PROGRESS SHEETS 2001/02

    

                                                                                                                                                                                                                                                                                                                                   Ref Site Scheme Proposed        Comments                      Cost Code 2001/02 £'000s date LAFIS to Expected Year end Manager Project Works

G/LS/01/1 Various sites - to be determined Safety Cameras & related initiatives H5P/SQ 30 3.64 30 IM TM 4 new sites agreed with Police. 3 in WY. Site meeting to agree exact locations - 07/01    

    G/LS/01/2 Various sites - to be determined Speed Dynamic Signs - pilot scheme H5N/LK 25 0 25 IM TM Equipment options being assessed. Awaiting TRL report.

A4155 Road/ Lane [25] [25] C/LS/00/6 Roundabout H5N/DF 0 JMJ AO Draft Design complete. Waiting for Stats Info and S Audit Comments.     junction, Well End 25 25

    A404/A4155 Westhorpe interchange approach Central Hatching to prevent overtaking (with maintenance To be developed in conjunction with AO maintenance scheme. Proposals to be developed by C/LS/00/7 H5N/FA [15] 0 [15] MPB AO from Bourne End & to Bourne End scheme) 08/01

C/LS/00/8 C100 Wycombe Road j/w Bobmore Lane, Marlow Possible junction improvement H5Q/AC [10] 0 [10] DGL AO To be investigated in conjunction with Safer Routes to School scheme (C/AS/01/22) - 09/01    

    Review signing & lining on southern section between Clay C/LS/00/9 B482 to Marlow Road H5P/CU [20] 0 [20] JMJ AO Investigated but on hold until maintenance scheme. 07/01 Lane and Marlow Route review to include i) possible roundabout at j/w Four C/LS/01/2 A4128 and Ashes Road; ii) traffic calming; iii) pedestrian crossing H5N/KG 50 0 50 DGL H Brief issued to Highways Engineering (Hyder) - 04/01. Report awaited.

    facilities & iv) improved footway provision. A4155 Little Marlow Road j/w Westhorpe Rbt     C/LS/01/3 Provide Skid Resistant Surfacing H5N/KH 5 0 5 WR TM Details agreed. Tenders returned 18/05/01. Start date awaited. (West side)

C/LS/01/4 C177 -roads Consider double mini-roundabout H5P/GK 50 0 50 DGL H Brief issued to Highways Engineering (Hyder) - 04/01. Report awaited.     A4155 between Mill End and Oxfordshire     C/LS/01/6 Review speed limit to address accident rate H5N/KJ 10 0 10 SHW TM Investigation - 07/01 Boundary

C/LS/01/8 B482 Dean Street, Marlow Consider low cost Lining and signing measures H5P/GQ 5 0 5 DGL TM Investigation - 07/01    

    C/LS/01/9 Lane, Little Marlow Consider low cost Lining and signing measures H5Q/JT 5 0 5 DGL TM Investigation - 07/01

A4155 From Little Marlow to and including A404 C/AS/00/3 Shared use to complete Well End to A404 H5N/LP [35] 0 [35] MPB AO Brief sent to AO - 04/01. Works date to be agreed following discussion with AO.     interchange

    C/AS/00/7 Road, Narrowings COM JMJ AO Draft design sent to PC for approval 05/01.

Glory Mill Lane, Green Traffic Calming DEV JMJ DEV Consultation ended - 15/06/01.    

    C/AS/00/8 Oxford Road, Marlow Traffic Calming DEV JMJ DEV Construction of Development underway 05/01. Scheme to be completed before occupancy.

C/AS/00/19 B482 End 50mph speed limit TRO ID TM COMPLETED. Operational date 04/06/01. Gateways to be provided -07/01    

    C/AS/00/20 Waiting restriction mini-review TRO JMJ TM Draft Orders with Legal. Advertise 06/01.

    C/AS/00/21 Marlow: Thames Industrial Estate Measures to be agreed TRO JMJ TM Awaiting Halcrow report

    C/AS/00/22 Marlow Waiting restriction review. Consolidation Order required TRO WR TM Detailed site work to begin 06/01. Consultation 07/01.

WY Progress Sheets 2001-02 1of5 03/07/2001 HIGH WYCOMBE PROGRESS SHEETS 2001/02

    

                                                                                                                                                                                                                                                                                                                                                       Ref Site Scheme Proposed        Comments                      Cost Code 2001/02 £'000s date LAFIS to Expected Year end Manager Project Works

C/AS/00/23 A4155 De-restriction Order (due to new lighting) TRO JMJ TM Speed surveys ordered from Hyder 05/01.    

    C/AS/01/3 A40/A4010 Resigning (throughout County) Resigning of primary/non-primary route H5N/SA 10 0 10 JMJ TM Wycombe (eastern) TC resigning completed. Wycombe (western) TC resigning - 07/01

Marlow Transport Strategy measures - to be agreed (to

    C/AS/01/6 A4155 & High Street (Town Centre), Marlow include improved pedestrian facilities in Spittal Street & West H5N/KL 100 0 100 DGL H Meeting to agree way forward - 26/06/01. Street and development of Cycle Network)

    C/AS/01/11 A40 Oxford Road, Stokenchurch Pelican Crossing (£25k developer funding) H5N/KR 35 0 35 SHW AO Awaiting funding from developer

    C/AS/01/12 A4129 Thame Road, Investigate pedestrian facilities H5N/KS 5 0 5 JMJ TM Investigate 06/01

    C/AS/01/13 C77 Valley Road, Investigate pedestrian facilities H5P/GN 5 0 5 JMJ TM Investigate 06/01

        C/AS/01/16 Mill Lane, Princes Risborough Footway H5Q/JX 5 0 5 JFS AO Details to be agreed - 07/01

    C/AS/01/17 Picts Lane, Princes Risborough Footway H5Q/JY 20 0 20 JFS AO Details to be agreed - 07/01

C/AS/01/18 Four Ashes Road, Cryers Hill Investigate footway provision H5Q/KA 5 0 5 JFS TM Details to be agreed - 07/01

   

    C/AS/01/19 Chalkpit Lane, Marlow Investigate improved footway H5Q/KB 5 0 5 JFS TM Details to be agreed - 07/01

C/AS/01/20 B482 j/w Clay Lane, Marlow Consider small roundabout H5P/GP 10 0 10 DGL H Brief issued to Highways Engineering (Hyder) - 04/01. Report awaited.

   

    C/AS/01/22 /Foxes Piece Schools, Marlow Safer Routes to School initiative H5Q/KD 20 0 20 DGL SRtS Awaiting first meeting of Working Group.

C/AS/01/23 Princes Risborough Development of Cycle Network H5Q/KE 5 0 5 MPB TM Consultant to be appointed - 07/01     Icknield Junior/Berryfield Schools, Princes     C/AS/01/28 School Travel Plan - Education DEV MR SRtS Initial meeting held - awaiting progress report from school Risborough

C/AS/01/33 The Causeway, Marlow Possible Market Order(s) TRO JMJ TM WDC Using Town Police Clauses Act.    

    C/AS/01/34 Watery Lane, Possible Questionnaire / survey re: Prohibition of Driving TRO TRO GJB TM Questionnaire / survey to be agreed - 09/01

Main Road, Little Lane & Lower Road, Loosley C/AS/01/35 30mph speed limit & 40mph Speed Limit Extension COM JMJ TM PC survey received. Response 06/01     Row

    W/LS/00/1 A4094 Road j/w Ferry Lane, Bourne End Signing and lining. H5N/RU [15] 0 [15] WR TM Details agreed & consultation completed. Works 06/01.

W/LS/00/2 A4094/B4440 The Green, Traffic Management Scheme H5N/SV [35] 0 [35] ID AO Final public consultation 06 & 07/01     A 40 London Rd/Harlow Rd/Stuart Road, High     W/LS/00/3 Conflict involving right turners egressing side roads - HMC/GU [5] 0 [0] JFS TM Investigated but no further action recommended. Wycombe [10] [10] W/LS/00/4 A 40 j/w The Pastures, Improvements to signals (Re-phasing) H5N/LM 0 DGL H Brief issued to Highways Engineering (Hyder) - 04/01. Report awaited.     10 10

WY Progress Sheets 2001-02 2of5 03/07/2001 HIGH WYCOMBE PROGRESS SHEETS 2001/02

    

                                                                                                                                                                                                                                                                                                                                             Ref Site Scheme Proposed        Comments                      Cost Code 2001/02 £'000s date LAFIS to Expected Year end Manager Project Works

W/LS/00/5 Western Dene / The Link junction, Kerbing and barrier works HMD/NS [5] 0 [5] SHW AO Work delayed due to flooding, should be 06/01     Holmers Farm Way j/w Crest Road, High     W/LS/00/6 Central refuges or possible mini roundabout H5Q/CN [15] 0 [15] SHW AO Scheme designed. Consultation ends 22/06/01. Wycombe

W/LS/00/7 B4440 Holtspur Lane, Wooburn Green Gateway feature and extension of 30mph speed limit HMD/NT [5] 0 [5] SHW TM Speed limit changes advertised - no objections. Final consultation with The Green scheme    

    W/LS/00/8 Cressex Rd, High Wycombe Traffic Calming scheme H5Q/CQ [30] 240 [30] MPB AO Brief sent to AO. Resurfacing completed. Traffic Calming works 06 & 07/01

[82] [82] Prelim design completed. Formal consultation 21/05/01 - 15/06/01. Public consultation incl W/LS/00/9 C102 Heath End Rd/Straight Bit, Traffic Calming scheme H5P/CY 0 IM H     20 20 exhibition 23 & 24/06/01.

    Road markings completed. One refuge, one central island to be constructed - consultation W/LS/00/10 A4010 New Road, High Wycombe Traffic Calming scheme H5N/EZ [50] 15 [50] IM AO underway. Brief to AO - 07/01. [10] [10] W/LS/00/11 A40 London Road Nr Abbey Barn Rd junction Pedestrian Crossing H5N/LJ 0 DGL H With Hyder for prelim design and consultation.     40 40

    W/LS/00/12 Bowerdean Road, High Wycombe Calming scheme including cushions H5Q/HM [30] [30] JMJ On hold pending Halcrow Sudy

    W/LS/00/13 Desborough Avenue, High Wycombe Calming scheme including narrowings and refuges H5Q/LK [35] [35] JMJ On hold pending Halcrow Sudy

    A404 Amersham Road j/w Hamilton Road, High W/LS/01/1 Investigate improved pedestrian provision (guardrail) H5N/LD 15 0 15 JFS AO Guardrail not feasible because of accesses. Monitor situation. Wycombe

    W/LS/01/2 C91 Sawpit Hill j/w Western Dene, Roundabout H5P/HA 60 0 60 DGL H Brief issued to Highways Engineering (Hyder) - 04/01. Report awaited.

    W/LS/01/3 The Pastures estate, High Wycombe Consider area traffic management scheme H5Q/KV 50 0 50 PAF H Brief issued to Highways Engineering (Hyder) - 11/06/01. Report awaited.

    W/LS/01/4 Blind Lane, Flackwell Heath/Bourne End Consider skid resistant surfacing and improved signing H5Q/KW 10 0 10 WR TM Anti skid tenders returned 18/05/01 - start date awaited. Signing to be agreed - 06/01.

W/LS/01/5 C99 Lane End Road, Sands Consider low cost Lining & signing measures H5P/HB 5 0 5 DGL TM Investigation - 07/01

   

    W/LS/01/6 B474 Penn Road, Hazlemere Consider low cost Lining & signing measures H5P/HC 5 0 5 DGL TM Investigation - 07/01

W/LS/01/7 Rose Avenue, Hazlemere Consider traffic calming H5Q/KX 20 0 20 DGL AO Investigation - 07/01

    C125 Totteridge Lane & Totteridge Road, High     W/LS/01/8 Consider traffic calming H5P/HD 10 0 10 DGL H Brief issued to Highways Engineering (Hyder) - 04/01. Report awaited. Wycombe A4128 Glenisters Road, High Wycombe near W/AS/00/1 Zebra Crossing (PLUS £18,000 DEVCON contribution) H5N/FC [10] 0 [10] WR AO Brief sent to AO - 11/00. Works to be completed by end 06/01.

    Safeway Awaiting Signal Reconfiguration - Feasibility Study from     W/AS/00/2 Crendon St j/w High Street, High Wycombe H5N/WA [5] 0 [5] JMJ H Babtie report received. GSS and RS to decide on progression 06/01 Babtie

W/AS/00/3 High Wycombe Town Centre Car Parks Demonstration Project - Dynamic Car Park signing H5P/WJ [75] 0 [75] JMJ TM Factory Acceptance tests 05/01. Erection, 06/01.     Holmers Farm Way to East - West route, High Consultation completed. Report to Rodney Royston needed - 05/01. Brief to be sent to AO -     W/AS/00/4 Cycle route H5Q/GJ [20] [20] MPB AO Wycombe 06/01.

WY Progress Sheets 2001-02 3of5 03/07/2001 HIGH WYCOMBE PROGRESS SHEETS 2001/02

    

                                                                                                                                                                                                                                                                                                                                             Ref Site Scheme Proposed        Comments                      Cost Code 2001/02 £'000s date LAFIS to Expected Year end Manager Project Works From East - West cycle route to A4094, High W/AS/00/5 Extend cycle route H5N/HP [20] [20] MPB AO Traffic calming scheme to be developed. Consultation next - 06/01.     Wycombe

    W/AS/00/6 Frogmoor, High Wycombe Various TROs TRO JMJ TM Implemention - 07/01

W/AS/00/7 Fraser Road, High Wycombe Prohibition of Driving TRO JMJ TM Consultation - 06/01    

    W/AS/00/8 Bus Stop Clearways - Marlow Hill Consultations required and Advert TRO JMJ TM To be investigated - 09/01

W/AS/00/9 Flackwell Heath Waiting Restriction Review TRO IM TM To be considered as part of traffic calming scheme - see W/LS/00/9.    

    W/AS/00/10 Wooburn Green to include Wooburn Town Waiting Restriction Review TRO ID TM On hold pending the "Green" scheme

W/AS/01/1 Wycombe Further development & updating of Cycle Network H5Q/KY 5 0 5 MPB TM Consultant to be appointed - 07/01    

    Investigate pedestrian facilities (in conjunction with cycle W/AS/01/2 Station Road, Loudwater H5Q/KZ 20 0 20 DGL AO Prelim design completed. Consultation 06/01. route) A404 Amersham Hill j/w The Shrubbery, High W/AS/01/3 Pedestrian Refuge H5N/LE 10 0 10 JMJ AO Investigate 06/01     Wycombe

    Cressex Road near Verney Avenue, High W/AS/01/4 Pedestrian Refuge H5N/LF 10 0 10 JMJ AO Investigate 06/01 Wycombe

    W/AS/01/5 Hamilton Road, High Wycombe Pelican Crossing H5Q/LA 20 0 30 DGL AO Prelim design underway. Consultation - 06/01

    W/AS/01/6 A4128 Hughenden Road, High Wycombe Consider traffic calming and/or Zebra Crossing H5N/LG 25 0 25 DGL AO Prelim design underway. Consultation - 06/01

    W/AS/01/7 A4155 Road, Bourne End Investigate pedestrian facilities H5N/LH 5 0 5 JMJ TM Investigate 06/01

A40 London Road near Thanstead Farm, High Prelim design underway. Consultation - 06/01. Amendment to speed limit also required. W/AS/01/8 Pelican or Toucan Crossing (£45k developer funding) H5N/LJ 15 0 15 DGL AO Wycombe Details sent to Legal 05/01.    

    W/AS/01/9 Daws Hill Lane, High Wycombe Footway H5Q/LB 15 0 15 JFS AO Details to be agreed - 07/01

W/AS/01/10 Treadaway Hill, Flackwell Heath Footway (£5k contribution from Oxford Diocese) H5Q/LC 15 0 15 JMJ AO Details agreed. Consultation next - 07/01

    Lansdowne Primary/Shelburne Infant/Cressex [60]     W/AS/01/11 Safer Routes to School initiative H5Q/LD 0 60 MPB SRtS Proposals being developed for next Working Group meeting - 06/01. Schools 60

W/AS/01/12 The Disraeli Combined School School Travel Plan H5Q/LE 20 0 20 PAF SRtS Next meeting of Working Group - 29/06/01

   

    W/AS/01/13 The Downley schools (both sites) School Travel Plan H5Q/LF 40 0 40 PAF SRtS Next meeting of Working Group - 05/10/01 (First meeting08/06/01)

W/AS/01/14 High Wycombe Combined School Travel Plan H5Q/LG 5 0 5 MR SRtS Initial meeting held - parent meeting planned - 13/06/01    

    W/AS/01/15 Special Parking Area Amendment Order TRO JFS TM Details to be agreed with GSS - 07/01

WY Progress Sheets 2001-02 4of5 03/07/2001 HIGH WYCOMBE PROGRESS SHEETS 2001/02

    

     

     

                                                                                                                                                         Ref Site Scheme Proposed        Comments                      Cost Code 2001/02 £'000s date LAFIS to Expected Year end Manager Project Works

W/AS/01/16 The Parade, Bourne End Cycle Racks and Notice Board H5N/GH 3 0 3 JMJ AO With AO for implementation    

   

    TOTAL for 2001/02 730 254.69 800

   

                          SCHEMES ALLOCATED HIGH OR MEDIUM PRIORITY (for investigation) AT LOCAL COMMITTEE

Totteridge Road, High Wycombe Waiting restrictions / extension of SPA JFS APRIL 2001 - M - See W/AS/01/15 above    

   

   

   

   

WY Progress Sheets 2001-02 5of5 03/07/2001