrance to this portion of the property is at 1255 Old Derry Road. The CVC Administrative Office was opened in 1987. By 2006, CVC staff completed a feasibility study and report recommending that the existing head office site be expanded to include a new 3-storey addition as a solution to space shortage and to accommodate staff growth over the following ten (10) years. The Board of Directors accepted the recommendation and approved the design and development of the proposed building in January 2007.
The CVC Administrative Office is described as :
Part of Lot 11, Concession 3, West of Hurontario Street Part 12, Plan 43R-17252 1255 Old Derry Road, Mississauga
Figure 5 is the overall site plan for CVC Administrative Building. Table 2 provides a breakdown of the building coverage for the 9.0 ha site.
Table 2 Building Lot Coverage for CVC Administrative Building
Building Lot Coverage (m 2) 2 Story Office Building (Building B) 1,051 3 Story Office Building (Building A) 645 Portable Building 207 Outdoor Storage Building 33 Total Existing Building Area 1,936
Table 3 provides a breakdown of the different paved and parking areas.
Table 3 Paved Area and parking area breakdown
Paved Area Surface Type Area (m 2) Parking Spaces Handicapped Spaces Parking Lot 1 Asphalt 1,989 67 3 Parking Lot 2 Permeable Pavers 1,539 60 Parking Lot 3 Permeable Pavers 2,327 75 Driveway Asphalt 3,066 2 Sidewalk Concrete 1,204 Totals 10 ,125 202 5
9
Figure 5 Overall Site Plan for the CVC Administrative Building
10
Table 4 provides a comparison of the impervious surface areas for the two areas of the property.
Table 4 Breakdown of surface areas per hard surface features
Hard Surface Feature Total Area Meadowvale CVC (m 2) Conservation Administrative Area (m 2) Office (m 2)
Buildings 2,291 355 1,936 Parking Lot (Gravel) 8,206 8,206 - Parking Lot (Asphalt) 1,989 - 1,989 Paved Trail (Asphalt) 80 80 - Pervious Parking 3,866 - 3,866 Road (Asphalt) 3,066 - 3,066 Sidewalk (Concrete) 1,204 - 1,204 Trail (Gravel) 3,108 3,108 - Total Area (m 2) 23,810 11,749 12,061
1.2. PRE-DEVELOPMENT CONDITIONS
The City of Mississauga’s e-Maps tool was used to estimate pre-development conditions based on 1954 air photography. The site was predominately under cultivation with scattered woodlots and meadows. The pre-development runoff coefficient was assumed to be 0.25 .
Figure 6 is an aerial photo of the site in 1954.
Pre-development conditions:
The intent of characterizing the pre-development site conditions is to: • Provide input into the pre-development hydrologic parameters used for modelling • Estimate the pre-development peak flow rates for the 100 year design storm for the critical storm distributions and durations (i.e., 4 hour Chicago distribution) for each sub catchment.
11
Figure 6 Aerial View of the CVC Site in 1954
2.0. INTEGRATED WATER MANAGEMENT (IWM)
2.1. BUSINESS OBJECTIVES
As the CVC Administrative Office site was expanded to accommodate growth, several key objectives were established to ensure innovative environmental management solutions in building and land use were considered:
• Design a new office expansion that demonstrates environmentally sound principles of construction, operation and equipment use by finding effective models to promote innovative solutions and design. • Apply Leadership in Energy and Environmental Design (LEED) to elements of the building and site to optimize the use of land, energy and materials in a cost efficient and effective manner.
Building A is registered with the Canada Green Building Council, and is certified LEED Gold. It includes many green features, including a rainwater harvesting system, where rainwater that falls on the roof is routed to a basement rainwater storage tank.
12
2.1.1. Integrated Water Management (IWM)
An IWM approach was adopted for the site which is intended to mimic the natural hydrologic cycle. It looked at drinking water, wastewater and stormwater holistically, rather than as separate systems. The following objectives were adopted for the site:
• Harvest stormwater for water supply, irrigation, and/or infiltration benefits – Look at stormwater as a resource rather than as a waste product to be managed, and find ways to harvest and reuse it on site.
• Apply the “right water for right use” – Treat water to a level of quality suitable for its intended use. Water for irrigation and toilet flushing does not need to be treated to potable standards.
• Implement cost-effective, demand-side controls and green infrastructure before increasing grey infrastructure - Green Infrastructure are stormwater management systems and features that emphasize drainage and conveyance characteristics that mimic pre-development conditions.
The site design incorporated a variety of innovative stormwater features that promote infiltration and reduce stormwater runoff generated by frequent storm events. By storing and infiltrating frequent storm events, a large percentage of the annually-generated runoff can be managed close to where it falls and reduce the burden on pre-existing and aging municipal infrastructure.
The IWM theme is also an embedded concept within the LEED certification requirements. Building A received the Gold certification and the following are some of the principles that were adopted into the site design:
• Sediment & Erosion control; • Reduced site disturbance; • Stormwater management (rate, quantity, treatment); • Water efficient landscaping; • A declaration that the site will not be irrigated using potable water; • Innovative wastewater technologies (50.64% reduction in wastewater generation); • Water use reduction; • Reduced Heat Island Effect (Non- Roof) - A minimum of 30% of non-roof impervious surface area was constructed with high albedo materials. Product data for the Eco-Stone unit paving indicates that the product has a reflectance of 30% and a solar reflective index (SRI) of 32. • Reduced Heat Island Effect (Roof) - 91% of the roof area is covered with high-albedo roofing product.
13
Table 5 provides a high level overview of design considerations for different green infrastructure/stormwater management practices.
Table 5 Design Considerations
Design Considerations Comments Risk of Groundwater Contamination The runoff that will be directed to the LID features included roof, parking lot and landscaped areas. De-icers are applied to trafficked areas during the winter months. Risk of Soil Contamination None Performance in Winter Conditions All practices will be operational and Spring Snowmelt throughout the winter months. Standing Water and Mosquitoes The facilities have been designed to have no surface ponding. Wellhead Protection Area (WHPA) The site is not located in a WHPA Site Topography Average slopes of contributing drainage areas are 1-5%. Available Head The permeable pavement facilities are designed to connect to a storm sewer which limits the available head to 200mm . Water Table The water table is 1.2m below the bottom of all infiltration facilities. Soils The native soil infiltration rate is estimated to be 15 mm/hr . An underdrain has been included in all infiltration and filtration designs to account for this. I:P Ratio Impervious to Pervious ratio Pollution Hot Spot Runoff The site is not a pollution hot spot. Runoff will not be contaminated. Proximity to Underground Utilities Utilities are identified on base plan. Overhead Wires No overhead wires.
Please refer to the CVC Head Office Case study (http://www.creditvalleyca.ca/wp- content/uploads/2016/06/CaseStudy_CVC_Final.pdf ) and Infrastructure Performance and Risk Assessment (IPRA) report (http://www.creditvalleyca.ca/wp- content/uploads/2016/06/TechReport_CVC_Final.pdf ) for additional information about the CVC head office.
14
2.2. MISSISSAUGA STORMWATER CRITERIA
The stormwater management system for CVC’s head office will be evaluated based on how well it is achieving the following City of Mississauga Stormwater Credit Criteria:
1. Peak Flow Reduction (40%) 2. Runoff Volume Reduction (15%) 3. Water Quality Treatment (10%) 4. Pollution Prevention (5%)
Per the credit program guidance manual, credits are performance-based and not technology-based. Therefore, credits are awarded based on how well the stormwater BMPs will achieve the performance criteria listed above.
It is recognized that many of the BMPs could be eligible for more than one type of credit such as permeable pavement which can provide a combination of peak flow, water quality treatment and runoff volume reduction. For this example credits could be applied to multiple categories.
Further, credit eligibility will be contingent on proof of functionality and on-going maintenance through self-certification reports and periodic City inspections.
2.3. EXISTING CONDITIONS
The following section describes the existing conditions for the site. Appendix A provides a detailed site plan of the CVC Administrative office that identifies all structures, including buildings, parking, driveways and other impervious area. Figure 7 below is a schematic representation of the site plan that describes the hydrologic and hydraulic components.
15
Figure 7 Flow Chart of CVC Administrative Office - Catchments and Infrastructures (Grey and Green)
16
17
2.3.1. Geotechnical Investigation
The geotechnical investigation is necessary for most LID practices with the exceptions of green roofs, rainwater harvesting, pollution prevention, and landscape alternatives. The scope of work required varies depending on the practice selected. Refer to Table 5.2.1 provided in CVC’s Grey to Green Business & Multi-Residential Retrofits Guide (http://www.creditvalleyca.ca/wp-content/uploads/2013/10/SWI-Grey-to-Green- Business-Multires-Retrofits-Complete1.pdf ) for a summary of the necessary geotechnical investigation activities for the detailed design of LID practices.
For the CVC Administration Building site, two (2) geotechnical investigations and reports were prepared by Terraprobe Limited: o Geotechnical Investigation Report, December 15, 2006 o Supplemental Geotechnical Investigation Report, November 30, 2007
As an addendum to the November 30, 2007 report, a proposed addition was submitted on January 14, 2008 recommending the Unilock Eco-Stone permeable pavement structure.
The geotechnical reports note that glacial till was encountered to the vertical limit of investigation for all boreholes except borehole 13. The reports note that the glacial till found beneath the site has a low permeability and that there is a ‘perched water table’ above the low permeable glacial till soils that would impede the downward movement of water. The report goes on to note that water levels in the perched zone can be expected to fluctuate from season to season with the highest levels in the spring. The geotechnical investigations were completed in November 2006 and September 2007. No long term groundwater level monitoring exists for the site.
Boreholes 10, 12, 13 & 14 all represent the surficial conditions in the immediate vicinity of Parking Lot #2 and were characterized as follows:
• All of these boreholes were observed to have no groundwater based on a vertical investigation limit of 2.8m; • The upper soil layers consisted of topsoil and fill material with glacial till further down (except borehole 13);
The permeable pavement lots were excavated to a minimum depth of 555mm. Given that borehole 14 intercepted the glacial till layer at the shallowest depth of 800mm, the bottom of the permeable pavement base layer would be above the glacial till layer within the fill zone. The fill zone is described as sand and gravel with traces of silt, trace clay, dense to very dense brown to brownish-grey, damp to moist soils.
The type of soil dictates the infiltration rates that can be used to characterize the infiltration performance of the facilities. Table 6 summarizes surficial characteristics within the vicinity of Parking Lot #2, as identified in the November 30 th , 2007 report.
18
Table 6 Geotechnical investigation results for boreholes 12 and 14.
Borehole No. 12 14 Depth (m) 0.8 to 1.2 0.8 to 1.2 Soil Type Sand and Gravel, some Sand Silt, some clay, silt, trace clay (GM) some gravel (ML) Soil Composition Gravel (%) 49 12 Sand (%) 36 25 Silt (%) 12 47 Clay (%) 3 16 D10 (mm) 0.03 0.0004 Estimated Coefficient of Permeability 0.009 0.0000002 (cm/s) (Hydraulic Conductivity) Estimated Coefficient of Permeability 324 0.0072 (mm/hr) Percolation Time, T (min/cm) 6 - 8 Greater than 50 General Comments Permeable to medium Low permeability permeability
For the design of Parking Lot #3, no additional geotechnical investigations were conducted. The engineer’s report noted that the design was based on existing geotechnical information from the building expansion work from 2009/2010.
An infiltration rate of 15mm/hr was selected for this site.
2.4. STORMWATER DRAINAGE SYSTEM
The original stormwater servicing reports and plans were prepared in accordance with design criteria and requirements of the City of Mississauga and CVC. The following section describes the stormwater drainage system in detail. 2.4.1. Minor System
According to the existing design briefs, the minor system for the site has been designed to accommodate the 2 year peak flow and includes storm sewers, catchbasins, gutters, grass swales and roof leaders. The minor system will convey the frequent events off of the driveway surface, parking lots and landscaped areas. None of the features on this site have been designed to pond water for any period of time. For further details on the minor system (engineering drawings for stormwater pipes, catchbasins, culverts), please refer to Appendix B .
19
Parking Lot 2 The minor system for parking lot #2 was designed to convey the 2-year peak flow from the parking and open space areas and the 100-year peak flow from the roof of Building A.
Tables 7 and 8 summarize the characteristics of the closed minor system for parking lot 2.
Table 7 Summary of catchbasin characteristics for Parking Lot #2
Catchbasin Size OPSD Top of Invert(s) Invert Depth to Sump I.D. (mm) Grate Elev. IN OUT Surface Depth (m) (mm) CB.1 600x600 705.01 170.44 169.03 1.41 600 CB.MH.2 1200 701.01 170.30 168.755 168.705 1.55 300 CB.MH.3 1200 701.01 170.18 168.465 168.415 1.72 300 CB.MH.4 1200 701.01 169.40 168.195 168.145 1.26 300
Table 8 Summary of pipe characteristics for Parking Lot #2
Pipe ID From To Pipe Material Length Slop Invert Invert Dia. (m) e (%) U/S D/S (mm) MD 1 CB.1 CB.MH.2 200 PVC 27.5 1 169.03 168.75 MD 2 CB.MH.2 CB.MH.3 250 PVC 24 1 168.705 168.46 MD 3 CB.MH.3 CB.MH.4 250 PVC 22 1 168.415 168.14 MD 4 CB.MH.4 Outfall #7 300 PVC 9 1 168.145 168.05 Br 1 RWH CB.MH.2 200 PVC 16.5 2 169.085 168.75 Total Length 99
Parking Lot 3
The minor system for parking lot 3 is comprised of a number of grass swales that lead to a ditch inlet catchbasin (DICB 5) and 600mm corrugated steel pipe (CSP; Culvert 1). There is also a 600x600mm catchbasin (CB 6) within the entrance lane to the parking lot that is connected to a second 600mm CSP (Culvert 2). Tables 9 and 10 describe the different components of the minor system for parking lot 3.
Table 9 Summary of catchbasin characteristics for Parking Lot 3
Catchbasin Size (mm) OPSD Top of Grate Invert OUT Depth to Sump I.D. Surface Depth (m) (mm) DICB 5 1200x1200 702.05 170.15 169.278 0.872 300 CB.6 600x600 701.01 170.25 169.427 0.82 600
20
Table 10 Summary of culvert and pipe characteristics for Parking Lot 3
Pipe ID From To Pipe Dia . Material Length Slope Invert Invert (mm) (m) (%) U/S D/S Culvert 1 DICB 5 Outfall 600 CSP 26 0.5 169.278 169.15 #8 Culvert 2 S3-3 Outfall 600 CSP 9 1 169.65 169.56 #9 CB Lead CB.6 600mm 250 PVC 5 1 169.427 169.377 CSP
Due to the low infiltration capacity of the sub soils, an underdrain was specified to facilitate the conveyance of excess water from beneath both permeable pavement lots. Table 11 summarizes the sub-drain characteristics within both parking lots 2 and 3.
Table 11 Summary of sub-drain characteristics for Parking Lots 2 & 3
Sub -drains Diameter Material Length (mm) Parking Lot #2 100 Perforated Corrugated PVC 46 Parking Lot #3 100 Perforated Corrugated PVC 100
Roof Drainage - Buildings A & B
Buildings A & B were not designed to include roof top storage for the larger storm events. Both buildings have a series of internal roof drains that then convey the water via 100mm pipes. Figures 8 contain photos of roof drain inlets. Table 12 summarizes information about the roof drain infrastructure.
21
Building A - 100mm roof drain inlets Building A - 450mm lip around perimeter of roof
Building B – 100mm roof drain inlets Building B – 100mm lip around perimeter of roof Figure 8 Roof Drainage Characteristics of Buildings A and B
22
Table 12 Roof drainage infrastructure details
Depth of Volume of Diameter of Roof Area #of Roof storage storage Building Roof Drain (m2) Drains above drain above drain (mm) (m) (m3) Building A 1,051.35 8 100 0 0 Building B 644.63 7 100 0 0
Vegetated Swale
The most common form of minor drainage conveyance is through a series of low gradient vegetated swales. Table 13 summarizes the characteristics of these swales.
23
Table 13 Swale Characterization for CVC Administration Building
Swale ID Swale Swale Upstream Downstream Manning's Length Slope Max Bottom Left Right Type Lining Invert (m) Invert (m) n (m) Depth Width (m) Side side (m) Slope Slope Swale 1 Saucer Forest 170.8 170.4 0.03 80 0.5% 0.34 4 0.08 0.025 Swale 3-1 Saucer Turf 170.4 170 0.03 30 1.3% 0.13 0.93 0.06 0.072 Swale 3-2 Saucer Turf 170 169.8 0.03 26 0.8% 0.13 0.93 0.06 0.03 Swale 3-3 Saucer Turf 169.8 169.65 0.03 28 0.5% 0.13 0.93 0.06 0.03 Swale 4 V Turf 170.76 170.15 0.024 58 1.1% 0.14 0 0.15 0.06 shaped Swale 5 V Turf 170.5 170.08 0.024 27 1.6% 0.09 0 0.10 0.014 shaped Swale 6 V Turf 170.08 169.4 0.024 19 3.6% 0.05 0 0.06 0.16 shaped Swale 7 V Turf 170.28 170.18 0.024 23 0.4% 0.02 0 0.02 0.03 shaped Swale 8 V Turf 170.36 170.3 0.024 12 0.5% 0.05 0 0.05 0.06 shaped Swale 9 V Turf 170.58 170.44 0.024 40 0.4% 0.05 0 0.05 0.06 shaped Swale 10 Saucer Forest 170.9 170.45 0.03 55 0.8% 0.18 3.97 0.09 0.03 Swale 11-2 Saucer Turf 171.2 170.45 0.03 42 1.8% 0.16 1.98 0.16 0.04 Swale 11-3 Saucer Turf 171.3 170.5 0.024 33 2.4% 0.07 0.96 0.07 0.02 Swale 14 Saucer Turf 170.85 170.45 0.03 40 1.50% 0.16 1.98 0.16 0.04
24
2.5. Stormwater Best Management Practices
A number of stormwater best management practices were incorporated into the site design such as rainwater harvesting system, permeable pavement parking lots and vegetated swales. 2.5.1. Rainwater Harvesting System (RWH) for Building A
Rainwater harvesting is the process of intercepting, conveying and storing rainfall for future use and provides the combined benefits of conserving potable water and reducing stormwater runoff. With minimal pre-treatment, harvested rainwater from Building A is used:
• Outside to irrigate landscaped areas and the water is either evapotranspired by vegetation or infiltrated into the soil, thereby helping to maintain predevelopment water balance; • Inside to flush toilets or urinals.
By providing a reliable and renewable source of water at the site, the rainwater harvesting system can also help reduce demand on drinking water supplies. By reducing demand on water resources, rainwater harvesting can result in significant cost savings due to:
• delayed expansion of municipal water treatment and distribution systems; • lowered energy use for pumping and treating water; and • lowered consumer water bills
The RWH system uses a 5,000 litre rainwater storage tank located in the basement of Building A. Rainwater from the roof is directed through interior 100mm drains to a central mechanical room. The drains then combine into a 150mm pipe and roof water enters the storage tank via a 75 mm diameter pipe. The same size pipe (75mm) is used to convey excess rainwater from the tank when there is too much volume in the storage tank.
All excess rainwater is discharged through the building’s 200mm PVC storm drain that then connects to catchbasin 2 (CB.2). The tank is also periodically filled with water from the building’s sump pump.
The rainwater and groundwater collected via the sump pump is used to supply non- potable water to toilets and urinals in Building A and also supplies water to outdoor hose taps. Figure 9 is a schematic diagram of the RWH system. Figure 10 is a plan view of the RWH. Please refer to Section 6.1 for a detailed description of the RWH system and operation & maintenance plan. Table 14 provides a summary of the RWH characteristics
25
Table 14 Summary of RWH system characteristics
Design Parameters Value Total Storage of Tank * 4,487 litres Total Roof Area 644 m2 Maximum Active 4,337 litres Storage** Available Active Storage 967 litres * Volume below 75mm overflow ** Lowest recorded tank volume
Water Balance: A simple water balance equation for the RWH tanks can be expressed as follows:
QIN1 + Q IN2 = QOUT1 + QOUT2 + QOUT3
Where: QIN1 = Roof drainage flowing into the tank (m3/s) QIN2 = Sump pump water discharged into the tank (m3/s) QOUT1 = Water pumped from tank for non-potable uses (m3/s) QOUT2 = Water by-pass (m3/s) QOUT3 = Water overflow (m3/s)
Table 15 below summarizes which inflows and outflows have been monitored for the RWH system.
Table 15 Water Balance Components of RWH System
Flow Description Measurement QIN1 Flow from roof drainage Level logger* QIN2 Flow from sump pump Level logger* QOUT1 Flow harvested for non- Probe potable use QOUT2 Water by-passing the Not measured RWH tank QOUT3 Water Overflow Level Logger *Inflow measurements are not able to distinguish rainwater inflow versus sump pump inflow.
It is not possible at this time to accurately perform a water balance for the RWH system. Based on existing monitoring work CVC is unable to estimate the total inflow to the tank during wet weather events due to sump-pump water inputs and bypass. However, the monitoring data does allow CVC to estimate the available active storage to be approximately 967 litres.
Figures 9 &10 provide a detailed schematic and plan view of the RWH system.
26
QIN1 QIN2 QOUT2 (Roof) (Sump Pump) (By-Pass)
QOUT3 (Overflow)
QOUT1 (Non-Potable)
Figure 9 Schematic of Rainwater Harvesting System
27
Figure 10 Plan View of Rainwater Harvesting System
28
2.5.2. Permeable Pavement Parking Lots
Permeable pavement is an innovative stormwater management approach that promotes the infiltration of stormwater between paving stones and into a stone reservoir where it is infiltrated into the underlying native soil and/or temporarily detained. This technique has been successfully implemented across the CVC watershed within low traffic roads, parking lots, driveways, and walkways.
The permeable pavement parking lots were designed for filtration, storage, and infiltration of runoff. Given the lower permeability of the native subsoil, underdrains were installed above the stone reservoirs to ensure drainage of the sub-base and prevent winter freeze/thaw damage.
Table 16 provides a detailed summary of the physical characteristics used to model the performance of the two permeable parking lots.
Table 16 Physical characteristics of Parking Lots 2 and 3
Parameter Value Parking Lot #2 Parking Lot #3 Paver Type & Thickness Standard Unilock Eco-Stone Standard Unilock Eco-Stone Natural Charcoal Grey 80mm 80mm Note: The pavers have nubs around them which leave a consistent 1 cm space between each paver that allows water to drain through.
Bedding Layer Material ASTM D 448 Aggregated Size No. 8 & Thickness 25mm Note: The same chip stone also fills the spaces between the pavers.
Granular Base Material 19.0mm clear open recycled 19.0mm clear open recycled & Thickness concrete, OPSS 1010 concrete, OPSS 1010 Gradation Requirements Gradation Requirements 450mm (250mm) 19.0mm clear stone (200mm) 450mm Geotextile Yes – Woven No Surface Area (m 2) 1,704 2,096 Total Excavation Depth 555mm Total Storage Depth 200mm (below underdrains) Total Storage (m 3) 136 168 Under -drain System 100mm Perforated Corrugated PVC subdrain with geotextile and granular filter material placed 300mm below subgrade Construction August 2009 August 2012 Completion Date
29
Measured Infiltration 798 mm/hr 1952 mm/hr Rates Permeability of 15 mm/hr Subgrade
2.5.2.1. Paver Type and Thickness
Figure 11 illustrate the different paver types implemented at the CVC Administrative Office.
Parking Lot 2 – Standard Unilock Parking Lot 3 - Standard Unilock Eco-Stone Eco-Stone Natural Charcoal Grey
Parking Lot 2 during a rainfall event (Oct 2015) Parking Lot 3 during the a rainfall event (Oct 2015) Figure 11 Paver Types installed in Parking Lot 2 and 3
2.5.2.2. Bedding Layer and Thickness
30
Figure 12 includes photos of the bedding material for parking lots 2 and 3 during construction.
Parking Lot 2 (left) and Parking Lot 3 (right) placed on 25mm base layer
ASTM D 448 Aggregated Size No. 8 25mm (Same materials is used to fill in joints between paving stones). Figure 12 Installation of bedding Materials for parking Lot 2 and 3
2.5.2.3. Granular Base Material and Thickness
31
Figure 13 shows images of the two (2) different types of granular base materials installed at Parking Lot 3.
Parking Lot 3 – First 250mm of Granular base Parking Lot 3 – Remaining 200mm of Granular layer was crushed concrete. base layer was clear stone.
Parking Lot 3 – Photo showing granular base profile with both crushed stone and clear stone. Figure 13 Installation of granular base layer
32
Figures 14 are photos of parking lots 2 and 3, taken during construction. Geotextile was installed in parking lot 2 at the interface between bedding and granular base layer but not in parking lot 3.
Geotextile used at Parking Lot #2 between Geotextile not placed at interface between gravel bedding and granular base layers layers in Parking Lot 3 Figure 14 Further details of permeable pavement 2.5.2.4. Underdrain System
A 100mm perforated corrugated PVC sub-drain with geotextile and granular filter material was placed 300mm below the subgrade of both parking lots. As water begins to pond in the subsurface granular base to a depth of over 200mm, excess water will be conveyed through the sub-drains and towards an outlet. All water below the 100mm sub-drain will infiltrate into the ground.
Figure 15 shows the sub-drain detail and photos of the sub-drains being installed during construction. Figure 16 illustrates a cross section of the permeable pavement lots representing as-built conditions.
33
Sub-drain detail Sub-drain layout for Parking Lot 3
Sub-drain installation Parking Lot 3 Sub-drain depth Parking Lot 3 Figure 15 Sub-drain details and installation photos
34
Figure 16 Cross Section of Permeable Pavement in Parking Lot 2 and 3
35
3. Vegetated Swales
Vegetated swales are designed to convey, treat and attenuate stormwater runoff. The swales have shallow longitudinal slopes to promote sedimentation, filtration, evapotranspiration, and infiltration into the underlying native soil.
These swales do not have engineered soil media and an underdrain to promote filtration and therefore have lower performance compared to bioretention facilities. However, vegetated grass swales are a preferred alternative to both curb and gutter and storm drains as a stormwater collection and conveyance system. The vegetated swales located on the CVC property are vegetated with both grass and forest.
Evaluating Vegetated Swale Performance
The following criteria were used for assessing water quality treatment performance:
• The velocity is 0.5 m/s or less for a 4 hour, 25 mm Chicago storm (CVC 2010); • Typical ratios of impervious drainage area to swale area range from 5:1 to 10:1 . The conveyance capacity should match the drainage area and sheet flow to the grass swale is preferable. High discharge through the swale may not allow for filtering and infiltration, and may create erosive conditions.
Figure 17 shows examples of vegetated swales around the perimeter of the parking areas and driveway.
Swale 9 (drains to CB1) Swale 4 (drains to CB 5)
36
Swale 8 (drains to CB 2) Swale 7 (drains to CB 3) Figure 17 Examples of vegetated Swales around the perimeter of the parking areas and the driveway
Note that the swale leading to the DICB 5 has 100mm of topsoil and No. 1 nursery sod. Figure 18 below is a photo of landscaping work taking place in June of 2012.
Figure 18 Landscaping and swale grading around Parking Lot # 2 (June 2011)
37
3.1.1.1. Wet Weather Drainage Patterns
The following images capture a number of different rainfall events at the CVC administration building site and the resulting flow paths. During heavy rainfall events, drainage from the impermeable surfaces sheet flows into the vegetated swales. The swales allow the water to spread out and gently flow towards the catchbasin inlets.
External drainage from catchment 11 flowing Parking lot #3 - overflow spillway into the top of onto parking lot 2 and flowing towards CBMH.4. Swale 3-3.
Parking lot #1 – sheet flow drainage into Swale 9. Swale 9 - low gradient swale conveying drainage towards catchbasin 1 during heavy rainfall event. Figure 19 Wet Weather Drainage Patterns
38
3.2. Major System
Flows exceeding the capacity of the minor system will be conveyed overland generally following the direction of the minor system.
For parking lot 2, the major system flows easterly towards the parking lot entrance and then spills down the asphalt laneway towards the Credit River.
For parking lot 3, the two (2) 600mm CSP culverts will direct flow to the existing swale and have the capacity to convey the 100-year peak flow.
Appendix C illustrates the drainage path and direction of flow for the major system/overland flow routes.
39
3.0. HYDROLOGIC MODELLING
The EPA Storm Water Management Model (SWMM) version 5.1 was used to develop a physical representation of the CVC administration building site for quantifying the stormwater benefits of the existing stormwater management system. Hydrologic modelling using the RUNOFF module was undertaken to help assess peak flow control, water quality treatment and runoff volume reduction from the stormwater features in the CVC administrative property. A hydraulic component of the model is currently under development and will be completed in 2017.
The following three scenarios were modelled:
1. Scenario 1: Pre-Conditions
o Pre-development condition means the 100-year flow from a theoretical “raw” land condition of the site, with an assumed runoff coefficient of 0.25. o All land is assumed to be pervious with a Curve number of 71 based on soil types (Silt-loam)
2. Scenario 2: Post Conditions without Stormwater Control
o Post development without LID refers to the site without any stormwater control (i.e. permeable pavers, rain water harvesting, vegetated swales) o The permeable paver parking lot is assumed to have smooth asphalt surfaces with a Manning’s n of 0.011 o The vegetated swales, S1 and S10 are assumed to be grass lined (short, prairie) with a Manning’s n of 0.15.
3. Scenario 3: Post Conditions with Stormwater Controls (LID Treatment Train)
o Permeable Pavement (Parking lots 2 and 3); o Vegetated Swales; o Rain Water Harvesting Tank (967 L of available active storage). o The vegetated swales, S1 and S10 have dense vegetation (woods with light underbrush) with a Manning’s n of 0.4. o Permeable Pavement Parking Lot 1 and 2 have an infiltration rate of 798 mm/hr and 1952 mm/hr respectively.
Figure 20 is a site plan showing the various subcatchment areas, drainage features and land use types.
40
Figure 20 Catchments Area Delineation for Hydrologic Modelling (Refer to Appendix D) It is important to note that, the hydraulic features of the minor system (catch basins, culverts and storm sewers) have not been modelled in the three scenarios. The hydrologic model assumes that the minor system does not function during the 100 year event. The major flow paths within the CVC site are illustrated in Figure 21 . The major flow route indicates that the north east catchments of the site (C1, C2, C4 and C5) drains towards the ravine, modelled in SWMM with Outfalls 1, 2, 5 and 6). The rest of the site is drained through the parking lots and perimeter swales onto the driveway. Further details of model parameters can be found in Appendix E .
41
Figure 21 Major Flow System of the CVC Office Site (Refer to Appendix C)
Figure 22 is a flow diagram showing the layout of the various catchments. The schematic describes the drainage pattern and the routing that occurs from:
• catchment to swale; • catchment to permeable paver; • catchment to outfall; • swale to outfall, and • swale to permeable pavers.
Figure 23 is a schematic diagram in the EPA SWMM model. Table 17 is a detailed summary of the SWMM Model parameters for Scenario 3. Detailed Model Output can be found in Appendix F .
42
43 Figure 22 Flow Chart of Hydrologic Model Set up
Figure 23 Schematic of Hydrology Model in SWMM. (Refer to Appendix F for detailed Model Outputs)
44
Table 17 SWMM Model Parameters with Catchment Area with LID Features (Scenario 3)
Directly Directly Depression Depression Connected Connected Manning's N Storage - Storage - Total Area Total Area Imp. Area Imp. Area Pervious Pervious Outlet Catchment Catchment Manning's N for Pervious imperv area perv area Weighted Contributes Drainage Catchment (m2) (ha) Soil Type (m2) (ha) Area Area (ha) (Catchment/Outfall) % Imperv Width Slope (%) for Imp Area Area (mm) (mm) Curve # to LID Features C1 2423 0.2423 Silt Loam 39 0.00390 2384 0.23840 S10 1.1 60 111 0.0 0.15 1.27 2.54 71 no Swale C2 2000 0.2000 Silt Loam 839 0.08387 1161 0.1161 S11-2 41.9 300.011 1 0.15 1.27 2.54 82 no Swale C5 1008 0.1008 Silt Loam 954 0.09540 55 0.0055 Outfall 5 94.60 2 1 0.011 0.15 1.27 2.54 82 no mone C6 894 0.0894 Silt Loam 90 0.00900 804 0.0804 Outfall 6 10.1 121 0.011 0.15 1.27 2.54 82 no none C7 671 0.0671 Silt Loam 597 0.05970 74 0.0074 Rain Water Tank 89 14 0 0.011 0.15 1.27 2.54 82 yes RWT C8 265 0.0265 Silt Loam 207 0.02070 58 0.0058 S8 78.1 12 2 0.011.15 1.27 0 2.54 82 Yes Swale C9 645 0.0645 Silt Loam 424 0.04240 221 0.0221 S7 65.8 20 2 0.0110.15 1.27 2.54 82 Yes Swale C10 2688 0.2688 Silt Loam 1745 0.17450 943 0.0943 S9 64.9 27 111 0.0 0.15 1.27 2.54 82 Yes Swale C11 372 0.0372 Silt Loam 173 0.01730 199 0.0199 PP1 46.5 18 11 0.01 0.15 1.27 2.54 82 yes Permeable Paver C13 2957 0.2957 Silt Loam 509 0.05086 2448 0.245 S1 33 30 1 0.011.4 1.27 0 7.62 71 Yes Swale C14A 101 0.0101 Silt Loam 0 0.00000 101 0.0101 PP2A 0 0.5 1 0 0.15.54 0 0 2 Yes Permeable Paver C14B 161 0.0161 Silt Loam 29 0.00290 132 0.0132 PP2B 18 18 2 0.011.15 1.27 0 2.54 82 yes Permeable Paver C14C 43 0.0043 Silt Loam 0 0.00000 43 0.0043 PP2C 0 0.5 1 0 0.154 0 82 2.5 yes Permeable Paver C18 10 0.0010 Silt Loam 10 0.00100 0 0 PP3 100 4 1 0.011 0 1.27 0 0Permeable yes Paver C19 32 0.0032 Silt Loam 16 0.00160 16 0.0016 PP4 50 0.5 1 0.0115 1.27 0.1 2.54 82 Yes Permeable Paver C20 263 0.0263 Silt Loam 79 0.00790 184 0.0184 PP5 30 4 1 0.0115 1.27 0.1 2.54 82 Yes Permeable Paver PP1 817 0.0817 Silt Loam 817 0.00000 0 0 CB4/Outfall 7 100 18 0.7 0 0 1.27 0 0 yesPaver Permeable PP2A 643 0.0643 Silt Loam 643 0.06430 0 0 S3-2 100 18 2 0.011 0 1.27 0 0 yes Swale PP2B 1025 0.1025 Silt Loam 1025 0.10250 0 0 Culvert/Outfall9 100 18 2 0.011 0 1.27 0 0 yesable Paver Perme PP2C 428 0.0428 Silt Loam 428 0.04280 0 0 S3-3 100 18 2 0.011 0 1.27 0 0 yes Swale PP3 469 0.0469 Silt Loam 469 0.04690 0 0 CB4 100 4 0.7 0.011 0 1.27 0 0 yes Permeable Paver PP4 174 0.0174 Silt Loam 174 0.01740 0 0 PP5 100 4 0.7 0.011 0 1.27 0 0 yes Permeable Paver PP5 244 0.0244 Silt Loam 244 0.02440 0 0 CB6 100 4 1 0.011 0 1.27 0 0 Yes Permeable Paver SW 1 1050 0.1050 Silt Loam 0 0.00000 1050 0.105 Outfall 10 0 45 0. 0 0.4 0 7.62 71 no none SW 3-2 150 0.0150 Silt Loam 0 0.00000 150 0.015 S3-3 0 1 0.8 0 0.1554 0 82 2. no none SW 3-3 120 0.0120 Silt Loam 0 0.00000 120 0.012 Culvert/Outfall 09 1 0.5 0 0.15 0 2.54 82 no none SW 4 558 0.0558 Silt Loam 0 0.00000 558 0.0558 Outfall 8 0 1 1.1.15 0 0 0 2.54 82 no none SW 7 70 0.0070 Silt Loam 0 0.00000 70 0.007 CB3 0 1 0.5 0 0.15 02 2.54 no 8 none SW8 40 0.0040 Silt Loam 0 0.00000 40 0.004 CB2 0 1 0.5 0 0.15 02 2.54 no 8 none SW 9 165 0.0165 Silt Loam 0 0.00000 165 0.0165 CB2 0 1 0.4 0 0.1554 0 82 2. no none SW 10 800 0.0800 Silt Loam 0 0.00000 800 0.08 CB1 0 4 0.8 0 0.4 02 7.62 no 8 none SW 11-2 215 0.0215 Silt Loam 0 0.00000 215 0.0215 Outfall 2 0 2 1.8.15 0 0 0 2.54 82 no none Total Area 21501 2.15 9510 0.87 11991.39 1.20
45
3.1. STORMWATER CRITERIA
The following section describes how the site was evaluated based on the applicable SWM criteria.
3.2. Peak Flow Reduction
Using the City of Mississauga intensity-duration frequency curves, the rainfall intensity for the 100yr storm was calculated using the following equation: