PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
PROPOSAL FOR FOREST CLEARANCE UNDER FOREST (CONSERVATION) ACT, 1980 FOR DIVERSION OF 4.0077 HA FOREST AREA FOR CONSTRUCTION OF MORSHI-CHANDURBAZAR-ACHALPUR (From Km 0.000 to 53.719)
AMRAVATI DIVISION
USER AGENCY
GOVERNMENT OF MAHARASHTRA PUBLIC WORKS DEPARTMENT (NATIONAL HIGHWAY)
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
NAME OF THE PROPOSAL: - Proposal for diversion of 4.0077 ha forest land for construction of Morshi-Chandurbazar-Achalpur National Highway from Km 0.000 To 53.719 in the State of Maharashtra for Upgradation to Two Lanes with Paved Shoulder/Four Lane Configurations.
Area: - 4.0077ha. Div: - Amravati
Check list for preparing proposals of Maharashtra State for diverting forest land for non-forest use under provisions of Forest (Conservation) Act, 1980 for road development project.
Sr. Page Details of Check list Compliance No Number 1. Information of proposal from item of Form 1(I) regarding short description Enclosed in of the proposal / project which should invariably include. Section 1. a) Cost of outlay b) Justification for locating the project in forest area giving alternative those were examined and reasons for the rejection. c) Financial and social benefits. d) Total population benefited. e) Employment generated. 2.a The Geo digital map in 1:10,000 or any suitable scale with geo-reference Enclosed in boundary in shape file prepared by using total stations or differential GPS Section 2 as and also indicate forest land, non-forest land & adjoining land to the 2.a proposed for diversion, in different colours must be duly signed by the Deputy Conservator of Forests concerned and Project Authority, as per the GOI letter No.F.no.11-9/98-FC, dt.8/7/2011. Compartment boundary on the map should clearly be marked. Satellite imageries to be used to show the density of forest cover to be enclosed. b Index Map in 1:50000 scale with Project location: Latitude/ Longitude to be Enclosed in enclosed. Section 2 as 1. Proposed area up to 1.00 ha Only one co-ordinate to be given 2.b 2.Proposed area up to 1.00 to 5.00 Two co-ordinate diagonally to be ha given 3. Proposed area above 5.00 ha. Four co-ordinates at four corners to be given. c Map of compensatory Afforestation of forest / Non forest area in 1:50000 Under scale with location of Latitude & Longitude. Process of 1. Proposed area up to 1.00 ha Only one co-ordinate to be given acquisition 2.Proposed area up to 1.00 to 5.00 Two co-ordinate diagonally to be land for CA ha given 3. Proposed area above 5.00 ha. Four co-ordinates at four corners to be given. d A comprehensive land use plan of the area required should be attached if Not land is required for more than one purpose the building plan and estimate Applicable should invariably be attached if the area is required for construction purpose. e The following information must be complied in the construction of State Enclosed in Highway /National Highway / Road/ Winding /Exploitation Purpose / Canal Section 2 as / Transmission line & all other linear Project as per GOI guideline vide 2.e No.6-MPB-071/2011-BHO-736, Dt.30/04/2012. i Map of the alternative alignments or route map examined by Dy.CF/ Project Authority to be enclosed.
PWDMSRDCPWD 2 2
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Sr. Page Details of Check list Compliance No Number ii Show proposed diversion of forest / non forest area in the Original, colored or legible topo-sheet and to be enclosed. iii To give the Latitude & Longitude of the proposed area at starting, ending turning point and breaking of the forest area Which should be identifiable. iv To show the existing Water body / Water channel or road Which should be identifiable. v To show the newly proposed bridge /culvert / underground pass / tunnel etc. to be identify clearly. vi To enclose the cross section Plan / Map indicating dimension of (Length / Width / Height /depth etc) clearly. vii To show the additional impacted area clearly which may be impacted temporarily by the proposed construction. viii To show the diversity of the ecology which is to be impacted by the proposed construction. f Map of Eco-Sensitive Zone, in 1:2,50,000 or 1” = 4-mile scale by showing Not the distance of “Protected Area” from proposed forest areas under Applicable diversion, in kilometer. g Map of Wind Mill and Wind mast to be enclosed by showing the 10.00 Km Not radius area from the wind mast site on 1:50,000 or 1:25000 scale topo Applicable sheet. Certificate by Dy. CF/ Chief Conservator of Forest and their authenticated Enclosed in documents. Section 3 3 Documents verification Certificate by the Deputy Conservator of Forest Enclosed 4 Certificate of Dy. Conservator of Forest for absences of alternative about Enclosed the Project and minimum demand of forest area. 5 Certificate by the Deputy Conservator of Forests that no violation done of Enclosed the FCA-1980 and their guideline. a If violated, circumstances leading to violation date of commencement of Not work /quantity of work done and the amount spent Certificate to be Applicable furnished by the concerned inspection of the site of violation. b If work started in forest land when and how much amount spent on the Not project and the works done in the forest land. Applicable c Detailed report of the disciplinary action or proposed to be taken against Not the concerned staff for violation of the provisions of the Act. Applicable d Details of clarification for violation, if administrative and technical sanction Not accorded to the project by project authority / user agency after the Applicable promulgation of the Forest (Conservation) Act, 1980. 6 Suitability certificate by the Deputy Conservator of Forests that forest and Enclosed non-forest land is suitable for raising trees species. A The Compensatory Afforestation certificate must be geo-tagged photos of Enclosed the areas proposed for Compensatory Afforestation. 7 Certificate of Identified Forest and Acquired Forest for Compensatory Enclosed Afforestation Area by Dy. Conservator of Forests 8 Certificate of Identified Forest and Acquired Forest for Non-Forest area Enclosed under the project by Dy. Conservator of Forests. 9 Certificate by the Dy.CF Whether the proposed project likely to affect any Enclosed monument site of cultural, historical, religious, archaeological or recreational importance including wild life sanctuaries and national parks to be enclosed
PWDMSRDCPWD 3 3
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Sr. Page Details of Check list Compliance No Number 10 Wild life Certificate by the Dy.C.F. Enclosed 11 Net Present Value Certificate must be marked with eco-class /category of Enclosed Forest as per the GOI letter F.No.5-3/2007/-FC, Dt.05/02/2009 to be enclosed. 12 No cutting and felling of trees Certificate of by the Dy. Conservator of Enclosed Forests to be enclosed 13 Certificate about distance of Project from Protected area by Deputy Enclosed Conservator of Forest. 14 Certificate of Dy. Conservator of Forests regarding alternative examined Enclosed for liner project (Certificate No-27) 15 Certificate by the Dy. CF Whether, the required Annexure and the Enclosed particulars to the proposal furnished in English? If any Govt. orders are in Marathi, English as required by the Government of India to be enclosed. 16 Zudpi Jungle land offered certificate by the Dy. CF for the compensatory Not afforestation is in a compact patch and is contingencies of the forest area Applicable and is suitable for the management point of view. 17 Site inspection report form Deputy Conservator of Forests if forest area Not involves is less than 10 ha and by Conservator of Forests if forest area Applicable involved is more than 10 ha in regard to sensitivity and potential value of the forest area in regard to forest types in catchments and submergence area. 18 Cetificicate of the Dy.CF regarding the proposal of the Eco-Tourism Not Scruitininzed vide GOM order No.WLP-1002/c.r.53/F-1/dated 20.2.2008 Applicable to be enclosed. 19 Compensatory Afforestation scheme prepared by Dy.CF. -- 20 Medicinal plantation / road side/ canal side plantation scheme prepared by Not PA /Dy.cf whether the proposed area is diverted for wind power/ Applicable transmission line and other linear proposals to be enclosed. 21 Cost benefits analysis. Whether the area is more than 20.00 ha. Not Applicable 22 Item wise break up of forest and non-forest area required category wise Enclosed (Damseat, submergence, quarry, roads, colony, canals etc.) area statement to be enclosed 23 List of the Identified forest form the Deputy Conservator of Forest Enclosed 24 List of tree, species wise/girth wise, with local and scientific name to be Enclosed given. If felling of trees is essential? The estimate of tree felling to be enclosed. As per GOI letter no. 7-1/89/(For)/Part-VIII/2012-BHO/848, dt.18/05/2012. Certificate by Chief Conservator of Forest and their authenticated documents. Enclosed in Section 4 25 Net Present Value Certificate must be counter signed by Chief Conservator Enclosed of Forest / with eco-class /category to be shown in the certificate of Forest as as per the GOI letter F.No.5-3/2007/-FC, Dt.05/02/2009 to be enclosed Certificate by Project Agency and their authenticated documents. Enclosed in Section 5 26 Chronological of Events 27 Attempts made to find out Non forest land for the proposal/ reasons for its -- rejection of the same and minimum demand of forest area. 28 Unqualified commitment from the project authority to bear cost of --
PWDMSRDCPWD 4 4
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Sr. Page Details of Check list Compliance No Number exploitation of felling of trees and their allied works under project. 29 Certificate by Project Authority for the cost of Compensatory Enclosed Afforestation. (Certificate No.6) 30 Certificate by the project authority that no violation done of the FCA-1980 Enclosed and their guideline. 31 Certificate by the Project Authority to furnish the Net Present Value as per Enclosed the ordered by Government of India. 32 Certificate of project authority (Providing i.e. water supply facilities to) Not Applicable 33 Certificate of the Project Authority to get the Environmental clearance as Enclosed per the Environmental Act. 2006 (whenever necessary) 34 Certificate of Non Indemnity to forest Department (by Project Authority) Not Applicable 35 Certificate or Noc from the private owner if the area under Private Forest Not Act, (Acquisition) Act.1975 to be enclosed. (By villagers) Applicable 36 Certificate of the Projects Authority to take up catchments area treatment Not plan as per the guideline of Government of India Applicable 37 Catchment area treatment plan. Not Applicable 38 Command area development plan. Not Applicable 39 Certificate by Project Authority Whether stipulation is made that 5 % of Not area under command of the project is made available to the Forest Applicable Department for planting trees and other vegetation for which necessary irrigation should be provided free of cost by the project authority / user agency. If the forest area involved is less than 2. 00 ha and there is no felling to tree growth; it is to be dealt with as per simplified procedure. 40 Project note by the project authority. With salient features. Not a) Total catchment area Applicable b) Total command area c) Full reservoir level d) High flood level e) Minimum drawal level f) Total catchment area of the dam (in Ha) and its breakup forest land, cultivated land, Pasture, Human cultivation and others. g) Details as per item (f) above for the area coming under submergence. h) Total No. of families and population affected, scheduled caste and scheduled tribe families to be displaced should be separately indicated. i) Proposal for the rehabilitation of affected persons (Rehabilitation Plan) j) Comprehensive land use plan for the area required outside the submergence i.e. building roads and other ancillary facilities outside submergence i.e. building roads and other ancillary facilities. 41 It has been observed that water hardly stands the ear around even upto Not FRL. Trees can definitely stand in water for one to three months and Applicable therefore submergence should be calculated 2 M below FRL for this following should be given for forest areas involved. i) Area of submergence at H.F.L. (High flood level)
PWDMSRDCPWD 5 5
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Sr. Page Details of Check list Compliance No Number ii) Area of submergence at F.R.L. (Full Reservoir level) iii) Area of submergence at 2 Meter below F.R.L. iv) Area of submergence at 4 Meter below F.R.L. 42 List of trees 2 Meter, 4 Meter below F.R.L. in submergence area species Not wise. Applicable 43 Administrative/Technical approval from the competent authority to be Enclosed enclosed. 44 Certificate/ undertaking by the project authority regarding the wind power Not project as per the GOI letter Dated 14/05/2004 to be enclosed. Applicable Certificate by Other Department. Enclosed in Section 6 45 In case of proposal related to stone quarries, the recommendation of the Not Director, Geological and Mines is required. Applicable 46 If any Protected/Archaeological/Heritage site and other Important Not Monument is located in the area. The Certificate by Archaeological Applicable Department to be enclosed 47 Certificate about the distance of Project from Protected area by the Dy. CF Enclosed Wildlife Department. Whether the Project area within 10.00 Km. should be clearly shown and marked. 48 No Objection Certificate of M.D., F.D.C.M. for involvement of their area. Enclosed 49 Relevant Notification/7/12 Extract/ restoration order/Rights of record etc. Not of the proposed forest land to be enclosed. Applicable Certificate by Collector: - Enclosed in Section 6 50 Certificate from the Collector that no alternative suitable non-forest land is Enclosed available for the project. (In A Form itself) 51 Certificate of Collector under the FRA-2006 with resolution of Gram Not Sabha/Gram Panchayat as per GOI letter dated 3/8/2009 to be enclosed. Applicable 52 Certificate of Compensatory Afforestation land made available by Not Collector. Applicable 53 Certificate of non-availability of non-forest area for Compensatory Not Afforestation by the Collector/Commissioner. Applicable 54 The agency has not given alternative land to the forest Department. If non Not forest land for C.A. scheme is not available in the entire state, the Applicable certificate from the Chief Secretary of the State to be enclosed. Vide GOI letter dt. 13/2/12 55 As the project, area is within the 10.00 km from the boundary of PA area Not therefore, the information regarding 16 points check list provided by Applicable Principle Chief Conservator of Forest (W.L.) Nagpur which is enclosed herewith to be furnished 56. All the certificate and documents must have name of the signatory, Enclosed designation, station, & date under the signature as per the GOM letter vide, dtd.01 December 2010. 57. Resolution of the Gram Sabha may not be required in cases of projects like Not transmission line, roads, canals, laying of pipeline/optical fibres where Applicable linear diversion of forest land in several villages are involved, unless recognized rights of PTG/ PAC are being affected as per Government of India F.No.11-9/98-FC(pt.) dated 05/02/2013
PWDMSRDCPWD 6 6
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Section 1:
Information of proposal from item of Form 1(I) regarding short description of the proposal / project
PWDMSRDCPWD 7 7
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
1. Information of the Proposal
i. Name of Project – Proposal For diversion of 4.0077 Ha Forest Area for upgradation to two lanes with paved shoulder/four lane configurations of Morshi-Chandurbazar-Achalpur section from Km 0.000 To 53.719 in the State of Maharashtra
ii. User Agency – Public Works Department (National Highway), Government of Maharashtra.
iii. Forest area for which diversion is sought – 4.0077 Ha.
iv. Aerial distance of project area from nearest Protected Areas – There are no National Park, Wildlife Sanctuary, Biosphere Reserve, Tiger Reserve, Wildlife Corridor etc. observed within 10 km study area from the project alignment.
v. Detailed Note on Project: -
The Government of India has decided to upgrade existing State Highway corridors having single lane/intermediate/two lane carriageway to two lane with paved shoulders/Four lane Configurations. In continuation of this, MORT&H has entrusted the work of preparation of Detailed Project Report of Morshi-Chandurbazar-Achalapur State Highways to Public Works Department (Maharashtra). The project alignment is spanning through Morshi, Chandurbazar & Achalpur taluka of Amravati districts with a total length of approximately 53.719 Kms. Presently the existing Highway is as per SH specification & the proposal is to upgrade the existing Highway to NH specification.
The project alignment, an amalgamation of SH-240, SH-203 & SH-201 passing through Morshi, Chandurbazar and Achalpur town forms an important artery for movement of goods from Amravati. Goods transported are seasonal crops and agricultural products throughout the year from different places located in Morshi, Chandurbazar and Achalpur to Daryapur, Akot, Paratwada Akola Chikhaldara. The Achalpur town had been a major trade center for Palmarosa oil in India. The major commodities for trade include natural gums, Cottons, Banana, Oranges, Red Chilies Ground Nut, Honey, Millet, Milo, wheat, Sunflower.
It is appreciated that over a horizon of next 20-30 years, this road will serve a critical purpose of linking Amravati & Warud to Paratwada & Chikhaldara to contribute substantially to the development of the local economy and Tourism. Further a number of remote villages are also being provided connectivity under the PMGSY and the take-off points emanate from this highway.
vi. Main benefits from project – The project alignment is an amalgamation of SH-240, SH-203 & SH-201 passing through Morshi, Chandurbazar and Achalpur town forms an important artery for movement of goods from Amravati. Goods transported are of seasonal crops majorly like Oranges during period of September to January and cotton during January to May and agricultural products throughout the year from different places located in Morshi, Chandurbazar and Achalpur to Daryapur, Akot, Paratwada Akola Chikhaldara. The Achalpur
PWDMSRDCPWD 8 8
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
town had been a major trade center for Palmarosa oil in India. The major commodities for trade include natural gums, Cottons, Banana, Oranges, Red Chilies Ground Nut, Honey, Millet, Milo, wheat, Sunflower.
1a. Cost of project: - Rs. 341.28 Cr.
1.b Justification for locating the project in forest area giving alternative those were examined and reasons for the rejection:
Since this is an upgradation project of existing highway to two lane/four lane with paved shoulders, so no alternative is required to be examined. Wherever possible, non-forest land has been used to its maximum to accommodate proposed upgradation. In view of above reason, alignment passes through 3.123 Kms of forest land in six patches which cannot be located on non-forest land. Hence the proposed diversion of 4.0077 ha in the final alignment is fully justified.
As far as possible improvements to the road are to be accommodate in the available ROW. However, Bypasses or detours will be provided to segregate the local traffic from the through traffic. Re-alignments will also be done at few locations having sub-standard curves.
PWDMSRDCPWD 9 9
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Project Sr.No. Parameters Road 1 Total Area of Land required (Ha) 125.4377 2 Total Area of Land already available (Ha) 117.1799 3 Total Area of additional Land required (Ha) 8.2578 3(i) Agricultural land (Ha) 3.8235 3(ii) Barren land (Ha) 0.4266 3(iii) Forest land /open scrub (Ha) 4.0077
1.c Financial and Social Benefits:
Evaluation of Benefit from Forests
S.No. Parameters Description 1 Increase in productivity The project alignment is an amalgamation of SH-240, SH-203 & attributable to the specific SH-201 passing through Morshi, Chandurbazar and Achalpur project. town forming an important artery for movement of goods from Amravati. Goods transported are seasonal crops and agricultural products throughout the year from different places located in Morshi, Chandurbazar and Achalpur to Daryapur, Akot, Paratwada Akola Chikhaldara. The Achalpur town had been a major trade center for Palmarosa oil in India. The major commodities for trade include natural gums, Cottons, Banana, Oranges, Red Chilies Ground Nut, Honey, Millet, Milo, wheat, Sunflower. The said project stretch has a one crusher plant and some religious places which also shall contribute in increase of traffic. 2 Benefits to economy The Morshi-Chandurbazar-Achalpur will provide uninterrupted free flow of traffic and shall result in (1) Saving in Travel time & Cost (2) Saving in foreign exchange due to less consumption of fuel. (3) Increase in income of Owners of truck, bus, taxi etc. as they will be able to communicate maximum distance in short time. (4) Reduction in accidents as it will provide safe travel , (5) Will act as catalyst to the industrial development It is appreciated that over a horizon of next 20-30 years, this road will serve a critical purpose of linking Amravati & Warud to Paratwada & Chikhaldara contribute substantially to the development of the local economy and Tourism. Further a number of remote villages are also being provided. Connectivity under the PMGSY and the take-off points emanate from this highway. 3 No. of population Entire population of the project alignment and proposed benefited growth center area will be benefited due to upgradation of this highway. 4 Employment potential Direct and indirect employment will be generated during construction and operation period. Mostly local people will be benefited during construction as well as operation period of this project alignment.
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
S.No. Parameters Description Rs. 3.33 Crores per year through employment generations as under:
Sr. Type of Employee During During No. Construction Operation 1. Skilled 20 10 2. Semiskilled 30 15 3. Unskilled 100 35 Total 150 60
Sr. Type of During Rate/day Amount No. Employee Construction (Rs.) (Nos.) 1. Skilled 20 1000 20,000 2. Semiskilled 30 600 18,000 3. Unskilled 100 400 40,000 Total 150 150 78, 000
Sr. Type of During Rate/day Amount No. Employee maintenance (Rs.) (Nos.) 1. Skilled 10 1000 10,000 2. Semiskilled 15 600 9,000 3. Unskilled 35 400 14,000 Total 60 33,000
Total cost of works out during construction & maintenance will be Rs. 1,11,000 per day. i.e. 3.33 Cr./year. 5 Cost of acquisition of As against 4.0077 ha of forest land proposed to be diverted facility on non-forest land during upgradation of Morshi-Chandurbazar-Achalpur Two lanes wherever feasible with paved shoulder/Four lane configurations from Km 0.000 to 53.719; an equivalent non-forest land will be transferred to the Forest Department. 6 Loss of (a) agriculture and Negligible as it is upgradation of existing SH (in principle NH) (b) Animal husbandry within existing RoW. production due to diversion of forest land. 7 Cost of rehabilitating the Not Applicable displaced persons as different from compensatory amounts given for displacement. 8 Cost of supply of free No workers will be allowed to live in Forest area and also use fuel-Wood to workers forest products for fuel and others. residing in or near forest area during the period of construction.
Note: This is as per guidelines of GoI.
PWDMSRDCPWD 12 12
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
1.d Total Population Benefited
i) Employment Numbers during construction and operation:
Sr. Type of Employee During During No. Construction Operation 1. Skilled 20 10 2. Semiskilled 30 15 3. Unskilled 100 35 Total 150 60
1.e Employment Generation
Sr. Type of Employee During During No. Construction Operation 1. Skilled 20 10 2. Semiskilled 30 15 3. Unskilled 100 35 Total 150 60
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
PWDMSRDCPWD 13 13
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Section 2: Maps as per Checklist
PWDMSRDCPWD 14 14
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
2.a The Geo digital map in 1:10,000 or any suitable scale with geo-reference boundary in shape file prepared by using total stations or differential GPS and also indicate forest land, non- forest land & adjoining land to the proposed for diversion, in different colors are duly signed by the Deputy Conservator of Forests concerned and Project Authority, as per the GOI letter No.F.no.11-9/98-FC, dt.8/7/2011. Compartment boundary on the map are clearly be marked. Satellite imageries are used to show the density of forest cover.
PWDMSRDCPWD 15 15
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Geo-Digital Maps in 1:10000 Scale Patch 1 (P1)
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Patch 2 (P2)
PWDMSRDCPWD 17 17
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Patch 3 (P3)
PWDMSRDCPWD 18 18
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Patch 4 (P4)
PWDMSRDCPWD 19 19
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Patch 5 (P5)
PWDMSRDCPWD 20 20
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Patch 6 (P6)
PWDMSRDCPWD 21 21
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
2.b - Index Map in 1:50000 Scale with Project Location: Latitude/Longitude to be enclosed
PWD 22
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
2.c Map of Compensatory Afforestation of forest / Non forest area in 1:50000 scale with location of Latitude & Longitude
We are in Process of browsing of site for Compensatory afforestation. Will furnish the maps of the areas once came to the conclusion.
PWD 23
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
2.d A comprehensive land use plan of the area required should be attached if land is required for more than one purpose the building plan and estimate should invariably be attached if the area is required for construction purpose.
This is an upgradation project of existing highway & entire forest land proposed for diversion will be used for road construction.
PWDMSRDCPWD 24 24
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
2.e The following information must be complied in the construction of State Highway /National Highway / Road/ Winding /Exploitation Purpose / Canal / Transmission line & all other linear Project as per GOI guideline vide No.6-MPB-071/2011-BHO-736, Dt.30/04/2012.
i. Map of the alternative alignments or route map examined by Dy.CF/ Project Authority. Not Applicable, because this is an upgradation project of existing highway.
ii. Show proposed diversion of forest / non forest area in the Original, colored or legible topo- sheet. Enclosed under this Section.
iii. To give the Latitude & Longitude of the proposed area at starting, ending turning point and breaking of the forest area which is identifiable. Enclosed under this Section.
iv. To show the existing Water body / Water channel or road which should be identifiable. Enclosed under this Section.
v. To show the newly proposed bridge /culvert / underground pass / tunnel etc. to be identify clearly. Enclosed under this Section.
vi. To enclose the cross section Plan / Map indicating dimension of (Length / Width / Height /depth etc) clearly. Enclosed under this Section.
vii. To show the additional impacted area clearly which may be impacted temporarily by the proposed construction. Enclosed under this Section.
viii. To show the diversity of the ecology which is to be impacted by the proposed construction. Not Applicable
PWDMSRDCPWD 25 25
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
i. Map of the Alternative Alignments or Route Map on MRSAC
Not Applicable
PWDPWD 26 26
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
ii. Show proposed diversion of forest area in the Original, colored or legible topo-sheet.
PWDPWD 27 27
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA iii. To give the Latitude & Longitude of the proposed area at starting, ending turning point and breaking of the forest area which should be identifiable
2 1 4
PWDMSRDCPWD 28 28
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
PWDMSRDCPWD 29 29
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
PWDMSRDCPWD 30 30
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
iv. Map of existing Water body / Water channel or road
3 1 2 4
PWDMSRDCPWD 31 31
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
v. Layout Showing Proposed Facilities Like Bridges / Culverts / Underpass, etc.
PWDPWD 32 32
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
vi. Cross Section Plans of the Proposed Alignment
PWDPWD 33 33
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
vii. Additional impacted area clearly which may be impacted temporarily by the proposed construction.
Please see the Section 2a.
PWDPWD 34 34
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
viii. Diversity of the Impacted Area during Construction
1. In part II the required data will be presented. Currently the team is collecting primary data from the field. 2. This will be supported with the report prepared by the district forest officials. 3. The report will be a part of Detailed Project Report to be prepared for this project.
PWDMSRDCPWD 35 35
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
2.f. Map of Eco-Sensitive Zone, in 1:2,50,000 or 1” = 4-mile scale by showing the distance of “Protected Area” from proposed forest areas under diversion, in kilometre.
Not Applicable
PWDMSRDCPWD 36 36
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
2.g. Map of Wind Mill and Wind mast to be enclosed by showing the 10.00 Km radius area from the wind mast site on 1: 50,000 or 1:25000 scale topo sheet.
Not applicable for highway project
PWDPWD 37 37
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Section 3
Certificate by Deputy Conservator of Forest / Chief Conservator of Forest and their authenticated documents
PWDMSRDCPWD 38 38
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 3
Certificate by the Deputy Conservator of Forest for Documents verification
Certified that all the documents enclosed here with the proposal of Forest clearance for “Preparation of Proposal for diversion of 4.0077 Ha Forest area for upgradation two lanes with paved shoulder/four lane configurations of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra.” have been scrutinized as per the revised check list and found to be correct.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 39 39
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 4
Certificate of Deputy Conservator of Forest For Absences of Alternative about the Project and Minimum Demand of Forest Area.
This is to certify that “Proposal for diversion of 4.0077Ha Forest area for upgradation two lanes with paved shoulder/four lane configurations of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra.” is to be constructed in accordance with specific alignment decided after detailed study and exploring various alternatives, therefore, the project is site specific. The forest land required for this project is only 4.0077 Ha. In view of this being an existing road, no alternative non-forest land can be used for the purpose.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forests
Amravati Division
PWDMSRDCPWD 40 40
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 5
Certificate by the Deputy Conservator of Forests that No Violation Done of the FCA-1980 and their Guideline
This is to certify that proposed upgradation of Morshi-Chandurbazar-Achalpur highway is to be constructed in accordance with standardized technical specifications and as per specific alignment decided after detailed study and exploring various alternatives. It is also certified that no construction is started; therefore, the provision of FCA-1980 and guidelines under it has not been violated.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forests
Amravati Division
PWDMSRDCPWD 41 41
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 6
Suitability certificate by the Deputy Conservator of Forests that Forest and Non-Forest Land is Suitable for Raising Trees Species.
This is to certify that undersigned has inspected the area ______ha from ______area Gut No. ____ /Sy. No. ______of Village ______, Taluka______, District ______to be transferred to the forest department as Alternate Land for Compensatory afforestation in lieu of forest land required for the proposed upgradation of Morshi-Chandurbazar-Achalpur From Km 0.000 to 53.719 in the State of Maharashtra and it is contiguous, suitable for afforestation and management purpose also and it is free from encroachment and an encumbrance.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 42 42
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 7
Certificate of Identified Forest and Acquired Forest for Compensatory Afforestation Area by Deputy Conservator of Forests
This is to certify that undersigned has inspected the area ______ha from ______area Gut No. ____ /Sy. No. ______of Village ______, Taluka______, District ______to be transferred to the forest department as Alternate Land for Compensatory afforestation in lieu of forest land required for the proposed upgradation of Morshi-Chandurbazar-Achalpur From Km 0.000 to 53.719 in the State of Maharashtra and it is contiguous, suitable for afforestation and management purpose also and it is free from encroachment and any encumbrance.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forests
Amravati Division
PWDMSRDCPWD 43 43
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 8
Certificate of Identified Forest and Acquired Forest for Non Forest area under the project by Deputy Conservator of Forests.
This is to certify that undersigned has inspected the area ______ha from ______area Gut No. ____ /Sy. No. ______of Village ______, Taluka______, District ______to be transferred to the forest department as Alternate Land for Compensatory afforestation in lieu of forest land required for proposed upgradation of Morshi-Chandurbazar-Achalpur From Km 0.000 to 53.719 in the State of Maharashtra and it is contiguous, suitable for afforestation and management purpose also and it is free from encroachment and an encumbrance.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forests
Amravati Division
PWDMSRDCPWD 44 44
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 9
Certificate by the Deputy Conservator of Forest Whether the proposed project likely to affect any monument site of cultural, historical, religious, archaeological or recreational importance including wild life sanctuaries and national parks to be enclosed
This is to certify that the proposed upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra is not likely to affect any Monument Site of Cultural, Historical, Religious, Archeological or Recreational Importance.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 45 45
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 10
Certificate by the Deputy Conservator of Forest For not having Wild Life Sanctuary in the Project Area
This is to certify that proposed upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra is not included in the area of 10 km ESZ of any National Park / Wild Life Sanctuary / Protected area or nature reserve.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 46 46
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 11
Net Present Value Certificate must be marked with eco-class /category of Forest as per the GOI letter F.No.5-3/2007/-FC, Dt.05/02/2009
Certified that 4.0077 hact of forest land used for upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra falls in the improvement working circle and has the less density.
It is also certified that the amount of Net Present Value of forest land calculated and to be collected Rs. ______/- (Rupees______Only) is exactly as per the rates and calculation provided in the GOI letter F.NO.5-3/2007/-FC, dt 05/02/2009.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Deputy Conservator of Forest
Amravati Division
Place: Amravati Date
PWDMSRDCPWD 47 47
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certficate No: - 12
Certificate of by the Deputy Conservator of Forests for No Cutting and Felling of Trees
This is to certify that in the proposed upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra, there is no cutting and felling of trees involved without prior permission.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 48 48
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certficate No: - 13
Certificate by Deputy Conservator of Forest About Distance of Project from Protected Area
This is to certify that there is no protected area falling within 10 km of proposed alignment of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 49 49
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certficate No: - 14
Certificate of Dy. Conservator of Forests regarding Alternative Examined for Linear Project
This is to certify that proposed alignment is upgradation of two lanes with paved shoulder/four lane configurations of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra, out of which forest land is only 4.0077 Ha. In view of this existing alignment upgradation, no alternative non-forest land can be used for the purpose.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 50 50
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 15
Certificate by the Deputy Conservator of Forest Whether, the required Annexure and the particulars to the proposal furnished in English? If any Govt. orders are in Marathi, English as required by the Government of India to be enclosed
Certified that all the documents enclosed therewith the proposal of diversion of Forest land for upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra have been scrutinized as per the checklist and found to be correct and all the particulars are furnished in English.
Dated:11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 51 51
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 16
Zudpi Jungle land offered certificate by the Dy. CF for the compensatory afforestation is in a compact patch and is contingencies of the forest area and is suitable for the management point of view.
Not applicable
PWDMSRDCPWD 52 52
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 17
Site inspection report form Deputy Conservator of Forests if forest area involves is less than 10 ha and by Conservator of Forests if forest area involved is more than 10 ha in regard to sensitivity and potential value of the forest area in regard to forest types in catchments and submergence area.
Not Applicable
PWDMSRDCPWD 53 53
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 18
Certificate of the Dy.CF regarding the proposal of the Eco-Tourism Scruitininzed vide GoM order No.WLP-1002/c.r.53/F-1/dated 20.2.2008 to be enclosed.
Not Applicable
PWDMSRDCPWD 54 54
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 19
Compensatory Afforestation scheme: To be formulated and enclosed by the Dy.CF.
PWDMSRDCPWD 55 55
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 20
Medicinal plantation/road side/canal side plantation scheme prepared by PA/Dy.cf whether the proposed area is diverted for wind power/transmission line and other linear proposals to be enclosed.
Not applicable
PWDMSRDCPWD 56 56
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 21
Cost benefits analysis. Whether the area is more than 20.00 ha.
Area is 4.0077ha (Less than 20 ha); hence Not Applicable
PWDMSRDCPWD 57 57
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 22
Item wise break up of forest and non-forest area required category wise (Damseat, submergence, quarry, roads, colony, canals etc.) area statement is enclosed-
Summary:
EXISTING PROJECT ALIGNMENT – Area Statement
Project Sr.No. Parameters Road 1 Total Area of Land required (Ha) 125.4377 2 Total Area of Land already available (Ha) 117.1799 3 Total Area of additional Land required (Ha) 8.2578 3(i) Agricultural land (Ha) 3.8235 3(ii) Barren land (Ha) 0.4266 3(iii) Forest land /open scrub (Ha) 4.0077
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 58 58
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Statement showing Details of forest area and non-forest area Proposed for diversion legal status of forest applied for diversion –
S. No. District Forest Area (Ha) Non- Forest Area (Ha) Total Area (Ha) 1 Amravati 4.0077 4.2501 8.2578
Total = 4.0077 4.2501 8.2578 Forest Area Statement:
Patch District Taluka Village Chainage Gat No. Area Legal Length (km) (Forest) Status under From To RHS LHS Acquisition (Ha) P1 Shivpuri 2+980 3+554 0.402 0.574 15, 17 0.8784 RF P2 Khanapur 5+050 6+020 0.970 0.076 4,5,6,7, 171 0.9414 RF P3 Amrav Khanapur 7+457 8+677 0.493 1.220 73,74,81,82 1.5417 RF Morshi P4 ati Ashtgaon 9+784 9+853 0 0.069 51 0.1242 RF P5 Ashtgaon 11+251 11+263 0.012 0 85 0.0216 RF P6 Udkhed 13+247 13+525 0.278 0.278 24 0.5004 RF Total Forest Area 3.123 km 4.0077
Purpose wise break up of forest area required: -
Sr. No. Purpose for which forest land is required Area (ha) 1 Upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 4.0077 in the State of Maharashtra 2 Any other purpose Nil Total area 4.0077 Entire forest land (4.0077 ha) will be used for road construction.
Statement showing Details of Non- forest area involved in the Proposal: -
Sr. District Tehsil Village Survey Type of Nature of land Area in No. number land hectares 1 Amravati Morshi Chikhal 103/1 Private Agriculture 2 Savangi 103/2 Private Agriculture 3 103/3 Private Agriculture 0.055818 4 103/3A Private Agriculture 5 103/4 Private Agriculture 6 104/1 Private Agriculture 7 104/2 Private Agriculture 8 104/2A Private Agriculture 0.07134 9 104/3 Private Agriculture 10 104/3A Private Agriculture 11 104/5 Private Agriculture 12 Ashtagaon 33 Private Agriculture 0.13916 13 34/1 Private Agriculture 14 34/2 Private Agriculture 15 34/3 Private Agriculture 0.3507 16 34/3A Private Agriculture 17 34/4 Private Agriculture
PWDPWD 59 59
PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Sr. District Tehsil Village Survey Type of Nature of land Area in No. number land hectares 18 49/1 Private Agriculture 19 49/2 Private Agriculture 0.0990 20 72 Private Agriculture 0.13457 21 73 Private Agriculture 0.17687 22 70 Private Agriculture 0.04652 23 Udkhed 19/1 Private Agriculture 24 19/2 Private Agriculture 25 19/3 Private Agriculture 0.004993 26 19/4 Private Agriculture 27 18 Private Agriculture 0.01724 28 31/1 Private Agriculture 29 31/2 Private Agriculture 30 31/3 Private Agriculture 0.017626 31 31/4 Private Agriculture 32 30 Private Agriculture 0.025487 33 28/1 Private Agriculture 34 28/2 Private Agriculture 0.03465 35 28/3 Private Agriculture 36 Chand Mochkheda 176 Govt. F-Class 0.03036 37 urbazar Tondgaon 489 Private Agriculture 0.27159 38 Kural 296 Private Agriculture 0.087985 39 298 Private Agriculture 0.16427 40 300 Private Agriculture 0.01618 41 299 Private Agriculture 0.70867 42 303 Govt. Barren Land 0.39629 43 3 Private Agriculture 0.21078 44 5 Private Agriculture 0.13551 45 8 Private Agriculture 0.05127 46 7 Private Agriculture 0.37973 47 13 Private Agriculture 0.11851 48 Masod 152 Private Agriculture 0.04352 49 Achalp Shekapur 32 Private Agriculture 0.33307 50 ur 31 Private Agriculture 0.01350 51 30 Private Agriculture 0.00896 52 25 Private Agriculture 0.0114 53 26 Private Agriculture 0.02432 54 Ramgaon 30 Private Agriculture 0.00925 55 17 Private Agriculture 0.03542 56 Khel 15/2 Private Agriculture 57 Bhaleray 15/2A Private Agriculture 0.01032 58 15/3 Private Agriculture 59 15/4 Private Agriculture 60 Khel 129/1 Private Agriculture 0.01519 61 Tapmali 129/2 Private Agriculture 62 129/3 Private Agriculture Total = 4.2501
PWDMSRDCPWD 60 60
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 61 61
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 23 List of the Identified forest from the Deputy Conservator of Forest
Sr. District Taluka Village Gat No. Total Gat Area (Forest) No. Area (Ha) Under Acquisition (Ha)
Total Forest Area =
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 62 62
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 24
List of tree, species wise/girth wise, with local and scientific name to be given. If felling of trees is essential? The estimate of tree felling to be enclosed as per GOI letter no. 7-1/89/ (For)/Part- VIII/2012-BHO/848, dt.18/05/2012.
To be furnished by the D.C.F. as a part of Part II of application.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
PWDMSRDCPWD 63 63
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Section 4 Certificate by Chief Conservator of Forest and their authenticated documents.
PWDMSRDCPWD 64 64
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 25
Net Present Value Certificate must be counter signed by Chief Conservator of Forest / with eco- class /category to be shown in the certificate of Forest as as per the GOI letter F.No.5-3/2007/-FC, Dt.05/02/2009 to be enclosed
Certified that 4.0077 Ha of forest land used in upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra. The proposed forest Range falls in Amravati working circle and as the density of 0.4. It is also certified that the amount of Net Present Value of forest land calculated and collected for Rs. (In words and figures) ...... is exactly as per the rates and calculation provided in the Government Resolution No.FLD- 1002/CR- 199/F-10 dated 19- 12-2003 of Government of Maharashtra. (Enclosed attested copy of challan)
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place:
Chief Conservator of Forest
Amravati Division
Place Amravati
PWDMSRDCPWD 65 65
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Section 5 Certificate by Project Agency
PWDMSRDCPWD 66 66
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 26
Information on the movement of the proposal from one office to other with dates
Not Applicable.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 67 67
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 27
Attempts made to find out Non forest land for the proposal/ reasons for its rejection of the same and minimum demand of forest area.
This upgradation of Morshi-Chandurbazar-Achalpur alignment from Km 0.000 to 53.719 will be done in the State of Maharashtra as per specific alignment which has been decided after exploring various alternatives. Attempt has been made to use minimum forest land for this project. It can be seen that major part of this alignment is located on non-forest land.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 68 68
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 28
Unqualified commitment from the project authority to the bear cost of exploitation of felling of trees and their allied works under project.
Cost of exploitation of felling of trees and their allied works under project in the event of any tree felling if required, shall be borne by the Project Authority.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 69 69
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 29
Certificate by Project Authority /User Agency for Cost of compensatory afforestation, duly countersigned by D.C.F.
Certified that, the project authority is agreed to defray the cost as determined by the Forest Department for Compensatory Afforestation in lieu of the forest area of 4.0077 ha diverted for proposed upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra as per prevailing wage rate at the time of plantation.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Place: Amravati
Deputy Conservator of Forest
Amravati Division
Place:
PWDMSRDCPWD 70 70
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 30
Certificate by Project Authority /User Agency for No Violation of FCA-1980/Guidelines under it
This is to certify that provisions of F.C.A., 1980 have not been violated by the User Agency i.e. Public Works Department as upgradation of Morshi-Chandurbazar- Achalpur from Km 0.000 to 53.719 in the State of Maharashtra has not been started. We further undertake that no work will be started on forest land without obtaining diversion of forest land as is being applied for through this proposal.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 71 71
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 31
Certificate by the Project Authority to furnish the Net Present Value as per the ordered by Government of India.
It is to certify that I/We have applied for diversion of 4.0077 ha forest area for the purpose of upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra. I/We, hereby, undertake to pay net present value (NPV) of the above forest land. I/We hereby also undertake to pay the additional amount of NPV, if so determined as per decision of the Honorable Supreme Court.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 72 72
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 32
Certificate of Project Authority (Providing i.e. water supply facilities to)
Not Applicable
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 73 73
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 33
Certificate by Project Authority /User Agency To get the Environmental clearance as per the Environmental Act. 2006 (whenever necessary)
Not Applicable
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 74 74
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 34
Certificate of Non Indemnity to forest Department (by Project Authority)
Not Applicable
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 75 75
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 35
Certificate or NOC from the private owner if the area under private forest act, (Acquisition) Act.1975 to be enclosed. (By villagers)
Not Applicable
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 76 76
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 36
Certificate of the Projects Authority to take up catchments area treatment plan as per the guideline of Government of India
Not Applicable
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 77 77
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 37 Catchment area treatment plan.
Not applicable-this is a linear project
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 78 78
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 38
Certificate No Command area development plan. - 38
Not applicable-this is a linear project
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 79 79
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 39
Certificate by Project Authority Whether stipulation is made that 5 % of area under command of the project is made available to the Forest Department for planting trees and other vegetation for which necessary irrigation should be provided free of cost by the project authority / user agency. If the forest area involved is less than 2.00 ha and there is no felling to tree growth; it is to be dealt with as per simplified procedure.
Not applicable-this is a linear upgradation project
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 80 80
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 40 Project note by the project authority with salient features (Also provided in the starting of the proposal for better understanding)
The PUBLIC WORKS DEPARTMENT (NATIONAL HIGHWAY) OF MAHARASHTRA STATE has been entrusted with the assignment of preparation of Detailed Project Reports in the state of Maharashtra. The project alignment an amalgamation of SH-240, SH-203 & SH-201 passes through Morshi, Chandurbazar and Achalpur town forming an important artery for movement of goods from Amravati. Goods transported are seasonal crops and agricultural products throughout the year from different places located in Morshi, Chandurbazar and Achalpur to Daryapur, Akot, Paratwada Akola Chikhaldara. The Achalpur town had been a major trade center for Palmarosa oil in India. The major commodities for trade include natural gums, Cottons, Banana, Oranges, Red Chilies Ground Nut, Honey, Millet, Milo, wheat, Sunflower. The said project stretch has a one crusher plants and Spiritual places also which does contributes to the traffic flow. At the northern extreme of the Amravati district of Maharashtra, on the border of Madhya Pradesh, lies the Melghat in the South-western Satpura mountain ranges. The project alignment is spanning through Amravati districts with a total length of approximately 53.719 Kms. Presently the existing Highway is as per SH specification & the proposal is to upgrade the existing Highway to NH specification. In addition a number of major and minor bridges exists which requires upgradation. Also, the town of Chandurbazar is developing population centers and would need to be bypassed for smooth flow of traffic. It is appreciated that over a horizon of next 20-30 years, this road will serve a critical purpose of linking Amravati & Warud to Paratwada & Chikhaldara contribute substantially to the development of the local economy and Tourism. Further a number of remote villages are also being provided connectivity under the PMGSY and the take-off points emanate from this highway.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 81 81
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 40-a,b,c,d,fe,f,g,h,I,j
a) Total catchment area -NA b) Total command area-NA c) Full reservoir level-NA d) High flood level-NA e) Minimum drawal level-NA f) Total catchment area of the dam (in Ha) and its breakup forest land, cultivated land, Pasture, Human cultivation and others. -NA g) Details as per item (f) above for the area coming under submergence. -NA h) Total No. of families and population affected, scheduled caste and scheduled tribe families to be displaced should be separately indicated. -NA i) Proposal for the rehabilitation of affected persons (Rehabilitation Plan)-NA j) Comprehensive land use plan for the area required outside the submergence i.e. building roads and other ancillary facilities outside submergence i.e. building roads and other ancillary facilities. NA
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 82 82
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 41-I, ii, iii, iv
It has been observed that water hardly stands the ear around even upto FRL. Trees can definitely stand in water for one to three months and therefore submergence should be calculated 2 M below FRL for this following should be given for forest areas involved.
Not Applicable
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 83 83
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 42 List of trees 2 Meter, 4 Meter below F.R.L. in submergence area species wise
Not Applicable
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 84 84
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 43 Administrative/Technical approval from the competent authority to be enclosed
Not Yet Recieved
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 85 85
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 44
Certificate/ undertaking by the project authority regarding the wind power project as per the GOI letter Dated 14/05/2004 to be enclosed.
Not Applicable
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
PWDMSRDCPWD 86 86
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Section 6
Certificate by Other Department
PWDMSRDCPWD 87 87
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 45
In case of proposal related to stone quarries, the recommendation of the Director, Geological and Mines is required
Not Applicable
PWDMSRDCPWD 88 88
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 46
If any Protected/Archeological/Heritage site and other Important Monument is located in the area. The Certificate by Archeological Department to be enclosed
Not Applicable
PWDMSRDCPWD 89 89
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 47
Certificate about the distance of Project from Protected area by the Dy.CF Wildlife Department. Whether the Project area within 10.00 Km. should be clearly shown and marked.
This is to certify that there is no protected area lying within 10 km study area of proposed alignment.
PWDMSRDCPWD 90 90
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 48 No Objection Certificate of M.D., F.D.C.M. for involvement of their area.
Certified that the area mentioned in the following statement is not under charge of F.D.C.M. Ltd. and as such we have no objectetion if forest land is diverted for purpose applied for under this proposal.
Chainage Area Length (km) (Forest) Legal Patch District Taluka Village Gat No. under From To Status RHS LHS Acquisition (Ha) P1 Shivpuri 2+980 3+554 0.402 0.574 15, 17 0.8784 RF P2 Khanapur 5+050 6+020 0.970 0.076 4,5,6,7, 171 0.9414 RF P3 Amrav Khanapur 7+457 8+677 0.493 1.220 73,74,81,82 1.5417 RF Morshi P4 ati Ashtgaon 9+784 9+853 0 0.069 51 0.1242 RF P5 Ashtgaon 11+251 11+263 0.012 0 85 0.0216 RF P6 Udkhed 13+247 13+525 0.278 0.278 24 0.5004 RF Total Forest Area 3.123 km 4.0077
PWDMSRDCPWD 91 91
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 49
Relevant Notification/7-12 Extract/ restoration order/Rights of record etc. of the proposed forest land to be enclosed.
To be complied by relevant applicable departments.
PWDMSRDCPWD 92 92
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Section 7
Certificate by Collector
PWDMSRDCPWD 93 93
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 50
Certificate from the Collector that no alternative suitable non-forest land is available for the project. (In A Form itself)
This is to certify that proposed upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra is to be constructed in accordance with specific alignment decided after detailed study and exploring various alternatives, therefore, the project is site specific. Wherever possible non-forest land has been used but, in view of above reason, the patch of alignment passing through forest cannot be located on non-forest land and, as such, the proposed diversion of 4.0077ha is required.
It is also certified that all other alternate for the purpose have been explored and the demand for the required forest land of Reserved forest for upgradation of Morshi- Chandurbazar-Achalpur from Km 0.000 to 53.719 in the Amravati district is the barest minimum demand.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Countersigned,
Collector Amravati District
PWDMSRDCPWD 94 94
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 51
Certificate of Collector under the FRA-2006 with resolution of Gram Sabha/Gram Panchayat as per GOI letter dated 3/8/2009 to be enclosed.
To be complied by the Collector.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Countersigned,
Collector Amravati District
PWDMSRDCPWD 95 95
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 52
Certificate of Compensatory Afforestation land made available by Collector
Certified that Revenue land at Village...... Tal ...... Dist...... Gut No/Sur. No ...... is available for handing over 4.0077ha to the forest Department in lieu of forest land required for upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to 53.719 in the State of Maharashtra. This land is not proposed for compensatory afforestation previously for any other project. (It is further certified on behalf of User Agency i.e. PWD that we will arrange to provide equivalent suitable non-forest land for compensatory afforestation in lieu of forest area proposed to be diverted under this proposal.)
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Countersigned,
Collector Amravati District
PWDMSRDCPWD 96 96
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 53
Certificate from Collector / Divisional Commissioner for Non-availability of Non-forest land for project.
This is to certify that proposed upgradation of Morshi-Chandurbazar-Achalpur from Km 0.000 to Km 53.719 in the State of Maharashtra is to be constructed in accordance with specific alignment decided after detailed study and exploring various alternatives, therefore, the project is site specific. In view of this no alternative non-forest land is available that can be used for the purpose.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Countersigned,
Collector Amravati District
PWDMSRDCPWD 97 97
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 54
The agency has not given alternative land to the forest Department. If non forest land for C.A. scheme is not available in the entire state, the certificate from the Chief Secretary of the State to be enclosed. vide GOI letter dt 13/2/12
Not Applicable
PWDMSRDCPWD 98 98
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 55
As the project, area is within the 10.00 km from the boundary of PA area therefore, the information regarding 16 points check list provided by Principle Chief Conservator of Forest (W.L.) Nagpur which is enclosed herewith to be furnished.
Not Applicable.
PWDMSRDCPWD 99 99
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 56
All the certificate and documents must have name of the signatory, designation, station & date under the signature as per the GOM letter vide, dtd.01 December 2010.
All the certificated and documents are signed with dates mentioned and place as per GOM letter vide, dtd. 01 December 2010.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola
Countersigned,
Collector Amravati District
PWDMSRDCPWD 100 100
16
MSRDC PROPOSAL FOR DIVERSION OF 4.0077 HA FOREST AREA FOR UPGRADATION TWO LANES WITH PAVED SHOULDER/ FOUR LANE CONFIGURATIONS OF MORSHI-CHANDURBAZAR-ACHALPUR FROM KM 0.000 TO 53.719 IN THE STATE OF MAHARASHTRA
Certificate No.: - 57
Resolution of the Gram Sabha may not be required in cases of projects like transmission line, roads, canals, laying of pipeline/optical fibers where linear diversion of forest land in several villages are involved, unless recognized rights of PTG/ PAC are being affected as per Government of India F.No.11-9/98-FC(pt.) dated 05/02/2013.
As per above GoI order the resolution of the Gram Sabhas are not required for this project.
Dated: 11.11.2016 Executive Engineer National Highway Division Akola