Environmental Monitoring Report

Semiannual Report (July to December 2018) April 2019

BAN: SASEC Cox’s Bazar Railway Project Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’ Bazar via Ramu and Ramu to Gundum near Myanmar Border

Prepared by Railway, for the Government of the People’s Republic of Bangladesh and the Asian Development Bank.

This Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH MINISTRY OF RAILWAYS

BAN: SASEC Chittagong – Cox’s Bazar Railway Project Phase-1

Construction of Single Line Dual Gauge Railway Track From Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum near Myanmar Border

Environmental Monitoring Report

Second Semi Annual Report ( July ,2018-to-December,2018)

CURRENCY EQUIVALENTS (as of 31st December 2018)

Currency unit - Taka (Tk) Tk1.00 = $0.012 $1.00 = Tk83.88

ABBREVIATONS

AAQ : Ambient Air Quality ADB : Asian Development Bank BR : Bangladesh Railway CSC : Construction Supervision Consultant DCRP : Dohazari to Cox’s Bazar Railway project DoE : Department of Environment EMP : Environmental Management Plan EMR : Environmental Monitoring Report EMWS : Environmental Management Implementation Work Schedule ESSU : Environmental and Social Safeguards Unit GoB : Government of Bangladesh SASEC : South Asia Sub Regional Economic Cooperation

NOTES In this report, "$" refers to US dollars.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

CONTENTS

EXECUTIVE SUMMARY ...... 1 INTRODUCTION ...... 3 A. Purpose of the Report...... 3 B. Project Description ...... 3 C. Environmental Monitoring Arrangement ...... 5 PHYSICAL PROGRESS OF WORK ...... 6 COMPLIANCE TO CONTRACT SPECIFICATIONS & ENVIRONMENTAL MANAGEMENT PLAN ... 12 SUMMARY OF ENVIRONMENTAL MONITORING ...... 17 A. Construction Period Environmental Quality Assessment ...... 17 1) Air Quality ...... 17 i) Ambient Air Quality Monitoring Frequency, and Locations ...... 17 ii) Ambient Air Quality Monitoring Methodology ...... 18 iii) Analysis of ambient air quality measurement Lot 1 ...... 18 iv) Comparison of air quality Status between baseline and quarterly monitoring results of Lot 1 ...... 20 v) Analysis of ambient air quality measurement Lot 2 ...... 21 vi) Comparison between June, September and December AAQ parameters of Lot 2 ...... 23 2) Noise Quality ...... 24 i) Noise Quality Monitoring Frequency, and Locations ...... 24 ii) Noise Quality Monitoring Methodology ...... 25 iii) Analysis of noise quality measurement of Lot 1 ...... 25 iv) Comparison of noise level status between baseline and quarterly monitoring results of Lot 1 ...... 27 v) Analysis of noise quality measurement Lot 2 ...... 27 vi) Comparison between June, September & December 2018 noise quality parameters of Lot 2 ...... 29 3) Surface Water Quality ...... 30 i) Surface Water Quality Monitoring Frequency and Locations ...... 30 ii) Surface Water Quality Monitoring Methodology ...... 31 iii) Analysis of Surface water quality measurement Lot 1 ...... 31 iv) Comparison of surface water quality status between baseline and quarterly monitoring results ...... 35

ii

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

v) Analysis of Surface water quality measurement Lot 2 ...... 36 vi) Comparison between June, September & December 2018 surface water quality parameters of lot 2 ...... 40 4) Groundwater Quality ...... 41 i) Groundwater quality monitoring frequency and locations ...... 41 ii) Groundwater Quality Monitoring Methodology ...... 42 iii) Analysis of groundwater quality Lot 1 ...... 43 iv) Analysis of groundwater quality Lot 2 ...... 45 v) Comparison between June and September groundwater quality parameters 2018 of Lot 2 ------46 5) Drinking water Quality ...... 47 i) Drinking water quality monitoring frequency and locations ...... 48 ii) Drinking Water Quality Monitoring Methodology ...... 48 iii) Analysis of Drinking Water Quality measurement of Lot 2 ...... 48 6) Noise Meter ...... 49 7) Flora and Fauna ...... 49 B. Construction Period Qualitative Assessment ...... 50 1) Environmental Issue EMP_2.6/H-6.1 (e.g. Noise attenuation measure) ...... 50 2) Air quality and dust control ...... 50 3) Environmental Issue EMP_2.4/H-6.3 (e.g. Protection of Wetlands/Ponds/Rivers/Canals) 51 4) Environmental Issue H_6.6 (Servicing and Operating Equipment) ...... 52 5) Control of Petroleum Product ...... 53 6) Occupational Health and Safety ...... 53 7) Environmental Issue EMP_2.3/H-6.11 (Protection of top soil and erosion) ...... 55 Grievances and Complaints ...... 57 UNANTICIPATED SAFEGUARD ISSUES ...... 57 CONCLUSION...... 57 A. Overall Progress with Implementation of Environmental Safeguard Measures ...... 57 B. Recommendations ...... 58 Appendices ...... 59 Appendix 1: (i) Environmental Management Implementation Work Schedule (EMWS) .. Error! Bookmark not defined. (II) Six month working plan (January 2019 to June 2019) for the DCRP Lot 2 ...... 60

iii

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Appendix 2: Environment Management Plan and Environmental Monitoring Checklist ...... 62 Appendix 3: Environmental Quality Sampling Report ...... 130 Ambient Air Quality Report (ENRAC) for the month of June 2018 ...... 130 Appendix 4: Photo Log ...... 160

List of Table Table 1: Actual Progress (%) between July to December 2018 (Lot 1) ...... 6 Table 2: Actual Progress (%) between July to December 2018 (Lot 2) ...... 6 Table 3: Definitions of terms used to evaluate environmental condition ...... 12 Table 4: Site definitions for active construction sites (Lot 1) ...... 12 Table 5: Site definitions for active construction sites (Lot 2) ...... 13 Table 6: Ambient Air Quality Sampling Locations ...... 17 Table 7: Ambient air quality measurement results (September, 2018) of Lot 1 ...... 18 Table 8: Ambient air quality measurement results (December, 2018) of Lot 1 ...... 19 Table 9: Comparison of air quality Status between baseline (September) and quarterly monitoring (December) results of Lot 1 ...... 20 Table 10: Ambient air quality measurement results (September, 2018) of Lot 2 ...... 22 Table 11: Ambient air quality measurement results (December, 2018) of Lot 2 ...... 23 Table 12: Comparison between quarterly reports for Air Quality Monitoring (June, September & December 2018) of Lot 2 ...... 23 Table 13: Noise quality Sampling Locations ...... 24 Table 14: Noise measurement results (September, 2018) of Lot 1 ...... 25 Table 15: Noise measurement results (December, 2018) of Lot 1 ...... 26 Table 16: Comparison of noise level status between baseline (September, 2018) and quarterly monitoring results (December, 2018) of Lot 1 ...... 27 Table 17: Noise measurement in September, 2018 at Lot 2 ...... 28 Table 18: Noise measurement in December, 2018 at Lot 2 ...... 29 Table 19: Comparison between three quarterly reports for Noise Quality Monitoring (June, September & December 2018) of Lot 2 ...... 30 Table 20: Surface water quality Sampling Locations ...... 30 Table 21: Result of surface water samples (September, 2018) of Lot 1 ...... 33 Table 22: Result of surface water samples (December, 2018) of Lot 1 ...... 34 Table 23: Comparison of surface water quality status between September, 2018 and December, 2018 of Lot 1 ...... 35 Table 24: Result of surface water parameters (September, 2018) of Lot 2 ...... 37 Table 25: Result of surface water parameters (December, 2018) of Lot 2 ...... 39 Table 26: Comparison between quarterly reports for Surface Water Quality Monitoring (September & December 2018) of Lot 2 ...... 41 Table 27: Groundwater quality Sampling Locations ...... 42 Table 28: Result of Groundwater parameters (September, 2018) of Lot 1 ...... 43 Table 29: Result of Groundwater parameters (September, 2018) of Lot 2 ...... 46

iv

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Table 30: Comparison between two quarterly reports (June & September 2018) for Ground Water Quality Monitoring of Lot 2 ...... 47 Table 31: Drinking water quality Sampling Locations ...... 48 Table 32: Result of Drinking water parameters (September, 2018) of Lot 2...... 48 Table 33: Result of Drinking water parameters (December, 2018) of Lot 2 ...... 49 Table 34: Top soil and erosion protection measure at different sites...... 55 Table 35: Recommendations for Improving Contractor Compliance and Progress ...... 58

List of Figure Figure 1: Proposed Location, Alignment and Rail Stations of the Project (Source: EIA, 2017) ...... 4 Figure 2: Safeguards Implementation and Reporting Work Flow ...... 5 Figure 3: Schematic representation of environmental safeguards monitoring status for Lot 1 ..... 14 Figure 4: Schematic representation of environmental safeguards monitoring status for Lot 2 ..... 15

List of Photo

Photo 1 Noise source was identified at BR 124 on 30.07.2018 behind a sensitive receptor (mosque) ...... 160 Photo 2 Major noise generated from generators observed at BR 96 on 27.10.2018 ...... 160 Photo 3: Major noise generated from generators observed at BR 130 on 05.11.2018 ...... 160 Photo 4 Noise source was identified at BR 124 observed on 23.12.2108 ...... 160 Photo 5 Observed air quality during the first pilot pile at BR 124 on 30.07.2018 ...... 160 Photo 6 Construction of CCEC-MAX JV Camp was ongoing and due to rain no dust observed on 11.07.2018 ...... 160 Photo 7: During load test at BR 124 no dust observed due to rain on 15.09.2018 ...... 161 Photo 8: During the last pilot pile no dust was observed at BR 130 on 05.11.2018 ...... 161 Photo 9 Oil tanker provides necessary fuel at different sites observed at Napith Khali on 02.10.2018 ...... 161 Photo 10 Temporary oil storage facility at Link road observed on 06.12.2018 ...... 161 Photo 11 Temporary oil storage facility at BR 129 observed on 23.12.2018...... 161 Photo 12 Temporary oil carrier facility at Ramu Camp observed on 23.12.2018 ...... 161 Photo 13 Lack of PPEs of workers obsered at Ramu Camp on 10.11.2018 ...... 162 Photo 14: Lack of PPEs of workers obsered at Ramu Camp on 21.10.2018 ...... 162 Photo 15: Identified electrical hazard by the consultant at CCECC-MAX JV camp on 3.10.2018 ...... 162 Photo 16: Lack of PPEs (Face Shield) caught red handed by the HSE officer observed at BR 120 on 06.12.2018 ...... 162 Photo 17: Potential suspect of child labor got red handed by the HSE manager at BR 124 on 11.11.2018 . 162 Photo 18 Identified fall from height hazard (lack of full body harness) on 21.10.2018 ...... 162 Photo 19: Lack of proper housekeeping observed at Ramu Laboratory on 10.11.2018 ...... 163 Photo 20: Lack of proper toilet observed at BR 124 on 27.10.2018 ...... 163 Photo 21: Quarterly Noise measurement held at BR 124 on 18.09.2018 ...... 163 Photo 22: Noise source inspection by the Consultant at Napith Khali on 03.10.2018 ...... 163 Photo 23: Enclosure was provided to reduce the noise level as well as to protect the machine from scorching sun observed at BR 124 on 11.11.2018 ...... 163 Photo 24: Quarterly Noise measurement held at BR 124 on 21.12.2018 ...... 163 Photo 25: Air quality monitoring at Ramu camp on 20.09.2018 ...... 164

v

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 26: Dust supression measure took place at BR 124 on 06.12.2018 ...... 164 Photo 27: Dust control measure takes place at Napith Khali Camp on 01.12.2018 ...... 164 Photo 28 Dust control measure includes local road held on 06.12.2018 ...... 164 Photo 29: Water sprinkler was seen at BR 130 on 23.12.2018 ...... 164 Photo 30: Water sprinklers used to clean local road on 20.12.2018 ...... 164 Photo 31: Wetland protection measure was taken at BR 124 observed on 13.11.2018 ...... 165 Photo 32: Wetland protection measure was taken at BR 124 observed on 23.12.2018 ...... 165 Photo 33: Wetland protection measure was taken at BR 120 observed on 06.12.2018 ...... 165 Photo 34: Wetland protection measure was taken at BR 96 observed on 07.10.2018 ...... 165 Photo 35: Wetland protection measure was taken at BR 162 observed on 26.12.2018 ...... 165 Photo 36: Collection of surface water samples at BR 155 on 20.09.2018 ...... 165 Photo 37: Permanent fuel storage area is uder construction at Ramu Camp observed on 10.11.2018 ...... 166 Photo 38: Fully functional 15000 L fuel station with fire prevention facility was observed at Ramu Camp observed on 29.12.2018 ...... 166 Photo 39: Permanent fuel storage area is uder construction at CCECC-MAX JV Camp observed on 29.12.2018 ...... 166 Photo 40: Fuel meter for the Permanent fuel storage at CCECC-MAX JV Camp observed on 29.12.2018... 166 Photo 41: Proper signage was seen at BR 124 on 23.12.2018 ...... 166 Photo 42: Proper barricading was observed at BR 124 on 23.12.2018 ...... 166 Photo 43: Proper housekeeping was ensured on 12.11.2018 ...... 167 Photo 44: Proper housekeeping was ensured on 12.11.2018 ...... 167 Photo 45: Housekeeping is ongoing observed at CCECC-MAX Camp on 22.07.2018 ...... 167 Photo 46: A regular housekeeping is maintained at CMJV camp observed on 19.09.2018 ...... 167 Photo 47: Top soil was stored along the edge of the RoW at Islamabad Station area Ch. 72 observed on 20.11.2018 ...... 167 Photo 48: Top soil was stored along the edge of the RoW at near BR 124 observed on 01.12.2018 ...... 167 Photo 49: Top soil was stored along the edge of the RoW at Cox’s Bazar Station observed on 26.12.2018 168 Photo 50: Top soil was stored along the edge of the RoW at Ramu Station observed on 25.12.2018 ...... 168 Photo 51: Clear, grubbing and stripping works ongoing observed at near BR 130 on 20.11.2018 ...... 168 Photo 52: Top soil was stored along the edge of the RoW at BR 129 observed on 23.12.2018 ...... 168 Photo 53: Stripping work is in progress at Ch. 6+000 ...... 168 Photo 54: HSE Training at site ...... 168 Photo 55: Pilot Pile concreting is in progress at Bridge no. 69 ...... 169 Photo 56: Monthly progress meeting at Engineer office with Lot-1...... 169 Photo 57: BR PD with Engineer Site Visit & Check PVD Installation at Ch.74+500 ...... 169 Photo 58: Rebar Cage Checking Before Installation at Bridge No.124(A1) Working Pile 02...... 169 Photo 59: Completed Clearing & Grubbing at Ch.99+500 to Ch.99+800 (Cox bazar Station area) ...... 169 Photo 60: Static Load Test For Bridge No.124 (A2) Working Pile ...... 169 Photo 61: Pilot Pile Concrete Casting Work Ongoing at Bridge No.162(Ch93+595) ...... 170 Photo 62: HIV Prevention Program at AIDS DAY at Edigon Local Community ...... 170

vi

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

EXECUTIVE SUMMARY

1. Bangladesh Railway has taken numbers of initiative to improve railway connectivity among the South Asian and other Asian countries with Bangladesh. The project for which this semi- annual report has prepared is entitled as “Construction of Single Line Dual Gauge (DG) Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum near Myanmar”. 2. Monitoring works mainly focused on inspection of construction activities during construction period as per approved EMP & EIA for this project. A monitoring checklist has submitted by the Contractor which is already approved by the Engineer and has used in the field level to monitor environmental safeguards. This Semi-annual EMR has gathered all the information, summarized all results and evaluated the overall environmental safeguard status from 1st July of 2018 to 31st December of 2018 for DCRP. 3. Considering the full compliance (C) issues over the reporting period, it is found that significant numbers of checklist items were complied with the standard level or EMP. As the project was at initial stage, most of the issues were found as not applicable (NA) for the specific sites. Beside this, since the commencement of the DCRP, HSE team of CREC-TOMA JV (CTJV) and CCECC-MAX JV (CMJV) has been working proficiently in order to comply with contract agreement, EMP of the EIA and eventually save every sector of environment from the construction effects. 4. During the reporting period, HSE team of CTJV & CMJV has submitted HSE Plan, Traffic Management Plan, Hill Cutting Management Plan and Waste Management Plan to the Engineer for approval. After reviewing the submitted plans, Engineer will approve based on which Contractor will implement environmental safeguards at construction site. According to the Subsection H: Environment Safeguard, a noise decibel meter and calibration tool will be used in the field level for recording spot noise readings as required. Accordingly, HSE team of CMJV has submitted an official letter to the Engineer for their review and approval where it enclosed necessary information such as Noise Meter Model with detailed specification. Consequently, the approval is being done from the Engineer’s side. 5. An environmental expert’s team from the Contractor’s side has conducted 2nd and 3rd Quarter Environmental Sampling from 18th September to 25th September and 19th December to 26th December 2018 respectively to monitor Air Quality, Noise, Surface Water & Groundwater Quality at different sites using sophisticated instrument. The 2nd & 3rd Quarter Environmental Sampling data has attached in this report. As a result, a comparison made between June (baseline survey), September 2018 and December 2018 quarterly findings. 6. Consultant’s environmental team along with the HSE team of CTJV & CMJV has been working on environmental, health and safety issues raised in the field level during regular visits at all construction sites. The team has taken mitigative and monitoring measures when required through physical activity, maintaining records and through reporting of different potential environmental impacts associated with construction activities.

1

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

7. During the site inspection generated noise pollution, dust pollution, disposal of construction waste, maintenance of equipment, pollution & contamination such as leaks & spillage of oils, hill cutting and occupational health & safety arrangement have monitored as a key environmental issue for the reporting period. 8. Overall based on the construction activity and its associated impact, it can likely be concluded that, the project has less significant impact to the environment till now. No major environmental impacts due to project activities have been identified or recorded, therefore, complied with the EMP as well as contract. 9. Furthermore, it is prime duty of all to cooperate to ensure both work place safety and carried out the construction work in an environmentally acceptable manner for the DCRP. Furthermore, to ensure the monitoring and reporting are completed in a compliant and timely fashion, acceptable to BR and ADB.

2

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

INTRODUCTION

A. Purpose of the Report 10. The Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu (about 100.8 Km) was classified as Category Red by the Department of Environment (DoE) and a Category A project by the Asian Development Bank (ADB), thus the EMP of the EIA report designates best applicable available mitigative measures to be taken either to avert negative impacts from taking place or if that is not possible to mitigate them to an acceptable limit. 11. The purpose of this Semi-annual EMR is to gather all the information, summarize all results and evaluate the overall environmental safeguard status from 1st July of 2018 to 31st December of 2018 for DCRP (Lot 1 & Lot 2). Accordingly, this report will reflect the Contractor’s professional effort to comply with contract agreement, EMP of the EIA and eventually save every sector of environment from the construction effects.

B. Project Description 12. The project area covers from Dohazari Upazila of to Cox’s Bazar Sadar Upazila of Cox’s Bazar District via Ramu and it covers Chandanaish, Satkania, and Lohagara Upazilas of Chittagong District; Chakaria, Cox's Bazar Sadar and Ramu Upazilas of Cox’s Bazar District. In addition, nine new rail stations and access roads have been designed for this project (Figure 1). 13. The proposed alignment will cross mainly crop land (59.67%), highland/hilly land (24.78%), orchard/ forest land (8.98%), homestead land (5.58%), and others (0.99%). The areas designated as reserve forest is owned mainly by the Bangladesh Forest Department (BFD). The first 29 km from Dohazari onward consist of flat-open land located in three Upazilas of Chittagong District. The next 33 km fall within the Chakaria Upazila of Cox’s Bazar District and traverse agricultural farmland and some forest land. For the next 33 km, within the Cox's Bazar Sadar and Ramu Upazilas of Cox’s Bazar District, the alignment climbs to about 400 m above sea level and passes through mostly tropical jungle and rural agricultural land.

3

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Figure 1: Proposed Location, Alignment and Rail Stations of the Project (Source: EIA, 2017)

4

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

C. Environmental Monitoring Arrangement 14. The Contractor has engaged an independent environmental monitoring firm who will implement all BoQ items mentioned in the Contract Document. The Engineer will monitor the implemented activities for environmental safeguards and will ensure that, the implementation of EMP has done as per ADB’s Guideline or Policy. 15. When the Engineer is appointed, BR’s technical management of the work will be delegated to the Engineer, but with final approval always passing through BR. Safeguard implementations and reporting workflow has given as needed for the project accomplishment (Figure 2).

Figure 2: Safeguards Implementation and Reporting Work Flow

5

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

PHYSICAL PROGRESS OF WORK 16. Due to issues related to land handover and compensation to the landowners and farmers, the actual target was not fulfilled. Table 1 & 2 shows the actual progress of DCRP Lot 1 & Lot 2 up to end of December 2018.

Table 1: Actual Progress (%) between July to December 2018 (Lot 1) Actual Physical Progress (%) of 2018 Progress Item July August September October November December General 16.55% 21.21% 25.72% 30.38% 34.89% 39.53% Requirements Earthworks 0.11% 0.18% 0.33% 0.44% 0.60% 0.82% Track Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Bridges & Culverts 0.00% 0.02% 0.06% 0.16% 0.26% 0.67% Stations & Buildings 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Ancillary Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Signaling & 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Telecommunication Environmental 0.06% 0.09% 0.15% 0.20% 0.26% 0.31% Safeguards Table 2: Actual Progress (%) between July to December 2018 (Lot 2) Program Item Actual Progress (%) of 2018 July August September October November December General 31.25 31.47 33.32 34.99 35.54 36.06 Requirements Earthworks 0.22 0.22 0.22 0.55 1.60 2.71 Track works 20.47 20.6 20.65 20.65 20.65 20.65 Bridge and 0.07 0.07 0.12 0.24 2.06 3.47 Culverts Stations and 0 0 0 0 0 0 Buildings Ancillary works 0 62.8 62.8 62.8 62.8 62.8 Environmental 0.03 0.3 0.38 0.41 0.61 0.66 Safeguards

17. The overall major activities of the project during the last six months, listed below as per discipline of construction activity. The mentioned construction works have significant environmental impact. Environmental Specialist of DCRP has shown CTJV & CMJV’s efforts to comply with environmental management in accordance with EMP and contract agreement for these activities. To achieve this target, Environment Specialists of CTJV & CMJV has conducted numerous site inspections also.

6

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

18. Earthworks

Lot 1: For the embankment fill and subgrade, approvals have already been given under the mentioned locations:

1 Ch. -02+000 to Ch. 0+000 2 Ch. 06+000 to Ch. 08+000 3 Dredged Material for Embankment fill, Sangu River (Ch0+400) 4 Dredged material for Embankment fill Dulokhal & Matamuhuri River (Ch. 49+200); 5 Borrow pit material source for embankment fill (500m, 2km & 2.5km away from Ch. 0+200) 6 Borrow pit material source for embankment fill (1.5 km away from Sangu river) 7 Borrow pit material source for embankment fill (Dohazari Station area) 8 Borrow pit material source for embankment fill (Right side of Ch: 37+700 to 38+00) 9 Borrow pit material source for embankment fill (Both side of Ch: 39+900 to 40+400) 10 Borrow pit material source for embankment fill (500 m right side of Ch: 38+000 11 Borrow pit material source for embankment fill (600 m left side of Ch: 38+200 12 Borrow pit material source for embankment fill and subgrade (300 m right side of Ch: 38+300 13 Borrow pit material source for embankment fill (200 m right side of Ch: 38+500 14 Borrow pit material source for embankment fill (400 m right side of Ch: 39+200 15 Borrow pit material source for embankment fill (500 m right side of Ch: 39+500 16 Borrow pit material source for embankment fill (100 m right side of Ch: 40+00 17 Existing ground Ch:10+560 to 10+860 18 Borrow pit material source for embankment fill (800 m left side of Ch: 40+700 19 Borrow pit material source for embankment fill and subgrade (300 m left side of Ch: 40+750 20 Borrow pit material source for embankment fill and subgrade (800 m left side of Ch: 41+00 21 Borrow pit material source for embankment fill (1.5 km away from Ch: -00+600

22 Existing ground materials Ch: -1+020 to -1+180, Ch: -1+200 to 3+450, Ch: 5+700 to 5+900, Ch: 6+00 to 6+600, Ch: 5+700 to 5+900 23 Dredged sand materials for embankment filling (source Borokoil), stockyard Dohazari Station at Ch: 0+040

Lot 2: For the embankment fill and subgrade, approvals have already been given under the mentioned locations:

1. Dredge sand at Ch. 86+200, Ch. 88+300 and Ch. 99+000, 2. Embankment Fill at Ch. 99+400, Ch.99+300, Ch.71+350, Ch.69+700, Ch. 69+400, Ch.50+300, Ch.62+100.4 and Ch77+700 3. 890m distance from Ch. 76+810 LHS 4. Existing ground Ch. 99+200 to 99+650.73+950 to 74+450, 74+600 to 74+800,75+00 to 75+980,74+800 to 74+980, and 71+300 to 72+950, 5. 130 m distance from Ch. 78+350 RHS. 6. 550 m distance from Ch. 71+100 LHS. 7. 60m distance from Ch. 71+240 LHS, 8. 400m distance from Ch. 71+600 LHS,

7

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

9. 490 m distance from Ch. 71+800 LHS. 10. Dredged sand materials Ch: 66+00, Ch: 72+200 to 72+900 11. Borrow pit materials Ch: 74+300 12. Borrow pit materials, 891m distance east from Ch: 76+810 13. Existing ground materials Ch: 71+300 to 72+950, Ch: 76+740 to 77+500, Ch: 96+00 to 97+800, Ch; 69+220 to 70+00, Ch: 69+220 to 70+00, Ch: 98+700 to 99+200, Ch: 70+00 to 70+640, Ch: 73+790 to 73+950, Ch: 76+00 to 76+715, Ch: 76+740 to 77+500 14. Borrow pit materials for embankment and subgrade filling from Ch: 71+810

Sampling and Testing Coarse (Dubai) and Fine (Sylhet) aggregates for source finalization; and Sampling & testing of water for concreting work for Dohazari station (Ch. 0+280). All the materials of above locations have been tested and approved. Approval of manufacturer /supplier’s source material of geotextile and PVD has been given for Lot-2. Field sample and testing of geotextile and PVD prior to placing at site have been followed up based on the specification

19. Embankment Construction

Lot 1: No physical work could be started before the last monsoon, during 2017-18, except preparatory works. After monsoon, contractor had commenced earthwork from 2nd fortnight of September 2018. Till November 2018, earthwork was in progress at different stages over a length of 9.92 km.

In December, earthworks over an additional 1.89 km had been commenced. With this, in total earthwork over a length of 11.81 km are in progress with different types of activities such as;

 Clearing, Grubbing and stripping has been completed for 9.57 km and ongoing over 2.24 km  Backfilling has been completed for 389 meter and preparation is in progress for 9.18 km  Laying of separator geotextile with drainage sand blanket has been completed for 80 meter  PVDs have been installed for 80 meter

Collection and stocking of embankment fill materials/sand drainage blanket materials is insignificant. Till, December 2018 contractor has brought 3350 cum sandy soil, 44846 cu.m local sand 16822 cu.m Sylhet sand at site.

Lot 2: Not much of works could be done during FY 2017-18. Embankment works had been commenced at km 99+200 to km 99+ 800 and km 100+600 to km 100+800, total 800 meter. In absence of approved design of retaining wall, conditional approval of RFI had been given during 2017-18 for clearing & grubbing of Cox’s Bazar Station Approach Road, km 0+000 to km 0+290 and work had been commenced.

The work has been restarted after rainy season from September 2018. In addition to previous works, new embankment works over a length of 9.03 km has been commenced. However, design of Retaining Wall of Approach Road leading to Cox’s Bazar Station could not be finalized yet.

8

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

In December, earthwork over an additional 2.803 km had been commenced. With this, in total earthwork over a length of 12.633 km is in progress with different types of activities as;

 Clearing, Grubbing and stripping has been completed for 5.313 km and ongoing over 7.32 km  Backfilling has been completed for 2.533 km and ongoing/under preparation for another 2.78 km  Laying of separator geotextile with drainage sand blanket has been completed for 290 meter and ongoing for 760m.  PVDs have been installed for 500m and ongoing for 160m.  Laying of high strength geotextile has been ongoing for 445m.

A reasonable quantity of embankment fill materials/sand drainage blanket materials have been collected and stocked at site. However, embankment fill materials collected and brought at site around km 68+000 to km 77+000 are sandy and embankment section needs cladding layer while working with the stocked sandy embankment fill materials.

20. Bridges

Lot 1:

a. Bridge No-3: 2 Nos Pilot Piles completed (Near A1 and Near P6) & Integrity Test and Static Load Test completed for Pilot piles. Working plies completed at A1 and started at A2. b. Bridge No-79: Pilot Pile 1 No completed near P1 completed & load test completed c. Bridge No-15: 1 No Pilot Pile near P1 Completed and PIT and load test completed. d. Bridge No-69: 1 No Pilot pile casting completed. Lot 2:

a. Bridge No- 124: 2 Nos Pilot Piles completed. (Near A1 & Near A2) & Integrity Test and Static Load Test completed for Pilot Pile Test near A2 b. Bridge No- 96: 1 No. Pilot Pile completed (near P1) & Integrity Test and Static Load Test Completed near P1 c. Bridge No-130 : 1 No Pilot Pile completed (near A1) d. Bridge No-155 : 1 No Pilot Pile completed (near A2) e. Bridge No-161 : 1 No Pilot Pile completed (near A1) f. Bridge No-147 : 1 No Pilot pile completed (near A2) g. Bridge No-162 : 1 No Pilot Pile completed (near A1)

As on December 2018 total 8 Nos Pilot piles have been completed and Pilot pile load test completed 3 Nos. PIT test completed 4 Nos, PDA test completed 1 No. At the End of Dec 2018 total 56 Working Piles have been completed at Bridge No-124 (30 Nos) , Bridge No-120 (12 Nos) Bridge No- 129 (12 Nos) and Bridge No- 130 (2 Nos) At the End of Dec 2018 Blinding & Pile Cap concrete completed at Pier1 & Pier 2 at Bridge No-124 and also Pier column first lift concrete completed at Pier 2 at same bridge.

9

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

21. Geotechnical

Lot 1: : As per contract, nineteen bridges and five railway stations will be constructed under Lot- 1 Among them, supplementary geotechnical investigation had been planned for sixteen bridges and all the five stations. Field works concerning geotechnical investigation have been completed in September 2018. Final Geotechnical Investigation Report (GIR) for twelve bridges and four stations had been submitted till 31/12/2018 and accepted. Draft GIR for Bridge 29, Bridge 74 and Harbang Station has been reviewed and waiting for final GIR. Contractor still to submit draft GIR for Bridge 22, Bridge 28 and Culvert (1 and 6) investigated by them. Other than these, there are three more bridges (Bridge 18, Bridge 27 and Bridge 71), where previous investigation is present and contractor need to submit their report/comment on existing pile design. The treatment schedule has been revised on available information and may need further amendment depending on the outcome of the remaining GIR.

Lot 2: As per contract, twenty bridges and four railway stations will be constructed under Lot 2. All investigation is completed and report finalized. A revised treatment schedule has been issued for Lot 2.

22. Survey works

Contractors of Lot 1 and Lot 2 have completed the survey and measurements to check the accuracy of the topographic survey control points (PGM, BR points) provided by the Engineer. Joint verification surveys with the Engineer has been done to check the physical conditions and accuracy of these topographic survey control points. The Engineer confirmed and approved 42 and 54 topographic survey control points for Lot 1 and Lot 2 respectively.

Before commencing construction works, the Contractors are continuing the establishment of a system of temporary points using GPS Static, GPS RTK, traverse and 3-wire double run levelling by referencing from the approved topographic survey control points. The Lot 1 has established 192 temporary points in or near the limits of the Right-of-Way while Lot 2 has 208 temporary points. There is ongoing installation of additional temporary points by the Contractors. These temporary points will be used for railway centerline fixing, cross section survey and other survey works in bridges, culverts, stations and level crossings.

In order to facilitate the setting out of construction works, the centerline of the railway has been fixed and marked with pegs at every 20 m interval for the length of 42.5 km for Lot 1 and 51.1 km as completed by Lot 2.

The Contractors have surveyed the terrain along the railway. There are 42.5 km cross section surveys every 20 m interval done by Lot 1 and 51.1 km as completed by Lot 2. Lot 1 has submitted working drawings of cross section for embankment for a total 7.0 km while Lot 2 has submitted the same with a total of 24.3 km.

10

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Topographic survey has been done for 26.7 km in Lot 1 and 51.1 km as completed by Lot 2, where surface features like trees, houses and building structures, roads, bridges and culverts, overhead and underground utilities, water bodies (ponds, ditch, canal, drainage, river) are measured.

Other survey works are done in Lot 1 to check the Land Administration Boundary Pillars against CROW in CH 0+600 to 15+500 and to inspect Bridges Nos. 3, 15, 69 and 79, and Dohazari Station, detailed topo survey at Bridge 15 and 43 with Level Crossings and Graveyard at CH -0+300 to CH - 0+400. Lot 2 inspections were done in Bridge Nos. 96, 120, 122, 123, 124, 129, 130, 147, 155, 161, 162, Cox’s Bazar, Islamabad and Ramu Stations, Access Road, Level Crossings and discrepancy of CROW / BR boundary pillars at CH 83+000 to CH 90+000 and in Cox’s Bazar Station. The Engineer has approved Lot 1 its horizontal alignment while for Lot 2 horizontal and vertical alignment have been approved.

11

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

COMPLIANCE TO CONTRACT SPECIFICATIONS & ENVIRONMENTAL MANAGEMENT PLAN 23. This section reviews the last six months performance of the Project with respect to the Applicable Standards specified in the EMP of the EIA report. This section has been constructed based on the (approved) filled up check list in the field level. Table 3 describes the definitions of terms used to evaluate environmental condition where as Table 4 & Table 5 illustrated definitions of sites including site ID for all active construction site. Environmental Management Plan for construction period mitigative and monitoring measures are described for both Lot 1 & Lot 2 in Appendix 2. Based on the approved, site specific summary of Environmental Monitoring Checklist over the month of July to December 2018 for Lot 1 & Lot 2 are also given in Appendix 2.

Table 3: Definitions of terms used to evaluate environmental condition Rating Definition Complied (C) Information available indicates that the Project fulfills the requirement and/or is aligned with intended outcome of the requirement. Partially Complied Information available indicates that the Project partially fulfills the (PC) requirement and/or is partially aligned with intended outcome of the requirement. Not Complied (NC) Information available indicates that the Project does not fulfill the requirement Not Applicable (NA) The requirements do not apply at the Project current time

Table 4: Site definitions for active construction sites (Lot 1) Chainage Site ID Location Activities (CH) S1 Dohazari Station 0+700 Earthwork activities at nearby station and Servicing activities at nearby batching plant S2 Bridge No. 3 0+463 Load Testing activities of the Bridge. S3 Level Crossing Near Keranirhat 5+860 Earthwork activities

S4 Bridge No. 15 8+170 Pilot Piling Activities and Earthwork activities S5 Satkania Station 8+760 Earthwork activities S6 Near Satkania Degree College 10+560 Earthwork activities S7 Harbang Base Camp 35+500 Construction activities at Base Camp S8 Bridge No. 69 (Near Bethua 44+509 Construction of Camps for workers Bazar) S9 Bridge No. 79 49+766 Construction activities at nearby (Near Chakaria Station) bridge and batching plant

12

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Table 5: Site definitions for active construction sites (Lot 2) Site ID Name/Location Chainage Activities

S1 BR- 96 Ch. 60+175 Pilot Pile Construction completed S2 BR- 120 Ch. 71+298 Pilot pile + Working pile construction

S3 BR- 124 Ch. 73+706 Pilot Pile + Working Pile + Pile cap construction

S4 BR- 129 Ch. 76+029 Working Pile Construction on going

S5 BR- 130 Ch. 76+740 Pilot pile construction completed S6 BR- 147 Ch. 84+886 Pilot Pile construction completed S7 BR- 155 Ch. 90+014 Pilot Pile construction completed S8 BR- 161 Ch. 92+969 Pilot Pile construction completed S9 BR- 162 Ch. 93+595 Pilot Pile construction completed S10 See Table 2; Earthwork only Clearing, Grubbing & Stripping S11 Cox’s Bazar 99+200 to 101+126 Clearing, Grubbing & Stripping Station

S12 Islamabad Ch. 72+480 Clearing, Grubbing & Stripping Station

S13 Ramu Station Ch. 89+129 Clearing, Grubbing & Stripping S14 CCECC-MAX Ch. 71+100 Construction Completed and fully functional Camp

S15 Ramu Ch. 88 Construction Completed and fully functional Laboratory

S16 Ramu Yard Ch. 88+100 Partially completed and construction on going

24. Figure 3 represents the overall status of the environmental safeguards monitoring over six months for Lot 1. It is evident that first three months of this year there was no major activities take place therefore; no issues have been recorded throughout this period. Afterwards, some noticeable activities were started gradually, for instance site preparation, earthwork and construction of Bridge No. 3 and nearby batching plant. From Figure 3, it is evident that record amount (5 out of 67) of non-compliance (NC) issues are found in the month of September in the field level at different sites as because of very initial moment of work and lack of proper 25. management and resource unavailability. However, the condition has been improving overtime and NC issues reduced from 5 to 3 in the end of December.On the other hand, partially compliance (PC) issues are found in highest quantity for instance, 24, 25, 29 and 31 out of 67 environmental monitoring items for the month of September, October, November and December respectively.

13

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Figure 3: Schematic representation of environmental safeguards monitoring status for Lot 1

26. Considering the full compliance (C) issues, over three months, it is found that significant number of checklist items for instance 19 in September, 22 in October, 20 in November and 22 in December, are complied with the standard level or EMP or found in good condition. Finally, there are some issues recorded, where the requirements do not apply at the Project current time which indicated as not applicable NA. And the NA amount was high in number during the commencement of the work. It can be concluded that, based on the statistics of major four months activities, the overall progress of environmental monitoring of this DCRP is good enough (PC) and have huge chances to improve noticeably NC and PC items in the coming months. 27. Figure 4 represents the overall status of the environmental safeguards monitoring over six months period (i.e. July to December 2018) for Lot 2. It is evident that the first three months of the second half of this year there was no major activities take place but started the pilot pile work at different places i.e. Camp construction and Bridge construction at BR 124, BR 96, and BR 130. 28. Besides, during this first three month it was rainy as well, therefore, no significant earthwork was performed. Additionally, sometimes it was hard to maintain proper housekeeping due to torrential rain. Afterwards, some noticeable activities were started gradually, for construction of pilot pile and working pile at 9 different bridge locations, earthworks (i.e. clearing, grubbing and stripping, installation PVD, Placement of Granular Sand Drainage Layer, installation of Geo textile, back filling, embankment filling, establishment of Ramu Lab and Ramu Yard.

14

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

29. Since, there were so many constructions at various places, therefore, it was hard to control eventually found some non-compliance issues. From the Figure 1, it is evident that record amount (12 out of 67) of non-compliance (NC) issues are found in the month of July in the field level at different sites as because of very initial moment of bridge construction works, lack of proper management and torrential rain. 30. However, the condition has been improved overtime and NC issues reduced from 12 to 0 in the end of December. Some partially compliance issues were recorded during this six month period such as in July there were 15 partially comply issues recorded. Likewise in August there were 22, September- 19, October- 16, November-10 and in December there were only 8. On the other hand, a record amount of compliance issues were found during the last six months period. Considering the full compliance (C) issues, during the last quarter, it is found that significant number of checklist items for instance 40 in October, 45 in November and 48 in December, are complied with the standard level or EMP or found in good condition. 31. Finally, there are some issues recorded, where the requirements do not apply at the Project current time which indicated as not applicable NA, for instance, human elephant conflict, and hill cutting. Apparently, these kinds of works not started yet due to land acquisition problem. Finally, it can be concluded that, based on the statistics of major last three months activities, the overall progress of environmental monitoring of this DCRP Lot 2 is good enough and put the level in between partially compliance an compliance. 32. However, there are lot of chances to improve noticeably NC and PC items in the coming months. HSE team of CT JV & CMJV has been working on new issues raised in the field and trying to overcome the worse situation.

Status of environmental safeguards monitoring between July to December 2018

250

200

150

100

No. of environmentlissues 50

0 July August September October November December Overall

NC PC C NA

Figure 4: Schematic representation of environmental safeguards monitoring status for Lot 2

15

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

16

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

SUMMARY OF ENVIRONMENTAL MONITORING

A. Construction Period Environmental Quality Assessment 33. In order to ensure proper implementation of the environmental safeguard requirements during the construction period, the Contractor has appointed Bangladesh Railway approved organization named Environmental and Resource Analysis Center (ENRAC) Ltd., to conduct air quality testing, noise measurements, surface water quality testing, and groundwater quality monitoring and recording on a quarterly basis. The organization has necessary technical resources and work experience to conduct this work credibly. All instrument used by the organization are maintained International Standard and calibrated in accordance with the manufacturer’s instructions. 34. ENRAC has conducted a baseline survey in the field level (26th to 30th of June 2018 at Lot 2 only), second quarterly survey from 18th to 25th September 2018 and the 3rd one between 19th to 26th December 2018 to measure Air, Noise, Surface Water and Ground Water quality at different sites using sophisticated instrument for accurate measurement. A comparison was made based on 2nd and 3rd sampling findings in the report. 35. According to the Clauses H 4.2 to H 4.5, Environmental safeguard implementation program is described in the following:

1) Air Quality 36. During every quarterly survey, air sampling was undertaken at 8 sample stations 2 samples per station, making a total of 16 samples. The objective of this air sampling at 8 different stations under DCRP Lot 1 & 2, is to verify air quality on a quarterly basis in order to make comparisons between pre-development and post-development, detect change, and make

comparisons against a standard. The measured parameters are such as CO, SO2, NO2, PM10,

PM2.5, & Air Temp (°C). The parameters were measured in the field using a real-time sampling device, the Environmental Parameter Air Sampler or EPAS (HAZ-SCANNER, model-HIMM- 6000) built by the Environmental Devices Corporation (EDC), USA. The ambient air quality monitoring was performed in presence of Consultant representatives. i) Ambient Air Quality Monitoring Frequency, and Locations 37. Table 6 shows the three quarters sampling locations of the DCRP.

Table 6: Ambient Air Quality Sampling Locations Lot 1 Lot 2 September December June September December (22 – 25 (19-22 (27-30 June 2018) (18 – 21 (23 – 26 December September December September 2018) 2018) 2018) 2018) AAQ_1 AAQ_1 AAQ_1 AAQ_1 AAQ_1 Dohazari Dohazari Cox’s Bazar Rubberdam Rubberdam Station _Ch Station _Ch Station_Ch100+126 Eidgoan_Ch Eidgoan_Ch 0+700 0+700 73+706 73+706

17

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

AAQ_2 AAQ_2 AAQ_2 AAQ_2 AAQ_2 Lohagara Lohagara Ramu Station_Ch Napit Khali Islamabad Station_ Station _Ch Station _Ch 89+129 Camp_Ch 71+100 Ch 72+480 21+500 21+500 AAQ_3 AAQ_3 AAQ_3 AAQ_3 AAQ_3 Harbang Harbang Islamabad Ramu Yard_Ch Ramu Station_Ch Station _Ch Station _Ch Station_Ch 72+480 88+300 89+129 37+460 37+460 AAQ_4 AAQ_4 AAQ_4 AAQ_4 AAQ_4 Chokoria Chokoria Dulahazra Cox’s Bazar Cox’s Bazar Station _Ch Station _Ch Station_Ch 59+625 Station_Ch100+150 Station_Ch100+150 48+970 48+970

ii) Ambient Air Quality Monitoring Methodology 38. Accordingly, to comply with both the EIA and EMP, the team has taken two samples from each station, the first at the closest sensitive receptors such as settlement areas less than 50m from the track, and the second at around 100 m distance from the centerline of the proposed alignment with maintaining 4hrs time period of continuous monitoring. The parameters were measured in the field using a real-time sampling device. Measurements were recorded continuously using a battery-operated instrument, sampling once every five minutes over a one-hour sample period (the sample time interval is selectable on the EPAS data logger). iii) Analysis of ambient air quality measurement Lot 1 39. The following Table 7 and Table 8 represent the ambient air quality measurements for four different stations during baseline environmental monitoring and second quarterly environmental monitoring respectively.

Table 7: Ambient air quality measurement results (September, 2018) of Lot 1

Sample Sampling Concentration CO SO2 NO2 PM2.5 PM10 ID Location of Ambient Air Quality µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 AQ_1 Dohazari Average 0.44 33.00 3.99 65.36 112.93 Station_0+700 Morning Average 0.57 48.22 2.07 14.71 14.32 Evening AQ_2 Lohagara Average 0.26 50.08 2.0 20.69 44.24 Station_21+500 Morning Average 0.16 34.71 2.0 18.12 42.77 Evening AQ_3 Harbang Average 0.24 62.68 2.0 29.21 39.92 Station_37+460 Morning Average 0.27 50.85 2.0 10.41 28.78 Evening

18

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

AQ_4 Chakaria Average 0.27 75.96 2.0 10.45 28.84 Station_48+970 Morning

Average 0.05 43.55 2.0 10.07 27.38 Evening GoB Air Quality Standards 10 (8 365 (24 100 65 (24 150 (24 hour) 40 hour) 80 (Annual) hour) 15 hour) 50 (1 hour) (Annual) (Annual) (Annual)

Table 8: Ambient air quality measurement results (December, 2018) of Lot 1

Sample Sampling Concentration CO SO2 NO2 PM2.5 PM10 ID Location of Ambient Air Quality1 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 AQ_1 Dohazari Average Station_0+700 Morning 0.19 13.42 5.17 59.72 39.2

Average 0.18 21.17 9.09 27.74 17.81 Evening AQ_3 Harbang Average Station_37+460 Morning 0.08 28.09 7.87 30.55 54.89

Average 0.20 24.31 2.0 25.59 38.28 Evening AQ_4 Chakaria Average Station_48+970 Morning 0.29 26.19 5.16 30.2 63.8

Average 0.01 23.55 5.13 23.49 56.26 Evening Bridge No Average 0.06 2.37 6.13 64.35 61.41 15_8+170 Morning AQ_5 Average 0.32 26.93 4.76 39.52 36.46 Evening GoB Air Quality Standards2 10 (8 365 (24 100 65 (24 150 (24 hour) 40 hour) 80 (Annual) hour) 15 hour) 50 (1 hour) (Annual) (Annual) (Annual)

1Morning: 10.0 am to 2.0 pm Evening: 2.0 pm to 6.0 pm 2The amended Schedule-2, 2005, of (Air Quality Standard) Environmental Conservation Rules, 1997

19

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

40. It is evident from the Table 7 and Table 8 that the Carbon Monoxide concentration ranges from 0.05 to 0.57 µg/m3 during baseline environmental monitoring whereas the concentration ranges from 0.01 to 0.32 µg/m3 during second quarterly environmental

monitoring. Both results comply with the GoB standards. Ambient SO2 concentrations in all sampling locations showed compliance with the specified air quality standards for BD which is 365 μg/³. Measued oetatio ages from . to .μg/³ during baseline environmental monitoring whereas the concentration ranges from . to . μg/³during second quarterly environmental monitoring.

41. Similarly, the measured concentrations for NO2 μg/³ during both baseline and second quarterly environmental monitoring were foud elo the pesied stadads μg/³ annual); ranging from 2.0 to 3.99 µg/m3and 2.0 to 9.09 µg/m3 respectively. Finally, the

concentration of Particulate Matter both PM2.5 & PM10 were measured within the

peissile liit & μg/³ espetiel. oetatioThe of PM2.5 ranges from 10.07 to .μg/³ Baselie Eioetal Moitoig ad . to 64.35μg/³ (Second Quartely Environmental Monitoring). PM10concentration was found14.32 to 112.93 μg/³ Baselie Eioetal Moitoig ad . to . μg/³ Seod Quatel

Environmental Monitoring). PM2.5concentration of AQ_1 was found a fraction higher (65.36 μg/³ tha the stadad liit μg/³. 42. However, the selected AQ_1 (average morning) sampling station (Batching Plant of Dohazari Station) was very near to the main road with considerable vehicle movement. Thus, the

concentration of both PM2.5 & PM10 were found higher at AQ_1 during baseline monitoring.

Only PM2.5 concentration of AQ_5 was found (64.35μg/³ very close to the standard limit μg/³ duig seod uarterly environmental monitoring. However, the selected AQ_5 (average morning) sampling station (Bridge No. 15) was located near the earthwork sites

where clearing and grubbing were taking place. Thus, the concentration of both PM2.5 &

PM10 were found higher at AQ_5 was found higher. iv) Comparison of air quality Status between baseline and quarterly monitoring results of Lot 1 43. Table 9 represents the comparison of air quality status between the baseline environmental monitoring and second quarterly environmental monitoring.

Table 9: Comparison of air quality Status between baseline (September) and quarterly monitoring (December) results of Lot 1 Sample Concentration of Parameters

ID Ambient Air Quality CO SO2 NO2 PM2.5 PM10 μg/³ μg/³ μg/³ μg/³ μg/³ AQ_1 Average Morning (B*) 0.44 33.00 3.99 65.36 112.93 Average Morning (Q*) 0.19 13.42 5.17 59.72 39.2 Average Evening (B) 0.57 48.22 2.07 14.71 14.32 Average Evening (Q) 0.18 21.17 9.09 27.74 17.81 AQ_2 Average Morning (B) 0.26 50.08 2.0 20.69 44.24 Average Morning (Q) - - - - -

20

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Sample Concentration of Parameters

ID Ambient Air Quality CO SO2 NO2 PM2.5 PM10 μg/³ μg/³ μg/³ μg/³ μg/³ Average Evening (B) 0.16 34.71 2.0 18.12 42.77 Average Evening (Q) - - - - - AQ_3 Average Morning (B) 0.24 62.68 2.0 29.21 39.92 Average Morning (Q) 0.08 28.09 7.87 30.55 54.89 Average Evening (B) 0.27 50.85 2.0 10.41 28.78 Average Evening (Q) 0.20 24.31 2.0 25.59 38.28 AQ_4 Average Morning (B) 0.27 75.96 2.0 10.45 28.84 Average Morning (Q) 0.29 26.19 5.16 30.2 63.8 Average Evening (B) 0.05 43.55 2.0 10.07 27.38 Average Evening (Q) 0.01 23.55 5.13 23.49 56.26 AQ_5 Average Morning (B) - - - - - Average Morning (Q) 0.06 2.37 6.13 64.35 61.41 Average Evening (B) - - - - - Average Evening (Q) 0.32 26.93 4.76 39.52 36.46 GoB Air Quality Standards 10 (8 365 (24 hour) 100 65 (24 hour) 15 150 (24 hour) hour) 40 80 (Annual) (Annual) (Annual) 50 (Annual) (1 hour)

Note: B = Baseline Environmental Monitoring; Q = Second Quarterly Environmental Monitoring

44. From the Table 9, it can be concluded that CO and SO2 concentration is showing a decreasing

trend whereas the NO2 concentration is showing an increasing trend from baseline to second

quarterly environmental monitoring. The PM2.5 and PM10 does not show any trend in concentration, that it means those parameter concentrations vary from one sampling station to the other. However, such comparisons can be made only for AQ_1, AQ_3 and AQ_4 as samples were taken from AQ_2 only during baseline monitoring while samples were taken from AQ_5 only during second quarterly monitoring. v) Analysis of ambient air quality measurement Lot 2 45. Analysis of ambient air quality measurement (September, 2018): It is evident from the Table 10 that the Carbon Monoxide concentration ranges from 0.02 to 0.61 µg/m3. The concentration of the samples was found within the DoE air quality standards. Additionally, breathing CO can cause headache, dizziness, vomiting, and nausea which is not recorded at any of our construction sites after having few conversations with workers. Overall due to any construction activities the concentration of CO in our selected stations is not increasing.

46. Ambient SO2 concentrations (which is released from the fossil fuel combustion) in all sampling locations showed compliance with the specified air quality standards for BD which

is μg/³. Despite feuet oeet of ehiles at the sites the oetatio of SO2 does’t sigifiatl iease. Measued oetatio ages fo . to .μg/³.

21

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

47. Similarly, the measured concentration for NO2 μg/³ also foud elo the pesied stadads μg/³ aual. Fiall, the oetatio of PM2.5 values found exceed the peissile liit μg/³, at oth the ap aea due to esee p of feuet oto vehicles movement & PM10 were measued ithi the peissile liit μg/³. The concentration of PM2.5 ages fo . to .μg/³ ad PM10 was found 28.80 to .μg/³. Hoee, at the seleted AAQ_ saplig statio,ost of the paaetes were found higher compared to the other stations as because of various construction’s activities were on going at that location. Overall, the result represents that the construction activities don’t significantly affect the ambient air quality at the site meaning a safe working environment for all.

Table 10: Ambient air quality measurement results (September, 2018) of Lot 2

Sample Sampling Location Sampling CO SO2 NO2 PM2.5 PM10 ID Period µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 AAQ_1 Rubber dam Morning 0.30 45.17 2.00 21.71 47.37 Eidgoan Afternoon 0.04 45.20 2.00 22.97 28.80

AAQ_2 Napit Khali Camp Morning 0.56 74.37 2.00 84.53 118.89 Afternoon 0.61 62.68 2.00 50.22 61.71 AAQ_3 Max Yard Morning 0.02 42.31 2.00 81.18 115.64 Afternoon 0.40 48.14 2.00 30.24 61.72 AAQ_4 Cox’s Bazar Morning 0.28 44.41 2.02 73.26 102.03 Station Afternoon 0.03 41.17 2.00 8.35 75 DoE Air Quality Standards (Schedule-2) 10 (8 365 (24 100 65 (24 150 (24 hour) 40 hour) 80 (Annual) hour) 15 hour) 50 (1 hour) (Annual) (Annual) (Annual)

48. Analysis of ambient air quality measurement Lot 2 (December, 2018): It is evident from the Table 11 that the Cao Mooide oetatio ages fo . to . μg/. The concentration of the samples was found within the GoB air quality standards.

49. Ambient SO2 concentrations in all sampling locations showed compliance with the specified ai ualit stadads fo BD hih is μg/³. Measued oetatio ages fo . to .μg/³. Siilal, the easued oetatio for NO2 .μg/³ to . μg/³ also foud elo the pesied stadads μg/³ aual. The oetatio of PM. alues foud eeed the peissile liit μg/³, at AAQ_ Da- . μg/³, AAQ_ (Day- . μg/³ ad AAQ_ Da- .μg/³) area due to presence of dusty work activities in the morning especially. On the other hand, PM10 were measured within the peissile liit μg/³ ages fo . to .μg/³. 50. Three PM2.5 was found slightly over the acceptable limit set by the DoE (ECR, 1997, Section 2, subsection A, page 204). PM2.5 is carcinogenic which is produced due to the combustion of solid and liquid fuels. Particles can affect both lungs and heart. As per mitigation measures, during the construction period water sprinklers have been using, and avoiding old vehicles

22

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

at the site. However, no objection was found from the workers. Besides, during the dusty work face mask was kept at the site for the workers.

Table 11: Ambient air quality measurement results (December, 2018) of Lot 2

Sample Sampling Location Sampling CO SO2 NO2 PM2.5 PM10 ID Period µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 AAQ_1 Rubber dam Morning 0.29 7.88 35.38 88.13 48.04 Eidgoan Afternoon 0.02 9.03 31.37 43.54 33.47

AAQ_2 Islamabad Station Morning 0.09 8.00 30.83 82.69 24.14 Afternoon 0.37 5.30 42.91 62.71 27.88 AAQ_3 Ramu Station Morning 0.10 6.02 51.09 45.62 18.10 Afternoon 0.25 8.33 46.03 36.38 16.18 AAQ_4 Cox’s Bazar Station Morning 0.28 8.23 36.85 85.34 56.03 Afternoon 0.00 2.28 38.89 63.42 42.31 DoE Air Quality Standards (Schedule-2) 10 (8 365 (24 100 65 (24 150 (24 hour) 40 hour) 80 (Annual) hour) 15 hour) 50 (1 hour) (Annual) (Annual) (Annual)

vi) Comparison between June, September and December AAQ parameters of Lot 2 51. Table 12 representing the comparison between quarterly reports namely, June, September and December 2018 in order to realize the air quality change over time due to influence of the construction activity. It shows that, only PM2.5 found slightly beyond the permissible limit set by the DoE during December at BR 124 (Day- . μg/³, Co’s Baza statio Da- .μg/³, ad Islaaad statio Da- . μg/³ opaig ith Jue ad September. Considerably, it can be concluded that the overall air quality around the project area is under control with hale and hearty condition for all working personnel. There is no significant impact on the existing air quality within the project area.

Table 12: Comparison between quarterly reports for Air Quality Monitoring (June, September & December 2018) of Lot 2

Sampling Date Concentration CO SO2 NO2 PM2.5 PM10 Location of Ambient Air Quality3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 Morning 0.09 166.94 2.00 51.27 51.82 Cox’s June, 2018 Afternoon Bazar 0.00 17.63 2.00 40.37 41.82 Station Morning 0.28 44.41 2.02 73.26 102.03

3 Morning: 10.0 am to 2.0 pm Evening: 2.0 pm to 6.0 pm

23

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

September, Afternoon 0.03 41.17 2.00 8.35 75.00 2018 December, Morning 0.28 8.23 36.85 85.34 56.03 2018 Afternoon 0.00 2.28 38.89 63.42 42.31 BR 124 Morning 0.3 45.17 2.0 21.71 47.37 September,

2018 Afternoon 0.04 45.2 2.0 22.97 28.8 December, Morning 0.29 7.88 35.38 88.13 48.04 2018 Afternoon 0.02 9.03 31.37 43.54 33.47 Islamabad Morning 0.02 25.20 2.0 19.96 24.0 Station June, 2018 Afternoon 0.17 39.00 2.0 33.23 46.46

Morning 0.09 8.00 30.83 82.69 24.14 December, 2018 Afternoon 0.37 5.30 42.91 62.71 27.88 Ramu Morning 0.36 33.30 2.0 16.19 21.91 Station June, 2018 Afternoon 0.09 39.30 2.0 41.02 42.42 Morning 0.10 6.02 51.09 45.62 18.1 December, 2018 Afternoon 0.25 8.33 46.03 36.38 16.18 DoE Air Quality Standards (Schedule-2) 10 (8 365 (24 100 65 (24 150 (24 hour) 40 hour) 80 (Annual) hour) 15 hour) 50 (1 hour) (Annual) (Annual) (Annual)

2) Noise Quality 52. During every quarterly survey, noise sampling was undertaken at 8 sample stations; 2 samples per station, making a total of 16 samples. The objective of this noise sampling at 8 different stations under DCRP Lot 1 & 2, is to verify noise quality on a quarterly basis in order to make comparisons between pre-development and post-development, detect change, and

make comparisons against a standard. The filed level noise was measured in (Leq) dBA using Lutron SL 4033SD Sound Level Meter (Photo 21 & 24). i) Noise Quality Monitoring Frequency, and Locations 53. Table 13 shows the three quarters sampling locations of the DCRP Lot 1 & 2.

Table 13: Noise quality Sampling Locations Lot 1 Lot 2 September December June September December (22 – 25 (19-22 December (27-30 June (18 – 21 (23 – 26 September 2018) 2018) 2018) September 2018) December 2018) NM_1 NM _1 NM_1 NM_1 NM1 Cox’s Bazar

24

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Dohazari Station Dohazari Station Rubberdam Rubberdam _Ch 0+700 _Ch 0+700 Eidgoan Eidgoan NM _2 NM _2 NM_2 NM_2 NM_2 Lohagara Station Lohagara Station Ramu Station Napit Khali Camp Islamabad _Ch 21+500 _Ch 21+500 Station NM _3 NM _3 NM_3 NM_3 NM_3 Harbang Station Harbang Station Islamabad Ramu Yard Ramu Yard _Ch 37+460 _Ch 37+460 Station NM _4 NM _4 NM_4 NM_4 NM_4 Chokoria Station Chokoria Station Dulahazra Cox’s Bazar Cox’s Bazar _Ch 48+970 _Ch 48+970 Station Station Station

ii) Noise Quality Monitoring Methodology 54. The environment team from the CTJV & CMJV has finished data collection from the field to measure required noise quality parameters from the pre-specified (Table 13) locations. Noticeably, the team followed both the EIA and EMP guidelines, therefore, two measurements per station, in two time periods, 1 sample during the day time (after 9.0 am) considerably 100m away from the source point while using a one-hour cycle recording values every minute and 1 sample after 9.00 pm 100m away from the source point using one measurement for 15 minutes with a one-minute interval. Likewise, a total of 16 samples were collected from 8 different sampling stations using Lutron SL 4033SD Sound Level Meter in presence of Consultant representative. iii) Analysis of noise quality measurement of Lot 1 55. Other than the noise from adjacent roads, there are no major noise pollution sources in the Project area. The noise level measurements of four sampling stations, in the day and night from 22nd to 25th September, 2018 during baseline environmental monitoring and 19th to 22nd December 2018 during second quarterly environmental monitoring, are shown in Table 14 and Table 15 respectively. 56. Of the five sampling stations, two stations were very near to the main road. For instance, Chakaria & Dohazari Stations which can be considered as mixed area since there is neither any big industry nor large scale commercial activities take place rather residential area; green fields can be seen very often. On the other hand, Lohagara and Harbang station is situated a bit far from the city crowds within the middle of the remote agricultural land. Consequently, this station can be put in the category of both residential and mixed zone. Bridge No. 15 is the newly added sampling station replacing Lohagara Station during second quarterly environmental monitoring located in a rural setting surrounded by residential houses.

Table 14: Noise measurement results (September, 2018) of Lot 1

Sampling ID Sampling Location Noise level (Leq) dBA Day Night Max. Min Avg. Max. Min Avg. NM_1 Dohazari Station 78.4 39.0 49.1 74.2 35.1 38.5 (Mixed Area)

25

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

NM_2 Lohagara Station 79.8 36.9 48.4 62.2 21.2 37.1 (Mixed Area) NM_3 Harbang Station 60.8 32.1 43.6 58.2 24.7 36.0 (Mixed Area) NM_4 Chakaria Station 61.3 30.9 42 59.5 21.3 33.9 (Mixed Area) Receptor Day (Avg.) Night (Avg.) Silent areas 50/NP 40/NP BD Noise Standards Residential 55/55 45/45 (2006)/World Bank Standard Mixed 60/NP 50/NP (2007) Commercial 70/70 60/70 Industrial 75/70 70/70

Table 15: Noise measurement results (December, 2018) of Lot 1

Sampling ID Sampling Noise level (Leq) dBA Location Day Night Max. Min Avg. Max. Min Avg. NM_1 Dohazari Station 60.9 40.8 45.81 54 35.5 44.57 (Mixed Area) NM_3 Harbang Station 58.1 40.1 48.35 46.4 37.5 40.62 (Mixed Area) NM_4 Chakaria Station 63.2 51.5 57 47.7 33 39.39 (Mixed Area) NM_5 Bridge No. 15 55 41.1 45.46 54.6 34.3 42.46 (Mixed Area) Receptor Day (Avg.) Night (Avg.) Silent areas 50/NP 40/NP BD Noise Standards Residential 55/55 45/45 (2006)/World Bank Standard Mixed 60/NP 50/NP (2007) Commercial 70/70 60/70 Industrial 75/70 70/70

57. The existing general average noise level within the study area varies from 33.9 dBA to 49.1 dBA found near to the batching plant of Chakaria station premises during night time and near the batching plant of Dohazari station area during the daytime respectively. During the second quarterly environmental monitoring, average noise level within the study area varies from 39.39 dBA to 57dBA found near to the batching plant of Chakaria station premises during both day and night time. 58. Noticeably, these recorded values are within the standard of mixed zone land use (DoE, 1997), as well as for the commercial zone, which is the designation for the railway corridor. Being a commercial area, the ambient standard is 70 dBA (day) and 60 dBA (night) (DoE, 2006). All the noise records of both day time and night time data meet the desired standard for mixed zone, residential and commercial area. Overall, the noise measurements were found moderate as all the sampling sites were located in semi-rural to rural setting.

26

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar iv) Comparison of noise level status between baseline and quarterly monitoring results of Lot 1 59. The Table 16 shows comparison of noise level status between the baseline environmental monitoring and second quarterly environmental monitoring. From the Table 16, it can be concluded that the average noise levels, both during day and night time showing an increasing trend from baseline to second quarterly environmental monitoring except for NM_1 during daytime. However, such comparisons can be made only for NM_1, NM_3 and NM_4 as samples were taken from NM_2 only during baseline monitoring while samples were taken from NM_5 only during second quarterly monitoring.

Table 16: Comparison of noise level status between baseline (September, 2018) and quarterly monitoring results (December, 2018) of Lot 1

Sampling ID Environmental Noise level (Leq) dBA Monitoring Day Night Max. Min. Avg. Max. Min Avg. NM_1 Baseline 78.4 39.0 49.1 74.2 35.1 38.5 Second 60.9 40.8 45.81 54 35.5 44.57 Quarterly NM_2 Baseline 79.8 36.9 48.4 62.2 21.2 37.1 Second ------Quarterly NM_3 Baseline 60.8 32.1 43.6 58.2 24.7 36.0 Second 58.1 40.1 48.35 46.4 37.5 40.62 Quarterly NM_4 Baseline 61.3 30.9 42 59.5 21.3 33.9 Second 63.2 51.5 57 47.7 33 39.39 Quarterly NM_5 Baseline ------Second 55 41.1 45.46 54.6 34.3 42.46 Quarterly BD Noise Standards Receptor Day Night (2006)/World Bank Standard Silent areas 50/NP 40/NP (2007) Residential 55/55 45/45 Mixed 60/NP 50/NP Commercial 70/70 60/70 Industrial 75/70 70/70

v) Analysis of noise quality measurement Lot 2 60. Analysis of noise quality measurement (September 2018) of Lot 2: The noise level measurements in the day and night from 18th to 21st September 2018 shown in Table 17. The data were collected from four different sampling stations. Of the four sampling stations, two stations, are very near to the Cox’s Bazar Chattogram high way, for instance, Cox’s Bazar, Max Yard/Ramu Yard which can be considered as mixed area since there is neither any big industry nor large scale commercial activities take place rather residential area, green fields can be seen very often. On the other hand, the remaining Rubber dam and Napith Khali camp

27

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

station is situated a bit far from the city crowds within the middle of the remote agricultural land. 61. Consequently, this station can be put in the category of both residential and mixed zone. The existing general average noise level within the study area varies from 63.17 dBA to 69.41 dBA found near to the Rubber dam area during night time and daytime respectively. Noticeably, these recorded values are slightly above the standard of both mixed and commercial zone land use (DoE, 1997). Being a mixed area, the ambient standard is Leq 60 dBA (daytime), and Leq 55 dBA (night time), and for the commercial area it is 70 dBA (day) and 60 dBA (night) (DoE, 2006). Most of the noise records during the day time data exceed the desired standard for mixed zone that varies from 58.68 to 69.41 dBA, however, on the other hand night measurements meet the minimum standard (ranges from 47.38 dBA to 63.17 dBA) but one that recorded at the rubber dam area which was 63.17 dBA because of rain drops sound. As the day and night time noise monitoring for each location has conducted parallelly (same location at same date). To maintain this, the night time measurement of noise at rubber Dam Area has conducted at the time of rainfall. Overall, the noise measurements were higher than what one would expect in a totally rural setting.

Table 17: Noise measurement in September, 2018 at Lot 2

Sampling ID Sampling Location Noise level (Leq) dBA Day4 Night5 Avg. Avg. Rubber dam Eidgoan NM_1 69.41 63.17 (Residential & Mixed Area) Napit Khali Camp (Residential & NM_2 68.16 47.38 Mixed Area) NM_3 Max Yard (Mixed Area) 60.41 47.89 Cox’s Bazar Station (Mixed NM_4 58.68 49.82 Area) Receptor Day Night (Avg.) (Avg.) Silent areas 50/NP 40/ NP BD Noise Standards (2006)/World Residential 55/55 45/45 Bank Standard (2007) Mixed 60/NP 50/NP Commercial 70/70 60/70 Industrial 75/70 70/70

62. Analysis of noise quality measurement (December 2018) of Lot 2: As there is no major noise pollution sources in the project areas and the nearby road located at more than 2 km away, the noise level is found within the acceptable level of ECR 1997 of DoE. The noise level

4 Day measurements taken in the morning after 9.0 am 5 Night measurement taken after 9.0 pm

28

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

measurements in the day and night from 23rd to 26th of December 2018 shown in Table 18. The data were collected from four different sampling stations (See Table 13) of the DCRP of Lot 2 as selected by the Engineers. Of the four sampling stations, two stations, are very near to the Cox’s Bazar Chattogram high way, for instance, Cox’s Bazar, Ramu Yard which can be considered as mixed area since there is neither any big industry nor large scale commercial activities take place rather residential area, green fields can be seen very often. 63. On the other hand, the remaining Rubber dam and Islamabad station is situated a bit far from the city crowds within the middle of the remote agricultural land. Consequently, this station can be put in the category of both residential and mixed zone. The existing general average noise level within the study area varies from 51.7 dBA to 48.8 dBA in Rubber dam area during day time and night time respectively which is under the standard of both mixed and commercial zone land use (DoE, 1997). Being a mixed area, the ambient standard is Leq 60 dBA (daytime), and Leq 55 dBA (night time), and for the commercial area it is 70 dBA (day) and 60 dBA (night) (DoE, 2006). Overall, the noise measurements during this quarter were found within the acceptable level.

Table 18: Noise measurement in December, 2018 at Lot 2

Sampling ID Sampling Location Noise level (Leq) dBA Day Night Avg. Avg. BR 124 (Residential & NM_1 51.7 48.8 Mixed Area) Islamabad Station NM_2 43.5 47.0 (Residential Area) NM_3 Ramu Station (Mixed Area) 45.9 45.2 Cox’s Bazar Station (Mixed NM_4 44.9 46.1 Area) Receptor Day Night (Avg.) (Avg.) Silent areas 50/NP 40/ NP BD Noise Standards (2006)/World Bank Residential 55/55 45/45 Standard (2007) Mixed 60/NP 50/NP Commercial 70/70 60/70 Industrial 75/70 70/70 vi) Comparison between June, September & December 2018 noise quality parameters of Lot 2 64. A comparison is made based on quarterly reports i.e. June, September and December 2018. Table 19 shows that September data found slightly over the permissible standard (Day- 69.41 & Night- 63.17 dBA) at BR 124. Noticeably, at that time many construction activities were on going therefore, exceeds the limit. Overall the noise quality under DCRP Lot 2 is under control and have no such negative impact identified on the workers. Additionally, noise barricading is provided as per controlling excessive noise near generator and workers usually don’t work nearby noise source for long time. Therefore, there is no objection recorded from the workers as well as from the local regarding the noise pollution at the construction sites.

29

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Table 19: Comparison between three quarterly reports for Noise Quality Monitoring (June, September & December 2018) of Lot 2

Sampling ID Date Noise level (Leq) dBA Day Night Avg. Avg. June 59.29 54.64 Cox’s Bazar Station September 58.68 49.82 December 44.9 46.1 BR 124 September 69.41 63.17 December 51.7 48.8 Islamabad Station June 55.73 68.81 December 46.5 47.0 Ramu Station June 52.56 55.68 December 45.9 45.2

3) Surface Water Quality 65. During every quarterly survey, surface water sampling was undertaken at 8 sample stations; 2 samples per station, making a total of 16 samples. The objective of this surface water sampling at 4 different stations under DCRP Lot 1 & 2, is to verify water quality on a quarterly basis in order to make comparisons between pre-development and post-development, detect change, and make comparisons against a standard. The measured parameters are

such as pH, Turbidity, Temperature, DO, BOD5, COD, TSS, TDS, Oil and grease. The collected sample water was tested at reputed scientific laboratory in Bangladesh i.e. DPHE & BCSIR. The surface water quality monitoring was performed for the DCRP in presence of Consultant representative. i) Surface Water Quality Monitoring Frequency and Locations 66. Table 20 shows the three quarters sampling locations of the DCRP.

Table 20: Surface water quality Sampling Locations Lot 1 Lot 2 September December June September December (23 September (22 December (30 June 2018) (21 September (26 December 2018) 2018) 2018) 2018) SW_1 SW_1 SW_1 SW_1 SW_1 Near Dohazari Near Dohazari Rubberdam Bridge no.161 Bridge no.161 Station _Ch Station _Ch Eidgoan Near Umkhali Near Umkhali +463_Bridge +463_Bridge Bazar Bazar No. 3 No. 3 SW_2 SW_2 SW_2 SW_2 SW_2 Bridge No. 38 Bridge No. 38 Ramu Tea Near Bakkhali Near Bakkhali River _Ch 25+131 _Ch 25+131 Garden River Bridge no.155 Bridge no.147 Bridge no.155 SW_3 SW_3 SW_3 SW_3 SW_3

30

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Bridge No. 69 _ Bridge No. 69 _ Near Bakkhali Rubberdam Rubberdam Ch 44+509 Ch 44+509 River Eidgoan Eidgoan Bridge no.155 Bridge no.124 Bridge no.124 SW_4 SW_4 SW_4 SW_4 SW_4 Bridge No.79 Bridge No.79 Dakkhin Bridge no.96 Bridge no.96 _Ch 49+766 _Ch 49+766 Mithasara Near Near Dulahazara Bridge no.161 Dulahazara Safari Park Safari Park (Mondirar Khal) (Mondirar Khal)

ii) Surface Water Quality Monitoring Methodology 67. According to the Clause 2.4.1 of the EMP, samples were collected at four proposed bridge crossing sites: two water samples per bridge: one 25m upstream and 25m downstream from the planned bridge alignment. Prior starting the sampling procedure, the team dressed appropriate PPEs. However, due to shallow water level of the source, sometimes it was not possible to maintain 1.5m depth. The collected water samples were poured into 1 plastic and 2 amber bottles (for E. coli and Oil & grease), then put some marking to identify them later before analysis and stored according to standard methods and analyzed within 24 hours of being collected at an ISO14000-certified laboratory. iii) Analysis of Surface water quality measurement Lot 1 68. Rivers, canals, and ponds water quality within the proposed alignment of the DCRP is one of the key concerns as they are used for drinking and domestic purpose, irrigation and aquatic life including fish and fisheries. Thus, it was a requisite to test surface water quality of the project area. Accordingly, four sampling stations were identified using GPS coordinates, with one station upstream and one downstream of the crossing area, for a total of 8 sampling points along the proposed alignment. 69. After collecting surface water quality samples, they were sent to the laboratory for testing the necessary parameters including Temperature, Turbidity, pH, TDS,TSS, Fe, DO, COD, BOD, Total P, Oil, and Grease. Department of Public Health Engineering (DPHE) and Bangladesh Council of Scientific and Industrial Research (BCSIR), Dhaka are the organization that tested the required parameters from the submitted samples and provided test reports enclosing in their official letter heading. Results of the water tests are shown in Table 26 and Table 27 respectively. 70. COD: The following Table 21 represents the laboratory analysis results of baseline environmental monitoring. It shows that the level of COD was found highest in all the upstream and downstream samples. COD value varies from 4.00 to 32 mg/l, most of which exceeds the permissible limit (4mg/l) of Bangladeshi standard (except the D/S concentrations at SW_2 and SW_3). In the second quarterly environmental monitoring (Table 22), COD value varies from 4 to 72 mg/l. Higher COD values were found only in both upstream (72 mg/l) and downstream (64 mg/l) water samples of SW_4 where utensils washing and bathing activities of local people was observed during sample collection. The upstream COD of SW_1 was also found higher (20 mg/l) than the acceptable limit.

31

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

71. BOD: Natural waters will have a BOD of 5mg/l or less. BOD directly affects the amount of dissolved oxygen in rivers or streams. The greater the BOD, the more rapidly oxygen is depleted in the stream. During the baseline environmental monitoring, the BOD values vary between 1.10 to 2.20 mg/l in only three out of eight collected water samples. No BOD value was found in five of the collected water samples, indicating less pollution load on water. The results of second quarterly environmental monitoring show the BOD values vary between 1 to 20 mg/l in eight collected water samples. Higher BOD values were found in both upstream (20 mg/l) and downstream (17 mg/l) water samples of SW_4 where utensils washing and bathing activities of local people was observed during sample collection. ADB (1994) and GoB (1997) proposed BOD of 10 mg/l in irrigation water quality standards for Bangladesh. 72. DO: Dissolved Oxygen or free oxygen is needed for respiration of aquatic organisms. It is evident that the DO levels below 1 mg/l will not support fish population, thus, 5 to 6 mg/l are required for fish survival. DO values in our collected samples are varied between 6.90 to 7.64 mg/l during baseline environmental monitoring and 4.8 to 7.02 mg/l during second quarterly environmental monitoring, indicating average quality of river/canals water. 73. TDS: Total Dissolve Solids (TDS) refers to the sum of all the components dissolved in water. Noticeably, the water that contains too much dissolve matter is not for common uses, therefore, the standard limit set for Bangladesh is 500 to 1000 mg/l. TDS in the collected samples were varied from 29.40 to 184.20 mg/l during baseline environmental monitoring and 25 to 142 mg/l during second quarterly environmental monitoring which is slightly less than baseline concentration. Comparison between tested values and standard value shows higher difference of concentrations in upstream and downstream samples of SW_1 and SW_3, while the samples of SW_2 and SW_4 shows relatively closer upstream and downstream concentrations during baseline environmental monitoring. During second quarterly environmental monitoring, higher difference of concentrations in upstream and downstream samples was found inSW_4 only while the samples of SW_1, SW_2 and SW_3 showed relatively closer upstream and downstream concentrations. Overall, the collected water samples showed TDS concentrations of less than 200 mg/l, thus indicating the water moderately suitable for common use. 74. TSS: The level of TSS found in the samples range between 58 to 224 mg/l during baseline monitoring while 7 to 15 mg/l range was found during second quarterly environmental monitoring which is quite low compared to the baseline concentration. However, the set standard is 150 mg/l. Accordingly, the downstream concentration of SW_1 and SW_3 exceeds the standard limit during baseline monitoring (158 and 224 mg/l respectively) 75. Turbidity: Turbidity values of the surface water samples range between 9.0 to 296 NTU during baseline monitoring and reduced to 1.04 to 37.3 NTU during second quarterly environmental monitoring. However, the set standard value is 10 NTU. All the collected samples show higher concentration of turbidity during baseline monitoring while only SW_2 show higher concentration of turbidity due to its shallow water depth and local people and cattle movement by foot crossing the canal during second quarterly environmental monitoring. 76. Oil and Grease: The concentration of oil and grease in most of the surface water sample were found 8 to 35 mg/l in the surface water sample which is beyond the standard limit for

32

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Bangladesh (< 1 mg/l). During second quarterly environmental monitoring, the oil and grease concentration reduced to less than 2 mg/l which is slightly beyond the standard limit for Bangladesh (< 1 mg/l). At SW_2, the upstream concentration was found 3.6 mg/l. In the selected surface water bodies, water usually used for irrigation, fishing and sometimes washing utensils and bathing purposes which give an indication of slightly higher level of oil and grease concentration. 77. pH: There is less significant version of pH in various sampling stations and the tested samples ranged from 6.80 to 7.57 during baseline monitoring and 6.9 to 7.3 during second quarterly environmental monitoring. The set standard is 6.5 to 8 .5 (FAO, 1992) indicating suitability of water for common purposes.

Table 21: Result of surface water samples (September, 2018) of Lot 1 Sample Sampling Results ID Location Tem BOD COD DO TDS TSS Turbidity pH Oil and Grease

°C (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) NTU - (mg/l)

SW_1 (25m 30.4 Nil 8 7.46 118.20 96 138 7.15 20 Bridge U6/S) No. 3 SW_1

(25m 31.2 1.20 16.0 7.11 29.40 224.0 296 6.8 35 D7/S) SW_2 (25m 31.3 1.10 12.0 7.57 154.80 68.0 37.9 7.57 16.0 U/S) Bridge SW_2 No. 38 (25m 32.6 Nil 4.0 7.53 183.60 83.0 47.30 7.05 12.0 D/S) SW_3 (25m 30.8 2.20 32 7.62 117.0 117.0 9.72 6.95 31.0 U/S) Bridge SW_3 No. 69 (25m 31.5 Nil 4.0 6.90 50.40 158.0 156.0 7.20 8.0 D/S) SW_4 (25m 32.4 Nil 8.0 7.64 148.0 80.0 43.6 6.85 14 U/S) Bridge SW_4 No. 79 (25m 32.9 Nil 8.0 7.50 184.20 58.0 48.0 7.10 20 D/S)

6U/S – Up Stream 7D/S – Down Stream

33

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Bangladeshi - 5- 50010- 6.5- 49 150 10 < 1 Standards 108 100011 8.5

Table 22: Result of surface water samples (December, 2018) of Lot 1 Sample Sampling Results ID Location Tem BOD COD DO TDS TSS Turbidity pH Oil and Grease

°C (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) NTU - (mg/l)

SW_1 (25m 22.3 6 20 6.32 104 12 3.6 7.3 <2 Bridge U/S) No. 3 SW_1

(25m 22.4 2 8 6.8 103 13 6.4 7.3 <2 D/S) SW_2 (25m 22.3 2 8 6.72 26 15 37.3 7 <2 U/S) Bridge SW_2 No. 38 (25m 22.4 1 4 6.97 25 14 36.9 6.9 3.6 D/S) SW_3 (25m 22.5 1 4 6.90 97 7 1.04 7 <2 U/S) Bridge SW_3 No. 69 (25m 22.4 1 4 7.02 100 9 5.72 7.1 <2 D/S) SW_4 (25m 22.4 20 72 4.8 102 12 3.3 7.2 <2 U/S) Bridge SW_4 No. 79 (25m 22.2 17 64 5.07 142 10 2.97 7.2 <2 D/S) Bangladeshi - 5- 50014- 6.5- 413 150 10 < 1 Standards 1012 100015 8.5

8 The Schedule-3(A) of (Standards for Inland Surface Water) Environmental Conservation Rules, 1997, has been considered 9DoE Standard, 2001 10 Bangladesh Standard for Fisheries (EQS,1997), Domestic Standards (De, 2005) 11 Drinking Standards (ADB,1994) 12 The Schedule-3(A) of (Standards for Inland Surface Water) Environmental Conservation Rules, 1997, has been considered 13DoE Standard, 2001 14 Bangladesh Standard for Fisheries (EQS,1997), Domestic Standards (De, 2005) 15 Drinking Standards (ADB,1994)

34

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

iv) Comparison of surface water quality status between baseline and quarterly monitoring results 78. The Table 23 below shows comparison of surface water quality status between baseline and quarterly monitoring results.

Table 23: Comparison of surface water quality status between September, 2018 and December, 2018 of Lot 1 Parameters Sample Environmental DO TSS Oil and Temp. BOD COD TDS Turbidity pH ID. Monitoring Grease °C (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) NTU - (mg/l) SW_1 Baseline 30.4 Nil 8 7.46 118.2 96 138 7.15 20 U/S Second 22.3 6 20 6.32 104 12 3.6 7.3 <2 Quarterly SW_1 Baseline 31.2 1.20 16 7.11 29.40 224.0 296 6.8 35 D/S Second 22.4 2 8 6.8 103 13 6.4 7.3 <2 Quarterly SW_2 Baseline 31.3 1.10 12 7.57 154.8 68.0 37.9 7.57 16.0 U/S Second 22.3 2 8 6.72 26 15 37.3 7 <2 Quarterly SW_2 Baseline 32.6 Nil 4 7.53 183.6 83.0 47.30 7.05 12.0 D/S Second 22.4 1 4 6.97 25 14 36.9 6.9 3.6 Quarterly SW_3 Baseline 30.8 2.20 32 7.62 117.0 117.0 9.72 6.95 31.0 U/S Second 22.5 1 4 6.90 97 7 1.04 7 <2 Quarterly SW_3 Baseline 31.5 Nil 4 6.90 50.40 158.0 156.0 7.20 8.0 D/S Second 22.4 1 4 7.02 100 9 5.72 7.1 <2 Quarterly SW_4 Baseline 32.4 Nil 8.0 7.64 148.0 80.0 43.6 6.85 14 U/S Second 22.4 20 72 4.8 102 12 3.3 7.2 <2 Quarterly SW_4 Baseline 32.9 Nil 8.0 7.50 184.2 58.0 48.0 7.10 20 D/S Second 22.2 17 64 5.07 142 10 2.97 7.2 <2 Quarterly Bangladeshi Standards - 500- 6.5- 5-10 4 150 10 < 1 1000 8.5

79. From the Table 23, it can be seen that, parameters like Temperature, TSS, Turbidity and Oil and grease shows a decreasing trend whereas BOD shows an increasing trend from baseline to second quarterly monitoring. DO and TDS are also showing a decreasing trend except for the sample SW_3 D/S (DO) and SW_1 D/S and SW_3 D/S respectively. In case of COD, three out of eight samples are showing increasing trend (SW_1 U/S, SW_4 U/S and SW_4 D/S), another three is showing decreasing trend (SW_1 D/S, SW_U/S and SW_3 U/S) and the rest

35

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

two remain unchanged (SW_2 D/S and SW_3 D/S). In case of pH, half of the samples showing an increasing trend whereas other half is showing a decreasing trend. v) Analysis of Surface water quality measurement Lot 2 80. Analysis of Surface water quality measurement Lot 2 (September, 2018): During the second quarter, Bangladesh Council of Scientific and Industrial Research (BCSIR) organization in Chattogram has tested the required parameters from the submitted samples and provided test reports enclosing in their official letter heading. Based on the test report, following parameter wise brief descriptions are given. 81. COD: The following Table 24 represents the laboratory analysis results. It shows that the level of COD, was found highest in most of the upstream and downstream samples. During this study, COD value varies from 0.00 to 52.00 mg/l that exceeds the permissible limit (4mg/l) of Bangladeshi standard. The found COD values are harmful for the aquatic organism and the water only can be used for irrigation purposes. Noticeably, no construction activity has been started yet nearby Bakkhali River but still found a higher concentration (52mg/l & 24mg/l). In this regard, the river water might be affected in the upstream with the industrial effluent and our project activity is not liable for this level of COD concentration at the surface water. 82. BOD: Unpolluted, natural waters will have a BOD of 5mg/l or less. BOD directly affects the amount of dissolved oxygen in rivers or streams. The greater the BOD, the more rapidly oxygen is depleted in the stream. Accordingly, the study shows the BOD values that varies between 0.0 to 8.0 mg/l with less deviation means good quality of river or stream water. The highest value recorded was 8.0mg/l in the upstream water sample of the Bakkhali River. However, ADB (1994) and GoB (1997) proposed BOD of 10 mg/l in irrigation water quality standards for Bangladesh. 83. TDS: Total Dissolve Solids (TDS) refers to the sum of all the components dissolved in water. Noticeably, the water that contains too much dissolve matter is not for common uses, therefore, the standard limit set for Bangladesh is 500 to 1000 mg/l. TDS in the collected samples were varied from 45.24 to 182.42 mg/l. Comparison between tested values and standard value show a small variation and the field value is less than the standard acceptable limit thus the river/canals water is moderately suitable for common use. 84. DO: Dissolve Oxygen or free oxygen is needed for respiration of aquatic organisms. It is evident that the DO levels below 1 mg/l will not support fish population, thus, 5 to 6 mg/l are required for fish survival. DO values in our collected samples are varied between 6.4 to 7.76 mg/l, indicates the average quality of river/canals water. 85. TSS: The level of TSS found in the samples range between 4.0 to 310.0 mg/l, however, the set standard is 150 mg/l. Noticeably, most of the tested samples exceed the standard limit and found highest 310.0 mg/l at the Bridge location 96. 86. Turbidity: Turbidity values of the surface water samples range between 21.3 to 288.0 NTU whereas the set standard value is 10 NTU. All the collected samples show higher concentration of turbidity. The increased turbidity could also have been due to the monsoon rains. The higher concentration might be because of dissolve particulate matter including sediment from the upstream due to surface runoff - especially clay and silt, fine organic and

36

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

inorganic matter, soluble colored organic compounds, algae, and other microscopic organisms. The project activity is not harming the existing water quality anyway. 87. Oil and Grease: The concentration of oil and grease were found higher (ranges from 7.0 to 65.0 mg/l) in the surface water sample which is beyond the standard limit (<1 mg/l) for Bangladesh. The selected surface water usually used for irrigation, fishing, sometimes bathing and boating (both shallow engine and manual) purposes etc. were observed during sample collection. However, the set BD standard is applicable for drinking water on the other hand 10mg/l is applicable for industrial discharge. Since, the construction activities are not started in these selected sampling locations, therefore, project impact will not be accounted here right now. The higher concentration of Oil & Grease in the tested water may be caused due to spillage of oils from the engine boats or from the irrigation pumps.

Table 24: Result of surface water parameters (September, 2018) of Lot 2 Sample ID Sampling Results Location Tem BOD COD DO TDS TSS Turbidity pH Oil and Grease °C (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) NTU - (mg/l) SW_01 BR 161 31.4 0.0 0.0 6.4 84.0 238.0 70.1 6.98 45.0 (25m U16/S) SW_01 31.6 4.0 20.0 6.64 86.42 31.0 62.5 7.64 12.0 (25m D17/S) SW_02 BR 155 30.2 8.0 52.0 6.96 45.24 280.0 164.0 7.30 65.0 (25m U/S) SW_02 30.6 2.5 24.0 6.91 48.14 292.0 288.0 7.39 7.0 (25m D/S) SW_03 BR 124 32.1 0.0 4.0 7.76 48.72 230.0 90.2 7.85 25.0 (25m U/S) SW_03 31.5 1.80 16.0 6.95 50.46 136.0 88.6 7.55 18.0 (25m D/S) SW_04 BR 96 32.4 3.0 24.0 7.0 182.42 310.0 21.3 6.77 16.0 (25m U/S) SW_04 32.8 3.2 24.0 7.25 174.58 4.0 27.1 7.19 22.0 (25m D/S) Bangladeshi Standards 5- 50020- 6.5- - 419 150 10 < 1 (DoE) 1018 100021 8.5 Data Source: Sample based laboratory test reports

16 U/S – Up Stream 17 D/S – Down Stream 18 The Schedule-3(A) of (Standards for Inland Surface Water) Environmental Conservation Rules, 1997, has been considered 19 DoE Standard, 2001 20 Bangladesh Standard for Fisheries (EQS,1997), Domestic Standards (De, 2005) 21 Drinking Standards (ADB,1994)

37

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

88. Analysis of Surface water quality measurement Lot 2 (December, 2018): Rivers, canals, and ponds water quality within the proposed alignment of the DCRP Lot 2 is one of the key concerns as they are used for drinking and domestic purpose, irrigation and aquatic life including fish and fisheries. Thus, it was a requisite to test surface water quality of the project area. Accordingly, four sampling stations were identified using GPS coordinates, with one station upstream and one downstream of the crossing area, for a total of 8 sampling points along the proposed alignment (See Appendix 5 for locations). 89. After collecting surface water quality samples, the sealed bottles were sent to the Department of Public Health Engineering (DPHE) and Bangladesh Council of Scientific and Industrial Research (BCSIR) Dhaka laboratory for testing the necessary parameters including Temperature, Turbidity, pH, TDS, TSS, Fe, DO, COD, BOD, Total P, Oil, and Grease. 90. COD: The following Table 25 represents the laboratory analysis results. It shows that the level of COD, was found highest in most of the upstream and downstream samples. During this study, COD value varies from 20.00 to 176.00 mg/l that exceeds the permissible limit (4mg/l) of Bangladeshi standard. Higher COD levels mean a greater amount of oxidizable organic material in the sample, which will reduce dissolved oxygen (DO) levels. A reduction in DO can lead to anaerobic conditions, which is deleterious to higher aquatic life forms. Noticeably at BR 96 the concentration was found higher (176 mg/l). Moderated deviation of river COD values refers moderate quality of the river water for fish or other aquatic organisms and applicable for irrigation purposes. Additionally, there is less chances to affect the water quality due to bridge construction since, proper barricading is provided and no chemical solvent is thrown away to the canal or river water. 91. BOD: Unpolluted, natural waters will have a BOD of 5mg/l or less. BOD directly affects the amount of dissolved oxygen in rivers or streams. Accordingly, the study shows the BOD values that varies between 5.0 to 46.0 mg/l. Among the four sampling stations, BOD found highest at BR 96 downstream sample (46mg/l) and BR 161 (12 & 16 mg/l for up and down stream water). However, ADB (1994) and GoB (1997) proposed BOD of 10 mg/l in irrigation water quality standards for Bangladesh. When BOD levels are high, dissolved oxygen (DO) levels decrease because the oxygen that is available in the water is being consumed by the bacteria. Since less dissolved oxygen is available in the water, fish and other aquatic organisms may not survive. Noticeably, canal was blocked with the sand bags temporarily for construction and water become stagnant at these points, therefore, BOD is found higher. Additionally, water quality is not affected anyway due to construction activity at any surface water body locations. The water can be used only for bathing, fishing and agricultural activities. Noticeably, this blockage helps the farmer for their upcoming irrigation during the summer. 92. TDS: Total Dissolve Solids (TDS) refers to the sum of all the components dissolved in water. Noticeably, the water that contains too much dissolve matter is not for common uses, therefore, the standard limit set for Bangladesh is 500 to 1000 mg/l. TDS in the collected samples were varied from 33.00 to 14500.00 mg/l. Only at BR 96 location sample shows the highest level of TDS caused by the presence of potassium, chlorides and sodium. These ions have little or no short-term effects, but toxic ions (lead arsenic, cadmium, nitrate and others)

38

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

may also be dissolved in the water. Despite this location, other tested values show a small variation and the field value is less than the standard acceptable limit thus the river/canals water is moderately suitable for common use. 93. DO: Dissolve Oxygen or free oxygen is needed for respiration of aquatic organisms. It is evident that the DO levels below 1 mg/l will not support fish population, thus, 5 to 6 mg/l are required for fish survival. DO values in our collected samples are varied between 3.87 to 6.24 mg/l, indicates the average quality of river/canals water. BR 96 shows the lowest DO concentration it is because of highest BOD and COD values and lack of natural flow of water. 94. TSS: The level of TSS found in the samples range between 12.0 to 18.0 mg/l, however, the set standard is 150 mg/l. Noticeably, most of the tested samples found within the standard limit. 95. Turbidity: Turbidity values of the surface water samples range between 10.8 to 61.70 NTU whereas the set standard value is 10 NTU. All the collected samples show higher concentration of turbidity. Too much algae or sediment in lakes and streams can make them unsuitable for recreation and aquatic life. Turbidity is caused by particles suspended or dissolved in water that scatter light making the water appear cloudy or murky. 96. Oil and Grease: The concentration of oil and grease were found slightly lower than 2mg/l in the surface water samples. Under this amount of oil and grease in every sampling location can induce skin rashes and scabies who take bath from Bakkhali River. It will be wise to note that the oil and grease have skin penetration properties. However, project activity has no significant impact due to taken precautionary measure at the construction area i.e. installation proper barricading, signage, restriction of dumping any chemical or washing equipment at the BR locations. The selected surface water is suitable for irrigation, fishing, sometimes bathing and boating (both shallow engine and manual) purposes etc. were observed during sample collection.

Table 25: Result of surface water parameters (December, 2018) of Lot 2 Sample Sampling Results ID Location Tem BOD COD DO TDS TSS Turbidity pH Oil and Grease °C (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) NTU - (mg/l) SW_01 BR 161 (25m 22.30 16.00 60.00 5.13 33.00 14.00 10.80 7.00 <2.0 U/S) SW_01 (25m 22.20 12.00 40.00 5.76 34.00 15.00 11.30 6.80 <2.0 D/S) SW_02 BR 155 (25m 22.40 6.00 28.00 5.93 53.00 17.00 25.60 6.80 <2.0 U/S) SW_02 (25m 22.30 5.00 20.00 6.24 54.00 15.00 21.80 6.70 <2.0 D/S) SW_03 BR 124 22.30 10.00 36.00 5.46 100.00 18.00 56.70 6.90 <2.0

39

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

(25m U/S) SW_03 (25m 22.40 8.00 28.00 5.90 77.00 16.00 61.70 6.80 <2.0 D/S) SW_04 BR 96 (25m 22.40 9.00 32.00 5.60 14200.00 13.00 15.10 7.00 <2.0 U/S) SW_04 (25m 22.30 46.00 176.00 3.87 14500.00 12.00 20.70 7.00 <2.0 D/S) Bangladeshi 500- 6.5- - 5-10 4 150.0 10.0 < 1 Standards (DoE) 1000 8.5 vi) Comparison between June, September & December 2018 surface water quality parameters of lot 2 97. A comparison is made shown in Table 26 based on quarterly reports (September and December 2018). BOD and COD values fond higher compared to September data. There is no significant changes in the DO concentration. The highest TDS value found in the December 2018. TSS concentration found higher in September quarter and Turbidity values change noticeably as ranges from 10.8 to 288.0 NTU within the nine months period. Finally, oil and grease concentration was found relatively higher in the month of September at most of the sampling locations. 98. Remarks: Considering the three quarterly reports, there is no significant changes found within the DCRP Lot 2 sampling locations or specifically BR locations. Despite some abrupt changes in few parameters, overall there is no noticeable changes observed. Therefore, it can be concluded that, the project activity has no significant on the surface water quality. Additionally, as per precautionary measure, at every active BR location safety in charge installed proper barricading, signage and restrict dumping of any chemical or washing equipment at the surface water body.

40

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Table 26: Comparison between quarterly reports for Surface Water Quality Monitoring (September & December 2018) of Lot 2 Results

Oil Sample Location Month Tem. BOD COD DO TDS TSS Turbidity pH and ID Grease

°C (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) NTU - (mg/l) SW_01 September 31.4 0.00 0.00 6.40 84.0 238.0 70.1 6.98 45.0 (25m December US) 22.3 16.0 60.0 5.13 33.0 14.0 10.8 7.00 <2 BR 161 SW_01 September 31.6 4.0 20.0 6.64 86.42 31.0 62.5 7.64 12.0 (25m December 22.2 12.0 40.0 5.76 34.0 15.0 11.3 6.80 <2.0 DS) SW_02 September 30.2 8.00 52.0 6.96 45.24 280.0 164.0 7.30 65.0 (25m December 22.4 6.00 28.0 5.93 53.0 17.0 25.6 6.80 <2 US) BR 155 SW_02 September 30.6 2.50 24.0 6.91 48.14 292.0 288.0 7.39 7.0 (25m December 22.3 5.00 20.0 6.24 54.0 15.0 21.8 6.70 <2 DS) SW_03 September 32.1 0.00 4.00 7.76 48.72 230.0 90.2 7.85 25.0 (25m December 22.3 10.0 36.0 5.46 100.0 18.0 56.7 6.90 <2 US) BR 124 SW_03 September 31.5 1.80 16.0 6.95 50.46 136.0 88.6 7.55 18.0 (25m December 22.4 8.00 28.0 5.9 77.0 16.0 61.7 6.80 <2 DS) SW_04 September 32.4 3.00 24.0 7.0 182.42 310.0 21.3 6.77 16.0 (25m December US) 22.4 9.00 32.0 5.6 14200 13.0 15.1 7.00 <2 BR 96 SW_04 September 32.8 3.20 24.0 7.25 174.58 4.00 27.1 7.19 22 (25m December DS) 22.3 46.0 176.0 3.87 14500 12.0 20.7 7.00 <2 500- 6.5- Bangladeshi Standards 5-10 4 150.0 10.0 < 1 1000 8.5

4) Groundwater Quality 99. Groundwater sampling has undertaken at 14 sample stations on a semi-annual basis. The objective of this groundwater sampling at 14 different stations under DCRP Lot 1 & 2, is to verify groundwater quality in order to make comparisons between pre-development and post-development stage & semi-annual basis, detect change, and make comparisons against a standard. The measured parameters are such as pH, TP, Mn, Fe, As, E. Coli, Temperature, and Oil and grease. The collected sample were tested at the BCSIR Dhaka and Chattogram Lab. The groundwater quality monitoring was performed for the DCRP in presence of Consultant representative. i) Groundwater quality monitoring frequency and locations 100. Table 27 shows the three quarters sampling locations of the DCRP.

41

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Table 27: Groundwater quality Sampling Locations Lot 1 Lot 2 September December June September December (24 September (30 June 2018) (21 September 2018) (26 2018) December 2018) GW_1 Null GW_1 GW_1 Null Dohazari Dulahazra Cox’s Bazar Station Station _Ch Station 0+700 GW_2 Null GW_2 GW_2 Null Satkania Station Islamabad Near Umkhali Bazar _Ch 8+760 Station Bridge no.161 GW_3 Null GW_3 GW_3 Null Lohagara Rubberdam Near Bakkhali River Station Eidgoan Bridge no.155 Ch 21+500 Bridge no.124 GW_4 Null GW_4 GW_4 Null Ch Ramu Station Max Yard 25+131_Bridge No. 38 GW_5 Null GW_5 GW_5 Null Harbang Station Near Bakkhali Rubberdam Eidgoan _Ch 37+460 River Bridge no.124 Bridge no.155 GW_6 Null GW_6 GW_6 Null Ch Dakkhin Napit Khali Camp 44+509_Bridge Mithasara No. 69 Bridge no.161 GW_7 Null GW_7 GW_7 Null Chokoria Cox’s Bazar Bridge no.96 Station _Ch Station Near Dulahazara Safari 48+970 Park (Mondirar Khal) ii) Groundwater Quality Monitoring Methodology 101. Ground water samples were collected from 14 sampling stations (14 tube wells around bridge crossings; and one sample per tube well). Prior starting the sampling, the team dressed appropriate PPEs and sterilized the faucet of the deep-well for 2 minutes and then took the samples. The parameters that were measured are pH, total phosphate (TP), arsenic (As), iron (Fe), manganese (Mn), and E-coli, Oil & Grease. All collected samples were stored in plastic sampling bottles, except E-coli and Oil & grease (amber bottle) then put some marking to identify them later before analysis and stored according to standard methods and analyzed within 24 hours of being collected at an ISO14000-certified laboratory.

42

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar iii) Analysis of groundwater quality Lot 1 102. Table 27 shows the groundwater sampling locations. The selected four samples i.e. GW_1, GW_3, GW_5 & GW_7 were collected from four proposed stations of the DCRP (Deep well of local people at the vicinity). Two of the remaining selected three samples i.e. GW_4 & GW_6 were collected from local people’s tube well near to the river or canal crossing bridge area. GW_2 water sample was collected from the nearby deep well of the proposed Satkania station (Ch 8+760). The sampling site is still a virgin land, surrounded by rice fields where no construction activity has been started yet. 103. Water for human consumption should be undergone regular physicochemical tests. Physicochemical properties are high priorities in determining acceptability, although they may have little bearing on whether the water is safe to drink or not. Generally, the standards used to evaluate the suitability of water for drinking and domestic purposes are more restrictive than those that would be applied to water for other purposes. 104. Groundwater samples were collected from 7 tube wells near the project corridor on 24th of September, 2018. The laboratory tests performed were for pH, Arsenic (As), Manganese (Mn), Iron (Fe), Phosphorus (as Phosphate), oil and grease, and E. coli and Temperature was recorded simultaneously during sample collection. The collected samples were sent to the Bangladesh Council of Scientific and Industrial Research (BCSIR) for testing the required parameters. Results of the groundwater testing are shown in Table 28.

Table 28: Result of Groundwater parameters (September, 2018) of Lot 1 Sample Sampling Results ID Location Tem As Fe Mn TP pH Oil and E. Coli Grease °C (ppb) (ppm) (ppm) (ppm) - (mg/l) CFU/100ml Below Dohazari GW_1 30 Nil 0.25 Detection 7.0 7.81 1.05 >1100 Station_0+700 Limit Below Satkania GW_2 29.6 Nil 2.8 Detection 3.0 7.58 1.25 Nil Station_8+760 Limit Below Lohagara GW_3 29.5 Nil 0.07 Detection 6.2 6.80 0.80 Nil Station_21+500 Limit Below Bridge No. GW_4 28.2 Nil 10.0 Detection 0.30 6.70 0.65 Nil 38_25+131 Limit Below Harbang GW_5 28.6 Nil 8.0 Detection 0.20 6.20 0.52 Nil Station_37+460 Limit Below Bridge No. GW_6 28.7 Nil 0.08 Detection 1.5 7.40 1.10 Nil 69_44+509 Limit Below Chakaria GW_7 28 Nil 0.30 Detection 2.20 7.42 0.54 Nil Station_48+970 Limit

43

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Bangladesh Standards 0.3 20- 6.5- for Drinking Water 0.05 – 0.1/np 622 0.0123 0 30 8.5 (ECR’97) 1/np WHO Guideline for 6.5- 0.01 0.3 0.5 - - 0 Drinking Water, 2004 8.5

105. The ground water test results for some parameters (As, Mn, Oil and Grease) received from BCSIR Chattogram Lab during baseline environmental monitoring has been found erroneous by the team of engineers. As per instruction of the team of engineers, the contractor has changed testing laboratory to Department of Public Health Engineering (DPHE), Dhaka from December, 2018. 106. Arsenic (As): Arsenic was not found in any of the collected water samples. The Bangladesh Standards for Drinking water (ECR, 1997) is 0.05 ppm and WHO guideline is 0.01 ppm for Arsenic in any water sample. Considering this, it can be concluded that the water samples are arsenic free. However, these results cannot be taken into account as BCSIR Laboratory has not been approved by the team of Engineers. So, the contractor has discarded the BCSIR Laboratory and opted DPHE (Department of Public Health Engineering) laboratory for future tests. 107. Iron (Fe): Concentrations of Iron have been found from 0.07 to 10 ppm (Table 28). The standard value ranges from 0.3 to 1.0 ppm for Bangladeshi perspective. Three out of seven samples were found exceeding the standard iron concentration; GW_2, GW_4 and GW_5. Although high iron in drinking water is not a major health problem, it may be unacceptable to users at such high concentrations. 108. Manganese (Mn): Manganese on the other hand, is regarded as a potential health problem in waters and WHO have set a guideline value of 0.5 mg/l for this element while BD sets 0.1 mg/l. The tested report shows (Table 28) the Mn value was found below the detection limit considering all the samples. However, these results cannot be taken into account as BCSIR Laboratory has not been approved by the team of Engineers. So, the contractor has discarded the BCSIR Laboratory and opted DPHE (Department of Public Health Engineering) laboratory for future tests. 109. P (as Phosphate) and pH: The concentrations of P (as Phosphate) found in the tested sample rage from 0.20 to 7 ppm, however, the standard value sets as 6.0ppm for drinking water. Accordingly, two (GW_1 and GW_3) of the seven water samples were found to have higher phosphate concentration than the permissible limit. However, groundwater samples meet the pH standards, however, the found values vary from 6.20 to 7.81 (Table 28). 110. Oil & Grease: Oil and grease concentrations found in the samples ranging from 0.52 to 1.25 mg/l which is higher than the standard 0.01 mg/l (Table 28). This may have happened as most of these tube wells are used to wash cooking utensils having some amount oil attached on

22Drinking water quality EQS Standard 23 The Schedule-3(A) of (Standards for Inland Surface Water) Environmental Conservation Rules, 1997, has been considered

44

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

its surface. However, these results cannot be taken into account as BCSIR Laboratory has not been approved by the team of Engineers. So, the contractor has discarded the BCSIR Laboratory and opted DPHE (Department of Public Health Engineering) laboratory for future tests. 111. E.Coli: Despite the significant improvement in bacterial quality afforded by groundwater over surface water sources, many ground water sample from tube wells in Bangladesh show higher than acceptable concentrations of bacterial contaminants. The tested report shows that only one tube well had significant levels of E.Coli which is >1100/100 ml whereas the standard set as 0 (Table 28). The reports indicating that, the supplied water sample are contaminated with thermo-tolerant Escherichia Coli. This appears related to a number of factors, including proximity of latrines or drains to the tube wells, tube well depth or method of completion, and factors such as the practice of tube well priming. iv) Analysis of groundwater quality Lot 2 112. Analysis of groundwater quality (September 2018) of Lot 2: Groundwater samples were collected from 7 tube wells near the project corridor on 21st of September 2018 (See Table 27 for locations). The laboratory tests performed were for Temperature, pH, Arsenic (As), Manganese (Mn), Iron (Fe), Phosphorus (as Phosphate), Oil and grease, and E. coli. The collected samples were sent to the Bangladesh Council of Scientific and Industrial Research (BCSIR) at Chattogram Lab for testing the required parameters. Results of the groundwater testing are shown in (Table 29). Bangladesh Council of Scientific and Industrial Research (BCSIR), Chattogram, has tested the required parameters from the submitted samples and provided test reports enclosing in their official letter heading. 113. Arsenic (As): The level of Arsenic (As) was found 0.00ppm in the tested water samples which complies the Bangladesh Standards for Drinking water (ECR, 1997) as 0.05 ppm and WHO guideline 0.01 ppm in all samples (Table 29). Considering this level of As found in the samples indicating the potability of water quality and workers are free form carcinogenic effect in future. 114. Iron (Fe): All the tested groundwater samples contain higher concentrations of Fe accept GW_04 and GW_06 (< 0.1 ppm) while the standard value ranges from 0.3 to 1.0 ppm for Bangladeshi perspective. Concentrations have been found from ranges from 0.1 to 2.80 ppm (Table 29). Although high iron in drinking water is not a major health problem, it may unacceptable to users at such high concentrations. 115. Manganese (Mn): Manganese on the other hand, is regarded as a potential health problem in waters and WHO have set a guideline value of 0.5 mg/l for this element while BD sets 0.1 mg/l. The tested report shows (Table 29) the Mn value found under detection level which meets both BD and the WHO guideline. The inhalation higher concentration Mn to the human body might cause brain effect. Since, the tested water doesn’t contain this element meaning we are safe and environment is well maintained. 116. TP (as Phosphate) and pH: The concentrations of TP (as Phosphate) found in the tested samples rage from 0.30 to 5.60 ppm, however, the standard value sets as 6.0ppm for drinking water. Accordingly, the concentration of P was less than the permissible limit. Similarly,

45

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

groundwater samples meet the pH standards, however, the found values vary from 6.20 to 7.84 (Table 29). The water is suitable for all household purposes. 117. Oil & Grease: Oil and grease concentrations found in the samples range between 0.3 to 2.0 mg/l which is higher than the standard 0.01ppm (Table 29). Further testing is required in order ensure the oil and grease amount found this time. The non-point sources of oil & grease tend to be in the form of pesticides and nutrients that enter the soil as a result of intense agricultural operations or the widespread use of road salts and chemicals. As the groundwater sampling stations are located nearby area of agricultural land and also salt firming is common here which can be a major source of oil & grease in groundwater. 118. E.Coli: The tested report shows 0.0 CFU/100ml levels of E.Coli which meets the standard set as 0. The water is potable for all users.

Table 29: Result of Groundwater parameters (September, 2018) of Lot 2 Sample Sampling Results ID Location Tem As Fe Mn TP pH Oil and E. Coli Grease °C (ppb) (ppm) (ppm) (ppm) - (mg/l) CFU/100ml GW-01 Cox’s Bazar 29.0 0.0 1.25 < 1.20 7.84 1.50 0.0 Station detection GW-02 BR 161 28.7 0.0 1.23 < 1.40 7.58 2.0 0.0 detection GW-03 BR 155 29.1 0.0 2.7 < 2.50 6.80 1.25 0.0 detection GW-04 Max Yard 26.6 0.0 0.10 < 1.80 6.70 0.85 0.0 detection GW-05 BR 124 27.6 0.0 2.80 < 5.6 6.20 0.45 0.0 detection GW-06 Napit Khali 27.2 0.0 0.50 < 0.40 7.40 0.30 0.0 Camp detection GW-07 BR 96 27.6 0.0 2.65 < 0.30 7.42 0.75 0.0 detection Bangladesh Standards 20- 0.05 0.3 – 0.1 624 6.5- 0.0125 0 for Drinking Water 30 1 8.5 (ECR’97) WHO Guideline for 0.01 0.3 0.5 - 6.5- - 0 Drinking Water, 2004 8.5

v) Comparison between June and September groundwater quality parameters 2018 of Lot 2 119. A comparison is made based on two distinguished quarterly reports only which matches the previous one’s sampling station. Therefore, 4 common stations are selected for this

24 Drinking water quality EQS Standard 25 The Schedule-3(A) of (Standards for Inland Surface Water) Environmental Conservation Rules, 1997, has been considered

46

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

comparison and it is found few changes overtime (Table 30). No significant changes were observed among the groundwater parameters. As recommended out during the ADB’s mission in November 2018, a change was made in laboratory for water quality analysis. As per ADB’s instruction the third quarter (December, 2018) water samples were tasted in DPHE, Dhaka and BCSIR, Dhaka (only oil & grease). Before ADB’s mission in November, 2018 the water samples were tested in BCSIR (Dhaka) & BCSIR (Chittagong) during first quarter (June 2018) and second (September 2018) quarter environmental sampling respectively.

Table 30: Comparison between two quarterly reports (June & September 2018) for Ground Water Quality Monitoring of Lot 2 Sampling Date Results Location Tem As Fe Mn TP pH Oil and E. Coli Grease °C (ppb) (ppm) (ppm) (ppm) - (mg/l) CFU/100ml Cox’s Bazar 30.06.2018 27.9 <2 1.23 <0.5 1.03 7.03 <5 0 Station 21.09.2018 29.0 0.0 1.25 < 1.20 7.84 1.50 0.0 100+150 detection BR 155 30.06.2018 30.0 <2 5.09 <0.5 4.94 6.94 <5 10 Ch.90+014 21.09.2018 29.1 0.0 2.7 < 2.50 6.80 1.25 0.0 detection BR 161 30.06.2018 27.2 < 2 7.52 < 0.5 1.11 6.55 < 5 0 Ch.92+969 21.09.2018 28.7 0.0 1.23 < 1.40 7.58 2.0 0.0 detection BR 124 30.06.2018 27.5 <2 4.02 <0.5 3.98 6.48 <5 0 Ch.73+706 21.09.2018 27.6 0.0 2.80 < 5.6 6.20 0.45 0.0 detection Bangladesh Standards for 20- 0.05 0.3 0.1/np 626 6.5- 0.0127 0 Drinking Water (ECR’97) 30 – 8.5 1/np WHO Guideline for Drinking 0.01 0.3 0.5 - 6.5- - 0 Water, 2004 8.5

5) Drinking water Quality 120. Based on the Engineers requirement in the month of September one sample (from CCECC- MAX JV Camp) and in December two samples (from Ramu Lab and Ramu Yard) were collected additionally in order to check the drinking water quality. The objective of these drinking water samplings was to verify existing water quality and make comparisons against a standard. Besides, it is essential to know the status of the drinking water since more than 100 workers are dependent on these sources. The measured parameters are such as pH, DO, TDS, TSS, Salinity, As, TC, FC, Fe, and Temperature. The collected sample were tested at the

26 Drinking water quality EQS Standard 27 The Schedule-3(A) of (Standards for Inland Surface Water) Environmental Conservation Rules, 1997, has been considered

47

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

BCSIR Chattogram (i.e. September 2018). The drinking water quality monitoring was performed in presence of Consultant Mr. Md. Saiful Islam, Junior Environment and Safety Specialist. i) Drinking water quality monitoring frequency and locations 121. Table 31 shows the two quarters drinking water sampling locations of the DCRP.

Table 31: Drinking water quality Sampling Locations Lot 1 Lot 2 September December September December (21 September 2018) (26 December 2018) DW_1 (Ramu Null Null DW_1 Laboratory) Napit Khali Camp Null Null DW_2 (Ramu Yard)

ii) Drinking Water Quality Monitoring Methodology 122. Drinking water samples were collected from the submersible pumps. Prior sampling the team dressed appropriate PPEs for sampling and sterilize the mouth of the deep-well for 2 minutes and then took the samples. All samples were collected in plastic sampling bottles, except TC, and FC (amber bottle) then put some marking to identify them later before analysis and stored according to standard methods and analyzed within 24 hours of being collected at an ISO14000-certified laboratory.

iii) Analysis of Drinking Water Quality measurement of Lot 2 123. Analysis of Drinking Water Quality measurement (September 2018) of Lot 2: One drinking water sample was collected from 1 sampling station such as Napith Khali camp yard on 21st of September 2018. The collected sample was sent to the Bangladesh Council of Scientific and Industrial Research (BCSIR) at Chattogram Lab for testing the required parameters. Results of the groundwater testing are shown in Table 32. The BCSIR provided test reports enclosing in their official letter heading. The Table 32 shows all the tested value of samples lie between the standard levels of parameters such as As, DO, TDS accept Fe (2.20 ppm).

Table 32: Result of Drinking water parameters (September, 2018) of Lot 2 Sample Sampling Results ID Location Tem. As Fe DO TDS TSS pH Salinity TC FC

°C ppb ppm ppm mg/l mg/l - mg/l CFU/100 CFU/100 ml ml Napit DW-01 Khali 29.1 0.0 2.20 7.36 374.0 131.72 6.80 90.0 0 0 Camp Bangladesh 0.01 0.3 - 500 - 6.5- - 0 0 Standards (Max.) 8.5 (BDS 1240:2001)

48

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

WHO Guideline 0.01 0.3- - - - 6.5- - 0 0 for Drinking 1.0 8.5 Water, 2004

124. Analysis of drinking water quality parameters (December 2018) of Lot 2: Drinking water samples were collected from 2 sampling station such as Ramu Laboratory and Ramu Camp on 26th of December 2018 (see Table 31 for locations). The collected sample was sent to the DPHE Laboratory Dhaka for testing the required parameters. Results of the groundwater testing are shown in Table 33. The Table 33 shows all the tested value of samples lie between the standard levels of parameters such as As, TDS, pH, TC & FC etc. 125. Table 38 shows that the Fe concentration is found within the permissible limit 0.7and 0.53 ppm for lab and camp respectively while the standard is 0.3-1.0ppm. Overall, the tested all other parameters found within the standard limit set by the DoE.

Table 33: Result of Drinking water parameters (December, 2018) of Lot 2 Sample Sampling Results ID Location Tem. As Fe DO TDS TSS pH Salinity TC FC

°C ppb ppm ppm mg/l mg/l - mg/l CFU/100ml CFU/100ml Napit DW-01 Khali 22.40 0.00 0.70 6.68 122.0 1.00 7.10 0.12 0.00 0.00 Camp Ramu DW-02 22.30 0.00 0.53 6.84 107.0 1.00 7.00 0.11 0.00 0.00 Camp Bangladesh 0.01 0.3 - 500 - 6.5- - 0 0 Standards (Max.) 8.5 (BDS 1240:2001) WHO Guideline 0.01 0.3- - - - 6.5- - 0 0 for Drinking 1.0 8.5 Water, 2004

6) Noise Meter 126. The Engineers gave approval to buy a noise meter which will be used on a regular basis in the field level (Ref: SMEC/5060126/CSC1/2018-745(DM). CCECC-MAX JV has been issued a work order to purchase the requested noise meter model (SL-4033SD LUTRON) and expected to be reached at the site very soon.

7) Flora and Fauna 127. During our visit on 23rd April,2018 we have seen The Chunati Reserve Forest harbours a rich floral resource of Garjan (Dipterocarpus spp.) and Boilam (Anisoptera scaphula) trees etc. We visited Medhakachhapia and Fasiakhali reserve forest and talked with the local people on 23rd April, 2018.The opined that movement of elephant (Elephas maximus) is frequent.Oher faunas wher are rarely seen are - slow loris (Nycticebus bengalensis), rhesus macaque (Macaca mulatta), capped langur (Trachypithecus pileatus), mouse deer (Tragulus javanicus), and Rufous-tailed hare (Lepus nigricollis).

49

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

B. Construction Period Qualitative Assessment 1) Environmental Issue EMP_2.6/H-6.1 (e.g. Noise attenuation measure) 128. According to the EMP 2.6, Noisy works may not be occurred near to the sensitive areas like residents, schools, religious places and hospitals. But during the pilot pile work at BR 124 (Ch. 73+706) which was located just beside of a local mosque where various machines were observed working for instance Rotary rigging, excavator, crane, generator etc. (Photo 1). During the reporting period, other noise sources also observed within the construction sites (Photo 2 to 4) 129. Due to lack of noise meter, it was not possible to measure the exact noise level during the field visit. However, during the quarterly noise measurement in September at BR 124 beside the sensitive receptor, it was found 69.41 dBA (Day) and 63.17 dBA (Night). Considering this zone as commercial, the standard is 70 dBA (Day) and 60 dBA (Night) for Bangladesh, meaning noise generation was around the standard limit. Additionally, due to work pressure at BR 124, the 3rd quarterly Noise monitoring in December has been performed at this site again. Data analysis was not performed yet, therefore, 3rd quarterly measurement result is not incorporated in this report. However, no objection found either from the mosque authority or local inhabitant nearby due to noisy work, therefore, no necessary immediate measures were taken on the spot. Considering the Napitkhali camp, the retention wall has been constructed which will act as a good noise barrier. Besides, usually tin shed was provided for generators at the site. 130. The Engineers gave approval to buy a noise meter which will be used on a regular basis in the field level (Ref: SMEC/5060126/CSC1/2018-745(DM). CCECC-MAX JV has been issued a work order to purchase the requested noise meter model (SL-4033SD LUTRON) and expected to be reached at the site very soon. 131. Environment Specialist along with HSSE team has been waiting to receive the digital noise meter. The noise measurement will take place during every field visit. Then necessary measure can be taken if exceeds standard limit, for instance, establishment of noise barrier/enclosure to minimize or reduce the noise level near to the residential area and providing hearing protecting device to the workers in order to comply with the EMP. Toolbox talk and training session will be conducted to raise awareness among the worker to maintain safe working environment and safe themselves.

2) Air quality and dust control 132. According to the Subsection H: Environment Safeguard, it is stated that, all roads, permanent or temporary, pukka or katcha, that become dusty and all areas where construction related activities are carried out, need to ensure necessary suppression measures i.e. watering, sweeping or other measures approved or directed by the Engineer. However, due to monsoon period the weather was humid and rainy (I.e. July to mid- October). Therefore, no dust suppression measures were taken or needed at all. Besides, rainy weather makes the work more difficult to progress (Photo 5 to Photo 8). During month of July to October, apparently there was no dust suppression measure taken due to frequent and torrential rain. Besides, humidity was high as well. Consequently, after the monsoon,

50

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

CMJV has been decided to ensure dust control measure. Overall, 5 vehicles have been using for dust control on a daily basis (2 times per day) to spread water at different sites. Approximately a total of 27, 000, 00 L of water has been spread throughout the month and covered a total of 8-10 Km daily including local road (Photo 26 to Photo 30). The information was collected informally from the field (CCECC part). However, the contractor doesn’t keep any record of dust control measure. CMJV’s higher official decided to keep maintain log book alike petroleum products from the next month which will be incorporated in the monthly report of January 2019. 133. Additionally, four air quality monitoring has been performed as quarterly basis at different sites (Photo 25). As the construction activity shifting on a regular basis for the good progress achieved by the Contractor, to define the impact of construction activity on the ambient air quality at different sites, same air monitoring stations for each and every sampling quarter was not possible to maintain. But since the camp sites will not shift, the Contractor will maintain the same sampling stations particularly where there are crushing plants or other polluting plants. 134. Weekly inspection is being conducted by the environment specialist in order to monitor and report environmental and safety noncompliance and compliance issues. Additionally, a log book will be maintained from the month of January 2019.

3) Environmental Issue EMP_2.4/H-6.3 (e.g. Protection of Wetlands/Ponds/Rivers/Canals) 135. Considering this clause 2.4 mentioned in the EMP as “Undertake protection of watercourses”, the contractor (CCECC-MAX JV) of Lot 2 has been working on to ensuring the protection of all wetlands, ponds, rivers and canals lied under the project boundary throughout Construction period of New Dual Gauge Railway Line from Dohazari to Cox's Bazar via Ramu (DCRP- Lot 2). 136. Construction activity i.e. pilot pile, working pile, and pile cap construction was performed at the BR 155 (Bakkhali River), BR 124, BR 120, BR 129, BR 130, BR 147, BR 161 and BR 162 over the last six months period but the earth moving in the vicinity of watercourses were kept to a minimum to avoid sedimentation and contamination from fuel and lubricants. Noticeably, considering the wetlands protection, CMJV has been working on ensuring the quality of water resources at bridge locations mainly. 137. There was no identifiable construction or earthwork activities were observed yet that might affect watercourses anyway. During the pilot pile (i.e. pilot pile 8) and working pile (i.e. working pile 48), water body near the Bridge construction area was not affected anyway. Noticeably, during the pilot pile/work pile, proper barricading was observed nearby water bodies to protect their natural flow and quality of water. However, at some point due to lack of flow of water (very narrow khal) the diversion road was made on the surface water body on a temporary basis (i.e. BR 129, 130, and 161). Besides at some points contractor put together concrete rings to maintain the flow of water bodies (i.e. BR 120, BR 124, and BR 162). The Photographs show the protection measures and existing status of water bodies (Photo 31 to Photo 35). Additionally, MAX has been constructing a temporary concrete based bentonite holding tanks on the ground in order to avoid contamination of soil as well as potential surface water bodies adjacent to the pilot pile area (i.e. BR 161, BR 147, BR 155, &

51

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

BR 162). The contractor was clearly informed about the importance of the surface water bodies to protect from any kind of pollutions. 138. Additionally, three surface water quality monitoring surveys have been conducted on a quarterly basis at different bridge locations i.e. BR 124, BR 96, BR 161, BR 147 & BR 155 (Photo 36) in order to monitor their exiting surface water quality and to know any potential impacts due to constructions. The water samples were collected to measure parameters

such as pH, Turbidity, Temp (°C), DO, BOD5, COD, TSS, TDS, and Oil & Grease. 139. New bridge construction will be continued at new places, therefore, the HSE team will ensure to protect wetlands and surface water quality near bridge locations. Regular visit will be conducted as well along with consultant and fill up approve checklist.

4) Environmental Issue H_6.6 (Servicing and Operating Equipment) 140. The work regarding servicing and operating equipment have been carried out by the CMJV’s experienced mechanical personnel in such a manner so that near rivers, streams or other bodies of water will not be affected and get polluted with gasoline, diesel fuel, oil, grease, or surplus or disposable materials. 141. During the field visit, a few servicing activity was observed at the Link road area, Ramu Camp, BR 124, BR 129 and Napith Khali camp. However, the safety team informed to the site engineer regarding the safe servicing and operating activities. No major servicing was observed, but minor because of using brand new vehicles and equipment during the operations which are all equipped with modern technology (CCECC part). A total of 314 (CCECC- 169 & MAX- 145) different types of equipment were used at different sites at the end of November 2018 for various activities and held very common servicing which maintained on a regular basis. In December there were 214 fully functional equipment mobilized to the field and few were under servicing due to break down at once on site. 142. No major servicing was observed, but minor because of using brand new vehicles and equipment during the operations which are all equipped with modern technology. A total of 314 (CCECC- 169 & MAX- 145) different types of equipment are listed to be used (i.e. some are idle at the CCEECC camp & some are yet to come but owned) or have been using at different sites for various activities and held very common servicing which maintained on a regular basis. However, site engineers, mentioned that for major servicing they usually send their vehicles/machines to the nearby garage or company’s own servicing area for further repairing activities. Besides, site engineers were instructed to perform servicing and operating equipment carefully in urgency and avoid pollution due to oil spillage, gasoline, diesel fuel, grease, or surplus or disposable materials. Additionally, mechanic have been informed clearly that they should not perform any servicing of machines or equipment near rivers, streams or other bodies of water to avoid water pollution. 143. Mechanical department at both camp (i.e. EMD workshop MAX site) site personnel and site engineers have been informed to perform servicing and operating equipment carefully in urgency and avoid pollution due to oil spillage, gasoline, diesel fuel, grease, or surplus or disposable materials. Additionally, HSE team will visit every site and keep informing mechanical engineers not to perform any servicing of machines or equipment near rivers, streams or other bodies of water to avoid water pollution.

52

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

5) Control of Petroleum Product 144. It is clearly stated in the specification H that all petroleum products need to be stored in a designated storage location i.e. fuel storage/tank, where any spillage can be safely maintained without contamination of surrounding area. Additionally, the storage site need to be established far away from the vicinity of streams, rivers or other bodies of water. Considering these requirements, the CCECC-MAX JV has been performing construction activities in such a manner so that they can comply with the specification. 145. Regarding the control of petroleum products, few non-compliance issues were recorded at different places. For instance, at various construction sites (i.e. bridge 124, 129, 130, 155, 161 & 162), the contractor usually uses temporary oil storage facility (i.e. plastic or tin made oil drum) in order to meet their essential oil demand (Photo 11). In this regard no oil abetment initiative was seen, however, no spillage or accident was reported due to momentary fuel oil storage facility at the sites. At Link road temporary oil usage facility was observed which was not complied with EMP, therefore the site engineers were informed to take permanent or at least some protection measures so that ground spillage can be prevented (Photo 10). On the other hand, at the Napith Khali camp, two oil tankers usually ensure their necessary fuel oil demand (i.e. fuel collected form the local fuel oil station) on a daily basis, therefore, no noncompliance issues have been found there (Photo 09 & 12). 146. The site engineer was instructed strictly before and during the field visit in presence of the Consultant team, to take necessary measures for instance, to install signage at the site indicating danger sign and oil storage area, arrange oil deep/spill tray under the oil container to avoid oil spillage to the ground or spill to the nearby area, provide fire extinguisher to avoid fire hazard. Besides, the identified noncompliance issues were informed to the responsible authorities to take recommended measures by preparing a report using photographs and send through email. Additionally, permanent cylindrical fuel oil storage tank having a capacity of 15,000 L was observed fully functional from December 2018 at Ramu camp wherever daily demand is around 3000 L (Photo 37 & Photo 38). On the other hand a permanent 2 cylindrical fuel oil storage tanks have been set (Photo 39 & Photo 40) to ensure fuel oil facility which is not functional yet. However, both stations have spill control capacity. 147. A regular site visit will be conducted in order to check whether the site engineer takes necessary measures or maintain their standards against non-compliance issues identified during every site visit. Additionally, spill abatement measures will be adopted as soon as possible after finishing their construction of fuel storage area.

6) Occupational Health and Safety 148. Occupational health and safety is one of the major construction issues that has been handling very carefully since the projected started by the CCECC-MAX JV in order to ensure workers welfare and safe working environment at the site. Therefore, workers safety issue in every aspects have been given first priority. A number of HSE officers have been engaged in order to perform and monitor workers health and safety. Over the last six months period, occupational health and safety measures were mainly observed at the bridge locations i.e.

53

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

BR 96, BR 124, BR 120, BR 129, BR 130, BR 155, BR 161, BR 162, CCECC-MAX JV camp, and Ramu Camp. 149. Proper PPEs, signage and barricading: During the field visit, the HSSE team always tried to observe and ensure proper PPEs at the site while workers working at different sites. During the month of July, when the first pilot pile work started, there was lack of proper PPEs especially shoes and hand globes. Gradually, the situation have changed for the CCECC part. Proper signage and barricading was observed very frequently at various sites (Photo 41 & 42). On the other hand during the commencement of Ramu Camp there were lack of PPEs of the workers which is because of few workers were from the subcontractor part (Photo 13 & Photo 14). However, overtime proper PPEs were ensured for the workers. Proper signage and barricading at the Ramu Camp was ensured from beginning. Despite some non- compliance issues sometimes, most of the cases PPEs were ensured for the workers (Photo 55, 57, 58, 60 & 61). Apparently, non-compliance issues were raised due to engaging subcontractors at different site for various constructions. However, CMJV’s higher official was informed regarding that issue and they only ensure PPEs for their staffs only. As per ADB’s requirement, the main contractor is also responsible for ensuring the subcontractor’s compliance with all environment safeguard requirements including PPE’s. Accordingly, subcontractors have been informed clearly to ensure their workers PPEs otherwise they are not allowed to work at the site. Additionally, proper signage and barricading was observed most of the construction sites over the whole last six months period. 150. Electrical and mechanical safety: From the Photo 15, it is evident that electrical safety was not properly ensured the site. Photo 16 shows the lack of proper PPEs of 2 welders. Additionally, sometimes found non-comply with the IEC 6066, BDS 1360- 1992, & BDS- 1436- 1994 codes. Therefore, the electrical department personnel was informed to either change electrical appliances, ensure proper insulation, and better face shield while electrical welding is performed. Additionally, at the MAX part, it was found haphazard conditions surrounded with electrical wears at the sites. Safety officer was informed to ensure proper housekeeping and if possible change old electrical appliances. However, it will take some time to improve electrical and mechanical safety at the workplace. 151. Drinking water, toilet and First aid Facility: CMJV has been working on ensuring primary facilities such as potable water at all construction sites, and hygienic toilets. Unfortunately, due to lack of permanent workers at the bridge construction sites, therefore, there was lack of proper toilet facility (Photo 20). Besides, readily accessible first aid facility was observed at work places. Noticeably, temporary accommodation facility was observed for workers at bridge 155, 147 and 162 since, they stayed for long time. Therefore, proper toilet and potable water facility was ensured. 152. Housekeeping and others: Photo 19 represent a lack of proper housekeeping at Ramu Laboratory area. It was because of under construction but proper initiative was taken later on. Additionally, Photo 17 shows a potential suspect of a child labor at the construction site by the HSE manager. To clarify this issue, the Foremen of the Team (under whom the suspected child labor has been working) has shown the National ID of the Suspect. Which clearly defined that, the suspect was not child labor. Therefore, he asked proper document from the subcontractor and stopped his work temporarily. Finally, Photo 18 reveal the

54

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

unsecured work on height. There was lack of full body harness for the workers. Photo 43 to Photo 56 shows a good example of proper housekeeping at different site. CMJV has been aiming to ensure that kind of proper housekeeping for all sites, however, it will take a little bit more time to establish. Photo Photo 54, shows an example of awareness training and tool box talk to the workers where safety officer provides necessary guidelines for safe work avoid occupational hazards. Finally Photo 62 represents the HIV-AIDS awareness action and orientation program conducted monthly basis by a NGO called EBS at different sites of the DCRP Lot 2.

7) Environmental Issue EMP_2.3/H-6.11 (Protection of top soil and erosion) 153. As defined in the EMP, Clause 2.3, it is necessary to implement topography, landscape and soil plans. Accordingly, CCECC-MAX JV has been working on protecting and storing top soil while excavated during the stripping work. Additionally, some erosion control measures were observed at different sites as well. 154. During the last six months few clearing, grubbing and stripping activities were performed where CMJV stored the top soil on the surface of the ground in a linear pattern adjacent to the filled/ developed land between RoW so that soil can be used later on used as per embankment preparation. It can be seen that top soil management practices at Ch- 88, 89, 83, 84, 79, 80, 77, 68, 69, 72, 73, 97, 98 and 100. Table 34 shows the various earthworks activities that have been performed throughout the last six months period 155. During the month of November and December 2018, some clearing, grubbing and stripping activities were performed where they stored the top soil on the surface of the ground in a linear pattern adjacent to the filled/ developed land between RoW so that soil can be used later on used as per embankment preparation. Photo 47 to Photo 53 & Photo 59 shows some example of top soil management practices at different changes (Table 34) i.e. Ch- 88, 89, 83, 84, 79, 80, 77, 68, 69, 72, 73, 97, 98 and 100. Overall a total of around 77,940.0 m3 top soil was stored temporarily for further use and covered an area of approximately 6.81 Km (Table 34). However, top soil stockpiling and/or disposal of material is not placed in any area where natural drainage or storm water could pond and become stagnant, or where could erode the material and cause silting of the adjacent area or of any natural or manmade water course.

Table 34: Top soil and erosion protection measure at different sites. Earthwork Chainage Status of Amount of top soil Top soil protection work stored measure Approximately (m3) Clearing, Ch. 88+00 to Not 3600 • Excavated Grubbing & Ch. 88+400 completed organic or Stripping yet superficial Clearing, Ch. 89+00 to Not 2700 materials were Grubbing & Ch. 89+300 completed stored along the Stripping yet RoW for further Clearing, Ch. 83+300 Not 6300 use during the Grubbing & to Ch. 84+00 completed embankment Stripping yet preparation

55

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Clearing, Ch. 79+500 Not 6300 • Additionally, Grubbing & to Ch. completed during the field Stripping 80+200 yet visit, it was not Clearing, Ch.77+500 Not 8460 observed that the Grubbing & to Ch. completed material is not Stripping 78+440 yet placed in any area Clearing, Ch-68+000 Not 10980 where natural Grubbing & to Ch- completed drainage or storm Stripping 69+220 yet water could pond Clearing, Ch. 72+950 Not 6300 and become Grubbing & to Ch. completed stagnant Stripping 73+650 yet • The stock Clearing, Ch. 98+700 Completed 29700 material is not Grubbing & to Ch. placed in such a Stripping 100+350 way so that they Clearing, Ch. 97+450 Completed 3600 could erode and Grubbing & to Ch. cause silting of Stripping 97+650 the adjacent area Total (6.81 Km) 77,940 or of any natural or man-made water course. • Besides, it is very dry season and less chances of rain therefore, no erosion issue raised.

156. In the upcoming month there will be lot of clear, grubbing and stripping work will take place. HSE will visit all the construction sites and ensure proper top soil and erosion protection measures.

56

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Grievances and Complaints 157. During the reporting period, no complaints has received or addressed due to the construction activity. But if in near future GRC receive any complaints, then the date of receipt of complaint; complainant’s name and location; nature of complaint; response provided; date of providing response; and whether the grievance has been redressed or not will be reported.

UNANTICIPATED SAFEGUARD ISSUES 158. During the reporting period from 1st July of 2018 to 31st December of 2018, no such anticipated safeguard issues came across.

CONCLUSION

A. Overall Progress with Implementation of Environmental Safeguard Measures 159. The environmental awareness creation, particularly regarding the direct construction impacts and especially for health, environmental pollution and safety issues are important. The need to develop self-regulation of the contractors will have to be emphasized, with the consultant’s supervisory role that to be in conformity the relevant Environmental Clauses (Section 6, Subsection H: Environmental Safeguards of contract technical specification) incorporated in the construction contracts and national legislation. 160. Overall during July 2018 to December 2018, environmental team has performed different activities related to environmental issues such as, visited different sites very frequently, monitoring site activities and record activities that might affect existing environment and inform appropriate personnel to take necessary measures to avoid environmental pollution and ensure work place safety. Despite some non-compliance issues at different sites, overall the construction activities have been progressing smoothly without hindering environmental quality and putting safety at the first place of this development. Furthermore, environmental safeguard awareness programs were conducted among the workers and necessary instructions were given to take effective measures to avoid environmental pollutions and become aware about our precious environment. 161. Additionally, quantitative assessment like air, water, and noise quality have been performed two times as quarterly basis in the reporting period and analyzed data presented here for better understanding of project effect to the environment. Based on the analysis, it can be concluded that, the construction activities have no significant impact on any of the environmental components. 162. Based on the present status, further next level planning needs to be executed. Proper planned activities could rather help to implement the EMP efficiently with minimum impact on the exiting environment. The disputes identified in the report, from those both the Engineer & the Contractor shall take lessons and advice the Contractor to work more effectively. However, cooperation from every one related to this project is very essential to make this project successful with minimum impact to the environment.

57

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

B. Recommendations 163. To make the process smoother and efficient, the following recommendations are proposed based on observations during the reporting period regarding environment safeguards to be followed with immediate effect. 164. Based on the site inspection and monitoring of the execution of the Environmental Safeguards program the accomplishments in response to the relevant recommendations are given in the following Table 35.

Table 35: Recommendations for Improving Contractor Compliance and Progress Sl. Recommendation Site Timeframe Implemented Supervision No. by by

1. A proper system needs to be Every site During Contractor Engineer developed to keep where project qualitative information like earthwork, period record keeping on amount of station and

water spread as a dust bridge suppression measure, construction construction waste material take place quantity, top soil quantity etc. 2. Few construction activities Bridge Within the Contractor Engineer took place at night when a construction next presence of a respective HSE site reporting personnel is important. period 3. So many non-compliance - Within the Contractor Engineer issues were generated due next to lack of proper reporting arrangement and shortage period of resources. Adequate resources should be ensured by the Contractor. 4. The Contractor must ensure Bridge During Contractor Engineer that the sampling of the construction project critical parameters for water site period quality, noise and air quality is carried out fully in line with the Sampling Program so that meaningful results can be obtained enabling further mitigative measures to be determined and initiated if required.

58

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

5. The on-site construction Every active During Contractor Engineer supervision and site where project management of the earthwork, period Contractor should be station and strengthened so that actions bridge taken to improve health and construction safety issues are maintained take place and not lost over time. It will be necessary to arrange the training and awareness in the health and safety issues for the construction workers with regular and repeated sessions presented & delivered by specialized personnel. 6. The overall management of Ramu & During Contractor Engineer camps and worksite must be Chakaria project further improved in line with camp period the best practices on

occupational health and safety so that these areas of the site can be made fully compliant. 7. The staffing provided to During Contractor Engineer address the environmental project safeguards program should period be enhanced to ensure that

all the requirements of the program can be correctly actioned and reports can be provided in a timely manner recognizing the importance of these matters to all stakeholders.

Appendices

Appendix 1: Environment Management Plan and Environmental Monitoring Checklist Appendix 2: Test Results of Collection Samples for Environmental Monitoring Appendix 3: Photo Log

59

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

(II) Six month working plan (January 2019 to June 2019) for the DCRP Lot 2 Environmental Safeguard Jan Feb- Mar May Apr-19 Jun-19 Implementation -19 19 -19 -19 H- Air Quality (CO, S02, N02, 1 4.2 PM2.5, PM10) H- 2 Noise (dBL) 4.3 Surface Water Quality (pH, H- Turbidity, Temperature, 3 H-4 4.4 DO, BODS, COD, TSS, TDS, oil and grease) Groundwater Quality (pH, H- 4 TP, Mn, Fe, As, Oil and 4.5 Grease and E.Coli) H- 5 Additional Sampling 4.6 Construction Period Reporting and Training H- Monthly Environmental 7 5.1 Report H- Quarterly Environmental 8 5.2 Inspections and Report H- 9 H-5 Semi Annual Report 5.3 1 H- Annual Environmental 0 5.4 Report 1 H- Contractor Training 1 5.5

Construction Period Mitigative Measures 1 H- Noise attenuation 2 6.1 measures 1 H- Dust control (PM 2.5, PM 3 6.2 10) Protection of 1 H- wetlands/Ponds/Rivers/Ca 4 6.3 nals 1 H-6 H- Borrow and Dredging Site 5 6.4 Impacts Disposal of construction 1 H·6 debris and other waste 6 .5 materials 1 H- Servicing and operating 7 6.6 equipment

60

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

1 H- Control of petroleum 8 6.7 products Conflict between elephant 1 H- and humans during 9 6.8 construction 2 H.6 Hill cutting protection 0 .9 H- 2 Occupational Health and 6.1 1 Safety 0 H- 2 Protection of topsoil and 6.1 2 erosion 1 H- The Environmental Submi Submis Submissi 6.1 Management ssion sion of on of 2 Implementation Work of Emerg water Schedule (EMWS) plus Noise ency pollutio other work plans as and and n 2 specified in EMP dust hazard preventi 3 Contr ous on and ol waste Dredgin Plan manag g ement Manage plan ment Plan

61

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Appendix 2: Environment Management Plan and Environmental Monitoring Checklist Environmental Management Plan: Construction Period Mitigative and Monitoring Measures (Lot 1 & Lot 2)

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

Construction Period 2.1 The Contractor does not prepare The Engineer will assist Complied Complied Lot 1 & Lot 2 Environmental a work plan defining details contractor prepare the EMWS, The draft of EMWS has been added to this Management on when mitigation and but interim payment report and provided a copy to The Engineer Implementation monitoring actions are to (mobilization) will be delayed during the environmental kickoff meeting Work Schedule take place, in relation to the until the EMWS is submitted to on 8th April 2018 at The Engineer’s office in (EMWS) work and then the EMP the Engineer. Further the Chittagong. requirements are not contractor will prepare; implemented properly. - traffic management plan, - health and safety management plan, - emergency management plan, - waste management plan, - hazardous materials management plan, - dust management plan, - noise management plan, - water pollution prevention management plan, -dredging management plan, and - construction biodiversity management plan, with method statements for all works in protected areas and in-river

62

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

works all in accordance with requirements of the EHS general and railway guidelines. 2.2 Air Quality The ambient levels of CO2, A dust suppression program will Partially Complied Lot 1 and Dust NOx, Sox, PM2.5, and PM10 be used at all times during Complied • Dust suppression measures like usage of may increase at busy construction of embankment, water browsing vehicle was active on a stations and construction stations and placement of ballast daily basis during the dry season. areas leading to temporary Dust suppression to include • A very limited level of visible smoke has localized air pollution. watering and suppression observed emitting from the pay loader. equipment on batch plant, as well • Severe level of visible smoke has as vehicle speed restrictions to observed emitting from a truck. But the k/h., ad finally rapid vehicle is not owned by the Contractor. 63vegetation including grass The vehicle has used to transport seeding. material supplied by local dealer. Ambient air quality testing for • No dust observed due to rainfall. SO2, NO2 and PM2.5, PM10 same • Loads (bricks & humid soil) were not that locations as ambient-conditions dusty to pollute the site but still survey , conducted quarterly at contractor was instructed to use stations and construction sites tarpaulin to cover the load throughout the construction • The environment specialist team from period, including at sensitive ENRAC has collected required air quality receptors such as mosque, parameters from the pre-specified hospitals and schools, and location, for instance, 4 Proposed immediate remedial actions Railway Stations of DCRP (Quarterly taken 2 exceedances occur at any basis). one site Lot 2

63

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

• During the monsoon no dust control measure was taken or needed

• During the post monsoon dust suppression measures like engaging of water sprinklers at most of the sites were observed at CCECC sites on a daily basis. • Dust suppression measures like usage of water browsing vehicle was active on a daily basis during the dry season. • During the monsoon dusty loads didn’t create any harm to the environment due to wetly condition • No such activities like waste oil, lubricant or other petroleum derivatives used as dust suppressants were observed • The environment specialist team from ENRAC has collected required air quality parameters from the pre-specified location, for instance, 3 Proposed Railway Stations of DCRP (Quarterly basis) and BR 124 on December 23 to 26 2018 2.3 Topography, Landscape and Soils

64

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

2.3.1 Erosion Clearing topsoil in proposed Topsoil storage areas must be Partially Partially Lot 1 embankment area can lead protected during the dry season, Complied Complied • Temporary stockpile was observed. to loss of nutrient and wind erosion by covering. • Cleared debris has found not only without erosion particularly along Rapid re-vegetation and use of stockpiling but also left on the surface of the >11 km of cut slopes and hydro-seeding and jute erosion the ground in a linear pattern adjacent to dust from unprotected protection mats will be applied in the filled/ developed land. But to avoid storage sites. The erosion areas where erosion is noted siltation on adjacent agricultural land the risk at embankment slopes is during the regular monthly construction of trench around the site is possible. Gully erosion along inspections on going. the exposed track slope Lot 2 during rainy season may • Temporary stockpile was observed. damage smother field crops • Cleared debris has found stockpiled at in adjacent areas. Cox’s Bazar Station Area but also left on the surface of the ground in a linear pattern adjacent to the filled/ developed land. But to avoid siltation on adjacent agricultural land the construction of trench around the site is on going. 2.3.2 Visual intrusion from large Embankment site to be planted Not Not Lot 1 & 2 Topography and piles of embankment trees to promote natural applicable applicable • This kind of activities has not started Landscape materials and ballast vegetation; as well as fast yet. changes obstructing views and growing grasses such as excavation along the edge of Vetiver/Napitar; however, not at the alignment leaving large elephant crossing sites identified. unsafe holes is possible. Only low grass and shrub erosion protection measures here., using

65

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

plant material not suited for elephant Material stockpiles will be removed as soon as work is completed and the area re- landscaped. Same applies to borrow areas. 2.3.3 Hill Cutting Total length of >11.00 km of Hill cutting will require a Prime Not Not Lot 1 cuts across hilly sections of Ministerial permit. Proper applicable applicable • Retaining wall will be constructed. Prior the alignment (See Annex 2) protection measure like slope to construction wall, Contractor has will be needed to achieve a retaining walls and completed digging trench along the design grade. These areas bioengineered measures such as adjacent area of hill cutting at Lot 1. will be highly erosion-prone. plant fascines, palisades and brush layering. A Hill Cutting Lot 2 Management Plan is given Annex • Hill cutting areas yet not handed over to 19. the contractor. Resettlement work is ongoing • Necessary measures will be undertaken during the hill cut. • Environment specialist along with the help from the Earthwork Engineering/Construction Department of the CCECC-MAX JV jointly worked on Hill Cutting Management Plan and submitted for the Engineers approval. The plan includes all the measures that need to be

66

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

taken care of during and post hill cutting period. • Retaining wall will be constructed. Prior to construction wall, Contractor has completed digging trench along the adjacent area of hill cutting at Lot 1. 2.4 Water Resources 1) Earthwork activities Ensure all earthworks are Complied Complied Lot 1 during construction of constructed according to design • Containment bund has constructed to embankment may result in and specifications. avoid water pollution drainage congestion Wastes, effluents and other • To reduce introduction of sediments on contaminant materials at the adjacent agricultural land and in 2) The surface water at camp/work sites to be stored, nearby water body through surface workers camp and Project handled, transported and runoff, the construction of trench site areas may become disposed in planned manners. around the site has completed 2.4.1 Hydrology pollute due to faecal, organic Garbage disposal service to be • Sands were stockpiled on a temporary and Surface and other contamination. provided, Concrete refuse reused basis. Sands from the stockpiles were Water Quality Disposed wastes and or disposed of without habitat eroded but due to the construction of effluents from the loss; All other effluents not to be containment bund, the siltation construction sites may cause disposed of directly into natural occurred within the project area further degradation of waters, but via settling basins to • Construction of retention wall, settling surface water. allow suspended sediment to basin, and improved drainage systems settle out. have been nearly finishing as a part of Quarterly surface water quality erosion control measures at camp site testing programme, with • The environment specialist team from sampling design as defined in the ENRAC has finished working in the field

67

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

EIA will be completed during the and measured required surface water construction period. quality parameters on 29th of June 2018, from the pre-specified location, for instance, 4 Proposed Railway Bridge of DCRP (Quarterly basis) Lot 2 • 20 major bridges will be constructed over 1 major river and other small canal or Khals. Out of 20 only 9 bridges construction have been started within the last six months. Only then contractor was undertaken steps to limit the impact (if any due to pilot pile or working pile) for each and individual bridge located water bodies. Accordingly, BR 124 pilot pile construction was started in July. Therefore, the CMJV was barricading the rubber dam area in order to protect the surface water body. Likewise the same initiative was taken for BR 96, 120, 130, 155,161 and 162. To reduce introduction of sediments on the adjacent agricultural land and in nearby water body through surface runoff, the construction of trench around the site has completed

68

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

• Construction of retention wall, settling basin, and improved drainage systems have been finished at CCECC-MAX JV Camp and Ramu Camp as a part of erosion control measures and ensure proper drainage at camp sites • The environment specialist team from ENRAC has finished working in the field and measured required surface water quality parameters on 26th of December 2018, from the four stations (i.e. BR 124, BR 155, BR 161, BR 96) (Quarterly basis) 2.4.2 The potential exists for Workforce camps will be located Complied Complied Lot 1 Groundwater drinking water sources to be away from water resources. All • The environment specialist team from contaminated by the practical measures such as ENRAC has finished measuring required seepage of wastes from provision of septic tanks, garbage ground water quality parameters in workers’ camps through the bags, and other sanitation September, 2018 from the pre- soil profile into the GW facilities will be implemented at aquifer (particularly if wells the construction camps to specified location, for instance, 4 access the shallow aquifer). prevent the wastewater and solid Proposed Railway Bridge of DCRP (deep wastes from entering well and wells) along with other 3 stations. groundwater recharge areas. Wells used for drinking will be Lot 2 tested once a year to ensure • From July to December, groundwater portability. sampling was conducted during the first quarter environmental sampling. As the ground water sampling should be

69

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

conducted semi-annually by the Contractor, so ground water quality check has not taken place during second quarter environmental sampling. • Also to prevent water pollution through surface runoff or infiltration, the campsites were equipped with septic tanks and proper waste water management measures 2.5 Waste Management 2.5.1 Waste Construction camp wastes Contain all solid wastes at Non- Partially- Lot 1 Management are often poorly managed designated location within complied complied • Due to lack of heavy construction and can lead to chronic construction sites. Service activities, adequate mitigative measures pollution of surface and machinery and vehicles strictly at to limit the impact of construction debris groundwater. designated maintenance was not observed within the workshops where waste oils and construction yard lubricants can be collected and • Apparently not construction debris but recycled. The monthly mostly paper and plastic wastes which monitoring report will provide were removed immediately after compliance update inspection • A designated area for disposing man made construction debris is under construction Lot 2 • The generated construction debris i.e. at BR 124, 120, 130 and 96 usually collected

70

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

through dump truck and send back to the CCECC Camp or Ramu Yard and if possible reuse them accordingly. Additionally, proper housekeeping has been ensured by the safety officer at all construction sites. Therefore, there was no recorded impact upon pedestrians, local communities and water bodies due to construction debris. • Sometimes the site personnel unattended left the debris on the surface of the ground for late removal. However, safety engineer was informed to ensure proper housekeeping. • CCECC-MAX JV camp & Ramu Camp have appropriate classified waste bin facilities i.e. bin for reusable waste and kitchen waste. After the regular collection of waste like kitchen waste are disposed/handed over to the municipality. On the other hand reusable waste such as PET bottles are sold to the local vendor. • For the construction sites, few poly bags were provided to collect manmade waste which are disposed in a designated location approved by the

71

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

engineer on a daily basis. Besides, most of the manmade construction debris are supposed to reuse further, therefore, the generation rate or final disposal rate is not that significant. • A waste management plan was submitted to the engineers’ office for their final approval (Ref: CCECC- MAX/DCRP/BR/18/R/0438) which is under review 2.6 Noise Work sites will be noisy due Keep oise pollutio at dB Partially Partially Lot 1 pile driving, operation, (Bangladesh standard) levels at Complied Complied • The environment specialist team from power generator, rock mosque, school, populated area ENRAC has finished to measure required crushing/ batch plants and and other sensitive sites by use of noise quality parameters from the pre- movement of construction low noise equipment or erection specified location, for instance, 4 vehicles, as well as the of temporary baffles. Work Proposed Railway Stations of DCRP constant movement of trains timing restrictions if noise levels, • Pale loader was working near a school along the existing line. based on field measures indicate and local house area in two different exceedances of existing spots during this reporting month. A mild conditions. noise was generating therefore no action Contractor will also be required was recommended. A noise test is to use only well-maintained required then necessary measures will functioning equipment. be taken if exceeds the standard limit of noise. However, no objection was recorded from the local inhabitant. • During the commencement of clear & grubbing, & earthworks equipment were

72

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

not in good condition but late May both sits have been using mostly new modern machines in good condition. Lot 2 • The environment specialist team from ENRAC has finished to measure required noise quality parameters (Quarterly basis) from the pre-specified location, for instance, 3 Proposed Railway Stations of DCRP Lot 2 and BR 124.

• S1-S5, S12-S15: CCECC has mostly brand new equipment equipped with noise abating gear such as mufflers for effective noise control • During the pilot pile construction noise was generated and a sensitive receptor (i.e. mosque) was identified. During the second quarter sampling the measured noise was found slightly beyond the standard. However, no objection was raised from the mosque or local people. • Other sites are mostly located far from the sensitive areas like residents, schools, religious places and hospitals.

73

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

2.7 Terrestrial The clearing of 239,000 trees A rapid revegetation / tree Not Not • Not mentioned in the BoQ item and Aquatic and associated understory replanting programme will applicable applicable Flora and Fauna vegetation and construction permit the rail-side habitat to of a 2-12 m high by 101 km- recover quickly long embankments will The rapid reestablishment of pre- reduce the habitat for mostly construction surface draining will birdlife, given that the help to bring wet areas, aquatic and terrestrial faunal somewhat reduced (marginally) is limited to common and by the new embankment to re- pest species. establish pre-construction habitat conditions. Small patches of wetland will Fisher surveys will be conducted be covered by the to gauge effect of construction on embankment fishing and fish at each of the 5 major bridge crossings during the fishing season, to track changes in total catch and species diversity. 2.8 Elephant Obstruction of elephant Implement plan developed Not Not Lot 1 & 2 travel routes travel routes during during the preconstruction applicable applicable • No construction activities have been and Elephant construction and later via period to minimize impact during started near to the seasonal and usual population deep cuts as crossing construction, including elephant trail. Necessary measures will be locations establishing work hours near taken when construction work starts. crossing areas to only full • Necessary measures will be taken when dalylight (0700-1700). construction work starts. Keep embankments at cut areas as low as possible, i.e., less than 4.1m to allow TIC viewing

74

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

Monitor movement of elephant at crossing points and ability to move around construction sites,- -seek cooperation of local villages, to continue a monitoring program during the construction period at the five active crossing areas. 2.9 Land Use, Population and Culture 2.9.1 Land Use The most significant Land acquisition / requisition will Not Not • Not mentioned in the BoQ item potential impacts on land be in accordance with the laws of applicable applicable use in the study area will be Bangladesh and as defined in the the removal of 540 ha of land Project RP, which specifies (primarily rice paddy) for the agreed to entitlement a construction of the proposed grievance mechanism and rail embankment, station timetable for implementation. It access roads and associated will be used by BR as its facilities. mitigation guide concerning this issue. 2.10 Heritage 40 CPRs will be affected by BR has defined a plan(as part of Not Not • Not mentioned in the BoQ item and Culture the rail line construction the RP) to prevent undue damage applicable applicable to these sites and/or relocate the CPRs, which will have to be completed before the work begins 2.11 Health, Safety and Contractor Camp

75

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

2.11.1 Health Personal and occupational Undertake check and cleaning at Partially Partially Lot 1 and Vector health issues, stemming all sites and areas where clean Complied Complied • A water pump was used to withdraw deep Borne Diseases from unsanitary toilet conditions should exist. water and reserved in a water tank from facilities, lack of potable Provision of potable water, where workers usually get their potable water and sanitary washing sanitary toilet facility and water. Safety officer was instructed to areas can lead to common hygienic accommodation for ensure safe water for the workers. disease outbreaks in work workers at camp sites. All potable • First aid facility was observed for the camps. water supplies will be tested semi workers on spot. However, First Aid boxes annually were provided in every office space and Construction work creates vehicles that carry office staffs. areas for water to form Provision of First-Aid facility for • Proper drainage system have been stagnant puddles; Also, them. Ensure that these facilities observed to remove rain/stagnant water water can collect in old are cleaned and disinfected from the site and settling basin has equipment waste tyre dump regularly. constructed to avoid erosion stored outside, ideal Lot 2 breeding areas for malaria Inspect for stagnant water and • S14- S16: Submersible water pump has and dengue mosquitoes. puddles every 3 days, including been installed to these sites in order to stored construction materials withdraw deep water and reserved in a such as tyres and old oil drums– water tank from where workers usually empty to prevent water ponding. get their potable water. Safety officer was instructed to ensure safe water for the workers at the construction sites as well. • S14 - S16: In the beginning of the construction of camps and laboratory there was lack of First Aid facility. Overtime the situation getting better in every construction sites. Contractor has

76

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

provided necessary first aid facility at each and every construction sites. • S14-S16: The camp, yard and Lab has adequate drainage facility where more than 300 workers stayed together • S14-S16: In the beginning of the construction of camp, there was lack of sanitary toilet facility. Overtime the situation improved and at the camp there are good sanitary facilities present for both workers and officers. • Even for the construction sites, especially at MAX part, they provided temporary toiled facility made of ring slab for the onsite workers. 2.11.2 Worksite Poor safety oversight and Construct fences separating the Complied Complied Lot 1 Safety management of the construction sites at rail stations • A brick wall (boundary) with a sufficient Management worksites by the contractor, from public access, and manage height was constructed surrounding the leads to accidents and train movements collaborating camp areas (for both; Harbang & unsafe working conditions with BR dispatch staff. Chakaria) which has acted as a noise Contractors must at all times barrier. ensure the local people needing • Proper fencing was observed near to the to move from one side of the construction area construction area to another • The Contractor was instructed to provide can do so effectively and without Fire-fighting equipment like fire undue delay. extinguishers, bucket with sand, fire hydrant at each & every work areas

77

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

Lot 2 • A brick wall (boundary) with a sufficient height was constructed surrounding the camp areas (for both; Napitkhali & Ramu) which has acted as a noise barrier. • Proper fencing was observed near to the construction area • The Contractor was instructed to provide Fire-fighting equipment like fire extinguishers, bucket with sand, fire hydrant at each & every work areas • S14: Initially, there was lack of fall prevention and protection measures. Thereafter, due to necessary actions the contractor has arranged full body harness while working on height. Besides, during the camp construction guard rail was ensured where needed. Nowadays, there is no such activity i.e. work at height exist. • S14- S16: Arrangement of ladders and scaffolds have ensured by the contractor. Applicable training is required for their proper use 2.11.3 HIV Due to influx of workers in Workers health training Complied Complied Lot 1 Awareness the Project area, AIDS/HIV programme will be organised during construction period to

78

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

may spread in local aware the health and hygienic • EBS has been working on this issue community issues. Training to be provided by independently with the guiding from health specialist such as a local the HSSE department of CREC TOMA JV NGO and Consultant

Lot 2 • EBS has been working on this issue independently with the guiding from the HSSE department of CCECC-MAX JV and Consultant 2.12 Occupational Health and Safety 2.12.1-Personal Contractor does not provide Workers will be provided with Partially Partially Lot 1 Safety adequate PSE or properly appropriate personal protection Complied Complied • Except the HPD (Hear Protecting Device) Equipment (PSE) enforces its use, leading to equipment, such as safety boots, during noisy work, contractor has accidents helmets, gloves, protective ensured other PPE’s for the workers. clothing, goggles and ear After measuring site noise level, protection, and contractor will necessary measures will be taken. enforce its use, so long as safety • Gumboot along with other PPE’s were does not suffer due to this action provided to the workers. • Initially there was lack of proper signage facility due to lack of full pace construction activities but later on the condition has improved as because of regular monitoring and site engineer was instructed to arrange signage and staffing at the work areas.

79

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

Lot 2 • S1- S16: Except the HPD (Hear Protecting Device) during noisy work, contractor has ensured other PPE’s for the workers. After measuring site noise level, necessary measures will be undertaken. • Gumboot along with other PPE’s were provided to the workers during the rainy season. • Initially there was lack of proper signage facility due to lack of full pace construction activities but later on the condition has improved as because of regular monitoring and site engineer was instructed to arrange signage and staffing at the work areas. 2.12.2-Drinking See 2.11.1 above Partially Partially Lot 1 Water Complied Complied • Five water pumps were used to withdraw deep water in five sites and reserved in water tank from where workers usually get their potable water. Safety officer was instructed to ensure safe water for the workers.

Lot 2

80

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

• S14- S16: Submersible water pump has been installed to these sites in order to withdraw deep water and reserved in a water tank from where workers usually get their potable water. Safety officer was instructed to ensure safe water for the workers at the construction sites as well (usually temporary water tank or water jars were provided to the workers) 2.12.3-Safety Lack of safety training by Construction workers will be Partially Complied Lot 1 Training contractor can lead to trained in general health and Complied • Often Toolbox talk (on a daily basis prior accidents and lost safety matters and on specific to construction work start) usually takes productivity hazards of their work place at work site • 39 Engineer and site supervisors have been trained on purpose Lot 2 • Regular Toolbox talk (on a daily basis prior to construction work start) usually takes place at work site • 348 personnel have been trained on purpose

81

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

2.12.4 Labour Labour standards ignored or No use of child labour permitted Partially Lot 1 Standards not complied with leading to that no workers under the age of Complied • Initially, some child labours were found infractions of basic labour 14 may be hired as general at the site but later on due to frequent standards as defined by ILO labours, and no workers under inspection and monitoring, the condition conventions as listed in Item the age of 17 are to be hired for has improved and now free from form 1.8 above. hazardous jobs such work on child labour. scaffolding, and structures • No-bonded or forced labor was found at elevated above the ground, etc. camp site No Bonded labour-All forms of Lot 2 bonded labour and forced labour, • Sometimes temporary appointed as defined by ILO Conventions 29 subcontractors bring child labour along & 105 with them. However, if identified any Equal treatment, equal instant action was ensured. opportunity- as defined by ILO • No bonded labour was found Conventions 100 & 111 and ILO • ILO standard has been maintaining Code of Practice for HIV/AIDS 85. proper workers welfare No discrimination based on race, caste, origin, religion, disability, gender, sexual orientation, union or political affiliation, or age; no sexual harassment Minimum wage- BR expects the contractor to pay all employees according to Bangladesh Labour Act standards.

82

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

2.13 Elephant and construction During construction contractor Not Not Lot 1 & 2 Construction operations interaction, and needs to be fully aware when applicable applicable • No construction activities have been along and across likely sever damage working in vicinity of elephant started near to the seasonal and usual elephant travel travel routes, taking care not to elephant trail. Necessary measures will routes block this with equipment of be taken when construction work starts. temporary storage shows these • Necessary measures will be taken when crossing areas with GPS construction work starts. coordinates. Need to consider output of Clause 1.13 2.14 The Contractor fails to prepare a Prepare a completion report and Complied Complied Lot 1 & 2 Construction summary report defining the deliver to the Engineer. • Monthly, quarterly, semi-annual and Period mitigation and monitoring annual basis environmental safeguard Environmental actions completed and what monitoring reports have been submitting Completion needs to be continued on a timely manner. Reporting during the Operating period. The result is a failed or weakened environmental safeguards programme. 2.15 Pollution Untreated wash water a) Conduct a survey to establish Not Not • The construction of the Cox’s Control discharged to local surface exact needs and then build applicable applicable bazaar stabling and washing facility Installation at water resulting in proper treatment facility has not yet started, hence it’s not Cox’s Bazar permanent water pollution according to description in the yet applicable. Stabling and EIA to meet DOE standards (ECR, Washing Facility 1997, Annex II, Schedule 9). Waste oil and sludge treatment also required.

83

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Project Period Compliance Status Observation / Recommended Action and Project Impact Mitigation Measures Environmental Lot 1 Lot 2 Parameters

b) Construct noise attenuation berms or barriers as agreed in consultation with Engineer and Local Community 2.16 Pilot No adequate preventative Undertake a two year pilot Not Not Initial discussions on the pilot test were just Program to Test measures leading to injuries program to test options methods applicable applicable held in November 2018 and the project is TIC and other or death to elephant as they and to defined the best method still at the planning stage for the pilot test. Elephant-Train try to cross the alignment or combination of methods Accident when trains are passing prevention methods 2.17 Elephant No adequate preventative Purchase, install and test 20 TIC Not Not Initial discussions held in November 2018 protection measures leading to injuries systems on locomotives applicable applicable and the project is still at the planning stage or death to elephant as they operating on the project rail line for the pilot test. try to cross the alignment when trains are passing 2.18 Elephant Lack of basic knowledge Design and deliver an awareness Not Not Awareness about elephant habits and raising program to BR and applicable applicable movement, leading to Contractor and future l agriculture damage and locomotive operators potential injury to people and structures 2.19 Tree 239,000 trees to be removed Undertake a replanting program Not Not Replacement from project construction such that for each tree cut three applicable applicable corridor are planted and all dead trees to be replanted

84

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Summary of Environmental Monitoring Checklist over the month of September to December 2018 (Lot 1) Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c 1. Noise 1.1 Modern plant PC PC PC PC S1, S2, S4: PC attenuati and equipment Generator on should be used with operated at sites measures appropriate was placed inside (H_6.1) muffling devices noise abatement shield. S7, S8, S9: Contractor was instructed to construct a noise barrier around the generator during operation or use noise free modern generators. No construction activities should occur at night at any construction site. And should ensure that not all noisy equipment’s are used at the same time. 1.2 Powered PC PC PC PC PC mechanical equipment and machinery should be fitted with noise abating gear such Same as 1.1 as mufflers for effective noise control, in compliance with DoE regulations 1.3 Noise mitigation PC PC PC PC The Contractor has PC measures minimized the should be adopted noise impact by (e.g. use noise adjusting the timing barrier /enclosure) of noisey activities such as having noisy activities

85

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c during the day time only

1.4 Noise quality C C C C An environmental C monitoring should specialist team be maintained as consisting of 3 per the schedule in members from the environmental ENRAC measured monitoring plan noise quality at different sites using sophisticated noise instrument on 22nd -25th September, 2018. Another noise level monitoring has been done on 19th – 22nd December 2018 at different construction sites. 1.5 Noisy works PC PC PC PC S1, S2, S8, PC should not be S9:Excavator, occurred near to loaders and the sensitive areas vehicles produced like residents, noise at sites where schools, religious local house were places and hospitals nearby. However, no objection was recorded from the local inhabitant. Spot noise measurement will be done from upcoming months. S7: As the base camp is located near to the local housing, a boundary wall has been made to abate noise generated from construction activities.

86

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c No construction activities should occur at night at any construction site. And should ensure that not all noisy equipment’s are used at the same time. 1.6 If noisy works NA NA NA NA NA S1-S9: No occurred, construction temporary noise activities have been barriers should be observed near installed near sensitive locations sensitive locations such as schools, such as schools, religious places and religious places and hospitals hospitals 1.7 Suitable hearing PC PC PC PC S1-S6:A noise test is PC protection like required then earplug, or necessary earmuffs etc. measures will be should be provided taken if exceeds the to the construction standard limit of workers and worn noise and the in noisy areas contractor will ensure suitable hearing protection like earplug, or earmuffs for the workers during noisy work. 2. Air quality 2.1 The PC C C C S1, S2: Dust C and dust construction sites suppression control should be watered measures like (H_6.2) and maintained usage of water with grass carpeting browsing vehicle to minimize dust was active on a generation daily basis during the dry season. S4, S7, S8, S9: No dust was observed during site visit. The contractor ensured they watered the

87

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c site but the unpaved surfaces inside constriction sites were very dry which may generate dust if any vehicle moves. 2.2. Dust masks PC PC PC PC Masks have been PC should be provided provided to some to workers where workers but most dust hazards exist of them do not uses the mask 2.3 All vehicles are NC NC NC NC S1, S2, S7, S9: Loads NC carrying dusty loads (silt clay soil) were should be found dusty. No covered/watered covering of loads over prior to leaving was observed. the site Contractor was instructed to use tarpaulin to cover the load 2.4 Air quality C C C C An environmental C monitoring should specialist team be carried out as consisting of 3 per the schedule in members from the environmental ENRAC has monitoring plan measured air quality at different sites using sophisticated instruments for accurate measurement on 22nd -25th September, 2018 and 19th -22nd December, 2018. 2.5 All roads, PC PC PC PC S1, S2, S7: Water PC permanent or browser operated temporary, pukka on roads at these or katcha, that three sites become dusty and regularly. all areas where S4, S8, S9: The construction nearby roads at related activities these sites were

88

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c are carried out, very dry and dusty. shall be subject to Contractor necessary occasionally suppression watered manually measures by but no water watering, sweeping browser was used or other measures at any of these approved or sites. directed by the Engineer

2.6 Waste oil, C C C C No such activities C lubricant or other like waste oil, petroleum lubricant or other derivatives should petroleum not be used as dust derivatives used as suppressants dust suppressants were observed 2.7 Contractor PC PC PC PC PC should take all reasonable precautions to S7, S8, S9: prevent accidental Contractor used spillage of steel or polythene petroleum sheet to control oil products, contact of spill, but a little such materials with amount of oil is soil or water course spilled out to soil. through discharge, run-off, and or seepage 2.8 Construction C PC PC PC S7, S8, S9: Old PC equipment should model generators be maintained to a were found during good standard and site inspection (Not idling of engines at operation) which discouraged will generate noise and smoke if operated at site.

89

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c 2.9 The machinery C PC PC PC PC emitting visible smoke should be banned from construction sites Same as 2.8

2.10 Contractor PC PC PC PC PC should take all reasonable measures to minimize dust- blowing from areas under his control by spraying water on Same as 2.5 stockpile, bare soil, haul road,un- surfaced traffic route and any other source of dust when conditions require dust suppression. 3. Water • 3.1 PC C C C S2, S4, S8: Used C Pollution Adequate bentonite has been Control mitigation measure disposed into an (H_6.3) should be earthen pit having undertaken to limit polythene cover the impact on all which will be buried water bodies within later. the Project area An environmental specialist team consisting of 3 members from ENRAC has collected water samples quality from different sites using sophisticated instruments for accurate measurement on 23rd September,

90

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c 2018 and 26th December, 2018. 3.2 Earth moving in NA NA NA NA NA the vicinity of watercourses should be kept to a minimum to avoid sedimentation and contamination from fuel and lubricants. 3.3 Proper disposal NA C C C C of bricks, cement, and steel reinforcement which will be removed as part of

the reconstruction of bridges/ culverts should be ensured not to block stream flow. 3.4 Temporary NA C PC PC S6: Erosion events PC erosion and took place in this sedimentation site due to control measures torrential and during frequent rain. rehabilitation of Contractor has cross-drainage been instructed to structures should take necessary be undertaken to measures like ensure that construction of sediment laden run settling basins, off does not enter improving camp the adjoining drainage system, watercourses and construction of boundary wall to avoid erosion. 3.5 Construction C C C C C materials and waste should not be

discharged in watercourse during construction of

91

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c bridges/culverts by implementing appropriate mitigation measure. 4. Borrow and • 4.1 NA NA NA PC S9: the NA dredging site Contractor should subcontractor of (H_6.4) have permits for MBEC was dredging extraction sites and sand from nearby quantities from matamuhuri river appropriate for filling the authorities wooden structure made for pilling. • 4.2 The NA NA NA PC S9: Water sample C water quality during quarterly should be environmental maintained through inspection was disposal of dredged taken from this site spoil using to evaluate appropriate outlet whether dredging activities had any negative impact on water quality. 4.3 The stockpiles NA NA NA C S9: The dredged C and earthwork sand was used should be well inside the wooden maintained/protect structure and no ed visible erosion of sand was observed during site inspection. 4.4 Erosion control NA NA NA C C measures should be Same as 4.3 taken where erosion has noted 5. Disposal of 5.1 Adequate C C C C Due to lack of heavy C construction mitigative construction debris (H_6.5) measures should be activities, adequate taken to limit the mitigative impact of measures to limit construction debris the impact of on pedestrians, construction debris local communities was not observed and water bodies within any construction.

92

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c within the Project area 5.2 Cleared debris C C C C C should not be left S1: Some on the surface of construction debris the ground or was reused for buried in any paving surface. agricultural land 5.3 Burning of C C C C C waste should not be allowed 5.4 Man-made PC PC PC PC S7, S8, S9: PC construction debris Generation of man- should be disposed made construction in designated debris has not disposal areas. The found as because location and nature only of such disposal commencement of shall be subject to earthwork.Apparen the approval of the tly not construction Engineer debris but mostly paper and plastic wastes which were disposed in waste bins. Contractor did not request for approval of such disposal area to the engineer. 5.5 All disposal NA NA NA NA NA areas should be finally graded to a uniform and level Disposal areas for condition and left all active sites are such that they not designated yet. create a minimum impact on the surrounding area 6. Servicing 6.1 Servicing of C C C C No such servicing C and machines or activities near to Operating equipment near the rivers or equipment rivers, streams or streams or other (H_6.6) other bodies of bodies of water water should be have been carried out in such a observed

93

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c manner as to avoid pollution with gasoline, diesel fuel, oil, grease, or surplus or disposable materials 6.2 The contractor PC PC C C S1: An oil tanker C should have the usually provides proper equipment their necessary fuel to transport fuel so on a daily basis. that spillage will not S7, S8: Fuel storage occur area is under construction. 6.3 The contractor C C C C C should ensure that, all hydraulic systems, fuel

systems and lubricating systems are in good condition 6.4 Fuel spills PC PC PC PC S7, S8, S9: PC should not be Contractor used condoned, and care steel or polythene shall be taken to sheet to control oil avoid overfilling spill, but a little machines amount of oil is spilled out to soil. 6.5 The contractor NC NC NC NC S1, S7, S8, S9: Fuel NC should have oil spill storage area has abatement lack of spill equipment on the abatement site at regular basis. equipment like sawdust, spill tray, sponge, or oil dispersant. After finishing the construction necessary measures will be taken immediately. 6.6 The type of NC NC NC NC NC No such equipment equipment shall be was found at any of subject to the

94

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c approval of the the construction Engineer, and the sites. equipment should be maintained in good working condition. 6.7 Disposal of used C C C C C oil, lubricants, tires, etc. should be in accordance with the EMP or as directed by the Engineer 7. Control of 7.1 Petroleum PC PC PC PC S1, S8: Contractor PC Petroleum products should be has a designated Products stored in a area to store (H_6.7) designated storage petroleum location where any products but a few spillage can be oil drums have safely maintained been observed without outside that area. contamination of S7, S8: Construction the surrounding of camp is ongoing areas including designated area for storing petroleum products. 7.2 Storage of C C C C C The locations of the petroleum products petroleum storage should not be facility at any site permitted in the are not in the vicinity of streams, vicinity of water rivers, or other bodies. bodies of water. 7.3 Usage of PC PC PC PC PC impermeable liner S9:Impermeable place on subsurface liner (concrete of the storage room surface) place on to avoid subsurface of the groundwater storage area to contamination avoid groundwater should be ensured contamination. by the Contractor 7.4 Presence of all PC PC PC PC S1, S2, S7, S8: Fire PC precautionary extinguisher have

95

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c measures been arranged by (sand/saw, fire the contractor extinguisher etc.) S4, S8: Contractor should ensure to has been instructed avoid to ensure provision environmental of fire extinguishers pollution or fire at these sites soon. hazard. 8. Conflict 8.1 Blockages NA NA NA NA No construction NA Between should be created activities have been Elephant and with equipment on started near to the Human the identified seasonal and usual During elephant travel elephant trail. Construction routes Necessary (H_6.8) measures will be taken when construction work starts. 8.2 Sign posts/land NA NA NA NA NA marks should be installed indicating

elephant travel track as a part of awareness creation 8.3 Storage sites NA NA NA NA NA should not establish at a location that might block or irritate the elephants movement 9. Hill cutting 9.1 Contractors NA NA NA NA Necessary NA and slope should have prime measures will be protection ministerial permit taken when (H_6.9) for hill cutting construction work starts. 9.2 Erosion & NA NA NA NA NA sediment control plans should be prepared by the Contractor prior to commencement of work 9.3 Proper NA NA NA NA NA

protection measure

96

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c should establish like slope retaining walls and bioengineered measures such as plant fascines, palisades and brush layering to avoid slope failures or landslides 10. 10.1 Provision of C C C C C Occupational potable water for

Health and workers at camp Safety (H_10) sites 10.2 Provision of C C PC PC S4, S8: Contractor PC readily accessible will provide first aid First-Aid facility for boxes at workers construction sites However, First Aid boxes were provided in every office space and vehicles that carry office staffs. 10.3 Adequate PC PC PC PC S1: Adequate PC drainage in workers drainage is absent camps should be at batching plant established to S7: Stagnant water prevent stagnant in the site was seen water and at some point formation of which is due to rain. breeding sites for Contractor has a mosquitoes plan to construct drains around the base camp S8: As construction of the camp is ongoing, contractor has a plan to construct drains around the camp S9: Drainage system is in place but water flow has not been observed

97

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c due improper sloping. 10.4 Provision of C C PC PC All sites have PC sanitary toilet sanitary toilet facility and hygienic facilities. accommodation for S8: Construction of workers at camp the camp is sites ongoing. The contractor has been instructed to provide temporary toilet facilities to the workers. 10.5 Workers PC PC PC PC S1, S2, S7, S8, S9: PC should be equipped Workers were with appropriate mostly found personal protection having no safety equipment (PPE), shoes or helmets. such as safety Some welding boots, helmets, workers were gloves, protective dismissed at S2 clothing, breathing having no mask, goggles and protective gloves ear protection, and and goggles. contractor will Overall, at all sites enforce its use, the safety officer has been instructed to provide sufficient PPEs to the workers. 10.6 Fire-fighting PC PC PC PC S1, S2, S7, S8: Fire PC equipment at the extinguisher have work areas and at been arranged by construction camps the contractor should be provided S4, S8: Contractor has been instructed to ensure provision of fire extinguishers at these sites soon. 10.7 NA NA C PC Initially, no workers PC Implementation of were engaged in fall prevention and works at height in protection any sites. measures should be S7: Safety belt with ensured whenever horizontal life lines

98

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c a worker is exposed were provided to to the hazard of the workers as a falling more than 2 precautionary fall meters, of falling prevention into operating initiative. machinery or S8: Workers of through an opening subcontractors were found working at height without any safety belts. The site engineer was instructed to provide safety belts if such works needed in future.

10.8 Installation of NA NA PC PC PC S7: Arrangement of guardrails with mid- ladders and rails and toe boards scaffolds will be at the edge of any ensured by the fall hazard area, contractor. Proper proper use of training on fall ladders and prevention will be scaffolds by trained provided to the employees should workers soon. be ensured 10.9 Ensuring no NC C C C S2, S7: Initially, C involvement of some child labours child labor were found at the site but later on due to frequent inspection and monitoring, the condition has improved and now free from form child labour. 10.10 Ensuring no C C C C C involvement of bonded labor 10.11 Safety NC PC PC PC PC S2, S4:Proper safety measures including signage/cordon will signage and staffing be provided by the in interface

99

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c between contractor around construction bentonite pit and/or S8: The site construction engineer has been related operations instructed to provide proper signage around the construction site.

10.12 Reversing C C C C C Proper reversing signals should be signal was installed on all maintained by all construction drivers at sites. vehicles 10.13 Undertake PC PC PC PC S7, S8, S9: Waste PC check and cleaning collection bins have at all sites and areas been placed at Site where cleanliness S1, S2, S4: should be ensured Contractor will provide waste collection bins soon at these sites. 10.14 Fences PC PC PC PC PC should be S1, S9: Lack of constructed to proper fencing has separate the been observed at construction sites both sites. at rail stations from public access 11. Protection 11.1 Topsoil PC PC PC PC PC of Topsoil and storage areas S1, S2, S4, S6: soil erosion should be Contractor will (H_6.11) protected during provide plastic the dry season from cover on topsoil wind erosion storage stockpiles. through arranging plastic cover 11.2 Rapid NA NA NA NA NA revegetation and use of hydro- seeding and jute

erosion protection mats should be applied in areas where erosion has

100

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c noted during the regular monthly inspections 11.3 Embankment NA NA NA NA NA site should beplanted with trees to promote natural vegetation; as well as fast growing grasses 11.4 Superficial or PC PC PC PC S1, S3, S4, S6: PC organic material Cleared debris has removed during the found not only excavation shall be without stockpiling stockpiled for but also left on the subsequent use, or surface of the if surplus to the ground in a linear Contract pattern adjacent to requirement, shall the filled/ be disposed of in developed land. designated disposal But to avoid areas. siltation on adjacent agricultural land the construction of trench around the site is ongoing. 11.5 The stockpiling C C PC C C and/or disposal of S1, S3, S4, S6: No material should not natural or be placed in any manmade water area where natural course was seen drainage or storm but storm water water could pond become stagnant and become on a temporary stagnant, or where basis which will be could erode the drained in a proper material and cause way. But the silting of the evidence of adjacent area or of siltation of any natural or man- stockpiled sand was made water course. found due to the runoff of storm water but settled down within the

101

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Items/ Status Observation / Overall Environment Description of Recommended observatio Se Oc No De al Safeguard activities Action n p t v c containment bund area. S6: Due to inadequate arrangement of erosion control, sand and loose soil from the stock pile has eroded to the nearby canal.

102

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Summary of Environmental Monitoring Checklist over the month of July to December 2018 (Lot 2) Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c.

4. Noise 1.1 Modern PC PC PC PC C C • S1-S5, S12-S15: PC attenu plant and CCECC has (80%) ation equipment mostly brand should be used measu new with res appropriate equipment (H_6.1 muffling equipped with ) devices modern technology in good condition. • On the other hand the MAX has been started with old and sometimes conventional equipment emit exhaust

1.2 Powered C C C PC PC PC S1-S5, S12-S15: C mechanical CCECC has mostly equipment and brand new machinery equipment should be fitted with equipped with noise abating noise abating gear gear such as such as mufflers for mufflers for effective noise effective noise control control, in compliance On the other hand with DoE the MAX has been regulations started with old and sometimes conventional equipment that

103

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. generates excess noise

1.3 Noise N PC PC PC C C S1-S5, S12-S15: In PC mitigation C the beginning of measures Pilot pile should be construction no adopted (e.g. noise mitigation use noise measure was barrier adopted (i.e. /enclosure) enclosure) thereafter, the situation got improved. However, due to lack of noise meter at the field, actual noise was not measured. No complain was recorded from the local due to noise. No construction activities have not conducted at night at any construction site. And the Contractor also ensured that not all noisy equipment’s are used at the same time. 1.4 Noise C C C C C C Three quarterly C quality environmental monitoring monitoring have should be been performed (4 maintained as sampling station 2 per the sample per station) schedule in the at different places environmental i.e. 4 stations of the monitoring DCRP Lot 2, CCECC- plan MAX Camp, Ramu Yard and BR 124

104

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. 1.5 Noisy works N C C C C C S3: During the pilot C should not be C pile construction occurred near noise was to the sensitive generated and a areas like sensitive receptor residents, (i.e. mosque) was schools, identified. During religious places the second quarter and hospitals sampling the measured noise was found slightly beyond the standard. However, no objection was raised from the mosque or local people. Other sites are mostly located far from the sensitive areas like residents, schools, religious places and hospitals. 1.6 If noisy N NA NA N NA NA No such place is NA works A A found during the occurred, last six months temporary construction works noise barriers should be installed near sensitive locations such as schools, religious places and hospitals 1.7 Suitable PC PC PC PC PC PC S1-S16: A field level PC hearing noise protection like measurement is earplug, or required then earmuffs etc. necessary should be measures will be provided to the taken if exceeds

105

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. construction the standard limit workers and of noise and the worn in noisy contractor will areas ensure suitable hearing protection like earplug, or earmuffs for the workers during noisy work. However, during the quarterly monitoring noise level mostly found within the standard limit. Besides, workers were trained not to stay beside a noise source for long time. Additionally, only diesel generators are considered as the major noise creating machine. 5. Air 2.1 The C C C PC PC C During the C quality construction monsoon no dust and sites should be control measure watered and dust was taken or maintained contro with grass needed l carpeting to During the post (H_6.2 minimize dust monsoon dust ) generation suppression measures like engaging of water sprinklers at most of the sites were observed at CCECC sites on a daily basis.

106

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. 2.2. Dust masks C C C C PC PC During the C should be monsoon (i.e. Until provided to September) no workers where such level of dust dust hazards exist observed that cause harm to the workers

Water sprinklers have been engaged at most sites, therefore, no mask was provided to the workers

2.3 All vehicles PC PC PC NC NC PC During the PC are carrying monsoon dusty (70%) dusty loads loads didn’t create should be any harm to the covered/water ed over prior to environment due leaving the site to wetly condition

During the Post monsoon dusty loads are not carefully handled and therefore, the specific site safety officers were informed to arrange tarpaulin to cover the load while moving thorough public road.

2.4 Air quality C C C C C C Three quarterly C monitoring environmental should be monitoring have carried out as been performed (4

107

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. per the sampling station 2 schedule in the sample per station) environmental at different places monitoring i.e. 4 stations of the plan DCRP Lot 2, CCECC- MAX Camp, Ramu Yard and BR 124 2.5 All roads, C C C PC PC C During the C permanent or monsoon dusty temporary, loads didn’t create pukka or any harm to the katcha, that become dusty local roads, and all areas therefore, no where suppression construction measures were related taken activities are carried out, During the post shall be subject monsoon to necessary sometimes dusty suppression loads make the measures by watering, construction area sweeping or or roads nearby other dusty as well. measures approved or From the mid directed by the November CCECC Engineer has engaged 5 water sprinkles to cover all their construction areas including local roads

2.6 Waste oil, C C C C C C No such activities C lubricant or like waste oil, other lubricant or other petroleum petroleum derivatives derivatives used as should not be dust suppressants were observed

108

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. used as dust suppressants 2.7 Contractor C C C C C C S14 & S16: Both C should take all side has reasonable permanent oil precautions to storage tank with prevent fully functional accidental condition. spillage of However, in the petroleum field level products, temporary fuel oil contact of such storage facility was materials with provided i.e. plastic soil or water containers or course through drums. No spill try discharge, run- was observed at ay off, and or site. Noticeably, no seepage fuel or fire related accident been recorded yet. 2.8 C C C C C C S1- S5: All the C Construction construction equipment equipment’s have should be deployed are brand maintained to new a good S6- S9: Most of the standard and construction idling of equipment’s have engines deployed are old discouraged required proper maintenance 2.9 The PC PC PC PC PC PC S1- S5: All the PC machinery construction emitting visible equipment’s have smoke should deployed are brand be banned new. A very limited from level of visible construction smoke was sites observed emitting from various machineries which is unavoidable. S6- S9: Most of the construction

109

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. equipment’s have deployed are old emit visible exhaust

2.10 C C C C C C S1- S5: During the C Contractor dry season, the should take all contractor used a reasonable water browsing measures to vehicle on a regular minimize dust- basis blowing from areas under his control by spraying water on stockpile, bare soil, haul road, un- surfaced traffic route and any other source of dust when conditions require dust suppression. 6. Water 3.1 Adequate PC PC PC C C C 20 major bridges C Polluti mitigation will be constructed on measure over 1 major river should be and other small Contro undertaken to canal or Khals. Out l limit the of 20 only 9 bridges (H_6.3 impact on all construction have ) water bodies been started within within the the last six months. Project area Only then contractor was undertaken steps to limit the impact (if any due to pilot pile or working

110

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. pile) for each and individual bridge located water bodies. Accordingly, BR 124 pilot pile construction was started in July. Therefore, the CMJV was barricading the rubber dam area in order to protect the surface water body. Likewise the same initiative was taken for BR 96, 120, 130, 155,161 and 162. 3.2 Earth N NA NA C C C At BR 124, 130, C moving in the A 120, 161 and 162 vicinity of locations, the watercourses contractor has should be kept been constructed to a minimum temporary to avoid diversion road sedimentation made of concrete and ring in order to contamination ensure or keep the from fuel and natural flow of lubricants. water. They also prepared some bund around the water courses with the sand bags. However, there were no chances of being pollution from fuel and lubricants. 3.3 Proper N C C C C C Proper disposal of C disposal of A bricks, cement, and bricks, cement, steel and steel reinforcement was

111

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. reinforcement ensured. Usually which will be CMJV bring back removed as the construction part of the waste to their reconstruction camp area and if of bridges/ possible reuse culverts should them accordingly. be ensured not Therefore, there to block stream were no chances to flow. block stream flow. Because of construction waste. 3.4 Temporary N NA C C C C At BR 124, 130, C erosion and A 120, 161 and 162 sedimentation locations, the control contractor has measures been constructed during temporary rehabilitation diversion of cross- road/cross drainage drainage structure structures on water body, should be made of concrete undertaken to ring in order to ensure that ensure or keep the sediment laden natural flow of run off does water. They also not enter the prepared some adjoining bund around the watercourses diversion channel with the sand bags. However, no sedimentation occurred yet due to lack of sufficient flow of water. 3.5 C C C C C C Construction C Construction materials and materials and waste was not waste should discharged in not be watercourse during discharged in construction of watercourse bridges/culverts

112

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. during because of construction of implementing bridges/culvert appropriate s by mitigation measure implementing i.e. proper appropriate barricading with mitigation bamboo fences and measure. create awareness among the workers. 4. Borrow 4.1 Contractor N NA NA N NA NA CMJV’s NA and should have A A subcontractors dredging permits for have been site extraction sites performing (H_6.4) and quantities dredging activities from with permission. appropriate CMJV only buys authorities dredged soil for construction 4.2 The water C C C C C C The water quality C quality should was maintained be maintained through disposal of through dredged spoil using disposal of appropriate outlet dredged spoil i.e. proper drainage using facility appropriate outlet 4.3 The N PC PC PC C C At Link road and PC stockpiles and C near Islamabad earthwork Station area should be well dredged sands maintained/pr were stockpiled on otected a temporary basis. Sands from the stockpiles were eroded but due to the construction of containment bund, the siltation occurred within the project area. 4.4 Erosion PC C C N NA NA S14: Construction C control A of retention wall,

113

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. measures settling basin, and should be improved drainage taken where systems have been erosion has finished as a part of noted erosion control measures. After monsoon drainage only to control erosion is not required. 5. Disposal 5.1 Adequate N NA NC PC C C The generated C of mitigative A construction debris constructi measures i.e. at BR 124, 120, on debris should be 130 and 96 usually (H_6.5) taken to limit collected through the impact of dump truck and construction send back to the debris on CCECC Camp or pedestrians, Ramu Yard and if local possible reuse communities them accordingly. and water Additionally, bodies within proper the Project housekeeping has area been ensured by the safety officer at all construction sites. Therefore, there was no recorded impact upon pedestrians, local communities and water bodies due to construction debris. 5.2 Cleared N PC PC PC C C The generated PC debris should C construction debris (70%) not be left on i.e. at BR 124, 120, the surface of 130 and 96 usually the ground or collected through buried in any dump truck and agricultural send back to the land CCECC Camp or Ramu Yard and if

114

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. possible reuse them accordingly. Sometimes the site personnel unattended left the debris on the surface of the ground for late removal. However, safety engineer was informed to ensure proper housekeeping. 5.3 Burning of C C C C C C No such thing C waste should happened at the not be allowed site 5.4 Man-made PC PC PC C C C S14, S15, & S16: PC construction These locations debris should have appropriate be disposed in classified waste bin designated facilities i.e. bin for disposal areas. reusable waste and The location kitchen waste. and nature of After the regular such disposal collection of waste shall be subject like kitchen waste to the approval are of the Engineer disposed/handed over to the municipality. On the other hand reusable waste such as PET bottles are sold to the local vendor. For the construction sites, few poly bags were provided to collect manmade waste which are disposed in a designated location approved by the engineer on

115

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. a daily basis. Besides, most of the manmade construction debris are supposed to reuse further, therefore, the generation rate or final disposal rate is not that significant. 5.5 All disposal PC PC PC PC PC PC Disposal areas are PC areas should be not designated yet finally graded due to lack of full to a uniform pace construction and level activities as well as condition and low generation left such that rate. However, at they create a the CCECC camp minimum they temporarily impact on the fixed a place to put surrounding their construction area debris which is secured with proper barricading. 6. 6.1 Servicing of C C C C C C No such servicing C Servicing machines or activities near to and equipment the rivers or Operating near rivers, streams or other equipment streams or bodies of water (H_6.6) other bodies of have been water should observed be carried out in such a manner as to avoid pollution with gasoline, diesel fuel, oil, grease, or surplus or disposable materials 6.2 The PC PC C C C C S14: Permanent C contractor Fuel storage area is should have

116

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. the proper under equipment to construction. transport fuel S16: MAX has so that spillage started their fuel oil will not occur facility at their yard. However, for the construction sites, every contractor has their own facility. Sometimes oil tanker go to the sites to ensure fuel facility. On the other hand they carry temporary fuel oil containers i.e. drum or tin container to the site. However, sometimes on site spillage was observed. Site officers were informed immediately to take necessary measures i.e. to use at least poly bags to avoid direct contact to the ground or arrange spill tray. 6.3 The C C C C C C All hydraulic C contractor systems, fuel should ensure systems and that, all lubricating systems hydraulic are found in good systems, fuel condition. systems and lubricating systems are in good condition

117

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. 6.4 Fuel spills C C C C C C No such thing C should not be observed at the site condoned, and during site visit. care shall be taken to avoid overfilling machines 6.5 The N NC PC PC C C S14: Fuel storage PC contractor C area is under should have oil construction. spill abatement Temporary storage equipment on area has lack of spill the site at abatement regular basis. equipment like sawdust, spill tray, sponge, or oil dispersant. After finishing the construction necessary measures will be taken immediately. S16: Fuel storage area has been constructed which is fully functional. Sand bucket was observed along with fire extinguisher near to the fuel station. Additionally, station is built in such a way spillage can controlled easily and possible to avoid direct contamination to the ground. 6.6 The type of C C C C C C The equipment are C equipment maintained in good shall be subject working condition. to the approval Regular of the maintenance was

118

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. Engineer, and undertaken by the the equipment appropriate should be personnel. maintained in good working condition. 6.7 Disposal of C C C C C C Disposal of used oil, C used oil, lubricants, tires, lubricants, etc. were done in tires, etc. accordance with should be in the EMP or as accordance directed by the with the EMP Engineer. or as directed by the Engineer 7. Control 7.1 Petroleum PC PC PC C C C S14: Permanent C of products Fuel storage area is Petroleum should be under construction Products stored in a which designed in (H_6.7) designated such a way spillage storage can be maintained. location where An oil tanker any spillage can usually be safely provides/meets maintained their daily fuel oil without demand. contamination S16: MAX has of the started their fuel oil surrounding facility at their areas yard. However, for the construction sites, every contractor has their own facility. Sometimes oil tanker go to the sites to ensure fuel facility. On the other hand they carry temporary fuel oil containers i.e. drum or tin container to the site. However,

119

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. sometimes on site spillage was observed. Site officers were informed immediately to take necessary measures i.e. to use at least poly bags to avoid direct contact to the ground or arrange spill tray. S5: No petroleum storage area either permanent or temporary was identified. An oil tanker usually provide/meet their daily fuel oil demand, readily available fire extinguishers were observed in the field. 7.2 Storage of C C C C C C Storage of C petroleum petroleum products products were not should not be observed to put in permitted in the vicinity of the vicinity of streams, rivers, or streams, rivers, other bodies of or other bodies water. of water. 7.3 Usage of PC PC C C C C S14: Permanent PC impermeable fuel storage site is liner place on under subsurface of construction. the storage S16: MAX has room to avoid started their fuel oil groundwater facility at their contamination yard. should be

120

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. ensured by the There is no such Contractor place of oil storage from where groundwater can be contaminated anyway 7.4 Presence of N NC PC PC PC C S14: Permanent PC all C fuel storage site is precautionary under measures construction. (sand/saw, fire However, extinguisher arrangement of etc.) should Fire extinguishers ensure to avoid for the whole site environmental have been pollution or fire observed during hazard. frequent visits to the site. S16: MAX has started their fuel oil facility at their yard. Sand bucket at the station area was observed. Fire extinguishers purchasing are ongoing. 8. Conflict 8.1 Blockages N NA NA N NA NA In September NA Between should be A A Monitoring of Elephant created with Biodiversity and equipment on Management Plan Human the identified (Revised During elephant travel wildlife/Elephant Constructi routes Parameters in on (H_6.8) Table 54, EMP) has been submitted to the Engineer for their approval (Ref: CCECC- MAX/DCRP/BR/18/ A/0260). 8.2 Sign N NA NA N NA NA Necessary NA posts/land A A measures will be marks should taken when

121

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. be installed construction work indicating starts. elephant travel track as a part of awareness creation 8.3 Storage N NA NA N NA NA Necessary NA sites should A A measures will be not establish at taken when a location that construction work might block or starts. irritate the elephants movement 9. Hill 9.1 Contractors N NA NA N NA NA Hill cutting areas NA cutting should have A A yet not handed and slope prime over to the protection ministerial contractor. (H_6.9) permit for hill Resettlement work cutting is ongoing. 9.2 Erosion & N NA NA N NA NA Necessary NA sediment A A measures will be control plans undertaken during should be the hill cut. prepared by the Contractor prior to commenceme nt of work 9.3 Proper N NA NA N NA NA Environment NA protection A A specialist along measure with the help from should the Earthwork establish like Engineering/Constr slope retaining uction Department walls and of the CCECC-MAX bioengineered JV jointly worked measures such on Hill Cutting as plant Management Plan fascines, and submitted for palisades and the Engineers brush layering approval. The plan to avoid slope includes all the measures that

122

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. failures or need to be taken landslides care of during and post hill cutting period. 10. 10.1 Provision C C C C C C S14- S16: C Occupatio of potable Submersible water nal Health water for pump has been and Safety workers at installed to these (H_10) camp sites sites in order to withdraw deep water and reserved in a water tank from where workers usually get their potable water. Safety officer was instructed to ensure safe water for the workers at the construction sites as well.

10.2 Provision N PC C C C C S14 - S16: In the C of readily C beginning of the accessible construction of First-Aid facility camps and for workers laboratory there was lack of First Aid facility. Overtime the situation getting better in every construction sites. Contractor has provided necessary first aid facility at each and every construction sites. 10.3 Adequate N PC C C C C S14-S16: The camp, C drainage in C yard and Lab has workers camps adequate drainage should be facility where more established to

123

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. prevent than 300 workers stagnant water stayed together. and formation of breeding sites for mosquitoes 10.4 Provision PC PC C C C C S14-S16: In the C of sanitary beginning of the toilet facility construction of and hygienic camp, there was accommodatio lack of sanitary n for workers toilet facility. at camp sites Overtime the situation improved and at the camp there are good sanitary facilities present for both workers and officers. Even for the construction sites, especially at MAX part, they provided temporary toiled facility made of ring slab for the onsite workers. 10.5 Workers PC PC C C C C S1- S16: Except the C should be HPD (Hear equipped with Protecting Device) appropriate during noisy work, personal contractor has protection ensured other equipment PPE’s for the (PPE), such as workers. After safety boots, measuring site helmets, noise level, gloves, necessary protective measures will be clothing, undertaken. breathing Gumboot along mask, goggles with other PPE’s and ear were provided to

124

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. protection, and the workers during contractor will the rainy season. enforce its use, 10.6 Fire- PC PC C C C C S1- S16: At each PC fighting and every equipment at construction sites the work areas including camp and and at yard, fire fighting construction equipment i.e. camps should different types of be provided fire extinguisher were arranged/put. However, since MAX has started their construction work very recently, therefore, at their sites there are lack of fire extinguisher which is under purchase process. 10.7 N NC PC PC C C S14: Initially, there PC Implementatio C was lack of fall n of fall prevention and prevention and protection protection measures. measures Thereafter, due to should be necessary actions ensured the contractor has whenever a arranged full body worker is harness while exposed to the working on height. hazard of Besides, during the falling more camp construction than 2 meters, guard rail was of falling into ensured where operating needed. machinery or Nowadays, there is through an no such activity i.e. opening work at height exist. 10.8 N PC PC C C C S14- S16: C Installation of A Arrangement of

125

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. guardrails with ladders and mid-rails and scaffolds have toe boards at ensured by the the edge of any contractor. fall hazard Applicable training area, proper is required for their use of ladders proper use. and scaffolds by trained employees should be ensured 10.9 Ensuring N C C C C C Sometimes C no C temporary involvement of appointed child labor subcontractors bring child labour along with them. However, if identified any instant action was ensured. 10.10 Ensuring C C C C C C Not identified yet C no involvement of bonded labor 10.11 Safety N PC C C C C S1-S16: Initially C measures C there was lack of including proper signage signage and facility due to lack staffing in of full pace interface construction between activities but later construction on the condition and/or has improved as construction because of regular related monitoring and site operations engineer was instructed to arrange signage and staffing at the work areas. At the MAX part, they also have arranged

126

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. necessary signage for their construction sits to be installed. 10.12 N C C C C C Signal men were C Reversing C set at different signals should entry and exit be installed on locations of the all construction construction sites. vehicles 10.13 PC PC PC PC C C Safety personnel PC Undertake was informed to check and take cleanliness cleaning at all initiative on a daily sites and areas basis prior leaving where the site. cleanliness should be ensured 10.14 Fences N C C C C C Proper barricading C should be A was observed at constructed to different separate the construction sites. construction sites at rail stations from public access 11. 11.1 Topsoil N NA NA PC PC PC S10, S11, S12 and PC Protection storage areas A S13: Top soil at of Topsoil should be these locations and soil protected were stored for erosion during the dry future (H_6.11) season from embankment wind erosion preparation. through However, no arranging plastic coverage plastic cover was possible to ensure. Besides, top soil is not sandy rather loamy, therefore, less chances to become loss the amount or

127

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. become even dusty. 11.2 Rapid re- N NA NA N NA NA Necessary NA vegetation and A A measures will be use of hydro- undertaken when seeding and needed jute erosion protection mats should be applied in areas where erosion has noted during the regular monthly inspections 11.3 N NA NA N NA NA Necessary NA Embankment A A measures will be site should be undertaken when planted with needed trees to promote natural vegetation; as well as fast growing grasses 11.4 Superficial N PC PC C C C During the C or organic A monsoon no material clearing, grubbing removed and stripping work during the was undertaken. excavation S10, S11, S12 and shall be S13: After clearing, stockpiled for grubbing and subsequent stripping, top soil use, or if at these locations surplus to the were stockpiled Contract along the RoW for requirement, subsequent use shall be during the disposed of in embankment designated preparation. disposal areas.

128

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Category/ Inspection Status Observation / Overall Environm Items/ Recommended observa ental Description of Ju Au Se Oc No De Action tion Safeguard activities ly g. pt. t. v. c. 11.5 The N C C C C C S10, S11, S12 and C stockpiling A S13: The and/or disposal stockpiling was not of material placed in any area should not be where natural placed in any drainage or storm area where water could pond natural and become drainage or stagnant, or where storm water could erode the could pond and material and cause become silting of the stagnant, or adjacent area or of where could any natural or man- erode the made water material and course. cause silting of the adjacent area or of any natural or man- made water course.

129

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Appendix 3: Environmental Quality Sampling Report Ambient Air Quality Report (ENRAC) for the month of June 2018

(I)

130

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Noise Monitoring Report for the month of June 2018

131

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

132

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

(II) Laboratory Test Repot of Surface Water Samples (SW1 – SW4) (BCSIR) for the month of June 2018

133

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

134

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

135

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

136

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

(III) Laboratory Test Repot of Ground Water Samples (GW1 – GW7) (BCSIR) for the month of June 2018

137

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

138

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

139

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

140

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

141

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

142

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

143

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

(I) Air Monitoring Report (ENRAC) for the month of September 2018

144

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

145

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

146

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

147

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

(II) Noise Monitoring Report for the month of September 2018

148

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

149

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

150

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

151

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

(III) Laboratory Test Repot of Surface Water Samples (SW1 – SW4) (BCSIR) for the month of September 2018

152

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

153

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

154

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

155

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

(IV) Laboratory Test Repot of Ground Water Samples (GW1 – GW7) (BCSIR) for the month of September 2018

156

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

157

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

158

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

(V) Laboratory Test Repot of Drinking Water Sample (BCSIR) for the month of September 2018

159

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Appendix 4: Photo Log

Photo 1 Noise source was identified at BR Photo 2 Major noise generated from 124 on 30.07.2018 behind a sensitive generators observed at BR 96 on 27.10.2018 receptor (mosque)

Photo 3: Major noise generated from Photo 4 Noise source was identified at BR generators observed at BR 130 on 05.11.2018 124 observed on 23.12.2108

Photo 5 Observed air quality during the first Photo 6 Dust pollution has not observed pilot pile at BR 124 on 30.07.2018 during construction of CCEC-MAX JV Camp on 11.07.2018

160

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 7: During load test at BR 124 no dust Photo 8: During the last pilot pile no dust observed due to rain on 15.09.2018 was observed at BR 130 on 05.11.2018

Photo 9 Oil tanker provides necessary fuel at Photo 10 Temporary oil storage facility at different sites observed at Napith Khali on Link road observed on 06.12.2018 02.10.2018

Photo 11 Temporary oil storage facility at BR Photo 12 Temporary oil carrier facility at 129 observed on 23.12.2018 Ramu Camp observed on 23.12.2018

161

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 13 Lack of PPEs of workers obsered at Photo 14: Lack of PPEs of workers obsered at Ramu Camp on 10.11.2018 Ramu Camp on 21.10.2018

Photo 15: Identified electrical hazard by the Photo 16: Lack of PPEs (Face Shield) caught consultant at CCECC-MAX JV camp on red handed by the HSE officer observed at BR 3.10.2018 120 on 06.12.2018

Photo 17: Potential suspect of child labor Photo 18 Identified fall from height hazard got red handed by the HSE manager at BR (lack of full body harness) on 21.10.2018 124 on 11.11.2018.But after inspection it was found that he was an adult.

162

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 19: Lack of proper housekeeping Photo 20: Lack of proper toilet observed at observed at Ramu Laboratory on 10.11.2018 BR 124 on 27.10.2018

Photo 21: Quarterly Noise measurement Photo 22: Noise source inspection by the held at BR 124 on 18.09.2018 Consultant at Napith Khali on 03.10.2018

Photo 23: Enclosure was provided to reduce Photo 24: Quarterly Noise measurement held the noise level as well as to protect the at BR 124 on 21.12.2018 machine from scorching sun observed at BR 124 on 11.11.2018

163

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 25: Air quality monitoring at Ramu Photo 26: Dust supression measure took camp on 20.09.2018 place at BR 124 on 06.12.2018

Photo 27: Dust control measure takes place Photo 28 Dust control measure includes local at Napith Khali Camp on 01.12.2018 road held on 06.12.2018

Photo 29: Water sprinkler was seen at BR Photo 30: Water sprinklers used to clean 130 on 23.12.2018 local road on 20.12.2018

164

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 31: Wetland protection measure was Photo 32: Wetland protection measure was taken at BR 124 observed on 13.11.2018 taken at BR 124 observed on 23.12.2018

Photo 33: Wetland protection measure was Photo 34: Wetland protection measure was taken at BR 120 observed on 06.12.2018 taken at BR 96 observed on 07.10.2018

Photo 35: Wetland protection measure was Photo 36: Collection of surface water taken at BR 162 observed on 26.12.2018 samples at BR 155 on 20.09.2018

165

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 37: Permanent fuel storage area is uder Photo 38: Fully functional 15000 L fuel construction at Ramu Camp observed on station with fire prevention facility was 10.11.2018 observed at Ramu Camp observed on 29.12.2018

Photo 39: Permanent fuel storage area is uder Photo 40: Fuel meter for the Permanent construction at CCECC-MAX JV Camp observed fuel storage at CCECC-MAX JV Camp on 29.12.2018 observed on 29.12.2018

Photo 41: Proper signage was seen at BR 124 Photo 42: Proper barricading was observed on 23.12.2018 at BR 124 on 23.12.2018

166

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 43: Proper housekeeping was ensured Photo 44: Proper housekeeping was ensured on 12.11.2018 on 12.11.2018

Photo 46: A regular housekeeping is Photo 45: Housekeeping is ongoing observed maintained at CMJV camp observed on at CCECC-MAX Camp on 22.07.2018 19.09.2018

Photo 47: Top soil was stored along the Photo 48: Top soil was stored along the edge edge of the RoW at Islamabad Station area of the RoW at near BR 124 observed on Ch. 72 observed on 20.11.2018 01.12.2018

167

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 49: Top soil was stored along the Photo 50: Top soil was stored along the edge edge of the RoW at Cox’s Bazar Station of the RoW at Ramu Station observed on observed on 26.12.2018 25.12.2018

Photo 51: Clear, grubbing and stripping Photo 52: Top soil was stored along the edge works ongoing observed at near BR 130 on of the RoW at BR 129 observed on 23.12.2018 20.11.2018

Photo 53: Stripping work is in progress at Photo 54: HSE Training at site Ch. 6+000

168

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 55: Pilot Pile concreting is in progress Photo 56: Monthly progress meeting at at Bridge no. 69 Engineer office with Lot-1

25/12/2018

Photo 57: BR PD with Engineer Site Visit & Photo 58: Rebar Cage Checking Before Check PVD Installation at Ch.74+500 Installation at Bridge No.124(A1) Working Pile 02

Photo 59: Completed Clearing & Grubbing Photo 60: Static Load Test For Bridge No.124 at Ch.99+500 to Ch.99+800 (Cox bazar (A2) Working Pile Station area)

169

Construction of Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum Near Myanmar

Photo 61: Pilot Pile Concrete Casting Work Photo 62: HIV Prevention Program at AIDS Ongoing at Bridge No.162(Ch93+595) DAY at Edigon Local Community

170