Bridges and Tunnels Committee Meeting

November 2020

Committee Members L. Lacewell, Chair A. Albert J. Barbas N. Brown R. Glucksman K. Law D. Mack H. Mihaltses J. Samuelsen L. Schwartz V. Tessitore N. Zuckerman Bridges & Tunnels Committee Meeting , 20th Floor Board Room , NY 10004 Wednesday, 11/18/2020 10:00 AM - 5:00 PM ET

1. Summary of Actions - None

2. Public Comments Period

3. Approval of Minutes - October 2020 B&T Committee Minutes - October 2020 - Page 3

4. Approval of Committee Work Plan B&T Committee Work Plan - Page 4

5. Report on Operations - September 2020 B&T Report on Operations - September 2020 - Page 11

6. Safety Report - September 2020 B&T Safety Report - September 2020 - Page 25

7. Capital Program Project Status Report - October 2020 B&T Capital Program Project Status Report - October 2020 - Page 30

8. Procurements - None

Minutes of Committee Meeting October 2020

Because of the ongoing COVID-19 public health crisis, the MTA Chairman convened a one-day, virtual Board and Committee meeting session on October 28, 2020 which included the following MTA committees:

Rail Road and Metro-North Railroad; • Transit; • MTA Bridges and Tunnels; • Finance; • Capital Program Oversight Committee; • Safety; and • Audit Committee.

To see a summary of the meeting and the actions taken by the Bridges and Tunnels Committee, please refer to the October 28, 2020 Board minutes in the November 2020 Board Book available here on the Board materials website: https://new.mta.info/transparency/board-and-committee-meetings/november- 2020.

______Master Page # 3 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020

Committee Work Plan

______Master Page # 4 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 BRIDGES & TUNNELS COMMITTEE WORK PLAN

______I. RECURRING AGENDA ITEMS

TOPIC Responsibility Approval of Minutes Committee Chair & Members Committee Work Plan Committee Chair & Members Report on Operations Revenue Management Safety Report Safety & Health Financial Report Controller/Planning & Budget Capital Program Project Status Report Construction & Development/ Planning & Budget Procurements Procurement & Materials Action Items (if any)

II. SPECIFIC AGENDA ITEMS Responsibility

November 2020 No items scheduled

December 2020 2021 Proposed Committee Work Plan Committee Chair & Members 2021 Proposed Final Budget Planning & Budget Diversity Report – 3rd Quarter 2020 EEO

January 2021 Approval of 2021 Work Plan Committee Chair & Members

February 2021 Preliminary Review of 2020 Operating Budget Results Planning & Budget 2021 Adopted Budget/Financial Plan 2021-2024 Planning & Budget 2020 B&T Operating Surplus Controller 2020 Customer Environment Report Operations Diversity Report – 4th Quarter 2020 EEO

March 2021 Annual Procurement Contracts Report Procurement & Materials/ Finance

April 2021 Final Review of 2020 Year-End Operating Results Planning & Budget

May 2021 Diversity Report – 1st Quarter 2021 EEO

______Master Page # 5 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 June 2021 No items scheduled

July 2021 No items scheduled

August 2021 No meeting scheduled

September 2021 2022 Preliminary Budget Planning & Budget Diversity Report – 2nd Quarter 2021 EEO

October 2021 2022 Preliminary Budget Planning & Budget

______Master Page # 6 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 BRIDGES & TUNNELS COMMITTEE WORK PLAN

Detailed Summary

I. RECURRING

Approval of Minutes Approval of the official proceedings of the Committee Meeting.

Report on Operations Summary of major B&T service indicators, including graphs and tables depicting total traffic for all facilities, average daily traffic by method of payment and vehicle type, traffic by facility, and data on factors that can impact B&T traffic such as weather and gasoline prices. The Report on Operations is provided on a two-month lag, except in September when it includes reports with June and July data.

Safety Report A compilation of key leading and lagging customer and employee safety indicators, including collision rates, employee lost time injury rates, construction injury rates, and leading indicators for roadway, construction, and fire safety. The Safety Report is provided on a two month lag, except in September when it includes reports with June and July data.

Financial Report Summary presentation of the financial indicators for the month, which includes the Balance Sheet for the reported month, Accrual Statement of Operations for the month and year-to- date, variance analysis, traffic volume and ridership information, toll collection rates, and headcount charts. The Financial Report is provided on a one-month lag, except in the month of September, at which time it includes the July and August reports.

Capital Program Project Status Report Summary of the status of the current capital program, including commitments, completions, and closeouts, in addition to graphic presentations of the commitments and completions for the plan vs. actuals for the year. The Capital Program Project Status Report is provided on a one-month lag, except in the month of September, at which time it includes the July and August reports.

Procurements List of procurement action items requiring Board approval. The non-competitive items are listed first, followed by competitive items, and then ratifications. The list will indicate items that require a 2/3 vote and a majority vote of the Board for approval. Procurements are for the current month; in the month of September, the August and September procurements are included.

Staff summary documents presented to the Board for approval for items affecting business standards and practices.

______Master Page # 7 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020

II. SPECIFIC AGENDA ITEMS

NOVEMBER 2020 No items scheduled.

DECEMBER 2020 2021 Proposed Committee Work Plan The Committee Chair will present a draft Bridges and Tunnels Committee Work Plan for 2021 that will address initiatives to be reported throughout the year.

2021 Proposed Final Budget The Committee will recommend action to the Board.

Diversity Report – 3rd Quarter 2020 Review and discuss workforce analysis and activities as presented to the Board’s Diversity Committee Quarterly meeting.

JANUARY 2021 Approval of Work Plan for 2021 The committee will have already received a draft work plan for 2021 at the December 2020 meeting. The committee will be requested to approve the amended work plan for the year.

FEBRUARY 2021

Preliminary Review of 2020 Operating Budget Results The agency will present a brief review of its 2020 Operating Budget results.

2021 Adopted Budget and February Financial Plan 2021-2024 The Agency will present its revised 2020 Adopted Budget and Financial Plan which will incorporate any changes made by the Board at the December 2020 meeting and any Agency technical adjustments.

2020 B&T Operating Surplus The Committee will recommend action to the Board.

______Master Page # 8 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020

FEBRUARY 2021 (cont’d)

2020 Customer Environment Report Review and discuss key customer service areas: improve customer service and traffic mobility at all facilities; ensure the safety of customers traveling over the bridges and tunnels; and enhance the customer environment of facilities.

Diversity Report – 4th Quarter 2020 Review and discuss workforce analysis and activities as presented to the Board’s Diversity Committee Quarterly meeting.

MARCH 2021 Annual Procurement Contracts Report This report contains information on contracts awarded during the previous fiscal year and contracts open from the previous years as required by Section 2879 of the State Public Authorities Law.

APRIL 2021 Final Review of 2020 Year-End Operating Results

The customary review of prior year’s budget results and their implications for current and future budget performance will be presented to the Committee. Each Agency will present for inclusion in the Agenda materials, and be prepared to answer questions, on a review of its experience. The MTA Budget Division will prepare an overall review also for inclusion in the materials that draws MTA-wide conclusions.

MAY 2021 Diversity Report – 1st Quarter 2021 Review and discuss workforce analysis and activities as presented to the Board’s Diversity Committee Quarterly meeting.

JUNE 2021 No items scheduled

JULY 2021 No items scheduled

AUGUST 2021 No meeting scheduled

SEPTEMBER 2021

2022 Preliminary Budget Agency will present highlights of the Preliminary Budget to the Committee. Public comment will be accepted on the 2022 Preliminary Budget.

______Master Page # 9 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020

SEPTEMBER 2021 (cont’d) Diversity Report – 2nd Quarter 2021 Review and discuss workforce analysis and activities as presented to the Board’s Diversity Committee Quarterly meeting.

OCTOBER 2021 2022 Preliminary Budget Public comment will be accepted on the 2022 Preliminary Budget.

______Master Page # 10 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 Report on Operations September 2020

______Master Page # 11 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 MTA Bridges and Tunnels September 2020 Traffic Trends

Summary

In September, B&T vehicle traffic continued to recover from the impacts of the COVID-19 pandemic. Paid vehicle traffic was 24.0 million vehicles, which was 13.6% lower than in the same period in 2019. Though there has been improvement in every month since April, when paid vehicle traffic was 65% below 2019 levels, the rate of recovery for traffic has begun to stabilize.

Average daily traffic decreased by 14.0% for passenger cars and 8.1% for other vehicles compared to September 2019. Average daily E-ZPass transactions decreased by 14.8% on a year-to-year basis for the month, whereas Tolls by Mail transactions increased by 11.7%. Year to Date E- ZPass market share remains at 95.5%.

Gas prices averaged $2.26 per gallon during the month of September compared to $2.71 during the same time last year. Since April, gas prices have remained significantly lower than 2019 levels.

______Master Page # 12 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 ______

MTA Bridges and Tunnels Traffic Volume - All Facilities Master Page # 13 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 Two Years Ending September 2020

32.00

29.25 29.44 30.00 28.79 28.86 28.30 27.79 27.79 27.42 28.00 28.11 26.91 26.96 27.33 27.18 26.58 26.95 25.37 26.00 24.54 25.01 24.00 24.42 23.53 23.32 24.00 22.00

20.00 20.00 18.93 18.00 Vehicles Vehicles in Millions 16.00 14.95 14.00

12.00

10.00 9.73 8.00 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

9/19 - 9/20 9/18 - 9/19 ______

MTA Bridges and Tunnels E-ZPass and Tolls by Mail Traffic September 2020 Preliminary data subject to final audit Master Page # 14 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 All B&T Facilities by Method of Payment

September 2020 September 2019 2020 YTD

E-ZPass1 22,578,988 26,511,119 175,901,556 Tolls by Mail1 1,423,376 1,274,514 9,377,112 Total 24,002,364 27,785,633 185,278,668

E-ZPass Market Share: Total 94.1% 95.4% 95.5% Cars 93.9% 95.3% 95.4% Trucks 96.5% 96.7% 96.5%

Average Weekday2 Average Weekend2 September 2020 E-ZPass Market Share September 2020 E-ZPass Market Share Facility Total E-ZPass TBM Sep 2020 Sep 2019 Change Total E-ZPass TBM Sep 2020 Sep 2019 Change Bronx-Whitestone Bridge 124,301 115,876 8,425 93.2% 94.7% -1.5% 125,319 114,409 10,911 91.3% 92.7% -1.4% Cross Bay Bridge 23,145 22,019 1,127 95.1% 97.4% -2.2% 21,191 19,817 1,375 93.5% 95.9% -2.4% 63,596 60,406 3,190 95.0% 96.2% -1.3% 53,200 49,733 3,468 93.5% 94.9% -1.4% Hugh L. Carey Tunnel 55,479 53,186 2,294 95.9% 96.4% -0.5% 36,466 34,255 2,211 93.9% 94.7% -0.7% Marine Parkway Bridge 23,065 22,180 885 96.2% 97.2% -1.1% 21,734 20,576 1,158 94.7% 96.2% -1.6% Midtown Tunnel 68,455 64,833 3,623 94.7% 97.1% -2.4% 51,344 47,460 3,884 92.4% 95.5% -3.1% Robert F. Kennedy Bridge 163,424 153,517 9,907 93.9% 95.7% -1.7% 146,855 135,056 11,800 92.0% 94.0% -2.1% 104,234 98,187 6,047 94.2% 95.2% -1.0% 109,917 101,250 8,668 92.1% 93.0% -0.9%

Verrazzano-Narrows Bridge1 200,911 192,208 8,704 95.7% 96.6% -1.0% 183,530 171,683 11,848 93.5% 94.7% -1.1% All Facilities1 826,610 782,409 44,201 94.7% 96.0% -1.4% 749,557 694,237 55,321 92.6% 94.2% -1.6%

Notes: 1. At the Verrazzano-Narrows Bridge (VNB), tolls are only collected in the westbound direction. These transactions are doubled to provide traffic statistics that are consistent with B&T's other facilities. 2. Average traffic and market share figures exclude holidays. MTA Bridges and Tunnels E-ZPass and Tolls by Mail Traffic September 2020 Preliminary data subject to final audit

Distribution by Facility & Time Period September 2020 Facility Weekday AM Peak Weekday PM Peak Off-Peak Bronx-Whitestone Bridge 22.5% 24.0% 53.5% Cross Bay Bridge 21.2% 25.7% 53.1% Henry Hudson Bridge 22.7% 29.8% 47.5% Hugh L. Carey Tunnel 24.6% 27.6% 47.8% Marine Parkway Bridge 21.9% 28.0% 50.0% Queens Midtown Tunnel 24.4% 24.7% 50.9% Robert F. Kennedy Bridge 24.3% 22.9% 52.8% Throgs Neck Bridge 23.6% 24.4% 52.0% Verrazzano-Narrows Bridge1 16.2% 29.9% 53.9% All Facilities 22.5% 25.7% 51.8%

Payment Method by Facility (Transactions) September 2020 NY CSC Non-NY CSC Tolls by Facility E-ZPass E-ZPass Mail Bronx-Whitestone Bridge 87.7% 4.9% 7.4% Cross Bay Bridge 92.8% 1.8% 5.4% Henry Hudson Bridge 83.6% 11.0% 5.4% Hugh L. Carey Tunnel 88.8% 6.6% 4.6% Marine Parkway Bridge 92.3% 3.4% 4.3% Queens Midtown Tunnel 86.7% 7.4% 5.8% Robert F. Kennedy Bridge 87.4% 6.0% 6.6% Throgs Neck Bridge 85.9% 7.7% 6.5% Verrazzano-Narrows Bridge 86.2% 8.9% 5.0% All Facilities 87.0% 7.1% 5.9%

Note: 1. Traffic distributions reported in westbound tolled direction only

______Master Page # 15 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 ______

MTA Bridges and Tunnels Average Daily Traffic Master Page # 16 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 All Vehicles September 2018- September 2020 1,000,000

900,000 905,838

800,079 800,000

700,000

600,000

500,000

400,000

300,000 ______

MTA Bridges and Tunnels

Master Page # 17 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 Average Daily Traffic E-ZPass September 2018- September 2020 Vehicles 1,000,000

900,000

854,324 800,000 752,633

700,000

600,000

500,000

400,000

300,000 ______

MTA Bridges and Tunnels

Master Page # 18 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 Average Daily Traffic Tolls by Mail September 2018- September 2020 Vehicles

60,000

51,514 50,000

47,446

40,000

30,000

20,000

10,000

- ______

MTA Bridges and Tunnels Average Daily Traffic Master Page # 19 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 September 2018- September 2020 Passenger 1,000,000 Vehicles

900,000 846,207

800,000 742,210

700,000

600,000

500,000

400,000

300,000

200,000 ______

MTA Bridges and Tunnels Other Average Daily Traffic Master Page # 20 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 September 2018 - September 2020 70,000 Vehicles

65,000

60,000 59,631 57,869

55,000

50,000

45,000

40,000

35,000 ______

MTA Bridges and Tunnels Percent Change in Average Daily Traffic by Toll Media

3 Months(2) 6 Months(3) 9 Months(4) 12 Months(5) Corridor Toll Media Sep(1) (Jul-Sep) (Apr-Sep) (Jan-Sep) (Oct-Sep) Master Page # 21 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 All Facilities Total Vehicles -13.6% -16.7% -32.1% -25.4% -19.1% E-ZPass -14.8% -17.5% -32.6% -25.1% -18.6% Tolls by Mail 11.7% -0.2% -23.6% -24.8% -22.4%

RFK Bridge Total Vehicles -16.2% -18.7% -34.0% -27.1% -20.2% E-ZPass -17.8% -19.9% -34.6% -26.9% -19.8% Tolls by Mail 14.1% 2.3% -22.5% -25.1% -23.2%

Queens Midtown Tunnel Total Vehicles -19.7% -23.6% -42.3% -33.1% -24.7% Hugh L. Carey Tunnel E-ZPass -21.4% -24.9% -43.0% -33.1% -24.5% Tolls by Mail 29.3% 10.6% -22.9% -26.1% -24.4%

Bronx-Whitestone Bridge Total Vehicles -13.0% -15.9% -30.2% -25.3% -17.9% Throgs Neck Bridge E-ZPass -14.1% -16.6% -30.5% -25.0% -17.3% Tolls by Mail 4.2% -5.4% -26.3% -24.9% -23.5%

Verrazano-Narrows Bridge Total Vehicles -8.4% -11.6% -25.4% -19.9% -15.0% E-ZPass -9.3% -12.2% -25.7% -19.6% -14.6% Tolls by Mail 11.8% 0.6% -19.2% -20.3% -18.1%

Henry Hudson Bridge Total Vehicles -17.6% -22.9% -44.0% -34.6% -25.8% E-ZPass -18.7% -23.5% -44.3% -34.3% -25.4% Tolls By Mail 7.1% -10.2% -37.9% -36.8% -31.3%

Marine Parkway Bridge Total Vehicles -5.8% -6.7% -18.9% -15.7% -12.2% Cross Bay Bridge E-ZPass -7.0% -7.7% -19.5% -15.7% -12.1% Tolls by Mail 25.6% 14.7% -4.8% -7.6% -9.0%

(1) September 2020 vs. September 2019 (2) July 2020 to September 2020 vs. July 2019 to September 2019 (3) April 2020 to September 2020 vs. April 2019 to September 2019 (4) January 2020 to September 2020 vs. January 2019 to September 2019 (5) October 2019 to September 2020 vs. October 2018 to September 2019 ______

MTA Bridges and Tunnels Percent Change in Average Daily Traffic by Vehicle Type

3 Months(2) 6 Months(3) 9 Months(4) 12 Months(5) Corridor Toll Media Sep(1)

Master Page # 22 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 (Jul-Sep) (Apr-Sep) (Jan-Sep) (Oct-Sep)

All Facilities Total Vehicles -13.6% -16.7% -32.1% -25.4% -19.1% Passenger -14.0% -17.1% -33.0% -26.1% -19.6% Other -8.1% -10.5% -20.4% -15.4% -11.5%

RFK Bridge Total Vehicles -16.2% -18.7% -34.0% -27.1% -20.2% Passenger -16.5% -19.1% -34.8% -27.8% -20.7% Other -12.8% -14.8% -24.3% -18.7% -14.3%

Queens Midtown Tunnel Total Vehicles -19.7% -23.6% -42.3% -33.1% -24.7% Hugh L. Carey Tunnel Passenger -20.0% -24.1% -42.9% -33.6% -25.1% Other -15.1% -17.6% -33.4% -25.1% -18.4%

Bronx-Whitestone Bridge Total Vehicles -13.0% -15.9% -30.2% -25.3% -17.9% Throgs Neck Bridge Passenger -13.9% -16.9% -31.8% -26.1% -18.9% Other -3.5% -5.2% -12.7% -14.8% -7.3%

Verrazano-Narrows Bridge Total Vehicles -8.4% -11.6% -25.4% -19.9% -15.0% Passenger -8.8% -11.9% -26.0% -20.4% -15.4% Other -3.4% -7.5% -16.7% -12.0% -8.4%

Henry Hudson Bridge Total Vehicles -17.6% -22.9% -44.0% -34.6% -25.8% Passenger -17.5% -22.8% -43.9% -34.6% -25.9% Other -26.1% -32.8% -51.6% -36.9% -25.5%

Marine Parkway Bridge Total Vehicles -5.8% -6.7% -18.9% -15.7% -12.2% Cross Bay Bridge Passenger -5.2% -6.2% -18.3% -15.3% -11.8% Other -16.5% -16.6% -28.3% -22.5% -18.6%

(1) September 2020 vs. September 2019 (2) July 2020 to September 2020 vs. July 2019 to September 2019 (3) April 2020 to September 2020 vs. April 2019 to September 2019 (4) January 2020 to September 2020 vs. January 2019 to September 2019 (5) October 2019 to September 2020 vs. October 2018 to September 2019 Supplemental Data Page for the Report on Operations

Traffic & Average Gas Price(1) Weather(2) Average Snow Precipitation Month Traffic Gas Temperature Rain Inches Inches Days Sep-18 27,175,132 $2.98 73 5.9 - 13 Oct-18 28,301,034 $2.97 60 3.0 - 11 Nov-18 26,584,637 $2.85 46 7.1 4.7 15 Dec-18 26,946,779 $2.66 41 6.9 - 11 Jan-19 25,005,762 $2.51 33 3.9 0.6 9 Feb-19 23,532,562 $2.48 36 3.6 3.3 11 Mar-19(3) 27,332,093 $2.63 42 3.9 10.4 9 Apr-19 27,419,476 $2.84 55 4.4 - 17 May-19 29,249,471 $3.00 64 6.4 - 18 Jun-19 28,792,254 $2.91 73 4.9 - 13 Jul-19 28,857,383 $2.90 82 6.1 - 10 Aug-19 29,442,733 $2.84 78 3.1 - 9 Sep-19 27,785,633 $2.71 72 0.6 - 3 Oct-19 28,109,963 $2.68 61 5.6 - 14 Nov-19 26,913,543 $2.68 45 1.6 - 9 Dec-19 26,955,736 $2.67 39 7.2 2.0 14 Jan-20 25,368,494 $2.71 39 1.6 2.6 9 Feb-20 24,540,667 $2.72 40 2.7 - 12 Mar-20 18,934,838 $2.48 48 2.7 - 12 Apr-20 9,730,391 $2.26 51 4.5 - 14 May-20 14,953,991 $2.15 61 1.2 - 11 Jun-20 20,001,851 $2.21 76 1.1 - 8 Jul-20 23,322,086 $2.26 83 4.7 - 12 Aug-20 24,423,986 $2.25 80 4.9 - 13 Sep-20 24,002,364 $2.26 70 4.1 - 9 Note: Bold numbers are preliminary.

TABLE 2 - Year-over-Year Differences Traffic & Gas Monthly Inc/(Dec) Weather Monthly Inc/(Dec) Average Snow Precipitation Month Traffic Gas Temperature Rain Inches Inches Days 2019 vs. 2018 September 610,501 ($0.27) (1) (5.3) - (10) October (191,071) ($0.29) 1 2.6 - 3 November 328,906 ($0.17) (1) (5.5) (5) (6) December 8,957 $0.01 (2) 0.3 2 3 2020 vs. 2019 January 362,732 $0.20 6 (2.3) 2 0 February 1,008,105 $0.24 4 (0.9) (3) 1 March (8,397,255) ($0.15) 6 (1.2) (10) 3 April (17,689,085) ($0.58) (4) 0.1 - (3) May (14,295,480) ($0.85) (3) (5.2) - (7) June (8,790,403) ($0.70) 3 (3.8) - (5) July (5,535,297) ($0.64) 1 (1.4) - 2 August (5,018,747) ($0.59) 2 1.8 - 4 September (3,783,269) ($0.45) (2) 3.5 - 6

1. Average gasoline (all types) price per gallon data are from the U.S. Bureau of Labor Statistics, NY-NJ-CT-PA area. 2. Local weather data are from the National Weather Service, LaGuardia Airport Station. 3. Toll Increase, March 31, 2019

______Master Page # 23 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 ______

Supplemental Graph Gas Prices in the NY-NJ-CT-PA Area Master Page # 24 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 September 2018 - September 2020

$3.20

$3.10

$3.00 $2.98

$2.90

$2.80 $2.71 $2.71 $2.70

$2.60

$2.50

$2.40

$2.30 $2.26 $2.20

$2.10

$2.00 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Sep 18 - Sep 19 Sep 19 - Sep 20

Safety Report September 2020

______Master Page # 25 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 MTA Bridges & Tunnels

Safety Report Statistical results for the 12-Month period are shown below. Performance Indicator 12-Month Average Performance Indicator October 2017 - October 2018 - October 2019 - September 2018 September 2019 September 2020 Customer Collisions Rate per Million Vehicles 6.49 6.38 4.82 Customer Injury Collisions Rate per Million 0.99 0.89 0.79 Vehicles Employee Accident Reports 288 180 151 Employee Lost Time Injuries Rate per 9.0 5.4 5.0 200,000 Hours Worked Construction Injuries per 200,000 Hours 1.18 2.25 2.57 Worked Leading Indicators Roadway Safety 2019 2020 September Year End September Year to Date Workforce Development (# of Participants) 63 429 57 236 Fleet Preventative Maintenance Insp. 158 1608 139 1094 Safety Taskforce Inspections 0 13 0 * 0 * Construction Safety September September September Year to Date Construction Safety Inspections 182 2381 130 1288 Fire Safety September Year End September Year to Date Fire Code Audits Completed 2 15 2 12 FDNY Liaison Visits 2 32 0 5 * Safety Manager evaluations at each B&T facility supersedes task force inspections due to COVID 19. Definitions: Workforce Development provides for focused safety and skills training to all operations, maintenance and staff personnel. Classes feature OSHA 10 and 30 Classes, operations mandatory safety and skills instruction and retraining and specialty training (TIMS, CDL, FDNY instruction, Wrecker Driver Instruction and Roadway Safety Rules). Fleet Preventative Maintenance Inspections are conducted at each location to improve the customer and worker safety environment. Inspections identify potential hazardous roadway or facility conditions and prescribe corrective actions to eliminate hazards. Safety Taskforce Inspections are conducted by the joint Labor and Management Committee at each facility throughout the year on a rotating basis. The inspections consist of reviewing past accident and incident experiences/reports and facility safety reports. The Taskforce meets with location management and union representatives and makes a complete tour of the facility. The Taskforce is comprised of representatives of the Safety and Operations groups and has representation from each of the represented unions. Construction Safety Inspections are conducted by an independent safety monitor to ensure that the necessary components for a safe construction are present. Inspections include review of safety organization, job hazard analysis, safe work plans for specific high risk activities, personal protective equipment, fire protection, industrial hygiene, and training. Fire Code Audits are required by the NYS Uniform Fire Prevention Code. They are conducted by the Safety and Health Department at each building and facility throughout the Agency. They feature a review of fire prevention activities and the condition of fire fighting and suppression equipment. FDNY Liaison Visits are conducted on a regular basis (typically twice a year) whereby local fire companies visit and tour the facilities to become familiar with the structures and buildings and the fire equipment provided. This facilitates the development of strategies for fighting fires and responding to emergencies. Additionally, special drills and training exercises are conducted to drill on communications and special rescue operations should they be required.

______Master Page # 26 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 ______Master Page # 27 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 Bridges and Tunnels Collision Rates – All Facilities Year over Year Comparison of Monthly Data

Collisions with Injuries per Million Vehicles 1.47 1.18 1.11 0.95 0.99 0.97 0.94 0.99 0.88 0.92 0.89 1.02 0.75 0.82 0.84 0.69 0.68 0.70 0.62 0.64 0.73 0.67

0.28 0.00 October November December January February March April May June July August September Oct 2018 - Sep 2019 Oct 2019 - Sep 2020

Total Collisions per Million Vehicles 9.28 7.28 7.00 6.60 6.40 6.66 6.21 5.74 5.57 6.03 5.41 6.63 4.62 5.90 5.96 4.35 4.68 4.68 4.26 3.99 3.94 4.06 3.81 2.02

October November December January February March April May June July August September

Oct 2018 - Sep 2019 Oct 2019 - Sep 2020 ______Master Page # 28 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 Bridges and Tunnels Collision Rates by Facility Year over Year Comparison of 12-Month Averages

Collisions with Injuries per Million Vehicles

1.70 1.50 1.15 1.08 0.89 0.73 0.59 0.66 0.58 0.79 0.48 0.36 0.41 0.34 0.36 0.52 0.15 0.05 0.26 0.13

RFK BWB HHB MPB CBB QMT HLC TNB VN Total

Oct 2018 - Sep 2019 Oct 2019 - Sep 2020

Total Collisions per Million Vehicles 10.68 8.01 7.95 6.44 6.38 4.70 5.09 5.24 4.68 4.82 4.06 3.86 3.81 3.07 1.78 0.54 0.72 0.97 0.80 0.39

RFK BWB HHB MPB CBB QMT HLC TNB VN Total

Oct 2018 - Sep 2019 Oct 2019 - Sep 2020 ______Master Page # 29 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 Bridges and Tunnels

Collision Rates by Facility Total Collisions per Million Vehicles: Sep 2019 – Sep 2020

19-Sep 19-Oct 19-Nov 19-Dec 20-Jan 20-Feb 20-Mar 20-Apr 20-May 20-Jun 20-Jul 20-Aug 20-Sep RFK 7.20 6.32 6.19 8.38 3.92 3.83 4.20 1.59 4.36 3.19 3.89 3.98 3.15 BWB 9.77 11.51 8.12 5.89 5.10 5.89 3.41 0.66 2.63 2.36 3.94 3.63 2.14 TNB 5.32 4.24 4.16 2.82 5.46 3.73 2.33 1.33 4.35 2.75 4.61 3.63 4.71 VNB 8.83 10.82 8.75 9.09 6.48 5.97 7.67 3.12 4.25 7.89 6.86 9.79 10.48 QMT 3.52 4.46 4.81 5.66 3.84 4.29 2.52 3.42 8.83 1.46 5.39 2.17 2.11 HLC 1.82 1.18 3.68 3.05 5.96 3.30 0.93 2.41 2.82 5.31 2.21 2.07 3.36 HHB 0.46 0.44 0.91 0.47 0.50 1.03 1.56 2.20 0.00 0.82 0.00 0.57 1.11 MPB 0.00 0.00 3.17 3.14 0.00 0.00 2.11 3.27 0.00 3.09 2.41 2.53 1.47 CBB 1.38 0.00 0.00 0.00 1.53 0.00 0.00 0.00 1.88 0.00 1.23 0.00 0.00 Total 6.21 6.63 5.90 5.96 4.62 4.26 4.06 2.02 3.81 3.99 4.35 4.68 4.68 Capital Program Project Status Report October 2020

F

______Master Page # 30 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 MTA BRIDGES & TUNNELS CAPITAL PROGRAM STATUS REPORT OCTOBER 31, 2020

Introduction This report presents the year’s planned versus actual and forecast commitments, completions, and close-outs in narrative, tabular and graphic formats.

Commitments In October, five commitments were made with a total value of $2.6 million, against a Plan calling for two commitments with a total value of $1.1 million. (See Attachment 1 – 2020 Commitments Chart and Attachment 2– 2020 Major Commitments). Year-to-date, 101 commitments totaling $130.8 million were made, against a plan of 84 commitments with a total value of $86.0 million. Of these, 23 commitments totaling $76.7 million are related to the Moving NY Forward initiative.

Completions In October, there were two Moving NY Forward initiatives completed: RK-75 - Deck Overlay at the Robert F. Kennedy Bridge with a total value of $9.7 million and HH-36Ph.2 – Keim Coating - Dyckman Street Bridge of the Henry Hudson Bridge with a total value of $1.2 million. Year-to-date, 17 projects were completed with a total value of $259.6 million against a year-to-date goal of $233.2 million. (See Attachment 3 – 2019 Completion Chart; Attachment 4 – 2019 Major Project Completions).

Close-outs In October, there were 30 task level closeouts with a total value of $136.1 million. There are 131 task level closeouts year-to-date totaling $604.2 million against an annual goal of 129 tasks totaling $570.6 million.

______Master Page # 31 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 ______

Attachment 1 2020 Commitment Chart

MTA Bridges and Tunnels 2020 Budget Goal: $258.7 Commitments as of October 31, 2020 2020 Annual Forecast $158.0

YTD Goal: $86.0

Master Page # 32 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 YTD Actual: $130.8 (152.1% of YTD Goal)

YTD Budgeted Value: $133.9 (155.7% of YTD Goal)

Left to Commit: $27.3

$200

$100 ($ in Millions)

$0 1Q 2Q 3Q 4Q YTD

2020GOAL 2020 ACTUAL+FORECAST 2020 BUDGET VALUE ______

Attachment 2 2020 Major Commitments

MTA Bridges and Tunnels: Status of Major Commitments as of October 31, 2020

Master Page # 33 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 Budget ($ in Millions) Award Date Actual / Budgeted Advertisement 2020 Goal 2020 Goal Actual / Forecast Notes Project ID ACEP Project Description Forecast* Value Date

VN-X4 D806VNX1 VN - Operational Improvements (Safety Fence) $40.0 $40.0 $40.0 Dec-20 May-20 Mar-21 F 1

Note 1: The award is delayed due to the financial impact on the MTA as a result of the COVID-19 pandemic and better alignment with ongoing VN Projects. ______

Attachment 3 2020 Completion Chart

MTA Bridges and Tunnels 2020 Budget Goal: $406.1 Completions as of October 31, 2020 2020 Annual Forecast: $435.4

Master Page # 34 of 35 - Bridges & Tunnels Committee Meeting 11/18/2020 YTD Goal: $233.2 YTD Actual: $259.6 (111.3% of YTD Goal)

Left to Complete: $175.8

$300

$250

$200

$150 ($ in Millions) $100

$50

$0 1Q 2Q 3Q 4Q YTD

2020 GOAL 2020 ACTUAL/FORECAST ______

Attachment 4 2020 Major Project Completions

MTA Bridges and Tunnels: Status of Major Completions as of October 31, 2020

Budget ($ in Millions) Completions Status Completion Date % Master Page # 35 of - Bridges & Tunnels Committee Meeting 11/18/2020 Actual / Physical % Actual /

Project ID ACEP Project Description 2020 Goal Contingency 2020 Goal Notes Forecast* Complete Forecast Spent

HH-89 D701HH89 Skewback Retrofit $100.4 $100.4 99 65 Aug-20 Sep-20 A 3

D704VN30 Elevator Rehabilitation VN-30/ VN-89 $44.2 $44.2 97 0 Oct-20 Jul-20 A 1, 2 D701VN89 Tower Pier Rehab/Construct Mooring Platform

D704BW39 Install Electronic Monitoring & Detection Systems BW39/RK60 $88.3 $88.3 95 55 Dec-20 Dec-20 F D704RK60 Install Electronic Monitoring & Detection Systems

RK-23C D702RK23 New HRD Ramp at RFK (D/B Sub-Project RK23C) $73.2 $73.2 97 12 Dec-20 Nov-20 F 4

Note 1: The VN30 - Elevator Rehabilitation portion of VN-30/VN-89 was substantially completed for $6.4 million in May 2020 Note 2: The VN89 - Tower Pier Rehab/Mooring Platform portion of VN-30/VN-89 was substantially completed for $37.7 million in July 2020 Note 3: During construction, unforeseen steel conditions requiring repair were uncovered, resulting in the forecast completion date slipping to September 2020 Note 4: The contractor has made good progress on the work activities, resulting in the forecasted completion date of November 2020